Section C.1.1. PEKERJAAN PELAPIS DINDING DAN PELAPIS LANTAI Rp. 1.154.927.364,38
B. LANTAI 2
1 Rail guard dengan wall guard Alumunium Extrude profil 122,65 m¹ Rp. 990.000,00 Rp. 121.423.500,00
(Cover Vinyl Handrail, Endcap Section)
- Alumunium Extrude profil 140mm
- Cover Vinyl Handrail 140mm
- Braket Wall
- Return Section (End Cap)
- Ongkos pasang, alat bantu dan overhead
2 Memasang lantai vinyl sheet 409,98 m² Rp. 748.012,50 Rp. 306.670.164,75
C. LANTAI 3
1 Rail guard dengan wall guard Alumunium Extrude profil 135,09 m¹ Rp. 990.000,00 Rp. 133.739.100,00
(Cover Vinyl Handrail, Endcap Section)
- Alumunium Extrude profil 140mm
- Cover Vinyl Handrail 140mm
- Braket Wall
- Return Section (End Cap)
- Ongkos pasang, alat bantu dan overhead
2 Memasang lantai vinyl sheet 381,24 m² Rp. 748.012,50 Rp. 285.172.285,50
Jumlah Section C.1.1. PEKERJAAN PELAPIS DINDING DAN PELAPIS LANTAI Rp. 1.154.927.364,38
i. Passbox Lapis Pb uk. 800 x 800 x 500 mm, SS Mirror Elektrik Interlock system 2,00 unit Rp. 73.950.000,00 Rp. 147.900.000,00
• Lampu LED dia.22 mm, 220 Volt, Warna Merah & Hijau, Mekanikal Interlock
• Power Supply, Pilot Lamp, Switch, Relay, Engsel,Handle, Seal & kaca Pb 15 mm
j. Lemari Alat : SS Mirror SUS 304 uk. 1200x1600x400mm 1,00 unit Rp. 43.350.000,00 Rp. 43.350.000,00
k. Lemari Obat : SS Mirror SUS 304 uk. 600x1600x400mm 1,00 unit Rp. 43.350.000,00 Rp. 43.350.000,00
l. Information Panel size 1194 x 1050 x 200 mm 1,00 unit Rp. 83.776.000,00 Rp. 83.776.000,00
• Material Electro - Static Spraying Iron
• Enable to Install necessary : air control box, Power Switch
m. Relief Damfer size : 340 x 340 mm Hemisphere, stainless steel, dia. 250 mm 1,00 unit Rp. 12.342.000,00 Rp. 12.342.000,00
• Material Electro - Static Spraying Steel
n. Vinil Homogenous ex. Amstrong, untuk Lantai tebal 2 mm 41,43 m² Rp. 748.012,50 Rp. 30.990.157,88
• Tebal : 2 mm
• Protection : Trueshield Coating / PUR
• Antibacterial, Anti Staining, Anti Static, Anti Iodine / Pewarna, Anti Scuffing
d. Accessories : Alumunium Curving & Consumable 1,00 lot Rp. 29.606.350,00 Rp. 29.606.350,00
e. LED Light 40 Watt size 1200x300x22,5mm 14,00 unit Rp. 5.376.250,00 Rp. 75.267.500,00
f. Operating Timer LED 32" (waktu, countdown, temp, humudity) 1,00 unit Rp. 25.755.000,00 Rp. 25.755.000,00
• TV LED 32", mouse wireless, HMI + kabel HDMI
g. X-Ray Film Viewer, kap. 2 NEC ukuran 800 (w) 600 (h) mm 1,00 unit Rp. 15.725.000,00 Rp. 15.725.000,00
h. Sliding Hermetic Automatic Single Door size 1600 (w) x 2150 (h) mm 1,00 unit Rp. 157.250.000,00 Rp. 157.250.000,00
• View window Uk. : 600 (w) x 400 (h) mm, anti radiasi glass 8 mm
• Frame door & Kusen ex. TORMAX
• Mesin : TORMAX
i. Passbox Lapis Pb uk. 800 x 800 x 500 mm, SS Mirror Elektrik Interlock system 2,00 unit Rp. 73.950.000,00 Rp. 147.900.000,00
• Lampu LED dia.22 mm, 220 Volt, Warna Merah & Hijau, Mekanikal Interlock
• Power Supply, Pilot Lamp, Switch, Relay, Engsel,Handle, Seal & kaca Pb 15 mm
j. Lemari Alat : SS Mirror SUS 304 uk. 1200x1600x400mm 1,00 unit Rp. 43.350.000,00 Rp. 43.350.000,00
k. Lemari Obat : SS Mirror SUS 304 uk. 600x1600x400mm 1,00 unit Rp. 43.350.000,00 Rp. 43.350.000,00
l. Information Panel size 1194 x 1050 x 200 mm 1,00 unit Rp. 83.776.000,00 Rp. 83.776.000,00
• Material Electro - Static Spraying Iron
• Enable to Install necessary : air control box, Power Switch
m. Relief Damfer size : 340 x 340 mm Hemisphere, stainless steel, dia. 250 mm 1,00 unit Rp. 12.342.000,00 Rp. 12.342.000,00
• Material Electro - Static Spraying Steel
n. Vinil Homogenous ex. Amstrong, untuk Lantai tebal 2 mm 31,97 m² Rp. 748.012,50 Rp. 23.913.959,63
• Tebal : 2 mm
• Protection : Trueshield Coating / PUR
• Antibacterial, Anti Staining, Anti Static, Anti Iodine / Pewarna, Anti Scuffing
6 Stainless Steel Scrub Sink For 3 Person 3,00 unit Rp. 178.500.000,00 Rp. 535.500.000,00
Product Feature :
Bak Scrup Station be hospital Equipment automatic Sensor, automatic hand drayer and shoap,
stainless steel plat 1.2mm, finishing polished dimensi 240 x 65 x 185, Power Suplay 250W 220
V AC 50 Hz Filtering & UV Sterilizer system, Filter : 1 Pcs main filter 5 micron UV lamp 2 pcs
30 W, 3 Faucets, Water Heater
B. LANTAI 2
1 Pembuatan meja nurse station (ruang PICU dan ICU) 14,68 m¹ Rp. 3.015.000,00 Rp. 44.260.200,00
• Multiplek playwood 18 mm
• Finishing HPL
• List edging PVC 22 mm
• Profil Stainless SUS.304
• Stop kontak
• Assesoris dekson
2 Pemasangan Laci/Rak Dibawah Meja (pantry) 1,85 m¹ Rp. 1.750.000,00 Rp. 3.237.500,00
• Multiplek playwood 18 mm
• Finishing HPL
• Assesoris dekson
3 Pemasangan hospital & curtain rail (ruang ICU) 47,30 m¹ Rp. 454.500,00 Rp. 21.497.850,00
C. LANTAI 3
1 Pembuatan meja nurse station 10,75 m¹ Rp. 3.015.000,00 Rp. 32.411.250,00
• Multiplek playwood 18 mm
• Finishing HPL
• List edging PVC 22 mm
• Profil Stainless SUS.304
• Stop kontak
• Assesoris dekson
Section C.2.5. PEKERJAAN PENGADAAN DAN PEMASANGAN PNEUMATIC TUBE SYSTEM (PTS) Rp. 4.167.698.469,00
B. Lantai 2
1 Pengadaan & Pemasangan Instalasi Hydrant
a. Fire Hose Cabinet ( FHC ), 125 x 75 x 18 cm 1,00 unit Rp. 4.736.250,00 Rp. 4.736.250,00
~ Hydrant box 125 x 75 x 18 cm (1 bh)
~ Jet star fire hose 1.5" x 30 m (1 rol)
~ Hydrant valve ozeki 1.5" (1 bh)
~ Seamless nozzle 1.5" (1 bh)
~ Hose rack 1.5" (1 bh)
b. Fire extinguisher (ABC type 6 kg) inc. bracket 8,00 bh Rp. 1.706.085,00 Rp. 13.648.680,00
