REKAPITULASI RENCANA ANGGARAN BIAYA PEKERJAAN RENOVASI

KTK FISIOTERAPI LANTAI 3


RS HERMINA PALEMBANG

NO. URAIAN PEKERJAAN TOTAL HARGA (RP)

GRAND TOTAL

I : PEKERJAAN PERSIAPAN Rp. 33,862,500.00

II : PEKERJAAN PEMBONGAKARAN Rp. 22,815,122.75

III : PEKERJAAN ARSITEKTUR


A. Pekerjaan Pasangan Dinding & Partisi Rp. 89,706,468.50
B. Pekerjaan Pasangan & Pelapis Lantai Rp. 134,531,375.00
C. Pekerjaan Kusen Pintu dan Jendela Rp. 119,136,875.00
D. Pekerjaan Plafond Rp. 60,309,000.00
E. Pekerjaan Finishing Dinding & Pengecatan Rp. 61,297,615.00
F. Pekerjaan Sanitary Rp. 74,194,350.00

IV : PEKERJAAN MEP
1 PEKERJAAN LISTRIK Rp. 86,639,625.00
2 PEKERJAAN FIRE ALARM Rp. 25,776,887.50
3 PEKERJAAN TELEPHONE Rp. 22,897,500.00
4 PEKERJAAN TATA SUARA Rp. 29,535,625.00
5 PEKERJAAN CCTV Rp. 11,825,000.00
6 PEKERJAAN MATV Rp. 6,557,500.00
7 PEKERJAAN PLUMBING Rp. 56,065,012.50
8 PEKERJAAN PEMADAM KEBAKARAN Rp. 31,169,625.00
9 PEKERJAAN TATA UDARA Rp. 234,599,400.00
10 PEKERJAAN TAMBAH ME Rp. 98,750,000.00

TOTAL I + II + III + IV Rp. 1,199,669,481.25

PPN 11% Rp. 131,963,642.94

TOTAL Rp. 1,331,633,124.19

DIBULATKAN Rp. 1,331,633,000.00

Terbilang : Satu Miliar Tiga Ratus Tiga Puluh Satu Juta Enam Ratus Tiga Puluh Tiga Ribu Rupiah

Diperiksa Oleh, Dibuat Oleh,


PT. ………….. PT. BUMI DAYA PLAZA

__________________ WWIEK WIDHARTI


(Nama & Jabatan) (Kepala Cabang)
Tanggal : Tanggal : 08 November 2022
RENCANA ANGGARAN BIAYA
KEGIATAN : Renovasi Area KTK LT 3 RS HERMINA PALEMBANG
PEKERJAAN : Renovasi Area KTK LT 3 RS HERMINA PALEMBANG
LOKASI : RS. HERMINA PALEMBANG
TAHUN : 2022

NO URAIAN PEKERJAAN VOL SAT HARSAT JUMLAH

I . Pekerjaan Persiapan
1 Pengukuran 1.00 ls 2,687,500.00 2,687,500.00
2 Mobilisasi Alat dan Pekerja 1.00 ls 5,375,000.00 5,375,000.00
3 Papan identitas pekerjaan 1.00 bh 537,500.00 537,500.00
4 Direksikeet dan Gudang 1.00 ls 5,375,000.00 5,375,000.00
5 Pelaksanaan SMK-3 keselamatan 1.00 lot 5,375,000.00 5,375,000.00
6 Partisi sementara dari gypsum 1.00 ls 5,375,000.00 5,375,000.00
7 Pek. Pembersihan 1.00 ls 2,687,500.00 2,687,500.00
8 Sosialisasi dan Keamanan 1.00 ls 3,225,000.00 3,225,000.00
9 Pengadaan Shop Drawing, As Built Drawing & pelaporan 1.00 ls 3,225,000.00 3,225,000.00
Sub total 33,862,500.00

II . Pekerjaan Pembongkaran
1 Pembongkaran Dinding Hebel Eksisting 58.29 m2 26,875.00 1,566,543.75
2 Pembongkaran Partisi 147.96 m2 16,125.00 2,385,822.75
3 Pembongkaran Lantai 257.05 m2 21,500.00 5,526,575.00
4 Pembongkaran Plafond 257.05 m2 16,125.00 4,144,931.25
5 Pembongkaran Pintu Single 4.00 unit 376,250.00 1,505,000.00
6 Pembongkaran Pintu Double 5.00 unit 483,750.00 2,418,750.00
7 Pembongkaran sanitair :
- Wastafel 4.00 unit 268,750.00 1,075,000.00
- Kran 6.00 unit 161,250.00 967,500.00
- Floor drain 6.00 unit 268,750.00 1,612,500.00
- Closet 4.00 unit 268,750.00 1,075,000.00
- Shower 2.00 unit 268,750.00 537,500.00
Sub total 22,815,122.75

III . Pekerjaan Arsitek


A Pekerjaan Pasangan Dinding & Partisi
1 Pas.dinding hebel tb.10 cm (jenis AAC) 86.54 m2 242,000.00 20,941,712.00

2 Plester dinding dan Acian 10 mm (dunia mortar) 173.07 m2 132,000.00 22,845,504.00


Pas. Full Partition Gypsume 9mm ex. Jayaboard/setara
3 termasuk rangka, alat bantu dan kelengkapan lainnya sesuai
163.71 m2 280,500.00 45,919,252.50
gambar dan spesifikasi

Sub total 89,706,468.50


B Pekerjaan Pasangan & Pelapis Lantai
1 Pas. Lantai HT 01 238.05 m2 467,500.00 111,288,375.00
Pas. Homogenous Tile (HT) uk 600x600mm New Crystal Grey
ex.Valentino Gress termasuk pembentukan pola adukan
perekat, alat bantu, dan kelengkapan lainnya sesuai gambar dan
Pelapis Lantai kamar mandi / area Basah :
spesifikasi
2 Pas. Lantai HT 06
Pasangan HT uk. 600x600mm type Rover Biege ex. Valentino 12.90 m2 467,500.00 6,030,750.00
Gress termasuk pembentukan pola screed adukan perekat, alat
bantu dan kelengkapan lainnya sesuai gambar dan spesifikasi
3 Pas. Lantai HT 07 6.10 m2 467,500.00 2,851,750.00
Pasangan HT uk. 600x600mm type Rover Grey ex. Valentino
Gress termasuk pembentukan pola screed adukan perekat, alat
bantu dan kelengkapan lainnya sesuai gambar dan spesifikasi
Plint :
4 Plint Lantai PHT 01 201.71 m1 50,000.00 10,085,500.00
Plint HT uk. 100x600mm New Crystal Grey ex.Valentino Gres
termasuk pembentukan pola adukan perekat, alat bantu dan
kelengkapan lainnya sesuai gambar dan spesifikasi

5 Waterproofing Lantai Area Basah 19.00 m2 225,000.00 4,275,000.00


Sub total 134,531,375.00
C Pekerjaan Kusen Pintu dan Jendela
PINTU:
1 TOI 1-AL 4.00 unit 6,987,500.00 27,950,000.00
Pintu ukuran 1000x2200mm kusen pintu aluminium profil 3"
finishing powder coating white, daun pintu engineered wood fin.
wood grain laminate main gold teak 5356M ex. Perform, Handle
LHTR 0016 6 22mm SSS, kunci MTS IL DL 8485, CYL DC DL
60mm SN engsel ESS EL 4x3x2mm BB SSS ex. Dekkson
2 PK1K 9.00 unit 6,987,500.00 62,887,500.00
Pintu kayu uk. 1000x2200mm, kusen solid wood fin. Taco sheet,
architrave engineered fin. Taco sheet, daun pintu engineered
wood, fin. HPL Main Gold Teak 5356M ex. Perform, kaca clear
6mm, frame uk. 126x1966mm, handle LHTR 0016 22mm SSS,
kunci MTS IL DL 8485, CYL DC DL 60MM SN, aksesoris engsel
3 PF2 CL 4x3x2mm BB SSS ex. Dekkson
E55 EL 3.00 unit 6,987,500.00 20,962,500.00
Pintu Aluminium uk. 1800x2200mm, kusen aluminium profil 3" x
1.00mm fin. Powder coating white ex. Alexindo, daun pintu
rangka aluminium dan kaca clear 6mm DENGAN STIKER
LOGO HERMINA, PH DL801 SSS 32XX432X400 WHITE FH 84
SSSS,
JENDELA:PT 20 PSS, PT 24 PSS ex. Dekson
4 W1E-I 5.00 unit 1,467,375.00 7,336,875.00
Jendela Aluminium Kaca Clear uk.300x1300 mm, kusen
aluminium profil 3"x1.0 mm fin. Powder coating white ex.
Alexindo, daun jendela rangka aluminium dan kaca clear 6mm

Sub total 119,136,875.00


D Pekerjaan Plafond

Plafond GP 01 Gypsum Board 9mm ex. Jayaboard termasuk


rangka alat bantu cat aksesoris dan kelengkapan lainnya sesuai
1 238.05 m2 185,000.00 44,039,250.00
gambar dan spesifikasi termasuk shadow line hollow galvanis
tebal 0,25 mm rangka jarak 400 x 1200mm, long drat+support

Plafond GP 02 Gypsum Board 9mm ex. Jayaboard Water


Resistant termasuk rangka alat bantu cat aksesoris dan
2 kelengkapan lainnya sesuai gambar dan spesifikasi termasuk 19.00 m2 247,500.00 4,702,500.00
shadow line hollow galvanis tebal 0,25 mm rangka jarak 400 x
1200mm, long drat+support

3 Cat Plafond 257.05 m2 45,000.00 11,567,250.00


Gloss White ex. Primashield

Sub total 60,309,000.00


E Pekerjaan Finishing Dinding & Pengecatan

1 Pengecatan dinding interior ruangan


81.78 m2 45,000.00 3,680,235.00
-Chrysan White ex. Dulux/Sunstone White ex. Primashield

2 Pengecatan dinding interior ruangan


539.03 m2 45,000.00 24,256,260.00
-Aqua Blue ex. Duluxe

Pelapis Dinding
- (DHT 04) kamarHT
Pasangan mandi:
uk. 600x600mm type Blunt Ivory ex.
3 Valentino Gress termasuk pembentukan pola screed adukan 80.57 m2 349,375.00 28,148,445.00
perekat, alat bantu dan kelengkapan lainnya sesuai gambar dan
spesifikasi
- (BHT 07) Pasangan HT uk. 600x600mm type Rover Grey ex.
4 Valentino Gress termasuk pembentukan pola screed adukan 14.92 m2 349,375.00 5,212,675.00
perekat, alat bantu dan kelengkapan lainnya sesuai gambar dan
spesifikasi
Sub total 61,297,615.00
F Pekerjaan Sanitary

1 Washtafel Reguler
- Washtafel Wallhung type Studio 50 ex. American Standart compl 10.00 bh 2,687,500.00 26,875,000.00
- Faucet ex. San-ei type Y50JPR 10.00 bh 322,500.00 3,225,000.00

2 Toilet R.Fisioterapy
- Closet duduk type newton Dual Flash ex. American Standart co 1.00 bh 4,837,500.00 4,837,500.00
- Washtafel Wallhung type Studio 50 ex. American Standart compl 1.00 bh 2,687,500.00 2,687,500.00
- Jet washer ex. San ei type SN75C 1.00 bh 430,000.00 430,000.00
- Faucet ex. San-ei type Y50JPR 1.00 bh 322,500.00 322,500.00
- Floor Drain type HN51P ex. San ei 1.00 bh 268,750.00 268,750.00
- Gantungan handuk ex. San ei type PWN532 1.00 bh 510,625.00 510,625.00
- Tissue Holder SAN EI WN 30 1.00 bh 376,250.00 376,250.00
- Kaca cermin wastafel 1.00 bh 376,250.00 376,250.00
- Grab Bar Type WN 59-2 ex. San Ei 1.00 bh 555,775.00 555,775.00
- Robe Hook ex. Sunlot type LD55214 (provisional) 1.00 bh 376,250.00 376,250.00

3 Toilet R.Dokter Konsul


- Closet duduk type newton Dual Flash ex. American Standart co 1.00 bh 4,837,500.00 4,837,500.00
- Jet washerr ex. San ei type SN75C 1.00 bh 430,000.00 430,000.00
- Washtafel Wallhung type Studio 50 ex. American Standart compl 1.00 bh 2,687,500.00 2,687,500.00
- Faucet ex. San-ei type Y50JPR 1.00 bh 322,500.00 322,500.00
- Shower ex. San ei type SK31P 1.00 bh 2,150,000.00 2,150,000.00
- Floor Drain type HN51P ex. San ei 1.00 bh 268,750.00 268,750.00
- Gantungan handuk ex. San ei type PWN532 1.00 bh 510,625.00 510,625.00
- Grab Bar Type WN 59-2 ex. San Ei (Provisional) 1.00 bh 555,775.00 555,775.00
- Tissue Holder SAN EI WN 30 1.00 bh 376,250.00 376,250.00
- Kaca cermin wastafel 1.00 bh 376,250.00 376,250.00
- Robe Hook ex. Sunlot type LD55214 (provisional) 1.00 bh 376,250.00 376,250.00

4 Toilet Koridor NS KTK


- Closet duduk type CW 660 J ex. TOTO complete set termasuk 1.00 bh 4,837,500.00 4,837,500.00
- Jet washerr ex. San ei type SN75C 1.00 bh 430,000.00 430,000.00
- Washtafel Wallhung type Studio 50 ex. American Standart compl 1.00 bh 2,687,500.00 2,687,500.00
- Faucet ex. San-ei type Y50JPR 1.00 bh 322,500.00 322,500.00
- Floor Drain type HN51P ex. San ei 1.00 bh 268,750.00 268,750.00
- Grab Bar Type WN 59-2 ex. San Ei (Provisional) 1.00 bh 555,775.00 555,775.00
- Tissue Holder SAN EI WN 30 1.00 bh 376,250.00 376,250.00
- Kaca cermin wastafel 1.00 bh 376,250.00 376,250.00
- Robe Hook ex. Sunlot type LD55214 (provisional) 1.00 bh 376,250.00 376,250.00

5 Toilet R.Tunggu Fisioteraphy


- Closet duduk type CW 660 J ex. TOTO complete set termasuk 1.00 bh 4,837,500.00 4,837,500.00
- Jet washerr ex. San ei type SN75C 1.00 bh 430,000.00 430,000.00
- Washtafel Wallhung type Studio 50 ex. American Standart compl 1.00 bh 2,687,500.00 2,687,500.00
- Faucet ex. San-ei type Y50JPR 1.00 bh 322,500.00 322,500.00
- Floor Drain type HN51P ex. San ei 1.00 bh 268,750.00 268,750.00
- Grab Bar Type WN 59-2 ex. San Ei (Provisional) 1.00 bh 555,775.00 555,775.00
- Tissue Holder SAN EI WN 30 1.00 bh 376,250.00 376,250.00
- Kaca cermin wastafel 1.00 bh 376,250.00 376,250.00
- Robe Hook ex. Sunlot type LD55214 (provisional) 1.00 bh 376,250.00 376,250.00

Sub total 74,194,350.00

JUMLAH ARSITEK 595,853,306.25


TOTAL 595,853,306.25
PPN 65,543,863.69
TOTAL 661,397,169.94
DIBULATKAN 661,397,000.00

Terbilang :
Pemb Din 58.29 Fin Dind
Pemb Partisi 147.958 cw04/pht01 4.86 dht 04
Pemb Plafond 257.05 cw04/pht01 4.86 dht 04
Pemb Lantai 257.05 cw04/pht01 1.4 x
Pintu single 12 dht 04 1.4 x
Pintu Double 10 dht 04 1.4 dht 04
dht 04 1.4 x
cw01/pht01 4.86 dht 04
Pas Lantai cw04/pht01 4.86 dht 04
HT 01 238.05 cw01/pht01 1.6 x
HT 06 12.9 dht 04 1.6 dht 04
HT 07 6.1 dht 04 1.6 x
86.536

Plafond
GP 01 238.05
GP 02 19

Kusen Pintu
PF2 CL-BV 1
PF2 CL 3
PK1K 10
PK1.5 1
PK1 1
TOI1AL 5
Fin Partisi eks din
cw04/pht01 2.85 cw04/pht01 cw04/pht01 18.83 cw 02
cw04/pht01 2.85 cw04/pht01 cw04/pht01 9.3 cw 02
cw04/pht01 2.85 cw04/pht01 cw04/pht01 7.87 cw 02
cw04/pht01 2.85 cw04/pht01 cw04/pht01 11.9
cw04/pht01 2.85 cw04/pht01 cw04/pht01 9
cw04/pht01 8.2 cw04/pht01 cw04/pht01 3.46
cw04/pht01 4.85 cw04/pht01 cw01/pht01 4.6
cw04/pht01 3.85 cw04/pht01 cw01/pht01 8.1
cw04/pht01 2.42 cw04/pht01 cw04/pht01 7.7
cw04/pht01 7.7 cw04/pht01 cw01/pht01 4.4 cw 02
cw04/pht01 2.5 cw04/pht01 cw01/pht01 4.4 cw04/pht01
cw04/pht01 4.88 cw04/pht01 cw01/pht01 8.1
cw04/pht01 3.9 cw04/pht01 cw04/pht01 8.8 cw04/pht01
cw04/pht01 3.9 cw04/pht01 cw04/pht01 14.12 cw04/pht01
163.705 cw04/pht01 3.9 cw04/pht01
cw04/pht01 3.9 cw04/pht01
PHT 01 298.84

CW 01 114.534

CW 04 696.384

DHT 04 80.568

cw04/pht01
71.23
cw04/pht01
cw04/pht01
cw04/pht01
cw04/pht01
157.356
Analisa Harga Satuan ini hanya dipergunakan ANALISA HARGA SATUAN
sebagai dasar/pendekatan dalam GALIAN TANAH (CUT & FILL) KODE
penyusunan DPA dan (MENGGUNAKAN ALAT) CUT 01
Mengevaluasi Harga Penawaran
Propinsi : Kota : Tanggal :
JAWA BARAT DEPOK

Proses : Anggapan :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat 1500 m2/hari
1. Bab Satuan Pekerjaan ini, Spesifikasi 2. Excavator
Umum Jalan Kabupaten, Bina Marga 4. Bulldozer
Maret 1992 5. Sesuai spek B.M No. 12/PT/B/1983 (tabel 3.3) dan rev. Spek Umum B.M. Maret 89 buku 3
2. Atau Addendum yang Berlaku

Upah Biaya Sub Total


No. Pekerja Vol. Satuan
(Rp/Org/Hari) Rp Rp

1 Mandor 0.03 jam 130,000.00 #REF!


2 Pekerja 0.12 jam 80,000.00 #REF!
JUMLAH I Pekerja #REF!

Harga Biaya Sub Total


No Material Satuan
(Rp/Unit) (Rp) (Rp)

1
2
3
4

Harga Biaya Sub Total


No. Peralatan Jumlah Satuan
(Rp/jam) (Rp) (Rp)

1 Excavator 0.03 jam #REF!


2 Bulldozer 0.00 jam #REF!
JUMLAH III Peralatan #REF!
Total (Rp) #REF!
GALIAN TANAH (CUT & FILL)
VOLUME : 1,500.00 satuan
Sub.
m3Total Harga Satuan Rp. #REF! Per m3
Jasa 10 % #REF!
Total Harga Satuan Rp. #REF! Per m3
Analisa Harga Satuan ini hanya dipergunakan ANALISA HARGA SATUAN
sebagai dasar/pendekatan dalam LAPIS ASPAL RESAP PELEKAT KODE
penyusunan DPA dan (PRIME COAT) PC
Mengevaluasi Harga Penawaran
Propinsi : Kota : Tanggal :
JAWA BARAT DEPOK

Proses : Anggapan :
Pekerjaan ini harus dilaksanakan sesuai : 1. Harga bahan, perangko (siap dilokasi)
1. Bab Satuan Pekerjaan ini, Spesifikasi 2. Perbandingan aspal dengan minyak tanah = 100 bagian aspal : 100 bagian minyak tanah
Umum Jalan Kabupaten, Bina Marga berdasarkan berat
Maret 1992 3. Berat jenis minyak tanah 0,86
2. Tingkat Penyemprotan 1 Kg/m2 disemprot 4. Berat jenis aspal 1,03
mempergunakan mesin penyemprot aspal

Total Vol. Upah Biaya Sub Total


No. Pekerja Vol. Hari
Org-hari (Rp/Org/Hari) Rp Rp

1 Mandor 1.00 0.50 0.50 -


2 Operator Terlatih 1.00 1.00 1.00 -
3 Pembantu Operator 1.00 1.00 1.00 -
4 Pekerja 4.00 1.00 4.00 -
JUMLAH I Pekerja -

Harga Biaya Sub Total


No Material Satuan Total Vol.
(Rp/Unit) (Rp) (Rp)

1 Aspal Bitumen 510.00 kg 510.00 -


2 Minyak Tanah 599.00 lt 599.00 -
3 Alat Bantu 0.16 Set 0.16 -
JUMLAH II Material -

Harga Biaya Sub Total


No. Peralatan Jumlah Hari Kerja Jam Kerja
(Rp/jam) (Rp) (Rp)

1 Asp. Sprayer Towed 200 ltr 1.00 1.00 5.00 -


2 Blower 1.00 1.00 5.00 -
JUMLAH III Peralatan -
Total (Rp) -
LAPIS ASPAL RESAP PELEKAT (Prime Coat)
VOLUME : 1,000.00 satuan
Sub. Total Harga Satuan Rp. - per M2
Jasa 10 % -
Total Harga Satuan Rp. - per M2
ANALISA BIAYA KONSTRUKSI
PEKERJAAN JALAN PAVING

1 1 M2 Pekerjaan Paving Block natural tb 8cm Harga Jumlah


Bahan 1.000 M2 Paving Block t=8 cm Natural 138,000.00 138,000.00
0.050 M2 Pasir Urug 325,200.00 16,260.00
1.000 lot Peralatan Bantu 15,426.00 15,426.00
Jumlah I 169,686.00

Tenaga 0.250 Oh Pekerja 110,000.00 27,500.00


0.500 Oh Tukang Setengah Terampil 99,000.00 49,500.00
0.025 Oh Kepala tukang 165,000.00 4,125.00
0.025 Oh Mandor 192,500.00 4,812.50
Jumlah II 85,937.50
Jumlah I + II 255,623.50
Keuntungan 10% 25,562.35
Total 281,185.85

2 1 BH Pekerjaan Kanstin 10.20.40 Harga Jumlah


1.000 bh Cansteen 36,000.00 36,000.00
0.040 m2 Adukan 1 : 5 96,206.77 3,848.27
0.030 set Alat bantu 39,848.27 1,195.45
Jumlah I 41,043.72

0.036 Oh Pekerja 110,000.00 3,960.00


0.012 Oh Tukang Setengah Terampil 99,000.00 1,188.00
0.006 Oh Kepala tukang 165,000.00 990.00
0.001 Oh Mandor 192,500.00 231.00
Jumlah II 6,369.00
Jumlah I + II 47,412.72
Keuntungan 10% 4,741.27
Total 52,153.99

3 1 BH Pekerjaan Kanstin type S (uk. 60x30x24) Harga Jumlah


1.000 bh Cansteen 80,400.00 80,400.00
0.040 m2 Adukan 1 : 5 96,206.77 3,848.27
0.030 set Alat bantu 84,248.27 2,527.45
Jumlah I 86,775.72

0.036 Oh Pekerja 110,000.00 3,960.00


0.012 Oh Tukang Setengah Terampil 99,000.00 1,188.00
0.006 Oh Kepala tukang 165,000.00 990.00
0.001 Oh Mandor 192,500.00 231.00
Jumlah II 6,369.00
Jumlah I + II 93,144.72
Keuntungan 10% 9,314.47
Total 102,459.19
4 1 BH Pekerjaan Kanstin DKI (uk. 60x28x18) Harga Jumlah
1.000 bh Cansteen 80,400.00 80,400.00
0.040 m2 Adukan 1 : 5 96,206.77 3,848.27
0.030 set Alat bantu 84,248.27 2,527.45
Jumlah I 86,775.72

0.036 Oh Pekerja 110,000.00 3,960.00


0.012 Oh Tukang Setengah Terampil 99,000.00 1,188.00
0.006 Oh Kepala tukang 165,000.00 990.00
0.001 Oh Mandor 192,500.00 231.00
Jumlah II 6,369.00
Jumlah I + II 93,144.72
Keuntungan 10% 9,314.47
Total 102,459.19
ANALISA BIAYA KONSTRUKSI
PEKERJAAN TANAH

PT 6.1. 1 m³ Galian tanah biasa sedalam 1 meter

6.1.1. Tenaga
- Pekerja 0.750 Oh x Rp. 110,000 = Rp. 82,500.00
- Mandor 0.025 Oh x Rp. 192,500 = Rp. 4,812.50
Jumlah (1) = Rp. 87,312.50
Keuntungan+Over head 10% = Rp 8,731.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 96,043.75

PT 6.2. 1 m³ Galian tanah biasa sedalam 2 meter

6.2.1. Tenaga
- Pekerja 0.900 Oh x Rp. 110,000 = Rp. 99,000.00
- Mandor 0.0450 Oh x Rp. 192,500 = Rp. 8,662.50
Jumlah (1) = Rp. 107,662.50
Keuntungan+Over head 10% = Rp 10,766.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 118,428.75

PT 6.3. 1 m³ Galian tanah biasa sedalam 3 meter

6.3.1. Tenaga
- Pekerja 1.050 Oh x Rp. 110,000 = Rp. 115,500.00
- Mandor 0.0670 Oh x Rp. 192,500 = Rp. 12,897.50
Jumlah (1) = Rp. 128,397.50
Keuntungan+Over head 10% = Rp 12,839.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 141,237.25

PT 6.4. 1 m³ Galian tanah keras sedalam 1 meter

6.4. Tenaga
- Pekerja 1.000 Oh x Rp. 110,000 = Rp. 110,000.00
- Mandor 0.032 Oh x Rp. 192,500 = Rp. 6,160.00
Jumlah (1) = Rp. 116,160.00
Keuntungan+Over head 10% = Rp 11,616.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 127,776.00

PT 6.5. 1 m³ Galian tanah cadas sedalam 1 meter

6.5.1. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000 = Rp. 165,000.00
- Mandor 0.060 Oh x Rp. 192,500 = Rp. 11,550.00
Jumlah (1) = Rp. 176,550.00
Keuntungan+Over head 10% = Rp 17,655.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 194,205.00

PT 6.6. 1 m³ Galian tanah lumpur sedalam 1 meter

6.6.1. Tenaga
- Pekerja 1.200 Oh x Rp. 110,000 = Rp. 132,000.00
- Mandor 0.045 Oh x Rp. 192,500 = Rp. 8,662.50
Jumlah (1) = Rp. 140,662.50
Keuntungan+Over head 10% = Rp 14,066.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 154,728.75

PT 6.7. 1 m² Pekerjaan stripping setinggi 1 meter

6.7.1. Tenaga
- Pekerja 0.050 Oh x Rp. 110,000 = Rp. 5,500.00
- Mandor 0.005 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (1) = Rp. 6,462.50
Keuntungan+Over head 10% = Rp 646.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 7,108.75

PT 6.8. 1 m³ Pembuangan tanah sejauh 150 meter

6.8.1. Tenaga
- Pekerja 0.515 Oh x Rp. 110,000 = Rp. 56,650.00
- Mandor 0.0515 Oh x Rp. 192,500 Rp. 9,913.75
Jumlah (1) = Rp. 66,563.75
Keuntungan+Over head 10% = Rp 6,656.38
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 73,220.13

PT 6.9. 1 m³ Urugan kembali

6.9.1. Tenaga
- Pekerja 0.252 Oh x Rp. 110,000 = Rp. 27,720.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (1) = Rp. 29,260.00
Keuntungan+Over head 10% = Rp 2,926.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 32,186.00

PT 6.10. 1 m³ Pemadatan tanah

6.10.1.Tenaga
- Pekerja 0.500 Oh x Rp. 110,000 = Rp. 55,000.00
- Mandor 0.050 Oh x Rp. 192,500 = Rp. 9,625.00
Jumlah (1) = Rp. 64,625.00
Keuntungan+Over head 10% = Rp 6,462.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 71,087.50

PT 6.11. 1 m³ Urugan pasir

6.11.1.Bahan
- Pasir urug 1.200 M³ x Rp. 325,200 = Rp. 390,240.00
Jumlah (1) = Rp. 390,240.00

6.11.2.Tenaga
- Pekerja 0.300 Oh x Rp. 110,000 = Rp. 33,000.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 34,925.00

Jumlah (1) + (2) = Rp. 425,165.00


Keuntungan+Over head 10% = Rp 42,516.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 467,681.50

PT 6.12. 1 m³ Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL

6.12.1.Bahan
- Pasir urug 0.400 M³ x Rp. 325,200 = Rp. 130,080.00
- Kapur padam 0.135 M³ x Rp. 2,208 = Rp. 298.08
- Tanah liat 0.948 M³ x Rp. 124,800 = Rp. 118,310.40
Jumlah (1) = Rp. 248,688.48

6.12.2.Tenaga
- Pekerja 0.800 Oh x Rp. 110,000 = Rp. 88,000.00
- Tukang 0.400 Oh x Rp. 137,500 = Rp. 55,000.00
- Kepala Tukang 0.040 Oh x Rp. 165,000 = Rp. 6,600.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 165,000.00

Jumlah (1) + (2) = Rp. 413,688.48


Keuntungan+Over head 10% = Rp 41,368.85
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 455,057.33

PT 6.13. 1 m³ Lapisan pudel campuran 1 Kp : 5 TL

6.13.1.Bahan
- Kapur padam 0.200 M³ x Rp. 2,208 = Rp. 441.60
- Tanah liat 1.000 M³ x Rp. 124,800 = Rp. 124,800.00
Jumlah (1) = Rp. 125,241.60

6.13.2.Tenaga
- Pekerja 0.500 Oh x Rp. 110,000 = Rp. 55,000.00
- Mandor 0.050 Oh x Rp. 192,500 = Rp. 9,625.00
Jumlah (2) = Rp. 64,625.00

Jumlah (1) + (2) = Rp. 189,866.60


Keuntungan+Over head 10% = Rp 18,986.66
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 208,853.26

PT 6.14. 1 m³ Pembuatan jalan sementara, tebal 25 cm

6.14.1.Bahan
- Batu belah 10/15 0.275 M³ x Rp. 298,800 = Rp. 82,170.00
- Batu koral 5/7 0.030 M³ x Rp. 209,601 = Rp. 6,288.02
- Pasir pasang 0.050 M³ x Rp. 342,000 = Rp. 17,100.00
Jumlah (1) = Rp. 105,558.02

6.14.2.Tenaga

- Pekerja 0.500 Oh x Rp. 110,000 = Rp. 55,000.00


- Mandor 0.050 Oh x Rp. 192,500 = Rp. 9,625.00
Jumlah (2) = Rp. 64,625.00

Jumlah (1) + (2) = Rp. 170,183.02


Keuntungan+Over head 10% = Rp 17,018.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 187,201.32

PT 6.15. 1 m³ Timbunan tanah berikut Pemadatan tanah tiap 20 cm (Tanah dari luar)

6.15.1.Bahan+alat berat
- Tanah urug pilihan 1.200 M³ x Rp. 124,800 = Rp. 149,760.00
- Kirim Ke site 1.200 M³ x Rp. 71,500 = Rp. 85,800.00
- Wheel loader 0.028 jam x Rp. 275,000 = Rp. 7,645.00
- Motor grader 0.006 jam x Rp. 325,000 = Rp. 1,982.50
- Vibrator roller 6-8 ton 0.016 jam x Rp. 215,500 = Rp. 3,469.55
Jumlah (1) = Rp. 248,657.05

6.15.2.Tenaga
- Pekerja 0.196 Oh x Rp. 15,714 = Rp. 3,084.71
- Mandor 0.018 Oh x Rp. 27,500 = Rp. 489.50
Jumlah (2) = Rp. 3,574.21

Jumlah (1) + (2) = Rp. 252,231.26


Keuntungan+Over head 10% = Rp 25,223.13
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 277,454.39

PT 6.15. 1 m³ Urugan tanah subur

6.15.1.Bahan
- Tanah Subur 1.200 M³ x Rp. 267,600 = Rp. 321,120.00
Jumlah (1) = Rp. 321,120.00

6.15.2.Tenaga
- Pekerja 0.250 Oh x Rp. 110,000 = Rp. 27,500.00
- Mandor 0.025 Oh x Rp. 192,500 = Rp. 4,812.50
Jumlah (2) = Rp. 32,312.50

Jumlah (1) + (2) = Rp. 353,432.50


Keuntungan+Over head 10% = Rp 35,343.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 388,775.75

PT 6.16. 1 m2Penanaman Rumput Gajah mini

6.16.1.Bahan
- Rumput Gajah 1.050 m2 x Rp. 25,000 = Rp. 26,250.00
Jumlah (1) = Rp. 26,250.00

6.16.2.Tenaga ( Upah menanam ) :


- Pekerja 0.060 Oh x Rp. 110,000 = Rp. 6,600.00
- Mandor 0.001 Oh x Rp. 192,500 = Rp. 231.00
Jumlah (2) = Rp. 6,831.00

Jumlah (1) + (2) = Rp. 33,081.00


Keuntungan+Over head 10% = Rp 3,308.10
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 36,389.10

PT 6.17. 1phnPenanaman Ketapang Kencana T = 2 - 4 m


6.17.1.Bahan
- Ketapang Kencana T = 1,5 1.000 plb x Rp. 400,000 = Rp. 400,000.00
- Ajir dolken uk.(dia 5" x 3 0.167 btg x Rp. 20,000 = Rp. 3,333.33
Jumlah (1) = Rp. 400,000.00

6.17.2.Tenaga ( Upah menanam ) :


- Pekerja 0.120 Oh x Rp. 110,000 = Rp. 13,200.00
- Tukang Taman terampil 0.048 Oh x Rp. 137,500 = Rp. 6,600.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,584.00
- Mandor 0.001 Oh x Rp. 192,500 = Rp. 154.00
Jumlah (2) = Rp. 21,538.00

Jumlah (1) + (2) = Rp. 421,538.00


Keuntungan+Over head 10% = Rp 42,153.80
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 463,691.80
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PONDASI

PP 6.1. 1 M³Pasangan pondasi batu kali, 1 Pc : 1 Ps

6.1.1. Bahan :
- Batu belah 15/20 1.100 M³ x Rp. 342,000.00 = Rp. 376,200.00
- Semen porland 392.000 Kg x Rp. 1,800.00 = Rp. 705,600.00
- Pasir pasang 0.314 M³ x Rp. 342,000.00 = Rp. 107,388.00
Jumlah (1) = Rp. 1,189,188.00

6.1.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.600 Oh x Rp. 137,500.00 = Rp. 82,500.00
- Kepala tukang 0.060 Oh x Rp. 165,000.00 = Rp. 9,900.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 271,837.50

Jumlah (1) + (2) = Rp. 1,461,025.50


Keuntungan+Over head 10% = Rp 146,102.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,607,128.05

PP 6.2. 1 M³Pasang pondasi batu kali 1 Pc : 2 Ps

6.2.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 342,000.00 = Rp. 376,200.00
- Semen porland 267.000 Kg x Rp. 1,800.00 = Rp. 480,600.00
- Pasir Pasang 0.427 M³ x Rp. 342,000.00 = Rp. 146,034.00
Jumlah (1) = Rp. 1,002,834.00

6.2.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.600 Oh x Rp. 137,500.00 = Rp. 82,500.00
- Kepala tukang 0.060 Oh x Rp. 165,000.00 = Rp. 9,900.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 271,837.50

Jumlah (1) +(2) = Rp. 1,274,671.50


Keuntungan+Over head 10% = Rp 127,467.15
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,402,138.65

PP 6.3. 1 M³Pasang pondasi batu kali, 1 Pc : 2,5 Ps

6.3.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 342,000.00 = Rp. 376,200.00
- Semen porland 392.000 Kg x Rp. 1,800.00 = Rp. 705,600.00
- Pasir Pasang 0.314 M³ x Rp. 342,000.00 = Rp. 107,388.00
Jumlah (1) = Rp. 1,189,188.00

6.3.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.600 Oh x Rp. 137,500.00 = Rp. 82,500.00
- Kepala tukang 0.060 Oh x Rp. 165,000.00 = Rp. 9,900.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 271,837.50
Jumlah (1) +(2) = Rp. 1,461,025.50
Keuntungan+Over head 10% = Rp 146,102.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,607,128.05

PP 6.4. 1 M³Pasang pondasi batu kali, 1 Pc : 3 Ps

6.4.1. Bahan
- Batu belah 15/20 cm 1.200 M³ x Rp. 342,000.00 = Rp. 410,400.00
- Semen porland 202.000 Kg x Rp. 1,800.00 = Rp. 363,600.00
- Pasir Pasang 0.485 M³ x Rp. 342,000.00 = Rp. 165,870.00
Jumlah (1) = Rp. 939,870.00

6.4.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.750 Oh x Rp. 137,500.00 = Rp. 103,125.00
- Kepala tukang 0.075 Oh x Rp. 165,000.00 = Rp. 12,375.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 294,937.50

Jumlah (1) +(2) = Rp. 1,234,807.50


Keuntungan+Over head 10% = Rp 123,480.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,358,288.25

PP 6.5. 1 M³Pasang pondasi batu kali, 1 Pc : 4 Ps.

6.5.1. Bahan
- Batu belah 15/20 cm 1.200 M³ x Rp. 342,000.00 = Rp. 410,400.00
- Semen porland 163.000 Kg x Rp. 1,800.00 = Rp. 293,400.00
- Pasir Pasang 0.520 M³ x Rp. 342,000.00 = Rp. 177,840.00
Jumlah (1) = Rp. 881,640.00

6.5.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.750 Oh x Rp. 137,500.00 = Rp. 103,125.00
- Kepala tukang 0.075 Oh x Rp. 165,000.00 = Rp. 12,375.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 294,937.50

Jumlah (1) +(2) = Rp. 1,176,577.50


Keuntungan+Over head 10% = Rp 117,657.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,294,235.25

PP 6.6. 1 M³Pasang pondasi batu kali, 1 Pc : 5 Ps

6.6.1. Bahan
- Batu belah 15/20 cm 1.200 M³ x Rp. 342,000.00 = Rp. 410,400.00
- Semen porland 136.000 Kg x Rp. 1,800.00 = Rp. 244,800.00
- Pasir Pasang 0.544 M³ x Rp. 342,000.00 = Rp. 186,048.00
Jumlah (1) = Rp. 841,248.00

6.6.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.750 Oh x Rp. 137,500.00 = Rp. 103,125.00
- Kepala tukang 0.075 Oh x Rp. 165,000.00 = Rp. 12,375.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) 294,937.50

Jumlah (1) +(2) 1,136,185.50


Keuntungan+Over head 10% = Rp 113,618.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,249,804.05

PP 6.7. 1 M³Pasang pondasi batu kali, 1 Pc : 6 Ps

6.7.1. Bahan
- Batu belah 15/20 cm 1.200 M³ x Rp. 342,000.00 = Rp. 410,400.00
- Semen porland 117.000 Kg x Rp. 1,800.00 = Rp. 210,600.00
- Pasir Pasang 0.561 M³ x Rp. 342,000.00 = Rp. 191,862.00
Jumlah (1) = Rp. 812,862.00
6.7.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.750 Oh x Rp. 137,500.00 = Rp. 103,125.00
- Kepala tukang 0.075 Oh x Rp. 165,000.00 = Rp. 12,375.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 294,937.50

Jumlah (1) +(2) 1,107,799.50


Keuntungan+Over head 10% = Rp 110,779.95
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,218,579.45

PP 6.8. 1 M³Pasang pondasi batu kali, Pc : 8 Ps

6.8.1. Bahan
- Batu belah 15/20 cm 1.200 M³ x Rp. 342,000.00 = Rp. 410,400.00
- Semen porland 91.000 Kg x Rp. 1,800.00 = Rp. 163,800.00
- Pasir Pasang 0.584 M³ x Rp. 342,000.00 = Rp. 199,728.00
Jumlah (1) = Rp. 773,928.00

6.8.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000.00 = Rp. 165,000.00
- Tukang batu 0.750 Oh x Rp. 137,500.00 = Rp. 103,125.00
- Kepala tukang 0.075 Oh x Rp. 165,000.00 = Rp. 12,375.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 294,937.50

Jumlah (1) +(2) = Rp. 1,068,865.50


Keuntungan+Over head 10% = Rp 106,886.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,175,752.05

PP 6.9. 1 M³Pasang pondasi batu kosong

6.9.1. Bahan
- Batu belah 10/15 cm 1.200 M³ x Rp. 298,800.00 = Rp. 358,560.00
- Pasir pasang 0.432 M³ x Rp. 342,000.00 = Rp. 147,744.00
Jumlah (1) = Rp. 506,304.00
6.9.2. Tenaga
- Pekerja 0.780 Oh x Rp. 110,000.00 = Rp. 85,800.00
- Tukang batu 0.390 Oh x Rp. 137,500.00 = Rp. 53,625.00
- Kepala tukang 0.039 Oh x Rp. 165,000.00 = Rp. 6,435.00
- Mandor 0.039 Oh x Rp. 192,500.00 = Rp. 7,507.50
Jumlah (2) = Rp. 153,367.50

Jumlah (1) +(2) = Rp. 659,671.50


Keuntungan+Over head 10% = Rp 65,967.15
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 725,638.65

PP 6.10. 1 M³Pasang pondasi siklop 40 % batu kali

6.10.1Bahan
- Besi beton 126.000 Kg x Rp. 13,200.00 = Rp. 1,663,200.00
- Semen portland 194.000 Kg x Rp. 1,800.00 = Rp. 349,200.00
- Pasir beton 0.312 Kg x Rp. 360,000.00 = Rp. 112,320.00
- Koral beton 0.468 M³ x Rp. 727,600.50 = Rp. 340,517.03
- Kawat beton 1.800 Kg x Rp. 21,600.00 = Rp. 38,880.00
- Batu belah 0.480 M³ x Rp. 298,800.00 = Rp. 143,424.00
Jumlah (1) = Rp. 2,504,117.03

6.10.2Tenaga
- Pekerja 3.400 Oh x Rp. 110,000.00 = Rp. 374,000.00
- Tukang batu 0.850 Oh x Rp. 137,500.00 = Rp. 116,875.00
- Kepala tukang 0.085 Oh x Rp. 165,000.00 = Rp. 14,025.00
- Mandor 0.170 Oh x Rp. 192,500.00 = Rp. 32,725.00
Jumlah (2) = Rp. 537,625.00

Jumlah (1) +(2) = Rp. 3,041,742.03


Keuntungan+Over head 10% = Rp 304,174.20
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 3,345,916.24

PP 6.11. 1 M³Pasang pondasi sumuran diameter 100 Cm

6.11.1Bahan
- Batu belah 15/20 cm 0.450 M³ x Rp. 342,000.00 = Rp. 153,900.00
- Semen portland 194.000 Kg x Rp. 1,800.00 = Rp. 349,200.00
- Pasir Pasang 0.312 M³ x Rp. 342,000.00 = Rp. 106,704.00
- Kerikil 0.468 M³ x Rp. 727,600.50 = Rp. 340,517.03
Jumlah (1) = Rp. 609,804.00

6.11.2Tenaga
- Pekerja 2.400 Oh x Rp. 110,000.00 = Rp. 264,000.00
- Tukang batu 0.800 Oh x Rp. 137,500.00 = Rp. 110,000.00
- Kepala tukang 0.080 Oh x Rp. 165,000.00 = Rp. 13,200.00
- Mandor 0.119 Oh x Rp. 192,500.00 = Rp. 22,907.50
Jumlah (2) = Rp. 410,107.50

Jumlah (1) +(2) = Rp. 1,019,911.50


Keuntungan+Over head 10% = Rp 101,991.15
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,121,902.65

PP 6.12. 1 M³Pembuatan tiang pancang (40 x 40) Cm, beton bertulang

6.12.1Bahan
- Pasir urug darat 0.019 M³ x Rp. 325,200.00 = Rp. 6,178.80
- Pasir beton 0.094 M³ x Rp. 360,000.00 = Rp. 33,840.00
- Koral beton 0.150 M³ x Rp. 727,600.50 = Rp. 109,140.08
- Semen porland 60.500 Kg x Rp. 1,800.00 = Rp. 108,900.00
- Besi beton 45.000 Kg x Rp. 13,200.00 = Rp. 594,000.00
- Kawat beton 0.900 Kg x Rp. 21,600.00 = Rp. 19,440.00
- Kayu kaso 5/7 0.032 M³ x Rp. 1,900,000.00 = Rp. 60,800.00
- Paku 0.120 Kg x Rp. 19,200.00 = Rp. 2,304.00
- Minyak bekisting 0.090 Lt x Rp. 4,800.00 = Rp. 432.00
- Plamur tembok 0.240 Kg x Rp. 24,000.00 = Rp. 5,760.00
Jumlah (1) = Rp. 940,794.88
6.12.2Tenaga
- Pekerja 1.000 Oh x Rp. 110,000.00 = Rp. 110,000.00
- Tukang batu 0.670 Oh x Rp. 137,500.00 = Rp. 92,125.00
- Kepala tukang 0.067 Oh x Rp. 165,000.00 = Rp. 11,055.00
- Mandor 0.050 Oh x Rp. 192,500.00 = Rp. 9,625.00
Jumlah (2) = Rp. 222,805.00

Jumlah (1) +(2) = Rp. 1,163,599.88


Keuntungan+Over head 10% = Rp 116,359.99
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,279,959.86

PP 6.13. 1 M³Pembuatan tiang pancang (35 x 35) Cm, beton bertulang

6.13.1Bahan
- Pasir urug darat 0.016 M³ x Rp. 325,200.00 = Rp. 5,203.20
- Pasir beton 0.080 M³ x Rp. 360,000.00 = Rp. 28,800.00
- Koral beton 0.125 M³ x Rp. 727,600.50 = Rp. 90,950.06
- Semen porland 49.000 Kg x Rp. 1,800.00 = Rp. 88,200.00
- Besi beton 34.500 Kg x Rp. 13,200.00 = Rp. 455,400.00
- Kawat beton 0.700 Kg x Rp. 21,600.00 = Rp. 15,120.00
- Kayu kaso 5/7 0.027 M³ x Rp. 1,900,000.00 = Rp. 51,300.00
- Paku 0.120 Kg x Rp. 19,200.00 = Rp. 2,304.00
- Minyak bekisting 0.090 Lt x Rp. 4,800.00 = Rp. 432.00
- Plamur tembok 0.200 Kg x Rp. 24,000.00 = Rp. 4,800.00
Jumlah (1) = Rp. 742,509.26

6.13.2Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang batu 0.500 Oh x Rp. 137,500.00 = Rp. 68,750.00
- Kepala tukang 0.050 Oh x Rp. 165,000.00 = Rp. 8,250.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 172,700.00

Jumlah (1) +(2) = Rp. 915,209.26


Keuntungan+Over head 10% = Rp 91,520.93
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,006,730.19

PP 6.1. 1 M' Pekerjaan Boring

6.13.1Alat
- Alat bantu 1.000 Ls x Rp. 90,000.00 = Rp. 90,000.00

Tenaga
- Pekerja 0.220 Oh x Rp. 110,000.00 = Rp. 24,200.00
- Mandor 0.044 Oh x Rp. 192,500.00 = Rp. 8,470.00
Jumlah (2) = Rp. 32,670.00

Jumlah (1) + (2) = Rp. 122,670.00


Keuntungan+Over head 10% = Rp 12,267.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 134,937.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PERSIAPAN

PA 6.1. 1 m' Pagar Sementara dari kayu tinggi 2 meter

6.1.1. Bahan
- Kayu Laut/Dolken Ø 8-10/400 cm 1.250 Btg x Rp 18,648 = Rp 23,310.00
- Semen Portland 5.000 Kg x Rp 1,800 = Rp 9,000.00
- Pasir Beton 0.005 M3 x Rp 360,000 = Rp 1,800.00
- Koral Beton 0.009 M3 x Rp 209,601 = Rp 1,886.40
- Kayu 5/7 0.072 M3 x Rp 1,900,000 = Rp 136,800.00
- Paku Biasa 2" - 5" 0.060 Kg x Rp 19,200 = Rp 1,152.00
- Residu/colter 0.400 Lt x Rp 4,800 = Rp 1,920.00
Jumlah (1) = Rp 175,868.40

6.1.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 137,500 = Rp 27,500.00
- Pekerja 0.400 Oh x Rp 110,000 = Rp 44,000.00
- Kepala tukang 0.020 Oh x Rp 165,000 = Rp 3,300.00
- Mandor 0.020 Oh x Rp 192,500 = Rp 3,850.00
Jumlah (2) = Rp 78,650.00

Jumlah (1) + (2) = Rp 254,518.40


Keuntungan+Over head 10% = Rp 25,451.84
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 279,970.24

PA 6.2. 1 m' Pagar sementara dari seng gelombang tinggi 2 meter

6.2.1. Bahan
- Kayu Laut/Dolken Ø 8-10/400 cm 1.250 Btg x Rp 18,648 = Rp 23,310.00
- Semen Portland 2.500 Kg x Rp 1,800 = Rp 4,500.00
- Seng Gelombang 1.200 Lbr x Rp 85,200 = Rp 102,240.00
- Pasir beton 0.005 M3 x Rp 360,000 = Rp 1,800.00
- Koral beton 0.009 M3 x Rp 209,601 = Rp 1,886.40
- Kayu 5/7 0.072 M3 x Rp 1,900,000 = Rp 136,800.00
- Paku biasa 2" - 5" 0.060 Kg x Rp 19,200 = Rp 1,152.00
- Meni besi 0.450 Kg x Rp 37,200 = Rp 16,740.00
Jumlah (1) = Rp 288,428.40

6.2.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 137,500 = Rp 27,500.00
- Pekerja 0.400 Oh x Rp 110,000 = Rp 44,000.00
- Kepala tukang 0.020 Oh x Rp 165,000 = Rp 3,300.00
- Mandor 0.020 Oh x Rp 192,500 = Rp 3,850.00
Jumlah (2) = Rp 78,650.00

Jumlah (1) + (2) = Rp 367,078.40


Keuntungan+Over head 10% = Rp 36,707.84
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 403,786.24

PA 6.3 1 m' Pagar sementara dari kawat duri tinggi 1,8 meter

6.3.1. Bahan
- Kayu Laut/Dolken Ø 8-10/400 cm 1.000 Btg x Rp 18,648 = Rp 18,648.00
- Semen Portland 2.000 Kg x Rp 1,800 = Rp 3,600.00
- Kawat duri 1.625 Kg x Rp 7,200 = Rp 11,700.00
- Pasir beton 0.005 M3 x Rp 360,000 = Rp 1,800.00
- Koral beton 0.009 M3 x Rp 209,601 = Rp 1,886.40
- Paku biasa 2" - 5" 0.060 Kg x Rp 19,200 = Rp 1,152.00
Jumlah (1) = Rp 38,786.40

6.3.2. Tenaga
- Tukang kayu 0.300 Oh x Rp 137,500 = Rp 41,250.00
- Pekerja 0.200 Oh x Rp 110,000 = Rp 22,000.00
- Kepala tukang 0.020 Oh x Rp 165,000 = Rp 3,300.00
- Mandor 0.020 Oh x Rp 192,500 = Rp 3,850.00
Jumlah (2) = Rp 70,400.00

Jumlah (1) + (2) = Rp 109,186.40


Keuntungan+Over head 10% = Rp 10,918.64
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 120,105.04

PP 2.1 1 m' Pengukuran dan Pemasangan bouplank

2.1.1 Bahan
- Kayu 5/7 0.012 M3 x Rp 1,900,000 = Rp 22,800.00
- Paku biasa 2" - 5" 0.020 Kg x Rp 19,200 = Rp 384.00
- Kayu papan 3/20 0.007 M3 x Rp 1,900,000 = Rp 13,300.00
Jumlah (1) = Rp 36,484.00

2.1.2 Tenaga
- Tukang kayu 0.100 Oh x Rp 137,500 = Rp 13,750.00
- Pekerja 0.100 Oh x Rp 110,000 = Rp 11,000.00
- Kepala tukang 0.010 Oh x Rp 165,000 = Rp 1,650.00
- Mandor 0.005 Oh x Rp 192,500 = Rp 962.50
Jumlah (2) = Rp 27,362.50

Jumlah (1) + (2) = Rp 63,846.50

PA 6.5 1 m2 Pembuatan Kantor Sementara dengan Lantai Plesteran

6.5.1. Bahan
- Kayu Laut/Dolken Ø 8-10/400 cm 1.250 Btg x Rp 18,648 = Rp 23,310.00
- Kayu 0.180 M3 x Rp 1,900,000 = Rp 342,000.00
- Batu Belah/Kali 15 - 20 cm 0.850 Kg x Rp 342,000 = Rp 290,700.00
- Paku biasa 0.080 Kg x Rp 19,200 = Rp 1,536.00
- Besi Strip 1.100 Kg x Rp 22,800 = Rp 25,080.00
- Semen Portland 35.000 Kg x Rp 1,800 = Rp 63,000.00
- Pasir pasang 0.150 M3 x Rp 342,000 = Rp 51,300.00
- Pasir beton 0.100 M3 x Rp 360,000 = Rp 36,000.00
- Koral beton 0.150 M3 x Rp 727,601 = Rp 109,140.08
- Bata merah 30.000 Bh x Rp 1,200 = Rp 36,000.00
- Seng plat 0.250 Lbr x Rp 194,400 = Rp 48,600.00
- Jendela nako 0.200 Bh x Rp 489,600 = Rp 97,920.00
- Kaca polos 0.080 M2 x Rp 103,200 = Rp 8,256.00
- Kunci tanam 0.150 Bh x Rp 168,000 = Rp 25,200.00
- Plywood 4 mm 0.060 Lbr x Rp 62,304 = Rp 3,738.24
Jumlah (1) = Rp 1,161,780.32
6.5.2. Tenaga
- Tukang kayu 2.000 Oh x Rp 137,500 = Rp 275,000.00
- Tukang batu 1.000 Oh x Rp 137,500 = Rp 137,500.00
- Pekerja 2.000 Oh x Rp 110,000 = Rp 220,000.00
- Kepala tukang 0.300 Oh x Rp 165,000 = Rp 49,500.00
- Mandor 0.050 Oh x Rp 192,500 = Rp 9,625.00
Jumlah (2) = Rp 691,625.00

Jumlah (1) + (2) = Rp 1,853,405.32


Keuntungan+Over head 10% = Rp 185,340.53
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 2,038,745.85

PP 2.2 1 m² Pembuatan gudang semen dan alat - alat

2.2.1 Bahan
- Kayu Laut/Dolken Ø 8-10/400 cm 1.700 Btg x Rp 18,648 = Rp 31,701.60
- Kayu 0.210 M3 x Rp 1,900,000 = Rp 399,000.00
- Paku biasa 0.300 Kg x Rp 19,200 = Rp 5,760.00
- Semen Portland 10.500 Kg x Rp 1,800 = Rp 18,900.00
- Pasir beton 0.030 M3 x Rp 360,000 = Rp 10,800.00
- Koral beton 0.050 M3 x Rp 727,601 = Rp 36,380.03
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 85,200 = Rp 127,800.00
Jumlah (1) = Rp 630,341.63

2.2.2 Tenaga
- Tukang kayu 0.200 Oh x Rp 137,500 = Rp 27,500.00
- Pekerja 0.400 Oh x Rp 110,000 = Rp 44,000.00
- Kepala tukang 0.020 Oh x Rp 165,000 = Rp 3,300.00
- Mandor 0.020 Oh x Rp 192,500 = Rp 3,850.00
Jumlah (2) = Rp 78,650.00

Jumlah (1) + (2) = '' 708,991.63


DAFTAR HARGA SATUAN UPAH DAN BAHAN
PEKERJAAN PEMBANGUNAN GEDUNG NEGARA
TAHUN ANGGARAN 2021

NO. URAIAN HARGA UPAH HARGA SATUAN


1 2 3 4

1 Pekerja @Rp. 110,000.00 / OH


2 Mandor @Rp. 192,500.00 / OH
3 Tukang Batu @Rp. 137,500.00 / OH
4 Tukang Kayu @Rp. 137,500.00 / OH
5 Tukang Besi @Rp. 137,500.00 / OH
6 Tukang Keramik @Rp. 137,500.00 / OH
7 Tukang Plafond @Rp. 137,500.00 / OH
8 Tukang Pasang Pipa @Rp. 137,500.00 / OH
9 Tukang Cat @Rp. 137,500.00 / OH
10 Tukang Setengah Terampil @Rp. 99,000.00 / OH
11 Kepala Tukang @Rp. 165,000.00 / OH
12 Alat Bantu @Rp. 93,500.00 / Jam

NO. URAIAN HARGA BAHAN HARGA SATUAN


1 2 3 4

A TIMBUNAN / GALIAN
1 Tanah Timbun/Merah @Rp. 124,800.00 / M3
2 Pasir Timbun / Urug @Rp. 325,200.00 / M3
3 Pasir Pasang @Rp. 342,000.00 / M3
4 Pasir beton @Rp. 360,000.00 / M3
5 Sirtu @Rp. 328,800.00 / M3
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
6 Tanah Humus @Rp. 267,600.00 / M3

B BAHAN PEREKAT
1 Portland Cement (PC) 50 Kg @Rp. 1,800.00 / Kg
2 Cement Putih @Rp. 13,200.00 / Kg
3 Lem Kayu @Rp. 104,400.00 / Kg
4 Lem Vinyl / Karet @Rp. 126,000.00 / Kg
5 Perekat Kaca @Rp. 214,800.00 / Kg
6 Waterfroof @Rp. 99,600.00 / Kg

C BATU / BATU CETAKAN


1 Batu Krikil / Koral 3 - 5 cm @Rp. 727,600.50 / M3
2 Batu Krikil / Koral 5 - 7 cm @Rp. 209,600.50 / M3
3 Batu Krikil / Koral 7 - 10 cm @Rp. 291,600.00 / M3
4 Batu Belah/Kali 10 - 15 cm @Rp. 298,800.00 / M3
5 Batu Belah/Kali 15 - 20 cm @Rp. 342,000.00 / M3
6 Batu Pecah 1 - 2 cm @Rp. 369,600.00 / M3
7 Batu Pecah 2 - 3 cm @Rp. 325,200.00 / M3
8 Batu Pecah 3 - 5 cm @Rp. 337,200.00 / M3
9 Batu Pecah 5 - 7 cm @Rp. 280,800.00 / M3
10 Batu Kacang /jagung 0,5 - 1 cm @Rp. 379,200.00 / M3
11 Batu Splyt @Rp. 298,800.00 / M3
Bata ringan 100x200x600 @Rp. 1,536,000.00 / M3
Bata ringan 100x400x600 @Rp. 1,564,800.00 / M3
12 Batu Bata biasa 5x10x20 cm @Rp. 1,200.00 / Bh
13 Batu Bata Mesin 5x10x20 cm @Rp. 1,920.00 / Bh
14 Batu Bataco 6x12x24 cm @Rp. 3,600.00 / Bh
15 Batu Krawang 10x10x20 cm @Rp. 6,000.00 / Bh
16 Batu Krawang 10x15x15 cm @Rp. 6,000.00 / Bh
17 Batu Krawang 10x20x20 cm @Rp. 7,200.00 / Bh
18 Concrete Block (CB) 10 @Rp. 6,000.00 / Bh
19 Concrete Block (CB) 15 @Rp. 8,400.00 / Bh
20 Concrete Block (CB) 20 @Rp. 13,200.00 / Bh
21 Bondbeam 40x20x20 cm @Rp. 25,200.00 / Bh
22 Con Block warna type Holland tb 6 cm @Rp. 2,064.00 / Bh
23 Con Block warna type Uni pave tb 6 cm @Rp. 1,920.00 / Bh
24 Con Block warna type Dosex Six tb 6 cm @Rp. 2,208.00 / Bh
25 Con Block warna type Hexagon tb 6 cm @Rp. 2,052.00 / Bh
26 Con Block K 125 @Rp. 2,100.00 / Bh
27 Con Block K 175 @Rp. 3,240.00 / Bh
28 Kanstin taman type S (uk. 60x30x24) @Rp. 80,400.00 / Bh
29 Kanstin DKI (uk. 60x28x18) @Rp. 80,400.00 / Bh

