RINCIAN PEKERJAAN

Nama Pekerjaan : PENGADAAN INSTALASI PENYALUR PETIR PLTD TELUK BETUNG ULPL TANJUNG KARANG
PT.PLN (Persero) UIK SUMBAGSEL UNIT PELAKSANA DAN PENGEDALIAN PEMBANGKITAN BANDAR LAMPUNG
Tanggal : 24 November 2020

HARGA SATUAN JUMLAH

NO ITEM SATUAN VOLUME MATERIAL JASA MATERIAL JASA TOTAL

RP RP RP RP

A PERALATAN UTAMA LIGHTING PROTECKTION

1 Dat Controller Plus 30 AT3W AT130 Ea 1 25.760.000 25.760.000

2 Adapting Place Mast‐1 1/2" merk AT3W AT‐001G Ea 1 1.250.000 1.250.000

3 Galvanis Steel Mastg Pole Ὸ1 1/2" 6m Ea 1 3.750.000 3.750.000

4 Lighting Even Conter Merk AT3W AT‐10A Ea 1 6.500.000 6.500.000

MATERIAL INSTALASI

Grounding ROD Sytem (Maks 5 ohm)

1 Earth Pit lot 1 8.500.000 8.500.000

Ground ROD Cooper 3/4 x 4m

Ground ROD Clamp Type cincin

Bording Bar

2 BC 50 mm2 m 200 165.000 33.000.000

3 MATERIAL BANTU dan ACCESSORIES Lot 1 5.550.000 5.550.000

Klem Kabel BC

PVC Conduit 20mm

Coupling

Sadle

Ficher

C TRANSPORTASI DAN AKOMODASI

1 Sewa Mobil Operasionam hari 20 300.000 6.000.000

2 Sewa Kontrakan hari 20 350.000 7.000.000

2 Tiket Peawat PP Org 4 600.000 2.400.000

D LABOUR COST

1 Site Manager (1 urg x 20 Hari) Oh 20 350.000 7.000.000

2 Safety Officer (1 urg x 20 Hari) Oh 20 155.000 3.100.000

3 Pekerja Sipil (1 urg x 20 Hari) Oh 20 155.000 3.100.000

4 Teknisi (1 urg x 400 Hari) Oh 40 155.000 6.200.000

5 Helper (1 urg x 40 Hari) Oh 40 120.000 4.800.000

E DIREKSI KET

1 Warehouse sementara Hari 20 150.000 3.000.000

2 Safety Equipment Oh 140 17.500 2.450.000

3 Dokumentasi Hari 20 77.500 1.550.000

4 Sewa Tools Hari 20 150.000 3.000.000

F DELIVERY SITE lot 1 12.550.000 12.550.000

G TEST COMMISIONONG DAN SERTIFIKASI Lot 1 25.000.000 25.000.000

JUMLAH Rp 171.460.000
PPLN 10 % Rp 17.146.000
TOTAL Rp 188.606.000
Terbilang : Seratus Delapan Puluh Delapan Juta Enam Ratus Enam Ribu Rupiah
Bandar Lampung , 24 November 2020
PT.NATAFARI
DIREKTUR

ZULKIFLI HOESNY