c. Pemipaan BSP Schedule 40 termasuk fitting, sambungan,
Pemipaan BSP Schedule 40 termasuk fitting, sambungan, penggantung
dan alat bantu lainnya :
c1. BSP Sch.40 diameter 65 mm 34,49 m¹ Rp. 203.544,56 Rp. 7.020.251,96
c2. BSP Sch.40 diameter 40 mm 2,05 m¹ Rp. 113.703,75 Rp. 233.092,69
2 Pengadaan & Pemasangan Instalasi Sprinkler
a. Pemipaan BSP Schedule 40 termasuk fitting, sambungan, penggantung
dan alat bantu lainnya :
a1. BSP Sch.40 diameter 25 mm 129,60 m¹ Rp. 69.244,88 Rp. 8.974.135,80
a2. BSP Sch.40 diameter 32 mm 17,40 m¹ Rp. 87.652,13 Rp. 1.525.146,98
a3. BSP Sch.40 diameter 40 mm 17,59 m¹ Rp. 113.703,75 Rp. 2.000.048,96
a4. BSP Sch.40 diameter 50 mm 24,93 m¹ Rp. 135.573,75 Rp. 3.379.853,59
a5. BSP Sch.40 diameter 65 mm 12,35 m¹ Rp. 203.544,56 Rp. 2.513.775,35
a6. BSP Sch.40 diameter 75 mm 14,22 m¹ Rp. 247.284,56 Rp. 3.516.386,48
a7. BSP Sch.40 diameter 80 mm 33,04 m¹ Rp. 247.284,56 Rp. 8.170.281,95
a8. BSP Sch.40 diameter 100 mm 3,89 m¹ Rp. 355.541,06 Rp. 1.383.054,73
b. Sprinkler head pendant type c/w ceiling plate 75,00 bh Rp. 113.355,00 Rp. 8.501.625,00
c. Flashing valve diameter 50 mm 1,00 bh Rp. 6.517.710,00 Rp. 6.517.710,00
d. Gate Valve dia 100 mm ( kontrol valve ) 1,00 bh Rp. 36.649.710,00 Rp. 36.649.710,00
e. Branch Control Valve ( BCV ) dia. 80 mm 1,00 set Rp. 18.438.750,00 Rp. 18.438.750,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
C. Lantai 3
1 Pengadaan & Pemasangan Instalasi Hydrant
a. Fire Hose Cabinet ( FHC ), 125 x 75 x 18 cm 1,00 unit Rp. 4.736.250,00 Rp. 4.736.250,00
~ Hydrant box 125 x 75 x 18 cm (1 bh)
~ Jet star fire hose 1.5" x 30 m (1 rol)
~ Hydrant valve ozeki 1.5" (1 bh)
~ Seamless nozzle 1.5" (1 bh)
~ Hose rack 1.5" (1 bh)
b. Fire extinguisher (ABC type 6 kg) inc. bracket 7,00 bh Rp. 1.706.085,00 Rp. 11.942.595,00
c. Pemipaan BSP Schedule 40 termasuk fitting, sambungan, penggantung
dan alat bantu lainnya :
c1. BSP Sch.40 diameter 65 mm 5,00 m¹ Rp. 203.544,56 Rp. 1.017.722,81
c2. BSP Sch.40 diameter 40 mm 2,05 m¹ Rp. 113.703,75 Rp. 233.092,69
2 Pengadaan & Pemasangan Instalasi Sprinkler
a. Pemipaan BSP Schedule 40 termasuk fitting, sambungan, penggantung
dan alat bantu lainnya :
a1. BSP Sch.40 diameter 25 mm 86,00 m¹ Rp. 69.244,88 Rp. 5.955.059,25
a2. BSP Sch.40 diameter 32 mm 7,30 m¹ Rp. 87.652,13 Rp. 639.860,51
a3. BSP Sch.40 diameter 40 mm 13,79 m¹ Rp. 113.703,75 Rp. 1.567.974,71
a4. BSP Sch.40 diameter 50 mm 20,34 m¹ Rp. 135.573,75 Rp. 2.757.570,08
a5. BSP Sch.40 diameter 65 mm 11,80 m¹ Rp. 203.544,56 Rp. 2.401.825,84
a6. BSP Sch.40 diameter 75 mm 21,50 m¹ Rp. 247.284,56 Rp. 5.316.618,09
a7. BSP Sch.40 diameter 80 mm 3,00 m¹ Rp. 247.284,56 Rp. 741.853,69
b. Sprinkler head pendant type c/w ceiling plate 43,00 bh Rp. 113.355,00 Rp. 4.874.265,00
c. Flashing valve diameter 50 mm 1,00 bh Rp. 6.517.710,00 Rp. 6.517.710,00
d. Gate Valve dia 75 mm ( kontrol valve ) 1,00 bh Rp. 22.602.960,00 Rp. 22.602.960,00
e. Branch Control Valve ( BCV ) dia. 80 mm 1,00 set Rp. 18.438.750,00 Rp. 18.438.750,00
E. SHAFT / RISER
1 Pemipaan BSP Schedule 40 termasuk fitting, sambungan, penggantung
dan alat bantu lainnya :
a. Sistem Hydrant
~ Diameter 150 mm 6,27 m¹ Rp. 587.545,31 Rp. 3.683.909,11
~ Diameter 100 mm 4,20 m¹ Rp. 355.541,06 Rp. 1.493.272,46
~ Diameter 65 mm 4,50 m¹ Rp. 203.544,56 Rp. 915.950,53
b. Sistem Sprinkler
~ Diameter 125 mm 6,27 m¹ Rp. 430.810,31 Rp. 2.701.180,66
~ Diameter 100 mm 4,20 m¹ Rp. 355.541,06 Rp. 1.493.272,46
~ Diameter 75 mm 4,50 m¹ Rp. 247.284,56 Rp. 1.112.780,53
2 Pengadaan & Pemasangan Gate Valve :
a. Diameter 25 mm 2,00 bh Rp. 6.466.230,00 Rp. 12.932.460,00
b. Diameter 65 mm 2,00 bh Rp. 21.889.710,00 Rp. 43.779.420,00
c. Diameter 100 mm 1,00 bh Rp. 36.649.710,00 Rp. 36.649.710,00
3 Pengadaan & Pemasangan Automatic Air Vent ( AAV ) 1,00 bh Rp. 1.680.772,50 Rp. 1.680.772,50
Lantai 3
B.1. Pekerjaan Pemipaan
a. Instalasi Jaringan Oksigen
→ Pipa Tembaga ASTM B 819 Type L
~ Diameter 3/8" 65,00 m¹ Rp. 89.200,00 Rp. 5.798.000,00
~ Diameter 1/2" 92,00 m¹ Rp. 143.100,00 Rp. 13.165.200,00
~ Diameter 5/8" 72,00 m¹ Rp. 203.600,00 Rp. 14.659.200,00
~ Diameter 3/4" 33,00 m¹ Rp. 258.300,00 Rp. 8.523.900,00
→ Supporting Material 1,00 ls Rp. 2.107.315,00 Rp. 2.107.315,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
a. Alat Utama
Pengadaan dan pemasangan peralatan utama H.V.A.C, lengkap dengan support dan accessories
1. AHU - 1.1 1,00 unit Rp. 390.000.000,00 Rp. 390.000.000,00
Kapasitas : 100.000 BTUH
A.F.R : 1.871 CFM
E.S.P : 750 Pa
P.I : 4,8kw, 380V, 3Ph, 50Hz
Type : Customize Split Duct
Lengkap dengan : ~ Pre Filter GFF 35%
~ Medium Filter GFF 95%
~ Booster Fan
~ Magnehelic 0 - 700 pa& Box
~ Hot Gas System
b. Instalasi Pipa
1. Pipa Refrigerant
Pengadaan dan pemasangan Pipa Copper Tube Class ASTM B.2.80 lengkap
dengan Isolasi Superlone, density = 70 kg/m3, t = 15 mm
- Diameter 3/8" 75,00 m¹ Rp. 91.400,00 Rp. 6.855.000,00
- Diameter 5/8" 75,00 m¹ Rp. 167.000,00 Rp. 12.525.000,00
2. Pipa Drain
Pengadaan dan pemasangan Pipa PVC Class AW
- Diameter 25 mm 30,00 m¹ Rp. 31.191,75 Rp. 935.752,50
c. Filter & Control
1. Room Pressure Differensial Indicator
- Hepa Pressure Differential Indicator( Magnehelic 0 ~ 700 pascal ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
- Room Pressure Differential Indicator( Magnehelic 0 ~ 60 Pa pascal ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