D KAYU / LANGIT - LANGIT


1 Balok Kayu Jati @Rp. 28,710,000.00 / M3
2 Papan Kayu Jati @Rp. 28,925,328.00 / M3
3 Balok Kayu Damar Laut @Rp. 11,220,000.00 / M3
4 Papan Kayu Damar Laut @Rp. 11,580,000.00 / M3
5 Balok Kayu Meranti Batu @Rp. 10,890,000.00 / M3
6 Papan Kayu Meranti Batu @Rp. 11,250,000.00 / M3
7 Balok Kayu Kapur @Rp. 7,788,000.00 / M3
8 Papan kayu Kapur @Rp. 8,148,000.00 / M3
9 Balok Kayu Meranti Kls I @Rp. 6,270,000.00 / M3
10 Papan Kayu Meranti Kls I @Rp. 6,570,000.00 / M3
11 Kayu Sembarang/Bekisting @Rp. 1,900,000.00 / M3
12 Kayu Bakar @Rp. 224,400.00 / M3
13 Papan Lambersering/Rider @Rp. 270,000.00 / M2
14 Kayu Lat Asbes 5x30x400 mm @Rp. 8,916.00 / Btg
15 Kayu Kaso 5 - 7 /400 cm @Rp. 68,400.00 / Btg
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
16 Kayu Dolken / Kayu Laut Ø 7,5 - 10 / 400 cm @Rp. 18,648.00 / Btg
17 Bambu Ø 6 - 8 /600 cm @Rp. 43,200.00 / Btg
18 Bilik Bambu @Rp. 19,608.00 / M2
19 Kayu Profil 1" @Rp. 7,524.00 / M'
20 Kayu Profil 2" @Rp. 15,048.00 / M'
21 Kayu Profil 3" @Rp. 22,572.00 / M'
22 Kayu Profil 4" @Rp. 30,096.00 / M'
23 Profil Gypsum 2" @Rp. 5,520.00 / M'
24 Profil Gypsum 3" @Rp. 6,540.00 / M'
25 Profil Gypsum 4" @Rp. 7,992.00 / M'
26 Profil Gypsum 6" @Rp. 9,444.00 / M'
27 Plywood 120x240 tbl. 18 mm @Rp. 280,368.00 / Lbr
28 Plywood 120x240 tbl. 12 mm @Rp. 186,912.00 / Lbr
29 Plywood 120x240 tbl. 9 mm @Rp. 160,800.00 / Lbr
30 Plywood 120x240 tbl. 6 mm @Rp. 93,456.00 / Lbr
31 Plywood 120x240 tbl. 4 mm @Rp. 62,304.00 / Lbr
32 Teakwood 120x240 tbl. 3 mm @Rp. 156,000.00 / Lbr
33 Triplek Jati 120x240 tbl. 3 mm @Rp. 102,300.00 / Lbr
34 Triplek Sungkai 120x240 tbl. 3 mm @Rp. 56,400.00 / Lbr
35 Formika 120x240 @Rp. 89,100.00 / Lbr
36 Soft Board 120x240 tbl. 4 mm @Rp. 67,188.00 / Lbr
37 Soft Board 120x240 tbl. 6 mm @Rp. 100,980.00 / Lbr
38 Soft Board 120x240 tbl. 9 mm @Rp. 151,476.00 / Lbr
39 Soft Board 120x240 tbl. 12 mm @Rp. 201,900.00 / Lbr
40 Gypsum 120x240 tbl. 6 mm @Rp. 71,940.00 / Lbr
41 Gypsum 120x240 tbl. 9 mm @Rp. 108,000.00 / Lbr
42 Gypsum 120x240 tbl. 12 mm @Rp. 112,200.00 / Lbr
43 Asbes Lokal 100x100 cm @Rp. 11,220.00 / Lbr
44 Asbes Atrisco 100x100 cm t= 4 mm @Rp. 13,860.00 / Lbr
45 Asbes Atrisco 100x100 cm t= 5 mm @Rp. 17,328.00 / Lbr
46 Asbes Atrisco 100x100 cm t= 6 mm @Rp. 20,796.00 / Lbr
47 Akustik 30x30 cm @Rp. 10,248.00 / Lbr
48 Akustik 30x60 cm @Rp. 20,484.00 / Lbr
49 Akustik 60x120 cm @Rp. 81,948.00 / Lbr
50 Rangka Furing Ceiling Gypsum @Rp. 62,700.00 / M2
51 Rangka Furing Dinding Gypsum @Rp. 76,560.00 / M2
52 Tepung Dempul @Rp. 6,000.00 / Kg
53 Kain kasa/Paper Tape @Rp. 69,300.00 / Roll

E BESI / ALUMINIUM
1 Besi Beton polos @Rp. 13,200.00 / Kg
2 Besi Beton Ulir @Rp. 13,200.00 / Kg
3 Besi Profil WF/INP @Rp. 19,200.00 / Kg
4 Besi siku @Rp. 22,800.00 / Kg
5 Besi CNP @Rp. 25,200.00 / Kg
6 Besi Plat Strip @Rp. 22,800.00 / Kg
7 Besi Plat Polos @Rp. 25,200.00 / Kg
8 Kawat Besi Beton @Rp. 21,600.00 / Kg
9 Kawat Licin / Seng Polos @Rp. 42,000.00 / Kg
10 Kawat Duri @Rp. 7,200.00 / M'
11 Kawat Nyamuk @Rp. 22,800.00 / M2
12 Kawat Kasa @Rp. 26,400.00 / M2
13 Kawat Harmonika # 1" @Rp. 43,200.00 / M2
14 Kawat Burung @Rp. 24,000.00 / M2
15 Pagar kawat BRC 120 Polos @Rp. 307,200.00 / Lbr
16 Pintu Besi @Rp. 1,528,800.00 / M2
17 Pintu gulung Besi @Rp. 1,551,600.00 / M2
18 Pintu Lipat Besi @Rp. 1,567,200.00 / M2
19 Pintu Rolling Door @Rp. 872,400.00 / M2
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
20 Jerajak besi Bermotif @Rp. 650,400.00 / M2
21 Jerajak Besi Strip @Rp. 584,400.00 / M2
22 Rangka Baja Ringan @Rp. 72,000.00 / M2
23 Kosen Pintu Aluminium (80 x 210) Coklat @Rp. 758,400.00 / Bh
24 Kosen Pintu Aluminium (80 x 210) Putih @Rp. 694,800.00 / Bh
25 Kosen Jendela aluminium (120x60) Coklat @Rp. 537,600.00 / Bh
26 Kosen Jendela aluminium (120x60) Putih @Rp. 464,400.00 / Bh
27 Pintu Aluminium ( 80 x 210) Coklat @Rp. 1,332,000.00 / Bh
28 Pintu Aluminium ( 80 x 210) Putih @Rp. 1,142,400.00 / Bh
29 Jendela Aluminium + Kaca 5 mm (120 x 60) Coklat @Rp. 570,000.00 / Bh
30 Jendela Aluminium + Kaca 5 mm (120 x 60) Putih @Rp. 489,600.00 / Bh
31 Kosen Pintu / Jendela Aluminium Coklat @Rp. 97,200.00 / M'
32 Kosen Pintu / Jendela Aluminium Putih @Rp. 122,400.00 / M'
33 Daun Jendela Aluminium Coklat @Rp. 102,000.00 / M'
34 Daun Jendela Aluminium Putih @Rp. 91,200.00 / M'
35 Profil Aluminium T @Rp. 16,800.00 / M'
36 Ventions Blinds @Rp. 306,000.00 / M2
37 Verticals Blinds @Rp. 328,800.00 / M2
38 Bingkai Naco Niki Hitam @Rp. 376,800.00 / M2
39 Bingkai Naco Niki Putih @Rp. 314,400.00 / M2
40 Paku Beton 0,5 - 2" @Rp. 1,200.00 / Bh
41 Paku Beton 2" - 5" @Rp. 1,920.00 / Bh
42 Paku Biasa 0,5 - 2" @Rp. 19,200.00 / Kg
43 Paku Biasa 2" - 5" @Rp. 19,200.00 / Kg
44 Sekrup macam ukuran @Rp. 39,600.00 / Kg
45 Sekrup 0,5 - 2" @Rp. 1,200.00 / Bh
46 Sekrup fisher @Rp. 1,200.00 / Bh
47 Baut Ø 5/8" - 8" @Rp. 21,600.00 / Bh
48 Baut Angker Ø 3/4" - 10" @Rp. 85,200.00 / Bh
49 Baut Ramset / Dina Bolt @Rp. 2,400.00 / Bh
50 Rangka Atap Twin light @Rp. 566,400.00 / M2
51 Metal stut @Rp. 90,000.00 / btg

F PENUTUP LANTAI DAN DINDING


1 Ubin Granito 30 x 30 cm @Rp. 32,400.00 / Bh
2 Ubin Granito 40 x 40 cm @Rp. 72,000.00 / Bh
3 Ubin Granito 60 x 60 cm @Rp. 130,800.00 / Bh
4 Ubin Mosaik 30 x 30 cm @Rp. 18,000.00 / Bh
5 Ubin Marmer Ex. DN @Rp. 540,000.00 / M2
6 Ubin teralux marmer 30 x 30 cm @Rp. 32,676.00 / Bh
7 Ubin teralux marmer 40 x 40 cm @Rp. 58,080.00 / Bh
8 Ubin teralux marmer 60 x 60 cm @Rp. 131,412.00 / Bh
9 Ubin keramik 10 x 20 cm warna @Rp. 1,800.00 / Bh
10 Ubin keramik 15 x 15 cm warna @Rp. 1,800.00 / Bh
11 Ubin keramik 20 x 20 cm warna @Rp. 3,000.00 / Bh
12 Ubin keramik 20 x 25 cm warna @Rp. 3,600.00 / Bh
13 Ubin keramik 25 x 25 cm warna @Rp. 4,800.00 / Bh
14 Ubin keramik 30 x 30 cm warna @Rp. 10,200.00 / Bh
15 Ubin keramik 30 x 30 cm anti slip warna @Rp. 13,800.00 / Bh
16 Ubin keramik 40 x 40 cm warna @Rp. 28,200.00 / Bh
17 Ubin keramik 60 x 60 cm warna @Rp. 48,000.00 / Bh
18 Ubin keramik 80 x 80 cm warna @Rp. 132,000.00 / Bh
19 Ubin keramik 100 x 100 cm warna @Rp. 156,000.00 / Bh
20 Ubin keramik artistik 5 x 20 cm @Rp. 1,200.00 / Bh
21 Ubin keramik artistik 10 x 10 cm @Rp. 1,200.00 / Bh
22 Ubin keramik artistik 10 x 20 cm @Rp. 2,400.00 / Bh
23 Ubin keramik Essenza 30 x 30 cm @Rp. 25,416.00 / Bh
24 Ubin keramik Essenza 40 x 40 cm @Rp. 45,156.00 / Bh
25 Porselin 11 x 11 cm Putih @Rp. 1,200.00 / Bh
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
0.00
26 Porselin 11 x 11 cm, warna @Rp. 2,400.00 / Bh
27 Porselin 15 x 15 cm, putih @Rp. 2,400.00 / Bh
28 Porselin 15 x 15 cm, warna @Rp. 3,600.00 / Bh
29 Plint ubin teralux marmer 10 x 30 cm @Rp. 19,608.00 / Bh
30 Plint ubin teralux marmer 10 x 40 cm @Rp. 34,848.00 / Bh
31 Plint ubin teralux marmer 10 x 60 cm @Rp. 78,840.00 / Bh
32 Plint ubin granito 10 x 30 cm @Rp. 34,800.00 / Bh
33 Plint ubin granito 10 x 40 cm @Rp. 79,200.00 / Bh
34 Plint ubin granito 10 x 60 cm @Rp. 195,600.00 / Bh
35 Plint ubin keramik 10 x 30 cm @Rp. 4,800.00 / Bh
36 Plint ubin keramik 10 x 40 cm @Rp. 7,200.00 / Bh
37 Plint ubin keramik 10 x 60 cm @Rp. 9,600.00 / Bh
38 Plint ubin keramik 15 x 30 cm @Rp. 7,200.00 / Bh
39 Plint ubin keramik 15 x 40 cm @Rp. 9,600.00 / Bh
40 Plint ubin keramik 15 x 60 cm @Rp. 14,400.00 / Bh
41 Batu Lapis Dinding 7x3x24 @Rp. 2,400.00 / Bh
42 Batu Tempel Hitam @Rp. 130,800.00 / M2
43 Batu Poros @Rp. 144,000.00 / M2
44 Carpet @Rp. 114,000.00 / M2
45 Carpet 80 % wool, 20 % nylon @Rp. 108,000.00 / M2
46 Feltex carpet 100 % wool-T-21 @Rp. 105,600.00 / M2
47 Underlyer tebal 6 mm / rubber corrugated @Rp. 130,800.00 / M2
48 Vynil asbes 30 x 30 cm @Rp. 9,600.00 / Bh
49 Vynil karet 30 x 30 cm KL I @Rp. 12,000.00 / Bh
50 Vynil karet 30 x 30 cm KL II @Rp. 10,800.00 / Bh
51 Vynil motif kembang ex DN 30 x 30 cm @Rp. 10,800.00 / Bh
52 Vynil wall covering lebar 50 cm @Rp. 79,200.00 / M2
53 Perquet Jati @Rp. 460,800.00 / M2
54 Gymfloor @Rp. 99,600.00 / M2
55 Paku Pancing 60 - 230 @Rp. 1,200.00 / Bh
56 Sekrup 3,5" @Rp. 1,200.00 / Bh
57 Sekrup 3,5" @Rp. 25,200.00 / Kg

G PENUTUP ATAP
1 Atap Genteng Palentong @Rp. 3,600.00 / Bh
2 Atap Genteng Palentong super @Rp. 7,200.00 / Bh
3 Atap Genteng Kodok @Rp. 3,600.00 / Bh
4 Atap Genteng Beton @Rp. 10,800.00 / Bh
5 Atap Genteng Keramik @Rp. 14,400.00 / Bh
6 Atap Genteng Aspal @Rp. 21,600.00 / Lbr
7 Atap Genteng Metal/Multi Roof 35 @Rp. 120,000.00 / M2
8 Atap Genteng Asbes cement 0,35 @Rp. 124,800.00 / Lbr
9 Atap Sirap @Rp. 2,400.00 / Bh
10 Atap Aluminium gelombang tebal 0,55 @Rp. 183,600.00 / Lbr
11 Atap seng Gelombang 3' x 6' bjls 35 @Rp. 85,200.00 / Lbr
12 Atap seng Super Deck 3' x 6' tbl 0,30 @Rp. 128,400.00 / Lbr
13 Roof light fibreglass gelombang @Rp. 87,600.00 / Lbr
14 Atap Asbes Gelombang 1,8 x 1,05 tbl.4 mm @Rp. 66,000.00 / Lbr
15 Atap Asbes Gelombang 2,1 x 1,05 tbl.4 mm @Rp. 76,800.00 / Lbr
16 Atap Asbes Gelombang 2,4 x 1,05 tbl.4 mm @Rp. 87,600.00 / Lbr
17 Atap Asbes Gelombang 2,7 x 1,05 tbl.4 mm @Rp. 111,600.00 / Lbr
18 Atap Asbes Gelombang 1,8 x 0,92 tbl.5 mm @Rp. 132,000.00 / Lbr
19 Atap Asbes Gelombang 2,1 x 0,92 tbl.5 mm @Rp. 96,000.00 / Lbr
20 Atap Asbes Gelombang 2,4 x 0,92 tbl.5 mm @Rp. 108,000.00 / Lbr
21 Atap Asbes Gelombang 2,7 x 0,92 tbl.5 mm @Rp. 199,200.00 / Lbr
22 Atap Asbes Gelombang 1,8 x 1,08 tbl.6 mm @Rp. 193,200.00 / Lbr
23 Atap Asbes Gelombang 2,1 x 1,08 tbl.6 mm @Rp. 225,600.00 / Lbr
24 Atap Asbes Gelombang 2,4 x 1,08 tbl.6 mm @Rp. 241,200.00 / Lbr
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
25 Atap Asbes Gelombang 2,7 x 1,08 tbl.6 mm @Rp. 290,400.00 / Lbr
26 Genteng bubung palentong @Rp. 18,000.00 / Bh
27 Genteng bubung palentong super @Rp. 24,000.00 / Bh
28 Genteng bubung kodok @Rp. 18,000.00 / Bh
29 Nok genteng beton @Rp. 25,200.00 / Bh
30 Nok genteng keramik @Rp. 28,800.00 / Bh
31 Nok Genteng Aspal @Rp. 55,200.00 / Bh
32 Nok Genteng Metal/Multi Roof (decra bond) @Rp. 76,800.00 / Bh
33 Nok Genteng Asbes cement 0,35 @Rp. 63,600.00 / Lbr
34 Nok Aluminium standard 40 cm 18 swg22 @Rp. 90,000.00 / M2
35 Bubung/Nok Stel Gelombang 0,92 m' tbl.5 mm @Rp. 36,000.00 / Lbr
36 Bubung/Nok Stel Gelombang 1,05 m' tbl.4 mm @Rp. 49,200.00 / Lbr
37 Bubung/Nok Stel Gelombang 1,08 m' tbl.6 mm @Rp. 54,000.00 / Lbr
38 Bubung/Nok Paten 0,92 m' tbl.5 mm @Rp. 68,400.00 / Lbr
39 Bubung/Nok Paten 1,05 m' tbl.4 mm @Rp. 57,600.00 / Lbr
40 Bubung/Nok Paten 1,08 m' tbl.6 mm @Rp. 80,400.00 / Lbr
41 Bubung/Nok Stel Rata 0,92 m' tbl.5 mm @Rp. 67,200.00 / Lbr
42 Bubung/Nok Stel Rata 1,05 m' tbl.4 mm @Rp. 56,400.00 / Lbr
43 Bubung/Nok Stel Rata 1,08 m' tbl.6 mm @Rp. 75,600.00 / Lbr
44 Seng Plat 3" x 6" bjls 35 @Rp. 216,000.00 / Lbr
45 Seng Plat 3" x 6" bjls 30 @Rp. 194,400.00 / Lbr
46 Plastic aerator @Rp. 51,600.00 / Bh
47 Plastik bond breaker @Rp. 3,600.00 / M2
48 Sisalation / aluminium foil @Rp. 145,200.00 / M2
49 Paku seng + Ring karet @Rp. 38,400.00 / Kg
50 Paku seng + Ring karet @Rp. 1,200.00 / Bh
51 Paku hak panjang 15 cm @Rp. 57,600.00 / Kg
52 Atap Seng Alumi Zinc warna 0,35 @Rp. 116,400.00 / M2
53 Atap Twin light @Rp. 138,000.00 / M2
54 Kalsiplank uk. 2,4m' x 0,25m x 9mm @Rp. 74,400.00 / Lbr

H KUNCI DAN KACA


1 Kunci tanam antik @Rp. 402,000.00 / Bh
2 Kunci tanam biasa @Rp. 168,000.00 / Bh
3 Kunci tanam kamar mandi @Rp. 102,000.00 / Bh
4 Kunci silinder @Rp. 64,800.00 / Bh
5 Kunci selot @Rp. 51,600.00 / Bh
6 Kunci lemari @Rp. 24,000.00 / Bh
7 Engsel pintu 4" @Rp. 28,800.00 / Bh
8 Engsel jendela 3" @Rp. 27,600.00 / Bh
9 Engsel angin @Rp. 48,000.00 / Bh
10 Kait angin @Rp. 36,000.00 / Bh
11 Rel pintu dorong @Rp. 300,000.00 / Bh
12 Sealent @Rp. 73,200.00 / Kg
13 Spring Knip @Rp. 18,000.00 / Bh
14 Door closer @Rp. 206,400.00 / Bh
15 Door handle @Rp. 212,400.00 / Bh
16 Door stoop @Rp. 70,800.00 / Bh
17 Espanyolet @Rp. 165,600.00 / Bh
18 Kaca Block 20 x 20 cm @Rp. 49,200.00 / Bh
19 Kaca polos tbl.3 mm @Rp. 103,200.00 / M2
20 Kaca polos tbl.5 mm @Rp. 141,600.00 / M2
21 Kaca polos tbl.8 mm @Rp. 540,000.00 / M2
22 Kaca Reyben tbl.5 mm @Rp. 126,000.00 / M2
23 Kaca Reyben tbl.8 mm @Rp. 578,400.00 / M2
24 Kaca Buram tbl.3 mm @Rp. 135,600.00 / M2
25 Kaca Buram tbl.5 mm @Rp. 208,800.00 / M2
26 Kaca buram tbl.8 mm @Rp. 362,400.00 / M2
27 Kaca cermin tbl.5 mm @Rp. 303,600.00 / M2
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
28 Kaca cermin tbl.6 mm @Rp. 363,600.00 / M2
29 Kaca cermin tbl.8 mm @Rp. 484,800.00 / M2
30 Kaca patri @Rp. 316,800.00 / M2
31 Kaca Wireglass @Rp. 283,200.00 / M2
32 Kaca Reyben Naco 30 x 60 cm tbl.5 mm @Rp. 25,200.00 / Lbr
33 Kaca Bening Naco 30 x 60 cm tbl.5 mm @Rp. 20,400.00 / Lbr

I CAT / MINYAK
1 Cat dasar @Rp. 38,400.00 / Kg
2 Cat Tembok setara Vinilex @Rp. 38,400.00 / Kg
3 Cat Minyak untuk kayu @Rp. 74,400.00 / Kg
4 Cat Minyak untuk Besi @Rp. 74,400.00 / Kg
5 Cat Menie kayu @Rp. 37,200.00 / Kg
6 Cat Menie besi @Rp. 37,200.00 / Kg
7 Cat sending @Rp. 102,000.00 / Kg
8 Cat Melamix @Rp. 111,600.00 / Kg
9 Cat Vernis Jadi @Rp. 90,000.00 / Kg
10 Plamir @Rp. 24,000.00 / Kg
11 Dempul gypsum @Rp. 6,000.00 / Kg
12 Dempul Cat @Rp. 22,800.00 / Kg
13 Minyak Cat @Rp. 22,800.00 / Kg
14 Minyak Bekisting @Rp. 4,800.00 / Ltr
15 Residu / Kolter @Rp. 4,800.00 / Ltr
16 Soda api @Rp. 22,800.00 / Kg
17 Sabun @Rp. 19,200.00 / Kg
18 Kuas @Rp. 12,000.00 / Bh
19 Ampelas / Kertas pasir @Rp. 6,000.00 / Lbr
20 Wall paper @Rp. 177,600.00 / M2
21 Ijuk @Rp. 12,000.00 / kg
22 Cat Marka @Rp. 115,080.00 / kg
23 Blass Bit @Rp. 48,000.00 / ltr
24 Oli @Rp. 78,000.00 / ltr
25 Thinner @Rp. 21,120.00 / ltr

J SANITASI / PIPA
1 Kloset duduk / monoblok lengkap tangki @Rp. 3,615,600.00 / Bh
2 Kloset duduk / monoblok tanpa tangki @Rp. 2,604,000.00 / Bh
3 Kloset jongkok porselin @Rp. 422,400.00 / Bh
4 Bakkif Porselin @Rp. 5,664,000.00 / Bh
5 Wastafel @Rp. 986,400.00 / Bh
6 Urinoir @Rp. 1,042,800.00 / Bh
7 Kran air Ø 1/2" - 3/4" @Rp. 51,600.00 / Bh
8 Kran air leher angsa Ø 1/2" @Rp. 163,200.00 / Bh
9 Kran shower @Rp. 60,000.00 / Bh
10 Kran Cebok @Rp. 134,400.00 / Bh
11 Bak fibreglass 0,3 M3 @Rp. 339,600.00 / Bh
12 Bak fibreglass 1 M3 @Rp. 978,000.00 / Bh
13 Bak cuci piring stainless 2 lobang @Rp. 873,600.00 / Bh
14 Bak cuci piring teraso 2 lobang @Rp. 508,800.00 / Bh
15 Tempat sabun keramik @Rp. 104,400.00 / Bh
16 Floor drain Ø 4" steinless @Rp. 28,800.00 / Bh
17 Stop kran Ø 3/4" @Rp. 51,600.00 / Bh
18 Tutup bak air Ø 1" Kuningan @Rp. 24,000.00 / Bh
19 Instalasi air bersih @Rp. 187,200.00 / Ttk
20 Instalasi air kotor/limbah @Rp. 235,200.00 / Ttk
21 Buis Beton 1/2 Ø 15 cm @Rp. 21,600.00 / M'
22 Buis Beton 1/2 Ø 20 cm @Rp. 33,600.00 / M'
23 Buis Beton 1/2 Ø 30 cm @Rp. 37,200.00 / M'
24 Buis Beton Ø 15 cm @Rp. 51,600.00 / M'
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
25 Buis Beton Ø 20 cm @Rp. 67,200.00 / M'
26 Buis Beton Ø 30 cm @Rp. 96,000.00 / M'
27 Buis Beton Ø 40 cm @Rp. 126,000.00 / M'
28 Buis Beton Ø 50 cm @Rp. 201,600.00 / M'
29 Buis Beton Ø 60 cm @Rp. 254,400.00 / M'
30 Buis Beton Ø 80 cm @Rp. 376,800.00 / M'
31 Buis Beton Ø 100 cm @Rp. 648,000.00 / M'
32 Pipa PVC Tipe AW Ø 1/2" @Rp. 48,000.00 / Btg
33 Pipa PVC Tipe AW Ø 3/4" @Rp. 13,200.00 / Btg
34 Pipa PVC Tipe AW Ø 1" @Rp. 25,200.00 / Btg
35 Pipa PVC Tipe AW Ø 1 1/2" @Rp. 37,200.00 / Btg
36 Pipa PVC Tipe AW Ø 2" @Rp. 43,200.00 / Btg
37 Pipa PVC Tipe AW Ø 2 1/2" @Rp. 50,400.00 / Btg
38 Pipa PVC Tipe AW Ø 3" @Rp. 56,400.00 / Btg
39 Pipa PVC Tipe AW Ø 4" @Rp. 93,600.00 / Btg
40 Pipa Besi Hitam Ø 1/2" @Rp. 27,600.00 / Btg
41 Pipa Besi Hitam Ø 3/4" @Rp. 37,200.00 / Btg
42 Pipa Besi Hitam Ø 1" @Rp. 55,200.00 / Btg
43 Pipa Besi Hitam Ø 1 1/2" @Rp. 69,600.00 / Btg
44 Pipa Besi Hitam Ø 2" @Rp. 88,800.00 / Btg
45 Pipa Besi Hitam Ø 2 1/2" @Rp. 93,600.00 / Btg
46 Pipa Galvanis Ø 1/2" @Rp. 27,600.00 / Btg
47 Pipa Galvanis Ø 3/4" @Rp. 37,200.00 / Btg
48 Pipa Galvanis Ø 1" @Rp. 55,200.00 / Btg
49 Pipa Galvanis Ø 1 1/4" @Rp. 62,400.00 / Btg
50 Pipa Galvanis Ø 1 1/2" @Rp. 69,600.00 / Btg
51 Pipa Galvanis Ø 2" @Rp. 88,800.00 / Btg
52 Pipa Galvanis Ø 2 1/2" @Rp. 98,400.00 / Btg
53 Fitting Pipa AW Ø 1" @Rp. 13,200.00 / Btg
54 Knee AW 1" @Rp. 9,600.00 / Bh
55 Tee AW 1" @Rp. 13,200.00 / Bh
56 Socht AW 1" @Rp. 8,400.00 / Bh
57 F-Knee 1" @Rp. 8,400.00 / Bh
58 F-Tee 1" @Rp. 21,600.00 / Bh
59 Bocht LL-D 1" @Rp. 45,600.00 / Bh
60 Union Socht 1" @Rp. 13,200.00 / Bh
61 D-Nipple 1" @Rp. 33,600.00 / Bh
62 Water Moer 1" @Rp. 55,200.00 / Bh
63 Water Drain @Rp. 12,000.00 / Bh
64 Dop PVC AW 1 " @Rp. 3,600.00 / Bh

K PIPA GI
1 Pipa GI Medium SII uk. 1/2" 214,200.00 Batang
2 Pipa GI Medium SII uk. 3/4" 283,500.00 Batang
3 Pipa GI Medium SII uk. 1" 434,700.00 Batang
4 Pipa GI Medium SII dia 1 1/4 614,250.00 Batang
5 Pipa GI Medium SII uk. 1 1/2" 642,600.00 Batang
6 Pipa GI Medium SII uk. 2" 900,900.00 Batang
7 Pipa GI Medium SII uk. 2 1/2" 1,146,600.00 Batang
8 Pipa GI Medium SII uk. 3" 1,512,000.00 Batang
9 Pipa GI Medium SII uk. 4" 2,167,200.00 Batang
10 Pipa GI Medium SII uk. 6" 3,408,300.00 Batang
11 Pipa GI Medium SII uk. 8" 5,166,000.00 Batang
12 Pipa GI Medium SII uk. 10" 6,438,600.00 Batang
13 Pipa GI Medium SII uk. 12" 9,702,000.00 Batang
14 Pipa GI Medium SII uk. 14" 11,302,200.00 Batang
15 Pipa GI Medium SII uk. 16" 12,959,100.00 Batang
16 Pipa GI Medium SII uk. 20" 17,820,000.00 Batang
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
L PIPA STEEL POLOS
1 Pipa Steel Polos Medium SII uk. 1/2" 174,510.00 Batang
2 Pipa Steel Polos Medium SII uk. 3/4" 221,760.00 Batang
3 Pipa Steel Polos Medium SII uk. 1" 340,200.00 Batang
4 Pipa Steel Polos Medium SII uk. 1 1/2" 526,680.00 Batang
5 Pipa Steel Polos Medium SII uk. 2" 700,560.00 Batang
6 Pipa Steel Polos Medium SII uk. 3" 762,300.00 Batang
7 Pipa Steel Polos Medium SII uk. 4" 1,088,010.00 Batang
8 Pipa Steel Polos Medium SII uk. 6" 2,683,800.00 Batang
9 Pipa Steel Polos Medium SII uk. 8" 5,077,800.00 Batang
10 Pipa Steel Polos Medium SII uk. 10" 6,363,000.00 Batang
11 Pipa Steel Polos Medium SII uk. 12" 7,978,320.00 Batang
12 Pipa Steel Polos Medium SII uk. 14" 8,883,000.00 Batang
13 Pipa Steel Polos Medium SII uk. 16" 10,499,580.00 Batang
14 Pipa Steel Polos Medium SII uk. 18" 15,384,600.00 Batang
15 Pipa Steel Polos Medium SII uk. 20" 18,824,400.00 Batang
16 Pipa Steel Polos Medium SII uk. 24" 22,657,320.00 Batang

M PIPA DCIP
1 Pipa DCIP Uk. 630 mm 3,572,100.00 Meter

N PIPA STEEL LINING


1 Pipa Steel Lining Cement non Wrapping dia. 6" 2,381,400.00 Batang
2 Pipa Steel Lining Cement non Wrapping dia. 8" 3,318,840.00 Batang
3 Pipa Steel Lining Cement non Wrapping dia. 10" 4,158,000.00 Batang
4 Pipa Steel Lining Cement non Wrapping dia. 12" 6,153,840.00 Batang
5 Pipa Steel Lining Cement non Wrapping dia. 14" 6,766,200.00 Batang
6 Pipa Steel Lining Cement non Wrapping dia. 16" 7,749,000.00 Batang
7 Pipa Steel Lining Cement non Wrapping dia. 18" 8,731,800.00 Batang
8 Pipa Steel Lining Cement non Wrapping dia. 20" 9,714,600.00 Batang
9 Pipa Steel Lining Cement non Wrapping dia. 22" 10,697,400.00 Batang
10 Pipa Steel Lining Cement non Wrapping dia. 24" 11,680,200.00 Batang
11 Pipa Steel Lining Cement with wrapping dia. 6" 8,164,800.00 Batang
12 Pipa Steel Lining Cement with wrapping dia. 8" 10,735,200.00 Batang
13 Pipa Steel Lining Cement with wrapping dia. 10" 13,419,000.00 Batang
14 Pipa Steel Lining Cement with wrapping dia. 12" 17,115,840.00 Batang
15 Pipa Steel Lining Cement with wrapping dia. 14" 18,805,500.00 Batang
16 Pipa Steel Lining Cement with wrapping dia. 16" 19,625,760.00 Batang
17 Pipa Steel Lining Cement with wrapping dia. 18" 24,207,120.00 Batang
18 Pipa Steel Lining Cement with wrapping dia. 20" 26,913,600.00 Batang
19 Pipa Steel Lining Cement with wrapping dia. 22" 29,612,520.00 Batang
20 Pipa Steel Lining Cement with wrapping dia. 24" 32,311,440.00 Batang

O PIPA ( TS. END) JIS


1 Pipa (Ts. End) JIS - Kelas VP 1/2" (4 meter) 41,580.00 Batang
2 Pipa (Ts. End) JIS - Kelas VP 3/4" (4 meter) 50,337.00 Batang
3 Pipa (Ts. End) JIS - Kelas VP 1" (4 meter) 72,702.00 Batang
4 Pipa (Ts. End) JIS - Kelas VP 1 1/4" (4 meter) 108,360.00 Batang
5 Pipa (Ts. End) JIS - Kelas VP 1 1/2" (4 meter) 128,142.00 Batang
6 Pipa (Ts. End) JIS - Kelas VP 2" (4 meter) 181,944.00 Batang
7 Pipa (Ts. End) JIS - Kelas VP 2 1/2" (4 meter) 234,360.00 Batang
8 Pipa (Ts. End) JIS - Kelas VP 3" (4 meter) 356,832.00 Batang
9 Pipa (Ts. End) JIS - Kelas VP 4" (4 meter) 552,258.00 Batang
10 Pipa (Ts. End) JIS - Kelas VP 5" (4 meter) 723,240.00 Batang
11 Pipa (Ts. End) JIS - Kelas VP 6" (4 meter) 1,085,616.00 Batang
12 Pipa (Ts. End) JIS - Kelas VP 8" (4 meter) 1,641,150.00 Batang
13 Pipa (Ts. End) JIS - Kelas VP 10" (4 meter) 2,508,030.00 Batang
14 Pipa (Ts. End) JIS - Kelas VP 12" (4 meter) 3,558,114.00 Batang
15 Pipa (Ts. End) JIS - Kelas VU 1 1/2" (4 meter) 67,032.00 Batang
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
16 Pipa (Ts. End) JIS - Kelas VU 2" (4 meter) 84,546.00 Batang
17 Pipa (Ts. End) JIS - Kelas VU 2 1/2" (4 meter) 133,812.00 Batang
18 Pipa (Ts. End) JIS - Kelas VU 3" (4 meter) 187,614.00 Batang
19 Pipa (Ts. End) JIS - Kelas VU 4" (4 meter) 281,484.00 Batang
20 Pipa (Ts. End) JIS - Kelas VU 5" (4 meter) 443,772.00 Batang
21 Pipa (Ts. End) JIS - Kelas VU 6" (4 meter) 638,442.00 Batang
22 Pipa (Ts. End) JIS - Kelas VU 8" (4 meter) 1,064,700.00 Batang
23 Pipa (Ts. End) JIS - Kelas VU 10" (4 meter) 1,580,796.00 Batang
24 Pipa (Ts. End) JIS - Kelas VU 12" (4 meter) 2,219,616.00 Batang

P PIPA ( BELL END) JIS


1 Pipa (Bell End) JIS - Kelas VP 2" (4 meter) 187,362.00 Batang
2 Pipa (Bell End) JIS - Kelas VP 2 1/2" (4 meter) 246,456.00 Batang
3 Pipa (Bell End) JIS - Kelas VP 3" (4 meter) 376,362.00 Batang
4 Pipa (Bell End) JIS - Kelas VP 4" (4 meter) 577,962.00 Batang
5 Pipa (Bell End) JIS - Kelas VP 5" (4 meter) 800,604.00 Batang
6 Pipa (Bell End) JIS - Kelas VP 6" (4 meter) 1,145,088.00 Batang
7 Pipa (Bell End) JIS - Kelas VP 8" (4 meter) 1,731,366.00 Batang
8 Pipa (Bell End) JIS - Kelas VP 10" (4 meter) 2,637,810.00 Batang
9 Pipa (Bell End) JIS - Kelas VP 12" (4 meter) 3,773,826.00 Batang
10 Pipa (Bell End) JIS - Kelas VU 2" (4 meter) 89,964.00 Batang
11 Pipa (Bell End) JIS - Kelas VU 2 1/2" (4 meter) 145,908.00 Batang
12 Pipa (Bell End) JIS - Kelas VU 3" (4 meter) 207,270.00 Batang
13 Pipa (Bell End) JIS - Kelas VU 4" (4 meter) 307,314.00 Batang
14 Pipa (Bell End) JIS - Kelas VU 5" (4 meter) 521,136.00 Batang
15 Pipa (Bell End) JIS - Kelas VU 6" (4 meter) 698,040.00 Batang
16 Pipa (Bell End) JIS - Kelas VU 8" (4 meter) 1,154,916.00 Batang
17 Pipa (Bell End) JIS - Kelas VU 10" (4 meter) 1,710,702.00 Batang
18 Pipa (Bell End) JIS - Kelas VU 12" (4 meter) 2,435,454.00 Batang

Q PIPA ( TS. END) SNI


1 Pipa (Ts. End) SNI S-10 20mm (1/2") RRJ S.10 4,920.00 Meter
2 Pipa (Ts. End) SNI S-10 25mm (3/4") RRJ S.10 7,320.00 Meter
3 Pipa (Ts. End) SNI S-10 32mm (1") RRJ S.10 12,120.00 Meter
4 Pipa (Ts. End) SNI S-10 40mm (1 1/4") RRJ S.10 17,760.00 Meter
5 Pipa (Ts. End) SNI S-10 50mm (1 1/2") RRJ S.10 27,720.00 Meter
6 Pipa (Ts. End) SNI S-10 63mm (2") RRJ S.10 43,200.00 Meter
7 Pipa (Ts. End) SNI S-10 75mm (2 1/2") RRJ S.10 69,000.00 Meter
8 Pipa (Ts. End) SNI S-10 90mm (3") RRJ S.10 87,900.00 Meter
9 Pipa (Ts. End) SNI S-10 110mm (4") RRJ S.10 132,000.00 Meter
10 Pipa (Ts. End) SNI S-10 140mm (5") RRJ S.10 237,600.00 Meter
11 Pipa (Ts. End) SNI S-10 160mm (6") RRJ S.10 279,600.00 Meter
12 Pipa (Ts. End) SNI S-10 200mm (8") RRJ S.10 487,200.00 Meter
13 Pipa (Ts. End) SNI S-10 225mm (8") RRJ S.10 615,600.00 Meter
14 Pipa (Ts. End) SNI S-10 250mm (10") RRJ S.10 756,378.00 Meter
15 Pipa (Ts. End) SNI S-10 315mm (12") RRJ S.10 1,207,200.00 Meter
16 Pipa (Ts. End) SNI S-10 63mm (2") RRJ S.12,5 35,280.00 Meter
17 Pipa (Ts. End) SNI S-10 75mm (2 1/2") RRJ S.12,5 56,400.00 Meter
18 Pipa (Ts. End) SNI S-10 90mm (3") RRJ S.12,5 73,200.00 Meter
19 Pipa (Ts. End) SNI S-10 110mm (4") RRJ S.12,5 106,800.00 Meter
20 Pipa (Ts. End) SNI S-10 140mm (5") RRJ S.12,5 195,600.00 Meter
21 Pipa (Ts. End) SNI S-10 160mm (6") RRJ S.12,5 229,200.00 Meter
22 Pipa (Ts. End) SNI S-10 200mm (8") RRJ S.12,5 396,000.00 Meter
23 Pipa (Ts. End) SNI S-10 225mm (8") RRJ S.12,5 498,000.00 Meter
24 Pipa (Ts. End) SNI S-10 250mm (10") RRJ S.12,5 619,200.00 Meter
25 Pipa (Ts. End) SNI S-10 315mm (12") RRJ S.12,5 988,800.00 Meter

R PIPA ( BELL END/ RRJ) SNI


1 Pipa (Bell End/RRJ) SNI S-10 63mm (2") RRJ S.10 44,478.00 Meter
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
2 Pipa (Bell End/RRJ) SNI S-10 75mm (2 1/2") RRJ S.10 71,820.00 Meter
3 Pipa (Bell End/RRJ) SNI S-10 90mm (3") RRJ S.10 90,720.00 Meter
4 Pipa (Bell End/RRJ) SNI S-10 110mm (4") RRJ S.10 135,921.60 Meter
5 Pipa (Bell End/RRJ) SNI S-10 140mm (5") RRJ S.10 248,346.00 Meter
6 Pipa (Bell End/RRJ) SNI S-10 160mm (6") RRJ S.10 285,705.60 Meter
7 Pipa (Bell End/RRJ) SNI S-10 200mm (8") RRJ S.10 446,160.00 Meter
8 Pipa (Bell End/RRJ) SNI S-10 225mm (8") RRJ S.10 636,426.00 Meter
9 Pipa (Bell End/RRJ) SNI S-10 250mm (10") RRJ S.10 693,840.00 Meter
10 Pipa (Bell End/RRJ) SNI S-10 315mm (12") RRJ S.10 1,112,400.00 Meter
11 Pipa (Bell End/RRJ) SNI S-10 355mm (14") RRJ S.10 1,617,777.00 Meter
12 Pipa (Bell End/RRJ) SNI S-10 400mm (16") RRJ S.10 1,818,936.00 Meter
13 Pipa (Bell End/RRJ) SNI S-10 450mm (18") RRJ S.10 2,712,024.00 Meter
14 Pipa (Bell End/RRJ) SNI S-10 500mm (20") RRJ S.10 2,893,905.00 Meter
15 Pipa (Bell End/RRJ) SNI S-10 630mm (24") RRJ S.10 4,687,263.00 Meter
16 Pipa (Bell End/RRJ) SNI S-10 63mm (2") RRJ S.12,5 36,729.00 Meter
17 Pipa (Bell End/RRJ) SNI S-10 75mm (2 1/2") RRJ S.12,5 59,031.00 Meter
18 Pipa (Bell End/RRJ) SNI S-10 90mm (3") RRJ S.12,5 74,875.50 Meter
19 Pipa (Bell End/RRJ) SNI S-10 110mm (4") RRJ S.12,5 110,029.50 Meter
20 Pipa (Bell End/RRJ) SNI S-10 140mm (5") RRJ S.12,5 204,876.00 Meter
21 Pipa (Bell End/RRJ) SNI S-10 160mm (6") RRJ S.12,5 234,864.00 Meter
22 Pipa (Bell End/RRJ) SNI S-10 200mm (8") RRJ S.12,5 363,447.00 Meter
23 Pipa (Bell End/RRJ) SNI S-10 225mm (8") RRJ S.12,5 516,222.00 Meter
24 Pipa (Bell End/RRJ) SNI S-10 250mm (10") RRJ S.12,5 568,701.00 Meter
25 Pipa (Bell End/RRJ) SNI S-10 315mm (12") RRJ S.12,5 914,130.00 Meter
26 Pipa (Bell End/RRJ) SNI S-10 355mm (14") RRJ S.12,5 1,326,528.00 Meter
27 Pipa (Bell End/RRJ) SNI S-10 400mm (16") RRJ S.12,5 1,479,492.00 Meter
28 Pipa (Bell End/RRJ) SNI S-10 450mm (18") RRJ S.12,5 2,223,648.00 Meter
29 Pipa (Bell End/RRJ) SNI S-10 500mm (20") RRJ S.12,5 2,356,641.00 Meter
30 Pipa (Bell End/RRJ) SNI S-10 630mm (24") RRJ S.12,5 3,827,848.50 Meter

S PIPA PVC
1 Pipa PVC (Ts. End) SNI 40mm Kelas A 1 1/4" 19,026.00 Meter
2 Pipa PVC (Ts. End) SNI 50mm Kelas A 1 1/2" 23,940.00 Meter
3 Pipa PVC (Ts. End) SNI 63mm Kelas A 2" 30,366.00 Meter
4 Pipa PVC (Ts. End) SNI 75mm Kelas A 2 1/2" 36,288.00 Meter
5 Pipa PVC (Ts. End) SNI 90mm Kelas A 3" 43,974.00 Meter
6 Pipa PVC (Ts. End) SNI 110mm Kelas A 4" 64,386.00 Meter
7 Pipa PVC (Ts. End) SNI 160mm Kelas A 6" 135,576.00 Meter
8 Pipa PVC (Ts. End) SNI 200mm Kelas A 8" 206,766.00 Meter
9 Pipa PVC (Ts. End) SNI 250mm Kelas A 10" 324,576.00 Meter
10 Pipa PVC (Ts. End) SNI 315mm Kelas A 12" 517,356.00 Meter
11 Pipa PVC (Bell End) SNI 63mm Kelas A 2" 31,626.00 Meter
12 Pipa PVC (Bell End) SNI 75mm Kelas A 2 1/2" 37,800.00 Meter
13 Pipa PVC (Bell End) SNI 90mm Kelas A 3" 45,612.00 Meter
14 Pipa PVC (Bell End) SNI 110mm Kelas A 4" 66,906.00 Meter
15 Pipa PVC (Bell End) SNI 160mm Kelas A 6" 140,616.00 Meter
16 Pipa PVC (Bell End) SNI 200mm Kelas A 8" 215,208.00 Meter
17 Pipa PVC (Bell End) SNI 250mm Kelas A 10" 338,058.00 Meter
18 Pipa PVC (Bell End) SNI 315mm Kelas A 12" 541,107.00 Meter
19 Pipa PVC (Bell End) SNI 400mm Kelas A 16" 879,165.00 Meter
20 Pipa PVC (Bell End) SNI 500mm Kelas A 20" 1,415,295.00 Meter
21 Pipa PVC (Bell End) SNI 630mm Kelas A 22" 2,216,844.00 Meter
22 Pipa PVC (Ts. End) SNI Kelas B 1 1/4" 31,374.00 Meter
23 Pipa PVC (Ts. End) SNI Kelas B 1 1/2" 39,942.00 Meter
24 Pipa PVC (Ts. End) SNI Kelas B 2" 51,156.00 Meter
25 Pipa PVC (Ts. End) SNI Kelas B 2 1/2" 61,425.00 Meter
26 Pipa PVC (Ts. End) SNI Kelas B 3" 74,277.00 Meter
27 Pipa PVC (Ts. End) SNI Kelas B 4" 91,665.00 Meter
28 Pipa PVC (Ts. End) SNI Kelas B 6" 168,084.00 Meter
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
29 Pipa PVC (Ts. End) SNI Kelas B 8" 257,040.00 Meter
30 Pipa PVC (Ts. End) SNI Kelas B 10" 405,657.00 Meter
31 Pipa PVC (Ts. End) SNI Kelas B 12" 639,324.00 Meter
32 Pipa PVC (Bell End) SNI Kelas B 2" 53,172.00 Meter
33 Pipa PVC (Bell End) SNI Kelas B 2 1/2" 63,756.00 Meter
34 Pipa PVC (Bell End) SNI Kelas B 3" 77,364.00 Meter
35 Pipa PVC (Bell End) SNI Kelas B 4" 95,382.00 Meter
36 Pipa PVC (Bell End) SNI Kelas B 6" 174,384.00 Meter
37 Pipa PVC (Bell End) SNI Kelas B 8" 267,624.00 Meter
38 Pipa PVC (Bell End) SNI Kelas B 10" 422,730.00 Meter
39 Pipa PVC (Bell End) SNI Kelas B 12" 668,808.00 Meter
40 Pipa PVC (Bell End) SNI Kelas B 16" 1,095,696.00 Meter
41 Pipa PVC (Bell End) SNI Kelas B 20" 1,735,272.00 Meter
42 Pipa PVC (Bell End) SNI Kelas B 22" 2,756,376.00 Meter

T PIPA HDPE
1 Pipa HDPE 100 PN-12.5 20mm (1/2") SNI 7,875.00 Meter
2 Pipa HDPE 100 PN-12.5 25mm (3/4") SNI 11,403.00 Meter
3 Pipa HDPE 100 PN-12.5 32mm (1") SNI 18,585.00 Meter
4 Pipa HDPE 100 PN-12.5 40mm (1 1/4") SNI 28,224.00 Meter
5 Pipa HDPE 100 PN-12.5 50mm (1 1/2") SNI 38,209.50 Meter
6 Pipa HDPE 100 PN-12.5 63mm (2") SNI 60,763.50 Meter
7 Pipa HDPE 100 PN-12.5 75mm (2 1/2") SNI 85,207.50 Meter
8 Pipa HDPE 100 PN-12.5 90mm (3") SNI 122,188.50 Meter
9 Pipa HDPE 100 PN-12.5 110mm (4") SNI 182,322.00 Meter
10 Pipa HDPE 100 PN-12.5 160mm (6") SNI 382,882.50 Meter
11 Pipa HDPE 100 PN-12.5 200mm (8") SNI 610,848.00 Meter
12 Pipa HDPE 100 PN-12.5 250mm (10") SNI 955,237.50 Meter
13 Pipa HDPE 100 PN-12.5 315mm (12") SNI 1,516,126.50 Meter
14 Pipa HDPE 100 PN-12.5 355mm (14") SNI 1,923,075.00 Meter
15 Pipa HDPE 100 PN-12.5 400mm (16") SNI 2,438,131.50 Meter
16 Pipa HDPE 100 PN-12.5 450mm (18") SNI 3,087,756.00 Meter
17 Pipa HDPE 100 PN-12.5 500mm (20") SNI 3,806,901.00 Meter
18 Pipa HDPE 100 PN-10 20mm (1/2") SNI 7,875.00 Meter
19 Pipa HDPE 100 PN-10 25mm (3/4") SNI 10,017.00 Meter
20 Pipa HDPE 100 PN-10 32mm (1") SNI 14,931.00 Meter
21 Pipa HDPE 100 PN-10 40mm (1 1/4") SNI 23,562.00 Meter
22 Pipa HDPE 100 PN-10 50mm (1 1/2") SNI 31,437.00 Meter
23 Pipa HDPE 100 PN-10 63mm (2") SNI 50,116.50 Meter
24 Pipa HDPE 100 PN-10 75mm (2 1/2") SNI 70,686.00 Meter
25 Pipa HDPE 100 PN-10 90mm (3") SNI 101,493.00 Meter
26 Pipa HDPE 100 PN-10 110mm (4") SNI 150,759.00 Meter
27 Pipa HDPE 100 PN-10 160mm (6") SNI 314,653.50 Meter
28 Pipa HDPE 100 PN-10 200mm (8") SNI 502,834.50 Meter
29 Pipa HDPE 100 PN-10 250mm (10") SNI 781,357.50 Meter
30 Pipa HDPE 100 PN-10 315mm (12") SNI 1,242,706.50 Meter
31 Pipa HDPE 100 PN-10 355mm (14") SNI 1,582,245.00 Meter
32 Pipa HDPE 100 PN-10 400mm (16") SNI 1,998,139.50 Meter
33 Pipa HDPE 100 PN-10 450mm (18") SNI 2,531,151.00 Meter
34 Pipa HDPE 100 PN-10 500mm (20") SNI 3,118,027.50 Meter
35 Pipa HDPE 100 PN-10 630.mm (24") SNI 4,950,036.00 Meter
36 Pipa HDPE 100 PN-10 710.mm (25") SNI 7,518,105.00 Meter
37 Pipa HDPE 100 PN-10 800.mm (26") SNI 9,528,750.00 Meter
38 Pipa HDPE 100 PN-8 40mm (1 1/4") SNI 18,900.00 Meter
39 Pipa HDPE 100 PN-8 50mm (1 1/2") SNI 35,178.00 Meter
40 Pipa HDPE 100 PN-8 63mm (2") SNI 55,915.20 Meter
41 Pipa HDPE 100 PN-8 75mm (2 1/2") SNI 78,421.20 Meter
42 Pipa HDPE 100 PN-8 90mm (3") SNI 112,417.80 Meter
43 Pipa HDPE 100 PN-8 110mm (4") SNI 167,811.60 Meter
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
44 Pipa HDPE 100 PN-8 160mm (6") SNI 352,440.00 Meter
45 Pipa HDPE 100 PN-8 200mm (8") SNI 562,742.40 Meter
46 Pipa HDPE 100 PN-8 250mm (10") SNI 880,030.80 Meter
47 Pipa HDPE 100 PN-8 315mm (12") SNI 1,396,751.40 Meter
48 Pipa HDPE 100 PN-8 355mm (14") SNI 1,771,618.20 Meter
49 Pipa HDPE 100 PN-8 400mm (16") SNI 2,245,419.00 Meter
50 Pipa HDPE 100 PN-8 450mm (18") SNI 2,585,952.00 Meter
51 Pipa HDPE 100 PN-8 500mm (20") SNI 3,188,220.00 Meter
52 Pipa HDPE 100 PN-8 630.mm (24") SNI 4,031,149.50 Meter
53 Pipa HDPE 100 PN-8 710.mm (25") SNI 6,128,325.00 Meter
54 Pipa HDPE 100 PN-8 800.mm (26") SNI 7,775,208.00 Meter

U PIPA BLOCK STEEL


1 Pipa Block Steel dia 4" Setara PRALON 1,020,600.00 Meter

V PIPA HEADER
1 Pipa Header GI Medium SII dia 16" 12,348,000.00 Batang

W LISTRIK / ACSESORIES
1 Lampu TL 1 x 20 W Lengkap Kotak @Rp. 65,340.00 / Set
2 Lampu TL 1 x 40 W Lengkap Kotak @Rp. 72,600.00 / Set
3 Lampu TL 2 x 20 W Lengkap Kotak @Rp. 196,020.00 / Set
4 Lampu TL 2 x 40 W Lengkap Kotak @Rp. 220,704.00 / Set
5 Lampu TL Bambu 1 x 20 W Lengkap @Rp. 130,680.00 / Set
6 Lampu TL Bambu 1 x 40 W Lengkap @Rp. 148,104.00 / Set
7 Lampu XL 5 W + Fitting @Rp. 30,492.00 / Set
8 Lampu XL 8 W + Fitting @Rp. 32,676.00 / Set
9 Lampu XL 10 W + Fitting @Rp. 34,848.00 / Set
10 Lampu XL 14 W + Fitting @Rp. 39,936.00 / Set
11 Lampu XL 18 W + Fitting @Rp. 40,656.00 / Set
12 Lampu XL 24 W + Fitting @Rp. 46,464.00 / Set
13 Lampu Downlight 5 W lengkap @Rp. 65,340.00 / Set
14 Lampu Pijar 5 w + Fitting @Rp. 9,900.00 / Set
15 Lampu Pijar 10 w + Fitting @Rp. 10,560.00 / Set
16 Lampu Pijar 15 w + Fitting @Rp. 11,220.00 / Set
17 Lampu Pijar 20 w + Fitting @Rp. 11,880.00 / Set
18 Lampu Pijar 25 w + Fitting @Rp. 12,540.00 / Set
19 Lampu Pijar 40 w + Fitting @Rp. 13,860.00 / Set
20 Stop Kontak tanam @Rp. 12,348.00 / Bh
21 Saklar tunggal @Rp. 17,424.00 / Bh
22 Saklar ganda @Rp. 18,876.00 / Bh
23 Saklar Triple @Rp. 21,780.00 / Bh
24 Zekring box 1 grup @Rp. 31,944.00 / Unit
25 Zekring box 2 grup @Rp. 37,620.00 / Unit
26 Zekring box 3 grup @Rp. 46,200.00 / Unit
27 Zekring box 4 grup @Rp. 55,440.00 / Unit
28 MCB 2 Ampere @Rp. 42,240.00 / Unit
29 MCB 4 Ampere @Rp. 51,480.00 / Unit
30 MCB 6 Ampere @Rp. 81,312.00 / Unit
31 MCB 8 Ampere @Rp. 119,064.00 / Unit
32 Kabel Listrik NYA Ø 1,5 mm @Rp. 1,344.00 / M'
33 Kabel Listrik NYA Ø 2,5 mm @Rp. 2,316.00 / M'
34 Kabel Listrik NYA Ø 4 mm @Rp. 9,900.00 / M'
35 Kabel Listrik NYM 2 Ø 1,5 mm @Rp. 4,824.00 / M'
36 Kabel Listrik NYM 2 Ø 2,5 mm @Rp. 11,880.00 / M'
37 Kabel Listrik NYM 2 Ø 4 mm @Rp. 19,164.00 / M'
38 Instalasi Listrik titik api / Lampu nyala @Rp. 122,100.00 / Ttk
39 Pas. Stop kontak (Setara Broco, Panasonic, Clipsal) @Rp. 54,000.00 / bh
40 Pas. Stop kontak AC (Setara Broco, Panasonic, Clipsal) @Rp. 90,000.00 / bh
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
41 Pas. saklar single (Setara Broco, Panasonic, Clipsal) @Rp. 54,000.00 / bh
42 Pas. saklar double (Setara Broco, Panasonic, Clipsal) @Rp. 66,000.00 / bh
43

X JALAN
1 Paving Blok Natural tbl. 8 cm @Rp. 138,000.00 / M2
2 Kanstin 10.20.40 @Rp. 36,000.00 / Bh
3 Hotmix jadi berikut alat dan bahan bakar ( T=5 cm => 9 m2 ) @Rp. 1,780,200.00 / ton
4 Aspal (ESO) 1 Drum 155 kg @Rp. 16,560.00 / kg
5 Aspal Curah @Rp. 14,400.00 / kg
6 Aspal RC 70 ( Cilacap ) @Rp. 14,400.00 / kg
7 Aspal Concrete / Laston ( AC - WC ) @Rp. 1,780,200.00 / ton
8 Aspal Threated Base ( ATB ) @Rp. 1,584,600.00 / ton
9 Lataston / Hot Rols Sheet ( HRS ) @Rp. 2,200,320.00 / ton

Y BIAYA QUALITY CONTROL , IZIN - IZIN, PENGUKURAN


BIASA DAN BIAYA PENYAMBUNGAN
1 Penyambungan Listrik PLN @Rp. 1.20 / 1w
2 Sondir Rata - rata @Rp. 1.20 / 1 ttk
3 Pengukuran Site + Patok @Rp. 1.20 / m²
4 Biaya Tes Jalan ( quality control ) @Rp. 1.20 / ttk
5 Biaya Tes 1 Macam Beton @Rp. 1.20 / 1 spl
6 Biaya Pengujian Bahan Agregat @Rp. 1.20 / 1 spl
7 Biaya Pengujian Listrik + gambar + trafo & Adm @Rp. 1.20 / 1 watt
8 Izin Sumur Artesis Lengkap @Rp. 1.20 / unit
9 Penyambungan PDAM untuk rumah @Rp. 1.20 / unit
10 Geolistrik @Rp. 1.20 / 1 ttk

Z STANDARD RATA - RATA SEWA ALAT BESAR , ALAT MEKANIK


TRUK, KENDARAAN RODA 4 & LAINNYA
1 Sewa Mesin Gilas 8 Ton s/d 10 ton @Rp. 1.20 / Jam
2 Tirud Roller 3 Jam / hari @Rp. 176,400.00 / Jam
3 Tamdam Roller 6 - 8 Ton 5 Jam / hr @Rp. 188,400.00 / Jam
4 Tamdam Roller 8 - 10 Ton 5 Jam / hr @Rp. 1.20 / Jam
5 Roller Viberator - Ped 1 Ton 4 Jam /hr @Rp. 1.20 / Jam
6 Roller Viberator - Self 7 Ton 5 Jam /hr @Rp. 1.20 / Jam
7 Roller 3 Wheeled - 8 Ton 5 Jam /hr @Rp. 1.20 / Jam
8 Roller Pneumatic 8 - 15 Ton 5 Jam /hr @Rp. 187,200.00 / Jam
9 Loader Wheeled 5 Jam /hr @Rp. 1.20 / Jam
10 Sewa Kran 30 Ton @Rp. 1.20 / Jam
11 Sewa Exavator Backhoe 5 Jam /hari @Rp. 1.20 / Jam
12 Sewa Draklint @Rp. 1.20 / Jam
13 Whell Loader @Rp. 1.20 / Jam
14 Buldozer 4 Jam /hr @Rp. 1.20 / Jam
15 Ecavator Hydr 1 m3 @Rp. 1.20 / Jam
16 Backu @Rp. 1.20 / Jam
17 Motor Grader 5 Jam /hr @Rp. 1.20 / Jam
18 Pheumatic Drill Hammer 3 Jam / hr @Rp. 1.20 / Jam
19 Vibro Roller @Rp. 1.20 / Jam
20 Stone Crusher @Rp. 1.20 / Jam
21 AMP @Rp. 1.20 / Jam
22 Teractor Equament 2 Jam /hr @Rp. 1.20 / Jam
23 Screning Plent 5 Jam /hr @Rp. 1.20 / Jam
24 Asphal Finisher @Rp. 342,000.00 / Jam
25 Asphal Melting Kalte @Rp. 1.20 / Jam
26 Asphal Spayer @Rp. 135,552.79 / Jam
27 Asphal MIxing Plant @Rp. 1.20 / Jam
28 Sprayer,Self - Prop. 10001 4 Jam/hr @Rp. 1.20 / Jam
29 Tamper, Viberator Plate 3 Jam /hari @Rp. 1.20 / Jam
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
30 Crusher / SCR @Rp. 1.20 / Jam
31 Concrete Mixer 0.125 m3 @Rp. 1.20 / Jam
32 Concrete Mixer 0.5 m3 @Rp. 1.20 / Jam
33 Concrete Viberator @Rp. 1.20 / Jam
34 Pick Up @Rp. 1.20 / Jam
35 Dump Truck 3.5 Ton @Rp. 189,720.00 / Jam
36 Dump Truck 5 Ton 4 Jam /hr @Rp. 189,720.00 / Jam
37 Flatbed Truck 3.5 Ton @Rp. 1.20 / Jam
38 Truck 3/4 ( Colt Disel ) @Rp. 1.20 / Jam
39 Truck Fuso @Rp. 1.20 / Jam
40 Mesin Las Listrik 18 pk 8 jam @Rp. 1.20 / Jam
41 Mesin Pompa Air 3 " @Rp. 1.20 / Jam
42 Stamper 8 Jam @Rp. 1.20 / Jam
43 Compresor @Rp. 156,300.00 / Jam
44 Pump Water ( 5 cm ) 30 m3 / hari @Rp. 1.20 / Jam
45 Trailler, Towed 1 Ton 3 Jam/hr @Rp. 1.20 / Jam
46 Water Tank Truck 2 Jam/hr @Rp. 1.20 / Jam
47 Blower @Rp. 21,600.00 / Jam
48 Cutter Machine @Rp. 54,000.00 / Jam

