Anda di halaman 1dari 6

RENCANA ANGGARAN BIAYA.

PEKERJAAN : PEMBANGUNAN GEDUNG NSC 2 STUDIO


LOKASI JOMBANG

PEKERJAAN SIPIL
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SAT
( Rp. ) ( Rp. )

I PEKERJAAN PERSIAPAN & PEMBONGKARAN


1 Sewa kontrakan, mobilisasi alat dan tenaga kerja 1.00 ls 12,000,000.00 4,920,000.00
2 Pembersihan lokasi 1.00 ls 7,500,000.00 3,075,000.00
3 Uitzet/pengukuran 1.00 ls 2,500,000.00 1,025,000.00
4 Mobilisasi peralatan 1.00 ls 5,000,000.00 2,050,000.00
5 Pembuangan bongkaran 1.00 ls 3,000,000.00 1,230,000.00
6 Listrik kerja 1.00 ls 7,500,000.00 3,075,000.00
7 Keamaman 1.00 ls 5,000,000.00 2,050,000.00
SUB TOTAL 17,425,000.00

II PEKERJAAN ENTRANCE, HALL, KASIR, CAFÉ, R. GANTI DAN KANTOR


1 Pasang partisi t. 4m rangka C. 80/0,55 penutup gybsumboard ex. IGP 2 sisi 356.00 m² 190,000.00 27,732,400.00
2 Pasang partisi t. 4m rangka Hollow 4/4 penutup gybsumboard ex. IGP 1 sisi 218.00 m² 105,000.00 9,384,900.00
3 Kusen aluminium 3" powder coating putih tulang ex. Alexindo 28.00 m' 130,000.00 1,492,400.00
4 Daun pintu teakwood komplit kunci, handel, engsel 4" 4.00 bh 1,350,000.00 2,214,000.00
5 Pasang plafond datar rangka holow 2/2 penutup gybsumboard ex. IGP 421.00 m² 105,000.00 1,250,676.41
6 Pasang plafond drop rangka holow 2/2 penutup gybsum board ex. IGP 132.00 m' 52,500.00 2,841,300.00
7 Pasang gantungan plafond kawat 4mm 421.00 m² 12,500.00 2,157,625.00
8 Cat dinding interior ex. Catylac 484.00 m² 27,500.00 5,457,100.00
9 Cat plafond datar ex. Catylac 421.00 m² 27,500.00 4,746,775.00
10 Melamin pintu teackwood 30.00 m² 75,000.00 922,500.00
11 Kaca bening 12 mm 32.60 m² 1,050,000.00 14,034,300.00
12 Pasang pintu kaca polos 12mm tempered (2 bh) 5.40 m² 1,050,000.00 2,324,700.00
13 Floor hing ex. Dorma 2.00 set 4,600,000.00 3,772,000.00
14 Kunci ex. Dekson 2.00 set 600,000.00 492,000.00
15 Handel Stainless Modivikasi 2.00 set 2,100,000.00 1,722,000.00
SUB TOTAL 80,544,676.41

III PEKERJAAN RUANG OPERATOR


1 Pasang partisi rangka galvalum 80/0,55mm - gybseumboard 9mm ex. IGP 2 sisi 142.00 m² 190,000.00 11,061,800.00
2 Pasang plafond rangka hollow 2/2 penutup gybsumboard 9mm ex. IGP 45.00 m² 105,000.00 1,937,250.00
3 Pasang gantungan plafond kawat 4mm 45.00 m² 12,500.00 230,625.00
4 Cat dinding interior ex. Catylac 88.00 m² 27,500.00 992,200.00
5 Cat plafond ex. Catylac 44.00 m² 27,500.00 496,100.00
6 Pasang plastik vinil lantai r. operator 44.00 m² 135,000.00 2,435,400.00
7 Kusen Aluminium 12.20 m' 156,000.00 780,312.00
8 Pintu Aluminium teack wood 2.00 bh 1,550,000.00 1,271,000.00
9 Handel pintu 2.00 set 350,000.00 287,000.00
10 Kunci pintu 2.00 set 180,000.00 147,600.00
SUB TOTAL 19,639,287.00

