BIAYA
NO. URAIAN
(Rp)
A. PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan 227,600,000
2 Perizinan PLN (1000 KVA) 150,000,000
3 Perizinan PT Telkom Indonesia 9,600,000
4 Perizinan PAL (Pembuangan air limbah) 12,000,000
B. PEKERJAAN MEKANIKAL
1 Pekerjaan Sistem Tata Udara (Air Conditioning) 2,293,882,000
2 Pekerjaan Sistem Transportasi (Lift) 1,373,000,000
3 Pekerjaan Sistem Plumbing 1,997,681,188
4 Seawage Treatment Plant (STP) 456,997,000
5 Pekerjaan Sistem Fire Fighting 2,845,815,864
6 Pekerjaan Sistem Gas Medic 1,553,439,767
C. PEKERJAAN ELEKTRIKAL
1 Pekerjaan Sistem Listrik 4,512,322,298
2 Pekerjaan Sistem Genset 1,914,503,750
3 Pekerjaan Sistem Penangkal Petir 41,400,000
4 Pekerjaan Sistem Telepon dan Data 294,710,000
5 Pekerjaan Sistem Tata Suara 141,120,000
6 Pekerjaan Fire Alarm 372,454,520
7 Pekerjaan Sistem MATV 112,926,000
8 Pekerjaan Sistem CCTV 288,495,320
9 Pekerjaan Sistem Nurse Call 1,651,986,275
Total A + B + C 20,249,933,982
Keuntungan Pemborong 10% 2,024,993,398
Sub total A + B + C + Keuntungan Pemborong 22,274,927,380
PPN 10 % 2,227,492,738
TOTAL 24,502,420,119
REKAPITALASI BIAYA
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RUMAH SAKIT - SARI ASIH CIPUTAT, TANGERANG
BIAYA
NO. URAIAN
(Rp)
A. PEKERJAAN PERSIAPAN
1 Pekerjaan Persiapan 227,600,000
2 Perizinan PLN (1000 KVA) 150,000,000
3 Perizinan PT Telkom Indonesia 9,600,000
4 Perizinan PAL (Pembuangan air limbah) 12,000,000
B. PEKERJAAN MEKANIKAL
1 Pekerjaan Sistem Tata Udara (Air Conditioning) 2,293,882,000
2 Pekerjaan Sistem Transportasi (Lift) ( By Owner )
3 Pekerjaan Sistem Plumbing 1,997,681,188
4 Seawage Treatment Plant (STP) ( By Owner )
5 Pekerjaan Sistem Fire Fighting 2,845,815,864
6 Pekerjaan Sistem Gas Medic ( By Owner )
C. PEKERJAAN ELEKTRIKAL
1 Pekerjaan Sistem Listrik 4,512,322,298
8 Pekerjaan Sistem Genset ( By Owner )
2 Pekerjaan Sistem Penangkal Petir 41,400,000
3 Pekerjaan Sistem Telepon dan Data 294,710,000
4 Pekerjaan Sistem Tata Suara 141,120,000
5 Pekerjaan Fire Alarm 372,454,520
6 Pekerjaan Sistem MATV 112,926,000
7 Pekerjaan Sistem CCTV 288,495,320
9 Pekerjaan Sistem Nurse Call 1,651,986,275
Total A + B + C 14,951,993,465
Keuntungan Pemborong 10% 1,495,199,347
Sub total A + B + C + Keuntungan Pemborong 16,447,192,812
PPN 10 % 1,644,719,281
TOTAL 18,091,912,093
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN PERSIAPAN
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Pekerjaan Persiapan
1 Biaya -biaya pengadaan staf dan peralatan kantor yang akan 1 lot 40,000,000 40,000,000
mengelola pelaksanaan pekerjaan dan mengurus segala hal
yang berhubungan dengan administrasi proyek (mobilisasi)
2 Biaya - Biaya pemindahan peralatan kantor dan staff yang 1 lot 25,000,000 25,000,000
telah dipergunakan untuk pelaksanaan proyek (demobilisasi)
3 Pemborong harus mengadakan peralatan kerja yang cukup, 1 lot ########## 100,000,000
jumlah kualitas dan kapasitasnya untuk melaksanakan peker-
jaan yang dimaksudkan dalam dokumen tender ini.
Termasuk dalam biaya ini adalah pembuatan dan pembong -
karan serta perampihan kembali tempat penyimpanan barang.
4 Pembuatan dan penggandaan dokumen kontrak lengkap gam- 1 lot 2,000,000 2,000,000
bar-gambar kontrak sebanyak lima (5) set, dimana 4(empat)
set diberikan kepada pemberi tugas.
5 Pembuatan gambar- gambar pelaksanaan /shop drawing, gam- 1 lot 5,000,000 5,000,000
bar-gambar yang telah dilaksanakan /as built drawing yang ha-
rus diberikan kepada pemberi tugas dalam bentuk kalkir 1(satu)
set dan 2(dua) set blue print.
6 Pengadaan contoh - contoh bahan yang dikehendaki oleh pem- 1 lot incl
beri tugas atau wakilnya sesuai dengan spesifikasi tehnis yang
dipersyaratkan dalam dokumen tender harus segera diadakan
tanpa keterlambatan
7 Pemborong harus mengangkat keluar lokasi proyek semua 1 lot 15,000,000 15,000,000
sampah-sampah hasil pekerjaan secara teratur sehingga kea-
daan lapangan selalu bersih. Termasuk didalamnya pengadaan
tempat sampah sementara dan peralatan kebesihannya.
