DAFTAR ISI
BAGIAN 1 PENDAHULUAN.................................................................................. 3
1.1 INFORMASI PROYEK ............................................................................ 3
BAGIAN 4 KESIMPULAN.................................................................................... 17
Lampiran 1 Surat PLN UPPJ Sumsel 1 perihal permintaan kajian proyek GI 150 kV
Tebing Tinggi
BAGIAN 1
PENDAHULUAN
8. Milestone Project
No. Tanggal Uraian
1. 08 Maret 2019 Penandatanganan Surat Perjanjian antara PLN
dengan Kontraktor
2. 26 Maret 2019 Kontrak Efektif (Serah Terima Lahan Tahap
Pertama kepada kontraktor)
3. 25 September 2019 Pekerjaan Sipil dimulai
4. 18 Maret 2020 Amandemen-1 Perpanjangan Waktu Pelaksanaan
pekerjaan ke-1 menjadi sampai dengan 14
September 2020
5. 9 September 2020 Amandemen-2 Perpanjangan Waktu Pelaksanaan
pekerjaan ke-2 menjadi sampai dengan 13 Maret
2021
6 9 Maret 2021 Amandemen-3 Penambahan Pasal Integritas,
Good Corporate Governance, Perubahan Pasal
Keselamatan dan Kesehatan Kerja (K3) dan
Perpanjangan Waktu Pelaksanaan ke-3 sampai
dengan 10 Agustus 2021
7 10 Agustus 2021 Amandemen-4 Perpanjangan waktu pelaksanaan
ke-4 menjadi sampai dengan 7 Januari 2022
8 28 Desember 2022 Amandemen-5 Perpanjangan waktu pelaksanaan
ke-5 menjadi sampai dengan 31 Maret 2022
BAGIAN 2
PERMASALAHAN
2.1 KRONOLOGI
BAGIAN 3
HASIL KAJIAN
e. Suspension
Sesuai dengan surat perjanjian Pasal 9 tentang Penghentian dan Pemutusan
Surat Perjanjian menyebutkan bahwa:
− Penghentian surat perjanjian ini dilakukan bilamana terjadi keadaan kahar
sesuai ketentuan pasal 10 surat perjanjian ini
− Pemutusan kontrak dapat dilakukan bilamana kedua belah pihak cidera janji
dan/atau tidak memenuhi kewajiban dan tanggung jawabnya sebagaimana
diatur di dalam surat perjanjian ini
− Pemutusan surat perjanjian ini yang disebabkan oleh kelalaian pihak kedua
dikenakan sanksi berupa jaminan pelaksanaan menjadi milik PT. PLN
(Persero), membayar denda dang anti rugi kepada PT. PLN (Persero) dan
pengenaan daftar hitam untuk jangka waktu 2 (dua) Tahun
− Pihak kesatu dapat memutuskan surat perjanjian ini secara sepihak apabila
denda keterlambatan pelaksanaan pekerjaan akibat kesalahan pihak kedua
sudah melampaui besarnya jaminan pelaksnaan
− Penghentian dan pemutusan surat perjanjian ini akan dilakukan secara
tertulis oleh Pihak Kesatu kepada Pihak Kedua.
g. Operational Acceptance
Sesuai dengan surat perjanjian pasal 6 ayat 3 tentang masa pemeliharaan
adalah selama 6 (enam) bulan sesudah serah terima pekerjaan tahap pertama.
Apabila terdapat kerusakan, kontraktor harus melakukan koreksi sesuai dengan
mekanisme yang ditetapkan.Sesuai dengan surat perjanjian pasal 6 ayat 3
tentang masa pemeliharaan adalah selama 6 (enam) bulan sesudah serah terima
pekerjaan tahap pertama. Apabila terdapat kerusakan, kontraktor harus
melakukan koreksi sesuai dengan mekanisme yang ditetapkan.
yang dilaksanakan selama periode EOT ke-5 yaitu pekerjaan sondir untuk
approval Dinding Penahan Tanah.
Selama periode EOT ke-5, tidak ada kemajuan progress untuk pekerjaan sipil.
