PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH

DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ


DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)
PEKERJAAN PENGADAAN
1 KONDUKTOR, KAWAT TANAH DAN FIBER OPTIC (OPGW):
1.1 Konduktor ACSR 435/55 mm2 km 465 Suplay oleh PLN
1.2 Galvanize Steel Wire (GSW) 70 mm2 km 39
1.3 Optical Ground Wire (OPGW) 70 mm2, 24 cores km 39
1.4 Armour Rod Konduktor ACSR Zebra 435/55 mm2 set 756
1.5 Armour Rod GSW 70 mm2 set 63
1.6 Armour Rod OPGW 70 mm2 set 63
1.7 Join Box OPGW 70 mm2 24 cores bh 13
1.8 Repair Sleeve ACSR 435/55 mm2 bh 60
1.9 Compression Joint ACSR 435/55 mm2 bh 305
1.10 Compression Joint GSW 70 mm2 bh 15
TOTAL ITEM 1

2 AKSESORIS KONDUKTOR DAN KAWAT TANAH :


2.1 Vibration Damper Konduktor ACSR Zebra 435/55 mm2 bh 3,528
2.2 Spacer Konduktor 400 mm ACSR Zebra 435/55 mm2 (untuk span) bh 2,892
2.3 Spacer Konduktor 200 mm for ACSR Zebra 435/55 mm2 (untuk jumper) bh 600
2.4 Vibration damper GSW 70 mm2 bh 228
2.5 Vibration damper OPGW 70 mm2 bh 228
TOTAL ITEM 2

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


1 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)
3 PENTANAHAN TOWER
3.1 Pentanahan tower (earthing device) lengkap terdiri dari 4 set Galvanized steel siku 45 x 45 x 5 twr 113
panjang 100 cm, Lead wire 2 m, termasuk clamping
3.2 Counterpoise Continuous set terbuat dari GSW dengan panjang 30 m, ditanam pada Set 20
kedalaman minimal 45 cm, termasuk galvanized steel angle siku 45 x 45 x 5 panjang 100 cm,
penyambungan, dan clamping.

TOTAL ITEM 3 -

4 ISOLATOR STRING SET, FITTING, AKSESORIS, DAN DISC ISOLATOR


4.1 Single Suspension String set Isolator 120 KN, creepage distance 5.270 mm Set 114
4.2 Double Suspension String set Isolator 120 KN, creepage distance 5.270 mm Set 264
4.3 Single Tension String set Isolator 210 KN, creepage distance 5.250 mm Set 228
4.4 Double Tension String set Isolator 210 KN, creepage distance 5.270 mm Set 378
4.5 Single Suspension String set Isolator 120 KN, creepage distance min.5.270 mm untuk Jumper Set 48
4.6 Disc Isolator 120 KN Fog Type pcs 8,300
4.7 Disc Isolator 210 KN Fog Type pcs 11,820
4.8 Suspension set GSW 70 mm2 Set 63
4.9 Tension set GSW 70 mm2 Set 105
4.10 Suspension set OPGW 70 mm2 Set 63
4.11 Double Tension set OPGW 70 mm2 (untuk 1 tower) Set 50
Catatan : Suspension dan Tension Stringset Isolator lengkap dengan arching horn
TOTAL ITEM 4

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


2 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)

5 PEKERJAAN PENARIKAN DAN PEMASANGAN


5.1 Pemasangan dan Pembongkaran Steiger kmr 38
5.2 Pemasangan Isolator String set, Fitting dan Aksesoris Konduktor Line :
- Single Suspension String set Isolator set 114
- Double Suspension String set Isolator set 264
- Single tension String set Isolator set 228
(Catatan : Pemasangan secara Inverse sesuai kebutuhan di lapangan)
- Double tension String set Isolator set 378
(Catatan : Pemasangan secara Inverse sesuai kebutuhan di lapangan)
- Single suspension String set Isolator untuk Jumper set 48
5.3 Penarikan ACSR 435/55 mm2 kms 76
5.4 Penarikan GSW 70 mm2 kms 38
5.5 Penarikan OPGW 70 mm2 kms 38
5.6 Sagging ACSR 435/55 mm2 kms 76
5.7 Sagging GSW 70 mm2 kms 38
5.8 Sagging OPGW 70 mm2 kms 38
5.9 Clamping ACSR 435 mm2 :
- Tower tension twr 63
- Tower suspension twr 50
5.10 Clamping GSW 70 mm twr 113
5.11 Clamping OPGW 70 mm2 twr 113
5.12 Pemasangan Joint Box & Penyambungan OPGW titik 13
BIDDER'S SIGNATURE MANUFACTURER SIGNATURE
3 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)
5.13 Pemasangan acessories ACSR 435/55 mm2 kms 76
5.14 Pemasangan acessories GSW kms 38
5.15 Pemasangan acessories OPGW kms 38
5.16 Penyambungan ke Switchyard lot 2
TOTAL ITEM 5 -
6 PEKERJAAN RE-CHECK SURVEY
6.1 Preliminary Survey km rute 38
Re-check survey termasuk pembuatan profil memanjang, gambar tower site dengan diagonal
6.2 km rute 38
section-nya
6.3 Soil Investigasi pada Lokasi Tower
a. Sondir bh 115
b. Boring Termasuk Test Laboratorium bh 25
c. Laporan Soil Investigasi termasuk Hard Copy dan Soft File set 3
Pembersihan Pohon Sepanjang Rute Transmisi Merujuk Kepada Peraturan Menteri yang
6.4 Berlaku. km rute 38
Lebar ROW 20m (10 m ke kiri dan 10 m ke kanan dari as rute transmisi)
TOTAL ITEM 6 -