AA BIDANG PERTAMANAN
1 Aglomena @Rp. 66,000.00 / batang
2 Bambu krisik/jepang @Rp. 66,000.00 / batang
3 Furadan @Rp. 31,800.00 / kg
4 Kompos/pupuk kandang @Rp. 33,000.00 / batang
5 Matoa (2 m) @Rp. 51,000.00 / batang
6 Palm (botol, ekor tupai, putri, dll) tinggi 2 m @Rp. 132,600.00 / batang
7 Philo @Rp. 99,600.00 / batang
8 Pohon pelindung (angsana, mahoni, kamboja dll) tinggi 2 m @Rp. 33,000.00 / batang
9 Pohon perdu (kaca piring, puring, mawar, melati, dll) @Rp. 12,600.00 / batang
10 Rumput gajah mini @Rp. 19,800.00 / m2

BB BAHAN PAGAR
1 Panel Beton Pracetak @Rp. 241,080.00 / lbr
2 Kolom Beton Pracetak @Rp. 348,600.00 / btg

CC READYMIX
1 Readymix Beton B 0, Mutu Slump 12±2 cm @Rp. 996,000.00 / M3
2 Readymix Beton K 125, Mutu Slump 12± 2 cm @Rp. 1,088,400.00 / M3
3 Readymix Beton K 175, Mutu Slump 12± 2 cm @Rp. 1,137,600.00 / M3
4 Readymix Beton K 225, Mutu Slump 12± 2 cm @Rp. 1,162,800.00 / M3
5 Readymix Beton K 250, Mutu Slump 12± 2 cm @Rp. 1,174,800.00 / M3
6 Readymix Beton K 275, Mutu Slump 12± 2 cm @Rp. 1,201,200.00 / M3
7 Readymix Beton K 300, Mutu Slump 12± 2 cm @Rp. 1,228,800.00 / M3
8 Readymix Beton K 325, Mutu Slump 12± 2 cm @Rp. 1,256,400.00 / M3
9 Readymix Beton K 350, Mutu Slump 12± 2 cm @Rp. 1,273,200.00 / M3
10 Readymix Beton K 375, Mutu Slump 12± 2 cm @Rp. 1,299,600.00 / M3
11 Readymix Beton K 400, Mutu Slump 12± 2 cm @Rp. 1,321,200.00 / M3
12 Readymix Beton K 450, Mutu Slump 12± 2 cm @Rp. 1,376,400.00 / M3
13 Readymix Beton K 500, Mutu Slump 12± 2 cm @Rp. 1,418,400.00 / M3

DD PINTU PLAT BAJA


1 Pintu Plat Baja Uk. 2.150 x 800 x 50 (Single Door) @Rp. 6,000,000.00 / Bh
2 Pintu Plat Baja Uk. 2.150 x 1200 x 50 Double Door (L1:80, L2:40) @Rp. 9,000,000.00 / Bh
3 Pintu Plat Baja Uk. 2.150 x 1600 x 50 Double Door (L1:80, L2:80) @Rp. 10,800,000.00 / Bh

EE PEKERJAAN LAIN-LAIN
1 Pek. Sumur Bor + Casing (pipa AW 4") @Rp. 7,200,000.00 / titik
NO. URAIAN HARGA BAHAN HARGA SATUAN
1 2 3 4
2 Torn Air Kapasitas 1000 liter @Rp. 3,000,000.00 / Bh
3 Torn Air Kapasitas 500 liter @Rp. 1,800,000.00 / Bh
4 Pintu Sketsel kayu, lapis teakwood (HPL), kusen alumanium, rel bagian atas @Rp. 17,640,000.00 / unit

Depok, Desember 2020


SATUAN

SATUAN
SATUAN
ANALISA BIAYA KONSTRUKSI
PEKERJAAN DINDING

PD 3.1 1 m²Pasang dinding bata ringan tebal 10 cm dengan mortar siap pakai

3.1.1 Bahan
- Bata ringan tebal 10 cm 8.400 M³ x Rp. 8,675 = Rp
- Mortar siap pakai 0.063 Kg x Rp. 2,044 = Rp

Jumlah (1) = Rp

3.1.2 Tenaga
- Pekerja 0.670 Oh x Rp. 110,000 = Rp
- Tukang batu 0.130 Oh x Rp. 137,500 = Rp
- Kepala tukang 0.013 Oh x Rp. 165,000 = Rp
- Mandor 0.013 Oh x Rp. 192,500 = Rp
Jumlah (2) = Rp

Jumlah (1) + (2) = Rp


ALISA BIAYA KONSTRUKSI
PEKERJAAN DINDING

72,867.47
128.79

72,996.26

73,700.00
17,875.00
2,145.00
2,502.50
96,222.50

169,218.76
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PLESTERAN

PPL 4.1 1 M² Plesteran 1 Pc : 4 Ps, tebal 15 mm

4.1.1 Bahan
- Semen portland 9.490 Kg x Rp. 1,800 = Rp. 17,082.00
- Pasir pasang 0.024 M³ x Rp. 342,000 = Rp. 8,208.00
Jumlah (1) = Rp. 25,290.00
4.1.2 Tenaga
- Pekerja 0.340 Oh x Rp. 110,000 = Rp. 37,400.00
- Tukang batu 0.150 Oh x Rp. 137,500 = Rp. 20,625.00
- Kepala tukang 0.015 Oh x Rp. 165,000 = Rp. 2,475.00
- Mandor 0.015 Oh x Rp. 192,500 = Rp. 2,887.50
Jumlah (2) = Rp. 63,387.50

Jumlah (1) + (2) = Rp. 88,677.50

PPL 4.2 1 M² Pemasangan acian

4.2.1 Bahan
- Semen portland 3.250 Kg x Rp. 1,800 = Rp. 5,850.00

Jumlah (1) = Rp. 5,850.00


4.2.2 Tenaga
- Pekerja 0.200 Oh x Rp. 110,000 = Rp. 22,000.00
- Tukang batu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 39,325.00

Jumlah (1) + (2) = Rp. 45,175.00


ANALISA BIAYA KONSTRUKSI
PEKERJAAN KAYU

PK 6.1. 1 M³ Pasang kusen pintu dan jendela kayu jati :

6.1.1. Bahan
- Kayu jati, balok 1.100 M³ x Rp. 28,710,000.00 = Rp. 31,581,000.00
Jumlah (1) = Rp. 31,581,000.00

6.1.2. Tenaga
- Pekerja 6.000 Oh x Rp. 110,000.00 = Rp. 660,000.00
- Tukang kayu 20.000 Oh x Rp. 137,500.00 = Rp. 2,750,000.00
- Kepala tukang 2.000 Oh x Rp. 165,000.00 = Rp. 330,000.00
- Mandor 0.300 Oh x Rp. 192,500.00 = Rp. 57,750.00
Jumlah (2) = Rp. 3,797,750.00

Jumlah (1) + (2) = Rp. 35,378,750.00

PK 6.2. 1 M³ Pasang kusen pintu dan jendela kayu damar laut :

6.2.1. Bahan
- Kayu meranti, balok 1.200 M³ x Rp. 10,890,000.00 = Rp. 13,068,000.00
Jumlah (1) = Rp. 13,068,000.00

6.2.2. Tenaga
- Pekerja 6.000 Oh x Rp. 110,000.00 = Rp. 660,000.00
- Tukang kayu 18.000 Oh x Rp. 137,500.00 = Rp. 2,475,000.00
- Kepala tukang 2.000 Oh x Rp. 165,000.00 = Rp. 330,000.00
- Mandor 0.300 Oh x Rp. 192,500.00 = Rp. 57,750.00
Jumlah (2) = Rp. 3,522,750.00

Jumlah (1) + (2) = Rp. 16,590,750.00

PK 6.3. 1 M³ Pasang kusen pintu dan jendela kayu meranti :

6.3.1. Bahan
- Kayu kapur, balok 1.200 M³ x Rp. 7,788,000.00 = Rp. 9,345,600.00
Jumlah (1) = Rp. 9,345,600.00

6.3.2. Tenaga
- Pekerja 6.000 Oh x Rp. 110,000.00 = Rp. 660,000.00
- Tukang kayu 18.000 Oh x Rp. 137,500.00 = Rp. 2,475,000.00
- Kepala tukang 2.000 Oh x Rp. 165,000.00 = Rp. 330,000.00
- Mandor 0.300 Oh x Rp. 192,500.00 = Rp. 57,750.00
Jumlah (2) = Rp. 3,522,750.00

Jumlah (1) +(2) = Rp. 12,868,350.00


PK 6.4. 1 M³ Pasang kusen pintu dan jendela kayu damar laut :

6.4.1. Bahan
- Kayu damar laut, balok 1.200 M³ x Rp. 11,220,000.00 = Rp. 13,464,000.00
Jumlah (1) = Rp. 13,464,000.00

6.4.2. Tenaga

- Pekerja 6.000 Oh x Rp. 110,000.00 = Rp. 660,000.00


- Tukang kayu 18.000 Oh x Rp. 137,500.00 = Rp. 2,475,000.00
- Kepala tukang 2.000 Oh x Rp. 165,000.00 = Rp. 330,000.00
- Mandor 0.300 Oh x Rp. 192,500.00 = Rp. 57,750.00
Jumlah (2) = Rp. 3,522,750.00

Jumlah (1) +(2) = Rp. 16,986,750.00

PK 6.5. 1 M² Pasang pintu klamp kayu meranti batu

6.5.1. Bahan
- Kayu meranti batu, papan 0.036 M³ x Rp. 11,250,000.00 = Rp. 405,000.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200.00 = Rp. 960.00
Jumlah (1) = Rp. 405,960.00
6.5.2. Tenaga
- Pekerja 0.350 Oh x Rp. 110,000.00 = Rp. 38,500.00
- Tukang kayu 1.050 Oh x Rp. 137,500.00 = Rp. 144,375.00
- Kepala tukang 0.105 Oh x Rp. 165,000.00 = Rp. 17,325.00
- Mandor 0.018 Oh x Rp. 192,500.00 = Rp. 3,465.00
Jumlah (2) = Rp. 203,665.00

Jumlah (1) +(2) = Rp. 609,625.00

PK 6.6. 1 M³ Pasang pintu klamp kayu jati

6.6.1. Bahan
- Kayu jati, papan 0.036 M³ x Rp. 28,925,328.00 = Rp. 1,041,311.81
- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200.00 = Rp. 960.00
Jumlah (1) = Rp. 1,042,271.81
6.6.2. Tenaga
- Pekerja 0.350 Oh x Rp. 110,000.00 = Rp. 38,500.00
- Tukang kayu 1.050 Oh x Rp. 137,500.00 = Rp. 144,375.00
- Kepala tukang 0.105 Oh x Rp. 165,000.00 = Rp. 17,325.00
- Mandor 0.018 Oh x Rp. 192,500.00 = Rp. 3,465.00
Jumlah (2) = Rp. 203,665.00

Jumlah (1) +(2) = Rp. 1,245,936.81

PK 6.7. 1 M² Pasang pintu panel kayu jati :

6.7.1. Bahan
- Kayu jati, papan 0.036 M³ x Rp. 28,925,328.00 = Rp. 1,041,311.81
Jumlah (1) 1,041,311.81
6.7.2. Tenaga
- Pekerja 1.000 Oh x Rp. 110,000.00 = Rp. 110,000.00
- Tukang kayu 2.500 Oh x Rp. 137,500.00 = Rp. 343,750.00
- Kepala tukang 0.250 Oh x Rp. 165,000.00 = Rp. 41,250.00
- Mandor 0.050 Oh x Rp. 192,500.00 = Rp. 9,625.00
Jumlah (2) = Rp. 504,625.00

Jumlah (1) +(2) = Rp. 1,545,936.81

PK 6.8. 1 M² Pasang pintu panel kayu meranti batu

6.8.1. Bahan
- Kayu meranti batu, papan 0.040 M³ x Rp. 11,250,000.00 = Rp. 450,000.00
Jumlah (1) = Rp. 450,000.00
6.8.2. Tenaga
- Pekerja 1.000 Oh x Rp. 110,000.00 = Rp. 110,000.00
- Tukang kayu 2.500 Oh x Rp. 137,500.00 = Rp. 343,750.00
- Kepala tukang 0.250 Oh x Rp. 165,000.00 = Rp. 41,250.00
- Mandor 0.050 Oh x Rp. 192,500.00 = Rp. 9,625.00
Jumlah (2) = Rp. 504,625.00

Jumlah (1) +(2) = Rp. 954,625.00

PK 6.9. 1 M² Pasang pintu dan jendela kaca panel kayu jati :

6.9.1. Bahan
- Kayu jati, papan 0.035 M³ x Rp. 28,925,328.00 = Rp. 1,012,386.48
- Kaca polos 5 mm 0.800 M2 x Rp. 141,600.00 = Rp. 113,280.00
Jumlah (1) = Rp. 1,125,666.48
6.9.2. Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 403,700.00

Jumlah (1) +(2) = Rp. 1,529,366.48

PK 6.10. 1 M² Pasang pintu dan jendela kaca panel kayu meranti batu :

6.10.1. Bahan
- Kayu meranti batu, papan 0.035 M³ x Rp. 11,250,000.00 = Rp. 393,750.00
- Kaca polos 5 mm 0.800 M³ x Rp. 141,600.00 = Rp. 113,280.00
Jumlah (1) = Rp. 507,030.00
6.10.2. Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 403,700.00

Jumlah (1) +(2) = Rp. 910,730.00

PK 6.11. 1 M² Pasang pintu dan jendela kaca panel kayu meranti :

6.11.1. Bahan
- Kayu meranti, papan 0.035 M³ x Rp. 6,570,000.00 = Rp. 229,950.00
- Kaca polos 5 mm 0.800 M³ x Rp. 141,600.00 = Rp. 113,280.00
Jumlah (1) = Rp. 343,230.00
6.11.2. Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 403,700.00

Jumlah (1) +(2) = Rp. 746,930.00

PK 6.12. 1 M² Pasang pintu dan jendela jalusi kayu jati :

6.12.1. Bahan
- Kayu jati, papan 0.064 M³ x Rp. 28,925,328.00 = Rp. 1,851,220.99
Jumlah (1) = Rp. 1,851,220.99
6.12.2. Tenaga
- Pekerja 1.000 Oh x Rp. 110,000.00 = Rp. 110,000.00
- Tukang kayu 3.000 Oh x Rp. 137,500.00 = Rp. 412,500.00
- Kepala tukang 0.300 Oh x Rp. 165,000.00 = Rp. 49,500.00
- Mandor 0.300 Oh x Rp. 192,500.00 = Rp. 57,750.00
Jumlah (2) = Rp. 629,750.00

Jumlah (1) +(2) = Rp. 2,480,970.99

PK 6.13. 1 M² Pasang pintu dan jendela jalusi kayu meranti batu :

6.13.1. Bahan
- Kayu meranti batu, papan 0.064 M³ x Rp. 11,250,000.00 = Rp. 720,000.00
Jumlah (1) = Rp. 720,000.00
6.13.2. Tenaga
- Pekerja 1.000 Oh x Rp. 110,000.00 = Rp. 110,000.00
- Tukang kayu 3.000 Oh x Rp. 137,500.00 = Rp. 412,500.00
- Kepala tukang 0.300 Oh x Rp. 165,000.00 = Rp. 49,500.00
- Mandor 0.500 Oh x Rp. 192,500.00 = Rp. 96,250.00
Jumlah (2) = Rp. 668,250.00

Jumlah (1) +(2) = Rp. 1,388,250.00


PK 6.14. 1 M² Pasang pintu plywood rangka, rangka kayu jati :

6.14.1. Bahan
- Kayu jati, papan 0.0196 M³ x Rp. 28,925,328.00 = Rp. 566,936.43
- Paku biasa ½" - 1" 0.030 Kg x Rp. 19,200.00 = Rp. 576.00
- Lem kayu 0.300 Lt x Rp. 104,400.00 = Rp. 31,320.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 62,304.00 = Rp. 62,304.00
Jumlah (1) = Rp. 661,136.43

6.14.2. Tenaga
- Pekerja 0.600 Oh x Rp. 110,000.00 = Rp. 66,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.030 Oh x Rp. 192,500.00 = Rp. 5,775.00
Jumlah (2) = Rp. 379,775.00

Jumlah (1) +(2) = Rp. 1,040,911.43

PK 6.15. 1 M² Pasang pintu plywood rangka, rangka kayu meranti batu :

6.15.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 11,250,000.00 = Rp. 220,500.00
- Paku biasa ½" - 1" 0.030 Kg x Rp. 19,200.00 = Rp. 576.00
- Lem kayu 0.300 Lt x Rp. 104,400.00 = Rp. 31,320.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 62,304.00 = Rp. 62,304.00
Jumlah (1) = Rp. 314,700.00
6.15.2. Tenaga
- Pekerja 0.600 Oh x Rp. 110,000.00 = Rp. 66,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.030 Oh x Rp. 192,500.00 = Rp. 5,775.00
Jumlah (2) = Rp. 379,775.00

Jumlah (1) +(2) = Rp. 694,475.00

PK 6.16. 1 M² Pasang jalusi mati kusen kayu jati :

6.16.1. Bahan
- Kayu jati, papan 0.060 M³ x Rp. 28,925,328.00 = Rp. 1,735,519.68
- Paku biasa ½" - 1" 0.150 Kg x Rp. 19,200.00 = Rp. 2,880.00
Jumlah (1) = Rp. 1,738,399.68
6.16.2. Tenaga
- Pekerja 0.500 Oh x Rp. 110,000.00 = Rp. 55,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.025 Oh x Rp. 192,500.00 = Rp. 4,812.50
Jumlah (2) = Rp. 367,812.50

Jumlah (1) +(2) = Rp. 2,106,212.18


PK 6.17. 1 M² Pasang jalusi mati kusen kayu damar laut :

6.17.1. Bahan
- Kayu damar laut, papan 0.060 M³ x Rp. 11,580,000.00 = Rp. 694,800.00
- Paku biasa ½" - 1" 0.150 Kg x Rp. 19,200.00 = Rp. 2,880.00
Jumlah (1) = Rp. 697,680.00
6.17.2. Tenaga
- Pekerja 0.500 Oh x Rp. 110,000.00 = Rp. 55,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.025 Oh x Rp. 192,500.00 = Rp. 4,812.50
Jumlah (2) = Rp. 367,812.50

Jumlah (1) +(2) = Rp. 1,065,492.50

PK 6.18. 1 M² Pasang pintu plywood rangka, rangka kayu meranti :

6.18.1. Bahan
- Kayu meranti, papan 0.0196 M³ x Rp. 6,570,000.00 = Rp. 128,772.00
- Paku biasa ½" - 1" 0.030 Kg x Rp. 19,200.00 = Rp. 576.00
- Lem kayu 0.300 Lt x Rp. 104,400.00 = Rp. 31,320.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 62,304.00 = Rp. 62,304.00
Jumlah (1) = Rp. 222,972.00
6.18.2. Tenaga
- Pekerja 0.600 Oh x Rp. 110,000.00 = Rp. 66,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.030 Oh x Rp. 192,500.00 = Rp. 5,775.00
Jumlah (2) = Rp. 379,775.00

Jumlah (1) +(2) = Rp. 602,747.00

PK 6.19. 1 M² Pasang pintu teakwood rangka, rangka kayu jati :

6.19.1. Bahan
- Kayu jati, papan 0.0196 M³ x Rp. 28,925,328.00 = Rp. 566,936.43
- Paku biasa ½" - 1" 0.300 Kg x Rp. 19,200.00 = Rp. 5,760.00
- Lem kayu 0.300 Lt x Rp. 104,400.00 = Rp. 31,320.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 156,000.00 = Rp. 156,000.00
Jumlah (1) = Rp. 760,016.43
6.19.2. Tenaga
- Pekerja 0.600 Oh x Rp. 110,000.00 = Rp. 66,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.030 Oh x Rp. 192,500.00 = Rp. 5,775.00
Jumlah (2) = Rp. 379,775.00

Jumlah (1) +(2) = Rp. 1,139,791.43


PK 6.20. 1 M² Pasang pintu teakwood rangka, rangka kayu meranti batu :

6.20.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 11,250,000.00 = Rp. 220,500.00
- Paku biasa ½" - 1" 0.300 Kg x Rp. 19,200.00 = Rp. 5,760.00
- Lem kayu 0.300 Lt x Rp. 104,400.00 = Rp. 31,320.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 156,000.00 = Rp. 156,000.00
Jumlah (1) = Rp. 413,580.00
6.20.2. Tenaga
- Pekerja 0.600 Oh x Rp. 110,000.00 = Rp. 66,000.00
- Tukang kayu 2.000 Oh x Rp. 137,500.00 = Rp. 275,000.00
- Kepala tukang 0.200 Oh x Rp. 165,000.00 = Rp. 33,000.00
- Mandor 0.030 Oh x Rp. 192,500.00 = Rp. 5,775.00
Jumlah (2) = Rp. 379,775.00

Jumlah (1) +(2) = Rp. 793,355.00

PK 6.21. 1 M² Pasang pintu plywood & formika, rangka kayu jati :

6.21.1. Bahan
- Kayu jati, papan 0.0196 M³ x Rp. 28,925,328.00 = Rp. 566,936.43
- Paku biasa ½" - 1" 0.300 Kg x Rp. 19,200.00 = Rp. 5,760.00
- Lem kayu 0.800 Lt x Rp. 104,400.00 = Rp. 83,520.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 62,304.00 = Rp. 62,304.00
- Formica 4' x 8' 1.000 Lbr x Rp. 89,100.00 = Rp. 89,100.00
Jumlah (1) = Rp. 807,620.43
6.21.2. Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang kayu 2.500 Oh x Rp. 137,500.00 = Rp. 343,750.00
- Kepala tukang 0.250 Oh x Rp. 165,000.00 = Rp. 41,250.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 480,700.00

Jumlah (1) +(2) = Rp. 1,288,320.43

PK 6.22. 1 M² Pasang pintu plywood & formika, rangka kayu meranti batu :

6.22.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 11,250,000.00 = Rp. 220,500.00
- Paku biasa ½" - 1" 0.300 Kg x Rp. 19,200.00 = Rp. 5,760.00
- Lem kayu 0.800 Lt x Rp. 104,400.00 = Rp. 83,520.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 62,304.00 = Rp. 62,304.00
- Formica 4' x 8' 1.000 Lbr x Rp. 89,100.00 = Rp. 89,100.00
Jumlah (1) = Rp. 461,184.00

6.22.2. Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang kayu 2.500 Oh x Rp. 137,500.00 = Rp. 343,750.00
- Kepala tukang 0.250 Oh x Rp. 165,000.00 = Rp. 41,250.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 480,700.00

Jumlah (1) +(2) = Rp. 941,884.00

PK 6.23. 1 M² Pasang pintu plywood & formika, rangka kayu jati :

6.23.1. Bahan
- Kayu jati, papan 0.0196 M³ x Rp. 28,925,328.00 = Rp. 566,936.43
- Paku biasa ½" - 1" 0.300 Kg x Rp. 19,200.00 = Rp. 5,760.00
- Lem kayu 0.800 Lt x Rp. 104,400.00 = Rp. 83,520.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 156,000.00 = Rp. 156,000.00
- Formica 4' x 8' 1.000 Lbr x Rp. 89,100.00 = Rp. 89,100.00
Jumlah (1) = Rp. 901,316.43

6.23.2. Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang kayu 2.500 Oh x Rp. 137,500.00 = Rp. 343,750.00
- Kepala tukang 0.250 Oh x Rp. 165,000.00 = Rp. 41,250.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 480,700.00

Jumlah (1) +(2) = Rp. 1,382,016.43

PK 6.24. 1 M² Pasang pintu plywood & formika, rangka kayu damar laut (divermis) :

6.24.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 11,250,000.00 = Rp. 220,500.00
- Paku biasa ½" - 1" 0.300 Kg x Rp. 19,200.00 = Rp. 5,760.00
- Lem kayu 0.800 Lt x Rp. 104,400.00 = Rp. 83,520.00
- Teakwood 4' x 8' x 4 mm 0.500 Lbr x Rp. 156,000.00 = Rp. 78,000.00
- Vernis 0.500 Lt x Rp. 90,000.00 = Rp. 45,000.00
- Formica 4' x 8' 0.500 Lbr x Rp. 89,100.00 = Rp. 44,550.00
Jumlah (1) = Rp. 477,330.00

6.24.2. Tenaga
- Pekerja 0.800 Oh x Rp. 110,000.00 = Rp. 88,000.00
- Tukang kayu 2.500 Oh x Rp. 137,500.00 = Rp. 343,750.00
- Kepala tukang 0.250 Oh x Rp. 165,000.00 = Rp. 41,250.00
- Mandor 0.040 Oh x Rp. 192,500.00 = Rp. 7,700.00
Jumlah (2) = Rp. 480,700.00

Jumlah (1) +(2) = Rp. 958,030.00

PK 6.25. 1 M³ Pasang konstruksi kuda-kuda kayu damar laut :

6.25.1. Bahan
- Kayu damar laut, balok 1.1000 M³ x Rp. 11,220,000.00 = Rp. 12,342,000.00
- Besi strip 15.000 Kg x Rp. 22,800.00 = Rp. 342,000.00
- Paku biasa 2" - 5" 0.800 Kg x Rp. 19,200.00 = Rp. 15,360.00
Jumlah (1) = Rp. 12,699,360.00

6.25.2. Tenaga
- Pekerja 4.000 Oh x Rp. 110,000.00 = Rp. 440,000.00
- Tukang kayu 12.000 Oh x Rp. 137,500.00 = Rp. 1,650,000.00
- Kepala tukang 1.200 Oh x Rp. 165,000.00 = Rp. 198,000.00
- Mandor 0.200 Oh x Rp. 192,500.00 = Rp. 38,500.00
Jumlah (2) = Rp. 2,326,500.00

Jumlah (1) +(2) = Rp. 15,025,860.00

PK 6.26. 1 M³ Pasang konstruksi kuda-kuda kayu meranti :

6.26.1. Bahan
- Kayu meranti, balok 1.1000 M³ x Rp. 6,270,000.00 = Rp. 6,897,000.00
- Besi strip 15.000 Kg x Rp. 22,800.00 = Rp. 342,000.00
- Paku biasa 2" - 5" 0.800 Kg x Rp. 19,200.00 = Rp. 15,360.00
Jumlah (1) = Rp. 7,254,360.00

6.26.2. Tenaga
- Pekerja 4.000 Oh x Rp. 110,000.00 = Rp. 440,000.00
- Tukang kayu 12.000 Oh x Rp. 137,500.00 = Rp. 1,650,000.00
- Kepala tukang 1.200 Oh x Rp. 165,000.00 = Rp. 198,000.00
- Mandor 0.200 Oh x Rp. 192,500.00 = Rp. 38,500.00
Jumlah (2) = Rp. 2,326,500.00

Jumlah (1) +(2) = Rp. 9,580,860.00

PK 6.27. 1 M² Pasang kaso + reng genteng kodok kayu meranti :

6.27.1. Bahan
- Kayu meranti, balok 0.012 M³ x Rp. 6,270,000.00 = Rp. 75,240.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 19,200.00 = Rp. 2,880.00
Jumlah (1) = Rp. 78,120.00
6.27.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500.00 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000.00 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 27,362.50

Jumlah (1) +(2) = Rp. 105,482.50

PK 6.28. 1 M² Pasang kaso + reng genteng kodok kayu damar laut :

6.28.1. Bahan
- Kayu damar laut, balok 0.012 M³ x Rp. 11,220,000.00 = Rp. 134,640.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 19,200.00 = Rp. 2,880.00
Jumlah (1) = Rp. 137,520.00

6.28.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500.00 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000.00 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 27,362.50

Jumlah (1) +(2) = Rp. 164,882.50

PK 6.29. 1 M² Pasang kaso + reng genteng monier kayu jati :

6.29.1. Bahan
- Kayu jati, balok 0.014 M³ x Rp. 28,710,000.00 = Rp. 401,940.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 19,200.00 = Rp. 2,880.00
Jumlah (1) = Rp. 404,820.00

6.29.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500.00 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000.00 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 27,362.50

Jumlah (1) +(2) = Rp. 432,182.50

PK 6.30. 1 M² Pasang kaso + reng genteng monier kayu damar laut :

6.30.1. Bahan
- Kayu damar laut, balok 0.014 M³ x Rp. 11,220,000.00 = Rp. 157,080.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 19,200.00 = Rp. 2,880.00
Jumlah (1) = Rp. 159,960.00

6.30.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500.00 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000.00 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 27,362.50

Jumlah (1) +(2) = Rp. 187,322.50

PK 6.31. 1 M² Pasang kaso + reng genteng beton kayu damar laut :

6.31.1. Bahan
- Kayu damar laut, balok 0.014 M³ x Rp. 11,220,000.00 = Rp. 157,080.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 19,200.00 = Rp. 2,880.00
Jumlah (1) = Rp. 159,960.00
6.31.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500.00 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000.00 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 27,362.50

Jumlah (1) +(2) = Rp. 187,322.50

PK 6.32. 1 M² Pasang kaso + reng atap sirap kayu damar laut :

6.32.1. Bahan
- Kayu damar laut, balok 0.165 M³ x Rp. 11,220,000.00 = Rp. 1,851,300.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 19,200.00 = Rp. 3,840.00
Jumlah (1) = Rp. 1,855,140.00

6.32.2. Tenaga
- Pekerja 0.120 Oh x Rp. 110,000.00 = Rp. 13,200.00
- Tukang kayu 0.120 Oh x Rp. 137,500.00 = Rp. 16,500.00
- Kepala tukang 0.012 Oh x Rp. 165,000.00 = Rp. 1,980.00
- Mandor 0.006 Oh x Rp. 192,500.00 = Rp. 1,155.00
Jumlah (2) = Rp. 32,835.00

Jumlah (1) +(2) = Rp. 1,887,975.00

PK 6.33. 1 M² Pasang kaso + reng atap sirap kayu meranti :

6.33.1. Bahan
- Kayu meranti, balok 0.165 M³ x Rp. 6,270,000.00 = Rp. 1,034,550.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 19,200.00 = Rp. 3,840.00
Jumlah (1) = Rp. 1,038,390.00
6.33.2. Tenaga
- Pekerja 0.120 Oh x Rp. 110,000.00 = Rp. 13,200.00
- Tukang kayu 0.120 Oh x Rp. 137,500.00 = Rp. 16,500.00
- Kepala tukang 0.012 Oh x Rp. 165,000.00 = Rp. 1,980.00
- Mandor 0.006 Oh x Rp. 192,500.00 = Rp. 1,155.00
Jumlah (2) = Rp. 32,835.00

Jumlah (1) +(2) = Rp. 1,071,225.00

PK 6.34. 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, kayu jati :

6.34.1. Bahan
- Kayu jati, balok 0.012 M³ x Rp. 28,710,000.00 = Rp. 344,520.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
Jumlah (1) = Rp. 346,440.00
6.34.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000.00 = Rp. 16,500.00
- Tukang kayu 0.250 Oh x Rp. 137,500.00 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000.00 = Rp. 4,125.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 69,437.50

Jumlah (1) +(2) = Rp. 415,877.50

PK 6.35. A 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, damar laut :

6.35.1. Bahan
- Kayu damar laut, balok 0.012 M³ x Rp. 11,220,000.00 = Rp. 134,640.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
Jumlah (1) = Rp. 136,560.00
6.35.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000.00 = Rp. 16,500.00
- Tukang kayu 0.250 Oh x Rp. 137,500.00 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000.00 = Rp. 4,125.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 69,437.50

Jumlah (1) +(2) = Rp. 205,997.50

PK 6.36. B 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, Kayu meranti :

6.36.1. Bahan
- Kayu meranti, balok 0.012 M³ x Rp. 6,270,000.00 = Rp. 75,240.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
Jumlah (1) = Rp. 77,160.00
6.36.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000.00 = Rp. 16,500.00
- Tukang kayu 0.250 Oh x Rp. 137,500.00 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000.00 = Rp. 4,125.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 69,437.50

Jumlah (1) +(2) = Rp. 146,597.50

PK 6.37. 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu jati :

6.37.1. Bahan
- Kayu jati, balok 0.027 M³ x Rp. 28,710,000.00 = Rp. 775,170.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 19,200.00 = Rp. 3,840.00
Jumlah (1) = Rp. 779,010.00
6.37.2. Tenaga
- Pekerja 0.250 Oh x Rp. 110,000.00 = Rp. 27,500.00
- Tukang kayu 0.350 Oh x Rp. 137,500.00 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000.00 = Rp. 5,775.00
- Mandor 0.0125 Oh x Rp. 192,500.00 = Rp. 2,406.25
Jumlah (2) = Rp. 83,806.25

Jumlah (1) +(2) = Rp. 862,816.25

PK 6.38. 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu damar laut :

6.38.1. Bahan
- Kayu damar laut, balok 0.027 M³ x Rp. 11,220,000.00 = Rp. 302,940.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 19,200.00 = Rp. 3,840.00
Jumlah (1) = Rp. 306,780.00
6.38.2. Tenaga
- Pekerja 0.250 Oh x Rp. 110,000.00 = Rp. 27,500.00
- Tukang kayu 0.350 Oh x Rp. 137,500.00 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000.00 = Rp. 5,775.00
- Mandor 0.0125 Oh x Rp. 192,500.00 = Rp. 2,406.25
Jumlah (2) = Rp. 83,806.25

Jumlah (1) +(2) = Rp. 390,586.25

PK 6.39. 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu meranti :

6.39.1. Bahan
- Kayu meranti, balok 0.027 M³ x Rp. 6,270,000.00 = Rp. 169,290.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 19,200.00 = Rp. 3,840.00
Jumlah (1) = Rp. 173,130.00
6.39.2. Tenaga
- Pekerja 0.250 Oh x Rp. 110,000.00 = Rp. 27,500.00
- Tukang kayu 0.350 Oh x Rp. 137,500.00 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000.00 = Rp. 5,775.00
- Mandor 0.0125 Oh x Rp. 192,500.00 = Rp. 2,406.25
Jumlah (2) = Rp. 83,806.25

Jumlah (1) +(2) = Rp. 256,936.25

PK 6.40. 1 M´ Pasang lisplang ukuran (3 x 20) cm, kayu meranti :

6.40.1. Bahan
- Kayu meranti, papan 0.0072 M³ x Rp. 6,570,000.00 = Rp. 47,304.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200.00 = Rp. 960.00
Jumlah (1) = Rp. 48,264.00
6.40.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.200 Oh x Rp. 137,500.00 = Rp. 27,500.00
- Kepala tukang 0.025 Oh x Rp. 165,000.00 = Rp. 4,125.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 43,587.50
Jumlah (1) +(2) = Rp. 91,851.50

PK 6.41. 1 M´ Pasang lisplang ukuran (3 x 20) cm, kayu meranti batu :

6.41.1. Bahan
- Meranti batu, papan 0.0072 M³ x Rp. 11,250,000.00 = Rp. 81,000.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200.00 = Rp. 960.00
Jumlah (1) = Rp. 81,960.00
6.41.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.200 Oh x Rp. 137,500.00 = Rp. 27,500.00
- Kepala tukang 0.020 Oh x Rp. 165,000.00 = Rp. 3,300.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 42,762.50

Jumlah (1) +(2) = Rp. 124,722.50

PK 6.42. 1 M´ Pasang lisplang ukuran (3 x 30) cm, kayu jati :

6.42.1. Bahan
- Kayu jati, papan 0.0110 M³ x Rp. 28,925,328.00 = Rp. 318,178.61
- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200.00 = Rp. 960.00
Jumlah (1) = Rp. 319,138.61
6.42.2. Tenaga
- Pekerja 0.110 Oh x Rp. 110,000.00 = Rp. 12,100.00
- Tukang kayu 0.220 Oh x Rp. 137,500.00 = Rp. 30,250.00
- Kepala tukang 0.022 Oh x Rp. 165,000.00 = Rp. 3,630.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 46,942.50

Jumlah (1) +(2) = Rp. 366,081.11

PK 6.43. 1 M´ Pasang lisplang ukuran (3 x 30) cm, kayu meranti batu :

6.43.1. Bahan
- Meranti batu, papan 0.011 M³ x Rp. 11,250,000.00 = Rp. 123,750.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200.00 = Rp. 960.00
Jumlah (1) = Rp. 124,710.00

6.43.2. Tenaga
- Pekerja 0.110 Oh x Rp. 110,000.00 = Rp. 12,100.00
- Tukang kayu 0.220 Oh x Rp. 137,500.00 = Rp. 30,250.00
- Kepala tukang 0.022 Oh x Rp. 165,000.00 = Rp. 3,630.00
- Mandor 0.005 Oh x Rp. 192,500.00 = Rp. 962.50
Jumlah (2) = Rp. 46,942.50
Jumlah (1) +(2) = Rp. 171,652.50

PK 6.44. 1 M´ Pasang lisplang ukuran 2 x (3 x 20) cm, kayu meranti batu :

6.44.1. Bahan
- Meranti batu, papan 0.0145 M³ x Rp. 11,250,000.00 = Rp. 163,125.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 19,200.00 = Rp. 1,152.00
Jumlah (1) = Rp. 164,277.00
6.44.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000.00 = Rp. 16,500.00
- Tukang kayu 0.250 Oh x Rp. 137,500.00 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000.00 = Rp. 4,125.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 69,437.50

Jumlah (1) +(2) = Rp. 233,714.50

PK 6.45. 1 M´ Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti batu :

6.45.1. Bahan
- Meranti batu, papan 0.0086 M³ x Rp. 11,250,000.00 = Rp. 96,750.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 19,200.00 = Rp. 1,152.00
Jumlah (1) = Rp. 97,902.00
6.45.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500.00 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000.00 = Rp. 1,650.00
- Mandor 0.050 Oh x Rp. 192,500.00 = Rp. 9,625.00
Jumlah (2) = Rp. 36,025.00

Jumlah (1) +(2) = Rp. 133,927.00

PK 6.46. 1 M´ Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti :

6.46.1. Bahan
- Kayu meranti,papan 0.0086 M³ x Rp. 6,570,000.00 = Rp. 56,502.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 19,200.00 = Rp. 1,152.00
Jumlah (1) = Rp. 57,654.00

6.46.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000.00 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500.00 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000.00 = Rp. 1,650.00
- Mandor 0.050 Oh x Rp. 192,500.00 = Rp. 9,625.00
Jumlah (2) = Rp. 36,025.00

Jumlah (1) +(2) = Rp. 93,679.00


PK 6.47. 1 M´ Pasang rangka dinding pemisah, kayu damar laut :

6.47.1. Bahan
- Kayu damar laut, balok 0.0195 M³ x Rp. 11,220,000.00 = Rp. 218,790.00
- Meranti batu, papan 0.007 M³ x Rp. 11,250,000.00 = Rp. 78,750.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
Jumlah (1) = Rp. 299,460.00
6.47.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000.00 = Rp. 16,500.00
- Tukang kayu 0.450 Oh x Rp. 137,500.00 = Rp. 61,875.00
- Kepala tukang 0.045 Oh x Rp. 165,000.00 = Rp. 7,425.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 100,237.50

Jumlah (1) +(2) = Rp. 399,697.50

PK 6.48. 1 M´ Pasang rangka dinding pemisah, kayu meranti :

6.48.1. Bahan
- Kayu meranti, balok 0.0195 M³ x Rp. 6,270,000.00 = Rp. 122,265.00
- Kayu meranti, papan 0.007 M³ x Rp. 6,570,000.00 = Rp. 45,990.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
Jumlah (1) = Rp. 170,175.00
6.48.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000.00 = Rp. 16,500.00
- Tukang kayu 0.450 Oh x Rp. 137,500.00 = Rp. 61,875.00
- Kepala tukang 0.045 Oh x Rp. 165,000.00 = Rp. 7,425.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 100,237.50

Jumlah (1) +(2) = Rp. 270,412.50

PK 6.49. 1 M² Pasang dinding pemisah teakwood rangka, rangka kayu damar laut :

6.49.1. Bahan
- Kayu damar laut, balok 0.0290 M³ x Rp. 11,220,000.00 = Rp. 325,380.00
- Teakwood 4' x 8' 1.200 M³ x Rp. 156,000.00 = Rp. 187,200.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
Jumlah (1) = Rp. 514,500.00
6.49.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000.00 = Rp. 16,500.00
- Tukang kayu 0.450 Oh x Rp. 137,500.00 = Rp. 61,875.00
- Kepala tukang 0.045 Oh x Rp. 165,000.00 = Rp. 7,425.00
- Mandor 0.075 Oh x Rp. 192,500.00 = Rp. 14,437.50
Jumlah (2) = Rp. 100,237.50

Jumlah (1) +(2) = Rp. 614,737.50


PK 6.50. 1 M² Pasang dinding pemisah double plywood, rangka kayu damar laut :

6.50.1. Bahan
- Kayu damar laut, balok 0.0195 M³ x Rp. 11,220,000.00 = Rp. 218,790.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
- Lem kayu 0.560 Lt x Rp. 104,400.00 = Rp. 58,464.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 62,304.00 = Rp. 62,304.00
Jumlah (1) = Rp. 341,478.00
6.50.2. Tenaga
- Pekerja 0.200 Oh x Rp. 110,000.00 = Rp. 22,000.00
- Tukang kayu 0.600 Oh x Rp. 137,500.00 = Rp. 82,500.00
- Kepala tukang 0.060 Oh x Rp. 165,000.00 = Rp. 9,900.00
- Mandor 0.010 Oh x Rp. 192,500.00 = Rp. 1,925.00
Jumlah (2) = Rp. 116,325.00

Jumlah (1) +(2) = Rp. 457,803.00

PK 6.51. 1 M² Pasang dinding lambrizering dari papan meranti :

6.51.1. Bahan
- Kayu meranti, papan 0.0120 M³ x Rp. 6,570,000.00 = Rp. 78,840.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 19,200.00 = Rp. 1,920.00
- Paku skrup 3,5" 0.150 Lbr x Rp. 39,600.00 = Rp. 5,940.00
Jumlah (1) = Rp. 86,700.00
6.51.2. Tenaga
- Pekerja 0.600 Oh x Rp. 110,000.00 = Rp. 66,000.00
- Tukang kayu 1.800 Oh x Rp. 137,500.00 = Rp. 247,500.00
- Kepala tukang 0.180 Oh x Rp. 165,000.00 = Rp. 29,700.00
- Mandor 0.030 Oh x Rp. 192,500.00 = Rp. 5,775.00
Jumlah (2) = Rp. 348,975.00

Jumlah (1) +(2) = Rp. 435,675.00

PK 6.52. 1 M² Pasang plywood tebal 4 mm, untuk dinding :

6.52.1. Bahan

- Plywood 4' x 8' x 4 mm 0.4000 Lbr x Rp. 62,304.00 = Rp. 24,921.60


- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200.00 = Rp. 960.00
Jumlah (1) = Rp. 25,881.60
6.52.2. Tenaga

- Pekerja 0.025 Oh x Rp. 110,000.00 = Rp. 2,750.00


- Tukang kayu 0.075 Oh x Rp. 137,500.00 = Rp. 10,312.50
- Kepala tukang 0.0075 Oh x Rp. 165,000.00 = Rp. 1,237.50
- Mandor 0.0013 Oh x Rp. 192,500.00 = Rp. 250.25
Jumlah (2) = Rp. 14,550.25

Jumlah (1) +(2) = Rp. 40,431.85


PK 6.53. 1 M' Pasang list plafond kayu profil :

6.53.1. Bahan

- Kayu profil 2" 1.050 M' x Rp. 15,048.00 = Rp. 15,800.40


Jumlah (1) = Rp. 15,800.40
6.53.2. Tenaga

- Pekerja 0.021 Oh x Rp. 110,000.00 = Rp. 2,310.00


- Tukang kayu 0.021 Oh x Rp. 137,500.00 = Rp. 2,887.50
- Kepala tukang 0.002 Oh x Rp. 165,000.00 = Rp. 330.00
- Mandor 0.001 Oh x Rp. 192,500.00 = Rp. 192.50
Jumlah (2) = Rp. 5,720.00

Jumlah (1) +(2) = Rp. 21,520.40


ANALISA BIAYA KONSTRUKSI
PEKERJAAN BETON

PB 6.1. 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr

6.1.1 Bahan
- Semen portland 218.000 Kg x Rp. 1,800 = Rp. 392,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 5/7 0.870 M³ x Rp. 209,601 = Rp. 182,352.44
Jumlah (1) = Rp. 761,952.44

6.1.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 997,352.44


Keuntungan+Over head 10% = Rp 99,735.24
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,097,087.68

PB 6.2. 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr

6.2.1 Bahan
- Semen portland 197.000 Kg x Rp. 1,800 = Rp. 354,600.00
- Pasir beton 0.470 M³ x Rp. 360,000 = Rp. 169,200.00
- Koral beton 5/7 0.940 M³ x Rp. 209,601 = Rp. 197,024.47
Jumlah (1) = Rp. 720,824.47

6.2.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 956,224.47


Keuntungan+Over head 10% = Rp 95,622.45
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,051,846.92

PB 6.3. 1 M³ Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr

6.3.1 Bahan
- Semen portland 173.000 Kg x Rp. 1,800 = Rp. 311,400.00
- Pasir beton 0.570 M³ x Rp. 360,000 = Rp. 205,200.00
- Koral beton 5/7 0.870 M³ x Rp. 209,601 = Rp. 182,352.44
Jumlah (1) = Rp. 698,952.44

6.3.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00
Jumlah (1) + (2) = Rp. 934,352.44
Keuntungan+Over head 10% = Rp 93,435.24
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,027,787.68

PB 6.4. 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 Cm

6.4.1 Bahan
- Semen portland 10.000 Kg x Rp. 1,800 = Rp. 18,000.00
- Pasir beton 0.026 M³ x Rp. 360,000 = Rp. 9,360.00
- Koral beton 5/7 0.044 M³ x Rp. 209,601 = Rp. 9,222.42
Jumlah (1) = Rp. 36,582.42

6.4.2. Tenaga
- Pekerja 0.165 Oh x Rp. 110,000 = Rp. 18,150.00
- Tukang batu 0.025 Oh x Rp. 137,500 = Rp. 3,437.50
- Kepala tukang 0.002 Oh x Rp. 165,000 = Rp. 330.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 23,072.50

Jumlah (1) + (2) = Rp. 59,654.92


Keuntungan+Over head 10% = Rp 5,965.49
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 65,620.41

PB 6.5. 1 M³ Membuat beton 1 Pc : 2 Ps : 3 Kr

6.5.1. Bahan
- Semen portland 232.000 Kg x Rp. 1,800 = Rp. 417,600.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 5/7 0.780 M³ x Rp. 209,601 = Rp. 163,488.39
Jumlah (1) = Rp. 768,288.39
6.5.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,003,688.39


Keuntungan+Over head 10% = Rp 100,368.84
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,104,057.23

PB 6.6. 1 M³ Membuat beton 1 Pc : 2 Ps : 4 Kr

6.6.1. Bahan
- Semen portland 280.000 Kg x Rp. 1,800 = Rp. 504,000.00
- Pasir beton 0.450 M³ x Rp. 360,000 = Rp. 162,000.00
- Koral beton 3/5 0.900 M³ x Rp. 727,601 = Rp. 654,840.45
Jumlah (1) = Rp. 1,320,840.45
6.6.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,556,240.45


Keuntungan+Over head 10% = Rp 155,624.05
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,711,864.50
PB 6.7. 1 M³ Membuat beton 1 Pc : 2 Ps : 2,5 Kr

6.7.1. Bahan
- Semen portland 352.000 Kg x Rp. 1,800 = Rp. 633,600.00
- Pasir beton 0.560 M³ x Rp. 360,000 = Rp. 201,600.00
- Koral beton 3/5 0.700 M³ x Rp. 727,601 = Rp. 509,320.35
Jumlah (1) = Rp. 1,344,520.35
6.7.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,579,920.35


Keuntungan+Over head 10% = Rp 157,992.04
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,737,912.39

PB 6.8. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 3 Kr

6.8.1. Bahan
- Semen portland 357.000 Kg x Rp. 1,800 = Rp. 642,600.00
- Pasir beton 0.420 M³ x Rp. 360,000 = Rp. 151,200.00
- Koral beton 3/5 0.540 M³ x Rp. 727,601 = Rp. 392,904.27
Jumlah (1) = Rp. 1,186,704.27
6.8.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,422,104.27


Keuntungan+Over head 10% = Rp 142,210.43
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,564,314.70

PB 6.9. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr

6.9.1. Bahan
- Semen portland 386.000 Kg x Rp. 1,800 = Rp. 694,800.00
- Pasir beton 0.470 M³ x Rp. 360,000 = Rp. 169,200.00
- Koral beton 3/5 0.780 M³ x Rp. 727,601 = Rp. 567,528.39
Jumlah (1) = Rp. 1,431,528.39
6.9.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,666,928.39


Keuntungan+Over head 10% = Rp 166,692.84
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,833,621.23

PB 6.10. 1 M³ Membuat beton 1 Pc : 1 Ps : 2 Kr


6.10.1. Bahan
- Semen portland 479.000 Kg x Rp. 1,800 = Rp. 862,200.00
- Pasir beton 0.370 M³ x Rp. 360,000 = Rp. 133,200.00
- Koral beton 3/5 0.740 M³ x Rp. 727,601 = Rp. 538,424.37
Jumlah (1) = Rp. 1,533,824.37

6.10.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,769,224.37


Keuntungan+Over head 10% = Rp 176,922.44
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,946,146.81

PB 6.11. 1 M³ Membuat tiang pancang prestressed beton

6.11.1. Bahan
- Semen portland 440.000 Kg x Rp. 1,800 = Rp. 792,000.00
- Pasir beton 0.500 M³ x Rp. 360,000 = Rp. 180,000.00
- Koral beton/batu pecah 2/3 0.800 M³ x Rp. 325,200 = Rp. 260,160.00
- Rapidrant 2.460 Gln x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 1,232,160.00
6.11.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,467,560.00


Keuntungan+Over head 10% = Rp 146,756.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,614,316.00

PB 6.12. 1 M³ Membuat beton dengan puzzdith - 100 XR

6.12.1. Bahan
- Semen portland 336.000 Kg x Rp. 1,800 = Rp. 604,800.00
- Pasir beton 0.540 M³ x Rp. 360,000 = Rp. 194,400.00
- Koral beton 0.810 M³ x Rp. 727,601 = Rp. 589,356.41
- Puzzdith - 100 XR 1.000 Ltr x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 1,388,556.41
6.12.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.080 Oh x Rp. 192,500 = Rp. 15,400.00
Jumlah (2) = Rp. 235,400.00

Jumlah (1) + (2) = Rp. 1,623,956.41


Keuntungan+Over head 10% = Rp 162,395.64
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,786,352.05

PB 6.13. 1 M³ Membuat beton 1 Pc : 2 Ps : 3 Kr


6.13.1. Bahan
- Semen portland 336.000 Kg x Rp. 1,800 = Rp. 604,800.00
- Pasir beton 0.540 M³ x Rp. 360,000 = Rp. 194,400.00
- Koral beton/batu pecah 2/3 0.810 M³ x Rp. 325,200 = Rp. 263,412.00
Jumlah (1) = Rp. 1,062,612.00
6.13.2. Tenaga
- Pekerja 2.000 Oh x Rp. 110,000 = Rp. 220,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 1.000 Oh x Rp. 192,500 = Rp. 192,500.00
Jumlah (2) = Rp. 466,400.00

Jumlah (1) + (2) = Rp. 1,529,012.00


Keuntungan+Over head 10% = Rp 152,901.20
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,681,913.20

PB 6.14. 1 M³ Membuat beton 1 Pc : 2 Ps : 4 Kr

6.14.1. Bahan
- Semen portland 291.000 Kg x Rp. 1,800 = Rp. 523,800.00
- Pasir beton 0.470 M³ x Rp. 360,000 = Rp. 169,200.00
- Koral beton/batu pecah 2/3 0.930 M³ x Rp. 325,200 = Rp. 302,436.00
Jumlah (1) = Rp. 995,436.00
6.14.2. Tenaga
- Pekerja 2.000 Oh x Rp. 110,000 = Rp. 220,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 1.000 Oh x Rp. 192,500 = Rp. 192,500.00
Jumlah (2) = Rp. 466,400.00

Jumlah (1) + (2) = Rp. 1,461,836.00


Keuntungan+Over head 10% = Rp 146,183.60
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,608,019.60

PB 6.15. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 3 Kr

6.15.1. Bahan
- Semen portland 367.000 Kg x Rp. 1,800 = Rp. 660,600.00
- Pasir beton 0.440 M³ x Rp. 360,000 = Rp. 158,400.00
- Koral beton 2/3 0.880 M³ x Rp. 325,200 = Rp. 286,176.00
Jumlah (1) = Rp. 1,105,176.00

6.15.2. Tenaga

- Pekerja 2.000 Oh x Rp. 110,000 = Rp. 220,000.00


- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 1.000 Oh x Rp. 192,500 = Rp. 192,500.00
Jumlah (2) = Rp. 466,400.00

Jumlah (1) + (2) = Rp. 1,571,576.00


Keuntungan+Over head 10% = Rp 157,157.60
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,728,733.60

PB 6.16. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr


6.16.1. Bahan
- Semen portland 400.000 Kg x Rp. 1,800 = Rp. 720,000.00
- Pasir beton 0.480 M³ x Rp. 360,000 = Rp. 172,800.00
- Koral beton 2/3 0.880 M³ x Rp. 325,200 = Rp. 286,176.00
Jumlah (1) = Rp. 1,178,976.00
6.16.2. Tenaga
- Pekerja 2.000 Oh x Rp. 110,000 = Rp. 220,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 1.000 Oh x Rp. 192,500 = Rp. 192,500.00
Jumlah (2) = Rp. 466,400.00

Jumlah (1) + (2) = Rp. 1,645,376.00


Keuntungan+Over head 10% = Rp 164,537.60
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,809,913.60

PB 6.17. 1 M³ Membuat beton 1 Pc : 1 Ps : 1 Kr

6.17.1. Bahan
- Semen portland 615.000 Kg x Rp. 1,800 = Rp. 1,107,000.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 2/3 0.520 M³ x Rp. 325,200 = Rp. 169,104.00
Jumlah (1) = Rp. 1,463,304.00
6.17.2. Tenaga
- Pekerja 2.000 Oh x Rp. 110,000 = Rp. 220,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 1.000 Oh x Rp. 192,500 = Rp. 192,500.00
Jumlah (2) = Rp. 466,400.00

Jumlah (1) + (2) = Rp. 1,929,704.00


Keuntungan+Over head 10% = Rp 192,970.40
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 2,122,674.40

PB 6.18. 1 M³ Membuat beton kedap air dengan strorox - 100

6.18.1. Bahan
- Semen portland 400.000 Kg x Rp. 1,800 = Rp. 720,000.00
- Pasir beton 0.480 M³ x Rp. 360,000 = Rp. 172,800.00
- Koral beton 2/3 0.800 M³ x Rp. 325,200 = Rp. 260,160.00
- Strorox - 100 1.200 M³ x Rp. = Rp. 0.00
Jumlah (1) = Rp. 1,152,960.00

6.18.2. Tenaga
- Pekerja 2.000 Oh x Rp. 110,000 = Rp. 220,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 1.000 Oh x Rp. 192,500 = Rp. 192,500.00
Jumlah (2) = Rp. 466,400.00

Jumlah (1) + (2) = Rp. 1,619,360.00


Keuntungan+Over head 10% = Rp 161,936.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,781,296.00

PB 6.19. 1 M' Memasang PVC Waterstop lebar 150 mm


6.19.1. Bahan
- Waterstop lebar 150 mm 1.050 M' x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.19.2. Tenaga
- Pekerja 0.050 Oh x Rp. 110,000 = Rp. 5,500.00
- Tukang batu 0.030 Oh x Rp. 137,500 = Rp. 4,125.00
- Kepala tukang 0.003 Oh x Rp. 165,000 = Rp. 495.00
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 10,505.00

Jumlah (1) + (2) = Rp. 10,505.00


Keuntungan+Over head 10% = Rp 1,050.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 11,555.50

PB 6.20. 1 M' Memasang PVC Waterstop lebar 200 mm

6.20.1. Bahan
- Waterstop lebar 200 mm 1.050 M' x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.20.2. Tenaga
- Pekerja 0.050 Oh x Rp. 110,000 = Rp. 5,500.00
- Tukang batu 0.035 Oh x Rp. 137,500 = Rp. 4,812.50
- Kepala tukang 0.0035 Oh x Rp. 165,000 = Rp. 577.50
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 11,275.00

Jumlah (1) + (2) = Rp. 11,275.00


Keuntungan+Over head 10% = Rp 1,127.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 12,402.50

PB 6.21. 1 M' Memasang PVC Waterstop lebar 230 mm

6.21.1. Bahan
- Waterstop lebar 230 mm 1.050 M' x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.21.2. Tenaga
- Pekerja 0.550 Oh x Rp. 110,000 = Rp. 60,500.00
- Tukang batu 0.035 Oh x Rp. 137,500 = Rp. 4,812.50
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 65,697.50

Jumlah (1) + (2) = Rp. 65,697.50


Keuntungan+Over head 10% = Rp 6,569.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 72,267.25

PB 6.22. 1 M' Memasang PVC Waterstop lebar 250 mm

6.22.1. Bahan
- Waterstop lebar 250 mm 1.050 M' x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.22.2. Tenaga
- Pekerja 0.550 Oh x Rp. 110,000 = Rp. 60,500.00
- Tukang batu 0.035 Oh x Rp. 137,500 = Rp. 4,812.50
- Mandor 0.003 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 65,890.00

Jumlah (1) + (2) = Rp. 65,890.00


Keuntungan+Over head 10% = Rp 6,589.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 72,479.00

PB 6.23. 1 M' Memasang PVC Waterstop lebar 300 mm

6.23.1. Bahan
- Waterstop lebar 300 mm 1.050 M' x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.23.2. Tenaga
- Pekerja 0.300 Oh x Rp. 110,000 = Rp. 33,000.00
- Tukang batu 0.260 Oh x Rp. 137,500 = Rp. 35,750.00
- Kepala tukang 0.026 Oh x Rp. 165,000 = Rp. 4,290.00
- Mandor 0.005 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (2) = Rp. 74,002.50

Jumlah (1) + (2) = Rp. 74,002.50


Keuntungan+Over head 10% = Rp 7,400.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 81,402.75

PB 6.24 1 Kg Pembesian dengan Besi polos

6.24.1 Bahan
Besi beton polos 1.050 Kg x Rp. 13,200 = Rp. 13,860.00
Kawat beton 0.015 Kg x Rp. 21,600 = Rp. 324.00
Jumlah (1) = Rp. 14,184.00

6.24.2 Tenaga
Pekerja 0.00455 Oh x Rp. 110,000 = Rp. 500.50
Tukang besi 0.00455 Oh x Rp. 137,500 = Rp. 625.63
Kepala tukang 0.000455 Oh x Rp. 165,000 = Rp. 75.08
Mandor 0.000455 Oh x Rp. 192,500 = Rp. 87.59
Jumlah (2) = Rp. 1,288.79

Jumlah (1) + (2) = Rp. 15,472.79


Keuntungan+Over head 10% = Rp 1,547.28
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 17,020.07

PB 6.25 1 M² Kabel Presstressed polos / strands

6.25.1 Bahan
Besi Presstressed polos 1.050 Kg x Rp. 13,200 = Rp. 13,860.00
Kawat beton 0.010 Kg x Rp. 21,600 = Rp. 216.00
Jumlah (1) = Rp. 14,076.00

