DAFTAR ANALISA HARGA SATUAN

A.4.1.1.6 Pemasangan Tiang Lampu PJU oktagonal 7 meter dan Instalasi Listrikc

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 Oh 4.650 73,500.00 341,775.00
2 Tukang Listrik L.02 Oh 0.875 102,500.00 89,687.50
3 Kepala tukang L.03 Oh 0.028 108,500.00 3,038.00
4 Mandor L.04 Oh 0.083 115,100.00 9,553.30
JUMLAH TENAGA KERJA 444,053.80
B BAHAN
1 Tiang Oktagonal Single Parabola 7 meter E259 Btg 1.000 4,350,000.00 4,350,000.00
hotdeep galvanized -
2 Kabel NYY 4x6 mm E843 m 6.000 105,700.00 634,200.00
3 Service Wadge E846 Bh 2.000 8,000.00 16,000.00
4 Box Panel Besi Topi Outdoor 30x40x18 E836 Bh 1.000 550,000.00 550,000.00
5 MCB schneider 1p 20a E837 Bh 1.000 90,200.00 90,200.00
6 Timer theben sul 181D E838 Bh 1.000 515,000.00 515,000.00
7 Kontaktor schneider 20A 220V E839 Bh 1.000 670,000.00 670,000.00
8 Terminal 6p25A E840 Bh 1.000 33,000.00 33,000.00
9 Indikator input volt Led E841 Bh 1.000 77,500.00 77,500.00
10 Lampu Led Philips SmartBright BRP 132 140Watt E842 Bh 1.000 3,000,000.00 3,000,000.00
JUMLAH HARGA BAHAN 9,935,900.00
C PERALATAN
Alat-alat bantu E869 Set 0.876 94,000.00 82,344.00
JUMLAH HARGA ALAT 82,344.00
D Jumlah (A+B+C) 10,462,297.80
E Overhead & Profit 10% x D 1,046,229.78
F Harga Satuan Pekerjaan (D+E) 11,508,527.58

A.4.1.1.7 Pemasangan Kabel Twisted 4x16 mm c

Harga Satuan Jumlah Harga


No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 Oh 0.248 73,500.00 18,257.29
2 Tukang Listrik L.02 Oh 0.065 102,500.00 6,662.50
3 Kepala tukang L.03 Oh 0.028 108,500.00 3,038.00
4 Mandor L.04 Oh 0.063 115,100.00 7,251.30
JUMLAH TENAGA KERJA 35,209.09
B BAHAN
1 Kabel NYY 3x16 m 1.000 105,700.00 105,700.00
JUMLAH HARGA BAHAN 105,700.00
C PERALATAN
-
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 140,909.09
E Overhead & Profit 10% x D 14,090.91
F Harga Satuan Pekerjaan (D+E) 155,000.00