KEGIATAN : PEMBANGUNAN BARU BAGI DAERAH YANG BELUM MEMILIKI LAYANAN AIR MINUM
PEMBANGUNAN SPL KAP. 5 /dtk DESA LENGORA, DESA LENGORA SELATAN DAN DESA ENANO KEC. KABAENA
PEKERJAAN :
TENGAH KAB. BOMBANA(SARING PASIR LAMBAT)
DESA/KEL. : DESA ENANO,DESA LENGORA SELATAN DAN DESA LENGORA
KECAMATAN : KABAENA TENGAH
KABUPATEN : BOMBANA
PROVINSI : SULAWESI TENGGARA
DHEDEN SUMARDIN, ST
NIP. 19820324 200901 1 001
PENGADAAN DAN PEMASANGAN JARINGAN PIPA
HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH HARGA Rp.
Rp.
1 2 3 4 5 6
I PEKERJAAN TANAH
1 Galian Tanah Biasa
Galian Pipa PVC Ø 110 mm m3 418,44 80.500,00 33.684.420,00
Galian Pipa PVC Ø 90 mm m3 409,92 80.500,00 32.998.560,00
Galian Pipa PVC Ø 63 mm m3 155,61 80.500,00 12.526.605,00
2 Urugan Kembali
Urugan Kembali Pipa PVC Ø 110 mm m3 385,32 57.500,00 22.155.827,00
Urugan Kembali Pipa PVC Ø 90 mm m3 385,10 57.500,00 22.143.043,92
Urugan Kembali Pipa PVC Ø 63 mm m3 150,22 57.500,00 8.637.823,37
Jumlah I 132.146.279,30
II PEKERJAAN PEMASANGAN PIPA
1 Pemas.Pipa Gip Ø 100 mm m' 500,00 335.110,00 167.555.000,00
2 Pemas.Pipa PVC Ø 110 mm m' 3.487,00 126.477,00 441.025.299,00
3 Pemas.Pipa PVC Ø 90 mm m' 3.904,00 89.849,50 350.772.448,00
4 Pemas.Pipa PVC Ø 63 mm m' 1.729,00 50.370,00 87.089.730,00
Jumlah II 1.046.442.477,00
III PEKERJAAN PEMASANGAN ACCESORIES PIPA
1 Pemas.Repair Socket Rubber Ring Ø 110 mm bh 3,00 112.860,00 338.580,00
2 Pemas.Repair Socket Rubber Ring Ø 90 mm bh 3,00 79.380,00 238.140,00
Cap Ø 90 mm bh 1,00 66.000,00 66.000,00
3 Pemas.Repair Socket Rubber Ring Ø 63 mm bh 3,00 50.460,00 151.380,00
Pemas. Rubber Ring Tee Ø 63 mm bh 5,00 523.860,00 2.619.300,00
Knee /Elbow Ø 63 mm bh 10,00 -
Cap Ø 63 mm bh 3,00 42.000,00 126.000,00
Jumlah III 3.539.400,00
J U M L A H I + II 1.182.128.156,30
RENCANA ANGGARAN BIAYA
KEGIATAN : PEMBANGUNAN BARU BAGI DAERAH YANG BELUM MEMILIKI LAYANAN AIR MINUM
PEKERJAAN : PEMBANGUNAN SPL KAP. 5 /dtk DESA LENGORA, DESA LENGORA SELATAN DAN DESA ENANO
KEC. KABAENA TENGAH KAB. BOMBANA(SARING PASIR LAMBAT)
DESA/KEL. : DESA ENANO,DESA LENGORA SELATAN DAN DESA LENGORA
KECAMATAN : KABAENA TENGAH
KABUPATEN : BOMBANA
PROVINSI : SULAWESI TENGGARA
HARGA SATUAN
NO URAIAN PEKERJAAN SAT VOLUME JUMLAH HARGA Rp.
Rp.