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


4 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)

PEKERJAAN PEMASANGAN TOWER DAN PONDASI TOWER TIPE AA6


7 63
TERMASUK FINAL CHECK SERTA PENGELASAN BAUT DAN MUR
7.1 Tower Tipe AA6 -3 set tower 0 Suplay oleh PLN
7.2 Tower Tipe AA6 ±0 (Tinggi Standard) set tower 0 Suplay oleh PLN
7.3 Tower Tipe AA6 +3 set tower 24 Suplay oleh PLN
7.4 Tower Tipe AA6 +6 set tower 25 Suplay oleh PLN
7.5 Tower Tipe AA6 +9 set tower 11 Suplay oleh PLN
7.6 Tower Tipe AA6 +12 set tower 3 Suplay oleh PLN

PEKERJAAN PONDASI TERMASUK SETTING STUBS TOWER AA6 63


7.7 Kelas 1 Pad dan Chimney set pondasi 6
7.8 Kelas 2 Pad and Chimney set pondasi 18
7.9 Kelas 3 Pad and Chimney set pondasi 30
7.10 Kelas 4 Block or Anchor Foundation (Batu) set pondasi 0
7.11 Kelas 5 Pad and Chimney (Enlarged) atau Rakit set pondasi 7
7.12 Kelas 6 Piled
- Pondasi Kelas 6 set pondasi 2
- Bore Pile Dia 40 cm m' 320
TOTAL ITEM 7 -

PEKERJAAN PEMASANGAN TOWER DAN PONDASI TOWER TIPE BB6


8 34
TERMASUK FINAL CHECK SERTA PENGELASAN BAUT DAN MUR
8.1 Tower Tipe BB6 -3 set tower 0 Suplay oleh PLN
8.2 Tower Tipe BB6 ±0 (Tinggi Stardard) set tower 0 Suplay oleh PLN
BIDDER'S SIGNATURE MANUFACTURER SIGNATURE
5 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)
8.3 Tower Tipe BB6 +3 set tower 20 Suplay oleh PLN
8.4 Tower Tipe BB6 +6 set tower 4 Suplay oleh PLN
8.5 Tower Tipe BB6 +9 set tower 6 Suplay oleh PLN
8.6 Tower Tipe BB6 +12 set tower 4 Suplay oleh PLN

PEKERJAAN PONDASI TERMASUK SETTING STUBS TOWER BB6 34


8.7 Kelas 1 Pad and Chimney set pondasi 4
8.8 Kelas 2 Pad and Chimney set pondasi 11
8.9 Kelas 3 Pad and Chimney set pondasi 15
8.10 Kelas 4 Block or Anchor Foundation (Batu) set pondasi 0
8.11 Kelas 5 Pad and Chimney (Enlarged) atau Rakit set pondasi 1
8.12 Kelas 6 Piled
- Pondasi Kelas 6 set pondasi 3
- Bore Pile Dia 40 cm m' 646
TOTAL ITEM 8

PEKERJAAN PEMASANGAN TOWER DAN PONDASI TOWER TIPE CC6


9 12
TERMASUK FINAL CHECK SERTA PENGELASAN BAUT DAN MUR
9.1 Tower Tipe CC6 -3 set tower 0 Suplay oleh PLN
9.2 Tower Tipe CC6 ±0 (Tinggi Standard) set tower 0 Suplay oleh PLN
9.3 Tower Tipe CC6 +3 set tower 3 Suplay oleh PLN
9.4 Tower Tipe CC6 +6 set tower 7 Suplay oleh PLN
9.5 Tower Tipe CC6 +9 set tower 0 Suplay oleh PLN
9.6 Tower Tipe CC6 +12 set tower 2 Suplay oleh PLN

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


6 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)

PEKERJAAN PONDASI TERMASUK SETTING STUBS TOWER CC6 12


9.7 Kelas 1 Pad and Chimney set pondasi 3
9.8 Kelas 2 Pad and Chimney set pondasi 4
9.9 Kelas 3 Pad and Chimney set pondasi 4
9.10 Kelas 4 Block or Anchor Foundation (Batu) set pondasi 0
9.11 Kelas 5 Pad and Chimney (Enlarged) atau Rakit set pondasi 0
9.12 Kelas 6 Piled
- Pondasi Kelas 6 set pondasi 1
- Bore Pile Dia 40 cm m' 400
TOTAL ITEM 9

PEKERJAAN PEMASANGAN TOWER DAN PONDASI TOWER TIPE DD6


10 2
TERMASUK FINAL CHECK SERTA PENGELASAN BAUT DAN MUR
10.1 Tower Tipe DD6 -3 set tower 0 Suplay oleh PLN
10.2 Tower Tipe DD6 ±0 (Tinggi Standard) set tower 0 Suplay oleh PLN
10.3 Tower Tipe DD6 +3 set tower 0 Suplay oleh PLN
10.4 Tower Tipe DD6 +6 set tower 0 Suplay oleh PLN
10.5 Tower Tipe DD6 +9 set tower 1 Suplay oleh PLN
10.6 Tower Tipe DD6 +12 set tower 1 Suplay oleh PLN

