PLN (PERSERO)
PUSAT MANAJEMEN PROYEK
UNIT PELAKSANA MANAJEMEN KONSTRUKSI III
DAFTAR ISI
BAGIAN 1
PENDAHULUAN
BOBOT Progress
NO ITEM PEKERJAAN ADD.03 s/d saat Deviasi
(%) ini
A.1 SUTET 275 kV PHI INCOMER MUARA ENIM ( PAKET PEPES ENIM )
Pekerjaan Elektromekanik
Pengadaan Insulator set Clamp & Fitting
0.172 - -0.172
serta Accessories
Penarikan Kawat (Stringing) 11.318 - -11.318
Penerapan K2 & K3 0.215 - -0.215
SUB TOTAL 11.705 - -11.705
Pekerjaan Sipil
Pengadaan Persiapan 0.041 0.023 -0,018
Pekerjaan Survey dan Penyelidikan Tanah 0.344 - -0.344
Pekerjaan Pengadaan Tower (Include stub
51.436 41,357 -10.079
& Accessories Tower)
Pekerjaan Pondasi 22.727 11,320 -11.407
Pekerjaan Erection Tower 7.027 1,941 -5.086
Pekerjaan Lain-lain 3.265 - -3.265
SUB TOTAL 84.840 54.640 -30.200
Pekerjaan Recover & Penormalan Jalur GK
Pekerjaan Sipil 3.288 3.288 -
Pekerjaan Elektromekanik 0.167 0.167 -
SUB TOTAL 3.455 3.455 -
TOTAL SEMUA 100 58.095 -41.905
Pekerjaan
ENERGIZE Pekerjaan RLB Pekerjaan Stringing
Comissioning
- - - -
BAGIAN 2
PERMASALAHAN PROYEK
BAGIAN 3
HASIL EVALUASI
b. Jaminan Pelaksanaan
Sesuai dengan Kesepakatan Diskusi Kontrak (Contract Discussion
Agreement) Poin 1.6 tentang Jaminan Pelaksanaan, menyebutkan bahwa:
Kontraktor menyerahkan Jaminan Peaksanaan selambat-lambatnya 14
(empat belas) hari kerja setelah Surat Perjanjian/ Kontrak
ditandatangani dengan nilai Jaminan sekurang-kurangnya 5% (lima
persen) dari Nilai Kontrak termasuk PPN yaitu sebesar Rp.
3.202.402.000,- (Tiga milyar dua ratus dua juta empat ratus dua ribu
rupiah).
Apabila sampai dengan batas waktu yang ditetapkan, Jaminan
Pelaksanaan belum diserahkan, maka Perjanjian/Kontrak dapat
dibatalkan sepihak oleh Pengguna Barang/Jasa, dan Penyedia
Barang/Jasa yang ditunjuk dapat dikenakan sanksi daftar hitam
(blacklist) serta Jaminan Penawaran (jika ada) dicairkan dan menjadi
milik PT PLN (Persero).
Masa berlaku Surat Jaminan Pelaksanaan sekurang-kurangnya Masa
Pelaksanaan Kontrak 365 (tiga ratus enam puluh lima) hari kalender
ditambah Masa Pemeliharaan 12 (dua belas) bulan dan ditambah 30
(tiga puluh) hari kalender berlaku sejak tanggal diterbitkannya Jaminan
Pelaksanaan tersebut. Sehingga secara keseluruhan Masa Berlaku
Jaminan Pelaksanaan sekurang-kurangnya selama 760 (tujuh ratus
d. Masa Pemeliharaan
Sesuai dengan Kesepakatan Diskusi Kontrak (Contract Discussion
Agreement) Poin 10.3 tentang Masa Pemeliharaan, menyebutkan bahwa:
Masa Pemeliharaan adalah 12 (dua belas) bulan sejak serah terima
pekerjaan 100% (ST-I).
