NO URAIAN PEKERJAAN HARGA

1 2 3
I. HARGA SATUAN PEKERJAAN PERSIAPAN
1 PENGUKURAN DAN PEMASANGAN 1 M' BOWPLANK Rp. 181,072.50
2 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH Rp. 1,347,475.50
3 1 M2 PENERABASAN SEMAK Rp. 10,762.50
4 PEMBONGKARAN 1 M' PAGAR BRC EXISTING Rp. 76,256.25

II. HARGA SATUAN PEKERJAAN TANAH


1 1 M3 GALIAN TANAH KERAS DALAM 1 METER Rp. 197,400.00
2 1 M3 GALIAN TANAH CADAS DALAM 1 METER Rp. 299,250.00
3 1 M3 URUGAN KEMBALI TANAH GALIAN Rp. 107,625.00
4 1 M3 URUGAN PASIR Rp. 311,325.00
5 1 M3 URUGAN LIMESTONE Rp. 563,325.00
6 1 M3 URUGAN TANAH SUBUR Rp. 311,325.00

III. HARGA SATUAN PEKERJAAN PONDASI


1 1 M3 BATU KARANG CAMP. 1 PC : 5 PS Rp. 1,608,862.50
2 1 M3 PASANGAN BATU KOSONG Rp. 1,339,096.50

IV. HARGA SATUAN PEKERJAAN KAYU


1 PEMBUATAN DAN PEMASANGAN 1 M3 KUSEN PINTU DAN JENDELA, KAYU KELAS I Rp. 18,626,475.00
2 PEMBUATAN DAN PEMASANGAN 1 M2 DAUN PINTU PANEL, KAYU KAMPER Rp. 1,242,675.00
MEMBUAT 1 M2 DAUN PINTU KAYU LAPIS HPL RANGKAP RANGKA TERTUTUP,
3 KAYU KELAS I (Lebar Sampai 90 Cm) Rp. 1,552,425.00
4 MEMASANG 1 M' PLIN KAYU 10 CM, KAYU KELAS I Rp. 82,346.25

V. PEKERJAAN ATAP
1 1 M1 PEKERJAAN PASANG ALUMINIUM FOIL Rp. 52,080.00
2 1 M1 PEKERJAAN PASANG KAWAT WIREMESH 2 MM BAWAH ALUMINIUM FOIL Rp. 133,455.00
3 1 M1 PASANG PENUTUP ATAP SPANDEK Rp. 598,080.00
4 1 M1 PASANG BUBUNGAN ATAP SPANDEK Rp. 245,154.00
VI. HARGA SATUAN PEKERJAAN TANAH DAN PASANGAN
1 1 M2 PASANGAN BATAKO CAMP. 1 PC : 4 PS Rp. 423,356.85
2 1 M2 PASANGAN BATA MERAH CAMP. 1 PC : 5 PS Rp. 389,121.60
3 MEMASANG 1 BH GLASS BLOCK Rp. 34,860.00
4 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM Rp. 120,539.58
5 1 M2 PEKERJAAN ACIAN Rp. 68,118.75

VII. HARGA SATUAN PEKERJAAN BETON


1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87 Rp. 2,707,930.50
2 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72 Rp. 2,791,090.50
3 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56 Rp. 2,922,645.50
4 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52 Rp. 2,952,480.50
5 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 363,552.00
PEMBESIAN 1 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 36,355.20
6 1 M2 PASANG WIREMESH M8 1 LAPIS Rp. 130,821.11
7 1 M2 PASANG BEKISTING UNTUK SLOOF Rp. 492,576.00
8 1 M2 PASANG BEKISTING UNTUK KOLOM Rp. 748,345.50
9 1 M2 PASANG BEKISTING UNTUK BALOK Rp. 770,395.50
10 1 M2 PASANG BEKISTING UNTUK LANTAI MENGGUNAKAN FLOOR DECK Rp. 407,977.50
11 1 M2 PASANG BEKISTING UNTUK LANTAI Rp. 832,345.50
12 1 M2 PASANG BEKISTING UNTUK TANGGA Rp. 674,058.00
13 1 M2 PASANG FLOOR DECK Rp. 410,602.50
14 MEMBUAT 1 M1 KOLOM PRAKTIS BETON BERTULANG 11 X 11 CM Rp. 203,899.50
15 MEMBUAT 1 M1 BALOK PRAKTIS BETON BERTULANG 10 X 15 CM Rp. 263,371.50

VIII. HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING


1 PEMASANGAN 1 M2 GRANITE TILE 60 X 60 CM Rp. 452,915.56
2 MEMASANG 1 M' PLIN GRANITE 10 X 60 CM Rp. 126,225.37
3 1 M2 PASANG LANTAI KERAMIK 50 X 50 CM Rp. 433,335.00
4 1 M1 PASANG PLIN KERAMIK 10X50 CM Rp. 149,289.00
5 1 M2 PASANG DINDING KERAMIK 25 X 40 CM Rp. 1,360,154.25
6 1 M2 PASANG EPOXY LANTAI TEBAL 1500 MICRON Rp. 224,437.50
7 1 M2 PASANGAN DINDING PEMISAH GYPSUM RANGKA METAL STUD Rp. 345,114.00

IX. HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


1 1 M2 PASANG LANGIT-LANGIT GYPSUM RANGKA HOLLOW Rp. 362,565.00
2 1 M2 PASANG LANGIT-LANGIT KALSIBOARD RANGKA HOLLOW Rp. 316,701.00
3 1 M' PEKERJAAN PASANGAN LIST PLAPOND GYPSUM 5/5 CM Rp. 53,917.50
4 1 M' PEKERJAAN PASANGAN LIST PLAPOND GYPSUM 7/7 CM Rp. 75,967.50

X. HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM


1 PEMASANGAN 1 M1 KUSEN ALUMINIUM Rp. 80,798.55
2 PEMASANGAN 1 M2 PINTU ALUMINIUM Rp. 375,606.00
3 1 KG PASANG BESI PROFIL Rp. 77,983.50
4 1 BH PASANG ANCHOR D 25 P=800 MM Rp. 107,205.00
5 1 BH PASANG BOLT D 19 HTB A325N Rp. 79,873.50
6 1 M2 PASANG REILLING DARI BESI HOLLOW FINISH CAT Rp. 2,264,508.75
7 PEMBUATAN DAN PEMASANGAN 1 M2 TUTUP GROUND TANK DARI PLAT BESI Rp. 856,813.13
8 PEMBUATAN DAN PEMASANGAN 1 M2 PINTU BAJA RANGKA BESI HOLLOW Rp. 4,395,090.00
9 PEMBUATAN DAN PEMASANGAN 1 M1 TANGGA DARI PIPA GALVANIS Rp. 662,576.25
10 1 M2 MEMASANG RANGKA KUDA - KUDA BAJA RINGAN C 75 Rp. 296,759.06

XI. HARGA SATUAN PEKERJAAN KUNCI DAN KACA


1 PEMASANGAN 1 BUAH KUNCI TANAM BIASA Rp. 109,252.50
2 PEMASANGAN 1 BUAH ENGSEL PINTU Rp. 34,860.00
3 PEMASANGAN 1 BUAH ENGSEL JENDELA Rp. 23,231.25
4 PEMASANGAN 1 BUAH GRENDEL JENDELA Rp. 44,441.25
5 PEMASANGAN 1 BUAH KAIT ANGIN Rp. 36,750.00
6 MEMASANG 1 BH DOOR CLOSER Rp. 116,287.50
7 1 M2 PASANG KACA 5 MM Rp. 99,540.00

XII. HARGA SATUAN PEKERJAAN PENGECATAN


1 1 M2 PENGECATAN TEMBOK BARU DULUX INTERIOR Rp. 56,753.55
(1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
2 1 M2 PENGECATAN TEMBOK BARU EXTERIOR EX. DULUX WEATHERSIELD Rp. 91,193.55
(1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
3 PELABURAN 1 M2 BIDANG KAYU DENGAN POLITUR Rp. 72,817.50
4 1 M2 PENGECATAN DINDING DENGAN WATERPROOFING Rp. 51,072.00
5 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA SECARA Rp. 94,185.00

XIII. HARGA SATUAN PEKERJAAN SANITASI


1 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" Rp. 20,055.00
2 MEMASANG 1 M1 PIPA PVC TYPE AW f 2" Rp. 38,220.00
3 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" Rp. 55,842.50
4 MEMASANG 1 BUAH KLOSET DUDUK Rp. 1,319,031.00
5 MEMASANG 1 BUAH KRAN WASHTAFEL BIASA Rp. 51,712.50
6 MEMASANG 1 BUAH WASHTAFEL GANTUNG LENGKAP ACCESORIS Rp. 947,625.00
7 MEMASANG 1 BUAH JET WHASER Rp. 88,462.50
8 MEMASANG 1 BUAH KRAN AIR Rp. 56,962.50
9 MEMASANG 1 BUAH FLOORDRAIN Rp. 45,412.50
10 PEMBUATAN 1 UNIT SEPTICTANK DAN RESAPAN Rp. 32,281,196.46

XIV. HARGA SATUAN PEKERJAAN ELEKTRIKAL


1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN Rp. 251,580.00
2 PEMASANGAN 1 M1 KABEL POWER POMPA AIR/LAMPU Rp. 34,072.50
3 PEMASANGAN 1 BH BOX PANEL MCB Rp. 1,006,950.00
4 PEMASANGAN 1 M1 KABEL POWER UDARA Rp. 104,658.75
5 PEMASANGAN 1 UNIT TIANG LISTRIK 8 METER Rp. 5,717,629.91
6 PEMASANGAN 1 SET CAMERA CCTV Rp. 7,644,000.00
7 PEMBUATAN DAN PEMASANGAN 1 UNIT SELING DAN KATROL LAMPU GUDANG Rp. 159,862.50
8 PEMASANGAN 1 BH LAMPU GUDANG Rp. 806,662.50
9 PEMASANGAN 1 BH LAMPU LED CEILLING PLAFOND 20 WATT Rp. 118,912.50
10 PEMASANGAN 1 BH LAMPU LED BARET 20 WATT Rp. 108,412.50
11 PEMASANGAN 1 SET FITTING + LAMPU LED 10 WATT Rp. 76,912.50
12 PEMASANGAN 1 BH LAMPU DINDING (LAMPU KAPAL) LED 16 WATT Rp. 139,912.50
13 PEMASANGAN 1 BH LAMPU SOROT LED 100 WATT Rp. 213,412.50
14 PEMASANGAN 1 SET LAMPU TAMAN LED 33 WATT + RUMAH + TIANG Rp. 1,686,734.31
15 PEMASANGAN 1 BH SAKLAR TUNGGAL Rp. 55,912.50
16 PEMASANGAN 1 BH SAKLAR GANDA Rp. 55,912.50
17 PEMASANGAN 1 BH SAKLAR 3 Rp. 55,912.50
18 PEMASANGAN 1 BH STOP KONTAK Rp. 55,912.50
19 PEMASANGAN 1 BH STOP KONTAK AC Rp. 55,912.50
20 PEMASANGAN 1 UNIT TURBINE VENTILATOR TURBINE Rp. 1,218,000.00
21 PEMASANGAN 1 UNIT PENANGKAL PETIR (1 BLITZEM+3 TOMBAK+PIT BOX CONTRO
Rp. 302,400,000.00

XV. HARGA SATUAN PEKERJAAN LANDSCAPE


1 1 M2 PASANGAN PAVING BETON 20/20 CM TEBAL 8 CM K-300 Rp. 212,441.25
2 1 M1 PASANGAN KANSTIN BETON Rp. 279,620.25
3 PENANAMAN 1 POHON JEPUN Rp. 115,500.00
4 PENANAMAN 1 POHON TABEBUYA Rp. 577,500.00
5 PENANAMAN 1 POHON JEMPIRING Rp. 57,750.00
6 PENANAMAN 1 POHON KEMBANG KERTAS Rp. 115,500.00
7 PENANAMAN 1 M2 RUMPUT MUTIARA/JEPANG Rp. 34,650.00
XVI. HARGA SATUAN PEKERJAAN LAIN-LAIN (TAMBAHAN)
1 PEMASANGAN 1 UNIT TANGKI AIR KAPASITAS 3600 LT Rp. 8,272,950.00
2 PEMASANGAN 1 UNIT TANGKI AIR KAPASITAS 1350 LT Rp. 6,146,700.00
3 PEMASANGAN 1 UNIT POMPA AIR PENDORONG Rp. 1,112,475.00
4 PEMASANGAN 1 UNIT POMPA AIR SUBMERSIBLE Rp. 2,928,922.50
5 1 M1 PEKERJAAN SUMUR BOR Rp. 910,533.75
A. Harga Satuan Bahan

NO NAMA BARANG SATUAN HARGA SATUAN

1 2 3 4

BATU KALI
1 Batu Karang m3 400,000.00
2 Batu pecah 5-7 cm (manual) m3 800,000.00
3 Batu pecah 3-5 cm (manual) m3 900,000.00
4 Batu pecah 2-3 cm (manual) m3 1,530,000.00
5 Koral Beton m3 1,530,000.00
6 Bata Merah tebal 5 cm bj 3,500.00
7 Batako kelas 1 buntu bj 4,000.00
8 Limestone m3 400,000.00
9 Pasir Halus m3 800,000.00
10 Pasir pasang m3 650,000.00
11 Pasir beton m3 800,000.00
12 Pasir urug m3 200,000.00
13 Ijuk kg 50,000.00
14 Sirtu m3 350,000.00
15 Tanah urug pilihan m3 200,000.00
16 Air campuran beton ltr 500.00

SEMEN
17 Semen Gresik 50 kg zak 95,000.00
18 MU 450 ( Perekat keramik) 40 kg/zak kg 120,000.00
19 Sement base Zika kg 1,900.00
20 Semen warna kg 3,000.00

