RUAS JALAN : 0
JENIS PEKERJAAN : 0
PANJANG : 0
LOKASI PROYEK : 0
JUMLAH 40,374,765.30
P P N 10% 4,037,476.53
JUMLAH TOTAL 44,412,241.83
DIBULATKAN 44,000,000.00
KONSULTAN PERENCANA
PT. NANDHA CITRA KREASI
0
0
ENGINEER'S ESTIMATE (EE)
RENCANA ANGGARAN BIAYA
PENINGKATAN JALAN LINGKUNGAN PERUMAHAN
RUAS JALAN : 0
JENIS PEKERJAAN : 0
PANJANG : 0
LOKASI PROYEK : 0
-
IV. PEKERJAAN PERKERASAN
1 Perbaikan Pasangan Onderlaag K - 516 M3 109.40 325,180.67 35,574,765.30
2 Pasangan Lapis Penetrasi (Lapen) K - 618 M2 79,012.68 -
3 Pasang Lapis Tipis Aspal Pasir (Latasir) K - 638 M2 63,956.00 -
35,574,765.30
JUMLAH 40,374,765.30
P P N 10% 4,037,476.53
JUMLAH TOTAL 44,412,241.83
DIBULATKAN 44,000,000.00
RUAS JALAN : 0
JENIS PEKERJAAN : 0
PANJANG : 0
LOKASI PROYEK : 0
HARGA SATUAN
NO URAIAN PEKERJAAN KODE SATUAN VOLUME
(Rp)
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
1 Administrasi, Pelaporan dan Dokumentasi Ls Ls 1.00 1,500,000.00
2 Pembuatan Papan Nama Proyek Ls Buah 1.00 500,000.00
3 Mobilisasi dan Demobilisasi Ls Ls 1.00 1,500,000.00
4 Pengukuran Ulang dan Pematokan Ls Ls 1.00 300,000.00
5 Sewa Direksi Keet Ls Unit 1.00 1,000,000.00
JUMLAH
P P N 10%
JUMLAH TOTAL
DIBULATKAN
JUMLAH HARGA
KET.
(Rp)
7 8
1,500,000.00
500,000.00
1,500,000.00
300,000.00
1,000,000.00
4,800,000.00
35,574,765.30
- 10,380.00
35,574,765.30
40,374,765.30
4,037,476.53
44,412,241.83
44,000,000.00
870.3
DAFTAR UPAH KERJA ORANG PERHARI
0
HARGA SATUAN
NO TENAGA KERJA SATUAN KODE
(Rp/Hari)
1 Mandor Lapangan Hari L. 061 70,000.00
2 Mekanik Hari L. 071 50,000.00
3 Kepala Tukang Hari L. 073 60,000.00
4 Tukang Hari L. 079 60,000.00
5 Operator Terlatih Hari L. 081 50,000.00
6 Operator Kurang Terlatih Hari L. 082 45,000.00
7 Pembantu Operator Hari L. 083 40,000.00
8 Supir terampil Hari L. 091 40,000.00
9 Pembantu Supir Hari L. 099 40,000.00
10 Buruh Lapangan Terlatih Hari L. 106 40,000.00
11 Buruh Lapangan Semi Terlatih Hari L. 103 40,000.00
12 Buruh Lapangan Tak Terlatih Hari L. 101 40,000.00
DAFTAR HARGA MATERIAL
0
HARGA SATUAN
NO MATERIAL/BAHAN SATUAN KODE
(Rp)
1 Batu gunung atau quarry M3 M 010 195,000.00
2 Kerikil galian M3 M 011 151,700.00
3 Kerikil sungai M3 M 012 151,700.00
4 Batu kali besar M3 M 013 182,500.00
5 Batu kali disaring M3 M 014 157,800.00
6 Batu pecah 10 - 15 cm M3 M 020 250,000.00
7 Batu pecah 7 - 10 cm M3 M 021 232,000.00
8 Batu pecah 5 - 7 cm M3 M 022 265,000.00
9 Batu pecah 3 - 5 cm M3 M 023 223,000.00
10 Batu pecah 2 - 3 cm M3 M 024 239,800.00
11 Batu pecah 1 - 2 cm M3 M 025 251,000.00
12 Batu pecah 0.5 - 1 cm M3 M 026 251,000.00
13 Pasir urug M3 M 040 100,000.00
14 Pasir beton M3 M 041 158,200.00
15 Sirtu M3 M 042 101,300.00
16 Timbunan pilihan M3 M 050 80,000.00
17 Aspal Kg M 061 11,000.00