Type Type
Type Tower Type Type Tower
Tower
AAE Tower CCE Tower DDE FFE
BBE
21 2 3 6 1
4. Sampai dengan saat ini mengacu berita acara penyerahan lahan tahap
1 (satu) sampai dengan tahap 4 (empat), terdapat sisa lahan atau tapak
tower (T.15, T.16, T.19, T.20, T.56, T.67, T.68, T.69, T.70, T.71, T.74,
T.77, T.78, T.79, T.80, T.81) yang belum dilakukan serah terima kepada
kontraktor mulai dari awal kontrak, sehingga berdampak menghambat
pekerjaan konstruksi di lapangan. Dengan rincian isu pembebasan lahan
pada tower tersebut diatas, sebagai berikut:
T. 15 dan T.16 telah dilakukan pembayaran kepada pemilik lahan,
dan saat ini sedang menunggu serah terima lahan dari PLN ke
Kontraktor
T.19 dan T.20 terdapat isu permasalahan tumpang tindih
kepemilikan antara warga dan KUD PT Minanga Ogan
T.56 terdapat isu permasalahan pemilik lahan meminta harga tanah
per meter seperti harga tanah kavlingan
T.67 – T.71, T.76 - T.81 (Area perkebunan PTPN VII 11 Tapak),
sedang dilakukan penjajakan sistem sewa dan izin kerja terlebih
dahulu.
5. Terdapat 16 tapak tower serta 19 Span ROW yang belum dibebaskan
dan 28 span yang belum tebang, dan berpotensi terhambatnya
pekerjaan konstruksi di lapangan dan memungkinkan proses
administrasi mulai dari musyawarah hingga negosiasi. Sesuai notulen
rapat tanggal 01 Maret 2022, bahwa target penyelesaian permasalahan
tersebut pada term 1 2022. Estimasi penyelesaian pembebasan tapak
a. Pondasi
Mengacu terhadap schedule bahwa pekerjaan pondasi (T.15, T.16, T.19,
T.20, T.56, T.67, T.68, T.69, T.70, T.71, T.74, T.77, T.78, T.79, T.80,
T.81) direncanakan akan dikerjakan pada periode Minggu ke-1 Jan 2022
dan rencana selesai pondasi pada Minggu ke-3 Maret 2022. Namun
sampai periode kontrak berakhir diinformasikan bahwa :
Terdapat 16 tapak tower dalam tahap pembebasan lahan dan
berada pada 3 kecamatan yang berbeda.
Diantara 16 tapak tower tersebut, terdapat 11 Tower (T.67, T.68,
T.69, T.70, T.71, T.74, T.77, T.78, T.79, T.80, T.81) yang berada di
area PTPN 7, dan mengalami peninggian tower sehingga
mengakibatkan terjadinya perubahan type tower.
Saat ini terdapat 6 tapak tower yang lahannya telah dibebaskan dan
dapat dikerjakan (4 tower on going konstruksi sampai dengan saat ini
T. 51 (on going cutting borepile), T.52 (sisa backfill), T.55 (sisa backfill),
dan T.60 (on going borepile), dan 2 Tower yang belum dikerjakan,
dikarenakan lahan T.1 dan T.31 baru dilakukan serah terima dari UPP ke
kontraktor pada tanggal 28 Maret 2022. Sehingga Durasi penyelesaian
sisa pekerjaan pondasi membutuhkan estimasi pelaksanaan 110 hari
dan dapat dilaksanakan paralel dengan 4 grup pondasi (1 Grup Pondasi
Borepile dan 3 Grup Pondasi Normal).
b. Erection
Pekerjaan erection tower terhadap pondasi yang telah selesai dapat
segera dimulai dan berlangsung paralel menyesuaikan dengan kondisi
proyek dan jalur kritis pekerjaan pondasi. Sisa Tower yang belum
dilakukan erection 33 erection (1 on going) dan sisa 10 tower yang telah
siap untuk dierection dapat segera dimulai dan berlangsung paralel
menyesuaikan dengan kondisi proyek dan jalur kritis pekerjaan pondasi.
Durasi yang dibutuhkan untuk penyelesaian sisa erection area PTPN 7
yang mengalami peninggian tower membutuhkan estimasi pelaksanaan
30 hari setelah penyelesaian pondasi dan dapat dilaksanakan paralel
dengan 4 grup erection.
c. Stringing
Mengacu terhadap schedule bahwa item pekerjaan stringing
direncanakan mulai dilaksanakan pada periode Februari 2022 dan
selesai pada Mei 2022. Hingga periode kontrak berakhir diinformasikan
bahwa masih ada 16 tapak tower beserta ROW 19 span masih dalam
proses penyelesaian.