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Bouwplank dan Pembersihan Lokasi Ls 1,00 250.000,00 250.000,00
Jumlah I 250.000,00
II PEKERJAAN TANAH
1 Galian Tanah Keras m3 4,50 107.180,00 482.310,00
2 Urugan Tanah Kembali m3 1,13 57.500,00 64.687,50
3 Urugan Pasir m3 0,72 262.660,00 189.115,20
Jumlah II 736.112,70
III PEKERJAAN PONDASI
1 Pas. Pondasi Batu Belah Camp 1SP:4PP m3 7,43 929.056,25 6.898.242,66
2 Pas.Batu Kosong (Anstamping) m3 1,44 498.266,25 717.503,40
Jumlah III 7.615.746,06
IV PEKERJAAN BETON
1 Membuat Lantai Kerja Mutu f'c 7,4 Mpa/K.100 m3 0,15 1.104.815,68 165.722,35
2 Membuat Beton Mutu f'c 16,9 Mpa/K.200 m3 1,24 1.277.913,74 1.587.648,08
3 Pembesian dengan Besi Polos kg 87,75 15.205,93 1.334.360,26
4 Pemas.Bekisting Slof m2 2,00 228.850,00 457.700,00
5 Pemas.Bekisting Balok m2 2,00 389.131,25 778.262,50
6 Pemas.Bekisting Lantai m2 1,50 447.781,25 671.671,88
7 Pemas.Bekisting Dinding m2 6,00 384.531,25 2.307.187,50
Jumlah IV 7.302.552,57
V PEKERJAAN PLESTERAN
1 Pemas.Plesteran 1SP : 4PP / 20 cm m2 33,34 93.817,00 3.127.858,78
2 Pemas.Acian m2 33,34 41.543,75 1.385.068,63
Jumlah V 4.512.927,41
VI PEKERJAAN PIPA DAN ACCESORIES
1 Pipa Inlet GIP. Ø 100 mm m' 3,00 335.110,00 1.005.330,00
Pemasangan Gate Valve Ø 100 mm bh 1,00 3.480.000,00 3.480.000,00
Pemasangan Flange GIP. Ø 100 mm bh 2,00 160.000,00 320.000,00
Pemasangan Bend 90 GIP. Ø 100 mm bh 2,00 246.960,00 493.920,00
2 Pipa Penguras GIP. Ø 90 mm m' 3,00 239.165,50 717.496,50
Pemasangan Gate Valve Ø 90 mm bh 1,00 2.146.800,00 2.146.800,00
Pemasangan Flange GIP. Ø 90 mm bh 2,00 150.000,00 300.000,00
Pemasangan Bend 90 GIP. Ø 90 mm bh 2,00 136.260,00 272.520,00
3 Box Gate Valve + Tutup Plate Baja unit 2,00 1.790.211,65 3.580.423,30
Jumlah VI 12.418.889,80
J U M L A H I + II + III + IV + V + VI 32.836.228,54
1 UNIT BAK SARING PASIR LAMBAT (SPL)
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
1 2 3 4 5 6,00
I PEKERJAAN PERSIAPAN
1 Bowplank dan Pembersihan Awal ls 1,00 250.000 250.000,00
Jumlah I 250.000,00
II PEKERJAAN TANAH
1 Galian Tanah Keras m3 21,53 107.180,00 2.307.049,50
2 Urugan Tanah Kembali m3 5,38 57.500,00 309.421,88
3 Urugan Pasir m3 6,69 262.660,00 1.757.195,40
Jumlah II 4.373.666,78
III PEKERJAAN PONDASI
1 Pas. Pondasi Batu Belah Camp 1SP:4PP m3 13,23 929.056,25 12.291.414,19
2 Pas.Batu Kosong (Anstamping) m3 4,70 498.266,25 2.343.844,44
Jumlah III 14.635.258,63
IV PEKERJAAN BETON
1 Membuat Lantai Kerja Mutu f'c 7,4 Mpa/K.100 m3 3,82 1.104.815,68 4.220.395,89
2 Membuat Beton Mutu f'c 16,9 Mpa/K.200 m3 41,95 1.277.913,74 53.603.369,71
3 Pembesian dengan Besi Polos kg 3.508,55 15.205,93 53.350.736,94
4 Pemas.Bekisting Slof m2 30,00 228.850,00 6.865.500,00
5 Pemas.Bekisting Dinding m2 233,80 384.531,25 89.903.406,25
6 Pemas.Bekisting balok m2 20,00 389.131,25 7.782.625,00
7 Pemas.Bekisting Plate penutup m2 49,96 447.781,25 22.371.151,25
Jumlah IV 238.097.185,05
V PEKERJAAN PLESTERAN
1 Pemas.Plesteran 1SP : 3PP / 15 cm m2 403,62 72.609,85 29.306.787,66
2 Pemas.Acian m2 403,62 41.543,75 16.767.888,38
Jumlah V 46.074.676,03
VI PEKERJAAN SARINGAN PASIR LAMBAT (SPL)
1 Lapisan Batu Belah m3 3,00 398.906,25 1.196.718,75
2 Lapisan Batu Pecah/Split m3 3,00 692.156,25 2.076.468,75
3 Lapisan Pasir m3 4,50 262.660,00 1.181.970,00
Jumlah VI 4.455.157,50