18 Minyak fluk Liter M 063 6,010.00
19 Minyak bakar Liter M 065 5,950.00
20 Kayu bakar M3 M 070 150,000.00
21 Semen Zak/50 kg M 080 59,500.00
22 Kapur M3 M 081 1,000,000.00
23 Baja untuk anyaman bronjong Kg M 162 17,200.00
24 Baja Struktur (Profil) Kg M 163 20,200.00
25 Baja tulangan beton U-24 Kg M 167 10,300.00
26 Alat bantu (set @ 3 alat) Set M 170 55,000.00
27 Kayu / papan perancah M3 M 180 2,100,000.00
28 Minyak diesel atau solar industri Liter M 183 6,640.00
29 Bensin atau premium Liter M 184 5,500.00
30 Minyak pelumas Liter M 185 32,000.00
31 Batu belah putih M3 B 001 190,000.00
32 Batu belah hitam M3 B 001a 195,000.00
33 Paving Block 8 cm Buah B 004 2,600.00
34 Paving Block 6 cm Buah B 004a 2,000.00
35 Cat marka jalan Kg B 008 60,000.00
DAFTAR SEWA ALAT PERJAM
0
HARGA SATUAN
NO NAMA PERALATAN HP KODE
(Rp/Jam)
1 Bulldozer 140 E 001 504,761.25
2 Motor grader 125 E 010 366,589.65
3 HydraulicExcavator 140 E 020 392,119.00
4 Crusher 20 t/h 220 E 031 1,162,762.65
5 Loader tracked 90 E 051 362,926.20
6 Loader wheeled 105 E 052 373,792.65
7 Tractor wheeled 60 E 053 72,963.00
8 Roller 3 wheeled 8 - 10 ton 55 E 080 154,890.75
9 Tandem roller 6 - 10 ton 60 E 081 165,526.20
10 Pneumatic Roller 8 - 15 T 60 E 084 227,174.85
11 Vibrator roller 10 ton 75 E 087 340,245.15
12 Stamper 5 E 088 38,659.95
13 Concrete Vibrator 10 E 089 54,691.35
14 Asphalt Sprayer 800 L 6 E 153 94,609.20
15 Asphalt Sprayer 400 L 6 E 154 59,158.00
16 Mesin pencampur Aspal 150 E 155 5,872,757.10
17 Asphalt Finisher 47 E 157 298,874.10
18 Water Tank Truck 100 E 182 238,523.25
19 Dump truck 3,5 ton 120 E 211 129,868.00
20 Dump truck 5 ton 140 E 212 189,554.40
21 Dump truck 10 ton 200 E 213 253,456.35
22 Flat Bed Truck 4 ton 100 E 221 197,878.80
23 Pickup Truck 61 E 222 77,568.00
24 Concrete Mixer 0.3 - 0.5 m3 15 E 251 62,431.95
25 Air Compressor 80 E 301 170,145.15
26 Generator 175 E 311 344,575.35
27 Water Pump 70 -100 mm 6 E 341 38,419.50
28 Tractor Equipment 115 E 401 72,963.00
29 Jack Hammer 3 E 346 40,020.75
ANALISA BIAYA KONSTRUKSI LAPIS PONDASI BAWAH (LPB) - TELFORD
4
5
6
7
8
9
10
4
5
6
7
8
9
10
T O T A L (Rp)
VOL : 80.00 SATUAN : M3 HARGA SATUAN 325,180.67 PER
KODE
K - 516
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
4,220,000.00
SUB TOTAL
(Rp)
###
SUB TOTAL
(Rp)
774,453.75
###
M3
ANALISA BIAYA ANALISA HARGA SATUAN
PENGHAMPARAN LAPIS TIPIS ASPAL PASIR 2 CM
(LATASIR)
TOTAL (Rp)
VOLUME : 1,600.00 SATUAN : M2 HARGA SATUAN : 63,956.00 PER M2
KODE
K - 638
Tanggal
30-Dec-99
SUB TOTAL
(Rp)
980,000.00
SUB TOTAL
(Rp)
97,923,480.00
SUB TOTAL
(Rp)
3,425,945.25
###
ANALISA BIAYA LAPIS PENETRASI MACADAM 5 CM (LAPEN)
4
5
6
7
8
9
10
T O T A L (Rp)
K - 618
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
