PT PLN ( PERSERO ) WILAYAH NTB

AREA MATARAM

DAFTAR LOKASI PEMASANGAN GARDU SISIPA


PENUNJANG PERBAIKAN TEGANGAN UJUNG DI AREA MA
FUNGSI GARDU DISTRIBUSI

SATUAN
NO

MATERIAL MATERIAL
PLN PEMB. PLN PEMB.

I MATERIAL UTAMA
1 Trafo Distribusi 50 kVA 3 phs 20 kV bh -
2 Trafo Distribusi 100 kVA 3 phs 20 kV bh -
3 Trafo Distribusi 160 kVA 3 phs 20 kV bh -
4 Trafo Distribusi 200 kVA 3 phs 20 kV bh -
5 Trafo Distribusi 250 kVA 3 phs 20 kV bh -
6 Isolator tumpu 20 kV bh -
7 Cut Out 24 kV set -
8 Lightning Arrester 24 kV set -
9 LV Board 3 phs :
a. LV Board 3 phs konst. 2 tiang 4 jur bh -
b. LV Board 3 phs konst. 2 tiang 2 jur bh -
10 Hotline Clamp ( LLC ) ukuran 70 - 150 mm2 bh -
11 Kawat AAAC 70 mm2 u/ jamperan di Gardu mtr -
12 Kabel NYY 1x70 mm2 untuk out let mtr -
13 Kabel NYY 1x95 mm2 untuk In let mtr -
14 Kabel NYY 1x95 mm2 untuk kotak APP mtr -
15 Kabel NA2XY 1x95 mm2 mtr -
16 Kabel NA2XY 1x120 mm2 mtr -
17 Kabel NA2XY 1x150 mm2 mtr -
18 Kawat ACSR 2/0 mm2 pengikat isol. mt -
19 Alluminium Binding Wire bh -

II MATERIAL NON UTAMA


1 Penghalang panjat set -
2 Tanda kilat besar bh -
3 Plat Identitas Gardu bh -
4 Yzer Werk 3 phs 20 kV :
a. Yzer Werk 3 phs 20 kV konst. 2 tiang set -
b. Yzer Werk 3 phs 20 kV konst. 1 tiang set -
5 Cross arm Cut out u/trf. Portal set -
6 Cross Arm UNP 100
a. Type A1 set -
b. Type B3 set -
7 Arde 5 Ohm pas. Luar set -
8 Arde 3 Ohm pas. Luar set -
9 Comp. jumper connector 70-150 mm2 AL-AL bh -
10 Sepatu Kabel AL-CU 70 bh -
11 Sepatu Kabel AL-CU 95 bh -
12 Sepatu Kabel AL-CU 120 bh -
13 Sepatu Kabel AL-CU 150 bh -
14 Sepatu Kabel 70 mm2 CU-CU untuk kabel out let bh -
15 Sepatu Kabel 95 mm2 CU-CU untuk kabel in let bh -
16 Comp. joint connector AL-CU 70-70 bh -
17 Comp. joint connector AL-CU 50-70 bh -
18 Lantai kerja Gardu bh -
19 Penomoran Gardu bh -
20 Pemasangan ikatan isolator tumpu bh -

III PEKERJAAN PENDUKUNG


1 Angkutan material ton -
2 Angkutan laut material ke pulau kecil ton -
3 Angkutan darat material di pulau kecil ton -
PT PLN ( PERSERO ) WILAYAH NTB
AREA MATARAM

DAFTAR LOKASI PEMASANGAN GARDU SISIPA


PENUNJANG PERBAIKAN TEGANGAN UJUNG DI AREA M
FUNGSI JARINGAN TEGANGAN MENENGAH

Pembangunan
MVTIC dari SPN
Belanting Sampai

SATUAN
Tiang POOL
NO Pelanggan Honggo
Tahap 7

MATERIAL MATERIAL
PLN PEMB. PLN PEMB.