8 Pemborong harus penyiapkan kantor proyek untuk wakil pem- 1 lot 12,000,000 12,000,000
beri tugas termasuk didalamnya kantor pemborong lengkap
dengan lampu penerangan dan instalasinya.
11 Pengadaan Sepatu Safety, Handy talky (HT), Helm proyek, 1 lot 9,000,000 9,000,000
jas hujan, payung untuk pemberi tugas dan pengawas lapangan
12 Semua pekerja pemborong harus mendaftarkan seluruh pega- 1 lot 15,000,000 15,000,000
wainya yang terlibat dalam proyek ini kepada asuransi JAM-
SOSTEK
A PEKERJAAN PLUMBING
I Peralatan Utama
1 Transfer Pump 2 Unit 16,100,000 32,200,000
Kapasitas : 475 l/m
Head : 40 mtr
Speed : 2900 rpm
Daya : 7,5 kw/ 3/ 380 V/50 hz/3 ph
Jenis : Pakaged (1set 2 pompa)
Berikut kabel electroda GWT dan Roof Tank
4 Sand Filter
Type : Automatic Backwash 1 Unit 42,625,000 42,625,000
Kap : 150 l/min
5 Carbon Filter
Type : Automatic Backwash 1 Unit 48,625,000 48,625,000
Kap : 150 l/min
6 Tanki Air Atas (Roof tank) , Lokasi Atap 1 set 83,125,000 83,125,000
Kapasitas : 20 m3
Bahan : FRP
Lengkap dengan dudukan pondasi, dan pipa over,
flow dan sistem drain. Termasuk tangga pengontrol
Flexibel joint
- 80 mm 2 bh 993,750 1,987,500
- 65 mm 2 bh 861,250 1,722,500
Foot Valve
- 80 mm 2 bh 1,613,750
Floating Valve
- 50 mm 1 bh 2,500,000 2,500,000
Site Plan
200 150 m 289,200 43,380,000
150 67 m 197,710 13,246,570
Lantai-dasar
150 73 m 197,710 14,432,830
Lantai-dua
150 95 m 197,710 18,782,450
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
80 70 m 55,650 3,895,500
Roof drain
80 10 bh 162,750 1,627,500
Lantai-tiga
150 76 m 93,780 7,127,280
Lantai-empat
150 76 m 93,780 7,127,280
Lantai-lima
100 76 m 93,780 7,127,280
Lantai-atap
100 76 m 93,780 7,127,280
Roof drain
100 20 bh 187,250 3,745,000
Roof drain
80 5 bh 162,750 813,750
100 4 bh 187,250 749,000
IV LANTAI BASEMENT
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 80 mm 30 mtr 210,825 6,324,750
dia. 50 mm 30 mtr 119,550 3,586,500
dia. 40 mm 55 mtr 87,345 4,803,975
dia. 32 mm 85 mtr 76,879 6,534,694
dia. 25 mm 75 mtr 61,155 4,586,625
dia. 20 mm 120 mtr 42,881 5,145,750
dia. 15 mm 300 mtr 33,608 10,082,250
Gate Valve
dia. 50 mm 1 bh 396,700 396,700
dia. 40 mm 2 bh 256,250 512,500
dia. 32 mm 2 bh 209,450 418,900
dia. 25 mm 8 bh 157,600 1,260,800
47,778,444
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
INSTALASI AIR KOTOR, BEKAS DAN VENT
Instalasi Air Bekas
(Pipa PVC Class AW, class 10 K) air kotor
dia. 150 mm 8 m 197,710 1,581,680
dia. 100 mm 88 m 93,780 8,252,640
dia. 80 mm 100 m 55,650 5,565,000
dia. 65 mm 72 m 44,295 3,189,240
dia. 50 mm 30 m 33,384 1,001,520
97,151,663
V LANTAI SATU
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 50 mm 6 m 119,550 717,300
dia. 40 mm 46 m 87,345 4,017,870
dia. 32 mm 85 m 76,879 6,534,694
dia. 25 mm 66 m 61,155 4,036,230
dia. 20 mm 133 m 42,881 5,703,206
dia. 15 mm 285 m 33,608 9,574,777
Gate Valve
dia. 50 mm 1 bh 396,700 396,700
dia. 32 mm 2 bh 209,450 418,900
dia. 25 mm 2 bh 157,600 315,200
dia. 20 mm 3 bh 120,000 360,000
74,975,845
VI LANTAI DUA
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 50 mm 3 mtr 119,550 358,650
dia. 40 mm 65 mtr 87,345 5,677,425
dia. 32 mm 36 mtr 76,879 2,767,635
dia. 25 mm 45 mtr 61,155 2,751,975
dia. 20 mm 68 mtr 42,881 2,915,925
dia. 15 mm 265 mtr 33,608 8,905,988
