Anda di halaman 1dari 106

ENGINEER ESTIMATE (EE)

DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK ­ BANGGAI


PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT

REKAPITULASI PEKERJAAN DED TAHUN 2015 

NO URAIAN  JUMLAH HARGA (Rp)

A PEKERJAAN REPLACEMENT
I Pekerjaan Persiapan 792.220.600,00

II.A Dermaga 20M x 54M ­ Tahun 1992 11.607.268.296,62

II.B Pembongkaran Dermaga Eksisting Tahun 1992 847.229.752,00

II.C Perbaikan Pile Cap Trestle 1992 4.783.778,30

II.D Dermaga 20M x 50M ­ Tahun 1998 10.693.973.140,85

II.E Pembongkaran Dermaga Eksisting Tahun 1998 825.075.545,00

II.F Dermaga 20M x 50M ­ Tahun 2015 10.125.097.161,76

II.G Trestle 10M x 20M ­ Tahun 2015 2.037.176.011,38

B III PEKERJAAN PENGERUKAN

A Pekerjaan Persiapan Pengerukan 580.000.000,00

B Pekerjaan Pengerukan 63.733.084,88

C PEKERJAAN GEDUNG TERMINAL PELABUHAN 2.087.600.000,00

JUMLAH A + B +C 39.664.157.370,79
PPN 10 % 3.966.415.737,08
JUMLAH TOTAL 43.630.573.107,87
DIBULATKAN 43.630.500.000,00 
Terbilang : 
= Empat puluh tiga milyar enam ratus tiga puluh juta lima ratus ribu rupiah = 

DED Pelabuhan LuwuK Thn. 2015  PT. Sarana Antar Nusa Perekayasa
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 
Mobilisasi dan Demobilisasi Peralatan Pekerjaan Dermaga 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Koefisien 
(Rp.)  (Rp.) 
1  Generator Set  Unit  2  750.000,0  1.500.000,00 
2  Air Compressor  Unit  1  300.000,0  300.000,00 
3  Demolition Drill  Unit  4  250.000,0  1.000.000,00 
4  Mesin Las  Unit  2  750.000,0  1.500.000,00 
5  Mixer Concrete, Kap. 0,3 ‐ 0,6 m3  Unit  4  1.000.000,0  4.000.000,00 
6  Vibrator Concrete  Unit  4  300.000,0  1.200.000,00 
7  Ponton Pancang  PP  1  243.000.000,0  243.000.000,00 
8  Crane Pancang  Unit  1  20.000.000,0  20.000.000,00 
9  Crane Service, Kap. 35 ton  Unit  1  20.000.000,0  20.000.000,00 
10  Diesel Hammer, K‐35  Unit  1  3.000.000,0  3.000.000,00 
11  Tug Boat  PP  1  300.000.000,0  300.000.000,00 
12  Truck Crane  Unit  1  2.500.000,0  2.500.000,00 
J u m l a h  598.000.000,0 
Pengukuran Darat & Laut 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 
Bahan : 
1  Cat Minyak  kg  12,0000  36.300,00  435.600,00 
2  Balok Kaso dan Bambu  ls  1,0000  1.500.000,00  1.500.000,00 

Jumlah Bahan  1.935.600,00 
Alat : 
1  Alat Bantu/perahu (30 % x 210 hr)  hari  31,5000  525.000,00  16.537.500,00 
2  Theodolit, (25 % x 210 hr)  hari  52,5000  150.000,00  7.875.000,00 
3  Waterpas, (25 % x 210 hr  hari  52,5000  150.000,00  7.875.000,00 
Upah : 
1  Surveyor (1 Orang)  hari  52,5000  151.000,00  7.927.500,00 
2  Pembantu Surveyor (2 Orang)  hari  105,0000  134.000,00  14.070.000,00 
3  Tenaga Harian (4 Orang)  hari  210,0000  84.000,00  17.640.000,00 

Jumlah Jasa  54.285.000,00 
Jumlah Bahan & Jasa  56.220.600,00 

Mobilisasi dan Demobilisasi Peralatan Pekerjaan Pengerukan 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Koefisien 
(Rp.)  (Rp.) 
1  Tug Boat  PP  1  300.000.000,0  300.000.000,0 
2  Kapal Keruk (CDS), Kap. 50 m3  PP  1  240.000.000,0  240.000.000,0 
3  Bulldozer  Unit  1  20.000.000,0  20.000.000,0 
4  Excavator  Unit  1  20.000.000,0  20.000.000,0 
J u m l a h  580.000.000,0 

PT. SARANA ANTAR NUSA PEREKAYASA  2  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 kg Pengadaan Tiang Pancang Pipa Baja 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Tiang pancang baja dia. 508 mm  kg  1,0000  15.170,00  15.170,00 
2  Lahan tempat stock material  kg  1,0000  250,00  250,00 

Jumlah Bahan  15.420,00 

Alat : 
Biaya penumpukan & Persiapan 
1  Crane service  Jam  0,0003  796.000,00  225,62 

Upah : 
1  Pekerja  hari  0,00021  84.000,00  17,86 
2  Mandor  hari  0,000021  117.000,00  2,49 

Jumlah Jasa  240,00 
Jumlah Bahan & Jasa  15.660,00 
1 m' Pengangkutan Tiang Pancang Ke Lokasi Pemancangan + 200 m 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 

Jumlah Bahan  ‐ 

Alat :  untuk 20 batang 
1  Crane service  Jam  2,5000  796.000,00  1.990.000,00 
2  Crane Pancang  Jam  3,0000  825.000,00  2.475.000,00 
3  Ponton Pancang  Jam  3,0000  3.750.000,00  11.250.000,00 
4  Tug Boad  Jam  0,7500  3.500.000,00  2.625.000,00 
5  Perahu/Sampan  Jam  3,0000  50.000,00  150.000,00 

Upah : 
1  Pekerja  hari  3,00000  84.000,00  252.000,00 
2  Mandor  hari  0,30000  117.000,00  35.100,00 
3  Operator  hari  1,50000  151.000,00  226.500,00 
4  Pembantu Operator  hari  1,500000  134.000,00  201.000,00 

Jumlah Jasa untuk 20 btg  19.204.600,00 
Jumlah Bahan & Jasa  19.204.600,00 
Biaya untuk 1 m'  96.023,00 

PT. SARANA ANTAR NUSA PEREKAYASA  3  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m' Pemancangan Tiang Pancang Tegak dia. 508 mm, 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 

‐ 

Alat : 
1  Ponton pancang  Jam  2,0000  3.750.000,00  7.500.000,00 
2  Crane pancang  Jam  2,0000  825.000,00  1.650.000,00 
3  Crane Service  Jam  2,0000  796.000,00  1.592.000,00 
4  Diesel hammer, K.35  Jam  2,0000  450.000,00  900.000,00 

Upah : 
1  Pekerja  hari  2,0000  84.000,00  168.000,00 
2  Mandor  hari  0,2000  117.000,00  23.400,00 
3  Operator  hari  0,7500  151.000,00  113.250,00 
4  Pembantu Operator  hari  0,5000  134.000,00  67.000,00 

Jumlah Jasa Untuk 24 m'  12.013.650,00 
Jumlah Jasa Untuk 1 m'  500.560,00 

1 m' Pemancangan Tiang Pancang Miring dia. 508 mm, 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 

‐ 

Alat : 
1  Ponton pancang  Jam  2,5000  3.750.000,00  9.375.000,00 
2  Crane pancang  Jam  2,5000  825.000,00  2.062.500,00 
3  Crane Service  Jam  2,5000  796.000,00  1.990.000,00 
4  Diesel hammer, K.35  Jam  2,5000  450.000,00  1.125.000,00 

Upah : 
1  Pekerja  hari  2,5000  84.000,00  210.000,00 
2  Mandor  hari  0,2500  117.000,00  29.250,00 
3  Operator  hari  0,9375  151.000,00  141.562,50 
4  Pembantu Operator  hari  0,6250  134.000,00  83.750,00 

Jumlah Jasa Untuk 24 m'  15.017.060,00 
Jumlah Jasa Untuk 1 m'  625.710,00 

PT. SARANA ANTAR NUSA PEREKAYASA  4  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

Ea. Penyambungan Tiang Pancang dia. 508 mm, 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Kawat Las  kg  5,0000  23.500,00  117.500,00 
2  Test Penetrans  ls  1,0000  45.000,00  45.000,00 
3  Cat Proteksi Sambungan  ls  1,0000  22.500,00  22.500,00 
(anti karat) 
Jumlah Bahan  185.000,00 

Alat : 
1  Mesin las  Jam  1,2000  188.000,00  225.600,00 
2  Genset  jam  0,6000  250.000,00  150.000,00 
3  Crane pancang  Jam  0,3000  825.000,00  247.500,00 

Upah : 
1  Pekerja  hari  0,1500  84.000,00  12.600,00 
2  Mandor  hari  0,0150  117.000,00  1.755,00 
3  Tukang las  hari  0,1500  134.000,00  20.100,00 

Jumlah Jasa  657.550,00 
Jumlah Jasa Untuk 1 Titik  842.550,00 

1 Titik. Pemotongan Kepala Tiang Pancang dia. 508 mm, 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Perancah, 1  m2  2,2500  69.265,00  155.846,25 

Jumlah Bahan  155.840,00 

Alat : 
1  Mesin las  Jam  0,7500  188.000,00  141.000,00 
2  Perahu  jam  0,7500  50.000,00  37.500,00 
3  Alat Bantu  ls  1,0000  1.000,00  1.000,00 

Upah : 
1  Pekerja  hari  0,5000  84.000,00  42.000,00 
2  Mandor  hari  0,0500  117.000,00  5.850,00 
3  Tukang las  hari  0,1875  134.000,00  25.125,00 

Jumlah Jasa  252.470,00 
Jumlah Jasa dan Bahan  408.310,00 

PT. SARANA ANTAR NUSA PEREKAYASA  5  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 Titik, Beton Isian Tiang Pancang, dia. 508 mm 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Beton K‐350  m3  0,2761  1.639.950,00  452.769,58 
2  Besi beton  kg  55,0000  23.170,00  1.274.350,00 
3  Pelat tebal : 10 mm  kg  15,0000  17.500,00  262.499,92 
4  Perancah, 1  m2  2,2500  69.265,00  155.846,25 

Jumlah Bahan  2.145.460,00 

Alat : 
1  Vibrator Concrete  Jam  1,2500  53.000,00  66.250,00 
2  Perahu  jam  1,2500  50.000,00  62.500,00 

Upah : 
1  Pekerja  hari  0,7813  84.000,00  65.625,00 
2  Mandor  hari  0,0781  117.000,00  9.140,63 
3  Tukang batu  hari  0,1563  134.000,00  20.937,50 

Jumlah Jasa  224.450,00 
Jumlah Jasa dan Bahan  2.369.910,00 

m3 Beton Pile Cap, (1,0 x 1,0 x 1,0) 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Beton K‐350  m3  1,0500  1.639.950,00  1.721.947,50 
2  Besi beton  kg  180,0000  23.170,00  4.170.600,00 
3  Bekisting  m2  5,0000  243.005,00  1.215.025,00 
4  Perancah, 2  m2  1,0000  274.440,00  274.440,00 
5  Jembatan Sementara/Perancah  m2  2,0000  69.265,00  138.530,00 

Jumlah Bahan  7.520.540,00 

Alat : 
1  Vibrator Concrete  Jam  0,8333  53.000,00  44.166,67 
2  Gerobak  Jam  8,0000  25.000,00  200.000,00 

Upah : 
1  Pekerja  hari  1,0417  84.000,00  87.500,00 
2  Tukang Batu  hari  0,2083  134.000,00  27.916,67 
3  Mandor  hari  0,1042  117.000,00  12.187,50 

Jumlah Jasa  371.770,00 
Jumlah Jasa dan Bahan  7.892.310,00 

PT. SARANA ANTAR NUSA PEREKAYASA  6  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

m3 Beton Pile Cap, (1,0 x 2,0 x 1,0) 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Beton K‐350  m3  1,0500  1.639.950,00  1.721.947,50 
2  Besi beton  kg  160,0000  23.170,00  3.707.200,00 
3  Bekisting  m2  4,0000  243.005,00  972.020,00 
4  Perancah, 2  m2  1,0000  274.440,00  274.440,00 
5  Jembatan Sementara/Perancah  m2  2,0000  69.265,00  138.530,00 

Jumlah Bahan  6.814.130,00 

Alat : 
1  Vibrator Concrete  Jam  0,8333  53.000,00  44.166,67 
2  Gerobak  Jam  8,0000  25.000,00  200.000,00 

Upah : 
1  Pekerja  hari  1,0417  84.000,00  87.500,00 
2  Tukang Batu  hari  0,2083  134.000,00  27.916,67 
3  Mandor  hari  0,1042  117.000,00  12.187,50 

Jumlah Jasa  371.770,00 
Jumlah Jasa dan Bahan  7.185.900,00 

m3 Balok Dudukan Fender, h : 250 cm 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Beton K‐350  m3  1,0500  1.639.950,00  1.721.947,50 
2  Besi beton  kg  145,0000  23.170,00  3.359.649,97 
3  Bekisting  m2  5,0000  243.005,00  1.215.025,35 
4  Perancah, 2  m2  2,8500  274.440,00  782.154,00 

Jumlah Bahan  7.078.770,00 

Alat : 
1  Vibrator Concrete  Jam  0,8333  53.000,00  44.166,67 
2  Gerobak  Jam  8,0000  25.000,00  200.000,00 

Upah : 
1  Pekerja  hari  1,0417  84.000,00  87.500,00 
2  Tukang Batu  hari  0,2083  134.000,00  27.916,67 
3  Mandor  hari  0,1042  117.000,00  12.187,50 

Jumlah Jasa  371.770,00 
Jumlah Jasa dan Bahan  7.450.540,00 

PT. SARANA ANTAR NUSA PEREKAYASA  7  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3 Beton Balok Melintang Dermaga, 50/80 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐350  m3  1,0500  1.639.950,00  1.721.947,50 
2  Besi Beton  kg  90,0000  23.170,00  2.085.300,00 
3  Begisting  m2  3,7500  243.005,00  911.268,75 
4  Perancah, 2  m2  2,8500  274.440,00  782.154,00 

Jumlah Bahan  5.500.670,00 

Alat : 
1  Gerobak  Jam  8,0000  25.000,00  200.000,00 
2  Vibrator Concrete  jam  0,8333  53.000,00  44.166,67 

Upah : 
1  Pekerja  hari  1,0417  84.000,00  87.500,00 
2  Tukang Batu  hari  0,2083  134.000,00  27.916,67 
3  Mandor  hari  0,1042  117.000,00  12.187,50 

Jumlah Jasa  371.770,00 
Jumlah Jasa dan Bahan  5.872.440,00 

1 m3 Beton Balok Memanjang Dermaga, 50/80 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐350  m3  1,0500  1.639.950,00  1.721.947,50 
2  Besi Beton  kg  90,0000  23.170,00  2.085.300,00 
3  Begisting  m2  3,7500  243.005,00  911.268,75 
4  Perancah, 2  m2  2,8500  274.440,00  782.154,00 

Jumlah Bahan  5.500.670,00 

Alat : 
1  Gerobak  Jam  8,0000  25.000,00  200.000,00 
2  Vibrator Concrete  jam  0,8333  53.000,00  44.166,67 

Upah : 
1  Pekerja  hari  1,0417  84.000,00  87.500,00 
2  Tukang Batu  hari  0,2083  134.000,00  27.916,67 
3  Mandor  hari  0,1042  117.000,00  12.187,50 

Jumlah Jasa  371.770,00 
Jumlah Jasa dan Bahan  5.872.440,00 

PT. SARANA ANTAR NUSA PEREKAYASA  8  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3 Pelat Lantai Dermaga, t : 0,30 m 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐350  m3  1,0500  1.639.950,00  1.721.947,50 
2  Besi Beton  kg  150,0000  23.170,00  3.475.499,92 
3  Begisting  m2  3,5000  243.005,00  850.518,31 
4  Perancah, 2  m2  3,5000  274.440,00  960.540,91 

Jumlah Bahan  7.008.500,00 

Alat : 
1  Gerobak  Jam  6,0000  25.000,00  150.000,00 
2  Vibrator Concrete  jam  1,0000  53.000,00  53.000,00 
3  Alat bantu  ls  1,0000  1.000,00  1.000,00 

Upah : 
1  Pekerja  hari  1,2500  84.000,00  105.000,00 
2  Tukang Batu  hari  0,5000  134.000,00  67.000,00 
3  Mandor  hari  0,1250  117.000,00  14.625,00 

Jumlah Jasa  390.620,00 
Jumlah Jasa dan Bahan  7.399.120,00 

1 bh Pengadaan & Pemasangan Fender Type V, 600H x 1500L 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Fender Type V, 600H x 2000L  set  1,0000  61.787.000,0  61.787.000,00 

Jumlah Bahan  61.787.000,00 

Alat : 
1  Truck Crane  Jam  1,0000  321.400,00  321.400,00 
2  Perahu  jam  2,0000  50.000,00  100.000,00 
3  Alat bantu/Kunci Moment  ls  1,0000  20.000,00  20.000,00 

Upah : 
1  Pekerja  hari  0,5000  84.000,00  42.000,00 
2  Operator  hari  0,1250  151.000,00  18.875,00 
3  Mandor  hari  0,0500  117.000,00  5.850,00 

Jumlah Jasa  508.120,00 
Jumlah Jasa dan Bahan  62.295.120,00 

PT. SARANA ANTAR NUSA PEREKAYASA  9  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 bh Bollard Kapasitas 70 ton 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Bollard Kapasitas 70 ton  set  1,0000  47.894.000,0  47.894.000,00 
2  Beton K‐350  m3  0,0500  ‐  ‐ 
3  Besi Beton 4 D 25  kg  15,4000  23.170,00  356.818,00 

Jumlah Bahan  48.250.810,00 

Alat : 
1  Truck Crane  Jam  0,5000  321.400,00  160.700,00 
2  Alat bantu/Kunci Moment  ls  1,0000  10.000,00  10.000,00 

Upah : 
1  Pekerja  hari  0,2500  84.000,00  21.000,00 
2  Operator  hari  0,0625  151.000,00  9.437,50 
3  Mandor  hari  0,0250  117.000,00  2.925,00 

Jumlah Jasa  204.060,00 
Jumlah Jasa dan Bahan  48.454.870,00 

1 m' Siku Dilatasi L 100x100x10, Galvanice 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Besi siku L100x100x10, Galvanice  kg  16,0000  17.500,00  280.000,00 
2  Besi angkur ke beton, dia. 10 mm  kg  0,5000  23.170,00  11.585,00 

Jumlah Bahan  291.580,00 

Alat : 
1  Mesin las  Jam  0,2500  188.000,00  47.000,00 
2  Alata bantu  ls  1,0000  2.500,00  2.500,00 

Upah : 
1  Pekerja  hari  0,0625  84.000,00  5.250,00 
2  Tukang Las  hari  0,0313  151.000,00  4.718,75 
3  Mandor  hari  0,0063  117.000,00  731,25 

Jumlah Jasa  60.200,00 
Jumlah Jasa dan Bahan  351.780,00 

PT. SARANA ANTAR NUSA PEREKAYASA  10  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3, Beton List Plank, 0,2/0,5 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐350  m3  1,0500  1.639.950,00  1.721.947,50 
2  Besi Beton  kg  70,0000  23.170,00  1.621.900,00 
3  Begisting  m2  12,0000  243.005,00  2.916.060,00 

Jumlah Bahan  6.259.907,50 

Alat : 
1  Gerobak  Jam  4,0000  25.000,00  100.000,00 
2  Vibrator Concrete  jam  1,2500  53.000,00  66.250,00 

Upah : 
1  Pekerja  hari  0,9375  84.000,00  78.750,00 
2  Tukang Batu  hari  0,1563  134.000,00  20.937,50 
3  Mandor  hari  0,0938  117.000,00  10.968,75 

Jumlah Jasa  276.900,00 
Jumlah Jasa dan Bahan  6.536.807,50 

1 m3 Pembongkaran Beton berikut Besi Tulangan 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 

