DAFTAR HARGA SATUAN BARANG DAN UPAH

No. Nama Barang Standar Satuan Harga (Rp)


1 2 3 4

I BAHAN MATERIAL
~ Batu Gunung Belah 15/20 (lokal) m3 175,000
~ Pasir Pasang (jawa) m3 285,000
~ Pasir Cor m3 350,000
~ Batu Gunung Pecah 2/3 (lokal) m3 300,000
~ Portland Semen 40 Kg zak 54,000
~ Pedel m3 85,000
~ Air ltr 50
~ Kayu papan begisting 2/20 x 4 M' m³ 1,500,000
~ Kayu Untuk Perancah m³ 2,250,000
~ Multiplek 1,22 x 2,44 x 6 mm Lbr 80,000
~ Paku 5-12 cm kg 16,000
~ Besi beton polos kg 12,000
~ Buis Beton D-30cm bh 125,000
~ Buis Beton D-20cm bh 90,000
~ Meteran bh 100,000
~ Minyak Bekisting ltr 10,500
~ Kawat beton kg 20,000
~ Alat bantu Unit 5,000
~ Prasasti Nama Kegiatan Unit 500,000
~ 3 Whell Roller Jam 399,990.46
~ Dump Truck Jam 235,557.24
~ Mobilisasi & Demobilisasi Ls 2,500,000.00
~ Helm Pelindung Kepala Bh 25,000
~ Rompi bh 12,000
~ Sarung Tangan Set 3,000
~ Masker Dus 25,000
~ Chainsaw 7,5 hp Hari 1,000,000

II UPAH
~ Mandor Hari 150,000
~ Kepala Tukang Hari 140,000
~ Tukang Hari 125,000
~ Pekerja Hari 100,000
~ Juru Ukur Hari 150,000
~ Pembantu Juru Ukur Hari 100,000
ANALISA HARGA SATUAN PEKERJAAN DAN UPAH KERJA
KABUPATEN BANGKALAN TAHUN 2023 (PERMENPU N0.1 Tahun 2022)

1 Pengukuran / Uitzet 1 m¹
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.012 100,000.00 1,200.00
Pembantu Juru Ukur OH 0.004 100,000.00 400.00
Juru Ukur OH 0.004 150,000.00 600.00
JUMLAH TENAGA KERJA 2,200.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Meteran OH 0.004 100,000.00 400.00
JUMLAH HARGA ALAT 400.00
D Jumlah (A+B+C) 2,600.00
E Overhead & Profit (Maksimal 15 %) 15% x D 390.00
F Harga Satuan Pekerjaan (D+E) 2,990.00

2 Pembersihan 1 m² Lapangan dan perataan 1.1.f


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Mandor OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 17,500.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 17,500.00
E Overhead & Profit (Maksimal 15 %) 15% x D 2,625.00
F Harga Satuan Pekerjaan (D+E) 20,125.00

3 Keselamatan dan Kesehatan Kerja


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
JUMLAH TENAGA KERJA -
B BAHAN
Helm pelindung kepala Bh 8.000 25,000.00 200,000.00
Rompi Bh 8.000 12,000.00 96,000.00
Sarung Tangan Bh 8.000 3,000.00 24,000.00
Masker Dus 1.000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 345,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 345,000.00
E Overhead & Profit (Maksimal 15 %) 15% x D 51,750.00
F Harga Satuan Pekerjaan (D+E) 396,750.00

4 Tebas tebang 1 pohon dia >30 sd 50 cm 1.7.3.1.b.4


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.170 100,000.00 17,000.00
Mandor OH 0.017 150,000.00 2,550.00
JUMLAH TENAGA KERJA 19,550.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Chainsaw 7,5 hp Hari 0.0800 1,000,000.00 80,000.00
JUMLAH HARGA ALAT 80,000.00
D Jumlah (A+B+C) 99,550.00
E Overhead & Profit (Maksimal 15 %) 15% x D 14,932.50
F Harga Satuan Pekerjaan (D+E) 114,482.50