Gate Valve
dia. 50 mm 1 bh 396,700 396,700
dia. 32 mm 2 bh 256,250 512,500
dia. 25 mm 2 bh 209,450 418,900
62,592,714
VII LANTAI TIGA
Instalasi Air Bersih
(Pipa Galvanized Iron Medium Class)
dia. 65 mm 20 mtr 164,260 3,285,200
dia. 40 mm 65 mtr 87,345 5,677,425
dia. 32 mm 64 mtr 76,879 4,920,240
dia. 25 mm 60 mtr 61,155 3,669,300
dia. 20 mm 60 mtr 42,881 2,572,875
dia. 15 mm 205 mtr 33,608 6,889,538
Gate Valve
dia. 65 mm 1 bh 164,260
dia. 40 mm 2 bh 465,476 930,952
dia. 32 mm 2 bh 186,174 372,348
dia. 25 mm 5 bh 156,603 783,013
dia. 15 mm 3 bh 33,608 100,823
116,408,003
Gate Valve
dia. 65 mm 1 bh 485,587 485,587
dia. 40 mm 2 bh 465,476 930,952
dia. 25 mm 16 bh 156,603 2,505,642
dia. 15 mm 3 bh
IX LANTAI LIMA
(Pipa Galvanized Iron Medium Class)
dia. 32 mm 60 mtr 76,879 4,612,725
dia. 25 mm 75 mtr 61,155 4,586,625
dia. 20 mm 220 mtr 42,881 9,433,875
dia. 15 mm 245 mtr 33,608 8,233,838
Gate Valve
dia. 32 mm 16 bh 186,174 2,978,785
59,862,585
X Lantai - Atap
(Pipa Galvanized Iron Medium Class)
dia. 100 mm 12 mtr 279,145 3,349,740
dia. 80 mm 189 mtr 210,825 39,845,925
dia. 65 mm 16 mtr 164,260 2,628,160
dia. 50 mm 8 mtr 119,550 956,400
dia. 40 mm 3 mtr 87,345 262,035
Gate Valve
dia. 32 mm 1 bh 186,174 186,174
dia. 25 mm 28 bh 156,603 4,384,873
Lantai- Atap
dia. 150 mm 6 m 197,710 1,186,260
dia. 100 mm 48 m 93,780 4,501,440
dia. 80 mm 6 m 55,650 333,900
dia. 65 mm 6 m 44,295 265,770
dia. 50 mm 6 m 33,384 200,304
77,075,190
Instalasi Ventilasi
dia 80 mm 50 mtr 71,888 3,594,375
55,184,375
Lantai Basement
dia 15 mm 50 mtr 24,900 1,245,000
Ball Valve dia 15 mm 6 bh 175,000 1,050,000
PERALATAN UTAMA
Pengadaan dan pemasangan matrial utama water
heater system solar panel lengkap dengan matrial
Pendukung dan Accesoriesnya sehingga dapat
berpungsi dengan baik
Lantai 1
dia 20 mm 17 mtr 38,900 661,300
dia 15 mm 33 mtr 24,900 821,700
Ball Valve dia 15 mm 1 bh 175,000 175,000
Lantai 2
dia 20 mm 22 mtr 38,900 855,800
dia 15 mm 65 mtr 24,900 1,618,500
Ball Valve dia 15 mm 2 bh 175,000 350,000
Lantai 3
dia 20 mm 22 mtr 38,900 855,800
dia 15 mm 90 mtr 24,900 2,241,000
Ball Valve dia 15 mm 3 bh 175,000 525,000
HARGA SATUAN JUMLAH HARGA
No Uraian QTY SAT
Rp. Rp.
Lantai 4
dia 20 mm 8 mtr 38,900 311,200
dia 15 mm 40 mtr 24,900 996,000
Ball Valve dia 15 mm 2 bh 175,000 350,000
Lantai 5
PPR dia 20 mm 136 mtr 38,900 5,290,400
dia 15 mm 320 mtr 24,900 7,968,000
Ball Valve dia 15 mm 8 bh 175,000 1,400,000
Lantai Atap
dia 25 mm 120 mtr 62,600 7,512,000
Ball Valve dia 25 mm 1 bh 225,000 225,000
Ball Valve dia 15 mm 13 bh 175,000 2,275,000
317,931,700
TOTAL 1,997,681,188
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM TATA UDARA
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Exhaust Air Grill Toilet ukuran 250 x 250 8 Buah 105,000 840,000
Grill Fan Toilet (EF-B.3) ukuran 500 x 500 1 Buah 450,000 450,000
Ducting Intake Fan Kitchen ukuran 600 x 300 34 Meter 280,000 9,520,000
Grill Kitchen (IF=B.2) Hood ukuran 600 x 300 1 Buah 600,000 600,000
Suplay Air Grill Kitchen ukuran 500 x 250 4 Buah 400,000 1,600,000
Ducting Exhaust Fan Kitchen ukuran 600 x 300 58 Meter 280,000 16,240,000
Grill Kitchen (EF=B.4) Hood ukuran 600 x 600 1 Buah 600,000 600,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Grill Fan Parkir Basement ( EF=B.5) Hood ukuran 600 x 600 1 Buah 600,000 600,000
