PROGRAM :
KEGIATAN :
PEKERJAAN : PEKERJAAN PERBAIKAN KM
LOKASI : DISHUB, PROVINSI JAWA TIMUR
A PEKERJAAN PERSIAPAN
JUMLAH 1,818,379.10
DIBULATKAN 1,818,000.00
TOTAL 1,999,800.00
PEKERJAAN MECHANICAL ELECTRIC
PASANG.LAMPU DOWNLIGHT RD 150 + PL 18 WATT /BH
HARGA SATUAN JUMLAH
NO Uraian KODE SATUAN KOEF.
Rp. Rp.
A Tenaga Kerja
1 Upah pasang L.01 ls 1.000 15,000.00 15,000.00
Jumlah Harga Tenaga Kerja 15,000.00
B Bahan
1 Lampu downlight bh 1.000 175,000.00 175,000.00
2 Matrial bantu / alat bantu ls 1.000 10,000.00 10,000.00
Jumlah Harga Bahan 185,000.00
C Peralatan
BALOK
%
1.51%
1.06%
1.97%
2.26%
A BERAT BESI BETON - PANJANG 12 M
Berat Berat
kg/12m kg/m
Berat Berat
kg/2.88m2 kg/m2
80 x 45 x 6 mm = 50 8.333
100 x 50 x 6 mm = 56 9.333
120 x 55 x 6 mm = 61 10.167
120 x 55 x 7 mm = 80.4 13.400
140 x 60 x 7 mm = 97.02 16.170
150 x 75 x 6.5 mm = 112 18.667
180 x 75 x 7 mm = 128 21.333
200 x 80 x 7.5 mm = 148 24.667
220 x 80 x 8 mm = 187.5 31.250
240 x 85 x 9.5 mm = 205 34.167
250 x 90 x 9 mm = 208.2 34.700
PEKERJAAN PERSIAPAN
PENGUKURAN DAN PEMASANGAN 1 m1 BOUPLANK
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 70,000.00 7,000.00
2 Tukang kayu L.02 OH 0.100 90,000.00 9,000.00
3 Kepala Tukang L.03 OH 0.010 100,000.00 1,000.00
4 Mandor L.04 OH 0.005 110,000.00 550.00
Jumlah Harga Tenaga Kerja 17,550.00
B Bahan
1 Kayu papan balok 5/7 m3 0.008 3,150,000.00 25,200.00
2 Paku 2" - 3" m3 0.020 16,500.00 330.00
3 Kayu papan 3/20 m3 0.002 2,300,000.00 4,600.00
Jumlah Harga Bahan 30,130.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah (A+B+C) 47,680.00
E Overhead + Profit 10 % x D 4,768.00
F Harga Satuan Pekerjaan (D+E) 52,448.00