RENCANA ANGGARAN BIAYA

Nama Pekerjaan : Penambahan 2 unit Kamar Kos


Lokasi : Yogyakarta

NO URAIAN SAT VOLUME HARGA SATUAN JUMLAH HARGA

A PEKERJAAN DINDING
1 Bongkar Keramik Lantai m2 28.00 12,710 355,880
2 Kolom Praktis m3 0.22 4,800,800 1,036,973
3 Pasang Dinding m2 54.20 84,720 4,591,824
4 Plesteran Dinding m2 108.40 77,660 8,418,344
5 Acian Dinding m2 108.40 42,360 4,591,824
6 Sponengan m' 64.40 35,300 2,273,320
7 Keramik Lantai Kamar m2 23.50 211,800 4,977,300
8 Plint Keramik Dinding m' 26.60 49,420 1,314,572
9 Pengecatan Dinding m2 108.40 37,420 4,056,328

B PEKERJAAN TOILET
1 Keramik Lantai Toilet m2 4.50 190,620 857,790
2 Keramik Dinding Toilet m2 33.00 232,980 7,688,340
3 Closet Duduk komplit (jet shower, kran, naple) unit 2.00 4,942,000 9,884,000
4 Instalasi Air Bersih ls 1.00 917,800 917,800
5 Instalasi Air Kotor ls 1.00 1,200,200 1,200,200
6 Shower Kamar Mandi unit 2.00 706,000 1,412,000
7 Kran Air unit 2.00 176,500 353,000

C PEKERJAAN PINTU DAN JENDELA


1 Pintu Utama Rangka Aluminium (200 x 85) unit 2.00 2,329,800 4,659,600
2 Jendela Rangka Aluminium (150 x 60) unit 2.00 1,200,200 2,400,400
3 Pintu Km.Mandi Rangka Aluminium (200 x 65) unit 2.00 2,188,600 4,377,200
4 Bouvenlight Rangka Aluminium (100 x 20) unit 2.00 1,059,000 2,118,000

D PEKERJAAN LISTRIK
1 Bongkar Instalasi Listrik di Kolom ls 1.00 282,400 282,400
2 Instalasi Listrik ls 1.00 1,059,000 1,059,000
3 Lampu LED 15 watt ttk 6.00 105,900 635,400
4 Rumah Lampu Downlight ttk 6.00 169,440 1,016,640
5 Stop Kontak ttk 2.00 84,720 169,440
6 Saklar ttk 4.00 84,720 338,880
7 Stop Kontak AC ttk 2.00 84,720 169,440
8 MCB 2 phase unit 2.00 353,000 706,000
9 Kabel Tofur 3 x 2,5 mm m' 1.00 155,320 155,320

Jumlah 72,017,215

Terbilang : Tujuh Puluh Dua Juta Tujuh Belas Ribu Dua Ratus Lima Belas Rupiah.

Yogyakarta, 28 Februari 2022


Yang Mengajukan

Muh. Solikin
ANALISA HARGA SATUAN

HARGA HARGA
KODE INDEK SAT URAIAN DASAR BAHAN UPAH ALAT SATUAN
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )

1 Survey dan Pengukuran MC-0


26.8456 oh Pekerja 183,560 4,927,778 4,927,778
1.9886 oh Mandor 247,100 491,383 491,383
24.1611 oh Juru ukur 211,800 5,117,321 5,117,321
32.2148 oh Juru Hitung 211,800 6,823,095 6,823,095
Jumlah 17,359,577
Dibulatkan 17,359,500
2 Direksi Keet dan Barak Pekerja
0.0167 oh Mandor 247,100 4,127 4,127
0.0333 oh Tukang Kayu 211,800 7,053 7,053
0.2667 oh Pekerja 183,560 48,955 48,955
0.0192 m3 Kayu Kelas III 5,224,400 100,308 100,308
0.5000 lbr Seng Plat BJLS 28 ( 80x180cm ) 105,900 52,950 52,950
0.4000 lbr Triplek t=4 mm 51,538 20,615 20,615
0.0667 kg Paku 28,240 1,884 1,884
0.0167 kg Paku Seng 25,416 424 424
0.0333 unit Pintu Panel Kelas III 494,200 16,457 16,457
0.0225 set Jendela Nako + Aksesoris 141,200 3,177 3,177
Jumlah 255,951
Dibulatkan 255,900
3 Penyediaan Air dan Listrik Kerja
2.0000 bln Air Kerja + Listrik Kerja 917,800 1,835,600 1,835,600
Jumlah 1,835,600
Dibulatkan 1,835,600
4 Leveling & Pemadatan Tanah setelah bongkaran
0.0603 oh Pekerja 183,560 11,069 11,069
0.0151 oh Mandor 247,100 3,731 3,731
1.1000 m3 Tanah Timbunan 17,650 19,415 19,415
0.0105 jam Excavator 568,217 5,966 5,966
0.0092 jam Dump Truck 144,730 1,332 1,332
0.0119 jam Vibro Roller kap 12 ton 586,008 6,973 6,973
0.0086 jam Watertank Truck 144,730 1,245 1,245
Jumlah 49,731
Dibulatkan 49,700
5 Urugan Pasir Urug
0.3110 oh Pekerja 183,560 57,087 57,087
0.1582 oh Mandor 247,100 39,091 39,091
0.1000 m3 Pasir urug 268,280 26,828 26,828
Jumlah 123,006
Dibulatkan 123,000
6 Lantai Kerja K.125
0.0141 oh Pekerja 183,560 2,588 2,588
0.0067 oh Mandor 247,100 1,656 1,656
1.1000 m3 Beton Readymix K.125 1,186,080 1,304,688 1,304,688
Jumlah 1,308,932
Dibulatkan 1,308,900
HARGA HARGA
KODE INDEK SAT URAIAN DASAR BAHAN UPAH ALAT SATUAN
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )

7 Pembesian M8 ; 2 lapis + Cakar Ayam tiap 50 cm


0.0898 oh Pekerja 183,560 16,484 16,484
0.0934 oh Mandor 247,100 23,079 23,079
0.1764 lbr Wiremesh M8 1,134,260 200,046 200,046
5.8333 kg Besi Dowel dia.13mm tiap 120mm 21,180 123,550 123,550
2.7750 kg Cakar Ayam besi dia.10mm 21,180 58,775 58,775
Jumlah 421,933
Dibulatkan 421,900
8 Pengecoran Beton K.400
0.0141 oh Pekerja 183,560 2,588 2,588
0.0067 oh Mandor 247,100 1,656 1,656
1.1000 m3 Beton Readymix K.500 1,708,520 1,879,372 1,879,372
1.0000 m2 Platik Cor 7,060 7,060 7,060
0.5000 jam Concrete Vibrator 302,902 151,451 151,451
Jumlah 2,042,127
Dibulatkan 2,042,100
9 Pasangan Kanstin
0.4233 oh Pekerja 183,560 77,697 77,697
0.1693 oh Tukang 211,800 35,860 35,860
0.0423 oh Mandor 247,100 10,459 10,459
1.6600 bh Kanstin 60 x 30 x 20 127,080 210,953 210,953
0.0420 jam Plat Bed Truck 345,460 14,509 14,509
Jumlah 349,478
Dibulatkan 349,400
10 Floor Hardener
0.1200 oh Pekerja 183,560 22,027 22,027
0.0060 oh Mandor 247,100 1,483 1,483
0.1320 oh Tukang 211,800 27,958 27,958
5.0000 kg Floorhadener 7,060 35,300 35,300
0.0250 jam Trowel 90,777 2,269 2,269
Jumlah 89,037
Dibulatkan 89,000
11 Saluran Air
0.1450 oh Pekerja 183,560 26,616 26,616
0.0135 oh Mandor 247,100 3,336 3,336
0.0350 oh Tukang 211,800 7,413 7,413
0.8000 bh Saluran U 30.40.120 240,040 192,032 192,032
0.1200 zak Semen 105,900 12,708 12,708
0.0200 m3 Pasir 317,700 6,354 6,354
Jumlah 248,459
Dibulatkan 248,400
12 Grill Saluran
0.3000 oh Pekerja 183,560 55,068 55,068
0.0245 oh Mandor 247,100 6,054 6,054
0.1500 oh Tukang 211,800 31,770 31,770
1.0000 bh Grill besi siku 1,341,400 1,341,400 1,341,400
Jumlah 1,434,292
Dibulatkan 1,434,200
HARGA DASAR SATUAN UPAH

HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
( Rp.)