Suplay Air Grill Loundry ukuran 500 x 250 3 Buah 400,000 1,200,000
Ducting Exhaust Fan Loundry ukuran 600 x 300 58 Meter 280,000 16,240,000
Suplay Air Grill Loundry ukuran 500 x 250 3 Buah 400,000 1,200,000
Grill Fan Loundry (EF=B.6) Hood ukuran 600 x 600 1 Buah 600,000 600,000
Exhaust Air Grill Dapur ukuran 300 x 300 2 Buah 105,000 210,000
Grill Fan Dapur (EF-B.7) Hood ukuran 500 x 500 1 Buah 450,000 450,000
Grill Fan Parkir Basement ( EF=B.8) Hood ukuran 600 x 600 1 Buah 600,000 600,000
Ducting Exhaust Gudang Apotik ukuran 200 x 200 9 Meter 160,000 1,440,000
Grill Fan Gudang Apotik (EF-B.9) ukuran 250 x 250 1 Buah 105,000 105,000
Grill Fan R jenazah (EF-B.10) ukuran 250 x 250 1 Buah 105,000 105,000
IU/OU - 2.7, 2.10, 2.18, 2.19, 2.24, 2.25, 2.32, 2.33, 2.34 10 Unit 9,200,000 92,000,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
2.36
Lokasi :Resulasi,RR, Keuangan, PT, Hemodialisa,
NS, Meeteng Room 2
Kapasitas :18100 BTUH
Air flow :572 CFM
Daya :1650 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ
IU/OU - 3.2, 3.6, 3.15, 3.16, 3.18,3.25,3.28, 3.31, 3.33 9 Unit 4,950,000 44,550,000
Lokasi :ICU VIP, R tunggu VK, NICU, Kala,
:Lounge, Preinatologi, Nurse
(OK, VK pakai AC Plasma Cluster)
Kapasitas :8900 BTUH
Air flow :311 CFM
Daya :815 WATT
Type :Split Wall
Power Suplai :1P/220V/50HZ
2
berikut hanger, suport, vibration mounting, plexible joint,
plenum box dan accesoriesnya sehingga dapat berpungsi
dengan baik.
Total A - H 2,293,882,000
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM PEMADAM KEBAKARAN
1.1 Pompa Elektrik Hydrant (Ruang pompa lt, B ) 1 unit 104,000,000 104,000,000
- Kapasitas : 500 GPM
- Head : 100 meter
- Put : 2900 Rpm
- Type : splite case
- Operation : start automatik,
stop manual
1.2 Pompa Diesel Hydrant (Ruang pompa lt, B ) 1 unit 200,000,000 200,000,000
- Kapasitas : 500 GPM
- Head : 100 meter
- Put : 2900 Rpm
- Type : splite case
- Operation : start automatik,
sub total 1
2.2 Assesories
- Gate valve
Dia. 150 mm 10 bh 10,459,980 104,599,800
Dia. 50 mm 2 bh 824,380 1,648,760
- Check valve
Dia. 150 mm 2 bh 6,940,020 13,880,040
Dia. 50 mm 1 bh 631,060 631,060
- Fleksible joint
Dia. 150 mm 4 bh 1,927,500 7,710,000
Dia. 50 mm 2 bh 533,800 1,067,600
- Strainer
Dia. 150 mm 2 bh 6,070,620 12,141,240
dia. 50 mm 1 bh 639,940 639,940
2.3 - Main Control Valve (MCV) dia. 150 mm 1 set 55,875,000 55,875,000
c/w Alarm gong, dan acesoriesnya
4 Gate valve
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 2 bh 4,399,590 8,799,180
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 4 bh 308,500 1,234,000
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 2 bh 4,399,590 8,799,180
Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 4 bh 553,500 2,214,000
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 2 bh 4,399,590 8,799,180
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 25 mm 4 bh 308,500 1,234,000
4 Gate valve
dia. 100 mm 1 bh 6,322,160 6,322,160
dia. 65 mm 4 bh 4,399,590 17,598,360
4 Gate valve
dia. 65 mm 2 bh 4,399,590 8,799,180
dia. 25 mm 4 bh 308,500 1,234,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
1 MVMDB (20 kV )
Spesifikasi Panel:
Free Standing- metal enclosed cubicle, fixed type,
Galvanized metal sheet.