6.25.2 Tenaga
Pekerja 0.005 Oh x Rp. 110,000 = Rp. 550.00
Tukang besi 0.005 Oh x Rp. 137,500 = Rp. 687.50
Kepala tukang 0.005 Oh x Rp. 165,000 = Rp. 825.00
Mandor 0.003 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 2,640.00

Jumlah (1) + (2) = Rp. 16,716.00


Keuntungan+Over head 10% = Rp 1,671.60
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 18,387.60

PB 6.26 1 M² Pasang bekisting untuk pondasi

6.26.1 Bahan
Kayu sembarang 0.0200 M³ x Rp. 1,900,000 = Rp. 38,000.00
Paku biasa 2" - 5" 0.1500 Kg x Rp. 19,200 = Rp. 2,880.00
Minyak bekisting 0.987 Ltr x Rp. 4,800 = Rp. 4,736.59
Jumlah (1) = Rp. 45,616.59

6.26.2 Tenaga
Pekerja 0.1500 Oh x Rp. 110,000 = Rp. 16,500.00
Tukang besi 0.1300 Oh x Rp. 137,500 = Rp. 17,875.00
Kepala tukang 0.0130 Oh x Rp. 165,000 = Rp. 2,145.00
Mandor 0.0025 Oh x Rp. 192,500 = Rp. 481.25
Jumlah (2) = Rp. 37,001.25

Jumlah (1) + (2) = Rp. 82,617.84


Keuntungan+Over head 10% = Rp 8,261.78
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 90,879.63

PB 6.27. 1 M² Pasang bekisting untuk sloof

6.27.1. Bahan
- Kayu sembarang 0.0225 M³ x Rp. 1,900,000 = Rp. 42,750.00
- Paku biasa 2' - 5" 0.1500 Kg x Rp. 19,200 = Rp. 2,880.00
- Minyak bekisting 0.987 Lt x Rp. 4,800 = Rp. 4,736.59
Jumlah (1) = Rp. 50,366.59

6.27.2. Tenaga
- Pekerja 0.1500 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang batu 0.1300 Oh x Rp. 137,500 = Rp. 17,875.00
- Kepala tukang 0.0130 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.0025 Oh x Rp. 192,500 = Rp. 481.25
Jumlah (2) = Rp. 37,001.25

Jumlah (1) + (2) = Rp. 87,367.84


Keuntungan+Over head 10% = Rp 8,736.78
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 96,104.63

PB 6.28. 1 M² Pasang bekisting untuk kolom


6.28.1. Bahan
- Kayu sembarang 0.0200 M³ x Rp. 1,900,000 = Rp. 38,000.00
- Paku biasa 2' - 5" 0.2000 Kg x Rp. 19,200 = Rp. 3,840.00
- Minyak bekisting 0.2467 Lt x Rp. 4,800 = Rp. 1,184.15
- Balok kayu sembarang 0.0075 M³ x Rp. 4,390,400 = Rp. 32,928.00
- Plywood tebal 9 mm 0.1750 Lbr x Rp. 160,800 = Rp. 28,140.00
- Kayu dolken/Laut Ø 3"-4"/4 m 1.0000 Btg x Rp. 18,648 = Rp. 18,648.00
Jumlah (1) = Rp. 122,740.15

6.28.2. Tenaga
- Pekerja 0.1500 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang batu 0.1650 Oh x Rp. 137,500 = Rp. 22,687.50
- Kepala tukang 0.0165 Oh x Rp. 165,000 = Rp. 2,722.50
- Mandor 0.0030 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 42,487.50

Jumlah (1) + (2) = Rp. 165,227.65


Keuntungan+Over head 10% = Rp 16,522.76
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 181,750.41

PB 6.29. 1 M² Pasang bekisting untuk balok

6.29.1. Bahan
- Kayu sembarang 0.0200 M³ x Rp. 1,900,000 = Rp. 38,000.00
- Paku biasa 2' - 5" 0.2000 Kg x Rp. 19,200 = Rp. 3,840.00
- Minyak bekisting 0.4934 Lt x Rp. 4,800 = Rp. 2,368.30
- Balok kayu sembarang 0.0090 M³ x Rp. 4,390,400 = Rp. 39,513.60
- Plywood tebal 9 mm 0.1750 Lbr x Rp. 160,800 = Rp. 28,140.00
- Kayu dolken/Laut Ø 3"-4"/4 m 1.0000 Btg x Rp. 18,648 = Rp. 18,648.00
Jumlah (1) = Rp. 130,509.90

6.29.2. Tenaga
- Pekerja 0.1600 Oh x Rp. 110,000 = Rp. 17,600.00
- Tukang batu 0.1650 Oh x Rp. 137,500 = Rp. 22,687.50
- Kepala tukang 0.0165 Oh x Rp. 165,000 = Rp. 2,722.50
- Mandor 0.0030 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 43,587.50

Jumlah (1) + (2) = Rp. 174,097.40


Keuntungan+Over head 10% = Rp 17,409.74
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 191,507.14

PB 6.30. 1 M² Pasang bekisting untuk lantai

6.30.1. Bahan
- Kayu sembarang 0.0200 M³ x Rp. 1,900,000 = Rp. 38,000.00
- Paku biasa 2' - 5" 0.2000 Kg x Rp. 19,200 = Rp. 3,840.00
- Minyak bekisting 0.9868 Lt x Rp. 4,800 = Rp. 4,736.59
- Balok kayu sembarang 0.0075 M³ x Rp. 4,390,400 = Rp. 32,928.00
- Plywood tebal 9 mm 0.1750 Lbr x Rp. 160,800 = Rp. 28,140.00
- Kayu dolken/Laut Ø 3"-4"/4 m 3.0000 Btg x Rp. 18,648 = Rp. 55,944.00
Jumlah (1) = Rp. 163,588.59

6.30.2. Tenaga
- Pekerja 0.1600 Oh x Rp. 110,000 = Rp. 17,600.00
- Tukang batu 0.1650 Oh x Rp. 137,500 = Rp. 22,687.50
- Kepala tukang 0.0165 Oh x Rp. 165,000 = Rp. 2,722.50
- Mandor 0.0030 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 43,587.50

Jumlah (1) + (2) = Rp. 207,176.09


Keuntungan+Over head 10% = Rp 20,717.61
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 227,893.70

PB 6.31. 1 M² Pasang bekisting untuk dinding

6.31.1. Bahan
- Kayu sembarang 0.0300 M³ x Rp. 1,900,000 = Rp. 57,000.00
- Paku biasa 2' - 5" 0.4000 Kg x Rp. 19,200 = Rp. 7,680.00
- Minyak bekisting 0.9868 Lt x Rp. 4,800 = Rp. 4,736.59
- Balok kayu sembarang 0.0200 M³ x Rp. 4,390,400 = Rp. 87,808.00
- Plywood tebal 9 mm 0.3500 Lbr x Rp. 160,800 = Rp. 56,280.00
- Kayu dolken/Laut Ø 3"-4"/4 m 3.0000 Btg x Rp. 18,648 = Rp. 55,944.00
- Formtie/penjaga jarak bekisting/spacer 4.0000 Btg x Rp. 5,000 = Rp. 20,000.00
Jumlah (1) = Rp. 289,448.59

6.31.2. Tenaga
- Pekerja 0.3200 Oh x Rp. 110,000 = Rp. 35,200.00
- Tukang batu 0.3300 Oh x Rp. 137,500 = Rp. 45,375.00
- Kepala tukang 0.0330 Oh x Rp. 165,000 = Rp. 5,445.00
- Mandor 0.0060 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 87,175.00

Jumlah (1) + (2) = Rp. 376,623.59


Keuntungan+Over head 10% = Rp 37,662.36
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 414,285.95

PB 6.32. 1 M² Pasang bekisting untuk tangga

6.32.1. Bahan
- Kayu sembarang 0.0200 M³ x Rp. 1,900,000 = Rp. 38,000.00
- Paku biasa 2' - 5" 0.2000 Kg x Rp. 19,200 = Rp. 3,840.00
- Minyak bekisting 0.9868 Lt x Rp. 4,800 = Rp. 4,736.59
- Balok kayu sembarang 0.0075 M³ x Rp. 4,390,400 = Rp. 32,928.00
- Plywood tebal 9 mm 0.1750 Lbr x Rp. 160,800 = Rp. 28,140.00
- Kayu dolken/Laut Ø 3"-4"/4 m 3.0000 Btg x Rp. 18,648 = Rp. 55,944.00
Jumlah (1) = Rp. 163,588.59

6.32.2. Tenaga
- Pekerja 0.1600 Oh x Rp. 110,000 = Rp. 17,600.00
- Tukang batu 0.1650 Oh x Rp. 137,500 = Rp. 22,687.50
- Kepala tukang 0.0165 Oh x Rp. 165,000 = Rp. 2,722.50
- Mandor 0.0030 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 43,587.50

Jumlah (1) + (2) = Rp. 207,176.09


Keuntungan+Over head 10% = Rp 20,717.61
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 227,893.70
PB 6.33. 1 M³ Pasang beton dengan mutu K 225

6.33.1. Bahan
- Semen portland 388.000 Kg x Rp. 1,800 = Rp. 698,400.00
- Pasir beton 0.605 M³ x Rp. 360,000 = Rp. 217,800.00
- Batu pecah 0.650 M³ x Rp. 369,600 = Rp. 240,240.00
Jumlah (1) = Rp. 1,156,440.00

6.33.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.075 Oh x Rp. 192,500 = Rp. 14,437.50
Jumlah (2) = Rp. 217,937.50

Jumlah (1) + (2) = Rp. 1,374,377.50


Keuntungan+Over head 10% = Rp 137,437.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,511,815.25

PB 6.34. 1 M³ Pasang beton dengan mutu K 275

6.34.1. Bahan
- Semen portland 400.000 Kg x Rp. 1,800 = Rp. 720,000.00
- Pasir beton 0.420 M³ x Rp. 360,000 = Rp. 151,200.00
- Koral beton 0.820 M³ x Rp. 369,600 = Rp. 303,072.00
Jumlah (1) = Rp. 1,174,272.00

6.34.2. Tenaga
- Pekerja 1.500 Oh x Rp. 110,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.075 Oh x Rp. 192,500 = Rp. 14,437.50
Jumlah (2) = Rp. 217,937.50

Jumlah (1) + (2) = Rp. 1,392,209.50


Keuntungan+Over head 10% = Rp 139,220.95
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,531,430.45

PB 6.35. 1 M² Pasang jembatan cor

6.35.1. Bahan
- Kayu sembarang 0.0264 M³ x Rp. 1,900,000 = Rp. 50,160.00
- Paku biasa 2" - 5 " 0.600 Kg x Rp. 19,200 = Rp. 11,520.00
- Kayu dolken/Laut Ø 3"-4"/4 m 0.500 Btg x Rp. 18,648 = Rp. 9,324.00
Jumlah (1) = Rp. 71,004.00

6.35.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang batu 0.050 Oh x Rp. 137,500 = Rp. 6,875.00
- Kepala tukang 0.005 Oh x Rp. 165,000 = Rp. 825.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 25,740.00

Jumlah (1) + (2) = Rp. 96,744.00


Keuntungan+Over head 10% = Rp 9,674.40
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 106,418.40

PB 6.36. 1 M³ Membuat pondasi beton bertulang (150 kg besi + bekisting)

6.36.1. Bahan
- Kayu sembarang 0.2000 M³ x Rp. 1,900,000 = Rp. 380,000.00
- Paku biasa 2" - 5 " 1.500 Kg x Rp. 19,200 = Rp. 28,800.00
- Minyak bekisting 0.400 Lt x Rp. 4,800 = Rp. 1,920.00
- Besi beton polos 150.000 Kg x Rp. 13,200 = Rp. 1,980,000.00
- Kawat beton 2.250 Kg x Rp. 21,600 = Rp. 48,600.00
- Semen portland 323.000 Kg x Rp. 1,800 = Rp. 581,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 0.780 M³ x Rp. 369,600 = Rp. 288,288.00
Jumlah (1) = Rp. 3,496,208.00

6.36.2. Tenaga
- Pekerja 3.900 Oh x Rp. 110,000 = Rp. 429,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Tukang kayu 1.040 Oh x Rp. 137,500 = Rp. 143,000.00
- Tukang besi 1.050 Oh x Rp. 137,500 = Rp. 144,375.00
- Kepala tukang 0.245 Oh x Rp. 165,000 = Rp. 40,425.00
- Mandor 0.165 Oh x Rp. 192,500 = Rp. 31,762.50
Jumlah (2) = Rp. 836,687.50

Jumlah (1) + (2) = Rp. 4,332,895.50


Keuntungan+Over head 10% = Rp 433,289.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 4,766,185.05

PB 6.37. 1 M³ Membuat sloof beton bertulang (200 kg besi + bekisting)

6.37.1. Bahan
- Kayu sembarang 0.2700 M³ x Rp. 1,900,000 = Rp. 513,000.00
- Paku biasa 2" - 5 " 2.000 Kg x Rp. 19,200 = Rp. 38,400.00
- Minyak bekisting 0.600 Lt x Rp. 4,800 = Rp. 2,880.00
- Besi beton polos 200.000 Kg x Rp. 13,200 = Rp. 2,640,000.00
- Kawat beton 3.000 Kg x Rp. 21,600 = Rp. 64,800.00
- Semen portland 323.000 Kg x Rp. 1,800 = Rp. 581,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 0.780 M³ x Rp. 369,600 = Rp. 288,288.00
Jumlah (1) = Rp. 4,315,968.00

6.37.2. Tenaga
- Pekerja 4.850 Oh x Rp. 110,000 = Rp. 533,500.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Tukang kayu 1.560 Oh x Rp. 137,500 = Rp. 214,500.00
- Tukang besi 1.400 Oh x Rp. 137,500 = Rp. 192,500.00
- Kepala tukang 0.331 Oh x Rp. 165,000 = Rp. 54,615.00
- Mandor 0.170 Oh x Rp. 192,500 = Rp. 32,725.00
Jumlah (2) = Rp. 1,075,965.00

Jumlah (1) + (2) = Rp. 5,391,933.00


Keuntungan+Over head 10% = Rp 539,193.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 5,931,126.30
PB 6.38. 1 M³ Membuat kolom beton bertulang (300 kg besi + bekisting)

6.38.1. Bahan
- Kayu sembarang 0.4000 M³ x Rp. 1,900,000 = Rp. 760,000.00
- Paku biasa 2" - 5 " 4.000 Kg x Rp. 19,200 = Rp. 76,800.00
- Minyak bekisting 2.000 Lt x Rp. 4,800 = Rp. 9,600.00
- Besi beton polos 300.000 Kg x Rp. 13,200 = Rp. 3,960,000.00
- Kawat beton 4.500 Kg x Rp. 21,600 = Rp. 97,200.00
- Semen portland 323.000 Kg x Rp. 1,800 = Rp. 581,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 0.780 M³ x Rp. 369,600 = Rp. 288,288.00
- Kayu sembarang balok 0.150 M³ x Rp. 1,900,000 = Rp. 285,000.00
- Plywood 9 mm 3.500 Lbr x Rp. 160,800 = Rp. 562,800.00
- Kayu dolken/Laut Ø 3"-4"/4 m 20.000 Btg x Rp. 18,648 = Rp. 372,960.00
Jumlah (1) = Rp. 7,181,248.00

6.38.2. Tenaga
- Pekerja 7.300 Oh x Rp. 110,000 = Rp. 803,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Tukang kayu 3.300 Oh x Rp. 137,500 = Rp. 453,750.00
- Tukang besi 2.100 Oh x Rp. 137,500 = Rp. 288,750.00
- Kepala tukang 0.570 Oh x Rp. 165,000 = Rp. 94,050.00
- Mandor 0.250 Oh x Rp. 192,500 = Rp. 48,125.00
Jumlah (2) = Rp. 1,735,800.00

Jumlah (1) + (2) = Rp. 8,917,048.00


Keuntungan+Over head 10% = Rp 891,704.80
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 9,808,752.80

PB 6.39. 1 M³ Membuat balok beton bertulang (200 kg besi + bekisting)

6.39.1. Bahan
- Kayu sembarang 0.3200 M³ x Rp. 1,900,000 = Rp. 608,000.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 19,200 = Rp. 61,440.00
- Minyak bekisting 1.600 Lt x Rp. 4,800 = Rp. 7,680.00
- Besi beton polos 200.000 Kg x Rp. 13,200 = Rp. 2,640,000.00
- Kawat beton 3.000 Kg x Rp. 21,600 = Rp. 64,800.00
- Semen portland 323.000 Kg x Rp. 1,800 = Rp. 581,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 0.780 M³ x Rp. 369,600 = Rp. 288,288.00
- Kayu sembarang balok 0.140 M³ x Rp. 1,900,000 = Rp. 266,000.00
- Plywood 9 mm 2.800 Lbr x Rp. 160,800 = Rp. 450,240.00
- Kayu dolken/Laut Ø 3"-4"/4 m 16.000 Btg x Rp. 18,648 = Rp. 298,368.00
Jumlah (1) = Rp. 5,453,416.00

6.39.2. Tenaga
- Pekerja 5.960 Oh x Rp. 110,000 = Rp. 655,600.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Tukang kayu 2.800 Oh x Rp. 137,500 = Rp. 385,000.00
- Tukang besi 1.400 Oh x Rp. 137,500 = Rp. 192,500.00
- Kepala tukang 0.455 Oh x Rp. 165,000 = Rp. 75,075.00
- Mandor 0.208 Oh x Rp. 192,500 = Rp. 40,040.00
Jumlah (2) = Rp. 1,396,340.00

Jumlah (1) + (2) = Rp. 6,849,756.00


Keuntungan+Over head 10% = Rp 684,975.60
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 7,534,731.60

PB 6.40. 1 M³ Membuat balok beton bertulang (150 kg besi + bekisting)

6.40.1. Bahan
- Kayu sembarang 0.320 M³ x Rp. 1,900,000 = Rp. 608,000.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 19,200 = Rp. 61,440.00
- Minyak bekisting 1.600 Lt x Rp. 4,800 = Rp. 7,680.00
- Besi beton polos 150.000 Kg x Rp. 13,200 = Rp. 1,980,000.00
- Kawat beton 2.250 Kg x Rp. 21,600 = Rp. 48,600.00
- Semen portland 323.000 Kg x Rp. 1,800 = Rp. 581,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 0.780 M³ x Rp. 369,600 = Rp. 288,288.00
- Kayu sembarang balok 0.120 M³ x Rp. 1,900,000 = Rp. 228,000.00
- Plywood 9 mm 2.800 Lbr x Rp. 160,800 = Rp. 450,240.00
- Kayu dolken/Laut Ø 3"-4"/4 m 32.000 Btg x Rp. 18,648 = Rp. 596,736.00
Jumlah (1) = Rp. 5,037,584.00
6.40.2. Tenaga
- Pekerja 5.800 Oh x Rp. 110,000 = Rp. 638,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Tukang kayu 2.800 Oh x Rp. 137,500 = Rp. 385,000.00
- Tukang besi 1.050 Oh x Rp. 137,500 = Rp. 144,375.00
- Kepala tukang 0.420 Oh x Rp. 165,000 = Rp. 69,300.00
- Mandor 0.185 Oh x Rp. 192,500 = Rp. 35,612.50
Jumlah (2) = Rp. 1,320,412.50

Jumlah (1) + (2) = Rp. 6,357,996.50


Keuntungan+Over head 10% = Rp 635,799.65
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 6,993,796.15

PB 6.41. 1 M³ Membuat dinding beton bertulang (150 kg besi + bekisting)

6.41.1. Bahan
- Kayu sembarang 0.240 M³ x Rp. 1,900,000 = Rp. 456,000.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 19,200 = Rp. 61,440.00
- Minyak bekisting 1.600 Lt x Rp. 4,800 = Rp. 7,680.00
- Besi beton polos 150.000 Kg x Rp. 13,200 = Rp. 1,980,000.00
- Kawat beton 2.250 Kg x Rp. 21,600 = Rp. 48,600.00
- Semen portland 323.000 Kg x Rp. 1,800 = Rp. 581,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 0.780 M³ x Rp. 369,600 = Rp. 288,288.00
- Kayu sembarang balok 0.160 M³ x Rp. 1,900,000 = Rp. 304,000.00
- Plywood 9 mm 2.800 Lbr x Rp. 160,800 = Rp. 450,240.00
- Kayu dolken/Laut Ø 3"-4"/4 m 24.000 Btg x Rp. 18,648 = Rp. 447,552.00
Jumlah (1) = Rp. 4,812,400.00

6.41.2. Tenaga
- Pekerja 5.600 Oh x Rp. 110,000 = Rp. 616,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Tukang kayu 2.640 Oh x Rp. 137,500 = Rp. 363,000.00
- Tukang besi 1.050 Oh x Rp. 137,500 = Rp. 144,375.00
- Kepala tukang 0.400 Oh x Rp. 165,000 = Rp. 66,000.00
- Mandor 0.193 Oh x Rp. 192,500 = Rp. 37,152.50
Jumlah (2) = Rp. 1,274,652.50

Jumlah (1) + (2) = Rp. 6,087,052.50


Keuntungan+Over head 10% = Rp 608,705.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 6,695,757.75

PB 6.42. 1 M³ Membuat tangga beton bertulang (150 kg besi + bekisting)

6.42.1. Bahan
- Kayu sembarang 0.250 M³ x Rp. 1,900,000 = Rp. 475,000.00
- Paku biasa 2" - 5 " 3.000 Kg x Rp. 19,200 = Rp. 57,600.00
- Minyak bekisting 1.200 Lt x Rp. 4,800 = Rp. 5,760.00
- Besi beton polos 200.000 Kg x Rp. 13,200 = Rp. 2,640,000.00
- Kawat beton 3.000 Kg x Rp. 21,600 = Rp. 64,800.00
- Semen portland 323.000 Kg x Rp. 1,800 = Rp. 581,400.00
- Pasir beton 0.520 M³ x Rp. 360,000 = Rp. 187,200.00
- Koral beton 0.780 M³ x Rp. 369,600 = Rp. 288,288.00
- Kayu sembarang balok 0.105 M³ x Rp. 1,900,000 = Rp. 199,500.00
- Plywood 9 mm 2.500 Lbr x Rp. 160,800 = Rp. 402,000.00
- Kayu dolken/Laut Ø 3"-4"/4 m 14.000 Btg x Rp. 18,648 = Rp. 261,072.00
Jumlah (1) = Rp. 5,162,620.00

6.42.2. Tenaga
- Pekerja 5.600 Oh x Rp. 110,000 = Rp. 616,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Tukang kayu 2.300 Oh x Rp. 137,500 = Rp. 316,250.00
- Tukang besi 1.400 Oh x Rp. 137,500 = Rp. 192,500.00
- Kepala tukang 0.405 Oh x Rp. 165,000 = Rp. 66,825.00
- Mandor 0.202 Oh x Rp. 192,500 = Rp. 38,885.00
Jumlah (2) = Rp. 1,278,585.00

Jumlah (1) + (2) = Rp. 6,441,205.00


Keuntungan+Over head 10% = Rp 644,120.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 7,085,325.50

PB 6.43. 1 M' Membuat kolom penguat beton bertulang (11 x 11) cm

6.43.1. Bahan
- Kayu sembarang 0.002 M³ x Rp. 1,900,000 = Rp. 3,800.00
- Paku biasa 2" - 5 " 0.010 Kg x Rp. 19,200 = Rp. 192.00
- Besi beton polos 2.749 Kg x Rp. 17,020 = Rp. 46,786.46
- Kawat beton 0.450 Kg x Rp. 21,600 = Rp. 9,720.00
- Semen portland 4.000 Kg x Rp. 1,800 = Rp. 7,200.00
- Pasir beton 0.006 M³ x Rp. 360,000 = Rp. 2,160.00
- Koral beton 0.009 M³ x Rp. 369,600 = Rp. 3,326.40
Jumlah (1) = Rp. 73,184.86

6.43.2. Tenaga
- Pekerja 0.180 Oh x Rp. 110,000 = Rp. 19,800.00
- Tukang batu 0.020 Oh x Rp. 137,500 = Rp. 2,750.00
- Tukang kayu 0.020 Oh x Rp. 137,500 = Rp. 2,750.00
- Tukang besi 0.020 Oh x Rp. 137,500 = Rp. 2,750.00
- Kepala tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.009 Oh x Rp. 192,500 = Rp. 1,732.50
Jumlah (2) = Rp. 30,772.50

Jumlah (1) + (2) = Rp. 103,957.36


Keuntungan+Over head 10% = Rp 10,395.74
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 114,353.10

PB 6.44. 1 M' Membuat ring balok beton bertulang (10 x 15) cm

6.44.1. Bahan
- Kayu sembarang 0.003 M³ x Rp. 1,900,000 = Rp. 5,700.00
- Paku biasa 2" - 5 " 0.020 Kg x Rp. 19,200 = Rp. 384.00
- Besi beton polos 3.600 Kg x Rp. 17,020 = Rp. 61,272.24
- Kawat beton 0.050 Kg x Rp. 21,600 = Rp. 1,080.00
- Semen portland 5.500 Kg x Rp. 1,800 = Rp. 9,900.00
- Pasir beton 0.009 M³ x Rp. 360,000 = Rp. 3,240.00
- Koral beton 0.015 M³ x Rp. 369,600 = Rp. 5,544.00
Jumlah (1) = Rp. 87,120.24

6.44.2. Tenaga
- Pekerja 0.297 Oh x Rp. 110,000 = Rp. 32,670.00
- Tukang batu 0.033 Oh x Rp. 137,500 = Rp. 4,537.50
- Tukang kayu 0.033 Oh x Rp. 137,500 = Rp. 4,537.50
- Tukang besi 0.033 Oh x Rp. 137,500 = Rp. 4,537.50
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.015 Oh x Rp. 192,500 = Rp. 2,887.50
Jumlah (2) = Rp. 50,820.00

Jumlah (1) + (2) = Rp. 137,940.24


Keuntungan+Over head 10% = Rp 13,794.02
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 151,734.26

PB 6.45. Membuat 1 m3 beton mutu f'c = 7,4 Mpa

6.45.1. Bahan
- Semen portland 247.000 Kg x Rp. 1,800 = Rp. 444,600.00
- Pasir beton 869.000 Kg x Rp. 257 = Rp. 223,457.14
- Kerikil (maks 30 mm) 999.000 Kg x Rp. 274 = Rp. 273,504.00

Jumlah (1) = Rp. 941,561.14

6.45.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,181,471.14


Keuntungan+Over head 10% = Rp 118,147.11
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,299,618.26

PB 6.46 Membuat 1 m3 beton mutu f'c = 9,8 Mpa


6.46.1. Bahan
- Semen portland 276.000 Kg x Rp. 1,800 = Rp. 496,800.00
- Pasir beton 828.000 Kg x Rp. 257 = Rp. 212,914.29
- Kerikil (maks 30 mm) 1012.000 Kg x Rp. 274 = Rp. 277,063.11

Jumlah (1) = Rp. 986,777.40

6.46.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,226,687.40


Keuntungan+Over head 10% = Rp 122,668.74
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,349,356.14

PB 6.47. Membuat 1 m3 beton mutu f'c = 12,2 Mpa

6.47.1. Bahan
- Semen portland 299.000 Kg x Rp. 1,800 = Rp. 538,200.00
- Pasir beton 799.000 Kg x Rp. 257 = Rp. 205,457.14
- Kerikil (maks 30 mm) 1017.000 Kg x Rp. 274 = Rp. 278,432.00

Jumlah (1) = Rp. 1,022,089.14

6.47.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,261,999.14


Keuntungan+Over head 10% = Rp 126,199.91
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,388,199.06

PB 6.48. Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa slump (3-6) cm, w/c=0,87

6.48.1. Bahan
- Semen portland 230.000 Kg x Rp. 1,800 = Rp. 414,000.00
- Pasir beton 893.000 Kg x Rp. 257 = Rp. 229,628.57
- Kerikil (maks 30 mm) 1027.000 Kg x Rp. 274 = Rp. 281,169.78

Jumlah (1) = Rp. 924,798.35

6.48.2. Tenaga
- Pekerja 1.200 Oh x Rp. 110,000 = Rp. 132,000.00
- Tukang batu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.060 Oh x Rp. 192,500 = Rp. 11,550.00
Jumlah (2) = Rp. 174,350.00

Jumlah (1) + (2) = Rp. 1,099,148.35


Keuntungan+Over head 10% = Rp 109,914.83
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,209,063.18

PB 6.49. Membuat 1 m3 lantai kerja beton mutu f'c = 14,5 Mpa slump (120±20) mm
6.49.1. Bahan
- Semen portland 326.000 Kg x Rp. 1,800 = Rp. 586,800.00
- Pasir beton 760.000 Kg x Rp. 257 = Rp. 195,428.57
- Kerikil (maks 30 mm) 1029.000 Kg x Rp. 274 = Rp. 281,717.33

Jumlah (1) = Rp. 1,063,945.90

6.49.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,303,855.90


Keuntungan+Over head 10% = Rp 130,385.59
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,434,241.50

PB 6.50. Membuat 1 m3 beton mutu f'c = 16,9 Mpa

6.50.1. Bahan
- Semen portland 352.000 Kg x Rp. 1,800 = Rp. 633,600.00
- Pasir beton 731.000 Kg x Rp. 257 = Rp. 187,971.43
- Kerikil (maks 30 mm) 1031.000 Kg x Rp. 274 = Rp. 282,264.89

Jumlah (1) = Rp. 1,103,836.32

6.50.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,343,746.32


Keuntungan+Over head 10% = Rp 134,374.63
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,478,120.95

PB 6.51. Membuat 1 m3 beton mutu f'c = 19,3 Mpa

6.51.1. Bahan
- Semen portland 371.000 Kg x Rp. 1,800 = Rp. 667,800.00
- Pasir beton 698.000 Kg x Rp. 257 = Rp. 179,485.71
- Kerikil (maks 30 mm) 1047.000 Kg x Rp. 274 = Rp. 286,645.33

Jumlah (1) = Rp. 1,133,931.05

6.51.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,373,841.05


Keuntungan+Over head 10% = Rp 137,384.10
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,511,225.15
PB 6.52. Membuat 1 m3 beton mutu f'c = 21,7 Mpa

6.52.1. Bahan
- Semen portland 384.000 Kg x Rp. 1,800 = Rp. 691,200.00
- Pasir beton 692.000 Kg x Rp. 257 = Rp. 177,942.86
- Kerikil (maks 30 mm) 1039.000 Kg x Rp. 274 = Rp. 284,455.11

Jumlah (1) = Rp. 1,153,597.97

6.52.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,393,507.97


Keuntungan+Over head 10% = Rp 139,350.80
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,532,858.77

PB 6.53. Membuat 1 m3 beton mutu f'c = 24,0 Mpa

6.53.1. Bahan
- Semen portland 406.000 Kg x Rp. 1,800 = Rp. 730,800.00
- Pasir beton 684.000 Kg x Rp. 257.14 = Rp. 175,885.71
- Kerikil (maks 30 mm) 1026.000 Kg x Rp. 273.78 = Rp. 280,896.00

Jumlah (1) = Rp. 1,187,581.71

6.53.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,427,491.71


Keuntungan+Over head 10% = Rp 142,749.17
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,570,240.89

PB 6.54. Membuat 1 m3 beton mutu f'c = 26,4 Mpa

6.54.1. Bahan
- Semen portland 413.000 Kg x Rp. 1,800 = Rp. 743,400.00
- Pasir beton 681.000 Kg x Rp. 257 = Rp. 175,114.29
- Kerikil (maks 30 mm) 1021.000 Kg x Rp. 274 = Rp. 279,527.11

Jumlah (1) = Rp. 1,198,041.40

6.54.2. Tenaga
- Pekerja 1.650 Oh x Rp. 110,000 = Rp. 181,500.00
- Tukang batu 0.275 Oh x Rp. 137,500 = Rp. 37,812.50
- Kepala tukang 0.028 Oh x Rp. 165,000 = Rp. 4,620.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 239,910.00

Jumlah (1) + (2) = Rp. 1,437,951.40


Keuntungan+Over head 10% = Rp 143,795.14
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,581,746.54
PB 6.55. Membuat 1 m3 beton mutu f'c = 28,8 Mpa

6.55.1. Bahan
- Semen portland 439.000 Kg x Rp. 1,800 = Rp. 790,200.00
- Pasir beton 670.000 Kg x Rp. 257 = Rp. 172,285.71
- Kerikil (maks 30 mm) 1006.000 Kg x Rp. 274 = Rp. 275,420.44

Jumlah (1) = Rp. 1,237,906.16

6.55.2. Tenaga
- Pekerja 2.100 Oh x Rp. 110,000 = Rp. 231,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 0.105 Oh x Rp. 192,500 = Rp. 20,212.50
Jumlah (2) = Rp. 305,112.50

Jumlah (1) + (2) = Rp. 1,543,018.66


Keuntungan+Over head 10% = Rp 154,301.87
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,697,320.52

PB 6.56. Membuat 1 m3 beton mutu f'c = 31,2 Mpa slump (120±20) mm

6.56.1. Bahan
- Semen portland 448.000 Kg x Rp. 1,800 = Rp. 806,400.00
- Pasir beton 667.000 Kg x Rp. 257 = Rp. 171,514.29
- Kerikil (maks 30 mm) 1000.000 Kg x Rp. 274 = Rp. 273,777.78

Jumlah (1) = Rp. 1,251,692.06

6.56.2. Tenaga
- Pekerja 2.100 Oh x Rp. 110,000 = Rp. 231,000.00
- Tukang batu 0.350 Oh x Rp. 137,500 = Rp. 48,125.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 0.105 Oh x Rp. 192,500 = Rp. 20,212.50
Jumlah (2) = Rp. 305,112.50

Jumlah (1) + (2) = Rp. 1,556,804.56


Keuntungan+Over head 10% = Rp 155,680.46
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,712,485.02

PB 6.57. Pemasangan 10 kg jaring kawat baja (wiremesh)

6.57.1. Bahan
- Jaring kawat baja di las 10.200 Kg x Rp. 13,200 = Rp. 134,640.00
- Kawat beton 0.050 Kg x Rp. 21,600 = Rp. 1,080.00

Jumlah (1) = Rp. 135,720.00

6.57.2. Tenaga
- Pekerja 0.025 Oh x Rp. 110,000 = Rp. 2,750.00
- Tukang besi 0.025 Oh x Rp. 137,500 = Rp. 3,437.50
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.001 Oh x Rp. 192,500 = Rp. 192.50
Jumlah (2) = Rp. 10,505.00

Jumlah (1) + (2) = Rp. 146,225.00


Keuntungan+Over head 10% = Rp 14,622.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 160,847.50
ANALISA BIAYA KONSTRUKSI
PEKERJAAN SANITASI

PS 6.1. Memasang 1 buah kloset duduk/monoblok

6.1.1. Bahan
- Klosed duduk/monoblok 1.000 Bh x Rp. 3,615,600 = Rp. 3,615,600.00
- Perlengkapan 6% harga klosed x Rp. 3,615,600 = Rp. 216,936.00
Jumlah (1) = Rp. 3,832,536.00
6.1.2. Tenaga
- Pekerja 3.300 Oh x Rp. 110,000 = Rp. 363,000.00
- Tukang batu 1.500 Oh x Rp. 137,500 = Rp. 206,250.00
- Kepala tukang 0.150 Oh x Rp. 165,000 = Rp. 24,750.00
- Mandor 0.160 Oh x Rp. 192,500 = Rp. 30,800.00
Jumlah (2) = Rp. 624,800.00

Jumlah (1) + (2) = Rp. 4,457,336.00


Keuntungan+Over head 10% = Rp 445,733.60
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 4,903,069.60

PS 6.2. Memasang 1 buah kloset jongkok porselen

6.2.1. Bahan
- Klosed jongkok porselin 1.000 Bh x Rp. 422,400 = Rp. 422,400.00
- Semen portland 6.000 Kg x Rp. 1,800 = Rp. 10,800.00
- Pasir pasang 0.010 M³ x Rp. 342,000 = Rp. 3,420.00
Jumlah (1) = Rp. 436,620.00
6.2.2. Tenaga
- Pekerja 1.100 Oh x Rp. 110,000 = Rp. 121,000.00
- Tukang batu 1.500 Oh x Rp. 137,500 = Rp. 206,250.00
- Kepala tukang 0.150 Oh x Rp. 165,000 = Rp. 24,750.00
- Mandor 0.110 Oh x Rp. 192,500 = Rp. 21,175.00
Jumlah (2) = Rp. 373,175.00

Jumlah (1) + (2) = Rp. 809,795.00


Keuntungan+Over head 10% = Rp 80,979.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 890,774.50

PS 6.2. Memasang 1 buah kloset jongkok porselen + flush (Toto, American Standart, Waser)

6.2.1. Bahan
- Klosed jongkok porselin + flush 1.000 Bh x Rp. 1,750,000 = Rp. 1,750,000.00
- Semen portland 6.000 Kg x Rp. 1,800 = Rp. 10,800.00
- Pasir pasang 0.010 M³ x Rp. 342,000 = Rp. 3,420.00
Jumlah (1) = Rp. 1,764,220.00
6.2.2. Tenaga
- Pekerja 1.100 Oh x Rp. 110,000 = Rp. 121,000.00
- Tukang batu 1.500 Oh x Rp. 137,500 = Rp. 206,250.00
- Kepala tukang 0.150 Oh x Rp. 165,000 = Rp. 24,750.00
- Mandor 0.110 Oh x Rp. 192,500 = Rp. 21,175.00
Jumlah (2) = Rp. 373,175.00

Jumlah (1) + (2) = Rp. 2,137,395.00


Keuntungan+Over head 10% = Rp 213,739.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 2,351,134.50
PS 6.3. Memasang 1 buah kloset jongkok teraso

6.3.1. Bahan
- Klosed jongkok teraso 1.000 Bh x Rp. 986,400 = Rp. 986,400.00
- Bata merah 5x10x20 cm 7.000 Bh x Rp. 1,200 = Rp. 8,400.00
- Semen portland 6.000 Kg x Rp. 1,800 = Rp. 10,800.00
- Pasir pasang 0.010 M³ x Rp. 342,000 = Rp. 3,420.00
Jumlah (1) = Rp. 1,009,020.00
6.3.2. Tenaga
- Pekerja 1.000 Oh x Rp. 110,000 = Rp. 110,000.00
- Tukang batu 1.500 Oh x Rp. 137,500 = Rp. 206,250.00
- Kepala tukang 0.150 Oh x Rp. 165,000 = Rp. 24,750.00
- Mandor 0.100 Oh x Rp. 192,500 = Rp. 19,250.00
Jumlah (2) = Rp. 360,250.00

Jumlah (1) + (2) = Rp. 1,369,270.00


Keuntungan+Over head 10% = Rp 136,927.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,506,197.00

PS 6.4 Memasang 1 buah urinoir (Toto, American Standart, Waser)

6.4.1. Bahan
- Urinoir 1.000 Bh x Rp. 2,000,000 = Rp. 2,000,000.00
- Perlengkapan 15% harga urinoir x Rp. 2,000,000 = Rp. 300,000.00
- Semen portland 6.000 Kg x Rp. 1,800 = Rp. 10,800.00
- Pasir pasang 0.010 M³ x Rp. 342,000 = Rp. 3,420.00
Jumlah (1) = Rp. 2,314,220.00
6.4.2. Tenaga
- Pekerja 1.000 Oh x Rp. 110,000 = Rp. 110,000.00
- Tukang batu 1.000 Oh x Rp. 137,500 = Rp. 137,500.00
- Kepala tukang 0.100 Oh x Rp. 165,000 = Rp. 16,500.00
- Mandor 0.100 Oh x Rp. 192,500 = Rp. 19,250.00
Jumlah (2) = Rp. 283,250.00

Jumlah (1) + (2) = Rp. 2,597,470.00


Keuntungan+Over head 10% = Rp 259,747.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 2,857,217.00

PS 6.5 Memasang 1 buah wastafel

6.5.1. Bahan
- Wastafel 1.000 Bh x Rp. 986,400 = Rp. 986,400.00
- Perlengkapan 12% harga wastafel x Rp. 986,400 = Rp. 118,368.00
- Semen portland 6.000 Kg x Rp. 1,800 = Rp. 10,800.00
- Pasir pasang 0.010 M³ x Rp. 342,000 = Rp. 3,420.00
Jumlah (1) = Rp. 1,118,988.00
6.5.2. Tenaga
- Pekerja 1.200 Oh x Rp. 110,000 = Rp. 132,000.00
- Tukang batu 1.450 Oh x Rp. 137,500 = Rp. 199,375.00
- Kepala tukang 0.150 Oh x Rp. 165,000 = Rp. 24,750.00
- Mandor 0.100 Oh x Rp. 192,500 = Rp. 19,250.00
Jumlah (2) = Rp. 375,375.00

Jumlah (1) + (2) = Rp. 1,494,363.00


Keuntungan+Over head 10% = Rp 149,436.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,643,799.30

PS 6.6. Memasang 1 buah bak mandi teraso volume 0,30 m³

6.6.1. Bahan
- Bak teraso 1.000 Bh x Rp. 339,600 = Rp. 339,600.00
- Semen portland 6.000 Kg x Rp. 1,800 = Rp. 10,800.00
- Pasir pasang 0.010 M³ x Rp. 342,000 = Rp. 3,420.00
Jumlah (1) = Rp. 353,820.00
6.6.2. Tenaga
- Pekerja 2.100 Oh x Rp. 110,000 = Rp. 231,000.00
- Tukang batu 0.750 Oh x Rp. 137,500 = Rp. 103,125.00
- Kepala tukang 0.075 Oh x Rp. 165,000 = Rp. 12,375.00
- Mandor 0.110 Oh x Rp. 192,500 = Rp. 21,175.00
Jumlah (2) = Rp. 367,675.00

Jumlah (1) + (2) = Rp. 721,495.00


Keuntungan+Over head 10% = Rp 72,149.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 793,644.50

PS 6.7. Memasang 1 buah bak mandi fibreglass volume 0,30 m³

6.7.1. Bahan
- Bak fibreglass 1.000 Bh x Rp. 339,600 = Rp. 339,600.00
- Perlengkapan 18% Harga bak x Rp. 339,600 = Rp. 61,128.00
Jumlah (1) = Rp. 400,728.00
6.7.2. Tenaga
- Pembantu tukang 1.800 Oh x Rp. 110,000 = Rp. 198,000.00
- Tukang batu 0.540 Oh x Rp. 137,500 = Rp. 74,250.00
- Kepala tukang 0.054 Oh x Rp. 165,000 = Rp. 8,910.00
- Mandor 0.110 Oh x Rp. 192,500 = Rp. 21,175.00
Jumlah (2) = Rp. 302,335.00

Jumlah (1) + (2) = Rp. 703,063.00


Keuntungan+Over head 10% = Rp 70,306.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 773,369.30

0.35129

PS 6.8. Memasang 1 buah bak mandi batu bata volume 0,30 m³

6.8.1. Bahan
- Batu bata 44.000 M³ x Rp. 1,200 = Rp. 52,800.00
- Semen portland 120.000 Kg x Rp. 1,800 = Rp. 216,000.00
- Pasir pasang 0.300 M³ x Rp. 342,000 = Rp. 102,600.00
- Porselin (11x11) cm 360.000 Bh x Rp. 2,400 = Rp. 864,000.00
- Semen putih 6.000 Kg x Rp. 13,200 = Rp. 79,200.00
Jumlah (1) = Rp. 1,314,600.00
6.8.2. Tenaga
- Pekerja 3.000 Oh x Rp. 110,000 = Rp. 330,000.00
- Tukang batu 3.000 Oh x Rp. 137,500 = Rp. 412,500.00
- Kepala tukang 0.300 Oh x Rp. 165,000 = Rp. 49,500.00
- Mandor 0.300 Oh x Rp. 192,500 = Rp. 57,750.00
Jumlah (2) = Rp. 849,750.00

Jumlah (1) + (2) = Rp. 2,164,350.00


Keuntungan+Over head 10% = Rp 216,435.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 2,380,785.00

PS 6.9. Memasang 1 buah badkip porselin

6.9.1. Bahan
- Badkip 1.000 Bh x Rp. 5,664,000 = Rp. 5,664,000.00
- Perlengkapan 20% Harga badkip x Rp. 5,664,000 = Rp. 1,132,800.00
Jumlah (1) = Rp. 6,796,800.00
6.9.2. Tenaga
- Pekerja 2.500 Oh x Rp. 110,000 = Rp. 275,000.00
- Tukang batu 0.750 Oh x Rp. 137,500 = Rp. 103,125.00
- Kepala tukang 0.075 Oh x Rp. 165,000 = Rp. 12,375.00
- Mandor 0.250 Oh x Rp. 192,500 = Rp. 48,125.00
Jumlah (2) = Rp. 438,625.00

Jumlah (1) + (2) = Rp. 7,235,425.00


Keuntungan+Over head 10% = Rp 723,542.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 7,958,967.50

PS 6.10. Memasang 1 buah bak mandi beton volume 1 m³ air

6.10.1Bahan
- Beton 1 : 1 ½ : 2½ 0.900 M³ x Rp. 0 = Rp. 0.00
- Besi beton 180.000 Kg x Rp. 13,200 = Rp. 2,376,000.00
- Kayu cetakan 0.096 M³ x Rp. 1,900,000 = Rp. 182,400.00
- Ubin porselin 420.000 M² x Rp. 2,400 = Rp. 1,008,000.00
- Perlengkapan 10% Hrg total bahan x Rp. 3,566,400 = Rp. 356,640.00
Jumlah (1) = Rp. 3,923,040.00

6.10.2Tenaga
- Pekerja 3.500 Oh x Rp. 110,000 = Rp. 385,000.00
- Tukang batu 4.500 Oh x Rp. 137,500 = Rp. 618,750.00
- Kepala tukang 0.900 Oh x Rp. 165,000 = Rp. 148,500.00
- Mandor 0.900 Oh x Rp. 192,500 = Rp. 173,250.00
Jumlah (2) = Rp. 1,325,500.00

Jumlah (1) + (2) = Rp. 5,248,540.00


Keuntungan+Over head 10% = Rp 524,854.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 5,773,394.00

PS 6.11. Memasang 1 buah bak fibreglass volume 1 m³ air

6.11.1Bahan
- Bak fibreglass 1.000 Bh x Rp. 339,600 = Rp. 339,600.00
- Perlengkapan 12% Harga bak x Rp. 339,600 = Rp. 40,752.00
Jumlah (1) = Rp. 380,352.00
6.11.2Tenaga
- Pekerja 3.000 Oh x Rp. 110,000 = Rp. 330,000.00
- Tukang batu 4.500 Oh x Rp. 137,500 = Rp. 618,750.00
- Kepala tukang 0.900 Oh x Rp. 165,000 = Rp. 148,500.00
- Mandor 0.900 Oh x Rp. 192,500 = Rp. 173,250.00
Jumlah (2) = Rp. 1,270,500.00
Jumlah (1) + (2) = Rp. 1,650,852.00
Keuntungan+Over head 10% = Rp 165,085.20
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,815,937.20

PS 6.12. Memasang 1 m' pipa beton, diameter 30 cm - 100 cm

6.12.1Bahan
- Pipa beton 1.100 Bh x Rp. 96,000 = Rp. 105,600.00
- Batu bata 55.000 Bh x Rp. 1,200 = Rp. 66,000.00
- Semen portland 10.300 Kg x Rp. 1,800 = Rp. 18,540.00
- Pasir pasang 0.061 M³ x Rp. 342,000 = Rp. 20,862.00
- Pasir urug 0.069 M³ x Rp. 325,200 = Rp. 22,438.80
Jumlah (1) = Rp. 233,440.80
6.12.2Tenaga
- Pekerja 0.380 Oh x Rp. 110,000 = Rp. 41,800.00
- Tukang batu 0.190 Oh x Rp. 137,500 = Rp. 26,125.00
- Kepala tukang 0.019 Oh x Rp. 165,000 = Rp. 3,135.00
- Mandor 0.019 Oh x Rp. 192,500 = Rp. 3,657.50
Jumlah (2) = Rp. 74,717.50

Jumlah (1) + (2) = Rp. 308,158.30


Keuntungan+Over head 10% = Rp 30,815.83
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 338,974.13

PS 6.13. Memasang 1 buah bak kontrol pasangan batu bata ukuran (30 x 30) cm
tinggi 35 cm

6.13.1Bahan
- Batu bata 145.000 Bh x Rp. 1,200 = Rp. 174,000.00
- Semen portland 44.000 Kg x Rp. 1,800 = Rp. 79,200.00
- Pasir pasang 0.070 M³ x Rp. 342,000 = Rp. 23,940.00
- Batu kerikil 0.070 M³ x Rp. 727,601 = Rp. 50,932.04
- Besi beton 1.600 Kg x Rp. 13,200 = Rp. 21,120.00
- Pasir beton 0.060 M³ x Rp. 360,000 = Rp. 21,600.00
Jumlah (1) = Rp. 370,792.04
6.13.2Tenaga
- Pekerja 3.200 Oh x Rp. 110,000 = Rp. 352,000.00
- Tukang batu 1.015 Oh x Rp. 137,500 = Rp. 139,562.50
- Kepala tukang 0.0015 Oh x Rp. 165,000 = Rp. 247.50
- Mandor 0.016 Oh x Rp. 192,500 = Rp. 3,080.00
Jumlah (2) = Rp. 494,890.00

Jumlah (1) + (2) = Rp. 865,682.04


Keuntungan+Over head 10% = Rp 86,568.20
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 952,250.24

PS 6.14. Memasang 1 buah bak kontrol pasangan batu bata ukuran (45 x 45) cm
tinggi 50 cm

6.14.1Bahan
- Batu bata 250.000 Bh x Rp. 1,200 = Rp. 300,000.00
- Semen portland 77.000 Kg x Rp. 1,800 = Rp. 138,600.00
- Pasir pasang 0.130 M³ x Rp. 342,000 = Rp. 44,460.00
- Batu kerikil 0.020 M³ x Rp. 727,601 = Rp. 14,552.01
- Besi beton 2.600 Kg x Rp. 13,200 = Rp. 34,320.00
- Pasir beton 0.090 M³ x Rp. 360,000 = Rp. 32,400.00
Jumlah (1) = Rp. 564,332.01
6.14.2Tenaga
- Pekerja 1.420 Oh x Rp. 110,000 = Rp. 156,200.00
- Tukang batu 0.473 Oh x Rp. 137,500 = Rp. 65,037.50
- Kepala tukang 0.047 Oh x Rp. 165,000 = Rp. 7,755.00
- Mandor 0.071 Oh x Rp. 192,500 = Rp. 13,667.50
Jumlah (2) = Rp. 242,660.00

Jumlah (1) + (2) = Rp. 806,992.01


Keuntungan+Over head 10% = Rp 80,699.20
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 887,691.21

PS 6.15. Memasang 1 buah bak kontrol pasangan batu bata ukuran (60 x 60) cm
tinggi 65 cm

6.15.1Bahan
- Batu bata 371.000 Bh x Rp. 1,200 = Rp. 445,200.00
- Semen portland 114.000 Kg x Rp. 1,800 = Rp. 205,200.00
- Pasir pasang 0.184 M³ x Rp. 342,000 = Rp. 62,928.00
- Batu koral 0.033 M³ x Rp. 727,601 = Rp. 24,010.82
- Besi beton 4.850 Kg x Rp. 13,200 = Rp. 64,020.00
- Pasir beton 0.120 M³ x Rp. 360,000 = Rp. 43,200.00
Jumlah (1) = Rp. 844,558.82
6.15.2Tenaga
- Pekerja 2.160 Oh x Rp. 110,000 = Rp. 237,600.00
- Tukang batu 0.720 Oh x Rp. 137,500 = Rp. 99,000.00
- Kepala tukang 0.072 Oh x Rp. 165,000 = Rp. 11,880.00
- Mandor 0.108 Oh x Rp. 192,500 = Rp. 20,790.00
- Tukang gali 0.100 Oh x Rp. 110,000 = Rp. 11,000.00
Jumlah (2) = Rp. 380,270.00

Jumlah (1) + (2) = Rp. 1,224,828.82


Keuntungan+Over head 10% = Rp 122,482.88
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,347,311.70

PS 6.16. Memasang 1 m' pipa galvanis diameter ½"

6.16.1Bahan
- Pipa galvanis 1.200 M´ x Rp. 27,600 = Rp. 33,120.00
- Perlengkapan 35% harga pipa x Rp. 27,600 = Rp. 9,660.00
Jumlah (1) = Rp. 42,780.00

6.16.2Tenaga
- Pekerja 0.054 Oh x Rp. 110,000 = Rp. 5,940.00
- Tukang batu 0.090 Oh x Rp. 137,500 = Rp. 12,375.00
- Kepala tukang 0.009 Oh x Rp. 165,000 = Rp. 1,485.00
- Mandor 0.027 Oh x Rp. 192,500 = Rp. 5,197.50
Jumlah (2) = Rp. 24,997.50

Jumlah (1) + (2) = Rp. 67,777.50


Keuntungan+Over head 10% = Rp 6,777.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 74,555.25
PS 6.17. Memasang 1 m' pipa galvanis diameter 3/4"

6.17.1Bahan
- Pipa galvanis 1.200 M´ x Rp. 37,200 = Rp. 44,640.00
- Perlengkapan 35% harga pipa x Rp. 37,200 = Rp. 13,020.00
Jumlah (1) = Rp. 57,660.00
6.17.2Tenaga
- Pekerja 0.054 Oh x Rp. 110,000 = Rp. 5,940.00
- Tukang batu 0.090 Oh x Rp. 137,500 = Rp. 12,375.00
- Kepala tukang 0.009 Oh x Rp. 165,000 = Rp. 1,485.00
- Mandor 0.027 Oh x Rp. 192,500 = Rp. 5,197.50
Jumlah (2) = Rp. 24,997.50

Jumlah (1) + (2) = Rp. 82,657.50


Keuntungan+Over head 10% = Rp 8,265.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 90,923.25

PS 6.18. Memasang 1 m' pipa galvanis diameter 1"

6.18.1Bahan
- Pipa galvanis 1.200 M´ x Rp. 55,200 = Rp. 66,240.00
- Perlengkapan 35% harga pipa x Rp. 55,200 = Rp. 19,320.00
Jumlah (1) = Rp. 85,560.00
6.18.2Tenaga
- Pekerja 0.054 Oh x Rp. 110,000 = Rp. 5,940.00
- Tukang batu 0.090 Oh x Rp. 137,500 = Rp. 12,375.00
- Kepala tukang 0.009 Oh x Rp. 165,000 = Rp. 1,485.00
- Mandor 0.027 Oh x Rp. 192,500 = Rp. 5,197.50
Jumlah (2) = Rp. 24,997.50

Jumlah (1) + (2) = Rp. 110,557.50


Keuntungan+Over head 10% = Rp 11,055.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 121,613.25

PS 6.19. Memasang 1 m' pipa galvanis diameter 1 ½"

6.19.1Bahan
- Pipa galvanis 1.200 M´ x Rp. 69,600 = Rp. 83,520.00
- Perlengkapan 35% harga pipa x Rp. 69,600 = Rp. 24,360.00
Jumlah (1) = Rp. 107,880.00
6.19.2Tenaga
- Pekerja 0.108 Oh x Rp. 110,000 = Rp. 11,880.00
- Tukang batu 0.180 Oh x Rp. 137,500 = Rp. 24,750.00
- Kepala tukang 0.018 Oh x Rp. 165,000 = Rp. 2,970.00
- Mandor 0.0054 Oh x Rp. 192,500 = Rp. 1,039.50
Jumlah (2) = Rp. 40,639.50

Jumlah (1) + (2) = Rp. 148,519.50


Keuntungan+Over head 10% = Rp 14,851.95
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 163,371.45

PS 6.20. Memasang 1 m' pipa galvanis diameter 2"

6.20.1Bahan
- Pipa galvanis 1.200 M´ x Rp. 88,800 = Rp. 106,560.00
- Perlengkapan 35% harga pipa x Rp. 88,800 = Rp. 31,080.00
Jumlah (1) = Rp. 137,640.00
6.20.2Tenaga
- Pekerja 0.108 Oh x Rp. 110,000 = Rp. 11,880.00
- Tukang batu 0.180 Oh x Rp. 137,500 = Rp. 24,750.00
- Kepala tukang 0.018 Oh x Rp. 165,000 = Rp. 2,970.00
- Mandor 0.0054 Oh x Rp. 192,500 = Rp. 1,039.50
Jumlah (2) = Rp. 40,639.50

Jumlah (1) + (2) = Rp. 178,279.50


Keuntungan+Over head 10% = Rp 17,827.95
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 196,107.45

PS 6.21. Memasang 1 m' pipa galvanis diameter 2,5"

6.21.1Bahan
- Pipa galvanis tebal 3,6 mm 1.200 M´ x Rp. 98,400 = Rp. 118,080.00
- Perlengkapan 35% harga pipa x Rp. 98,400 = Rp. 34,440.00
Jumlah (1) = Rp. 152,520.00
6.21.2Tenaga
- Pekerja 0.135 Oh x Rp. 110,000 = Rp. 14,850.00
- Tukang batu 0.225 Oh x Rp. 137,500 = Rp. 30,937.50
- Kepala tukang 0.0225 Oh x Rp. 165,000 = Rp. 3,712.50
- Mandor 0.0068 Oh x Rp. 192,500 = Rp. 1,309.00
Jumlah (2) = Rp. 50,809.00

Jumlah (1) + (2) = Rp. 203,329.00


Keuntungan+Over head 10% = Rp 20,332.90
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 223,661.90

PS 6.22. Memasang 1 m' pipa PVC tipe AW diameter ½"

6.22.1Bahan
- Pipa PVC 1.200 M´ x Rp. 12,000 = Rp. 14,400.00
- Perlengkapan 35% harga pipa x Rp. 12,000 = Rp. 4,200.00
Jumlah (1) = Rp. 18,600.00
6.22.2Tenaga
- Pekerja 0.036 Oh x Rp. 110,000 = Rp. 3,960.00
- Tukang batu 0.060 Oh x Rp. 137,500 = Rp. 8,250.00
- Kepala tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.0018 Oh x Rp. 192,500 = Rp. 346.50
Jumlah (2) = Rp. 13,546.50

Jumlah (1) + (2) = Rp. 32,146.50


Keuntungan+Over head 10% = Rp 3,214.65
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 35,361.15

PS 6.23. Memasang 1 m' pipa PVC tipe AW diameter ¾"

6.23.1Bahan
- Pipa PVC 1.200 M´ x Rp. 13,200 = Rp. 15,840.00
- Perlengkapan 35% harga pipa x Rp. 13,200 = Rp. 4,620.00
Jumlah (1) = Rp. 20,460.00
6.23.2Tenaga
- Pekerja 0.036 Oh x Rp. 110,000 = Rp. 3,960.00
- Tukang batu 0.060 Oh x Rp. 137,500 = Rp. 8,250.00
- Kepala tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.0018 Oh x Rp. 192,500 = Rp. 346.50
Jumlah (2) = Rp. 13,546.50

Jumlah (1) + (2) = Rp. 34,006.50


Keuntungan+Over head 10% = Rp 3,400.65
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 37,407.15

PS 6.24. Memasang 1 m' pipa PVC tipe AW diameter 1"

6.24.1Bahan
- Pipa PVC 1.200 M´ x Rp. 25,200 = Rp. 30,240.00
- Perlengkapan 35% harga pipa x Rp. 25,200 = Rp. 8,820.00
Jumlah (1) = Rp. 39,060.00
6.24.2Tenaga
- Pekerja 0.036 Oh x Rp. 110,000 = Rp. 3,960.00
- Tukang batu 0.060 Oh x Rp. 137,500 = Rp. 8,250.00
- Kepala tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.0018 Oh x Rp. 192,500 = Rp. 346.50
Jumlah (2) = Rp. 13,546.50

Jumlah (1) + (2) = Rp. 52,606.50


Keuntungan+Over head 10% = Rp 5,260.65
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 57,867.15

PS 6.25. Memasang 1 m' pipa PVC tipe AW diameter 1 ½"

6.25.1Bahan
- Pipa PVC 1.200 M´ x Rp. 37,200 = Rp. 44,640.00
- Perlengkapan 35% harga pipa x Rp. 37,200 = Rp. 13,020.00
Jumlah (1) = Rp. 57,660.00
6.25.2Tenaga
- Pekerja 0.036 Oh x Rp. 110,000 = Rp. 3,960.00
- Tukang batu 0.060 Oh x Rp. 137,500 = Rp. 8,250.00
- Kepala tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.0018 Oh x Rp. 192,500 = Rp. 346.50
Jumlah (2) = Rp. 13,546.50

Jumlah (1) + (2) = Rp. 71,206.50


Keuntungan+Over head 10% = Rp 7,120.65
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 78,327.15

PS 6.26. Memasang 1 m' pipa PVC tipe AW diameter 2"

