No.
A.
A.I.
A.I.1.1.
A.I.1.2.
A.I.1.3.
A.I.1.4.
A.I.1.5.
A.I.1.6.
A.II.
A.II.2.1.
A.II.2.2.
A.II.2.3.
A.II.2.4.
A.II.2.5.
A.II.2.6.
A.II.2.7.
B.
B.I.
B.I.1.1.
B.I.1.2.
B.I.1.3.
B.I.1.4.
B.I.1.5.
B.I.1.6.
B.II.
B.II.2.1.
B.II.2.2.
B.II.2.3.
B.II.2.4.
B.II.2.5.
C.
C.I.
C.I.1.1.
C.I.1.2.
C.I.1.3.
C.I.1.4.
C.I.1.5.
C.I.1.6.
C.II.
C.II.2.1.
C.II.2.2.
C.II.2.3.
C.II.2.4.
C.II.2.5.
C.II.2.6.
BILL of QUANTITY PEKERJAAN JALAN HAULING PAKET SUNGAI K
Uraian
PAKET PEKERJAAN SUNGAI KERAMASAN - CONTAINER YARD (lebar badan jalan 12 meter)
PEKERJAAN PERSIAPAN
Mobilisasi dan demobilisasi peralatan
Setting pengukuran dan persiapan lahan kerja
Pos & workshop 2x3x4 meter
Air kerja dan listrik
Shop drawing / as built drawing
Quality control urugan
PAKET PEKERJAAN CONTAINER YARD - STASIUN SIMPANG (lebar badan jalan 6 meter)
PEKERJAAN PERSIAPAN
Mobilisasi dan demobilisasi peralatan
Setting pengukuran dan persiapan lahan kerja
Pos & workshop 2x3x4 meter
Air kerja dan listrik
Shop drawing / as built drawing
Quality control urugan
1,550 m'
1,200 m'
1,600 m'