PANJANG LEBAR TEBAL DRAINASE (M') TPT


NO NAMA RUAS STA AWAL STA AKHIR JENIS (M) (M) (M) PANJANG POSISI
1 CILEGON - PASAURAN I 000/19+450/129+000 800/20+250/129+800 HOTMIX 800.00 7.50 0.10 1,250 KI/KA
CILEGON - PASAURAN II 000/23+750/133+320 300/24+050/133+620 HOTMIX 300.00 7.50 0.10 100 KA
CILEGON - PASAURAN III 000/33+362/142+952 396/33+758/143+348 HOTMIX 396.00 7.50 0.10 792 KA
CILEGON - PASAURAN IV 000/42+000/151+575 250/42+250/151+825 HOTMIX 250.00 7.50 0.10 250 KA 250.00
2 PASAURAN - LABUAN I 000/14+950/157+115 840/14+110/157+955 BETON 840.00 7.00 0.30 1,180 KI/KA
PASAURAN - LABUAN II 000/12+135/159+973 175/11+960/160+148 BETON 175.00 7.00 0.30 200 KI/KA 150.00
PASAURAN - LABUAN III 000/10+180/161+695 130/10+050/161+825 BETON 130.00 7.00 0.30 260 TUTUP
PASAURAN - LABUAN IV 000/2+950/168+805 1+000/1+950/169+805 BETON 1000.00 7.00 0.30 1,850 KI/KA 100.00
3 REKONSTRUKSI JALAN
CILEGON - PASAURAN I 000/24+050/133+620 250/24+300/133+870 BETON 250.00 7.50 0.30 500 KI/KA
CILEGON - PASAURAN II 000/25+138/134+980 108/25+246/135+088 BETON 108.00 7.50 0.30 216 KI/KA
CILEGON - PASAURAN III 000/33+000/142+590 362/33+362/142+952 BETON 362.00 7.50 0.30 624 KI/KA PENUTUP 362 M
CILEGON - PASAURAN IV 000/33+758/143+348 182/33+940/143+530 BETON 182.00 7.50 0.30 364 KI/KA
CILEGON - PASAURAN V 000/36+630/146+150 098/36+728/146+248 BETON 98.00 7.00 0.30 196 KI/KA WLC 15 CM
4 CITEUREP - TANJUNG LESUNG 000/3+000/179+910 1+000/4+000/180+910 HOTMIX 1000.00 4.50 0.175 1,575 KI/KA
5,891 9,357

1 Total Panjang penanganan 5,891 M


2 Panjang Hotmix 2,746 M
3 Panjang Beton 3,145 M
TPT

KI

KI/KA

KA

PENUTUP 362 M

WLC 15 CM