6.26.1Bahan
- Pipa PVC 1.200 M´ x Rp. 43,200 = Rp. 51,840.00
- Perlengkapan 35% harga pipa x Rp. 43,200 = Rp. 15,120.00
Jumlah (1) = Rp. 66,960.00
6.26.2Tenaga
- Pekerja 0.054 Oh x Rp. 110,000 = Rp. 5,940.00
- Tukang batu 0.090 Oh x Rp. 137,500 = Rp. 12,375.00
- Kepala tukang 0.009 Oh x Rp. 165,000 = Rp. 1,485.00
- Mandor 0.0027 Oh x Rp. 192,500 = Rp. 519.75
Jumlah (2) = Rp. 20,319.75
Jumlah (1) + (2) = Rp. 87,279.75
Keuntungan+Over head 10% = Rp 8,727.98
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 96,007.73

PS 6.27. Memasang 1 m' pipa PVC tipe AW diameter 2 ½"

6.27.1Bahan
- Pipa PVC 1.200 M´ x Rp. 50,400 = Rp. 60,480.00
- Perlengkapan 35% harga pipa x Rp. 50,400 = Rp. 17,640.00
Jumlah (1) = Rp. 78,120.00
6.27.2Tenaga
- Pekerja 0.036 Oh x Rp. 110,000 = Rp. 3,960.00
- Tukang batu 0.060 Oh x Rp. 137,500 = Rp. 8,250.00
- Kepala tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.0018 Oh x Rp. 192,500 = Rp. 346.50
Jumlah (2) = Rp. 13,546.50

Jumlah (1) + (2) = Rp. 91,666.50


Keuntungan+Over head 10% = Rp 9,166.65
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 100,833.15

PS 6.28. Memasang 1 m' pipa PVC tipe AW diameter 3"

6.28.1Bahan
- Pipa PVC 1.200 M´ x Rp. 56,400 = Rp. 67,680.00
- Perlengkapan 35% harga pipa x Rp. 56,400 = Rp. 19,740.00
Jumlah (1) = Rp. 87,420.00
6.28.2Tenaga
- Pekerja 0.081 Oh x Rp. 110,000 = Rp. 8,910.00
- Tukang batu 0.135 Oh x Rp. 137,500 = Rp. 18,562.50
- Kepala tukang 0.0135 Oh x Rp. 165,000 = Rp. 2,227.50
- Mandor 0.0041 Oh x Rp. 192,500 = Rp. 789.25
Jumlah (2) = Rp. 30,489.25

Jumlah (1) + (2) = Rp. 117,909.25


Keuntungan+Over head 10% = Rp 11,790.93
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 129,700.18

PS 6.29. Memasang 1 m' pipa PVC tipe AW diameter 4"

6.29.1Bahan
- Pipa PVC 1.200 M´ x Rp. 93,600 = Rp. 112,320.00
- Perlengkapan 35% harga pipa x Rp. 93,600 = Rp. 32,760.00
Jumlah (1) = Rp. 145,080.00
6.29.2Tenaga
- Pekerja 0.081 Oh x Rp. 110,000 = Rp. 8,910.00
- Tukang batu 0.135 Oh x Rp. 137,500 = Rp. 18,562.50
- Kepala tukang 0.0135 Oh x Rp. 165,000 = Rp. 2,227.50
- Mandor 0.0041 Oh x Rp. 192,500 = Rp. 789.25
Jumlah (2) = Rp. 30,489.25

Jumlah (1) + (2) = Rp. 175,569.25


Keuntungan+Over head 10% = Rp 17,556.93
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 193,126.18
PS 6.30. Memasang 1 bh bak cuci piring stainles steel

6.30.1Bahan
- Bak cuci stainless steel 1.000 Bh x Rp. 873,600 = Rp. 873,600.00
- Water drain asesories 1.000 Set x Rp. 12,000 = Rp. 12,000.00
Jumlah (1) = Rp. 885,600.00
6.30.2Tenaga
- Pekerja 0.030 Oh x Rp. 110,000 = Rp. 3,300.00
- Tukang batu 0.300 Oh x Rp. 137,500 = Rp. 41,250.00
- Kepala tukang 0.030 Oh x Rp. 165,000 = Rp. 4,950.00
- Mandor 0.0015 Oh x Rp. 192,500 = Rp. 288.75
Jumlah (2) = Rp. 49,788.75

Jumlah (1) + (2) = Rp. 935,388.75


Keuntungan+Over head 10% = Rp 93,538.88
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 1,028,927.63

PS 6.31. Memasang 1 bh bak cuci piring teraso

6.31.1Bahan
- Bak cuci teraso 1.000 Bh x Rp. 508,800 = Rp. 508,800.00
- Water drain + asesories 1.000 Bh x Rp. 12,000 = Rp. 12,000.00
- Semen portland 20.000 Kg x Rp. 1,800 = Rp. 36,000.00
- Pasir 0.050 M³ x Rp. 342,000 = Rp. 17,100.00
Jumlah (1) = Rp. 573,900.00
6.31.2Tenaga
- Pekerja 0.050 Oh x Rp. 110,000 = Rp. 5,500.00
- Tukang batu 0.500 Oh x Rp. 137,500 = Rp. 68,750.00
- Kepala tukang 0.050 Oh x Rp. 165,000 = Rp. 8,250.00
- Mandor 0.0025 Oh x Rp. 192,500 = Rp. 481.25
Jumlah (2) = Rp. 82,981.25

Jumlah (1) + (2) = Rp. 656,881.25


Keuntungan+Over head 10% = Rp 65,688.13
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 722,569.38

PS 6.32. Memasang 1 bh kran diameter ¾" atau ½"

6.32.1Bahan
- Kran air 1.000 Bh x Rp. 51,600 = Rp. 51,600.00
- Seal tape 0.025 Bh x Rp. 0 = Rp. 0.00
Jumlah (1) = Rp. 51,600.00

6.32.2Tenaga
- Pekerja 0.010 Oh x Rp. 110,000 = Rp. 1,100.00
- Tukang batu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (2) 17,462.50

Jumlah (1) + (2) = Rp. 69,062.50


Keuntungan+Over head 10% = Rp 6,906.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 75,968.75

PS 6.33. Memasang 1 bh Floor drain


6.33.1Bahan
- Floor drain 1.000 Bh x Rp. 28,800 = Rp. 28,800.00
Jumlah (1) = Rp. 28,800.00

6.33.2Tenaga
- Pekerja 0.010 Oh x Rp. 110,000 = Rp. 1,100.00
- Tukang batu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (2) 17,462.50

Jumlah (1) + (2) = Rp. 46,262.50


Keuntungan+Over head 10% = Rp 4,626.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 50,888.75

PS 6.32. Memasang 1 unit sumur resapan buis beton dia. 1 m kedalaman 2 m

6.32.1Bahan
- Galian tanah 1.570 m3 x Rp. 118,429 = Rp. 185,933.14
- Buis beton dia. 1 m 2.000 Bh x Rp. 648,000 = Rp. 1,296,000.00
- Kerikil 0.393 m3 x Rp. 727,601 = Rp. 285,583.20
- Penutup Beton 0.113 m3 x Rp. 3,000,000 = Rp. 339,120.00
- Pipa PVC 4"+sambungan 1.000 m' x Rp. 23,400 = Rp. 23,400.00

Jumlah (1) = Rp. 2,130,036.33

6.32.2Tenaga
- Pekerja 0.500 Oh x Rp. 110,000 = Rp. 55,000.00
- Tukang batu 0.335 Oh x Rp. 137,500 = Rp. 46,062.50
- Kepala tukang 0.335 Oh x Rp. 165,000 = Rp. 55,275.00
- Mandor 0.168 Oh x Rp. 192,500 = Rp. 32,243.75
Jumlah (2) 188,581.25

Jumlah (1) + (2) = Rp. 2,318,617.58


Keuntungan+Over head 10% = Rp 231,861.76
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 2,550,479.34

PS 6.35. Memasang 1 Unit Septictank Biotech kav. 2m3

6.35.1Bahan
- Septictank Biotech kap.2m3 1.000 unit x Rp. 7,500,000.00 = Rp. 7,500,000.00
- Perlengkapan 35% Harga Septic 1.000 ls Rp. 2,625,000.00 = Rp. 2,625,000.00
Jumlah (1) = Rp. 10,125,000.00

6.35.2Tenaga
- Pekerja 1.450 Oh x Rp. 110,000 = Rp. 159,500.00
- Tukang batu 1.200 Oh x Rp. 137,500 = Rp. 165,000.00
- Kepala tukang 0.150 Oh x Rp. 165,000 = Rp. 24,750.00
- Mandor 0.075 Oh x Rp. 192,500 = Rp. 14,437.50
Jumlah (2) 363,687.50
Jumlah (1) + (2) = Rp. 10,488,687.50
Keuntungan+Over head 10% = Rp 1,048,868.75
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 11,537,556.25
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PENUTUP ATAP

PPA 6.1 1 M² Pasang atap genteng palentong kecil

6.1.1 Bahan
- Genteng Palentong 25.000 Buah x Rp. 3,600 = Rp. 90,000.00
Jumlah (1) = Rp. 90,000.00
6.1.2 Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang Kayu 0.075 Oh x Rp. 137,500 = Rp. 10,312.50
- Kepala Tukang 0.008 Oh x Rp. 165,000 = Rp. 1,320.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 29,672.50

Jumlah (1) + (2) = Rp. 119,672.50


Keuntungan+Over head 10% = Rp 11,967.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 131,639.75

PPA 6.2 1 M² Pasang atap genteng kodok / glazzur

6.2.1 Bahan
- Genteng Kodok 25.000 Buah x Rp. 3,600 = Rp. 90,000.00
Jumlah (1) = Rp. 90,000.00
6.2.2 Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang Kayu 0.075 Oh x Rp. 137,500 = Rp. 10,312.50
- Kepala Tukang 0.008 Oh x Rp. 165,000 = Rp. 1,320.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 29,672.50

Jumlah (1) + (2) = Rp. 119,672.50


Keuntungan+Over head 10% = Rp 11,967.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 131,639.75

PPA 6.3 1 M² Pasang atap genteng palentong super / besar

6.3.1 Bahan
- Genteng Palentong super 12.000 Buah x Rp. 7,200 = Rp. 86,400.00
Jumlah (1) = Rp. 86,400.00
6.3.2 Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang Kayu 0.060 Oh x Rp. 137,500 = Rp. 8,250.00
- Kepala Tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 27,280.00

Jumlah (1) + (2) = Rp. 113,680.00


Keuntungan+Over head 10% = Rp 11,368.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 125,048.00

PPA 6.4 1 M² Pasang genteng bubung palentong

6.4.1 Bahan
- Bubung geneteng palentong 5.000 Buah x Rp. 18,000 = Rp. 90,000.00
- Semen portland 8.000 Kg x Rp. 1,800 = Rp. 14,400.00
- Pasir Pasang 0.032 M³ x Rp. 342,000 = Rp. 10,944.00
Jumlah (1) = Rp. 115,344.00
6.4.2 Tenaga
- Pekerja 0.400 Oh x Rp. 110,000 = Rp. 44,000.00
- Tukang Kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala Tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 75,185.00

Jumlah (1) + (2) = Rp. 190,529.00


Keuntungan+Over head 10% = Rp 19,052.90
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 209,581.90

PPA 6.5 1 M' Pasang bubung genteng kodok glazzuur

6.5.1 Bahan
- Bubung genteng kodok 5.000 Buah x Rp. 18,000 = Rp. 90,000.00
- Semen portland 8.000 Kg x Rp. 1,800 = Rp. 14,400.00
- Pasir Pasang 0.032 M³ x Rp. 342,000 = Rp. 10,944.00
Jumlah (1) = Rp. 115,344.00
6.5.2 Tenaga
- Pekerja 0.400 Oh x Rp. 110,000 = Rp. 44,000.00
- Tukang Kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala Tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 75,185.00

Jumlah (1) + (2) = Rp. 190,529.00


Keuntungan+Over head 10% = Rp 19,052.90
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 209,581.90

PPA 6.6 1 M' Pasang bubung genteng palentong besar

6.6.1 Bahan
- Bubung genteng palentong super 4.000 Buah x Rp. 24,000 = Rp. 96,000.00
- Semen portland 8.000 Kg x Rp. 1,800 = Rp. 14,400.00
- Pasir Pasang 0.032 M³ x Rp. 342,000 = Rp. 10,944.00
Jumlah (1) = Rp. 121,344.00
6.6.2 Tenaga
- Pekerja 0.400 Oh x Rp. 110,000 = Rp. 44,000.00
- Tukang Kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala Tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 75,185.00

Jumlah (1) + (2) = Rp. 196,529.00


Keuntungan+Over head 10% = Rp 19,652.90
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 216,181.90

PPA 6.7 1 M² Pasang roof light fiberglass ( 180 x 90 ) cm

6.7.1 Bahan
- Roof light fibreglass 0.600 Lbr x Rp. 87,600 = Rp. 52,560.00
- Paku biasa ½ " - 1" 0.050 Kg x Rp. 19,200 = Rp. 960.00
Jumlah (1) = Rp. 53,520.00
6.7.2 Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 80,635.00


Keuntungan+Over head 10% = Rp 8,063.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 88,698.50

PPA 6.8 1 M² Pasang atap asbes gelombang ( 2,70 x 0,92 m ) x 5 mm

6.8.1 Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 199,200 = Rp. 89,640.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 94,248.00
6.8.2 Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.075 Oh x Rp. 137,500 = Rp. 10,312.50
- Kepala Tukang 0.008 Oh x Rp. 165,000 = Rp. 1,320.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 28,572.50

Jumlah (1) + (2) = Rp. 122,820.50


Keuntungan+Over head 10% = Rp 12,282.05
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 135,102.55

PPA 6.9 1 M² Pasang atap asbes gelombang ( 2,40 x 0,92 m ) x 5 mm

6.9.1 Bahan
- Atap asbes gelombang 0.500 Lbr x Rp. 108,000 = Rp. 54,000.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 58,608.00
6.9.2 Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.075 Oh x Rp. 137,500 = Rp. 10,312.50
- Kepala Tukang 0.008 Oh x Rp. 165,000 = Rp. 1,320.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 28,572.50

Jumlah (1) + (2) = Rp. 87,180.50


Keuntungan+Over head 10% = Rp 8,718.05
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 95,898.55

PPA 6.10 1 M² Pasang atap asbes gelombang ( 2,10 x 0,92 m ) x 5 mm

6.10. Bahan
- Atap asbes gelombang 0.600 Lbr x Rp. 96,000 = Rp. 57,600.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 62,208.00
6.10. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.075 Oh x Rp. 137,500 = Rp. 10,312.50
- Kepala Tukang 0.008 Oh x Rp. 165,000 = Rp. 1,320.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 28,572.50

Jumlah (1) + (2) = Rp. 90,780.50


Keuntungan+Over head 10% = Rp 9,078.05
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 99,858.55

PPA 6.11 1 M² Pasang atap asbes gelombang ( 1,80 x 0,92 m ) x 5 mm

6.11. Bahan
- Atap asbes gelombang 0.750 Lbr x Rp. 132,000 = Rp. 99,000.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 103,608.00
6.11. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.070 Oh x Rp. 137,500 = Rp. 9,625.00
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,527.50

Jumlah (1) + (2) = Rp. 131,135.50


Keuntungan+Over head 10% = Rp 13,113.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 144,249.05

PPA 6.12 1 M² Pasang atap asbes gelombang ( 2,40 x 1,05 m ) x 4 mm

6.12. Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 87,600 = Rp. 39,420.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 44,028.00
6.12. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.070 Oh x Rp. 137,500 = Rp. 9,625.00
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,527.50

Jumlah (1) + (2) = Rp. 71,555.50


Keuntungan+Over head 10% = Rp 7,155.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 78,711.05

PPA 6.13 1 M² Pasang atap asbes gelombang ( 2,10 x 1,05 m ) x 4 mm

6.13. Bahan
- Atap asbes gelombang 0.500 Lbr x Rp. 76,800 = Rp. 38,400.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 43,008.00
6.13. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.070 Oh x Rp. 137,500 = Rp. 9,625.00
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,527.50

Jumlah (1) + (2) = Rp. 70,535.50


Keuntungan+Over head 10% = Rp 7,053.55
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 77,589.05

PPA 6.14 1 M² Pasang atap asbes gelombang ( 1,80 x 1,05 m ) x 4 mm

6.14. Bahan
- Atap asbes gelombang 0.600 Lbr x Rp. 66,000 = Rp. 39,600.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 44,208.00
6.14. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 71,323.00


Keuntungan+Over head 10% = Rp 7,132.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 78,455.30

PPA 6.15 1 M² Pasang atap asbes gelombang ( 2,10 x 1,05 m ) x 4 mm

6.15. Bahan
- Atap asbes gelombang 0.510 Lbr x Rp. 66,000 = Rp. 33,660.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 38,268.00
6.15. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 65,383.00


Keuntungan+Over head 10% = Rp 6,538.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 71,921.30

PPA 6.16 1 M² Pasang atap asbes gelombang ( 1,5 x 1,05 m ) x 4 mm

6.16. Bahan
- Atap asbes gelombang 0.800 Lbr x Rp. 66,000 = Rp. 52,800.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 57,408.00
6.16. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 84,523.00


Keuntungan+Over head 10% = Rp 8,452.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 92,975.30

PPA 6.17 1 M² Pasang atap asbes gelombang ( 3,00 x 1,08 m ) x 6 mm

6.17. Bahan
- Atap asbes gelombang 0.370 Lbr x Rp. 66,000 = Rp. 24,420.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 29,028.00
6.17. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 56,143.00


Keuntungan+Over head 10% = Rp 5,614.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 61,757.30

PPA 6.18 1 M² Pasang atap asbes gelombang ( 2,70 x 1,08 m ) x 6 mm

6.18. Bahan
- Atap asbes gelombang 0.380 Lbr x Rp. 290,400 = Rp. 110,352.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 114,960.00
6.18. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 142,075.00


Keuntungan+Over head 10% = Rp 14,207.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 156,282.50

PPA 6.19 1 M² Pasang atap asbes gelombang ( 2,4 x 1,08 m ) x 6 mm

6.19. Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 241,200 = Rp. 108,540.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 113,148.00
6.19. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 140,263.00


Keuntungan+Over head 10% = Rp 14,026.30
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 154,289.30

PPA 6.20 1 M² Pasang atap asbes gelombang ( 2,1 x 1,08 m ) x 6 mm

6.20. Bahan
- Atap asbes gelombang 0.490 Lbr x Rp. 225,600 = Rp. 110,544.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 115,152.00
6.16. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 142,267.00


Keuntungan+Over head 10% = Rp 14,226.70
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 156,493.70

PPA 6.21 1 M² Pasang atap asbes gelombang ( 1,80 x 1,08 m ) x 6 mm

6.21. Bahan
- Atap asbes gelombang 0.570 Lbr x Rp. 193,200 = Rp. 110,124.00
- Paku seng 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
Jumlah (1) = Rp. 114,732.00
6.21. Tenaga
- Pekerja 0.140 Oh x Rp. 110,000 = Rp. 15,400.00
- Tukang Kayu 0.067 Oh x Rp. 137,500 = Rp. 9,212.50
- Kepala Tukang 0.007 Oh x Rp. 165,000 = Rp. 1,155.00
- Mandor 0.007 Oh x Rp. 192,500 = Rp. 1,347.50
Jumlah (2) = Rp. 27,115.00

Jumlah (1) + (2) = Rp. 141,847.00


Keuntungan+Over head 10% = Rp 14,184.70
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 156,031.70

PPA 6.22 1 M' Pasang bubung stel gelombang 0,92 m

6.22. Bahan
- Bubung stel gelombang 2.400 Lbr x Rp. 36,000 = Rp. 86,400.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 93,600.00
6.22. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 122,942.50


Keuntungan+Over head 10% = Rp 12,294.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 135,236.75

PPA 6.23 1 M' Pasang nok stel gelombang 1,05 m

6.23. Bahan
- Bubung stel gelombang 2.100 Lbr x Rp. 49,200 = Rp. 103,320.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 110,520.00

6.23. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 139,862.50


Keuntungan+Over head 10% = Rp 13,986.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 153,848.75

PPA 6.24 1 M' Pasang nok stel gelombang 1,08 m

6.24. Bahan
- Bubung stel gelombang 2.050 Lbr x Rp. 54,000 = Rp. 110,700.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 117,900.00
6.24. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 147,242.50


Keuntungan+Over head 10% = Rp 14,724.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 161,966.75

PPA 6.25 1 M' Pasang nok paten 1,05 m

6.25. Bahan
- Nok paten 5 mm 1.200 Lbr x Rp. 68,400 = Rp. 82,080.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 89,280.00
6.25. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 118,622.50


Keuntungan+Over head 10% = Rp 11,862.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 130,484.75

PPA 6.26 1 M' Pasang nok paten 1,05 m

6.26. Bahan
- Nok paten 4 mm 1.200 Lbr x Rp. 57,600 = Rp. 69,120.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 76,320.00
6.26. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 105,662.50


Keuntungan+Over head 10% = Rp 10,566.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 116,228.75

PPA 6.27 1 M' Pasang nok paten 1,08 m

6.27. Bahan
- Nok paten 6 mm 1.200 Lbr x Rp. 80,400 = Rp. 96,480.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 103,680.00
6.27. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 133,022.50


Keuntungan+Over head 10% = Rp 13,302.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 146,324.75

PPA 6.28 1 M' Pasang nok stel rata 0,92 m

6.28. Bahan
- Nok stel rata 5 mm 1.100 Lbr x Rp. 67,200 = Rp. 73,920.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 81,120.00
6.28. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000 = Rp. 11,000.00
- Tukang Kayu 0.150 Oh x Rp. 137,500 = Rp. 20,625.00
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 34,540.00
Jumlah (1) + (2) = Rp. 115,660.00
Keuntungan+Over head 10% = Rp 11,566.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 127,226.00

PPA 6.29 1 M' Pasang nok stel rata 1,05 m

6.29. Bahan
- Nok stel rata 4 mm 1.100 Lbr x Rp. 56,400 = Rp. 62,040.00
- Paku seng 6.000 Bh x Rp. 1,200 = Rp. 7,200.00
Jumlah (1) = Rp. 69,240.00
6.29. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 98,582.50


Keuntungan+Over head 10% = Rp 9,858.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 108,440.75
PPA 6.30 1 M² Pasang atap genteng beton

6.30. Bahan
- Atap genteng beton 11.000 Bh x Rp. 10,800 = Rp. 118,800.00
- Paku biasa 2" - 5" 0.030 Kg x Rp. 19,200 = Rp. 576.00
Jumlah (1) = Rp. 119,376.00
6.30. Tenaga
- Pekerja 0.200 Oh x Rp. 110,000 = Rp. 22,000.00
- Tukang Kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 39,325.00

Jumlah (1) + (2) = Rp. 158,701.00


Keuntungan+Over head 10% = Rp 15,870.10
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 174,571.10

PPA 6.31 1 M² Pasang atap genteng aspal

6.31. Bahan
- Nok genteng aspal 6.900 Lbr x Rp. 21,600 = Rp. 149,040.00
- Plywood 4" x 8" x 6 mm 0.350 Lbr x Rp. 93,456 = Rp. 32,709.60
- Paku biasa ½" - 1" 0.030 Kg x Rp. 19,200 = Rp. 576.00
- Plastic aerator 0.500 Bh x Rp. 51,600 = Rp. 25,800.00
Jumlah (1) = Rp. 208,125.60
6.31. Tenaga
- Pekerja 0.200 Oh x Rp. 110,000 = Rp. 22,000.00
- Tukang Kayu 0.300 Oh x Rp. 137,500 = Rp. 41,250.00
- Kepala Tukang 0.003 Oh x Rp. 165,000 = Rp. 495.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 65,670.00

Jumlah (1) + (2) = Rp. 273,795.60


Keuntungan+Over head 10% = Rp 27,379.56
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 301,175.16

PPA 6.32 1 M² Pasang atap genteng metal / multi roof

6.32. Bahan
- Atap genteng metal 1.020 Bh x Rp. 120,000 = Rp. 122,400.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 19,200 = Rp. 3,840.00
Jumlah (1) = Rp. 126,240.00
6.32. Tenaga
- Pekerja 0.200 Oh x Rp. 110,000 = Rp. 22,000.00
- Tukang Kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 39,325.00

Jumlah (1) + (2) = Rp. 165,565.00


Keuntungan+Over head 10% = Rp 16,556.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 182,121.50
PPA 6.33 1 M² Pasang atap sirap

6.33. Bahan
- Atap sirap 60.000 Bh x Rp. 2,400 = Rp. 144,000.00
- Paku biasa ½" - 1" 0.200 Kg x Rp. 19,200 = Rp. 3,840.00
Jumlah (1) = Rp. 147,840.00
6.33. Tenaga
- Pekerja 0.166 Oh x Rp. 110,000 = Rp. 18,260.00
- Tukang Kayu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala Tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 58,300.00

Jumlah (1) + (2) = Rp. 206,140.00


Keuntungan+Over head 10% = Rp 20,614.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 226,754.00

PPA 6.34 1 M' Pasang nok genteng beton

6.34. Bahan
- Nok atap genteng beton 3.500 Bh x Rp. 25,200 = Rp. 88,200.00
- Paku biasa 2" x 5" 0.050 Kg x Rp. 19,200 = Rp. 960.00
- Semen PC 10.800 Kg x Rp. 1,800 = Rp. 19,440.00
- Pasir pasang 0.032 M³ x Rp. 342,000 = Rp. 10,944.00
- Semen warna 1.000 Kg x Rp. 13,200 = Rp. 13,200.00
Jumlah (1) = Rp. 132,744.00
6.34. Tenaga
- Pekerja 0.400 Oh x Rp. 110,000 = Rp. 44,000.00
- Tukang Kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala Tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.020 Oh x Rp. 192,500 = Rp. 3,850.00
Jumlah (2) = Rp. 78,650.00

Jumlah (1) + (2) = Rp. 211,394.00


Keuntungan+Over head 10% = Rp 21,139.40
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 232,533.40

PPA 6.35 1 M' Pasang nok genteng aspal

6.35. Bahan
- Nok genteng aspal 2.000 Bh x Rp. 21,600 = Rp. 43,200.00
- Paku biasa ½" - 1" 0.050 Kg x Rp. 19,200 = Rp. 960.00
- Kayu papan 0.0035 M³ x Rp. 11,580,000 = Rp. 40,530.00
Jumlah (1) = Rp. 84,690.00
6.35. Tenaga
- Pekerja 0.125 Oh x Rp. 110,000 = Rp. 13,750.00
- Tukang Kayu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala Tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 53,405.00

Jumlah (1) + (2) = Rp. 138,095.00


Keuntungan+Over head 10% = Rp 13,809.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 151,904.50
PPA 6.36 1 M' Pasang nok genteng metal

6.36. Bahan
- Nok genteng decra bond 1.100 Bh x Rp. 76,800 = Rp. 84,480.00
- Paku biasa ½" - 1" 0.050 Kg x Rp. 19,200 = Rp. 960.00
Jumlah (1) = Rp. 85,440.00
6.36. Tenaga
- Pekerja 0.250 Oh x Rp. 110,000 = Rp. 27,500.00
- Tukang Kayu 0.150 Oh x Rp. 137,500 = Rp. 20,625.00
- Kepala Tukang 0.015 Oh x Rp. 165,000 = Rp. 2,475.00
- Mandor 0.013 Oh x Rp. 192,500 = Rp. 2,502.50
Jumlah (2) = Rp. 53,102.50

Jumlah (1) + (2) = Rp. 138,542.50


Keuntungan+Over head 10% = Rp 13,854.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 152,396.75

PPA 6.37 1 M' Pasang nok sirap

6.37. Bahan
- Seng plat 3" x 6" BJLS 35 0.400 Lbr x Rp. 216,000 = Rp. 86,400.00
- Paku biasa ½" - 1" 0.060 Kg x Rp. 19,200 = Rp. 1,152.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 19,200 = Rp. 960.00
- Kayu papan tbl. 3 cm 0.004 M³ x Rp. 11,580,000 = Rp. 46,320.00
Jumlah (1) = Rp. 134,832.00
6.37. Tenaga
- Pekerja 0.125 Oh x Rp. 110,000 = Rp. 13,750.00
- Tukang Kayu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala Tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 53,405.00

Jumlah (1) + (2) = Rp. 188,237.00


Keuntungan+Over head 10% = Rp 18,823.70
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 207,060.70

PPA 6.38 1 M' Pasang atap seng gelombang

6.38. Bahan
- Seng gelombang 3" x 6" BJLS 30 0.700 Lbr x Rp. 85,200 = Rp. 59,640.00
- Paku seng 0.040 Kg x Rp. 38,400 = Rp. 1,536.00
Jumlah (1) = Rp. 61,176.00
6.38. Tenaga
- Pekerja 0.120 Oh x Rp. 110,000 = Rp. 13,200.00
- Tukang Kayu 0.060 Oh x Rp. 137,500 = Rp. 8,250.00
- Kepala Tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 23,595.00

Jumlah (1) + (2) = Rp. 84,771.00


Keuntungan+Over head 10% = Rp 8,477.10
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 93,248.10
PPA 6.39 1 M' Pasang atap nok seng

6.39. Bahan
- Seng plat 3" x 6" BJLS 35 0.300 Bh x Rp. 216,000 = Rp. 64,800.00
- Paku seng 0.020 Kg x Rp. 38,400 = Rp. 768.00
Jumlah (1) = Rp. 65,568.00
6.39. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang Kayu 0.070 Oh x Rp. 137,500 = Rp. 9,625.00
- Kepala Tukang 0.008 Oh x Rp. 165,000 = Rp. 1,320.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 28,600.00

Jumlah (1) + (2) = Rp. 94,168.00


Keuntungan+Over head 10% = Rp 9,416.80
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 103,584.80

PPA 6.40 1 M' Pasang atap aluminium

6.40. Bahan
- Atap aluminium gelombang 0,55 1.050 Bh x Rp. 183,600 = Rp. 192,780.00
- Paku hak panjang 15 cm 0.020 Kg x Rp. 57,600 = Rp. 1,152.00
Jumlah (1) = Rp. 193,932.00
6.40. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang Kayu 0.075 Oh x Rp. 137,500 = Rp. 10,312.50
- Kepala Tukang 0.008 Oh x Rp. 165,000 = Rp. 1,320.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 29,287.50

Jumlah (1) + (2) = Rp. 223,219.50


Keuntungan+Over head 10% = Rp 22,321.95
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 245,541.45

PPA 6.41 1 M' Pasang nok aluminium

6.41. Bahan
- Nok standard 40 cm 18 SWG 22 1.200 Bh x Rp. 90,000 = Rp. 108,000.00
- Paku hak panjang 15 cm 0.040 Kg x Rp. 57,600 = Rp. 2,304.00
Jumlah (1) = Rp. 110,304.00
6.41. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000 = Rp. 11,000.00
- Tukang Kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 28,325.00

Jumlah (1) + (2) = Rp. 138,629.00


Keuntungan+Over head 10% = Rp 13,862.90
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 152,491.90

PPA 6.42 1 M' Pasang aluminium foil / sisalation

6.42. Bahan
- Sisalation / Aluminium foil 1.050 M² x Rp. 145,200 = Rp. 152,460.00
Jumlah (1) = Rp. 152,460.00
6.42. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang Kayu 0.050 Oh x Rp. 137,500 = Rp. 6,875.00
- Kepala Tukang 0.005 Oh x Rp. 165,000 = Rp. 825.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 25,740.00

Jumlah (1) + (2) = Rp. 178,200.00


Keuntungan+Over head 10% = Rp 17,820.00
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 196,020.00

PPA 6.43 1 M² Pasang penutup atap bitumen bergelombang motif genteng 3 mm, lebar 40 cm, panjang =106 cm

6.32. Bahan
- Bitumen Bergelombang 3 mm H.38 (On 3.724 lembar x Rp. 50,900 = Rp. 189,551.60
- Paku atau Sekrup 16.15 buah x Rp. 1,100 = Rp. 17,765.00
Jumlah (1) = Rp. 207,316.60
6.32. Tenaga
- Pekerja 0.200 Oh x Rp. 110,000 = Rp. 22,000.00
- Tukang Kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 39,325.00

Jumlah (1) + (2) = Rp. 246,641.60


Keuntungan+Over head 10% = Rp 24,664.16
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 271,305.76

PPA 6.44 1 M' Pasang atap nok bitumen

6.39. Bahan
- Nok 1.438 lembar x Rp. 85,000 = Rp. 122,230.00
- Paku atau Sekrup 10 buah x Rp. 1,100 = Rp. 11,000.00
Jumlah (1) = Rp. 133,230.00
6.39. Tenaga
- Pekerja 0.084 Oh x Rp. 110,000 = Rp. 9,240.00
- Tukang Kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
- Kepala Tukang 0.013 Oh x Rp. 165,000 = Rp. 2,145.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 29,342.50

Jumlah (1) + (2) = Rp. 162,572.50


Keuntungan+Over head 10% = Rp 16,257.25
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 178,829.75

PPA 6.30 1 M² Pasang atap genteng keramik

6.30. Bahan
- Atap genteng keramik 14.500 Bh x Rp. 14,400 = Rp. 208,800.00

Jumlah (1) = Rp. 208,800.00


6.30. Tenaga
- Pekerja 0.200 Oh x Rp. 110,000 = Rp. 22,000.00
- Tukang Kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 39,325.00

Jumlah (1) + (2) = Rp. 248,125.00


Keuntungan+Over head 10% = Rp 24,812.50
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 272,937.50

PPA 6.34 1 M' Pasang nok genteng keramik

6.34. Bahan
- Nok atap genteng keramik 4.000 Bh x Rp. 19,800 = Rp. 79,200.00
- Semen PC 8.000 Kg x Rp. 1,800 = Rp. 14,400.00
- Pasir pasang 0.032 M3 x Rp. 342,000 = Rp. 10,944.00

Jumlah (1) = Rp. 104,544.00


6.34. Tenaga
- Pekerja 0.400 Oh x Rp. 110,000 = Rp. 44,000.00
- Tukang Kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala Tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.020 Oh x Rp. 192,500 = Rp. 3,850.00
Jumlah (2) = Rp. 78,650.00

Jumlah (1) + (2) = Rp. 183,194.00


Keuntungan+Over head 10% = Rp 18,319.40
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 201,513.40
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PENUTUP LANTAI

5.1 1 M2 Pasang Lantai Homogenius Tile (HT) Ukuran 60x60 Cm

5.1.1 Bahan
Ubin HT 60 x 60 Cm 2.7778 Bh x Rp. 66,600 = Rp. 185,000.00
Semen Portland 9.3000 Kg x Rp. 1,800 = Rp. 16,740.00
Pasir Pasang 0.0420 M3 x Rp. 342,000 = Rp. 14,364.00
Semen Warna 1.5000 Kg x Rp. 13,200 = Rp. 19,800.00
Jumlah (1) = Rp. 235,904.00
5.1.2 Tenaga
Pekerja 0.240 Oh x Rp. 110,000 = Rp. 26,400.00
Tukang kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
Kepala tukang 0.013 Oh x Rp. 165,000 = Rp. 2,062.50
Mandor 0.013 Oh x Rp. 192,500 = Rp. 2,502.50
Jumlah (2) = Rp 48,152.50

Jumlah (1) + (2) = Rp 284,056.50

1 M2 Pasang Dinding Keramik 20x20 Cm Corak

Bahan
Keramik 20x20 Cm Corak 25.0000 Bh x Rp. 5,760 = Rp. 144,000.00
Semen Abu - Abu 8.0000 Kg x Rp. 1,800 = Rp. 14,400.00
Pasir Pasang 0.0180 M3 x Rp. 342,000 = Rp. 6,156.00
Semen Warna 0.0130 Kg x Rp. 13,200 = Rp. 171.60
Jumlah (1) = Rp. 164,727.60
Tenaga
Pekerja 0.1875 Oh x Rp. 110,000 = Rp. 20,625.00
Tukang kayu 0.1750 Oh x Rp. 137,500 = Rp. 24,062.50
Kepala tukang 0.0145 Oh x Rp. 165,000 = Rp. 2,392.50
Mandor 0.0188 Oh x Rp. 192,500 = Rp. 3,619.00
Jumlah (2) = Rp. 50,699.00

Jumlah (1) + (2) = Rp 215,426.60

1 M2 Pasang Lantai Keramik 30x30 Cm Kamar Mandi

Bahan
Keramik 30x30 Cm Corak 11.1111 Bh x Rp. 14,000 = Rp. 155,555.56
Semen Abu - Abu 8.0000 Kg x Rp. 1,800 = Rp. 14,400.00
Pasir Pasang 0.0180 M3 x Rp. 342,000 = Rp. 6,156.00
Semen Warna 0.0130 Kg x Rp. 13,200 = Rp. 171.60
Jumlah (1) = Rp. 176,283.16
Tenaga
Pekerja 0.1875 Oh x Rp. 110,000 = Rp. 20,625.00
Tukang kayu 0.1750 Oh x Rp. 137,500 = Rp. 24,062.50
Kepala tukang 0.0145 Oh x Rp. 165,000 = Rp. 2,392.50
Mandor 0.0188 Oh x Rp. 192,500 = Rp. 3,619.00
Jumlah (2) = Rp. 50,699.00

Jumlah (1) + (2) = Rp 226,982.16


1 M2 Pasang Dinding Keramik 30x60 Cm

Bahan
Keramik 30x60 Cm Corak 5.5556 Bh x Rp. 29,000 = Rp. 161,111.11
Semen Abu - Abu 8.0000 Kg x Rp. 1,800 = Rp. 14,400.00
Pasir Pasang 0.0180 M3 x Rp. 342,000 = Rp. 6,156.00
Semen Warna 0.0130 Kg x Rp. 13,200 = Rp. 171.60
Jumlah (1) = Rp. 181,838.71
Tenaga
Pekerja 0.1875 Oh x Rp. 110,000 = Rp. 20,625.00
Tukang kayu 0.1750 Oh x Rp. 137,500 = Rp. 24,062.50
Kepala tukang 0.0145 Oh x Rp. 165,000 = Rp. 2,392.50
Mandor 0.0188 Oh x Rp. 192,500 = Rp. 3,619.00
Jumlah (2) = Rp. 50,699.00

Jumlah (1) + (2) = Rp 232,537.71

5.2 1 M2 Pasang Lantai Homogenius Tile (HT) Ukuran 20x20 Cm

5.2.1 Bahan
Ubin HT 20 x 20 Cm 25.0000 Bh x Rp. 3,500 = Rp. 87,500.00
Semen Portland 9.3000 Kg x Rp. 1,800 = Rp. 16,740.00
Pasir Pasang 0.0420 M3 x Rp. 342,000 = Rp. 14,364.00
Semen Warna 1.5000 Kg x Rp. 13,200 = Rp. 19,800.00
Jumlah (1) = Rp. 138,404.00
5.2.2 Tenaga
Pekerja 0.240 Oh x Rp. 110,000 = Rp. 26,400.00
Tukang kayu 0.125 Oh x Rp. 137,500 = Rp. 17,187.50
Kepala tukang 0.013 Oh x Rp. 165,000 = Rp. 2,062.50
Mandor 0.013 Oh x Rp. 192,500 = Rp. 2,502.50
Jumlah (2) = Rp 48,152.50

Jumlah (1) + (2) = Rp 186,556.50

5.3 1 M2 Pasang Dinding Homogenius Tile (HT) Ukuran 20x25 Cm

5.3.1 Bahan
Ubin HT 20 x 25 Cm 20.0000 Bh x Rp. 3,750 = Rp. 75,000.00
Semen Portland 9.3000 Kg x Rp. 1,800 = Rp. 16,740.00
Pasir Pasang 0.0420 M3 x Rp. 342,000 = Rp. 14,364.00
Semen Warna 1.5000 Kg x Rp. 13,200 = Rp. 19,800.00
Jumlah (1) = Rp. 125,904.00
5.3.2 Tenaga
Pekerja 0.420 Oh x Rp. 110,000 = Rp. 46,200.00
Tukang kayu 0.210 Oh x Rp. 137,500 = Rp. 28,875.00
Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
Mandor 0.025 Oh x Rp. 192,500 = Rp. 4,812.50
Jumlah (2) = Rp 84,012.50

Jumlah (1) + (2) = Rp 209,916.50


ANALISA BIAYA KONSTRUKSI
PEKERJAAN KUNCI DAN KACA

PKK 6.1 1 buah pasang kunci tanam antik


6.1.1 Bahan
- Kunci tanam antik 1.000 Bh x Rp. 402,000 = Rp. 402,000.00
Jumlah (1) = Rp. 402,000.00
6.1.2 Tenaga
- Pekerja 0.060 Oh x Rp. 110,000 = Rp. 6,600.00
- Tukang Kayu 0.600 Oh x Rp. 137,500 = Rp. 82,500.00
- Kepala Tukang 0.060 Oh x Rp. 165,000 = Rp. 9,900.00
- Mandor 0.003 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 99,577.50

Jumlah (1) + (2 = Rp. 501,577.50

PKK 6.2 1 buah pasang kunci tanam biasa


6.2.1 Bahan
- Kunci tanam biasa 1.000 Bh x Rp. 168,000 = Rp. 168,000.00
Jumlah (1) = Rp. 168,000.00
6.1.2 Tenaga
- Pekerja 0.010 Oh x Rp. 110,000 = Rp. 1,100.00
- Tukang Kayu 0.500 Oh x Rp. 137,500 = Rp. 68,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (2) = Rp. 72,462.50

Jumlah (1) + (2 = Rp. 240,462.50

PKK 6.3 1 buah pasang kunci tanam kamar mandi


6.3.1 Bahan
- Kunci tanam kamar mandi 1.000 Bh x Rp. 102,000 = Rp. 102,000.00
Jumlah (1) = Rp. 102,000.00
6.3.2 Tenaga
- Pekerja 0.005 Oh x Rp. 110,000 = Rp. 550.00
- Tukang Kayu 0.500 Oh x Rp. 137,500 = Rp. 68,750.00
- Kepala Tukang 0.005 Oh x Rp. 165,000 = Rp. 825.00
- Mandor 0.0025 Oh x Rp. 192,500 = Rp. 481.25
Jumlah (2) = Rp. 70,606.25

Jumlah (1) + (2 = Rp. 172,606.25

PKK 6.4 1 buah pasang kunci silinder


6.4.1 Bahan
- Kunci silinder 1.000 Bh x Rp. 64,800 = Rp. 64,800.00
Jumlah (1) = Rp. 64,800.00
6.4.2 Tenaga
- Pekerja 0.005 Oh x Rp. 110,000 = Rp. 550.00
- Tukang Kayu 0.500 Oh x Rp. 137,500 = Rp. 68,750.00
- Kepala Tukang 0.005 Oh x Rp. 165,000 = Rp. 825.00
- Mandor 0.00025 Oh x Rp. 192,500 = Rp. 48.13
Jumlah (2) = Rp. 70,173.13

Jumlah (1) + (2 = Rp. 134,973.13

PKK 6.5 1 buah pasang engsel pintu


6.5.1 Bahan
- engsel pintu 1.000 Bh x Rp. 28,800 = Rp. 28,800.00
Jumlah (1) = Rp. 28,800.00
6.5.2 Tenaga
- Pekerja 0.015 Oh x Rp. 110,000 = Rp. 1,650.00
- Tukang Kayu 0.150 Oh x Rp. 137,500 = Rp. 20,625.00
- Kepala Tukang 0.015 Oh x Rp. 165,000 = Rp. 2,475.00
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 24,894.38

Jumlah (1) + (2 = Rp. 53,694.38

PKK 6.6 1 buah pasang engsel jendela kupu-kupu


6.6.1 Bahan
- Engsel jendela 1.000 Bh x Rp. 27,600 = Rp. 27,600.00
Jumlah (1) = Rp. 27,600.00
6.6.2 Tenaga
- Pekerja 0.010 Oh x Rp. 110,000 = Rp. 1,100.00
- Tukang Kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.0005 Oh x Rp. 192,500 = Rp. 96.25
Jumlah (2) = Rp. 16,596.25

Jumlah (1) + (2 = Rp. 44,196.25

PKK 6.7 1 buah pasang engsel angin

6.7.1 Bahan
- Engsel angin 1.000 Bh x Rp. 48,000 = Rp. 48,000.00
Jumlah (1) = Rp. 48,000.00
6.7.2 Tenaga
- Pekerja 0.020 Oh x Rp. 110,000 = Rp. 2,200.00
- Tukang Kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala Tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.010 Oh x Rp. 192,500 = Rp. 1,925.00
Jumlah (2) = Rp. 34,925.00

Jumlah (1) + (2 = Rp. 82,925.00


PKK 6.8 1 buah pasang spring knip

6.8.1 Bahan
- Spring knip 1.000 Bh x Rp. 18,000 = Rp. 18,000.00
Jumlah (1) = Rp. 18,000.00
6.8.2 Tenaga
- Pekerja 0.015 Oh x Rp. 110,000 = Rp. 1,650.00
- Tukang Kayu 0.150 Oh x Rp. 137,500 = Rp. 20,625.00
- Kepala Tukang 0.015 Oh x Rp. 165,000 = Rp. 2,475.00
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 24,894.38

Jumlah (1) + (2 = Rp. 42,894.38

PKK 6.9 1 buah pasang kait angin


6.9.1 Bahan
- Kait angin 1.000 Bh x Rp. 36,000 = Rp. 36,000.00
Jumlah (1) = Rp. 36,000.00
6.9.2 Tenaga
- Pekerja 0.015 Oh x Rp. 110,000 = Rp. 1,650.00
- Tukang Kayu 0.150 Oh x Rp. 137,500 = Rp. 20,625.00
- Kepala Tukang 0.015 Oh x Rp. 165,000 = Rp. 2,475.00
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 24,894.38

Jumlah (1) + (2 = Rp. 60,894.38

PKK 6.10 1 buah pasang door closer


6.10.1 Bahan
- Door closer 1.000 Bh x Rp. 206,400 = Rp. 206,400.00
Jumlah (1) = Rp. 206,400.00
6.10.2 Tenaga
- Pekerja 0.050 Oh x Rp. 110,000 = Rp. 5,500.00
- Tukang Kayu 0.500 Oh x Rp. 137,500 = Rp. 68,750.00
- Kepala Tukang 0.050 Oh x Rp. 165,000 = Rp. 8,250.00
- Mandor 0.0025 Oh x Rp. 192,500 = Rp. 481.25
Jumlah (2) = Rp. 82,981.25

Jumlah (1) + (2 = Rp. 289,381.25

PKK 6.11 1 buah pasang kunci selot


6.11.1 Bahan
- Kunci selot 1.000 Bh x Rp. 51,600 = Rp. 51,600.00
Jumlah (1) = Rp. 51,600.00
6.11.2 Tenaga
- Pekerja 0.020 Oh x Rp. 110,000 = Rp. 2,200.00
- Tukang Kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala Tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.001 Oh x Rp. 192,500 = Rp. 192.50
Jumlah (2) = Rp. 33,192.50

Jumlah (1) + (2 = Rp. 84,792.50

PKK 6.12 1 buah pasang pegangan pintu / door holder


6.12.1 Bahan
- Pegangan pintu / door holder 1.000 Bh x Rp. 212,400 = Rp. 212,400.00
Jumlah (1) = Rp. 212,400.00
6.12.2 Tenaga
- Pekerja 0.050 Oh x Rp. 110,000 = Rp. 5,500.00
- Tukang Kayu 0.500 Oh x Rp. 137,500 = Rp. 68,750.00
- Kepala Tukang 0.050 Oh x Rp. 165,000 = Rp. 8,250.00
- Mandor 0.0025 Oh x Rp. 192,500 = Rp. 481.25
Jumlah (2) = Rp. 82,981.25

Jumlah (1) + (2 = Rp. 295,381.25

PKK 6.13 1 buah pasang door stop

6.13.1 Bahan
- Door stop 1.000 Bh x Rp. 70,800 = Rp. 70,800.00
Jumlah (1) = Rp. 70,800.00
6.13.2 Tenaga
- Pekerja 0.010 Oh x Rp. 110,000 = Rp. 1,100.00
- Tukang Kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala Tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.0005 Oh x Rp. 192,500 = Rp. 96.25
Jumlah (2) = Rp. 16,596.25

Jumlah (1) + (2 = Rp. 87,396.25

PKK 6.14 1 buah pasang rel pintu dorong


6.14.1 Bahan
- Rel pintu dorong 1.000 Bh x Rp. 300,000 = Rp. 300,000.00
Jumlah (1) = Rp. 300,000.00
6.14.2 Tenaga
- Pekerja 0.060 Oh x Rp. 110,000 = Rp. 6,600.00
- Tukang Kayu 0.600 Oh x Rp. 137,500 = Rp. 82,500.00
- Kepala Tukang 0.060 Oh x Rp. 165,000 = Rp. 9,900.00
- Mandor 0.003 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 99,577.50

Jumlah (1) + (2 = Rp. 399,577.50


PKK 6.15 1 buah pasang kunci lemari

6.15.1 Bahan
- Kunci lemari 1.000 Bh x Rp. 24,000 = Rp. 24,000.00
Jumlah (1) = Rp. 24,000.00
6.15.2 Tenaga
- Pekerja 0.025 Oh x Rp. 110,000 = Rp. 2,750.00
- Tukang Kayu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala Tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.00125 Oh x Rp. 192,500 = Rp. 240.63
Jumlah (2) = Rp. 41,490.63

Jumlah (1) + (2 = Rp. 65,490.63

PKK 6.16 1 M² pasang kaca, tebal 3 mm


6.16.1 Bahan
- Kaca 1.100 M² x Rp. 103,200 = Rp. 113,520.00
Jumlah (1) = Rp. 113,520.00
6.16.2 Tenaga
- Pekerja 0.015 Oh x Rp. 110,000 = Rp. 1,650.00
- Tukang Kayu 0.150 Oh x Rp. 137,500 = Rp. 20,625.00
- Kepala Tukang 0.015 Oh x Rp. 165,000 = Rp. 2,475.00
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 24,894.38

Jumlah (1) + (2 = Rp. 138,414.38

PKK 6.17 1 M² pasang kaca, tebal 5 mm


6.17.1 Bahan
- Kaca 1.100 M² x Rp. 141,600 = Rp. 155,760.00
Jumlah (1) = Rp. 155,760.00
6.17.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00
- Tukang Kayu 0.1550 Oh x Rp. 137,500 = Rp. 21,312.50
- Kepala Tukang 0.0155 Oh x Rp. 165,000 = Rp. 2,557.50
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 25,719.38

Jumlah (1) + (2 = Rp. 181,479.38

PKK 6.18 1 M² pasang kaca, tebal 8 mm


6.18.1 Bahan
- Kaca polos 1.100 M² x Rp. 540,000 = Rp. 594,000.00
Jumlah (1) = Rp. 594,000.00
6.18.2 Tenaga
- Pekerja 0.0165 Oh x Rp. 110,000 = Rp. 1,815.00
- Tukang Kayu 0.165 Oh x Rp. 137,500 = Rp. 22,687.50
- Kepala Tukang 0.0165 Oh x Rp. 165,000 = Rp. 2,722.50
- Mandor 0.0008 Oh x Rp. 192,500 = Rp. 154.00
Jumlah (2) = Rp. 27,379.00

Jumlah (1) + (2 = Rp. 621,379.00

PKK 6.19 1 M² pasang kaca buram, tebal 5 mm

6.19.1 Bahan
- Kaca buram 1.100 M² x Rp. 208,800 = Rp. 229,680.00
- Sealent 0.050 Kg x Rp. 73,200 = Rp. 3,660.00
Jumlah (1) = Rp. 233,340.00
6.19.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00
- Tukang Kayu 0.1550 Oh x Rp. 137,500 = Rp. 21,312.50
- Kepala Tukang 0.0155 Oh x Rp. 165,000 = Rp. 2,557.50
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 25,719.38

Jumlah (1) + (2 = Rp. 259,059.38

PKK 6.20 1 M² pasang kaca cermin, tebal 5 mm

6.20.1 Bahan
- Kaca cermin 1.100 M² x Rp. 303,600 = Rp. 333,960.00
Jumlah (1) = Rp. 333,960.00
6.20.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00
- Tukang Kayu 0.1550 Oh x Rp. 137,500 = Rp. 21,312.50
- Kepala Tukang 0.0155 Oh x Rp. 165,000 = Rp. 2,557.50
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 25,719.38

Jumlah (1) + (2 = Rp. 359,679.38

PKK 6.21 1 M² pasang kaca cermin, tebal 8 mm

6.21.1 Bahan
- Kaca cermin 1.100 M² x Rp. 484,800 = Rp. 533,280.00
Jumlah (1) = Rp. 533,280.00
6.21.2 Tenaga
- Pekerja 0.0165 Oh x Rp. 110,000 = Rp. 1,815.00
- Tukang Kayu 0.165 Oh x Rp. 137,500 = Rp. 22,687.50
- Kepala Tukang 0.0165 Oh x Rp. 165,000 = Rp. 2,722.50
- Mandor 0.0008 Oh x Rp. 192,500 = Rp. 154.00
Jumlah (2) = Rp. 27,379.00

Jumlah (1) + (2 = Rp. 560,659.00


PKK 6.22 1 M² pasang kaca "wireglass" , tebal 5 mm

6.22.1 Bahan
- Kaca wireglass 1.100 M² x Rp. 283,200 = Rp. 311,520.00
Jumlah (1) = Rp. 311,520.00
6.22.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00
- Tukang Kayu 0.1550 Oh x Rp. 137,500 = Rp. 21,312.50
- Kepala Tukang 0.0155 Oh x Rp. 165,000 = Rp. 2,557.50
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 25,719.38

Jumlah (1) + (2 = Rp. 337,239.38

PKK 6.23 1 M² pasang kaca patri, tebal 5 mm


6.23.1 Bahan
- Kaca patri 1.100 M² x Rp. 316,800 = Rp. 348,480.00
Jumlah (1) = Rp. 348,480.00
6.23.2 Tenaga
- Pekerja 0.0250 Oh x Rp. 110,000 = Rp. 2,750.00
- Tukang Kayu 0.2500 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala Tukang 0.0250 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.00125 Oh x Rp. 192,500 = Rp. 240.63
Jumlah (2) = Rp. 41,490.63

Jumlah (1) + (2 = Rp. 389,970.63

PKK 6.24. 1 M² pasang kaca Reyben, tebal 5 mm

6.24.1 Bahan
- Kaca reyben 1.100 M² x Rp. 126,000 = Rp. 138,600.00
Jumlah (1) = Rp. 138,600.00
6.24.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 110,000 = Rp. 1,705.00
- Tukang Kayu 0.1550 Oh x Rp. 137,500 = Rp. 21,312.50
- Kepala Tukang 0.0155 Oh x Rp. 165,000 = Rp. 2,557.50
- Mandor 0.00075 Oh x Rp. 192,500 = Rp. 144.38
Jumlah (2) = Rp. 25,719.38

Jumlah (1) + (2 = Rp. 164,319.38


ANALISA BIAYA KONSTRUKSI
PEKERJAAN BESI DAN ALUMINIUM

PBA 6.1 1 Kg Pasang rangka atap baja

6.1.1 Bahan
- Besi profil WF 1.100 Kg x Rp. 19,200 = Rp. 21,120.00
- Meni besi 0.080 Kg x Rp. 37,200 = Rp. 2,976.00
Jumlah (1) = Rp. 24,096.00
6.1.2. Tenaga
- Tukang besi 0.006 Oh x Rp. 137,500 = Rp. 825.00
- Pekerja 0.030 Oh x Rp. 110,000 = Rp. 3,300.00
- Kepala tukang 0.006 Oh x Rp. 165,000 = Rp. 990.00
- Mandor 0.0003 Oh x Rp. 192,500 = Rp. 57.75
Jumlah (2) = Rp. 5,172.75

Jumlah (1) + (2= Rp. 29,268.75

PBA 6.2 1 M² Pasang pintu besi baja

6.2.1 Bahan
- Pintu besi baja 1.000 M² x Rp. 1,528,800 = Rp. 1,528,800.00
Jumlah (1) = Rp. 1,528,800.00
6.2.2. Tenaga
- Tukang besi konstruksi 0.650 Oh x Rp. 137,500 = Rp. 89,375.00
- Pekerja 0.650 Oh x Rp. 110,000 = Rp. 71,500.00
- Kepala tukang 0.065 Oh x Rp. 165,000 = Rp. 10,725.00
- Mandor 0.032 Oh x Rp. 192,500 = Rp. 6,160.00
Jumlah (2) = Rp. 177,760.00

Jumlah (1) + (2= Rp. 1,706,560.00

PBA 6.3 1 M² Pasang jendela besi


6.3.1 Bahan
- Jendela besi 1.000 M² x Rp. 650,400 = Rp. 650,400.00
Jumlah (1) = Rp. 650,400.00
6.3.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 137,500 = Rp. 144,375.00
- Pekerja 1.050 Oh x Rp. 110,000 = Rp. 115,500.00
- Kepala tukang 0.105 Oh x Rp. 165,000 = Rp. 17,325.00
- Mandor 0.00525 Oh x Rp. 192,500 = Rp. 1,010.63
Jumlah (2) = Rp. 278,210.63

Jumlah (1) + (2= Rp. 928,610.63

PBA 6.4 1 M² Pasang pintu gulung besi


6.4.1 Bahan
- Pintu gulung besi 1.000 M² x Rp. 1,551,600 = Rp. 1,551,600.00
Jumlah (1) = Rp. 1,551,600.00
6.4.2. Tenaga
- Tukang besi konstruksi 1.200 Oh x Rp. 137,500 = Rp. 165,000.00
- Pekerja 1.200 Oh x Rp. 110,000 = Rp. 132,000.00
- Kepala tukang 0.120 Oh x Rp. 165,000 = Rp. 19,800.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 317,955.00

Jumlah (1) + (2= Rp. 1,869,555.00

PBA 6.5 1 M² Pasang pintu lipat

6.5.1 Bahan
- Pintu lipat 1.000 M² x Rp. 1,567,200 = Rp. 1,567,200.00
Jumlah (1) = Rp. 1,567,200.00
6.5.2. Tenaga
- Tukang besi konstruksi 1.200 Oh x Rp. 137,500 = Rp. 165,000.00
- Pekerja 1.000 Oh x Rp. 110,000 = Rp. 110,000.00
- Kepala tukang 0.120 Oh x Rp. 165,000 = Rp. 19,800.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 295,955.00

Jumlah (1) + (2= Rp. 1,863,155.00


PBA 6.6 1 M² Pasang pintu Sunscreen alluminium

6.6.1 Bahan
- Sunscreen alluminium 1.000 M² x Rp. 160,000 = Rp. 160,000.00
Jumlah (1) = Rp. 160,000.00
6.6.2. Tenaga
- Tukang besi konstruksi 0.800 Oh x Rp. 137,500 = Rp. 110,000.00
- Pekerja 0.080 Oh x Rp. 110,000 = Rp. 8,800.00
- Kepala tukang 0.080 Oh x Rp. 165,000 = Rp. 13,200.00
- Mandor 0.004 Oh x Rp. 192,500 = Rp. 770.00
Jumlah (2) = Rp. 132,770.00

Jumlah (1) + (2= Rp. 292,770.00

PBA 6.7 1 M² Pasang Rolling door

6.7.1 Bahan
- Roll door 1.000 M² x Rp. 872,400 = Rp. 872,400.00
Jumlah (1) = Rp. 872,400.00
6.7.2. Tenaga
- Tukang besi konstruksi 1.200 Oh x Rp. 137,500 = Rp. 165,000.00
- Pekerja 1.200 Oh x Rp. 110,000 = Rp. 132,000.00
- Kepala tukang 0.120 Oh x Rp. 165,000 = Rp. 19,800.00
- Mandor 0.006 Oh x Rp. 192,500 = Rp. 1,155.00
Jumlah (2) = Rp. 317,955.00

Jumlah (1) + (2= Rp. 1,190,355.00

PBA 6.8 1 M² Pasang pintu alluminium

6.8.1 Bahan
- Pintu alluminium 1.000 M² x Rp. 758,400 = Rp. 758,400.00
Jumlah (1) = Rp. 758,400.00

6.8.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 137,500 = Rp. 144,375.00
- Pekerja 1.050 Oh x Rp. 110,000 = Rp. 115,500.00
- Kepala tukang 0.105 Oh x Rp. 165,000 = Rp. 17,325.00
- Mandor 0.0052 Oh x Rp. 192,500 = Rp. 1,001.00
Jumlah (2) = Rp. 278,201.00

Jumlah (1) + (2= Rp. 1,036,601.00

PBA 6.9 1 M² Pasang Venetions blinds

6.9.1 Bahan
- Venetions blinds 1.000 M² x Rp. 306,000 = Rp. 306,000.00
Jumlah (1) = Rp. 306,000.00

6.9.2. Tenaga
- Tukang kayu 0.350 Oh x Rp. 61,775 = Rp. 21,621.25
- Pekerja 0.350 Oh x Rp. 110,000 = Rp. 38,500.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 0.018 Oh x Rp. 192,500 = Rp. 3,465.00
Jumlah (2) = Rp. 69,361.25