ATAP/GENTENG
21 Bubungan Karang Pilang isi 3,5/m bj 200,000.00
22 Atap spandek 0.50 mm m2 370,000.00
23 Bubung stel gel. 0.92 m lbr 80,000.00
24 Alluminium foil solartek 1,2x25x4mm roll 300,000.00
25 Ikut Celedu Paras Bh 40,000.00
26 Murda Paras Bh 60,000.00

KERAMIK DAN GRANITE


27 Keramik Platinum 50x50 cm m2 150,000.00
28 Keramik Platinum 25 x 40 motif halus kelas I m2 140,000.00
29 Granite tile Granito ukuran 60 x 60 cm Granito m2 170,000.00

KAYU
30 Kayu kamper balok m3 11,000,000.00
31 Kayu kamper papan m3 9,000,000.00
32 Kayu kruing balok m3 7,000,000.00
33 Plywood 4 mm setara meranti Lbr 140,000.00
34 Plywood 9 mm lbr 260,000.00
35 Multiplek 12 mm lbr 230,000.00
36 Kayu kruing papan m3 9,000,000.00
37 Kayu bekesting m3 7,000,000.00
38 Kayu dolken skapolding ls 20,000.00
39 Minyak bekisting ltr 15,000.00
40 HPL motif kayu lbr 200,000.00
41 Lem Kayu ltr 50,000.00

SANITAIR
42 Kloset Duduk Toto type CW637J/SW637JP bh 400,000.00
43 Washtafel gantung type LW246J+kran type TX129L set 350,000.00
44 Kran Air Onda bh 30,000.00
45 Kran Washtafel Biasa Toto type TX129L bh 25,000.00
46 Jet Whaser Toto type THX20NB bh 60,000.00
47 Floor Drain Stainless type TX1EA/TX1EAV1 bh 20,000.00
48 Seal Tape bh 40,000.00
49 ljr
50 Pipa Setara Maspion AW 2 ljr 30,000.00
51 Pipa Setara Maspion AW 3 ljr 40,000.00
52 Pipa Setara Maspion AW 6 ljr 50,000.00
53 Tangki Air Profil Tank TDA Kapasitas 3600 lt unt 5,000,000.00
54 Tangki Air Profil Tank Stainless Stell Kapasitas 1500 lt unt 3,500,000.00
55 Pompa Jet Pump Grundfos type JPA 4-54 unt 500,000.00
56 Pompa Air submersible Grundfos type SP 3A-22+Panel unt 600,000.00
57 Stop kran bh 30,000.00

BESI BETON DAN PAGAR


58 Hollow Galvanis 20x20x1.10 mm btg 90,000.00
59 Hollow Galvanis 30x30x1.10 mm btg 120,000.00
60 Hollow Galvanis 50x50x1.10 mm btg 170,000.00
61 Hollow Galvanis 75x75x2 mm btg 200,000.00
62 Pipa Galvanis 2" m1 92,500.00
63 Pipa Galvanis 1" m1 85,000.00
64 Besi beton kg 30,000.00
65 Besi/baja
Anchor profil
D 25 P=800 mm kg 44,000.00
66 Bolt D 19 HTB A325N bh 40,000.00
67 bh 60,000.00
68 Floor dek 0.75mm m2 50,000.00
69 Besi siku 50 x 50 x 5 mm btg 200,000.00
70 Plat baja 1 mm m2 160,000.00
71 Plat baja 1.2 mm m2 180,000.00
72 Rell pintu baja m1 2,500,000.00
73 Besi beton Ø 6 polos btg 115,000.00
74 Besi beton Ø 8 polos btg 125,000.00
75 Besi beton Ø 10 polos btg 135,000.00
76 Besi beton Ø 12 polos btg 140,000.00
77 Besi beton Ø 16 polos btg 160,000.00
78 Besi beton Ø 10 ulir btg 140,000.00
79 Besi beton Ø 13 ulir btg 145,000.00
80 Besi beton Ø 16 ulir btg 170,000.00
81 Besi beton Ø 19 ulir btg 190,000.00
82 Besi beton Ø 22 ulir btg 195,000.00
83 Floor dek 0.75mm m2 50,000.00
84 Kawat wiremesh 2 mm m2 80,000.00
85 Wiremess M6 2,1 x 55 roll 6,000,000.00
86 Wiremess M7 2,1 x 5,6 lbr 750,000.00
87 Wiremesh M8 2,1 x 5,4 lbr 870,000.00
88 Kawat beton RRT kg 35,000.00
89 Pengelasan cm 50,000.00
90 Aluminium 4 inch YKK m1 60,000.00
91 Aluminium strip/ jalusi m1 90,000.00
92 Rangka C 75068 @ 7 m galvalume btg 120,000.00
93 Reng (butten Ω 30) @ 6 m btg 40,000.00
94 Reng pengikat kuda-kuda @ 6 m btg 35,000.00
95 Pelat strips @ 1 m bh 20,000.00
96 Baut kuda-kuda SDS 6-19 bh 1,000.00
97 Baut reng SDS 6-16 btg 1,000.00
98 Baut listplank Ø 6-70 bh 1,000.00
99 Dinabold Ø 10-65 bh
100 Seling baja 3 mm m1
101 Katrol
102 Penggulung dan pengunci seling

FINISHING
103 Amplas lbr 20,000.00
104 Kuas untuk mengecat bh 20,000.00
105 Kapi bh 80,000.00
106 Cat menie besi kanzai 1 lt ltr 130,000.00
107 Cat besi kansai property gloss 1 lt ltr 130,000.00
108 Cat Alkali kg 60,000.00
109 Cat dasar Tembok kg 70,000.00
110 Cat tembok Dulux Exterior kg 120,000.00
111 Cat tembok Dulux Interior kg 120,000.00
112 Cat tembok Vinilex kg 110,000.00
113 Waterproofing kg 70,000.00
114 Cat Baja Chromate (anti karat) kg 140,000.00
115 Minyak cat ltr 20,000.00
116 Thiner A Spesial ltr 15,000.00
117 Dempul / Plamir ltr 15,000.00
118 Plamir Kayu kg 10,000.00
119 Lem Fox kg 25,000.00
120 Politur ltr 10,000.00
121 Politur ultra lasur ltr 15,000.00
122 Pre treatment/cleanol F Propan ltr 30,000.00
123 First layer Polycor Propan kg 50,000.00
124 Second layer Pollyfloor Propan kg 60,000.00
125 Finish coat Pollyfloor Propan kg 60,000.00
126 Thinner epoxy ltr 20,000.00

BAHAN LISTRIK
127 Box panel SDP bh 500,000.00
128 MCB 6 A Schneider bh 300,000.00
129 MCB 4 A Schneider bh 350,000.00
130 Tiang listrik baja aluminium tinggi 8 m unt 2,500,000.00
131 Lampu dinding LED 16 Watt bh 80,000.00
132 Kap lampu aluminium diameter 18" unt 50,000.00
133 Lampu Philips mercury 400 watt bh 350,000.00
134 Travo Philips bh 150,000.00
135 LED Baret 20 watt Philips bh 50,000.00
136 LED ceilling plafond 20 watt Philips bh 60,000.00
137 Fitting + Lampu LED 10 watt Philips bh 20,000.00
138 Lampu sorot LED 100 watt Philips bh 150,000.00
139 Lampu taman LED 33 watt + rumah + tiang set 1,500,000.00
140 Inbow dos plastik bj 100,000.00
141 Kabel NYM 3 x 2.5 mm m1 10,000.00
142 Kabel NYY ( 4 x 35 ) mm + BC 25 mm m1 15,000.00
143 Kabel NYY ( 4 x 16 ) mm + BC 16 mm m2 12,000.00
144 Klem 20 mm bj
145 Pipa 20 mm bt
146 Sock 20 mm bj
147 Stop Kontak Clipsal bh
148 Stop Kontak AC Clipsal bh
149 Tee dos 20 mm bh
150 Saklar Single Clipsal bh
151 Saklar Double Clipsal bh
152 Saklar 3 Clipsal bh
153 Isolasi bh
154 Turbine Ventilator Cyclone Type TB-FQ 800 AY Kapasitas unt 800,000.00
155 Blacksem 1" bh
156 Sok Galvanis 1" bh
157 GIP Galvanis 1" bt
158 Kawat BC 50 mm2 m1
159 Klem Begel 1" bh
160 Klem sisir 50 mm2 bh
161 Kotak Kontrol 10 cm x 15 cm bh
162 Perluv sok 1" bh
163 Pipa Conduit PVC 3/4" bt
164 Camera Hikvision resolusi 5 MP unt 70,000.00
165 Kabel Kyomitsu Coaxial RG6 + Power m1 7,000.00
166 DVR CCTV Hikvison Support Camera 5 MP unt 20,000.00
167 HDD WD 4 TB unt 1,500,000.00
168 Power Supply SPC Central 12V 10A unt 200,000.00
169 Monitor LG LED 20" unt 800,000.00

KUNCI DAN PENGGANTUNG


170 Engsel pintu bh
171 Engsel jendela ps
172 Kunci + hendle pintu bh
173 Grendel jendela ps
174 Kait angin ps
173 Door closer bh

KACA
174 Kaca Tebal 5 mm m2
175 Glass Block bh
176 Sealant kg

PAKU
177 Paku 10 cm kg
178 Paku kalsiboard kg
179 Paku reng kg
180 Paku seng kg
181 Paku list kg
182 Sekrup Kalisiboard kg
183 Paku skrup 3.5" kg
184 Paku skrup bh
185 Screw 6 x 1 bh
186 Paku Beton bh
187 Dinabolt ø 12mm M12 X 75 bh

PLAFOND
188 Gypsum Board (120x240x9) lbr 160,000.00
189 Calsiboard 4.5 mm lbr 40,000.00
189 List Gypsum 5/5 cm m1 30,000.00
190 List Gypsum 7/7 cm m1 50,000.00
191 Textile Tape m1 30,000.00
192 Cornice adhesive kg 20,000.00
193 Hollow Galvanis 40x40x0,35mm btg 60,000.00
194 Hollow Galvanis 20x40x0,35mm btg 40,000.00
195 Siku (Angel) m1 30,000.00
196 Rangka Metal Stud btg 30,000.00

PAVING
197 Paving 20 x 20 cm tebal 8 cm K-300 PC m2
198 Kanstein Jumbo (P:50,L:15,T:30 cm K225) bh

TANAMAN
199 Pohon Jepun / Plumeria Rubra pohon 100,000.00
200 Pohon Tabebuya / Chrysotricha sp pohon 500,000.00
201 Jempiring / Gardenia Jasminioides polybag 50,000.00
202 Kembang Kertas Daun Kecil / Bogenvile small leave polybag 100,000.00
203 Tanaman Rumput Mutiara/Jepang m2 30,000.00

PERALATAN K3
204 Helm Proyek Bh 30,000.00
205 Rompi Proyek Bh 30,000.00
206 Masker Bh 10,000.00
207 Sabuk Penggantung Bh 40,000.00
208 Kaca Mata Pelindung Bh 50,000.00
209 Sarung Tangan Ps 10,000.00
210 Sepatu Proyek Ps 350,000.00
211 Kotak P3K Set 1,000,000.00
212 Rambu-rambu Set 500,000.00
HARGA
NO NAMA BARANG SPESIFIKASI SATUAN
(Rp.)
1 2 3 3 4

1 Mandor Hari 250,000.00


2 Kepala Tukang Lapangan Hari 220,000.00
3 Kepala Tukang Besi Hari 220,000.00
4 Kepala Tukang Batu Hari 220,000.00
5 Kepala Tukang Kayu Hari 220,000.00
6 Kepala Tukang Cat Hari 220,000.00
7 Tukang Batu Hari 180,000.00
8 Tukang Besi Hari 180,000.00
9 Tukang Pipa Hari 180,000.00
10 Tukang Kayu Hari 180,000.00
11 Tukang Cat Hari 180,000.00
12 Tukang Politur Hari 180,000.00
13 Tukang Las Hari 180,000.00
14 Pekerja / Pekerja Tidak Terlatih Hari 180,000.00
15 Tukang Gali Hari 180,000.00
16 Tukang Listrik Hari 180,000.00
17 1 Ttk Instalasi Stop Kontak, Lampu, Exhaust Fan & Titik 1,500,000.00
Ceiling Fan
18 Biaya Pasang Instalasi penangkal petir Ls 40,000,000.00
19 Biaya pengeboran M1 20,000,000.00
20 Biaya sewa mobil crane Bln 240,000,000.00
I. HARGA SATUAN PEKERJAAN PERSIAPAN 5%
0.10
1 PENGUKURAN DAN PEMASANGAN 1 M' BOWPLANK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang Kayu L.02 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 39,450.00
B. BAHAN
Kayu 5/7 m3 0.012 7,000,000.000 84,000.00
Paku 2”-5” Kg 0.020 - -
Kayu papan 3/20 m3 0.007 7,000,000.000 49,000.00
JUMLAH HARGA BAHAN 133,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 172,450.00
E. Overhead & Profit 5% x D 8,622.50
F. Harga Satuan Pekerjaan (D+E) 181,072.50

2 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 6.6670 180,000.00 1,200,060.00
Mandor L.04 OH 0.3330 250,000.00 83,250.00
JUMLAH TENAGA KERJA 1,283,310.00
B. BAHAN
JUMLAH HARGA BAHAN

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,283,310.00
E. Overhead & Profit 5% x D 64,165.50
F. Harga Satuan Pekerjaan (D+E) 1,347,475.50
3 1 M2 PENERABASAN SEMAK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 10,250.00
B. BAHAN
JUMLAH HARGA BAHAN

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 10,250.00
E. Overhead & Profit 5% x D 512.50
F. Harga Satuan Pekerjaan (D+E) 10,762.50

4 PEMBONGKARAN 1 M' PAGAR BRC EXISTING

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.4000 180,000.00 72,000.00
Mandor L.04 OH 0.0025 250,000.00 625.00
JUMLAH TENAGA KERJA 72,625.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 72,625.00
E. Overhead & Profit 5% x D 3,631.25
F. Harga Satuan Pekerjaan (D+E) 76,256.25