2. Hose Pneumatic dan Nozzle 1,00 ls Rp. 4.000.000,00 Rp. 4.000.000,00
3. Temprature dan Humidity Control lengkap dengan sensor 1,00 set Rp. 12.875.030,00 Rp. 12.875.030,00
4. Box Magnehelic SS. 304, Size. 300 x 300 x 70 2,00 set Rp. 2.574.620,00 Rp. 5.149.240,00
d. Elektrikal
1. Panel control AC 1,00 unit Rp. 140.833.000,00 Rp. 140.833.000,00
~ MCCB, MCB, Push Button, Contactor, Relay, Selector, Switch, Pilot Lamp
2. Kabel power
Dari panel Control ke panel incoming 100 m¹ Rp. 60.676,88 Rp. 6.067.687,50
~ NYY 4 x 4mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke unit outdoor 100 m¹ Rp. 34.689,38 Rp. 3.468.937,50
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Booster Fan 27 m¹ Rp. 34.689,38 Rp. 936.613,13
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Dehumidifier 27 m¹ Rp. 35.870,63 Rp. 968.506,88
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm
Kabel Control NYMHY 2 (3 x 0,75mm) 100 m¹ Rp. 29.846,25 Rp. 2.984.625,00
e. Instalasi ducting
Pengadaan dan Pemasangan Duct Galvanished Sheet lengkap dengan Isolasi
Thermobreak, Density = 25 kg/m2, t = 15mm
1. Supply
~ Dimensi 500x500 mm 10,00 m¹ Rp. 1.166.000,00 Rp. 11.660.000,00
~ Dimensi 450x450 mm 7,00 m¹ Rp. 1.058.000,00 Rp. 7.406.000,00
~ Dimensi 250x250 mm 15,00 m¹ Rp. 624.000,00 Rp. 9.360.000,00
2. Return
~ Dimensi 450x450 mm 10,00 m¹ Rp. 1.058.000,00 Rp. 10.580.000,00
~ Dimensi 350x350 mm 10,00 m¹ Rp. 841.000,00 Rp. 8.410.000,00
~ Dimensi 250x250 mm 22,00 m¹ Rp. 624.000,00 Rp. 13.728.000,00
3. Fresh Air
~ Dimensi 200x200 mm 17,00 m¹ Rp. 515.000,00 Rp. 8.755.000,00
4. Accessories Duct
~ Plenum Box, 1000 x 800 x 500 mm 2,00 set Rp. 5.060.460,00 Rp. 10.120.920,00
` S.A.D Perforated SS 304, 400x400 mm 6,00 pcs Rp. 3.137.215,00 Rp. 18.823.290,00
~ R.A.G Perforated SS 304, 500x250 mm 4,00 pcs Rp. 2.941.320,00 Rp. 11.765.280,00
~ Louver Grille Alumunium Amodized c/w OBD, 350x350 mm 2,00 pcs Rp. 1.553.650,00 Rp. 3.107.300,00
~ Volume Damper, 300x300 mm 7,00 pcs Rp. 1.265.115,00 Rp. 8.855.805,00
` Box Chamber, 550x300 mm 4,00 pcs Rp. 2.483.910,00 Rp. 9.935.640,00
~ Box Chamber, 400x400 mm 6,00 pcs Rp. 2.338.195,00 Rp. 14.029.170,00
B. Lantai 2
1 Outdoor Unit VRV
• Outdoor Kapasitas : 341000 BTU/h VRF SMMS 7 MMY-AP3617T8P-ID 1,00 unit Rp. 292.988.475,00 Rp. 292.988.475,00
2 Indoor Unit VRV
• Indoor Kapasitas : 19100 BTU/h Cassette (4 Way) MMU-AP0184HP-ID 3,00 unit Rp. 14.877.405,00 Rp. 44.632.215,00
• Indoor Kapasitas : 24200 BTU/h Cassette (4 Way) MMU-AP0244HP-ID 4,00 unit Rp. 15.007.680,00 Rp. 60.030.720,00
• Indoor Kapasitas : 30700 BTU/h Cassette (4 Way) MMU-AP0304HP-ID 2,00 unit Rp. 15.520.095,00 Rp. 31.040.190,00
• Indoor Kapasitas : 7500 BTU/h Wall Mounted MMK-AP0077HP-ID 16,00 unit Rp. 10.682.550,00 Rp. 170.920.800,00
• Indoor Kapasitas : 12300 BTU/h Wall Mounted MMK-AP0127HP-ID 2,00 unit Rp. 11.637.900,00 Rp. 23.275.800,00
3 Y-Branch (Indoor pipe connection) 26,00 bh Rp. 2.283.000,00 Rp. 59.358.000,00
4 T-Branch 1,00 bh Rp. 2.963.000,00 Rp. 2.963.000,00
5 Remote wired control 27,00 bh Rp. 1.146.000,00 Rp. 30.942.000,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
3 Fresh Air
~ Dimensi 200x200 mm 34,00 m¹ Rp. 515.000,00 Rp. 17.510.000,00
4 Accessories Duct
~ Plenum Box, 1000 x 800 x 500 mm 4,00 set Rp. 5.060.460,00 Rp. 20.241.840,00
~ S.A.D Perforated SS 304, 400x400 mm 12,00 pcs Rp. 3.137.215,00 Rp. 37.646.580,00
~ R.A.G Perforated SS 304, 500x250 mm 8,00 pcs Rp. 2.941.320,00 Rp. 23.530.560,00
~ Louver Grille Alumunium Amodized c/w OBD, 350x350 mm 4,00 pcs Rp. 1.553.650,00 Rp. 6.214.600,00
~ Volume Damper, 300x300 mm 14,00 pcs Rp. 1.265.115,00 Rp. 17.711.610,00
~ Box Chamber, 550x300 mm 8,00 pcs Rp. 2.483.910,00 Rp. 19.871.280,00
~ Box Chamber, 400x400 mm 12,00 pcs Rp. 2.338.195,00 Rp. 28.058.340,00
14 Air Handling Unit (AHU) Untuk Ruang ISOLASI 1
Dimensi : 6000 x3000 x 3000
Temperature : 23 ± 2 ᵒC
Humidity : 55 ± 5%
Room Class : 100.000 Class (0,5 micron)
a, Alat Utama
Pengadaan dan pemasangan peralatan utama H.V.A.C, lengkap dengan support dan accessories
1 AHU - 2.2 1,00 unit Rp. 172.000.000,00 Rp. 172.000.000,00
Kapasitas : 40.000 BTUH
A.F.R : 793 CFM
E.S.P : - Pa
P.I : 4,8kw, 380V, 3Ph, 50Hz
Type : Customize Split Duct
Lengkap dengan : √ Pre Filter GFF 35%
√ Medium Filter GFF 95%
√ Booster Fan
√ Magnehelic 0 - 700 pa& Box
√ Hot Gas System
Exhaust Fan : √ Kap. 1058 CFM 1,00 unit Rp. 24.414.500,00 Rp. 24.414.500,00
√ Type AXIAL FAN
b. Instalasi Pipa
1. Pipa Refrigerant
Pengadaan dan pemasangan Pipa Copper Tube Class ASTM B.2.80 lengkap
dengan Isolasi Superlone, density = 70 kg/m3, t = 15 mm
- Diameter 3/8" 70,00 m¹ Rp. 91.400,00 Rp. 6.398.000,00
- Diameter 5/8" 70,00 m¹ Rp. 167.000,00 Rp. 11.690.000,00
2. Pipa Drain
Pengadaan dan pemasangan Pipa PVC Class AW
- Diameter 25 mm 30,00 m¹ Rp. 31.191,75 Rp. 935.752,50
c. Filter & Control
1. Room Pressure Differensial Indicator
- Hepa Pressure Differential Indicator( Magnehelic 0 ~ 700 pascal ) 2,00 pcs Rp. 6.437.515,00 Rp. 12.875.030,00
- Room Pressure Differential Indicator( Magnehelic -30 ~ 30 Pa ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
- Housing filter (Exhaust) 1,00 pcs Rp. 5.150.205,00 Rp. 5.150.205,00
- Prefilter 24x24x2 1,00 pcs Rp. 9.012.135,00 Rp. 9.012.135,00
- HEPA Filter 24x24x12 1,00 pcs Rp. 9.012.135,00 Rp. 9.012.135,00