9,000,000.00
SUB TOTAL
(Rp)
96,459,000.00
SUB TOTAL
(Rp)
5,158,751.25
###
M2
ANALISA BIAYA GALIAN TANAH KONSTRUKSI
4
5
6
7
8
9
10
4
5
6
7
8
9
10
1
2
3
PERALATAN
4
5
6
7
8
9
10
T O T A L (Rp)
4
5
6
7
8
9
10
4
5
6
7
8
9
10
4
5
6
7
8
9
10
T O T A L (Rp)
4
5
6
7
8
9
10
4
5
6
7
8
9
10
1
2
3
PERALATAN
4
5
6
7
8
9
10
T O T A L (Rp)
K - 224
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
1,350,000.00
SUB TOTAL
(Rp)
550,000.00
SUB TOTAL
(Rp)
0.00
1,900,000.00
M3
KODE
K - 220
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
3,860,000.00
SUB TOTAL
(Rp)
5,130,000.00
SUB TOTAL
(Rp)
827,631.00
9,817,631.00
M3
KODE
K - 210
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
1,510,000.00
SUB TOTAL
(Rp)
82,500.00
SUB TOTAL
(Rp)
0.00
1,592,500.00
M2
ANALISA HARGA BETON STRUKTUR KELAS K-225
(MENGGUNAKAN ALAT PENGADUK BETON 125 LITER)
SATUAN
KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL
PROPINSI : 0
0 0 30-Dec-99
5
6
7
8
9
10
T O T A L (Rp)
K - 722
TANGGAL
30-Dec-99
Adukan 1 Pc: 2 Ps : 3 Kr (yaitu 1 : 5) ; semen 350 Kg/m3 ; air 160 Kg/m3; 2487 Kg/m3
Anggap tiap adukan membutuhkan 1 Zak (27,8 liter lepas) semen portland; 55,6 liter pasir;
Tidak termasuk acuan dan tulangan besi beton yang sudah dipasang
Beton bertulang dipakai untuk pilar, gorong-gorong, dinding penahan dll
Sesuai dengan Peraturan Beton Bertulang Indonesia (PBI 1971 N.1.2)
SUB TOTAL
(Rp)
3,780,000.00
SUB TOTAL
(Rp)
22,689,000.00
SUB TOTAL
(Rp)
4,677,472.80
###
M3
ANALISA BIAYA PASANG PAVING BLOCK
4
5
6
7
8
9
10
4
5
6
7
8
9
10
1
2
3
PERALATAN
4
5
6
7
8
9
10
PER
T O T A L (Rp)
4
5
6
7
8
9
10
1
2
3
PERALATAN
4
5
PERALATAN 6
7
8
9
10
T O T A L (Rp)
G 60
TANGGAL
30-Dec-99
eh leveransir
SUB TOTAL
(Rp)
230,000.00
SUB TOTAL
(Rp)
911,000.00
SUB TOTAL
(Rp)
0.00
1,141,000.00
M2
KODE
G 61
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
1,270,000.00
SUB TOTAL
(Rp)
3,008,615.00
SUB TOTAL
(Rp)
0.00
4,278,615.00
M'
ANALISA BIAYA KONSTRUKSI LAPIS PONDASI BAWAH (LPB) KLAS B KODE
4
5
6
7
8
9
10
PER
2,864,421.00
T O T A L (Rp) 18,561,721.00
4
5
6
7
8
9
10
4
5
6
7
8
9
10
T O T A L (Rp)
VOL : 60.00 SATUAN : M3 HARGA SATUAN Err:509 PER
ANALISA BIAYA PENGADAAN KERIKIL SUNGAI (TAK DISARING)
4
5
6
7
8
9
10
4
5
6
7
8
9
10
4
5
6
7
8
9
10
T O T A L (Rp)
VOL : 60.00 SATUAN : M3 HARGA SATUAN 227,845.80 PER
KODE
K - 515
TANGGAL
30-Dec-99
mpat pekerjaan
SUB TOTAL
(Rp)
2,640,000.00
SUB TOTAL
(Rp)
17,225,935.00
SUB TOTAL
(Rp)
Err:509
Err:509
M3
KODE
K - 013
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
2,780,000.00
SUB TOTAL
(Rp)
6,215,500.00
SUB TOTAL
(Rp)
4,675,248.00
13,670,748.00
M3
ANALISA BIAYA MEMBERSIHKAN PARIT SAMPING
4
5
6
7
8
9
10
4
5
6
7
8
9
10
4
5
6
7
8
9
10
T O T A L (Rp)