PEKERJAAN PONDASI TERMASUK SETTING STUBS TOWER DD6 2


10.7 Kelas 1 Pad and Chimney set pondasi 1
10.8 Kelas 2 Pad and Chimney set pondasi 1
10.9 Kelas 3 Pad and Chimney set pondasi 0

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


7 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)
10.10 Kelas 4 Block or Anchor Foundation (Batu) set pondasi 0
10.11 Kelas 5 Pad and Chimney (Enlarged) atau Rakit set pondasi 0
10.12 Kelas 6 Piled
- Pondasi Kelas 6 set pondasi 0
- Bore Pile Dia 40 cm m' 0
TOTAL ITEM 10 -

PEKERJAAN PEMASANGAN TOWER DAN PONDASI TOWER TIPE DDR6


11 2
TERMASUK FINAL CHECK SERTA PENGELASAN BAUT DAN MUR
11.1 Tower Tipe DDR6 -3 set tower 0 Suplay oleh PLN
11.2 Tower Tipe DDR6 ±0 (Tinggi Standard) set tower 2 Suplay oleh PLN
11.3 Tower Tipe DDR6 +3 set tower 0 Suplay oleh PLN
11.4 Tower Tipe DDR6 +6 set tower 0 Suplay oleh PLN
11.5 Tower Tipe DDR6 +9 set tower 0 Suplay oleh PLN
11.6 Tower Tipe DDR6 +12 set tower 0 Suplay oleh PLN

PEKERJAAN PONDASI TERMASUK SETTING STUBS TOWER DDR6 2


11.7 Kelas 1 Pad and Chimney set pondasi 0
11.8 Kelas 2 Pad and Chimney set pondasi 1
11.9 Kelas 3 Pad and Chimney set pondasi 0
11.10 Kelas 4 Block or Anchor Foundation (Batu) set pondasi 0
11.11 Kelas 5 Pad and Chimney (Enlarged) atau Rakit set pondasi 1
11.12 Kelas 6 Piled
- Pondasi Kelas 6 set pondasi 0
- Bore Pile Dia 40 cm m' 0

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


8 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)
TOTAL ITEM 11 -

PEKERJAAN PEMASANGAN TOWER MODIFIKASI / LEG EKSTENSION (DIKERJAKAN


12
JIKA DIINSTRUKSIKAN ENJINER)
12.1 Structural Mild Steel ton 12 Suplay oleh PLN
12.2 Structural HT Steel ton 8 Suplay oleh PLN
TOTAL ITEM 12

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


9 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)

PERLINDUNGAN LERENG, EKSTENSI CHIMNEY DAN PEKERJAAN TIE BEAM


13.0
(DIKERJAKAN JIKA DIINSTRUKSIKAN ENJINER)
13.1 Pasangan Batu Kali 1 : 3 m3 300
13.2 Dinding Penahan Tanah (Beton Bertulang K225, Fe: 100 kg/m3, Termasuk Bekisting) m3 70
Ekstensi Chimney atau Tie Beam (Beton Bertulang K225 , Fe: 200 kg/m3, Termasuk
13.3 m3 35
Bekisting)
13.4 Tanah Urug dari Luar Lokasi Tower (Termasuk Pemadatan) m3 200
13.5 Galian Tanah m3 500
13.6 Penimbunan Kembali (Termasuk Pemadatan) m3 300
TOTAL ITEM 13

PENGUJIAN PONDASI DAN PILE (DIKERJAKAN SETELAH DIINSTRUKSIKAN OLEH


14
ENJINER)
14.1 Uji Tipe Pondasi
a. Kelas 2 Pad and Chimney per leg 1
b. Piled per pile 1
TOTAL ITEM 14

15 AKSESORIS TOWER
15.1 Plang Tanda Bahaya Komplit Terpasang Set 226 Suplay oleh PLN
15.2 Plang Nomor Tower dan Plang Fasa Komplit Terpasang Set 226 Suplay oleh PLN
15.3 Anti Climbing Set 452 Suplay oleh PLN
TOTAL ITEM 15

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


10 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ
DAFTAR ISIAN 3.1 : DAFTAR HARGA DAN KUANTITAS (BOQ) PEKERJAAN
SUTT 150 kV
HARGA PENGADAAN SA
MATERIAL
NO. ITEM MATERIAL DAN PEKERJAAN SATUAN VOLUME
SATUAN JUMLAH
(Rp.) (Rp.)
(1) (2) (3) (4) (5) (6) = (4) x (5)
16 PEKERJAAN SIPIL LAINNYA
16.1 Kantor Lapangan (6mx10m) Lengkap dengan Furniture ls 1
16.2 Gudang Lapangan dengan Atap (6mx12 m) ls 1
TOTAL ITEM 16

17 PENGUJIAN DAN KOMISIONING lot 1


TOTAL ITEM 17

18 AS BUILT DRAWING (TERDIRI DARI 3 SOFT COPY DAN 3 HARD COPY) lot 1
- Laporan Soil Investigation, dan Foundation Schedule
- Rute Peta, Line Profile, dan Tower Schedule (Termasuk koordinat GPS Tower)
- Spesifikasi Teknis dan Brosur Material Transmisi
- Perhitungan Desain dan Gambar Desain
- Laporan Pengujian untuk Pondasi, Tower, dan Material Transmisi
- Gambar Konstruksi
- Laporan Pengujian dan Komisioning
TOTAL ITEM 18
TOTAL ITEM 1 - 18