II. HARGA SATUAN PEKERJAAN TANAH

1 1 M3 GALIAN TANAH KERAS DALAM 1 METER

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.0000 180,000.00 180,000.00
Mandor L.04 OH 0.0320 250,000.00 8,000.00
JUMLAH TENAGA KERJA 188,000.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 188,000.00
E. Overhead & Profit 5% x D 9,400.00
F. Harga Satuan Pekerjaan (D+E) 197,400.00

2 1 M3 GALIAN TANAH CADAS DALAM 1 METER

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.5000 180,000.00 270,000.00
Mandor L.04 OH 0.0600 250,000.00 15,000.00
JUMLAH TENAGA KERJA 285,000.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 285,000.00
E. Overhead & Profit 5% x D 14,250.00
F. Harga Satuan Pekerjaan (D+E) 299,250.00

3 1 M3 URUGAN KEMBALI TANAH GALIAN

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.5000 180,000.00 90,000.00
Mandor L.04 OH 0.0500 250,000.00 12,500.00
JUMLAH TENAGA KERJA 102,500.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 102,500.00
E. Overhead & Profit 5% x D 5,125.00
F. Harga Satuan Pekerjaan (D+E) 107,625.00

4 1 M3 URUGAN PASIR

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.3000 180,000.00 54,000.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 56,500.00
B. BAHAN
Pasir Urug m3 1.200 200,000.000 240,000.00
JUMLAH HARGA BAHAN 240,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 296,500.00
E. Overhead & Profit 5% x D 14,825.00
F. Harga Satuan Pekerjaan (D+E) 311,325.00

5 1 M3 URUGAN LIMESTONE

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.3000 180,000.00 54,000.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 56,500.00
B. BAHAN
Limestone m3 1.200 400,000.000 480,000.00
JUMLAH HARGA BAHAN 480,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 536,500.00
E. Overhead & Profit 5% x D 26,825.00
F. Harga Satuan Pekerjaan (D+E) 563,325.00

6 1 M3 URUGAN TANAH SUBUR

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.3000 180,000.00 54,000.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 56,500.00
B. BAHAN
Tanah subur m3 1.200 200,000.000 240,000.00
JUMLAH HARGA BAHAN 240,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 296,500.00
E. Overhead & Profit 5% x D 14,825.00
F. Harga Satuan Pekerjaan (D+E) 311,325.00

III. HARGA SATUAN PEKERJAAN PONDASI

1 1 M3 BATU KARANG CAMP. 1 PC : 5 PS

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.5000 180,000.00 270,000.00
Tukang Batu L.02 OH 0.7500 180,000.00 135,000.00
Kepala Tukang L.03 OH 0.0750 220,000.00 16,500.00
Mandor L.04 OH 0.0750 250,000.00 18,750.00
JUMLAH TENAGA KERJA 440,250.00
B. BAHAN
Batu karang m3 1.200 400,000.000 480,000.00
Semen Portlan Kg 136.000 1,900.00 258,400.00
Pasir Pasang m3 0.544 650,000.00 353,600.00
JUMLAH HARGA BAHAN 1,092,000.00

C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 1,532,250.00
E. Overhead & Profit 5% x D 76,612.50
F. Harga Satuan Pekerjaan (D+E) 1,608,862.50

2 1 M3 PASANGAN BATU KOSONG

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.7800 180,000.00 140,400.00
Tukang Batu L.02 OH 0.3900 180,000.00 70,200.00
Kepala Tukang L.03 OH 0.0390 220,000.00 8,580.00
Mandor L.04 OH 0.0390 250,000.00 9,750.00
JUMLAH TENAGA KERJA 228,930.00
B. BAHAN
Batu belah m3 1.200 800,000.00 960,000.00
Pasir Urug m3 0.432 200,000.00 86,400.00
JUMLAH HARGA BAHAN 1,046,400.00

C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 1,275,330.00
E. Overhead & Profit 5% x D 63,766.50
F. Harga Satuan Pekerjaan (D+E) 1,339,096.50

IV. HARGA SATUAN PEKERJAAN KAYU

1 PEMBUATAN DAN PEMASANGAN 1 M3 KUSEN PINTU DAN JENDELA, KAYU KELAS I

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 7.0000 180,000.00 1,260,000.00
Tukang kayu L.03 OH 21.0000 180,000.00 3,780,000.00
Kepala Tukang L.03 OH 2.1000 220,000.00 462,000.00
Mandor L.04 OH 0.3500 250,000.00 87,500.00
JUMLAH TENAGA KERJA 5,589,500.00
B. BAHAN
Balok kayu M² 1.1000 11,000,000.00 12,100,000.00
paku 10 cm Kg 1.2500 - -
Lem kayu Kg 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 12,150,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 17,739,500.00
E. Overhead & Profit 5% x D 886,975.00
F. Harga Satuan Pekerjaan (D+E) 18,626,475.00

2 PEMBUATAN DAN PEMASANGAN 1 M2 DAUN PINTU PANEL, KAYU KAMPER

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.0000 180,000.00 180,000.00
Tukang kayu L.03 OH 3.0000 180,000.00 540,000.00
Kepala Tukang L.03 OH 0.3000 220,000.00 66,000.00
Mandor L.04 OH 0.0500 250,000.00 12,500.00
JUMLAH TENAGA KERJA 798,500.00
B. BAHAN
Papan kayu kamper M³ 0.0400 9,000,000.00 360,000.00
Lem kayu Kg 0.5000 50,000.00 25,000.00
JUMLAH HARGA BAHAN 385,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,183,500.00
E. Overhead & Profit 5% x D 59,175.00
F. Harga Satuan Pekerjaan (D+E) 1,242,675.00

3 MEMBUAT 1 M2 DAUN PINTU KAYU LAPIS HPL RANGKAP


RANGKA TERTUTUP, KAYU KELAS I (Lebar Sampai 90 Cm)

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.0000 180,000.00 180,000.00
Tukang kayu L.03 OH 3.0000 180,000.00 540,000.00
Kepala Tukang L.03 OH 0.3000 220,000.00 66,000.00
Mandor L.04 OH 0.0500 250,000.00 12,500.00
JUMLAH TENAGA KERJA 798,500.00
B. BAHAN
Papan Kayu Kamper m3 0.0250 9,000,000.00 225,000.00
Paku 1-2,5 Cm Kg 0.0300 - -
Lem Kayu Kg 0.5000 50,000.00 25,000.00
Multiplek 12 mm Lbr 1.0000 230,000.00 230,000.00
HPL motif kayu Lbr 1.0000 200,000.00 200,000.00
JUMLAH HARGA BAHAN 680,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,478,500.00
E. Overhead & Profit 5% x D 73,925.00
F. Harga Satuan Pekerjaan (D+E) 1,552,425.00

4 MEMASANG 1 M' PLIN KAYU 10 CM, KAYU KELAS I

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang kayu L.02 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0025 250,000.00 625.00
JUMLAH TENAGA KERJA 29,825.00
B. BAHAN
Papan Kayu Kamper M3 0.0054 9,000,000.00 48,600.00
Paku 5 Cm dan 7 Cm Kg 0.0500 - -
JUMLAH HARGA BAHAN 48,600.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 78,425.00
E. Overhead & Profit 5% x D 3,921.25
F. Harga Satuan Pekerjaan (D+E) 82,346.25

V. PEKERJAAN ATAP

1 1 M1 PEKERJAAN PASANG ALUMINIUM FOIL

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1500 180,000.00 27,000.00
Tukang kayu L.02 OH 0.0500 180,000.00 9,000.00
Kepala Tukang L.03 OH 0.0050 220,000.00 1,100.00
Mandor L.04 OH 0.0080 250,000.00 2,000.00
JUMLAH TENAGA KERJA 39,100.00
B. BAHAN
Aluminium foil lbr 1.0500 10,000.00 10,500.00
JUMLAH HARGA BAHAN 10,500.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 49,600.00
E. Overhead & Profit 5% x D 2,480.00
F. Harga Satuan Pekerjaan (D+E) 52,080.00

2 1 M1 PEKERJAAN PASANG KAWAT WIREMESH 2 MM BAWAH ALUMINIUM FOIL

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1500 180,000.00 27,000.00
Tukang kayu L.02 OH 0.0500 180,000.00 9,000.00
Kepala Tukang L.03 OH 0.0050 220,000.00 1,100.00
Mandor L.04 OH 0.0080 250,000.00 2,000.00
JUMLAH TENAGA KERJA 39,100.00
B. BAHAN
Kawat wiremesh m2 1.1000 80,000.00 88,000.00
JUMLAH HARGA BAHAN 88,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 127,100.00
E. Overhead & Profit 5% x D 6,355.00
F. Harga Satuan Pekerjaan (D+E) 133,455.00

3 1 M1 PASANG PENUTUP ATAP SPANDEK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1500 180,000.00 27,000.00
Tukang kayu L.02 OH 0.7500 180,000.00 135,000.00
Kepala Tukang L.03 OH 0.0800 220,000.00 17,600.00
Mandor L.04 OH 0.0060 250,000.00 1,500.00
JUMLAH TENAGA KERJA 181,100.00
B. BAHAN
Aluminium gel tebal 0,50 lbr 1.0500 370,000.00 388,500.00
Paku hak panjang 15 cm Kg 0.0200 - -
JUMLAH HARGA BAHAN 388,500.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 569,600.00
E. Overhead & Profit 5% x D 28,480.00
F. Harga Satuan Pekerjaan (D+E) 598,080.00

4 1 M1 PASANG BUBUNGAN ATAP SPANDEK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.0840 180,000.00 15,120.00
Tukang kayu L.02 OH 0.1250 180,000.00 22,500.00
Kepala Tukang L.03 OH 0.0130 220,000.00 2,860.00
Mandor L.04 OH 0.0040 250,000.00 1,000.00
JUMLAH TENAGA KERJA 41,480.00
B. BAHAN
Bubung stel gel. 0.92 mm lbr 2.4000 80,000.00 192,000.00
Paku skrup 3,5” bh 6.0000 - -
JUMLAH HARGA BAHAN 192,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 233,480.00
E. Overhead & Profit 5% x D 11,674.00
F. Harga Satuan Pekerjaan (D+E) 245,154.00

VI. HARGA SATUAN PEKERJAAN TANAH DAN PASANGAN

1 1 M2 PASANGAN BATAKO CAMP. 1 PC : 4 PS

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.3000 180,000.00 54,000.00
Tukang batu L.02 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0150 250,000.00 3,750.00
JUMLAH TENAGA KERJA 77,950.00
B. BAHAN
HB-10 m³ 12.5000 4,000.00 50,000.00
Semen portland Kg 12.1300 1,900.00 23,047.00
Pasir pasang m³ 0.3880 650,000.00 252,200.00
Besi angker Ø 8 Kg 0.2800 - -
JUMLAH HARGA BAHAN 325,247.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 403,197.00
E. Overhead & Profit 5% x D 20,159.85
F. Harga Satuan Pekerjaan (D+E) 423,356.85

2 1 M2 PASANGAN BATA MERAH CAMP. 1 PC : 5 PS


HARGA SATUANJUMLAH HARGA
NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.3000 180,000.00 54,000.00
Tukang batu L.02 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0150 250,000.00 3,750.00
JUMLAH TENAGA KERJA 77,950.00
B. BAHAN
Bata Merah bh 70.0000 3,500.00 245,000.00
Semen portland Kg 9.6800 1,900.00 18,392.00
Pasir pasang m³ 0.0450 650,000.00 29,250.00
JUMLAH HARGA BAHAN 292,642.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 370,592.00
E. Overhead & Profit 5% x D 18,529.60
F. Harga Satuan Pekerjaan (D+E) 389,121.60

3 MEMASANG 1 BH GLASS BLOCK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0150 180,000.00 2,700.00
Tukang Batu L.03 OH 0.1500 180,000.00 27,000.00
Kepala Tukang L.03 OH 0.0150 220,000.00 3,300.00
Mandor L.04 OH 0.0008 250,000.00 200.00
JUMLAH TENAGA KERJA 33,200.00
B. BAHAN
Glass Block Bh 1.0000 - -
JUMLAH HARGA BAHAN -

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,200.00
E. Overhead & Profit 5% x D 1,660.00
F. Harga Satuan Pekerjaan (D+E) 34,860.00

4 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.3000 180,000.00 54,000.00
Tukang batu L.02 OH 0.1500 180,000.00 27,000.00
Kepala Tukang L.03 OH 0.0150 220,000.00 3,300.00
Mandor L.04 OH 0.0150 250,000.00 3,750.00
JUMLAH TENAGA KERJA 88,050.00
B. BAHAN
Semen portland kg 5.1840 1,900.00 9,849.60
Pasir pasang m³ 0.0260 650,000.00 16,900.00
JUMLAH HARGA BAHAN 26,749.60

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 114,799.60
E. Overhead & Profit 5% x D 5,739.98
F. Harga Satuan Pekerjaan (D+E) 120,539.58

5 1 M2 PEKERJAAN ACIAN

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.2000 180,000.00 36,000.00
Tukang batu L.03 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 58,700.00
B. BAHAN
Semen portland Kg 3.2500 1,900.00 6,175.00
JUMLAH HARGA BAHAN 6,175.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 64,875.00
E. Overhead & Profit 5% x D 3,243.75
F. Harga Satuan Pekerjaan (D+E) 68,118.75

VII.HARGA SATUAN PEKERJAAN BETON

1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87

HARGA SATUANJUMLAH HARGA 1400


NO. URAIAN KODESATUAN KOEFISIEN
NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.) 1350

