Anda di halaman 1dari 1

RENCANA ANGGARAN BIAYA

KEGIATAN : PEMBANGUNAN BANGUNAN GEDUNG STASIUN UJI SUBSTANTIF (BUSS) DATARAN RENDAH
PEKERJAAN : PEMBANGUNAN GEDUNG STASIUN UJI SUBSTANTIF (BUSS) DATARAN RENDAH (TAHAP 2)
LOKASI : JL. GAJAH MADA NO.17 MOJOSARI KAB MOJOKERTO- JATIM
TAHUN ANGGARAN : 2019

PEKERJAAN MEKANIKAL & PLUMBING


HARGA JUMLAH
NO. JENIS PEKERJAAN VOLUME SAT
SATUAN (RP) (Rp)
I.B PEKERJAAN INSTALASI AIR BERSIH
I PEKERJAAN POMPA DAN TANDON
1 Ground Water Tank kap 3.000 liter ( type tanam ) 3,00 unit 18.605.100,00 55.815.300,00
Pek. Galian dan urugan kembali 1,00 ls 16.744.590,00 16.744.590,00
2 Pompa Transfer dari Ground Tank Satu Paket terdiri :
Transfer Pump 1,00 unit 10.000.000,00 10.000.000,00
Panel kontrol untuk 2 unit pompa 1,00 unit 2.500.000,00 2.500.000,00
Water level Control (WLC) ke Reservooir bawah 1,00 unit 1.048.058,00 1.048.058,00
Water level Control (WLC) ke Reservooir atas 1,00 unit 1.048.058,00 1.048.058,00
Kabel WLC NYM 2x1,5mm2 20,00 m' 12.563,75 251.275,00
Gate valve Ø 25mm 6,00 bh 1.150.275,50 6.901.653,00
Check valve Ø 25mm 3,00 bh 531.426,50 1.594.279,50
Strainer Ø 25mm 3,00 bh 1.939.140,50 5.817.421,50
Flexible joint Ø 25mm 6,00 bh 965.475,50 5.792.853,00
Pressure gauge 4,00 bh 945.840,50 3.783.362,00
Foot Valve Ø25mm 6,00 bh 215.000,00 1.290.000,00
Floating Valve Ø25mm 6,00 bh 475.000,00 2.850.000,00
Pressure switch 3,00 bh 810.000,00 2.430.000,00
Fitting ( elbow, reducer, knie, dll ) 1,00 ls 9.137.870,70 9.137.870,70
Box panel untuk sistem pompa 1,00 ls 600.000,00 600.000,00
SUB TOTAL(I) PEKERJAAN POMPA DAN TANDON Sub Jumlah 127.604.720,70
II PEKERJAAN INSTALASI IRIGASI AREA SCREEN & GREEN HOUSE
1 Pipa mainline irigasi :
a. Pipa PVC AW class 10 -Ø25mm 176,00 m' 28.481,75 5.012.788,00
2 Pekerjan instalasi irigasi : 6,00 unit 699.000,00 4.194.000,00
a. Timer Digital Irigasi
b. Kran ulir 1/2 inch
c. Flat TEE 7mm (10pcs)
d. Bent drip stake
e. Selang 6x4m (10 meter)
f. Selang 5x3m (5 meter)
3 Material bantu (fitting ,longdrat , dynabolt, hanger clamp,dll) 1,00 ls 2.762.036,40 2.762.036,40
SUB TOTAL Sub Jumlah 11.968.824,40
III PEKERJAAN INSTALASI IRIGASI KEBUN
1 Pipa mainline irigasi :
a. Pipa PVC AW class 10 -Ø50mm 331,00 m' 122.034,00 40.393.254,00
b. Pipa PVC AW class 10 -Ø80mm 148,00 m' 226.194,21 33.476.743,08
2 Accesories : 6,00 unit 699.000,00 4.194.000,00
a. Kran taman 11,00 pcs 35.000,00 385.000,00
b. Selang @30meter 11,00 pcs 268.000,00 2.948.000,00
3 Material bantu ( fitting ,longdrat , dynabolt, hanger clamp,dll) 1,00 ls 24.419.099,12 24.419.099,12
SUB TOTAL Sub Jumlah 105.816.096,20
GRAND TOTAL TOTAL 245.389.641,30