- Carbon filter 24x24x2 1,00 pcs Rp. 15.450.615,00 Rp. 15.450.615,00
2. Hose Pneumatic dan Nozzle 1,00 ls Rp. 4.000.000,00 Rp. 4.000.000,00
3. Temprature dan Humidity Control lengkap dengan sensor 1,00 set Rp. 12.875.030,00 Rp. 12.875.030,00
4. Box Magnehelic SS. 304, Size. 300 x 300 x 70 3,00 set Rp. 2.574.620,00 Rp. 7.723.860,00
d. Elektrikal
1. Panel control AC 1,00 unit Rp. 140.833.000,00 Rp. 140.833.000,00
~ MCCB, MCB, Push Button, Contactor, Relay, Selector, Switch, Pilot Lamp
2. Kabel power
Dari panel Control ke panel incoming 100 m¹ Rp. 60.676,88 Rp. 6.067.687,50
~ NYY 4 x 4mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke unit outdoor 100 m¹ Rp. 34.689,38 Rp. 3.468.937,50
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Booster Fan 27 m¹ Rp. 34.689,38 Rp. 936.613,13
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Dehumidifier 27 m¹ Rp. 35.870,63 Rp. 968.506,88
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm
Kabel Control NYMHY 2 (3 x 0,75mm) 100 m¹ Rp. 29.846,25 Rp. 2.984.625,00
Dari panel Control ke Exhaust 100 m¹ Rp. 35.870,63 Rp. 3.587.062,50
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm
e. Instalasi ducting
Pengadaan dan Pemasangan Duct Galvanished Sheet lengkap dengan Isolasi
Thermobreak, Density = 25 kg/m2, t = 15mm
1 Supply
~ Dimensi 300x300 mm 25,00 m¹ Rp. 732.000,00 Rp. 18.300.000,00
~ Dimensi 250x250 mm 7,00 m¹ Rp. 624.000,00 Rp. 4.368.000,00
~ Dimensi 150x150 mm 7,00 m¹ Rp. 407.000,00 Rp. 2.849.000,00
2 Return
~ Dimensi 300x300 mm 15,00 m¹ Rp. 732.000,00 Rp. 10.980.000,00
~ Dimensi 250x250 mm 12,00 m¹ Rp. 624.000,00 Rp. 7.488.000,00
~ Dimensi 150x150 mm 7,00 m¹ Rp. 407.000,00 Rp. 2.849.000,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
3 Exhaust
~ Dimensi 300x300 mm 15,00 m¹ Rp. 732.000,00 Rp. 10.980.000,00
4 Fresh Air
~ Dimensi 200x200 mm 15,00 m¹ Rp. 515.000,00 Rp. 7.725.000,00
5 Accessories Duct
~ Plenum Box, 1000 x 800 x 500 mm 2,00 set Rp. 5.060.460,00 Rp. 10.120.920,00
~ S.A.D Perforated SS 304, 400x400 mm 3,00 pcs Rp. 3.137.215,00 Rp. 9.411.645,00
~ R.A.G Perforated SS 304, 500x250 mm 2,00 pcs Rp. 2.941.320,00 Rp. 5.882.640,00
~ Louver Grille Alumunium Amodized c/w OBD, 350x350 mm 2,00 pcs Rp. 1.553.650,00 Rp. 3.107.300,00
~ Volume Damper, 300x300 mm 2,00 pcs Rp. 1.265.115,00 Rp. 2.530.230,00
~ Volume Damper, 250x250 mm 1,00 pcs Rp. 1.054.745,00 Rp. 1.054.745,00
~ Volume Damper, 150x150 mm 1,00 pcs Rp. 633.040,00 Rp. 633.040,00
~ Box Chamber, 550x300 mm 2,00 pcs Rp. 2.483.910,00 Rp. 4.967.820,00
~ Box Chamber, 400x400 mm 3,00 pcs Rp. 2.338.195,00 Rp. 7.014.585,00
15 Air Handling Unit (AHU) Untuk Ruang ISOLASI 2
Dimensi : 6000 x3000 x 3000
Temperature : 23 ± 2 ᵒC
Humidity : 55 ± 5%
Room Class : 100.000 Class (0,5 micron)
a. Alat Utama
Pengadaan dan pemasangan peralatan utama H.V.A.C, lengkap dengan support dan accessories
1. AHU - 2.3 1,00 unit Rp. 172.000.000,00 Rp. 172.000.000,00
Kapasitas : 40.000 BTUH
A.F.R : 793 CFM
E.S.P : - Pa
P.I : 4,8kw, 380V, 3Ph, 50Hz
Type : Customize Split Duct
Lengkap dengan : √ Pre Filter GFF 35%
√ Medium Filter GFF 95%
√ Booster Fan
√ Magnehelic 0 - 700 pa& Box
√ Hot Gas System
Exhaust Fan : √ Kap. 1058 CFM 1,00 unit Rp. 24.414.500,00 Rp. 24.414.500,00
√ Type AXIAL FAN
b. Instalasi Pipa
1. Pipa Refrigerant
Pengadaan dan pemasangan Pipa Copper Tube Class ASTM B.2.80 lengkap
dengan Isolasi Superlone, density = 70 kg/m3, t = 15 mm
- Diameter 3/8" 70,00 m¹ Rp. 91.400,00 Rp. 6.398.000,00
- Diameter 5/8" 70,00 m¹ Rp. 167.000,00 Rp. 11.690.000,00
2. Pipa Drain
Pengadaan dan pemasangan Pipa PVC Class AW
- Diameter 25 mm 30,00 m¹ Rp. 31.191,75 Rp. 935.752,50
c. Filter & Control
1. Room Pressure Differensial Indicator
- Hepa Pressure Differential Indicator( Magnehelic 0 ~ 700 pascal ) 2,00 pcs Rp. 6.437.515,00 Rp. 12.875.030,00
- Room Pressure Differential Indicator( Magnehelic -30 ~ 30 Pa ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
- Housing filter (Exhaust) 1,00 pcs Rp. 5.150.205,00 Rp. 5.150.205,00
- Prefilter 24x24x2 1,00 pcs Rp. 9.012.135,00 Rp. 9.012.135,00
- HEPA Filter 24x24x12 1,00 pcs Rp. 9.012.135,00 Rp. 9.012.135,00
- Carbon filter 24x24x2 1,00 pcs Rp. 15.450.615,00 Rp. 15.450.615,00
2. Hose Pneumatic dan Nozzle 1,00 ls Rp. 4.000.000,00 Rp. 4.000.000,00
3. Temprature dan Humidity Control lengkap dengan sensor 1,00 set Rp. 12.875.030,00 Rp. 12.875.030,00
4. Box Magnehelic SS. 304, Size. 300 x 300 x 70 3,00 set Rp. 2.574.620,00 Rp. 7.723.860,00
d. Elektrikal
1. Panel control AC 1,00 unit Rp. 140.833.000,00 Rp. 140.833.000,00
~ MCCB, MCB, Push Button, Contactor, Relay, Selector, Switch, Pilot Lamp
2. Kabel power
Dari panel Control ke panel incoming 100 m¹ Rp. 60.676,88 Rp. 6.067.687,50
~ NYY 4 x 4mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke unit outdoor 100 m¹ Rp. 34.689,38 Rp. 3.468.937,50
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Booster Fan 27 m¹ Rp. 34.689,38 Rp. 936.613,13
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Dehumidifier 27 m¹ Rp. 35.870,63 Rp. 968.506,88
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm
Kabel Control NYMHY 2 (3 x 0,75mm) 100 m¹ Rp. 29.846,25 Rp. 2.984.625,00
Dari panel Control ke Exhaust 100 m¹ Rp. 35.870,63 Rp. 3.587.062,50
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm
e. Instalasi ducting