A. TENAGA
Pekerja L.01 OH 1.6500 180,000.00 297,000.00
Tukang Batu L.02 OH 0.2750 180,000.00 49,500.00
Kepala Tukang L.03 OH 0.0280 220,000.00 6,160.00
Mandor L.04 OH 0.0830 250,000.00 20,750.00
JUMLAH TENAGA KERJA 373,410.00
B. BAHAN
Semen Portlan Kg 247.000 1,900.00 469,300.00
Pasir Beton m3 0.621 800,000.000 496,571.43
Kerikil (Maks 30mm) m3 0.740 1,530,000.000 1,132,200.00
Air Liter 215.000 500.000 107,500.00
JUMLAH HARGA BAHAN 2,205,571.43
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 2,578,981.43
E. Overhead & Profit 5% x D 128,949.07
F. Harga Satuan Pekerjaan (D+E) 2,707,930.50

2 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.6500 180,000.00 297,000.00
Tukang Batu L.02 OH 0.2750 180,000.00 49,500.00
Kepala Tukang L.03 OH 0.0280 220,000.00 6,160.00
Mandor L.04 OH 0.0830 250,000.00 20,750.00
JUMLAH TENAGA KERJA 373,410.00
B. BAHAN
Semen Portlan Kg 299.000 1,900.00 568,100.00
Pasir Beton m3 0.571 800,000.00 456,571.43
Kerikil (Maks 30mm) m3 0.753 1,530,000.00 1,152,600.00
Air Liter 215.000 500.00 107,500.00
JUMLAH HARGA BAHAN 2,284,771.43
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 2,658,181.43
E. Overhead & Profit 5% x D 132,909.07
F. Harga Satuan Pekerjaan (D+E) 2,791,090.50

3 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56
HARGA SATUANJUMLAH HARGA
NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.6500 180,000.00 297,000.00
Tukang Batu L.02 OH 0.2750 180,000.00 49,500.00
Kepala Tukang L.03 OH 0.0280 220,000.00 6,160.00
Mandor L.04 OH 0.0830 250,000.00 20,750.00
JUMLAH TENAGA KERJA 373,410.00
B. BAHAN
Semen Portlan Kg 384.000 1,900.00 729,600.00
Pasir Beton m3 0.494 800,000.00 395,428.57
Kerikil (Maks 30mm) m3 0.770 1,530,000.00 1,177,533.33
Air Liter 215.000 500.00 107,500.00
JUMLAH HARGA BAHAN 2,410,061.90
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 2,783,471.90
E. Overhead & Profit 5% x D 139,173.60
F. Harga Satuan Pekerjaan (D+E) 2,922,645.50

4 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.6500 180,000.00 297,000.00
Tukang Batu L.02 OH 0.2750 180,000.00 49,500.00
Kepala Tukang L.03 OH 0.0280 220,000.00 6,160.00
Mandor L.04 OH 0.0830 250,000.00 20,750.00
JUMLAH TENAGA KERJA 373,410.00
B. BAHAN
Semen Portlan Kg 413.000 1,900.00 784,700.00
Pasir Beton m3 0.486 800,000.00 389,142.86
Kerikil (Maks 30mm) m3 0.756 1,530,000.00 1,157,133.33
Air Liter 215.000 500.00 107,500.00
JUMLAH HARGA BAHAN 2,438,476.19
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 2,811,886.19
E. Overhead & Profit 5% x D 140,594.31
F. Harga Satuan Pekerjaan (D+E) 2,952,480.50

CATATAN
Bobot isi pasir = 1.400 kg/m3, bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20%

5 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0700 180,000.00 12,600.00
Tukang Besi L.02 OH 0.0700 180,000.00 12,600.00
Kepala Tukang L.03 OH 0.0070 220,000.00 1,540.00
Mandor L.04 OH 0.0040 250,000.00 1,000.00
JUMLAH TENAGA KERJA 27,740.00
B. BAHAN
Besi beton (polos/ulir) kg 10.5000 30,000.000 315,000.00
Kawat beton kg 0.1000 35,000.000 3,500.00
JUMLAH HARGA BAHAN 318,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 346,240.00
E. Overhead & Profit 5% x D 17,312.00
F. Harga Satuan Pekerjaan (D+E) 363,552.00
36,355.20

6 1 M2 PASANG WIREMESH M8 1 LAPIS

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang Besi L.02 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0010 250,000.00 250.00
JUMLAH TENAGA KERJA 38,450.00
B. BAHAN
Wiremesh M8 m2 1.1000 76,719.577 84,391.53
Kawat beton kg 0.0500 35,000.000 1,750.00
JUMLAH HARGA BAHAN 86,141.53
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 124,591.53
E. Overhead & Profit 5% x D 6,229.58
F. Harga Satuan Pekerjaan (D+E) 130,821.11

7 1 M2 PASANG BEKISTING UNTUK SLOOF


HARGA SATUANJUMLAH HARGA
NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.5200 180,000.00 93,600.00
Tukang Kayu L.02 OH 0.2600 180,000.00 46,800.00
Kepala Tukang L.03 OH 0.0260 220,000.00 5,720.00
Mandor L.04 OH 0.0260 250,000.00 6,500.00
JUMLAH TENAGA KERJA 152,620.00
B. BAHAN
Kayu kelas III m3 0.045 7,000,000.00 315,000.00
Paku 5 - 10 cm kg 0.300 - -
Minyak bekisting Liter 0.100 15,000.00 1,500.00
JUMLAH HARGA BAHAN 316,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 469,120.00
E. Overhead & Profit 5% x D 23,456.00
F. Harga Satuan Pekerjaan (D+E) 492,576.00

8 1 M2 PASANG BEKISTING UNTUK KOLOM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.6600 180,000.00 118,800.00
Tukang Kayu L.02 OH 0.3300 180,000.00 59,400.00
Kepala Tukang L.03 OH 0.0330 220,000.00 7,260.00
Mandor L.04 OH 0.0330 250,000.00 8,250.00
JUMLAH TENAGA KERJA 193,710.00
B. BAHAN
Kayu kelas III m3 0.040 7,000,000.00 280,000.00
Paku 5 - 12 cm kg 0.400 - -
Minyak bekisting Liter 0.200 15,000.00 3,000.00
Balok kayu kelas II m3 0.015 7,000,000.00 105,000.00
Plywood tebal 9 mm Lbr 0.350 260,000.00 91,000.00
Dolken kayu ø 8 - 10cm - panjan Batang 2.000 20,000.00 40,000.00
JUMLAH HARGA BAHAN 519,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 712,710.00
E. Overhead & Profit 5% x D 35,635.50
F. Harga Satuan Pekerjaan (D+E) 748,345.50
9 1 M2 PASANG BEKISTING UNTUK BALOK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.6600 180,000.00 118,800.00
Tukang Kayu L.02 OH 0.3300 180,000.00 59,400.00
Kepala Tukang L.03 OH 0.0330 220,000.00 7,260.00
Mandor L.04 OH 0.0330 250,000.00 8,250.00
JUMLAH TENAGA KERJA 193,710.00
B. BAHAN
Kayu kelas III m3 0.040 7,000,000.00 280,000.00
Paku 5 - 12 cm kg 0.400 - -
Minyak bekisting Liter 0.200 15,000.00 3,000.00
Balok kayu kelas II m3 0.018 7,000,000.00 126,000.00
Plywood tebal 9 mm Lbr 0.350 260,000.00 91,000.00
Dolken kayu ø 8 - 10cm - panjan Batang 2.000 20,000.00 40,000.00
JUMLAH HARGA BAHAN 540,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 733,710.00
E. Overhead & Profit 5% x D 36,685.50
F. Harga Satuan Pekerjaan (D+E) 770,395.50

10 1 M2 PASANG BEKISTING UNTUK LANTAI MENGGUNAKAN FLOOR DECK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang Kayu L.02 OH 0.5000 180,000.00 90,000.00
Kepala Tukang L.03 OH 0.0250 220,000.00 5,500.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 110,750.00
B. BAHAN
Floor dek 0.75 mm m2 1.100 50,000.00 55,000.00
Kayu perancah m3 0.005 7,000,000.00 37,800.00
Paku kg 0.100 - -
Balok Kayu Kelas II m3 0.015 7,000,000.00 105,000.00
Dolken kayu galam ø 8- 10cm pa Batang 4.000 20,000.00 80,000.00
JUMLAH HARGA BAHAN 277,800.00
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 388,550.00
E. Overhead & Profit 5% x D 19,427.50
F. Harga Satuan Pekerjaan (D+E) 407,977.50

11 1 M2 PASANG BEKISTING UNTUK LANTAI

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.6600 180,000.00 118,800.00
Tukang Kayu L.02 OH 0.3300 180,000.00 59,400.00
Kepala Tukang L.03 OH 0.0330 220,000.00 7,260.00
Mandor L.04 OH 0.0330 250,000.00 8,250.00
JUMLAH TENAGA KERJA 193,710.00
B. BAHAN
Kayu Kelas III m3 0.040 7,000,000.00 280,000.00
Paku 5 - 12 cm Kg 0.400 - -
Minyak Bekesting Liter 0.200 15,000.00 3,000.00
Balok Kayu Kelas II m3 0.015 7,000,000.00 105,000.00
Plywood tebal 9 mm Lbr 0.350 260,000.00 91,000.00
Dolken kayu galam ø 8- 10cm pa Batang 6.000 20,000.00 120,000.00
JUMLAH HARGA BAHAN 599,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 792,710.00
E. Overhead & Profit 5% x D 39,635.50
F. Harga Satuan Pekerjaan (D+E) 832,345.50

12 1 M2 PASANG BEKISTING UNTUK TANGGA

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.6600 180,000.00 118,800.00
Tukang Kayu L.02 OH 0.3300 180,000.00 59,400.00
Kepala Tukang L.03 OH 0.0330 220,000.00 7,260.00
Mandor L.04 OH 0.0330 250,000.00 8,250.00
JUMLAH TENAGA KERJA 193,710.00
B. BAHAN
Kayu Kelas III m3 0.030 7,000,000.00 210,000.00
Paku 5 - 12 cm Kg 0.400 - -
Minyak Bekesting Liter 0.150 15,000.00 2,250.00
Balok Kayu Kelas II m3 0.015 7,000,000.00 105,000.00
Plywood tebal 9 mm Lbr 0.350 260,000.00 91,000.00
Dolken kayu galam ø 8- 10cm pa Batang 2.000 20,000.00 40,000.00
JUMLAH HARGA BAHAN 448,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 641,960.00
E. Overhead & Profit 5% x D 32,098.00
F. Harga Satuan Pekerjaan (D+E) 674,058.00

13 1 M2 PASANG FLOOR DECK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang L.02 OH 0.5000 180,000.00 90,000.00
Kepala Tukang L.03 OH 0.0250 220,000.00 5,500.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 110,750.00
B. BAHAN
Floor dek 0.75 mm m2 1.100 50,000.00 55,000.00
Kayu perancah m3 0.005 7,000,000.00 37,800.00
Paku kg 0.100 - -
Balok Kayu Kelas II m3 0.015 7,000,000.00 105,000.00
Dolken kayu galam ø 8- 10cm pa btg 4.000 20,000.00 80,000.00
JUMLAH HARGA BAHAN 277,800.00
C. PERALATAN
Alat bantu ls 1.000 2,500.00 2,500.0000
JUMLAH HARGA ALAT 2,500.00

D. Jumlah (A + B + C) 391,050.00
E. Overhead & Profit 5% x D 19,552.50
F. Harga Satuan Pekerjaan (D+E) 410,602.50

14 MEMBUAT 1 M1 KOLOM PRAKTIS BETON BERTULANG 11 X 11 CM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1800 180,000.00 32,400.00
Tukang Batu L.02 OH 0.0200 180,000.00 3,600.00
Tukang Kayu L.02 OH 0.0200 180,000.00 3,600.00
Tukang Besi L.02 OH 0.0200 180,000.00 3,600.00
Kepala Tukang L.03 OH 0.0060 220,000.00 1,320.00
Mandor L.04 OH 0.0090 250,000.00 2,250.00
JUMLAH TENAGA KERJA 46,770.00
B. BAHAN
Kayu kelas III m3 0.0020 7,000,000.000 14,000.00
Paku 5 - 12 cm kg 0.010 - -
Minyak bekisting Liter 0.100 15,000.00 1,500.00
Besi beton polos kg 3.000 30,000.000 90,000.00
Kawat beton kg 0.450 35,000.000 15,750.00
Semen Portland kg 4.000 1,900.00 7,600.00
Pasir beton m3 0.006 800,000.00 4,800.00
Kerikil m3 0.009 1,530,000.00 13,770.00
JUMLAH HARGA BAHAN 147,420.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 194,190.00
E. Overhead & Profit 5% x D 9,709.50
F. Harga Satuan Pekerjaan (D+E) 203,899.50

15 MEMBUAT 1 M1 BALOK PRAKTIS BETON BERTULANG 10 X 15 CM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.2970 180,000.00 53,460.00
Tukang Batu L.02 OH 0.0330 180,000.00 5,940.00
Tukang Kayu L.02 OH 0.0330 180,000.00 5,940.00
Tukang Besi L.02 OH 0.0330 180,000.00 5,940.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0150 250,000.00 3,750.00
JUMLAH TENAGA KERJA 77,230.00
B. BAHAN
Kayu kelas III m3 0.0030 7,000,000.000 21,000.00
Paku 5 - 12 cm kg 0.020 - -
Minyak bekisting Liter 0.150 15,000.000 2,250.00
Besi beton polos kg 3.600 30,000.000 108,000.00
Kawat beton kg 0.050 35,000.000 1,750.00
Semen Portland kg 5.500 1,900.000 10,450.00
Pasir beton m3 0.009 800,000.000 7,200.00
Kerikil m3 0.015 1,530,000.000 22,950.00
JUMLAH HARGA BAHAN 173,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 250,830.00
E. Overhead & Profit 5% x D 12,541.50
F. Harga Satuan Pekerjaan (D+E) 263,371.50
VIII.HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING

1 PEMASANGAN 1 M2 GRANITE TILE 60 X 60 CM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.7000 180,000.00 126,000.00
Tukang batu L.02 OH 0.3500 180,000.00 63,000.00
Kepala Tukang L.03 OH 0.0350 220,000.00 7,700.00
Mandor L.04 OH 0.0350 250,000.00 8,750.00
JUMLAH TENAGA KERJA 205,450.00
B. BAHAN
Granite tile 60 X 60 Bh 3.0556 56,666.67 173,148.15
Semen portlandd Kg 10.0000 1,900.00 19,000.00
Pasir pasang M³ 0.0450 650,000.00 29,250.00
Semen warna Kg 1.5000 3,000.00 4,500.00
JUMLAH HARGA BAHAN 225,898.15
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 431,348.15
E. Overhead & Profit 5% x D 21,567.41
F. Harga Satuan Pekerjaan (D+E) 452,915.56

2 MEMASANG 1 M' PLIN GRANITE 10 X 60 CM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0900 180,000.00 16,200.00
Tukang batu L.02 OH 0.0900 180,000.00 16,200.00
Kepala Tukang L.03 OH 0.0090 220,000.00 1,980.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 35,630.00
B. BAHAN
Granite tile 60 X 60 Bh 1.7000 10,240.96 17,409.64
Semen portlandd Kg 1.1400 1,900.00 2,166.00
Pasir pasang M³ 0.1000 650,000.00 65,000.00
Semen warna Kg 0.0030 3,000.00 9.00
JUMLAH HARGA BAHAN 84,584.64
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 120,214.64
E. Overhead & Profit 5% x D 6,010.73
F. Harga Satuan Pekerjaan (D+E) 126,225.37

3 1 M2 PASANG LANTAI KERAMIK 50 X 50 CM

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.7000 180,000.00 126,000.00
Tukang batu L.02 OH 0.3500 180,000.00 63,000.00
Kepala Tukang L.03 OH 0.0350 220,000.00 7,700.00
Mandor L.04 OH 0.0350 250,000.00 8,750.00
JUMLAH TENAGA KERJA 205,450.00
B. BAHAN
Keramik 50x50 cm m2 1.0500 150,000.00 157,500.00
Semen Portlan Kg 10.0000 1,900.00 19,000.00
Pasir pasang M³ 0.0450 650,000.00 29,250.00
Semen warna Kg 0.5000 3,000.00 1,500.00
JUMLAH HARGA BAHAN 207,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 412,700.00
E. Overhead & Profit 5% x D 20,635.00
F. Harga Satuan Pekerjaan (D+E) 433,335.00

4 1 M1 PASANG PLIN KERAMIK 10X50 CM

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0900 180,000.00 16,200.00
Tukang batu L.02 OH 0.0900 180,000.00 16,200.00
Kepala Tukang L.03 OH 0.0090 220,000.00 1,980.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 35,630.00
B. BAHAN
Keramik 50x50 cm Bh 1.0500 37,500.00 39,375.00
Semen Portland Kg 1.1400 1,900.00 2,166.00
Pasir Pasang M³ 0.1000 650,000.00 65,000.00
Semen warna/semen grouting Kg 0.0030 3,000.00 9.00
JUMLAH HARGA BAHAN 106,550.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 142,180.00
E. Overhead & Profit 5% x D 7,109.00
F. Harga Satuan Pekerjaan (D+E) 149,289.00

5 1 M2 PASANG DINDING KERAMIK 25 X 40 CM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.9000 180,000.00 162,000.00
Tukang batu L.02 OH 0.4500 180,000.00 81,000.00
Kepala Tukang L.03 OH 0.0450 220,000.00 9,900.00
Mandor L.04 OH 0.0450 250,000.00 11,250.00
JUMLAH TENAGA KERJA 264,150.00
B. BAHAN
Keramik 25 x 40 cm Bh 10.8000 14,000.00 151,200.00
semen instan/perekat keramik Kg 7.3333 120,000.00 879,996.00
Semen warna/semen grouting Kg 0.0130 3,000.00 39.00
JUMLAH HARGA BAHAN 1,031,235.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,295,385.00
E. Overhead & Profit 5% x D 64,769.25
F. Harga Satuan Pekerjaan (D+E) 1,360,154.25

6 1 M2 PASANG EPOXY LANTAI TEBAL 1500 MICRON

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Tukang Cat L.02 OH 0.0750 180,000.00 13,500.00
Mandor L.04 OH 0.0350 250,000.00 8,750.00
JUMLAH TENAGA KERJA 22,250.00
B. BAHAN
Pre treatment /cleanol F Ltr 0.3000 30,000.00 9,000.00
First layer Polycor Kg 0.2500 50,000.00 12,500.00
Second layer Pollyfloor Kg 1.7500 60,000.00 105,000.00
Finish coat Pollyfloor Kg 1.0000 60,000.00 60,000.00
Thinner epoxy Ltr 0.2500 20,000.00 5,000.00
JUMLAH HARGA BAHAN 191,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 213,750.00
E. Overhead & Profit 5% x D 10,687.50
F. Harga Satuan Pekerjaan (D+E) 224,437.50

7 1 M2 PASANGAN DINDING PEMISAH GYPSUM RANGKA METAL STUD

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.2000 180,000.00 36,000.00
Tukang Kayu L.02 OH 0.6000 180,000.00 108,000.00
Kepala Tukang L.03 OH 0.0600 220,000.00 13,200.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 159,700.00
B. BAHAN
Gypsumboard 9 mm Lbr 0.7280 160,000.00 116,480.00
Metal stud Btg 0.7500 30,000.00 22,500.00
Screw 6 x 1 Bh 15.0000 - -
Compound Gypsum Bh 1.5000 20,000.00 30,000.00
Dinabold Ø 10 - 65 Kg 1.0000 - -
JUMLAH HARGA BAHAN 168,980.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 328,680.00
E. Overhead & Profit 5% x D 16,434.00
F. Harga Satuan Pekerjaan (D+E) 345,114.00

IX. HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

1 1 M2 PASANG LANGIT-LANGIT GYPSUM RANGKA HOLLOW

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.4000 180,000.00 72,000.00
Tukang kayu L.02 OH 0.2000 180,000.00 36,000.00
Kepala Tukang L.03 OH 0.0200 220,000.00 4,400.00
Mandor L.04 OH 0.0200 250,000.00 5,000.00
JUMLAH TENAGA KERJA 117,400.00
B. BAHAN
Gypsumboard 9 mm Lbr 0.3640 160,000.00 58,240.00
Textile Tape M' 0.1000 30,000.00 3,000.00
Cornice adhesive Kg 0.2780 20,000.00 5,560.00
Hollow Galvanis 40x40x0,35mm M' 1.5000 10,000.00 15,000.00
Hollow Galvanis 20x40x0,35mm M' 2.5000 15,000.00 37,500.00
Rangka penggantung 20x40x0,3 M' 3.9000 15,000.00 58,500.00
Siku (Angel) M' 1.6700 30,000.00 50,100.00
Screw 6 x 1 Bh 15.0000 - -
Paku beton Bh 5.0000 - -
JUMLAH HARGA BAHAN 227,900.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 345,300.00
E. Overhead & Profit 5% x D 17,265.00
F. Harga Satuan Pekerjaan (D+E) 362,565.00

2 1 M2 PASANG LANGIT-LANGIT KALSIBOARD RANGKA HOLLOW

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.4000 180,000.00 72,000.00
Tukang kayu L.02 OH 0.2000 180,000.00 36,000.00
Kepala Tukang L.03 OH 0.0200 220,000.00 4,400.00
Mandor L.04 OH 0.0200 250,000.00 5,000.00
JUMLAH TENAGA KERJA 117,400.00
B. BAHAN
Kalsiboard 4.5 mm Lbr 0.3640 40,000.00 14,560.00
Textile Tape M' 0.1000 30,000.00 3,000.00
Cornice adhesive Kg 0.2780 20,000.00 5,560.00
Hollow Galvanis 40x40x0,35mm M' 1.5000 10,000.00 15,000.00
Hollow Galvanis 20x40x0,35mm M' 2.5000 15,000.00 37,500.00
Rangka penggantung 20x40x0,3 M' 3.9000 15,000.00 58,500.00
Siku (Angel) M' 1.6700 30,000.00 50,100.00
Screw 6 x 1 Bh 15.0000 - -
Paku beton Bh 5.0000 - -
JUMLAH HARGA BAHAN 184,220.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 301,620.00
E. Overhead & Profit 5% x D 15,081.00
F. Harga Satuan Pekerjaan (D+E) 316,701.00

3 1 M' PEKERJAAN PASANGAN LIST PLAPOND GYPSUM 5/5 CM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang kayu L.02 OH 0.0500 180,000.00 9,000.00
Kepala Tukang L.03 OH 0.0050 220,000.00 1,100.00
Mandor L.04 OH 0.0030 250,000.00 750.00
JUMLAH TENAGA KERJA 19,850.00
B. BAHAN
List gypsum 5/5 cm m1 1.0500 30,000.00 31,500.00
JUMLAH HARGA BAHAN 31,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 51,350.00
E. Overhead & Profit 5% x D 2,567.50
F. Harga Satuan Pekerjaan (D+E) 53,917.50

4 1 M' PEKERJAAN PASANGAN LIST PLAPOND GYPSUM 7/7 CM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang kayu L.02 OH 0.0500 180,000.00 9,000.00
Kepala Tukang L.03 OH 0.0050 220,000.00 1,100.00
Mandor L.04 OH 0.0030 250,000.00 750.00
JUMLAH TENAGA KERJA 19,850.00
B. BAHAN
List gypsum 5/5 cm m1 1.0500 50,000.00 52,500.00
JUMLAH HARGA BAHAN 52,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 72,350.00
E. Overhead & Profit 5% x D 3,617.50
F. Harga Satuan Pekerjaan (D+E) 75,967.50

X. HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM

1 PEMASANGAN 1 M1 KUSEN ALUMINIUM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0430 180,000.00 7,740.00
Tukang Besi L.02 OH 0.0430 180,000.00 7,740.00
Kepala Tukang L.03 OH 0.0043 220,000.00 946.00
Mandor L.04 OH 0.0021 250,000.00 525.00
JUMLAH TENAGA KERJA 16,951.00
B. BAHAN
Profil alumunium m 1.0000 60,000.00 60,000.00
Skrup fixer bh 2.0000 - -
Sealant Tube 0.0600 - -
JUMLAH HARGA BAHAN 60,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 76,951.00
E. Overhead & Profit 5% x D 3,847.55
F. Harga Satuan Pekerjaan (D+E) 80,798.55

2 PEMASANGAN 1 M2 PINTU ALUMINIUM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0850 180,000.00 15,300.00
Tukang Besi L.02 OH 0.0850 180,000.00 15,300.00
Kepala Tukang L.03 OH 0.0085 220,000.00 1,870.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 33,720.00
B. BAHAN
Profil alumunium m 5.4000 60,000.00 324,000.00
Sealant tube 0.2700 - -
JUMLAH HARGA BAHAN 324,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 357,720.00
E. Overhead & Profit 5% x D 17,886.00
F. Harga Satuan Pekerjaan (D+E) 375,606.00

3 1 KG PASANG BESI PROFIL

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0600 180,000.00 10,800.00
Tukang las L.03 OH 0.0600 180,000.00 10,800.00
Kepala Tukang L.03 OH 0.0060 220,000.00 1,320.00
Mandor L.04 OH 0.0030 250,000.00 750.00
JUMLAH TENAGA KERJA 23,670.00
B. BAHAN
Besi profil Kg 1.1500 44,000.00 50,600.00
JUMLAH HARGA BAHAN 50,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 74,270.00
E. Overhead & Profit 5% x D 3,713.50
F. Harga Satuan Pekerjaan (D+E) 77,983.50

4 1 BH PASANG ANCHOR D 25 P=800 MM

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang las L.03 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0300 220,000.00 6,600.00
Mandor L.04 OH 0.0300 250,000.00 7,500.00
JUMLAH TENAGA KERJA 50,100.00
B. BAHAN
Anchor D 25 P=800 mm Bh 1.0000 40,000.00 40,000.00
JUMLAH HARGA BAHAN 40,000.00
C. PERALATAN
Alat bantu % 0.3000 40,000.00 12,000.00
JUMLAH HARGA ALAT 12,000.00

D. Jumlah (A + B + C) 102,100.00
E. Overhead & Profit 5% x D 5,105.00
F. Harga Satuan Pekerjaan (D+E) 107,205.00

5 1 BH PASANG BOLT D 19 HTB A325N

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang besi L.03 OH 0.0100 180,000.00 1,800.00
Kepala Tukang L.03 OH 0.0010 220,000.00 220.00
Mandor L.04 OH 0.0010 250,000.00 250.00
JUMLAH TENAGA KERJA 4,070.00
B. BAHAN
Bolt D 19 HTB A325N Bh 1.0000 60,000.00 60,000.00
JUMLAH HARGA BAHAN 60,000.00
C. PERALATAN
Alat bantu % 0.2000 60,000.00 12,000.00
JUMLAH HARGA ALAT 12,000.00
D. Jumlah (A + B + C) 76,070.00
E. Overhead & Profit 5% x D 3,803.50
F. Harga Satuan Pekerjaan (D+E) 79,873.50

6 1 M2 PASANG REILLING DARI BESI HOLLOW FINISH CAT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.5000 180,000.00 90,000.00
Tukang las L.02 OH 1.0000 180,000.00 180,000.00
Tukang cat L.03 OH 0.5000 180,000.00 90,000.00
Kepala Tukang L.03 OH 0.3500 220,000.00 77,000.00
Mandor L.04 OH 0.0500 250,000.00 12,500.00
JUMLAH TENAGA KERJA 449,500.00
B. BAHAN
Besi hollow 2x2 btg 0.5500 90,000.00 49,500.00
Besi hollow 3x3 btg 0.4500 120,000.00 54,000.00
Besi hollow 5x5 btg 0.3500 170,000.00 59,500.00
Pengelasan cm 25.0000 50,000.00 1,250,000.00
Cat menie kg 0.2000 130,000.00 26,000.00
Cat finish kg 0.3500 130,000.00 45,500.00
JUMLAH HARGA BAHAN 1,484,500.00
C. PERALATAN
Alat bantu % 0.1500 1,484,500.00 222,675.00
JUMLAH HARGA ALAT 222,675.00