Jumlah (1) + (2= Rp. 375,361.25

PBA 6.10 1 M² Pasang Vertikals blinds

6.10.1 Bahan
- Vertikals blinds 1.000 M² x Rp. 328,800 = Rp. 328,800.00
Jumlah (1) = Rp. 328,800.00

6.10.2. Tenaga
- Tukang kayu 0.350 Oh x Rp. 61,775 = Rp. 21,621.25
- Pekerja 0.350 Oh x Rp. 110,000 = Rp. 38,500.00
- Kepala tukang 0.035 Oh x Rp. 165,000 = Rp. 5,775.00
- Mandor 0.018 Oh x Rp. 192,500 = Rp. 3,465.00
Jumlah (2) = Rp. 69,361.25

Jumlah (1) + (2= Rp. 398,161.25


PBA 6.11 1 M² Pasang terali besi

6.11.1 Bahan
- Besi strip 2 x 3 11.500 M' x Rp. 22,800 = Rp. 262,200.00
Jumlah (1) = Rp. 262,200.00
6.11.2. Tenaga
- Tukang las 1.670 Oh x Rp. 137,500 = Rp. 229,625.00
- Pekerja 1.670 Oh x Rp. 110,000 = Rp. 183,700.00
- Kepala tukang 0.167 Oh x Rp. 165,000 = Rp. 27,555.00
- Mandor 0.083 Oh x Rp. 192,500 = Rp. 15,977.50
Jumlah (2) = Rp. 456,857.50

Jumlah (1) + (2= Rp. 719,057.50

PBA 6.12 1 M² Pasang kawat harmonika

6.12.1 Bahan
- Kawat harmonika 1.100 M² x Rp. 43,200 = Rp. 47,520.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 19,200 = Rp. 384.00
- Kayu meranti 0.0018 M³ x Rp. 6,270,000 = Rp. 11,286.00
Jumlah (1) = Rp. 59,190.00
6.12.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.0005 Oh x Rp. 192,500 = Rp. 96.25
Jumlah (2) = Rp. 26,496.25

Jumlah (1) + (2= Rp. 85,686.25

PBA 6.13 1 M² Pasang kawat nyamuk

6.13.1 Bahan
- Kawat nyamuk 1.100 M² x Rp. 22,800 = Rp. 25,080.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 19,200 = Rp. 384.00
- Kayu meranti 0.0018 M³ x Rp. 6,270,000 = Rp. 11,286.00
Jumlah (1) = Rp. 36,750.00
6.13.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.005 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (2) = Rp. 27,362.50

Jumlah (1) + (2= Rp. 64,112.50

PBA 6.14 1 M² Pasang kawat kassa

6.14.1 Bahan
- Kawat kassa 1.100 M² x Rp. 26,400 = Rp. 29,040.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 19,200 = Rp. 384.00
- Kayu meranti 0.0018 M³ x Rp. 6,270,000 = Rp. 11,286.00
Jumlah (1) = Rp. 40,710.00

6.14.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.0005 Oh x Rp. 192,500 = Rp. 96.25
Jumlah (2) = Rp. 26,496.25

Jumlah (1) + (2= Rp. 67,206.25


PBA 6.15 1 M² Pasang kawat burung

6.15.1 Bahan
- Kawat burung 1.100 M² x Rp. 24,000 = Rp. 26,400.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 19,200 = Rp. 384.00
- Kayu meranti 0.0018 M³ x Rp. 6,270,000 = Rp. 11,286.00
Jumlah (1) = Rp. 38,070.00

6.15.2. Tenaga
- Pekerja 0.100 Oh x Rp. 110,000 = Rp. 11,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.0005 Oh x Rp. 192,500 = Rp. 96.25
Jumlah (2) = Rp. 26,496.25

Jumlah (1) + (2= Rp. 64,566.25

PBA 6.16 1 M² Pasang jendela nako dan tralis

6.16.1 Bahan
- Jendela nako 1.100 M² x Rp. 376,800 = Rp. 414,480.00
- Paku biasa ½" - 1" atau skrup 0.020 Kg x Rp. 19,200 = Rp. 384.00
- Besi strip # 12 mm 1.500 M² x Rp. 22,800 = Rp. 34,200.00
Jumlah (1) = Rp. 449,064.00

6.16.2. Tenaga
- Pekerja 0.200 Oh x Rp. 110,000 = Rp. 22,000.00
- Tukang kayu 0.200 Oh x Rp. 137,500 = Rp. 27,500.00
- Kepala tukang 0.020 Oh x Rp. 165,000 = Rp. 3,300.00
- Mandor 0.001 Oh x Rp. 192,500 = Rp. 192.50
Jumlah (2) = Rp. 52,992.50

Jumlah (1) + (2= Rp. 502,056.50

PBA 6.17 1 M' Pasang talang datar, seng bjls 35

6.17.1 Bahan
- Seng plat 3' x 6' bjls 35 0.500 Lbr x Rp. 216,000 = Rp. 108,000.00
- Paku biasa ½" - 1" atau skrup 0.015 Kg x Rp. 19,200 = Rp. 288.00
- Kayu meranti 0.0096 M³ x Rp. 6,270,000 = Rp. 60,192.00
- Flincote / meni besi 0.250 Kg x Rp. 37,200 = Rp. 9,300.00
Jumlah (1) = Rp. 177,780.00
6.17.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang kayu 0.400 Oh x Rp. 137,500 = Rp. 55,000.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.00125 Oh x Rp. 192,500 = Rp. 240.63
Jumlah (2) = Rp. 75,865.63

Jumlah (1) + (2= Rp. 253,645.63

PBA 6.18 1 M' Pasang talang miring, seng bjls 35

6.18.1 Bahan
- Seng plat 3' x 6' bjls 35 0.500 Lbr x Rp. 216,000 = Rp. 108,000.00
- Paku biasa ½" - 1" atau skrup 0.015 Kg x Rp. 19,200 = Rp. 288.00
- Kayu meranti 0.019 M³ x Rp. 6,270,000 = Rp. 119,130.00
- Flincote / meni besi 0.300 Kg x Rp. 37,200 = Rp. 11,160.00
Jumlah (1) = Rp. 238,578.00
6.18.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang kayu 0.400 Oh x Rp. 137,500 = Rp. 55,000.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.00125 Oh x Rp. 192,500 = Rp. 240.63
Jumlah (2) = Rp. 75,865.63

Jumlah (1) + (2= Rp. 314,443.63

PBA 6.19 1 M' Pasang talang ½ lingkaran D-10 cm, seng bjls 35

6.19.1 Bahan
- Seng plat 3' x 6' bjls 35 0.300 Lbr x Rp. 216,000 = Rp. 64,800.00
- Paku biasa ½" - 1" atau skrup 0.100 Kg x Rp. 19,200 = Rp. 1,920.00
- Kayu meranti 0.019 M³ x Rp. 6,270,000 = Rp. 119,130.00
- Besi strip 0.500 Kg x Rp. 22,800 = Rp. 11,400.00
Jumlah (1) = Rp. 197,250.00
6.19.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang kayu 0.250 Oh x Rp. 137,500 = Rp. 34,375.00
- Kepala tukang 0.025 Oh x Rp. 165,000 = Rp. 4,125.00
- Mandor 0.00125 Oh x Rp. 192,500 = Rp. 240.63
Jumlah (2) = Rp. 55,240.63

Jumlah (1) + (2= Rp. 252,490.63


PBA 6.20 1 M' Pasang talang ½ lingkaran D-10 cm, seng bjls 30

6.20.1 Bahan
- Seng plat 3' x 6' bjls 30 0.300 Lbr x Rp. 194,400 = Rp. 58,320.00
- Paku biasa ½" - 1" atau skrup 0.010 Kg x Rp. 19,200 = Rp. 192.00
- Kayu meranti 0.019 M³ x Rp. 6,270,000 = Rp. 119,130.00
- Besi strip 0.500 Kg x Rp. 22,800 = Rp. 11,400.00
Jumlah (1) = Rp. 189,042.00
6.20.2. Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang kayu 0.300 Oh x Rp. 137,500 = Rp. 41,250.00
- Kepala tukang 0.030 Oh x Rp. 165,000 = Rp. 4,950.00
- Mandor 0.008 Oh x Rp. 192,500 = Rp. 1,540.00
Jumlah (2) = Rp. 64,240.00

Jumlah (1) + (2= Rp. 253,282.00

PBA 6.21 1 M2 Pasang atap pelana rangka atap baja canai dingin profil C-75

6.21.1 Bahan
- Baja ringan canai dingin C-75 3.065 Kg x Rp. 10,309 = Rp. 31,597.94

Jumlah (1) = Rp. 31,597.94


6.21.2. Tenaga
- Pekerja 0.489 Oh x Rp. 110,000 = Rp. 53,826.67
- Tukang kayu 0.489 Oh x Rp. 137,500 = Rp. 67,283.33
- Kepala tukang 0.073 Oh x Rp. 165,000 = Rp. 12,045.00
- Mandor 0.037 Oh x Rp. 192,500 = Rp. 7,122.50
Jumlah (2) = Rp. 140,277.50

Jumlah (1) + (2= Rp. 171,875.44

PBA 6.22 1 M2 Pasang atap jurai rangka atap baja canai dingin profil C-75

6.22.1 Bahan
- Baja ringan canai dingin C-75 4.0500 Kg x Rp. 10,309 = Rp. 41,752.58

Jumlah (1) = Rp. 41,752.58


6.22.2. Tenaga
- Pekerja 0.5069 Oh x Rp. 110,000 = Rp. 55,762.67
- Tukang kayu 0.5069 Oh x Rp. 137,500 = Rp. 69,703.33
- Kepala tukang 0.0760 Oh x Rp. 165,000 = Rp. 12,540.00
- Mandor 0.0380 Oh x Rp. 192,500 = Rp. 7,315.00
Jumlah (2) = Rp. 145,321.00

Jumlah (1) + (2= Rp. 187,073.58

PBA 6.23 1 M' Memasang Kusen Alumunium 4" tebal 1.35mm Warna

6.23.1 Bahan
- Bahan kusen Alluminium 4 " ( warna / silver / natural )
1.1000 m x Rp. 122,400 = Rp. 134,640.00
Skrup Fixer 2.0000 bh x Rp. 1,200 = 2,400.00
Sealant 0.0600 tb x Rp. 73,200 = 4,392.00
Jumlah (1) = Rp. 141,432.00
6.23.2. Tenaga
- Pekerja 0.0430 Oh x Rp. 110,000 = Rp. 4,730.00
- Tukang khusus alumunium 0.0430 Oh x Rp. 137,500 = Rp. 5,912.50
- Kepala Tukang 0.0043 Oh x Rp. 165,000 = Rp. 709.50
- Mandor 0.0021 Oh x Rp. 192,500 = Rp. 404.25
Jumlah (2) = Rp. 11,756.25

Jumlah (1) + (2= Rp. 153,188.25


PBA 6.24 1 M2 Memasang Pintu Kaca Rangka Alumunium

6.24.1 Bahan
- Profil Alumunium 4.4000 m x Rp. 102,000 = Rp. 448,800.00
- List Kaca karet L 1 cm 4.5000 m x Rp. 5,600 = 25,200.00
- Sealant 0.2700 tube x Rp. 73,200 = 19,764.00
Jumlah (1) = Rp. 493,764.00
6.24.2. Tenaga
- Pekerja 0.0850 Oh x Rp. 110,000 = Rp. 9,350.00
- Tukang khusus alumunium 0.0850 Oh x Rp. 137,500 = Rp. 11,687.50
- Kepala Tukang 0.0090 Oh x Rp. 165,000 = Rp. 1,485.00
- Mandor 0.0050 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (2) = Rp. 23,485.00

Jumlah (1) + (2= Rp. 517,249.00

PBA 6.25 1 M2 Memasang Jendela Kaca Rangka Alumunium

6.25.1 Bahan
- Profil Alumunium jendela l=6cm 4.4000 m x Rp. 91,200 = Rp. 401,280.00
- List Kaca karet L 1 cm 4.5000 m x Rp. 5,600 = 25,200.00
- Sealant 0.2700 tube x Rp. 73,200 = 19,764.00
Jumlah (1) = Rp. 446,244.00
6.25.2. Tenaga
- Pekerja 0.0850 Oh x Rp. 110,000 = Rp. 9,350.00
- Tukang khusus alumunium 0.0850 Oh x Rp. 137,500 = Rp. 11,687.50
- Kepala Tukang 0.0090 Oh x Rp. 165,000 = Rp. 1,485.00
- Mandor 0.0050 Oh x Rp. 192,500 = Rp. 962.50
Jumlah (2) = Rp. 23,485.00

Jumlah (1) + (2= Rp. 469,729.00

6.23 1 unit Pek. Jendela Alumunium type Ukuran 1,5 x 1,6 (J1)
- pasang kusen alumunium 4" Warna lengkap accessories 8.985 M' x Rp. 127,114.02 1,142,119.47
- pasang jalusi aluminium 11.745 M' x Rp. 54,825.00 643,919.63
- pasang daun jendela alumunium +kaca 5 mm 1.3608 M2 x Rp. 679,423.59 924,559.62
- pasang kunci slot 2 Bua x Rp. 80,465.00 160,930.00
- pasang engsel jendela 4 Bua x Rp. 41,882.50 167,530.00
3,039,058.72

Jumlah (1) + (2= Rp. 3,039,058.72

6.24 1 unit Pek. Bouvenlight Alumunium WC/KM, type Ukuran 0,7 x 0,5 m
- pasang kusen alumunium 4" Warna lengkap accessories 2.64 M' x Rp. 127,114.02 = Rp. 335,581.01
- pasang jalusi aluminium 5.265 M' x Rp. 54,825.00 = Rp. 288,653.63
624,234.64

Jumlah (1) + (2= Rp. 624,234.64

Pek. Jendela Alumunium type Ukuran 1,5 x 1,6


- pasang kusen alumunium 4" Warna lengkap accessories 9.255 M' x Rp. 127,114.02 1,176,440.26
- pasang jalusi aluminium 12.76 M' x Rp. 54,825.00 699,567.00
- pasang daun jendela alumunium +kaca 5 mm 1.4256 M2 x Rp. 679,423.59 968,586.27
- pasang kunci slot 2 Bua x Rp. 80,465.00 160,930.00
- pasang engsel jendela 4 Bua x Rp. 41,882.50 167,530.00
3,173,053.53
Jumlah (1) + (2= Rp. 3,173,053.53
ANALISA BIAYA KONSTRUKSI
PEKERJAAN LANGIT - LANGIT

PLL 6.1 1 M² Langit - langit akustik ( 60 x 60 ) cm + rangka alluminium

6.1.1 Bahan
- Akustik ukuran 60 x 60 cm 5.800 Lbr x Rp. 20,484 = Rp. 118,807.20
Profil alluminium "T" 3.600 M' x Rp. 16,800 = Rp. 60,480.00
Kawat seng polos 0.150 Kg x Rp. 42,000 = Rp. 6,300.00
Ramset/dina bolt 1.000 Bh x Rp. 2,400 = Rp. 2,400.00
- Paku 0.050 Kg x Rp. 19,200 = Rp. 960.00
Jumlah (1) = Rp. 188,947.20
6.1.2 Tenaga
- Pekerja 0.060 Oh x Rp. 110,000 = Rp. 6,600.00
- Tukang kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.003 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 22,577.50

Jumlah (1) + (2) = Rp. 211,524.70

PLL 6.2 1 M² Langit - langit gyptile


6.2.1 Bahan
- Soft board 4' x 8' x 4 mm 0.350 Lbr x Rp. 67,188 = Rp. 23,515.80
- Paku sekrup 12.000 bh x Rp. 1,400 = Rp. 16,800.00
- Rangka besi hollow galvnis 40x40x 0.415 btg x Rp. 36,750 = Rp. 15,251.25
- Rangka besi hollow galvnis 20x40x 0.150 btg x Rp. 30,000 = Rp. 4,500.00
- Ramset/dina bolt 4.000 bh x Rp. 2,000 = Rp. 8,000.00
- Paku biasa 0.030 Kg x Rp. 19,200 = Rp. 576.00
Jumlah (1) = Rp. 68,643.05
6.2.2 Tenaga
- Pekerja 0.600 Oh x Rp. 110,000 = Rp. 66,000.00
- Tukang kayu 0.100 Oh x Rp. 137,500 = Rp. 13,750.00
- Kepala tukang 0.010 Oh x Rp. 165,000 = Rp. 1,650.00
- Mandor 0.003 Oh x Rp. 192,500 = Rp. 577.50
Jumlah (2) = Rp. 81,977.50

Jumlah (1) + (2) = Rp. 150,620.55

PLL 6.3 1 M² Langit - langit akustik 60 x 120 cm + rangka alluminium

6.3.1 Bahan
- Profil alluminium "T" 3.600 M' x Rp. 16,800 = Rp. 60,480.00
- Kawat seng polos 0.150 Kg x Rp. 42,000 = Rp. 6,300.00
- Ramset/dina bolt 1.000 Bh x Rp. 2,400 = Rp. 2,400.00
- Akustik arm strong 60 x 120 cm 1.400 Lbr x Rp. 81,948 = Rp. 114,727.20
Jumlah (1) = Rp. 183,907.20
6.3.2 Tenaga
- Pekerja 0.150 Oh x Rp. 110,000 = Rp. 16,500.00
- Tukang kayu 0.500 Oh x Rp. 137,500 = Rp. 68,750.00
- Kepala tukang 0.050 Oh x Rp. 165,000 = Rp. 8,250.00
- Mandor 0.0075 Oh x Rp. 192,500 = Rp. 1,443.75
Jumlah (2) = Rp. 94,943.75

Jumlah (1) + (2) = Rp. 278,850.95


ANALISA BIAYA KONTRUKSI
PEKERJAAN PENGECATAN

PC 7.1 1M² Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )

7.1.1 Bahan
- Plamir 0.120 Kg x Rp. 24,000 = Rp. 2,880.00
- Cat dasar 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
- Cat tembok 2 x 0.260 Kg x Rp. 38,400 = Rp. 9,984.00
Jumlah (1) = Rp. 17,472.00
7.1.2 Tenaga
- Pekerja 0.040 Oh x Rp. 110,000 = Rp. 4,400.00
- Tukang cat 0.120 Oh x Rp. 137,500 = Rp. 16,500.00
- Kepala tukang 0.0120 Oh x Rp. 165,000 = Rp. 1,980.00
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 23,265.00

Jumlah (1) + (2) = Rp. 40,737.00

PC 6.12 1M² Pengecatan tembok baru exterior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )

6.12.1 Bahan
- Plamir 0.120 Kg x Rp. 24,000 = Rp. 2,880.00
- Cat dasar 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
- Cat tembok 2 x exterior 0.260 Kg x Rp. 54,000 = Rp. 14,040.00
Jumlah (1) = Rp. 21,528.00
6.12.2 Tenaga
- Pekerja 0.040 Oh x Rp. 110,000 = Rp. 4,400.00
- Tukang cat 0.120 Oh x Rp. 137,500 = Rp. 16,500.00
- Kepala tukang 0.0120 Oh x Rp. 165,000 = Rp. 1,980.00
- Mandor 0.002 Oh x Rp. 192,500 = Rp. 385.00
Jumlah (2) = Rp. 23,265.00

Jumlah (1) + (2) = Rp. 44,793.00

PC 6.13 1M² Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )

6.13.1 Bahan
- Cat dasar 0.120 Kg x Rp. 38,400 = Rp. 4,608.00
- Cat tembok 2 x 0.260 Kg x Rp. 38,400 = Rp. 9,984.00
Jumlah (1) = Rp. 14,592.00
6.13.2 Tenaga
- Pekerja 0.030 Oh x Rp. 110,000 = Rp. 3,300.00
- Tukang cat 0.090 Oh x Rp. 137,500 = Rp. 12,375.00
- Kepala tukang 0.0090 Oh x Rp. 165,000 = Rp. 1,485.00
- Mandor 0.0015 Oh x Rp. 192,500 = Rp. 288.75
Jumlah (2) = Rp. 17,448.75

Jumlah (1) + (2) = Rp. 32,040.75


Keuntungan+Over head 10% = Rp 3,204.08
Total = Jumlah+(Keuntungan+Over head 10%) = Rp 35,244.83
ANALISA BIAYA KONSTRUKSI
PEKERJAAN AIR BERSIH

SAT HARGA
KODE . URAIAN INDEX SAT SATUAN
PEK Rp.
1 2 3 4 5 6
PEKERJAAN PEMASANGAN PIPA PVC
P001 M' Harga per 1M' ….. Rp.
Ø 25 MM PADA TANAH BIASA
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 4,020.00
25 mm
Galian tanah biasa 0.1300 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.0800 m³ 93,885.00
Urugan pasir 0.0500 m³ 325,200.00
Buangan sisa galian 0.0500 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P002 M' Harga per 1M' ….. Rp.
Ø 40 MM PADA TANAH BIASA
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 6,410.00
40 mm
Galian tanah biasa 0.1600 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.1000 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P003 M' Harga per 1M' ….. Rp.
Ø 50 MM PADA TANAH BIASA
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 8,020.00
50 mm
Galian tanah biasa 0.2200 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P004 M' Harga per 1M' ….. Rp.
Ø 75 MM PADA TANAH BIASA
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 11,980.00
75 mm
Galian tanah biasa 0.2800 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P005 M' Harga per 1M' ….. Rp.
Ø 100 MM PADA TANAH BIASA
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 15,950.00
100 mm
Galian tanah biasa 0.3400 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P006 M' Harga per 1M' ….. Rp.
Ø 150 MM PADA TANAH BIASA
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 23,540.00
150 mm
Galian tanah biasa 0.4500 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P007 M' Harga per 1M' ….. Rp.
Ø 200 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 31,980.00
200 mm
Galian tanah biasa 0.5200 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P008 M' Harga per 1M' ….. Rp.
Ø 250 MM PADA TANAH BIASA
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 39,670.00
250 mm
Galian tanah biasa 0.6100 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P009 M' Harga per 1M' ….. Rp.
Ø 300 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 48,360.00
300 mm
Galian tanah biasa 0.7300 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P010 M' Harga per 1M' ….. Rp.
Ø 400 MMdan
Peletakan PADA TANAH BIASA
Penyambungan Pipa PVC Ø
1.0000 m¹ 76,980.00
400 mm
Galian tanah biasa 0.9000 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P011 M' Harga per 1M' ….. Rp.
Ø 500 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 105,300.00
500 mm
Galian tanah biasa 1.1520 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P012 M' Harga per 1M' ….. Rp.
Ø 600 MMdan
Peletakan PADA TANAH BIASA
Penyambungan Pipa PVC Ø
1.0000 m¹ 157,950.00
600 mm
Galian tanah biasa 1.3940 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P013 M' Harga per 1M' ….. Rp.
Ø 25 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 4,020.00
25 mm
Galian tanah Keras 0.1300 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.0800 m³ 93,885.00
Urugan pasir 0.0500 m³ 325,200.00
Buangan sisa galian 0.0500 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P014 M' Harga per 1M' ….. Rp.
Ø 40 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 6,410.00
40 mm
Galian tanah Keras 0.1600 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.1000 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P015 M' Harga per 1M' ….. Rp.
Ø 50 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 8,020.00
50 mm
Galian tanah Keras 0.2200 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA PVC
P016 M' Harga per 1M' ….. Rp.
Ø 75 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 11,980.00
75 mm
Galian tanah Keras 0.2800 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P017 M' Harga per 1M' ….. Rp.
Ø 100 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 15,950.00
100 mm
Galian tanah Keras 0.3400 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P018 M' Harga per 1M' ….. Rp.
Ø 150 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 23,540.00
150 mm
Galian tanah Keras 0.4500 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P019 M' Harga per 1M' ….. Rp.
Ø 200 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 31,980.00
200 mm
Galian tanah Keras 0.5200 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P020 M' Harga per 1M' ….. Rp.
Ø 250 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 39,670.00
250 mm
Galian tanah Keras 0.6100 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P021 M' Harga per 1M' ….. Rp.
Ø 300 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 48,360.00
300 mm
Galian tanah Keras 0.7300 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P022 M' Harga per 1M' ….. Rp.
Ø 400 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 76,980.00
400 mm
Galian tanah Keras 0.9000 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA PVC
P023 M' Harga per 1M' ….. Rp.
Ø 500 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 105,300.00
500 mm
Galian tanah Keras 1.1520 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P024 M' Harga per 1M' ….. Rp.
Ø 600 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 157,950.00
600 mm
Galian tanah Keras 1.3940 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P025 M' Harga per 1M' ….. Rp.
Ø 25 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 4,020.00
25 mm
Galian tanah Berbatu 0.1300 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.0800 m³ 93,885.00
Urugan pasir 0.0500 m³ 325,200.00
Buangan sisa galian 0.0500 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P026 M' Harga per 1M' ….. Rp.
Ø 40 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 6,410.00
40 mm
Galian tanah Berbatu 0.1600 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.1000 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P027 M' Harga per 1M' ….. Rp.
Ø 50 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 8,020.00
50 mm
Galian tanah Berbatu 0.2200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P028 M' Harga per 1M' ….. Rp.
Ø 75 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 11,980.00
75 mm
Galian tanah Berbatu 0.2800 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P029 M' Harga per 1M' ….. Rp.
Ø 100 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 15,950.00
100 mm
Galian tanah Berbatu 0.3400 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P030 M' Harga per 1M' ….. Rp.
Ø 150 MM PADA TANAH BERBATU
Peletakan dan Penyambungan Pipa PVC Ø
1.0000 m¹ 23,540.00
150 mm
Galian tanah Berbatu 0.4500 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P031 M' Harga per 1M' ….. Rp.
Ø 200 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 31,980.00
200 mm
Galian tanah Berbatu 0.5200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P032 M' Harga per 1M' ….. Rp.
Ø 250 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 39,670.00
250 mm
Galian tanah Berbatu 0.6100 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P033 M' Harga per 1M' ….. Rp.
Ø 300 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 48,360.00
300 mm
Galian tanah Berbatu 0.7300 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P034 M' Harga per 1M' ….. Rp.
Ø 400 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 76,980.00
400 mm
Galian tanah Berbatu 0.9000 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P035 M' Harga per 1M' ….. Rp.
Ø 500 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 105,300.00
500 mm
Galian tanah Berbatu 1.1520 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P036 M' Harga per 1M' ….. Rp.
Ø 600 MM PADA TANAH BERBATU

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 157,950.00
600 mm

Galian tanah Berbatu 1.3940 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P037 M' Harga per 1M' ….. Rp.
Ø 25 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 4,020.00
25 mm
Galian tanah Cadas 0.1300 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.0800 m³ 93,885.00
Urugan pasir 0.0500 m³ 325,200.00
Buangan sisa galian 0.0500 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P038 M' Harga per 1M' ….. Rp.
Ø 40 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 6,410.00
40 mm
Galian tanah Cadas 0.1600 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.1000 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P039 M' Harga per 1M' ….. Rp.
Ø 50 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 8,020.00
50 mm
Galian tanah Cadas 0.2200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P040 M' Harga per 1M' ….. Rp.
Ø 75 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 11,980.00
75 mm
Galian tanah Cadas 0.2800 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA PVC
P041 M' Harga per 1M' ….. Rp.
Ø 100 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 15,950.00
100 mm
Galian tanah Cadas 0.3400 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P042 M' Harga per 1M' ….. Rp.
Ø 150 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 23,540.00
150 mm
Galian tanah Cadas 0.4500 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P044 M' Harga per 1M' ….. Rp.
Ø 200 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 31,980.00
200 mm
Galian tanah Cadas 0.5200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P045 M' Harga per 1M' ….. Rp.
Ø 250 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 39,670.00
250 mm
Galian tanah Cadas 0.6100 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P046 M' Harga per 1M' ….. Rp.
Ø 300 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 48,360.00
300 mm
Galian tanah Cadas 0.7300 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P047 M' Harga per 1M' ….. Rp.
Ø 400 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 76,980.00
400 mm
Galian tanah Cadas 0.9000 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA PVC


P048 M' Harga per 1M' ….. Rp.
Ø 500 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 105,300.00
500 mm
Galian tanah Cadas 1.1520 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA PVC
P049 M' Harga per 1M' ….. Rp.
Ø 600 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m¹ 157,950.00
600 mm
Galian tanah Cadas 1.3940 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P050 M' STEEL / GI Ø 50 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 21,850.00
Pengelasan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 10,490.00
Galian tanah biasa 0.2200 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P051 M' STEEL / GI Ø 75 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA

Peletakan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 26,770.00


Pengelasan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 15,740.00
Galian tanah biasa 0.2800 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P052 M' STEEL / GI Ø 100 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 45,450.00
Pengelasan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 20,990.00
Galian tanah biasa 0.3400 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P053 M' STEEL / GI Ø 150 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 58,550.00
Pengelasan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 31,480.00
Galian tanah biasa 0.4500 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P054 M' STEEL / GI Ø 200 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 74,030.00
Pengelasan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 41,970.00
Galian tanah biasa 0.5200 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P055 M' STEEL / GI Ø 250 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 81,950.00
Pengelasan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 52,460.00
Galian tanah biasa 0.6100 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P056 M' STEEL / GI Ø 300 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 90,220.00
Pengelasan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 62,960.00
Galian tanah biasa 0.7300 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P057 M' STEEL / GI Ø 400 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA

Peletakan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 107,900.00


Pengelasan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 83,940.00
Galian tanah biasa 0.9000 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P058 M' STEEL / GI Ø 500 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 141,410.00
Pengelasan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 104,930.00
Galian tanah biasa 1.1520 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P059 M' STEEL / GI Ø 600 MM PADA TANAH Harga per 1M' ….. Rp.
BIASA
Peletakan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 168,400.00
Pengelasan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 125,910.00
Galian tanah biasa 1.3940 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P060 M' STEEL / GI Ø 50 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS
Peletakan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 21,850.00
Pengelasan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 10,490.00
Galian tanah Keras 0.2200 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P061 M' STEEL / GI Ø 75 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS

Peletakan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 26,770.00


Pengelasan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 15,740.00
Galian tanah Keras 0.2800 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P062 M' STEEL / GI Ø 100 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS

Peletakan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 45,450.00


Pengelasan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 20,990.00
Galian tanah Keras 0.3400 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P063 M' STEEL / GI Ø 150 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS
Peletakan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 58,550.00
Pengelasan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 31,480.00
Galian tanah Keras 0.4500 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P064 M' STEEL / GI Ø 200 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS
Peletakan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 74,030.00
Pengelasan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 41,970.00
Galian tanah Keras 0.5200 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P065 M' STEEL / GI Ø 250 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS

Peletakan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 81,950.00


Pengelasan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 52,460.00
Galian tanah Keras 0.6100 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P066 M' STEEL / GI Ø 300 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS
Peletakan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 90,220.00
Pengelasan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 62,960.00
Galian tanah Keras 0.7300 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P067 M' STEEL / GI Ø 400 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS
Peletakan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 107,900.00
Pengelasan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 83,940.00
Galian tanah Keras 0.9000 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P068 M' STEEL / GI Ø 500 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS
Peletakan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 141,410.00
Pengelasan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 104,930.00
Galian tanah Keras 1.1520 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P069 M' STEEL / GI Ø 600 MM PADA TANAH Harga per 1M' ….. Rp.
KERAS

Peletakan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 168,400.00


Pengelasan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 125,910.00
Galian tanah Keras 1.3940 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P070 M' STEEL / GI Ø 50 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 21,850.00
Pengelasan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 10,490.00
Galian tanah Berbatu 0.2200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P071 M' STEEL / GI Ø 75 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 26,770.00
Pengelasan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 15,740.00
Galian tanah Berbatu 0.2800 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P072 M' STEEL / GI Ø 100 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 45,450.00
Pengelasan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 20,990.00
Galian tanah Berbatu 0.3400 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P073 M' STEEL / GI Ø 150 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 58,550.00
Pengelasan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 31,480.00
Galian tanah Berbatu 0.4500 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P074 M' STEEL / GI Ø 200 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 74,030.00
Pengelasan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 41,970.00
Galian tanah Berbatu 0.5200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P075 M' STEEL / GI Ø 250 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 81,950.00


Pengelasan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 52,460.00
Galian tanah Berbatu 0.6100 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P076 M' STEEL / GI Ø 300 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 90,220.00
Pengelasan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 62,960.00
Galian tanah Berbatu 0.7300 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P077 M' STEEL / GI Ø 400 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 107,900.00


Pengelasan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 83,940.00
Galian tanah Berbatu 0.9000 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P078 M' STEEL / GI Ø 500 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 141,410.00
Pengelasan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 104,930.00
Galian tanah Berbatu 1.1520 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P079 M' STEEL / GI Ø 600 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 168,400.00
Pengelasan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 125,910.00
Galian tanah Berbatu 1.3940 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P080 M' STEEL / GI Ø 50 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 21,850.00
Pengelasan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 10,490.00
Galian tanah Cadas 0.2200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P081 M' STEEL / GI Ø 75 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS

Peletakan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 26,770.00


Pengelasan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 15,740.00
Galian tanah Cadas 0.2800 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P082 M' STEEL / GI Ø 100 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS

Peletakan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 45,450.00


Pengelasan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 20,990.00
Galian tanah Cadas 0.3400 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P083 M' STEEL / GI Ø 150 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 58,550.00
Pengelasan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 31,480.00
Galian tanah Cadas 0.4500 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P084 M' STEEL / GI Ø 200 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 74,030.00
Pengelasan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 41,970.00
Galian tanah Cadas 0.5200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P085 M' STEEL / GI Ø 250 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 81,950.00
Pengelasan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 52,460.00
Galian tanah Cadas 0.6100 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P086 M' STEEL / GI Ø 300 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 90,220.00
Pengelasan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 62,960.00
Galian tanah Cadas 0.7300 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P087 M' STEEL / GI Ø 400 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 107,900.00
Pengelasan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 83,940.00
Galian tanah Cadas 0.9000 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P088 M' STEEL / GI Ø 500 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 141,410.00
Pengelasan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 104,930.00
Galian tanah Cadas 1.1520 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P089 M' STEEL / GI Ø 600 MM PADA TANAH Harga per 1M' ….. Rp.
CADAS
Peletakan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 168,400.00
Pengelasan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 125,910.00
Galian tanah Cadas 1.3940 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P090 M' Harga per 1M' ….. Rp.
HDPE Ø 50 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 18,520.00
Ø 50 mm
Galian tanah biasa 0.2200 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P091 M' Harga per 1M' ….. Rp.
HDPE Ø 75 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 25,980.00
Ø 75 mm
Galian tanah biasa 0.2800 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P092 M' Harga per 1M' ….. Rp.
HDPE Ø 100 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 43,950.00
Ø 100 mm

Galian tanah biasa 0.3400 m³ 87,312.50


Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P093 M' Harga per 1M' ….. Rp.
HDPE Ø 150 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 69,040.00
Ø 150 mm
Galian tanah biasa 0.4500 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P094 M' Harga per 1M' ….. Rp.
HDPE Ø 200 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 84,480.00
Ø 200 mm
Galian tanah biasa 0.5200 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P095 M' Harga per 1M' ….. Rp.
HDPE Ø 250 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 95,670.00
Ø 250 mm
Galian tanah biasa 0.6100 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P096 M' Harga per 1M' ….. Rp.
HDPE Ø 300 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 125,360.00
Ø 300 mm
Galian tanah biasa 0.7300 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P097 M' Harga per 1M' ….. Rp.
HDPE Ø 400 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 164,480.00
Ø 400 mm
Galian tanah biasa 0.9000 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P098 M' Harga per 1M' ….. Rp.
HDPE Ø 500 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 205,050.00
Ø 500 mm
Galian tanah biasa 1.1520 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P099 M' Harga per 1M' ….. Rp.
HDPE Ø 600 MM PADA TANAH BIASA

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 273,450.00
Ø 600 mm
Galian tanah biasa 1.3940 m³ 87,312.50
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P100 M' Harga per 1M' ….. Rp.
HDPE Ø 50 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 18,520.00
Ø 50 mm
Galian tanah Keras 0.2200 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P101 M' Harga per 1M' ….. Rp.
HDPE Ø 75 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 25,980.00
Ø 75 mm
Galian tanah Keras 0.2800 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P102 M' Harga per 1M' ….. Rp.
HDPE Ø 100 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 43,950.00
Ø 100 mm
Galian tanah Keras 0.3400 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P103 M' Harga per 1M' ….. Rp.
HDPE Ø 150 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 69,040.00
Ø 150 mm

Galian tanah Keras 0.4500 m³ 116,160.00


Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P104 M' Harga per 1M' ….. Rp.
HDPE Ø 200 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 84,480.00
Ø 200 mm
Galian tanah Keras 0.5200 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P105 M' Harga per 1M' ….. Rp.
HDPE Ø 250 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 95,670.00
Ø 250 mm
Galian tanah Keras 0.6100 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P106 M' Harga per 1M' ….. Rp.
HDPE Ø 300 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 125,360.00
Ø 300 mm
Galian tanah Keras 0.7300 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P107 M' Harga per 1M' ….. Rp.
HDPE Ø 400 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 164,480.00
Ø 400 mm
Galian tanah Keras 0.9000 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P108 M' Harga per 1M' ….. Rp.
HDPE Ø 500 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 205,050.00
Ø 500 mm
Galian tanah Keras 1.1520 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P109 M' Harga per 1M' ….. Rp.
HDPE Ø 600 MM PADA TANAH KERAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 273,450.00
Ø 600 mm
Galian tanah Keras 1.3940 m³ 116,160.00
Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P110 M' HDPE Ø 50 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan dan Penyambungan Pipa HDPE
1.0000 m¹ 18,520.00
Ø 50 mm
Galian tanah Berbatu 0.2200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P111 M' HDPE Ø 75 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 25,980.00
Ø 75 mm
Galian tanah Berbatu 0.2800 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P112 M' HDPE Ø 100 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 43,950.00
Ø 100 mm
Galian tanah Berbatu 0.3400 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P113 M' HDPE Ø 150 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan dan Penyambungan Pipa HDPE
1.0000 m¹ 69,040.00
Ø 150 mm
Galian tanah Berbatu 0.4500 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P114 M' HDPE Ø 200 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 84,480.00
Ø 200 mm
Galian tanah Berbatu 0.5200 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P115 M' HDPE Ø 250 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan dan Penyambungan Pipa HDPE
1.0000 m¹ 95,670.00
Ø 250 mm
Galian tanah Berbatu 0.6100 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P116 M' HDPE Ø 300 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 125,360.00
Ø 300 mm
Galian tanah Berbatu 0.7300 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P117 M' HDPE Ø 400 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU
Peletakan dan Penyambungan Pipa HDPE
1.0000 m¹ 164,480.00
Ø 400 mm
Galian tanah Berbatu 0.9000 m³ 176,550.00
Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P118 M' HDPE Ø 500 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 205,050.00
Ø 500 mm

Galian tanah Berbatu 1.1520 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P119 M' HDPE Ø 600 MM PADA TANAH Harga per 1M' ….. Rp.
BERBATU

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 273,450.00
Ø 600 mm

Galian tanah Berbatu 1.3940 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P120 M' Harga per 1M' ….. Rp.
HDPE Ø 50 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 18,520.00
Ø 50 mm

Galian tanah Cadas 0.2200 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.1500 m³ 93,885.00
Urugan pasir 0.0600 m³ 325,200.00
Buangan sisa galian 0.0700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P121 M' Harga per 1M' ….. Rp.
HDPE Ø 75 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 25,980.00
Ø 75 mm

Galian tanah Cadas 0.2800 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.2000 m³ 93,885.00
Urugan pasir 0.0800 m³ 325,200.00
Buangan sisa galian 0.0800 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P122 M' Harga per 1M' ….. Rp.
HDPE Ø 100 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 43,950.00
Ø 100 mm

Galian tanah Cadas 0.3400 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.2400 m³ 93,885.00
Urugan pasir 0.0900 m³ 325,200.00
Buangan sisa galian 0.1000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P123 M' Harga per 1M' ….. Rp.
HDPE Ø 150 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 69,040.00
Ø 150 mm

Galian tanah Cadas 0.4500 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.3200 m³ 93,885.00
Urugan pasir 0.1100 m³ 325,200.00
Buangan sisa galian 0.1300 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P124 M' Harga per 1M' ….. Rp.
HDPE Ø 200 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 84,480.00
Ø 200 mm

Galian tanah Cadas 0.5200 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.3600 m³ 93,885.00
Urugan pasir 0.1300 m³ 325,200.00
Buangan sisa galian 0.1600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P125 M' Harga per 1M' ….. Rp.
HDPE Ø 250 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 95,670.00
Ø 250 mm

Galian tanah Cadas 0.6100 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.4100 m³ 93,885.00
Urugan pasir 0.1500 m³ 325,200.00
Buangan sisa galian 0.2000 m³ 66,563.75
Jumlah
Keuntungan 10%
Total
PEKERJAAN PEMASANGAN PIPA
P126 M' Harga per 1M' ….. Rp.
HDPE Ø 300 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 125,360.00
Ø 300 mm

Galian tanah Cadas 0.7300 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.4600 m³ 93,885.00
Urugan pasir 0.1900 m³ 325,200.00
Buangan sisa galian 0.2700 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P127 M' Harga per 1M' ….. Rp.
HDPE Ø 400 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 164,480.00
Ø 400 mm

Galian tanah Cadas 0.9000 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.5400 m³ 93,885.00
Urugan pasir 0.2344 m³ 325,200.00
Buangan sisa galian 0.3600 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P128 M' Harga per 1M' ….. Rp.
HDPE Ø 500 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 205,050.00
Ø 500 mm

Galian tanah Cadas 1.1520 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.6336 m³ 93,885.00
Urugan pasir 0.3061 m³ 325,200.00
Buangan sisa galian 0.5184 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

PEKERJAAN PEMASANGAN PIPA


P129 M' Harga per 1M' ….. Rp.
HDPE Ø 600 MM PADA TANAH CADAS

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 273,450.00
Ø 600 mm

Galian tanah Cadas 1.3940 m³ 176,550.00


Urugan tanah kembali dipadatkan 0.7216 m³ 93,885.00
Urugan pasir 0.3667 m³ 325,200.00
Buangan sisa galian 0.6724 m³ 66,563.75
Jumlah
Keuntungan 10%
Total

P190 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 50 MM
Sewa Alat bantu 0.5500 jam 93,500.00
Mandor 0.1800 Org 192,500.00
Kepala Tukang Pipa 0.1800 Org 165,000.00
Pekerja Setengah Terampil 0.5000 Org 99,000.00
Pembuangan Tanah 0.0060 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 21,850.00
Pengelasan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 10,490.00
Galian Tanah Keras 0.0180 m³ 116,160.00
Urugan Tanah dipadatkan 0.0140 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P191 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 50 MM
Sewa Alat bantu 0.4500 jam 93,500.00
Mandor 0.1530 Org 192,500.00
Kepala Tukang Pipa 0.1530 Org 165,000.00
Pekerja Setengah Terampil 0.4000 Org 99,000.00
Pembuangan Tanah 0.0060 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 21,850.00
Pengelasan Pipa Steel / GI Ø 50 mm 1.0000 m¹ 10,490.00
Galian Tanah Keras 0.0180 m³ 116,160.00
Urugan Tanah dipadatkan 0.0140 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P192 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 75 MM
Sewa Alat bantu 0.7500 jam 93,500.00
Mandor 0.1800 Org 192,500.00
Kepala Tukang Pipa 0.1800 Org 165,000.00
Pekerja Setengah Terampil 0.7000 Org 99,000.00
Pembuangan Tanah 0.0090 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 26,770.00
Pengelasan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 15,740.00
Galian Tanah Keras 0.0250 m³ 116,160.00
Urugan Tanah dipadatkan 0.0190 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P193 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 75 MM
Sewa Alat bantu 0.7000 jam 93,500.00
Mandor 0.1530 Org 192,500.00
Kepala Tukang Pipa 0.1530 Org 165,000.00
Pekerja Setengah Terampil 0.6200 Org 99,000.00
Pembuangan Tanah 0.0090 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 26,770.00
Pengelasan Pipa Steel / GI Ø 75 mm 1.0000 m¹ 15,740.00
Galian Tanah Keras 0.0250 m³ 116,160.00
Urugan Tanah dipadatkan 0.0190 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P194 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 100 MM
Sewa Alat bantu 1.0000 jam 93,500.00
Mandor 0.2100 Org 192,500.00
Kepala Tukang Pipa 0.2100 Org 165,000.00
Pekerja Setengah Terampil 0.9000 Org 99,000.00
Pembuangan Tanah 0.0110 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 45,450.00
Pengelasan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 20,990.00
Galian Tanah Keras 0.0330 m³ 116,160.00
Urugan Tanah dipadatkan 0.0250 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P195 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 100 MM
PEMASANGAN PIPA DENGAN CARA
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 100 MM
Sewa Alat bantu 0.9500 jam 93,500.00
Mandor 0.1790 Org 192,500.00
Kepala Tukang Pipa 0.1790 Org 165,000.00
Pekerja Setengah Terampil 0.8500 Org 99,000.00
Pembuangan Tanah 0.0110 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 45,450.00
Pengelasan Pipa Steel / GI Ø 100 mm 1.0000 m¹ 20,990.00
Galian Tanah Keras 0.0330 m³ 116,160.00
Urugan Tanah dipadatkan 0.0250 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P196 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 150 MM
Sewa Alat bantu 1.3300 jam 93,500.00
Mandor 0.3150 Org 192,500.00
Kepala Tukang Pipa 0.3150 Org 165,000.00
Pekerja Setengah Terampil 1.5750 Org 99,000.00
Pembuangan Tanah 0.0170 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 58,550.00
Pengelasan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 31,480.00
Galian Tanah Keras 0.0500 m³ 116,160.00
Urugan Tanah dipadatkan 0.0380 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P197 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 150 MM
Sewa Alat bantu 1.1310 jam 93,500.00
Mandor 0.2680 Org 192,500.00
Kepala Tukang Pipa 0.2680 Org 165,000.00
Pekerja Setengah Terampil 1.3390 Org 99,000.00
Pembuangan Tanah 0.0170 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 58,550.00
Pengelasan Pipa Steel / GI Ø 150 mm 1.0000 m¹ 31,480.00
Galian Tanah Keras 0.0500 m³ 116,160.00
Urugan Tanah dipadatkan 0.0380 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P198 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 200 MM
Sewa Alat bantu 1.4000 jam 93,500.00
Mandor 0.4200 Org 192,500.00
Kepala Tukang Pipa 0.4200 Org 165,000.00
Pekerja Setengah Terampil 2.1000 Org 99,000.00
Pembuangan Tanah 0.0230 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 74,030.00
Pengelasan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 41,970.00
Galian Tanah Keras 0.0670 m³ 116,160.00
Urugan Tanah dipadatkan 0.0500 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P199 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 200 MM
Sewa Alat bantu 1.1900 jam 93,500.00
Mandor 0.3570 Org 192,500.00
Kepala Tukang Pipa 0.3570 Org 165,000.00
Pekerja Setengah Terampil 1.7850 Org 99,000.00
Pembuangan Tanah 0.0230 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 74,030.00
Pengelasan Pipa Steel / GI Ø 200 mm 1.0000 m¹ 41,970.00
Galian Tanah Keras 0.0670 m³ 116,160.00
Urugan Tanah dipadatkan 0.0500 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P200 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 250 MM
Sewa Alat bantu 1.4700 jam 93,500.00
Mandor 0.5250 Org 192,500.00
Kepala Tukang Pipa 0.5250 Org 165,000.00
Pekerja Setengah Terampil 2.6250 Org 99,000.00
Pembuangan Tanah 0.0280 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 81,950.00
Pengelasan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 52,460.00
Galian Tanah Keras 0.0830 m³ 116,160.00
Urugan Tanah dipadatkan 0.0630 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P201 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 250 MM
Sewa Alat bantu 1.2500 jam 93,500.00
Mandor 0.4470 Org 192,500.00
Kepala Tukang Pipa 0.4470 Org 165,000.00
Pekerja Setengah Terampil 2.2320 Org 99,000.00
Pembuangan Tanah 0.0280 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 81,950.00
Pengelasan Pipa Steel / GI Ø 250 mm 1.0000 m¹ 52,460.00
Galian Tanah Keras 0.0830 m³ 116,160.00
Urugan Tanah dipadatkan 0.0630 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P202 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 300 MM
Sewa Alat bantu 1.5400 jam 93,500.00
Mandor 0.6300 Org 192,500.00
Kepala Tukang Pipa 0.6300 Org 165,000.00
Pekerja Setengah Terampil 3.1500 Org 99,000.00
Pembuangan Tanah 0.0340 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 90,220.00
Pengelasan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 62,960.00
Galian Tanah Keras 0.1000 m³ 116,160.00
Urugan Tanah dipadatkan 0.0750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P203 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 300 MM
Sewa Alat bantu 1.3090 jam 93,500.00
Mandor 0.5360 Org 192,500.00
Kepala Tukang Pipa 0.5360 Org 165,000.00
Pekerja Setengah Terampil 2.6780 Org 99,000.00
Pembuangan Tanah 0.0340 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 90,220.00
Pengelasan Pipa Steel / GI Ø 300 mm 1.0000 m¹ 62,960.00
Galian Tanah Keras 0.1000 m³ 116,160.00
Urugan Tanah dipadatkan 0.0750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P204 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 400 MM
Sewa Alat bantu 1.6800 jam 93,500.00
Mandor 0.8400 Org 192,500.00
Kepala Tukang Pipa 0.8400 Org 165,000.00
Pekerja Setengah Terampil 4.2000 Org 99,000.00
Pembuangan Tanah 0.0450 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 107,900.00
Pengelasan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 83,940.00
Galian Tanah Keras 0.1330 m³ 116,160.00
Urugan Tanah dipadatkan 0.1000 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P205 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 400 MM
Sewa Alat bantu 1.4280 jam 93,500.00
Mandor 0.7140 Org 192,500.00
Kepala Tukang Pipa 0.7140 Org 165,000.00
Pekerja Setengah Terampil 3.5700 Org 99,000.00
Pembuangan Tanah 0.0450 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 107,900.00
Pengelasan Pipa Steel / GI Ø 400 mm 1.0000 m¹ 83,940.00
Galian Tanah Keras 0.1330 m³ 116,160.00
Urugan Tanah dipadatkan 0.1000 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P206 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 500 MM
PEMASANGAN PIPA DENGAN CARA
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 500 MM
Sewa Alat bantu 2.9400 jam 93,500.00
Mandor 1.4700 Org 192,500.00
Kepala Tukang Pipa 1.4700 Org 165,000.00
Pekerja Setengah Terampil 7.3500 Org 99,000.00
Pembuangan Tanah 0.0790 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 141,410.00
Pengelasan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 104,930.00
Galian Tanah Keras 0.2330 m³ 116,160.00
Urugan Tanah dipadatkan 0.1750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P207 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 500 MM
Sewa Alat bantu 2.4990 jam 93,500.00
Mandor 1.2500 Org 192,500.00
Kepala Tukang Pipa 1.2500 Org 165,000.00
Pekerja Setengah Terampil 6.2480 Org 99,000.00
Pembuangan Tanah 0.0790 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 141,410.00
Pengelasan Pipa Steel / GI Ø 500 mm 1.0000 m¹ 104,930.00
Galian Tanah Keras 0.2330 m³ 116,160.00
Urugan Tanah dipadatkan 0.1750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P208 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
PADA JALAN BINA MARGA U/ STEEL
Ø 600 MM
Sewa Alat bantu 5.1450 jam 93,500.00
Mandor 2.5730 Org 192,500.00
Kepala Tukang Pipa 2.5730 Org 165,000.00
Pekerja Setengah Terampil 12.8630 Org 99,000.00
Pembuangan Tanah 0.1390 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 168,400.00
Pengelasan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 125,910.00
Galian Tanah Keras 0.4080 m³ 116,160.00
Urugan Tanah dipadatkan 0.3060 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P209 M' PEMASANGAN PIPA DENGAN CARA Harga per 1M' ….. Rp.
BORING HORIZONTAL DRILLING
DILINGKUNGAN PERUMAHAN U/
STEEL Ø 600 MM
Sewa Alat bantu 4.3740 jam 93,500.00
Mandor 2.1870 Org 192,500.00
Kepala Tukang Pipa 2.1870 Org 165,000.00
Pekerja Setengah Terampil 10.9330 Org 99,000.00
Pembuangan Tanah 0.1390 m³ 66,563.75
Peletakan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 168,400.00
Pengelasan Pipa Steel / GI Ø 600 mm 1.0000 m¹ 125,910.00
Galian Tanah Keras 0.4080 m³ 116,160.00
Urugan Tanah dipadatkan 0.3060 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P210 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
50 MM
Sewa Alat bantu 0.5500 jam 93,500.00
Mandor 0.1800 Org 192,500.00
Kepala Tukang Pipa 0.1800 Org 165,000.00
Pekerja Setengah Terampil 0.5000 Org 99,000.00
Pembuangan Tanah 0.0060 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m³ 8,020.00
50 mm

Galian Tanah Keras 0.0180 m³ 116,160.00


Urugan Tanah dipadatkan 0.0140 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P211 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 50 MM
Sewa Alat bantu 0.4500 jam 93,500.00
Mandor 0.1530 Org 192,500.00
Kepala Tukang Pipa 0.1530 Org 165,000.00
Pekerja Setengah Terampil 0.4000 Org 99,000.00
Pembuangan Tanah 0.0060 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC Ø


1.0000 m³ 8,020.00
50 mm
Galian Tanah Keras 0.0180 m³ 116,160.00
Urugan Tanah dipadatkan 0.0140 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P212 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
75 MM
Sewa Alat bantu 0.7500 jam 93,500.00
Mandor 0.1800 Org 192,500.00
Kepala Tukang Pipa 0.1800 Org 165,000.00
Pekerja Setengah Terampil 0.7000 Org 99,000.00
Pembuangan Tanah 0.0090 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 11,980.00
dia. 75 mm

Galian Tanah Keras 0.0250 m³ 116,160.00


Urugan Tanah dipadatkan 0.0190 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P213 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 75 MM
Sewa Alat bantu 0.7000 jam 93,500.00
Mandor 0.1530 Org 192,500.00
Kepala Tukang Pipa 0.1530 Org 165,000.00
Pekerja Setengah Terampil 0.6200 Org 99,000.00
Pembuangan Tanah 0.0090 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 11,980.00
dia. 75 mm

Galian Tanah Keras 0.0250 m³ 116,160.00


Urugan Tanah dipadatkan 0.0190 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P214 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
100 MM
Sewa Alat bantu 1.0000 jam 93,500.00
Mandor 0.2100 Org 192,500.00
Kepala Tukang Pipa 0.2100 Org 165,000.00
Pekerja Setengah Terampil 0.9000 Org 99,000.00
Pembuangan Tanah 0.0110 m³ 66,563.75
Peletakan dan Penyambungan Pipa PVC
1.0000 m³ 15,950.00
dia. 100 mm

Galian Tanah Keras 0.0330 m³ 116,160.00


Urugan Tanah dipadatkan 0.0250 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P215 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 100 MM
Sewa Alat bantu 0.9500 jam 93,500.00
Mandor 0.1790 Org 192,500.00
Kepala Tukang Pipa 0.1790 Org 165,000.00
Pekerja Setengah Terampil 0.8500 Org 99,000.00
Pembuangan Tanah 0.0110 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 15,950.00
dia. 100 mm

Galian Tanah Keras 0.0330 m³ 116,160.00


Urugan Tanah dipadatkan 0.0250 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P216 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
150 MM
Sewa Alat bantu 1.3300 jam 93,500.00
Mandor 0.3150 Org 192,500.00
Kepala Tukang Pipa 0.3150 Org 165,000.00
Pekerja Setengah Terampil 1.5750 Org 99,000.00
Pembuangan Tanah 0.0170 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 23,540.00
dia. 150 mm

Galian Tanah Keras 0.0500 m³ 116,160.00


Urugan Tanah dipadatkan 0.0380 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P217 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 150 MM
Sewa Alat bantu 1.1310 jam 93,500.00
Mandor 0.2680 Org 192,500.00
Kepala Tukang Pipa 0.2680 Org 165,000.00
Pekerja Setengah Terampil 1.3390 Org 99,000.00
Pembuangan Tanah 0.0170 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 23,540.00
dia. 150 mm

Galian Tanah Keras 0.0500 m³ 116,160.00


Urugan Tanah dipadatkan 0.0380 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P218 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
200 MM
Sewa Alat bantu 1.4000 jam 93,500.00
Mandor 0.4200 Org 192,500.00
Kepala Tukang Pipa 0.4200 Org 165,000.00
Pekerja Setengah Terampil 2.1000 Org 99,000.00
Pembuangan Tanah 0.0230 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 31,980.00
dia. 200 mm

Galian Tanah Keras 0.0670 m³ 116,160.00


Urugan Tanah dipadatkan 0.0500 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P219 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 200 MM
Sewa Alat bantu 1.1900 jam 93,500.00
Mandor 0.3570 Org 192,500.00
Kepala Tukang Pipa 0.3570 Org 165,000.00
Pekerja Setengah Terampil 1.7850 Org 99,000.00
Pembuangan Tanah 0.0230 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 31,980.00
dia. 200 mm

Galian Tanah Keras 0.0670 m³ 116,160.00


Urugan Tanah dipadatkan 0.0500 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P220 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
250 MM
Sewa Alat bantu 1.4700 jam 93,500.00
Mandor 0.5250 Org 192,500.00
Kepala Tukang Pipa 0.5250 Org 165,000.00
Pekerja Setengah Terampil 2.6250 Org 99,000.00
Pembuangan Tanah 0.0280 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 39,670.00
dia. 250 mm

Galian Tanah Keras 0.0830 m³ 116,160.00


Urugan Tanah dipadatkan 0.0630 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P222 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 250 MM
Sewa Alat bantu 1.2500 jam 93,500.00
Mandor 0.4470 Org 192,500.00
Kepala Tukang Pipa 0.4470 Org 165,000.00
Pekerja Setengah Terampil 2.2320 Org 99,000.00
Pembuangan Tanah 0.0280 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 39,670.00
dia. 250 mm

Galian Tanah Keras 0.0830 m³ 116,160.00


Urugan Tanah dipadatkan 0.0630 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P223 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
300 MM
Sewa Alat bantu 1.5400 jam 93,500.00
Mandor 0.6300 Org 192,500.00
Kepala Tukang Pipa 0.6300 Org 165,000.00
Pekerja Setengah Terampil 3.1500 Org 99,000.00
Pembuangan Tanah 0.0340 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 48,360.00
dia. 300 mm

Galian Tanah Keras 0.1000 m³ 116,160.00


Urugan Tanah dipadatkan 0.0750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total
PEMASANGAN PIPA DENGAN CARA
BORING HORIZONTAL DRILLING
P224 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 300 MM
Sewa Alat bantu 1.3090 jam 93,500.00
Mandor 0.5360 Org 192,500.00
Kepala Tukang Pipa 0.5360 Org 165,000.00
Pekerja Setengah Terampil 2.6780 Org 99,000.00
Pembuangan Tanah 0.0340 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m³ 48,360.00
dia. 300 mm

Galian Tanah Keras 0.1000 m³ 116,160.00


Urugan Tanah dipadatkan 0.0750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P225 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
400 MM
Sewa Alat bantu 1.6800 jam 93,500.00
Mandor 0.8400 Org 192,500.00
Kepala Tukang Pipa 0.8400 Org 165,000.00
Pekerja Setengah Terampil 4.2000 Org 99,000.00
Pembuangan Tanah 0.0450 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m¹ 76,980.00
dia. 400 mm

Galian Tanah Keras 0.1330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1000 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P226 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 400 MM
Sewa Alat bantu 1.4280 jam 93,500.00
Mandor 0.7140 Org 192,500.00
Kepala Tukang Pipa 0.7140 Org 165,000.00
Pekerja Setengah Terampil 3.5700 Org 99,000.00
Pembuangan Tanah 0.0450 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m¹ 76,980.00
dia. 400 mm

Galian Tanah Keras 0.1330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1000 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P227 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
500 MM
Sewa Alat bantu 2.9400 jam 93,500.00
Mandor 1.4700 Org 192,500.00
Kepala Tukang Pipa 1.4700 Org 165,000.00
Pekerja Setengah Terampil 7.3500 Org 99,000.00
Pembuangan Tanah 0.0790 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m¹ 105,300.00
dia. 500 mm

Galian Tanah Keras 0.2330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P228 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 500 MM
Sewa Alat bantu 2.4990 jam 93,500.00
Mandor 1.2500 Org 192,500.00
Kepala Tukang Pipa 1.2500 Org 165,000.00
Pekerja Setengah Terampil 6.2480 Org 99,000.00
Pembuangan Tanah 0.0790 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m¹ 105,300.00
dia. 500 mm

