Anda di halaman 1dari 68

REKAPITALASI BIAYA

PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


PROYEK RUMAH SAKIT - SARI ASIH CIPUTAT, TANGERANG

BIAYA
NO. URAIAN
(Rp)

A. PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan 227,600,000
2 Perizinan PLN (1000 KVA) 150,000,000
3 Perizinan PT Telkom Indonesia 9,600,000
4 Perizinan PAL (Pembuangan air limbah) 12,000,000

B. PEKERJAAN MEKANIKAL
1 Pekerjaan Sistem Tata Udara (Air Conditioning) 2,293,882,000
2 Pekerjaan Sistem Transportasi (Lift) 1,373,000,000
3 Pekerjaan Sistem Plumbing 1,997,681,188
4 Seawage Treatment Plant (STP) 456,997,000
5 Pekerjaan Sistem Fire Fighting 2,845,815,864
6 Pekerjaan Sistem Gas Medic 1,553,439,767

C. PEKERJAAN ELEKTRIKAL
1 Pekerjaan Sistem Listrik 4,512,322,298
2 Pekerjaan Sistem Genset 1,914,503,750
3 Pekerjaan Sistem Penangkal Petir 41,400,000
4 Pekerjaan Sistem Telepon dan Data 294,710,000
5 Pekerjaan Sistem Tata Suara 141,120,000
6 Pekerjaan Fire Alarm 372,454,520
7 Pekerjaan Sistem MATV 112,926,000
8 Pekerjaan Sistem CCTV 288,495,320
9 Pekerjaan Sistem Nurse Call 1,651,986,275

Total A + B + C 20,249,933,982
Keuntungan Pemborong 10% 2,024,993,398
Sub total A + B + C + Keuntungan Pemborong 22,274,927,380
PPN 10 % 2,227,492,738
TOTAL 24,502,420,119
REKAPITALASI BIAYA
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RUMAH SAKIT - SARI ASIH CIPUTAT, TANGERANG

BIAYA
NO. URAIAN
(Rp)

A. PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan 227,600,000
2 Perizinan PLN (1000 KVA) 150,000,000
3 Perizinan PT Telkom Indonesia 9,600,000
4 Perizinan PAL (Pembuangan air limbah) 12,000,000

B. PEKERJAAN MEKANIKAL
1 Pekerjaan Sistem Tata Udara (Air Conditioning) 2,293,882,000
2 Pekerjaan Sistem Transportasi (Lift) ( By Owner )
3 Pekerjaan Sistem Plumbing 1,997,681,188
4 Seawage Treatment Plant (STP) ( By Owner )
5 Pekerjaan Sistem Fire Fighting 2,845,815,864
6 Pekerjaan Sistem Gas Medic ( By Owner )

C. PEKERJAAN ELEKTRIKAL
1 Pekerjaan Sistem Listrik 4,512,322,298
8 Pekerjaan Sistem Genset ( By Owner )
2 Pekerjaan Sistem Penangkal Petir 41,400,000
3 Pekerjaan Sistem Telepon dan Data 294,710,000
4 Pekerjaan Sistem Tata Suara 141,120,000
5 Pekerjaan Fire Alarm 372,454,520
6 Pekerjaan Sistem MATV 112,926,000
7 Pekerjaan Sistem CCTV 288,495,320
9 Pekerjaan Sistem Nurse Call 1,651,986,275

Total A + B + C 14,951,993,465
Keuntungan Pemborong 10% 1,495,199,347
Sub total A + B + C + Keuntungan Pemborong 16,447,192,812
PPN 10 % 1,644,719,281
TOTAL 18,091,912,093
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN PERSIAPAN

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

Pekerjaan Persiapan
1 Biaya -biaya pengadaan staf dan peralatan kantor yang akan 1 lot 40,000,000 40,000,000
mengelola pelaksanaan pekerjaan dan mengurus segala hal
yang berhubungan dengan administrasi proyek (mobilisasi)

2 Biaya - Biaya pemindahan peralatan kantor dan staff yang 1 lot 25,000,000 25,000,000
telah dipergunakan untuk pelaksanaan proyek (demobilisasi)

3 Pemborong harus mengadakan peralatan kerja yang cukup, 1 lot ########## 100,000,000
jumlah kualitas dan kapasitasnya untuk melaksanakan peker-
jaan yang dimaksudkan dalam dokumen tender ini.
Termasuk dalam biaya ini adalah pembuatan dan pembong -
karan serta perampihan kembali tempat penyimpanan barang.

4 Pembuatan dan penggandaan dokumen kontrak lengkap gam- 1 lot 2,000,000 2,000,000
bar-gambar kontrak sebanyak lima (5) set, dimana 4(empat)
set diberikan kepada pemberi tugas.

5 Pembuatan gambar- gambar pelaksanaan /shop drawing, gam- 1 lot 5,000,000 5,000,000
bar-gambar yang telah dilaksanakan /as built drawing yang ha-
rus diberikan kepada pemberi tugas dalam bentuk kalkir 1(satu)
set dan 2(dua) set blue print.

6 Pengadaan contoh - contoh bahan yang dikehendaki oleh pem- 1 lot incl
beri tugas atau wakilnya sesuai dengan spesifikasi tehnis yang
dipersyaratkan dalam dokumen tender harus segera diadakan
tanpa keterlambatan

7 Pemborong harus mengangkat keluar lokasi proyek semua 1 lot 15,000,000 15,000,000
sampah-sampah hasil pekerjaan secara teratur sehingga kea-
daan lapangan selalu bersih. Termasuk didalamnya pengadaan
tempat sampah sementara dan peralatan kebesihannya.

8 Pemborong harus penyiapkan kantor proyek untuk wakil pem- 1 lot 12,000,000 12,000,000
beri tugas termasuk didalamnya kantor pemborong lengkap
dengan lampu penerangan dan instalasinya.

9 Pengadaan peralatan pencegahan terhadap bahan kebakaran 1 lot 600,000 600,000


berupa APAR dan menyediakan tenaga-tenaga yang terlatih.

10 Pemborong bertanggung jawab terhadap penjagaan / perlindu- 1 lot 4,000,000 4,000,000


ngan peralatan kerja dan material kerja terhadap kehilangan
atau kerusakan yang sedang dipergunakan dalam proyek.

11 Pengadaan Sepatu Safety, Handy talky (HT), Helm proyek, 1 lot 9,000,000 9,000,000
jas hujan, payung untuk pemberi tugas dan pengawas lapangan

12 Semua pekerja pemborong harus mendaftarkan seluruh pega- 1 lot 15,000,000 15,000,000
wainya yang terlibat dalam proyek ini kepada asuransi JAM-
SOSTEK

Sub Total 227,600,000


PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM TATA UDARA

HARGA SATUAN JUMLAH HARGA


No Uraian QTY SAT
Rp. Rp.

A PEKERJAAN PLUMBING

I Peralatan Utama
1 Transfer Pump 2 Unit 16,100,000 32,200,000
Kapasitas : 475 l/m
Head : 40 mtr
Speed : 2900 rpm
Daya : 7,5 kw/ 3/ 380 V/50 hz/3 ph
Jenis : Pakaged (1set 2 pompa)
Berikut kabel electroda GWT dan Roof Tank

2 Booster Pump 1 Unit 48,000,000 48,000,000


Kapasitas : 150 l/m
Head : 20 mH20
Speed : 2900 rpm
Daya : 3 kw/ 3/ 380 V/50 hz/3 ph
Jenis : Pakaged (1set 2 pompa)
Spesifikasi Pompa :
1 Paket Booster Pump terdiri dari :
- 2 unit Pompa + Motor
- 1 unit Panel Control Automatic/ Alternate
- 1 unit Diagprahma Pressure Tank
- 1 lot Accessories

3 Pompa Deep Well 1 Unit 262,500,000 262,500,000


Kapasitas : 150 Lpm
Head : 20 mH20
Speed : 2900 rpm
Daya : 3 kw/ 3/ 380 V/50 hz/3 ph

4 Sand Filter
Type : Automatic Backwash 1 Unit 42,625,000 42,625,000
Kap : 150 l/min

5 Carbon Filter
Type : Automatic Backwash 1 Unit 48,625,000 48,625,000
Kap : 150 l/min

6 Tanki Air Atas (Roof tank) , Lokasi Atap 1 set 83,125,000 83,125,000
Kapasitas : 20 m3
Bahan : FRP
Lengkap dengan dudukan pondasi, dan pipa over,
flow dan sistem drain. Termasuk tangga pengontrol

7 Sump Pump 1 (Basement) 18 unit 15,312,000 275,616,000


Kapasitas : 150 Lpm
Head : 20 m H2O
Speed : 1450 rpm
Daya : 1,5 kW, 3, 380 V, 50 Hz
Jenis : Submersible Pump, lengkap dengan
panel kontrol dan pengkabelannya dan Accessories

8 Material bantu 1 lot 3,500,000 3,500,000

9 Testing commissioning 1 lot 7,500,000 7,500,000


HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.

Sub. Total I 803,691,000

II Site Plan dan R. Pompa


- 100 mm ( Header ) 1 lot 3,500,000 3,500,000
- 65 mm 131 mtr 164,260 21,518,060
- 32 mm 70 mtr 76,879 5,381,513
- 25 mm 196 mtr 61,155 11,986,380
- 20 mm 210 mtr 42,881 9,005,063

Water meter dia 65mm 1 bh 1,970,250 1,970,250


Bak kontrol 40 x 40 x 40 cm 8 bh 1,750,000 14,000,000

Gate valve , tekanan kerja 10 bar


- 150 mm 5 bh 3,787,500 18,937,500
- 80 mm 2 bh 1,413,750 2,827,500
- 20 mm 8 bh 156,603 1,252,821

Check Valve, tekanan kerja 10 kg


- 65 mm 2 bh 1,970,250 3,940,500
Strainer, tekanan kerja 10 bar :
- 80 mm 2 bh 1,833,750 3,667,500

Flexibel joint
- 80 mm 2 bh 993,750 1,987,500
- 65 mm 2 bh 861,250 1,722,500

Foot Valve
- 80 mm 2 bh 1,613,750

Pressure Gauge 2 bh 185,000 370,000

Floating Valve
- 50 mm 1 bh 2,500,000 2,500,000

Kran Taman 9 bh 130,000 1,170,000

Instalasi Air Kotor


(Pipa PVC Class AW, class 10 K) air kotor
dia. 150 mm 48 m 131,719 6,322,514
dia. 100 mm 102 m 51,333 5,236,000

Sub Total II 117,295,600

III INSTALASI AIR HUJAN


Pipa PVC AW Class 10 K

Site Plan
200 150 m 289,200 43,380,000
150 67 m 197,710 13,246,570

Instalasi pipa tegak


50 28 m 33,384 934,752
80 56 m 55,650 3,116,400
150 168 m 197,710 33,215,280

Lantai-dasar
150 73 m 197,710 14,432,830

Lantai-dua
150 95 m 197,710 18,782,450
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
80 70 m 55,650 3,895,500

Roof drain
80 10 bh 162,750 1,627,500

Lantai-tiga
150 76 m 93,780 7,127,280

Lantai-empat
150 76 m 93,780 7,127,280

Lantai-lima
100 76 m 93,780 7,127,280

Lantai-atap
100 76 m 93,780 7,127,280

Roof drain
100 20 bh 187,250 3,745,000

Lantai-atap (ruang mesin)


80 41 m 51,333 2,104,667
100 20 m 93,780 1,875,600

Roof drain
80 5 bh 162,750 813,750
100 4 bh 187,250 749,000

Fitting-fitting 1 lot 12,500,000 12,500,000

Material bantu 1 lot 5,000,000 5,000,000

Testing commissioning 1 lot 4,500,000 4,500,000

Sub. Total III 192,428,419

IV LANTAI BASEMENT
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 80 mm 30 mtr 210,825 6,324,750
dia. 50 mm 30 mtr 119,550 3,586,500
dia. 40 mm 55 mtr 87,345 4,803,975
dia. 32 mm 85 mtr 76,879 6,534,694
dia. 25 mm 75 mtr 61,155 4,586,625
dia. 20 mm 120 mtr 42,881 5,145,750
dia. 15 mm 300 mtr 33,608 10,082,250

Gate Valve
dia. 50 mm 1 bh 396,700 396,700
dia. 40 mm 2 bh 256,250 512,500
dia. 32 mm 2 bh 209,450 418,900
dia. 25 mm 8 bh 157,600 1,260,800

Fitting 1 lot 2,750,000 2,750,000

Material bantu 1 lot 1,375,000 1,375,000

Pengetesan 1 lot 2,500,000 2,500,000

47,778,444
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
INSTALASI AIR KOTOR, BEKAS DAN VENT
Instalasi Air Bekas
(Pipa PVC Class AW, class 10 K) air kotor
dia. 150 mm 8 m 197,710 1,581,680
dia. 100 mm 88 m 93,780 8,252,640
dia. 80 mm 100 m 55,650 5,565,000
dia. 65 mm 72 m 44,295 3,189,240
dia. 50 mm 30 m 33,384 1,001,520

Gate valve dia 80 mm 18 bh 1,335,750 24,043,500


Check valve dia 80 mm 18 bh 1,593,750 28,687,500

Instalasi Air Kotor


(Pipa PVC Class AW, class 10 K) air bekas
dia. 150 mm 48 m 197,710 9,490,080
dia. 100 mm 30 m 93,780 2,813,400

Instalasi Air Vent


dia. 50 mm 71 m 32,100 2,279,100
dia. 40 mm 17 m 24,825 422,025
dia. 32 mm 45 m 22,688 1,020,938

Floor Drain (FD)


dia. 50 mm 9 bh 147,650 1,328,850

Clean Out lantai (Co)


dia. 100 mm 2 bh 164,286 328,571
dia. 50 mm 4 bh 136,905 547,619

Fitting 1 lot 2,750,000 2,750,000

Material bantu 1 lot 1,350,000 1,350,000

Pengetesan 1 lot 2,500,000 2,500,000

97,151,663

V LANTAI SATU
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 50 mm 6 m 119,550 717,300
dia. 40 mm 46 m 87,345 4,017,870
dia. 32 mm 85 m 76,879 6,534,694
dia. 25 mm 66 m 61,155 4,036,230
dia. 20 mm 133 m 42,881 5,703,206
dia. 15 mm 285 m 33,608 9,574,777

Gate Valve
dia. 50 mm 1 bh 396,700 396,700
dia. 32 mm 2 bh 209,450 418,900
dia. 25 mm 2 bh 157,600 315,200
dia. 20 mm 3 bh 120,000 360,000

Fitting 1 lot 1,250,000 1,250,000

Material bantu 1 lot 750,000 750,000

INSTALASI AIR KOTOR, BEKAS DAN VENT


Instalasi Air Bekas
(Pipa PVC Class AW, class 10 K) air kotor
dia. 100 mm 25 m 93,780 2,344,500
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
dia. 80 mm 75 m 55,650 4,173,750
dia. 65 mm 90 m 44,295 3,986,550
dia. 50 mm 115 m 44,295 5,093,925

Instalasi Air Kotor


(Pipa PVC Class AW, class 10 K) air bekas
dia. 150 mm 22 m -
dia. 100 mm 85 m 93,780 7,971,300
dia. 80 mm 12 m 55,650 667,800

Pipa Vent PVC Class D Class 5 K


dia. 50 mm 92 m 32,100 2,953,200
dia. 40 mm 54 m 24,825 1,340,550
dia. 32 mm 120 m 22,688 2,722,500

Floor Drain (FD)


dia. 50 mm 15 bh 147,650 2,214,750

Clean out lantai (Co)


dia. 80 mm 5 bh 164,286 821,429
dia. 65 mm 3 bh 136,905 410,714

Fitting 1 lot 2,250,000 2,250,000

Material bantu 1 lot 1,450,000 1,450,000

Pengetesan 1 lot 2,500,000 2,500,000

74,975,845

VI LANTAI DUA
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 50 mm 3 mtr 119,550 358,650
dia. 40 mm 65 mtr 87,345 5,677,425
dia. 32 mm 36 mtr 76,879 2,767,635
dia. 25 mm 45 mtr 61,155 2,751,975
dia. 20 mm 68 mtr 42,881 2,915,925
dia. 15 mm 265 mtr 33,608 8,905,988

Gate Valve
dia. 50 mm 1 bh 396,700 396,700
dia. 32 mm 2 bh 256,250 512,500
dia. 25 mm 2 bh 209,450 418,900

Fitting 1 lot 1,000,000 1,000,000

Material bantu 1 lot 650,000 650,000

Instalasi Air Bekas


(Pipa PVC Class AW, class 10 K) air kotor
dia. 100 mm 150 mtr 93,780 14,067,000
dia. 80 mm 20 m 55,650 1,113,000
dia. 65 mm 25 m 44,295 1,107,375
dia. 50 mm 25 m 32,100 802,500

Instalasi Air Kotor


(Pipa PVC Class AW, class 10 K) air bekas
dia. 100 mm 14 mtr 93,780 1,312,920
dia. 150 mm 14 mtr 197,750 2,768,500
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
Pipa Vent PVC Class D Class 5 K
dia. 50 mm 51 mtr 32,100 1,637,100
dia. 40 mm 50 mtr 24,825 1,241,250
dia. 32 mm 80 mtr 22,688 1,815,000

Floor Drain (FD)


dia. 50 mm 5 bh 147,650 738,250
dia. 65 mm 2 bh 175,000 350,000

Clean out lantai (Co)


dia. 50 mm 3 bh 32,100 96,300
dia. 65 mm 5 bh 136,905 684,524
dia. 150 mm 7 bh 197,750 1,384,250

Fitting 1 lot 2,738,095 2,738,095

Material bantu 1 lot 2,190,476 2,190,476


.
Pengetesan 1 lot 2,190,476 2,190,476

62,592,714
VII LANTAI TIGA
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 65 mm 20 mtr 164,260 3,285,200
dia. 40 mm 65 mtr 87,345 5,677,425
dia. 32 mm 64 mtr 76,879 4,920,240
dia. 25 mm 60 mtr 61,155 3,669,300
dia. 20 mm 60 mtr 42,881 2,572,875
dia. 15 mm 205 mtr 33,608 6,889,538