5 Prasasti Nama Kegiatan


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
OH -
JUMLAH TENAGA KERJA -
B BAHAN
Prasasti Nama Kegiatan Unit 1.000 500,000.00 500,000.00
JUMLAH HARGA BAHAN 500,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 500,000.00
E Overhead & Profit (Maksimal 15 %) 15% x D 75,000.00
F Harga Satuan Pekerjaan (D+E) 575,000.00

6 Penggalian 1 m³ tanah biasa sedalam 1 m 1.7.1.a / A.2.3.1.1.

No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja OH 0.750 100,000.00 75,000.00
Mandor OH 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 78,750.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 78,750.00
E Overhead & Profit (Maksimal 15 %) 15% x D 11,812.50
F Harga Satuan Pekerjaan (D+E) 90,562.50

7 Pengurugan 1 m³ dengan pedel putih 1.7.2.e / A.2.3.1.14.


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.250 100,000.00 25,000.00
Mandor OH 0.025 150,000.00 3,750.00
JUMLAH TENAGA KERJA 28,750.00
B BAHAN
Pedel putih M³ 1.200 85,000.00 102,000.00
JUMLAH HARGA BAHAN 102,000.00
C PERALATAN
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 130,750.00


E Overhead & Profit (Maksimal 15 %) 15% x D 19,612.50
F Harga Satuan Pekerjaan (D+E) 150,362.50

8 Pengurugan 1 m³ dengan pedel putih dengan Pemadatan / Wales Analisa El-321a / Jakon 2021
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja Jam 0.1675 14,285.71 2,392.86
Mandor Jam 0.0419 21,428.57 897.86
JUMLAH TENAGA KERJA 3,290.71
B BAHAN
Pedel putih M³ 1.200 85,000.00 102,000.00
JUMLAH HARGA BAHAN 102,000.00
C PERALATAN
3 Whell Roller Jam 0.0808 399,990.46 32,319.23
Dump Truck Jam 0.2142 235,557.24 50,456.36
JUMLAH HARGA ALAT 82,775.59

D Jumlah (A+B+C) 188,066.30


E Overhead & Profit (Maksimal 15 %) 15% x D 28,209.95
F Harga Satuan Pekerjaan (D+E) 216,276.25

9 Pemasangan 1 m³ batu Kosong A.3.2.1.9. / 1.5.1.1.b.(a)


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.780 100,000.00 78,000.00
Tukang OH 0.390 125,000.00 48,750.00
Kepala Tukang OH 0.039 140,000.00 5,460.00
Mandor OH 0.039 150,000.00 5,850.00
JUMLAH TENAGA KERJA 138,060.00
B BAHAN
Batu belah m³ 1.200 175,000.00 210,000.00
Pasir urug M³ 0.432 285,000.00 123,120.00
JUMLAH HARGA BAHAN 333,120.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 471,180.00
E Overhead & Profit (Maksimal 15 %) 15% x D 70,677.00
F Harga Satuan Pekerjaan (D+E) 541,857.00

10 Pemasangan 1 m³ pondasi batu belah campuran 1SP : 6PP 2.1.1.d / A.3.2.1.4.


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 1.500 100,000.00 150,000.00
Tukang OH 0.750 125,000.00 93,750.00
Kepala Tukang OH 0.075 140,000.00 10,500.00
Mandor OH 0.075 150,000.00 11,250.00
JUMLAH TENAGA KERJA 265,500.00
B BAHAN
Batu belah m³ 1.200 175,000.00 210,000.00
Semen Portland Kg 117.000 1,350.00 157,950.00
Pasir pasang M³ 0.561 285,000.00 159,885.00
JUMLAH HARGA BAHAN 527,835.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 793,335.00
E Overhead & Profit (Maksimal 15 %) 15% x D 119,000.25
F Harga Satuan Pekerjaan (D+E) 912,335.25