Jumlah Bahan  ‐ 

Alat : 
1  Demolition drill  Jam  6,0000  125.000,00  750.000,00 
2  Generator set  Jam  1,5000  250.000,00  375.000,00 
3  Crane Service  Jam  0,7500  796.000,00  597.000,00 
4  Mesin Las  Jam  3,0000  188.000,00  564.000,00 

Upah : 
1  Pekerja  hari  1,5000  84.000,00  126.000,00 
2  Mandor  hari  0,1500  117.000,00  17.550,00 
3  Tukang Las  hari  0,3750  134.000,00  50.250,00 
4  Operator  hari  1,1250  151.000,00  169.875,00 
5  Pembantu Operator  hari  1,1250  84.000,00  94.500,00 

Jumlah Jasa  2.744.170,00 

PT. SARANA ANTAR NUSA PEREKAYASA  11  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

Btg. Pemotongan Kepala Tiang Pancang dia. 508 mm, dan Pengangkatan 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Perancah, 1  m2  2,2500  69.265,00  155.846,25 

Jumlah Bahan  155.840,00 

Alat : 
1  Mesin las  Jam  0,7500  188.000,00  141.000,00 
2  Crane Service  Jam  0,3000  796.000,00  238.800,00 
3  Perahu  jam  0,7500  50.000,00  37.500,00 
4  Alat Bantu  ls  1,0000  1.000,00  1.000,00 

Upah : 
1  Pekerja  hari  0,5000  117.000,00  58.500,00 
2  Mandor  hari  0,0500  134.000,00  6.700,00 
3  Tukang las  hari  0,1875  151.000,00  28.312,50 

Jumlah Jasa  511.810,00 
Jumlah Jasa dan Bahan  667.650,00 

1 m2 Pemasangan Perancah 1 Berikut Pembongkarannya 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Bambu dia. 10 ‐ 15 cm  btg  50,0000  35.000,00  1.750.000,00 
2  Tali rami/Ijuk  kg  5,0000  8.500,00  42.500,00 

Jumlah Bahan untuk 16 m2  1.792.500,00 
Jumlah Bahan untuk 1 m2  112.030,00 
Jumlah Bahan untuk 1 m2 (asumsi 2 x pakai)  56.015,00 

Alat : 
1  Alat bantu  ls  1,0000  1.500,00  1.500,00 

Upah : 
1  Pekerja  hari  1,5000  84.000,00  126.000,00 
2  Tukang kayu  hari  0,5000  134.000,00  67.000,00 
3  Mandor  hari  0,1500  117.000,00  17.550,00 

Jumlah Jasa untuk 16 m2  212.050,00 
Jumlah Jasa untuk 1 m2  13.250,00 
Jumlah Jasa dan Bahan  69.265,00 

PT. SARANA ANTAR NUSA PEREKAYASA  12  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m2 Pemasangan Perancah 2 Berikut Pembongkarannya, (Perancah pengecoran) 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  WF 10" x 5.75", (2@4,5m)  kg  281,2500  17.500,00  4.921.875,00 
2  Siku L 50 x 50 x 5, (8 x 1m)  kg  30,1600  17.500,00  527.800,00 
3  Baut, 5/8" ‐ 8 cm  bh  32,0000  3.500,00  112.000,00 

Jumlah Bahan untuk 5 m'  5.561.670,00 
Jumlah Bahan untuk 1 m'  1.112.330,00 
Jumlah Bahan untuk 1 m' (asumsi 5 x pakai)  222.460,00 

Alat : 
1  Alat bantu  ls  1,0000  1.500,00  1.500,00 

Upah : 
1  Pekerja  hari  2,0000  84.000,00  168.000,00 
2  Tukang kayu  hari  0,5000  134.000,00  67.000,00 
3  Mandor  hari  0,2000  117.000,00  23.400,00 

Jumlah Jasa untuk 5 m'  259.900,00 
Jumlah Jasa untuk 1 m'  51.980,00 
Jumlah Jasa dan Bahan  274.440,00 

1 m3 Beton K‐350 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 
Bahan : 
1  Semen  kg  385,0000  2.500,00  962.500,00 
2  Pasir beton  m3  0,5100  291.000,00  148.410,00 
3  Batu split 1,0/2,0 & 2,0/3,0  m3  0,8200  416.000,00  341.120,00 
4  Karung goni  bh  10,0000  2.500,00  25.000,00 

Jumlah Bahan  1.477.030,00 
Alat : 
1  Concrete mixer  Jam  1,0000  80.000,00  80.000,00 
2  Alat bantu  ls  1,0000  1.500,00  1.500,00 

Upah : 
1  Pekerja  hari  0,7500  84.000,00  63.000,00 
2  Tukang batu  hari  0,1250  134.000,00  16.750,00 
3  Mandor  hari  0,0125  134.000,00  1.675,00 

Jumlah Jasa  162.920,00 
Jumlah Jasa dan Bahan  1.639.950,00 

PT. SARANA ANTAR NUSA PEREKAYASA  13  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 kg Pembesian Tulangan Beton 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 
Bahan : 
1  Besi beton  kg  1,0500  17.500,00  18.375,00 
2  Kawat bendrat  kg  0,0500  22.900,00  1.145,00 
Jumlah Bahan  19.520,00 
Alat : 
1  Bar Cutter  Jam  0,0083  60.000,00  500,00 
2  Bar Bender  Jam  0,0083  60.000,00  500,00 
3  Generator set  Jam  0,0083  250.000,00  2.083,33 
4  Alat bantu  ls  1,0000  250,00  250,00 
Upah : 
1  Pekerja  hari  0,0021  84.000,00  175,00 
2  Tukang besi  hari  0,0010  134.000,00  139,58 
3  Mandor  hari  0,0001  134.000,00  6,98 
Jumlah Jasa  3.650,00 
Jumlah Jasa dan Bahan  23.170,00 

1 m2 Pemasangan Begisting Berikut Pembongkarannya 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Kayu klas 2  m3  0,0060  2.563.500,00  15.381,00 
2  Multiplek film t = 12 mm  m2  1,0500  73.300,00  76.965,00 
3  Besi siku 50*50*5  kg  4,4800  17.500,00  78.400,00 
4  Dyna bolt dia. 0,5"  bh  5,0000  12.500,00  62.500,00 
5  Baut/mur  bh  5,0000  7.500,00  37.500,00 
6  Minyak begisting  ltr  0,0500  27.500,00  1.375,00 
7  Seal karet  m  2,4000  27.500,00  66.000,00 
8  Paku  kg  0,2500  18.500,00  4.625,00 
9  Kawat las  kg  0,1000  23.500,00  2.350,00 
Jumlah Bahan  345.090,00 
Alat : 
1  Mesin las  Jam  0,0500  188.000,00  9.400,00 
2  Alat bantu  ls  1,0000  ‐  ‐ 
Upah : 
1  Pekerja  hari  0,8000  84.000,00  67.200,00 
2  Tukang kayu  hari  0,3000  134.000,00  40.200,00 
3  Tukang las  hari  0,1000  134.000,00  13.400,00 
4  Mandor  hari  0,0800  134.000,00  10.720,00 
Jumlah Jasa  140.920,00 
Jumlah Jasa dan Bahan  486.010,00 
Asumsi dipakai 2 x  243.005,00 
PT. SARANA ANTAR NUSA PEREKAYASA  14  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m' Beton Kanstin 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐350  m3  0,0300  1.639.950,00  49.198,50 
2  Besi Beton  kg  2,8000  23.170,00  64.876,00 
3  Begisting  m2  0,4000  243.005,00  97.202,00 
4  PVC 2" (drainase) Ka / Ki  m'  0,2500  26.000,00  6.500,00 

Jumlah Bahan  217.770,00 

Alat : 
1  Gerobak  Jam  2,0000  25.000,00  50.000,00 
2  Vibrator Concrete  jam  0,0833  53.000,00  4.416,67 

Upah : 
1  Pekerja  hari  0,0208  84.000,00  1.750,00 
2  Tukang Batu  hari  0,0100  134.000,00  1.340,00 
3  Mandor  hari  0,0021  117.000,00  243,75 

Jumlah Jasa  57.750,00 
Jumlah Jasa dan Bahan  275.520,00 

1 set, Penerangan Dermaga + Solar Cell, H : 9 m 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Beton K‐350  m3  0,1000  1.639.950,00  163.995,00 
2  Besi Tulangan  kg  11,0000  23.170,00  254.870,00 
3  Bekisting  m2  1,0000  243.005,00  243.005,00 
4  Tiang lampu solar cell lengkap +  Unit  1,0000  12.750.000,00  12.750.000,00 
baut angkur dan bolam LED 50 W 
Jumlah Bahan  13.411.870,00 

Alat : 
1  Crane, Pasang Tiang Lampu  Jam  0,2500  796.000,00  199.000,00 
2  Vibrator Concrete  Jam  0,2500  53.000,00  13.250,00 

Upah : 
1  Pekerja  hari  0,0625  84.000,00  5.250,00 
2  Tukang Lampu  hari  0,0310  134.000,00  4.154,00 
3  Operator  hari  0,0310  134.000,00  4.154,00 
4  Mandor  hari  0,0063  134.000,00  837,50 

Jumlah Jasa  226.640,00 
Jumlah Jasa dan Bahan  13.638.510,00 

PT. SARANA ANTAR NUSA PEREKAYASA  15  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

Pekerjaan Pengerukan Kolam dan Alur 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 

Jumlah Bahan  ‐ 

Alat : 
1  Kapal Keruk (CDS), Kap. 50 m3  Jam  0,0200  2.500.000,00  50.000,00 
2  Alat Bantu  ls  1,0000  2.500,00  2.500,00 

Upah : 
1  Pekerja  hari  0,0200  84.000,00  1.680,00 
2  Mandor  hari  0,0010  117.000,00  117,00 
3  Operator  hari  0,0025  151.000,00  377,50 
4  Mekanik  hari  0,0025  134.000,00  335,00 
5  Pembantu Operator  hari  0,0025  84.000,00  210,00 

Jumlah Jasa  55.210,00 
Jumlah Jasa dan Bahan  55.210,00 

Ea. Pembuatan Sepatu Tiang Pancang dia. 508 mm, 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Tiang Pancang dia 508 mm  kg  ‐  15.170,00  ‐ 
2  Kawat Las  kg  15,0000  23.500,00  352.500,00 
3  Ace telyn  kg  12,5000  16.500,00  206.250,00 

Jumlah Bahan  558.750,00 

Alat : 
1  Mesin las  Jam  1,5000  188.000,00  282.000,00 
2  Genset  jam  1,5000  250.000,00  375.000,00 
3  Regulator  jam  1,2500  125.000,00  156.250,00 
4  Crane Service  Jam  0,3000  796.000,00  238.800,00 

Upah : 
1  Pekerja  hari  0,7500  84.000,00  63.000,00 
2  Mandor  hari  0,0750  117.000,00  8.775,00 
3  Operator  hari  0,0938  151.000,00  14.156,25 
4  Tukang las  hari  0,3750  134.000,00  50.250,00 

Jumlah Jasa  1.188.230,00 
Jumlah Jasa Untuk 1 Titik  1.746.980,00 

PT. SARANA ANTAR NUSA PEREKAYASA  16  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

m2. Bobokan Pile Cap Eksisting 1992, 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Perancah begisting 1  m2  2,2500  69.265,00  155.846,25 

Jumlah Bahan  155.846,25 

Alat : 
1  Alat bantu  Ls  1,0000  2.500,00  2.500,00 

Upah : 
1  Pekerja  hari  1,5000  84.000,00  126.000,00 
2  Mandor  hari  0,1500  117.000,00  17.550,00 
3  Tukang batu  hari  0,5000  134.000,00  67.000,00 

Jumlah Jasa  213.050,00 
Jumlah Jasa dan Bahan  368.896,25 

m3. Groutting Pile Cap Eksisting 1992, 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Groutting  kg  2.270,00  4.500,00  10.215.000,00 
2  Air  ltr  795,00  250,00  198.750,00 
3  Begisting  m2  20,00  243.005,00  4.860.100,00 

Jumlah Bahan  15.273.850,00 

Alat : 
1  Air Compressor  Jam  4,0000  60.000,00  240.000,00 
2  Generator Zet  Jam  4,0000  75.000,00  300.000,00 
3  Mixer  Jam  4,0000  50.000,00  200.000,00 
4  Sagola  jam  4,0000  75.000,00  300.000,00 
5  Alat bantu  Ls  1,0000  10.000,00  10.000,00 

Upah : 
1  Pekerja  hari  3,0000  84.000,00  252.000,00 
2  Mandor  hari  0,3000  117.000,00  35.100,00 
3  Tukang batu  hari  1,0000  134.000,00  134.000,00 

Jumlah Jasa  1.471.100,00 
Jumlah Jasa dan Bahan  16.744.950,00 

PT. SARANA ANTAR NUSA PEREKAYASA  17  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3 Beton K‐225 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  371,0000  2.500,00  927.500,00 
2  Pasir beton  m3  0,4363  291.000,00  126.948,75 
3  Batu split 1,0/2,0 & 2,0/3,0  m3  0,6544  416.000,00  272.220,00 
4  Karung goni  bh  10,0000  2.500,00  25.000,00 

Jumlah Bahan  1.351.660,00 

Alat : 
1  Concrete mixer  Jam  1,0000  80.000,00  80.000,00 
2  Alat bantu  ls  1,0000  1.500,00  1.500,00 

Upah : 
1  Pekerja  hari  0,7500  84.000,00  63.000,00 
2  Tukang batu  hari  0,1250  134.000,00  16.750,00 
3  Mandor  hari  0,0750  117.000,00  8.775,00 

Jumlah Jasa  170.020,00 
Jumlah Jasa dan Bahan  1.521.680,00 

1 m3 Beton K‐125 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  275,0000  2.500,00  687.500,00 
2  Pasir beton  m3  0,5175  291.000,00  150.592,50 
3  Batu split 1,0/2,0 & 2,0/3,0  m3  0,6325  416.000,00  263.120,00 

Jumlah Bahan  1.101.210,00 

Alat : 
1  Concrete mixer  Jam  0,8333  80.000,00  66.666,67 
2  Alat bantu  ls  1,0000  1.500,00  1.500,00 

Upah : 
1  Pekerja  hari  0,8333  84.000,00  70.000,00 
2  Tukang batu  hari  0,1042  134.000,00  13.958,33 
3  Mandor  hari  0,0833  117.000,00  9.750,00 

Jumlah Jasa  161.870,00 
Jumlah Jasa dan Bahan  1.263.080,00 

PT. SARANA ANTAR NUSA PEREKAYASA  18  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3 Beton Slof, 15/25 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐225  m3  1,0500  1.521.680,00  1.597.764,00 
2  Besi Beton  kg  230,0000  23.170,00  5.329.100,00 
3  Begisting  m2  13,5000  243.005,00  3.280.575,60 

Jumlah Bahan  10.207.430,00 

Alat : 
1  Gerobak  Jam  8,0000  25.000,00  200.000,00 
2  Vibrator Concrete  jam  0,8333  80.000,00  66.666,67 

Upah : 
1  Pekerja  hari  1,0417  84.000,00  87.500,00 
2  Tukang Batu  hari  0,2083  134.000,00  27.916,67 
3  Mandor  hari  0,1042  117.000,00  12.187,50 

Jumlah Jasa  394.270,00 
Jumlah Jasa dan Bahan  10.601.700,00 

1 m3 Beton Kolom Praktis, 15/15 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐225  m3  1,0500  1.521.680,00  1.597.764,00 
2  Besi Beton  kg  205,0000  23.170,00  4.749.849,23 
3  Begisting  m2  13,5000  243.005,00  3.280.568,31 

Jumlah Bahan  9.628.180,00 

Alat : 
1  Gerobak  Jam  8,0000  25.000,00  200.000,00 
2  Vibrator Concrete  jam  1,2500  53.000,00  66.250,00 

Upah : 
1  Pekerja  hari  1,5625  84.000,00  131.250,00 
2  Tukang Batu  hari  0,3125  134.000,00  41.875,00 
3  Mandor  hari  0,1563  117.000,00  18.281,25 

Jumlah Jasa  457.650,00 
Jumlah Jasa dan Bahan  10.085.830,00 

PT. SARANA ANTAR NUSA PEREKAYASA  19  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3 Beton Ring Balok, 15/15 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐225  m3  1,0500  1.521.680,00  1.597.764,00 
2  Besi Beton  kg  205,0000  23.170,00  4.749.849,23 
3  Begisting  m2  13,5000  243.005,00  3.280.568,31 

Jumlah Bahan  9.628.180,00 

Alat : 
1  Gerobak  Jam  8,0000  25.000,00  200.000,00 
2  Vibrator Concrete  jam  1,2500  53.000,00  66.250,00 

Upah : 
1  Pekerja  hari  1,5625  84.000,00  131.250,00 
2  Tukang Batu  hari  0,3125  134.000,00  41.875,00 
3  Mandor  hari  0,1563  117.000,00  18.281,25 

Jumlah Jasa  457.650,00 
Jumlah Jasa dan Bahan  10.085.830,00 

1 m3 Beton Kuda‐Kuda, 15/25 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Material Beton K‐225  m3  1,0500  1.521.680,00  1.597.764,00 
2  Besi Beton  kg  230,0000  23.170,00  5.329.100,00 
3  Begisting  m2  21,5000  243.005,00  5.224.615,60 
4  Perancah 2  m2  0,2500  274.440,00  68.610,00 

Jumlah Bahan  12.220.080,00 

Alat : 
1  Gerobak  Jam  8,0000  25.000,00  200.000,00 
2  Vibrator Concrete  jam  1,2500  53.000,00  66.250,00 

Upah : 
1  Pekerja  hari  1,5625  84.000,00  131.250,00 
2  Tukang Batu  hari  0,3125  134.000,00  41.875,00 
3  Mandor  hari  0,1563  117.000,00  18.281,25 

Jumlah Jasa  457.650,00 
Jumlah Jasa dan Bahan  12.677.730,00 

PT. SARANA ANTAR NUSA PEREKAYASA  20  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3 Pasangan Batu Kali, 1 : 4 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  145,0000  2.500,00  362.500,00 
2  Pasir pasang  m3  0,5440  280.000,00  152.320,00 
3  Batu kali 15/25  m3  1,1000  306.000,00  336.600,00 

Jumlah Bahan  851.420,00 

Alat : 
1  Concrete mixer  Jam  0,8333  80.000,00  66.666,67 
2  Alat bantu  ls  1,0000  1.500,00  1.500,00 

Upah : 
1  Pekerja  hari  0,1500  84.000,00  12.600,00 
2  Tukang batu  hari  0,7500  134.000,00  100.500,00 
3  Mandor  hari  0,0150  117.000,00  1.755,00 

Jumlah Jasa  183.020,00 
Jumlah Jasa dan Bahan  1.034.440,00 

1 m2 Pasangan Bata Merah, 1 : 4 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  11,5000  2.500,00  28.750,00 
2  Pasir pasang  m3  0,0430  280.000,00  12.040,00 
3  Batu bata merah  bh  70,0000  550,00  38.500,00 

Jumlah Bahan  79.290,00 

Alat : 
1  Concrete mixer  Jam  0,3000  80.000,00  24.000,00 
2  Alat bantu  ls  1,0000  250,00  250,00 

Upah : 
1  Pekerja  hari  0,1875  84.000,00  15.750,00 
2  Tukang batu  hari  0,0375  134.000,00  5.025,00 
3  Mandor  hari  0,0188  117.000,00  2.193,75 

Jumlah Jasa  47.210,00 
Jumlah Jasa dan Bahan  126.500,00 

PT. SARANA ANTAR NUSA PEREKAYASA  21  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m3 Galian Tanah Pondasi 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 

Jumlah Bahan  ‐ 

Alat : 

Upah : 
1  Pekerja  hari  0,7500  84.000,00  63.000,00 
2  Mandor  hari  0,0750  117.000,00  8.775,00 

Jumlah Jasa  71.770,00 
Jumlah Jasa dan Bahan  71.770,00 

1 m3 Urugan Pasir Dibawah Pondasi 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Pasir Urug  m3  1,2000  203.500,00  244.200,00 
Jumlah Bahan  244.200,00 