1 Pekerja oh 183,560.00
2 Tukang oh 211,800.00
3 Mandor oh 247,100.00
4 Operator oh 211,800.00
5 Pembantu Operator oh 176,500.00
6 Sopir / Driver oh 211,800.00
7 Pembantu Sopir / Driver oh 176,500.00
8 Mekanik oh 211,800.00
9 Pembantu Mekanik oh 176,500.00
10 Kepala Tukang oh 225,920.00
11 Juru Ukur oh 211,800.00
12 Juru Hitung oh 211,800.00

HARGA DASAR SATUAN BAHAN

HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
( Rp.)

1 Air Kerja + Listrik Lerja Bln 917,800.00


2 Bahan Distribusi Kg 1,412.00
3 Bata Merah Bh 1,129.60
4 Besi Beton dia. 10mm Kg 21,180.00
5 Besi Beton dia. 13mm Kg 21,180.00
6 Batu Gunung M3 543,620.00
7 Batu Split M3 381,240.00
8 Beton Readymix K.125 M3 1,186,080.00
9 Beton Readymix K.500 M3 1,708,520.00
10 BBM Pertalite Ltr 10,801.80
11 Floorhardener M2 7,060.00
12 Grill Besi Siku lebar 30 cm M' 1,341,400.00
13 Jendela Naco + accessories Set 141,200.00
14 Kanstin 60 x 30 x 20 Bh 127,080.00
15 Kawat Bendrat Kg 24,004.00
16 Kayu Klas III M3 5,224,400.00
17 Kayu Klas IV M3 5,083,200.00
18 Keramik 40 x 40 Dos 307,816.00
19 Multipleks 12 mm Lbr 256,278.00
20 Paku Kg 28,240.00
21 Paku Seng Kg 25,416.00
HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
( Rp.)

22 Pasir Beton (Kasar) M3 317,700.00


23 Pasir Urug M3 268,280.00
24 Pintu Panel Klas III Bh 494,200.00
25 Plastik Cor M2 7,060.00
26 Seng Plat BJLS 28 ( 80x180cm ) Lbr 105,900.00
27 Sirtu M3 176,500.00
28 Solar Non Subsidi Ltr 13,272.80
29 Semen / PC (50kg) Zak 105,900.00
30 Semen / PC (kg) Kg 2,118.00
31 Saluran U 30.40.120 Buah 240,040.00
32 Strause Pile dia.30cm p.6m' Buah 105,900.00
33 Tanah Timbunan M3 17,650.00
34 Triplek t=4 mm Lbr 51,538.00
35 Wiremesh M8 2,1 x 5,4 m (8mm) Lbr 1,134,259.60

HARGA DASAR SATUAN ALAT

HARGA
No. URAIAN SATUAN SATUAN KETERANGAN
( Rp.)

1 Bulldozer Jam 536,588.24


2 Beton Molen / Concrete Mixer Jam 307,138.24
3 Concrete Vibrator Jam 302,902.24
4 Dump Truck Jam 144,730.00
5 Excavator Jam 568,217.04
6 Flat Bed Truck Jam 345,459.92
7 Generator Set Jam 339,713.08
8 Motor Grader Jam 713,088.24
9 Vibro Roller kap 12 ton Jam 586,008.24
10 Sheepfoot Roller Jam 586,008.24
11 Compressor Jam 361,599.08
12 Tandem Roller Jam 366,639.92
13 Wheel Loader Jam 397,901.60
14 Water tank truck Jam 144,730.00
15 Trowel Jam 90,777.48