Anda di halaman 1dari 5

SPESIFIKASI TEKNIS PERALATAN PJU

TENAGA SURYA 100 WATT

*Komponen Solar Cell :


Mono/Polycrystaline 26 Wp
Max. Voltage (Vmp) 10.V
Cells Type Mono/Poly

*Komponen Lampu :
Type: Street Light LED 100 W 3,2 Vdc
LED Chip : Samsung Brand
Liminaire
Body EfficiencyAlloy
: Alumunium >90%

Ukuran Body : 70x22x4,5cm


CCT : 6000-6500 K
IP Level : IP 65
Life Span > 50,000 Hours

*Komponen Battery :
Type : Battery LifePO4 3,2V 30Ah
Nominal Voltage : 3,7V
Rated Capacity : 30 Ah

*Komponen Controler/Regulator :
PIR Sensor : Yes
Remote Control : Yes
*Spesifikasi Teknis Tiang :
Tiang terbuat dari Plate Stell Ketebalan Plate 2,6 mm Finishing Hotdip Galvanized
Tinggi : 6M
Type Tiang : Bulat
Ukuran Diameter Tiang : 4" 3" 2,5"
Flandes : 30 x 30 x 14 cm
Ornamen : 1.5" - 2" x 2m
Galvaniez
Sudah termasuk Baut Angkur + Dudukan Lampu

*Pemasangan / Setting Erection :


- Perakitan Instalasi PJU Solar Sell
- Perakitan Instalasi Grounding Tiang
- Tidak termasuk biaya Untuk supervisi dan biaya uji coba
I PEK. PENGADAN TIANG DAN PERALATAN PJUTS
1. Pengad.Tiang LJU Bulat 5 M & PJU Solar Cell All in One 20 W 1.00 Set 7,692,000.00
2. Pemas. Tiang LJU Galvanise Bulat T.5M 1.00 Btng 577,400.00
3. Pemas. Paket PJU Solar Cell All in One 20 Watt 1.00 Set 145,400.00

II PEK. PENGADAAN SOLAR CELL DAN PERALATAN PENERANGAN


1. Pengadaan Solar Cell 50Wp dan Peralatan Penerangan 1.00 Set 4,039,500.00
2. Pemas. Lampu LED 18W 12-24 V DC 1.00 Set 145,400.00
3. Pemas. Modul Surya/Solar Cell 50 Wp 1.00 Set 145,400.00
4. Pemas. Battere + Controller +Box Panel 1.00 Set 145,400.00
8,414,800
7,692,000
577,400
145,400

4,475,700
4,039,500
145,400
145,400
145,400
31. 5 BATANG PEMASANGAN TIANG PJU
Truck Jam 7.000 300,000 2,100,000.00
Tangga Jam 7.000 50,000 350,000.00
Alat Bantu Set 0.320 350,000 112,000.00
Pekerja Hk 1.000 75,000 75,000.00
Mandor Hk 1.000 100,000 100,000.00
Tukang Hk 1.000 90,000 90,000.00
Buruh Tak Terlatih Hk 1.000 60,000 60,000.00
2,887,000.00
Untuk 1 Batang Pemasangan 577,400.00

32. 5 SET PEMASANGAN LAMPU PJU LED SOLAR CELL ALL IN ONE
Tangga Jam 7.000 50,000 350,000.00
Alat Bantu Set 0.320 350,000 112,000.00
Pekerja Hk 1.000 75,000 75,000.00
Mandor Hk 1.000 100,000 100,000.00
Tukang Hk 1.000 90,000 90,000.00
727,000.00
Untuk 1 Set Pemasangan 145,400.00

33. 5 SET PEMASANGAN SOLAR CELL/PANEL SURYA


Tangga Jam 7.000 50,000 350,000.00
Alat Bantu Set 0.320 350,000 112,000.00
Pekerja Hk 1.000 75,000 75,000.00
Mandor Hk 1.000 100,000 100,000.00
Tukang Hk 1.000 90,000 90,000.00
727,000.00
Untuk 1 Set Pemasangan 145,400.00

33. 5 SET PEMASANGAN CONTROLER+BATERE/ACCU+BOX PANEL


Tangga Jam 7.000 50,000 350,000.00
Alat Bantu Set 0.320 350,000 112,000.00
Pekerja Hk 1.000 75,000 75,000.00
Mandor Hk 1.000 100,000 100,000.00
Tukang Hk 1.000 90,000 90,000.00
727,000.00
Untuk 1 Set Pemasangan 145,400.00