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


11 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


12 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


13 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


14 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


15 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


16 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


17 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


18 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


19 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


20 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


21 dari 67
T 150 KV MALINGPING - BAYAH
R HARGA DAN KUANTITAS (BOQ)
KUANTITAS (BOQ) PEKERJAAN TRANSMISI 150 KV

HARGA PENGADAAN SAMPAI SITE


JASA PEMASANGAN
TRANSPORTASI TOTAL
SATUAN JUMLAH SATUAN JUMLAH
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(7) (8) = (4) x (7) (9) (10) = (4) x (9) (11) = (6) + (8) + (10)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


22 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING - BAYAH
DAFTAR ISIAN 3 : DAFTAR HARGA DAN KUANTITAS (BOQ)
DAFTAR ISIAN 3.2 : REKAPITULASI HARGA

TOTAL PRICE
NO. DESCRIPTION
(Rp)
(1) (2) (3)

1 HARGA PENGADAAN, PEMASANGAN, DAN TRANSPORTASI PEKERJAAN TRANSMISI 150 KV

SUB TOTAL
PPN 10 %
TOTAL

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


23 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

1 PEMASANGAN & PEMBONGKARAN STEGER unit


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam
- Supir oh/8 jam

b. Sewa
- Truk unit/hari

c. Material bantu :
- Bambu ls
- Tali Nilon Roll
- Paku kg
Biaya per steger
Jumlah biaya untuk 1 kmr

2 PEMASANGAN FITTING & HARDWARE


2.1 DOUBLE TENSION STRING SET ISOLATOR (+ ROLL) set
a. Upah :
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll unit/hari
- Chain block unit/hari

c. Material bantu :
- Tali Nilon Roll

Jumlah biaya per set

2.2 SINGLE TENSION STRING SET ISOLATOR (+ ROLL) set


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


24 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll unit/hari
- Chain block unit/hari

c. Material bantu :
- Tali Nilon Roll
Jumlah biaya per set

2.3 DOUBLE SUSPENSION STRING SET ISOLATOR (+ ROLL) set


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll unit/hari
- Chain block unit/hari

c. Material bantu :
- Tali Nilon Roll
Jumlah biaya per set

2.4 SINGLE SUSPENSION STRING SET ISOLATOR (+ROLL) set


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll unit/hari
- Chain block unit/hari

c. Material bantu :
- Tali Nilon Roll
Jumlah biaya per set

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


25 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

2.5 SINGLE SUSPENSION STRING SET ISOLATOR FOR JUMPER CONDUCTOR set
a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll unit/hari
- Chain block unit/hari

c. Material bantu :
- Tali Nilon Roll
Jumlah biaya per set

3 PENARIKAN ACSR 435/55 mm2 km


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam
- Operator oh/8 jam

b. Peralatan kerja :
- Peralatan stringing set/hari
- Theodolit unit/hari
- Peralatan Komunikasi set/hari
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll set/hari

c. Material:
- Bambu btg
- Kawat galvanis 4 mm kg

Biaya penarikan per km


Jumlah biaya penarikan per kms

4 PENARIKAN GSW 70 mm2 kms


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam
- Operator oh/8 jam

b. Peralatan kerja :
- Peralatan Stringing set/hari
- Theodolit unit/hari
- Peralatan Komunikasi set/hari
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll set/hari

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


26 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

c. Material:
- Bambu btg
- Kawat galvanis 4 mm kg
Jumlah

5 PENARIKAN OPGW 24 CORE 70 mm2 km


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam
- Operator oh/8 jam

b. Peralatan kerja :
- Peralatan Stringing set/hari
- Theodolit unit/hari
- Peralatan Komunikasi set/hari
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll set/hari

c. Material:
- Bambu btg
- Kawat galvanis 4 mm kg
Jumlah

6 SAGGING ACSR 435/55 mm2 kms


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Enjinir oh/8 jam
- Mandor oh/8 jam
- Operator oh/8 jam

b. Peralatan kerja :
- Theodolit unit/hari
- Peralatan Sagging set/hari
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll set/hari
- Peralatan Komunikasi set/hari
Jumlah

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


27 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

7 SAGGING GSW 70 mm2 kms


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Enjinir oh/8 jam
- Mandor oh/8 jam
- Operator oh/8 jam

b. Peralatan kerja :
- Theodolit unit/hari
- Peralatan Sagging set/hari
- Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan safety, dll set/hari
- Peralatan Komunikasi set/hari
Jumlah

8 SAGGING OPGW 70 mm2 kms


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Enjinir oh/8 jam
- Mandor oh/8 jam
- Operator oh/8 jam

b. Peralatan kerja :
- Theodolit unit/hari
- Peralatan Sagging set/hari
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
- Peralatan Komunikasi set/hari
Jumlah

9 PEKERJAAN CLAMPING TOWER TENSION TERMASUK JUMPER set


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Mesin press lengkap set/hari
- Tackle set/hari
- Stringing ladder set/hari
- Grounding stick set/hari
- Came along/wire grip set/hari
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
Biaya clamping per set
Jumlah Biaya untuk 1 Tower

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


28 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

10 PEKERJAAN CLAMPING & PEMASANGAN ARMOUR ROD TOWER SUSPENSION set

a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Tackle set/hari
- Stringing ladder set/hari
- Grounding stick set/hari
- Came along/wire grip set/hari
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
Biaya clamping per set
Jumlah Biaya untuk 1 Tower