Gate Valve
dia. 65 mm 1 bh 164,260
dia. 40 mm 2 bh 465,476 930,952
dia. 32 mm 2 bh 186,174 372,348
dia. 25 mm 5 bh 156,603 783,013
dia. 15 mm 3 bh 33,608 100,823

Fitting 1 lot 2,738,095 2,738,095

Material bantu 1 lot 2,190,476 2,190,476

Instalasi Air Bekas


(Pipa PVC Class AW, class 10 K) air kotor
dia. 80 mm 230 m 55,650 12,799,500
dia. 65 mm 230 m 44,295 10,187,850

Instalasi Air Kotor


(Pipa PVC Class AW, class 10 K) air bekas
dia. 100 mm 329 m 93,780 30,853,620
dia. 150 mm 91 m 55,650 5,064,150

Pipa Vent PVC Class D Class 5 K


dia. 50 mm 45 m 32,100 1,444,500
dia. 40 mm 60 m 24,825 1,489,500
dia. 32 mm 132 m 22,688 2,994,750

Floor Drain (FD)


dia. 50 mm 32 bh 147,650 4,724,800
dia. 65 mm 6 bh 175,000 1,050,000
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
Clean out lantai (Co)
dia. 100 mm 4 bh 164,286 657,143
dia. 65 mm 22 bh 136,905 3,011,905

Fitting 1 lot 3,500,000 3,500,000

Material bantu 1 lot 2,000,000 2,000,000


.
Pengetesan 1 lot 2,500,000 2,500,000

116,408,003

VIII LANTAI EMPAT


Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 65 mm 20 mtr 164,260 3,285,200
dia. 50 mm 6 mtr 119,550 717,300
dia. 40 mm 65 mtr 87,345 5,677,425
dia. 25 mm 60 mtr 61,155 3,669,300
dia. 20 mm 60 mtr 42,881 2,572,875
dia. 15 mm 205 mtr 33,608 6,889,538

Gate Valve
dia. 65 mm 1 bh 485,587 485,587
dia. 40 mm 2 bh 465,476 930,952
dia. 25 mm 16 bh 156,603 2,505,642
dia. 15 mm 3 bh

Fitting 1 lot 2,738,095 2,738,095

Material bantu 1 lot 2,190,476 2,190,476

Instalasi Air Bekas


(Pipa PVC Class AW, class 10 K) air kotor
dia. 80 mm 230 m 55,650 12,799,500
dia. 65 mm 230 m 44,295 10,187,850

Instalasi Air Kotor


(Pipa PVC Class AW, class 10 K) air bekas
dia. 100 mm 329 m 93,780 30,853,620
dia. 150 mm 75 m 55,650 4,173,750

Pipa Vent PVC Class D Class 5 K


dia. 50 mm 45 m 32,100 1,444,500
dia. 40 mm 60 m 24,825 1,489,500
dia. 32 mm 132 m 22,688 2,994,750

Floor Drain (FD)


dia. 50 mm 32 bh 147,650 4,724,800
dia. 65 mm 6 bh 175,000 1,050,000

Clean out lantai (Co)


dia. 100 mm 29 bh 164,286 4,764,294
dia. 65 mm 31 bh 136,905 4,244,048

Fitting 1 lot 3,500,000 3,500,000

Material bantu 1 lot 2,000,000 2,000,000


.
Pengetesan 1 lot 2,500,000 2,500,000
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
118,389,002

IX LANTAI LIMA
(Pipa Galvanized Iron Medium Class)
dia. 32 mm 60 mtr 76,879 4,612,725
dia. 25 mm 75 mtr 61,155 4,586,625
dia. 20 mm 220 mtr 42,881 9,433,875
dia. 15 mm 245 mtr 33,608 8,233,838

Gate Valve
dia. 32 mm 16 bh 186,174 2,978,785

Fitting 1 lot 2,400,000 2,400,000

Material bantu 1 lot 1,250,000 1,250,000

INSTALASI AIR KOTOR, BEKAS DAN VENT


(Pipa PVC Class AW, class 10 K) air kotor
dia. 150 mm 6 m 197,710 1,186,260
dia. 100 mm 48 m 93,780 4,501,440
dia. 80 mm 6 m 55,650 333,900
dia. 65 mm 6 m 44,295 265,770
dia. 50 mm 6 m 33,384 200,304

(Pipa PVC Class AW, class 10 K) air bekas


dia. 150 mm 34 m 197,710 6,722,140
dia. 100 mm 25 m 93,780 2,344,500
dia. 80 mm 6 m 55,650 333,900
dia. 65 mm 25 m 44,295 1,107,375
dia. 50 mm 20 m 33,384 667,680

Pipa Vent PVC Class D Class 5 K


dia. 50 mm 6 m 32,100 192,600
dia. 40 mm 22 m 24,825 546,150
dia. 32 mm 21 m 22,688 476,438
dia. 50 mm 6 bh 147,650 885,900

Clean out lantai (Co)


dia. 100 mm 2 bh 164,286 328,571
dia. 50 mm 2 bh 136,905 273,810
Fitting 1 lot 2,000,000 2,000,000

Material bantu 1 lot 1,500,000 1,500,000

Pengetesan 1 lot 2,500,000 2,500,000

59,862,585
X Lantai - Atap
(Pipa Galvanized Iron Medium Class)
dia. 100 mm 12 mtr 279,145 3,349,740
dia. 80 mm 189 mtr 210,825 39,845,925
dia. 65 mm 16 mtr 164,260 2,628,160
dia. 50 mm 8 mtr 119,550 956,400
dia. 40 mm 3 mtr 87,345 262,035

Gate Valve
dia. 32 mm 1 bh 186,174 186,174
dia. 25 mm 28 bh 156,603 4,384,873

Fitting 1 lot 1,750,000 1,750,000

Material bantu 1 lot 1,500,000 1,500,000


HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.

INSTALASI AIR KOTOR, BEKAS DAN VENT

Lantai- Atap
dia. 150 mm 6 m 197,710 1,186,260
dia. 100 mm 48 m 93,780 4,501,440
dia. 80 mm 6 m 55,650 333,900
dia. 65 mm 6 m 44,295 265,770
dia. 50 mm 6 m 33,384 200,304

(Pipa PVC Class AW, class 10 K) Air bekas


dia. 150 mm 34 m 197,710 6,722,140
dia. 100 mm 6 m 93,780 562,680
dia. 80 mm 6 m 55,650 333,900
dia. 65 mm 6 m 44,295 265,770
dia. 50 mm 20 m 33,384 667,680

Pipa Vent PVC Class D Class 5 K


dia. 65 mm 6 m 44,295 265,770
dia. 50 mm 6 m 32,100 192,600
dia. 40 mm 6 m 24,825 148,950
dia. 32 mm 21 m 22,688 476,438

Floor Drain (FD)


dia. 50 mm 6 bh 147,650 885,900

Clean out lantai (Co)


dia. 100 mm 2 bh 164,286 328,571
dia. 50 mm 2 bh 136,905 273,810

Fitting 1 lot 1,350,000 1,350,000

Material bantu 1 lot 750,000 750,000

Pengetesan 1 lot 2,500,000 2,500,000

77,075,190

Instalasi Air Bersih


dia 80 mm ( supplay ke Roof Tank ) 70 mtr 210,825 14,757,750
dia 80 mm ( Gravitasi ke lt. B dan lt. 1 ) 70 mtr 210,825 14,757,750

Instalasi Air Kotor & Air Bekas


dia 150 mm 50 mtr 197,710 9,885,500
dia 100 mm 50 mtr 93,780 4,689,000

Instalasi Ventilasi
dia 80 mm 50 mtr 71,888 3,594,375

Testing commissioning 1 lot 7,500,000 7,500,000

55,184,375

VI. Instalasi Air Panas Sistem Water Heater


PERALATAN UTAMA
Pengadaan dan pemasangan matrial utama water
heater system Gas lengkap dengan matrial
Pendukung dan Accesoriesnya sehingga dapat
berpungsi dengan baik

Air Panas Sistem Electrical


HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
GWH (Gas Water Heater) di lantai Basement 2 unit 11,000,000 22,000,000
Model : 25V30-7P
ENERGY : LPG/Nat Gas
Heat Input : 30.000 BTUH
Capacity : 30 USG/114 Liter
Dray Weight : 44 Kg

Instalasi pipa air panas dari Water heater solar panel


ke Outlet. Menggunakan pipa PPR Type PN - 20

Lantai Basement
dia 15 mm 50 mtr 24,900 1,245,000
Ball Valve dia 15 mm 6 bh 175,000 1,050,000

Instalasi Air Panas Sistem Water Heater


PERALATAN UTAMA
Pengadaan dan pemasangan matrial utama water
heater system Electrical lengkap dengan matrial
Pendukung dan Accesoriesnya sehingga dapat
berpungsi dengan baik

Air Panas Sistem Electrical


EWH (Electric Water Heater) di lantai 2 2 unit 1,600,000 3,200,000
Kapasitas 50 Liter
Daya1500 Watt

Instalasi pipa air panas dari Water heater solar panel


ke Outlet. Menggunakan pipa PPR Type PN - 20
Lantai Dua
dia 15 mm 50 mtr 24,900 1,245,000
Ball Valve dia 15 mm 3 bh 175,000 525,000

PERALATAN UTAMA
Pengadaan dan pemasangan matrial utama water
heater system solar panel lengkap dengan matrial
Pendukung dan Accesoriesnya sehingga dapat
berpungsi dengan baik

Air Panas Sistem Solar Panel


SWH (Solar Water Heater) di lantai atap 13 unit 21,000,000 273,000,000
Kapasitas 300 Liter
Type 300 LXC
Daya 1500 Watt

Instalasi pipa air panas dari Water heater solar panel


ke Outlet. Menggunakan pipa PPR Type PN - 20

Lantai 1
dia 20 mm 17 mtr 38,900 661,300
dia 15 mm 33 mtr 24,900 821,700
Ball Valve dia 15 mm 1 bh 175,000 175,000

Lantai 2
dia 20 mm 22 mtr 38,900 855,800
dia 15 mm 65 mtr 24,900 1,618,500
Ball Valve dia 15 mm 2 bh 175,000 350,000

Lantai 3
dia 20 mm 22 mtr 38,900 855,800
dia 15 mm 90 mtr 24,900 2,241,000
Ball Valve dia 15 mm 3 bh 175,000 525,000
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.

Lantai 4
dia 20 mm 8 mtr 38,900 311,200
dia 15 mm 40 mtr 24,900 996,000
Ball Valve dia 15 mm 2 bh 175,000 350,000

Lantai 5
PPR dia 20 mm 136 mtr 38,900 5,290,400
dia 15 mm 320 mtr 24,900 7,968,000
Ball Valve dia 15 mm 8 bh 175,000 1,400,000

Lantai Atap
dia 25 mm 120 mtr 62,600 7,512,000
Ball Valve dia 25 mm 1 bh 225,000 225,000
Ball Valve dia 15 mm 13 bh 175,000 2,275,000

Material bantu 1 lot 3,000,000 3,000,000

Testing commissioning 1 lot 7,500,000 7,500,000

317,931,700

TOTAL 1,997,681,188
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM TATA UDARA

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

A. TATA UDARA LANTAI BASEMENT


1 Pengadaan dan Pemasangan peralatan utama AC & FAN
Lengkap dengan Instalasi pengkabelan, berikut -
Pipa Refrigran, Isolasi, Thermostat, hanger, suport,
vibration mounting, flexible joint,plenum box dan
accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - B.1,B.2,B.3, B.9 4 Unit 6,150,000 66,500,000


Lokasi :Rekam Medis, R.Dewasa, Lift Lobby
Kapasitas :12200 BTUH
Air flow :350 CFM
Daya :1120 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - B.4,B.7 B.8, B.11, B.12, B.14 6 Unit 4,950,000 29,700,000


Lokasi :Ruangan I, Work Shop, R.Kebidanan,
R. Anak, Bank
Kapasitas :8900 BTUH
Air flow :311 CFM
Daya :815 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - B.6, B.15, B.16, B.17 4 Unit 9,200,000 36,800,000


Lokasi :R.Dewasa,Gudang Apotik, Bank
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - B.13 1 Unit 4,500,000 4,500,000


Lokasi :KA
Kapasitas :4500 BTUH
Air flow :240 CFM
Daya :350 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

EF - B.1 1 Unit 2,200,000 2,200,000


Lokasi :R.pompa
Air flow :1000 CFM
Daya :150 WATT
Type :Wall Industrial
Power Suplai :3P/380V/50HZ

EF - B.2 1 Unit 5,000,000 5,000,000


Lokasi :Parkir Basement
Air flow :3000 CFM
Daya :350 WATT
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Type :Wall Industrial
Power Suplai :3P/380V/50HZ

EF - B.3 1 Unit 2,200,000 2,200,000


Lokasi Toilet
Air flow :1000 CFM
Daya :150 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

EF - B.4 1 Unit 5,000,000 5,000,000


Lokasi :Parkir Basement
Air flow :3000 CFM
Daya :350 WATT
Type :Wall Industrial
Power Suplai :3P/380V/50HZ

EF - B.5 1 Unit 5,000,000 5,000,000


Lokasi :Parkir Basement
Air flow :3000 CFM
Daya :350 WATT
Type :Wall Industrial
Power Suplai :3P/380V/50HZ

EF - B.6 1 Unit 5,000,000 5,000,000


Lokasi :Loundry
Air flow :3000 CFM
Daya :350 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

EF - B.7 1 Unit 700,000 700,000


Lokasi :Dapur
Air flow :200 CFM
Daya :150 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

EF - B.8 1 Unit 5,000,000 5,000,000


Lokasi :Parkir Basement
Air flow :3000 CFM
Daya :350 WATT
Type :Wall Industrial
Power Suplai :3P/380V/50HZ

EF - B.9 1 Unit 1,100,000 1,100,000


Lokasi :Gudang Apotik
Air flow :100 CFM
Daya :30 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ

EF - B.10 1 Unit 1,100,000 1,100,000


Lokasi :R Jenazah
Air flow :100 CFM
Daya :30 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ

EF - B.11 1 Unit 2,200,000 2,200,000


Lokasi Koridor
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Air flow :1000 CFM
Daya :150 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

IF - B.1 1 Unit 5,000,000 5,000,000


Lokasi :Loundry
Air flow :3000 CFM
Daya :350 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

IF - B.2 1 Unit 5,000,000 5,000,000


Lokasi Kitchen
Air flow :3000 CFM
Daya :350 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

IF - B.3 1 Unit 2,200,000 2,200,000


Lokasi Koridor
Air flow :1000 CFM
Daya :150 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

Grill Fan R Pompa ( EF=B.1) ukuran


500 x 500 1 Buah 450,000 450,000

Grill Fan Parkir Basement ( EF=B.2) ukuran


600 x 600 1 Buah 600,000 600,000

Ducting Exhaust Toilet ukuran


100 x 100 30 Meter 120,000 3,600,000
150 x 100 8 Meter 130,000 1,040,000
200 x 200 7 Meter 160,000 1,120,000
300 x 250 10 Meter 190,000 1,900,000
350 x 250 10 Meter 200,000 2,000,000
400 x 300 20 Meter 220,000 4,400,000
400 x 400 5 Meter 240,000 1,200,000

Exhaust Air Grill Toilet ukuran 250 x 250 8 Buah 105,000 840,000

Grill Fan Toilet (EF-B.3) ukuran 500 x 500 1 Buah 450,000 450,000

Ducting Intake Fan Kitchen ukuran 600 x 300 34 Meter 280,000 9,520,000

Grill Kitchen (IF=B.2) Hood ukuran 600 x 300 1 Buah 600,000 600,000

Suplay Air Grill Kitchen ukuran 500 x 250 4 Buah 400,000 1,600,000

Ducting Exhaust Fan Kitchen ukuran 600 x 300 58 Meter 280,000 16,240,000

Stove Hood Ukuran 5000 x 1500 2 Set 6,500,000 13,000,000

Grill Kitchen (EF=B.4) Hood ukuran 600 x 600 1 Buah 600,000 600,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

Grill Fan Parkir Basement ( EF=B.5) Hood ukuran 600 x 600 1 Buah 600,000 600,000

Ducting Intake Fan Loundry ukuran 34 Meter 280,000 9,520,000

Grill Loundry (IF=B.1) ukuran 600 x 300 1 Buah 600,000 600,000

Suplay Air Grill Loundry ukuran 500 x 250 3 Buah 400,000 1,200,000

Ducting Exhaust Fan Loundry ukuran 600 x 300 58 Meter 280,000 16,240,000

Suplay Air Grill Loundry ukuran 500 x 250 3 Buah 400,000 1,200,000

Grill Fan Loundry (EF=B.6) Hood ukuran 600 x 600 1 Buah 600,000 600,000

Ducting Exhaust Dapur ukuran 200 x 200 7 Meter 160,000 1,120,000

Exhaust Air Grill Dapur ukuran 300 x 300 2 Buah 105,000 210,000

Grill Fan Dapur (EF-B.7) Hood ukuran 500 x 500 1 Buah 450,000 450,000

Grill Fan Parkir Basement ( EF=B.8) Hood ukuran 600 x 600 1 Buah 600,000 600,000

Ducting Exhaust Gudang Apotik ukuran 200 x 200 9 Meter 160,000 1,440,000

Grill Fan Gudang Apotik (EF-B.9) ukuran 250 x 250 1 Buah 105,000 105,000

Ducting Exhaust R jenazah ukuran 200 x 200 9 Meter 160,000 1,440,000

Grill Fan R jenazah (EF-B.10) ukuran 250 x 250 1 Buah 105,000 105,000

Ducting Intake dan Exhaust Fan Koridor ukuran


250 x 250 16 Meter 180,000 2,880,000
300 x 250 16 Meter 190,000 3,040,000
300 x 300 16 Meter 200,000 3,200,000
350 x 300 16 Meter 220,000 3,520,000
350 x 350 16 Meter 220,000 3,520,000
400 x 400 42 Meter 240,000 10,080,000
Grill Fan Koridor (IF-B.3) ukuran
500 x 500 1 Buah 600,000 600,000
Suplay Air Grill Koridor ukuran
400 x 400 6 Buah 400,000 2,400,000
Grill Fan Koridor (EF-B.3) ukuran
500 x 500 1 Buah 600,000 600,000
Exhaust Air Grill Koridor ukuran
400 x 400 6 Buah 400,000 2,400,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW


lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan
accesoriesnya sehingga dapat berfungsi dengan baik