Kontraktor hanya melaksanakan pekerjaan sondir untuk Dinding Penahan Tanah
selama periode EOT ke-5.
b. Pekerjaan Elektromekanik
No. Item Pekerjaan Jumlah Keterangan
Motor & Mechanical
1. 3 Set Surat Instruksi 30
Disconnecting Switch
November 2021
Arm Blade Disconnecting Switch
2. 2 Set
(1600A)
Pengambilan Material dari
Neutral Grounding Resistance
3. 1 Unit GI Bengkurnat
(NGR 10 Ohm)
4. Auxilliari Transformer (Trafo PS 1 Unit
Surat Instruksi 1
Current Transformers (CT) Line Desember 2021
5. 3 Unit
150 kV Pegambilan material dari
GI Bayung Lincir
Penarikan kabel dari MK ke Panel
control dan proteksi bayline Surat Instruksi 7 Februari
6.
Tebing 1 dan 2 di GI Lubuk 2020
Linggau
Pengadaan dan pemasangan 1
buah multiplexer dan 2 buah Surat Instruksi 7 Februari
7.
teleproteksi untuk bayline tebing 1 2020
dan 2 di GI Lubuk Linggau
Pemasangan panel proteksi untuk
Surat Instruksi 7 Februari
8. bayline tebing 1 dan 2 pada GI
2020
Lubuk Linggau
Pemasangan 4 set DS Busbar
Surat Instruksi 7 Februari
9. untuk bayline tebing 1 dan 2 di GI
2020
Lubuk Linggau
Pengadaan dan pemasangan
grounding mesh untuk bayline Surat Instruksi 7 Februari
10.
tebing 1 dan 2 di GI Lubuk 2020
Linggau
Pengadaan dan pemasangan MK
Surat Instruksi 7 Februari
11. untuk bayline Tebing 1 dan 2 di GI
2020
Lubuk Linggau
12. Pelaksanaan Testing dan Surat Instruksi 7 Februari
dilengkapi
Bay Trafo
Belum dilaksanakan Flushing
Oil dan Komissioning
1. Trafo Daya 30 MVA
Bushing tersier trafo belum
ada
2. NGR Material belum onsite
3. NCT Material belum onsite
Busbar terminal kabel MV 20 kV &
4. Material belum onsite
Flexible (Copper Braide)
Bay Coupler
1. Stringset tension GSW 55 Material belum onsite
2. GSW 55 Material belum onsite
3. Trafo PS 20 kV/400V Material belum onsite
4. Shielding mes / tower grounding Material belum onsite
PANEL 20 KV
Bus Section
1. Material belum onsite
a. Relay Proteksi
Incomer Trafo 150/20 kV Material belum onsite
a. Relay Proteksi
2.
b. Digital KWh meter
c. Digital amp Meter (Poundful-L)
Outgoing Material belum onsite
3. b. Bus Bar terminal Kabel MV (phasa
RST)
4. Cover end panel Material belum onsite
5. Handle Rack IN/OUT (incomer & BBVT) Material belum onsite
Handle Aux Transformer (handle LBS & Material belum onsite
6.
ES)
7. Clamp Joint Bus Bar Material belum onsite
8. End Plate Bus Bar Material belum onsite
PANEL KONTROL PROTEKSI / AC-DC POWER SUPPLY
Trafo Bay Material belum onsite
1.
d. AVR
2. Server Material belum onsite
a. Modem
b. LAN switch
ACDB 380/400 VAC Material belum onsite
3.
a. Main MCB (sesuai dengan gambar)
DCDB 110 VDC Material belum onsite
4.
a. Main MCB (sesuai dengan gambar)
DCDB 48 VDC Material belum onsite
5.