11 CLAMPING GSW 70 mm2 set


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
- Mesin press lengkap set/hari
Jumlah biaya per tower

12 CLAMPING OPGW 70 mm2 set


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Peralatan kerja :
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
- Mesin press lengkap set/hari
Jumlah biaya per tower

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


29 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

13 PEMASANGAN JOINT BOX & OPGW set


a. Upah:
- Pekerja oh/8 jam
- Mandor oh/8 jam
- Enjinir oh/8 jam

b. Peralatan kerja :
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
Jumlah

14 PEMASANGAN ACESSORIES ACSR kms


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Mandor oh/8 jam

b. Sewa:
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
Jumlah

15 PEMASANGAN ACESSORIES GSW/OPGW kms


a. Upah:
- Pekerja oh/8 jam
- Mandor oh/8 jam

b. Sewa:
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
Jumlah

16 PENYAMBUNGAN KE SWITCHYARD lot


a. Upah:
- Pekerja oh/8 jam
- Kepala Tukang oh/8 jam
- Operator oh/8 jam
- Mandor oh/8 jam
- Enjinir oh/8 jam

b. Sewa:
- Peralatan Stringing unit/hari
- Mesin press unit/hari
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari

Jumlah

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


30 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN PENGGULUNGAN, PEMASANGAN DAN PENARIK

NO. DESKRIPSI PEKERJAAN UNIT

17 AS BUILT DRAWING IN HARD AND SOFT COPY CONSIST OF : lot


a. Upah:
- Pekerja/drafter oh/8 jam
- Enjinir oh/8 jam
- Enjinir Ahli Muda oh/8 jam

b. Material
- ATK, Printer, Tinta lot
Jumlah

18 PENGUJIAN DAN KOMISIONING lot


a. Upah:
- Pekerja oh/8 jam
- Mandor oh/8 jam
- Enjinir oh/8 jam
- Enjinir Ahli Muda oh/8 jam
- Enjinir Ahli Utama oh/8 jam

b. Sewa:
- Peralatan Pengujian untuk Testing dan Komisioning Transmisi set/hari
- Peralatan Komunikasi set/hari
- Peralatan supporting (Kunci momen, kunci pas, sling, tambang, safety, dll.) set/hari
Jumlah

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


31 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3
1

4 0.25
1 0.25
1 0.25
1 0.25

1 0.25

1 1
1 1
1 1

12 0.5
1 0.5
1 0.5

6 0.5
1 0.5

1 1

12 0.45
1 0.45
1 0.45

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


32 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3
6 0.5
1 0.5

1 1

12 0.4
1 0.4
1 0.4

6 0.5
1 0.5

1 1

12 0.35
1 0.35
1 0.35

6 0.5
1 0.5

1 1

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


33 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3

12 0.35
1 0.35
1 0.35

6 0.5
1 0.5

1 1

12 1.5
2 1
2 1
2 1

2 1
3 1
5 1
8 1

10 1
5 1

6 0.8
1 0.8
1 0.8
2 0.8

2 0.8
1 0.8
2 0.8
8 0.8

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


34 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3

5 1
3 1

6 0.8
1 0.8
1 0.8
2 0.8

2 0.8
1 0.8
2 0.8
7 0.8

5 1
3 1

4 1
2 1
1 1
3 1
2 1

2 1
2 1
4 1
2 1

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


35 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3

4 0.3
1 0.3
1 0.3
2 0.3
2 0.3

1 0.3
2 0.3
4 0.3
2 0.3

4 0.3
1 0.3
1 0.3
2 0.3
2 0.3

1 0.3
2 0.3
4 0.3
2 0.3

4 0.17
1 0.17
1 0.17

1 0.17
1 0.17
1 0.17
1 0.17
1 0.17
4 0.17

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


36 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3

4 0.067
1 0.067
1 0.067

1 0.15
1 0.15
1 0.15
1 0.15
4 0.15

2 0.2
1 0.2
1 0.2

2 0.2
1 0.2

2 0.2
1 0.2
1 0.2

2 0.2
1 0.2

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


37 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3

2 0.5
1 0.5
1 0.5

5 0.5

4 1
1 1
1 1

4 1

1 0.5
1 0.5

2 0.5

3 1.5
1 1.5
1 1.5
1 1.5
1 0.5

1 1.5
1 1.5
3 1.5

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


38 dari 67
PING - BAYAH
ASANGAN DAN PENARIKAN KONDUKTOR

DURASI
HARGA SATUAN TOTAL HARGA
QTY KERJA
(Hari) (Rupiah) (Rupiah)
1 2 3 4=1x2x3

2 30
4 30
1 30

1 1

15 15
3 15
3 15
3 15
3 15

2 30
2 15
15 15

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


39 dari 67
PEMBANGUNAN SUTT 150 KV MALINGPING-BAYAH
ANALISA HARGA SATUAN PEKERJAAN TOWER

HARGA SATUAN/KG
TYPE TOWER
NO SAT VOLUME
(LATTICE)
DELIVERY ERECTION
(1) (2) (3) (4) (6) (7)
1 Tower Type AA6
AA6 - 3 kg 7,716.0
AA6 + 0 kg 8,391.0
AA6 + 3 kg 9,160.0
AA6 + 6 kg 9,917.0
AA6 + 9 kg 10,835.0
AA6 + 12 kg 11,796.0