11 Pemasangan 1 m² plesteran dinding 1SP : 6PP tebal 15 mm 3.2.2.2.18.(c)


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.300 100,000.00 30,000.00
Tukang OH 0.150 125,000.00 18,750.00
Kepala Tukang OH 0.015 140,000.00 2,100.00
Mandor OH 0.015 150,000.00 2,250.00
JUMLAH TENAGA KERJA 53,100.00
B BAHAN
Semen Portland Kg 4.416 1,350.00 5,961.60
Pasir pasang M³ 0.027 285,000.00 7,695.00
JUMLAH HARGA BAHAN 13,656.60
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 66,756.60
E Overhead & Profit (Maksimal 15 %) 15% x D 10,013.49
F Harga Satuan Pekerjaan (D+E) 76,770.09

12 Membuat 1 m³ lantai kerja beton mutu f' = 7,4 MPa (K 100) A.4.1.1.1 / 2.2.2.1.b.(c)

No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang OH 0.275 125,000.00 34,375.00
Kepala Tukang OH 0.028 140,000.00 3,920.00
Mandor OH 0.083 150,000.00 12,450.00
JUMLAH TENAGA KERJA 215,745.00
B BAHAN
Semen Portland Kg 247 1,350.00 333,450.00
Pasir Beton M³ 0.621 350,000.00 217,250.00
Kerikil 2/3 (lokal) M³ 0.740 300,000.00 222,000.00
Air Ltr 215 50.00 10,750.00
JUMLAH HARGA BAHAN 783,450.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 999,195.00
E Overhead & Profit (Maksimal 15 %) 15% x D 149,879.25
F Harga Satuan Pekerjaan (D+E) 1,149,074.25

13 Membuat 1 m³ beton mutu f'c = 16,9 MPa (K 200), manual A.4.1.1.6 / 2.2.2.1.g.(c)
No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 1.650 100,000.00 165,000.00
Tukang OH 0.275 125,000.00 34,375.00
Kepala Tukang OH 0.028 140,000.00 3,920.00
Mandor OH 0.083 150,000.00 12,450.00
JUMLAH TENAGA KERJA 215,745.00
B BAHAN
Semen Portland Kg 352 1,350.00 475,200.00
Pasir Beton M³ 0.522 350,000.00 182,750.00
Kerikil 2/3 (lokal) M³ 0.764 300,000.00 229,111.11
Air ltr 215 50.00 10,750.00
JUMLAH HARGA BAHAN 897,811.11
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,113,556.11
E Overhead & Profit (Maksimal 15 %) 15% x D 167,033.42
F Harga Satuan Pekerjaan (D+E) 1,280,589.53

14 Membuat 100 kg penulangan besi polos dan ulir 2.2.6.1.b.(c)


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.700 100,000.00 70,000.00
Tukang OH 0.700 125,000.00 87,500.00
Kepala Tukang OH 0.070 140,000.00 9,800.00
Mandor OH 0.040 150,000.00 6,000.00
JUMLAH TENAGA KERJA 173,300.00
B BAHAN
Besi beton polos Kg 105.000 12,000.00 1,260,000.00
Kawat beton Kg 1.500 20,000.00 30,000.00
JUMLAH HARGA BAHAN 1,290,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,463,300.00
E Overhead & Profit (Maksimal 15 %) 15% x D 219,495.00
F Harga Satuan Pekerjaan (D+E) 1,682,795.00
G Harga Satuan Pekerjaan 1 Kg Besi (D+E)/100 16,827.95

15 Membuat 1 m² bekisting untuk lantai beton A.4.1.1.22


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.660 100,000.00 66,000.00
Tukang OH 0.330 125,000.00 41,250.00
Kepala Tukang OH 0.033 140,000.00 4,620.00
Mandor OH 0.033 150,000.00 4,950.00
JUMLAH TENAGA KERJA 116,820.00
B BAHAN
Kayu kelas III/papan begesting M³ 0.040 1,500,000.00 60,000.00
Paku 5 - 12 cm Kg 0.400 16,000.00 6,400.00
Minyak bekisting Ltr 0.200 -
Kayu kelas II balok M³ 0.015 -
Plywood 6 mm Lbr 0.350 80,000.00 28,000.00
Dolken kayu Ø(8-10) cm panjang 4 m Btg 6.000 -
JUMLAH HARGA BAHAN 34,400.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 151,220.00
E Overhead & Profit (Maksimal 15 %) 15% x D 22,683.00
F Harga Satuan Pekerjaan (D+E) 173,903.00