Rencana section penarikan pada Pepes Enim terdiri dari 5 section (10
sirkit) dengan membutuhkan durasi waktu 155 hari dengan 2 tim kerja
paralel bersama pekerjaan pondasi dan erection dan asumsi durasi
waktu yang diperlukan untuk penyelesaian sisa pekerjaan stringing atau
penarikan terakhir adalah 36 hari (include mobdemob peralatan),
dimana jadwal penarikan dipengaruhi oleh kesiapan erection tower dan
dapat dimulai pada segmen tarikan yang telah selesai ROW dan Span
tebang, sehingga jadwal stringing tidak akan mengalami kemunduran
bilamana produktifitas erection tower dan ROW berlangsung secara
bersamaan.
d. Final Check
Terhadap point (a) sampai dengan poin (d) jangka waktu penyelesaian
dengan asumsi pelaksanaan pembebasan lahan beserta ROW dapat
dilaksanakan sesuai pada rencana yang telah disusun, maka durasi yang
didapat untuk penyelesaian secara menyeluruh seperti barchart berikut:
BAGIAN 4
KESIMPULAN
Waktu pelaksanaan proyek akan berakhir pada tanggal 31 Mei 2022, terhadap
usulan kontraktor terkait perpanjangan waktu dapat disimpulkan hal berikut:
1. Pentingnya penyelesaian jalur SUTET 275 kV kV Phi Incomer Muara
Enim (Paket Pepes Enim) untuk kebutuhan back feeding antara GITET
Lumut Balai 275 kV dan GITET Muara Enim 275 kV. Terdapat beberapa
Tapak Tower dan ROW yang belum bebas hingga periode kontrak
berakhir serta korelasi jadwal pekerjaan transmisi PLG Section 01 dan 02
yang harus segera diselesaikan, maka permohonan perpanjangan waktu
yang dapat dipertimbangkan yaitu 183 hari.
2. Kontraktor berkomitmen untuk mendatangkan tim kerja lapangan sesuai
dengan schedule pelaksanaan yang telah disampaikan kontraktor melalui
surat dengan nomor 073/MSJ-P.ENIM/V/2022 perihal Permohonan
Perpanjangan Waktu Pelaksanaan Penyelesaian Pembangunan SUTET
275 kV Phi Incomer Muara Enim (Paket Papes Enim).
3. Apabila perpanjangan waktu pelaksanaan disetujui para pihak, maka
kontraktor agar segera memproses dokumen perpanjangan jaminan
pelaksanaan.
4. Evaluasi disusun berdasarkan informasi yang dimiliki UPMK III dengan
estimasi sesuai pengalaman empiris pengawasan proyek sebagai salah
satu pertimbangan perubahan jangka waktu pelaksanaan proyek.
5. Penambahan informasi, perubahan kondisi eksternal atau internal proyek
dan target pelaksanaan proyek (PLN-red) dapat mempengaruhi
kesesuaian hasil kajian sebagaimana tercantum.
6. Dalam pelaksanaan perjanjian, perlu diperhatikan bahwa tidak hanya
berkaitan dengan aspek bisnis, pemenuhan aspek legal harus menjadi
bagian penting dalam penyelesaian proyek. Sehingga, bentuk konsultasi
dengan bidang/unit hukum koorporasi diyakini dapat memberikan
alternatif legal sesuai kondisi para pihak.