Rated voltage : 24 kV
Serviced voltage : 20 kV
Short time wistand current : 26 kA
Insulation voltage level :
a. 50 Hz- 1 minute : 50 kVrms
b. Impulse 1,2/50 mS : 125 kVpeak
Elektrodynamic withstand current : 36,5 kA
Phase: 3
Arc extinguishing media : SF6
Cubicle thickness : min 2.0 mm
In/out cable entry : bottom
Busbar rated current : 630 A
44 Grounding Panel OK, ICU, NICU, PR-3, PN, HC dan HD. 1 ttk 2,500,000 2,500,000
Bak kontrol 1 bh 300,000 300,000
Kabel dari Gardu PLN ke Incomonig Cubicle NXSEFGBY 3 x 120 mm2 110 m 600,000 66,000,000
Kabel Feeder Dari Trafo ke PUTR NYY 3 x 4 x (1 x 300 mm2) 16 m 3,750,000 60,000,000
Kabel Feeder Dari PKG ke PUTR NYY 3 x 4 x (1 x 300 mm2) 15 m 3,750,000 56,250,000
Kabel Sensing Dari PKG ke PUTR NYY 4 x 2.5 mm2 15 m 20,000 300,000
Kabel Kontrol Dari Trafo (DGPT-2) ke PUTR NYY 3 x 2.5 mm2 15 m 15,000 225,000
Kabel Kontrol Dari Trafo (DGPT-2) ke Cubicle (Shunt Trip) 15 m 15,000 225,000
NYY 3 x 2,5 mm2
Lantai Basement
LP BS - A. NYY 4 x 16 mm2 + BC 10 mm2 54 m 86,000 4,644,000
LP BS - B. NYY 4 x 25 mm2 + BC 16 mm2 54 m 106,000 5,724,000
P - AC.BS. NYY 4 x 25 mm2 + BC 16 mm2 54 m 106,000 5,724,000
LP BNK BS NYY 4 x 6 mm2 + BC 4 mm2 99 m 47,000 4,653,000
PP - LOUNDRY. NYY 4 x 16 mm2 + BC 10 mm2 96 m 86,000 8,256,000
PP - HYDRANT. FRC 4 x 1 x 120 mm2 + BC 50 mm2 96 m 425,000 40,800,000
PP - POMPA AB. NYY 4 x 35 mm2 + BC 25 mm2 96 m 143,000 13,728,000
PP - KITCHEN. NYY 4 x 16 mm2 + BC 10 mm2 78 m 86,000 6,708,000
PP - STP. NYY 4 x 6 mm2 + BC 4 mm2 80 m 47,000 3,760,000
LP - OL. NYY 4 x 6 mm2 + BC 4 mm2 60 m 47,000 2,820,000
LP - G. NYY 4 x 6 mm2 + BC 4 mm2 60 m 47,000 2,820,000
Lantai 1
LP 1A. NYY 4 x 35 mm2 + BC 25 mm2 58 m 143,000 8,294,000
LP 1B. NYY 4 x 25 mm2 + BC 16 mm2 58 m 106,000 6,148,000
PP - AC.1. NYY 4 x 120 mm2 + BC 50 mm2 58 m 468,000 27,144,000
PP - LAB. NYY 4 x 10 mm2 + BC 6 mm2 70 m 74,000 5,180,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
LP BNK 1. NYY 4 x 6 mm2 + BC 4 mm2 95 m 47,000 4,465,000
LP FC. NYY 4 x 6 mm2 + BC 4 mm2 102 m 47,000 4,794,000
PP - ATM. NYY 4 x 6 mm2 + BC 4 mm2 113 m 47,000 5,311,000
PP - PRI. NYY 4 x 16 mm2 + BC 10 mm2 58 m 86,000 4,988,000
Kabel Dari PP - PRI Ke :
PP - SCAN. NYY 4 x 10 mm2 +BC 6 mm2 18 m 74,000 1,332,000
PP - RONTGEN. NYY 4 x 10 mm2 + BC 6 mm2 35 m 74,000 2,590,000
Lantai 2
PP - OK. NYY 4 x 25 mm2 + BC 16 mm2 110 m 106,000 11,660,000
LP - 2A. NYY 4 x 25 mm2 + BC 16 mm2 72 m 106,000 7,632,000
LP - 2B. NYY 4 x 25 mm2 + BC 16 mm2 72 m 106,000 7,632,000
PP - AC.2. NYY 4 x 50 mm2 + BC 35 mm2 72 m 190,000 13,680,000
PP - HD. NYY 4 x 16 mm2 + BC 10 mm2 118 m 86,000 10,148,000
Lantai 3
LP - 3A. NYY 4 x 25 mm2 + BC 16 mm2 66 m 106,000 6,996,000
LP - 3B. NYY4 x 25mm2 + BC 16 mm2 66 m 106,000 6,996,000
PP - AC.3. NYY 4 x 50 mm2 +BC 35 mm2 66 m 190,000 12,540,000
PP - PR.3. NYY 4 x 35 mm2 + BC 25 mm2 16 m 143,000 2,288,000
Kabel Dari PP - PR3 Ke :
PP - ICU. NYY 4 x 10 mm2 + BC 6 mm2 32 m 74,000 2,368,000
PP - NICU. NYY 4 x 10 mm2 + BC 6 mm2 67 m 74,000 4,958,000
PP - PN. NYY 4 x 10 mm2 + BC 6 mm2 61 m 74,000 4,514,000
PP - HC. NYY 4 x 10 mm2 + BC 6 mm2 79 m 74,000 5,846,000
Lantai 4
LP - 4A. NYY 4 x 25 mm2 + BC 16 mm2 70 m 106,000 7,420,000
PP - AC.3. NYY 4 x 50 mm2 +BC 35 mm2 70 m 190,000 13,300,000
PP - AC.4. NYY 4 x 50 mm2 + BC 35 mm2 70 m 190,000 13,300,000
Lantai 5
LP - 5A. NYY 4 x 25 mm2 + BC 16 mm2 74 m 106,000 7,844,000
LP - 5B. NYY 4 x 25 mm2 + BC 16 mm2 74 m 106,000 7,844,000
PP - AC.5. NYY 4 x 50 mm2 + BC 35 mm2 74 m 190,000 14,060,000
Lantai Atap
P - LIFT 1. FRC 4 x 35 mm2 + BC 25 mm2 90 m 150,000 13,500,000
P - LIFT 2. FRC 4 x 35 mm2 + BC 25 mm2 136 m 150,000 20,400,000
PP - P. BOOSTER. NYY 4 x 10 mm2 + BC 6 mm2 106 m 74,000 7,844,000