Alat : 

Upah : 
1  Pekerja  hari  0,3000  84.000,00  25.200,00 
2  Mandor  hari  0,0300  117.000,00  3.510,00 

Jumlah Jasa  28.710,00 
Jumlah Jasa dan Bahan  272.910,00 

1 m3 Urugan Tanah Kembali 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 

Jumlah Bahan  ‐ 

Alat : 

Upah : 
1  Pekerja  hari  0,2500  84.000,00  21.000,00 
2  Mandor  hari  0,0250  117.000,00  2.925,00 

Jumlah Jasa  23.920,00 
Jumlah Jasa dan Bahan  23.920,00 
PT. SARANA ANTAR NUSA PEREKAYASA  22  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m2 Pekerjaan Plesteran, 1 : 4; t : 15 cm 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  6,2500  2.500,00  15.625,00 
2  Pasir pasang  m3  0,0240  280.000,00  6.720,00 

Jumlah Bahan  22.340,00 

Alat : 
1  Concrete mixer  Jam  0,2500  80.000,00  20.000,00 
2  Alat bantu  ls  1,0000  250,00  250,00 

Upah : 
1  Pekerja  hari  0,1563  84.000,00  13.125,00 
2  Tukang batu  hari  0,0313  134.000,00  4.187,50 
3  Mandor  hari  0,0156  117.000,00  1.828,13 

Jumlah Jasa  39.390,00 
Jumlah Jasa dan Bahan  61.730,00 

1 m2 Pasang Plafond Eternit GRC t : 4 mm 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Eternit GRC, t : 4 mm, ( 1 x 1m)  m2  1,0000  21.500,00  21.500,00 
2  Paku Eternit  kg  0,1000  18.500,00  1.850,00 

Jumlah Bahan  23.350,00 

Alat : 

Upah : 
1  Pekerja  hari  0,0300  84.000,00  2.520,00 
2  Tukang kayu  hari  0,0800  134.000,00  10.720,00 
3  Mandor  hari  0,0030  117.000,00  351,00 

Jumlah Jasa  13.590,00 
Jumlah Jasa dan Bahan  36.940,00 

PT. SARANA ANTAR NUSA PEREKAYASA  23  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m2 Pasang Rangka Plafond Hollo, (50 x 100) 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Hollo 4cm x 4mm  m'  3,0000  11.500,00  34.500,00 
2  Paku Skrup  kg  0,2000  18.500,00  3.700,00 

Jumlah Bahan  38.200,00 

Alat : 

Upah : 
1  Pekerja  hari  0,1500  84.000,00  12.600,00 
2  Tukang kayu  hari  0,3000  134.000,00  40.200,00 
3  Mandor  hari  0,0150  117.000,00  1.755,00 

Jumlah Jasa  54.550,00 
Jumlah Jasa dan Bahan  92.750,00 

1 m2 Pasang Keramik Lantai, 40/40 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  6,2500  2.500,00  15.625,00 
2  Pasir pasang  m3  0,0240  280.000,00  6.720,00 
3  Keramik 40/40  m2  1,0000  75.000,00  75.000,00 
4  Semen Warna  kg  0,7500  3.500,00  2.625,00 

Jumlah Bahan  99.970,00 

Alat : 
1  Concrete mixer  Jam  0,2000  80.000,00  16.000,00 
2  Alat bantu  ls  1,0000  250,00  250,00 

Upah : 
1  Pekerja  hari  0,2500  84.000,00  21.000,00 
2  Tukang batu  hari  0,1250  134.000,00  16.750,00 
3  Mandor  hari  0,0250  117.000,00  2.925,00 

Jumlah Jasa  56.920,00 
Jumlah Jasa dan Bahan  156.890,00 

PT. SARANA ANTAR NUSA PEREKAYASA  24  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m2 Pasang Keramik Lantai, 20/20 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  6,2500  2.500,00  15.625,00 
2  Pasir pasang  m3  0,0240  280.000,00  6.720,00 
3  Keramik 20/20  m2  1,0000  70.000,00  70.000,00 
4  Semen Warna  kg  0,8000  3.500,00  2.800,00 

Jumlah Bahan  95.140,00 

Alat : 
1  Concrete mixer  Jam  0,2000  80.000,00  16.000,00 
2  Alat bantu  ls  1,0000  250,00  250,00 

Upah : 
1  Pekerja  hari  0,2500  84.000,00  21.000,00 
2  Tukang batu  hari  0,1250  134.000,00  16.750,00 
3  Mandor  hari  0,0250  117.000,00  2.925,00 

Jumlah Jasa  56.920,00 
Jumlah Jasa dan Bahan  152.060,00 

1 m2 Pasang Keramik Dinding, 20/25 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Semen  kg  6,2500  2.500,00  15.625,00 
2  Pasir pasang  m3  0,0240  280.000,00  6.720,00 
3  Keramik 20/25  m2  1,0000  85.000,00  85.000,00 
4  Semen Warna  kg  0,7500  3.500,00  2.625,00 

Jumlah Bahan  109.970,00 

Alat : 
1  Concrete mixer  Jam  0,2000  80.000,00  16.000,00 
2  Alat bantu  ls  1,0000  250,00  250,00 

Upah : 
1  Pekerja  hari  0,2500  84.000,00  21.000,00 
2  Tukang batu  hari  0,1250  134.000,00  16.750,00 
3  Mandor  hari  0,0250  117.000,00  2.925,00 

Jumlah Jasa  56.920,00 
Jumlah Jasa dan Bahan  166.890,00 
PT. SARANA ANTAR NUSA PEREKAYASA  25  DED Luwuk Banggai
ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m2 Pengecatan Dinding Tembok Baru 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Cat Dasar  kg  0,2500  29.500,00  7.375,00 
2  Cat Dinding ICI  kg  0,3250  42.500,00  13.812,50 

Jumlah Bahan  21.180,00 

Alat : 
1  Amplas  lbr  0,2500  4.500,00  1.125,00 
2  Alat Bantu  ls  1,0000  250,00  250,00 

Upah : 
1  Pekerja  hari  0,0250  84.000,00  2.100,00 
2  Tukang Cat  hari  0,0650  134.000,00  8.710,00 
3  Mandor  hari  0,0025  117.000,00  292,50 

Jumlah Jasa  12.470,00 
Jumlah Jasa dan Bahan  33.650,00 

1 m2 Pengecatan Plafod 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Cat Dasar  kg  0,2000  29.500,00  5.900,00 
2  Cat Plafond  kg  0,3250  32.500,00  10.562,50 

Jumlah Bahan  16.460,00 

Alat : 
1  Roll cat  bh  0,1000  24.000,00  2.400,00 
2  Alat Bantu  ls  1,0000  250,00  250,00 

Upah : 
1  Pekerja  hari  0,0250  84.000,00  2.100,00 
2  Tukang Cat  hari  0,0650  134.000,00  8.710,00 
3  Mandor  hari  0,0025  117.000,00  292,50 

Jumlah Jasa  13.750,00 
Jumlah Jasa dan Bahan  30.210,00 

PT. SARANA ANTAR NUSA PEREKAYASA  26  DED Luwuk Banggai


ANALISA HARGA SATUAN 
DETAIL ENGINEERING DESIGN (DED) 
PELABUHAN LUWUK BANGGAI ‐ TA 2015 

1 m2 Pengecatan Bidang Kayu 
Harga Satuan  Jumlah Harga 
No.  U r a I a n  Satuan  Volume 
(Rp.)  (Rp.) 

Bahan : 
1  Cat Meni  kg  0,2000  27.500,00  5.500,00 
2  Cat Kayu  kg  0,3250  35.500,00  11.537,50 
3  Dempul  kg  0,1500  20.000,00  3.000,00 

Jumlah Bahan  20.030,00 

Alat : 
1  Kwas Cat  bh  0,1000  24.000,00  2.400,00 
2  Amplas  bh  0,2500  4.500,00  1.125,00 

Upah : 
1  Pekerja  hari  0,0200  84.000,00  1.680,00 
2  Tukang Cat  hari  0,0650  134.000,00  8.710,00 
3  Mandor  hari  0,0020  117.000,00  234,00 

Jumlah Jasa  14.140,00 
Jumlah Jasa dan Bahan  34.170,00 

PT. SARANA ANTAR NUSA PEREKAYASA  27  DED Luwuk Banggai



Mob 100 m 

Lokal  0 
Lokal  0 
Lokal  0 
Lokal  1.500.000,00 
Lokal  4.000.000,00 
Lokal  1.200.000,00 
Mksr ‐ Luwuk = 650 km  360  mil  1,75  675 
Mksar  243.000.000,00  20.000.000,00 
Mksar  20.000.000,00 
Mksar  Keruk  3.000.000,00 
300.000.000,00  300.000.000,00 
Mksar  0 

Dermaga  598.000.000,00  349.700.000,00 


87.425.000,00 

40 jam ato 5 hr 

########### 

PT. SARANA ANTAR NUSA PEREKAYASA  28  DED Luwuk Banggai


277,78  ,500 rb/btg 

30  Naik, turun dan Transportasi 

6  Orang

15.660,00 

150 
180 
180
45 
180 


PT. SARANA ANTAR NUSA PEREKAYASA  29  DED Luwuk Banggai


120 

8  orang 

3  Operator 
2  Orang 

24 
500.568,75 

150 

8  orang 

3  Operator 
2  Orang 

24 
625.710,83 

PT. SARANA ANTAR NUSA PEREKAYASA  30  DED Luwuk Banggai


0,60  0,60  = 2 tkg Las, 

2  orang 

2  orang 

842.550,00 

45 



PT. SARANA ANTAR NUSA PEREKAYASA  31  DED Luwuk Banggai


10

75 

11 

3,8462 

50  menit 
8  8 GEROBAK 

10  orang 

PT. SARANA ANTAR NUSA PEREKAYASA  32  DED Luwuk Banggai


12

50 
8

10 
2

13

50 
8

10 

PT. SARANA ANTAR NUSA PEREKAYASA  33  DED Luwuk Banggai


14 

3,75 
2,5 

8
50

10 
2

15 

8
50

10 

PT. SARANA ANTAR NUSA PEREKAYASA  34  DED Luwuk Banggai


16 

6,25 
3,3500  2,35  3,50  3,3333 

6
60  menit 

10  orang 
4

17

10  Truck : Rp.  30.000.000,0 

60  menit 


########### 

PT. SARANA ANTAR NUSA PEREKAYASA  35  DED Luwuk Banggai


18

15  Truck : Rp. 

30 


1

19

15  menit 

2  orang 

351.780,00 

PT. SARANA ANTAR NUSA PEREKAYASA  36  DED Luwuk Banggai


20 

4
75 


1

21 

4  alat 
90 

2  Mesin Las 

8  orang 



PT. SARANA ANTAR NUSA PEREKAYASA  37  DED Luwuk Banggai


22

45
18 



2

23 

69.265,00 

PT. SARANA ANTAR NUSA PEREKAYASA  38  DED Luwuk Banggai


24 

281,25 
30,16 

8 Orang 
2 orang 

274.440,00 

25

60  menit 


PT. SARANA ANTAR NUSA PEREKAYASA  39  DED Luwuk Banggai


26 

0,5 
0,5 
0,5 


23.170,00 

27 

486.010,00 

PT. SARANA ANTAR NUSA PEREKAYASA  40  DED Luwuk Banggai


28 

2  2 Gerobak 
5  5 menit 

2  2 orang 
1  1 orang 

275.520,00 

29 

PT. SARANA ANTAR NUSA PEREKAYASA  41  DED Luwuk Banggai


30 

1,2 



1

31

90

75
18 

PT. SARANA ANTAR NUSA PEREKAYASA  42  DED Luwuk Banggai


32

90

30

33 

240 

Dermaga 

PT. SARANA ANTAR NUSA PEREKAYASA  43  DED Luwuk Banggai


Gedung 
34 

335  371,0 
0,82  698,0 
0,87  1.047,0 

60  menit 


1

35 

275,0 
828,0 
1.012,0 

50 


PT. SARANA ANTAR NUSA PEREKAYASA  44  DED Luwuk Banggai


36

50

10 
2

37

75

10 

PT. SARANA ANTAR NUSA PEREKAYASA  45  DED Luwuk Banggai


38 

75,00 

10,00 
2,00 

39

75

10 

PT. SARANA ANTAR NUSA PEREKAYASA  46  DED Luwuk Banggai


40

50

41

18 

PT. SARANA ANTAR NUSA PEREKAYASA  47  DED Luwuk Banggai


42

43

44 

PT. SARANA ANTAR NUSA PEREKAYASA  48  DED Luwuk Banggai


45

15 

46 

PT. SARANA ANTAR NUSA PEREKAYASA  49  DED Luwuk Banggai


47

48

12 

PT. SARANA ANTAR NUSA PEREKAYASA  50  DED Luwuk Banggai


49

12

50

12 

PT. SARANA ANTAR NUSA PEREKAYASA  51  DED Luwuk Banggai


51

12

52

12 

PT. SARANA ANTAR NUSA PEREKAYASA  52  DED Luwuk Banggai


53

54 

PT. SARANA ANTAR NUSA PEREKAYASA  53  DED Luwuk Banggai


DAFTAR HARGA SATUAN UPAH 

Pekerjaan  : DETAIL ENGINEERING DESIGN (DED) 
Lokasi  : PELABUHAN LUWUK BANGGAI ‐ TA 2015 

No  Uraian  Satuan  Harga satuan 

III  Tenaga Kerja 

1  Mandor  org/hr  117.000,00 


2  Kepala Tukang  org/hr  151.000,00 
3  Pekerja  org/hr  84.000,00 
4  Tukang Batu  org/hr  134.000,00 
5  Tukang Kayu  org/hr  134.000,00 
6  Tukang Cat  org/hr  134.000,00 
7  Tukang Besi  org/hr  134.000,00 
8  Tukang Las  org/hr  134.000,00 
9  Penjaga Malam  org/hr  84.000,00 
10  Operator  org/hr  151.000,00 
11  Mekanik  org/hr  134.000,00 
12  Surveyor  org/hr  151.000,00 
13  Pembantu Surveyor  org/hr  134.000,00 

Sumber : 
*  JURNAL Edisi 34, Tahun 2015 
*  Standar Satuan Harga Tahun 2015 
Pemerintah Daerah Kabupaten Banggai Provinsi Sulawesi Tengah 

DED Pelabuhan Luwuk Tahun 2015
117.000 
151.000 
84.000 
134.000 
134.000 
134.000 
134.000 
134.000 
84.000 
134.000 
134.000 
151.000 
134.000 

DED Pelabuhan Luwuk Tahun 2015
DAFTAR HARGA SATUAN ALAT 

Pekerjaan  : DETAIL ENGINEERING DESIGN (DED) 
Lokasi  : PELABUHAN LUWUK BANGGAI ‐ TA 2015 

No  Uraian  Satuan  Harga Satuan ( Rp. ) 

II  Peralatan 

1  Concrete Mixer 0,3 ­ 0,6 m3  jam  80.000,00 


2  Concrete vibrator  jam  53.000,00 
3  Mesin las  jam  188.000,00 
4  Air Compressor  jam  60.000,00 
5  Generator Set, 25 Kv.A  jam  250.000,00 
6  Generator Set, 10 Kv.A  jam  75.000,00 
7  Sagola  jam  75.000,00 
8  Mixer  jam  50.000,00 
9  Demolition drill  jam  125.000,00 
10  Ponton Pancang,  jam  3.750.000,00 
11  Crane Pancang, kap. 50 ton  jam  825.000,00 
12  Crane Service, kap.36 ton  jam  796.000,00 
13  Excavator  jam  863.000,00 
14  Buldozer  Jam  855.000,00 
15  Tug Boad  Jam  3.500.000,00 
16  Perahu / sampan  jam  50.000,00 
17  Gerobak  Jam  25.000,00 
18  diesel Hammer, K­25  jam  450.000,00 
19  Truck Crane, kap. 20 ton  jam  321.400,00 
20  Kapal Keruk (CDS), Kap. 50 m3  Jam  2.500.000,00 
21  Concrete Pump  Jam  446.000,00 
22  Jacxk Hammer  Jam  44.000,00 
23  Bar Cutter  Jam  60.000,00 
24  Bar Bender  Jam  60.000,00 
25  Alat Ukur  Jam  150.000,00 
26  Regulator  Jam  125.000,00 
27 

Sumber : 
*  JURNAL Edisi 34, Tahun 2015 
*  Standar Satuan Harga Tahun 2015 
Pemerintah Daerah Kabupaten Banggai Provinsi Sulawesi Tengah 

DED Pelabuhan Luwuk Tahun 2015
Sewa / Jam 

80.000,0 
53.000,0 
188.000,0 
60.000,0 
783.000,0  135kVA 

125.000,0 

1.114.000,0  75 ton 
796.000,0  35 ton 
863.000,0  140 hp 

50.000,0 
25.000,0 
448.000,0  K‐25 

446.000,0 
44.000,0 

DED Pelabuhan Luwuk Tahun 2015
DAFTAR HARGA SATUAN MATERIAL 
Pekerjaan  : DETAIL ENGINEERING DESIGN (DED) 
Lokasi  : PELABUHAN LUWUK BANGGAI ‐ TA 2015 

No  Uraian  Satuan  Harga Satuan ( Rp. ) 

I  Bahan 
1  Batu Belah  m3  306.000,00 
2  Splite/Batu pecah  m3  416.000,00 
3  Pasir Beton  m3  291.000,00 
4  Pasir Pasang  m3  280.000,00 
5  Pasir urug  m3  203.500,00 
6  PC (50 Kg)  kg  2.500,00 
7  Semen warna  kg  3.500,00 
8  Material Grouting  kg  4.500,00 
9  Kawat Bendrat  kg  22.900,00 
10  Besi beton  kg  17.500,00 
11  Karung goni  bh  2.500,00 
12  Kawat las  kg  23.500,00 
13  Pipa Baja Tiang Pancang  kg  15.170,00 
14  Baja Siku­siku/Plat  kg  17.500,00 
15  Paku kayu 1" ­ 5"  kg  18.500,00 
16  Kayu klas 1  m3  5.575.000,00 
17  Kayu klas 2  m3  2.563.500,00 
18  Kayu klas 3 / Papan  m3  1.725.000,00 
19  Multiplek film t : 12 mm  m2  73.300,00 
20  Kabel NYFGBY, (4 x 6)  m  54.800,00 
21  Minyak begisting  ltr  27.500,00 
22  Cat minyak  kg  36.300,00 
23  Solar, (industri)  lt  13.200,00 
24  Fender Type V, 600H x 2000L  set  61.787.000,00 
25  Bolard Kapasitas 70 ton  bh  47.894.000,00 
26  PVC 1,5" AW  m'  12.500,00 
27  Bambu dia. 10 ­ 15 cm  btg  35.000,00 
28  Tali ijuk  kg  8.500,00 
29  Baut dia. 3/8"  bh  3.500,00 
30  Batu Bata Merah  bh  550,00 
31  Plafond Eternit GRC. T : 4 mm, ( 1 x 1m )  lbr  21.500,00 
32  Besi Hollo 4cm; t : 0,4 mm  m'  11.500,00 
33  Keramik 40 x 40  m2  75.000,00 
34  Keramik 20 x 25  m2  85.000,00 
35  Keramik 20 x 20  m2  70.000,00 
36  Cat Dinding Tembok ICI  kg  42.500,00 
37  Cat Dasar  kg  29.500,00 
38  Cat Plafond Vinilex  kg  32.500,00 
39  Cat Kayu  kg  35.500,00 
40  Klosed Jongkok warna, TOTO  bh  235.000,00 
41  Klosed Duduk TOTO  bh  2.250.000,00 
42  Orinoir lengkap TOTO, (type Muslim)  bh  1.665.000,00 
43  Wastafel bulat warna standard lengkap (TOTO)  bh  815.000,00 
44  Kran Tembok ITAP dia. 1/2"  bh  43.500,00 

Sumber : 
*  JURNAL Edisi 34, Tahun 2015 
*  Standar Satuan Harga Tahun 2015 
Pemerintah Daerah Kabupaten Banggai Provinsi Sulawesi Tengah 
DED Pelabuhan Luwuk Tahun 2015
306.000,0 
416.000,0 
291.000,0 
280.000,0 