LAMPIRAN 1
ADDENDUM KONTRAK PERPANJANGAN WAKTU NO.03
LAMPIRAN 2
SURAT PERMOHONAN PERPANJANGAN WAKTU PELAKSANAAN
KONTRAKTOR
LAMPIRAN 3
TIME SCHEDULE KONTRAKTOR
BOBOT BOBOT TAHUN 2021 TAHUN 2021 TAHUN 2021 TAHUN 2022 TAHUN 2022
NO URAIAN PEKERJAAN KONTRAK ADD. SISA KETERANGAN
(%) (%) PROGRES SISA SISA
JAN PEB MAR APR MEI JUN JUL CCO AGU SEP OKT NOP DES JAN FEB MAR APR MEI JUN JUL AGT SEP OKT NOV
B PENARIKAN KAWAT (STRINGING) 11,723 11,318 0,586 1,758 11,318 2,264 2,264 2,264 11,318 2,264 2,264 2,264 2,264 2,264 11,318 2,264 2,264 2,264 2,264 2,264
C PENERAPAN K2 & K3 0,223 0,215 0,019 0,019 0,019 0,019 0,019 0,019 0,215 0,036 0,036 0,036 0,215 0,043 0,043 0,043 0,043 0,043 0,215 0,036 0,036 0,036 0,036 0,036 0,036
Pondasi Group 1
T.01 FF + 6 Re-Design
Erection Group 1
Pondasi
T.02 AA + 6 1
Erection
Pondasi
T.03 AA + 6 1
Erection
Pondasi
T.04 AA + 9 1
Erection
Pondasi
T.05 AA + 9 3
Erection
Pondasi
T.06 AA + 3 2
Erection
Pondasi
T.07 AA + 3 6
Erection
Pondasi
SECTION 4
T.08 AA + 9 1
Erection
Pondasi
T.09 AA + 9 1
Erection
Pondasi
T.10 CC + 9 2
Erection Group 1
Pondasi
T.11 AA + 3 1
Erection
Pondasi
T.12 AA + 6 1
Erection
Pondasi
T.13 AA + 3 2
Erection
Pondasi
T.14 AA + 3 2
Erection
Pondasi Group 2
T.15 AA + 3 1
Erection Group 2
Pondasi Group 1
T.16 AA + 6 1
Erection Group 1
Pondasi
T.17 DD + 9 2
Erection Group 2
Pondasi
T.18 AA + 9 2
Erection
Pondasi Group 1
T.19 AA + 3 2
Erection Group 1
Pondasi Group 3
T.20 BB + 9 1
Erection Group 2
Pondasi
T.21 AA + 9 1
Erection
Pondasi
T.22 AA + 9 1
Erection
Pondasi
T.23 AA + 6 1
Erection
Pondasi
T.24 AA + 9 2
Erection
Pondasi
T.25 AA + 6 2
Erection
Pondasi
T.26 AA + 9 1
Erection
Pondasi
T.27 DD + 9 2
SECTION 3
Erection Group 3
Pondasi
T.28 AA + 3 2
Erection
Pondasi
T.29 AA + 3 2
Erection
Pondasi
T.30 AA + 6 2
Erection
Pondasi Group 1
T.31 AA + 9 1
Erection Group 3
Pondasi
T.32 AA + 3 1
Erection
Pondasi
T.33 AA + 6 1
Erection
Pondasi
T.34 AA + 3 1
Erection
Pondasi
T.35 AA + 9 2
Erection
Pondasi
T.36 AA + 9 1
Erection
Pondasi
T.37 CC + 6 2
Erection Group 1
Pondasi
T.38 AA + 3 2
Erection
Pondasi
T.39 AA + 0 2
Erection
Pondasi
T.40 AA + 6 2
Erection
Pondasi
T.41 AA + 3 6
Erection
Pondasi
T.42 AA + 9 2
Erection
Pondasi
T.43 CC + 3 3
Erection Group 1
SECTION 1
Pondasi
T.44 AA + 6 1
Erection
Pondasi
T.45 AA + 6 6
Erection
Pondasi
T.46 AA + 6 2
STATUS TAHUN 2022
NO Kelas STATUS May-22 Jun-22 Jul-22 Aug-22 Sep-22 Oct-22 Nov-22
TYPE TOWER PONDASI /
TOWER Pondasi STRINGING
ERECTION 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
T.46 AA + 6 2
Erection
Pondasi
T.47 AA + 3 2
Erection
Pondasi
T.48 AA + 9 2
Erection
Pondasi