34. 1 SET PENGADAAN TIANG DAN PERALATAN PJUTS


Paket PJU Solar Cell All in One 20 Watt Set 1.000 4,124,000 4,124,000.00
Tiang PJU Bulat T 5 Meter Btng 1.000 3,568,000 3,568,000.00

7,692,000.00

34. 1 SET PENGADAAN TIANG DAN PERALATAN PJUTS


Paket PJU Solar Cell All in One 100 Watt Set 1.000 7,000,000 7,000,000.00
Tiang PJU Bulat T 7 Meter Btng 1.000 3,949,000 3,949,000.00

10,949,000.00

34. 1 SET PENGADAAN SOLAR CELL DAN PERALATAN PENERANGAN


Dudukan Solar Cell Set 1.000 250,000 250,000.00
Solar Panel 30 Wp Pcs 1.000 810,000 810,000.00
Lampu LED 18W 12-24 V DC Pcs 1.000 250,000 250,000.00
Controler 10A Pcs 1.000 450,000 450,000.00
Kabel+Asecories Instalasi Paket 1.000 350,000 350,000.00
Panel Box Bh 1.000 850,000 850,000.00
Batere/Accu VRLA 12 V 18 AH Bh 1.000 1,079,500 1,079,500.00
4,039,500.00
DAFTAR HARGA BAHAN DAN UPAH KERJA

Lokasi : Kabupaten Buol - Sulawesi Tengah

NO URAIAN SAT HARGA SATUAN KET


1 2 3 4 5
A UPAH PEKERJA
1 Mandor Hk 100,000.00
2 Pekerja Hk 75,000.00
3 Tukang Listrik Hk 90,000.00
4 Kepala Tukang Hk 110,000.00
5 Operator Terlatih Hk 90,000.00
6 Operator Kurang Terlatih Hk 75,000.00
7 Sopir Hk 70,000.00
8 Pembantu Sopir / Kenek Hk 60,000.00
9 Pembantu Operator Hk 60,000.00
10 Mekanik Hk 80,000.00
11 Buruh Terlatih Hk 65,000.00
12 Buruh Tidak Terlatih Hk 60,000.00

B BAHAN MATERIAL
1 Pasir Urug M3 125,000.00
2 Pasir Pasangan M 3
125,000.00
3 Kerikil Sungai (disaring) M3 242,000.00
4 Batu Kali M3 242,000.00
5 Semen 50 Kg Zak 80,000.00 1,600 /kg
6 BAHAN KAYU PAPAN
7 Papan Tebal 2 cm Lbr 20,000.00
8 Papan Tebal 3 cm Lbr 22,000.00
BAHAN BESI
1 Besi Beton Kg 11,000.00
2 Besi Beton Ulir Kg 13,000.00
3 Baja WF/CNP Kg 17,167.00
4 Kawat Beton Kg 17,250.00
5 Kawat las Kg 50,000.00
6 Paku Biasa Kg 18,750.00
7 Paku Seng Kg 20,200.00
8 Baut Lengkap Psg 25,000.00
BAHAN FINISHING
1 Cat Kayu Lux Kg 43,000.00
2 Cat Kayu Biasa Kg 30,000.00
3 Minyak Bekisting Ltr 23,000.00
4 Meni Kg 10,350.00
BAHAN LISTRIK
1 Paket PJU Solar Cell All in One 150 Watt Set 7,500,000.00
2 Paket PJU Solar Cell All in One 100 Watt Set 7,000,000.00
3 Paket PJU Solar Cell All in One 50 Watt Unit 6,250,000.00
4 Paket PJU Solar Cell All in One 20 Watt Unit 5,780,000.00
5 Tiang PJU Octagonal T 7 Meter Btg 4,124,000.00
6 Tiang PJU Octagonal T 6 Meter Btg 3,950,000.00
7 Tiang PJU Octagonal T 5 Meter Btg 3,775,000.00
8 Tiang PJU Bulat T 7 Meter Btg 3,949,000.00
9 Tiang PJU Bulat T 6 Meter Btg 3,695,000.00
10 Tiang PJU Bulat T 5 Meter Btg 3,568,000.00

Anda mungkin juga menyukai