2.500,0 

22.900,0 
17.500,0 

kg  Rp  per kg  naik/turun tak terduga 


8100  9.720  50.000  250.000.000,0  5.000  350  100  15.170 
12.500,00 
18.500,0 
5.575.000,0 

0,900 
110%  ‐  56.170.000,0  50.553.000,0 
110%  ‐  43.540.000,0 

DED Pelabuhan Luwuk Tahun 2015
Pekerjaan Pengerukan 
Cross No. 01 
Cross No. 01  Jarak (X)  Elevasi (Y)  A 
1  1,100  (5,0000)  Xn*Yn+1 : 
2  11,000  (7,0000)  (180,6450) 
3  11,000  (6,9000)  0,399 
4  6,209  (6,0000)  Yn*Xn+1 : 
5  1,100  (5,0000)  (181,4421) 



10,00  6,738  67,38  m3 

Cross No. 02 
Cross No. 02  Jarak (X)  Elevasi (Y)  A 
1  ‐  (4,0000)  Xn*Yn+1 : 
2  11,000  (7,0000)  (268,8078) 
3  15,460  (7,0000)  13,077 
4  13,000  (6,0000)  Yn*Xn+1 : 
5  7,460  (5,0000)  (294,9617) 
6  1,910  (4,0000) 
7  ‐  (3,6690) 
8  (0,700)  (3,0500) 
9  ‐  (4,0000) 

10,00  19,068  190,68  m3 

Cross No. 03 
Cross No. 03  Jarak (X)  Elevasi (Y)  A 
1  ‐  (4,0000)  Xn*Yn+1 : 
2  11,000  (7,0000)  (330,3601) 
3  19,250  (7,0000)  25,059 
4  16,548  (6,0000)  Yn*Xn+1 : 
5  11,073  (5,0000)  (380,4773) 
6  4,925  (4,0000) 
7  ‐  (3,4250) 
8  (1,510)  (3,0000) 
9  ‐  (4,0000) 

10,00  29,881  298,81  m3 

Cross No. 04
Cross No. 04  Jarak (X)  Elevasi (Y)  A 
1  ‐  (4,0000)  Xn*Yn+1 : 
2  11,000  (7,0000)  (388,5294) 
3  24,847  (7,0000)  34,704 
4  20,812  (6,0000)  Yn*Xn+1 : 
5  12,040  (5,0000)  (457,9375) 
6  5,511  (4,0000) 
7  ‐  (3,1260) 
8  (1,750)  (2,6500) 
9  ‐  (4,0000) 

10,00  30,286  302,86  m3 

Cross No. 05 
Cross No. 05  Jarak (X)  Elevasi (Y)  A 
1  8,471  (4,1500)  Xn*Yn+1 : 
2  18,950  (7,0000)  (596,6271) 
3  30,913  (7,0000)  25,867 
4  25,973  (6,0000)  Yn*Xn+1 : 
5  21,527  (5,0000)  (648,3615) 
6  8,471  (4,1500) 
7  ‐  ‐ 

10,00  21,073  210,73  m3 

Cross No. 06 
Cross No. 06  Jarak (X)  Elevasi (Y)  A 
1  17,762  (4,0000)  Xn*Yn+1 : 
2  29,446  (7,0000)  (931,2720) 
3  35,744  (7,0000)  16,279 
4  31,028  (6,0000)  Yn*Xn+1 : 
5  26,371  (5,0000)  (963,8290) 
6  21,680  (4,0000) 
7  12,462  (3,5000) 
8  17,762  (4,0000) 
9  ‐  ‐ 
10,00  8,139  81,39  m3 

Cross No. 07 
Cross No. 07  Jarak (X)  Elevasi (Y)  A 
1  27,172  (4,0000)  Xn*Yn+1 : 
2  40,292  (7,0000)  (1.022,9640) 
3  40,512  (7,0000)  0,506 
4  36,204  (6,0000)  Yn*Xn+1 : 
5  31,656  (5,0000)  (1.023,9760) 
6  27,172  (4,0000) 


VOLUME PENGERUKAN
Pekerjaan Dermaga Pengembangan
No. LUAS LUAS JARAK VOLUME KETE
CROSS RATA­RATA (M) ( M3 ) NGAN

1 0,399
6,738 10 67,378
2 13,077
19,068 10 190,678
3 25,059
29,881 10 298,813
4 34,704
30,286 10 302,856
5 25,867
21,073 10 210,729
6 16,279
8,392 10 83,922
7 0,506
TOTAL VOLUME 1.154,38
LK ‐ REPLACEMENT DERMAGA 
I  Dermaga Tahun 1992 
A Tiang Pancang Dermaga 1992 
1 Tiang Pancang Pipa Baja : dia. 508 mm 
a Tiang pancang, Dia.  =  508,0  mm  =  0,5080  m 
b Tebal Tiang pancang  =  12,0  mm  =  0,01200  m 
c Berat / m'  =  147  Kg/m' 
d Panjang / titik  =  18,0  m 
Tegak  Miring 
e Jumlah tiang pancang  =  Axis A  =  15  titik  ­ 
Axis B  =  7  titik  16,0 
Axis C  =  15  titik  ­ 
Axis D  =  7  titik  16,0 
Axis E  =  15  titik 
Jumlah  =  59  =  32,0  = 91,00 titik 
f Panjang 1.062,0  m' 576,0  m' 
g Jumlah panjang  =  18,0  x  91  = 1.638,00 m' 
h Berat tiang miring  =  147,0  x  1.638,0  = 240.786,00 kg 

2 Proteksi kulit tiang pancang 
Diameter T.Pancang  =  508,0  =  0,508  m 
Jumlah titik  =  91,00  titik
Proteksi tiang pancang : Phi x d x h 
h  =  350,0  ­  180,0  +  50,0  =  220,0  cm 

(phi x d x h x n)  =  3,143  x  0,508  x  2,20  x  91,00  = 319,63 m

3 Beton Isian Tiang Pancang 


a Diameter luar  =  508,0  =  0,508  m 
Tebal dinding  =  12,0  =  0,012  m 
Diameter dalam (D)  =  484,0  =  0,484  m 
Panjang beton isian (h)  =  1,50  m 
Volume beton  =  0,25 x phi x D2 x h  =  0,276  m3 
b Besi beton : 5 D 25  =  5  x  3,85  x  2,25  =  43,31  kg 
Spiral f 10 mm  =  18,0  x  0,620  =  11,16  kg 
berat  =  54,47  kg 
~  55,00  kg 
c Pelat 10 mm  =  0,786  x  0,484  x  0,01  x  7.850,00  =  15,00  kg

B Pekerjaan Beton  Dermaga 20 x 54 


1 Pelat lantai t : 30 cm 
a Panjang  =  54,00  m 
Lebar  =  20,00  m 
Tebal  =  0,30  m 
Volume  =  54,00  x  20,00  x  0,30  =  324,00  m3 
Delatasi ke trestle  =  6,70  x  0,70  x  0,30  =  1,41 

DED PELABUHAN LUWUK TAHUN 2015  64  PT. SARANA ANTAR NUSA PEREKAYASA


b Balok Memanjang : 50/80 
Lebar  =  0,50  m 
Jumlah  =  5  unit  ( A, B, C, D, E) 
Panjang  =  54,00  m 
Pengurang  =  0,50  x  (5,00)  x  54,00  x  0,30  =  (40,50) m3 
c Balok Melintang : 50/80 
Panjang  =  19,50  ­  2,50  =  17,00  m 
Lebar  =  0,50 
Jumlah  =  15,00 
Pengurang  =  17,00  x  0,50  x  (15,00)  x  0,30  =  (38,25) m3 
d Delatasi ke trestle  =  0,70  x  0,50  x  (2,00)  x  0,30  =  (0,21) m3
Pelat Lantai  = 246,45 m3 

2 Balok Memanjang 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  5  baris 
Panjang  =  54,00  m 
Volume  =  0,50  x  0,80  x  5,00  x  54,00  = 108,00 m3 

3 Balok Melintang : 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  15  baris 
Panjang  =  19,50  ­  2,50  =  17,00  m 
Volume  =  0,50  x  0,80  x  15,00  x  17,00  = 102,00 m3 

4 Balok dudukan Fender 


Tebal  =  0,50  m 
Labar  =  1,40  m 
Tinggi  =  2,50  m 
Jumlah  =  15,00  ­  1,0  =  14,0  titik 
Volume  =  0,50  x  1,40  x  2,50  x  14,00  = 24,50 m3 

5 Pile Cap Kecil / Tiang Tunggal 


Panjang  =  1,00  m 
Lebar  =  1,00  m 
Tinggi  =  1,00  m 
Volume  =  1,00  x  1,00  x  1,00  =  1,000  m3 
Pengurang  =  0,7857  x  0,508  x  0,508  x  (0,30)  =  (0,061) m3 
Volume Per Unit  =  0,939  m3 
Jumlah Pile Cap Kcl  =  15,0  x  3,0  +  14,0  =  59,0  unit 
Volume Total  =  59,00  x  0,939  = 55,41 m3 

DED PELABUHAN LUWUK TAHUN 2015  65  PT. SARANA ANTAR NUSA PEREKAYASA


6 Pile Cap Besar, (Axis B & D) 
Panjang  =  2,00  m 
Lebar  =  1,00  m 
Tinggi  =  1,00  m 
Volume  =  2,00  x  1,00  x  1,00  =  2,000  m3 
Pengurang  =  0,7857  x  0,508  x  0,508  x  (0,60)  =  (0,122) m3 
Volume Per Unit  =  1,878  m3 
Jumlah Pile Cap  =  8,0  x  2,0  =  16,0  titik 
Volume Total  =  1,878  x  16,0  = 30,05 m3 

6 List Plank Samping, (0,2 x 0,5) 


Lebar  =  0,20  m 
Tinggi  =  0,50  m 
Panjang,      belakang  =  44,00  ­  6,7  =  37,30  m 
Samping (di trestle)  =  1,00  x  2,0  =  2,00  m 
Depan  =  54,00  ­  1,40  x  14,0  =  34,40  m 
Panjang  =  73,70  m 
Volume  =  0,20  x  0,50  x  73,70  = 7,37 m3 

7 Kanstin 15/20 
Panjang,      belakang  =  54,00  ­  6,7  ­  ­  =  47,30  m 
Samping  =  1,00  x  2,0  =  2,00  m 
Depan  =  54,00  =  54,00  m 
Panjang  = 103,30 m

II  Dermaga Tahun 1998 
A Tiang Pancang Dermaga 1998 
1 Tiang Pancang Pipa Baja : dia. 508 mm 
a Tiang pancang, Dia.  =  508,0  mm  =  0,5080  m 
b Tebal Tiang pancang  =  12,0  mm  =  0,01200  m 
c Berat / m'  =  147  Kg/m' 
d Panjang / titik  =  18,0  m 
Tegak  Miring 
e Jumlah tiang pancang  =  Axis A  =  14  titik  ­ 
Axis B  =  7  titik  14,0 
Axis C  =  14  titik  ­ 
Axis D  =  7  titik  14,0 
Axis E  =  14  titik 
Jumlah  =  56  =  28,0  = 84,00 titik 
f Panjang 1.008,0  m' 504,0  m' 
g Jumlah panjang  =  18,0  x  84  = 1.512,00 m' 
h Berat tiang miring  =  147,0  x  1.512,0  = 222.264,00 kg 

2 Proteksi kulit tiang pancang 
Diameter T.Pancang  =  508,0  =  0,508  m 
Jumlah titik  =  84,00  titik
Proteksi tiang pancang : Phi x d x h 
h  =  350,0  ­  180,0  +  50,0  =  220,0  cm 

(phi x d x h x n)  =  3,143  x  0,508  x  2,20  x  84,00  = 295,05 m

DED PELABUHAN LUWUK TAHUN 2015  66  PT. SARANA ANTAR NUSA PEREKAYASA


B Pekerjaan Beton  Dermaga 20 x 50 
1 Pelat lantai t : 30 cm 
a Panjang  =  50,00  m 
Lebar  =  20,00  m 
Tebal  =  0,30  m 
Volume  =  50,00  x  20,00  x  0,30  =  300,00  m3 
b Balok Memanjang : 50/80 
Lebar  =  0,50  m 
Jumlah  =  5  unit  ( A, B, C, D, E) 
Panjang  =  50,00  m 
Pengurang  =  0,50  x  (5,00)  x  50,00  x  0,30  =  (37,50) m3 
c Balok Melintang : 50/80 
Panjang  =  19,50  ­  2,50  =  17,00  m 
Lebar  =  0,50 
Jumlah  =  14,00 
Pengurang  =  17,00  x  0,50  x  (14,00)  x  0,30  =  (35,70) m3
Pelat Lantai  = 226,80 m3 

2 Balok Memanjang 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  5  baris 
Panjang  =  50,00  m 
Volume  =  0,50  x  0,80  x  5,00  x  50,00  = 100,00 m3 

3 Balok Melintang : 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  14  baris 
Panjang  =  19,50  ­  2,50  =  17,00  m 
Volume  =  0,50  x  0,80  x  14,00  x  17,00  = 95,20 m3 

4 Balok dudukan Fender 


Tebal  =  0,50  m 
Labar  =  1,40  m 
Tinggi  =  2,50  m 
Jumlah  =  14,00  ­  1,0  =  13,0  titik 
Volume  =  0,50  x  1,40  x  2,50  x  13,00  = 22,75 m3 

5 Pile Cap Kecil / Tiang Tunggal 


Panjang  =  1,00  m 
Lebar  =  1,00  m 
Tinggi  =  1,00  m 
Volume  =  1,00  x  1,00  x  1,00  =  1,000  m3 
Pengurang  =  0,7857  x  0,508  x  0,508  x  (0,30)  =  (0,061) m3 
Volume Per Unit  =  0,939  m3 
Jumlah Pile Cap Kcl  =  14,0  x  3,0  +  14,0  =  56,0  unit 
Volume Total  =  56,00  x  0,939  = 52,59 m3 

DED PELABUHAN LUWUK TAHUN 2015  67  PT. SARANA ANTAR NUSA PEREKAYASA


6 Pile Cap Besar, (Axis B & D) 
Panjang  =  2,00  m 
Lebar  =  1,00  m 
Tinggi  =  1,00  m 
Volume  =  2,00  x  1,00  x  1,00  =  2,000  m3 
Pengurang  =  0,7857  x  0,508  x  0,508  x  (0,60)  =  (0,122) m3 
Volume Per Unit  =  1,878  m3 
Jumlah Pile Cap  =  7,0  x  2,0  =  14,0  titik 
Volume Total  =  1,878  x  14,0  = 26,30 m3 

6 List Plank Samping, (0,2 x 0,5) 


Lebar  =  0,20  m 
Tinggi  =  0,50  m 
Panjang,      belakang  =  50,00  ­  6,0  =  44,00  m 
Depan  =  50,00  ­  1,40  x  13,0  =  31,80  m 
Panjang  =  75,80  m 
Volume  =  0,20  x  0,50  x  75,80  = 7,58 m3 

7 Kanstin 15/20 
Panjang,      belakang  =  50,00  ­  6,0  ­  ­  =  44,00  m 
Depan  =  50,00  =  50,00  m 
Panjang  = 94,00 m

III  Dermaga Tahun 2015 
A Tiang Pancang Dermaga 2015 
1 Tiang Pancang Pipa Baja : dia. 508 mm 
a Tiang pancang, Dia.  =  508,0  mm  =  0,5080  m 
b Tebal Tiang pancang  =  12,0  mm  =  0,01200  m 
c Berat / m'  =  147  Kg/m' 
d Panjang / titik  =  18,0  m 
Tegak  Miring 
e Jumlah tiang pancang  =  Axis A  =  13  titik  ­ 
Axis B  =  7  titik  12,0 
Axis C  =  13  titik  ­ 
Axis D  =  7  titik  12,0 
Axis E  =  13  titik 
Jumlah  =  53  =  24,0  = 77,00 titik 
f Panjang 954,0  m' 432,0  m' 
g Jumlah panjang  =  18,0  x  77  = 1.386,00 m' 
h Berat tiang miring  =  147,0  x  1.386,0  = 203.742,00 kg 

2  Proteksi kulit tiang pancang 
Diameter T.Pancang  =  508,0  =  0,508  m 
Jumlah titik  =  77,00  titik
Proteksi tiang pancang : Phi x d x h 
h  =  350,0  ­  180,0  +  50,0  =  220,0  cm 

(phi x d x h x n)  =  3,143  x  0,508  x  2,20  x  77,00  = 270,46 m

DED PELABUHAN LUWUK TAHUN 2015  68  PT. SARANA ANTAR NUSA PEREKAYASA


B Pekerjaan Beton  Dermaga 20 x 50 
1 Pelat lantai t : 30 cm 
a Panjang  =  50,00  m 
Lebar  =  20,00  m 
Tebal  =  0,30  m 
Volume  =  50,00  x  20,00  x  0,30  =  300,00  m3 
b Balok Memanjang : 50/80 
Lebar  =  0,50  m 
Jumlah  =  5  unit  ( A, B, C, D, E) 
Panjang  =  50,00  m 
Pengurang  =  0,50  x  (5,00)  x  50,00  x  0,30  =  (37,50) m3 
c Balok Melintang : 50/80 
Panjang  =  19,50  ­  2,50  =  17,00  m 
Lebar  =  0,50 
Jumlah  =  13,00 
Pengurang  =  17,00  x  0,50  x  (13,00)  x  0,30  =  (33,15) m3
Pelat Lantai  = 229,35 m3 

2 Balok Memanjang 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  5  baris 
Panjang  =  50,00  m 
Volume  =  0,50  x  0,80  x  5,00  x  50,00  = 100,00 m3 

3 Balok Melintang : 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  13  baris 
Panjang  =  19,50  ­  2,50  =  17,00  m 
Volume  =  0,50  x  0,80  x  13,00  x  17,00  = 88,40 m3 

4 Balok dudukan Fender 


Tebal  =  0,50  m 
Labar  =  1,40  m 
Tinggi  =  2,50  m 
Jumlah  =  13,00  titik 
Volume  =  0,50  x  1,40  x  2,50  x  13,00  = 22,75 m3 

5 Pile Cap Kecil / Tiang Tunggal 


Panjang  =  1,00  m 
Lebar  =  1,00  m 
Tinggi  =  1,00  m 
Volume  =  1,00  x  1,00  x  1,00  =  1,000  m3 
Pengurang  =  0,7857  x  0,508  x  0,508  x  0,30  =  0,061  m3 
Volume Per Unit  =  0,939  m3 
Jumlah Pile Cap Kcl  =  13,0  x  3,0  +  14,0  =  53,0  unit 
Volume Total  =  53,00  x  0,939  = 49,78 m3 

DED PELABUHAN LUWUK TAHUN 2015  69  PT. SARANA ANTAR NUSA PEREKAYASA


6 Pile Cap Besar, (Axis B & D) 
Panjang  =  2,00  m 
Lebar  =  1,00  m 
Tinggi  =  1,00  m 
Volume  =  2,00  x  1,00  x  1,00  =  2,000  m3 
Pengurang  =  0,7857  x  0,508  x  0,508  x  0,60  =  0,122  m3 
Volume Per Unit  =  1,878  m3 
Jumlah Pile Cap  =  6,0  x  2,0  x  1,0  =  12,0  titik 
Volume Total  =  1,878  x  12,0  = 22,54 m3 

6 List Plank Samping, (0,2 x 0,5) 


Lebar  =  0,20  m 
Tinggi  =  0,50  m 
Panjang,      belakang  =  50,00  ­  14,5  =  35,50  m 
Samping  =  20,00  =  20,00  m 
Depan  =  50,00  ­  1,40  x  13,0  =  31,80  m 
Panjang  =  87,30  m 
Volume  =  0,20  x  0,50  x  87,30  = 8,73 m3 
7 Kanstin 15/20 
Panjang,      belakang  =  50,00  ­  14,5  ­  ­  =  35,50  m 
Samping  =  20,00  =  20,00  m 
Depan  =  50,00  =  50,00  m 
Panjang  = 105,50 m