T.49 AA + 6 6
Erection
Pondasi
T.50 AA + 6 6
Erection Group 2
Pondasi Group 2
T.51 DD + 6 6
Erection Group 1
Pondasi
T.52 AA + 9 2
Erection Group 1
Pondasi Group 2
T.53 AA + 9 2
Erection Group 2
Pondasi
T.54 AA + 9 2
Erection Group 2
Pondasi
T.55 AA + 9 2
Erection Group 3
Pondasi Group 3
T.56 DD + 6 2
Erection Group 4
Pondasi
T.57 AA + 9 2
SECTION 2
Erection
Pondasi
T.58 AA + 6 2
Erection
Pondasi
T.59 AA + 9 1
Erection
Pondasi Group 3
T.60 AA + 9 6
Erection Group 1
Pondasi
T.61 AA + 6 3
Erection
Pondasi
T.62 AA + 3 2
Erection Group 2
Pondasi
T.63 AA + 3 2
Erection Group 3
Pondasi
T.64 AA + 3 2
Erection Group 4
Pondasi
T.65 DD + 3 6
Erection Group 2
Pondasi
T.66 AA + 9 3
Erection
Pondasi Group 2
T.67 AA + 21 Re-Design
Erection Group 3
Pondasi Group 3
T.68 AA + 18 3
Erection Group 2
Pondasi Group 4
T.69 AA + 21 2
Erection Group 3
Pondasi Group 1
T.70 AA + 21 2
Erection Group 1
Pondasi Group 2
T.71 AA + 21 6
Erection Group 2
Pondasi
T.72 AA + 9 2
Erection
Pondasi
T.73 AA + 6 1
Erection
SECTION 5
Pondasi Group 3
T.74 BB + 12 1
Erection Group 3
Pondasi
T.75 AA + 6 2
Erection
Pondasi
T.76 AA + 9 2
Erection
Pondasi Group 4
T.77 AA + 15 Re-Design
Erection Group 4
Pondasi Group 5
T.77 A AA + 18 New-Design
Erection Group 5
Pondasi Group 1
T.78 AA + 18 Re-Design
Erection Group 1
Pondasi Group 2
T.79 BB + 18 6
Erection Group 2
Pondasi Group 3
T.80 AA + 21 3
Erection Group 3
Pondasi Group 4
T.81 DD + 15 3
Erection Group 4
Pondasi Group 5
T.82 FF + 3 New-Design
Erection Group 5
LAMPIRAN 4
PROGRES PEKERJAAN
Pekerjaan : PENYELESAIAN PEMBANGUNAN SUTET 275 KV PHI INCOMER MUARA ENIM (PAKET PEPES ENIM)
Nomor Kontrak / Tanggal : 0012.PJ/DAN.01.03/UIP SUMBAGSEL/2020, Tanggal 26 Oktober 2020
Kontraktor : PT. MEDAN SMART JAYA
Nilai Kontrak : Rp. 64.048.021.675
Nilai Adendum 03 : Rp. 66.340.049.935
Progress : 58,095 %
I. PEKERJAAN ELEKTROMEKANIK
A PENGADAAN INSULATOR SET CLAMP & FITTING, SERTA ACCESORIES 0,172 - - -
B PENARIKAN KAWAT (STRINGING) 11,318 - - -
C PENERAPAN K2 & K3 0,215 - - -
SUB-TOTAL I 11,705 - - -
Pekerjaan : PENYELESAIAN PEMBANGUNAN SUTET 275 KV PHI INCOMER MUARA ENIM (PAKET PEPES ENIM)
Nomor Kontrak / Tanggal : Tanggal 26 Oktober 2020
Kontraktor : PT. MEDAN SMART JAYA
Nilai Kontrak
Progress : 54,640 %
A. PEKERJAAN PERSIAPAN
1 Mobilisasi Tenaga Kerja dan Peralatan 1,00 ls 0,0414 0,56 0,023 - 0,56 0,023
1 Type AA
a. AA + 0 - 1,00 set 0,7375 0,97 0,713 - - 0,97 0,713
b. AA + 3 - 9,00 set 7,0904 5,82 4,585 - 5,82 4,585
c. AA + 6 1 9,00 set 7,5922 8,74 7,375 - - 8,74 7,375
d. AA + 9 - 19,00 set 16,9797 18,50 16,529 - - 18,50 16,529
e. AA + 12 N/A set - - - - - - -