VII PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru m2 161,40 20.915,63 3.375.781,88
Jumlah VII 3.375.781,88
VIII PEKERJAAN PIPA DAN ACCESORIES
1 Pipa Inlet Gip. Ø 100 mm m' 3,00 335.110,00 1.005.330,00
Gate Valve Ø 100 mm bh 1,00 3.480.000,00 3.480.000,00
Flange GIP Ø 100 mm bh 2,00 160.000,00 320.000,00
Bend 90 GIP Ø 100 mm bh 2,00 246.960,00 493.920,00
2 Pipa Outlet Gip. Ø 100 mm m' 3,00 335.110,00 1.005.330,00
Bend 90 GIP Ø 100 mm bh 2,00 246.960,00 493.920,00
3 Pipa Penguras Gip Ø 100 mm m' 3,00 335.110,00 1.005.330,00
Gate Valve Ø 100 mm bh 3,00 3.480.000,00 10.440.000,00
Bend 90 GIP Ø 100 mm bh 6,00 246.960,00 1.481.760,00
Tee GIP. Ø 100 mm bh 2,00 259.250,00 518.500,00
Flange GIP Ø 100 mm bh 6,00 160.000,00 960.000,00
4 Pipa Pembuang Gip Ø 100 mm m' 3,00 335.110,00 1.005.330,00
Bend 90 GIP Ø 100 mm bh 2,00 246.960,00 493.920,00
5 Tangga Unit 1,00 1.500.000,00 1.500.000,00
6 Tutup Plate Baja Manhole Unit 2,00 1.000.000,00 2.000.000,00
7 Box Gate Valve + Tutup Plate Baja Unit 4,00 1.790.211,65 7.160.846,61
Jumlah VIII 33.364.186,61
IX PEKERJAAN AKHIR
1 Pembersihan Akhir ls 1,00 500.000 500.000,00
Jumlah IX 500.000,00
J U M L A H I + II + III + IV + V + VI + VII + VIII + IX 345.125.912,47
1. Unit Pemasangan Box - Water Meter Induk
1 2 3 4 5 6,00
I PEKERJAAN PERSIAPAN
1 Bowplank dan Pembersihan Lokasi ls 1,00 150.000,00 150.000,00
Jumlah I 150.000,00
2 PEKERJAAN TANAH
1 Galian Tanah Keras m3 3,15 107.180 337.617,00
2 Urugan Tanah Kembali m3 0,79 57.500 45.281,25
3 Urugan Pasir m3 0,15 262.660 39.399,00
4 Urugan Gravel m3 0,41 692.156 282.399,75
Jumlah II 704.697,00
3 PEKERJAAN PASANGAN DINDING
1 Pas.Dinding Bata Camp. 1PC : 3 PP m2 6,70 129.151 865.310,03
Jumlah III 865.310,03
4 PEKERJAAN PLESTERAN
1 Plesteran Dinding Camp.1PC : 3PP m2 13,40 72.610 972.971,99
2 Acian m2 13,40 41.544 556.686,25
Jumlah IV 1.529.658,24
5 PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru 6,70 20.916 140.134,69
Jumlah V 140.134,69
6 PEKERJAAN PIPA DAN ACSESORIES
1
Pemasangan Pipa Inlet GIP Ø 100 mm m' 1,00 335.110,00 335.110,00
2
Pemasangan Pipa GIP Ø 100 mm (Dlm Box Mtr) bh 3,50 335.110,00 1.172.885,00
3
Pemasangan Tee GIP Ø 100 x 100 mm bh 2,00 259.250,00 518.500,00
4
Pemasangan Flange GIP Ø 100 mm bh 4,00 160.000,00 640.000,00
5
Pemasangan Gate Valve Ø 100 mm bh 3,00 3.480.000,00 10.440.000,00
6
Pemasangan Dismantling Joint bh 1,00 600.000,00 600.000,00
7
Pemasangan Meter Air Ø 100 mm bh 1,00 5.158.800,00 5.158.800,00
8 Pemasangan Bend 90° GIP Ø 100 mm bh 2,00 246.960,00 493.920,00
9 Pemasangan Pipa Outlet GIP Ø 100 mm bh 1,00 335.110,00 335.110,00
10 Tutup Plate Baja (1 x 1,5 )m Unit 2,00 2.500.000,00 5.000.000,00
Jumlah VI 24.694.325,00
J U M L A H I + II + III + IV + V + VI 28.084.124,95
ANGGARAN BIAYA
PEMBUATAN PERLINTASAN PIPA TYPE L > 12 m
Pipa Diameter 4"
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME
SATUAN HARGA
1 2 3 4 5 6,00
1 Pemasangan Pipa GIP. Ø 100 mm m' 12,00 335.110,00 4.021.320,00
2 Trushtblock Beton f'c = 14,5 Mpa bh 2,00 2.381.590,10 4.763.180,20
3 Flange Socket R.Ring Ø 110 mm bh 2,00 744.300,00 1.488.600,00
4 Flange GIP Ø 100 mm bh 2,00 160.000,00 320.000,00
5 Bend 45 Dia. 4" GIP bh 4,00 136.260,00 545.040,00
6 Pengikat (Angkur, platstrip, Baut/Mur, Sealkare) unit 2,00 500.000,00 1.000.000,00
7 Pengaman Lintasan Pipa ls 2,00 150.000,00 300.000,00