Galian Tanah Keras 0.2330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P229 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ PVC Ø
600 MM
Sewa Alat bantu 5.1450 jam 93,500.00
Mandor 2.5730 Org 192,500.00
Kepala Tukang Pipa 2.5730 Org 165,000.00
Pekerja Setengah Terampil 12.8630 Org 99,000.00
Pembuangan Tanah 0.1390 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m¹ 157,950.00
dia. 600 mm

Galian Tanah Keras 0.4080 m³ 116,160.00


Urugan Tanah dipadatkan 0.3060 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P230 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
PVC Ø 600 MM
Sewa Alat bantu 4.3740 jam 93,500.00
Mandor 2.1870 Org 192,500.00
Kepala Tukang Pipa 2.1870 Org 165,000.00
Pekerja Setengah Terampil 10.9330 Org 99,000.00
Pembuangan Tanah 0.1390 m³ 66,563.75

Peletakan dan Penyambungan Pipa PVC


1.0000 m¹ 157,950.00
dia. 600 mm

Galian Tanah Keras 0.4080 m³ 116,160.00


Urugan Tanah dipadatkan 0.3060 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P231 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 50 MM
Sewa Alat bantu 0.5500 jam 93,500.00
Mandor 0.1800 Org 192,500.00
Kepala Tukang Pipa 0.1800 Org 165,000.00
Pekerja Setengah Terampil 0.5000 Org 99,000.00
Pembuangan Tanah 0.0060 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 18,520.00
Ø 50 mm

Galian Tanah Keras 0.0180 m³ 116,160.00


Urugan Tanah dipadatkan 0.0140 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P232 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 50 MM
Sewa Alat bantu 0.4500 jam 93,500.00
Mandor 0.1530 Org 192,500.00
Kepala Tukang Pipa 0.1530 Org 165,000.00
Pekerja Setengah Terampil 0.4000 Org 99,000.00
Pembuangan Tanah 0.0060 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 18,520.00
Ø 50 mm
Galian Tanah Keras 0.0180 m³ 116,160.00
Urugan Tanah dipadatkan 0.0140 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P233 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 75 MM
Sewa Alat bantu 0.7500 jam 93,500.00
Mandor 0.1800 Org 192,500.00
Kepala Tukang Pipa 0.1800 Org 165,000.00
Pekerja Setengah Terampil 0.7000 Org 99,000.00
Pembuangan Tanah 0.0090 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 25,980.00
dia. 75 mm

Galian Tanah Keras 0.0250 m³ 116,160.00


Urugan Tanah dipadatkan 0.0190 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P234 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 75 MM
Sewa Alat bantu 0.7000 jam 93,500.00
Mandor 0.1530 Org 192,500.00
Kepala Tukang Pipa 0.1530 Org 165,000.00
Pekerja Setengah Terampil 0.6200 Org 99,000.00
Pembuangan Tanah 0.0090 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 25,980.00
dia. 75 mm

Galian Tanah Keras 0.0250 m³ 116,160.00


Urugan Tanah dipadatkan 0.0190 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P235 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 100 MM
Sewa Alat bantu 1.0000 jam 93,500.00
Mandor 0.2100 Org 192,500.00
Kepala Tukang Pipa 0.2100 Org 165,000.00
Pekerja Setengah Terampil 0.9000 Org 99,000.00
Pembuangan Tanah 0.0110 m³ 66,563.75
Peletakan dan Penyambungan Pipa
1.0000 m³ 43,950.00
HDPEdia. 100 mm

Galian Tanah Keras 0.0330 m³ 116,160.00


Urugan Tanah dipadatkan 0.0250 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P236 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 100 MM
Sewa Alat bantu 0.9500 jam 93,500.00
Mandor 0.1790 Org 192,500.00
Kepala Tukang Pipa 0.1790 Org 165,000.00
Pekerja Setengah Terampil 0.8500 Org 99,000.00
Pembuangan Tanah 0.0110 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 43,950.00
dia. 100 mm

Galian Tanah Keras 0.0330 m³ 116,160.00


Urugan Tanah dipadatkan 0.0250 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P237 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 150 MM
Sewa Alat bantu 1.3300 jam 93,500.00
Mandor 0.3150 Org 192,500.00
Kepala Tukang Pipa 0.3150 Org 165,000.00
Pekerja Setengah Terampil 1.5750 Org 99,000.00
Pembuangan Tanah 0.0170 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 23,540.00
dia. 150 mm

Galian Tanah Keras 0.0500 m³ 116,160.00


Urugan Tanah dipadatkan 0.0380 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P238 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 150 MM
Sewa Alat bantu 1.1310 jam 93,500.00
Mandor 0.2680 Org 192,500.00
Kepala Tukang Pipa 0.2680 Org 165,000.00
Pekerja Setengah Terampil 1.3390 Org 99,000.00
Pembuangan Tanah 0.0170 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 23,540.00
dia. 150 mm

Galian Tanah Keras 0.0500 m³ 116,160.00


Urugan Tanah dipadatkan 0.0380 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P239 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 200 MM
Sewa Alat bantu 1.4000 jam 93,500.00
Mandor 0.4200 Org 192,500.00
Kepala Tukang Pipa 0.4200 Org 165,000.00
Pekerja Setengah Terampil 2.1000 Org 99,000.00
Pembuangan Tanah 0.0230 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 84,480.00
dia. 200 mm

Galian Tanah Keras 0.0670 m³ 116,160.00


Urugan Tanah dipadatkan 0.0500 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P240 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 200 MM
Sewa Alat bantu 1.1900 jam 93,500.00
Mandor 0.3570 Org 192,500.00
Kepala Tukang Pipa 0.3570 Org 165,000.00
Pekerja Setengah Terampil 1.7850 Org 99,000.00
Pembuangan Tanah 0.0230 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 84,480.00
dia. 200 mm

Galian Tanah Keras 0.0670 m³ 116,160.00


Urugan Tanah dipadatkan 0.0500 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P241 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 250 MM
Sewa Alat bantu 1.4700 jam 93,500.00
Mandor 0.5250 Org 192,500.00
Kepala Tukang Pipa 0.5250 Org 165,000.00
Pekerja Setengah Terampil 2.6250 Org 99,000.00
Pembuangan Tanah 0.0280 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 95,670.00
dia. 250 mm

Galian Tanah Keras 0.0830 m³ 116,160.00


Urugan Tanah dipadatkan 0.0630 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P242 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 250 MM
Sewa Alat bantu 1.2500 jam 93,500.00
Mandor 0.4470 Org 192,500.00
Kepala Tukang Pipa 0.4470 Org 165,000.00
Pekerja Setengah Terampil 2.2320 Org 99,000.00
Pembuangan Tanah 0.0280 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 95,670.00
dia. 250 mm

Galian Tanah Keras 0.0830 m³ 116,160.00


Urugan Tanah dipadatkan 0.0630 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P243 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 300 MM
Sewa Alat bantu 1.5400 jam 93,500.00
Mandor 0.6300 Org 192,500.00
Kepala Tukang Pipa 0.6300 Org 165,000.00
Pekerja Setengah Terampil 3.1500 Org 99,000.00
Pembuangan Tanah 0.0340 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 125,360.00
dia. 300 mm

Galian Tanah Keras 0.1000 m³ 116,160.00


Urugan Tanah dipadatkan 0.0750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total
PEMASANGAN PIPA DENGAN CARA
BORING HORIZONTAL DRILLING
P244 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 300 MM
Sewa Alat bantu 1.3090 jam 93,500.00
Mandor 0.5360 Org 192,500.00
Kepala Tukang Pipa 0.5360 Org 165,000.00
Pekerja Setengah Terampil 2.6780 Org 99,000.00
Pembuangan Tanah 0.0340 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m³ 125,360.00
dia. 300 mm

Galian Tanah Keras 0.1000 m³ 116,160.00


Urugan Tanah dipadatkan 0.0750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P245 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 400 MM
Sewa Alat bantu 1.6800 jam 93,500.00
Mandor 0.8400 Org 192,500.00
Kepala Tukang Pipa 0.8400 Org 165,000.00
Pekerja Setengah Terampil 4.2000 Org 99,000.00
Pembuangan Tanah 0.0450 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 164,480.00
dia. 400 mm

Galian Tanah Keras 0.1330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1000 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P246 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 400 MM
Sewa Alat bantu 1.4280 jam 93,500.00
Mandor 0.7140 Org 192,500.00
Kepala Tukang Pipa 0.7140 Org 165,000.00
Pekerja Setengah Terampil 3.5700 Org 99,000.00
Pembuangan Tanah 0.0450 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 164,480.00
dia. 400 mm

Galian Tanah Keras 0.1330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1000 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P247 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 500 MM
Sewa Alat bantu 2.9400 jam 93,500.00
Mandor 1.4700 Org 192,500.00
Kepala Tukang Pipa 1.4700 Org 165,000.00
Pekerja Setengah Terampil 7.3500 Org 99,000.00
Pembuangan Tanah 0.0790 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 205,050.00
dia. 500 mm

Galian Tanah Keras 0.2330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P248 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 500 MM
Sewa Alat bantu 2.4990 jam 93,500.00
Mandor 1.2500 Org 192,500.00
Kepala Tukang Pipa 1.2500 Org 165,000.00
Pekerja Setengah Terampil 6.2480 Org 99,000.00
Pembuangan Tanah 0.0790 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 205,050.00
dia. 500 mm

Galian Tanah Keras 0.2330 m³ 116,160.00


Urugan Tanah dipadatkan 0.1750 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P249 M' Harga per 1M' ….. Rp.
PADA JALAN BINA MARGA U/ HDPE
Ø 600 MM
Sewa Alat bantu 5.1450 jam 93,500.00
Mandor 2.5730 Org 192,500.00
Kepala Tukang Pipa 2.5730 Org 165,000.00
Pekerja Setengah Terampil 12.8630 Org 99,000.00
Pembuangan Tanah 0.1390 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 273,450.00
dia. 600 mm

Galian Tanah Keras 0.4080 m³ 116,160.00


Urugan Tanah dipadatkan 0.3060 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

PEMASANGAN PIPA DENGAN CARA


BORING HORIZONTAL DRILLING
P250 M' Harga per 1M' ….. Rp.
DILINGKUNGAN PERUMAHAN U/
HDPE Ø 600 MM
Sewa Alat bantu 4.3740 jam 93,500.00
Mandor 2.1870 Org 192,500.00
Kepala Tukang Pipa 2.1870 Org 165,000.00
Pekerja Setengah Terampil 10.9330 Org 99,000.00
Pembuangan Tanah 0.1390 m³ 66,563.75

Peletakan dan Penyambungan Pipa HDPE


1.0000 m¹ 273,450.00
dia. 600 mm

Galian Tanah Keras 0.4080 m³ 116,160.00


Urugan Tanah dipadatkan 0.3060 m³ 93,885.00
Jumlah
Keuntungan 10%
Total

P251 CM PEKERJAAN PENGELASAN Harga per 1 CM' ….. Rp.


Kawat las listrik 0.0400 kg 38,800.00
Bahan bakar solar 0.0300 lt 7,100.00
Pelumas (olie SAE 20-40) 0.0040 lt 56,400.00
Pekerja Terampil 0.0040 org 100,000.00
Tukang Las terlatih 0.0020 org 120,000.00
Pembantu Tukang Las 0.0020 org 70,000.00
Kepala tukang besi profil 0.0020 org 130,000.00
Mandor 0.0010 org 130,000.00
Alat bantu ( Mesin Las Listrik, Gurinda, Sikat 0.0100 set 85,000.00
Jumlah
Dibulatkan

P252 M' PENGELASAN PIPA STEEL Ø 50 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 50 mm 2.617 cm 4,010.00


Jumlah
Dibulatkan

P253 M' PENGELASAN PIPA STEEL Ø 75 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 75 mm 3.925 cm 4,010.00


Jumlah
Dibulatkan
P254 M' PENGELASAN PIPA STEEL Ø 100 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 100 mm 5.233 cm 4,010.00


Jumlah
Dibulatkan

P255 M' PENGELASAN PIPA STEEL Ø 150 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 150 mm 7.850 cm 4,010.00


Jumlah
Dibulatkan

P256 M' PENGELASAN PIPA STEEL Ø 200 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 200 mm 10.467 cm 4,010.00


Jumlah
Dibulatkan

P257 M' PENGELASAN PIPA STEEL Ø 250 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 250 mm 13.083 cm 4,010.00


Jumlah
Dibulatkan

P258 M' PENGELASAN PIPA STEEL Ø 300 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 300 mm 15.700 cm 4,010.00


Jumlah
Dibulatkan

P259 M' PENGELASAN PIPA STEEL Ø 400 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 400 mm 20.933 cm 4,010.00


Jumlah
Dibulatkan

P260 M' PENGELASAN PIPA STEEL Ø 500 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 500 mm 26.167 cm 4,010.00


Jumlah
Dibulatkan
P261 M' PENGELASAN PIPA STEEL Ø 600 MM Harga per 1M' ….. Rp.

Las Pipa Steel dia. 600 mm 31.400 cm 4,010.00


Jumlah
Dibulatkan

P262 M' PELETAKAN PIPA STEEL Ø 50 mm Harga per 1M' ….. Rp.
Mandor 0.0035 Org 130,000.00
Tukang pipa Terampil 0.0640 Org 120,000.00
Kepala Tukang Pipa 0.0350 Org 130,000.00
Pekerja Setengah Terampil 0.0640 Org 90,000.00
Alat bantu 0.0400 Set 85,000.00
Jumlah
Dibulatkan

P263 M' PELETAKAN PIPA STEEL Ø 75 mm Harga per 1M' ….. Rp.
Mandor 0.0050 Org 130,000.00
Tukang pipa Terampil 0.1077 Org 120,000.00
Kepala Tukang Pipa 0.0500 Org 130,000.00
Pekerja Setengah Terampil 0.0177 Org 90,000.00
Alat bantu 0.0600 Set 85,000.00
Jumlah
Dibulatkan

P264 M' PELETAKAN PIPA STEEL Ø 100 mm Harga per 1M' ….. Rp.
Mandor 0.0050 Org 130,000.00
Tukang pipa Terampil 0.1500 Org 120,000.00
Kepala Tukang Pipa 0.0500 Org 130,000.00
Pekerja Setengah Terampil 0.1500 Org 90,000.00
Alat bantu 0.0800 Set 85,000.00
Jumlah
Dibulatkan

P265 M' PELETAKAN PIPA STEEL Ø 150 mm Harga per 1M' ….. Rp.
Mandor 0.0060 Org 130,000.00
Tukang pipa Terampil 0.1875 Org 120,000.00
Kepala Tukang Pipa 0.0630 Org 130,000.00
Pekerja Setengah Terampil 0.1875 Org 90,000.00
Alat bantu 0.1200 Set 85,000.00
Jumlah
Dibulatkan

P266 M' PELETAKAN PIPA STEEL Ø 200 mm Harga per 1M' ….. Rp.
Mandor 0.0080 Org 130,000.00
Tukang pipa Terampil 0.2345 Org 120,000.00
Kepala Tukang Pipa 0.0780 Org 130,000.00
Pekerja Setengah Terampil 0.2345 Org 90,000.00
Alat bantu 0.1600 Set 85,000.00
Jumlah
Dibulatkan

P267 M' PELETAKAN PIPA STEEL Ø 250 mm Harga per 1M' ….. Rp.
Mandor 0.0084 Org 130,000.00
Tukang pipa Terampil 0.2521 Org 120,000.00
Kepala Tukang Pipa 0.0840 Org 130,000.00
Pekerja Setengah Terampil 0.2521 Org 90,000.00
Alat bantu 0.2000 Set 85,000.00
Jumlah
Dibulatkan

P268 M' PELETAKAN PIPA STEEL Ø 300 mm Harga per 1M' ….. Rp.
Mandor 0.0090 Org 130,000.00
Tukang pipa Terampil 0.2710 Org 120,000.00
Kepala Tukang Pipa 0.0903 Org 130,000.00
Pekerja Setengah Terampil 0.2710 Org 90,000.00
Alat bantu 0.2400 Set 85,000.00
Jumlah
Dibulatkan

P269 M' PELETAKAN PIPA STEEL Ø 400 mm Harga per 1M' ….. Rp.
Mandor 0.0104 Org 130,000.00
Tukang pipa Terampil 0.3132 Org 120,000.00
Kepala Tukang Pipa 0.1044 Org 130,000.00
Pekerja Setengah Terampil 0.3132 Org 90,000.00
Alat bantu 0.3200 Set 85,000.00
Jumlah
Dibulatkan

P270 M' PELETAKAN PIPA STEEL Ø 500 mm Harga per 1M' ….. Rp.
Mandor 0.1210 Org 130,000.00
Tukang pipa Terampil 0.3619 Org 120,000.00
Kepala Tukang Pipa 0.1206 Org 130,000.00
Pekerja Setengah Terampil 0.3619 Org 90,000.00
Alat bantu 0.4000 Set 85,000.00
Jumlah
Dibulatkan

P271 M' PELETAKAN PIPA STEEL Ø 600 mm Harga per 1M' ….. Rp.
Mandor 0.0243 Org 130,000.00
Tukang pipa Terampil 0.4878 Org 120,000.00
Kepala Tukang Pipa 0.2439 Org 130,000.00
Pekerja Setengah Terampil 0.4878 Org 90,000.00
Alat bantu 0.3658 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P272 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 25 mm

Mandor 0.0025 Org 130,000.00


Tukang pipa Terampil 0.0116 Org 120,000.00
Pekerja Setengah Terampil 0.0225 Org 90,000.00
Alat bantu 0.0033 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P273 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 40 mm

Mandor 0.0040 Org 130,000.00


Tukang pipa Terampil 0.0184 Org 120,000.00
Pekerja Setengah Terampil 0.0360 Org 90,000.00
Alat bantu 0.0052 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P274 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 50 mm

Mandor 0.0050 Org 130,000.00


Tukang pipa Terampil 0.0230 Org 120,000.00
Pekerja Setengah Terampil 0.0450 Org 90,000.00
Alat bantu 0.0066 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P275 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 75 mm

Mandor 0.0080 Org 130,000.00


Tukang pipa Terampil 0.0340 Org 120,000.00
Pekerja Setengah Terampil 0.0670 Org 90,000.00
Alat bantu 0.0098 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P276 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 100 mm

Mandor 0.0110 Org 130,000.00


Tukang pipa Terampil 0.0450 Org 120,000.00
Pekerja Setengah Terampil 0.0890 Org 90,000.00
Alat bantu 0.0131 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P277 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 150 mm

Mandor 0.0130 Org 130,000.00


Tukang pipa Terampil 0.0680 Org 120,000.00
Pekerja Setengah Terampil 0.1340 Org 90,000.00
Alat bantu 0.0192 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P278 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 200 mm

Mandor 0.0210 Org 130,000.00


Tukang pipa Terampil 0.0910 Org 120,000.00
Pekerja Setengah Terampil 0.1790 Org 90,000.00
Alat bantu 0.0262 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P279 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 250 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1100 Org 120,000.00
Pekerja Setengah Terampil 0.2200 Org 90,000.00
Alat bantu 0.0326 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P280 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 300 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1400 Org 120,000.00
Pekerja Setengah Terampil 0.2700 Org 90,000.00
Alat bantu 0.0396 Set 85,000.00
Jumlah
Dibulatkan
PELETAKAN DAN PENYAMBUNGAN
P281 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 400 mm

Mandor 0.0380 Org 130,000.00


Tukang pipa Terampil 0.2280 Org 120,000.00
Pekerja Setengah Terampil 0.4350 Org 90,000.00
Alat bantu 0.0650 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P282 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 500 mm

Mandor 0.0450 Org 130,000.00


Tukang pipa Terampil 0.3150 Org 120,000.00
Pekerja Setengah Terampil 0.6000 Org 90,000.00
Alat bantu 0.0900 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P283 M' Harga per 1M' ….. Rp.
PIPA PVC Ø 600 mm

Mandor 0.0675 Org 130,000.00


Tukang pipa Terampil 0.4725 Org 120,000.00
Pekerja Setengah Terampil 0.9000 Org 90,000.00
Alat bantu 0.1350 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P284 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 50 mm

Mandor 0.0050 Org 130,000.00


Tukang pipa Terampil 0.0230 Org 120,000.00
Pekerja Setengah Terampil 0.0450 Org 90,000.00
Welding HDPE 0.0600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.0600 Jam 50,000.00
Alat bantu 0.0066 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P285 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 75 mm

Mandor 0.0080 Org 130,000.00


Tukang pipa Terampil 0.0340 Org 120,000.00
Pekerja Setengah Terampil 0.0670 Org 90,000.00
Welding HDPE 0.0800 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.0800 Jam 50,000.00
Alat bantu 0.0098 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P286 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 100 mm

Mandor 0.0110 Org 130,000.00


Tukang pipa Terampil 0.0450 Org 120,000.00
Pekerja Setengah Terampil 0.0890 Org 90,000.00
Welding HDPE 0.1600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.1600 Jam 50,000.00
Alat bantu 0.0131 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P287 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 150 mm

Mandor 0.0130 Org 130,000.00


Tukang pipa Terampil 0.0680 Org 120,000.00
Pekerja Setengah Terampil 0.1340 Org 90,000.00
Welding HDPE 0.2600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.2600 Jam 50,000.00
Alat bantu 0.0192 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P288 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 200 mm

Mandor 0.0210 Org 130,000.00


Tukang pipa Terampil 0.0910 Org 120,000.00
Pekerja Setengah Terampil 0.1790 Org 90,000.00
Welding HDPE 0.3000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.3000 Jam 50,000.00
Alat bantu 0.0262 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P289 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 250 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1100 Org 120,000.00
Pekerja Setengah Terampil 0.2200 Org 90,000.00
Welding HDPE 0.3200 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.3200 Jam 50,000.00
Alat bantu 0.0326 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P290 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 300 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1400 Org 120,000.00
Pekerja Setengah Terampil 0.2700 Org 90,000.00
Welding HDPE 0.4400 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.4400 Jam 50,000.00
Alat bantu 0.0396 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P291 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 400 mm

Mandor 0.0380 Org 130,000.00


Tukang pipa Terampil 0.2280 Org 120,000.00
Pekerja Setengah Terampil 0.4350 Org 90,000.00
Welding HDPE 0.5000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.5000 Jam 50,000.00
Alat bantu 0.0650 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P292 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 500 mm

Mandor 0.0450 Org 130,000.00


Tukang pipa Terampil 0.3150 Org 120,000.00
Pekerja Setengah Terampil 0.6000 Org 90,000.00
Welding HDPE 0.5700 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.5700 Jam 50,000.00
Alat bantu 0.0900 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P293 M' Harga per 1M' ….. Rp.
PIPA HDPE Ø 600 mm

Mandor 0.0675 Org 130,000.00


Tukang pipa Terampil 0.4725 Org 120,000.00
Pekerja Setengah Terampil 0.9000 Org 90,000.00
Welding HDPE 0.6600 Jam 125,000.00
0.6600 Jam 50,000.00
Alat bantu 0.1350 Set 85,000.00
Jumlah
Dibulatkan

P294 M' PEK PENGETESAN PIPA Ø 25 MM Harga per 1M' ….. Rp.

Pompa Air dan Kompresor 0.0080 J/M 170,800.00


Air Bersih 0.0005 m³ 14,400.00
Bensin (Premium) 0.0046 ltr 9,000.00
Operator Kurang Terlatih 0.0002 Org 85,000.00
Pekerja setengah terampil 0.0006 Org 90,000.00
Mandor 0.0001 Org 130,000.00
Alat bantu 0.0018 SET 85,000.00
Jumlah
Dibulatkan

P295 M' PEK PENGETESAN PIPA Ø 40 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0080 J/M 170,800.00
Air Bersih 0.0014 m³ 14,400.00
Bensin (Premium) 0.0074 ltr 9,000.00
Operator Kurang Terlatih 0.0003 Org 85,000.00
Pekerja setengah terampil 0.0009 Org 90,000.00
Mandor 0.0001 Org 130,000.00
Alat bantu 0.0023 SET 85,000.00
Jumlah
Dibulatkan

P296 M' PEK PENGETESAN PIPA Ø 50 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0080 J/M 170,800.00
Air Bersih 0.0022 m³ 14,400.00
Bensin (Premium) 0.0092 ltr 9,000.00
Operator Kurang Terlatih 0.0004 Org 85,000.00
Pekerja setengah terampil 0.0011 Org 90,000.00
Mandor 0.0002 Org 130,000.00
Alat bantu 0.0028 SET 85,000.00
Jumlah
Dibulatkan

P297 M' PEK PENGETESAN PIPA Ø 75 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0120 J/M 170,800.00
Air Bersih 0.0049 m³ 14,400.00
Bensin (Premium) 0.0138 ltr 9,000.00
Operator Kurang Terlatih 0.0006 Org 85,000.00
Pekerja setengah terampil 0.0017 Org 90,000.00
Mandor 0.0003 Org 130,000.00
Alat bantu 0.0035 SET 85,000.00
Jumlah
Dibulatkan

P298 M' PEK PENGETESAN PIPA Ø 100 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0160 J/M 170,800.00
Air Bersih 0.0086 m³ 14,400.00
Bensin (Premium) 0.0184 ltr 9,000.00
Operator Kurang Terlatih 0.0007 Org 85,000.00
Pekerja setengah terampil 0.0022 Org 90,000.00
Mandor 0.0004 Org 130,000.00
Alat bantu 0.0047 SET 85,000.00
Jumlah
Dibulatkan

P299 M' PEK PENGETESAN PIPA Ø 150 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0160 J/M 170,800.00
Air Bersih 0.0194 m³ 14,400.00
Bensin (Premium) 0.0276 ltr 9,000.00
Operator Kurang Terlatih 0.0010 Org 85,000.00
Pekerja setengah terampil 0.0029 Org 90,000.00
Mandor 0.0005 Org 130,000.00
Alat bantu 0.0049 SET 85,000.00
Jumlah
Dibulatkan

P300 M' PEK PENGETESAN PIPA Ø 200 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0200 J/M 170,800.00
Air Bersih 0.0345 m³ 14,400.00
Bensin (Premium) 0.0368 ltr 9,000.00
Operator Kurang Terlatih 0.0013 Org 85,000.00
Pekerja setengah terampil 0.0037 Org 90,000.00
Mandor 0.0007 Org 130,000.00
Alat bantu 0.0063 SET 85,000.00
Jumlah
Dibulatkan

P301 M' PEK PENGETESAN PIPA Ø 250 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0240 J/M 170,800.00
Air Bersih 0.0540 m³ 14,400.00
Bensin (Premium) 0.0614 ltr 9,000.00
Operator Kurang Terlatih 0.0016 Org 85,000.00
Pekerja setengah terampil 0.0046 Org 90,000.00
Mandor 0.0008 Org 130,000.00
Alat bantu 0.0079 SET 85,000.00
Jumlah
Dibulatkan

P302 M' PEK PENGETESAN PIPA Ø300 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0320 J/M 170,800.00
Air Bersih 0.0777 m³ 14,400.00
Bensin (Premium) 0.0942 ltr 9,000.00
Operator Kurang Terlatih 0.0016 Org 85,000.00
Pekerja setengah terampil 0.0046 Org 90,000.00
Mandor 0.0008 Org 130,000.00
Alat bantu 0.0140 SET 85,000.00
Jumlah
Dibulatkan

P303 M' PEK PENGETESAN PIPA Ø 400 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0360 J/M 170,800.00
Air Bersih 0.1382 m³ 14,400.00
Bensin (Premium) 0.1256 ltr 9,000.00
Operator Kurang Terlatih 0.0022 Org 85,000.00
Pekerja setengah terampil 0.0062 Org 90,000.00
Mandor 0.0011 Org 130,000.00
Alat bantu 0.0187 SET 85,000.00
Jumlah
Dibulatkan

P304 M' PEK PENGETESAN PIPA Ø 500 MM Harga per 1M' ….. Rp.
Pompa Air dan Kompresor 0.0380 J/M 170,800.00
Air Bersih 0.1963 m³ 14,400.00
Bensin (Premium) 0.1258 ltr 9,000.00
Operator Kurang Terlatih 0.0024 Org 85,000.00
Pekerja setengah terampil 0.0072 Org 90,000.00
Mandor 0.0015 Org 130,000.00
Alat bantu 0.0198 SET 85,000.00
Jumlah
Dibulatkan

P305 BH PEMASANGAN GATE VALVE Ø 50 MM Harga per 1 BH ….. Rp.

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Terampil 0.1428 Org 100,000.00
Pekerja Setengah Terampil 0.1428 Org 90,000.00
Alat bantu 0.0714 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0134 m³ 883,700.00
Jumlah
Dibulatkan
P306 BH PEMASANGAN GATE VALVE Ø 75 MM Harga per 1 BH ….. Rp.

Mandor 0.0095 Org 130,000.00


Tukang pipa terampil 0.0952 Org 120,000.00
Pekerja Terampil 0.1904 Org 100,000.00
Pekerja Setengah Terampil 0.1904 Org 90,000.00
Alat bantu 0.0952 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0268 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN GATE VALVE Ø 100


P307 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0119 Org 130,000.00


Tukang pipa terampil 0.1190 Org 120,000.00
Pekerja Terampil 0.2380 Org 100,000.00
Pekerja Setengah Terampil 0.2380 Org 90,000.00
Alat bantu 0.1190 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0338 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN GATE VALVE Ø 150


P308 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0142 Org 130,000.00


Tukang pipa terampil 0.1428 Org 120,000.00
Pekerja Terampil 0.2857 Org 100,000.00
Pekerja Setengah Terampil 0.2857 Org 90,000.00
Alat bantu 0.1428 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0658 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN GATE VALVE Ø 200


P309 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0158 Org 130,000.00


Tukang pipa terampil 0.1587 Org 120,000.00
Pekerja Terampil 0.3174 Org 100,000.00
Pekerja Setengah Terampil 0.3174 Org 90,000.00
Alat bantu 0.1587 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.1012 m³ 883,700.00
Jumlah
Dibulatkan
P310 BH PEMASANGAN GATE VALVE Ø250 MM Harga per 1 BH ….. Rp.

Mandor 0.0178 Org 130,000.00


Tukang pipa terampil 0.1785 Org 120,000.00
Pekerja Terampil 0.3571 Org 100,000.00
Pekerja Setengah Terampil 0.3571 Org 90,000.00
Alat bantu 0.1785 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.1828 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN GATE VALVE Ø 300


P311 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0200 Org 130,000.00


Tukang pipa terampil 0.2000 Org 120,000.00
Pekerja Terampil 0.4000 Org 100,000.00
Pekerja Setengah Terampil 0.4000 Org 90,000.00
Alat bantu 0.2000 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.2186 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN GATE VALVE Ø 400


P312 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0250 Org 130,000.00


Tukang pipa terampil 0.2500 Org 120,000.00
Pekerja Terampil 0.5000 Org 100,000.00
Pekerja Setengah Terampil 0.5000 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.2927 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN GATE VALVE Ø 500


P313 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0333 Org 130,000.00


Tukang pipa terampil 0.3333 Org 120,000.00
Pekerja Terampil 0.6666 Org 100,000.00
Pekerja Setengah Terampil 0.6666 Org 90,000.00
Alat bantu 0.3333 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.3927 m³ 883,700.00
Jumlah
Dibulatkan
PEMASANGAN FLANGE SOCKET Ø 50
P314 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0036 Org 130,000.00


Tukang pipa terampil 0.0357 Org 120,000.00
Pekerja Terampil 0.0714 Org 100,000.00
Pekerja Setengah Terampil 0.0714 Org 90,000.00
Alat bantu 0.0357 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø 75


P315 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0048 Org 130,000.00


Tukang pipa terampil 0.0476 Org 120,000.00
Pekerja Terampil 0.0952 Org 100,000.00
Pekerja Setengah Terampil 0.0952 Org 90,000.00
Alat bantu 0.0476 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø


P316 BH Harga per 1 BH ….. Rp.
100 MM

Mandor 0.0060 Org 130,000.00


Tukang pipa terampil 0.0595 Org 120,000.00
Pekerja Terampil 0.1190 Org 100,000.00
Pekerja Setengah Terampil 0.1190 Org 90,000.00
Alat bantu 0.0595 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø


P317 BH Harga per 1 BH ….. Rp.
150 MM

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Terampil 0.1429 Org 100,000.00
Pekerja Setengah Terampil 0.1429 Org 90,000.00
Alat bantu 0.0714 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø


P318 BH Harga per 1 BH ….. Rp.
200 MM
Mandor 0.0079 Org 130,000.00
Tukang pipa terampil 0.0794 Org 120,000.00
Pekerja Terampil 0.1587 Org 100,000.00
Pekerja Setengah Terampil 0.1587 Org 90,000.00
Alat bantu 0.0794 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø


P319 BH Harga per 1 BH ….. Rp.
250 MM

Mandor 0.0089 Org 130,000.00


Tukang pipa terampil 0.0893 Org 120,000.00
Pekerja Terampil 0.1786 Org 100,000.00
Pekerja Setengah Terampil 0.1786 Org 90,000.00
Alat bantu 0.0893 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø


P320 BH Harga per 1 BH ….. Rp.
300 MM

Mandor 0.0100 Org 130,000.00


Tukang pipa terampil 0.1000 Org 120,000.00
Pekerja Terampil 0.2000 Org 100,000.00
Pekerja Setengah Terampil 0.2000 Org 90,000.00
Alat bantu 0.1000 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø


P321 BH Harga per 1 BH ….. Rp.
400 MM

Mandor 0.0125 Org 130,000.00


Tukang pipa terampil 0.1250 Org 120,000.00
Pekerja Terampil 0.2500 Org 100,000.00
Pekerja Setengah Terampil 0.2500 Org 90,000.00
Alat bantu 0.1250 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE SOCKET Ø


P322 BH Harga per 1 BH ….. Rp.
500 MM

Mandor 0.0167 Org 130,000.00


Tukang pipa terampil 0.1667 Org 120,000.00
Pekerja Terampil 0.3333 Org 100,000.00
Pekerja Setengah Terampil 0.3333 Org 90,000.00
Alat bantu 0.1667 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN STREET POOTH


P323 BH Harga per 1 BH ….. Rp.
SMALL

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Setengah Terampil 0.1428 Org 90,000.00
Pipa PVC AW dia. 100 mm 1.0000 M¹ 57,570.00
Alat bantu 0.0071 set 85,000.00
Beton Tumbuk 1:3:5 0.0205 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN STREET POOTH


P324 BH Harga per 1 BH ….. Rp.
MEDIUM

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Setengah Terampil 0.1428 Org 90,000.00
Pipa PVC AW dia. 100 mm 1.0000 M¹ 57,570.00
Alat bantu 0.0071 set 85,000.00
Beton Tumbuk 1:3:5 0.0287 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN STREET POOTH


P325 BH Harga per 1 BH ….. Rp.
LARGE

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Setengah Terampil 0.1428 Org 90,000.00
Pipa PVC AW dia. 100 mm 1.0000 M¹ 57,570.00
Alat bantu 0.0071 set 85,000.00
Beton Tumbuk 1:3:5 0.0456 m³ 883,700.00
Jumlah
Dibulatkan

PEMASANGAN GIBOULT JOINT Ø 50


P326 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0035 Org 130,000.00


Tukang pipa terampil 0.0357 Org 120,000.00
Pekerja Terampil 0.0714 Org 100,000.00
Pekerja Setengah Terampil 0.0714 Org 90,000.00
Alat bantu 0.0357 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN GIBOULT JOINT Ø75


P327 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0047 Org 130,000.00


Tukang pipa terampil 0.0476 Org 120,000.00
Pekerja Terampil 0.0952 Org 100,000.00
Pekerja Setengah Terampil 0.0952 Org 90,000.00
Alat bantu 0.0476 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN GIBOULT JOINT Ø 100


P328 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0059 Org 130,000.00


Tukang pipa terampil 0.0595 Org 120,000.00
Pekerja Terampil 0.1190 Org 100,000.00
Pekerja Setengah Terampil 0.1190 Org 90,000.00
Alat bantu 0.0595 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN GIBOULT JOINT Ø 150


P329 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Terampil 0.1428 Org 100,000.00
Pekerja Setengah Terampil 0.1428 Org 90,000.00
Alat bantu 0.0714 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN GIBOULT JOINT Ø200


P330 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0095 Org 130,000.00


Tukang pipa terampil 0.0952 Org 120,000.00
Pekerja Terampil 0.1904 Org 100,000.00
Pekerja Setengah Terampil 0.1904 Org 90,000.00
Alat bantu 0.0952 set 85,000.00
Jumlah
Dibulatkan
PEMASANGAN GIBOULT JOINT Ø 250
P331 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0119 Org 130,000.00


Tukang pipa terampil 0.1190 Org 120,000.00
Pekerja Terampil 0.2380 Org 100,000.00
Pekerja Setengah Terampil 0.2380 Org 90,000.00
Alat bantu 0.1190 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN GIBOULT JOINT Ø 300


P332 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0142 Org 130,000.00


Tukang pipa terampil 0.1428 Org 120,000.00
Pekerja Terampil 0.2857 Org 100,000.00
Pekerja Setengah Terampil 0.2857 Org 90,000.00
Alat bantu 0.1428 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN GIBOULT JOINT Ø 400


P333 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0181 Org 130,000.00


Tukang pipa terampil 0.1818 Org 120,000.00
Pekerja Terampil 0.3636 Org 100,000.00
Pekerja Setengah Terampil 0.3636 Org 90,000.00
Alat bantu 0.1818 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø 50


P334 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0023 Org 130,000.00


Tukang pipa terampil 0.0238 Org 120,000.00
Pekerja Terampil 0.0476 Org 100,000.00
Pekerja Setengah Terampil 0.0476 Org 90,000.00
Alat bantu 0.0238 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø 75


P335 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0034 Org 130,000.00


Tukang pipa terampil 0.0344 Org 120,000.00
Pekerja Terampil 0.0689 Org 100,000.00
Pekerja Setengah Terampil 0.0689 Org 90,000.00
Alat bantu 0.0344 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø 100


P336 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0047 Org 130,000.00


Tukang pipa terampil 0.0476 Org 120,000.00
Pekerja Terampil 0.0952 Org 100,000.00
Pekerja Setengah Terampil 0.0952 Org 90,000.00
Alat bantu 0.0476 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø 150


P337 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0059 Org 130,000.00


Tukang pipa terampil 0.0595 Org 120,000.00
Pekerja Terampil 0.1190 Org 100,000.00
Pekerja Setengah Terampil 0.1190 Org 90,000.00
Alat bantu 0.0595 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø 200


P338 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0076 Org 130,000.00


Tukang pipa terampil 0.0769 Org 120,000.00
Pekerja Terampil 0.1538 Org 100,000.00
Pekerja Setengah Terampil 0.1538 Org 90,000.00
Alat bantu 0.0769 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø 250


P339 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0084 Org 130,000.00


Tukang pipa terampil 0.0847 Org 120,000.00
Pekerja Terampil 0.1694 Org 100,000.00
Pekerja Setengah Terampil 0.1694 Org 90,000.00
Alat bantu 0.0847 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø300


P340 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0111 Org 130,000.00


Tukang pipa terampil 0.1111 Org 120,000.00
Pekerja Terampil 0.2222 Org 100,000.00
Pekerja Setengah Terampil 0.2222 Org 90,000.00
Alat bantu 0.1111 set 85,000.00
Jumlah
Dibulatkan

PEMASANGAN CLAMP SADLE Ø 400


P341 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0156 Org 130,000.00


Tukang pipa terampil 0.1562 Org 120,000.00
Pekerja Terampil 0.3125 Org 100,000.00
Pekerja Setengah Terampil 0.3125 Org 90,000.00
Alat bantu 0.1562 set 85,000.00
Jumlah
Dibulatkan

P342 BH PEMASANGAN FLANGE LAS Ø 50 MM Harga per 1 BH ….. Rp.

Mandor 0.0033 Org 130,000.00


Tukang pipa terampil 0.0333 Org 120,000.00
Pekerja Terampil 0.0666 Org 100,000.00
Pekerja Setengah Terampil 0.0666 Org 90,000.00
Alat bantu 0.0333 set 85,000.00
Pengelasan 15.7000 cm 4,010.00
Jumlah
Dibulatkan

P343 BH PEMASANGAN FLANGE LAS Ø 75 MM Harga per 1 BH ….. Rp.

Mandor 0.0040 Org 130,000.00


Tukang pipa terampil 0.0400 Org 120,000.00
Pekerja Terampil 0.0800 Org 100,000.00
Pekerja Setengah Terampil 0.0800 Org 90,000.00
Alat bantu 0.0400 set 85,000.00
Pengelasan 23.5500 cm 4,010.00
Jumlah
Dibulatkan
PEMASANGAN FLANGE LAS Ø 100
P344 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0047 Org 130,000.00


Tukang pipa terampil 0.0476 Org 120,000.00
Pekerja Terampil 0.0952 Org 100,000.00
Pekerja Setengah Terampil 0.0952 Org 90,000.00
Alat bantu 0.0476 set 85,000.00
Pengelasan 31.4000 cm 4,010.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE LAS Ø 150


P345 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Terampil 0.1428 Org 100,000.00
Pekerja Setengah Terampil 0.1428 Org 90,000.00
Alat bantu 0.0714 set 85,000.00
Pengelasan 47.1000 cm 4,010.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE LAS Ø 200


P346 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0095 Org 130,000.00


Tukang pipa terampil 0.0952 Org 120,000.00
Pekerja Terampil 0.1904 Org 100,000.00
Pekerja Setengah Terampil 0.1904 Org 90,000.00
Alat bantu 0.0952 set 85,000.00
Pengelasan 62.8000 cm 4,010.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE LAS Ø 250


P347 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0153 Org 130,000.00


Tukang pipa terampil 0.1538 Org 120,000.00
Pekerja Terampil 0.3076 Org 100,000.00
Pekerja Setengah Terampil 0.3076 Org 90,000.00
Alat bantu 0.1538 set 85,000.00
Pengelasan 78.5000 cm 4,010.00
Jumlah
Dibulatkan
PEMASANGAN FLANGE LAS Ø 300
P348 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0200 Org 130,000.00


Tukang pipa terampil 0.2000 Org 120,000.00
Pekerja Terampil 0.4000 Org 100,000.00
Pekerja Setengah Terampil 0.4000 Org 90,000.00
Alat bantu 0.2000 set 85,000.00
Pengelasan 94.2000 cm 4,010.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE LAS Ø 400


P349 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0250 Org 130,000.00


Tukang pipa terampil 0.2500 Org 120,000.00
Pekerja Terampil 0.5000 Org 100,000.00
Pekerja Setengah Terampil 0.5000 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Pengelasan 125.6000 cm 4,010.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE LAS Ø 500


P350 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0333 Org 130,000.00


Tukang pipa terampil 0.3333 Org 120,000.00
Pekerja Terampil 0.6666 Org 100,000.00
Pekerja Setengah Terampil 0.6666 Org 90,000.00
Alat bantu 0.3333 set 85,000.00
Pengelasan 157.0000 cm 4,010.00
Jumlah
Dibulatkan

PEMASANGAN FLANGE LAS Ø 600


P351 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0500 Org 130,000.00


Tukang pipa terampil 0.5000 Org 120,000.00
Pekerja Terampil 1.0000 Org 100,000.00
Pekerja Setengah Terampil 1.0000 Org 90,000.00
Alat bantu 0.5000 set 85,000.00
Pengelasan 188.4000 cm 4,010.00
Jumlah
Dibulatkan
P352 BH PAS. ALL FLANGE TEE Ø 50 MM Harga per 1 BH ….. Rp.

Mandor 0.0071 Org 130,000.00


Tukang pipa terampil 0.0714 Org 120,000.00
Pekerja Terampil 0.1428 Org 100,000.00
Pekerja Setengah Terampil 0.1428 Org 90,000.00
Alat bantu 0.0714 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0123 m³ 883,700.00
Jumlah
Dibulatkan

P353 BH PAS. ALL FLANGE TEE Ø 75 MM Harga per 1 BH ….. Rp.


Mandor 0.0095 Org 130,000.00
Tukang pipa terampil 0.0952 Org 120,000.00
Pekerja Terampil 0.1904 Org 100,000.00
Pekerja Setengah Terampil 0.1904 Org 90,000.00
Alat bantu 0.0952 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0182 m³ 883,700.00
Jumlah
Dibulatkan

P354 BH PAS. ALL FLANGE TEE Ø 100 MM Harga per 1 BH ….. Rp.
Mandor 0.0119 Org 130,000.00
Tukang pipa terampil 0.1190 Org 120,000.00
Pekerja Terampil 0.2380 Org 100,000.00
Pekerja Setengah Terampil 0.2380 Org 90,000.00
Alat bantu 0.1190 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0433 m³ 883,700.00
Jumlah
Dibulatkan

P355 BH PAS. ALL FLANGE TEE Ø 150 MM Harga per 1 BH ….. Rp.
Mandor 0.0142 Org 130,000.00
Tukang pipa terampil 0.1428 Org 120,000.00
Pekerja Terampil 0.2857 Org 100,000.00
Pekerja Setengah Terampil 0.2857 Org 90,000.00
Alat bantu 0.1428 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0883 m³ 883,700.00
Jumlah
Dibulatkan

P356 BH PAS. ALL FLANGE TEE Ø200 MM Harga per 1 BH ….. Rp.
Mandor 0.0158 Org 130,000.00
Tukang pipa terampil 0.1587 Org 120,000.00
Pekerja Terampil 0.3174 Org 100,000.00
Pekerja Setengah Terampil 0.3174 Org 90,000.00
Alat bantu 0.1587 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.1761 m³ 883,700.00
Jumlah
Dibulatkan

P357 BH PAS. ALL FLANGE TEE Ø 250 MM Harga per 1 BH ….. Rp.
Mandor 0.0178 Org 130,000.00
Tukang pipa terampil 0.1785 Org 120,000.00
Pekerja Terampil 0.3571 Org 100,000.00
Pekerja Setengah Terampil 0.3571 Org 90,000.00
Alat bantu 0.1785 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.3322 m³ 883,700.00
Jumlah
Dibulatkan

P358 BH PAS. ALL FLANGE TEE Ø 300 MM Harga per 1 BH ….. Rp.
Mandor 0.0200 Org 130,000.00
Tukang pipa terampil 0.2000 Org 120,000.00
Pekerja Terampil 0.4000 Org 100,000.00
Pekerja Setengah Terampil 0.4000 Org 90,000.00
Alat bantu 0.2000 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.5687 m³ 883,700.00
Jumlah
Dibulatkan

P359 BH PAS. ALL FLANGE TEE Ø400 MM Harga per 1 BH ….. Rp.
Mandor 0.0250 Org 130,000.00
Tukang pipa terampil 0.2500 Org 120,000.00
Pekerja Terampil 0.5000 Org 100,000.00
Pekerja Setengah Terampil 0.5000 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.7850 m³ 883,700.00
Jumlah
Dibulatkan

P360 BH PAS. ALL FLANGE TEE Ø500 MM Harga per 1 BH ….. Rp.
Mandor 0.0250 Org 130,000.00
Tukang pipa terampil 0.2500 Org 120,000.00
Pekerja Terampil 0.5000 Org 100,000.00
Pekerja Setengah Terampil 0.5000 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.9850 m³ 883,700.00
Jumlah
Dibulatkan
P361 BH PAS. ALL FLENGE BEND Ø 50 MM Harga per 1 BH ….. Rp.
Mandor 0.0076 Org 130,000.00
Tukang pipa terampil 0.0769 Org 120,000.00
Pekerja Terampil 0.1538 Org 100,000.00
Pekerja Setengah Terampil 0.1538 Org 90,000.00
Alat bantu 0.0769 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0123 m³ 883,700.00
Jumlah
Dibulatkan

P362 BH PAS. ALL FLENGE BEND Ø 75 MM Harga per 1 BH ….. Rp.


Mandor 0.0100 Org 130,000.00
Tukang pipa terampil 0.1000 Org 120,000.00
Pekerja Terampil 0.2000 Org 100,000.00
Pekerja Setengah Terampil 0.2000 Org 90,000.00
Alat bantu 0.1000 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0182 m³ 883,700.00
Jumlah
Dibulatkan

P363 BH PAS. ALL FLENGE BEND Ø 100 MM Harga per 1 BH ….. Rp.
Mandor 0.0125 Org 130,000.00
Tukang pipa terampil 0.1250 Org 120,000.00
Pekerja Terampil 0.2500 Org 100,000.00
Pekerja Setengah Terampil 0.2500 Org 90,000.00
Alat bantu 0.1250 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0433 m³ 883,700.00
Jumlah
Dibulatkan

P364 BH PAS. ALL FLENGE BEND Ø 150 MM Harga per 1 BH ….. Rp.
Mandor 0.0142 Org 130,000.00
Tukang pipa terampil 0.1428 Org 120,000.00
Pekerja Terampil 0.2857 Org 100,000.00
Pekerja Setengah Terampil 0.2857 Org 90,000.00
Alat bantu 0.1428 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0883 m³ 883,700.00
Jumlah
Dibulatkan

P365 BH PAS. ALL FLENGE BEND Ø 200 MM Harga per 1 BH ….. Rp.
Mandor 0.0166 Org 130,000.00
Tukang pipa terampil 0.1666 Org 120,000.00
Pekerja Terampil 0.3333 Org 100,000.00
Pekerja Setengah Terampil 0.3333 Org 90,000.00
Alat bantu 0.1666 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.1761 m³ 883,700.00
Jumlah
Dibulatkan

P366 BH PAS. ALL FLENGE BEND Ø 250 MM Harga per 1 BH ….. Rp.
Mandor 0.0222 Org 130,000.00
Tukang pipa terampil 0.2222 Org 120,000.00
Pekerja Terampil 0.4444 Org 100,000.00
Pekerja Setengah Terampil 0.4444 Org 90,000.00
Alat bantu 0.2222 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.3322 m³ 883,700.00
Jumlah
Dibulatkan

P367 BH PAS. ALL FLENGE BEND Ø 300 MM Harga per 1 BH ….. Rp.
Mandor 0.0250 Org 130,000.00
Tukang pipa terampil 0.2500 Org 120,000.00
Pekerja Terampil 0.5000 Org 100,000.00
Pekerja Setengah Terampil 0.5000 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.5687 m³ 883,700.00
Jumlah
Dibulatkan

P368 BH PAS. ALL FLENGE BEND Ø 400 MM Harga per 1 BH ….. Rp.
Mandor 0.0285 Org 130,000.00
Tukang pipa terampil 0.2857 Org 120,000.00
Pekerja Terampil 0.5714 Org 100,000.00
Pekerja Setengah Terampil 0.5714 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.7850 m³ 883,700.00
Jumlah
Dibulatkan

P369 BH PAS. ALL FLENGE BEND Ø 500 MM Harga per 1 BH ….. Rp.
Mandor 0.0285 Org 130,000.00
Tukang pipa terampil 0.2857 Org 120,000.00
Pekerja Terampil 0.5714 Org 100,000.00
Pekerja Setengah Terampil 0.5714 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.9850 m³ 883,700.00
Jumlah
Dibulatkan

P370 BH PAS. ALL FLANGE REDUCER Ø 50 MM Harga per 1 BH ….. Rp.


Mandor 0.0074 Org 130,000.00
Tukang pipa terampil 0.0740 Org 120,000.00
Pekerja Terampil 0.1481 Org 100,000.00
Pekerja Setengah Terampil 0.1481 Org 90,000.00
Alat bantu 0.0740 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0123 m³ 883,700.00
Jumlah
Dibulatkan

P371 BH PAS. ALL FLANGE REDUCER Ø 75 MM Harga per 1 BH ….. Rp.

Mandor 0.0090 Org 130,000.00


Tukang pipa terampil 0.0909 Org 120,000.00
Pekerja Terampil 0.1818 Org 100,000.00
Pekerja Setengah Terampil 0.1818 Org 90,000.00
Alat bantu 0.0909 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0182 m³ 883,700.00
Jumlah
Dibulatkan

PAS. ALL FLANGE REDUCER Ø 100


P372 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0111 Org 130,000.00


Tukang pipa terampil 0.1111 Org 120,000.00
Pekerja Terampil 0.2222 Org 100,000.00
Pekerja Setengah Terampil 0.2222 Org 90,000.00
Alat bantu 0.1111 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0433 m³ 883,700.00
Jumlah
Dibulatkan

PAS. ALL FLANGE REDUCER Ø 150


P373 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0125 Org 130,000.00


Tukang pipa terampil 0.1250 Org 120,000.00
Pekerja Terampil 0.2500 Org 100,000.00
Pekerja Setengah Terampil 0.2500 Org 90,000.00
Alat bantu 0.1250 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.0883 m³ 883,700.00
Jumlah
Dibulatkan

P374 BH PAS. ALL FLANGE REDUCER Ø200 MM Harga per 1 BH ….. Rp.
Mandor 0.0142 Org 130,000.00
Tukang pipa terampil 0.1428 Org 120,000.00
Pekerja Terampil 0.2857 Org 100,000.00
Pekerja Setengah Terampil 0.2857 Org 90,000.00
Alat bantu 0.1428 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.1761 m³ 883,700.00
Jumlah
Dibulatkan

PAS. ALL FLANGE REDUCER Ø 250


P375 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0166 Org 130,000.00


Tukang pipa terampil 0.1666 Org 120,000.00
Pekerja Terampil 0.3333 Org 100,000.00
Pekerja Setengah Terampil 0.3333 Org 90,000.00
Alat bantu 0.1666 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.3322 m³ 883,700.00
Jumlah
Dibulatkan

PAS. ALL FLANGE REDUCER Ø 300


P376 BH Harga per 1 BH ….. Rp.
MM

Mandor 0.0200 Org 130,000.00


Tukang pipa terampil 0.2000 Org 120,000.00
Pekerja Terampil 0.4000 Org 100,000.00
Pekerja Setengah Terampil 0.4000 Org 90,000.00
Alat bantu 0.2000 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.5687 m³ 883,700.00
Jumlah
Dibulatkan

PAS. ALL FLANGE REDUCER Ø 400


P377 M' Harga per 1 BH ….. Rp.
MM

Mandor 0.0250 Org 130,000.00


Tukang pipa terampil 0.2500 Org 120,000.00
Pekerja Terampil 0.5000 Org 100,000.00
Pekerja Setengah Terampil 0.5000 Org 90,000.00
Alat bantu 0.2500 set 85,000.00
Beton Tumbuk 1:3:5 (A022) 0.9850 m³ 883,700.00
Jumlah
Dibulatkan

PEKERJAAN PEMASANGAN THRUST BLOCK TEE PVC


P378 BH Thrust Block Tee Ø 25 mm (Beton Tumbuk a 0.0100 m³/bh 883,700.00
P379 BH Thrust Block Tee Ø 40 mm (Beton Tumbuk a 0.0100 m³/bh 883,700.00
P380 BH Thrust Block Tee Ø 50 mm (Beton Tumbuk a 0.0100 m³/bh 883,700.00
P381 BH Thrust Block Tee Ø 75 mm (Beton Tumbuk a 0.0200 m³/bh 883,700.00
P382 BH Thrust Block Tee Ø 100 mm (Beton Tumbuk 0.0400 m³/bh 883,700.00
P383 BH Thrust Block Tee Ø 150 mm (Beton Tumbuk 0.0800 m³/bh 883,700.00
P384 BH Thrust Block Tee Ø 200 mm (Beton Tumbuk 0.1800 m³/bh 883,700.00
P385 BH Thrust Block Tee Ø 250 mm (Beton Tumbuk 0.3300 m³/bh 883,700.00
P386 BH Thrust Block Tee Ø 300 mm (Beton Tumbuk 0.5700 m³/bh 883,700.00

PEKERJAAN PEMASANGAN THRUST BLOCK BEND 90° PVC


P387 BH Thrust Block Bend 90° Ø 25 mm (Beton Tum 0.0200 m³/bh 883,700.00
P388 BH Thrust Block Bend 90° Ø 40 mm (Beton Tum 0.0200 m³/bh 883,700.00
P389 BH Thrust Block Bend 90° Ø 50 mm (Beton Tum 0.0200 m³/bh 883,700.00
P390 BH Thrust Block Bend 90° Ø 75 mm (Beton Tum 0.0300 m³/bh 883,700.00
P391 BH Thrust Block Bend 90° Ø 100 mm (Beton Tu 0.0600 m³/bh 883,700.00
P392 BH Thrust Block Bend 90° Ø 150 mm (Beton Tu 0.1300 m³/bh 883,700.00
P393 BH Thrust Block Bend 90° Ø 200 mm (Beton Tu 0.2600 m³/bh 883,700.00
P394 BH Thrust Block Bend 90° Ø 250 mm (Beton Tu 0.4900 m³/bh 883,700.00
P395 BH Thrust Block Bend 90° Ø 300 mm (Beton Tu 0.9300 m³/bh 883,700.00

PEKERJAAN PEMASANGAN THRUST BLOCK BEND 45° PVC


P396 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 25 0.0100 m³/bh 883,700.00
P397 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 40 0.0100 m³/bh 883,700.00
P398 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 50 0.0100 m³/bh 883,700.00
P399 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 75 0.0100 m³/bh 883,700.00
P400 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 10 0.0300 m³/bh 883,700.00
P401 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 15 0.0600 m³/bh 883,700.00
P402 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 20 0.1300 m³/bh 883,700.00
P403 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 25 0.2400 m³/bh 883,700.00
P404 BH Thrust Block Bend 45°, 22,5°, 11.25° Ø 30 0.4200 m³/bh 883,700.00

PEKERJAAN PEMASANGAN THRUST BLOCK REDUCER PVC


P405 BH Thrust Block Reducer Ø 25 mm (Beton Tumb 0.0100 m³/bh 883,700.00
P406 BH Thrust Block Reducer Ø 40 mm (Beton Tumb 0.0100 m³/bh 883,700.00
P407 BH Thrust Block Reducer Ø 50 mm (Beton Tumb 0.0100 m³/bh 883,700.00
P408 BH Thrust Block Reducer Ø 75 mm (Beton Tumb 0.0200 m³/bh 883,700.00
P409 BH Thrust Block Reducer Ø 100 mm (Beton Tum 0.0400 m³/bh 883,700.00
P410 BH Thrust Block Reducer Ø 150 mm (Beton Tum 0.0900 m³/bh 883,700.00
P411 BH Thrust Block Reducer Ø 200 mm (Beton Tum 0.1800 m³/bh 883,700.00
P412 BH Thrust Block Reducer Ø 250 mm (Beton Tum 0.3300 m³/bh 883,700.00
P413 BH Thrust Block Reducer Ø 300 mm (Beton Tum 0.5700 m³/bh 883,700.00

PEKERJAAN PEMASANGAN THRUST BLOCK DOP PVC


P414 BH Thrust Block Dop Ø 25 mm (Beton Tumbuk a 0.0100 m³/bh 883,700.00
P415 BH Thrust Block Dop Ø 40 mm (Beton Tumbuk a 0.0100 m³/bh 883,700.00
P416 BH Thrust Block Dop Ø 50 mm (Beton Tumbuk a 0.0100 m³/bh 883,700.00
P417 BH Thrust Block Dop Ø 75 mm (Beton Tumbuk a 0.0200 m³/bh 883,700.00
P418 BH Thrust Block Dop Ø 100 mm (Beton Tumbuk 0.0400 m³/bh 883,700.00
P419 BH Thrust Block Dop Ø 150 mm (Beton Tumbuk 0.0900 m³/bh 883,700.00
P420 BH Thrust Block Dop Ø 200 mm (Beton Tumbuk 0.1800 m³/bh 883,700.00
P421 BH Thrust Block Dop Ø 250 mm (Beton Tumbuk 0.3300 m³/bh 883,700.00
P422 BH Thrust Block Dop Ø 300 mm (Beton Tumbuk 0.5700 m³/bh 883,700.00

PELETAKAN DAN PENYAMBUNGAN


P423 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 50 mm

Mandor 0.0050 Org 130,000.00


Tukang pipa Terampil 0.0230 Org 120,000.00
Pekerja Setengah Terampil 0.0450 Org 90,000.00
Welding HDPE 0.1760 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.1760 Jam 50,000.00
Alat bantu 0.0066 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P424 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 75 mm

Mandor 0.0080 Org 130,000.00


Tukang pipa Terampil 0.0340 Org 120,000.00
Pekerja Setengah Terampil 0.0670 Org 90,000.00
Welding HDPE 0.2850 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.2850 Jam 50,000.00
Alat bantu 0.0098 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P425 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 100 mm

Mandor 0.0110 Org 130,000.00


Tukang pipa Terampil 0.0450 Org 120,000.00
Pekerja Setengah Terampil 0.0890 Org 90,000.00
Welding HDPE 0.4000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.4000 Jam 50,000.00
Alat bantu 0.0131 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P426 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 150 mm

Mandor 0.0130 Org 130,000.00


Tukang pipa Terampil 0.0680 Org 120,000.00
Pekerja Setengah Terampil 0.1340 Org 90,000.00
Welding HDPE 0.7800 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.7800 Jam 50,000.00
Alat bantu 0.0192 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P427 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 200 mm