IV  Trestle Tahun 2015 
A Tiang Pancang Trestle 2015 
1 Tiang Pancang Pipa Baja : dia. 508 mm 
a Tiang pancang, Dia.  =  508,0  mm  =  0,5080  m 
b Tebal Tiang pancang  =  12,0  mm  =  0,01200  m 
c Berat / m'  =  147  Kg/m' 
d Panjang / titik  =  18,0  m 
Tegak 
e Jumlah tiang pancang  =  Axis F  =  5  titik 
Axis G  =  3  titik 
Axis H  =  3  titik 
Axis I  =  3  titik 
Axis J  =  3  titik 
Jumlah  =  17  =  = 17,00 titik 
f Jumlah panjang  =  18,0  x 17,0  m'  = 306,00 m' 
g Jumlah Berat tiang  =  147,0  x  306,0  = 44.982,00 kg 

2  Proteksi kulit tiang pancang 
Diameter T.Pancang  =  508,0  =  0,508  m 
Jumlah titik  =  17,00  titik
Proteksi tiang pancang : Phi x d x h 
h  =  350,0  ­  180,0  +  50,0  =  220,0  cm 

(phi x d x h x n)  =  3,143  x  0,508  x  2,20  x  17,00  = 59,71 m

DED PELABUHAN LUWUK TAHUN 2015  70  PT. SARANA ANTAR NUSA PEREKAYASA


B Pekerjaan Beton 
1 Pelat lantai t : 30 cm 
a Panjang  =  20,00  m 
Lebar  =  10,00  m 
Tebal  =  0,30  m 
Volume  =  20,00  x  10,00  x  0,30  =  60,00  m3 
Segitiga  =  5,00  x  5,50  x  0,30  =  8,25  m3 
b Balok Memanjang : 50/80 
Lebar  =  0,50  m 
Jumlah  =  3  unit 
Panjang  =  20,00  m 
Pengurang  =  0,50  x  (3,00)  x  20,00  x  0,30  =  (9,00) m3 
Diagonal  =  0,50  x  (2,00)  x  5,50  x  0,30  =  (1,65) m3 
c Balok Melintang : 50/80 
Panjang  =  10,00  m 
Lebar  =  0,50 
Jumlah  =  5,0 
Pengurang  =  10,00  x  0,50  x  (5,00)  x  0,30  =  (7,50) m3
Pelat Lantai  = 50,10 m3 

2 Balok Memanjang 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  3  baris 
Panjang  =  20,00  m 
Volume  =  0,50  x  0,80  x  3,00  x  20,00  = 24,00 m3 

3 Balok Melintang : 50/80 


Lebar  =  0,50  m 
Tinggi  =  0,80  m 
Jumlah  =  5  baris 
Panjang  =  10,00  m 
Volume  =  0,50  x  0,80  x  5,00  x  10,00  = 20,00 m3 

4 Pile Cap Kecil / Tiang Tunggal 


Panjang  =  1,00  m 
Lebar  =  1,00  m 
Tinggi  =  1,00  m 
Volume  =  1,00  x  1,00  x  1,00  =  1,000  m3 
Pengurang  =  0,7857  x  0,508  x  0,508  x  (0,30)  =  (0,061) m3 
Volume Per Unit  =  0,939  m3 
Jumlah Pile Cap Kcl  =  5,0  x  3,0  +  2,0  =  17,0  unit 
Volume Total  =  17,00  x  0,939  = 15,97 m3 

DED PELABUHAN LUWUK TAHUN 2015  71  PT. SARANA ANTAR NUSA PEREKAYASA


5 List Plank Samping, (0,2 x 0,5) 
Lebar  =  0,20  m 
Tinggi  =  0,50  m 
Panjang,      samping  = (  14,50  +  6,0  ) *  2,0  =  41,00  m 
Pengurang  = (  0,50  x  5,00  ) *  (2,0)  =  (5,00) m 
Panjang  =  36,00  m 
Volume  =  0,20  x  0,50  x  36,00  = 3,60 m3 

6 Kanstin 15/20 
Panjang,      samping  = (  14,50  +  6,0  ) *  2,0  = 41,00 m

V VOLUME KANDUNGAN BESI


A Dermaga Rehap 
1 Beton Isian Tiang Pancang, dia. 508 mm  (Dermaga Rehap) 
Diameter  =  0,508  m 
Tebal  =  0,0120  m  0,4840  m 
Tinggi  =  1,500  m 
Volume beton  =  0,78571  x  0,484  x  0,484  x  1,500  = 0,276  m3 
Besi : 5 D 25, L : 2 m  =  5  x  3,850  x  2,0  =  38,50  kg  38,50  kg 
Sengkang f 10 ­ 15cm  =  1  x  0,62  x  14,0  =  8,68  kg  8,68  kg 
berat besi  = 50,00  kg 
Besi plat, t : 10 mm  =  0,78571  x  0,239  x  0,010  x  7.850,00  = 14,74  kg 

2 Balok Bentang : 4 m 50/80 cm  (Balok Memanjang) 


Derah tumpuan isi tulangan     : 4 D 22mm & 4 D 22mm 
Daerah lapangan isi tulangan : 4 D 22mm & 4 D 22mm 
Isi tulangan rata­rata  :  4 D 22mm & 4 D 22mm  sengkang f 10 ­ 20 cm 
Volume beton  =  0,50  x  0,80  = 0,40  m3 
Berat besi 8 D 22  =  8  x  1,00  x  2,98  =  23,84  kg 
sengkang f 10 ­ 20  =  5  x  2,10  x  0,62  =  6,51  kg 
2 D 16  =  2  x  1,00  x  1,58  =  3,16  kg 
berat besi  = 33,51  kg 
Berat besi / m3  =  33,51  /  0,40  ~ 90,00  kg/m3 

Luas Begisting  = (  1,00  +  0,50  ) /  0,40  =  3,75  m2 3,75 m

3 Balok Bentang: 4,5 m 50/80 cm  (Balok Melintang) 


Derah tumpuan isi tulangan     : 4 D 22mm & 4 D 22mm 
Daerah lapangan isi tulangan : 4 D 22mm & 4 D 22mm 
Isi tulangan rata­rata  :  4 D 22mm & 4 D 22mm  sengkang f 10 ­ 20 cm 
Volume beton  =  0,50  x  0,80  = 0,40  m3 
Berat besi 8 D 22  =  8,0  x  1,00  x  2,98  =  23,84  kg 
sengkang f 10 ­ 20  =  5  x  2,10  x  0,62  =  6,51  kg 
2 D 16  =  2  x  1,00  x  1,58  =  3,16  kg 
berat besi  = 33,51  kg 
Berat besi / m3  =  33,51  /  0,40  ~ 90,00  kg/m3 

Luas Begisting  = (  1,00  +  0,50  ) /  0,40  =  3,75  m2 3,75 m

DED PELABUHAN LUWUK TAHUN 2015  72  PT. SARANA ANTAR NUSA PEREKAYASA


4 Pelat lantai, t : 0,30 m  Volume beton lantai  =  0,30  m3 
Tulangan rangkap :  D 16 ­ 15 cm dan D 16 ­ 15 cm 
D16 ­ 15 cm  =  14  x  1,0  x  1,58  =  22,12  kg 
D16 ­ 15 cm  =  14  x  1,0  x  1,58  =  22,12  kg 
berat besi  = 44,24  kg 
Berat besi / m3  =  44,24  /  0,30  ~ 150,00  kg/m3 
Luas Begisting  =  1,00  /  0,30  =  3,33333  ~ 3,50  m2 

5 Pile cap Tiang Tunggal, =  1 x 1 x 1  =  1,00  m3 


Tulangan rangkap :  7 D 22mm dan 1 D 16 mm 
2 x 7 D 22mm  =  14,00  x  3,60  x  2,98  =  150,192  kg 
1 D 16mm  =  1,00  x  3,60  x  1,58  =  5,688  kg 
Steck ke Balok, 8 D 22  =  8,00  x  0,90  x  2,98  =  21,456  kg 
berat besi  = 177,34  kg 
Berat besi / m3  =  177,34  /  1,00  ~ 180,00  kg/m3 
Luas Begisting  = (  1,00  x  5,00  ) /  1,00  = 5,00  m2 

6 Pile cap Tiang ganda, =  1 x 2 x 1  =  2,00  m3 


Tulangan rangkap : D 22mm dan 1 D 16 mm 
7 D 22mm  =  7,00  x  5,60  x  2,98  =  116,816  kg 
14 D 22mm  =  14,00  x  3,60  x  2,98  =  150,192  kg 
1 D 16mm  =  1,00  x  5,60  x  1,58  =  8,848  kg 
Steck ke Balok, 12 D 22  =  12,00  x  0,90  x  2,98  =  32,184  kg 
berat besi  = 308,04  kg 
Berat besi / m3  =  308,04  /  2,00  ~ 160,00  kg/m3 
Luas Begisting  = (  6,00  +  2,00  ) /  2,00  = 4,00  m2 

7 Balok Dudukan Fender  =  0,50 x 1,40 x 2,50  = 1,750  m3 


Tulangan rangkap : D 22mm dan 2 D 16 mm 
7 D 22mm  =  7,00  x  4,75  x  2,98  =  99,085  kg 
4 D 22mm  =  4,00  x  6,60  x  2,98  =  78,672  kg 
1 D 16mm  =  1,00  x  6,00  x  1,58  =  9,480  kg 
11 D 16mm  =  11,00  x  3,40  x  1,58  =  59,092  kg 
berat besi  = 246,329  kg 
Berat besi / m3  =  246,33  /  1,750  ~ 145,00  kg/m3 
Luas Begisting  =  0,50  x  5,00  =  2,50  m2 
0,50  x  1,40  =  0,70  m2 
1,00  x  1,40  =  1,40  m2 
2,50  x  1,40  =  3,50  m2 
Luas  = 8,10  m2 
Luas Begisting  = 5,00  m2 

8 List Plank, 0,20/0,50m  =  0,20 x 0,50  = 0,10  m3 


3 D 16mm  =  3,00  x  1,00  x  1,58  =  4,740  kg 
Dia. 10 ­ 250mm  =  4,00  x  0,75  x  0,62  =  1,860  kg 
berat besi  = 6,60  kg 
Berat besi / m3  =  6,60  /  0,10  ~ 70,00  kg/m3 
Luas Begisting  = (  1,00  +  0,20  ) /  0,10  = 12,00  m2 

DED PELABUHAN LUWUK TAHUN 2015  73  PT. SARANA ANTAR NUSA PEREKAYASA


IV PEKERJAAN PEMBONGKARAN
A Dermaga Tengah (1992) 12 x 54m 
1 Pelat lantai 
a Tebal  =  0,25  m 
b Lebar  =  12,00  m 
c Panjang  =  54,00  m 
Volume  =  0,25  x  12,00  x  54,00  =  162,00  m3 
2 Balok Memanjang 
Bagian Tepi : 50/50 cm 
a Lebar  =  0,50  m 
b Tinggi  =  0,50  m 
c Panjang  =  54,00  m 
d Jumlah  =  2  bh 
Volume  =  0,50  x  0,50  x  108,00  =  27,00  m3 
Bagian Tengah : 60/50 cm 
a Lebar  =  0,60  m 
b Tinggi  =  0,50  m 
c Panjang  =  54,00  m 
d Jumlah  =  1  bh 
Volume  =  0,60  x  0,50  x  54,00  =  16,20  m3 
3  Balok Melintang : 50/50 cm 
a Lebar  =  0,50  m 
b Tinggi  =  0,50  m 
c Panjang  =  11,50  ­  1,60  =  9,90  m 
d Jumlah  =  14  bh 
Volume  =  0,50  x  0,50  x  9,9 x 14  =  34,65  m3 
4  Balok Dudukan Fender:  0,50 x 2,50 x 1,0 m 
a Tebal  =  0,50  m 
b Tinggi  =  2,25  m 
c Lebar  =  1,00  m 
d Jumlah  =  14  bh 
Volume  =  0,50  x  2,25  x  1 x 14  =  15,75  m3 
Volume Balok + Pelat, Dermaga 1992  =  255,60  m3 
5  Pile Cap Tiang Tunggal:  1,0 x 1,0 x 0,80 m 
a Lebar  =  1,00  m 
b Tinggi  =  0,80  m 
c Panjang  =  1,00  m 
d Jumlah  =  28  +  6  =  34  bh 
Volume  =  1,00  x  0,80  x  34,00  =  27,20  m3 
6  Pile Cap Tiang Ganda :  1,0 x 2,0 x 0,80 m 
a Lebar  =  1,00  m 
b Tinggi  =  0,80  m 
c Panjang  =  2,00  m 
d Jumlah  =  8  bh 
Volume  =  1,00  x  0,80  x  2,0 x 8  =  12,80  m3 
Volume Pile Cap  =  40,00  m3 

DED PELABUHAN LUWUK TAHUN 2015  74  PT. SARANA ANTAR NUSA PEREKAYASA


B Dermaga Kiri (1998) 12 x 50m 
1 Pelat lantai 
a Tebal  =  0,25  m 
b Lebar  =  12,00  m 
c Panjang  =  50,00  m 
Volume  =  0,25  x  12,00  x  50,00  =  150,00  m3 
2 Balok Memanjang 
Bagian Tepi : 50/50 cm 
a Lebar  =  0,50  m 
b Tinggi  =  0,50  m 
c Panjang  =  50,00  m 
d Jumlah  =  2  bh 
Volume  =  0,50  x  0,50  x  108,00  =  27,00  m3 
Bagian Tengah : 60/50 cm 
a Lebar  =  0,60  m 
b Tinggi  =  0,50  m 
c Panjang  =  50,00  m 
d Jumlah  =  1  bh 
Volume  =  0,60  x  0,50  x  54,00  =  16,20  m3 
3  Balok Melintang : 50/50 cm 
a Lebar  =  0,50  m 
b Tinggi  =  0,50  m 
c Panjang  =  11,50  ­  1,60  =  9,90  m 
d Jumlah  =  13  bh 
Volume  =  0,50  x  0,50  x  9,9 x 13  =  32,18  m3 
4  Balok Dudukan Fender:  0,50 x 2,50 x 1,0 m 
a Tebal  =  0,50  m 
b Tinggi  =  2,25  m 
c Lebar  =  1,00  m 
d Jumlah  =  13  bh 
Volume  =  0,50  x  2,25  x  1 x 13  =  14,63  m3 
5  Morring Sisi Barat  2,50 x 2,50 x 2,0 m 
a Tinggi  =  2,00  m 
b Panjang  =  2,50  m 
c Lebar  =  2,50  m 
d Jumlah  =  1  bh 
Volume  =  2,00  x  2,50  x  2,50  =  12,50  m3 
Volume Balok + Pelat, Dermaga 1998  =  252,50  m3 
6  Pile Cap Tiang Tunggal:  1,0 x 1,0 x 0,80 m 
a Lebar  =  1,00  m 
b Tinggi  =  0,80  m 
c Panjang  =  1,00  m 
d Jumlah  =  26  +  7  =  33  bh 
Volume  =  1,00  x  0,80  x  33,00  =  26,40  m3 

DED PELABUHAN LUWUK TAHUN 2015  75  PT. SARANA ANTAR NUSA PEREKAYASA


7  Pile Cap Tiang Ganda :  1,0 x 2,0 x 0,80 m 
a Lebar  =  1,00  m 
b Tinggi  =  0,80  m 
c Panjang  =  2,00  m 
d Jumlah  =  6  bh 
Volume  =  1,00  x  0,80  x  2,0 x 6  =  9,60  m3 
Volume Pile Cap  =  36,00  m3 

8  Pemotongan Tiang Pancang Eksisting  Dermaga 1992 


Axis A  =  14,0  ‐  =  14,0  titik 
Axis B.miring  =  16,0  ‐  =  16,0  titik 
Axis B.tegak  =  6,0  ‐  =  6,0  titik 
Axis C  =  14,0  ‐  =  14,0  titik  50,0 
Trestle  =  2,0  x  2,0  =  4,0  titik 
=  54,0  titik 

9  Pemotongan Tiang Pancang Eksisting  Dermaga 1998 


Axis A  =  13,0  +  ‐  =  13,0  titik 
Axis B.miring  =  12,0  +  ‐  =  12,0  titik 
Axis B.tegak  =  7,0  +  ‐  =  7,0  titik 
Axis C  =  13,0  +  ‐  =  13,0  titik 
Mooring  =  1,0  x  5,0  =  5,0  titik 
=  50,0  titik 

10  Bobokan / Chipping Pile Cap Bagian Trestle 
Lebar  =  0,40  m 
Tinggi  =  0,50  m 
Tebal rata‐rata  =  0,08  m 
Jumlah Pile cap  =  14,00  m 
Volume  =  0,40  x  0,50  x  0,08  x  14,00  =  0,22  m3 

Luas Bobokan  =  0,40  x  0,50  x  14,00  =  2,80  m2 

DED PELABUHAN LUWUK TAHUN 2015  76  PT. SARANA ANTAR NUSA PEREKAYASA


ENGINEER ESTIMATE (EE)
DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK BANGGAI
PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT
PEKERJAAN REPLACEMENT DERMAGA TAHUN 2015

HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran Darat & Laut 1,00 ls 56.220.600,00 56.220.600,00
2 Mobilisasi & Demobilisasi Alat Kerja 1,00 ls 598.000.000,00 598.000.000,00
3 Pasang Papan Nama Proyek 1,00 bh 2.000.000,00 2.000.000,00
4 Direksi Keet 48,00 m2 2.250.000,00 108.000.000,00
5 Gudang Material 32,00 m2 875.000,00 28.000.000,00
JUMLAH I 792.220.600,00

II PEKERJAAN REPLACEMENT DERMAGA


A Dermaga 20M x 54M ­ Tahun 1992
1 Pengadaan dan pengangkutan tiang pancang pipa baja 240.786,00 Kg 15.660,00 3.770.708.760,00
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 1.638,00 m' 96.023,00 157.285.674,00
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 1.062,00 m' 500.560,00 531.594.720,00
4 Pemancangan Tiang Miring, Dia. 508mm T : 12mm 576,00 m' 625.710,00 360.408.960,00
5 Penyambungan Tiang Pancang Baja Dia. 508 mm, 91,00 ea 842.550,00 76.672.050,00
6 Pemotongan Kepala Tiang Pancang Dia. 508 mm 91,00 ttk 408.310,00 37.156.210,00
7 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 319,63 m2 3.978.000,00 1.271.502.460,80
8 Pembuatan Sepatu Tiang Pancang 91,00 ea 1.746.980,00 158.975.180,00
9 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 91,00 titik 2.369.910,00 215.661.810,00
10 Beton Pelat Lantai, K­350 ; t : 30 cm 246,45 m3 7.399.120,00 1.823.490.926,64
11 Balok Memanjang Beton K­350, (50/80 cm) 108,00 m3 5.872.440,00 634.223.520,00
12 Balok Melintang Beton K­350, (50/80 cm) 102,00 m3 5.872.440,00 598.988.880,00
13 Balok Dudukan Fender Beton K­350, (50/140/280 cm) 24,50 m3 7.450.540,00 182.538.230,00
14 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 55,41 m3 7.892.310,00 437.321.318,87
15 Pilecap Tiang Ganda Beton K­350, (1,0 x 1,0 x 2,0), 30,05 m3 7.185.900,00 215.961.159,04
16 Beton Kanstin, K350 tinggi : 15/20 cm 103,30 m' 275.520,00 28.461.216,00
17 Beton List Plank Depan & Belakang, (0,2x0,5) 7,37 m3 6.536.807,50 48.176.271,28
18 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 38,00 m' 351.780,00 13.367.640,00
19 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik 13.638.510,00 27.277.020,00
20 Fender Type V, 600H x 2000L 14,00 bh 62.295.120,00 872.131.680,00
21 Bollard Curve Kap. 70 ton 3,00 bh 48.454.870,00 145.364.610,00
JUMLAH II A 11.607.268.296,62

B Pembongkaran Dermaga Eksisting 12M x 54M ­ Tahun 1992


1 Pembongkaran Pelat Lantai & Balok 255,60 m3 2.744.170,00 701.409.852,00
2 Pembongkaran Pile Cap 40,00 m3 2.744.170,00 109.766.800,00
3 Pemotongan Tiang Pancang Eksisting + Angkut ke Darat 54,00 titik 667.650,00 36.053.100,00