D. Jumlah (A + B + C) 2,156,675.00
E. Overhead & Profit 5% x D 107,833.75
F. Harga Satuan Pekerjaan (D+E) 2,264,508.75

7 PEMBUATAN DAN PEMASANGAN 1 M2 TUTUP GROUND TANK DARI PLAT BESI

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.9500 180,000.00 171,000.00
Tukang las biasa L.02 OH 0.9500 180,000.00 171,000.00
Tukang cat L.02 OH 0.6500 180,000.00 117,000.00
Kepala Tukang L.03 OH 0.0950 220,000.00 20,900.00
Mandor L.04 OH 0.0300 250,000.00 7,500.00
JUMLAH TENAGA KERJA 487,400.00
B. BAHAN
Besi siku L 50.50.5 btg 0.4500 200,000.00 90,000.00
Besi pelat baja 1 mm m2 1.1000 160,000.00 176,000.00 94.20
Kawat las kg 0.0500 50,000.00 2,500.00
Cat menie besi Ltr 0.0500 130,000.00 6,500.00
Cat Kg 0.0750 130,000.00 9,750.00
Kuas buah 0.0500 20,000.00 1,000.00
JUMLAH HARGA BAHAN 285,750.00

C. PERALATAN
Alat bantu % 0.1500 285,750.00 42,862.50
JUMLAH HARGA ALAT 42,862.50

D. Jumlah (A + B + C) 816,012.50
E. Overhead & Profit 5% x D 40,800.63
F. Harga Satuan Pekerjaan (D+E) 856,813.13

8 PEMBUATAN DAN PEMASANGAN 1 M2 PINTU BAJA RANGKA BESI HOLLOW

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.9500 180,000.00 171,000.00
Tukang las biasa L.02 OH 0.9500 180,000.00 171,000.00
Tukang cat L.02 OH 0.6500 180,000.00 117,000.00
Kepala Tukang L.03 OH 0.0950 220,000.00 20,900.00
Mandor L.04 OH 0.0300 250,000.00 7,500.00
JUMLAH TENAGA KERJA 487,400.00
B. BAHAN
Besi hollow 3x3 btg 0.7000 120,000.00 84,000.00
Besi hollow 7.5x7.5 btg 0.8000 200,000.00 160,000.00
Besi pelat baja 1.2 mm m2 1.1000 180,000.00 198,000.00
Besi rell m1 1.1000 2,500,000.00 2,750,000.00
Kawat las kg 0.0700 50,000.00 3,500.00
Cat menie besi Ltr 0.0500 130,000.00 6,500.00
Cat Kg 0.1000 130,000.00 13,000.00
Kuas buah 0.0500 20,000.00 1,000.00
JUMLAH HARGA BAHAN 3,216,000.00

C. PERALATAN
Alat bantu % 0.1500 3,216,000.00 482,400.00
JUMLAH HARGA ALAT 482,400.00

D. Jumlah (A + B + C) 4,185,800.00
E. Overhead & Profit 5% x D 209,290.00
F. Harga Satuan Pekerjaan (D+E) 4,395,090.00

9 PEMBUATAN DAN PEMASANGAN 1 M1 TANGGA DARI PIPA GALVANIS


HARGA SATUANJUMLAH HARGA
NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.9500 180,000.00 171,000.00
Tukang las biasa L.02 OH 0.9500 180,000.00 171,000.00
Tukang cat L.02 OH 0.6500 180,000.00 117,000.00
Kepala Tukang L.03 OH 0.0950 220,000.00 20,900.00
Mandor L.04 OH 0.0300 250,000.00 7,500.00
JUMLAH TENAGA KERJA 487,400.00
B. BAHAN
Pipa galvanis 2" m1 2.2500 20,000.00 45,000.00
Pipa galvanis 1" m1 1.3500 20,000.00 27,000.00
Kawat las kg 0.0650 50,000.00 3,250.00
Cat menie besi Ltr 0.0500 130,000.00 6,500.00
Cat Kg 0.1000 130,000.00 13,000.00
Kuas buah 0.0500 20,000.00 1,000.00
JUMLAH HARGA BAHAN 95,750.00

C. PERALATAN
Alat bantu % 0.5000 95,750.00 47,875.00
JUMLAH HARGA ALAT 47,875.00

D. Jumlah (A + B + C) 631,025.00
E. Overhead & Profit 5% x D 31,551.25
F. Harga Satuan Pekerjaan (D+E) 662,576.25

10 1 M2 MEMASANG RANGKA KUDA - KUDA BAJA RINGAN C 75

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.2000 180,000.00 36,000.00
Tukang Besi L.02 OH 0.4500 180,000.00 81,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0500 250,000.00 12,500.00
JUMLAH TENAGA KERJA 131,700.00
B. BAHAN
Rangka C 75068 @ 7 m galvalum Btg 0.4559 120,000.00 54,712.61
Reng (butten Ω 30) @ 6 m Btg 0.6179 40,000.00 24,715.35
Reng pengikat kuda-kuda @ 6 m Btg 0.0673 35,000.00 2,354.44
Pelat strips @ 1 m Bh 0.1694 20,000.00 3,388.39
Baut kuda-kuda SDS 6-19 Bh 35.0001 1,000.00 35,000.12
Baut reng SDS 6-16 Btg 20.0000 1,000.00 20,000.00
Baut listplank Ø 6-70 Bh 0.9468 1,000.00 946.76
Dinabold Ø 10-65 Bh 0.9468 - -
Material dan alat bantu % 0.0450 218,000.00 9,810.00 10,000.00
JUMLAH HARGA BAHAN 150,927.67

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 282,627.67
E. Overhead & Profit 5% x D 14,131.38
F. Harga Satuan Pekerjaan (D+E) 296,759.06

XI. HARGA SATUAN PEKERJAAN KUNCI DAN KACA

1 PEMASANGAN 1 BUAH KUNCI TANAM BIASA

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang kayu L.02 OH 0.5000 180,000.00 90,000.00
Kepala Tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 104,050.00
B. BAHAN
Kunci tanam biasa Bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 104,050.00
E. Overhead & Profit 5% x D 5,202.50
F. Harga Satuan Pekerjaan (D+E) 109,252.50

2 PEMASANGAN 1 BUAH ENGSEL PINTU

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0150 180,000.00 2,700.00
Tukang kayu L.02 OH 0.1500 180,000.00 27,000.00
Kepala Tukang L.03 OH 0.0150 220,000.00 3,300.00
Mandor L.04 OH 0.0008 250,000.00 200.00
JUMLAH TENAGA KERJA 33,200.00
B. BAHAN
Engsel pintu Bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,200.00
E. Overhead & Profit 5% x D 1,660.00
F. Harga Satuan Pekerjaan (D+E) 34,860.00

3 PEMASANGAN 1 BUAH ENGSEL JENDELA

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang kayu L.02 OH 0.1000 180,000.00 18,000.00
Kepala Tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0005 250,000.00 125.00
JUMLAH TENAGA KERJA 22,125.00
B. BAHAN
Engsel Bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 22,125.00
E. Overhead & Profit 5% x D 1,106.25
F. Harga Satuan Pekerjaan (D+E) 23,231.25

4 PEMASANGAN 1 BUAH GRENDEL JENDELA

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang kayu L.02 OH 0.2000 180,000.00 36,000.00
Kepala Tukang L.03 OH 0.0200 220,000.00 4,400.00
Mandor L.04 OH 0.0005 250,000.00 125.00
JUMLAH TENAGA KERJA 42,325.00
B. BAHAN
Grendel jendela Bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 42,325.00
E. Overhead & Profit 5% x D 2,116.25
F. Harga Satuan Pekerjaan (D+E) 44,441.25

5 PEMASANGAN 1 BUAH KAIT ANGIN

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0150 180,000.00 2,700.00
Tukang kayu L.02 OH 0.1500 180,000.00 27,000.00
Kepala Tukang L.03 OH 0.0150 220,000.00 3,300.00
Mandor L.04 OH 0.0080 250,000.00 2,000.00
JUMLAH TENAGA KERJA 35,000.00
B. BAHAN
Kait angin Bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 35,000.00
E. Overhead & Profit 5% x D 1,750.00
F. Harga Satuan Pekerjaan (D+E) 36,750.00

6 MEMASANG 1 BH DOOR CLOSER

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang kayu L.03 OH 0.5000 180,000.00 90,000.00
Kepala Tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0030 250,000.00 750.00
JUMLAH TENAGA KERJA 110,750.00
B. BAHAN
Door closer Bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 110,750.00
E. Overhead & Profit 5% x D 5,537.50
F. Harga Satuan Pekerjaan (D+E) 116,287.50

7 1 M2 PASANG KACA 5 MM
HARGA SATUANJUMLAH HARGA
NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1600 180,000.00 28,800.00
Tukang Kaca L.02 OH 0.1600 180,000.00 28,800.00
Kepala Tukang L.03 OH 0.1600 220,000.00 35,200.00
Mandor L.04 OH 0.0080 250,000.00 2,000.00
JUMLAH TENAGA KERJA 94,800.00
B. BAHAN
Kaca 5 mm m2 1.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 94,800.00
E. Overhead & Profit 5% x D 4,740.00
F. Harga Satuan Pekerjaan (D+E) 99,540.00

XII.HARGA SATUAN PEKERJAAN PENGECATAN

1 1 M2 PENGECATAN TEMBOK BARU DULUX INTERIOR


(1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0200 180,000.00 3,600.00
Tukang cat L.02 OH 0.0630 180,000.00 11,340.00
Kepala Tukang L.03 OH 0.0063 220,000.00 1,386.00
Mandor L.04 OH 0.0025 250,000.00 625.00
JUMLAH TENAGA KERJA 16,951.00
B. BAHAN
Plamir Kg 0.1000 15,000.00 1,500.00
Cat dasar Kg 0.1000 70,000.00 7,000.00
Cat Penutup 2x Kg 0.2600 110,000.00 28,600.00
JUMLAH HARGA BAHAN 37,100.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,051.00
E. Overhead & Profit 5% x D 2,702.55
F. Harga Satuan Pekerjaan (D+E) 56,753.55

2 1 M2 PENGECATAN TEMBOK BARU EXTERIOR EX. DULUX WEATHERSIELD


(1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
HARGA SATUANJUMLAH HARGA
NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0200 180,000.00 3,600.00
Tukang cat L.02 OH 0.0630 180,000.00 11,340.00
Kepala Tukang L.03 OH 0.0063 220,000.00 1,386.00
Mandor L.04 OH 0.0025 250,000.00 625.00
JUMLAH TENAGA KERJA 16,951.00
B. BAHAN
Plamir Kg 0.1000 15,000.00 1,500.00
Cat Alkali Kg 0.1000 60,000.00 6,000.00
Cat Penutup 2x ex.dulux Kg 0.5200 120,000.00 62,400.00
JUMLAH HARGA BAHAN 69,900.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 86,851.00
E. Overhead & Profit 5% x D 4,342.55
F. Harga Satuan Pekerjaan (D+E) 91,193.55

3 PELABURAN 1 M2 BIDANG KAYU DENGAN POLITUR

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0400 180,000.00 7,200.00
Tukang cat L.02 OH 0.0600 180,000.00 10,800.00
Kepala tukang L.03 OH 0.0160 220,000.00 3,520.00
Mandor L.04 OH 0.0030 250,000.00 750.00
JUMLAH TENAGA KERJA 22,270.00
B. BAHAN
Politur Ltr 0.1500 10,000.00 1,500.00
Politur jadi Ltr 0.3720 15,000.00 5,580.00
Amplas Lbr 2.0000 20,000.00 40,000.00
JUMLAH HARGA BAHAN 47,080.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 69,350.00
E. Overhead & Profit 5% x D 3,467.50
F. Harga Satuan Pekerjaan (D+E) 72,817.50

4 1 M2 PENGECATAN DINDING DENGAN WATERPROOFING


HARGA SATUANJUMLAH HARGA
NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0200 180,000.00 3,600.00
Tukang cat L.02 OH 0.0630 180,000.00 11,340.00
Kepala Tukang L.03 OH 0.0600 220,000.00 13,200.00
Mandor L.04 OH 0.0300 250,000.00 7,500.00
JUMLAH TENAGA KERJA 35,640.00
B. BAHAN
Waterproofing Kg 0.1800 70,000.00 12,600.00
Kuas Bh 0.0200 20,000.00 400.00
JUMLAH HARGA BAHAN 13,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 48,640.00
E. Overhead & Profit 5% x D 2,432.00
F. Harga Satuan Pekerjaan (D+E) 51,072.00

5 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA SECARA MANUAL

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1500 180,000.00 27,000.00
Tukang cat L.02 OH 0.1500 180,000.00 27,000.00
Kepala tukang L.03 OH 0.0150 220,000.00 3,300.00
Mandor L.04 OH 0.0080 250,000.00 2,000.00
JUMLAH TENAGA KERJA 59,300.00
B. BAHAN
Cat Warna Zingkronasi Kg 0.2000 140,000.00 28,000.00
Minyak Cat Kg 0.1000 20,000.00 2,000.00
Kuas Bh 0.0200 20,000.00 400.00
JUMLAH HARGA BAHAN 30,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 89,700.00
E. Overhead & Profit 5% x D 4,485.00
F. Harga Satuan Pekerjaan (D+E) 94,185.00

XIII. HARGA SATUAN PEKERJAAN SANITASI

1 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"


HARGA SATUANJUMLAH HARGA
NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0360 180,000.00 6,480.00
Tukang pipa L.02 OH 0.0600 180,000.00 10,800.00
Kepala tukang L.03 OH 0.0060 220,000.00 1,320.00
Mandor L.04 OH 0.0020 250,000.00 500.00
JUMLAH TENAGA KERJA 19,100.00
B. BAHAN
Pipa PVC Bh 1.2000 - -
Perlengkapan % 0.3500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 19,100.00
E. Overhead & Profit 5% x D 955.00
F. Harga Satuan Pekerjaan (D+E) 20,055.00