8 Pengecatan Pipa GIP. m2 9,42 32.752,00 308.523,84
JUMLAH 12.746.664,04
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME
SATUAN HARGA
1 2 3 4 5 6,00
1 Pemasangan Pipa GIP Ø 90 mm m 12,00 239.165,50 2.869.986,00
2 Trushtblock Beton f'c = 14,5 Mpa bh 2,00 2.381.590,10 4.763.180,20
3 Flange Socket R.Ring Ø 90 mm bh 2,00 510.300,00 1.020.600,00
4 Flange GIP Ø 90 mm bh 2,00 150.000,00 300.000,00
5 Bend 45 Dia. 3" GIP bh 4,00 276.768,00 1.107.072,00
6 Pengikat (Angkur, platstrip, Baut/Mur, Sealkare) unit 2,00 500.000,00 1.000.000,00
7 Pengaman Lintasan Pipa ls 2,00 150.000,00 300.000,00
8 Pengecatan Pipa GIP. m2 7,63 32.752,00 249.904,31
JUMLAH 11.610.742,51
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME
SATUAN HARGA
1 2 3 4 5 6,00
1 Pemasangan Pipa GIP Ø 63 mm m 12,00 179.135,50 2.149.626,00
2 Trushtblock Beton f'c = 14,5 Mpa bh 2,00 2.381.590,10 4.763.180,20
3 Flange Socket R.Ring Ø 63 mm bh 2,00 327.840,00 655.680,00
4 Flange GIP Ø 60 mm bh 2,00 101.500,00 203.000,00
5 Bend 45 Dia. 2" GI bh 4,00 246.960,00 987.840,00
6 Pengikat (Angkur, platstrip, Baut/Mur, Sealkare unit 2,00 500.000,00 1.000.000,00
7 Pengaman Lintasan Pipa Is 2,00 150.000,00 300.000,00
8 Pengecatan Pipa GIP. m2 3,39 32.752,00 111.068,58
JUMLAH 10.170.394,78
ANGGARAN BIAYA
PEMBUATAN PERLINTASAN PIPA TYPE L > 6 m
Pipa Diameter 4"
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME SATUAN HARGA
1 2 3 4 5 6,00
1 Pemasangan Pipa GIP. Ø 100 mm m' 6,00 335.110,00 2.010.660,00
2 Trushtblock Beton f'c = 14,5 Mpa bh 2,00 2.381.590,10 4.763.180,20
3 Flange Socket R.Ring Ø 110 mm bh 2,00 744.300,00 1.488.600,00
4 Flange GIP Ø 100 mm bh 2,00 160.000,00 320.000,00
5 Bend 45 Dia. 4" GIP bh 4,00 136.260,00 545.040,00
6 Pengikat (Angkur, platstrip, Baut/Mur, Sealkare) unit 2,00 500.000,00 1.000.000,00
7 Pengaman Lintasan Pipa ls 2,00 150.000,00 300.000,00
8 Pengecatan Pipa GIP. m2 4,71 32.752,00 154.261,92
JUMLAH 10.581.742,12
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME SATUAN HARGA
1 2 3 4 5 6,00
1 Pemasangan Pipa GIP Ø 90 mm m 6,00 239.165,50 1.434.993,00
2 Trushtblock Beton f'c = 14,5 Mpa bh 2,00 2.381.590,10 4.763.180,20
3 Flange Socket R.Ring Ø 90 mm bh 2,00 510.300,00 1.020.600,00
4 Flange GIP Ø 90 mm bh 2,00 150.000,00 300.000,00
5 Bend 45 Dia. 3" GIP bh 4,00 276.768,00 1.107.072,00
6 Pengikat (Angkur, platstrip, Baut/Mur, Sealkare) unit 2,00 500.000,00 1.000.000,00
7 Pengaman Lintasan Pipa ls 2,00 150.000,00 300.000,00
8 Pengecatan Pipa GIP. m2 3,82 32.752,00 124.952,16
JUMLAH 10.050.797,35
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME SATUAN HARGA
1 2 3 4 5 6,00
1 Pemasangan Pipa GIP Ø 63 mm m 6,00 179.135,50 1.074.813,00
2 Trushtblock Beton f'c = 14,5 Mpa bh 2,00 2.381.590,10 4.763.180,20
3 Flange Socket R.Ring Ø 63 mm bh 2,00 327.840,00 655.680,00
4 Flange GIP Ø 60 mm bh 2,00 101.500,00 203.000,00
5 Bend 45 Dia. 2" GI bh 4,00 246.960,00 987.840,00
6 Pengikat (Angkur, platstrip, Baut/Mur, Sealkare unit 2,00 500.000,00 1.000.000,00
7 Pengaman Lintasan Pipa Is 2,00 150.000,00 300.000,00
8 Pengecatan Pipa GIP. m2 1,70 32.752,00 55.534,29
JUMLAH 9.040.047,49
ANGGARAN BIAYA
J U M L A H I + II + III + IV + V 1.790.211,65
1 UNIT BAK PELEPAS TEKAN (BPT)
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