JUMLAH II B  847.229.752,00

DED PELABUHAN LUWUK TAHUN 2015
DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK BANGGAI
PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT
PEKERJAAN REPLACEMENT DERMAGA TAHUN 2015

HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

C Perbaikan Pile Cap Trestle 1992


1 Pekerjaan Bobokan Pile Cap Eksisting 2,80 m2 368.896,25 1.032.909,50
2 Pekerjaan Groutting Pile Cap Trestle Eksisting 0,22 m3 16.744.950,00 3.750.868,80

JUMLAH II C  4.783.778,30

D Dermaga 20M x 50M ­ Tahun 1998


1 Pengadaan dan pengangkutan tiang pancang pipa baja 222.264,00 Kg 15.660,00 3.480.654.240,00
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 1.512,00 m' 96.023,00 145.186.776,00
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 1.008,00 m' 500.560,00 504.564.480,00
4 Pemancangan Tiang Miring, Dia. 508mm T : 12mm 504,00 m' 625.710,00 315.357.840,00
5 Penyambungan Tiang Pancang Baja Dia. 508 mm, 84,00 ea 842.550,00 70.774.200,00
6 Pemotongan Kepala Tiang Pancang Dia. 508 mm 84,00 ttk 408.310,00 34.298.040,00
7 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 295,05 m2 3.978.000,00 1.173.694.579,20
8 Pembuatan Sepatu Tiang Pancang 84,00 ea 1.746.980,00 146.746.320,00
9 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 84,00 titik 2.369.910,00 199.072.440,00
10 Beton Pelat Lantai, K­350 ; t : 30 cm 226,80 m3 7.399.120,00 1.678.120.416,00
11 Balok Memanjang Beton K­350, (50/80 cm) 100,00 m3 5.872.440,00 587.244.000,00
12 Balok Melintang Beton K­350, (50/80 cm) 95,20 m3 5.872.440,00 559.056.288,00
13 Balok Dudukan Fender Beton K­350, (50/140/280 cm) 22,75 m3 7.450.540,00 169.499.785,00
14 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 52,59 m3 7.892.310,00 415.084.641,64
15 Pilecap Tiang Ganda Beton K­350, (1,0 x 1,0 x 2,0), 26,30 m3 7.185.900,00 188.966.014,16
16 Beton Kanstin, K350 tinggi : 15/20 cm 94,00 m' 275.520,00 25.898.880,00
17 Beton List Plank Depan & Belakang, (0,2x0,5) 7,58 m3 6.536.807,50 49.549.000,85
18 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 46,00 m' 351.780,00 16.181.880,00
19 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik 13.638.510,00 27.277.020,00
20 Fender Type V, 600H x 2000L 13,00 bh 62.295.120,00 809.836.560,00
21 Bollard Curve Kap. 70 ton 2,00 bh 48.454.870,00 96.909.740,00
JUMLAH II D 10.693.973.140,85

E Pembongkaran Dermaga Eksisting 12M x 50M ­ Tahun 1998


1 Pembongkaran Pelat Lantai & Balok 252,50 m3 2.744.170,00 692.902.925,00
2 Pembongkaran Pile Cap 36,00 m3 2.744.170,00 98.790.120,00
3 Pemotongan Tiang Pancang Eksisting + Angkut ke Darat 50,00 titik 667.650,00 33.382.500,00

JUMLAH II E 825.075.545,00

DED PELABUHAN LUWUK TAHUN 2015
DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK BANGGAI
PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT
PEKERJAAN REPLACEMENT DERMAGA TAHUN 2015

HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

F Dermaga 20M x 50M ­ Tahun 2015


1 Pengadaan dan pengangkutan tiang pancang pipa baja 203.742,00 Kg 15.660,00 3.190.599.720,00
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 1.386,00 m' 96.023,00 133.087.878,00
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 954,00 m' 500.560,00 477.534.240,00
4 Pemancangan Tiang Miring, Dia. 508mm T : 12mm 432,00 m' 625.710,00 270.306.720,00
5 Penyambungan Tiang Pancang Baja Dia. 508 mm, 77,00 ea 842.550,00 64.876.350,00
6 Pemotongan Kepala Tiang Pancang Dia. 508 mm 77,00 ttk 408.310,00 31.439.870,00
7 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 270,46 m2 3.978.000,00 1.075.886.697,60
8 Pembuatan Sepatu Tiang Pancang 77,00 ea 1.746.980,00 134.517.460,00
9 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 77,00 titik 2.369.910,00 182.483.070,00
10 Beton Pelat Lantai, K­350 ; t : 30 cm 229,35 m3 7.399.120,00 1.696.988.172,00
11 Balok Memanjang Beton K­350, (50/80 cm) 100,00 m3 5.872.440,00 587.244.000,00
12 Balok Melintang Beton K­350, (50/80 cm) 88,40 m3 5.872.440,00 519.123.696,00
13 Balok Dudukan Fender Beton K­350, (50/140/280 cm) 22,75 m3 7.450.540,00 169.499.785,00
14 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 49,78 m3 7.892.310,00 392.847.964,41
15 Pilecap Tiang Ganda Beton K­350, (1,0 x 1,0 x 2,0), 22,54 m3 7.185.900,00 161.970.869,28
16 Beton Kanstin, K350 tinggi : 15/20 cm 105,50 m' 275.520,00 29.067.360,00
17 Beton List Plank Depan & Belakang, (0,2x0,5) 8,73 m3 6.536.807,50 57.066.329,48
18 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 47,00 m' 351.780,00 16.533.660,00
19 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik 13.638.510,00 27.277.020,00
20 Fender Type V, 600H x 2000L 13,00 bh 62.295.120,00 809.836.560,00
21 Bollard Curve Kap. 70 ton 2,00 bh 48.454.870,00 96.909.740,00
JUMLAH II F 10.125.097.161,76

G Trestle 10M x 20M ­ Tahun 2015


1 Pengadaan dan pengangkutan tiang pancang pipa baja 44.982,00 Kg 15.660,00 704.418.120,00
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 306,00 m' 96.023,00 29.383.038,00
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 306,00 m' 500.560,00 153.171.360,00
4 Penyambungan Tiang Pancang Baja Dia. 508 mm, 17,00 ea 842.550,00 14.323.350,00
5 Pemotongan Kepala Tiang Pancang Dia. 508 mm 17,00 ttk 408.310,00 6.941.270,00
6 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 59,71 m2 3.978.000,00 237.533.426,74
7 Pembuatan Sepatu Tiang Pancang 17,00 ea 1.746.980,00 29.698.660,00
8 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 17,00 titik 2.369.910,00 40.288.470,00
9 Beton Pelat Lantai, K­350 ; t : 30 cm 50,10 m3 7.399.120,00 370.695.912,00
10 Balok Memanjang Beton K­350, (50/80 cm) 24,00 m3 5.872.440,00 140.938.560,00
11 Balok Melintang Beton K­350, (50/80 cm) 20,00 m3 5.872.440,00 117.448.800,00
12 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 15,97 m3 7.892.310,00 126.007.837,64
13 Beton Kanstin, K350 tinggi : 15/20 cm 41,00 m' 275.520,00 11.296.320,00
14 Beton List Plank Depan & Belakang, (0,2x0,5) 3,60 m3 6.536.807,50 23.532.507,00
15 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 12,00 m' 351.780,00 4.221.360,00
16 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik 13.638.510,00 27.277.020,00
JUMLAH II G  2.037.176.011,38

DED PELABUHAN LUWUK TAHUN 2015
DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK BANGGAI
PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT
PEKERJAAN REPLACEMENT DERMAGA TAHUN 2015

HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

III PEKERJAAN PENGERUKAN


A Pekerjaan Persiapan
1 Mobilisasi & Demobilisasi Alat Kerja 1,00 ls 580.000.000,00 580.000.000,00

B Pekerjaan Pengerukan
1 Pekerjaan Pengerukan Kolam Pelabuhan 1.154,38 m3 55.210,00 63.733.084,88

J u m l a h : I + II.A + II.B + II.C + II.D + II.E + II.F + II.G + III.A + III.B  37.576.557.370,79
PPN 10 % 3.757.655.737,08
JUMLAH TOTAL 41.334.213.107,87
DIBULATKAN 41.334.200.000,00
Terbilang :
= Empat puluh satu milyar tiga ratus tiga puluh empat juta dua ratus ribu rupiah =

DED PELABUHAN LUWUK TAHUN 2015
BILL OF QUANTITY (BOQ)
DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK BANGGAI
PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT
PEKERJAAN REPLACEMENT DERMAGA TAHUN 2015

HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran Darat & Laut 1,00 ls ­ ­
2 Mobilisasi & Demobilisasi Alat Kerja 1,00 ls ­ ­
3 Pasang Papan Nama Proyek 1,00 bh ­ ­
4 Direksi Keet 48,00 m2 ­ ­
5 Gudang Material 32,00 m2 ­ ­
JUMLAH I  ­

II PEKERJAAN REPLACEMENT DERMAGA


A Dermaga 20M x 54M ­ Tahun 1992
1 Pengadaan dan pengangkutan tiang pancang pipa baja 240.786,00 Kg ­ ­
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 1.638,00 m' ­ ­
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 1.062,00 m' ­ ­
4 Pemancangan Tiang Miring, Dia. 508mm T : 12mm 576,00 m' ­ ­
5 Penyambungan Tiang Pancang Baja Dia. 508 mm, 91,00 ea ­ ­
6 Pemotongan Kepala Tiang Pancang Dia. 508 mm 91,00 ttk ­ ­
7 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 319,63 m2 ­ ­
8 Pembuatan Sepatu Tiang Pancang 91,00 ea ­ ­
9 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 91,00 titik ­ ­
10 Beton Pelat Lantai, K­350 ; t : 30 cm 246,45 m3 ­ ­
11 Balok Memanjang Beton K­350, (50/80 cm) 108,00 m3 ­ ­
12 Balok Melintang Beton K­350, (50/80 cm) 102,00 m3 ­ ­
13 Balok Dudukan Fender Beton K­350, (50/140/280 cm) 24,50 m3 ­ ­
14 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 55,41 m3 ­ ­
15 Pilecap Tiang Ganda Beton K­350, (1,0 x 1,0 x 2,0), 30,05 m3 ­ ­
16 Beton Kanstin, K350 tinggi : 15/20 cm 103,30 m' ­ ­
17 Beton List Plank Depan & Belakang, (0,2x0,5) 7,37 m3 ­ ­
18 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 38,00 m' ­ ­
19 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik ­ ­
20 Fender Type V, 600H x 2000L 14,00 bh ­ ­
21 Bollard Curve Kap. 70 ton 3,00 bh ­ ­
JUMLAH II A ­

B Pembongkaran Dermaga Eksisting 12M x 54M ­ Tahun 1992


1 Pembongkaran Pelat Lantai & Balok 255,60 m3 ­ ­
2 Pembongkaran Pile Cap 40,00 m3 ­ ­
3 Pemotongan Tiang Pancang Eksisting + Angkut ke Darat 54,00 titik ­ ­

JUMLAH II B ­

DED PELABUHAN LUWUK
HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

C Perbaikan Pile Cap Trestle 1992


1 Pekerjaan Bobokan Pile Cap Eksisting 2,80 m2 ­ ­
2 Pekerjaan Groutting Pile Cap Trestle Eksisting 0,22 m3 ­ ­

JUMLAH II C ­

D Dermaga 20M x 50M ­ Tahun 1998


1 Pengadaan dan pengangkutan tiang pancang pipa baja 222.264,00 Kg ­ ­
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 1.512,00 m' ­ ­
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 1.008,00 m' ­ ­
4 Pemancangan Tiang Miring, Dia. 508mm T : 12mm 504,00 m' ­ ­
5 Penyambungan Tiang Pancang Baja Dia. 508 mm, 84,00 ea ­ ­
6 Pemotongan Kepala Tiang Pancang Dia. 508 mm 84,00 ttk ­ ­
7 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 295,05 m2 ­ ­
8 Pembuatan Sepatu Tiang Pancang 84,00 ea ­ ­
9 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 84,00 titik ­ ­
10 Beton Pelat Lantai, K­350 ; t : 30 cm 226,80 m3 ­ ­
11 Balok Memanjang Beton K­350, (50/80 cm) 100,00 m3 ­ ­
12 Balok Melintang Beton K­350, (50/80 cm) 95,20 m3 ­ ­
13 Balok Dudukan Fender Beton K­350, (50/140/280 cm) 22,75 m3 ­ ­
14 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 52,59 m3 ­ ­
15 Pilecap Tiang Ganda Beton K­350, (1,0 x 1,0 x 2,0), 26,30 m3 ­ ­
16 Beton Kanstin, K350 tinggi : 15/20 cm 94,00 m' ­ ­
17 Beton List Plank Depan & Belakang, (0,2x0,5) 7,58 m3 ­ ­
18 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 46,00 m' ­ ­
19 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik ­ ­
20 Fender Type V, 600H x 2000L 13,00 bh ­ ­
21 Bollard Curve Kap. 70 ton 2,00 bh ­ ­
JUMLAH II D ­

E Pembongkaran Dermaga Eksisting 12M x 50M ­ Tahun 1998


1 Pembongkaran Pelat Lantai & Balok 252,50 m3 ­ ­
2 Pembongkaran Pile Cap 36,00 m3 ­ ­
3 Pemotongan Tiang Pancang Eksisting + Angkut ke Darat 50,00 titik ­ ­

JUMLAH II E  ­

F Dermaga 20M x 50M ­ Tahun 2015


1 Pengadaan dan pengangkutan tiang pancang pipa baja 203.742,00 Kg ­ ­
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 1.386,00 m' ­ ­
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 954,00 m' ­ ­
4 Pemancangan Tiang Miring, Dia. 508mm T : 12mm 432,00 m' ­ ­
5 Penyambungan Tiang Pancang Baja Dia. 508 mm, 77,00 ea ­ ­
6 Pemotongan Kepala Tiang Pancang Dia. 508 mm 77,00 ttk ­ ­
7 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 270,46 m2 ­ ­
8 Pembuatan Sepatu Tiang Pancang 77,00 ea ­ ­
9 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 77,00 titik ­ ­
10 Beton Pelat Lantai, K­350 ; t : 30 cm 229,35 m3 ­ ­

DED PELABUHAN LUWUK
HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

11 Balok Memanjang Beton K­350, (50/80 cm) 100,00 m3 ­ ­


12 Balok Melintang Beton K­350, (50/80 cm) 88,40 m3 ­ ­
13 Balok Dudukan Fender Beton K­350, (50/140/280 cm) 22,75 m3 ­ ­
14 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 49,78 m3 ­ ­
15 Pilecap Tiang Ganda Beton K­350, (1,0 x 1,0 x 2,0), 22,54 m3 ­ ­
16 Beton Kanstin, K350 tinggi : 15/20 cm 105,50 m' ­ ­
17 Beton List Plank Depan & Belakang, (0,2x0,5) 8,73 m3 ­ ­
18 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 47,00 m' ­ ­
19 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik ­ ­
20 Fender Type V, 600H x 2000L 13,00 bh ­ ­
21 Bollard Curve Kap. 70 ton 2,00 bh ­ ­
JUMLAH II F ­

G Trestle 10M x 20M ­ Tahun 2015


1 Pengadaan dan pengangkutan tiang pancang pipa baja 44.982,00 Kg ­ ­
dia. 508mm, t = 12mm.
2 Pengangkutan Tiang Pancang Ke Lokasi Pemancangan 306,00 m' ­ ­
3 Pemancangan Tiang Tegak, Dia. 508mm T : 12mm 306,00 m' ­ ­
4 Penyambungan Tiang Pancang Baja Dia. 508 mm, 17,00 ea ­ ­
5 Pemotongan Kepala Tiang Pancang Dia. 508 mm 17,00 ttk ­ ­
6 Pekerjaan Proteksi Lapis Luar Pipa Tiang Pancang 59,71 m2 ­ ­
7 Pembuatan Sepatu Tiang Pancang 17,00 ea ­ ­
8 Beton Isian Tiang Pancang Pipa Baja Dia. 508 mm 17,00 titik ­ ­
9 Beton Pelat Lantai, K­350 ; t : 30 cm 50,10 m3 ­ ­
10 Balok Memanjang Beton K­350, (50/80 cm) 24,00 m3 ­ ­
11 Balok Melintang Beton K­350, (50/80 cm) 20,00 m3 ­ ­
12 Pilecap Tiang Tunggal Beton K­350, (1,0 x 1,0 x 1,0) 15,97 m3 ­ ­
13 Beton Kanstin, K350 tinggi : 15/20 cm 41,00 m' ­ ­
14 Beton List Plank Depan & Belakang, (0,2x0,5) 3,60 m3 ­ ­
15 Siku Dilatasi, 100 x 100 x 10 mm ( Galvanice ) 12,00 m' ­ ­
16 Penerangan Dermaga + Solar Cell, LED 50 W, Tiang : 9 m, 2,00 titik ­ ­
JUMLAH II G  ­

III PEKERJAAN PENGERUKAN


A Pekerjaan Persiapan
1 Mobilisasi & Demobilisasi Alat Kerja 1,00 ls ­ ­

B Pekerjaan Pengerukan
1 Pekerjaan Pengerukan Kolam Pelabuhan 1.154,38 m3 ­ ­

J u m l a h : I + II.A + II.B + II.C + II.D + II.E + II.F + II.G + III.A + III.B ­


PPN 10 % ­
JUMLAH TOTAL ­
DIBULATKAN ­
Terbilang :
= …………………………………………………………. =

DED PELABUHAN LUWUK
1.080,00 

DED PELABUHAN LUWUK
1.000,00 

DED PELABUHAN LUWUK
DED PELABUHAN LUWUK
LK ‐ TERMINAL PELABUHAN 
A  PEKERJAAN PONDASI 
1 Galian Pondasi 
a Lebar  =  0,90  m 
b Dalam  =  0,60  m 
Luas Penampang  =  0,90  x  0,60  =  0,540  m2 
c Panjang  : 
Panjang  =  22,0  x  3,0  +  3,5  x  6,0  =  87,00  m 
=  2,0  x  4,0  +  3,0  x  2,0  =  14,00  m 
Lebar  =  17,0  x  4,0  +  3,0  x  5,0  =  83,00  m 
Panjang  =  184,00  m 
3
Volume Galian  =  0,540  x  184,00  = 99,36 m

3
2 Urugan Pasir Bawah Pondasi  =  184,00  x  0,10  x  0,80  = 14,72 m

3.a Pondasi Batu Kali 


a Lebar atas  =  0,25  m  Rata2  =  0,425  m 
b Lebar bawah  =  0,60  m 
c Dalam  =  0,50  m
3
Volume Pondasi  =  0,425  x  0,50  x  184,00  = 39,10 m

3.b Pondasi Batu Kali, Bagian Luar 


a Lebar atas  =  0,20  m  Rata2  =  0,275  m 
b Lebar bawah  =  0,35  m 
c Dalam  =  0,40  m 
d Panjang  =  19,00  x  2  +  18 x 2  =  74,00  m

Volume Pondasi  =  0,275  x  0,40  x  74,00  = 8,14 m

Jumlah  = 47,24 m

4 Beton Slof 
Lebar  =  0,15  m 
Tinggi  =  0,25  m 
Panjang  =  184,0  m

Volume Slof  =  0,150  x  0,25  x  184,00  = 6,90 m

5 Urugan Kembali Pondasi + Bawah Lantai 


a Sisi Pondasi  = (  0,90  x  0,50  ­  0,21  ) x  184,00  =  43,70 
b Bawah lantai  =  0,25  x  21,0  x  17,0  =  89,25 
c Urugan Sisi Luar  =  0,90  x  46,0  +  0,9  x  34,0  =  72,00 

Volume  = 204,95 m
6 Lantai kerja dibawah lantai, t : 5 cm 

a Lantai dalam  =  0,05  x  21,0  x  17,0  = 17,85 m

b Lantai luar  =  0,045  x  46,0  +  0,045  x  34,0  = 3,60 m

Volume  = 21,45 m
7 Keramik Lantai Toilet : 20/20 
a Lebar  =  3,50  m 
b Panjang  =  8,00  m 