f. AA + 15 N/A set - - - - - - -
2 Type BB
a. BB + 0 - 1,00 set 0,9933 0,94 0,938 - 0,94 0,938
b. BB + 3 - N/A set - - - - - -
c. BB + 6 1 1,00 set 1,1894 0,95 1,134 - 0,95 1,134
d. BB + 9 - N/A set - - - - - -
e. BB + 12 N/A set - - - - - -
f. BB + 15 N/A set - - - - - -
3 Type CC
a. CC + 0 - N/A set - - - - - -
b. CC + 3 - 1,00 set 1,3728 0,94 1,294 - 0,94 1,294
c. CC + 6 1 1,00 set 1,4699 0,95 1,391 - 0,95 1,391
d. CC + 9 - 1,00 set 1,5972 0,95 1,518 - 0,95 1,518
e. CC + 12 N/A set - - - - - - -
f. CC + 15 N/A set - - - - - - -
4 Type DD/DDR
a. DD/DDR + 0 - N/A set - - - - - - -
b. DD/DDR + 3 - 1,00 set 1,9363 0,95 1,841 - 0,95 1,841
c. DD/DDR + 6 1 3,00 set 6,0562 0,95 1,923 - 0,95 1,923
d. DD/DDR + 9 - 2,00 set 4,4211 0,96 2,115 - 0,96 2,115
e. DD/DDR + 12 N/A set - - - - - -
f. DD/DDR + 15 N/A set - - - - - - -
D. PEKERJAAN PONDASI
1 Type AA
a. Klas 1 6,00 unit 1,5888 2,00 0,530 - 2,00 0,530
b. Klas 2 15,00 unit 5,1730 6,00 2,069 - 6,00 2,069
c. Klas 3 2,00 unit 1,0239 1,00 0,512 - 1,00 0,512
d. Klas 6 (exclude borepile) 5,00 unit 2,4156 1,00 0,483 1,00 0,4831 2,00 0,966
2 Type BB
a. Klas 1 1,00 unit 0,4949 - - - - -
b. Klas 2 N/A unit - - - -
c. Klas 3 1,00 unit 0,7534 - - - - -
d. Klas 6 (exclude borepile) N/A unit - - - -
3 Type CC
a. Klas 1 N/A unit - - - -
b. Klas 2 N/A unit - - - -
c. Klas 3 1,00 unit 0,8711 1,00 0,8711 - 1,00 0,8711
d. Klas 6 (exclude borepile) N/A unit - - - -
4 Type DD/DDR
a. Klas 1 N/A unit - - - -
b. Klas 2 1,00 unit 0,8495 - - - -
c. Klas 3 1,00 unit 1,1836 - - - -
d. Klas 6 (exclude borepile) 3,00 unit 2,3371 1,00 0,7790 - 1,00 0,7790
- - - -
5 Pekerjaan Borepile diameter 60 cm (Untuk pondasi Klas 6) - - - -
a. Mobilisasi Alat Borepile 8,00 Ttk 0,0102 4,00 0,0051 - 4,00 0,0051
b. Pekerjaan Pengeboran Borepile (dia 60cm) 1.718,40 m' 1,3224 1.080,00 0,8311 540,00 0,4156 1.620,00 1,2467
c. Pengadaan, Pemasangan dan Pembongkaran Casing 236,00 m' 0,0682 - - - - -
d. Cutting Kepala Borepile 180,00 bh 0,0692 76,00 0,0292 18,00 0,0069 94,00 0,0361
e. Borepile dia 60 cm(include beton K225, besi tulangan BJTD32&BJTP24 dan langsir material 1.718,40 m' 4,5660 1.080,00 2,8697 540,00 1,4349 1.620,00 4,3046
borepile)
1 Type AA
a. AA + 0 - 1,00 set 0,0902 1,00 0,0902 - 1,00 0,0902
b. AA + 3 - 9,00 set 0,8676 5,00 0,4820 - 5,00 0,4820
c. AA + 6 1 9,00 set 0,9290 4,00 0,4129 - 4,00 0,4129
d. AA + 9 - 19,00 set 2,0777 7,00 0,7655 - 7,00 0,7655
e. AA + 12 N/A set - - - -
f. AA + 15 N/A set - - - -
g. Pengelasan baut tower sampai ketinggian 9m 38,00 set 0,5569 12,00 0,1759 1,00 0,0147 13,00 0,1905
2 Type BB
a. BB + 0 - 1,00 set 0,1215 - - - -