PP - FAN / ATAP. NYY 4 x 16 mm2 + BC 10 mm2 100 m 86,000 8,600,000
LP - ATAP. NYY 4 x 16 mm2 + BC 10mm2 100 m 86,000 8,600,000
Instalasi Penerangan, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 305 ttk 211,250 64,431,250
Instalasi Stop Kontak, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 118 ttk 241,250 28,467,500
2 LANTAI SATU
Down Light 1 x 13 W 175 bh 187,000 32,725,000
Down Light 1 x 13 W c/w Battery 13 bh 875,000 11,375,000
TL 1 x 36 W TKI 2 bh 223,050 446,100
TL 2 x 18 W TKI 131 bh 296,190 38,800,890
TL 2 x 18 W TKI + Battery 16 bh 947,910 15,166,560
Exit 2 x 10 W + Battery 3 bh 897,750 2,693,250
Stop Kontak 1Phase 10 A 200 Watt 185 bh 45,625 8,440,625
Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 340 ttk 211,250 71,825,000
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 185 ttk 241,250 44,631,250
3 LANTAI DUA
Down Light 1 x 13 W 120 bh 187,000 22,440,000
Down Light 1 x 13 W c/w Battery 8 bh 907,000 7,256,000
TL 1 x 36 W TKI 2 bh 223,050 446,100
TL 4 x 18 W TKI (Acrillic) 12 bh 916,000 10,992,000
TL 2 x 18 W TKI 64 bh 296,190 18,956,160
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
TL 2 x 18 W TKI (Acrillic) 21 bh 572,000 12,012,000
TL 2 x 18 W TKI + Battery 21 bh 947,910 19,906,110
Wall Lamp 13 Watt 4 bh 150,000 600,000
Exit 2 x 10 W + Battery 2 bh 897,750 1,795,500
Stop Kontak 1Phase 10 A 200 Watt 151 bh 45,625 6,889,375
Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 250 ttk 211,250 52,812,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 151 ttk 241,250 36,428,750
4 LANTAI TIGA
Down Light 1 x 13 W 112 bh 187,000 20,944,000
Down Light 1 x 13 W c/w Battery 8 bh 907,000 7,256,000
Down Light 2 x 13 W 27 bh 260,000 7,020,000
TL 1 x 36 W TKI 3 bh 223,050 669,150
TL 2 x 18 W TKI 44 bh 296,190 13,032,360
TL 2 x 18 W TKI (Acrillic) 47 bh 572,000 26,884,000
TL 2 x 18 W TKI + Battery 11 bh 947,910 10,427,010
TL 2 x 18 W TKI Acrillic + Battery. 4 bh 1,245,500 4,982,000
Wall Lamp PL C 1 x 13 w 4 bh 150,000 600,000
Exit 2 x 10 W + Battery 2 bh 897,750 1,795,500
Stop Kontak 1Phase 10 A 200 Watt 286 bh 45,625 13,048,750
Receptacle 1Phase 3000 Watt (ICU dan NICU) 2 bh 140,000 280,000
3
Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 258 ttk 211,250 54,502,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 286 ttk 241,250 68,997,500
Instalasi Receptacle 1Phase 3000 Watt 2 ttk 241,250 482,500
5 LANTAI EMPAT
Down Light 1 x 13 W 134 bh 187,000 25,058,000
Down Light 1 x 13 W c/w Battery 7 bh 907,000 6,349,000
Down Light 2 x 13 W 83 bh 260,000 21,580,000
TL 1 x 36 W TKI 2 bh 223,050 446,100
TL 2 x 18 W TKI 28 bh 296,190 8,293,320
TL 2 x 18 W TKI + Battery 2 bh 947,910 1,895,820
Exit 2 x 10 W + Battery 2 bh 897,750 1,795,500
Stop Kontak 1Phase 10 A 200 Watt 220 bh 45,625 10,037,500
Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 262 ttk 211,250 55,347,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 220 ttk 241,250 53,075,000
6 LANTAI LIMA
Instalasi Penerangan, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 266 ttk 211,250 56,192,500
Instalasi Stop Kontak, NYM 3x2,5 mm2 (Inconduit PVC dia. 20) 194 ttk 241,250 46,802,500
7 LANTAI ATAP
Instalasi Penerangan, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 60 ttk 211,250 12,675,000
Instalasi Stop Kontak, NYM 3x2,5 mm2 (In Conduit PVC dia. 20) 13 bh 241,250 3,136,250
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
V UPS
Pengadaan, pemasangan dan pengetesan UPS 12000 VA 3 Unit 80,700,000 242,100,000
lengkap dengan Battry, Instalasi pengkabelan dan Accesoriesnya,
sehingga dapat berpungsi dengan baik.
VI KABEL TRAY
Pengadaan dan pemasangan Rak Kabel lengkap dengan jointing 3 Unit 80,700,000 242,100,000
Suport, Hanger rood, dan Accesoriesnya sehingga dapat berpungsi
dengan baik.