Pengadaan dan Pemasangan Duct Galvanished Sheet lengkap dengan Isolasi
Thermobreak, Density = 25 kg/m2, t = 15mm
1 Supply
~ Dimensi 300x300 mm 25,00 m¹ Rp. 732.000,00 Rp. 18.300.000,00
~ Dimensi 250x250 mm 7,00 m¹ Rp. 624.000,00 Rp. 4.368.000,00
~ Dimensi 150x150 mm 7,00 m¹ Rp. 407.000,00 Rp. 2.849.000,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
2 Return
~ Dimensi 300x300 mm 15,00 m¹ Rp. 732.000,00 Rp. 10.980.000,00
~ Dimensi 250x250 mm 12,00 m¹ Rp. 624.000,00 Rp. 7.488.000,00
~ Dimensi 150x150 mm 7,00 m¹ Rp. 407.000,00 Rp. 2.849.000,00
3 Exhaust
~ Dimensi 300x300 mm 15,00 m¹ Rp. 732.000,00 Rp. 10.980.000,00
4 Fresh Air
~ Dimensi 200x200 mm 15,00 m¹ Rp. 515.000,00 Rp. 7.725.000,00
5 Accessories Duct
~ Plenum Box, 1000 x 800 x 500 mm 2,00 set Rp. 5.060.460,00 Rp. 10.120.920,00
~ S.A.D Perforated SS 304, 400x400 mm 3,00 pcs Rp. 3.137.215,00 Rp. 9.411.645,00
~ R.A.G Perforated SS 304, 500x250 mm 2,00 pcs Rp. 2.941.320,00 Rp. 5.882.640,00
~ Louver Grille Alumunium Amodized c/w OBD, 350x350 mm 2,00 pcs Rp. 1.553.650,00 Rp. 3.107.300,00
~ Volume Damper, 300x300 mm 2,00 pcs Rp. 1.265.115,00 Rp. 2.530.230,00
~ Volume Damper, 250x250 mm 1,00 pcs Rp. 1.054.745,00 Rp. 1.054.745,00
~ Volume Damper, 150x150 mm 1,00 pcs Rp. 633.040,00 Rp. 633.040,00
~ Box Chamber, 550x300 mm 2,00 pcs Rp. 2.483.910,00 Rp. 4.967.820,00
~ Box Chamber, 400x400 mm 3,00 pcs Rp. 2.338.195,00 Rp. 7.014.585,00
C. Lantai 3
1 Outdoor Unit VRV
• Outdoor Kapasitas : 191000 BTU/h VRF SMMS 7 MMY-MAP2007T8P-ID 1,00 unit Rp. 153.776.610,00 Rp. 153.776.610,00
2 Indoor Unit VRV
• Indoor Kapasitas : 24200 BTU/h Cassette (4 Way) MMU-AP0244HP-ID 4,00 unit Rp. 15.007.680,00 Rp. 60.030.720,00
• Indoor Kapasitas : 7500 BTU/h Wall Mounted MMK-AP0077HP-ID 7,00 unit Rp. 10.682.550,00 Rp. 74.777.850,00
• Indoor Kapasitas : 12300 BTU/h Wall Mounted MMK-AP0127HP-ID 1,00 unit Rp. 11.637.900,00 Rp. 11.637.900,00
3 Y-Branch (Indoor pipe connection) 11,00 bh Rp. 2.283.000,00 Rp. 25.113.000,00
4 Remote wired control 12,00 bh Rp. 1.146.000,00 Rp. 13.752.000,00
5 Panel cassette 4,00 unit Rp. 3.187.000,00 Rp. 12.748.000,00
6 Pemipaan (Refrigerant dengan isolasi) 175,00 m¹ Rp. 413.700,00 Rp. 72.397.500,00
7 Pemipaan drain (PVC ø 1") 131,00 m¹ Rp. 31.191,75 Rp. 4.086.119,25
8 Instalasi control AWG 16 184,00 m¹ Rp. 39.690,00 Rp. 7.302.960,00
9 Titik instalasi Indoor Unit (NYM 3x2,5 mm²) 12,00 ttk Rp. 326.025,00 Rp. 3.912.300,00
10 Freon R410a 3,00 can Rp. 3.715.250,00 Rp. 11.145.750,00
11 Pekerjaan Fresh Air
a Outdoor Unit Fresh Air
SMMS-7 Kap. 230000 BTUH MMY-MAP2407T8P-ID 1,00 unit Rp. 104.841.000,00 Rp. 104.841.000,00
b Indoor Unit Freesh Air
Fresh Air Intake Duct Kap. 76400 BTUH MMD-AP0721HFE 3,00 unit Rp. 58.905.000,00 Rp. 176.715.000,00
c Accessories Fresh Air
Main Remote Controller RBC-AMT32E 3,00 unit Rp. 1.146.000,00 Rp. 3.438.000,00
Y-Shape Branching Joint RBM-BY… 2,00 unit Rp. 2.283.000,00 Rp. 4.566.000,00
For high-eciency lter or long life prelter TCB-FCY100DE 3,00 unit Rp. 5.572.000,00 Rp. 16.716.000,00
Dust collecting eect: 50% TCB-PF4D-1E 3,00 unit Rp. 1.372.230,00 Rp. 4.116.690,00
Drain Pump Kit TCB-DP32DFE 3,00 unit Rp. 5.698.000,00 Rp. 17.094.000,00
Pengondisian AC Critical
12 Air Handling Unit (AHU) Untuk Ruang OK 3 dan 5
Dimensi : 6000 x5500 x 3000
Temperature : 23 ± 2 ᵒC
Humidity : 55 ± 5%
Room Class : 100.000 Class (0,5 micron)
a. Alat Utama
Pengadaan dan pemasangan peralatan utama H.V.A.C, lengkap dengan support dan accessories
1. R. OKA (IU-3.84) 1,00 unit Rp. 370.000.000,00 Rp. 370.000.000,00
Kapasitas : 120.000 BTUH
A.F.R : 4.140 CFM
E.S.P : 1000 Pa
P.I : 14.4kw, 380V, 3Ph, 50Hz
Type : Customize Split Duct
Lengkap dengan : ~ Pre Filter GFF 35%
~ Medium Filter GFF 95%
~ Booster Fan
~ Magnehelic 0 - 700 pa& Box
~ Magnehelic 0 - 60 pa& Box
~ Box Magnehelic
2. DH-1 (Dehumidifier) 1,00 unit Rp. 21.451.950,00 Rp. 21.451.950,00
Kapasitas : 290 CMH
P.I. : 3.54Kw, 220V, 1ph, 50Hz
Type : Refrigerant
3. EF-1 (Exhaust) 1,00 unit Rp. 11.097.500,00 Rp. 11.097.500,00
Kapasitas : 500 CMH
Type : Axial Fan
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
b. Instalasi Pipa
1. Pipa Refrigerant
Pengadaan dan pemasangan Pipa Copper Tube Class ASTM B.2.80 lengkap
dengan Isolasi Superlone, density = 70 kg/m3, t = 15 mm
- Diameter 1/2" 36,00 m¹ Rp. 143.000,00 Rp. 5.148.000,00
- Diameter 3/4" 36,00 m¹ Rp. 214.000,00 Rp. 7.704.000,00
2. Pipa Drain
Pengadaan dan pemasangan Pipa PVC Class AW
- Diameter 25 mm 18,00 m¹ Rp. 31.191,75 Rp. 561.451,50
c. Filter & Control
1. Hepa Filter - EFF 99.995 %
- Size. 24 x 48 x 6" 4,00 pcs Rp. 9.012.135,00 Rp. 36.048.540,00
- Size. 24 x 24 x 6" 2,00 pcs Rp. 9.012.135,00 Rp. 18.024.270,00
2. Housing Hepa Filter - EFF 99.995 %
- Size. 610 x 1220 x 600 4,00 pcs Rp. 6.339.085,00 Rp. 25.356.340,00
- Size. 610 x 610 x 600 2,00 pcs Rp. 5.150.205,00 Rp. 10.300.410,00
3. Filter Pressure Differensial Indicator ( Magnehelic 0 ~ 700 pascal ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
4. Room Pressure Differential Indicator( Magnehelic 0 ~ 60 Pa pascal ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
5. Hose Pneumatic dan Nozzle 1,00 ls Rp. 4.000.000,00 Rp. 4.000.000,00
6. Temprature dan Humidity Control lengkap dengan sensor 1,00 set Rp. 12.875.030,00 Rp. 12.875.030,00
7. Box Magnehelic SS. 304, Size. 600 x 300 x 70 1,00 set Rp. 2.574.620,00 Rp. 2.574.620,00