Diameter 3/4" 39 Meter 37,000 1,443,000


Diameter 1" 96 Meter 40,000 3,840,000
Riser Diameter 2" 16 Meter 75,000 1,200,000

Sub Total A 317,513,000

B TATA UDARA LANTAI 1 ( SATU )


1 Pengadaan dan Pemasangan peralatan utama AC & FAN
Lengkap dengan Instalasi pengkabelan, berikut -
Pipa Refrigran, Isolasi, Thermostat, hanger, suport,
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
vibration mounting, flexible joint,plenum box dan
accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 1.1,1.5,1.10, 1.11,1.12,1.13,1.14,1.16,1.21, 1.22, 20 Unit 4,750,000 95,000,000


1.23,1.24,1.25, 1.27,1.28,1.29,1.30,1.35,1.36,1.39
Lokasi :Play room, Nursery, USG, Dokter,
Kapasitas :6750 BTUH
Air flow :296 CFM
Daya :552 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 1.2,1.3,1.4 1.6, 1.7,1.8, 1.17,1.18,1.3.7, 1.4.4,1.4.5,1.4.6 12 Unit 4,500,000 54,000,000


Lokasi :Alat, KA, Panoramic, Dokter, KA Lab,
:Sperma
Kapasitas :4500 BTUH
Air flow :240 CFM
Daya :350 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 1.9,1.15,1.26,1.38, 1.62, 1.63, 1.64 7 Unit 4,950,000 34,650,000


Lokasi :R.Tunggu Exutive, Locket, Rawat jalan,
:Pendaptaran, Bank
Kapasitas :8900 BTUH
Air flow :311 CFM
Daya :815 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 1.19,1.20,1.40,1.41,1.42,1.43, 1.60, 1.61 8 Unit 9,200,000 73,600,000


Lokasi :Racik, KA, IGD,
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 1.31,1.32,1.33,1.34,1.47,1.51, 1.65 7 Unit 6,150,000 43,050,000


Lokasi :Rontgen, CT Scan, Lab, Minimarket
Kapasitas :12200 BTUH
Air flow :350 CFM
Daya :1120 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 1.52 1 Unit 42,000,000 42,000,000


Lokasi :Ruang tunggu Poliklinik
Kapasitas :90 000 BTUH
Air flow : CFM
Daya :9650 WATT
Type :Split Duct
Power Suplai :3P/380V/50HZ

IU/OU - 1.53 1 Unit 9,200,000 9,200,000


Lokasi :Ruang tunggu
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

IU/OU - 1.54 1 Unit 9,200,000 9,200,000


Lokasi :Ruang tunggu
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 1.55 1 Unit 4,750,000 4,750,000


Lokasi :Poli Umum
Kapasitas :6750 BTUH
Air flow :296 CFM
Daya :552 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 1.56 1 Unit 39,000,000 39,000,000


Lokasi :Ruang tunggu, Koridor
Kapasitas :774 00 BTUH
Air flow : CFM
Daya :6500 WATT
Type :Split Duct
Power Suplai :3P/380V/50HZ

IU/OU - 1.57 1 Unit 46,500,000 46,500,000


Lokasi :Koridor, Food Court
Kapasitas :115 000 BTUH
Air flow : CFM
Daya :9 800 WATT
Type :Split Duct
Power Suplai :3P/380V/50HZ

IU/OU - 1.58 1 Unit 48,000,000 48,000,000


Lokasi :Lift Lobby
Kapasitas :126 000 BTUH
Air flow : CFM
Daya :10 000 WATT
Type :Split Duct
Power Suplai :3P/380V/50HZ

IU/OU - 1.59 1 Unit 46,500,000 46,500,000


Lokasi :Ruang tunggu
Kapasitas :116 000 BTUH
Air flow : CFM
Daya :9 800 WATT
Type :Split Duct
Power Suplai :3P/380V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

EF - 1.1 1 Unit 1,100,000 1,100,000


Lokasi :Toilet Poli
Air flow :100 CFM
Daya :30 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
EF - 1.2 1 Unit 1,400,000 1,400,000
Lokasi :Toilet Publik
Air flow :700 CFM
Daya :100 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

EF - 1.3 1 Unit 1,100,000 1,100,000


Lokasi :R Gelap
Air flow :100 CFM
Daya :30 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ

EF - 1.4 dan EF 1.5 2 Unit 1,100,000 2,200,000


Lokasi :R Racik Apotik
Air flow :100 CFM
Daya :30 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ

EF - 1.6 dan 1.7 1 Unit 1,100,000 1,100,000


Lokasi :Wastafel Lab
Air flow :100 CFM
Daya :30 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ

EF - 1.8 1 Unit 1,300,000 1,300,000


Lokasi :Micro Biologi
Air flow :200 CFM
Daya :30 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ

3 Pengadaan dan Pemasangan Ducting AC Split Duct fan leng


kap berikut isolasi, hanger, suport, vibration mounting, plexible
joint,plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

Flexible Duct c/w Isolasi dia 200 mm 35 Meter 95,000 3,325,000


200 x 200 bjls 50 80 Meter 148,000 11,840,000
250 x 200 bjls 50 30 Meter 185,000 5,550,000
250 x 250 bjls 50 40 Meter 231,000 9,240,000
300 x 250 bjls 50 16 Meter 277,000 4,432,000
300 x 300 bjls 50 22 Meter 333,000 7,326,000
350 x 300 bjls 50 7 Meter 388,000 2,716,000

SAD 250 x 250 34 Buah 147,500 5,015,000


RAG 250 x 250 15 Buah 105,000 1,575,000
FAG 250 x 250 5 Buah 165,000 825,000
Plenum Box 5 Set 200,000 1,000,000

4 Pengadaan dan Pemasangan Ducting exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.
Ducting Exhaust Toilet Poli (EF-1.1) ukuran
100 x 100 12 Meter 110,000 1,320,000

Ducting Exhaust Toilet Publik (EF-1.2) ukuran


H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
100 x 100 51 Meter 110,000 5,610,000
150 x 100 15 Meter 130,000 1,950,000
200 x 200 2 Meter 160,000 320,000
300 x 300 3 Meter 200,000 600,000

Ducting Exhaust R Gelap (EF-1.3) ukuran


100 x 100 3 Meter 110,000 330,000

Ducting Exhaust R Racik (EF-1.4dan EF-1.5) ukuran


200 x 200 26 Meter 160,000 4,160,000

Ducting Exhaust Wastafel Lab (EF-1.6) ukuran


PVC Type D 100 22 Meter 25,000 550,000

Ducting Exhaust R Lab (EF-1.7) ukuran


PVC Type D 100 20 Meter 25,000 500,000

Ducting Exhaust Micro Biologi (EF-1.7) ukuran


PVC Type D 150 15 Meter 30,000 450,000

Exhaust Air Grill Toilet Publik ukuran


250 x 250 11 Buah 105,000 1,155,000
Grill fan Toilet Poli (EF-1.1) ukuran
250 x 250 1 Buah 105,000 105,000
Grill fan Toilet Publik (EF-1.2) ukuran
300 x 300 1 Buah 180,000 180,000
Grill fan R Gelap (EF-1.3) ukuran
250 x 250 1 Buah 105,000 105,000
Grill fan R Racik (EF-1.4 dan EF- 1.5) ukuran
300 x 300 1 Buah 180,000 180,000
Grill fan Wastafel Lab (EF-1.6) ukuran
250 x 250 1 Buah 105,000 105,000
Grill fan R Lab (EF-1.7) ukuran
250 x 250 1 Buah 105,000 105,000
Grill fan Micro Biologi (EF-1.8) ukuran
300 x 300 1 Buah 180,000 180,000

5 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW


lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan
accesoriesnya sehingga dapat berpungsi dengan baik
Diameter 3/4" 320 Meter 37,000 11,840,000
Diameter 1" 112 Meter 40,000 4,480,000
Diameter 2" 90 Meter 75,000 6,750,000

Sub Total B 647,469,000

C TATA UDARA LANTAI 2 ( DUA )


1 Pengadaan dan Pemasangan peralatan utama AC & FAN
Lengkap dengan Instalasi pengkabelan, berikut -
Pipa Refrigran, Isolasi, Thermostat, hanger, suport,
vibration mounting, flexible joint,plenum box dan
accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 2.1, 2.3, 2.6 3 Unit 9,200,000 27,600,000


Lokasi :OK1, OK2, OK3 (Plasma Cluster)
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :PLASMA CLUSTER
Power Suplai :1P/220V/50HZ

IU/OU - 2.7, 2.10, 2.18, 2.19, 2.24, 2.25, 2.32, 2.33, 2.34 10 Unit 9,200,000 92,000,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
2.36
Lokasi :Resulasi,RR, Keuangan, PT, Hemodialisa,
NS, Meeteng Room 2
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 2.8,2.9,2.17,2.31,2.32 4 Unit 6,150,000 24,600,000


Lokasi :Dirut, Fisio terafi, Meeting
:room 1, SPI
Kapasitas :12200 BTUH
Air flow :350 CFM
Daya :1120 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 2.11,2.12,2.16, 2.21,2.22,2.23,2.28,2.29,2.36 9 Unit 4,750,000 42,750,000


Lokasi :RR, NS, Meeting, EDP, SDM, Scre
:tary, Dokter, KA, RO
Kapasitas :6750 BTUH
Air flow :296 CFM
Daya :552 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 2.13,2.14,2,15, 2.20, 2.26,2.30 6 Unit 4,950,000 29,700,000


Lokasi :ODC, Dokter,R.Tunggu OK, Keuangan
Kapasitas :8900 BTUH
Air flow :311 CFM
Daya :815 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

EF - 2.1 1 Unit 2,200,000 2,200,000


Lokasi :OK1, OK2, OK3
Air flow :1000 CFM
Daya :150 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

EF - 2.2 1 Unit 1,300,000 1,300,000


Lokasi Toilet
Air flow :250 CFM
Daya :100 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

EF - 2.3 1 Unit 1,100,000 1,100,000


Lokasi :Toilet
Air flow :100 CFM
Daya :30 WATT
Type :Axial
Power Suplai :1P/220V/50HZ
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
EF - 2.4 1 Unit 2,200,000 2,200,000
Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

EF - 2.5 1 Unit 1,100,000 1,100,000


Lokasi :Hemodialisa
Air flow :100 CFM
Daya :30 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

EF - 2.6 1 Unit 1,100,000 1,100,000


Lokasi :Hempdialisa
Air flow :100 CFM
Daya :30 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

EF - 2.7 1 Unit 1,100,000 1,100,000


Lokasi :Alat
Air flow :100 CFM
Daya :30 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

IF - 2.1 1 Unit 2,200,000 2,200,000


Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

Exhaust Air Grill OK1, OK2, OK3 ukuran


400 x 400 3 Buah 400,000 1,200,000
Grill fan (EF-2.1) OK1, OK2, OK3) ukuran
400 x 400 1 Buah 400,000 400,000
Filter 3 Set 2,000,000 6,000,000

Ducting Exhaust Fan Toilet ukuran


100 x 100 36 Meter 110,000 3,960,000
150 x 150 15 Meter 130,000 1,950,000
200 x 200 12 Meter 160,000 1,920,000

Ducting Exhaust Fan OK ukuran


300 x 200 20 Meter 130,000 2,600,000
300 x300 10 Meter 160,000 1,600,000

Exhaust Air Grill Toilet Publik ukuran


250 x 250 6 Buah 105,000 630,000
Grill fan (EF-2.2) Toilet Publik ukuran
300 x 300 1 Buah 105,000 105,000
Grill fan (EF-2.3) Toilet Hemodilisa ukuran
250 x 250 1 Buah 105,000 105,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Ducting Exhaust (EF-2.5 dan EF-2.6) Hemodialisa ukuran
100 x 100 8 Meter 110,000 880,000

Grill fan (EF-2.5 dan EF-2.6) Hemodialisa ukuran


250 x 250 2 Buah 105,000 210,000

Ducting Intake dan Exhaust Fan Koridor ukuran


250 x 250 20 Meter 180,000 3,600,000
300 x 250 20 Meter 190,000 3,800,000
300 x 300 20 Meter 200,000 4,000,000
350 x 300 20 Meter 210,000 4,200,000
350 x 350 20 Meter 220,000 4,400,000
400 x 350 20 Meter 230,000 4,600,000
400 x 400 40 Meter 240,000 9,600,000
Grill Fan Koridor (IF=2.1) ukuran
500 x 500 1 Buah 600,000 600,000
Suplay Air Grill Koridor ukuran
400 x 400 7 Buah 400,000 2,800,000
Grill Fan Koridor (EF=2.4) ukuran
500 x 500 1 Buah 600,000 600,000
Return Air Grill Koridor ukuran
400 x 400 6 Buah 400,000 2,400,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW


lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan
accesoriesnya sehingga dapat berpungsi dengan baik
Diameter 3/4" 328 Meter 37,000 12,136,000
Diameter 2" 80 Meter 75,000 6,000,000

Sub Total C 309,246,000

D TATA UDARA LANTAI 3 ( TIGA )


1 Pengadaan dan Pemasangan peralatan utama AC & FAN
Lengkap dengan Instalasi pengkabelan, berikut -
Pipa Refrigran, Isolasi, Thermostat, hanger, suport,
vibration mounting, flexible joint,plenum box dan
accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 3.1,3.5,3.13,3.17,3.20,3.21,3.22,3.24,3.26, 3.29,3.30 11 Unit 4,750,000 52,250,000


Lokasi :Dokter, Isolasi, Karu, menyusui, mandi
:bayi, kala
Kapasitas :6750 BTUH
Air flow :296 CFM
Daya :552 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 3.2, 3.6, 3.15, 3.16, 3.18,3.25,3.28, 3.31, 3.33 9 Unit 4,950,000 44,550,000
Lokasi :ICU VIP, R tunggu VK, NICU, Kala,
:Lounge, Preinatologi, Nurse
(OK, VK pakai AC Plasma Cluster)
Kapasitas :8900 BTUH
Air flow :311 CFM
Daya :815 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 3.6, 3.7,3.8,3.9,3.10,3.11,3.12, 3.19, 13 Unit 4,150,000 53,950,000


3.27,3.34,3.35,3.36,3.37,3.38
Lokasi :Kelas I, II, III, VTP, NICU, Primatologi
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
:Kala, Bayi VIP,
Kapasitas :12200 BTUH
Air flow :350 CFM
Daya :1120 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 3.14,3.23, 3.32, 3.33, 3.34, 3.39 6 Unit 9,200,000 55,200,000


Lokasi :High Care, VK, Bayi, TCU
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

2
berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

EF -.3.1 1 Unit 2,200,000 2,200,000


Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

EF - 3.2 s/d EF-3.21 20 Unit 1,100,000 22,000,000


Lokasi :Toilet
Air flow :100 CFM
Daya :30 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

IF - 3.1 1 Unit 2,200,000 2,200,000


Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

CF - 3.1 1 Unit 700,000 700,000


Lokasi :Mushola
Air flow :200 CFM
Daya :100 WATT
Type :Ceilling
Power Suplai :1P/220V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.
Ducting Exhaust Toilet ukuran
100 x 100 82 Meter 110,000 9,020,000

Ducting Intake dan Exhaust Fan Koridor ukuran


250 x 250 32 Meter 180,000 5,760,000
300 x 250 32 Meter 190,000 6,080,000
300 x 300 32 Meter 200,000 6,400,000
350 x 300 32 Meter 220,000 7,040,000
400 x 400 20 Meter 240,000 4,800,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Grill Fan Koridor (IF=3.1) ukuran
500 x 500 1 Buah 600,000 600,000
Suplay Air Grill Koridor ukuran
400 x 400 8 Buah 400,000 3,200,000
Grill Fan Koridor (EF=3.1) ukuran
500 x 500 1 Buah 600,000 600,000
Return Air Grill Koridor ukuran
400 x 400 9 Buah 400,000 3,600,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW


lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan
accesoriesnya sehingga dapat berfungsi dengan baik
Diameter 3/4" 280 Meter 37,000 10,360,000
Diameter 1" 10 Meter 40,000 400,000
Diameter 2" 80 Meter 75,000 6,000,000

Sub Total D 296,910,000

E TATA UDARA LANTAI 4 ( EMPAT )


1 Pengadaan dan Pemasangan peralatan utama AC & FAN
Lengkap dengan Instalasi pengkabelan, berikut -
Pipa Refrigran, Isolasi, Thermostat, hanger, suport,
vibration mounting, flexible joint,plenum box dan
accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 4.1,4.2,4.8,4.9,4.25, 5 Unit 9,200,000 46,000,000


Lokasi :Kelas III, Rtunggu,
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 4.3,4.4,4.5,4.6,4.7,4.10,4.11,4.12,4.13,4.14,4.15, 23 Unit 6,150,000 141,450,000


4.16,4.17,4.18,4.19,4.23,4.24,4.27,4.28,4.29,4.30
4.31,4.34
Lokasi :Kelas II, Nurse
Kapasitas :12200 BTUH
Air flow :350 CFM
Daya :1120 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 4.20,4.21,4.32,4.33,4.36 5 Unit 4,750,000 23,750,000