16 Membuat 1 m³ plat beton bertulang tebal 10 cm beton mutu f' = 16,9 MPa (K 200)
A Pekerjaan Bekisting 2 X pakai M² 10.00 173,903.00 1,739,030.00
B Pekerjaan Pembesian Kg 82.67 #REF! #REF!
C Pekerjaan Beton K-200 M³ 1.00 #REF! #REF!
D Jumlah (A+B+C) JUMLAH TENAGA KERJA #REF!

17 Pemasangan 1 m¹ gorong-gorong buis beton Ø 30 cm


No. Uraian Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.100 100,000.00 10,000.00
Tukang OH 0.100 125,000.00 12,500.00
Mandor OH 0.050 150,000.00 7,500.00
JUMLAH TENAGA KERJA 30,000.00
B BAHAN
Buis beton bulat Ø 30 cm bh 1.000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 125,000.00
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 155,000.00
E Overhead & Profit (Contoh 15 %) 15% x D 23,250.00
F Harga Satuan Pekerjaan (D+E) 178,250.00
BESI ULIR
1 D 10 0.56 Kg/m
2 D 13 1.04 Kg/m
3 D 16 1.58 Kg/m
4 D 19 2.23 Kg/m
5 D 22 2.98 Kg/m
6 D 25 3.85 Kg/m
7 D 29 5.19 Kg/m
8 D 32 6.31 Kg/m

