NO URAIAN PEKERJAAN SAT VOLUME HARGA SATUAN JUMLAH HARGA

A TOLOK UKUR : JTM


I Pengadaan MDU
1 Kawat N2XS 120 mm2 m' 120 1,206,000
2 kawat AAAC 3 x 150 mm2 m' 52 52,650 2,737,800
3 Isolator Tumpu 20 Kv Set 1 1,414,500
4 Isolator Tarik Type Suspension / Starin Rod Set 1 1,762,000
5 Tiang Listrik Beton 13 Meter/200 daN btg 1 15,405,000
Sub Total 2,737,800
II PEKERJAAN JASA JTM
1 Penarikan Kawat JTM 3 Ph. N2XS 120 mm2 kms 0.120 17,740,000
2 Penarikan Kawat JTM 3 Ph. 3x150 mm2 kms 0.052 18,684,000 971,568
3 Pemas. Pembesian & Isolator Tumpu Set 4 4,038,000
4 Pemas. Pembesian & Isolator Afspan Ujung Set 1 3,498,000
5 Pemancangan Tiang Beton 13 Meter, 200 daN btg 1 3,470,000
6 Pemas. Tupang tarik Set 4 1,781,000
Sub Total 971,568
B TOLOK UKUR : JTR
I Pengadaan MDU
1 Kabel NFGBY 4 x 95 mm2 m' 25 730,000 18,250,000
Sub Total 18,250,000
II PEKERJAAN JASA JTR
1 Pemasangan NFGBY 4 x 95 mm2 kms 0.025 12,470,000 311,750
Sub Total 311,750
C TOLOK UKUR : GD
I Pengadaan MDU
1 Tiang Listrik Beton 13 Meter/200 daN (Portal) btg 2 11,500,000 23,000,000
2 Trafo distribusi 200 kVa 3 ph 220/380 V B2,20 kV (Type D3) Unit 1 75,000,000 75,000,000
3 Ligtning Arester 10 kA, 20 kV Polymer Set 1 2,000,000 2,000,000
4 Fuse Cut Out 250 A, 20 kV polymer Set 1 2,000,000 2,000,000
5 Panel Set 1 10,000,000 10,000,000
6 Kabel Nyy 1x95 mm m' 74 100,000 7,400,000
7 Kabel Nyy 1x120 mm m' 36 125,000 4,500,000
Sub Total 123,900,000
II PEKERJAAN JASA GD dan Kwh Meter 3 Phasa 20,000,000
1 Pembangunan GD Portal 3 Phasa 2 Jurusan (Trafo 200 kVa) Set 1 29,378,000
2 Pemancangan Tiang Beton Trafo 13 Meter, 200 daN btg 2 3,470,000
3 Pemasangan Kabel Naik Turun bh 1 6,861,000
Sub Total 20,000,000
JUMLAH 166,171,118
PPN 10%
JUMLAH SETELAH PAJAK
DIBULATKAN 166,100,000