VOL : 500.00 SATUAN : M HARGA SATUAN 5,909.36 PER
KODE
K - 424
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
1,590,000.00
SUB TOTAL
(Rp)
66,000.00
SUB TOTAL
(Rp)
1,298,680.00
2,954,680.00
M
ANALISA BIAYA PEKERJAAN PLESTERAN
4
5
6
7
8
9
10
1
2
3
PERALATAN
4
5
6
7
8
9
10
T O T A L (Rp)
VOL : 200.00 SATUAN : M2 HARGA SATUAN 35,258.00 PER
KODE
G50k
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
5,460,000.00
SUB TOTAL
(Rp)
1,591,620.00
SUB TOTAL
(Rp)
0.00
7,051,620.00
M2
ANALISA BIAYA PEMBENTUKAN DAN PERATAAN BAHU JALAN
4
5
6
7
8
9
10
4
5
6
7
8
9
10
4
5
6
7
8
9
10
T O T A L (Rp)
VOL : 5.00 SATUAN : KM HARGA SATUAN 424,790.00 PER
KODE
K - 855
TANGGAL
30-Dec-99
SUB TOTAL
(Rp)
280,000.00
SUB TOTAL
(Rp)
11,000.00
SUB TOTAL
(Rp)
1,832,948.25
2,123,948.25
KM
ANALISA BIAYA MEMBERSIHKAN RUMPUT DAN TANAMAN DI BAHU JALAN KODE
4
5
6
7
8
9
10
1,070,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
55,000.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
1
2
3
PERALATAN
4
5
6
7
8
9
10
0.00
T O T A L (Rp) 1,125,000.00
VOL : 1,500.00 SATUAN : M2 HARGA SATUAN 750.00 PER M2
ANALISA BIAYA MEMBENTUK BAHU JALAN PADAT KODE
4
5
6
7
8
9
10
2,820,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
9,737,500.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
4
5
6
7
8
9
10
1,701,225.75
T O T A L (Rp) ###
VOL : 96.00 SATUAN : M3 HARGA SATUAN 148,528.39 PER M3
ANALISA BIAYA MEMBERSIHKAN PARIT SAMPING KODE
4
5
6
7
8
9
10
1,590,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
66,000.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
4
5
6
7
8
9
10
1,298,680.00
T O T A L (Rp) 2,954,680.00
VOL : 500.00 SATUAN : M HARGA SATUAN 5,909.36 PER M
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
ANALISA BIAYA TIMBUNAN TANAH DIPADATKAN KODE
4
5
6
7
8
9
10
3,860,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
330,000.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
4
5
6
7
8
9
10
827,631.00
T O T A L (Rp) 5,017,631.00
VOL : 60.00 SATUAN : M3 HARGA SATUAN 83,627.00 PER M3
ANALISA BIAYA PENGUPASAN TANAH DAN KODE
PEMBERSIHAN SEMAK PADA DAMIJA
4
5
6
7
8
9
10
1,510,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
82,500.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
1
2
3
PERALATAN
4
5
6
7
8
9
10
0.00
T O T A L (Rp) 1,592,500.00
VOL : 900.00 SATUAN : M2 HARGA SATUAN 1,769.00 PER M2
ANALISA BIAYA MEMBUAT PARIT GALIAN TANAH KODE
4
5
6
7
8
9
10
1,590,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
82,500.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
4
5
6
7
8
9
10
1,298,680.00
T O T A L (Rp) 2,971,180.00
VOL : 54.00 SATUAN : M3 HARGA SATUAN 55,021.85 PER M3
ANALISA BIAYA PASANGAN BATU PADA PARIT GALIAN TANAH KODE
4
5
6
7
8
9
10
1,298,680.00
T O T A L (Rp) ###