I MATERIAL UTAMA
1 Isolator tumpu 20 kV bh 30 -
2 Isolator tarik 20 kV, komplit set - -
3 Lightning Arrester 24 kV set 6 -
4 Cut Out 24 kV set - -
5 Hotline Clamp ( LLC ) ukuran 70 - 150 mm2 bh - -
6 Kabel MVTIC 3x1x150 mm2 + Andongan 5% mtr 1,111 -
7 Konduktor AAAC/S 150 mm2 + Andongan 3% mtr - -
8 Penarikan Kabel MVTIC 3x1x150 mm2 + Andongan 5% ms 1,058
9 Kawat ACSR 2/0 mm2 pengikat isol. mt - -
10 Alluminium Binding Wire bh - -

II MATERIAL NON UTAMA


1 Terminating 24 KV, 1C, OD 70-240 mm set - 2
2 Jointing 24 KV, 1C, OD 70-240 mm set - 1
3 Perlengkapan Druckschoor TM set - -
4 Perlengkapan Kontramast TM set - -
5 Treck schoor TM set - -
6 Cross Arm UNP 100 -
a. Type A1 set - 21
b. Type A2 set - -
c. Type A3 set - -
d. Type B3 set - -
7 Suspension assembly MVTIC set - 32
8 2xFixed Dead End Assembly set - 14
9 Fixed dead end assembly MVTIC set - 2
10 Dudukan terminal set - 2
11 Penghalang panjat set - 21
12 Tanda kilat kecil bh - 21
13 Arde 5 Ohm pas. Luar u/ ujung MVTIC di pangkal set 1 -
14 Arde 3 Ohm pas. Luar set - -
15 Terminal lug/Sepatu kabel for 150 mm AL bh - -
16 Comp. Jumper Connector 150-150 mm2 AL bh - -
17 Comp. Jumper Connector 70-150 mm2 AL bh - -
18 Comp.Tension Joint Sleeve 150 mm2 AL bh - -
19 Comp.Non Tension Joint Sleeve 150 mm2 AL bh - -
20 Sepatu Kabel AL-CU 70 bh - -
21 Pemasangan ikatan isolator tumpu bh 30

III PEKERJAAN PENDUKUNG


1 Ongkos perabasan kms -
2 Foto Dokumentasi 4R + tagging GPS ttk -
3 Gambar revisi lbr -
4 Commisioning test ls -
5 Penebangan Pohon Standar Diameter diatas 10 s/d 20 cm. phn -
6 Penebangan Pohon Standar Diameter diatas 21 s/d 25 cm. phn -
7 Penebangan Pohon Diameter diatas 25 cm. phn -
8 Angkutan material ton 6
9 Angkutan laut material ke pulau kecil ton -
10 Angkutan darat material di pulau kecil ton -
PT PLN ( PERSERO ) WILAYAH NTB
AREA MATARAM

DAFTAR LOKASI PEMASANGAN GARDU SISIPA


PENUNJANG PERBAIKAN TEGANGAN UJUNG DI AREA M
FUNGSI SALURAN KABEL TEGANGAN MENENGAH

SATUAN
NO

MATERIAL MATERIAL
PLN PEMB. PLN PEMB.

I MATERIAL UTAMA
1 Kabel TM NA2XSEBY 20 kV three core 3x150 mm2 ms -
2 Kabel TM NA2XSEBY 20 kV three core 3x240 mm2 ms -
3 Kabel TM NA2XSEBY 20 kV single core 1x150 mm2 ms -
4 Kabel TM NA2XSEBY 20 kV single core 1x240 mm2 ms -
5 Cubicle Incoming unit -
6 Cubicle Outgoing unit -
7 Cubicle Metering unit -
8 Bateray Charger unit -
9 Cut Out 24 kV set -
10 Lightning Arrester 24 kV set -

II MATERIAL NON UTAMA


1 Terminating kabel 3C, 70-240 mm set -
2 Terminating kabel 1C, 70-240 mm set -
3 Terminating Elastimol 70-240 mm set -
4 Jointing Kabel 3C, 70-240 mm set -
5 Jointing Kabel 1C, 70-240 mm set -
6 Terminal lug/Sepatu kabel for 150 mm AL bh -
7 Sepatu Kabel AL-CU 70 bh -
8 Box joint kabel bh -
9 Pipa Galvanized 5" 6 m pelindung kabel + Beugel bh -
10 Dudukan terminal bh -
11 Arde 3 Ohm pas. luar (u/Cubicle) set -
12 Arde 3 Ohm pas. luar set -
13 Patok tanda kabel bh -