Luas Lantai  =  2,0  x  3,50  x  11,50  = 80,50 m

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
8 Dinding Keramik WC : 20/25 
Tinggi  =  1,60  m 
Panjang  =  2,00  x  6,50  =  13,00  m 
=  2,00  x  8,00  x  2,00  =  32,00  m 
=  0,75  x  4,00  x  2,00  =  6,00  m 
Tempat Wudhu  =  2,00  x  3,00  =  6,00  m 
Panjang  =  57,00  m 

Luas Dinding  =  1,60  x  57,00  = 91,20 m

9 Keramik Ruang Tunggu & Ruang Kerja : 40/40 



Ruang Utama  =  21,00  x  17,00  ­  80,50  =  276,50  m 
Mushola  =  3,50  x  3,60  =  12,60 

Teras  =  2,0  x  3,00  x  2,80  =  16,80  m 

Selasar luar  =  1,1  x  74,00  =  81,40  m 
2
=  Luas  = 387,30 m

B PEKERJAAN DINDING
1 Dinding Batu Bata 
a Tinggi dinding  =  3,88  ­  0,15  =  3,73  m 
b Panjang dinding  =  184,0  m 

Luas dinding  =  3,73  x  184,0  =  686,320  m 
c Pengurang  : 

1 Pintu ( P.1 )  =  (3,0)  x  2,05  x  1,50  =  (9,225)  m 

2 Pintu ( P.2 )  =  (5,0)  x  2,05  x  0,90  =  (9,225)  m 

3 Pintu ( P.3 )  =  (10,0)  x  1,80  x  0,70  =  (12,600)  m 

4 Pintu sorong ( P.5 )  =  (2,0)  x  1,80  x  0,80  =  (2,880)  m 

5 Jendela ( J.2 )  =  (16,0)  x  1,25  x  1,15  =  (23,000)  m 

6 Jendela ( J.3 )  =  (1,0)  x  1,90  x  1,15  =  (2,185)  m 

7 Bouven ( BV )  =  (9,0)  x  0,40  x  0,60  =  (2,160)  m 

Luas dinding  = 625,05 m
2 Plesteran 

Luas dinding  =  625,05  m 

Luas plesteran  =  2,00  x  625,05  =  1.250,09  m 

Pengurang,  Plafond  =  (2,0)  x  0,15  x  184,00  =  (55,200)  m 

Dinding keramik  =  =  (91,20)  m 

Luas Plester  = 1.103,69 m

3 Kolom Praktis, 15/15 



Lebar  =  0,15  m  Luas  =  0,0225  m 
Panjang  =  0,15  m 
Tinggi  =  7,65  ­  3,92  =  3,73  m 
Jumlah  =  46,0  titik 

Volume Kolom  =  0,0225  x  3,73  x  46,0  = 3,86 m

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
4 Ring Balok, 15/15 

Lebar  =  0,15  m  Luas  =  0,0225  m 
Tinggi  =  0,15  m 
Panjang  =  184,00  m 

Volume Ring  =  0,0225  x  184,00  = 4,14 m

5 Saluran Keliling Bangunan 


Depan & Belakang  = (  21,00  +  2,50  +  3,00  ) x  2,0  =  53,00  m 
Samping  = (  17,00  +  2,50  ) x  2,00  =  39,00  m 
Panjang  = 92,00 m
C Pekerjaan Plafond 
1 Plafond luar,  lebar  =  1,2  m 
Panjang  =  19,5  x  2,0  =  39,0  m 
18,0  x  2,0  =  36,0  m 
5,4  x  2,0  =  10,8  m 
3,0  x  4,0  =  12,0  m 
Panjang  =  97,8  m 

Luas  =  1,2  x  97,8  =  117,36  m 

Teras  =  3,0  x  2,5 x  2  =  15,00  m 

Plafond Dalam  =  17,0  x  21,0  =  357,00  m 

Panjang  = 489,36 m
2 List Plafond 
Arah Memanjang  =  22,0  x  3,0  x  2  =  132,00  m 
= (  8,0  +  6,0  ) x  2  =  28,00  m 
= (  3,5  +  6,0  ) x  2  =  19,00  m 
Arah melebar  =  17,0  x  4,0  x  2  =  136,00  m 
=  3,0  x  5,0  x  2  =  30,00  m 
Luar  =  19,5  x  2,0  =  39,00  m 
=  23,5  x  2,0  =  47,0  m 
Teras  = (  6,0  +  5,4  ) x  2  =  22,80  m 
Panjang  = 453,80 m
D Atap dan Rangka Atap 
1 Beton Kuda­Kuda, 15/25 cm 
Lebar  =  0,15  m  Luas  =  0,0375  m2  0,5 Kuda­kuda 
Tinggi  =  0,25  m 
Panjang rangka  =  17,00  +  3,96  =  20,96  m  8,50  m 
9,37  x  2,00  =  18,74  m  9,37  m 
1,43  x  2,00  =  2,86  m  1,43  m 
3,17  x  2,00  =  6,34  m  3,17  m 
2,64  x  2,00  =  5,28  m  2,64  m 
3,87  x  2,00  =  7,74  m  3,87  m 
Panjang  =  61,92  m  =  28,98  m 
Volume 1 unit Kuda­kuda  =  0,0375  x  61,92  = 2,32 m3 1,09 m3 

Volume 2 unit Kuda­kuda  =  2,32  x  2,0  =  4,644  m3 


Volume 2 unit 1/2 Kuda­kuda  =  1,09  x  2,0  =  2,174  m3 
Volume 4 unit 1/2 Kuda­kuda/Jurai  =  1,52  x  4,0  =  6,086  m3 
Balok atas, L : 4 m  =  0,0375  x  4,0  =  0,150  m3 
Volume  = 13,05 m3 

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
2 Atap Genteng Metal Pasir 
Segitiga  =  19,50  x  10,80  =  210,60 
Trapesium  = (  4,00  +  23,50  ) x  10,80  =  297,00 
=  3,00  x  2,50  x  4,00  =  30,00 
Luas Atap  = 537,60 m2 
3 Nok / Bubungan 
Atas  =  4,00  +  5,00  +  12,00  =  21,00 
Diagonal  =  4,00  x  10,80  x  1,414  =  61,08 
Panjang Nok  = 82,08 m' 

4 Lisplank Kayu 2/20 cm 
=  19,5  x  2,0  +  23,5 x  2  = 96,00 m' 

5 Gording, besi profil canal. 100 x 50 x 20 x 3,2 


Berat  =  5,50  kg/m' 
Jumlah  =  12,00  jalur 
a Berat, 2 segitiga  =  2,0  x  10,0  x  12,00  x  5,50  =  1.320,00  kg 
b Berat, 2 trapesium  =  2 x ( 4 + 23,50 )/2  x  12,00  x  5,50  =  1.815,00  kg 
c Berat, 2 segitiga teras  =  2,0  x  9,0  x  5,00  x  5,50  =  495,00  kg 
d Skur gording,  2.C  =  2,0  x  6,0  x  16,00  x  5,50  =  1.056,00  kg 
Berat  =  4.686,00  kg 
Total Berat  = 4.920,30 kg 
6 Luasan Cat Gording  =  0,24  x  2,0  =  0,48  m2 
Panjang Profil : 
a  Panjang 2 Segitiga  =  2,0  x  10,0  x  12,00  =  240,00  m' 
b  Panjang 2 trapesium  =  2 x ( 4 + 23,50 )/2  x  12,00  =  330,00  m' 
c Panjang 2 segitiga teras  =  2,0  x  9,0  x  5,00  =  90,00  m' 
d Skur gording,  2.C  =  2,0  x  6,0  x  16,00  =  192,00  m' 
Panjang  =  852,00  m' 
Total panjang  = 894,60 m' 
=  0,48  x  894,60  = 429,41 m2
E Menara Air 
1 Galian Tanah  =  0,70  x  0,60  x  4,00  = 1,68 m3 
2 Pasangan Batu Kali  =  0,375  x  0,50  x  4,00  = 0,75 m3 
3 Slof 15/15  =  0,15  x  0,15  x  1,00  x  4,00  =  0,09  m3 
4 Kolom 15/15  =  0,15  x  0,15  x  4,00  x  4,00  =  0,36  m3 
5 Balok atas 15/15  =  0,15  x  0,15  x  1,20  x  4,00  =  0,11  m3 
Balok silang  =  0,15  x  0,15  x  1,50  x  2,00  =  0,07  m3 
Balok tengah  =  0,15  x  0,15  x  0,85  x  4,00  =  0,08  m3 
Volume beton  = 0,70 m3 

6 Besi siku : 50x50x5  =  1,40  x  2,00  x  4,00  x  3,77  =  42,22  kg 


Tiang  =  0,70  x  3,00  x  4,00  x  3,77  =  31,67  kg 
Tangga  =  4,50  x  2,00  x  1  x  3,77  =  33,93  kg 
=  0,50  x  8,00  x  1  x  3,77  =  15,08  kg 
Berat profil L.50  = 122,90 kg 

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
F Sign Post, Laut & Darat
1 Galian Tanah 
Luas galian  =  1,00  x  1,0  =  1,00  m2 
Dalam  =  0,85  m 
Jumlah  =  7,00  titik 
Volume  =  1,00  x  0,85  x  7,00  = 5,95 m3 
2 Unit  = 11,90 m3 
2 Urugan kembali  =  5,95  ­  0,28  ­  1,01  = 4,66 = 9,32 m3 
3 Lantai kerja, pelat kaki 
Tebal  =  0,05  m 
Luas  =  0,9  x  0,9  =  0,81  m2 
Jumlah  =  7,0  titik 
Volume  =  0,05  x  0,81  x  7,00  =  0,28 m3
Lantai kerja Slof 
Tebal  =  0,05  m 
Luas  =  0,30  x  2,35  =  0,71  m2 
Jumlah  =  6,0  titik 
Volume  =  0,05  x  0,71  x  6,00  =  0,21 m3 
Volume Lantai Kerja  = 0,50 m3 
2 Unit  = 0,99 m3 
4 Pelat kaki,  tebal  =  0,225  m 
Panjang  =  0,80  m 
Lebar  =  0,80  m 
Jumlah  =  7,0  titik 
Volume  =  0,225  x  0,80  x  0,80  x  7,0  = 1,01 m3 
2 Unit  = 2,02 m3 
5 Kolom,  Panjang  =  3,30  m 
Panjang  =  0,15  m 
Lebar  =  0,15  m 
Jumlah  =  7,0  bh 
Volume  =  3,30  x  0,15  x  0,15  x  7,0  = 0,52 m3 
2 Unit  = 1,04 m3 
6 Slof, 
Luas  =  0,15  x  0,20  =  0,03  m2 
Panjang  =  15,15  m' 
Volume  =  0,03  x  15,15  = 0,45 m3 
2 Unit  = 0,91 m3 
7 Balok, 
Luas  =  0,15  x  0,15  =  0,0225  m2 
Panjang  =  2,35  x  6,00  =  14,10  m' 
Jumlah Balok  =  2,0 
Volume  =  0,0225  x  14,10  x  2,00  = 0,63 m3 
2 Unit  = 1,27 m3 

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
8 Cat Luar 
Kolom,  =  0,60  x  2,80  x  7,00  =  11,76  m2 
Slof,  =  0,55  x  2,35  x  6,00  =  7,76  m2 
Balok,  =  0,60  x  15,00  x  2,00  =  18,00  m2 
Luas  = 37,52 m2 
2 Unit  = 75,03 m2

G Pintu Gerbang : 2 Unit


1 Galian Tanah 
Luas galian  =  1,80  x  1,8  =  3,24  m2 
Dalam  =  1,05  m 
Jumlah  =  2,00  titik 
Volume  =  3,24  x  1,05  x  2,00  = 6,80 m3 
2 Unit  = 13,61 m3 
2 Urugan kembali  =  6,80  ­  0,29  ­  1,54  = 4,98 = 9,96 m3 
3 Lantai kerja, pelat kaki 
Tebal  =  0,05  m 
Luas  =  1,7  x  1,7  =  2,89  m2 
Jumlah  =  2,0  titik 
Volume  =  0,05  x  2,89  x  2,00  =  0,29 m3 
2 Unit  = 0,58 m3 
4 Pelat kaki,  tebal  =  0,30  m 
Panjang  =  1,60  m 
Lebar  =  1,60  m 
Jumlah  =  2,0  m 
Volume  =  0,300  x  1,60  x  1,60  x  2,0  = 1,54 m3 
2 Unit  = 3,07 m3 
5 Kolom,  Tinggi  =  6,60  m 
Lebar  =  0,80  m 
Tebal  =  0,15  m 
Jumlah  =  4,0  m 
Volume  =  6,60  x  0,80  x  0,15  x  4,0  = 3,17 m3 
2 Unit  = 6,34 m3 
6 Pelat Sekat,     tebal  =  0,15  m 
Panjang  =  1,50  m 
Lebar  =  1,50  m 
Jumlah  =  2,0  m 
Volume  =  0,15  x  1,50  x  1,50  x  2,0  = 0,68 m3 
2 Unit  = 1,35 m3 
7 Balok Bawah, Panjang  =  7,40  m 
Lebar  =  0,20  m 
Tinggi  =  0,40  m 
Jumlah  =  1,0 
Volume  =  7,40  x  0,20  x  0,40  x  1,0  = 0,59 m3 
2 Unit  = 1,18 m3 

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
Balok Atas,     Panjang  =  10,50  m 
Tebal  =  0,12  m 
Tinggi  =  0,90  m 
Jumlah  =  2,0 
Volume  =  10,50  x  0,12  x  0,90  x  2,0  =  2,27 m3 
2 Unit  =  4,54 m3 
Total Balok  = 5,72 m3 
8  Pasangan Batu Bata 
Tinggi  =  0,80  +  2,80  =  3,60  m 
Lebar  =  0,50 
Jumlah  =  4,0 
Volume  =  3,60  x  0,50  x  4,00  =  7,20 m3 
2 Unit  = 14,40 m3 
9 Plesteran + ACI 
Tinggi  =  3,60  m 
Lebar  =  0,50 
Jumlah  =  4,00 
Luas  =  3,60  x  0,50  x  4,00  =  7,20  m2 
2 Unit  = 14,40 m2 
10 Cat Luar 
a Dinding bawah 
Tinggi  =  2,00  m 
Lebar  = (  0,30  +  1,60  ) x  4,00  =  7,60  m 
Luas  =  2,00  x  7,60  =  15,20 m2 
b Dinding atas 
Tinggi  =  3,60  m 
Lebar  =  0,80  x  4,00  =  3,20  m 
Luas  =  3,60  x  3,20  =  11,52 m2 
c Balok bawah 
Tinggi  =  0,40  m 
Panjang  =  7,40  m 
Lebar  =  0,60  x  2,00  =  1,20  m 
Luas  =  7,40  x  1,20  =  8,88 m2 
d Balok Atas, 
Tinggi  =  0,90  m 
Panjang  =  10,50  m 
Lebar  =  0,30  +  1,80  =  2,10  m 
Jumlah  =  2,00 
Luas  =  10,50  x  2,10  x  2,00  =  44,10 m2 
Luasan Cat  = 79,70 m2 
2 Unit  = 159,40 m2 

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
F Kandungan besi beton 
1 Beton Slof 15/25  =  0,15  x  0,25  = 0,038  m3 
Tulangan Slof :  4 D 16 mm 
4 D 16mm  =  4,00  x  1,00  x  1,58  =  6,320  kg 
Sengkang f 10 ­ 200  =  5,00  x  0,70  x  0,62  =  2,170  kg 
berat besi  = 8,49  kg 
Berat besi / m3  =  8,49  /  0,038  ~  226,40  ~ 230,00 kg/m3 
Luas Begisting  =  0,25  x  2,00  =  0,50  m2 
Luas Begisting  =  13,3333  ~ 13,50 m2 

2 Ring Balok, 15/15  =  0,15  x  0,15  = 0,0225  m3 


4 f 12mm  =  4,00  x  1,00  x  0,89  =  3,560  kg 
Sengkang f 8 ­ 200  =  5,00  x  0,50  x  0,40  =  1,000  kg 
berat besi  = 4,56  kg 
Berat besi / m3  =  4,56  /  0,0225  ~ 205,00  kg/m3 
Luas Begisting  = (  0,15  x  2,00  ) /  0,0225  = 13,50  m2 

3 Kolom Praktis, 15/15  =  0,15  x  0,15  = 0,0225  m3 


4 f 12mm  =  4,00  x  1,00  x  0,89  =  3,560  kg 
Sengkang f 8 ­ 200  =  5,00  x  0,50  x  0,40  =  1,000  kg 
berat besi  = 4,56  kg 
Berat besi / m3  =  4,56  /  0,0225  ~ 205,00  kg/m3 
Luas Begisting  = (  0,15  x  2,00  ) /  0,0225  = 13,50  m2 

4 Beton Kuda2 15/25  =  0,15  x  0,25  = 0,038  m3 


Tulangan Slof :  4 D 16 mm 
4 D 16mm  =  4,00  x  1,00  x  1,58  =  6,320  kg 
Sengkang f 10 ­ 200  =  5,00  x  0,70  x  0,62  =  2,170  kg 
berat besi  = 8,49  kg 
Berat besi / m3  =  8,49  /  0,038  ~  226,40  ~ 230,00 kg/m3 
Luas Begisting  =  0,25  x  2,00  =  0,50  m2 
=  0,15  x  2,00  =  0,30  m2 
=  0,80  m2 
Luas Begisting  =  21,3333  ~ 21,50 m2 

DED PELABUHAN LUWUK  LK‐GEDUNG TERMINAL
ENGINEER ESTIMATE (EE)
DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK BANGGAI
PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT
PEKERJAAN TERMINAL PELABUHAN

HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran Darat 1,00 ls 7.500.000,00 7.500.000,00
2 Pasang Papan Nama Proyek 1,00 bh 2.000.000,00 2.000.000,00
3 Direksi Keet 32,00 m2 2.000.000,00 64.000.000,00
4 Gudang Material 24,00 m2 1.800.000,00 43.200.000,00
5 Bedeng Pekerja 32,00 m2 2.000.000,00 64.000.000,00
6 Penyediaan Air Kerja & Penerangan 1,00 Ls 17.500.000,00 17.500.000,00
JUMLAH I  198.200.000,00

II PEKERJAAN TERMINAL PELABUHAN : 17m x 21m


A Pekerjaan Pondasi
1 Pekerjaan Galian Tanah 99,36 m3 81.150,00 8.063.064,00
2 Urugan Pasir Bawah Pondasi 14,72 m3 375.000,00 5.520.000,00
3 Pondasi Pasangan Batu Kali 1 : 4 47,24 m3 1.034.440,00 48.866.945,60
4 Beton Slof K­225, (15/25 cm) 6,90 m3 10.601.700,00 73.151.730,00
5 Urugan Samping Pondasi & Bawah Lantai 204,95 m3 23.920,00 4.902.404,00
6 Lantai Kerja Dibawah Lantai Keramik, K­125 21,45 m3 1.263.080,00 27.093.066,00

B Pekerjaan Dinding & Plesteran


1 Pekerjaan Dinding Batu Bata, 1 : 4 625,05 m3 126.500,00 79.068.192,50
2 Pekerjaan Plesteran t : 15 cm 1.103,69 m2 61.730,00 68.130.783,70
3 Pekerjaan Kolom Praktis, 15/15 cm 3,86 m3 10.085.830,00 38.936.851,01
4 Pekerjaan Ring Balok, 15/15 cm 4,14 m3 10.085.830,00 41.755.336,20
5 Saluran Keliling Bangunan, 0,5 Lingkaran, Dia. 30 cm 92,00 m' 185.000,00 17.020.000,00