d. Elektrikal
1. Panel control AC 1,00 unit Rp. 140.833.000,00 Rp. 140.833.000,00
~ MCCB, MCB, Push Button, Contactor, Relay, Selector, Switch, Pilot Lamp
2. Kabel power
Dari panel Control AC-1 ke unit AC 36 m¹ Rp. 60.676,88 Rp. 2.184.367,50
~ NYY 4 x 4mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Booster Fan 20 m¹ Rp. 34.689,38 Rp. 693.787,50
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm
Dari panel Control AC-1 ke Dehumidifier 20 m¹ Rp. 35.870,63 Rp. 717.412,50
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm
Kabel Control NYMHY 2 (3 x 0,75mm) 40 m¹ Rp. 29.846,25 Rp. 1.193.850,00
Dari panel Control ke Exhaust 26 m¹ Rp. 35.870,63 Rp. 932.636,25
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm
e. Instalasi ducting
Pengadaan dan Pemasangan Duct Galvanished Sheet lengkap dengan Isolasi
Thermobreak, Density = 25 kg/m2, t = 15mm
1 Supply
~ Dimensi 500x400 mm 28,00 m¹ Rp. 1.058.000,00 Rp. 29.624.000,00
~ Dimensi 350x300 mm 10,00 m¹ Rp. 787.000,00 Rp. 7.870.000,00
~ Dimensi 300x200 mm 20,00 m¹ Rp. 624.000,00 Rp. 12.480.000,00
2 Return
~ Dimensi 450x450 mm 56,00 m¹ Rp. 1.058.000,00 Rp. 59.248.000,00
~ Dimensi 350x350 mm 10,00 m¹ Rp. 841.000,00 Rp. 8.410.000,00
~ Dimensi 300x200 mm 26,00 m¹ Rp. 624.000,00 Rp. 16.224.000,00
3 Accessories Duct
~ Plenum Box, 1000 x 800 x 500 mm 1,00 set Rp. 5.060.460,00 Rp. 5.060.460,00
~ S.A.D Perforated SS 304, 1220 x 610 mm 4,00 pcs Rp. 7.175.740,00 Rp. 28.702.960,00
~ S.A.D Perforated SS 304, 610 x 610 mm 2,00 pcs Rp. 4.783.505,00 Rp. 9.567.010,00
~ R.A.G Perforated SS 304, 500x250 mm 4,00 pcs Rp. 2.941.320,00 Rp. 11.765.280,00
~ Louver Grille Alumunium Amodized c/w OBD, 350x350 mm 2,00 pcs Rp. 1.553.650,00 Rp. 3.107.300,00
~ Volume Damper, 300x200 mm 4,00 pcs Rp. 1.054.745,00 Rp. 4.218.980,00
~ Volume Damper, 250x200 mm 4,00 pcs Rp. 948.595,00 Rp. 3.794.380,00
~ Box Chamber, 550x300 mm 4,00 pcs Rp. 2.483.910,00 Rp. 9.935.640,00
~ Box Chamber, 400x400 mm 2,00 pcs Rp. 2.338.195,00 Rp. 4.676.390,00
13 Air Handling Unit (AHU) Untuk Ruang OK 1, 2 dan 4
Dimensi : 8500 x 5500 x 3000
Temperature : 23 ± 2 ᵒC
Humidity : 55 ± 5%
Room Class : 100.000 Class (0,5 micron)
a. Alat Utama
Pengadaan dan pemasangan peralatan utama H.V.A.C, lengkap dengan support dan accessories
1. R. OKA (IU-3.5) 1,00 unit Rp. 393.000.000,00 Rp. 393.000.000,00
Kapasitas : 140.000 BTUH
A.F.R : 6.950 CFM
E.S.P : 1000 Pa
P.I : 6.6kw, 380V, 3Ph, 50Hz
Type : Customize Split Duct
Lengkap dengan : √ Pre Filter GFF 35%
√ Medium Filter GFF 95%
√ Booster Fan
√ Magnehelic 0 - 700 pa& Box
√ Box Magnehelic
2. DH-1 (Dehumidifier) 1,00 unit Rp. 31.816.050,00 Rp. 31.816.050,00
Kapasitas : 430 CMH
P.I. : 4.57Kw, 220V, 1ph, 50Hz
Type : Refrigerant
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
~ Booster Fan
~ Magnehelic 0 - 700 pa& Box
2. DH-1 (Dehumidifier) 1,00 unit Rp. 31.816.050,00 Rp. 31.816.050,00
Kapasitas : 430 CMH
P.I. : 4.57Kw, 220V, 1ph, 50Hz
Type : Refrigerant
b. Instalasi Pipa
1. Pipa Refrigerant
Pengadaan dan pemasangan Pipa Copper Tube Class ASTM B.2.80 lengkap
dengan Isolasi Superlone, density = 70 kg/m3, t = 15 mm
- Diameter 1/2" 36,00 m¹ Rp. 143.000,00 Rp. 5.148.000,00
- Diameter 1" 36,00 m¹ Rp. 367.000,00 Rp. 13.212.000,00
2. Pipa Drain
Pengadaan dan pemasangan Pipa PVC Class AW
- Diameter 25 mm 26,00 m¹ Rp. 31.191,75 Rp. 810.985,50
c. Filter & Control
1. Pre Filter F8 2,00 pcs Rp. 9.012.135,00 Rp. 18.024.270,00
- Size. 24 x 24 x 6"
2. Medium Filter F8 2,00 pcs Rp. 9.012.135,00 Rp. 18.024.270,00
- Size. 24 x 24 x 6"
3. Filter Pressure Differensial Indicator ( Magnehelic 0 ~ 700 pascal ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
4. Room Pressure Differential Indicator( Magnehelic 0 ~ 60 Pa pascal ) 1,00 pcs Rp. 6.437.515,00 Rp. 6.437.515,00
5. Hose Pneumatic dan Nozzle 1,00 ls Rp. 4.000.000,00 Rp. 4.000.000,00
6. Temprature dan Humidity Control lengkap dengan sensor 1,00 set Rp. 12.875.030,00 Rp. 12.875.030,00
7. Box Magnehelic SS. 304, Size. 300 x 300 x 70 2,00 set Rp. 2.574.620,00 Rp. 5.149.240,00
8. Inverter 3kw (Modulating) 1,00 set Rp. 19.312.545,00 Rp. 19.312.545,00
d. Elektrikal
1. Panel control AC 1,00 unit Rp. 140.833.000,00 Rp. 140.833.000,00
~ MCCB, MCB, Push Button, Contactor, Relay, Selector, Switch, Pilot Lamp
2. Kabel power
Dari panel Control AC-1 ke unit AC
~ NYY 4 x 10mm + NYA 1 x 10mm 52,00 m¹ Rp. 137.700,00 Rp. 7.160.400,00
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm 96,00 m¹ Rp. 34.689,38 Rp. 3.330.180,00
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm 48,00 m¹ Rp. 35.870,63 Rp. 1.721.790,00
Dari panel Control AC-1 ke Booster Fan
~ NYY 4 x 2,5mm + NYA 1 x 2,5mm 48,00 m¹ Rp. 34.689,38 Rp. 1.665.090,00
Dari panel Control AC-1 ke Dehumidifier
~ NYY 3 x 2,5mm + NYA 1 x 2,5mm 48,00 m¹ Rp. 35.870,63 Rp. 1.721.790,00
Kabel Control NYMHY 2 (3 x 0,75mm) 196,00 m¹ Rp. 29.846,25 Rp. 5.849.865,00
e. Instalasi ducting
Pengadaan dan Pemasangan Duct Galvanished Sheet lengkap dengan Isolasi
Thermobreak, Density = 25 kg/m2, t = 15mm
1 Supply
~ Dimensi 500x400 mm 38,00 m¹ Rp. 1.058.000,00 Rp. 40.204.000,00
~ Dimensi 400x300 mm 2,00 m¹ Rp. 841.000,00 Rp. 1.682.000,00
~ Dimensi 350x250 mm 3,00 m¹ Rp. 732.000,00 Rp. 2.196.000,00
~ Dimensi 350x200 mm 5,00 m¹ Rp. 678.000,00 Rp. 3.390.000,00
~ Dimensi 300x200 mm 20,00 m¹ Rp. 624.000,00 Rp. 12.480.000,00