III KONSTRUKSI
1 Pasir urug 1x0.2x0.4 m3 -
2 Concrete plate 40x20x6cm bh -
3 Penggalian tanah 1x1x0,4 m pada tanah biasa m3 -
4 Pengurugan tanah m3 -
5 Pekerjaan Boring 1 Kabel dengan pelindung pipa PVC AW5- 6" mt -

IV LAIN LAIN
1 Angkutan material ton -
2 Angkutan laut material ke pulau kecil ton -
3 Angkutan darat material di pulau kecil ton -
PT PLN ( PERSERO ) WILAYAH NTB
AREA MATARAM

DAFTAR LOKASI PEMASANGAN GARDU SISIPA


PENUNJANG PERBAIKAN TEGANGAN UJUNG DI AREA M
FUNGSI JARINGAN TEGANGAN RENDAH

SATUAN
NO

MATERIAL MATERIAL
PLN PEMB. PLN PEMB.

I MATERIAL UTAMA
1 LVTC 3x70+1x50 mm2 u/ belalai = 70 cm. mt -
2 LVTC 3x70+1x50 mm2. + 3% mt -

II MATERIAL NON UTAMA


1 Perlengkapan Kontramast TR set -
2 Perlengkapan Druckschoor TR set -
3 Treckschoor TR set -
Accessories LVTC
4 Suspension Assembly set -
5 Large Angle Assembly set -
6 Fixed Dead End Assembly set -
7 Bundle End Assembly set -
8 Comp. Con. AL for jumper 70-70 mm2 + Cover/Vinil bh -
9 Comp. Con. Joint Sleeve AL 70 mm2 + Hs bh -
10 Pemasangan Belalai ttk
11 Penomoran tiang bh -
12 Arde 5 Ohm pasangan luar set -
13 Pembetonan Tiang 70x70x70 cm bh -
14 Angkutan material ton -
15 Angkutan laut material ke pulau kecil ton -
16 Angkutan darat material di pulau kecil ton -
PEMASANGAN GARDU SISIPAN
N TEGANGAN UJUNG DI AREA MATARAM
SI GARDU DISTRIBUSI

JUMLAH

MATERIAL MATERIAL MATERIAL MATERIAL


PLN PEMB. PLN PEMB. PLN PEMB. PLN PEMB.

-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-

-
-
-

-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
PEMASANGAN GARDU SISIPAN
TEGANGAN UJUNG DI AREA MATARAM
NGAN TEGANGAN MENENGAH

JUMLAH

MATERIAL MATERIAL MATERIAL MATERIAL


PLN PEMB. PLN PEMB. PLN PEMB. PLN PEMB.

30
-
6
-
-
1,111
-
- 1,058
- -
-

- 2
- 1
- -
- -
- -
-
- 21
- -
- -
- -
- 32
- 14
- 2
- 2
- 21
- 21
1 -
- -
- -
- -
- -
- -
- -
- -
30 -

-
-
-
-
-
-
-
6
-
-
PEMASANGAN GARDU SISIPAN
TEGANGAN UJUNG DI AREA MATARAM
N KABEL TEGANGAN MENENGAH

JUMLAH

MATERIAL MATERIAL MATERIAL MATERIAL


PLN PEMB. PLN PEMB. PLN PEMB. PLN PEMB.

-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-

-
-
-
PEMASANGAN GARDU SISIPAN
TEGANGAN UJUNG DI AREA MATARAM
INGAN TEGANGAN RENDAH

JUMLAH

MATERIAL MATERIAL MATERIAL MATERIAL


PLN PEMB. PLN PEMB. PLN PEMB. PLN PEMB.