VOL : 60.00 SATUAN : M' HARGA SATUAN 283,068.00 PER M'
ANALISA BIAYA PASANG PIPA GORONG-GORONG DIA. 60 CM KODE
(PRACETAK, TAK BERTULANG, TANPA DINDING KEPALA)
4
5
6
7
8
9
10
1,400,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
Err:509
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
4
5
6
7
8
9
10
386,599.50
T O T A L (Rp) Err:509
VOL : 8.00 SATUAN : M' HARGA SATUAN Err:509 PER M'
ANALISA BIAYA BETON NON STRUKTUR / RABAT KODE
KLAS K-125
PEKERJAAN K - 720
4
5
6
7
8
9
10
777,714.00
T O T A L (Rp) 5,554,314.00
VOL : 6.00 SATUAN : M3 HARGA SATUAN 925,719.00 PER M3
ANALISA BIAYA DINDING SAYAP GORONG-GORONG PASANGAN BATU KODE
(SATU PASANG),
4
5
6
7
8
9
10
76,839.00
T O T A L (Rp) ###
VOL : 8.00 SATUAN : M3 HARGA SATUAN 1,580,638.00 PER M3
ANALISA BIAYA PENIMBUNAN DAN PEMADATAN KODE
(UNTUK JEMBATAN & GORONG-GORONG)
4
5
6
7
8
9
10
590,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
1,616,500.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
4
5
6
7
8
9
10
2,087,825.25
T O T A L (Rp) 4,294,325.25
VOL : 15.00 SATUAN : M3 HARGA SATUAN 286,288.00 PER M3
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
NGGAL
-Dec-99
B TOTAL
(Rp)
B TOTAL
(Rp)
B TOTAL
(Rp)
ANALISA HARGA KONSTRUKSI PASANGAN BATU
4
5
6
7
8
9
10
4
5
6
7
8
9
10
T O T A L (Rp)
VOL : 5.00 SATUAN : M3 HARGA SATUAN 595,048.00 PER
3
4
5
6
7
3
4
5
6
7
8
1
2
PERALATAN
3
4
5
6
PERALATA
7
8
T O T A L (Rp)
3
4
5
6
7
1
2
MATERIAL
3
4
5
6
7
8
1
2
PERALATAN
PERALATAN
3
4
5
6
7
8
T O T A L (Rp)
K - 705
TANGGAL
December-99
Biaya alat bantu tambahan sudah termasuk biaya kira-kira ekivalen dari
SUB TOTAL
(Rp)
780,000.00
SUB TOTAL
(Rp)
2,118,400.00
SUB TOTAL
(Rp)
76,839.00
2,975,239.00
M3
KODE
A 18
TANGGAL
December-99
SUB TOTAL
(Rp)
1,270,000.00
SUB TOTAL
(Rp)
12,000,000.00
SUB TOTAL
(Rp)
0.00
13,270,000.00
M3
KODE
L3
TANGGAL
December-99
SUB TOTAL
(Rp)
1,880,000.00
SUB TOTAL
(Rp)
0.00
SUB TOTAL
(Rp)
0.00
1,880,000.00
M3
ANALISA HARGA PEMBUATAN PIPA BETON BERTULANG KODE
600 MM x 1,0 M
4
5
6
7
8
9
10
1,868,963.25
T O T A L (Rp) 12,123,464.74
VOL : 44.00 SATUAN : M' HARGA SATUAN 275,533.00 PER M'
ANALISA HARGA PASANG PIPA BETON PRACETAK BERTULANG 600 MM KODE
TANPA DINDING KEPALA
5
6
7
8
9
10
1,400,000.00
HARGA SATUAN BIAYA SUB TOTAL
MATERIAL SATUAN KODE VOLUME
(Rp) (Rp) (Rp)
4
5
6
7
8
9
10
3,729,376.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
4
5
6
7
8
9
10
36,485,600.00
JUMLAH HARI HARGA BIAYA SUB TOTAL
PERALATAN KODE JAM KERJA
ALAT KERJA (Rp/Jam) (Rp) (Rp)
Beton kelas K225 diaduk di lokasi pekerjaan (54 adukan / hari @ 114 liter/adukan)
SUB TOTAL
(Rp)
SUB TOTAL
(Rp)
SUB TOTAL
(Rp)
TANGGAL
December-99
SUB TOTAL
(Rp)
SUB TOTAL
(Rp)
SUB TOTAL
(Rp)
TANGGAL
December-99
SUB TOTAL
(Rp)
SUB TOTAL
(Rp)
SUB TOTAL
(Rp)