Lokasi :Observasi, Karu, Kelas II, obat, Kon
sultasi
Kapasitas :6750 BTUH
Air flow :296 CFM
Daya :552 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 4.22 1 Unit 4,950,000 4,950,000


Lokasi :Nurse
Kapasitas :8900 BTUH
Air flow :311 CFM
Daya :815 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
2 Pengadaan dan Pemasangan exhaust fan lengkap
berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

EF -.4.1 1 Unit 2,200,000 2,200,000


Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

EF - 4.2 s/d EF-4.30 29 Unit 1,100,000 31,900,000


Lokasi :Toilet
Air flow :100 CFM
Daya :30 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

IF - 4.1 1 Unit 2,200,000 2,200,000


Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.
Ducting Exhaust Toilet ukuran
100 x 100 75 Meter 110,000 8,250,000

Ducting Exhaust Toilet (Riser) ukuran


300 x 300 108 Meter 200,000 21,600,000

Ducting Intake dan Exhaust Fan Koridor ukuran


250 x 250 16 Meter 180,000 2,880,000
300 x 250 16 Meter 190,000 3,040,000
300 x 300 16 Meter 200,000 3,200,000
350 x 300 16 Meter 220,000 3,520,000
350 x 350 16 Meter 220,000 3,520,000
400 x 350 16 Meter 230,000 3,680,000
400 x 400 16 Meter 240,000 3,840,000
450 x 400 16 Meter 250,000 4,000,000
Grill Fan Koridor (IF=4.1) ukuran
500 x 500 1 Buah 600,000 600,000
Suplay Air Grill Koridor ukuran
400 x 400 9 Buah 400,000 3,600,000
Grill Fan Koridor (EF=4.1) ukuran
500 x 500 1 Buah 600,000 600,000
Return Air Grill Koridor ukuran
400 x 400 8 Buah 400,000 3,200,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW


lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan
accesoriesnya sehingga dapat berpungsi dengan baik
Diameter 3/4" 260 Meter 37,000 9,620,000
Diameter 1" 4 Meter 40,000 160,000
Diameter 2" 80 Meter 75,000 6,000,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Sub Total E 333,760,000

F TATA UDARA LANTAI 5 ( LIMA )


1 Pengadaan dan Pemasangan peralatan utama AC & FAN
Lengkap dengan Instalasi pengkabelan, berikut -
Pipa Refrigran, Isolasi, Thermostat, hanger, suport,
vibration mounting, flexible joint,plenum box dan
accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - 5.1,5.2,5.3,5.4,5.5,5.6,5.7,5.8,5.9,5.10,5.11,5.12, 33 Unit 6,150,000 202,950,000


5.13,5.14,5.15,5.16,5.17,5.18,5.19,5.20,5.21,5.22,
5.23,5.24,5.25,5.26,5.27,5.28,5.29,5.30,5.31,
5.32,5.36
Lokasi :VIP, R TUNGGU,Kelas I, Obat, NS
Kapasitas :12200 BTUH
Air flow :350 CFM
Daya :1120 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

IU/OU - 5.33,5.34,5.37 3 Unit 4,750,000 14,250,000


Lokasi :Konsultasi, Karu,
:sultasi
Kapasitas :6750 BTUH
Air flow :296 CFM
Daya :552 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.

EF -.5.1 1 Unit 2,200,000 2,200,000


Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

EF - 5.2 s/d EF-5.33 32 Unit 1,100,000 35,200,000


Lokasi :Toilet
Air flow :100 CFM
Daya :30 WATT
Type :Axial
Power Suplai :1P/220V/50HZ

IF - 5.1 1 Unit 2,200,000 2,200,000


Lokasi :Koridor
Air flow :1000 CFM
Daya :250 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting exhaust fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.
Ducting Exhaust Toilet ukuran
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
100 x 100 92 Meter 110,000 10,120,000

Ducting Exhaust Toilet (Riser) ukuran


300 x 300 120 Meter 200,000 24,000,000

Ducting Intake Fan Koridor ukuran


250 x 250 16 Meter 180,000 2,880,000
300 x 250 16 Meter 190,000 3,040,000
300 x 300 16 Meter 200,000 3,200,000
350 x 300 16 Meter 220,000 3,520,000
350 x 350 16 Meter 220,000 3,520,000
400 x 350 16 Meter 230,000 3,680,000
400 x 400 16 Meter 240,000 3,840,000
450 x 400 16 Meter 250,000 4,000,000
Grill Fan Koridor (IF=5.1) ukuran
500 x 500 1 Buah 600,000 600,000
Suplay Air Grill Koridor ukuran
400 x 400 9 Buah 400,000 3,600,000
Grill Fan Koridor (EF=5.1) ukuran
500 x 500 1 Buah 600,000 600,000
Return Air Grill Koridor ukuran
400 x 400 8 Buah 400,000 3,200,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW


lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan
accesoriesnya sehingga dapat berpungsi dengan baik
Diameter 3/4" 250 Meter 37,000 9,250,000
Diameter 1" 8 Meter 40,000 320,000
Diameter 2" 80 Meter 75,000 6,000,000

Sub Total F 342,170,000

G TATA UDARA LANTAI A ( ATAP )


1 Pengadaan dan Pemasangan peralatan utama AC & FAN
Lengkap dengan Instalasi pengkabelan, berikut -
Pipa Refrigran, Isolasi, Thermostat, hanger, suport,
vibration mounting, flexible joint,plenum box dan
accesoriesnya.sehingga dapat berpungsi dengan baik

IU/OU - A.01,A.02,A.03 3 Unit 4,950,000 14,850,000


Lokasi :R mesin Lift
Kapasitas :8900 BTUH
Air flow :311 CFM
Daya :815 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ

2 Pengadaan dan Pemasangan Presh Air fan lengkap


berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berfungsi
dengan baik.(Interpace to Fire Alarm)

PAF - A..1 1 Unit 14,000,000 14,000,000


Lokasi :Lantai Tangga kebakaran
Air flow :11000 CFM
Daya :3000 WATT
Type :Axial
Power Suplai :3P/380V/50HZ

3 Pengadaan dan Pemasangan Ducting/Hood PAF lengkap


berikut hanger, suport, vibration mounting, flexible joint,
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
plenum box dan accesoriesnya sehingga dapat berfungsi
dengan baik.

Ducting Presh air fan ukuran


800 x 800 4 Meter 440,000 1,760,000
Presh air fan grill
800 x 800 2 Buah 480,000 960,000

4 Pengadaan dan Pemasangan Pipa Drain AC, PVC Class AW


lengkap berikut Isolasi Class 1 APDM tebal 1,3mm dan
accesoriesnya sehingga dapat berpungsi dengan baik
Diameter 3/4" 12 Meter 37,000 444,000

5 Grill tangga kebakaran 600 x 300 6 Buah 400,000 2,400,000

Sub Total G 34,414,000

H TATA UDARA R. GENSET DAN TRAFO


1 Pengadaan dan Pemasangan peralatan utama FAN
Lengkap dengan Instalasi pengkabelan, berikut -
accesoriesnya.sehingga dapat berpungsi dengan baik

EF - G.1/ EF - G.2 2 Unit 3,800,000 7,600,000


Lokasi :R. Genset
Air flow :2000 CFM
Daya :250 WATT
Type :Wall Industrial
Power Suplai :3P/380V/50HZ

EF - T1 1 Unit 4,800,000 4,800,000


Lokasi :R. Trafo
Air flow :7000 CFM
Daya :700 WATT
Type :Wall Industrial
Power Suplai :3P/380V/50HZ

Sub Total H 12,400,000

Total A - H 2,293,882,000
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM PEMADAM KEBAKARAN

HARGA SATUAN JUMLAH HARGA


No Uraian QTY SAT
Rp. Rp.

Pekerjaan Pemadam Kebakaran

1 Pekerjaan Equipment Utama

1.1 Pompa Elektrik Hydrant (Ruang pompa lt, B ) 1 unit 104,000,000 104,000,000
- Kapasitas : 500 GPM
- Head : 100 meter
- Put : 2900 Rpm
- Type : splite case
- Operation : start automatik,
stop manual

1.2 Pompa Diesel Hydrant (Ruang pompa lt, B ) 1 unit 200,000,000 200,000,000
- Kapasitas : 500 GPM
- Head : 100 meter
- Put : 2900 Rpm
- Type : splite case
- Operation : start automatik,

1.3 Pompa Jokey (Ruang pompa lt, B ) 1 unit 25,794,500 25,794,500


- Kapasitas : 25 GPM
- Head : 100 meter
- Put : 2900 Rpm
- Type : Vertikal
- Operation : start/stop automatik

1.4 Panel Kontrol Pompa Kebakaran Mengacu ke 3 set INCLUDE


Standard NFPA
- Lengkap dengan Pressure tank dan acce
sories Dan dapat interface dengan MCFA

1.5 Assesories instalasi pompa


Material Bantu 1 lot 12,500,000 12,500,000
Termasuk pondasi pompa, support,hangger,
Vibration mounting , dan tanki solar harian -
kap200 ltr , berikut instalasinya + pengecatan

sub total 1

2 Instalasi Pemadam Kebakaran


di Ruang Pompa

2.1 Pengadaan dan pemasangan Pipa Black Steel


Sch 40 (ASTM A53) berikut Support, penge
catan Blind Flange dan Accessories

Header dia. 200 mm termasuk support, 2 set 7,352,500 14,705,000


blind flanges fitting weldolet,air realease dia
25 mm2dan pengecatan.
Pipa dia. 150 mm 54 m 781,128 42,180,912
Pipa dia. 100 mm 30 m 470,400 14,112,000
Pipa dia. 50 mm 30 m 185,400 5,562,000
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
Knalpot pipa dia 80 mm 75 m 375,000 28,125,000
termasuk isolasi panas (asbes type) dan diberi
metal Jakecting

2.2 Assesories
- Gate valve
Dia. 150 mm 10 bh 10,459,980 104,599,800
Dia. 50 mm 2 bh 824,380 1,648,760

- Check valve
Dia. 150 mm 2 bh 6,940,020 13,880,040
Dia. 50 mm 1 bh 631,060 631,060

- Fleksible joint
Dia. 150 mm 4 bh 1,927,500 7,710,000
Dia. 50 mm 2 bh 533,800 1,067,600

- Strainer
Dia. 150 mm 2 bh 6,070,620 12,141,240
dia. 50 mm 1 bh 639,940 639,940

- Foot Valve ( lihat diimeter pipa


pompa)
Dia. 150 mm 2 bh 3,421,140 6,842,280
dia. 50 mm 1 bh 2,165,740 2,165,740

- Flow meter dia 150 mm 1 bh 21,156,250 21,156,250

- Pressure Gauge 3 bh 211,250 633,750


- Pressure Switch 3 bh 2,131,250 6,393,750

2.3 - Main Control Valve (MCV) dia. 150 mm 1 set 55,875,000 55,875,000
c/w Alarm gong, dan acesoriesnya

Pressure Reducing Valve (PRV) dia 150 mm 1 set 46,815,000 46,815,000


c/w stainer, valve , presurre gauge dan pemi
paan

2.4 Safety Valve dia 150 mm 1 bh 21,156,550 21,156,550

2.5 FE 10 kg (gas) 1 bh 5,282,000 5,282,000

2.6 Fiting- fitting 1 lot 16,562,500 16,562,500

2.7 Material bantu termasuk pengecatan 1 lot 6,625,000 6,625,000

2.8 Pengetesan 1 lot 9,375,000 9,375,000

sub total 2 445,886,172

3 Instalasi Pipa Kebakaran


(Dari R Pompa dan dalam Shaft)

3.1 Instalasi Pipa Hydrant dan Sprinkler


dalam Shaft s/d Lantai Atap
Pengadaan dan pemasangan Pipa Black Steel
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
Sch 40 (ASTM A53) berikut Support
dia. 150 mm 90 m 799,120 71,920,764
air realease valve dia 40mm dan Accessories 2 bh 1,831,250 3,662,500

3.2 Fitting- fiting 1 lot 16,875,000 16,875,000

3.3 Material bantu 1 lot 6,937,500 6,937,500


Termasuk suport pipa tegak, klem pipa dan
pengecatan.

3.4 Pengetesan 1 lot 3,125,000 3,125,000

sub total 3 102,520,764

4 Instalasi Pipa Kebakaran


di Site Plan
Sprinkler
4.1 Instalasi pemadam kebakaran
Pengadaan dan pemasangan Pipa Black Steel
Sch 40 (ASTM A53) berikut Support
Isolasi pipa dalam tanah (Wrapping) &
Primer Coating dan Accessories
dan Accessories
dia. 150 mm 437 meter 781,128 341,196,710
dia. 100 mm 40 meter 471,360 18,972,240

Galian Tanah 477 meter 20,000 9,541,000

4.2 Gate valve


dia. 100 mm 5 bh 6,322,160 31,610,800

4.3 Check valve


dia. 150 mm 1 bh 6,940,020 6,940,020
4.5 Siamisse conection 1 bh 3,073,500 3,073,500
4.6 Outdoor hyhdrant Pilar c/w Box 6 bh 3,242,410 19,454,460
Pilar Hidrand 6 bh 3,024,250 18,145,500
4.7 Fitting- fiting 1 lot 18,125,000 18,125,000
4.8 Material Bantu termasuk bak kontrol
pondasi siamesse dan pilar hydrant 1 lot 6,750,000 6,750,000

4.9 Pengetesan 1 lot 6,250,000 6,250,000

sub total 4 480,059,230

5 Instalasi Pemadam Kebakaran


Lantai Basement

5.1 Instalasi Sprinkler


1 Head sprinkler 291 ttk 60,375 17,569,125
2 Branch Control Valve dia 100 " 1 bh 9,334,000 9,334,000
lengkap dengan pressure gauge
3 Flow Switch dia. 80 mm 1 bh 1,171,250 1,171,250
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 3 bh 308,500 925,500
5 Sight Glass dia. 25 mm 1 bh 931,250 931,250
Pressure Gauge 1 bh 241,250 241,250
7 Pengadaan dan pemasangan Pipa Black Steel
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
6 Sch 40 (ASTM A53) berikut Support
dan Accessories
dia. 150 mm 69 m 799,128 55,139,832
dia. 100 mm 178 m 470,400 83,543,040
dia. 80 mm 46 m 343,704 15,810,384
dia. 65 mm 20 m 258,240 5,164,800
dia. 50 mm 66 m 186,000 12,276,000
dia. 40 mm 288 m 132,138 38,055,744
dia. 32 mm 242 m 117,030 28,262,745
dia. 25 mm 522 m 88,728 46,316,016

5.2 Instalasi Hydrant


1 Indoor hydrant box lenkap dengan 2 bh 3,770,410 7,540,820

2 Pemadam Api Ringan (PAR)


FE 2 KG (Klas ABC) 2 bh 1,218,750 2,437,500

3 Pengadaan dan pemasangan Pipa Black Steel


Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan
dia. 150 mm 72 m 799,128 57,137,652
dia. 100 mm 125 m 471,360 58,920,000
dia. 80 mm 33 m 343,704 11,342,232

4 Gate valve

dia. 100 mm 1 bh 6,322,160 6,322,160


dia. 65 mm 5 bh 4,399,590 21,997,950

5 Fitting- fiting 1 lot 21,087,500 21,087,500

6 Material Bantu 1 lot 7,237,500 7,237,500

sub total 5 515,086,410

8 Instalasi Pemadam Kebakaran


Lantai Satu

8.1 Instalasi Sprinkler


1 Head sprinkler 165 ttk 60,375 9,961,875
2 Branch Control Valve dia 100mm 1 bh 9,334,000 9,334,000
lengkap dengan pressure gauge
3 Flow Switch dia. 100 mm 1 bh 1,171,250 1,171,250
4 Gate valve
dia. 150 mm 1 bh 10,459,980 10,459,980
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 3 bh 308,500 925,500
5 Sight Glass dia. 25 mm 2 bh 931,250 1,862,500
Pressure Gauge 1 bh 241,250 241,250

Pengadaan dan pemasangan Pipa Black Steel


Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan

dia. 100 mm 16 m 470,400 7,526,400


dia. 80 mm 28 m 341,904 9,573,312
dia. 65 mm 46 m 258,240 11,879,040
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
dia. 50 mm 55 m 186,000 10,230,000
dia. 40 mm 90 m 132,138 11,892,420
dia. 32 mm 120 m 117,030 14,043,600
dia. 25 mm 588 m 88,728 52,172,064

8.2 Instalasi Hydrant


1 Indoor hidran box 2 bh 3,770,410 7,540,820

2 Pemadam Api Ringan (PAR)


FE 2 KG (Klas ABC) 3 bh 1,218,750 3,656,250

3 Pengadaan dan pemasangan Pipa Black Steel


Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan

dia. 100 mm 16 m 471,360 7,541,760


dia. 80 mm 55 m 343,704 18,903,720
dia. 65 mm 8 m 258,240 2,065,920

4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 2 bh 4,399,590 8,799,180

5 Fitting- fiting 1 lot 23,912,500 23,912,500

6 Material Bantu 1 lot 9,937,500 9,937,500

sub total 8( lantai Satu ) 246,275,161

11 Instalasi Pemadam Kebakaran


Lantai 2 ( dua )

11.1 Instalasi Sprinkler


1 Head sprinkler 125 ttk 60,375 7,546,875
2 Branch Control Valve dia 100mm 1 bh 9,334,000 9,334,000
lengkap dengan pressure gauge
3 Flow Switch dia. 100 mm 1 bh 1,171,250 1,171,250
Sight Glass dia. 25 mm 1 bh 931,250 931,250
Pressure Gauge 1 bh 241,250 241,250

4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 4 bh 308,500 1,234,000

5 Pengadaan dan pemasangan Pipa Black Steel


Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan

dia. 100 mm 18 mtr 471,360 8,484,480


dia. 80 mm 12 mtr 343,704 4,124,448
dia. 65 mm 42 mtr 258,240 10,846,080
dia. 50 mm 78 mtr 185,400 14,461,200
dia. 40 mm 82 mtr 139,338 11,425,716
dia. 32 mm 136 mtr 117,030 15,916,080
dia. 25 mm 595 mtr 88,728 52,810,906