~ Dimensi 200x200 mm 10,00 m¹ Rp. 515.000,00 Rp. 5.150.000,00
2 Return
~ Dimensi 400x400 mm 38,00 m¹ Rp. 949.000,00 Rp. 36.062.000,00
~ Dimensi 350x250 mm 7,00 m¹ Rp. 732.000,00 Rp. 5.124.000,00
~ Dimensi 350x200 mm 12,00 m¹ Rp. 678.000,00 Rp. 8.136.000,00
~ Dimensi 300x200 mm 10,00 m¹ Rp. 624.000,00 Rp. 6.240.000,00
~ Dimensi 200x200 mm 15,00 m¹ Rp. 515.000,00 Rp. 7.725.000,00
3 Accessories Duct
~ Plenum Box, 1000 x 800 x 600 mm 1,00 set Rp. 5.060.460,00 Rp. 5.060.460,00
~ Plenum Box, 900 x 600 x 400 mm 1,00 set Rp. 4.217.050,00 Rp. 4.217.050,00
~ S.A.D Perforated SS 304, 300 x 300 mm 8,00 pcs Rp. 2.352.670,00 Rp. 18.821.360,00
~ R.A.G Perforated SS 304, 350x200 mm 8,00 pcs Rp. 2.156.775,00 Rp. 17.254.200,00
~ Louver Grille Alumunium Amodized c/w OBD, 900x300 mm 1,00 pcs Rp. 2.663.400,00 Rp. 2.663.400,00
~ Volume Damper, 650x350 mm 1,00 pcs Rp. 2.108.525,00 Rp. 2.108.525,00
~ Volume Damper, 350x300 mm 3,00 pcs Rp. 1.370.300,00 Rp. 4.110.900,00
~ Box Chamber, 950 x 350 mm 1,00 pcs Rp. 3.799.205,00 Rp. 3.799.205,00
~ Box Chamber, 600 x 300 mm 9,00 pcs Rp. 2.630.590,00 Rp. 23.675.310,00
~ Box Chamber, 400 x 400 mm 11,00 pcs Rp. 2.338.195,00 Rp. 25.720.145,00
f. Kelengkapan : ARD
- Earth Quake controller
- Safety Device Controller (Emergency Break Hoist)
- Over load Protection
- Over limit velocity Protection
- Emergency Lighting
- Emergency Call
- Hand rail
2 Earthquake Sensor 2,00 unit Rp. 8.437.500,00 Rp. 16.875.000,00
3 Pekerjaan Dumbwaiter 2,00 unit Rp. 395.750.000,00 Rp. 791.500.000,00
a. Jenis : Lift Barang
b. Kapasitas : 200 kg
c. Kecepatan : 30 Mpm
d. Lintasan : 3 Lantai
e. Jasa pemasangan, perijinan & test comm
f. Pekerjaan Separator Beam
Jumlah Section C.2.4. PEKERJAAN PENGADAAN DAN PEMASANGAN ELEVATOR Rp. 2.411.741.500,00
Section C.2.5. PEKERJAAN PENGADAAN DAN PEMASANGAN PNEUMATIC TUBE SYSTEM (PTS)
I. PERALATAN UTAMA DAN PENDUKUNG
A. TRANSFER ROOM, MAIN CONTROL & CABLES
1. Central Control Unit Dual Line System and Power Supply Unit 1,00 set Rp. 200.193.800,00 Rp. 200.193.800,00
2. Blower incl. assesories 1,00 paket Rp. 385.618.200,00 Rp. 385.618.200,00
• Blower 3-Phase 2 unit
• Blower Connecting Set 2 set
• Blower Mounting Buffer 4 buah
• Blower Sound Absorber 2 buah
• Blower Controller 2 buah
• Air/Transfer Diverter 4 unit
• Bypass 2 buah
• Transfer Bend 16 buah
• Hose Clamp 50-70 8 buah
• Air Hose 2 meter
• Air Lid 2 buah
• Air Bow 10 buah
• Reduction Air Diverter 4 buah
• Connecting Tube 2 buah
3. PC-Monitoring and Programing System RFID, 2-Line System 1,00 set Rp. 234.696.000,00 Rp. 234.696.000,00
B. DIVERTERS AND ACCESSORIES
• Diverter 3-Way 2,00 unit Rp. 36.000.100,00 Rp. 72.000.200,00
C. TUBE AND LINE SYSTEM (CENTRAL)
• Tubes PVC - Diam. 110 MM RAL 7000 20,00 meter Rp. 217.800,00 Rp. 4.356.000,00
• Bend R=800, RAL 7001, Grey 10,00 buah Rp. 1.503.400,00 Rp. 15.034.000,00
• Sleeve 45,00 buah Rp. 80.100,00 Rp. 3.604.500,00
• Cable 2x2x0.22 + 3x2.5F 60,00 meter Rp. 167.000,00 Rp. 10.020.000,00
D. VARIOUS INSTALLATION MATERIAL
• Supporting Material 1,00 lot Rp. 23.138.067,50 Rp. 23.138.067,50
(Clutch Clamp, PVC Conduit, Pipeclamp, Screw Bolt, Adhesive Glue, dll)
• Biaya Instalasi 1,00 ls Rp. 18.510.454,00 Rp. 18.510.454,00
Jumlah Section C.2.5. PEKERJAAN PENGADAAN DAN PEMASANGAN PNEUMATIC TUBE SYSTEM (PTS) Rp. 4.167.698.469,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
URAIAN P E K E R J A A N JUMLAH
Section C.3.5. SISTEM PUBLIC ADRESS & TATA SUARA Rp. 110.761.135,00
C.2 Lantai - 1
1 Telepon terminal box (TTB-BS.1, 30 pair) 1,00 bh Rp. 591.000,00 Rp. 591.000,00
1 Inst. telepon ITC (4 x 0.6 mm²) in HIPVC ø 20 mm 5,00 ttk Rp. 178.368,75 Rp. 891.843,75
2 Outlet telepon 5,00 bh Rp. 89.662,50 Rp. 448.312,50
3 Hand set telephone analog 5,00 bh Rp. 426.375,00 Rp. 2.131.875,00
C.3 Lantai - 2
1 Telepon terminal box (TTB-BS.2, 10 pair) 1,00 bh Rp. 591.000,00 Rp. 591.000,00
2 Inst. telepon ITC (4 x 0.6 mm²) in HIPVC ø 20 mm 6,00 ttk Rp. 178.368,75 Rp. 1.070.212,50
3 Outlet telepon 6,00 bh Rp. 89.662,50 Rp. 537.975,00
4 Hand set telephone analog 6,00 bh Rp. 426.375,00 Rp. 2.558.250,00
C.4 Lantai - 3
1 Telepon terminal box (TTB-BS.3, 10 pair) 1,00 bh Rp. 591.000,00 Rp. 591.000,00
2 Inst. telepon ITC (4 x 0.6 mm²) in HIPVC ø 20 mm 7,00 ttk Rp. 178.368,75 Rp. 1.248.581,25
3 Outlet telepon 7,00 bh Rp. 89.662,50 Rp. 627.637,50
4 Hand set telephone analog 7,00 bh Rp. 426.375,00 Rp. 2.984.625,00
B. Lantai - 2
1 Switch HUB-BS.2 (16 port) 1,00 bh Rp. 991.350,00 Rp. 991.350,00
Rack HUB c/w : 1,00 unit Rp. 2.998.000,00 Rp. 2.998.000,00
~ wall mounted type
~ depth 490 mm (double door)
~ fan (1 unit)
~ power distribusi panel 5 outlet (1 unit)
~ UPS 500 VA
~ material support & instalasi
2 Outlet IT, RG45 cat.6 12,00 bh Rp. 95.512,50 Rp. 1.146.150,00
3 Instalasi kabel UTP category 6 termasuk pipa 12,00 ttk Rp. 271.406,25 Rp. 3.256.875,00
C. Lantai - 3
1 Switch HUB-BS.3 (16 port) 1,00 bh Rp. 991.350,00 Rp. 991.350,00
2 Rack HUB c/w : 1,00 unit Rp. 2.998.000,00 Rp. 2.998.000,00
~ wall mounted type
~ depth 490 mm (double door)
~ fan (1 unit)
~ power distribusi panel 5 outlet (1 unit)
~ UPS 500 VA
~ material support & instalasi
3 Outlet IT, RG45 cat.6 8,00 bh Rp. 95.512,50 Rp. 764.100,00
4 Instalasi kabel UTP category 6 termasuk pipa 8,00 ttk Rp. 271.406,25 Rp. 2.171.250,00
Jumlah Section C.3.3. SISTEM LOCAL AREA NETWORK (LAN) Rp. 37.025.775,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