1 LANTAI BASEMENT & SITE
a. Straight
W = 600 20 m 578,125 11,562,500
W = 500 30 m 495,625 14,868,750
W = 300 200 m 330,625 66,125,000
W = 200 65 m 247,500 16,087,500
b. Elbow
200 x 300 1 bh 431,250 431,250
300 x 300 1 bh 431,250 431,250
c Tee
600 x 600 x 300 2 bh 1,111,875 2,223,750
300 x 600 x 300 1 bh 1,111,875 1,111,875
300 x 200 x 200 1 bh 583,125 583,125
300 x 300 x 200 1 bh 583,125 583,125
2 LANTAI 1
a. Straight
W = 400 4 m 413,125 1,652,500
W = 300 67 m 330,625 22,151,875
W = 200 75 m 247,500 18,562,500
b. Elbow
300 x 300 2 bh 431,250 862,500
300 x 200 1 bh 431,250 431,250
200 x 200 4 bh 303,750 1,215,000
c Tee
300 x 400 x 300 1 bh 731,250 731,250
300 x 300 x 200 1 bh 583,125 583,125
300 x 200 x 200 1 bh 583,125 583,125
3 LANTAI 2
a. Straight
W = 400 14 m 413,125 5,783,750
W = 300 40 m 330,625 13,225,000
W = 200 35 m 247,500 8,662,500
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
300 x 400 x 200 1 bh 731,250 731,250
4 LANTAI 3
a. Straight
W = 300 46 m 330,625 15,208,750
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
W = 200 45 m 247,500 11,137,500
b. Elbow
400 x 400 2 bh 555,000 1,110,000
300 x 300 1 bh 431,250 431,250
300 x 200 1 bh 431,250 431,250
200 x 200 1 bh 303,750 303,750
c Tee
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
300 x 400 x 300 1 bh 731,250 731,250
300 x 200 x 200 1 bh 583,125 583,125
5 LANTAI 4
a. Straight
W = 400 15 m 449,721 6,745,819
W = 300 75 m 283,461 21,259,594
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
300 x 400 x 300 1 bh 731,250 731,250
6 LANTAI 5
a. Straight
W = 400 15 m 413,125 6,196,875
W = 300 75 m 330,625 24,796,875
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
300 x 400 x 300 1 bh 731,250 731,250
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
A PERALATAN UTAMA
B Instalasi Genset
1 - Pekerjaan persiapan
- Mobilisasi matrial dan alat-alat kerja
- Dokumentasi shop drawing
- Kebersihan tempat kerja 1 Lot 15,000,000 15,000,000
2 Setting dan Levelling Genset dan PKG diatas pondasi 1 Lot 18,000,000 18,000,000
7 Pompa bahan bakar dengan kapasitas 30 Lpm Ebara 1 Unit 18,250,000 18,250,000
9 Pengdaan dan pemasangan piompa tangan (hand pump) 1 Unit 1,500,000 1,500,000
10 Pengdaan dan pemasangan tangki harian 1000 liter 1 Unit 9,500,000 9,500,000
11 Pengdaan dan pemasangan tangki bulanan 10000 liter 1 Unit 45,000,000 45,000,000
TOTAL 1,914,503,750
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM ELEKTRIKAL
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Total 41,400,000
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM TELEPON DAN DATA
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
A PERALATAN UTAMA
3 PANEL DISTRIBUSI ( TB - TP )
Lantai Basement ( B) 10 pair 1 unit 1,400,000 1,400,000
Lantai Satu ( 1 ) 40 pair 1 unit 3,800,000 3,800,000
Lantai Dua ( 2 ) 30 pair 1 unit 2,600,000 2,600,000
Lantai Tiga ( 3 ) 20 pair 1 unit 2,600,000 2,600,000
Lantai Empat ( 4 ) 20 pair 1 unit 2,600,000 2,600,000
Lantai Lima ( 5 ) 30 pair 1 unit 2,600,000 2,600,000
5.8 HANDSET
1 Hand set telepon digital 90 unit 250,000 22,500,000
2 Hand set telepon digital dan display 1 unit 1,440,000 1,440,000
B PEKERJAAN INSTALASI
294,710,000
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM TATA SUARA
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
A. PERALATAN UTAMA
Pengadaan dan Pemasangan peralatan utama
pada ruang control sehingga berfungsi dengan
baik, sbb:
1 Tape cassette player 1 buah 5,400,000 5,400,000
2 CD Player 1 buah 4,560,000 4,560,000
3 Paging Mikrophone 1 buah 1,800,000 1,800,000
4 Mixer 1 buah 14,400,000 14,400,000
5 Power Amplifier 240 Watt 2 buah 9,600,000 19,200,000
6 Cabinet Rack 1 set 7,800,000 7,800,000
7 Pengadaan dan pemasangan terminal box TB-B 1 unit 960,000 960,000
8 Pengadaan dan pemasangan terminal box TB-1 1 unit 960,000 960,000
9 Pengadaan dan pemasangan terminal box TB-2 1 unit 960,000 960,000
10 Pengadaan dan pemasangan terminal box TB-3 1 unit 960,000 960,000
11 Pengadaan dan pemasangan terminal box TB-4 1 unit 960,000 960,000
12 Pengadaan dan pemasangan terminal box TB-5 1 unit 960,000 960,000
C. PEKERJAAN INSTALASI
Pemasangan Instalasi Sound System dengan meng
gunakan kabel NYMHY 2x1,5 mm2 di dalam conduit
PVC high impact diameter 20 mm2 komplit dengan
sok, clamp, Tee dos, dan matrial bantu lainnya, se
sehingga dapat berfungsi dengan baik.