2 MEMASANG 1 M1 PIPA PVC TYPE AW f 2"

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0540 180,000.00 9,720.00
Tukang pipa L.02 OH 0.0900 180,000.00 16,200.00
Kepala tukang L.03 OH 0.0090 220,000.00 1,980.00
Mandor L.04 OH 0.0030 250,000.00 750.00
JUMLAH TENAGA KERJA 28,650.00
B. BAHAN
Pipa PVC Bh 1.2000 5,000.00 6,000.00
Perlengkapan % 0.3500 1,750.00 1,750.00
JUMLAH HARGA BAHAN 7,750.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 36,400.00
E. Overhead & Profit 5% x D 1,820.00
F. Harga Satuan Pekerjaan (D+E) 38,220.00

3 MEMASANG 1 M1 PIPA PVC TYPE AW f 3"

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
Pekerja L.01 OH 0.0810 180,000.00 14,580.00
Tukang pipa L.02 OH 0.1350 180,000.00 24,300.00
Kepala tukang L.03 OH 0.0135 220,000.00 2,970.00
Mandor L.04 OH 0.0040 250,000.00 1,000.00
JUMLAH TENAGA KERJA 42,850.00
B. BAHAN
Pipa PVC Bh 1.2000 6,666.67 8,000.00
Perlengkapan % 0.3500 2,333.33 2,333.33
JUMLAH HARGA BAHAN 10,333.33
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 53,183.33
E. Overhead & Profit 5% x D 2,659.17
F. Harga Satuan Pekerjaan (D+E) 55,842.50

4 MEMASANG 1 BUAH KLOSET DUDUK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 3.3000 180,000.00 594,000.00
Tukang batu L.02 OH 1.1000 180,000.00 198,000.00
Kepala tukang L.03 OH 0.0010 220,000.00 220.00
Mandor L.04 OH 0.1600 250,000.00 40,000.00
JUMLAH TENAGA KERJA 832,220.00
B. BAHAN
Kloset duduk Bh 1.0000 400,000.00 400,000.00
Perlengkapan % 6% dr harga kloset 24,000.00 24,000.00
JUMLAH HARGA BAHAN 424,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,256,220.00
E. Overhead & Profit 5% x D 62,811.00
F. Harga Satuan Pekerjaan (D+E) 1,319,031.00

5 MEMASANG 1 BUAH KRAN WASHTAFEL BIASA

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang batu L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 23,250.00
B. BAHAN
Kran Washtafel Bh 1.0000 25,000.00 25,000.00
Seal tape Bh 0.0250 40,000.00 1,000.00
JUMLAH HARGA BAHAN 26,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 49,250.00
E. Overhead & Profit 5% x D 2,462.50
F. Harga Satuan Pekerjaan (D+E) 51,712.50

6 MEMASANG 1 BUAH WASHTAFEL GANTUNG LENGKAP ACCESORIS

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.2000 180,000.00 216,000.00
Tukang batu L.02 OH 1.4500 180,000.00 261,000.00
Kepala tukang L.03 OH 0.1500 220,000.00 33,000.00
Mandor L.04 OH 0.1000 250,000.00 25,000.00
JUMLAH TENAGA KERJA 535,000.00
B. BAHAN
Washtafel Bh 1.0000 350,000.00 350,000.00
Perlengkapan % dr harga washtafel 17,500.00 17,500.00
JUMLAH HARGA BAHAN 367,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 902,500.00
E. Overhead & Profit 5% x D 45,125.00
F. Harga Satuan Pekerjaan (D+E) 947,625.00

7 MEMASANG 1 BUAH JET WHASER

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang batu L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 23,250.00
B. BAHAN
Jet Whaser Bh 1.0000 60,000.00 60,000.00
Seal tape Bh 0.0250 40,000.00 1,000.00
JUMLAH HARGA BAHAN 61,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 84,250.00
E. Overhead & Profit 5% x D 4,212.50
F. Harga Satuan Pekerjaan (D+E) 88,462.50

8 MEMASANG 1 BUAH KRAN AIR

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang batu L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 23,250.00
B. BAHAN
Kran air Bh 1.0000 30,000.00 30,000.00
Seal tape Bh 0.0250 40,000.00 1,000.00
JUMLAH HARGA BAHAN 31,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,250.00
E. Overhead & Profit 5% x D 2,712.50
F. Harga Satuan Pekerjaan (D+E) 56,962.50

9 MEMASANG 1 BUAH FLOORDRAIN

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0100 180,000.00 1,800.00
Tukang batu L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0100 220,000.00 2,200.00
Mandor L.04 OH 0.0050 250,000.00 1,250.00
JUMLAH TENAGA KERJA 23,250.00
B. BAHAN
Floor drain Bh 1.0000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 43,250.00
E. Overhead & Profit 5% x D 2,162.50
F. Harga Satuan Pekerjaan (D+E) 45,412.50

10 PEMBUATAN 1 UNIT SEPTICTANK DAN RESAPAN

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. PEKERJAAN
Galian tanah m3 4.284 285,000.00 1,220,940.00
Pas. Batako m2 27.940 403,197.00 11,265,324.18
Plesteran m2 27.940 114,799.60 3,207,500.82
Acian m2 27.940 64,875.00 1,812,607.50
Beton K-150 m3 0.582 2,658,181.43 1,547,061.59
Besi Beton kg 50.920 34,624.00 1,763,054.08
Ring Praktis m1 4.000 250,830.00 1,003,320.00
Batu Karang m3 1.248 400,000.00 499,200.00
Ijuk kg 25.000 50,000.00 1,250,000.00
Pipa Galvanis 1'' m1 4.000 20,055.00 80,220.00
23,649,228.18

Perlengkapan % 0.3000 23,649,228.18 7,094,768.45


7,094,768.45

D. Jumlah (A + B + C) 30,743,996.63
E. Overhead & Profit 5% x D 1,537,199.83
F. Harga Satuan Pekerjaan (D+E) 32,281,196.46

XIV. HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang listrik L.02 OH 0.0200 180,000.00 3,600.00
Kepala tukang L.03 OH 0.1000 220,000.00 22,000.00
Mandor L.04 OH 0.1000 250,000.00 25,000.00
JUMLAH TENAGA KERJA 59,600.00
B. BAHAN
Kabel NYM 2 x 2,5 mm m 8.0000 10,000.00 80,000.00
Pipa Clipsal 20 mm hitam btng 3.0000 - -
Tee dos clipsal 20 mm bh 2.0000 - -
Sock clipsal 20 mm hitam bh 3.0000 - -
Isolasi bh 0.5000 - -
Inbow dos plastik clipsal E 157 P bh 1.0000 100,000.00 100,000.00
Klem bh 10.0000 - -
JUMLAH HARGA BAHAN 180,000.00
C. PERALATAN -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 239,600.00
E. Overhead & Profit 5% x D 11,980.00
F. Harga Satuan Pekerjaan (D+E) 251,580.00

2 PEMASANGAN 1 M1 KABEL POWER POMPA AIR/LAMPU

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0450 180,000.00 8,100.00
Tukang listrik L.02 OH 0.0450 180,000.00 8,100.00
Kepala tukang L.03 OH 0.0125 220,000.00 2,750.00
Mandor L.04 OH 0.0060 250,000.00 1,500.00
JUMLAH TENAGA KERJA 20,450.00
B. BAHAN
Kabel NYM 3 x 2,5 mm m 1.2000 10,000.00 12,000.00
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN 12,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 32,450.00
E. Overhead & Profit 5% x D 1,622.50
F. Harga Satuan Pekerjaan (D+E) 34,072.50

3 PEMASANGAN 1 BH BOX PANEL MCB

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.0500 180,000.00 9,000.00
Tukang listrik L.02 OH 1.0000 180,000.00 180,000.00
Kepala tukang L.03 OH 1.0000 220,000.00 220,000.00
JUMLAH TENAGA KERJA 409,000.00
B. BAHAN
Box panel bh 1.0000 500,000.00 500,000.00
JUMLAH HARGA BAHAN 500,000.00
C. PERALATAN
Alat bantu % 0.1000 500,000.00 50,000.00
JUMLAH HARGA ALAT 50,000.00

D. Jumlah (A + B + C) 959,000.00
E. Overhead & Profit 5% x D 47,950.00
F. Harga Satuan Pekerjaan (D+E) 1,006,950.00

4 PEMASANGAN 1 M1 KABEL POWER UDARA

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Kabel Twisted 2x10 mm m 1.1000 12,000.00 13,200.00
JUMLAH HARGA BAHAN 13,200.00
C. PERALATAN
Alat bantu % 0.5000 66,450.00 33,225.00
JUMLAH HARGA ALAT 33,225.00

D. Jumlah (A + B + C) 99,675.00
E. Overhead & Profit 5% x D 4,983.75
F. Harga Satuan Pekerjaan (D+E) 104,658.75

5 PEMASANGAN 1 UNIT TIANG LISTRIK 8 METER

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. BAHAN
Tiang listrik Unt 1.0000 2,500,000.00 2,500,000.00
JUMLAH TENAGA KERJA 2,500,000.00
B. PERALATAN
Alat bantu % 5.0000 125,000.00 125,000.00
JUMLAH HARGA BAHAN 125,000.00

C. ONGKOS PASANG % 15.0000 375,000.00 375,000.00


JUMLAH HARGA ALAT 375,000.00
D. PEKERJAAN SENDI
Galian m3 0.5760 285,000.00 164,160.00
Beton K-150 m3 0.5760 2,658,181.43 1,531,112.50
Pas. Batako m3 1.1200 403,197.00 451,580.64
Plesteran m2 1.1200 114,799.60 128,575.55
Acian m2 1.1200 64,875.00 72,660.00
Cat m2 1.1200 86,851.00 97,273.12
2,445,361.81

D. Jumlah (A + B + C+D) 5,445,361.81


E. Overhead & Profit 5% x D 272,268.09
F. Harga Satuan Pekerjaan (D+E) 5,717,629.91

6 PEMASANGAN 1 SET CAMERA CCTV

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. BAHAN
Camera resolusi 5 MP Unt 8.0000 70,000.00 560,000.00
Kabel Coaxial RG6 + Power m1 360.0000 7,000.00 2,520,000.00
DVR CCTV Support Camera 5 M Unt 1.0000 20,000.00 20,000.00
HDD 4 TB Unt 1.0000 1,500,000.00 1,500,000.00
Power Supply Central 12V 10A Unt 1.0000 200,000.00 200,000.00
Monitor LED 20" Unt 1.0000 800,000.00 800,000.00
JUMLAH TENAGA KERJA 5,600,000.00
B. PERALATAN
Alat bantu % 0.1000 5,600,000.00 560,000.00
JUMLAH HARGA BAHAN 560,000.00

C. ONGKOS PASANG % 0.2000 5,600,000.00 1,120,000.00


JUMLAH HARGA ALAT 1,120,000.00

D. Jumlah (A + B + C) 7,280,000.00
E. Overhead & Profit 5% x D 364,000.00
F. Harga Satuan Pekerjaan (D+E) 7,644,000.00

7 PEMBUATAN DAN PEMASANGAN 1 UNIT SELING DAN KATROL LAMPU GUDANG

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.2500 180,000.00 45,000.00
Tukang besi L.02 OH 0.5000 180,000.00 90,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 152,250.00
B. BAHAN
Seling 3 mm m1 21.0000 - -
Katrol bh 2.0000 - -
Penggulung dan pengunci seling bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Alat bantu % 0.1000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 152,250.00
E. Overhead & Profit 5% x D 7,612.50
F. Harga Satuan Pekerjaan (D+E) 159,862.50

8 PEMASANGAN 1 BH LAMPU GUDANG

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Lampu mercuri 400 watt bh 1.0000 350,000.00 350,000.00
Travo bh 1.0000 150,000.00 150,000.00
Kap lampu bh 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 550,000.00
C. PERALATAN
Alat bantu % 0.3000 550,000.00 165,000.00
JUMLAH HARGA ALAT 165,000.00

D. Jumlah (A + B + C) 768,250.00
E. Overhead & Profit 5% x D 38,412.50
F. Harga Satuan Pekerjaan (D+E) 806,662.50

9 PEMASANGAN 1 BH LAMPU LED CEILLING PLAFOND 20 WATT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
LED ceilling 20 watt bh 1.0000 60,000.00 60,000.00
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN 60,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 113,250.00
E. Overhead & Profit 5% x D 5,662.50
F. Harga Satuan Pekerjaan (D+E) 118,912.50

10 PEMASANGAN 1 BH LAMPU LED BARET 20 WATT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
LED Baret bh 1.0000 50,000.00 50,000.00
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN 50,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 103,250.00
E. Overhead & Profit 5% x D 5,162.50
F. Harga Satuan Pekerjaan (D+E) 108,412.50

11 PEMASANGAN 1 SET FITTING + LAMPU LED 10 WATT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Fitting plafond + lampu LED 10 bh 1.0000 20,000.00 20,000.00
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN 20,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 73,250.00
E. Overhead & Profit 5% x D 3,662.50
F. Harga Satuan Pekerjaan (D+E) 76,912.50

12 PEMASANGAN 1 BH LAMPU DINDING (LAMPU KAPAL) LED 16 WATT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Lampu dinding bh 1.0000 80,000.00 80,000.00
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN 80,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 133,250.00
E. Overhead & Profit 5% x D 6,662.50
F. Harga Satuan Pekerjaan (D+E) 139,912.50

13 PEMASANGAN 1 BH LAMPU SOROT LED 100 WATT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Lampu sorot bh 1.0000 150,000.00 150,000.00
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 203,250.00
E. Overhead & Profit 5% x D 10,162.50
F. Harga Satuan Pekerjaan (D+E) 213,412.50