IV PEKERJAAN R. CINEMA STUDIO 1 & STUDIO 2


1 Pasang dinding partisi rangka Hollow 4/4 0,45 gybsumboard 9mm 1 sisi ex IGP 877.40 m² 115,000.00 41,369,410.00
2 Pasang dinding partisi rangka C.80/0,55 gybsumboard 9mm ex 2 sisi IGP 877.40 m² 190,000.00 68,349,460.00
3 Pasang partisi pintu masuk rangka C.80/0,55 penutup multipleks 9mm 112.56 m² 185,000.00 8,537,676.00
4 Pasang partisi layar rangka hollow 4/4 penutup gybsumborad 9mm 122.47 m² 115,000.00 5,774,460.50
5 Pasang Rock wool 5cm density 80 877.40 m² 177,000.00 63,672,918.00
6 Pasang plafond t.6m rangka holow 2/2 penutup gybsumboard 9mm 420.00 m² 105,000.00 18,081,000.00
7 Pasang gantungan plafond kawat d. 4mm 420.00 m² 15,000.00 2,583,000.00
8 Plesteran + acian lantai r. cinema 225.00 m² 65,000.00 5,996,250.00
9 Kusen, pintu masuk + acesoris 2.00 unit 18,000,000.00 14,760,000.00
10 Cat dinding luar r. cinema ex. Catylac 98.08 m² 27,500.00 1,105,852.00
11 Cat dico pintu cinema ex. Sintetic 42.24 m² 75,000.00 1,298,880.00
12 Pasang lantai multiplek 18mm 439.60 m² 208,000.00 37,489,088.00
13 Pasang karpet dinding, pasang spone 2cm + pasang kain 877.40 m² 155,000.00 55,758,770.00
14 Pasang karpet lantai r. cinema 248.00 m² 102,500.00 10,422,200.00
15 Pasang karpet plafond 382.00 m² 87,500.00 13,704,250.00
16 Pasang rangka layar pipa 2,5" 2.00 unit 12,000,000.00 9,840,000.00
17 Pasang panggung tempat spiker 2.00 unit 6,000,000.00 4,920,000.00
18 Pasang vinil lantai tribune 345.00 m² 135,000.00 19,095,750.00
19 Pasang karung goni dinding belakang layar 154.00 m² 12,500.00 789,250.00
SUB TOTAL 383,548,214.50

V PEKERJAAN PELAPIS LANTAI


1 Keramik lantai r. tunggu granit tile 60x60 ex. Garuda 406.00 m² 230,000.00 38,285,800.00
SUB TOTAL 38,285,800.00

VI PEKERJAAN LAIN-LAIN
1 Pekerjaan pemasangan logo "NEW STAR CINEPLEX" + accesoris atas pintu 1.00 ls 30,000,000.0 12,300,000.00
SUB TOTAL 12,300,000.00

TOTAL 551,742,977.91

Surabaya, 29 Desember 2015


PT. ROSA AGUNG MULIA

Ir. BINTARAN ARYANTO


Arsitek
RENCANA ANGGARAN BIAYA PEKERJAAN ELEKTRIKAL
PEKERJAAN : PEMBANGUNAN GEDUNG NSC 2 STUDIO
LOKASI JOMBANG
PEKERJAAN ELEKTRIKAL ENTRANCE, KASIR, CAFÉ, R. GANTI DAN KANTOR
Volume Harga Satuan Total Harga
No. Uraian Pekerjaan Satuan
Kontrak (Rp.) (Rp.)

1 Instalasi Titik lampu Cable NYM 2,5mm (Suprime)/Setara Ttk 110.00 255,000.00 11,500,500.00
2 Instalasi Stop Contak Cable NYM 2,5mm (Suprime)/setara Ttk 24.00 255,000.00 2,509,200.00
3 Saklar Satu Gang (Panasonic) Bh 7.00 38,500.00 110,495.00
4 Saklar Dua Gang (Panasonic) Bh 32.00 49,500.00 649,440.00
5 Stop Kontak (Panasonic) Bh 24.00 42,500.00 418,200.00
6 Down Light 5''+PL 18Watt (Meiwa DL 996 white) Unit 110.00 105,000.00 4,735,500.00
7 Panel SDP Penerangan, stop contak dan AC Unit 1.00 12,000,000.00 4,920,000.00
8 Material bantu dan support ls 1.00 1,000,000.00 410,000.00

SUB TOTAL 25,253,335

PEKERJAAN INSTALASI LISTRIK R. CINEMA1-2 DAN R. OPERATOR

Volume Harga Satuan Total Harga


No. Uraian Pekerjaan Satuan
Kontrak (Rp.) (Rp.)