Strousse Ø 20 cm

TULANGAN UTAMA

DIMENSI R H Diameter
Diameter m m mm

Ø 20 0.15 8

SENGKANG

Panjang sengkang Panjang Ø Jarak Sengkang


m m mm m

0.471 31.847 6 0.15

Pondasi Plat 60 x 60 x 20

TULANGAN UTAMA

DIMENSI B H Diameter
B/H m m mm

60 x 60 x 20 0.6 0.2 10

SENGKANG
Panjang sengkang Panjang Ø Jarak Sengkang
m m mm m

1.340 8.333 10 0.15

Sloof 15 x 20 cm

TULANGAN UTAMA

DIMENSI B H Diameter
B/H m m mm

15 x 20 0.15 0.2 10

SENGKANG

Panjang sengkang Panjang sloof Ø Jarak Sengkang


m m mm m

0.500 33.333 6 0.2

Kolom Praktis 12 x 12

TULANGAN UTAMA

DIMENSI B H Diameter
B/H m m mm

12x12 0.12 0.12 10

SENGKANG

Panjang sengkang Panjang Ø Jarak Sengkang


m m mm m

0.32 69.444 6 0.2


Kolom 20 x 30 cm Papan Nama

TULANGAN UTAMA

DIMENSI B H Ø
B/H m m mm

20 x 30 0.2 0.3 10

SENGKANG

Panjang sengkang Panjang sloof Ø Jarak Sengkang


m m mm m

0.80 16.667 6 0.2

Kolom 20 x 20 cm

TULANGAN UTAMA

DIMENSI B H Ø
B/H m m mm

20 x 20 0.2 0.2 10

SENGKANG

Panjang sengkang Panjang sloof Ø Jarak Sengkang


m m mm m

0.60 25.000 6 0.15

Kolom 20 x 30 cm Pagar

TULANGAN UTAMA

DIMENSI B H Diameter
B/H m m mm
20 x 30 0.2 0.3 10

SENGKANG

Panjang sengkang Panjang Ø Jarak Sengkang


m m mm m

0.80 16.667 6 0.2

Balok Gantung 15 x 25

TULANGAN UTAMA

DIMENSI B H Diameter
B/H m m mm

15 x 25 0.15 0.25 10

SENGKANG

Panjang sengkang Panjang Ø Jarak Sengkang


m m mm m

0.60 26.667 6 0.2

Ring Balok , Balok Latai 12 x 15

TULANGAN UTAMA

DIMENSI B H Diameter
B/H m m mm

12x15 0.12 0.15 10

SENGKANG
Panjang sengkang Panjang Ø Jarak Sengkang
m m mm m

0.36 55.556 6 0.2

Plat tebal 10 cm

TULANGAN UTAMA
Memanjang
DIMENSI B H Diameter
B/H m m mm

10x100 0.1 1 10

Melintang / Berdiri
DIMENSI B H Diameter
B/H m m mm

10x100 0.1 1 10
BESI POLOS
ø 6 mm 0.22 Kg/m
ø 8 mm 0.40 Kg/m
ø 10 mm 0.62 Kg/m
ø 12 mm 0.89 Kg/m
ø 16 mm 1.58 Kg/m
ø 19 mm 2.23 Kg/m
ø 22 mm 2.98 Kg/m
ø 25 mm 3.85 Kg/m

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3

31.847 5 63.694

Jumlah Sengkang Volume Besi


bh Kg

212.314 22.000

Tul. Utama 63.694 Kg/m3 Polos


Tul. Sengkang 22.000 Kg/m3 Polos
TOTAL 85.694 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3

8.333
Jumlah Sengkang Volume Besi
bh Kg

111.111 92.311

Tul. Utama 0.000 Kg/m3 Polos


Tul. Sengkang 92.311 Kg/m3 Polos
TOTAL 92.311 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3

33.333 4 82.667

Jumlah Sengkang Volume Besi


bh Kg

166.667 18.333

Tul. Utama 82.667 Kg/m3 Ulir


Tul. Sengkang 18.333 Kg/m3 Polos
TOTAL 101.000 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3

69.444 4 172.222

Jumlah Sengkang Volume Besi


bh Kg

347.222 24.444

Tul. Utama 172.222 Kg/m3 Polos


Tul. Sengkang 24.444 Kg/m3 Polos
TOTAL 196.667 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3

16.667 8 82.667

Jumlah Sengkang Volume Besi


bh Kg

83.333 14.667

Tul. Utama 82.667 Kg/m3 Ulir


Tul. Sengkang 14.667 Kg/m3 Polos
TOTAL 97.333 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3

25.000 6 93.000

Jumlah Sengkang Volume Besi


bh Kg

166.667 22.000

Tul. Utama 93.000 Kg/m3 Ulir


Tul. Sengkang 22.000 Kg/m3 Polos
TOTAL 115.000 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3
11.111111111
16.667 6 62.000 70.112

Jumlah Sengkang Volume Besi


bh Kg

83.333 14.667

Tul. Utama 62.000 Kg/m3 Ulir


Tul. Sengkang 14.667 Kg/m3 Polos
TOTAL 76.667 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3
11.111111111
26.667 6 99.200 70.112

Jumlah Sengkang Volume Besi


bh Kg

133.333 17.600

Tul. Utama 99.200 Kg/m3 Ulir


Tul. Sengkang 17.600 Kg/m3 Polos
TOTAL 116.800 Kg/m3 Polos

Panjang/m3 Jumlah Volume Besi


m bh Kg/m3

55.556 4 137.778
Jumlah Sengkang Volume Besi
bh Kg

277.778 22.000

Tul. Utama 137.778 Kg/m3 Polos


Tul. Sengkang 22.000 Kg/m3 Polos
TOTAL 159.778 Kg/m3 Polos

Panjang/m3 L / Jarak Jumlah Volume Besi


m m bh Kg/m3

10.000 0.15 6.667 41.333

Panjang/m3 L / Jarak Jumlah Volume Besi


m m bh Kg/m3

10.000 0.15 6.667 41.333

Tul. Memanjang 41.333 Kg/m3 Polos


Tul. Melintang 41.333 Kg/m3 Polos
TOTAL 82.667 Kg/m3 Polos

Anda mungkin juga menyukai