-
-

-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
PT PLN ( PERSERO ) WILAYAH NTB
AREA MATARAM

RENCANA ANGGARAN BIAYA ( RAB )


FUNGSI JARINGAN TEGANGAN MENENGAH

Pekerjaan : Pembangunan MVTIC Dari SPN Belanting Sampai Tiang Pool Pelanggan Honggo Tahap 7

MATERIAL HARGA SATUAN

SATUAN
NO BAHAN
PLN PEMB
(Rp)

I MATERIAL UTAMA
1 Isolator tumpu 20 kV bh 30
2 Isolator tarik 20 kV, komplit set -
3 Lightning Arrester 24 kV set 1
4 Cut Out 24 kV set -
5 Hotline Clamp ( LLC ) ukuran 70 - 150 mm2 bh -
6 Kabel MVTIC 3x1x150 mm2 + Andongan 5% mtr 1,111
7 Konduktor AAAC/S 150 mm2 + Andongan 3% mtr -
8 Penarikan Kabel MVTIC 3x1x150 mm2 + Andongan 5% ms 1,058
9 Kawat ACSR 2/0 mm2 pengikat isol. mt -
10 Alluminium Binding Wire bh -

II MATERIAL NON UTAMA


1 Terminating 24 KV, 1C, OD 70-240 mm set 2 5,500,000
2 Jointing 24 KV, 1C, OD 70-240 mm set 1 6,500,000
3 Perlengkapan Druckschoor TM set - 618,000
4 Perlengkapan Kontramast TM set - 1,281,000
5 Treck schoor TM set - 716,000
6 Cross Arm UNP 100
a. Type A1 set 21 790,000
b. Type A2 set - 1,638,000
c. Type A3 set - 1,638,000
d. Type B3 set - 1,741,000
7 Suspension assembly MVTIC set 32 400,000
8 2xFixed Dead End Assembly set 14 375,000
9 Fixed dead end assembly MVTIC set 2 375,000
10 Dudukan terminal set 2 790,000
11 Penghalang panjat set 21 99,000
12 Tanda kilat kecil bh 21 53,000
13 Arde 5 Ohm pas. Luar u/ ujung MVTIC di pangkal set 1 - 218,000
14 Arde 3 Ohm pas. Luar set - 386,000
15 Terminal lug/Sepatu kabel for 150 mm AL bh - 51,000
16 Comp. Jumper Connector 150-150 mm2 AL bh - 35,000
17 Comp. Jumper Connector 70-150 mm2 AL bh - 25,000
18 Comp.Tension Joint Sleeve 150 mm2 AL bh - 75,000
19 Comp.Non Tension Joint Sleeve 150 mm2 AL bh - 40,381
20 Sepatu Kabel AL-CU 70 bh - 43,740
21 Pemasangan ikatan isolator tumpu bh 30

III PEKERJAAN PENDUKUNG


1 Ongkos perabasan kms -
2 Foto Dokumentasi 4R + tagging GPS ttk -
3 Gambar revisi lbr -
4 Commisioning test ls -
5 Penebangan Pohon Standar Diameter diatas 10 s/d 20 cm. phn -
6 Penebangan Pohon Standar Diameter diatas 21 s/d 25 cm. phn -
7 Penebangan Pohon Diameter diatas 25 cm. phn -
8 Angkutan material ton 6
9 Angkutan laut material ke pulau kecil ton -
10 Angkutan darat material di pulau kecil ton -

Sub. Jumlah
ANGGARAN BIAYA ( RAB )
NGAN TEGANGAN MENENGAH

langgan Honggo Tahap 7

HARGA SATUAN JUMLAH HARGA JUMLAH


UPAH BAHAN UPAH TOTAL
(Rp) (Rp) (Rp) (Rp)

30,900 927,000 927,000


55,700 - -
43,600 43,600 43,600
43,600 - -
26,800 - -
18,300 20,329,470 20,329,470