C Pekerjaan Pintu dan Jendela


1 Pekerjaan Pintu Utama ( P.1 ), kaca : 12mm 3,00 unit 5.375.000,00 16.125.000,00
2 Pekerjaan Pintu Ruangan ( P.2 ) 5,00 unit 2.525.000,00 12.625.000,00
3 Pekerjaan Pintu Toilet ( P.3 ) 10,00 unit 975.000,00 9.750.000,00
4 Pekerjaan Pintu Slidding Aluminium ( P.4 ) 2,00 unit 2.550.000,00 5.100.000,00
5 Pekerjaan Jendela 2 Daun ( J.2 ) 15,00 unit 1.395.000,00 20.925.000,00
6 Pekerjaan Jendela 3 Daun ( J.1 ), Loket Pendaftaran 1,00 unit 1.835.000,00 1.835.000,00
7 Pekerjaan Jendela Bouvenlight ( BV ) 10,00 unit 351.780,00 3.517.800,00

D Pekerjaan Plafond
1 Pekerjaan Pasang Plafont GRC, tebal 4 mm 489,36 m2 36.940,00 18.076.958,40
2 Rangka Plafond Besi Hollo, 4 cm, t : 4mm 489,36 m2 92.750,00 45.388.140,00
3 Pasang List Plafond 453,80 m' 12.500,00 5.672.500,00

DED PELABUHAN LUWUK‐TA. 2015  95  BANGUNAN TERMINAL PENUMPANG


HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

E Pekerjaan Pasang Keramik


1 Pasang Keramik Lantai Toilet 20/20 80,50 m2 152.060,00 12.240.830,00
2 Pasang Keramik Lantai R. Tunggu & R. Kerja 40/40 387,30 m2 156.890,00 60.763.497,00
3 Pasang Keramik Dinding Toilet 20/25, h : 160 cm 91,20 m2 166.890,00 15.220.368,00

F Pekerjaan Atap dan Rangka Atap


1 Beton Rangka Kuda­Kuda, K.225 13,05 m3 12.677.730,00 165.486.213,01
2 Gording Profil Canal, C.100 x 50 x 20 x 3,2mm 4.920,30 kg 24.200,00 119.071.260,00
3 Cat Anti Karat, (zincromate) 429,41 m2 28.750,00 12.345.480,00
4 Pasang Genteng Metal Pasir, t : 0.5 mm 537,60 m2 82.500,00 44.352.000,00
5 Pasang Nok Genteng Metal 82,08 m' 92.500,00 7.592.844,00
6 Pekerjaan Talang seng BJLS 15,00 m' 114.140,00 1.712.100,00
7 Pasang List Plank kayu 2/20 cm 96,00 m' 72.000,00 6.912.000,00

G Pekerjaan Pengecatan
1 Pengecatan Dinding / Tembok, ICI 1.103,69 m2 33.650,00 37.139.168,50
2 Pengecatan Plafond 489,36 m2 30.210,00 14.783.565,60
3 Pengecatan List Plank Kayu, (2/20cm) 28,80 m2 34.170,00 984.096,00
4 Pengecatan List Plafond 453,80 m' 7.500,00 3.403.500,00

H Pekerjaan Sanitair
1 Pasang Klosed Jongkok, (TOTO) 6,00 bh 295.000,00 1.770.000,00
2 Pasang Klosed Duduk, (TOTO) 2,00 bh 2.325.000,00 4.650.000,00
3 Pasang Orinoir (TOTO), type muslim 6,00 bh 1.915.000,00 11.490.000,00
4 Pembuatan Septictank (1 x 1,5 x 2m) dan Peresapan 2,00 unit 9.255.000,00 18.510.000,00
5 Wastafel bulat warna standar lengkap, (TOTO) 8,00 bh 875.000,00 7.000.000,00
6 Pasang Cermin Wastafel, tebal 5 mm 2,52 m2 145.000,00 365.400,00
7 Pasang Kran 3/4" 16,00 bh 46.000,00 736.000,00
8 Instalasi Pipa Air Bersih, 3/4"; 1"; 2" 1,00 Ls 7.500.000,00 7.500.000,00
9 Floor Drain 4" 8,00 bh 114.000,00 912.000,00

I Pekerjaan Instalasi Listrik


1 Sambung Daya PLN­16500 VA 1,00 Ls 12.500.000,00 12.500.000,00
2 Panel Penerangan + Grounding 1,00 Unit 7.500.000,00 7.500.000,00
3 Lampu TL­36 Balk 15,00 bh 425.000,00 6.375.000,00
4 Lampu SL 18 Watt E­27 32,00 bh 75.000,00 2.400.000,00
5 Saklar Single 12,00 bh 40.000,00 480.000,00
6 Saklar Double 11,00 bh 45.000,00 495.000,00
7 Stop Kontak 9,00 bh 45.000,00 405.000,00
8 Stop Kontak AC 12,00 bh 85.000,00 1.020.000,00
9 Instalasi penerangan 91,00 titik 285.000,00 25.935.000,00
10 Instalasi Stop Kontak 12,00 titik 295.000,00 3.540.000,00
11 AC 18000 BTU/H 6,00 Unit 11.550.000,00 69.300.000,00
12 AC 9000 BTU/H 2,00 Unit 5.450.000,00 10.900.000,00
13 AC 6500 BTU/H 2,00 Unit 5.200.000,00 10.400.000,00
14 AC 4500 BTU/H 2,00 Unit 4.800.000,00 9.600.000,00
15 Penutup Kondensor AC, 12,00 Unit 1.455.000,00 17.460.000,00
16 Penangkal Petir 1,00 Ls 11.500.000,00 11.500.000,00 

DED PELABUHAN LUWUK‐TA. 2015  96  BANGUNAN TERMINAL PENUMPANG


HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

J Pekerjaan Assesories
1 Signage Terminal Penumpang 1,00 Ls 24.500.000,00 24.500.000,00
2 Pengadaan Tempat Duduk Ruang Tunggu 202,00 bh 225.000,00 45.450.000,00
3 Exos Vane 350 CFM Wall Type 1,00 bh 1.250.000,00 1.250.000,00

K Menara Air Tinggi 4m, Kapasitas 1000 Ltr.


1 Galian Tanah Pondasi 1,68 m3 81.150,00 136.332,00
2 Pasangan Batu Kali 1 : 4 0,75 m3 1.034.440,00 775.830,00
3 Pekerjaan Beton K­225, (15/15) 0,70 m3 12.677.730,00 8.899.766,46
4 Pekerjaan Baja Profil L.50x50x5, + Tangga 122,90 kg 24.200,00 2.974.228,40
5 Tangki Air Atas 1,00 bh 2.450.000,00 2.450.000,00
6 Pompa Air, deschart 9 m 1,00 bh 2.750.000,00 2.750.000,00
7 Instalasi Air Bersih dia. 3/4" 50,00 m' 15.000,00 750.000,00

L Sign Post : Darat dan Laut, ( 2 Unit )


1 Galian Tanah Pondasi 11,90 m3 81.150,00 965.685,00
2 Tanah Urug Kembali 9,32 m3 23.920,00 222.862,64
3 Beton Lantai Kerja K­125, ( t : 5 cm ) 0,99 m3 1.263.080,00 1.250.449,20
4 Beton Pelat Kaki K­225 2,02 m3 10.601.700,00 21.373.027,20
5 Beton Slof K­225, ( 15/20 cm ) 0,91 m3 10.601.700,00 9.636.945,30
6 Beton Kolom K­225, ( 15/15 cm) 1,04 m3 10.085.830,00 10.484.220,29
7 Beton Balok K­225, (15/15) 1,27 m3 10.085.830,00 12.798.918,27
8 Baut Dynabolt & Pemasangan 106,00 bh 37.500,00 3.975.000,00
9 Letter Box + Lampu + Logo + Aksesoris ( 15 huruf ) 30,00 bh 925.000,00 27.750.000,00
10 Finishing Cat Exterior 75,03 m2 33.650,00 2.524.759,50

M Pintu Gerbang, ( 2 Unit )


1 Galian Tanah Pondasi 13,61 m3 81.150,00 1.104.289,20
2 Tanah Urug Kembali 9,96 m3 23.920,00 238.195,36
3 Beton Lantai Kerja K­125, ( t : 5 cm ) 0,58 m3 1.263.080,00 730.060,24
4 Beton Pelat Kaki K­225 3,07 m3 10.601.700,00 32.568.422,40
5 Beton Kolom K­225, ( 15/80 cm ) 6,34 m3 10.085.830,00 63.903.818,88
6 Beton Pelat Sekat K­225, (t : 10 cm) 1,35 m3 7.399.120,00 9.988.812,00
7 Beton Balok K­225, (20/40) & (15/30) 5,72 m3 10.085.830,00 57.690.947,60
8 Pasangan Batu bata 1 : 4 14,40 m2 126.500,00 1.821.600,00
9 Plesteran ACI 14,40 m2 61.730,00 888.912,00
10 Letter Box + Lampu + Logo + Aksesoris ( 15 huruf ) 30,00 bh 925.000,00 27.750.000,00
11 Finishing Cat Exterior 159,40 m2 33.650,00 5.363.810,00
12 Asesoris Dinding 28,80 bh 225.000,00 6.480.000,00
13 Profilan Kolom, (Atas + Bawah) 72,00 m' 175.000,00 12.600.000,00
14 Lampu Spot GL E.27+PAR38/80W 4,00 bh 325.000,00 1.300.000,00

JUMLAH II  1.699.620.985,45

J u m l a h : I + II 1.897.820.985,45
PPN 10 % 189.782.098,55
JUMLAH TOTAL 2.087.603.084,00
DIBULATKAN 2.087.600.000,00
Terbilang :
= Dua milyar delapan puluh tujuh juta enam ratus ribu rupiah =

DED PELABUHAN LUWUK‐TA. 2015  97  BANGUNAN TERMINAL PENUMPANG


81.150,00
375.000,00
987.500,00

27.550,00

125.500,00
74.500,00

2.000.000,00

750.000,00

33.500,00
94.500,00
12.500,00 

DED PELABUHAN LUWUK‐TA. 2015  98  BANGUNAN TERMINAL PENUMPANG


164.850,00
180.650,00
172.500,00

82.500,00
92.500,00
114.140,00

41.750,00 36250
29.500,00
37.500,00

295.000,00
2.325.000,00
1.225.000,00

875.000,00
145.000,00

114.000,00

91,00 

DED PELABUHAN LUWUK‐TA. 2015  99  BANGUNAN TERMINAL PENUMPANG


18.736.156,86

90.981.867,40

222.428.867,68

1.748.800.000,0 

DED PELABUHAN LUWUK‐TA. 2015  100  BANGUNAN TERMINAL PENUMPANG


BILL OF QUANTITY (BOQ)
DETAIL ENGINEERING DESIGN (DED) PELABUHAN LUWUK BANGGAI
PROVINSI SULAWESI TENGAH
DIREKTORAT JENDERAL PERHUBUNGAN LAUT
PEKERJAAN TERMINAL PELABUHAN

HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran Darat 1,00 ls ­ ­
2 Pasang Papan Nama Proyek 1,00 bh ­ ­
3 Direksi Keet 32,00 m2 ­ ­
4 Gudang Material 24,00 m2 ­ ­
5 Bedeng Pekerja 32,00 m2 ­ ­
6 Penyediaan Air Kerja & Penerangan 1,00 Ls ­ ­
JUMLAH I  ­

II PEKERJAAN TERMINAL PELABUHAN : 17m x 21m


A Pekerjaan Pondasi
1 Pekerjaan Galian Tanah 99,36 m3 ­ ­
2 Urugan Pasir Bawah Pondasi 14,72 m3 ­ ­
3 Pondasi Pasangan Batu Kali 1 : 4 47,24 m3 ­ ­
4 Beton Slof K­225, (15/25 cm) 6,90 m3 ­ ­
5 Urugan Samping Pondasi & Bawah Lantai 204,95 m3 ­ ­
6 Lantai Kerja Dibawah Lantai Keramik, K­125 21,45 m3 ­ ­

B Pekerjaan Dinding & Plesteran


1 Pekerjaan Dinding Batu Bata, 1 : 4 625,05 m3 ­ ­
2 Pekerjaan Plesteran t : 15 cm 1.103,69 m2 ­ ­
3 Pekerjaan Kolom Praktis, 15/15 cm 3,86 m3 ­ ­
4 Pekerjaan Ring Balok, 15/15 cm 4,14 m3 ­ ­
5 Saluran Keliling Bangunan, 0,5 Lingkaran, Dia. 30 cm 92,00 m' ­ ­

C Pekerjaan Pintu dan Jendela


1 Pekerjaan Pintu Utama ( P.1 ), kaca : 12mm 3,00 unit ­ ­
2 Pekerjaan Pintu Ruangan ( P.2 ) 5,00 unit ­ ­
3 Pekerjaan Pintu Toilet ( P.3 ) 10,00 unit ­ ­
4 Pekerjaan Pintu Slidding Aluminium ( P.4 ) 2,00 unit ­ ­
5 Pekerjaan Jendela 2 Daun ( J.2 ) 15,00 unit ­ ­
6 Pekerjaan Jendela 3 Daun ( J.1 ), Loket Pendaftaran 1,00 unit ­ ­
7 Pekerjaan Jendela Bouvenlight ( BV ) 10,00 unit ­ ­

D Pekerjaan Plafond
1 Pekerjaan Pasang Plafont GRC, tebal 4 mm 489,36 m2 ­ ­
2 Rangka Plafond Besi Hollo, 4 cm, t : 4mm 489,36 m2 ­ ­
3 Pasang List Plafond 453,80 m' ­ ­

DED PELABUHAN LUWUK
HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

E Pekerjaan Pasang Keramik


1 Pasang Keramik Lantai Toilet 20/20 80,50 m2 ­ ­
2 Pasang Keramik Lantai R. Tunggu & R. Kerja 40/40 387,30 m2 ­ ­
3 Pasang Keramik Dinding Toilet 20/25, h : 160 cm 91,20 m2 ­ ­

F Pekerjaan Atap dan Rangka Atap


1 Beton Rangka Kuda­Kuda, K.225 13,05 m3 ­ ­
2 Gording Profil Canal, C.100 x 50 x 20 x 3,2mm 4.920,30 kg ­ ­
3 Cat Anti Karat, (zincromate) 429,41 m2 ­ ­
4 Pasang Genteng Metal Pasir, t : 0.5 mm 537,60 m2 ­ ­
5 Pasang Nok Genteng Metal 82,08 m' ­ ­
6 Pekerjaan Talang seng BJLS 15,00 m' ­ ­
7 Pasang List Plank kayu 2/20 cm 96,00 m' ­ ­

G Pekerjaan Pengecatan
1 Pengecatan Dinding / Tembok, ICI 1.103,69 m2 ­ ­
2 Pengecatan Plafond 489,36 m2 ­ ­
3 Pengecatan List Plank Kayu, (2/20cm) 28,80 m2 ­ ­
4 Pengecatan List Plafond 453,80 m' ­ ­

H Pekerjaan Sanitair
1 Pasang Klosed Jongkok, (TOTO) 6,00 bh ­ ­
2 Pasang Klosed Duduk, (TOTO) 2,00 bh ­ ­
3 Pasang Orinoir (TOTO), type muslim 6,00 bh ­ ­
4 Pembuatan Septictank (1 x 1,5 x 2m) dan Peresapan 2,00 unit ­ ­
5 Wastafel bulat warna standar lengkap, (TOTO) 8,00 bh ­ ­
6 Pasang Cermin Wastafel, tebal 5 mm 2,52 m2 ­ ­
7 Pasang Kran 3/4" 16,00 bh ­ ­
8 Instalasi Pipa Air Bersih, 3/4"; 1"; 2" 1,00 Ls ­ ­
9 Floor Drain 4" 8,00 bh ­ ­
­
I Pekerjaan Instalasi Listrik
1 Sambung Daya PLN­16500 VA 1,00 Ls ­ ­
2 Panel Penerangan + Grounding 1,00 Unit ­ ­
3 Lampu TL­36 Balk 15,00 bh ­ ­
4 Lampu SL 18 Watt E­27 32,00 bh ­ ­
5 Saklar Single 12,00 bh ­ ­
6 Saklar Double 11,00 bh ­ ­
7 Stop Kontak 9,00 bh ­ ­
8 Stop Kontak AC 12,00 bh ­ ­
9 Instalasi penerangan 91,00 titik ­ ­
10 Instalasi Stop Kontak 12,00 titik ­ ­
11 AC 18000 BTU/H 6,00 Unit ­ ­
12 AC 9000 BTU/H 2,00 Unit ­ ­
13 AC 6500 BTU/H 2,00 Unit ­ ­
14 AC 4500 BTU/H 2,00 Unit ­ ­
15 Penutup Kondensor AC, 12,00 Unit ­ ­
16 Penangkal Petir 1,00 Ls ­ ­ 

DED PELABUHAN LUWUK
HARGA JUMLAH
NO URAIAN VOLUME/SAT
SATUAN (Rp) HARGA (Rp)

J Pekerjaan Assesories
1 Signage Terminal Penumpang 1,00 Ls ­ ­
2 Pengadaan Tempat Duduk Ruang Tunggu 202,00 bh ­ ­
3 Exos Vane 350 CFM Wall Type 1,00 bh ­ ­

K Menara Air Tinggi 4m, Kapasitas 1000 Ltr.


1 Galian Tanah Pondasi 1,68 m3 ­ ­
2 Pasangan Batu Kali 1 : 4 0,75 m3 ­ ­
3 Pekerjaan Beton K­225, (15/15) 0,70 m3 ­ ­
4 Pekerjaan Baja Profil L.50x50x5, + Tangga 122,90 kg ­ ­
5 Tangki Air Atas 1,00 bh ­ ­
6 Pompa Air, deschart 9 m 1,00 bh ­ ­
7 Instalasi Air Bersih dia. 3/4" 50,00 m' ­ ­

L Sign Post : Darat dan Laut, ( 2 Unit )


1 Galian Tanah Pondasi 11,90 m3 ­ ­
2 Tanah Urug Kembali 9,32 m3 ­ ­
3 Beton Lantai Kerja K­125, ( t : 5 cm ) 0,99 m3 ­ ­
4 Beton Pelat Kaki K­225 2,02 m3 ­ ­
5 Beton Slof K­225, ( 15/20 cm ) 0,91 m3 ­ ­
6 Beton Kolom K­225, ( 15/15 cm) 1,04 m3 ­ ­
7 Beton Balok K­225, (15/15) 1,27 m3 ­ ­
8 Baut Dynabolt & Pemasangan 106,00 bh ­ ­
9 Letter Box + Lampu + Logo + Aksesoris ( 15 huruf ) 30,00 bh ­ ­
10 Finishing Cat Exterior 75,03 m2 ­ ­

M Pintu Gerbang, ( 2 Unit )


1 Galian Tanah Pondasi 13,61 m3 ­ ­
2 Tanah Urug Kembali 9,96 m3 ­ ­
3 Beton Lantai Kerja K­125, ( t : 5 cm ) 0,58 m3 ­ ­
4 Beton Pelat Kaki K­225 3,07 m3 ­ ­
5 Beton Kolom K­225, ( 15/80 cm ) 6,34 m3 ­ ­
6 Beton Pelat Sekat K­225, (t : 10 cm) 1,35 m3 ­ ­
7 Beton Balok K­225, (20/40) & (15/30) 5,72 m3 ­ ­
8 Pasangan Batu bata 1 : 4 14,40 m2 ­ ­
9 Plesteran ACI 14,40 m2 ­ ­
10 Letter Box + Lampu + Logo + Aksesoris ( 15 huruf ) 30,00 bh ­ ­
11 Finishing Cat Exterior 159,40 m2 ­ ­
12 Asesoris Dinding 28,80 bh ­ ­
13 Profilan Kolom, (Atas + Bawah) 72,00 m' ­ ­
14 Lampu Spot GL E.27+PAR38/80W 4,00 bh ­ ­

JUMLAH II  ­

J u m l a h : I + II ­
PPN 10 % ­
JUMLAH TOTAL ­
DIBULATKAN ­
Terbilang :
= ………………………………………………………………….. =

DED PELABUHAN LUWUK
­
­
­
­
­
­
­

­
­

­
­
­ 

DED PELABUHAN LUWUK
­
­
­

­
­
­

­ 36250
­
­

­
­
­

­
­

­ 

DED PELABUHAN LUWUK
­

­ 

DED PELABUHAN LUWUK

Anda mungkin juga menyukai