2 Tower Type BB6


BB6 - 3 kg 9,398.0
BB6 + 0 kg 10,205.0
BB6 + 3 kg 11,579.0
BB6 + 6 kg 12,404.0
BB6 + 9 kg 14,020.0
BB6 + 12 kg 14,932.0

3 Tower Type CC6


CC6 - 3 kg 11,837.0
CC6 + 0 kg 12,910.0
CC6 + 3 kg 14,781.0
CC6 + 6 kg 15,953.0
CC6 + 9 kg 18,285.0
CC6 + 12 kg 19,948.0

4 Tower Type DD6


DD6 - 3 kg 0.0
DD6 + 0 kg 17,661.0
DD6 + 3 kg 19,111.0
DD6 + 6 kg 21,192.0
DD6 + 9 kg 22,866.0
DD6 + 12 kg 25,390.0

5 Tower Type DDR6


DDR - 3 kg 0.0
DDR + 0 kg 19,170.0
DDR + 3 kg 20,619.0
DDR + 6 kg 22,701.0
DDR + 9 kg 24,375.0
DDR + 12 kg 26,898.0

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


40 dari 67
BANGUNAN SUTT 150 KV MALINGPING-BAYAH
ALISA HARGA SATUAN PEKERJAAN TOWER

HARGA DELIVERY
HARGA ERECTION
SATU SET TOWER
SATU SET TOWER
SAMPAI SITE

(8) = (4) X (6) (9) = (4) X (7)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


41 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


1 1m' Bowplank
Material :
- Kayu Papan 2/20 m3 0.007
- Kayu Broti 5/7 m3 0.007
- Paku kg 0.020
Upah :
- Mandor oh 0.005
- Kepala Tukang oh 0.010
- Tukang Kayu oh 0.100
- Pekerja oh 0.100

2 1 m2 Membersihkan Lokasi
- Upah :
- Pekerja oh 0.010
- Mandor oh 0.050

3 1 m3 Galian Tanah
- Pekerja oh 0.750
- Mandor oh 0.025

4 1 m3 Galian Tanah Keras


- Pekerja oh 1.000
- Mandor oh 0.060

5 1 m3 Pengurugan Kembali dan Pemadatan Tanah per 20 cm


- Pekerja oh 0.692
- Mandor oh 0.069

6 1 m3 Pengurugan dan pemadatan Pasir


Material :
- Pasir m3 1.200
Peralatan :
- Stamper oh 1.000
Upah :
- Pekerja oh 0.300
- Mandor oh 0.010

7 1 m3 Beton Lantai Kerja 1 PC : 3 Pasir : 5 Split


Material :
- Portland Cement kg 230.000
- Pasir m3 0.520
- Split m3 0.870
BIDDER'S SIGNATURE MANUFACTURER SIGNATURE
42 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


Upah :
- Pekerja oh 1.200
- Tukang Batu oh 0.200
- Mandor oh 0.600

8 1 m3 Beton K 225
Material :
- Portland Cement kg 371.000
- Pasir m3 0.499
- Split m3 0.776
Sewa Peralatan :
- Mesin Molen jam 0.425
- Vibrator jam 0.425
Upah :
- Mandor oh 0.080
- Tukang Batu oh 0.275
- Pekerja oh 1.650
Langsir 200 m ke site m3 1.000

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


43 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


9 1 Ton Transportasi Material Tower
Material :
- BBM/Solar ltr 25.313
Sewa Peralatan :
- Truck hari 0.250
- Forklift hari 0.250
Upah :
- Driver oh 0.250
- Pekerja oh 2.250
- Tukang Besi oh 0.250
- Mandor oh 0.250
Langsir rata-rata 400 m ke lokasi tower ton 1.000

10 1 Ton Erection Tower


Material/Peralatan kerja:
- BV lengkap set 0.025
- Tool Set set 0.084
- Tiang gerek set 0.025
- Skepp (double single) unit 0.034
- Tambang ls 1.000

Upah :
- Pekerja oh 12.000
- Mandor oh 1.000
- Enjiner oh 1.000

11 1 Ton Baja untuk Tower dan Gantry


Material :
- Galvanis of Steel Angle HTS ton 0.650
- Galvanis of Steel Angle MS ton 0.350
- Baut dan Mur Galvanis bh 120.000
- Plat Baja Galvanis ton 0.100
Sewa Peralatan :
- Mesin Bor jam 1.000
- Mesin Las jam 1.000
Upah :
- Tukang Besi oh 10.000
- Pekerja oh 20.000
- Mandor oh 2.000

12 1 m3 Pasangan Batu Kali 1 : 3


Material :

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


44 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


- Batu Kali m3 1.200
- Portland Cemen kg 202.000
- Pasir m3 0.485
Upah :
- Pekerja oh 1.500
- Tukang Batu oh 0.750
- Kepala Tukang oh 0.075
- Mandor oh 0.075

13 Test Concrete Cube/Sample


(15x15x15 cm3) / 15 cm dia, 30 cm Height bh 1.000

14 1 m3 Tanah Urug dari luar (Dipadatkan)


Material :
- Tanah m3 1.200
Peralatant :
- Stamper jam 0.250
Upah :
- Pekerja oh 0.300
- Mandor oh 0.010