(Rp.) (Rp.)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Bowplank dan Pembersihan Awal ls 1,00 100.000,00 100.000,00
Jumlah I 100.000,00
II PEKERJAAN TANAH
1 Galian Tanah Biasa m3 1,54 107.180,00 165.222,26
2 Urugan Kembali m3 0,39 57.500,00 22.159,64
3 Urugan Pasir Lantai 0,1 m m3 0,24 262.660,00 62.292,45
Jumlah II 249.674,34
III PEKERJAAN BETON
1 Lantai Kerja mutu f'c = 7,4 Mpa (K.100) m3 0,12 1.104.815,68 131.009,04
2 Beton mutu f'c= 16,9 Mpa (K.200) m3 0,31 1.277.913,74 395.846,56
3 Pembesian Dengan Besi Polos kg 72,26 15.205,93 1.098.761,40
4 Bekisting
Plate Lantai m2 0,92 378.781,25 349.993,88
Dinding m2 10,91 384.531,25 4.196.005,00
Plate Penutup m2 1,54 389.131,25 598.328,21
5 Pemas Plate penutup Baja ls 1,00 1.500.000,00 1.500.000,00
Jumlah III 8.269.944,09
IV PEKERJAAN PLESTERAN
1 Pemasangan Plesteran 1PC : 3PP tebal 15cm m2 14,46 72.609,85 1.050.025,56
2 Acian m2 14,46 41.543,75 600.772,48
Jumlah IV 1.650.798,04
V PEKERJAAN PENGECATAN
1 Pengecatan Tembok Baru m2 14,46 20.915,63 302.465,04
2 Pengecatan Plate Baja m2 0,36 32.752,00 11.790,72
Jumlah V 314.255,76
VI PEKERJAAN PIPA DAN ACCESORIES
1 Pipa Inlet Gip. Ø 100 mm m' 3,00 335.110,00 1.005.330,00
Gate Valve Inlet Ø 100 mm bh 1,00 3.480.000,00 3.480.000,00
Flange Gip. Ø 100 mm bh 2,00 160.000,00 320.000,00
Bend 90 Gip. Ø 100 mm bh 2,00 246.960,00 493.920,00
2 Pipa Outlet Gip. Ø 100 mm m' 2,00 335.110,00 670.220,00
Gate Valve Outlet Ø 100 mm bh 1,00 3.480.000,00 3.480.000,00
Flange Gip. Ø 100 mm bh 2,00 160.000,00 320.000,00
3 Pipa Penguras Ø 100 mm m' 6,00 335.110,00 2.010.660,00
Gate Valve Penguras Ø 100 mm bh 1,00 3.480.000,00 3.480.000,00
Flange Gip. Ø 100 mm bh 2,00 160.000,00 320.000,00
Bend 90 Gip. Ø 100 mm bh 2,00 246.960,00 493.920,00
Tee Gip. Ø 100 mm bh 2,00 259.250,00 518.500,00
4 Tutup Manhole Unit 1,00 1.000.000,00 1.000.000,00
5 Box Gate Valve + Tutup Plate Baja Unit 3,00 1.790.211,65 5.370.634,95
Jumlah VI 22.963.184,95
VII PEKERJAAN AKHIR
1 Pembersihan Akhir ls 1,00 500.000,00 500.000,00
Jumlah VII 500.000,00
KEGIATAN : PEMBANGUNAN BARU BAGI DAERAH YANG BELUM MEMILIKI LAYANAN AIR MINUM
: PEMBANGUNAN SPL KAP. 5 /dtk DESA LENGORA, DESA LENGORA SELATAN DAN DESA ENANO
PEKERJAAN
KEC. KABAENA TENGAH KAB. BOMBANA(SARING PASIR LAMBAT)
DESA/KEL. : DESA ENANO,DESA LENGORA SELATAN DAN DESA LENGORA
KECAMATAN : KABAENA TENGAH
KABUPATEN : BOMBANA
PROVINSI : SULAWESI TENGGARA
J U M L A H I + II + III + IV + V + VI 7.643.320,33
PEMERINTAH KABUPATEN BOMBANA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KAB. BOMBANA
Jl. Yos Sudarso No. 85 Telp. Kode Pos 93771 Rumbia - Kab. Bombana
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
A.4.1.1.6. Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K 200 ), slump (12 ± 2 ) cm, w/c = 0,61
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 0 5 6
A Tenaga Kerja
Pekerja L.01 OH 1,650 90.000,00 148.500,00
Tukang Batu L.02 OH 0,275 110.000,00 30.250,00
Kepala Tukang L.03 OH 0,028 125.000,00 3.500,00
Mandor L.04 OH 0,083 100.000,00 8.300,00
Jumlah Harga Tenaga Kerja 190.550,00
B Bahan
Semen Portland Kg 352,0 1.500,00 528.000,00
Pasir beton kg 731 119,29 87.197,86
Kerikil (Maks. 30 mm) kg 1031 296,30 305.481,48
Air Ltr 215 - -
Jumlah Harga Bahan 920.679,34
C Peralatan
-
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1.111.229,34