b. BB + 3 - N/A set - - - -
c. BB + 6 1 1,00 set 0,1455 - - - -
d. BB + 9 - N/A set - - - -
e. BB + 12 N/A set - - - -
f. BB + 15 N/A set - - - -
g. Pengelasan baut tower sampai ketinggian 9m 3,00 set 0,0440 - - - -
3 Type CC
a. CC + 0 - N/A set - - - -
b. CC + 3 - 1,00 set 0,1680 - - - - -
c. CC + 6 1 1,00 set 0,1799 - - - - -
d. CC + 9 - 1,00 set 0,1954 - - - - -
e. CC + 12 N/A set - - - -
f. CC + 15 N/A set - - - -
g. Pengelasan baut tower sampai ketinggian 9m 3,00 set 0,0440 - - - - -
4 Type DD/DDR
a. DD/DDR + 0 - N/A set - - - -
b. DD/DDR + 3 - 1,00 set 0,2369 - - - -
c. DD/DDR + 6 1 3,00 set 0,7411 - - - -
d. DD/DDR + 9 - 2,00 set 0,5410 - - - -
e. DD/DDR + 12 N/A set - - - -
f. DD/DDR + 15 N/A set - - - -
g. Pengelasan baut tower sampai ketinggian 9m 6,00 set 0,0879 - - - -
Pekerjaan : PENYELESAIAN PEMBANGUNAN SUTET 275 KV PHI INCOMER MUARA ENIM (PAKET PEPES ENIM)
Nomor Kontrak / Tanggal : KONTRAK NO. 0004.PJ/KON.02.01/UIP SUMBAGSEL/2018
Kontraktor : PT. MEDAN SMART JAYA
Nilai Kontrak :
Progress 0,000 %
I. PEKERJAAN ELEKTROMEKANIK
KONTRAK PROGRESS
PERIODE LALU PERIODE INI TOTAL S/D PERIODE INI
NO. URAIAN PEKERJAAN BOBOT
JUMLAH SATUAN
(%) JUMLAH BOBOT (%) JUMLAH BOBOT (%) JUMLAH BOBOT (%)
C. PENERAPAN K2 & K3
1 Penerapan K2 dan K3 Untuk Pekerjaan Pondasi, Erection dan Stringing (Sewa Peralatan) 1,00 Ls 0,215 - - - -
- Safety Shoes
- Safety Helmet
- Wearpack (Cover Up/Jaket)
- Gloves
- Full Body Harness
- Caution Marking/Tagging
- Perlengkapan P3K
Subtotal C 0,215 0,000 0,000 0,000
TOTAL 11,705 0,000 0,000 0,000
I. PEKERJAAN SIPIL
ADD. 03 PROGRESS
PERIODE LALU PERIODE INI TOTAL S/D PERIODE INI
NO URAIAN PEKERJAAN BOBOT
VOLUME SAT BOBOT BOBOT
(%) VOLUME VOLUME VOLUME BOBOT (%)
(%) (%)
A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi tenaga kerja dan peralatan kerja 1,00 Ls 0,454 1,00 0,45 - - 1,00 0,454
2 Sewa gudang dan Base Camp sementara 1,00 Ls 0,086 1,00 0,09 - - 1,00 0,086
Page 6 of 8
ADD. 03 PROGRESS
PERIODE LALU PERIODE INI TOTAL S/D PERIODE INI
NO URAIAN PEKERJAAN BOBOT
VOLUME SAT BOBOT BOBOT
(%) VOLUME VOLUME VOLUME BOBOT (%)
(%) (%)
Page 7 of 8
II PEKERJAAN ELEKTROMEKANIK
ADD. 03 PROGRESS
PERIODE LALU PERIODE INI TOTAL S/D PERIODE INI
NO URAIAN PEKERJAAN BOBOT
SATUAN VOLUME BOBOT BOBOT BOBOT
(%) VOLUME VOLUME VOLUME
(%) (%) (%)
B. PENERAPAN K2 & K3
1 Penerapan K2 dan K3 Untuk Pekerjaan Pondasi, Erection dan Stringing (Sewa Peralatan) Ls 1,00 0,027 1,000 0,027 - - 1,000 0,027
- Safety Shoes
- Safety Helmet
- Wearpack (Cover Up/Jaket)
- Gloves
- Full Body Harness
- Caution Marking/Tagging
- Perlengkapan P3K
Page 8 of 8