1 Instalasi Titik lampu Cable NYM 2,5mm (Suprime) Ttk 30.00 225,000.00 2,767,500.00
2 Instalasi Stop Contak Cable NYM 2,5mm (Suprime) Ttk 12.00 225,000.00 1,107,000.00
3 Intalasi kabel power Dogotal proyektor m 46.00 30,000.00 565,800.00
4 Saklar Daimer (Panasonic) Bh 6.00 250,000.00 615,000.00
4 Saklar satu Gang (Panasonic) Bh 2.00 38,500.00 31,570.00
5 Saklar Dua Gang (Panasonic) Bh 2.00 49,500.00 40,590.00
6 Stop Kontak (Panasonic) Bh 12.00 42,500.00 209,100.00
7 Down Light 5''+PL 18Watt (Meiwa DL 996 white) Unit 30.00 105,000.00 1,291,500.00

SUB TOTAL 6,628,060

PEKERJAAN AIR CONDITIONER ENTRANCE, KANTOR, KASIR, CAFÉ KANTOR

Volume Harga Satuan Total Harga


No. Uraian Pekerjaan Satuan
Kontrak (Rp.) (Rp.)

1 AC Split Wall Mounted 2 PK ''Changhong''/SETARA Unit 1.00 9,550,000.00 3,915,500.00


2 AC Floort Standing 5 PK ''Changhong'' Unit 3.00 24,000,000.00 29,520,000.00
3 Instalasi Pipa Refrigrant dan Kabel Kontrol AC 1+ 2 PK Mtr 73.00 125,000.00 3,741,250.00
4 Instalasi Stop kontak AC Ttk 6.00 360,000.00 885,600.00
5 Stop Kontak (Panasonic) Bh 6.00 42,500.00 104,550.00
6 Instalasi Cable Power + Control AC 2 PK Mtr 237.00 35,000.00 3,400,950.00
7 Drainase AC + Isolasi Mtr 90.00 45,000.00 1,660,500.00
8 Material Bantu Lot 1.00 2,000,000.00 820,000.00

SUB TOTAL 44,048,350

PEKERJAAN AIR CONDITIONER R. CINEMA1-2 DAN R. OPERATOR

Volume Harga Satuan Total Harga


No. Uraian Pekerjaan Satuan
Kontrak (Rp.) (Rp.)

1 AC Split Wall Mounted 2 PK ''Changhong''/setara Unit 2.00 9,500,000.00 7,790,000.00


2 AC Kaset 5 PK ''Changhong'' Unit 4.00 24,000,000.00 39,360,000.00
3 Instalasi Pipa Refrigrant dan Kabel Kontrol AC 2 PK Mtr 40.00 125,000.00 2,050,000.00
4 Instalasi Pipa Refrigrant dan Kabel Kontrol AC 5 PK Mtr 76.00 175,000.00 5,453,000.00
5 Instalasi Stop kontak AC Ttk 6.00 360,000.00 885,600.00
6 Stop Kontak (Panasonic) Bh 6.00 42,500.00 104,550.00
7 Instalasi Cable Power AC 2 PK mtr 63.00 25,000.00 645,750.00
8 Instalasi Cable Power AC 5 PK (3 Phase) mtr 231.00 60,000.00 5,682,600.00
9 Drainase AC + Isolasi Mtr 62.00 45,000.00 1,143,900.00
10 Panel SDP Penerangan, stop contak dan AC Unit 1.00 13,000,000.00 5,330,000.00
11 Material Bantu Lot 1.00 1,500,000.00 615,000.00

SUB TOTAL 69,060,400

PEKERJAAN KABEL POWER


Volume Harga Satuan Total Harga
No. Uraian Pekerjaan Satuan
Kontrak (Rp.) (Rp.)

