ESTIMASI BIAYA PENGADAAN & PEMASANGAN KABEL TM/TR, PANEL TM & Trafo 1 X 400 kva (daya 240 kva)

LOKASI :BOJONEGARA CILEGON


Hal 1/2
Material Jasa
NO. URAIAN satuan volume Harga Satuan Jumlah Harga Harga Satuan Jumlah Harga
(Rp.) (Rp.) (Rp.) (Rp.)

A PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasai lots 1 - 20,000,000 20,000,000
2 Shop Drawing & As Built Drawing -
3 Pembuatan Direksi Keet

B PEKERJAAN BANGUNAN GARDU


1 Gardu PLN Type 7R2 unit 1 By PLN
2 Gardu Konsumen Type ST16 unit 1 135,000,000 135,000,000
C PENGADAAN & PEMASANGAN TRAFO, PANEL TM/TR -
1 Panel TM 24 KV (Type LBS) set 1 45,000,000 45,000,000 2,500,000 2,500,000
2 Panel TM 24 KV (Type LBS + Fuse + Shunt Trip) set 1 56,000,000 56,000,000 2,500,000 2,500,000
3 Trafo Distribusi 400 KVA, unit 1 145,000,000 145,000,000 4,000,000 4,000,000
c/w Elastimold & DGPT -
4 Pengadaan LVMDP 2500 A + Capasitor Bank 1250 KVAR set 1 By Owner 3,000,000 3,000,000
5 Pengadaan & Pemasangan Grounding set 3 1,750,000 5,250,000 800,000 2,400,000

D PENGADAAN DAN PEMASANGAN KABEL TM


1 Dari Gardu PLN ke Panel TM 24 KV
NA2XSEbY, 3 X 70 mm meter 25 565,000 14,125,000 47,500 1,187,500
2 Dari Panel TM 24 KV ke Trafo 500 kva
N2XSY, 1 X 50 mm meter 25 366,000 9,150,000 20,000 500,000
3 Dari Trafo 500 kva ke Panel LVMDP & Capasitor Bank meter 960 500,000 480,000,000 30,000 28,800,000
NYY 1 x 300 mm -
4 MV Termination Kit set 4 3,500,000 14,000,000 450,000 1,800,000
5 LV Termination Kit set 16 200,000 3,200,000 50,000 800,000

E PENGADAAN DAN PEMASANGAN KABEL LADDER


1 W=500 mm, H=100mm meter 10 669,500 6,695,000 85,000 850,000
2 Support lots 1 2,000,000 2,000,000 500,000 500,000
3 Jembatan Kabel, UNP 14, meter
F GALIAN …..

Hal 2/2
Material Jasa
NO. URAIAN satuan volume Harga Satuan Jumlah Harga Harga Satuan Jumlah Harga
(Rp.) (Rp.) (Rp.) (Rp.)
F GALIAN TANAH & LAIN-LAIN
1 Galian Tanah & Urug kembali meter 120 - 65,000 7,800,000
2 Pengadaan Batu Pelindung kabel buah 480 4,500 2,160,000 -
3 Pengadaan Pasir Urug m3 12 150,000 1,800,000 -
4 Pembuatan Sertifikasi Laik Operasi (SLO) va 240000 - 155 37,200,000
5 Testing & Comissioning lots 1 - 7,500,000 7,500,000
6 Jasa Pengurusan ke PLN lots 1 - 35,000,000 35,000,000

Jumlah 784,380,000 Jumlah 291,337,500


Jumlah (A,B,C,D,E,F) 1,075,717,500
G Biaya ke PLN, 240000 va 240000 505 121,200,000
Uang Jaminan Langganan va 240000 202 48,480,000
Jumlah G 169,680,000
Jumlah Total 1,245,397,500

Terbilang : " Satu milyar dua ratus empat puluh lima juta tiga ratus sembilan puluh tujuh ribu lima ratus rupiah "

Catatan :
- Harga tersebut belum termasuk PPN + PPh
- Harga LVMDP, Capasitor Bank dan Panel TR lainnya akan kami sampaikan setelah persetujuan teknis disepakati bersama.
- Harga dapat berubah sesuai dengan kondisi aktual di lapangan, spesifikasi teknis yang disepakati & kebijakan akhir yang berlaku di PLN

Serang 25 November 2014


CV.IRUL MANDIRI
USWATUN HASANAH
Direktur
ESTIMASI BIAYA PENGADAAN & PEMASANGAN KABEL TM/TR, PANEL TM & Trafo 1
LOKASI :BOJONEGARA CILEGON