E Overhead + Profit 15% x D 166.684,40
F Harga Satuan Pekerjaan ( D+E ) 1.277.913,74
1 2 3 4 5 6
A Tenaga Kerja
Pekerja L.01 OH 0,300 90.000,00 27.000,00
Tukang Batu L.02 OH 0,100 110.000,00 11.000,00
Kepala Tukang L.03 OH 0,010 125.000,00 1.250,00
Mandor L.04 OH 0,015 100.000,00 1.500,00
Jumlah Harga Tenaga Kerja 40.750,00
B Bahan
Bata merah bh 70,000 600,00 42.000,00
Portland semen Kg 11,500 1.500,00 17.250,00
Pasir pasang m3 0,043 200.000,00 8.600,00
Jumlah Harga Bahan 67.850,00
C Peralatan
-
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 108.600,00
E Overhead + Profit 15% x D 16.290,00
F Harga Satuan Pekerjaan ( D+E ) 124.890,00
A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN
A.4.7.1.10. Pengecatan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6
A Tenaga Kerja
Pekerja L.01 OH 0,020 90.000,00 1.800,00
Tukang cat L.02 OH 0,063 100.000,00 6.300,00
Kepala tukang L.03 OH 0,0063 125.000,00 787,50
Mandor L.04 OH 0,003 100.000,00 300,00
Jumlah Harga Tenaga Kerja 9.187,50
B Bahan
Plamur kg 0,150 25.000,00 3.750,00
Cat dasar kg 0,050 35.000,00 1.750,00
Cat penutup kg 0,100 35.000,00 3.500,00
Jumlah Harga Bahan 9.000,00
C Peralatan
-
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 18.187,50
E Overhead + Profit 15% x D 2.728,13
F Harga Satuan Pekerjaan ( D+E ) 20.915,63
A.4.7.1.19. Pengecatan 1 m2 permukaan baja galvanis secara manual sitem 1 lapis cat mutakhir
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
1 2 3 4 5 6
A Tenaga Kerja
Pekerja L.01 OH 0,060 90.000,00 5.400,00
Tukang cat L.02 OH 0,060 100.000,00 6.000,00
Kepala tukang L.03 OH 0,0120 125.000,00 1.500,00
Mandor L.04 OH 0,00300 100.000,00 300,00
Jumlah Harga Tenaga Kerja 13.200,00
B Bahan
Cat kg 0,30 50.000,00 15.000,00
Kuas bh 0,01 13.000,00 130,00
Pengencer ltr 0,01 15.000,00 150,00
Jumlah Harga Bahan 15.280,00
C Peralatan
-
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 28.480,00
E Overhead + Profit 15% x D 4.272,00
F Harga Satuan Pekerjaan ( D+E ) 32.752,00
1 2 3 4 5 6
A Tenaga Kerja
Pekerja L.01 OH 0,081 90.000,00 7.290,00
Tukang pipa L.02 OH 0,041 110.000,00 4.510,00
Mandor L.04 OH 0,008 100.000,00 800,00
Jumlah Harga Tenaga Kerja 12.600,00
B Bahan
Pipa PVC Ø 63 mm m 1,00 31.200,00 31.200,00
Jumlah Harga Bahan 31.200,00
C Peralatan
Sewa tripot/trackel & handle crane 2 T hari 0,006 -
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 43.800,00
E Overhead + Profit 15% x D 6.570,00
F Harga Satuan Pekerjaan ( D+E ) 50.370,00
1 2 3 4 5 6
A Tenaga Kerja
Pekerja L.01 OH 0,094 90.000,00 8.460,00
Tukang pipa L.02 OH 0,047 110.000,00 5.170,00
Mandor L.04 OH 0,009 100.000,00 900,00
Jumlah Harga Tenaga Kerja 14.530,00
B Bahan
Pipa PVC Ø 90 mm m 1,00 63.600,00 63.600,00
Jumlah Harga Bahan 63.600,00
C Peralatan
Sewa tripot/trackel & handle crane 2 T hari 0,008 -
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 78.130,00
E Overhead + Profit 15% x D 11.719,50
F Harga Satuan Pekerjaan ( D+E ) 89.849,50
A.8.4.1.3. (K3) Pemasangan 1 m pipa PVC Ø 110 mm
1 2 3 4 5 6
A Tenaga Kerja
Pekerja L.01 OH 0,105 90.000,00 9.450,00
Tukang pipa L.02 OH 0,053 110.000,00 5.830,00
Mandor L.04 OH 0,011 100.000,00 1.100,00
Jumlah Harga Tenaga Kerja 16.380,00
B Bahan
Pipa PVC Ø 110 mm m 1,00 93.600,00 93.600,00
Jumlah Harga Bahan 93.600,00
C Peralatan
Sewa tripot/trackel & handle crane 2 T hari 0,008 -
