PENAWARAN HARGA PEKERJAAN GUDANG DI TANJUNG MORAWA

No. RINCIAN KEGIATAN DAN PEKERJAAN VOLUME SAT ANALISA HARGA SATUAN JUMLAH
(1) (2) (3) (4) (5) (6) (7)

I PEKERJAAN PENDAHULUAN
1. Pembersihan awal 1 Ls Taksir 1.500.000,00 1.500.000,00
2. Pembongkaran Dinding 33,6 M3 A.22.1.14 175.000,00 5.880.000,00
-
-
II PEKERJAAN PONDASI & BETON -
1. Lantai kerja cor beton fc = 7,4 Moa (K-100) 10 M3 A.A.41.14 1.268.000,00 12.680.000,00
2. Sloof Uk.25x30cm -
2.1 Bekisting 6,0 M2 A.41.1.21 195.916,88 1.175.501,28
2.2 Pembesian 61,92 KG A.41.1.17 17.898,60 1.108.281,31
2.3 Beton Cor fc = 19.3Moa (K-225) 0,75 M3 A.41.17 2.535.000,00 1.901.250,00
3. Kolom K2 Uk 40x40cm -
3.1 Bekisting 38,5 M2 A.41.1.22.A 195.916,88 7.542.799,88
3.2 Pembesian 456,81 KG A.41.1.17 17.898,60 8.176.259,47
3.3 Beton Cor fc = 19.3 Moa (K-225) 4,81 M3 A.41.17 2.535.000,00 12.193.350,00
4. Ring Balok 10 M' A.41.1.35 976.495,77 9.764.957,70
5. Plat Lantai -
5.1 Bekisting 27 M2 A.41.1.21 195.916,88 5.289.755,76
5.2 Wiremesh 2.224,44 KG A.41.1.19 17.898,60 39.814.361,78
5.3 Beton Cor fc = 19 Moa (K-300) 60 M3 A.44.4.10 3.640.000,00 218.400.000,00
-
-
III PEKERJAAN DINDING & PLASTERAN -
1. Pas Bata 1 : 4 345,6 M2 A.44.1.9 132.381,53 45.751.056,77
2. Plasteran 1 : 4 691,2 M2 A.44.2.4 74.847,75 51.734.764,80
3. Acian 691,2 M2 A.44.2.27 74.847,75 51.734.764,80
-
-
IV PEKERJAAN RANGKA BAJA -
1. Besi CNP 100x50x20x2.3 459,53 KG A.42.1.1 35.000,00 16.083.550,00
2. Atap Seng Zincaluro 0.35 120 M2 A.45.2.40 70.000,00 8.400.000,00
3. Baut Panjang 132 Bb Taksir 2.000,00 264.000,00
4. Pengelasan 11 M' Taksir 350.000,00 3.850.000,00
-
-
V PEKERJAAN ELEKTRIKAL -
1. Instalasi Titik Lampu 10 Titik Taksir 250.000,00 2.500.000,00
2. Instalasi Stop Kontak 5 Titik Taksir 250.000,00 1.250.000,00
3. Lampu XL 23 watt Fitting 10 Set Taksir 250.000,00 2.500.000,00
4. Stop Kontak 5 Bb Taksir 250.000,00 1.250.000,00
5. Saklar Ganda 2 Bb Taksir 250.000,00 500.000,00
-
-
VI PEKERJAAN PENGECATAN -
1. Cat Dinding 691,2 M2 A.47.1.10 28.911,00 19.983.283,20
2. Cat Minyak Manie 400 M2 A.47.1.16 28.911,00 11.564.400,00

-
-
TOTAL : 542.792.336,75
dibulatkan : 542.800.000,00
Terbilang : Lima ratus empat puluh dua juta delapan ratus ribu rupiah