11.2 Instalasi Hydrant


1 Indoor hidrant box 2 bh 3,770,410 7,540,820
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.

2 Pemadam Api Ringan (PAR)


FE 5 KG (Klas ABC) 3 bh 1,218,750 3,656,250
FE 10 KG (Gas) 1 bh 5,521,850 5,521,850
3 Pengadaan dan pemasangan Pipa Black Steel
Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan
dia. 100 mm 14 m 470,400 6,585,600
dia. 80 mm 45 m 343,704 15,466,680
dia. 65 mm 8 m 258,240 2,065,920

4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 2 bh 4,399,590 8,799,180

5 Fitting- fiting 1 lot 22,923,500 22,923,500

6 Material Bantu 1 lot 23,328,000 23,328,000

sub total 11 (lantai tiga ) 247,059,655

12 Instalasi Pemadam Kebakaran


Lantai 3 ( tiga )

12.1 Instalasi Sprinkler


1 Head sprinkler 94 ttk 60,375 5,675,250
2 Branch Control Valve dia 100mm 1 bh 9,334,000 9,334,000
lengkap dengan pressure gauge
3 Flow Switch dia. 100 mm 1 bh 1,171,250 1,171,250
Sight Glass dia. 25 mm 1 bh 931,250 931,250
4 Pressure Gauge 1 bh 241,250 241,250

Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 4 bh 553,500 2,214,000

Pengadaan dan pemasangan Pipa Black Steel


5 Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan

dia. 100 mm 18 mtr 471,360 8,484,480


dia. 80 mm 10 mtr 343,704 3,437,040
dia. 65 mm 38 mtr 258,240 9,813,120
dia. 50 mm 55 mtr 185,400 10,197,000
dia. 40 mm 55 mtr 139,338 7,663,590
dia. 32 mm 20 mtr 117,030 2,340,600
dia. 25 mm 538 mtr 88,728 47,700,173

12.2 Instalasi Hydrant


1 Indoor hidran box 2 bh 3,770,410 7,540,820

2 Pemadam Api Ringan (PAR)


FE 5 KG (Klas ABC) 3 bh 1,218,750 3,656,250
3 Pengadaan dan pemasangan Pipa Black Steel
Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan

dia. 100 mm 16 mtr 471,360 7,541,760


HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
dia. 80 mm 55 mtr 343,704 18,903,720
dia. 65 mm 8 mtr 258,240 2,065,920

4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 2 bh 4,399,590 8,799,180

5 Fitting- fiting 1 lot 17,748,125 17,748,125

6 Material Bantu 1 lot 9,802,500 9,802,500

sub total 12 (lantai tiga ) 197,905,598

13 Instalasi Pemadam Kebakaran


Lantai 4 ( empat )

13.1 Instalasi Sprinkler


1 Head sprinkler 98 ttk 60,375 5,916,750
2 Branch Control Valve dia 100mm 1 bh 9,334,000 9,334,000
lengkap dengan pressure gauge
3 Flow Switch dia. 100 mm 1 bh 1,171,250 1,171,250
Pressure Gauge 1 bh 241,250 241,250
Sight Glass dia. 25 mm 1 bh 931,250 931,250

4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 4 bh 308,500 1,234,000

Pengadaan dan pemasangan Pipa Black Steel


5 Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan
dia. 150 mm
dia. 100 mm 20 mtr 471,360 9,427,200
dia. 80 mm 32 mtr 343,704 10,998,528
dia. 65 mm 44 mtr 258,240 11,362,560
dia. 50 mm 39 mtr 185,400 7,230,600
dia. 40 mm 78 mtr 139,338 10,868,364
dia. 32 mm 42 mtr 117,030 4,915,260
dia. 25 mm 598 mtr 88,728 53,023,853

13.2 Instalasi Hydrant


1 Indoor hidran box 2 bh 3,770,410 7,540,820

2 Pemadam Api Ringan (PAR)


FE 5 KG (Klas ABC) 3 bh 1,218,750 3,656,250
3 Pengadaan dan pemasangan Pipa Black Steel
Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan
dia. 100 mm 14 m 471,360 6,599,040
dia. 80 mm 48 m 343,704 16,497,792
dia. 65 mm 8 m 258,240 2,065,920

4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 4 bh 4,399,590 17,598,360

5 Fitting- fiting 1 lot 19,632,500 19,632,500


HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
6 Material Bantu 1 lot 9,847,500 9,847,500

sub total 13 (lantai empat ) 222,737,367

14 Instalasi Pemadam Kebakaran


Lantai 5 ( lima )

14.1 Instalasi Sprinkler


1 Head sprinkler 110 ttk 60,375 6,641,250
2 Branch Control Valve dia 100mm 1 bh 9,334,000 9,334,000
lengkap dengan pressure gauge
3 Flow Switch dia. 80 mm 1 bh 1,171,250 1,171,250
Pressure Gauge 1 bh 241,250 241,250
Sight Glass dia. 25 mm 1 bh 931,250 931,250

4 Gate valve
dia. 65 mm 2 bh 4,399,590 8,799,180
dia. 25 mm 4 bh 308,500 1,234,000

5 Pengadaan dan pemasangan Pipa Black Steel


Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan
dia. 150 mm 6 mtr 471,360 2,828,160
dia. 100 mm 25 m 471,360 11,784,000
dia. 80 mm 32 m 343,704 11,136,010
dia. 65 mm 44 m 258,240 11,362,560
dia. 50 mm 36 m 185,400 6,674,400
dia. 40 mm 77 m 139,338 10,729,026
dia. 32 mm 35 m 117,030 4,096,050
dia. 25 mm 504 m 88,728 44,718,912

14.1 Instalasi Hydrant


1 Indoor hidran box 2 bh 3,770,410 7,540,820
- Hose rack , selang 30 m + Nozzle
2 - Vander hydarnt dia 2 1/2 & 1 1/2
Pemadam Api Ringan (PAR)
FE 5 KG (Klas ABC) 3 bh 2,700,000 8,100,000
3 Pengadaan dan pemasangan Pipa Black Steel
Sch 40 (ASTM A53) berikut Support
dan Accessories + pengecatan
dia. 150 mm 6 mtr 471,360 2,828,160
dia. 100 mm 14 m 471,360 6,599,040
dia. 80 mm 45 m 343,704 15,466,680
dia. 65 mm 8 m 258,240 2,065,920
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 2 bh 4,399,590 8,799,180

5 Fitting- fiting 1 lot 18,490,000 18,490,000

6 Material Bantu 1 lot 9,245,000 9,245,000

sub total 14 (lantai lima ) 217,138,258

TOTAL PEKERJAAN PEMADAM 2,845,815,864


PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS. SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM LISTRIK

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

I PEKERJAAN SYSTEM TEGANGAN MENENGAH


Pengadaan Panel Tegangan Menengah lengkap dengan komponen
busbar, metering, kontrol dan pemasangan (komponen
dan accessories) dipasang/ diadakan oleh kontraktor tidak terbatas
pada jumlah yang tercantum di bawah ini).

1 MVMDB (20 kV )
Spesifikasi Panel:
Free Standing- metal enclosed cubicle, fixed type,
Galvanized metal sheet.
Rated voltage : 24 kV
Serviced voltage : 20 kV
Short time wistand current : 26 kA
Insulation voltage level :
a. 50 Hz- 1 minute : 50 kVrms
b. Impulse 1,2/50 mS : 125 kVpeak
Elektrodynamic withstand current : 36,5 kA
Phase: 3
Arc extinguishing media : SF6
Cubicle thickness : min 2.0 mm
In/out cable entry : bottom
Busbar rated current : 630 A

Incoming Cubicle 1 Unit 51,600,000 51,600,000


Pengadaan dan pemasangan harus sesuai gambar rencana
dan spesifikasi teknis sehingga berfungsi dengan baik
Incoming cubicle SM 6, Type : IM 630A
Rated Voltage 20 kV, 14.5A / 1 sec.
LBS 3P 400 A, 16 kA/1s, internal Erthing switch, manual, Arrester
3 Phase Busbar 630 A
Voltage Indicator, Earthing Switch, Heater, Shunt Trip

Out Going cubicle SM 6, Type : QM 630A 1 Unit 80,606,250 80,606,250


Rated Voltage 20 kV, 16kA / 1 sec.
LBS 3P 400A, 16 kA/1s, internal Erthing switch, manual
3 Phase Busbar 630 A
Voltage Indicator, Earthing Switch, Heater, Shunt Trip
Solfiuse 630A / 1000 kVA

Trafo 1000 kVA,20 kV/400 V, 3 ph, 50 Hz 1 Unit 180,000,000 180,000,000


5,5 % lengkap dengan peralatan kontrol yang dihubungkan
ke MVMDP
Type : Indoor, Oil Immersed, Total Filled
Hermetically Sealed, IEC Std, SPLN
Primery Voltage : 20kV
Secondary Voltage : 400 V
Impedance Voltage : 5.5%
Perlengkapan Standar : Wheel, Earth
Terminal, Lifting Eye, Oil Filiing Hole, Drain
Plug Rating Plate dan Sertifikat Test Pabrik
Perlengkapan Tambahan : Elastimold MV
Bushing, DCMR

Grounding Cubicle 1 ttk 2,500,000 2,500,000


Grounding Body Trafo 1 ttk 2,500,000 2,500,000
Grounding Titik Netral Trafo 1 ttk 3,500,000 3,500,000
Bak kontrol 3 bh 300,000 900,000

Grounding PUTR/LVMDP 1 ttk 2,500,000 2,500,000


H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Bak kontrol 1 bh 300,000 300,000

Material Bantu 1 Ls 3,000,000 3,000,000

Testing & Commissioning 1 Ls 6,000,000 6,000,000

SUB TOTAL I 333,406,250

II PEKERJAAN PANEL DAYA


Pengadaan, pemasangan dan pengetesan Panel Daya
lengkap dengan Accesoriesnya, Sehingga dapat
berpungsi dengan baik.

1 PUTR/LVMDP 1 Unit 536,970,000 536,970,000


2 PANEL KAPASITOR BANK 350 KVAR 1 Unit 297,810,000 297,810,000

3 LP BS - A 1 Unit 5,530,000 5,530,000


4 LP BS - B 1 Unit 9,850,000 9,850,000
5 P - AC.BS 1 Unit 12,510,000 12,510,000
6 LP BNK BS 1 Unit 5,260,000 5,260,000
7 PP - LOUNDRY 1 Unit 7,800,000 7,800,000
8 PP - HYDRANT 1 Unit 14,420,000 14,420,000
9 PP - POMPA AB 1 Unit 20,750,000 20,750,000
10 PP - SP (AIR KOTOR/ HUJAN) 1 Unit 9,600,000 9,600,000
11 CP - SP1 (PARKIR BASEMENT) 1 Unit 2,000,000 2,000,000
12 CP - SP2 (PARKIR BASEMENT) 1 Unit 2,000,000 2,000,000
13 CP - SP3 (PARKIR BASEMENT) 1 Unit 2,000,000 2,000,000
14 CP - SP4 (PARKIR SITE) 1 Unit 2,000,000 2,000,000
15 CP - SP5 (PARKIR SITE) 1 Unit 2,000,000 2,000,000
16 CP - GREASE TRAP (KITCHEN) 1 Unit 2,000,000 2,000,000
17 CP - SUMPIT (LOUNDRY) 1 Unit 2,000,000 2,000,000
18 CP - SEAWAGE 1 Unit 2,000,000 2,000,000
19 CP - GREASE TRAP (DAPUR) 1 Unit 2,000,000 2,000,000
20 PP - KITCHEN 1 Unit 8,000,000 8,000,000
21 PP - STP 1 Unit 11,160,000 11,160,000
22 LP - OL 1 Unit 8,630,000 8,630,000
23 LP - G 1 Unit 3,610,000 3,610,000

24 LP 1A 1 Unit 9,550,000 9,550,000


25 LP 1B 1 Unit 8,610,000 8,610,000
26 PP - AC.1 1 Unit 24,190,000 24,190,000
27 PP - LAB 1 Unit 3,350,000 3,350,000
28 LP BNK 1 1 Unit 4,290,000 4,290,000
29 LP FC 1 Unit 3,610,000 3,610,000
30 PP - ATM 1 Unit 3,830,000 3,830,000
31 PP - PRI 1 Unit 20,740,000 20,740,000
32 PP - SCAN 1 Unit 5,010,000 5,010,000
33 PP - RONTGEN 1 Unit 4,270,000 4,270,000

34 PP - OK 1 Unit 6,960,000 6,960,000


35 LP - 2A 1 Unit 7,460,000 7,460,000
36 LP - 2B 1 Unit 8,400,000 8,400,000
37 PP - AC.2 1 Unit 14,850,000 14,850,000
38 PP - HD 1 Unit 6,710,000 6,710,000

39 LP - 3A 1 Unit 10,140,000 10,140,000


40 LP - 3B 1 Unit 13,950,000 13,950,000
41 PP - AC.3 1 Unit 14,850,000 14,850,000
42 PP - PR.3 1 Unit 20,160,000 20,160,000
43 PP - ICU 1 Unit 8,200,000 8,200,000
44 PP - NICU 1 Unit 6,680,000 6,680,000
45 PP - PN 1 Unit 5,700,000 5,700,000
46 PP - HC 1 Unit 6,690,000 6,690,000

47 LP - 4A 1 Unit 9,850,000 9,850,000


H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
48 LP - 4B 1 Unit 10,790,000 10,790,000
49 PP - AC.4 1 Unit 14,250,000 14,250,000

50 LP - 5A 1 Unit 7,550,000 7,550,000


51 LP - 5B 1 Unit 9,680,000 9,680,000
52 PP - AC.5 1 Unit 13,520,000 13,520,000

53 P - LIFT 1 1 Unit 6,920,000 6,920,000


54 P - LIFT 2 1 Unit 6,920,000 6,920,000
56 PP - FAN / ATAP 1 Unit 6,180,000 6,180,000
57 LP - ATAP 1 Unit 7,030,000 7,030,000

44 Grounding Panel OK, ICU, NICU, PR-3, PN, HC dan HD. 1 ttk 2,500,000 2,500,000
Bak kontrol 1 bh 300,000 300,000

45 Material Bantu 1 Ls 3,000,000 3,000,000

46 Testing & Commissioning 1 Ls 5,000,000 5,000,000

SUB TOTAL II 1,291,590,000

III KABEL FEEDER

1 KABEL TEGANGAN MENENGAH


Pengadaan, pemasangan dan pengetesan Kabel TM
lengkap dengan Ceilling End, Elastimold dan
Accesoriesnya, sehingga dapat berpungsi dengan baik.

Kabel dari Gardu PLN ke Incomonig Cubicle NXSEFGBY 3 x 120 mm2 110 m 600,000 66,000,000

Kabel dari Outgoing Cubicle ke Trafo N2XSY 3 x 1x 95 mm2 15 m 500,000 7,500,000

2 KABEL TEGANGAN RENDAH


Pengadaan, pemasangan dan pengetesan Kabel Feeder
lengkap dengan Cable Gland, Suport dan Accesoriesnya,
sehingga dapat berpungsi dengan baik.