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
V PERALATAN UTAMA
V.3 PERALATAN
1 LT. BASEMENT
Camera Fix Dome 5 Unit 4,462,500 22,312,500
2 LT.SATU
Camera Fix Dome 5 Unit 4,462,500 22,312,500
3 SITE PLAN
Camera Fix Dome Night Day + Housing 3 Unit 7,225,000 21,675,000
Camera Fix Dome Night Day 3 Unit 4,462,500 13,387,500
4 LT.DUA
Camera Fix Dome 3 Unit 4,462,500 13,387,500
5 LT.TIGA
Camera Fix Dome 5 Unit 4,462,500 22,312,500
6 LT.EMPAT
Camera Fix Dome 3 Unit 4,462,500 13,387,500
7 LT.LIMA
Camera Fix Dome 3 Unit 4,462,500 13,387,500
V.4 INSTALASI
1 LT. BASEMENT
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 91 m 17,531 1,595,321
2 LT. SATU
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 127 m 17,531 2,229,943
3 LT. SITE PLAN
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 225 m 17,531 3,944,475
4 LT. DUA
Kabel Power NYM 3x1.5mm + conduit untuk camera 100 m 21,038 2,103,800
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 95 m 17,531 1,665,445
5 LT. TIGA
Kabel Power NYM 3x1.5mm + conduit untuk camera 105 m 21,038 2,208,990
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 167 m 17,531 2,927,677
6 LT. EMPAT
Kabel Power NYM 3x1.5mm + conduit untuk camera 119 m 21,038 2,503,522
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 119 m 17,531 2,086,189
7 LT. LIMA
Kabel Power NYM 3x1.5mm + conduit untuk camera 120 m 21,038 2,524,560
Coaxial Cable RG - 6 7 Ohm + conduit untuk camera 133 m 17,531 2,331,623
TOTAL 288,495,320
PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PROYEK RS . SARI ASIH CIPUTAT, TANGERANG, BANTEN
PEKERJAAN SISTEM MATV
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
A. PERALATAN UTAMA
B. PEKERJAAN INSTALASI
Pekerjaan ini termasuk pemasangan kabel coaxial di-
dalam pipa conduit dengan diameter 20 mm, high impact
lengkap dengan accesoriesnya.
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
A. PERALATAN UTAMA
B. PEKERJAAN INSTALASI
Pemasangan isntalasi detektor, menggunakan ka
bel NYA diameter 1 x 1,5mm2 didalam conduit high
impact diameter 20 mm2 lengkap dengan acceso
riesnya.
B.1 Interface
1 Pengadaan dan Pemasangan Instalasi Interface ke :
Sound System, Dial DPK, Flow Switch, Tampre
Switch, Panel AC, Panel Penerangan, Panel Lift,
Presh Air fan, MATV, Hydrant/ Sprinkler dll. 1 lot 5,175,000 5,175,000
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
A. PERALATAN UTAMA
CENTRAL PROCESSOR UNIT
Pengadaan dan Pemasangan peralatan utama nurse call
dan Accesoriesnya sehingga dapat berpungsi dengan baik.
B. PEKERJAAN INSTALASI
Pengadaan dan pemasangan Nurse call push button,
lampu indicator, Pull cord, Reset push button.Mikropho
ne, dan instalasi pengkabelannya di dalam conduit PVC
high impact diameter 20 mm2 lengkap dengan acceso
riesnya sehingga dapat berfungsi dengan baik.
Total I 58,470,800
Total II 727,779,600
1 LANTAI BASEMENT
a. Straight
W = 300 72 m 330,625 23,805,000
W = 200 48 m 247,500 11,880,000
b. Elbow
300 x 300 1 bh 431,250 431,250
c Tee
300 x 300 x 300 1 bh 583,125 583,125
300 x 200 x 200 1 bh 583,125 583,125
2 LANTAI 1
a. Straight
W = 400 4 m 413,125 1,652,500
W = 300 16 m 330,625 5,290,000
W = 200 96 m 247,500 23,760,000
b. Elbow
300 x 300 1 bh 431,250 431,250
200 x 200 2 bh 303,750 607,500
c Tee
400 x 300 x 200 1 bh 731,250 731,250
300 x 200 x 200 1 bh 583,125 583,125
3 LANTAI 2
a. Straight
W = 400 20 m 413,125 8,262,500
W = 300 2 m 330,625 661,250
W = 200 72 m 247,500 17,820,000
b. Elbow
400 x 400 1 bh 555,000 555,000
c Tee
400 x 400 x 300 1 bh 731,250 731,250
300 x 400 x 200 1 bh 731,250 731,250
300 x 200 x 200 1 bh 583,125 583,125
4 LANTAI 3
a. Straight
W = 300 16 m 330,625 5,290,000
W = 200 75 m 247,500 18,562,500
b. Elbow
300 x 300 1 bh 431,250 431,250
200 x 200 2 bh 303,750 607,500
c Tee
300 x 200 x 200 1 bh 583,125 583,125
5 LANTAI 4
a. Straight
H.Sat Total
No Uraian Qty Sat
(Rp) (Rp)
W = 300 22 m 330,625 7,273,750
W = 200 72 m 247,500 17,820,000
b. Elbow
300 x 300 1 bh 431,250 431,250
c Tee
300 x 200 x 200 1 bh 583,125 583,125
6 LANTAI 5
a. Straight
W = 300 22 m 330,625 7,273,750
W = 200 72 m 247,500 17,820,000
b. Elbow
300 x 300 1 bh 431,250 431,250
c Tee
300 x 200 x 200 1 bh 583,125 583,125