a. Main MCB (sesuai dengan gambar)
BATTERY
1. 110 DC (type baterry TMP 304) Material belum onsite
1. a. Accesorries kebel jumper battery
b. Fuse 110V DC
48 DC (type battery TMP 152) Material belum onsite
2. a. Accesorries kebel jumper battery
b. Rak battery 48V DC type TPM 152
I GI TEBING TINGGI
1 Remaining Sipil Work 95
Hamparan Split
Dinding Penahan Tanah
Pekerjaan Drainase
2 Pengadaan Material
20 kV NGR, 40 ohm, 10 sec, 20 kV NCT for REF,
2.1 NCT for SBEF and Accessories to complete the 90
scope of work
II GI LUBUK LINGGAU
1. ELECTROMECHANICAL EQUIPMENT
1.1 Pemasangan DS 150 kV 30
5 ENERGIZE 1
BAGIAN 4
KESIMPULAN
Beberapa hal yang dapat disimpulkan dari Kajian Keterlambatan Penyelesaian Pekerjaan
GI 150 kV Tebing Tinggi (Paket Tebing Sumba) yang berakhir durasi kontraknya pada 31
Maret 2022, antara lain:
1. Penyebab keterlambatan penyelesaian pembangunan Gardu Induk 150 kV Tebing
Tinggi adalah:
a. Tidak adanya man power untuk pekerjaan sipil, sehingga tidak ada progress
kemajuan pekerjaan sipil selama periode EOT ke-5.
Berdasarkan monitoring supervisi konstruksi selama periode EOT ke 5 yaitu
tanggal 7 Januari 2022 sampai dengan bulan 31 Maret 2022, tidak ditemukannya
upaya kontraktor untuk penyelesaian pekerjaan sipil, dimana selama periode
tersebut seharusnya pelaksanaan pekerjaan sipil dapat terselesaikan selama
periode EOT ke-5 tersebut. Hal ini menjadi tanggungjawab kontraktor sehingga
tidak dapat diakomodir menjadi alasan perpanjangan waktu penyelesaian
pekerjaan di GI Lubuk linggau dan GI Tebing Tinggi.
b. Adanya kerusakan material elektromekanik existing serta beberapa item pekerjaan
tambah yang belum terakomodir secara kontraktual sehingga diperlukan adanya
amandemen pekerjaan tambah kurang. Pertimbangan ini dapat diakomodir
menjadi alasan pemberian perpanjangan waktu dengan durasi 120 hari kalender.
c. Keterlambatan penyelesaian konstruksi SUTT 150 kV Lubuk Linggau – Tebing
Tinggi yang mengakibatkan tertundanya pelaksanaan Test and Commissioning
seperti intertrip dan pengujian poin to poin. Pertimbangan ini dapat diakomodir
menjadi alasan pemberian perpanjangan waktu dengan durasi 30 hari kalender
2. Berdasarkan uraian diatas, untuk evaluasi perpanjangan waktu yang dapat
diakomodir yaitu terkait dengan diperlukannya perbaikan pada material existing yang
rusak dan pelaksanaan instruksi kerja tambah serta belum selesainya jalur transmisi .
Adapun terkait penyelesaian pekerjaan tersebut dapat dilaksanakan sesuai dengan
pengajuan dari kontraktor yaitu selama 120 hari hingga terbit BAST 1.
3. Evaluasi disusun berdasarkan informasi yang dimiliki UPMK III dengan estimasi
sesuai pengalaman empiris pelaksanaan pekerjaan sebagai salah satu pertimbangan
perubahan jangka waktu pelaksanaan proyek dan tidak menutup kemungkinan
adanya penambahan informasi, perubahan kondisi eksternal atau internal proyek
serta perubahan target pelaksanaan yang dapat mempengaruhi estimasi hasil kajian
sebagaimana tercantum.