Kabel Feeder Dari Trafo ke PUTR NYY 3 x 4 x (1 x 300 mm2) 16 m 3,750,000 60,000,000

Kabel Feeder Dari PKG ke PUTR NYY 3 x 4 x (1 x 300 mm2) 15 m 3,750,000 56,250,000
Kabel Sensing Dari PKG ke PUTR NYY 4 x 2.5 mm2 15 m 20,000 300,000
Kabel Kontrol Dari Trafo (DGPT-2) ke PUTR NYY 3 x 2.5 mm2 15 m 15,000 225,000
Kabel Kontrol Dari Trafo (DGPT-2) ke Cubicle (Shunt Trip) 15 m 15,000 225,000
NYY 3 x 2,5 mm2

Kabel Feeder Dari PUTR ke :

Lantai Basement
LP BS - A. NYY 4 x 16 mm2 + BC 10 mm2 54 m 86,000 4,644,000
LP BS - B. NYY 4 x 25 mm2 + BC 16 mm2 54 m 106,000 5,724,000
P - AC.BS. NYY 4 x 25 mm2 + BC 16 mm2 54 m 106,000 5,724,000
LP BNK BS NYY 4 x 6 mm2 + BC 4 mm2 99 m 47,000 4,653,000
PP - LOUNDRY. NYY 4 x 16 mm2 + BC 10 mm2 96 m 86,000 8,256,000
PP - HYDRANT. FRC 4 x 1 x 120 mm2 + BC 50 mm2 96 m 425,000 40,800,000
PP - POMPA AB. NYY 4 x 35 mm2 + BC 25 mm2 96 m 143,000 13,728,000
PP - KITCHEN. NYY 4 x 16 mm2 + BC 10 mm2 78 m 86,000 6,708,000
PP - STP. NYY 4 x 6 mm2 + BC 4 mm2 80 m 47,000 3,760,000
LP - OL. NYY 4 x 6 mm2 + BC 4 mm2 60 m 47,000 2,820,000
LP - G. NYY 4 x 6 mm2 + BC 4 mm2 60 m 47,000 2,820,000

Lantai 1
LP 1A. NYY 4 x 35 mm2 + BC 25 mm2 58 m 143,000 8,294,000
LP 1B. NYY 4 x 25 mm2 + BC 16 mm2 58 m 106,000 6,148,000
PP - AC.1. NYY 4 x 120 mm2 + BC 50 mm2 58 m 468,000 27,144,000
PP - LAB. NYY 4 x 10 mm2 + BC 6 mm2 70 m 74,000 5,180,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
LP BNK 1. NYY 4 x 6 mm2 + BC 4 mm2 95 m 47,000 4,465,000
LP FC. NYY 4 x 6 mm2 + BC 4 mm2 102 m 47,000 4,794,000
PP - ATM. NYY 4 x 6 mm2 + BC 4 mm2 113 m 47,000 5,311,000
PP - PRI. NYY 4 x 16 mm2 + BC 10 mm2 58 m 86,000 4,988,000
Kabel Dari PP - PRI Ke :
PP - SCAN. NYY 4 x 10 mm2 +BC 6 mm2 18 m 74,000 1,332,000
PP - RONTGEN. NYY 4 x 10 mm2 + BC 6 mm2 35 m 74,000 2,590,000

Lantai 2
PP - OK. NYY 4 x 25 mm2 + BC 16 mm2 110 m 106,000 11,660,000
LP - 2A. NYY 4 x 25 mm2 + BC 16 mm2 72 m 106,000 7,632,000
LP - 2B. NYY 4 x 25 mm2 + BC 16 mm2 72 m 106,000 7,632,000
PP - AC.2. NYY 4 x 50 mm2 + BC 35 mm2 72 m 190,000 13,680,000
PP - HD. NYY 4 x 16 mm2 + BC 10 mm2 118 m 86,000 10,148,000

Lantai 3
LP - 3A. NYY 4 x 25 mm2 + BC 16 mm2 66 m 106,000 6,996,000
LP - 3B. NYY4 x 25mm2 + BC 16 mm2 66 m 106,000 6,996,000
PP - AC.3. NYY 4 x 50 mm2 +BC 35 mm2 66 m 190,000 12,540,000
PP - PR.3. NYY 4 x 35 mm2 + BC 25 mm2 16 m 143,000 2,288,000
Kabel Dari PP - PR3 Ke :
PP - ICU. NYY 4 x 10 mm2 + BC 6 mm2 32 m 74,000 2,368,000
PP - NICU. NYY 4 x 10 mm2 + BC 6 mm2 67 m 74,000 4,958,000
PP - PN. NYY 4 x 10 mm2 + BC 6 mm2 61 m 74,000 4,514,000
PP - HC. NYY 4 x 10 mm2 + BC 6 mm2 79 m 74,000 5,846,000

Lantai 4
LP - 4A. NYY 4 x 25 mm2 + BC 16 mm2 70 m 106,000 7,420,000
PP - AC.3. NYY 4 x 50 mm2 +BC 35 mm2 70 m 190,000 13,300,000
PP - AC.4. NYY 4 x 50 mm2 + BC 35 mm2 70 m 190,000 13,300,000

Lantai 5
LP - 5A. NYY 4 x 25 mm2 + BC 16 mm2 74 m 106,000 7,844,000
LP - 5B. NYY 4 x 25 mm2 + BC 16 mm2 74 m 106,000 7,844,000
PP - AC.5. NYY 4 x 50 mm2 + BC 35 mm2 74 m 190,000 14,060,000

Lantai Atap
P - LIFT 1. FRC 4 x 35 mm2 + BC 25 mm2 90 m 150,000 13,500,000
P - LIFT 2. FRC 4 x 35 mm2 + BC 25 mm2 136 m 150,000 20,400,000
PP - P. BOOSTER. NYY 4 x 10 mm2 + BC 6 mm2 106 m 74,000 7,844,000
PP - FAN / ATAP. NYY 4 x 16 mm2 + BC 10 mm2 100 m 86,000 8,600,000
LP - ATAP. NYY 4 x 16 mm2 + BC 10mm2 100 m 86,000 8,600,000

Kabel Dari PP - Loundry Ke Water Heater 300 L (Loundry) 20 m 17,000 340,000


NYM 4 x 2,5 mm2
Kabel Dari PP - Kitchen Ke Water Heater 100 L (Kitchen) 20 m 13,000 260,000
NYM 3 x 2,5 mm2
Kabel Dari PP - Kitchen Ke Water Heater 100 L (Dapur) 40 m 13,000 520,000
NYM 3 x 2,5 mm2

Kabel Dari PP - Hydrant Ke :


CP - Diesel Pump FRC 5 x 1 x 2,5 mm2 16 m 30,000 480,000
CP - Electric Pump FRC 4 x 1 x 95 mm2 + BC 50 mm2 16 m 360,000 5,760,000
Kabel Dari CP - Electric Pump Ke Motor Pump
FRC 3 x 1 x 50 mm2 + BC 50 7 m 220,000 1,540,000
FRC 3 x 1 x 50 mm2 7 m 200,000 1,400,000
CP - Electric Jokey FRC 4 x 1 x 6 mm2 + BC 4 mm2 16 m 50,000 800,000
Kabel Dari CP - Jokey Pump Ke Motor Pump
FRC 4 x 1 x 2,5 mm2 7 m 30,000 210,000

Kabel Dari PP - SP (AIR KOTOR/HUJAN) Ke :


CP - PS-1 NYY 4 x 4 mm2 + BC 4 mm2 47 m 35,000 1,645,000
CP - PS-2 NYY 4 x 4 mm2 + BC 4 mm2 64 m 35,000 2,240,000
CP - PS-3 NYY 4 x 4 mm2 + BC 4 mm2 110 m 35,000 3,850,000
CP - PS-4 NYY 4 x 4 mm2 + BC 4 mm2 82 m 35,000 2,870,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
CP - PS-5 NYY 4 x 4 mm2 + BC 4 mm2 74 m 35,000 2,590,000
CP - PS-6 NYY 4 x 4 mm2 + BC 4 mm2 82 m 35,000 2,870,000
CP - PS-7 NYY 4 x 4 mm2 + BC 4 mm2 104 m 35,000 3,640,000
CP - PS-8 NYY 4 x 4 mm2 + BC 4 mm2 150 m 35,000 5,250,000
CP - PS-9 NYY 4 x 4 mm2 + BC 4 mm2 190 m 35,000 6,650,000

Kabel Dari PP - A.B Ke :


Pompa Transfer 1 dan 2 NYY 4 x 4 mm2 15 m 35,000 525,000
Pompa Transfer 1 dan 2 NYY 3 x 4 mm2 15 m 23,000 345,000
CP - Deep Wheel NYFGBY 4 x 4 mm2 + BC 4mm2 80 m 35,000 2,800,000
PP - SP (AIR KOTOR/HUJAN) NYY 4 x 16 mm2 + BC 10 mm2 50 m 86,000 4,300,000

Kabel dari LP - 2 Ke Auto Cluv NYY 3 x 6 mm2 84 m 32,000 2,688,000

Material Bantu 1 Ls 10,000,000 10,000,000

Testing & Commissioning 1 Ls 5,000,000 5,000,000

SUB TOTAL III 648,926,000

IV LIGHTING & SOCKET OUTLET INSTALLATION


Instalasi Penerangan dan Stop Kontak menggunakan kabel
NYM 3 x 2.5 mm2, Inconduit PVC High Impact 20 mm2
beserta assesorisnya sehingga dapat berfungsi dengan baik.

1 LANTAI BASEMENT & SITE


Down Light 1 x 13 W 60 bh 195,750 11,745,000
Down Light 1 x 13 W c/w Battery 5 bh 907,000 4,535,000
Down Light 2 x 13 W 19 bh 260,000 4,940,000
TL 1 x 36 W TKO 117 bh 235,550 27,559,350
TL 1 x 36 W TKO + Battery 9 bh 899,450 8,095,050
TL 2 x 36 W TKI + Battery 16 bh 515,313 8,245,000
TL 2 x 36 W TKI + Battery 1 bh 1,159,375 1,159,375
TL 2 x 18 W TKI 66 bh 515,313 34,010,625
TL 1 x 18 W TKI + Battery 10 bh 515,313 5,153,125
Exit 2 x 10 W + Battery 2 bh 949,375 1,898,750
Stop Kontak 1Phase 10 A 200 Watt 118 bh 45,625 5,383,750

Instalasi Penerangan, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 305 ttk 211,250 64,431,250
Instalasi Stop Kontak, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 118 ttk 241,250 28,467,500

Lampu Taman Mercury 1 x 80 W 77 bh 663,750 51,108,750


Lampu Jalan SON 1 x 150 W 16 bh 5,714,280 91,428,480
Lampu Sorot 4 bh 1,083,750 4,335,000
Instalasi Penerangan Luar, NYYGBY 4x4 mm2 77 ttk 350,000 26,950,000

2 LANTAI SATU
Down Light 1 x 13 W 175 bh 187,000 32,725,000
Down Light 1 x 13 W c/w Battery 13 bh 875,000 11,375,000
TL 1 x 36 W TKI 2 bh 223,050 446,100
TL 2 x 18 W TKI 131 bh 296,190 38,800,890
TL 2 x 18 W TKI + Battery 16 bh 947,910 15,166,560
Exit 2 x 10 W + Battery 3 bh 897,750 2,693,250
Stop Kontak 1Phase 10 A 200 Watt 185 bh 45,625 8,440,625

Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 340 ttk 211,250 71,825,000
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 185 ttk 241,250 44,631,250

3 LANTAI DUA
Down Light 1 x 13 W 120 bh 187,000 22,440,000
Down Light 1 x 13 W c/w Battery 8 bh 907,000 7,256,000
TL 1 x 36 W TKI 2 bh 223,050 446,100
TL 4 x 18 W TKI (Acrillic) 12 bh 916,000 10,992,000
TL 2 x 18 W TKI 64 bh 296,190 18,956,160
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
TL 2 x 18 W TKI (Acrillic) 21 bh 572,000 12,012,000
TL 2 x 18 W TKI + Battery 21 bh 947,910 19,906,110
Wall Lamp 13 Watt 4 bh 150,000 600,000
Exit 2 x 10 W + Battery 2 bh 897,750 1,795,500
Stop Kontak 1Phase 10 A 200 Watt 151 bh 45,625 6,889,375

Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 250 ttk 211,250 52,812,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 151 ttk 241,250 36,428,750

4 LANTAI TIGA
Down Light 1 x 13 W 112 bh 187,000 20,944,000
Down Light 1 x 13 W c/w Battery 8 bh 907,000 7,256,000
Down Light 2 x 13 W 27 bh 260,000 7,020,000
TL 1 x 36 W TKI 3 bh 223,050 669,150
TL 2 x 18 W TKI 44 bh 296,190 13,032,360
TL 2 x 18 W TKI (Acrillic) 47 bh 572,000 26,884,000
TL 2 x 18 W TKI + Battery 11 bh 947,910 10,427,010
TL 2 x 18 W TKI Acrillic + Battery. 4 bh 1,245,500 4,982,000
Wall Lamp PL C 1 x 13 w 4 bh 150,000 600,000
Exit 2 x 10 W + Battery 2 bh 897,750 1,795,500
Stop Kontak 1Phase 10 A 200 Watt 286 bh 45,625 13,048,750
Receptacle 1Phase 3000 Watt (ICU dan NICU) 2 bh 140,000 280,000
3
Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 258 ttk 211,250 54,502,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 286 ttk 241,250 68,997,500
Instalasi Receptacle 1Phase 3000 Watt 2 ttk 241,250 482,500

5 LANTAI EMPAT
Down Light 1 x 13 W 134 bh 187,000 25,058,000
Down Light 1 x 13 W c/w Battery 7 bh 907,000 6,349,000
Down Light 2 x 13 W 83 bh 260,000 21,580,000
TL 1 x 36 W TKI 2 bh 223,050 446,100
TL 2 x 18 W TKI 28 bh 296,190 8,293,320
TL 2 x 18 W TKI + Battery 2 bh 947,910 1,895,820
Exit 2 x 10 W + Battery 2 bh 897,750 1,795,500
Stop Kontak 1Phase 10 A 200 Watt 220 bh 45,625 10,037,500

Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 262 ttk 211,250 55,347,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 220 ttk 241,250 53,075,000

6 LANTAI LIMA

Down Light 1 x 13 W 158 bh 187,000 29,546,000


Down Light 1 x 13 W c/w Battery 6 bh 907,000 5,442,000
Down Light 2 x 13 W 60 bh 260,000 15,600,000
TL 1 x 36 W TKI 1 bh 223,050 223,050
TL 2 x 18 W TKI 11 bh 296,190 3,258,090
TL 2 x 18 W TKI + Battery 1 bh 947,910 947,910
Wall Lamp PL C 1 x 13 w 38 bh 150,000 5,700,000
Exit 2 x 10 W + Battery 2 bh 897,750 1,795,500
Stop Kontak 1Phase 10 A 200 Watt 194 bh 45,625 8,851,250

Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 266 ttk 211,250 56,192,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 194 ttk 241,250 46,802,500

7 LANTAI ATAP

Lampu Sorot 12 bh 1,083,750 13,005,000


Wall Lamp 13 Watt 17 bh 150,000
TL 1 x 36 W TKO 27 bh 235,550 6,359,850
TL 1 x 36 W TKO + Battery 4 bh 899,450 3,597,800
Stop Kontak 1Phase 10 A 200 Watt 13 bh 45,625 593,125

Instalasi Penerangan, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 60 ttk 211,250 12,675,000
Instalasi Stop Kontak, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 13 bh 241,250 3,136,250
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

Material Bantu 1 lot 12,500,000 12,500,000

Testing & Commissioning 1 lot 7,500,000 7,500,000

SUB TOTAL IV 1,444,609,010

V UPS
Pengadaan, pemasangan dan pengetesan UPS 12000 VA 3 Unit 80,700,000 242,100,000
lengkap dengan Battry, Instalasi pengkabelan dan Accesoriesnya,
sehingga dapat berpungsi dengan baik.

Material Bantu 1 lot 500,000 500,000

Testing & Commissioning 1 lot 500,000 500,000

SUB TOTAL V 243,100,000

VI KABEL TRAY
Pengadaan dan pemasangan Rak Kabel lengkap dengan jointing 3 Unit 80,700,000 242,100,000
Suport, Hanger rood, dan Accesoriesnya sehingga dapat berpungsi
dengan baik.
1 LANTAI BASEMENT & SITE
a. Straight
W = 600 20 m 578,125 11,562,500
W = 500 30 m 495,625 14,868,750
W = 300 200 m 330,625 66,125,000
W = 200 65 m 247,500 16,087,500
b. Elbow
200 x 300 1 bh 431,250 431,250
300 x 300 1 bh 431,250 431,250
c Tee
600 x 600 x 300 2 bh 1,111,875 2,223,750
300 x 600 x 300 1 bh 1,111,875 1,111,875
300 x 200 x 200 1 bh 583,125 583,125
300 x 300 x 200 1 bh 583,125 583,125

2 LANTAI 1
a. Straight
W = 400 4 m 413,125 1,652,500
W = 300 67 m 330,625 22,151,875
W = 200 75 m 247,500 18,562,500
b. Elbow
300 x 300 2 bh 431,250 862,500
300 x 200 1 bh 431,250 431,250
200 x 200 4 bh 303,750 1,215,000
c Tee
300 x 400 x 300 1 bh 731,250 731,250
300 x 300 x 200 1 bh 583,125 583,125
300 x 200 x 200 1 bh 583,125 583,125

3 LANTAI 2
a. Straight
W = 400 14 m 413,125 5,783,750
W = 300 40 m 330,625 13,225,000
W = 200 35 m 247,500 8,662,500
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
300 x 400 x 200 1 bh 731,250 731,250

4 LANTAI 3
a. Straight
W = 300 46 m 330,625 15,208,750
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
W = 200 45 m 247,500 11,137,500
b. Elbow
400 x 400 2 bh 555,000 1,110,000
300 x 300 1 bh 431,250 431,250
300 x 200 1 bh 431,250 431,250
200 x 200 1 bh 303,750 303,750
c Tee
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
300 x 400 x 300 1 bh 731,250 731,250
300 x 200 x 200 1 bh 583,125 583,125

5 LANTAI 4
a. Straight
W = 400 15 m 449,721 6,745,819
W = 300 75 m 283,461 21,259,594
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
300 x 400 x 300 1 bh 731,250 731,250

6 LANTAI 5
a. Straight
W = 400 15 m 413,125 6,196,875
W = 300 75 m 330,625 24,796,875
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
300 x 400 x 300 1 bh 731,250 731,250

d Cable Tray Vertikal


Straight
w = 600 30 m 578,125 17,343,750

e Material Bantu 1 lot 10,000,000 10,000,000

SUB TOTAL VI 550,691,038

TOTAL I s.d VI 4,512,322,298


PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM GENSET

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

A PERALATAN UTAMA

1 Pengadaan Generator-set dengan kapasitas 1050 KVA


dengan putaran 1500 rpm, 220 volt / 380 volt - 400 volt
3 phase, lengkap dengan panel control, vibration
mounting dan industrial silincer 1 Unit 1,475,000,000 1,475,000,000

2 Pengadaan dan pemasangan panel genset lengkap


dengan AMF 1 Unit 115,000,000 115,000,000

B Instalasi Genset
1 - Pekerjaan persiapan
- Mobilisasi matrial dan alat-alat kerja
- Dokumentasi shop drawing
- Kebersihan tempat kerja 1 Lot 15,000,000 15,000,000

2 Setting dan Levelling Genset dan PKG diatas pondasi 1 Lot 18,000,000 18,000,000

3 Pengadaan dan pemasangan kabel power dari Gene -

rator ke PKG, NYY 4 x 3 x 1 x 300mm2 15 Meter 4,275,000 64,125,000


4 Kabel Ladder 400 x 100 15 Meter 325,000 4,875,000

5 Pengadaan dan pemasangan sound attenuator dan


louvre grill
- Intake attenuator ukuran 2500 x 2000 x 1500 mm 1 Unit 21,562,500 21,562,500
- Exhaust attenuator ukuran 3500 x 1500 x 1500 mm 1 Unit 19,406,250 19,406,250
- Intake grill ukuran 2500 x 2000 mm 1 Unit 7,500,000 7,500,000
- Exhaust grill ukuran 2500 x 1500 mm 1 Unit 6,750,000 6,750,000

6 Pengadaan dan pemasangan ducting radiator lengkap


dengan seng dengan ketebalan BJLS 100 1 Unit 4,500,000 4,500,000

7 Pompa bahan bakar dengan kapasitas 30 Lpm Ebara 1 Unit 18,250,000 18,250,000

8 Pengdaan dan pemasangan instalasi bahan bakar


lengkap dengan pipa black steel valve dan stainer 1 Lot 18,875,000 18,875,000

9 Pengdaan dan pemasangan piompa tangan (hand pump) 1 Unit 1,500,000 1,500,000

10 Pengdaan dan pemasangan tangki harian 1000 liter 1 Unit 9,500,000 9,500,000

11 Pengdaan dan pemasangan tangki bulanan 10000 liter 1 Unit 45,000,000 45,000,000

12 Pengdaan dan pemasangan Rock wool density 80 kg/cm


tebal 2" lengkap dengan waremesh 188 Meter 195,000 36,660,000

13 Grounding sytem dengan BC 50mm2 1 Lot 10,000,000 10,000,000

14 Pengdaan dan pemasangan kabel kontrol 1 Lot 4,500,000 4,500,000

15 Testing dan Commisioning 1 Lot 15,000,000 15,000,000

16 Izin Depnaker 1 Unit 3,500,000 3,500,000

TOTAL 1,914,503,750
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM ELEKTRIKAL

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

1 Pengadaan dan pemasangan batang penangkal petir


menggunakan pipa galvanis diameter 2" dan 3 " dilengkapi
Head protector merk EF dengan radius pengamanan
100 m 2. 1 set 18,000,000 18,000,000

2 Pengadaan dan pemasangan batang pentanahan meng -


gunakan elektroda tembaga dengan diameter 3/4", pipa
galvanis dengan BC 50 mm2 dengan minimal keda -
laman 12 meter 1 unit 3,000,000 3,000,000

3 Pembuatan bak kontrol 40 x 40 x 40 cm komplit dengan


cover 1 unit 400,000 400,000

4 Pengadaan dan pemasangan kabel Coaxial Diameter


2x 35 mm2 didalampipa PVC diameter 1 "
pada kolom terpasang rapi. 40 meter 450,000 18,000,000

5 Testing & Commisioning 1 lot 2,000,000 2,000,000

Total 41,400,000
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM TELEPON DAN DATA

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

A PERALATAN UTAMA

Pengadaan dan Pemasangan peralatan, sehingga dapat


berfungsi dengan baik, termasuk pengadaan support -
suport yang dibutuhkan

1 Pengurusan Perizinan pemasangan line telepon 16 600,000 9,600,000

2 Pengadaan dan Pemasangan MDF150 Pair, 1 set 135,000,000 135,000,000


Attenden Console.
PABX Kapasitas 24/120 Extention, Billing System -
Battery + Charger
Komputer Pentium 4, Hard disc 20 GB, Ram 128.