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 109.980,00
E Overhead + Profit 15% x D 16.497,00
F Harga Satuan Pekerjaan ( D+E ) 126.477,00
1 2 3 4 5 6
A Tenaga Kerja
Pekerja L.01 OH 0,118 90.000,00 10.620,00
Tukang pipa L.02 OH 0,059 110.000,00 6.490,00
Mandor L.04 OH 0,012 100.000,00 1.200,00
Jumlah Harga Tenaga Kerja 18.310,00
B Bahan
Pipa PVC Ø 150 mm m 1,00 200.400,00 200.400,00
Jumlah Harga Bahan 200.400,00
C Peralatan
Sewa tripot/trackel & handle crane 2 T hari 0,012 -
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 218.710,00
E Overhead + Profit 15% x D 32.806,50
F Harga Satuan Pekerjaan ( D+E ) 251.516,50
II BAHAN PEREKAT
1 Semen (50 kg) Semen Indonesia Zak 75.000 1.500
2 Semen Warna Semen Indonesia kg 25.000
IV BAHAN KAYU
1 Kayu kls I Jati m3 3.500.000
2 Kayu kls I I Kamper m3 3.000.000
3 Kayu kls I I I Meranti m3 2.500.000
4 Kayu kls I V Terentang m3 2.200.000
5 Dolken dia. 8 s/d 10 cm Pjg. 4m btg 15.000
Bambu dia. 8 cm pjg 4 m btg 10.200
V BAHAN ALUMINIUM
1 Kusen Aluminium 3" Alexindo m' 62.000
2 Rangka Jendela Aluminium Alexindo m' 90.000
3 Rangka Pintu Aluminium Alexindo m' 155.000
4 Kusen & Pintu PVC Toilet Maspion Unit 1.000.000
5 Engsel 3" ex Bos bh 20.000
6 Handle pintu Type HRE 75.01 ex Cisa bh 125.000
7 Selinder Type 08510 ex Cisa bh 242.000
8 Door Stoper bh 44.000
9 Door Closer bh 350.000
10 Slot tanam bh 85.000
11 Kait Angin bh 15.000
12 Grendel bh 10.000
Kunci Tanam Antik bh 175.000
VI BAHAN PELAPIS
1 Tripleks t. 3 mm Uk. 120 x 240 cm lbr 55.000
2 Tripleks t. 4 mm Uk. 120 x 240 cm lbr 73.000
3 Tripleks t. 9 mm Uk. 120 x 240 cm lbr 125.000
IX BAHAN KACA
1 Kaca Polos 3 mm m2 145.000
2 Kaca Polos 5 mm m2 155.000
3 Kaca Polos 8 mm m2 200.000
XI BAHAN FINISHING
1 Cat kayu/besi ex. SEIV kg 50.000
2 Plamir Kayu kg 35.000
3 Meni Kayu ex.Nippon kg 25.000
4 Wood Filler Impra kg 50.000
5 Thinner ND.IMPALA Ltr 15.000
6 Amplas kayu Lbr 2.000
7 Kuas cat bh 13.000
8 Cat Tembok kw1 ex.Dulux warna kg 85.000
9 Cat tembok kw2 ex.Vinilex kg 65.000
10 Plamir tembok kg 9.500
11 Lem kayu kg 20.000
12 Seal Tape bh 3.000
13 Minyak bekisting Ltr 7.500
Meni Besi kg 20.400
Residu kg 4.000
- Wall Pipe
Wallpipe ND. 50 x 600 mm bh 220.800
Wallpipe ND. 75 x 600 mm bh 396.000
Wallpipe ND. 100 x 600 mm bh 475.200
Wallpipe ND. 150 x 600 mm bh 528.000
Wallpipe ND. 200 x 750 mm bh 1.142.400
Wallpipe ND. 250 x 750 mm bh 1.675.200
- Band Steel All Flange
Bend All Flange ND. 90° x ND. 50 mm bh 268.800
Bend All Flange ND. 90° x ND. 75 mm bh 308.400
Bend All Flange ND. 90° x ND. 100 mm bh 459.360
Bend All Flange ND. 90° x ND. 150 mm bh 758.160
Bend All Flange ND. 90° x ND. 200 mm bh 1.308.154
Bend All Flange ND. 90° x ND. 250 mm bh 1.781.770
Bend All Flange ND. 45° x ND. 50 mm bh 235.200
Bend All Flange ND. 45° x ND. 75 mm bh 268.800
Bend All Flange ND. 45° x ND.100 mm bh 369.600
Bend All Flange ND. 45° x ND. 150 mm bh 628.800
Bend All Flange ND. 45° x ND. 200 mm bh 911.808
Bend All Flange ND. 45° x ND. 250 mm bh 1.312.128
Bend All Flange ND. 22,5° x ND. 50 mm bh 302.016
Bend All Flange ND. 22,5° x ND. 75 mm bh 348.504
Bend All Flange ND. 22,5° x ND. 100 mm bh 480.480
Bend All Flange ND. 22,5° x ND. 150 mm bh 781.872
Bend All Flange ND. 22,5° x ND. 200 mm bh 1.131.624
Bend All Flange ND. 22,5° x ND. 250 mm bh 1.443.936
- Band Steel