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


45 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


15 100 kg Pembesian tulangan U 40 - BJTD 40
Material :
- Besi Tulangan U 32 - BJTD 40 kg 110.000
- Kawat Beton kg 2.500
Upah :
- Tukang Besi oh 2.000
- Pekerja oh 4.500
- Mandor oh 0.400

For 1 kg
16 100 kg Pembesian Tulangan U 24 - BJTP24
Material :
- Besi Tulangan U 24 - BJTP 24 kg 110.000
- Kawat Beton kg 2.500
Upah :
- Tukang Besi oh 2.000
- Pekerja oh 4.500
- Mandor oh 0.400

For 1 kg
17 1 Ton Sortir Material Tower
- Pekerja oh 6.000
- Mandor oh 1.000

18 1 m2 Bekisting
Material :
- Plywood/multiplex/triplex 120 x 240, t=9 mm lbr 0.500
- Kayu m3 0.050
- Paku kg 0.450
Upah :
- Tukang Kayu oh 0.400
- Pekerja oh 0.500
- Mandor oh 0.010

19 1 m' Point Bored Pile Concrete dia 40 cm


Material :
- Concrete K 225 m3 0.126
- Screew Reinforced of Steel U 32 - BJTD 40 kg 11.000
- Plain Reinforced of Steel U 24 - BJTD 24 kg 7.800
- Casing ls 1.000
Sewa Peralatan :
- Mesin Boring jam 0.150

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


46 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


- Pipa Tremi jam 0.150
- Total Station jam 0.150
- Peralatan Pendukung jam 0.150
Mobilisasi :
- Mobilisasi Mesin Bor ls 1.000
Upah :
- Pekerja oh 0.100
- Mandor oh 0.010
- Operator oh 0.100
- Engineer oh 0.010
- Surveyor oh 0.010
- Langsir 200 m ke Site m' 0.126

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


47 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


20 1 Unit Test Pile
Material :
- Pondasi Bore Pile m 20.000
- Balok dan Plat pembebanan kg 120.000
- Oli Mesin ltr 4.000
Sewa Peralatan :
- Alat ukur jam 48.000
- Jack Hydrolic jam 48.000
- Genset jam 24.000
- Penerangan jam 24.000
- Place of Work jam 48.000
- Peralatan Pendukung ( Mesin las dan Mesin Potong ) jam 48.000
Upah :
- Pekerja oh 4.000
- Mandor oh 0.400
- Operator oh 4.000
- Engineer oh 2.000
- Surveyor oh 0.200

21 1 Unit Test Pondasi


Material :
- Pondasi Kelas 2 set 0.250
- Balok dan Plat pembebanan kg 120.000
- Oli Mesin ltr 4.000
Sewa Peralatan :
- Alat ukur jam 24.000
- Jack Hydrolic jam 24.000
- Genset jam 24.000
- Penerangan jam 12.000
- Place of Work jam 24.000
- Peralatan Pendukung ( Mesin las dan Mesin Potong ) jam 24.000
Upah :
- Pekerja oh 4.000
- Mandor oh 0.400
- Operator oh 4.000
- Engineer oh 2.000
- Surveyor oh 0.200

22 1 bh Pemasangan Plang Tanda Bahaya


Sewa Peralatan :
- Peralatan Pendukung ( Kunci-kunci dan Sabuk Pengaman ) unit/hari 0.200
Upah :

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


48 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


- Pekerja oh 0.250
- Mandor oh 0.100

23 1 bh Pemasangan Plang Fasa


Sewa Peralatan :
- Peralatan Pendukung ( Kunci-kunci dan Sabuk Pengaman ) unit/hari 0.200
Upah :
- Pekerja oh 0.250
- Mandor oh 0.100

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


49 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


24 1 bh Pemasangan Anti Climbing
Sewa Peralatan :
- Peralatan Pendukung ( Kunci-kunci dan Sabuk Pengaman ) unit/hari 0.200
Upah :
- Pekerja oh 0.250
- Mandor oh 0.100

25 1 m2 Kantor Lapangan
- Material :
- Kayu Papan dan Broti m3 0.210
- Paku kg 0.200
- Plat besi kg 1.100
- Portland cement kg 0.700
- Pasir m3 0.250
- Split m3 0.150
- Batu Bata bh 30.000
- Atap Asbes lbr 0.800
- Pintu dan Jendela set 0.042
- Kaca 5 mm m2 0.080
- Kunci dan Engsel bh 0.150
- Plywood lbr 0.060

- Upah :
- Pekerja oh 2.000
- Tukang Kayu oh 2.000
- Tukang Batu oh 1.000
- Kepala Tukang oh 0.300
- Mandor oh 0.050

26 1 m2 Gudang Lapangan
- Material :
- Kayu Dolken btg 1.700
- Kayu Papan/Broti m 3 0.210
- Paku kg 0.300
- Portland cement kg 10.000
- Pasir m3 0.300
- Split m3 0.050
- Seng Gelombang lbr 1.500

- Upah :
- Tukang Kayu oh 1.000

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


50 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
ANALISA HARGA SATUAN PEKERJAAN

NO URAIAN SATUAN VOLUME

(1) (2) (3) (4)


- Pekerja oh 1.000
- Kepala Tukang oh 0.200
- Mandor oh 0.050

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


51 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


52 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


53 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


54 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


55 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


56 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


57 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


58 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


59 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


60 dari 67
GUNAN SUTT 150 kV MALIMPING - BAYAH
ALISA HARGA SATUAN PEKERJAAN

HARGA SATUAN JUMLAH HARGA


(RUPIAH) (RUPIAH)
(5) (6) = (4) x (5)

