Anda di halaman 1dari 1

RENCANA ANGGARAN BIAYA

Lokasi : Tridaya
Proyek : Pasang Baru 36 Unit x 1.300 VA/R1T
NORMALISASI SUB RINCIAB MATERIAL DAN JASA SAT VOL HARGA SATUAN JUMLAH
I. TIANG
Tiang beton 9/200 daN ( Terpasang ) bh 2 3.000.000 6.000.000
Tiang beton 9/350 daN ( Terpasang ) bh 3 4.000.000 12.000.000
Sub Jumlah I 18.000.000
IV. SUTR
311004 1/2 TIC 3 x 70 + N ( CABLE PWR;NFA2X-T;3X70+1X70;0.6/1KV;OH ) Mtr 530 70.000 37.100.000
MATERIAL NON MDU
3280114 CCO 70 / 70 bh 4 35.000 140.000
3060213 Joint bimetal 70 / 70 bh 4 70.000 280.000
3050004 A3C 70 mm ( U/ Pentanahan ) mtr 28 40.000 1.120.000
419026 4/1 Earthing rod 16 x 2500 sqmm + klem bh 4 170.000 680.000
3120038 Fixed dead assimbly set 1 100.000 100.000
3120033 Adjustable dead assimbly set 3 120.000 360.000
3120092 Suspension sys set 11 60.000 660.000
3120058 Large Angel assimbly set 4 120.000 480.000
3120006 EMP ( Electric and Mecanical Protection ) set 2 60.000 120.000
Stainless Steel Strip mtr 6 15.000 90.000
Link 25 x 25 bh 6 3.000 18.000
Stoping Buckle bh 6 2.500 15.000
Sub Jumlah IV A 41.163.000
JASA
Pasang SUTR TIC 3 x 70 + N kms 0,530 8.000.000 4.240.000
Pondasi tiang TR bh 3 300.000 900.000
Pasang pentanahan TR ( ERR ) set 2 200.000 400.000
Pasang Kontruksi TR 1B ( Jaringan < 45 Derajat ) bh 10 50.000 500.000
Pasang Kontruksi TR 2B ( Jaringan 45-120 Derajat ) bh 4 50.000 200.000
Pasang Kontruksi TR 4B ( Jaringan 1 Percabangan ) bh 1 150.000 150.000
Pasang Kontruksi TR 10B ( Jaringan Akhir ) bh 2 70.000 140.000
Pasang Kontruksi TR 11B ( Jaringan Awal Gardu Tiang ) bh 1 120.000 120.000
Pipa galvanis 0,75 " x 3m u/pelindung Ardhe btg 2 150.000 300.000
CONN;1KV;PG;CU-CU;6-50MM2;BOLT; bh 2 20.000 40.000
Sub Jumlah IV B 6.990.000
XI. LAIN - LAIN
BP Kwh 1300 VA unit 36 1.300.000 46.800.000
Pulsa Kwh plg 36 100.000 3.600.000
Sertifikat Laiak Operasi 1300 VA unit 36 220.000 7.920.000
Pemasangan Kwh unit 36 50.000 1.800.000
Sub Jumlah XI 60.120.000

TOTAL 126.273.000