1 Kabel tray Mtr 48.00 150,000.00 2,952,000.00


2 Kabel Power 4x70mm + tray Mtr 48.00 450,000.00 8,856,000.00
3 Material Bantu Lot 1.00 3,000,000.00 1,230,000.00
4 NFB 100 Amper Unit 1.00 850,000.00 348,500.00

SUB TOTAL 13,386,500

TOTAL PEKERJAAN ELEKTRIKAL DAN AIR CONDITIONER + KABEL FEEDER 158,376,645.00

Surabaya, 29 Desember 2015


CATATAN : PT. ROSA AGUNG MULIA
PEKERJAAN ELEKTRIKAL TIDAK TERMASUK SAMBUNGAN
KE PANEL INDUK

Ir. BINTARAN ARYANTO


Arsitek
RENCANA ANGGARAN BIAYA.
PEKERJAAN : PEMBANGUNAN GEDUNG NSC 2 STUDIO
LOKASI JOMBANG

PEKERJAAN TRIBUN
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SAT
( Rp. ) ( Rp. )

PEKERJAAN TRIBUN & R. PROYEKTOR


1 UNP 100 1,857.40 kg 18,500.00 14,088,379.00
2 WF 150 906.40 kg 18,500.00 6,875,044.00
3 Pipa dia 2,5" Tebal 2,2 mm 3,240.00 kg 18,500.00 24,575,400.00
4 Siku 40.40 Tebal, 3,2 SNI 1,918.00 kg 18,500.00 14,548,030.00
5 Besi cor dia 16 3,117.83 kg 18,500.00 23,648,740.55
6 Besi cor dia 12 151.17 kg 18,500.00 1,146,624.45
7 Suport Mob + demob alat kerja & pekerja 1.00 ls 4,000,000.00 1,640,000.00
10,687.00 SUB TOTAL 86,522,218.00

Surabaya, 29 Desember 2015


PT. ROSA AGUNG MULIA

Ir. BINTARAN ARYANTO


Arsitek
REKAPITULASI RENCANA ANGGARAN BIAYA.

PEKERJAAN : PEMBANGUNAN GEDUNG NSC 2 STUDIO


LOKASI : JOMBANG

JUMLAH HARGA
NO URAIAN PEKERJAAN
(Rp)

A PEKERJAAN SIPIL
I PEKERJAAN PERSIAPAN & PEMBONGKARAN Rp. 17,425,000.00
II PEKERJAAN ENTRANCE, HALL, KASIR, CAFÉ, R. GANTI DAN KANTOR Rp. 80,544,676.41
III PEKERJAAN RUANG OPERATOR Rp. 19,639,287.00
IV PEKERJAAN R. CINEMA Rp. 383,548,214.50
V PEKERJAAN PELAPIS LANTAI Rp. 38,285,800.00
VI PEKERJAAN LAIN-LAIN Rp. 12,300,000.00

SUB TOTAL Rp. 551,742,977.91

II PEKERJAAN TRIBUN DAN R. PROYEKTOR Rp. 86,522,218.00

SUB TOTAL Rp. 86,522,218.00

B PEKERJAAN MEKANIKAL DAN ELEKTRICAL


I PEKERJAAN ELEKTRIKAL ENTRANCE, KASIR, CAFÉ, R. GANTI DAN KANTOR Rp. 25,253,335.00
II PEKERJAAN INSTALASI LISTRIK R. CINEMA1-2 DAN R. OPERATOR Rp. 6,628,060.00
III PEKERJAAN AIR CONDITIONER ENTRANCE, KANTOR, KASIR, CAFÉ KANTOR Rp. 44,048,350.00
IV PEKERJAAN AIR CONDITIONER R. CINEMA1-2 DAN R. OPERATOR Rp. 69,060,400.00
V PEKERJAAN KABEL POWER Rp. 13,386,500.00

SUB TOTAL Rp. 158,376,645.00

C PEKERJAAN FURNITURE Rp. 50,225,000.00

TOTAL Rp. 846,866,840.91


DIBULATKAN Rp. 846,800,000.00
TERBILANG : Delapan Ratus Empat Puluh Enam Juta Delapan Ratus Ribu Rupiah

CATATAN : Surabaya, 29 Desember 2015


PEKERJAAN ELEKTRIKAL TIDAK TERMASUK SAMBUNGAN PT. ROSA AGUNG MULIA
KE PLN DAN TAMBAH DAYA PLN

Ir. BINTARAN ARYANTO


Arsitek

Anda mungkin juga menyukai