BIDDER'S SIGNATURE MANUFACTURER SIGNATURE


61 dari 67
PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
RENCANA ANGGARAN BIAYA (RAB)
DAFTAR HARGA SATUAN

NO. MATERIAL, UPAH DAN SEWA PERALATAN UNIT


I MATERIAL :
1 Portland Cemen (PC) kg
2 Batu Belah 20-30 cm m3
3 Batu Bata bh
4 Split m3
5 Sirtu m3
6 Pasir Beton m3
7 Tanah Urug m3
8 BBM/Solar liter
9 BBM/Bensin liter
10 Besi Beton Polos U 24 - BJTP 24 kg
11 Besi Beton Ulir U 32 - BJTD 40 kg
12 Concrete Wire kg
13 Kayu Albasia m3
14 Kayu Meranti m3
15 Kayu Borneo m3
16 Dolken dia. 6-8 cm, panjang 4 m btg
17 Minyak bekisting liter
18 Paku kg
19 PVC Pipe dia 2 AW" m'
20 PVC Pipe dia 4 AW" m'
21 PVC Pipe dia 6 AW" m'
22 Seng Gelombang BJLS 0.25mm 80 x 180 cm lbr
23 Triplex 120 x 240, t=9 mm lbr
24 Oli liter
25 Bambu btg
26 Kawat galvanis 4 mm kg
28 Tali nilon Roll

II UPAH :
1 Pekerja oh/8 jam
4 Operator oh/8 jam
5 Tukang Batu oh/8 jam
6 Tukang Kayu oh/8 jam
7 Tukang Besi oh/8 jam
8 Tukang Las oh/8 jam
9 Tukang Cat oh/8 jam
11 Mekanik oh/8 jam
12 Mandor oh/8 jam
13 Kepala Tukang oh/8 jam
14 Enjiner oh/8 jam
15 Enjinir Ahli Muda oh/8 jam
16 Enjinir Ahli Utama oh/8 jam
17 Supir oh/8 jam

Date :Name of Bidder :Signature of Bidder : PAGE 62 of 67


PEMBANGUNAN SUTT 150 kV MALIMPING - BAYAH
RENCANA ANGGARAN BIAYA (RAB)
DAFTAR HARGA SATUAN

NO. MATERIAL, UPAH DAN SEWA PERALATAN UNIT

III SEWA PERALATAN :


1 Mesin Molen jam
2 Truck 8 Ton hari
3 Forklift unit/hari
3 Mesin Boring jam
4 Support Equipment jam
5 Stamper jam
6 Total Station jam
7 Small crane hari
8 Pipa Tremi jam
9 Vibrator jam
11 Gergaji bh
12 Drum stand lengkap dengan as unit/hari
13 Swivel unit/hari
14 Tripod unit/hari
15 Tackle 5 ton unit/hari
16 Dongkrak 5 ton unit/hari
17 Tool set lengkap unit/hari
18 Peralatan Supporting/ Kunci momen, kunci pas, tali panjat, sling, tambang, peralatan unit/hari
safety, dll
19 Chain block unit/hari
20 Peralatan stringing unit/hari
21 Peralatan sagging unit/hari
22 Mesin press lengkap unit/hari
23 Stringing ladder unit/hari
24 Ground stick unit/hari
25 Came along/wire grip unit/hari
26 Theodolit unit/hari
27 Peralatan komunikasi unit/hari
28 Peralatan Pengujian untuk Testing dan Komisioning Transmisi unit/hari
29 ATK, printer, Tinta, dll lot
30 Genset 40 KVA hari

Date :Name of Bidder :Signature of Bidder : PAGE 63 of 67


AN SUTT 150 kV MALIMPING - BAYAH
ANA ANGGARAN BIAYA (RAB)
AFTAR HARGA SATUAN

PRICE
(Rp.)

Date :Name of Bidder :Signature of Bidder : PAGE 64 of 67


AN SUTT 150 kV MALIMPING - BAYAH
ANA ANGGARAN BIAYA (RAB)
AFTAR HARGA SATUAN

PRICE
(Rp.)

Date :Name of Bidder :Signature of Bidder : PAGE 65 of 67


Kebutuhan Material Pondasi Batu Kali

NO Description Unit Vol

1 Batu Kali 1 : 3 M³ 56.16

2 Pasir M³ 22.70

3 Semen Zak 187.20

4 Pasir Urug pondasi M³ 3.00

5 Tanah Urug M³ 300.00

6 Galian tanah pondasi M³ 39.60

7 Pengurugan tanah pondasi M³ 0.99

8 Semen untuk plester Zak 10.00

Volume Pondasi Batu Kali = 46.80


Volume 46.8
Pasir Urug 2.40
Kebutuhan Material Pondasi Batu Kali

NO Description Unit Vol

1 Batu Kali 1 : 3 M³ 46.98

2 Pasir M³ 18.99

3 Semen Zak 156.60

4 Pasir Urug pondasi M³ 3.00

5 Tanah Urug M³ 199.85

6 Semen untuk plester Zak 10.00

7 Galian tanah pondasi M³ 39.60

Volume Pondasi Batu Kali = 46.80


Volume 43.2 13.05 1.5
Pasir Urug 2.40 9.9
16.2 85.95
39.15