Bend ND. 90° x ND. 50 mm bh 46.836
Bend ND. 90° x ND. 75 mm bh 136.260
Bend ND. 90° x ND. 100 mm bh 246.960
Bend ND. 90° x ND. 150 mm bh 979.338
Bend ND. 90° x ND. 200 mm bh -
- Flange Adaptor
Flange Adaptor ND. 50 mm bh 180.000
Flange Adaptor ND. 75 mm bh 225.000
Flange Adaptor ND. 100 mm bh 280.000
Flange Adaptor ND. 150 mm bh 350.000
Flange Adaptor ND. 200 mm bh 548.000
Flange Adaptor ND. 250 mm bh 750.500
- Flange Spigot
- dia 150 mm bh 379.000,00
- dia 100 mm bh 234.600,00
- dia 75 mm bh 138.900,00
- dia 50 mm bh 109.800,00
- Flange PVC
- Flange PVC dia.150 mm bh 230.400,00
- Flange PVC dia.110 mm bh 198.000,00
- Flange PVC dia.90 mm bh 168.000,00
- Flange PVC dia. 63 mm bh 162.000,00
- End Cap
- dia 150 mm bh 120.000,00
- dia 110 mm bh 102.000,00
- dia 90 mm bh 66.000,00
- dia 63 mm bh 42.000,00
- Water Meter
- dia 150 mm bh 8.100.000,00
- dia 100 mm bh 5.158.800,00
- dia 75 mm bh 4.260.000,00
- dia 50 mm bh 3.480.000,00
- Gilboult Joint
Gilboult Joint ND. 100 mm bh 375.000,00
Gilboult Joint ND. 75 mm bh 375.000,00
Pressure Gauge ND. 160 mm bh 200.000,00
Ball Valve ND. 3/4 " bh 275.000,00
Reduser All Flange 150 x 100 bh 175.500,00
Flow meter magnetic drive ND 150 mm Unit 40.000.000,00
Bell mouth ND 150 mm bh 1.500.000,00
7. Assesories Steel
- Bend Steel 22.5 derajat dia.150 mm bh 259.250,00
- Bend Steel 90 derajat dia.150 mm bh 979.338,00
- Bend Steel 45 derajat dia. 150 mm bh 936.762,00
- Bend Steel 22.5 derajat dia.50 mm bh 118.000,00
- Bend Steel 22.5 derajat dia.75 mm bh 146.250,00
- Bend Steel 22.5 derajat dia.100 mm bh 202.750,00
- Bend Steel 90 derajat dia.100 mm bh 246.960,00
- Bend Steel 45 derajat dia.100 mm bh 276.768,00
- Bend Steel 90 derajat dia.90 mm bh 136.260,00
- Bend Steel 45 derajat dia. 90 mm bh 161.808,00
- Bend Steel 22.5 derajat dia.50 mm bh 89.750,00
- Bend Steel 90 derajat dia.50 mm bh 46.836,00
- Bend Steel 45 derajat dia. 50 mm bh 51.102,00
- Valve Socket dia 63 mm bh 80.000,00
- Valve Socket dia 90 mm bh 90.000,00
- Valve Socket dia 110 mm PVC bh 100.800,00
- Valve Socket dia 150 mm bh
- Dismantling Joint 150 mm bh 1.200.000,00
- Dismantling Joint 100 mm bh 600.000,00
- Tee GIP dia.150 x 150mm bh 400.500,00
- Tee GIP dia.150 x 75 mm bh 344.000,00
- Tee GIP dia.100 x 100 mm bh 259.250,00
- Tee GIP dia.75 x 75 mm bh 202.750,00
- Tee GIP dia.50 x 50 mm bh 140.600,00
- Tee PVC dia.110 x 63 mm bh 144.000,00
- Flange Adaptor dia.150 mm bh 626.500,00
- Flange Adaptor dia.75 mm bh 513.500,00
- Reduser GIP dia.150 x 75 mm bh 202.750,00
- Reduser GIP dia.150 x 100 mm bh 174.500,00
- Reduser GIP dia.75 x 50 mm bh 146.250,00
- Air Valve dia. 150 mm bh 570.000,00
- Air Valve dia. 100 mm bh 457.000,00
- Air Valve dia. 75 mm bh 344.000,00
- Air Valve dia. 50 mm bh 287.500,00
- Steel Sleeve dia. 150 mm bh 46.810,00
- Steel Sleeve dia. 75 mm bh 33.250,00
- Steel Sleeve dia. 50 mm bh 27.600,00
- Check Valve dia.100mm bh 2.520.000,00
- Klem Plat bh 50.000,00
- Angker Baut bh 75.000,00
- Plat Besi Tipis t= 2 s/d 5 mm Kg 23.750,00
- Water Stop m'
- Bar Pengaman bh 380.000,00
VII. LAIN - LAIN
1. Gerobak Air bh 900.000,00
2. Jerigen Air kap. 20 liter bh 35.000,00
3. Jerigen Air kap. 10 liter bh 25.000,00
5. Tawas kg 10.250,00
6. Soda Ash kg 25.000,00
7. Pompa Kap. 10 - 30 l/menit Bh 3.500.000,00
8. Genset 3.5 kva bh 7.000.000,00