LAMPIRAN 1
Surat PLN UPPJ Sumsel 1 perihal permintaan kajian proyek GI 150 kV Tebing Tinggi
AN
LIN
SA
JL. RESIDEN A. ROZAK NO. 2180 SEKOJO PALEMBANG, SUMATERA SELATAN 30118
T -
F - W-
LAMPIRAN 2
Surat Kontraktor tentang usulan perpanjangan waktu
Kepada Yth :
GENERAL MANAJER
PT. PLN (PERSERO) UNIT INDUK
PEMBANGUNAN SUMBAGSEL
Jl. Residen A. Rozak No. 2180 Sekojo
Palembang
Dengan Hormat,
INFORMATION DATASYSTEM
J A K A R T A
ADIL MUNADJAT
Direktur Utama
Tindasan
1. Senior Manager OPKON PLN UIP SBS
2. Manager UPP Sumbagsel 1
3. Manager UPP Sumbagsel 2
4. Arsip
OFFICE :
Komplek Rukan
Malibu City Resort Blok I, No. 11, Jl. Kamal Raya Outer Ring Road, Kelurahan Cengkareng Timur, JAKARTA BARAT 11730 - INDONESIA
Telp. : 021 – 54391562, 021 – 54391568, Fax. : 021 – 54366622
WORKSHOP :
Jl. Raya Duri Kosambi No. 26B, RT/RW 007/002, Kelurahan Duri Kosambi Cengkareng, JAKARTA BARAT 11750 – INDONESIA Telp. : 021 – 54366611
PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI PT PLN (PERSERO) PUSMANPRO UPMK III
LAMPIRAN 3
Notulen Rapat
LAMPIRAN 4
Instruksi Kerja Tambah dan Persetujuan kerja tambah
PT INFORMATION DATA
N
SYSTEMS
NA
dengan ini kami intruksikan untuk dapat merelokasi Material Transmisi Utama (MTU)
150 kV di Gardu Induk Bayung Lincir dengan uraian sebagai berikut :
No. Nama Peralatan Jumlah
1. Current Transformers (CT) Line 150 kV 3 Unit
LAMPIRAN 5
Progress Pekerjaan
KONTRAK PROGES PERIODE LALU PROGES PERIODE INI PROGES S.D. PERIODE INI
ITEM URAIAN PEKERJAAN BOBOT PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL
SAT. VOL.
BOBOT BOBOT BOBOT
PENGADAAN PEMASANGAN TOTAL VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT
A TELECOMMUNICATION EQUIPMENTS
1. PAX set 1 - 0,077 0,077 - - - - - - - - - - - - - - -
- Cabinet : 160 Port ( expandable up to 640 ports)
- CPU-4000 and S/W 810
- BSPlicence ( Port licence) up to 96 extension
- 8 Line E&M Networking 4 wire ( expandable)
- 16 Line Extension Analog ( expandable)
- Mdf 2 x 100 pairs (krone) LSA + solder less with metal box
- Support to SDH,PDH
- 2 set Analogue Telephone Set " Baseline"
- cable network 2x2x0.6 mm include supporting material for analogue telephone set "
Baseline" (2 Point)
- cable layout from PAX to MDF
- PAX Programing
- System Testing & Commissioning
3 AC Distribution Board 220/380 Volt, minimum for 13 bays set 1 - 0,051 0,051 - - 1,00 0,051 0,051 - - - - - - - 1,0 0,051 0,051
PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI DAN PENYELESAIAN BUS COUPLER BAY 1/6
KONTRAK PROGES PERIODE LALU PROGES PERIODE INI PROGES S.D. PERIODE INI
ITEM URAIAN PEKERJAAN BOBOT PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL
SAT. VOL.
BOBOT BOBOT BOBOT
PENGADAAN PEMASANGAN TOTAL VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT
20 kV NGR, 40 ohm, 10 sec. 20 kV NCT for REF, NCT for SBEF and accessories to
2 set 1 - 0,122 0,122 - - - - - - - - - - - - - - -
complete the scope of work
Incoming Cubicle with 1-phase VT and busbar VT Cubicle include 20 kV CB, digital
2 voltmeter, single tarif rate metering digital Kwh meter class 0,2 (All equipment are set 1 - 0,122 0,122 - - 1,00 0,122 0,122 - - - - - - 1,0 0,122 0,122
according to IEC 61850) 0
Outgoing Cubicle including 20 kV CB, Single Rate Tarif metering Digital kWH Meter
3 sets 5 - 0,612 0,612 - - 4,00 0,490 0,490 - - - - - - 4,0 0,490 0,490
class 0.2 (All equipment are according to IEC 61850) 0
Auxialiary transformer 20/0.4 kV, 200 kVA including power cables and termination, etc to
4 set 1 - 0,153 0,153 - - - - - - - - - - - - - - -
complete the scope of work
5 Auxiliary Transformer Cubicle include all accessories to complete the scope of work set 1 - 0,122 0,122 - - - - - - - - - - - - - - -
Bus Section Cubicle including 2000 A CB, Protections, syncro relay etc to complete the
6 set 1 - 0,122 0,122 - - 1,00 0,122 0,122 - - - - - - - 1,0 0,122 0,122
scope of work