5,000 5,290,000 5,290,000

7,300 - -

610,800 11,000,000 1,221,600 12,221,600


763,500 6,500,000 763,500 7,263,500
130,800 - - -
183,200 - - -
152,700 - - -

41,700 16,590,000 875,700 17,465,700


65,400 - - -
65,400 - - -
76,300 - - -
38,600 12,800,000 1,235,200 14,035,200
57,200 5,250,000 800,800 6,050,800
57,200 750,000 114,400 864,400
34,800 1,580,000 69,600 1,649,600
9,600 2,079,000 201,600 2,280,600
9,600 1,113,000 201,600 1,314,600
114,500 - 114,500 114,500
136,200 - - -
13,100 - - -
24,400 - - -
24,400 - - -
29,100 - - -
26,900 - - -
13,100 - - -
7,300 219,000 219,000

1,016,100 - -
5,000 - -
18,800 - -
273,100 - -
100,000 - -
200,000 - -
250,000 - -
678,000 4,068,000 4,068,000
3,504,000 - -
750,000 - -

57,662,000 36,475,570 94,137,570


PT PLN ( PERSERO ) WILAYAH NTB
AREA MATARAM

REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )

MATERIAL
NO URAIAN PEKERJAAN VOLUME
( Rp )

I
Pembangunan MVTIC Dari SPN Belanting Sampai Tiang Pool
Pelanggan Honggo Tahap 7

1 FUNGSI JARINGAN TEGANGAN MENENGAH 1.058 Kms 57,662,000


2 FUNGSI SALURAN KABEL TEGANGAN MENENGAH - Kms -
3 FUNGSI GARDU DISTRIBUSI - Bh -
4 FUNGSI JARINGAN TEGANGAN RENDAH - Kms -

Jumlah 57,662,000
P P N 10 % 5,766,200
Jumlah total 63,428,200

Terbilang : Seratus Tiga Juta Lima Ratus Lima Puluh Satu Ribu Tiga Ratus Dua Puluh Tujuh Rupiah

Mengetahui, Diperiksa/disetujui,
MANAJER ASMAN JARINGAN

GURUH DIYUSAKMANA JERIMIAS WATU


REKAPITULASI
ANGGARAN BIAYA ( RAB )

JASA JUMLAH
( Rp ) ( Rp )

36,475,570 94,137,570
- -
- -
- -

36,475,570 94,137,570
3,647,557 9,413,757
40,123,127 103,551,327

Mataram, 26 Juni 2018 Februari 2015

Diencanakan/dihitung,
SUPV. HARJAR

I GEDE SUDIKA
PT PLN. ( Persero ) Wilayah NTB
Area Mataram

PERMINTAAN PENCADANGAN ANGGARAN INVESTASI (

VO SA
NO URAIAN PEKERJAAN LU TU
ME AN
I Pembangunan MVTIC Dari SPN Belanting Sampai Tiang Pool

Pelanggan Honggo Tahap 7

1 FUNGSI JARINGAN TEGANGAN MENENGAH 1.058 Kms

2 FUNGSISALURAN KABEL TEGANGAN MENENGAH - Kms

3 FUNGSI GARDU DISTRIBUSI - Bh

4 FUNGSI JARINGAN TEGANGAN RENDAH - Kms

JUMLAH
PPN 10 %
JUMLAH TOTAL

Terbilang : Seratus Tiga Juta Lima Ratus Lima Puluh Satu Ribu Tiga Ratus Dua Puluh Tujuh Rupiah

MENGETAHUI DIPERIKSA/DISETUJUI
MANAJER ASMAN JARINGAN

GURUH DIYUSAKMANA JERIMIAS WATU

Catatan Bidang Keuangan :

Diterima Tanggal :
1. SETUJU / TIDAK SETUJU
2. Nomor :
3. Tanggal :
4. Kode Perkiraan :
5. Pos Anggaran :
6. Ket. Pos Anggaran :
7. Catatan :
8. No. PRK :
9. No. SKKI / SKKO :
10. Catatan :
PENCADANGAN ANGGARAN INVESTASI ( AI )

Nomor :
Tanggal :
HARGA HARGA
MATERIAL JASA JUMLAH ( Rp )
( Rp ) ( Rp )

57,662,000 36,475,570 94,137,570

- - -

- - -

- - -

57,662,000 36,475,570 94,137,570


5,766,200 3,647,557 9,413,757
63,428,200 40,123,127 103,551,327