Material Bantu 1 Ls 3,000,000 3,000,000

Testing & Comissioning 1 lot 2,000,000 2,000,000

3 PANEL DISTRIBUSI ( TB - TP )
Lantai Basement ( B) 10 pair 1 unit 1,400,000 1,400,000
Lantai Satu ( 1 ) 40 pair 1 unit 3,800,000 3,800,000
Lantai Dua ( 2 ) 30 pair 1 unit 2,600,000 2,600,000
Lantai Tiga ( 3 ) 20 pair 1 unit 2,600,000 2,600,000
Lantai Empat ( 4 ) 20 pair 1 unit 2,600,000 2,600,000
Lantai Lima ( 5 ) 30 pair 1 unit 2,600,000 2,600,000

4 Kabel distribusi ITC 3 x 0.8 mm dari MDF menuju lantai


Lantai Basement ( B ) 10 pair 57 mtr 25,000 1,425,000
Lantai Satu ( 1 ) 40 pair 67 mtr 100,000 6,700,000
Lantai Dua ( 2 ), 30 pair 77 mtr 75,000 5,775,000
Lantai Tiga ( 3 ), 20 pair 87 mtr 50,000 4,350,000
Lantai Empat ( 4 ), 20 pair 97 mtr 50,000 4,850,000
Lantai Lima ( 5 ), 30 pair 107 mtr 75,000 8,025,000

Sub Total I 196,325,000

B PEKERJAAN INSTALASI TELEPON


Pemasangan isntalasi kabel telepon menggunakan ka-
bel ITC 3 x 0.6 mm didalam conduit PVC high impact
diameter 20 mm komplit dengan sok, clamp, T- Dos
dan Outlet Telepon, merk Clipsal, MK, Legrand,

5.1. Lantai Basement


1 Pengadaan dan pemasangan instalasi Extention telephone 6 buah 290,000 1,740,000

5.2. Lantai Satu


1 Pengadaan dan pemasangan instalasi line telephone 6 buah 290,000 1,740,000
2 Pengadaan dan pemasangan instalasi Extention telephone 31 buah 290,000 8,990,000

5.3 Lantai Dua


1 Pengadaan dan pemasangan instalasi line telephone 1 buah 290,000 290,000
2 Pengadaan dan pemasangan instalasi Extention telephone 19 buah 290,000 5,510,000
3 Pengadaan dan pemasangan instalasi Public telepon Card 1 buah 290,000 290,000
4 Pengadaan dan pemasangan instalasi Faximile 2 buah 290,000 580,000

5.4 Lantai Tiga


1 Pengadaan dan pemasangan instalasi Public telephone coin 1 buah 290,000 290,000
2 Pengadaan dan pemasangan instalasi Extention telephone 11 buah 290,000 3,190,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
3 Pengadaan dan pemasangan instalasi Public telepon Card 1 buah 290,000 290,000

5.5 Lantai Empat


1 Pengadaan dan pemasangan instalasi Public telephone coin 1 buah 290,000 290,000
2 Pengadaan dan pemasangan instalasi Extention telephone 4 buah 290,000 1,160,000
3 Pengadaan dan pemasangan instalasi Public telepon Card 1 buah 290,000 290,000

5.6 Lantai Lima


1 Pengadaan dan pemasangan instalasi Public telephone coin 1 buah 290,000 290,000
2 Pengadaan dan pemasangan instalasi Extention telephone 21 buah 290,000 6,090,000
3 Pengadaan dan pemasangan instalasi Public telepon Card 1 buah 290,000 290,000

5.7 Lantai Atap ( R. Mesin Lift )


1 Pengadaan dan pemasangan instalasi Extention telephone 1 buah 290,000 290,000

5.8 HANDSET
1 Hand set telepon digital 90 unit 250,000 22,500,000
2 Hand set telepon digital dan display 1 unit 1,440,000 1,440,000

5.9 Testing & Comissioning 1 lot 6,000,000 6,000,000

Sub Total II 61,550,000

Total I-II 257,875,000

PEKERJAAN SISTEM DATA


A PERALATAN UTAMA

1 Pengadaan dan Pemasangan peralatan, Utama sehingga


dapat berfungsi dengan baik, termasuk pengadaan support -
suport yang dibutuhkan

2 Pengadaan dan Pemasangan SERVER lengkap 1 set 125,000,000 125,000,000


dengan software dan Accesoriesnya sehingga dapat ber
pungsi dengan baik

3 Hub Switch 60 port 1 unit 23,000,000 23,000,000

B PEKERJAAN INSTALASI

Pemasangan instalasi kabel telepon menggunakan kabel


Data CAT 5 didalam conduit PVC high impact
diameter 20 mm komplit dengan sok, clamp, T- Dos
dan Outlet Telepon, merk Clipsal, MK, Legrand,

5.1. Lantai Basement


1 Pengadaan dan pemasangan instalasi Data 2 Titik 430,000 860,000

5.2. Lantai Satu


1 Pengadaan dan pemasangan instalasi Data 22 Titik 430,000 9,460,000

5.3 Lantai Dua


1 Pengadaan dan pemasangan instalasi Data 20 Titik 430,000 8,600,000

5.4 Lantai Tiga


1 Pengadaan dan pemasangan instalasi Data 4 Titik 430,000 1,720,000

5.5 Lantai Empat


1 Pengadaan dan pemasangan instalasi Data 4 Titik 430,000 1,720,000

5.6 Lantai Lima


1 Pengadaan dan pemasangan instalasi Data 5 Titik 430,000 2,150,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
5.6 Grounding Arus Lemah (semua panel arus lemah) 1 ttk 2,500,000 2,500,000
Bak kontrol 1 bh 300,000 300,000

BC 1 x 25mm2 35 mtr 15,000 525,000

Material Bantu 1 Ls 3,000,000 3,000,000

Testing & Comissioning 1 lot 6,000,000 6,000,000

Sub Total I 36,835,000

294,710,000
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM TATA SUARA

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

A. PERALATAN UTAMA
Pengadaan dan Pemasangan peralatan utama
pada ruang control sehingga berfungsi dengan
baik, sbb:
1 Tape cassette player 1 buah 5,400,000 5,400,000
2 CD Player 1 buah 4,560,000 4,560,000
3 Paging Mikrophone 1 buah 1,800,000 1,800,000
4 Mixer 1 buah 14,400,000 14,400,000
5 Power Amplifier 240 Watt 2 buah 9,600,000 19,200,000
6 Cabinet Rack 1 set 7,800,000 7,800,000
7 Pengadaan dan pemasangan terminal box TB-B 1 unit 960,000 960,000
8 Pengadaan dan pemasangan terminal box TB-1 1 unit 960,000 960,000
9 Pengadaan dan pemasangan terminal box TB-2 1 unit 960,000 960,000
10 Pengadaan dan pemasangan terminal box TB-3 1 unit 960,000 960,000
11 Pengadaan dan pemasangan terminal box TB-4 1 unit 960,000 960,000
12 Pengadaan dan pemasangan terminal box TB-5 1 unit 960,000 960,000

Sub Total I 58,920,000

B. PERALATAN CAR CALL


Pengadaan dan Pemasangan peralatan Car Call
pada ruang reception sehingga berfungsi dengan
baik, sbb:
1 Paging Mikrophone 1 unit 1,800,000 1,800,000
2 Premixer 1 unit 6,000,000 6,000,000
3 Power Amplifier 240 Watt 1 unit 9,600,000 9,600,000
4 Cabinet Rack 1 unit 12,000,000 12,000,000
5 Pengadaan dan pemasangan terminal box TB-B 1 unit 960,000 960,000
6 Pengadaan dan pemasangan Horn speaker 30 Watt
lengkap dengan tiang dan fondasi serta pengkabelan
nya dan berfungsi dengan baik. ( Site ) 4 set 240,000 960,000
7 Pengadaan dan pemasangan Coloumn speaker leng
kap dengan pengkabelannya dan berfungsi dengan
baik.( Lantai Basement ). 3 buah 240,000 720,000
8 Instalasi Horn speaker dan Coloumn speaker 7 titik 192,000 1,344,000

Sub Total II 33,384,000

C. PEKERJAAN INSTALASI
Pemasangan Instalasi Sound System dengan meng
gunakan kabel NYMHY 2x1,5 mm2 di dalam conduit
PVC high impact diameter 20 mm2 komplit dengan
sok, clamp, Tee dos, dan matrial bantu lainnya, se
sehingga dapat berfungsi dengan baik.

C.1 Lantai Basement ( B )


1 Pengadaan dan pemasangan ceilling speaker 15 buah 180,000 2,700,000
2 Instalasi ceilling speaker 15 buah 192,000 2,880,000

C.2 Lantai Satu ( 1 )


1 Pengadaan dan pemasangan ceilling speaker 31 buah 180,000 5,580,000
2 Pengadaan dan pemasangan wall speaker pada
tangga kebakaran 2 buah 240,000 480,000
3 Instalasi ceilling speaker 31 titik 192,000 5,952,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
4 Instalasi wall speaker pada tangga kebakaran 2 titik 192,000 384,000

C.3 Lantai dua ( 2 )


1 Pengadaan dan pemasangan ceilling speaker 14 buah 180,000 2,520,000
2 Pengadaan dan pemasangan wall speaker pada
tangga kebakaran 2 buah 240,000 480,000
3 Instalasi ceilling speaker 14 titik 192,000 2,688,000
4 Instalasi wall speaker pada tangga kebakaran 2 titik 192,000 384,000

C.4 Lantai Tiga ( 3 )


1 Pengadaan dan pemasangan ceilling speaker 16 buah 180,000 2,880,000
2 Pengadaan dan pemasangan wall speaker pada
tangga kebakaran 2 buah 240,000 480,000
3 Instalasi ceilling speaker 16 titik 192,000 3,072,000
4 Instalasi wall speaker pada tangga kebakaran 2 titik 192,000 384,000

C.5 Lantai Empat ( 4 )


1 Pengadaan dan pemasangan ceilling speaker 12 buah 180,000 2,160,000
2 Pengadaan dan pemasangan wall speaker pada
tangga kebakaran 2 buah 240,000 480,000
3 Instalasi ceilling speaker 12 titik 192,000 2,304,000
4 Instalasi wall speaker pada tangga kebakaran 2 titik 192,000 384,000

C.6 Lantai Lima ( 5 )


1 Pengadaan dan pemasangan ceilling speaker 12 buah 180,000 2,160,000
2 Pengadaan dan pemasangan wall speaker pada
tangga kebakaran 2 buah 240,000 480,000
3 Instalasi ceilling speaker 12 titik 192,000 2,304,000
4 Instalasi wall speaker pada tangga kebakaran 2 titik 192,000 384,000

C.7 Lantai Atap ( A )


1 Pengadaan dan pemasangan wall speaker pada
Ruang mesin lift 2 buah 240,000 480,000
2 Pengadaan dan pemasangan wall speaker pada
tangga kebakaran 1 buah 240,000 240,000
3 Instalasi wall speaker pada Ruang mesin Lift 2 titik 192,000 384,000
4 Instalasi wall speaker pada tangga kebakaran 1 titik 192,000 192,000

C.8 Testing & Comissioning 1 lot 6,000,000 6,000,000

Sub Total III 48,816,000

Total I-III 141,120,000


PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM CCTV

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

V PERALATAN UTAMA

V.1 PERALATAN UTAMA DAN KABEL UTAMA


Peralatan Utama
Ruang Kontrol Basement
1 Digital Multiplexer Recorder hard disk 320 Gb, 16
Canel lengkap dengan controler eternet. 1 unit 87,550,000 87,550,000
2 LCD monitor 21" 1 unit 14,875,000 14,875,000
4 UPS 1KVA lengkap dengan back up battery, rectifier
dan line arester 1 unit 6,375,000.00 6,375,000

V.2 KABEL UTAMA


Ruang Kontrol Lt 2
1 Pengkabelan untuk peralatan utama CCTV 1 lot 1,487,500 1,487,500
2 Pekerjaan grounding sistem untuk peralatan utama CCTV 1 lot 3,612,375 3,612,375

V.3 PERALATAN
1 LT. BASEMENT
Camera Fix Dome 5 Unit 4,462,500 22,312,500
2 LT.SATU
Camera Fix Dome 5 Unit 4,462,500 22,312,500
3 SITE PLAN
Camera Fix Dome Night Day + Housing 3 Unit 7,225,000 21,675,000
Camera Fix Dome Night Day 3 Unit 4,462,500 13,387,500
4 LT.DUA
Camera Fix Dome 3 Unit 4,462,500 13,387,500
5 LT.TIGA
Camera Fix Dome 5 Unit 4,462,500 22,312,500
6 LT.EMPAT
Camera Fix Dome 3 Unit 4,462,500 13,387,500
7 LT.LIMA
Camera Fix Dome 3 Unit 4,462,500 13,387,500

V.4 INSTALASI
1 LT. BASEMENT
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 91 m 17,531 1,595,321
2 LT. SATU
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 127 m 17,531 2,229,943
3 LT. SITE PLAN
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 225 m 17,531 3,944,475
4 LT. DUA
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 95 m 17,531 1,665,445
5 LT. TIGA
Kabel Power NYM 3x1.5mm + conduit untuk camera 105 m 21,038 2,208,990
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 167 m 17,531 2,927,677
6 LT. EMPAT
Kabel Power NYM 3x1.5mm + conduit untuk camera 119 m 21,038 2,503,522
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 119 m 17,531 2,086,189
7 LT. LIMA
Kabel Power NYM 3x1.5mm + conduit untuk camera 120 m 21,038 2,524,560
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 133 m 17,531 2,331,623

TOTAL 288,495,320
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM MATV

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

A. PERALATAN UTAMA

1 Pengadaan dan pemasangan head end amplifier 1 unit 4,560,000 4,560,000


2 Pengadaan dan pemasangan antene YAGI -UHF
untuk program lokal 21 unit 600,000 12,600,000
3 Pengadaan dan pemasangan antene YAGI -VHF
untuk program lokal 1 unit 480,000 480,000
4 Instalasi peralatan utama 1 lot 5,400,000 5,400,000
5 Pengadaan dan pemasangan line amplifier 2 unit 7,200,000 14,400,000
6 Pengadaan dan pemasangan Box panel TB - TV 6 buah 960,000 5,760,000
7 Pengadaan dan pemasangan TV Monitor 14", digital
merk Toshiba, Sony 1 unit 1,500,000 1,500,000
8 Kabel dari antena UHF dan VHF ke ruang kontrol lt 2 40 meter 30,000 1,200,000

Sub Total I 45,900,000

B. PEKERJAAN INSTALASI
Pekerjaan ini termasuk pemasangan kabel coaxial di-
dalam pipa conduit dengan diameter 20 mm, high impact
lengkap dengan accesoriesnya.

