Jumlah 33,511,812,489.38
PPn 11% 3,686,299,373.83
Total 37,198,111,863.21
Dibulatkan 37,198,111,000.00
Terbilang :
Dua Belas Milyar Seratus Tiga Puluh Satu Juta Delapan Ratus Dua Puluh Ribu Rupiah
I Upah :
1 Upah Pemasangan Kanopi 9.6000 m2
Mandor 0.1920 O.H 256,000.00 49,152.00
Kepala Tukang 0.1920 O.H 244,000.00 46,848.00
Tukang 1.9200 O.H 233,000.00 447,360.00
Pekerja 3.8400 O.H 186,000.00 714,240.00
Jumlah Harga Upah : 1,257,600.00
II Bahan :
1 Beton Readymix Kelas C 0.02 m3 1,850,000.00 29,600.00
2 Bekisiting 0.25 m2 203,000.00 50,750.00
3 Dynabolt 8.00 buah 20,000.00 160,000.00
Plat plendes t = 12 mm 9.42 kg 49,000.00 461,580.00
4 Pipa Besi Dia 3 Inch 0.80 m1 173,000.00 138,400.00
5 Pipa Besi Dia 4 Inch 4.00 m1 238,000.00 952,000.00
6 Hollow 100 x 100 9.20 m1 355,000.00 3,266,000.00
7 Hollow 60 x 60 6.40 m1 152,000.00 972,800.00
8 Kawat Las 1.00 ls 28,200.00 28,200.00
9 Atap Polycarbonat 9.60 m2 570,000.00 5,472,000.00
Skrup Atap Kanopi Solartuff Solarflat
6.00 buah
Policarbonat - 25mm, Seal Hitam
Sambungan Solarflat Solar Tuff Plat
1.00 ljr
Policarbonate Lis H U - Lis U
Sambungan Solarflat Solar Tuff Plat
1.50 ljr
Policarbonate Lis H U - Lis H
10 Cat Dasar 21.71 m2 98,000.00 2,127,580.00
11 Cat Finishing 21.71 m2 98,000.00 2,127,580.00
Jumlah Harga Bahan : 15,786,490.00
III Peralatan :
1 Alat Las 1.0000 Ls 75,000.00 75,000.00
2 Alat Angkutan 1.0000 Ls 55,000.00 55,000.00
3 Alat Bantu 1.0000 Ls 7,600.00 7,600.00
Jumlah Harga Peralatan : 137,600.00
IV Jumlah I + II + III : 17,181,690.00
Profit 10 % : 1,718,169.00
Nilai AHSP per segmen 9,6 m2 18,899,859.00
Nilai AHSP per m2 1,968,735.31