7 Bus Riser included terminations conductor etc to complate scope of work set 1 - 0,122 0,122 - - 1,00 0,122 0,122 - - - - - - - 1,0 0,122 0,122
(Semua fungsi control, metering, data dan status seluruh Kubikel 20 kV harus bisa di
akses dari HMI)
2 Single Suspension Insulator String Set & Hardware (1set consist of 12 discs) sets 14 - 0,071 0,071 - - - - - - - - 0 - - - - - -
Mercury Vapour Fluorescent Lamp 1 x 250 Watt for switchyard, complete w/ fitting,
3 titik 12 - 0,184 0,184 - - - - - - - - - - - - - -
junction box, fuse box, grounding, cable, etc to complete the scope of work
0
2 Protection and Control Cubicle for 150/20kV Transformer Bay : set 1 - 0,510 0,510 - - - - - - - - - - - - - - -
- IED Main Transformer Protection (Differential, REF HV/LV Side)
- IED Back Up Protection (OCR, DEF, Fault Locator, metering, etc)
- IED Bay Control
- AVR with auto and manual operation
- 1 mimic diagram
- 1 set of discrepancy switch and indicator
- 1 set of Wiring including connection to outdoor MK, Terminal Block and
switches, Links, Fuses, Test Facilities etc to complete the scope of work
3 Central Control Equipment / HMI Client & Server (Operator Workstation) : set 1 - 0,765 0,765 - - - - - - - - - - - - - - -
- CPU / Keyboard & Mouse /VDU
- Logger printer
- Color Laser Printer
- GPS Time Reference Clock
- Gateway
- Modem
- Ethernet Switch for Inter-bay System 1
PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI DAN PENYELESAIAN BUS COUPLER BAY 2/6
KONTRAK PROGES PERIODE LALU PROGES PERIODE INI PROGES S.D. PERIODE INI
ITEM URAIAN PEKERJAAN BOBOT PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL
SAT. VOL.
BOBOT BOBOT BOBOT
PENGADAAN PEMASANGAN TOTAL VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT
5 AC Supply for SAS: set 1 0,879 0,031 0,910 1 0,879 - - 0,879 - - - - - 1,00 0,879 - - 0,879
- Inverter
- Standing Panel
2 Single phase Current Transformer complete w/ supporting structure pcs 6 6,329 0,918 7,247 6 6,329 6,00 0,918 7,247 - - - - - 6,00 6,329 6,0 0,918 7,247
- Core 1 : 1000-2000/1 A, 30 VA class 5P20 for OCR Protection
- Core 2 : 1000-2000/1 A, class PX for Main Busbar Protection
Three phase Busbar Disconnector, 2000 A, 40 kA, 1 sec with 3-phase driving
3 sets 2 2,578 0,408 2,986 2 2,578 1,60 0,327 2,905 - - - - - 2,00 2,578 1,6 0,327 2,905
mechanism motor operated, complete w/ supporting structure
5 Outdoor Marshalling Kiosk with dimension min. 600 mm x 800 mm x 1120 mm unit 1 0,586 0,051 0,637 1 0,586 1,00 0,051 0,637 - - - - - 1,00 0,586 1,0 0,051 0,637
TOTAL ITEMS A 20,814 2,245 23,059 20,814 2,077 22,891 - - - 20,814 2,077 22,891
2 Single Tension Insulator String Set & Hardware (1 set consist of 12 discs) sets 6 0,633 0,046 0,679 - - 6,00 0,046 0,046 - - - - - - - 6,0 0,046 0,046
3 Single Suspension Insulator String Set & Hardware (1set consist of 12 discs) sets 6 0,563 0,031 0,593 - - 6,00 0,031 0,031 - - - - - - - 6,0 0,031 0,031
Installation of Grounding System in control building panel (BCC size 1 x 120 sqmm) and
5 raiser (BCC 2 x 120 sqmm) to all of HV apparatus, steel supports and cubicles, including bay 1 1,046 0,204 1,250 1 1,046 - - 1,046 - - - - - 1,00 1,046 - - 1,046
accessories etc to complete the scope of work
Mercury Vapour Fluorescent Lamp 1 x 250 Watt for switchyard, complete w/ fitting,
6 titik 3 0,264 0,046 0,310 - - - - - - - - - - - - - - -
junction box, fuse box, grounding, cable, etc to complete the scope of work
LV Power and Multicore Control Cables including all accessories to complete the scope
7 bay 1 2,930 0,408 3,338 1 2,930 1,00 0,408 3,338 - - - - - 1,00 2,930 1,0 0,408 3,338
of work (1 BC)
TOTAL ITEMS B 6,666 0,862 7,528 3,976 0,536 4,512 - - - 3,976 0,536 4,512
PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI DAN PENYELESAIAN BUS COUPLER BAY 3/6
KONTRAK PROGES PERIODE LALU PROGES PERIODE INI PROGES S.D. PERIODE INI
ITEM URAIAN PEKERJAAN BOBOT PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL
SAT. VOL.