B.1. Lantai Basement


1 Pengadaan dan pemasangan kabel coaxial type 7-C
atau RG -11, merk Juri, Belden, Hansen 55 meter 30,000 1,650,000
2 Pengadaan dan pemasangan kabel coaxial type 5-C
atau RG -9, merk Juri, Belden, Hansen 63 meter 18,000 1,134,000
3 Pengadaan dan pemasangan outlet TV, termasuk T-Dos
merk MK, Clipsal 1 buah 126,000 126,000

B.2. Lantai Satu


1 Pengadaan dan pemasangan kabel coaxial type 7-C
atau RG -11, merk Juri, Belden, Hansen 65 meter 30,000 1,950,000
2 Pengadaan dan pemasangan kabel coaxial type 5-C
atau RG -9, merk Juri, Belden, Hansen 240 meter 18,000 4,320,000
3 Pengadaan dan pemasangan splitter 4 way 5 buah 228,000 1,140,000
4 Pengadaan dan pemasangan outlet TV, termasuk T-Dos
merk MK, Clipsal 14 buah 126,000 1,764,000
5 Pengadaan dan pemasangan kabel RCA 16 meter 30,000 480,000
merk Juri, Belden, Hansen
6 Pengadaan dan pemasangan outlet RCA, termasuk
T-Dos merk MK, Clipsal 2 buah 126,000 252,000

B.3. Lantai Dua


1 Pengadaan dan pemasangan kabel coaxial type 7-C
atau RG -11, merk Juri, Belden, Hansen 75 meter 30,000 2,250,000
2 Pengadaan dan pemasangan kabel coaxial type 5-C
atau RG -9, merk Juri, Belden, Hansen 160 meter 18,000 2,880,000
3 Pengadaan dan pemasangan splitter 4 way 6 buah 228,000 1,368,000
4 Pengadaan dan pemasangan outlet TV, termasuk T-Dos
merk MK, Clipsal 13 buah 126,000 1,638,000

B.4. Lantai Tiga


1 Pengadaan dan pemasangan kabel coaxial type 7-C
atau RG -11, merk Juri, Belden, Hansen 95 meter 30,000 2,850,000
2 Pengadaan dan pemasangan kabel coaxial type 5-C
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
atau RG -9, merk Juri, Belden, Hansen 102 meter 18,000 1,836,000
3 Pengadaan dan pemasangan splitter 4 way 2 buah 1,428,000 2,856,000
4 Pengadaan dan pemasangan outlet TV, termasuk T-Dos
merk MK, Clipsal 6 buah 126,000 756,000

B.5. Lantai Empat


1 Pengadaan dan pemasangan kabel coaxial type 7-C
atau RG -11, merk Juri, Belden, Hansen 95 meter 30,000 2,850,000
2 Pengadaan dan pemasangan kabel coaxial type 5-C
atau RG -9, merk Juri, Belden, Hansen 368 meter 18,000 6,624,000
3 Pengadaan dan pemasangan splitter 4 way 7 buah 228,000 1,596,000
4 Pengadaan dan pemasangan outlet TV, termasuk T-Dos
merk MK, Clipsal 26 buah 126,000 3,276,000

B.6. Lantai Lima


1 Pengadaan dan pemasangan kabel coaxial type 7-C
atau RG -11, merk Juri, Belden, Hansen 105 meter 30,000 3,150,000
2 Pengadaan dan pemasangan kabel coaxial type 5-C
atau RG -9, merk Juri, Belden, Hansen 437 meter 18,000 7,866,000
3 Pengadaan dan pemasangan splitter 4 way 11 buah 228,000 2,508,000
4 Pengadaan dan pemasangan outlet TV, termasuk T-Dos
merk MK, Clipsal 31 buah 126,000 3,906,000

B.7 Testing & Comissioning 1 lot 6,000,000 6,000,000

Sub Total II 67,026,000

Total I-II 112,926,000


PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM FIRE ALARM

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

A. PERALATAN UTAMA

1. Pengadaan dan Pemasangan Master Control


fire alarm (MCFA) type conventional dengan ka-
pasitas 16 zone komplit dengan batteray ditem -
patkan pada ruang Kontrol 1 unit ######### 81,000,000

2 Pengadaan dan Pemasangan MDF 1 unit 2,160,000 2,160,000

3 Pengadaan dan pemasangan kabel distribusi dari


MDF ke MCFA, Annunciator dan TB - FA perlantai
terpasang pada kabel tray dengan lebar 40 cm 1 lot ######### 15,552,000

4 Pengadaan panel Terminal box (TB - FA) 6 unit 1,620,000 9,720,000

5. Pengadaan dan pemasangan Annunciator yang


ditempatkan pada ruang keamanan 1 unit ######### 43,200,000

Sub Total I ##########

B. PEKERJAAN INSTALASI
Pemasangan isntalasi detektor, menggunakan ka
bel NYA diameter 1 x 1,5mm2 didalam conduit high
impact diameter 20 mm2 lengkap dengan acceso
riesnya.

B.1 Interface
1 Pengadaan dan Pemasangan Instalasi Interface ke :
Sound System, Dial DPK, Flow Switch, Tampre
Switch, Panel AC, Panel Penerangan, Panel Lift,
Presh Air fan, MATV, Hydrant/ Sprinkler dll. 1 lot 5,175,000 5,175,000

B.2 Lantai Basement ( B )


1 Pengadaan dan Pemasangan Rate OF Rise (ROR) 87 buah 174,960 15,221,520
2 Pengadaan dan Pemasangan heat detektor 10 buah 216,000 2,160,000
3 Instalasi detektor 97 titik 270,000 26,190,000
4 Pengadaan dan Pemasangan alarm bell, lampu
indicator, break glass, jack telepon dan instalasinya 2 set 432,000 864,000
5 Pengadaan dan pemasangan instalasi flow switch 1 titik 270,000 270,000

B.3 Lantai Satu ( 1 )


1 Pengadaan dan Pemasangan Rate OF Rise (ROR) 102 buah 216,000 22,032,000
2 Pengadaan dan Pemasangan Smoke detektor 1 buah 378,000 378,000
3 Pengadaan dan Pemasangan heat detektor 1 buah 216,000 216,000
4 Instalasi detektor 104 titik 270,000 28,080,000
5 Pengadaan dan Pemasangan alarm bell, lampu
indicator, break glass, jack telepon dan instalasinya 2 set 480,000 960,000
6 Pengadaan dan pemasangan instalasi flow switch 1 titik 270,000 270,000

B.4. Lantai Dua ( 2 )


1 Pengadaan dan Pemasangan Rate OF Rise (ROR) 61 buah 216,000 13,176,000
2 Pengadaan dan Pemasangan Smoke detektor 4 buah 278,000 1,112,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
3 Pengadaan dan Pemasangan heat detektor 4 buah 216,000 864,000
4 Instalasi detektor 69 titik 270,000 18,630,000
5 Pengadaan dan Pemasangan alarm bell, lampu
indicator, break glass, jack telepon dan instalasinya 2 set 432,000 864,000
6 Pengadaan dan pemasangan instalasi flow switch 1 titik 270,000 270,000

B.5. Lantai Tiga ( 3 )


1 Pengadaan dan Pemasangan Rate OF Rise (ROR) 69 buah 216,000 14,904,000
2 Pengadaan dan Pemasangan Smoke detektor 3 buah 378,000 1,134,000
3 Pengadaan dan Pemasangan heat detektor 2 buah 216,000 432,000
4 Instalasi detektor 74 titik 27,000 1,998,000
5 Pengadaan dan Pemasangan alarm bell, lampu
indicator, break glass, jack telepon dan instalasinya 2 set 432,000 864,000
6 Pengadaan dan pemasangan instalasi flow switch 1 titik 270,000 270,000

B.6. Lantai Empat ( 4 )


1 Pengadaan dan Pemasangan Rate OF Rise (ROR) 52 buah 216,000 11,232,000
2 Pengadaan dan Pemasangan heat detektor 5 buah 240,000 1,200,000
3 Instalasi detektor 57 titik 270,000 15,390,000
4 Pengadaan dan Pemasangan alarm bell, lampu
indicator, break glass, jack telepon dan instalasinya 2 set 432,000 864,000
5 Pengadaan dan pemasangan instalasi flow switch 1 titik 270,000 270,000

B.7. Lantai Lima ( 5 )


1 Pengadaan dan Pemasangan Rate OF Rise (ROR) 50 buah 216,000 10,800,000
2 Pengadaan dan Pemasangan Smoke detektor 1 buah 378,000 378,000
3 Pengadaan dan Pemasangan heat detektor 3 buah 216,000 648,000
4 Instalasi detektor 54 titik 270,000 14,580,000
5 Pengadaan dan Pemasangan alarm bell, lampu
indicator, break glass, jack telepon dan instalasinya 2 set 432,000 864,000
6 Pengadaan dan pemasangan instalasi flow switch 1 titik 270,000 270,000

B.8 Lantai Atap ( A )


1 Pengadaan dan Pemasangan Rate OF Rise (ROR) 3 buah 216,000 648,000
2 Pengadaan dan Pemasangan Smoke detektor 1 buah 378,000 378,000
3 Pengadaan dan Pemasangan heat detektor 1 buah 216,000 216,000
4 Instalasi detektor 5 titik 270,000 1,350,000

B.9. Testing & Commissioning 1 lot 5,400,000 5,400,000

Sub Total II ##########

Total I-II ##########


PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM NURSE CALL

H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

A. PERALATAN UTAMA
CENTRAL PROCESSOR UNIT
Pengadaan dan Pemasangan peralatan utama nurse call
dan Accesoriesnya sehingga dapat berpungsi dengan baik.

1 AE4000 System Suport Hardware with interface to Dim;


stor up 250 vigil rooms 1 unit 40,837,600 40,837,600

2 AE402 Batery Back up for IP8000 to operate file boat


Mode when mains power is off ( typical 4 hour ) 1 buah 7,150,000 7,150,000

3. 157/1 Pengadaan dan pemasangan 1 gang (94x54x43mm)


Australian Std Range, flush mounting box (inbow) 1 lot 3,600,000 3,600,000

B. PEKERJAAN INSTALASI
Pengadaan dan pemasangan Nurse call push button,
lampu indicator, Pull cord, Reset push button.Mikropho
ne, dan instalasi pengkabelannya di dalam conduit PVC
high impact diameter 20 mm2 lengkap dengan acceso
riesnya sehingga dapat berfungsi dengan baik.

B.1 Lantai Basement ( B )


1 Ruang Kebidanan @ 3 Tempat tidur 1 kamar mandi
1 Ruang Anak @ 3 Tempat tidur 1 kamar mandi
1 Ruang Dewasa @ 7 Tempat tidur 1 kamar mandi
1 ACQ 121 Call cancel station with Assurance LED
(with pendan socket) Vertical Mounting 13 buah 1,210,000 15,730,000
2 AP3301 3 Metre Single button PendanT Cord for ACQ
Series Call Station 13 buah 715,000 9,295,000
3 ALL402 Over door light with green and yelow globe 3 buah 935,000 2,805,000
4 ASQ01P Ceilling pull switch slave wet area station with
LED assurance light (with 3 metre heavy duty
detachable pull cord and anchors) 3 buah 1,430,000 4,290,000
5 ACQ023 Presence/Cancel station with assurance LED
(No Pendant Socket/Splashproof) vertical 3 buah 121,000 363,000
mounting
6 ANQ401 Data interface Moduler - 16 inputs
RJ Connected (Configurable) 3 buah 4,537,600 13,612,800
7 ADIC13 12 Character 50 mm single sided 3 Colour
Full Alpha Annunciator with ding sound
Central and Multiple Address Capability 1 Unit 12,375,000 12,375,000

Total I 58,470,800

B.2 Lantai 3 ( Tiga )


2 Ruang VIP @ 1 Tempat tidur 1 kamar mandi
2 Ruang Kls I @ 2 Tempat tidur 1 kamar mandi
4 Ruang Kls II @ 3 Tempat tidur 1 kamar mandi
1 Ruang Kls III @ 7 Tempat tidur 1 kamar mandi
1 Ruang ICU, @ 5 Tempat Tidur.
1 Ruang High Care, @ 4 Tempat Tidur
1 Ruang VK, @ 4 Tempat Tidur 2 Kamar Mandi
1 Ruang VK, @ 1 Tempat Tidur 1 Kamar Mandi
1 ACQ 121 Call cancel station with Assurance LED
(with pendan socket) Vertical Mounting 39 buah 1,210,000 47,190,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
2 AP3301 3 Metre Single button PendanT Cord for ACQ
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Series Call Station 39 buah 715,000 27,885,000
3 ALL402 Over door light with green and yelow globe 17 buah 935,000 15,895,000
4 ASQ01P Ceilling pull switch slave wet area station with
LED assurance light (with 3 metre heavy duty
detachable pull cord and anchors) 17 buah 1,430,000 24,310,000
5 ACQ023 Presence/Cancel station with assurance LED
(No Pendant Socket/Splashproof) vertical 17 buah 121,000 2,057,000
mounting
6 ANQ401 Data interface Moduler - 16 inputs
RJ Connected (Configurable) 2 buah 4,537,600 9,075,200
7 ADIC13 12 Character 50 mm single sided 3 Colour
Full Alpha Annunciator with ding sound
Central and Multiple Address Capability 1 Unit 12,375,000 12,375,000

B.3 Lantai 4 ( Empat )


3 Ruang Kls III @ 13 Tempat tidur 2 kamar mandi
21 Ruang Kls I I @ 6 Tempat tidur 2 kamar mandi
2 Ruang observasi @ 4 Tempat tidur @ 2 kamar mandi
1 ACQ 121 Call cancel station with Assurance LED
(with pendan socket)Vertical Mounting 88 buah 1,210,000 106,480,000
2 AP3301 3 Metre Single button PendanT Cord for ACQ
Series Call Station 88 buah 715,000 62,920,000
3 ALL402 Over door light with green and yelow globe 26 buah 935,000 24,310,000
4 ASQ01P Ceilling pull switch slave wet area station with
LED assurance light (with 3 metre heavy duty
detachable pull cord and anchors) 26 buah 1,430,000 37,180,000
5 ACQ023 Presence/Cancel station with assurance LED
(No Pendant Socket/Splashproof) vertical 26 buah 121,000 3,146,000
mounting
6 ANQ401 Data interface Moduler - 16 inputs
RJ Connected (Configurable) 8 buah 4,537,600 36,300,800
7 ADIC13 12 Character 50 mm single sided 3 Colour
Full Alpha Annunciator with ding sound
Central and Multiple Address Capability 1 Unit 12,375,000 12,375,000

B.4 Lantai 5 ( Lima )


19 Ruang VIP @ 1 Tempat tidur @ 1 kamar mandi
11 Ruang Kls I @ 2 Tempat tidur @ 1 kamar mandi
1 ACQ 121 Call cancel station with Assurance LED
(withpendan socket) Vertical Mounting 41 buah 1,210,000 49,610,000
2 AP3301 3 Metre Single button PendanT Cord for ACQ
Series Call Station 41 buah 715,000 29,315,000
3 ALL402 Over door light with green and yelow globe 30 buah 935,000 28,050,000
4 ASQ01P Ceilling pull switch slave wet area station with
LED assurance light (with 3 metre heavy duty
detachable pull cord and anchors) 30 buah 1,430,000 42,900,000
5 ACQ023 Presence/Cancel station with assurance LED
(No Pendant Socket/Splashproof) vertical 30 buah 121,000 3,630,000
mounting
6 ANQ401 Data interface Moduler - 16 inputs
RJ Connected (Configurable) 6 buah 4,537,600 27,225,600
7 ADIC13 12 Character 50 mm single sided 3 Colour
Full Alpha Annunciator with ding sound
Central and Multiple Address Capability 1 Unit 12,375,000 12,375,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

B5 Instalasi Nurse Call 1 lot 103,175,000 103,175,000

B.6 Testing & Commissioning 1 lot 10,000,000 10,000,000

Total II 727,779,600

Total I-II 786,250,400

C KABEL TRAY ARUS LEMAH


Pengadaan dan pemasangan Rak Kabel lengkap dengan - 3 Unit 80,700,000 242,100,000
Jointing, Suport, Hanger rood, dan Accesoriesnya sehingga
dapat berpungsi dengan baik.

1 LANTAI BASEMENT
a. Straight
W = 300 72 m 330,625 23,805,000
W = 200 48 m 247,500 11,880,000
b. Elbow
300 x 300 1 bh 431,250 431,250
c Tee
300 x 300 x 300 1 bh 583,125 583,125
300 x 200 x 200 1 bh 583,125 583,125

2 LANTAI 1
a. Straight
W = 400 4 m 413,125 1,652,500
W = 300 16 m 330,625 5,290,000
W = 200 96 m 247,500 23,760,000
b. Elbow
300 x 300 1 bh 431,250 431,250
200 x 200 2 bh 303,750 607,500
c Tee
400 x 300 x 200 1 bh 731,250 731,250
300 x 200 x 200 1 bh 583,125 583,125

3 LANTAI 2
a. Straight
W = 400 20 m 413,125 8,262,500
W = 300 2 m 330,625 661,250
W = 200 72 m 247,500 17,820,000
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
400 x 400 x 300 1 bh 731,250 731,250
300 x 400 x 200 1 bh 731,250 731,250
300 x 200 x 200 1 bh 583,125 583,125

4 LANTAI 3
a. Straight
W = 300 16 m 330,625 5,290,000
W = 200 75 m 247,500 18,562,500
b. Elbow
300 x 300 1 bh 431,250 431,250
200 x 200 2 bh 303,750 607,500
c Tee
300 x 200 x 200 1 bh 583,125 583,125

5 LANTAI 4
a. Straight
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
W = 300 22 m 330,625 7,273,750
W = 200 72 m 247,500 17,820,000
b. Elbow
300 x 300 1 bh 431,250 431,250
c Tee
300 x 200 x 200 1 bh 583,125 583,125

6 LANTAI 5
a. Straight
W = 300 22 m 330,625 7,273,750
W = 200 72 m 247,500 17,820,000
b. Elbow
300 x 300 1 bh 431,250 431,250
c Tee
300 x 200 x 200 1 bh 583,125 583,125

d Cable Tray Vertikal


Straight
w = 600 30 m 578,125 17,343,750

e Material Bantu 1 lot 10,000,000 10,000,000

SUB TOTAL VI 446,816,875

TOTAL I s.d VI 1,651,986,275


H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)

Anda mungkin juga menyukai