A PEKERJAAN DINDING
1 Bongkar Keramik Lantai m2 28.00 12,710 355,880
2 Kolom Praktis m3 0.22 4,800,800 1,036,973
3 Pasang Dinding m2 54.20 84,720 4,591,824
4 Plesteran Dinding m2 108.40 77,660 8,418,344
5 Acian Dinding m2 108.40 42,360 4,591,824
6 Sponengan m' 64.40 35,300 2,273,320
7 Keramik Lantai Kamar m2 23.50 211,800 4,977,300
8 Plint Keramik Dinding m' 26.60 49,420 1,314,572
9 Pengecatan Dinding m2 108.40 37,420 4,056,328
B PEKERJAAN TOILET
1 Keramik Lantai Toilet m2 4.50 190,620 857,790
2 Keramik Dinding Toilet m2 33.00 232,980 7,688,340
3 Closet Duduk komplit (jet shower, kran, naple) unit 2.00 4,942,000 9,884,000
4 Instalasi Air Bersih ls 1.00 917,800 917,800
5 Instalasi Air Kotor ls 1.00 1,200,200 1,200,200
6 Shower Kamar Mandi unit 2.00 706,000 1,412,000
7 Kran Air unit 2.00 176,500 353,000
D PEKERJAAN LISTRIK
1 Bongkar Instalasi Listrik di Kolom ls 1.00 282,400 282,400
2 Instalasi Listrik ls 1.00 1,059,000 1,059,000
3 Lampu LED 15 watt ttk 6.00 105,900 635,400
4 Rumah Lampu Downlight ttk 6.00 169,440 1,016,640
5 Stop Kontak ttk 2.00 84,720 169,440
6 Saklar ttk 4.00 84,720 338,880
7 Stop Kontak AC ttk 2.00 84,720 169,440
8 MCB 2 phase unit 2.00 353,000 706,000
9 Kabel Tofur 3 x 2,5 mm m' 1.00 155,320 155,320
Jumlah 72,017,215
Terbilang : Tujuh Puluh Dua Juta Tujuh Belas Ribu Dua Ratus Lima Belas Rupiah.
Muh. Solikin
ANALISA HARGA SATUAN
HARGA HARGA
KODE INDEK SAT URAIAN DASAR BAHAN UPAH ALAT SATUAN
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
( Rp.)
1 Pekerja oh 183,560.00
2 Tukang oh 211,800.00
3 Mandor oh 247,100.00
4 Operator oh 211,800.00
5 Pembantu Operator oh 176,500.00
6 Sopir / Driver oh 211,800.00
7 Pembantu Sopir / Driver oh 176,500.00
8 Mekanik oh 211,800.00
9 Pembantu Mekanik oh 176,500.00
10 Kepala Tukang oh 225,920.00
11 Juru Ukur oh 211,800.00
12 Juru Hitung oh 211,800.00
HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
( Rp.)
HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
( Rp.)