Mandor 0.0210 Org 130,000.00


Tukang pipa Terampil 0.0910 Org 120,000.00
Pekerja Setengah Terampil 0.1790 Org 90,000.00
Welding HDPE 0.9000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.9000 Jam 50,000.00
Alat bantu 0.0262 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P428 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 250 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1100 Org 120,000.00
Pekerja Setengah Terampil 0.2200 Org 90,000.00
Welding HDPE 0.9600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.9600 Jam 50,000.00
Alat bantu 0.0326 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P429 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 300 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1400 Org 120,000.00
Pekerja Setengah Terampil 0.2700 Org 90,000.00
Welding HDPE 1.3200 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 1.3200 Jam 50,000.00
Alat bantu 0.0396 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P430 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 400 mm

Mandor 0.0380 Org 130,000.00


Tukang pipa Terampil 0.2280 Org 120,000.00
Pekerja Setengah Terampil 0.4350 Org 90,000.00
Welding HDPE 1.5000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 1.5000 Jam 50,000.00
Alat bantu 0.0650 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P431 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 500 mm

Mandor 0.0450 Org 130,000.00


Tukang pipa Terampil 0.3150 Org 120,000.00
Pekerja Setengah Terampil 0.6000 Org 90,000.00
Welding HDPE 1.7100 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 1.7100 Jam 50,000.00
Alat bantu 0.0900 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P432 M' Harga per 1M' ….. Rp.
TEE HDPE Ø 600 mm

Mandor 0.0675 Org 130,000.00


Tukang pipa Terampil 0.4725 Org 120,000.00
Pekerja Setengah Terampil 0.9000 Org 90,000.00
Welding HDPE 1.9800 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 1.9800 Jam 50,000.00
Alat bantu 0.1350 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P433 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 50 mm

Mandor 0.0050 Org 130,000.00


Tukang pipa Terampil 0.0230 Org 120,000.00
Pekerja Setengah Terampil 0.0450 Org 90,000.00
Welding HDPE 0.1320 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.1320 Jam 50,000.00
Alat bantu 0.0066 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P434 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 75 mm

Mandor 0.0080 Org 130,000.00


Tukang pipa Terampil 0.0340 Org 120,000.00
Pekerja Setengah Terampil 0.0670 Org 90,000.00
Welding HDPE 0.2100 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.2100 Jam 50,000.00
Alat bantu 0.0098 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P435 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 100 mm

Mandor 0.0110 Org 130,000.00


Tukang pipa Terampil 0.0450 Org 120,000.00
Pekerja Setengah Terampil 0.0890 Org 90,000.00
Welding HDPE 0.3200 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.3200 Jam 50,000.00
Alat bantu 0.0131 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P436 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 150 mm

Mandor 0.0130 Org 130,000.00


Tukang pipa Terampil 0.0680 Org 120,000.00
Pekerja Setengah Terampil 0.1340 Org 90,000.00
Welding HDPE 0.5200 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.5200 Jam 50,000.00
Alat bantu 0.0192 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P437 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 200 mm

Mandor 0.0210 Org 130,000.00


Tukang pipa Terampil 0.0910 Org 120,000.00
Pekerja Setengah Terampil 0.1790 Org 90,000.00
Welding HDPE 0.6000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.6000 Jam 50,000.00
Alat bantu 0.0262 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P438 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 250 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1100 Org 120,000.00
Pekerja Setengah Terampil 0.2200 Org 90,000.00
Welding HDPE 0.6400 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.6400 Jam 50,000.00
Alat bantu 0.0326 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P439 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 300 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1400 Org 120,000.00
Pekerja Setengah Terampil 0.2700 Org 90,000.00
Welding HDPE 0.8800 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.8800 Jam 50,000.00
Alat bantu 0.0396 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P440 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 400 mm

Mandor 0.0380 Org 130,000.00


Tukang pipa Terampil 0.2280 Org 120,000.00
Pekerja Setengah Terampil 0.4350 Org 90,000.00
Welding HDPE 1.0000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 1.0000 Jam 50,000.00
Alat bantu 0.0650 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P441 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 500 mm

Mandor 0.0450 Org 130,000.00


Tukang pipa Terampil 0.3150 Org 120,000.00
Pekerja Setengah Terampil 0.6000 Org 90,000.00
Welding HDPE 1.1400 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 1.1400 Jam 50,000.00
Alat bantu 0.0900 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P442 M' Harga per 1M' ….. Rp.
BEND HDPE Ø 600 mm

Mandor 0.0675 Org 130,000.00


Tukang pipa Terampil 0.4725 Org 120,000.00
Pekerja Setengah Terampil 0.9000 Org 90,000.00
Welding HDPE 1.3200 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 1.3200 Jam 50,000.00
Alat bantu 0.1350 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P443 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 50 mm

Mandor 0.0050 Org 130,000.00


Tukang pipa Terampil 0.0230 Org 120,000.00
Pekerja Setengah Terampil 0.0450 Org 90,000.00
Welding HDPE 0.1056 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.1056 Jam 50,000.00
Alat bantu 0.0066 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P444 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 75 mm

Mandor 0.0080 Org 130,000.00


Tukang pipa Terampil 0.0340 Org 120,000.00
Pekerja Setengah Terampil 0.0670 Org 90,000.00
Welding HDPE 0.1710 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.1710 Jam 50,000.00
Alat bantu 0.0098 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P445 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 100 mm

Mandor 0.0110 Org 130,000.00


Tukang pipa Terampil 0.0450 Org 120,000.00
Pekerja Setengah Terampil 0.0890 Org 90,000.00
Welding HDPE 0.2400 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.2400 Jam 50,000.00
Alat bantu 0.0131 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P446 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 150 mm

Mandor 0.0130 Org 130,000.00


Tukang pipa Terampil 0.0680 Org 120,000.00
Pekerja Setengah Terampil 0.1340 Org 90,000.00
Welding HDPE 0.3900 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.3900 Jam 50,000.00
Alat bantu 0.0192 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P447 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 200 mm

Mandor 0.0210 Org 130,000.00


Tukang pipa Terampil 0.0910 Org 120,000.00
Pekerja Setengah Terampil 0.1790 Org 90,000.00
Welding HDPE 0.4500 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.4500 Jam 50,000.00
Alat bantu 0.0262 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P448 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 250 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1100 Org 120,000.00
Pekerja Setengah Terampil 0.2200 Org 90,000.00
Welding HDPE 0.4800 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.4800 Jam 50,000.00
Alat bantu 0.0326 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P449 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 300 mm

Mandor 0.0300 Org 130,000.00


Tukang pipa Terampil 0.1400 Org 120,000.00
Pekerja Setengah Terampil 0.2700 Org 90,000.00
Welding HDPE 0.6600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.6600 Jam 50,000.00
Alat bantu 0.0396 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P450 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 400 mm

Mandor 0.0380 Org 130,000.00


Tukang pipa Terampil 0.2280 Org 120,000.00
Pekerja Setengah Terampil 0.4350 Org 90,000.00
Welding HDPE 0.7500 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.7500 Jam 50,000.00
Alat bantu 0.0650 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P451 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 500 mm
Mandor 0.0450 Org 130,000.00
Tukang pipa Terampil 0.3150 Org 120,000.00
Pekerja Setengah Terampil 0.6000 Org 90,000.00
Welding HDPE 0.8550 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.8550 Jam 50,000.00
Alat bantu 0.0900 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P452 M' Harga per 1M' ….. Rp.
REDUCER HDPE Ø 600 mm
Mandor 0.0675 Org 130,000.00
Tukang pipa Terampil 0.4725 Org 120,000.00
Pekerja Setengah Terampil 0.9000 Org 90,000.00
Welding HDPE 0.9900 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.9900 Jam 50,000.00
Alat bantu 0.1350 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P453 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 50 mm
Mandor 0.0050 Org 130,000.00
Tukang pipa Terampil 0.0230 Org 120,000.00
Pekerja Setengah Terampil 0.0450 Org 90,000.00
Welding HDPE 0.0880 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.0880 Jam 50,000.00
Alat bantu 0.0066 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P454 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 75 mm
Mandor 0.0080 Org 130,000.00
Tukang pipa Terampil 0.0340 Org 120,000.00
Pekerja Setengah Terampil 0.0670 Org 90,000.00
Welding HDPE 0.1140 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.1140 Jam 50,000.00
Alat bantu 0.0098 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P455 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 100 mm
Mandor 0.0110 Org 130,000.00
Tukang pipa Terampil 0.0450 Org 120,000.00
Pekerja Setengah Terampil 0.0890 Org 90,000.00
Welding HDPE 0.1600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.1600 Jam 50,000.00
Alat bantu 0.0131 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P456 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 150 mm
Mandor 0.0130 Org 130,000.00
Tukang pipa Terampil 0.0680 Org 120,000.00
Pekerja Setengah Terampil 0.1340 Org 90,000.00
Welding HDPE 0.2600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.2600 Jam 50,000.00
Alat bantu 0.0192 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P457 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 200 mm
Mandor 0.0210 Org 130,000.00
Tukang pipa Terampil 0.0910 Org 120,000.00
Pekerja Setengah Terampil 0.1790 Org 90,000.00
Welding HDPE 0.3000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.3000 Jam 50,000.00
Alat bantu 0.0262 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P458 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 250 mm
Mandor 0.0300 Org 130,000.00
Tukang pipa Terampil 0.1100 Org 120,000.00
Pekerja Setengah Terampil 0.2200 Org 90,000.00
Welding HDPE 0.3200 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.3200 Jam 50,000.00
Alat bantu 0.0326 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P459 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 300 mm
Mandor 0.0300 Org 130,000.00
Tukang pipa Terampil 0.1400 Org 120,000.00
Pekerja Setengah Terampil 0.2700 Org 90,000.00
Welding HDPE 0.4400 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.4400 Jam 50,000.00
Alat bantu 0.0396 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P460 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 400 mm
Mandor 0.0380 Org 130,000.00
Tukang pipa Terampil 0.2280 Org 120,000.00
Pekerja Setengah Terampil 0.4350 Org 90,000.00
Welding HDPE 0.5000 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.5000 Jam 50,000.00
Alat bantu 0.0650 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P461 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 500 mm
Mandor 0.0450 Org 130,000.00
Tukang pipa Terampil 0.3150 Org 120,000.00
Pekerja Setengah Terampil 0.6000 Org 90,000.00
Welding HDPE 0.5700 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.5700 Jam 50,000.00
Alat bantu 0.0900 Set 85,000.00
Jumlah
Dibulatkan

PELETAKAN DAN PENYAMBUNGAN


P462 M' Harga per 1M' ….. Rp.
STUBE END HDPE Ø 600 mm
Mandor 0.0675 Org 130,000.00
Tukang pipa Terampil 0.4725 Org 120,000.00
Pekerja Setengah Terampil 0.9000 Org 90,000.00
Welding HDPE 0.6600 Jam 125,000.00
Genset Kap. 7000 - 12000 Watt 0.6600 Jam 50,000.00
Alat bantu 0.1350 Set 85,000.00
Jumlah
Dibulatkan
P463 UNITPEMASANGAN SAMBUNGAN RUMAH Harga per Unit ….. Rp.
Pekerja 0.427 h/o 80,000.00
Mandor 0.018 h/o 130,000.00
Tukang Pipa 0.250 h/o 120,000.00
Pekerja setengah terampil 0.215 h/o 90,000.00
Kepala Tukang Pipa 0.040 h/o 130,000.00
Tukang Kayu setengah terampil 0.004 h/o 90,000.00
Pasir Urug 0.086 m³ 261,000.00
Cement Portland 3.087 kg 1,500.00
Pasir beton 0.019 m3 273,000.00
Batu pecah 2/3 0.026 m3 296,000.00
Papan Klas III 0.004 m3 2,222,300.00
Paku 0.050 kg 16,900.00
Jumlah
Dibulatkan
SA BIAYA KONSTRUKSI
ERJAAN AIR BERSIH

JUMLAH HARGA
SAT. PEKERJAAN
Rp.
7
46,716.57

4,020.00

11,350.63
7,510.80
16,260.00
3,328.19
42,469.61
4,246.96
46,716.57

58,601.76

6,410.00

13,970.00
9,388.50
19,512.00
3,993.83
53,274.33
5,327.43
58,601.76

72,031.26

8,020.00

19,208.75
14,082.75
19,512.00
4,659.46
65,482.96
6,548.30
72,031.26

95,200.16
11,980.00

24,447.50
18,777.00
26,016.00
5,325.10
86,545.60
8,654.56
95,200.16

114,502.33

15,950.00

29,686.25
22,532.40
29,268.00
6,656.38
104,093.03
10,409.30
114,502.33

151,029.02

23,540.00
39,290.63
30,043.20
35,772.00
8,653.29
137,299.11
13,729.91
151,029.02

180,518.03

31,980.00

45,402.50
33,798.60
42,276.00
10,650.20
164,107.30
16,410.73
180,518.03

212,867.85
39,670.00
53,260.63
38,492.85
48,780.00
13,312.75
193,516.23
19,351.62
212,867.85

258,549.98

48,360.00

63,738.13
43,187.10
61,788.00
17,972.21
235,045.44
23,504.54
258,549.98

337,093.88
76,980.00
78,581.25
50,697.90
76,226.88
23,962.95
306,448.98
30,644.90
337,093.88

439,374.77

105,300.00

100,584.00
59,485.54
99,555.43
34,506.65
399,431.61
39,943.16
439,374.77

562,575.53
157,950.00
121,713.63
67,747.42
119,263.80
44,757.47
511,432.30
51,143.23
562,575.53

50,841.77

4,020.00

15,100.80
7,510.80
16,260.00
3,328.19
46,219.79
4,621.98
50,841.77

63,678.92

6,410.00

18,585.60
9,388.50
19,512.00
3,993.83
57,889.93
5,788.99
63,678.92

79,012.35

8,020.00

25,555.20
14,082.75
19,512.00
4,659.46
71,829.41
7,182.94
79,012.35
104,085.19

11,980.00

32,524.80
18,777.00
26,016.00
5,325.10
94,622.90
9,462.29
104,085.19

125,291.29

15,950.00

39,494.40
22,532.40
29,268.00
6,656.38
113,901.18
11,390.12
125,291.29

165,308.54

23,540.00

52,272.00
30,043.20
35,772.00
8,653.29
150,280.49
15,028.05
165,308.54

197,018.80

31,980.00

60,403.20
33,798.60
42,276.00
10,650.20
179,108.00
17,910.80
197,018.80

232,224.52

39,670.00

70,857.60
38,492.85
48,780.00
13,312.75
211,113.20
21,111.32
232,224.52

281,714.52

48,360.00

84,796.80
43,187.10
61,788.00
17,972.21
256,104.11
25,610.41
281,714.52

365,652.90

76,980.00

104,544.00
50,697.90
76,226.88
23,962.95
332,411.73
33,241.17
365,652.90
475,930.32

105,300.00

133,816.32
59,485.54
99,555.43
34,506.65
432,663.93
43,266.39
475,930.32

606,810.29

157,950.00

161,927.04
67,747.42
119,263.80
44,757.47
551,645.72
55,164.57
606,810.29

59,477.54

4,020.00

22,951.50
7,510.80
16,260.00
3,328.19
54,070.49
5,407.05
59,477.54

74,307.56

6,410.00

28,248.00
9,388.50
19,512.00
3,993.83
67,552.33
6,755.23
74,307.56

93,626.73

8,020.00

38,841.00
14,082.75
19,512.00
4,659.46
85,115.21
8,511.52
93,626.73

122,685.31

11,980.00

49,434.00
18,777.00
26,016.00
5,325.10
111,532.10
11,153.21
122,685.31

147,877.15

15,950.00

60,027.00
22,532.40
29,268.00
6,656.38
134,433.78
13,443.38
147,877.15

195,201.59
23,540.00

79,447.50
30,043.20
35,772.00
8,653.29
177,455.99
17,745.60
195,201.59

231,561.88

31,980.00

91,806.00
33,798.60
42,276.00
10,650.20
210,510.80
21,051.08
231,561.88

272,746.21

39,670.00

107,695.50
38,492.85
48,780.00
13,312.75
247,951.10
24,795.11
272,746.21

330,207.69

48,360.00

128,881.50
43,187.10
61,788.00
17,972.21
300,188.81
30,018.88
330,207.69

425,439.00

76,980.00

158,895.00
50,697.90
76,226.88
23,962.95
386,762.73
38,676.27
425,439.00

552,456.53

105,300.00

203,385.60
59,485.54
99,555.43
34,506.65
502,233.21
50,223.32
552,456.53

699,412.32

157,950.00

246,110.70
67,747.42
119,263.80
44,757.47
635,829.38
63,582.94
699,412.32

59,477.54

4,020.00
22,951.50
7,510.80
16,260.00
3,328.19
54,070.49
5,407.05
59,477.54

74,307.56

6,410.00

28,248.00
9,388.50
19,512.00
3,993.83
67,552.33
6,755.23
74,307.56

93,626.73

8,020.00

38,841.00
14,082.75
19,512.00
4,659.46
85,115.21
8,511.52
93,626.73

122,685.31

11,980.00

49,434.00
18,777.00
26,016.00
5,325.10
111,532.10
11,153.21
122,685.31
147,877.15

15,950.00

60,027.00
22,532.40
29,268.00
6,656.38
134,433.78
13,443.38
147,877.15

195,201.59

23,540.00

79,447.50
30,043.20
35,772.00
8,653.29
177,455.99
17,745.60
195,201.59

231,561.88

31,980.00

91,806.00
33,798.60
42,276.00
10,650.20
210,510.80
21,051.08
231,561.88

272,746.21

39,670.00

107,695.50
38,492.85
48,780.00
13,312.75
247,951.10
24,795.11
272,746.21

330,207.69

48,360.00

128,881.50
43,187.10
61,788.00
17,972.21
300,188.81
30,018.88
330,207.69

425,439.00

76,980.00

158,895.00
50,697.90
76,226.88
23,962.95
386,762.73
38,676.27
425,439.00

552,456.53

105,300.00

203,385.60
59,485.54
99,555.43
34,506.65
502,233.21
50,223.32
552,456.53
699,412.32

157,950.00

246,110.70
67,747.42
119,263.80
44,757.47
635,829.38
63,582.94
699,412.32

98,783.26

21,850.00
10,490.00
19,208.75
14,082.75
19,512.00
4,659.46
89,802.96
8,980.30
98,783.26

128,783.16

26,770.00
15,740.00
24,447.50
18,777.00
26,016.00
5,325.10
117,075.60
11,707.56
128,783.16

170,041.33

45,450.00
20,990.00
29,686.25
22,532.40
29,268.00
6,656.38
154,583.03
15,458.30
170,041.33

224,168.02

58,550.00
31,480.00
39,290.63
30,043.20
35,772.00
8,653.29
203,789.11
20,378.91
224,168.02

272,940.03

74,030.00
41,970.00
45,402.50
33,798.60
42,276.00
10,650.20
248,127.30
24,812.73
272,940.03

317,081.85

81,950.00
52,460.00
53,260.63
38,492.85
48,780.00
13,312.75
288,256.23
28,825.62
317,081.85
373,851.98

90,220.00
62,960.00
63,738.13
43,187.10
61,788.00
17,972.21
339,865.44
33,986.54
373,851.98

463,439.88

107,900.00
83,940.00
78,581.25
50,697.90
76,226.88
23,962.95
421,308.98
42,130.90
463,439.88

594,518.77

141,410.00
104,930.00
100,584.00
59,485.54
99,555.43
34,506.65
540,471.61
54,047.16
594,518.77

712,571.53

168,400.00
125,910.00
121,713.63
67,747.42
119,263.80
44,757.47
647,792.30
64,779.23
712,571.53

105,764.35

21,850.00
10,490.00
25,555.20
14,082.75
19,512.00
4,659.46
96,149.41
9,614.94
105,764.35

137,668.19

26,770.00
15,740.00
32,524.80
18,777.00
26,016.00
5,325.10
125,152.90
12,515.29
137,668.19

180,830.29

45,450.00
20,990.00
39,494.40
22,532.40
29,268.00
6,656.38
164,391.18
16,439.12
180,830.29
238,447.54

58,550.00
31,480.00
52,272.00
30,043.20
35,772.00
8,653.29
216,770.49
21,677.05
238,447.54

289,440.80

74,030.00
41,970.00
60,403.20
33,798.60
42,276.00
10,650.20
263,128.00
26,312.80
289,440.80

336,438.52

81,950.00
52,460.00
70,857.60
38,492.85
48,780.00
13,312.75
305,853.20
30,585.32
336,438.52

397,016.52

90,220.00
62,960.00
84,796.80
43,187.10
61,788.00
17,972.21
360,924.11
36,092.41
397,016.52

491,998.90

107,900.00
83,940.00
104,544.00
50,697.90
76,226.88
23,962.95
447,271.73
44,727.17
491,998.90

631,074.32

141,410.00
104,930.00
133,816.32
59,485.54
99,555.43
34,506.65
573,703.93
57,370.39
631,074.32

756,806.29

168,400.00
125,910.00
161,927.04
67,747.42
119,263.80
44,757.47
688,005.72
68,800.57
756,806.29
120,378.73

21,850.00
10,490.00
38,841.00
14,082.75
19,512.00
4,659.46
109,435.21
10,943.52
120,378.73

156,268.31

26,770.00
15,740.00
49,434.00
18,777.00
26,016.00
5,325.10
142,062.10
14,206.21
156,268.31

203,416.15

45,450.00
20,990.00
60,027.00
22,532.40
29,268.00
6,656.38
184,923.78
18,492.38
203,416.15

268,340.59

58,550.00
31,480.00
79,447.50
30,043.20
35,772.00
8,653.29
243,945.99
24,394.60
268,340.59

323,983.88

74,030.00
41,970.00
91,806.00
33,798.60
42,276.00
10,650.20
294,530.80
29,453.08
323,983.88

376,960.21

81,950.00
52,460.00
107,695.50
38,492.85
48,780.00
13,312.75
342,691.10
34,269.11
376,960.21

445,509.69

90,220.00
62,960.00
128,881.50
43,187.10
61,788.00
17,972.21
405,008.81
40,500.88
445,509.69
551,785.00

107,900.00
83,940.00
158,895.00
50,697.90
76,226.88
23,962.95
501,622.73
50,162.27
551,785.00

707,600.53

141,410.00
104,930.00
203,385.60
59,485.54
99,555.43
34,506.65
643,273.21
64,327.32
707,600.53

849,408.32

168,400.00
125,910.00
246,110.70
67,747.42
119,263.80
44,757.47
772,189.38
77,218.94
849,408.32

120,378.73

21,850.00
10,490.00
38,841.00
14,082.75
19,512.00
4,659.46
109,435.21
10,943.52
120,378.73

156,268.31

26,770.00
15,740.00
49,434.00
18,777.00
26,016.00
5,325.10
142,062.10
14,206.21
156,268.31

203,416.15

45,450.00
20,990.00
60,027.00
22,532.40
29,268.00
6,656.38
184,923.78
18,492.38
203,416.15

268,340.59

58,550.00
31,480.00
79,447.50
30,043.20
35,772.00
8,653.29
243,945.99
24,394.60
268,340.59
323,983.88

74,030.00
41,970.00
91,806.00
33,798.60
42,276.00
10,650.20
294,530.80
29,453.08
323,983.88

376,960.21

81,950.00
52,460.00
107,695.50
38,492.85
48,780.00
13,312.75
342,691.10
34,269.11
376,960.21

445,509.69

90,220.00
62,960.00
128,881.50
43,187.10
61,788.00
17,972.21
405,008.81
40,500.88
445,509.69

551,785.00

107,900.00
83,940.00
158,895.00
50,697.90
76,226.88
23,962.95
501,622.73
50,162.27
551,785.00

707,600.53

141,410.00
104,930.00
203,385.60
59,485.54
99,555.43
34,506.65
643,273.21
64,327.32
707,600.53

849,408.32

168,400.00
125,910.00
246,110.70
67,747.42
119,263.80
44,757.47
772,189.38
77,218.94
849,408.32

83,581.26

18,520.00

19,208.75
14,082.75
19,512.00
4,659.46
75,982.96
7,598.30
83,581.26
110,600.16

25,980.00
24,447.50
18,777.00
26,016.00
5,325.10
100,545.60
10,054.56
110,600.16

145,302.33

43,950.00

29,686.25
22,532.40
29,268.00
6,656.38
132,093.03
13,209.30
145,302.33

201,079.02

69,040.00

39,290.63
30,043.20
35,772.00
8,653.29
182,799.11
18,279.91
201,079.02

238,268.03

84,480.00

45,402.50
33,798.60
42,276.00
10,650.20
216,607.30
21,660.73
238,268.03

274,467.85

95,670.00

53,260.63
38,492.85
48,780.00
13,312.75
249,516.23
24,951.62
274,467.85

343,249.98

125,360.00

63,738.13
43,187.10
61,788.00
17,972.21
312,045.44
31,204.54
343,249.98

433,343.88

164,480.00

78,581.25
50,697.90
76,226.88
23,962.95
393,948.98
39,394.90
433,343.88
549,099.77

205,050.00

100,584.00
59,485.54
99,555.43
34,506.65
499,181.61
49,918.16
549,099.77

689,625.53

273,450.00

121,713.63
67,747.42
119,263.80
44,757.47
626,932.30
62,693.23
689,625.53

90,562.35

18,520.00

25,555.20
14,082.75
19,512.00
4,659.46
82,329.41
8,232.94
90,562.35

119,485.19

25,980.00

32,524.80
18,777.00
26,016.00
5,325.10
108,622.90
10,862.29
119,485.19

156,091.29

43,950.00

39,494.40
22,532.40
29,268.00
6,656.38
141,901.18
14,190.12
156,091.29

215,358.54

69,040.00

52,272.00
30,043.20
35,772.00
8,653.29
195,780.49
19,578.05
215,358.54

254,768.80

84,480.00

60,403.20
33,798.60
42,276.00
10,650.20
231,608.00
23,160.80
254,768.80
293,824.52

95,670.00

70,857.60
38,492.85
48,780.00
13,312.75
267,113.20
26,711.32
293,824.52

366,414.52

125,360.00

84,796.80
43,187.10
61,788.00
17,972.21
333,104.11
33,310.41
366,414.52

461,902.90

164,480.00

104,544.00
50,697.90
76,226.88
23,962.95
419,911.73
41,991.17
461,902.90

585,655.32

205,050.00

133,816.32
59,485.54
99,555.43
34,506.65
532,413.93
53,241.39
585,655.32

733,860.29

273,450.00

161,927.04
67,747.42
119,263.80
44,757.47
667,145.72
66,714.57
733,860.29

105,176.73

18,520.00

38,841.00
14,082.75
19,512.00
4,659.46
95,615.21
9,561.52
105,176.73

138,085.31

25,980.00

49,434.00
18,777.00
26,016.00
5,325.10
125,532.10
12,553.21
138,085.31
178,677.15

43,950.00

60,027.00
22,532.40
29,268.00
6,656.38
162,433.78
16,243.38
178,677.15

245,251.59

69,040.00

79,447.50
30,043.20
35,772.00
8,653.29
222,955.99
22,295.60
245,251.59

289,311.88

84,480.00

91,806.00
33,798.60
42,276.00
10,650.20
263,010.80
26,301.08
289,311.88

334,346.21

95,670.00

107,695.50
38,492.85
48,780.00
13,312.75
303,951.10
30,395.11
334,346.21

414,907.69

125,360.00

128,881.50
43,187.10
61,788.00
17,972.21
377,188.81
37,718.88
414,907.69

521,689.00

164,480.00

158,895.00
50,697.90
76,226.88
23,962.95
474,262.73
47,426.27
521,689.00

662,181.53

205,050.00

203,385.60
59,485.54
99,555.43
34,506.65
601,983.21
60,198.32
662,181.53
826,462.32

273,450.00

246,110.70
67,747.42
119,263.80
44,757.47
751,329.38
75,132.94
826,462.32

105,176.73

18,520.00

38,841.00
14,082.75
19,512.00
4,659.46
95,615.21
9,561.52
105,176.73

138,085.31

25,980.00

49,434.00
18,777.00
26,016.00
5,325.10
125,532.10
12,553.21
138,085.31

178,677.15

43,950.00

60,027.00
22,532.40
29,268.00
6,656.38
162,433.78
16,243.38
178,677.15

245,251.59

69,040.00

79,447.50
30,043.20
35,772.00
8,653.29
222,955.99
22,295.60
245,251.59

289,311.88

84,480.00

91,806.00
33,798.60
42,276.00
10,650.20
263,010.80
26,301.08
289,311.88

334,346.21

95,670.00

107,695.50
38,492.85
48,780.00
13,312.75
303,951.10
30,395.11
334,346.21
414,907.69

125,360.00

128,881.50
43,187.10
61,788.00
17,972.21
377,188.81
37,718.88
414,907.69

521,689.00

164,480.00

158,895.00
50,697.90
76,226.88
23,962.95
474,262.73
47,426.27
521,689.00

662,181.53

205,050.00

203,385.60
59,485.54
99,555.43
34,506.65
601,983.21
60,198.32
662,181.53

826,462.32

273,450.00

246,110.70
67,747.42
119,263.80
44,757.47
751,329.38
75,132.94
826,462.32

221,561.62

51,425.00
34,650.00
29,700.00
49,500.00
399.38
21,850.00
10,490.00
2,090.88
1,314.39
201,419.65
20,141.97
221,561.62

189,768.87

42,075.00
29,452.50
25,245.00
39,600.00
399.38
21,850.00
10,490.00
2,090.88
1,314.39
172,517.15
17,251.72
189,768.87

276,729.08

70,125.00
34,650.00
29,700.00
69,300.00
599.07
26,770.00
15,740.00
2,904.00
1,783.82
251,571.89
25,157.19
276,729.08

252,256.83

65,450.00
29,452.50
25,245.00
61,380.00
599.07
26,770.00
15,740.00
2,904.00
1,783.82
229,324.39
22,932.44
252,256.83

364,130.37

93,500.00
40,425.00
34,650.00
89,100.00
732.20
45,450.00
20,990.00
3,833.28
2,347.13
331,027.61
33,102.76
364,130.37

341,352.12
88,825.00
34,457.50
29,535.00
84,150.00
732.20
45,450.00
20,990.00
3,833.28
2,347.13
310,320.11
31,032.01
341,352.12

542,772.69

124,355.00
60,637.50
51,975.00
155,925.00
1,131.58
58,550.00
31,480.00
5,808.00
3,567.63
493,429.71
49,342.97
542,772.69

478,122.39

105,748.50
51,590.00
44,220.00
132,561.00
1,131.58
58,550.00
31,480.00
5,808.00
3,567.63
434,656.71
43,465.67
478,122.39

680,853.73

130,900.00
80,850.00
69,300.00
207,900.00
1,530.97
74,030.00
41,970.00
7,782.72
4,694.25
618,957.94
61,895.79
680,853.73

600,176.98

111,265.00
68,722.50
58,905.00
176,715.00
1,530.97
74,030.00
41,970.00
7,782.72
4,694.25
545,615.44
54,561.54
600,176.98

810,521.05

137,445.00
101,062.50
86,625.00
259,875.00
1,863.79
81,950.00
52,460.00
9,641.28
5,914.76
736,837.32
73,683.73
810,521.05

714,422.85

116,875.00
86,047.50
73,755.00
220,968.00
1,863.79
81,950.00
52,460.00
9,641.28
5,914.76
649,475.32
64,947.53
714,422.85

940,682.10

143,990.00
121,275.00
103,950.00
311,850.00
2,263.17
90,220.00
62,960.00
11,616.00
7,041.38
855,165.54
85,516.55
940,682.10

828,557.45

122,391.50
103,180.00
88,440.00
265,122.00
2,263.17
90,220.00
62,960.00
11,616.00
7,041.38
753,234.04
75,323.40
828,557.45

1,202,138.46

157,080.00
161,700.00
138,600.00
415,800.00
2,995.37
107,900.00
83,940.00
15,449.28
9,388.50
1,092,853.15
109,285.31
1,202,138.46

1,058,063.76

133,518.00
137,445.00
117,810.00
353,430.00
2,995.37
107,900.00
83,940.00
15,449.28
9,388.50
961,876.15
96,187.61
1,058,063.76

2,005,474.56
274,890.00
282,975.00
242,550.00
727,650.00
5,258.54
141,410.00
104,930.00
27,065.28
16,429.88
1,823,158.69
182,315.87
2,005,474.56

1,753,594.91

233,656.50
240,625.00
206,250.00
618,552.00
5,258.54
141,410.00
104,930.00
27,065.28
16,429.88
1,594,177.19
159,417.72
1,753,594.91

3,359,429.10

481,057.50
495,302.50
424,545.00
1,273,437.00
9,252.36
168,400.00
125,910.00
47,393.28
28,728.81
3,054,026.45
305,402.65
3,359,429.10

2,918,160.25

408,969.00
420,997.50
360,855.00
1,082,367.00
9,252.36
168,400.00
125,910.00
47,393.28
28,728.81
2,652,872.95
265,287.30
2,918,160.25

194,809.62

51,425.00
34,650.00
29,700.00
49,500.00
399.38

8,020.00

2,090.88
1,314.39
177,099.65
17,709.97
194,809.62

163,016.87

42,075.00
29,452.50
25,245.00
39,600.00
399.38

8,020.00
2,090.88
1,314.39
148,197.15
14,819.72
163,016.87

243,146.08

70,125.00
34,650.00
29,700.00
69,300.00
599.07

11,980.00

2,904.00
1,783.82
221,041.89
22,104.19
243,146.08

218,673.83

65,450.00
29,452.50
25,245.00
61,380.00
599.07

11,980.00

2,904.00
1,783.82
198,794.39
19,879.44
218,673.83

308,591.37

93,500.00
40,425.00
34,650.00
89,100.00
732.20
15,950.00

3,833.28
2,347.13
280,537.61
28,053.76
308,591.37

285,813.12

88,825.00
34,457.50
29,535.00
84,150.00
732.20

15,950.00

3,833.28
2,347.13
259,830.11
25,983.01
285,813.12

469,633.69

124,355.00
60,637.50
51,975.00
155,925.00
1,131.58

23,540.00

5,808.00
3,567.63
426,939.71
42,693.97
469,633.69

404,983.39

105,748.50
51,590.00
44,220.00
132,561.00
1,131.58

23,540.00

5,808.00
3,567.63
368,166.71
36,816.67
404,983.39

588,431.73

130,900.00
80,850.00
69,300.00
207,900.00
1,530.97

31,980.00

7,782.72
4,694.25
534,937.94
53,493.79
588,431.73

507,754.98

111,265.00
68,722.50
58,905.00
176,715.00
1,530.97

31,980.00

7,782.72
4,694.25
461,595.44
46,159.54
507,754.98

706,307.05

137,445.00
101,062.50
86,625.00
259,875.00
1,863.79

39,670.00

9,641.28
5,914.76
642,097.32
64,209.73
706,307.05

610,208.85

116,875.00
86,047.50
73,755.00
220,968.00
1,863.79

39,670.00

9,641.28
5,914.76
554,735.32
55,473.53
610,208.85

825,380.10

143,990.00
121,275.00
103,950.00
311,850.00
2,263.17

48,360.00

11,616.00
7,041.38
750,345.54
75,034.55
825,380.10
713,255.45

122,391.50
103,180.00
88,440.00
265,122.00
2,263.17

48,360.00

11,616.00
7,041.38
648,414.04
64,841.40
713,255.45

1,075,792.46

157,080.00
161,700.00
138,600.00
415,800.00
2,995.37

76,980.00

15,449.28
9,388.50
977,993.15
97,799.31
1,075,792.46

931,717.76

133,518.00
137,445.00
117,810.00
353,430.00
2,995.37

76,980.00

15,449.28
9,388.50
847,016.15
84,701.61
931,717.76

1,850,330.56

274,890.00
282,975.00
242,550.00
727,650.00
5,258.54

105,300.00

27,065.28
16,429.88
1,682,118.69
168,211.87
1,850,330.56

1,598,450.91

233,656.50
240,625.00
206,250.00
618,552.00
5,258.54

105,300.00

27,065.28
16,429.88
1,453,137.19
145,313.72
1,598,450.91

3,209,433.10

481,057.50
495,302.50
424,545.00
1,273,437.00
9,252.36

157,950.00

47,393.28
28,728.81
2,917,666.45
291,766.65
3,209,433.10

2,768,164.25

408,969.00
420,997.50
360,855.00
1,082,367.00
9,252.36

157,950.00

47,393.28
28,728.81
2,516,512.95
251,651.30
2,768,164.25

206,359.62

51,425.00
34,650.00
29,700.00
49,500.00
399.38

18,520.00

2,090.88
1,314.39
187,599.65
18,759.97
206,359.62

174,566.87

42,075.00
29,452.50
25,245.00
39,600.00
399.38

18,520.00
2,090.88
1,314.39
158,697.15
15,869.72
174,566.87

258,546.08

70,125.00
34,650.00
29,700.00
69,300.00
599.07

25,980.00

2,904.00
1,783.82
235,041.89
23,504.19
258,546.08

234,073.83

65,450.00
29,452.50
25,245.00
61,380.00
599.07

25,980.00

2,904.00
1,783.82
212,794.39
21,279.44
234,073.83

339,391.37

93,500.00
40,425.00
34,650.00
89,100.00
732.20
43,950.00

3,833.28
2,347.13
308,537.61
30,853.76
339,391.37

316,613.12

88,825.00
34,457.50
29,535.00
84,150.00
732.20

43,950.00

3,833.28
2,347.13
287,830.11
28,783.01
316,613.12

469,633.69

124,355.00
60,637.50
51,975.00
155,925.00
1,131.58

23,540.00

5,808.00
3,567.63
426,939.71
42,693.97
469,633.69

404,983.39

105,748.50
51,590.00
44,220.00
132,561.00
1,131.58

23,540.00

5,808.00
3,567.63
368,166.71
36,816.67
404,983.39

646,181.73

130,900.00
80,850.00
69,300.00
207,900.00
1,530.97

84,480.00

7,782.72
4,694.25
587,437.94
58,743.79
646,181.73

565,504.98

111,265.00
68,722.50
58,905.00
176,715.00
1,530.97

84,480.00

7,782.72
4,694.25
514,095.44
51,409.54
565,504.98

767,907.05

137,445.00
101,062.50
86,625.00
259,875.00
1,863.79

95,670.00

9,641.28
5,914.76
698,097.32
69,809.73
767,907.05

671,808.85

116,875.00
86,047.50
73,755.00
220,968.00
1,863.79

95,670.00

9,641.28
5,914.76
610,735.32
61,073.53
671,808.85

910,080.10

143,990.00
121,275.00
103,950.00
311,850.00
2,263.17

125,360.00

11,616.00
7,041.38
827,345.54
82,734.55
910,080.10
797,955.45

122,391.50
103,180.00
88,440.00
265,122.00
2,263.17

125,360.00

11,616.00
7,041.38
725,414.04
72,541.40
797,955.45

1,172,042.46

157,080.00
161,700.00
138,600.00
415,800.00
2,995.37

164,480.00

15,449.28
9,388.50
1,065,493.15
106,549.31
1,172,042.46

1,027,967.76

133,518.00
137,445.00
117,810.00
353,430.00
2,995.37

164,480.00

15,449.28
9,388.50
934,516.15
93,451.61
1,027,967.76

1,960,055.56

274,890.00
282,975.00
242,550.00
727,650.00
5,258.54

205,050.00

27,065.28
16,429.88
1,781,868.69
178,186.87
1,960,055.56

1,708,175.91

233,656.50
240,625.00
206,250.00
618,552.00
5,258.54

205,050.00

27,065.28
16,429.88
1,552,887.19
155,288.72
1,708,175.91

3,336,483.10

481,057.50
495,302.50
424,545.00
1,273,437.00
9,252.36

273,450.00

47,393.28
28,728.81
3,033,166.45
303,316.65
3,336,483.10

2,895,214.25

408,969.00
420,997.50
360,855.00
1,082,367.00
9,252.36

273,450.00

47,393.28
28,728.81
2,632,012.95
263,201.30
2,895,214.25

4,010.00
1,552.00
213.00
225.60
400.00
240.00
140.00
260.00
130.00
850.00
4,010.60
4,010.00

10,490.00

10,492.83
10,492.83
10,490.00

15,740.00

15,739.25
15,739.25
15,740.00
20,990.00

20,985.67
20,985.67
20,990.00

31,480.00

31,478.50
31,478.50
31,480.00

41,970.00

41,971.33
41,971.33
41,970.00

52,460.00

52,464.17
52,464.17
52,460.00

62,960.00

62,957.00
62,957.00
62,960.00

83,940.00

83,942.67
83,942.67
83,940.00

104,930.00

104,928.33
104,928.33
104,930.00
125,910.00

125,914.00
125,914.00
125,910.00

21,850.00
455.00
7,680.00
4,550.00
5,760.00
3,400.00
21,845.00
21,850.00

26,770.00
650.00
12,924.00
6,500.00
1,593.00
5,100.00
26,767.00
26,770.00

45,450.00
650.00
18,000.00
6,500.00
13,500.00
6,800.00
45,450.00
45,450.00

58,550.00
780.00
22,500.00
8,190.00
16,875.00
10,200.00
58,545.00
58,550.00

74,030.00
1,040.00
28,140.00
10,140.00
21,105.00
13,600.00
74,025.00
74,030.00

81,950.00
1,092.00
30,252.00
10,920.00
22,689.00
17,000.00
81,953.00
81,950.00

90,220.00
1,170.00
32,520.00
11,739.00
24,390.00
20,400.00
90,219.00
90,220.00

107,900.00
1,352.00
37,584.00
13,572.00
28,188.00
27,200.00
107,896.00
107,900.00

141,410.00
15,730.00
43,428.00
15,678.00
32,571.00
34,000.00
141,407.00
141,410.00

168,400.00
3,159.00
58,536.00
31,707.00
43,902.00
31,093.00
168,397.00
168,400.00

4,020.00

325.00
1,392.00
2,025.00
280.50
4,022.50
4,020.00

6,410.00

520.00
2,208.00
3,240.00
445.40
6,413.40
6,410.00

8,020.00

650.00
2,760.00
4,050.00
556.75
8,016.75
8,020.00

11,980.00

1,040.00
4,080.00
6,030.00
833.44
11,983.44
11,980.00

15,950.00

1,430.00
5,400.00
8,010.00
1,110.10
15,950.10
15,950.00

23,540.00

1,690.00
8,160.00
12,060.00
1,628.60
23,538.60
23,540.00

31,980.00

2,730.00
10,920.00
16,110.00
2,223.60
31,983.60
31,980.00

39,670.00

3,900.00
13,200.00
19,800.00
2,766.75
39,666.75
39,670.00

48,360.00

3,900.00
16,800.00
24,300.00
3,361.75
48,361.75
48,360.00
76,980.00

4,940.00
27,360.00
39,150.00
5,525.00
76,975.00
76,980.00

105,300.00

5,850.00
37,800.00
54,000.00
7,650.00
105,300.00
105,300.00

157,950.00

8,775.00
56,700.00
81,000.00
11,475.00
157,950.00
157,950.00

18,520.00

650.00
2,760.00
4,050.00
7,500.00
3,000.00
556.75
18,516.75
18,520.00

25,980.00

1,040.00
4,080.00
6,030.00
10,000.00
4,000.00
833.44
25,983.44
25,980.00

43,950.00

1,430.00
5,400.00
8,010.00
20,000.00
8,000.00
1,110.10
43,950.10
43,950.00

69,040.00

1,690.00
8,160.00
12,060.00
32,500.00
13,000.00
1,628.60
69,038.60
69,040.00

84,480.00

2,730.00
10,920.00
16,110.00
37,500.00
15,000.00
2,223.60
84,483.60
84,480.00

95,670.00

3,900.00
13,200.00
19,800.00
40,000.00
16,000.00
2,766.75
95,666.75
95,670.00

125,360.00

3,900.00
16,800.00
24,300.00
55,000.00
22,000.00
3,361.75
125,361.75
125,360.00

164,480.00

4,940.00
27,360.00
39,150.00
62,500.00
25,000.00
5,525.00
164,475.00
164,480.00

205,050.00

5,850.00
37,800.00
54,000.00
71,250.00
28,500.00
7,650.00
205,050.00
205,050.00

273,450.00

8,775.00
56,700.00
81,000.00
82,500.00
33,000.00
11,475.00
273,450.00
273,450.00

1,650.00

1,366.40
7.20
41.40
17.00
54.00
13.00
153.00
1,652.00
1,650.00

1,770.00
1,366.40
20.16
66.60
25.50
81.00
13.00
195.50
1,768.16
1,770.00

1,880.00
1,366.40
31.68
82.80
34.00
99.00
26.00
238.00
1,877.88
1,880.00

2,780.00
2,049.60
70.56
124.20
51.00
153.00
39.00
297.50
2,784.86
2,780.00

3,730.00
2,732.80
123.84
165.60
59.50
198.00
52.00
399.50
3,731.24
3,730.00

4,090.00
2,732.80
279.36
248.40
85.00
261.00
65.00
416.50
4,088.06
4,090.00

5,310.00
3,416.00
496.80
331.20
110.50
333.00
91.00
535.50
5,314.00
5,310.00

6,750.00
4,099.20
777.60
552.60
136.00
414.00
104.00
671.50
6,754.90
6,750.00

9,280.00
5,465.60
1,118.88
847.80
136.00
414.00
104.00
1,190.00
9,276.28
9,280.00

11,750.00
6,148.80
1,990.08
1,130.40
187.00
558.00
143.00
1,589.50
11,746.78
11,750.00

13,180.00
6,490.40
2,826.72
1,132.20
204.00
648.00
195.00
1,683.00
13,179.32
13,180.00

54,530.00

923.00
8,568.00
14,280.00
12,852.00
6,069.00
11,841.58
54,533.58
54,530.00
80,610.00

1,235.00
11,424.00
19,040.00
17,136.00
8,092.00
23,683.16
80,610.16
80,610.00

101,030.00

1,547.00
14,280.00
23,800.00
21,420.00
10,115.00
29,869.06
101,031.06
101,030.00

143,550.00

1,846.00
17,136.00
28,570.00
25,713.00
12,138.00
58,147.46
143,550.46
143,550.00

184,320.00

2,054.00
19,044.00
31,740.00
28,566.00
13,489.50
89,430.44
184,323.94
184,320.00
268,300.00

2,314.00
21,420.00
35,710.00
32,139.00
15,172.50
161,540.36
268,295.86
268,300.00

312,780.00

2,600.00
24,000.00
40,000.00
36,000.00
17,000.00
193,176.82
312,776.82
312,780.00

408,160.00

3,250.00
30,000.00
50,000.00
45,000.00
21,250.00
258,658.99
408,158.99
408,160.00

546,340.00

4,329.00
39,996.00
66,660.00
59,994.00
28,330.50
347,028.99
546,338.49
546,340.00
21,350.00

468.00
4,284.00
7,140.00
6,426.00
3,034.50
21,352.50
21,350.00

28,470.00

624.00
5,712.00
9,520.00
8,568.00
4,046.00
28,470.00
28,470.00

35,590.00

780.00
7,140.00
11,900.00
10,710.00
5,057.50
35,587.50
35,590.00

42,710.00

923.00
8,568.00
14,290.00
12,861.00
6,069.00
42,711.00
42,710.00

47,460.00
1,027.00
9,528.00
15,870.00
14,283.00
6,749.00
47,457.00
47,460.00

53,400.00

1,157.00
10,716.00
17,860.00
16,074.00
7,590.50
53,397.50
53,400.00

59,800.00

1,300.00
12,000.00
20,000.00
18,000.00
8,500.00
59,800.00
59,800.00

74,750.00

1,625.00
15,000.00
25,000.00
22,500.00
10,625.00
74,750.00
74,750.00

99,670.00

2,171.00
20,004.00
33,330.00
29,997.00
14,169.50
99,671.50
99,670.00

98,630.00

923.00
8,568.00
12,852.00
57,570.00
603.50
18,115.85
98,632.35
98,630.00

105,880.00

923.00
8,568.00
12,852.00
57,570.00
603.50
25,362.19
105,878.69
105,880.00

120,810.00

923.00
8,568.00
12,852.00
57,570.00
603.50
40,296.72
120,813.22
120,810.00

21,340.00

455.00
4,284.00
7,140.00
6,426.00
3,034.50
21,339.50
21,340.00

28,460.00

611.00
5,712.00
9,520.00
8,568.00
4,046.00
28,457.00
28,460.00

35,570.00

767.00
7,140.00
11,900.00
10,710.00
5,057.50
35,574.50
35,570.00

42,690.00

923.00
8,568.00
14,280.00
12,852.00
6,069.00
42,692.00
42,690.00

56,930.00

1,235.00
11,424.00
19,040.00
17,136.00
8,092.00
56,927.00
56,930.00
71,160.00

1,547.00
14,280.00
23,800.00
21,420.00
10,115.00
71,162.00
71,160.00

85,400.00

1,846.00
17,136.00
28,570.00
25,713.00
12,138.00
85,403.00
85,400.00

108,710.00

2,353.00
21,816.00
36,360.00
32,724.00
15,453.00
108,706.00
108,710.00

14,220.00

299.00
2,856.00
4,760.00
4,284.00
2,023.00
14,222.00
14,220.00

20,590.00

442.00
4,128.00
6,890.00
6,201.00
2,924.00
20,585.00
20,590.00

28,460.00

611.00
5,712.00
9,520.00
8,568.00
4,046.00
28,457.00
28,460.00

35,570.00

767.00
7,140.00
11,900.00
10,710.00
5,057.50
35,574.50
35,570.00

45,970.00

988.00
9,228.00
15,380.00
13,842.00
6,536.50
45,974.50
45,970.00

50,640.00

1,092.00
10,164.00
16,940.00
15,246.00
7,199.50
50,641.50
50,640.00

66,440.00

1,443.00
13,332.00
22,220.00
19,998.00
9,443.50
66,436.50
66,440.00

93,420.00

2,028.00
18,744.00
31,250.00
28,125.00
13,277.00
93,424.00
93,420.00

82,870.00

429.00
3,996.00
6,660.00
5,994.00
2,830.50
62,957.00
82,866.50
82,870.00

118,360.00

520.00
4,800.00
8,000.00
7,200.00
3,400.00
94,435.50
118,355.50
118,360.00
154,370.00

611.00
5,712.00
9,520.00
8,568.00
4,046.00
125,914.00
154,371.00
154,370.00

231,560.00

923.00
8,568.00
14,280.00
12,852.00
6,069.00
188,871.00
231,563.00
231,560.00

308,760.00

1,235.00
11,424.00
19,040.00
17,136.00
8,092.00
251,828.00
308,755.00
308,760.00

406,750.00

1,989.00
18,456.00
30,760.00
27,684.00
13,073.00
314,785.00
406,747.00
406,750.00
497,340.00

2,600.00
24,000.00
40,000.00
36,000.00
17,000.00
377,742.00
497,342.00
497,340.00

653,160.00

3,250.00
30,000.00
50,000.00
45,000.00
21,250.00
503,656.00
653,156.00
653,160.00

828,880.00

4,329.00
39,996.00
66,660.00
59,994.00
28,330.50
629,570.00
828,879.50
828,880.00

1,054,480.00

6,500.00
60,000.00
100,000.00
90,000.00
42,500.00
755,484.00
1,054,484.00
1,054,480.00
53,560.00

923.00
8,568.00
14,280.00
12,852.00
6,069.00
10,869.51
53,561.51
53,560.00

73,010.00
1,235.00
11,424.00
19,040.00
17,136.00
8,092.00
16,083.34
73,010.34
73,010.00

109,430.00
1,547.00
14,280.00
23,800.00
21,420.00
10,115.00
38,264.21
109,426.21
109,430.00

163,430.00
1,846.00
17,136.00
28,570.00
25,713.00
12,138.00
78,030.71
163,433.71
163,430.00

250,510.00
2,054.00
19,044.00
31,740.00
28,566.00
13,489.50
155,619.57
250,513.07
250,510.00

400,320.00
2,314.00
21,420.00
35,710.00
32,139.00
15,172.50
293,565.14
400,320.64
400,320.00

622,160.00
2,600.00
24,000.00
40,000.00
36,000.00
17,000.00
502,560.19
622,160.19
622,160.00

843,200.00
3,250.00
30,000.00
50,000.00
45,000.00
21,250.00
693,704.50
843,204.50
843,200.00

1,019,940.00
3,250.00
30,000.00
50,000.00
45,000.00
21,250.00
870,444.50
1,019,944.50
1,019,940.00
56,840.00
988.00
9,228.00
15,380.00
13,842.00
6,536.50
10,869.51
56,844.01
56,840.00

75,880.00
1,300.00
12,000.00
20,000.00
18,000.00
8,500.00
16,083.34
75,883.34
75,880.00

113,010.00
1,625.00
15,000.00
25,000.00
22,500.00
10,625.00
38,264.21
113,014.21
113,010.00

163,430.00
1,846.00
17,136.00
28,570.00
25,713.00
12,138.00
78,030.71
163,433.71
163,430.00

255,260.00
2,158.00
19,992.00
33,330.00
29,997.00
14,161.00
155,619.57
255,257.57
255,260.00

426,440.00
2,886.00
26,664.00
44,440.00
39,996.00
18,887.00
293,565.14
426,438.14
426,440.00

652,060.00
3,250.00
30,000.00
50,000.00
45,000.00
21,250.00
502,560.19
652,060.19
652,060.00

861,510.00
3,705.00
34,284.00
57,140.00
51,426.00
21,250.00
693,704.50
861,509.50
861,510.00

1,038,250.00
3,705.00
34,284.00
57,140.00
51,426.00
21,250.00
870,444.50
1,038,249.50
1,038,250.00

55,140.00
962.00
8,880.00
14,810.00
13,329.00
6,290.00
10,869.51
55,140.51
55,140.00

70,430.00

1,170.00
10,908.00
18,180.00
16,362.00
7,726.50
16,083.34
70,429.84
70,430.00

104,700.00

1,443.00
13,332.00
22,220.00
19,998.00
9,443.50
38,264.21
104,700.71
104,700.00

152,780.00

1,625.00
15,000.00
25,000.00
22,500.00
10,625.00
78,030.71
152,780.71
152,780.00

241,020.00
1,846.00
17,136.00
28,570.00
25,713.00
12,138.00
155,619.57
241,022.57
241,020.00

393,200.00

2,158.00
19,992.00
33,330.00
29,997.00
14,161.00
293,565.14
393,203.14
393,200.00

622,160.00

2,600.00
24,000.00
40,000.00
36,000.00
17,000.00
502,560.19
622,160.19
622,160.00

1,019,940.00

3,250.00
30,000.00
50,000.00
45,000.00
21,250.00
870,444.50
1,019,944.50
1,019,940.00

8,837.00
8,837.00
8,837.00
17,674.00
35,348.00
70,696.00
159,066.00
291,621.00
503,709.00

17,674.00
17,674.00
17,674.00
26,511.00
53,022.00
114,881.00
229,762.00
433,013.00
821,841.00

8,837.00
8,837.00
8,837.00
8,837.00
26,511.00
53,022.00
114,881.00
212,088.00
371,154.00

8,837.00
8,837.00
8,837.00
17,674.00
35,348.00
79,533.00
159,066.00
291,621.00
503,709.00

8,837.00
8,837.00
8,837.00
17,674.00
35,348.00
79,533.00
159,066.00
291,621.00
503,709.00

38,820.00

650.00
2,760.00
4,050.00
22,000.00
8,800.00
556.75
38,816.75
38,820.00

61,860.00

1,040.00
4,080.00
6,030.00
35,625.00
14,250.00
833.44
61,858.44
61,860.00

85,950.00

1,430.00
5,400.00
8,010.00
50,000.00
20,000.00
1,110.10
85,950.10
85,950.00

160,040.00

1,690.00
8,160.00
12,060.00
97,500.00
39,000.00
1,628.60
160,038.60
160,040.00

189,480.00

2,730.00
10,920.00
16,110.00
112,500.00
45,000.00
2,223.60
189,483.60
189,480.00

207,670.00

3,900.00
13,200.00
19,800.00
120,000.00
48,000.00
2,766.75
207,666.75
207,670.00

279,360.00

3,900.00
16,800.00
24,300.00
165,000.00
66,000.00
3,361.75
279,361.75
279,360.00

339,480.00

4,940.00
27,360.00
39,150.00
187,500.00
75,000.00
5,525.00
339,475.00
339,480.00

404,550.00

5,850.00
37,800.00
54,000.00
213,750.00
85,500.00
7,650.00
404,550.00
404,550.00

504,450.00

8,775.00
56,700.00
81,000.00
247,500.00
99,000.00
11,475.00
504,450.00
504,450.00

31,120.00

650.00
2,760.00
4,050.00
16,500.00
6,600.00
556.75
31,116.75
31,120.00

48,730.00

1,040.00
4,080.00
6,030.00
26,250.00
10,500.00
833.44
48,733.44
48,730.00

71,950.00

1,430.00
5,400.00
8,010.00
40,000.00
16,000.00
1,110.10
71,950.10
71,950.00

114,540.00

1,690.00
8,160.00
12,060.00
65,000.00
26,000.00
1,628.60
114,538.60
114,540.00

136,980.00

2,730.00
10,920.00
16,110.00
75,000.00
30,000.00
2,223.60
136,983.60
136,980.00

151,670.00

3,900.00
13,200.00
19,800.00
80,000.00
32,000.00
2,766.75
151,666.75
151,670.00

202,360.00

3,900.00
16,800.00
24,300.00
110,000.00
44,000.00
3,361.75
202,361.75
202,360.00

251,980.00

4,940.00
27,360.00
39,150.00
125,000.00
50,000.00
5,525.00
251,975.00
251,980.00

304,800.00

5,850.00
37,800.00
54,000.00
142,500.00
57,000.00
7,650.00
304,800.00
304,800.00

388,950.00

8,775.00
56,700.00
81,000.00
165,000.00
66,000.00
11,475.00
388,950.00
388,950.00

26,500.00

650.00
2,760.00
4,050.00
13,200.00
5,280.00
556.75
26,496.75
26,500.00

41,910.00

1,040.00
4,080.00
6,030.00
21,375.00
8,550.00
833.44
41,908.44
41,910.00

57,950.00

1,430.00
5,400.00
8,010.00
30,000.00
12,000.00
1,110.10
57,950.10
57,950.00

91,790.00

1,690.00
8,160.00
12,060.00
48,750.00
19,500.00
1,628.60
91,788.60
91,790.00

110,730.00

2,730.00
10,920.00
16,110.00
56,250.00
22,500.00
2,223.60
110,733.60
110,730.00

123,670.00

3,900.00
13,200.00
19,800.00
60,000.00
24,000.00
2,766.75
123,666.75
123,670.00

163,860.00

3,900.00
16,800.00
24,300.00
82,500.00
33,000.00
3,361.75
163,861.75
163,860.00

208,230.00

4,940.00
27,360.00
39,150.00
93,750.00
37,500.00
5,525.00
208,225.00
208,230.00

254,930.00

5,850.00
37,800.00
54,000.00
106,875.00
42,750.00
7,650.00
254,925.00
254,930.00

331,200.00

8,775.00
56,700.00
81,000.00
123,750.00
49,500.00
11,475.00
331,200.00
331,200.00

23,420.00

650.00
2,760.00
4,050.00
11,000.00
4,400.00
556.75
23,416.75
23,420.00

31,930.00

1,040.00
4,080.00
6,030.00
14,250.00
5,700.00
833.44
31,933.44
31,930.00

43,950.00

1,430.00
5,400.00
8,010.00
20,000.00
8,000.00
1,110.10
43,950.10
43,950.00

69,040.00

1,690.00
8,160.00
12,060.00
32,500.00
13,000.00
1,628.60
69,038.60
69,040.00

84,480.00

2,730.00
10,920.00
16,110.00
37,500.00
15,000.00
2,223.60
84,483.60
84,480.00

95,670.00

3,900.00
13,200.00
19,800.00
40,000.00
16,000.00
2,766.75
95,666.75
95,670.00

125,360.00

3,900.00
16,800.00
24,300.00
55,000.00
22,000.00
3,361.75
125,361.75
125,360.00

164,480.00

4,940.00
27,360.00
39,150.00
62,500.00
25,000.00
5,525.00
164,475.00
164,480.00

205,050.00

5,850.00
37,800.00
54,000.00
71,250.00
28,500.00
7,650.00
205,050.00
205,050.00

273,450.00

8,775.00
56,700.00
81,000.00
82,500.00
33,000.00
11,475.00
273,450.00
273,450.00
141,100.00
34,160.00
2,340.00
30,000.00
19,350.00
5,200.00
360.00
22,446.00
4,630.50
5,187.00
7,696.00
8,889.20
845.00
141,103.70
141,100.00

Anda mungkin juga menyukai