A Distribution System :
1 MCFA (Addressable) kapasitas 2 loop : 1,00 set Rp. 34.470.000,00 Rp. 34.470.000,00
~ c/w Rechargegeable Lead acid battery
~ c/w Master intercom
2 Anunciator 1,00 unit Rp. 12.973.500,00 Rp. 12.973.500,00
3 MDF 1,00 unit Rp. 8.438.625,00 Rp. 8.438.625,00
4 Kabel distribusi AWG18 dalam HI PVC ø 20 mm dari :
• MCFA ke MDF (2 pair) 3,00 m¹ Rp. 49.140,00 Rp. 147.420,00
• MDF ke FTB-BS.1 (2 pair) 20,00 m¹ Rp. 49.140,00 Rp. 982.800,00
• MDF ke FTB-BS.2 (2 pair) 33,00 m¹ Rp. 49.140,00 Rp. 1.621.620,00
• MDF ke FTB-BS.3 (2 pair) 39,00 m¹ Rp. 49.140,00 Rp. 1.916.460,00
5 Kabel telepon ITC 2 x 0.6 mm² dlm HI PVC ø 20 mm dari :
• MCFA ke MDF (2 pair) 3,00 m¹ Rp. 12.521,25 Rp. 37.563,75
• MDF ke FTB-BS.1 (2 pair) 20,00 m¹ Rp. 12.521,25 Rp. 250.425,00
• MDF ke FTB-BS.2 (2 pair) 33,00 m¹ Rp. 12.521,25 Rp. 413.201,25
• MDF ke FTB-BS.3 (2 pair) 39,00 m¹ Rp. 12.521,25 Rp. 488.328,75
6 Kabel kontrol NYM 2 x 2.5 mm² dlm HI PVC ø 20 mm dari :
• MCFA ke MDF (2 pair) 3,00 m¹ Rp. 20.790,00 Rp. 62.370,00
• MDF ke FTB-BS.1 (2 pair) 20,00 m¹ Rp. 20.790,00 Rp. 415.800,00
• MDF ke FTB-BS.2 (2 pair) 33,00 m¹ Rp. 20.790,00 Rp. 686.070,00
• MDF ke FTB-BS.3 (2 pair) 39,00 m¹ Rp. 20.790,00 Rp. 810.810,00
B.2 Lantai - 2
1 Combination box with fire hydrant cabinet c/w :
• Manual call point / manual pull station 1,00 bh Rp. 463.000,00 Rp. 463.000,00
• Bell / alarm 1,00 bh Rp. 664.425,00 Rp. 664.425,00
• Indicating lamp 1,00 bh Rp. 1.110.937,50 Rp. 1.110.937,50
• Line telepon FHC / jack telepon 1,00 bh Rp. 305.000,00 Rp. 305.000,00
2 Instalasi & Fixtures
• Photo elektric smoke detector c/w base 19,00 bh Rp. 793.000,00 Rp. 15.067.000,00
• Rate of rise heat detector 22,00 bh Rp. 399.825,00 Rp. 8.796.150,00
• Fire terminal box (FTB-F) 1,00 bh Rp. 2.566.125,00 Rp. 2.566.125,00
• Instalasi AWG 18 (1 pair) dlm HI PVC ø 20 mm 42,00 ttk Rp. 290.587,50 Rp. 12.204.675,00
• Instalasi NYM 3 x 1.5 mm² dlm HI PVC ø 20 mm 1,00 ttk Rp. 256.837,50 Rp. 256.837,50
• Instalasi ITC 2 x 0.6 mm² dlm HI PVC ø 20 mm 1,00 ttk Rp. 107.493,75 Rp. 107.493,75
B.2 Lantai - 2
1 Ceiling speaker 3 W 32,00 bh Rp. 152.167,50 Rp. 4.869.360,00
2 Volume control 6 W 7,00 bh Rp. 216.180,00 Rp. 1.513.260,00
3 Instalasi NYMHY 3 x 1.5 mm² dalam HI PVC ø 20 mm 32,00 ttk Rp. 273.375,00 Rp. 8.748.000,00
B.3 Lantai - 3
1 Ceiling speaker 3 W 29,00 bh Rp. 152.167,50 Rp. 4.412.857,50
2 Volume control 5 W 6,00 bh Rp. 216.180,00 Rp. 1.297.080,00
3 Instalasi NYMHY 3 x 1.5 mm² dalam HI PVC ø 20 mm 29,00 ttk Rp. 273.375,00 Rp. 7.927.875,00
Jumlah Section C.3.5. SISTEM PUBLIC ADRESS & TATA SUARA Rp. 110.761.135,00
A Distribution System :
1 Antenna parabola 6 feet c/w F,H LNB & tiang 1,00 unit Rp. 5.737.000,00 Rp. 5.737.000,00
2 VHF antenna 10 elemen 1,00 unit Rp. 1.068.000,00 Rp. 1.068.000,00
3 UHF antenna 36 elemen 2,00 unit Rp. 1.647.000,00 Rp. 3.294.000,00
4 Masterhead Amplifier 1,00 unit Rp. 949.500,00 Rp. 949.500,00
5 Power devider 2,00 unit Rp. 726.480,00 Rp. 1.452.960,00
6 Receiver digital 10,00 unit Rp. 2.250.000,00 Rp. 22.500.000,00
7 Modulator 10,00 unit Rp. 3.768.000,00 Rp. 37.680.000,00
8 Programable amplifier 10 filter 1,00 unit Rp. 10.462.000,00 Rp. 10.462.000,00
9 Combiner 16 channel 1,00 unit Rp. 2.250.000,00 Rp. 2.250.000,00
10 Open rack 42U 2,00 unit Rp. 6.300.000,00 Rp. 12.600.000,00
11 Booster amplifier 2,00 unit Rp. 2.920.230,00 Rp. 5.840.460,00
12 Coaxial cable RG-11 dari parabola ke ruang kontrol dan kabel distribusi utama 28,00 m¹ Rp. 17.443,13 Rp. 488.407,50
B.2 Lantai - 2
1 Coupler 2 way 1,00 unit Rp. 332.730,00 Rp. 332.730,00
2 Spliter 4 way 1,00 unit Rp. 276.480,00 Rp. 276.480,00
3 Spliter 3 way 1,00 unit Rp. 237.105,00 Rp. 237.105,00
4 Outlet TV 7,00 bh Rp. 161.662,50 Rp. 1.131.637,50
5 Instalasi kabel coaxial RG-11 dalam HI PVC ø 20 mm 7,00 ttk Rp. 273.375,00 Rp. 1.913.625,00
C.3 Lantai - 3
1 Coupler 2 way 1,00 unit Rp. 332.730,00 Rp. 332.730,00
2 Spliter 4 way 1,00 unit Rp. 276.480,00 Rp. 276.480,00
3 Outlet TV 6,00 bh Rp. 161.662,50 Rp. 969.975,00
4 Instalasi kabel coaxial RG-11 dalam HI PVC ø 20 mm 6,00 ttk Rp. 273.375,00 Rp. 1.640.250,00
Jumlah Section C.3.6. SISTEM MASTER AREAL TELEVISION (MATV) Rp. 115.149.485,00
DAFTAR KUANTITAS DAN HARGA (DKH)
PELAYANAN TATA USAHA PADA UPT RSUD MALINGPING
BELANJA MODAL PEMBANGUNAN GEDUNG IBS DAN ICU
TAHUN ANGGARAN 2021
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH
B.2. Lantai - 2
1 Dome camera fixed lens 3.6 mm 4,00 unit Rp. 3.333.960,00 Rp. 13.335.840,00
2 Dome camera fixed lens 3.6 mm (16 x zoom) 3,00 unit Rp. 4.329.585,00 Rp. 12.988.755,00
3 Instalasi kabel video dari camera ke ruang kontrol 7,00 ttk Rp. 273.375,00 Rp. 1.913.625,00
kabel coaxial RG-11 dalam pipa conduit ø 20 mm
4 Instalasi kabel power NYM 3 x 2.5 mm² untuk setiap 7,00 ttk Rp. 300.937,50 Rp. 2.106.562,50
camera dalam pipa conduit ø 20 mm
B.3. Lantai - 3
1 Dome camera fixed lens 3.6 mm 4,00 unit Rp. 3.333.960,00 Rp. 13.335.840,00
2 Dome camera fixed lens 3.6 mm (16 x zoom) 2,00 unit Rp. 4.329.585,00 Rp. 8.659.170,00
3 Instalasi kabel video dari camera ke ruang kontrol 6,00 ttk Rp. 273.375,00 Rp. 1.640.250,00
kabel coaxial RG-11 dalam pipa conduit ø 20 mm
4 Instalasi kabel power NYM 3 x 2.5 mm² untuk setiap 6,00 ttk Rp. 300.937,50 Rp. 1.805.625,00
camera dalam pipa conduit ø 20 mm