BOBOT BOBOT BOBOT
PENGADAAN PEMASANGAN TOTAL VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT
1.a Control Relay Panel for 150 kV Coupler Bay : set 1 11,477 0,510 11,987 1 11,477 0,80 0,408 11,885 - - - - - 1,00 11,477 0,8 0,408 11,885
- IED Back Up Protection (OCR, GFR, UFR for Island Operation, Synchrocheck Relay,
etc)
- IED Control (Bay Control Unit including Manual Closing Synchrocheck)
- Ethernet Switch for Inter-bay System (Ring Type)
- Mimic Diagram for Coupler Bay Control Panel
- Discrepancy Switch and Indicator
- Local/Remote/Supervisory Switch
- Synchro Column
- Wiring, Terminal Block, Links, Fuses, Test Facilities, Auxiliary Relays, etc to complete
the scope of work
All equipment should comply to IEC 61850
1.b Low Impedance Busbar Protection Panel minimum for 13 Bays Feeder : set 1 1 - - - - - - - - - 1,00 - - - -
- IED Main Busbar Protection (Buspro, CBF, Check and Short Zone, etc)
- Ethernet Switch for Inter-bay System (Ring Type)
- Wiring, Terminal Block, Links, Fuses, Test Facilities, Auxiliary Relays, etc to complete
the scope of work
All equipment should comply to IEC 61850
2 Digital Fault Recorder (Installed for 2 LB, 1 TB and 1 BC) set 2 7,032 0,408 7,440 2 7,032 2,00 0,408 7,440 - - - - - 2,00 7,032 2,0 0,408 7,440
New free standing sheet steel cubicle as follows :
Fault recording equipment comprising necessary quantity of fault recorders equipped
with oscillograph printer to record the information as specified. The recorders shall be
provided with date and time indicators and time synchronising equipment clock via
satelite.
TOTAL ITEMS C 23,196 1,429 24,625 18,508 0,816 19,325 - - - 18,508 0,816 19,325
GRAND TOTAL ITEMS (A-C) 50,676 4,536 55,212 43,298 3,429 46,727 - - - 43,298 3,429 46,727
B. PEKERJAAN SIPIL
A PEKERJAAN PERSIAPAN UNTUK SWITCHYARD
1 Mobilisasi dan Demobilisasi Peralatan pekerjaan sipil ls 0,333 - 0,183 0,183 - - - - - - - - - - - - - - -
2 Sondir (termasuk Report) ttk 2 - 0,114 0,114 - - - - - - - - - - - - - - -
3 Hand Boring (termasuk Test Laboratory + Report) ttk 1 - 0,041 0,041 - - - - - - - - - - - - - - -
4 Pembangunan Direksi Keet 4x6 m2 (bangunan temporary) unit 1 - 0,264 0,264 - - 0,50 0,132 0,132 - - - - - - - 0,5 0,132 0,132
5 Penyediaan Listrik dan Air untuk Kerja ls 0 - - - - - - - - - - - - - - - -
6 Biaya Desain (Perhitungan, Detail Gambar Desain dan As Built Drawing) ls 0 - 0,183 0,183 - - - - - - - - - - - - - - -
Pagar BRC Hot Dip Galvanized h = 120 cm diameter 7 mm (termasuk beton sloof) - 0,876 0,876 - - - - - - - - - - - - - - -
1.1 m1 101
1.2 Pintu pagar BRC h=120 cm L = 4 m bh 1 - 0,150 0,150 - - - - - - - - - - - - - - -
PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI DAN PENYELESAIAN BUS COUPLER BAY 4/6
KONTRAK PROGES PERIODE LALU PROGES PERIODE INI PROGES S.D. PERIODE INI
ITEM URAIAN PEKERJAAN BOBOT PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL
SAT. VOL.