NO. URAIAN satuan volume

A PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasai lots 1
2 Shop Drawing & As Built Drawing
3 Pembuatan Direksi Keet

B PEKERJAAN BANGUNAN GARDU


1 Gardu PLN Type 7R2 unit 1
2 Gardu Konsumen Type ST16 unit 1
C PENGADAAN & PEMASANGAN TRAFO, PANEL TM/TR
1 Panel TM 24 KV (Type LBS) set 1
2 Panel TM 24 KV (Type LBS + Fuse + Shunt Trip) set 1
3 Trafo Distribusi 500 KVA, unit 1
c/w Elastimold & DGPT
4 Pengadaan LVMDP 2500 A + Capasitor Bank 1250 KVAR set 1
5 Pengadaan & Pemasangan Grounding set 3

D PENGADAAN DAN PEMASANGAN KABEL TM


1 Dari Gardu PLN ke Panel TM 24 KV
NA2XSEbY, 3 X 70 mm meter 25
2 Dari Panel TM 24 KV ke Trafo 500 kva
N2XSY, 1 X 50 mm meter 25
3 Dari Trafo 500 kva ke Panel LVMDP & Capasitor Bank meter 960
NYY 1 x 300 mm
4 MV Termination Kit set 4
5 LV Termination Kit set 16

E PENGADAAN DAN PEMASANGAN KABEL LADDER


1 W=500 mm, H=100mm meter 10
2 Support lots 1
3 Jembatan Kabel, UNP 14, meter

F GALIAN …..

NO. URAIAN satuan volume


F GALIAN TANAH & LAIN-LAIN
1 Galian Tanah & Urug kembali meter 120
2 Pengadaan Batu Pelindung kabel buah 480
3 Pengadaan Pasir Urug m3 12
4 Pembuatan Sertifikasi Laik Operasi (SLO) va 450000
5 Testing & Comissioning lots 1
6 Jasa Pengurusan ke PLN lots 1

G Biaya ke PLN, 450000 va 450000


Uang Jaminan Langganan va 450000

Terbilang : " Satu milyar empat ratus empat puluh satu juta empat ratus tujuh belas ribu lima ratus rupiah "

Catatan :
- Harga tersebut belum termasuk PPN + PPh
- Harga LVMDP, Capasitor Bank dan Panel TR lainnya akan kami sampaikan setelah persetujuan teknis disepakati bersama.
- Harga dapat berubah sesuai dengan kondisi aktual di lapangan, spesifikasi teknis yang disepakati & kebijakan akhir yang berl
TM/TR, PANEL TM & Trafo 1 X 500 kva (daya 450 kva)
GARA CILEGON
Hal 1/2
Material Jasa
Harga Satuan Jumlah Harga Harga Satuan Jumlah Harga
(Rp.) (Rp.) (Rp.) (Rp.)

- 20,000,000 20,000,000
-

By PLN
- 135,000,000 135,000,000
-
45,000,000 45,000,000 2,500,000 2,500,000
56,000,000 56,000,000 2,500,000 2,500,000
160,000,000 160,000,000 4,000,000 4,000,000
-
By Owner 3,000,000 3,000,000
1,750,000 5,250,000 800,000 2,400,000

565,000 14,125,000 47,500 1,187,500

366,000 9,150,000 20,000 500,000


500,000 480,000,000 30,000 28,800,000
-
3,500,000 14,000,000 450,000 1,800,000
200,000 3,200,000 50,000 800,000

669,500 6,695,000 85,000 850,000


2,000,000 2,000,000 500,000 500,000

Hal 2/2
Material Jasa
Harga Satuan Jumlah Harga Harga Satuan Jumlah Harga
(Rp.) (Rp.) (Rp.) (Rp.)

- 65,000 7,800,000
4,500 2,160,000 -
150,000 1,800,000 -
- 155 69,750,000
- 7,500,000 7,500,000
- 35,000,000 35,000,000

Jumlah 799,380,000 Jumlah 323,887,500


Jumlah (A,B,C,D,E,F) 1,123,267,500
505 227,250,000
202 90,900,000
Jumlah G 318,150,000
Jumlah Total 1,441,417,500

ribu lima ratus rupiah "

teknis disepakati bersama.


ati & kebijakan akhir yang berlaku di PLN

Serang 25 November 2014


CV.IRUL MANDIRI

USWATUN HASANAH
Direktur