BOBOT BOBOT BOBOT
PENGADAAN PEMASANGAN TOTAL VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT VOL BOBOT
2 PAGAR SITE
Pagar BRC h = 175 cm, Ø 7mm, Hot Dip Galvanized (termasuk sloof beton bertulang
dan pasangan bata t = 40 cm) - 5,782 5,782 - - - - - - - - - - - - - - -
2.1 m1 594
PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI DAN PENYELESAIAN BUS COUPLER BAY 5/6
Periode : MARET 2022
Pekerjaan : PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI DAN PENYELESAIAN BUS COUPLER BAY
No. Kontrak / Tanggal : 005.PJ/KON.02.04/UIP SUMBAGSEL/2019, tanggal 08 Maret 2019
Kontraktor : PT. INFORMATION DATA SYSTEM
Nilai Kontrak : Rp 32.484.290.865
BOBOT KONTRAK PROGES PERIODE LALU PROGES PERIODE INI PROGES S.D. PERIODE INI
ITEM URAIAN PEKERJAAN
PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL PENGADAAN PEMASANGAN TOTAL
PENGADAAN PEMASANGAN TOTAL
BOBOT BOBOT BOBOT
A. PEKERJAAN ELEKTROMEKANIK
D 20 kV SWITCHGEAR, POWER CABLES AND AUXILIARY - 2,021 2,021 - 0,857 0,857 - - - - 0,857 0,857
F SUBSTATION AUTOMATION SYSTEM (SAS) 2,051 4,368 6,418 0,879 - 0,879 - - - 0,879 - 0,879
GRAND TOTAL ITEMS (A-F) 4,985 10,265 15,250 0,879 1,061 1,940 - - - 0,879 1,061 1,940
A ELECTROMECHANICAL EQUIPMENT OF BUS COUPLER BAY : 1 BC 20,814 2,245 23,059 20,814 2,077 22,891 - - - 20,814 2,077 22,891
B CONDUCTOR, INSULATOR SET, HV CONNECTOR, EARTHING SYSTEM, LIGHTING SYSTEM AND CONTROL CABLE
6,666 0,862 7,528 3,976 0,536 4,512 - - - 3,976 0,536 4,512
C SUBSTATION AUTOMATION SYSTEM (SAS) 23,196 1,429 24,625 18,508 0,816 19,325 - - - 18,508 0,816 19,325
GRAND TOTAL ITEMS (A-C) 50,676 4,536 55,212 43,298 3,429 46,727 - - - 43,298 3,429 46,727
B. PEKERJAAN SIPIL
A PEKERJAAN PERSIAPAN UNTUK SWITCHYARD - 0,785 0,785 - 0,132 0,132 - - - - 0,132 0,132
B PEKERJAAN TEMBOK PENAHAN (GI Tebing Tinggi) - 2,186 2,186 - 0,267 0,267 - - - - 0,267 0,267
C PEKERJAAN JALAN KOMPLEK (GI Tebing Tinggi) - 9,023 9,023 - 4,564 4,564 - - - - 4,564 4,564
E PEKERJAAN PAGAR SWITCHYARD & PAGAR SITE (GI Tebing Tinggi) - 6,999 6,999 - - - - - - - - -
F PEKERJAAN PONDASI TRAFO, SERANDANG & PERALATAN - 2,004 2,004 - 0,476 0,476 - - - - 0,476 0,476
G PEKERJAAN SALURAN KABEL SWITCHYARD AREA - 1,218 1,218 - 0,140 0,140 - - - - 0,140 0,140
GRAND TOTAL ITEMS (A-i) - 29,538 29,538 - 5,579 5,579 - - - - 5,579 5,579
GRAND TOTAL 55,661 44,339 100,000 44,177 10,069 54,246 - - - 44,177 10,069 54,246
PENYELESAIAN GARDU INDUK 150 KV TEBING TINGGI DAN PENYELESAIAN BUS COUPLER BAY 6/6