14 PEMASANGAN 1 SET LAMPU TAMAN LED 33 WATT + RUMAH + TIANG

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Lampu taman+rumah+tiang bh 1.0000 1,500,000.00 1,500,000.00
Isolasi bh 0.2500 - -
Beton tiang m3 0.0200 2,658,181.43 53,163.63
JUMLAH HARGA BAHAN 1,553,163.63
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,606,413.63
E. Overhead & Profit 5% x D 80,320.68
F. Harga Satuan Pekerjaan (D+E) 1,686,734.31

15 PEMASANGAN 1 BH SAKLAR TUNGGAL

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Saklar tunggal bh 1.0000 - -
Mangkok listrik bh 1.0000 - -
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 53,250.00
E. Overhead & Profit 5% x D 2,662.50
F. Harga Satuan Pekerjaan (D+E) 55,912.50

16 PEMASANGAN 1 BH SAKLAR GANDA

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Saklar ganda bh 1.0000 - -
Mangkok listrik bh 1.0000 - -
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 53,250.00
E. Overhead & Profit 5% x D 2,662.50
F. Harga Satuan Pekerjaan (D+E) 55,912.50

17 PEMASANGAN 1 BH SAKLAR 3

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Saklar 3 bh 1.0000 - -
Mangkok listrik bh 1.0000 - -
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 53,250.00
E. Overhead & Profit 5% x D 2,662.50
F. Harga Satuan Pekerjaan (D+E) 55,912.50

18 PEMASANGAN 1 BH STOP KONTAK

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Stop kontak bh 1.0000 - -
Mangkok listrik bh 1.0000 - -
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 53,250.00
E. Overhead & Profit 5% x D 2,662.50
F. Harga Satuan Pekerjaan (D+E) 55,912.50

19 PEMASANGAN 1 BH STOP KONTAK AC

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.1000 180,000.00 18,000.00
Tukang listrik L.02 OH 0.1000 180,000.00 18,000.00
Kepala tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0250 250,000.00 6,250.00
JUMLAH TENAGA KERJA 53,250.00
B. BAHAN
Stop kontak AC bh 1.0000 - -
Mangkok listrik bh 1.0000 - -
Isolasi bh 0.2500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 53,250.00
E. Overhead & Profit 5% x D 2,662.50
F. Harga Satuan Pekerjaan (D+E) 55,912.50

20 PEMASANGAN 1 UNIT TURBINE VENTILATOR TURBINE

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Ongkos Pasang 35 % harga bahan % 0.3500 800,000.00 280,000.00
JUMLAH TENAGA KERJA 280,000.00
B. BAHAN
Turbine Ventilator Cyclone bh 1.0000 800,000.00 800,000.00
Bahan Bantu 5 % harga bahan % 0.0500 800,000.00 40,000.00
JUMLAH HARGA BAHAN 840,000.00

C. PERALATAN
Alat Bantu 5 % harga bahan % 0.0500 800,000.00 40,000.00
JUMLAH HARGA ALAT 40,000.00

D. Jumlah (A + B + C) 1,160,000.00
E. Overhead & Profit 5% x D 58,000.00
F. Harga Satuan Pekerjaan (D+E) 1,218,000.00

21 PEMASANGAN 1 UNIT PENANGKAL PETIR (1 BLITZEM+3 TOMBAK+PIT BOX CONTROL)

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. BIAYA PASANG
Biaya Pasang Instalasi ls 1.0000 40,000,000.00 40,000,000.00
Biaya pengeboran m1 6.0000 20,000,000.00 120,000,000.00
JUMLAH TENAGA KERJA 160,000,000.00
B. BAHAN
Blacksem 1" bh 4.0000 - -
Sok Galvanis 1" bh 4.0000 - -
GIP Galvanis 1" bt 3.0000 - -
Kawat BC 50 mm2 m1 42.5000 - -
Klem Begel 1" bh 6.0000 - -
Klem sisir 50 mm2 bh 3.0000 - -
Kotak Kontrol 10 cm x 15 cm bh 1.0000 - -
Perluv sok 1" bh 1.0000 - -
Pipa Conduit PVC 3/4" bt 10.0000 - -
Pit box control Unt 1.0000 48,000,000.00 48,000,000.00
JUMLAH HARGA BAHAN 48,000,000.00
C. PERALATAN
Alat bantu ls 1.0000 80,000,000.00 80,000,000.00
JUMLAH HARGA ALAT 80,000,000.00
D. Jumlah (A + B + C) 288,000,000.00
E. Overhead & Profit 5% x D 14,400,000.00
F. Harga Satuan Pekerjaan (D+E) 302,400,000.00

XV. HARGA SATUAN PEKERJAAN LANDSCAPE

1 1 M2 PASANGAN PAVING BETON 20/20 CM TEBAL 8 CM K-300

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.5000 180,000.00 90,000.00
Tukang Batu L.02 OH 0.5000 180,000.00 90,000.00
Kepala Tukang L.03 OH 0.0500 220,000.00 11,000.00
Mandor L.04 OH 0.0013 250,000.00 325.00
JUMLAH TENAGA KERJA 191,325.00
B. BAHAN
Paving 20 x 20 cm tebal 8 cm m2 1.0100 - -
Pasir urug m3 0.0500 200,000.00 10,000.00
JUMLAH HARGA BAHAN 10,000.00

C. PERALATAN % 10.0000 1,000.00


JUMLAH HARGA ALAT 1,000.00

D. Jumlah (A + B + C) 202,325.00
E. Overhead & Profit 5% x D 10,116.25
F. Harga Satuan Pekerjaan (D+E) 212,441.25

2 1 M1 PASANGAN KANSTIN BETON

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODESATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 0.9500 180,000.00 171,000.00
Tukang Batu L.02 OH 0.3500 180,000.00 63,000.00
Kepala Tukang L.03 OH 0.0350 220,000.00 7,700.00
Mandor L.04 OH 0.0950 250,000.00 23,750.00
JUMLAH TENAGA KERJA 265,450.00
B. BAHAN
Kanstein m1 2.0000 - -
Semen 50 kg zak 0.4500 1,900.00 855.00
JUMLAH HARGA BAHAN 855.00
C. PERALATAN ls 1.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 266,305.00
E. Overhead & Profit 5% x D 13,315.25
F. Harga Satuan Pekerjaan (D+E) 279,620.25

3 PENANAMAN 1 POHON JEPUN

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. ONGKOS TANAM
10% dari harga tanaman % 0.1000 10,000.00 10,000.00
JUMLAH ONGKOS TANAM 10,000.00
B. BAHAN
Jepun Bh 1.0000 100,000.00 100,000.00
JUMLAH HARGA BAHAN 100,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 110,000.00
E. Overhead & Profit 5% x D 5,500.00
F. Harga Satuan Pekerjaan (D+E) 115,500.00

4 PENANAMAN 1 POHON TABEBUYA

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. ONGKOS TANAM
10% dari harga tanaman % 0.1000 50,000.00 50,000.00
JUMLAH ONGKOS TANAM 50,000.00
B. BAHAN
Tabebuya Bh 1.0000 500,000.00 500,000.00
JUMLAH HARGA BAHAN 500,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 550,000.00
E. Overhead & Profit 5% x D 27,500.00
F. Harga Satuan Pekerjaan (D+E) 577,500.00
5 PENANAMAN 1 POHON JEMPIRING

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. ONGKOS TANAM
10% dari harga tanaman % 0.1000 5,000.00 5,000.00
JUMLAH ONGKOS TANAM 5,000.00
B. BAHAN
Jempiring Bh 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 55,000.00
E. Overhead & Profit 5% x D 2,750.00
F. Harga Satuan Pekerjaan (D+E) 57,750.00

6 PENANAMAN 1 POHON KEMBANG KERTAS

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. ONGKOS TANAM
10% dari harga tanaman % 0.1000 10,000.00 10,000.00
JUMLAH ONGKOS TANAM 10,000.00
B. BAHAN
Kembang Kertas Bh 1.0000 100,000.00 100,000.00
JUMLAH HARGA BAHAN 100,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 110,000.00
E. Overhead & Profit 5% x D 5,500.00
F. Harga Satuan Pekerjaan (D+E) 115,500.00

7 PENANAMAN 1 M2 RUMPUT MUTIARA/JEPANG

HARGA SATUAN JUMLAH HARGA


NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (Rp.)

A. ONGKOS TANAM
10% dari harga tanaman % 0.1000 3,000.00 3,000.00
JUMLAH ONGKOS TANAM 3,000.00
B. BAHAN
Rumput Mutiara/Jepang m2 1.0000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,000.00
E. Overhead & Profit 5% x D 1,650.00
F. Harga Satuan Pekerjaan (D+E) 34,650.00

XVI. HARGA SATUAN PEKERJAAN LAIN-LAIN (TAMBAHAN)

1 PEMASANGAN 1 UNIT TANGKI AIR KAPASITAS 3600 LT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 3.0000 180,000.00 540,000.00
Tukang pipa L.02 OH 3.0000 180,000.00 540,000.00
Kepala tukang L.03 OH 0.2000 220,000.00 44,000.00
Mandor L.04 OH 0.0200 250,000.00 5,000.00
JUMLAH TENAGA KERJA 1,129,000.00
B. BAHAN
Tangki Air Kapasitas 3600 ltr unit 1.0000 5,000,000.00 5,000,000.00
Accesoris pipa lot 35 % dari tangki 1,750,000.00 1,750,000.00
JUMLAH HARGA BAHAN 6,750,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 7,879,000.00
E. Overhead & Profit 5% x D 393,950.00
F. Harga Satuan Pekerjaan (D+E) 8,272,950.00

2 PEMASANGAN 1 UNIT TANGKI AIR KAPASITAS 1350 LT

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 3.0000 180,000.00 540,000.00
Tukang pipa L.02 OH 3.0000 180,000.00 540,000.00
Kepala tukang L.03 OH 0.2000 220,000.00 44,000.00
Mandor L.04 OH 0.0200 250,000.00 5,000.00
JUMLAH TENAGA KERJA 1,129,000.00
B. BAHAN
Tangki Air Kapasitas 1350 ltr unit 1.0000 3,500,000.00 3,500,000.00
Accesoris pipa lot 35 % dari tangki 1,225,000.00 1,225,000.00
JUMLAH HARGA BAHAN 4,725,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 5,854,000.00
E. Overhead & Profit 5% x D 292,700.00
F. Harga Satuan Pekerjaan (D+E) 6,146,700.00

3 PEMASANGAN 1 UNIT POMPA AIR PENDORONG

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.0000 180,000.00 180,000.00
Tukang pipa L.02 OH 1.0000 180,000.00 180,000.00
Kepala tukang L.03 OH 0.1000 220,000.00 22,000.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 384,500.00
B. BAHAN
Pompa air unit 1.0000 500,000.00 500,000.00
Accesoris pipa lot 35 % dari pompa 175,000.00 175,000.00
JUMLAH HARGA BAHAN 675,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,059,500.00
E. Overhead & Profit 5% x D 52,975.00
F. Harga Satuan Pekerjaan (D+E) 1,112,475.00

4 PEMASANGAN 1 UNIT POMPA AIR SUBMERSIBLE

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 1.0000 180,000.00 180,000.00
Tukang pipa L.02 OH 1.0000 180,000.00 180,000.00
Kepala tukang L.03 OH 0.1000 220,000.00 22,000.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 384,500.00
B. BAHAN
Pompa Submersible unit 1.0000 600,000.00 600,000.00
Pas pipa Dia 1 1/5" m1 90.0000 20,055.00 1,804,950.00
JUMLAH HARGA BAHAN 2,404,950.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 2,789,450.00
E. Overhead & Profit 5% x D 139,472.50
F. Harga Satuan Pekerjaan (D+E) 2,928,922.50

5 1 M1 PEKERJAAN SUMUR BOR

HARGA SATUANJUMLAH HARGA


NO. URAIAN KODE KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja L.01 OH 2.0000 180,000.00 360,000.00
Tukang pipa L.02 OH 2.0000 180,000.00 360,000.00
Kepala tukang L.03 OH 0.1000 220,000.00 22,000.00
Mandor L.04 OH 0.0100 250,000.00 2,500.00
JUMLAH TENAGA KERJA 744,500.00
B. BAHAN
Cassing Pipa PVC AW 6" m 1.2000 8,333.33 10,000.00
Accesoris pipa lot 10 % pipa 1,000.00 1,000.00
JUMLAH HARGA BAHAN 11,000.00

C. PERALATAN
Alat bantu 15% dari ongkos kerja 111,675.00
JUMLAH HARGA ALAT 111,675.00

D. Jumlah (A + B + C) 867,175.00
E. Overhead & Profit 5% x D 43,358.75
F. Harga Satuan Pekerjaan (D+E) 910,533.75
RENCANA ANGGARAN BIAYA (RAB)

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME
Rp. Rp.

I. PEKERJAAN PERSIAPAN
1 Persiapan perlengkapan kesehatan dan keselamatan kerja (K3)
-Helm Proyek 26.00 Bh
-Rompi Proyek (Safety Rompi) 26.00 Bh
-Masker Proyek 26.00 Bh
-Sabuk Penggantung (Safety Belt) 20.00 Bh
-Kaca Mata Las 10.00 Bh
-Sarung Tangan Safety 26.00 Ps
-Sepatu Proyek (Safety Boot) 26.00 Ps
-Kotak P3K 1.00 Set
-Rambu-rambu 1.00 Set
2 Pek. Penerabasan semak area lahan 2,392.00 M2
3 Pek. Pembongkaran bangunan existing 69.00 M3
4 Pek. Cut dan fill area bangunan 358.80 M3
5 Pek. Pembongkaran pagar BRC existing 60.00 M1
6 Pek. Pengukuran dan bowplank 185.00 M1
7 Pek. Sewa mobil Crane 1.00 Bln

II. PEKERJAAN TANAH DAN PASIR


1 Pek. Galian tanah pondasi menerus 15.45 M3
2 Pek. Galian tanah pondasi setempat 121.09 M3
3 Pek. Galian tanah sloof dan saluran 51.32 M3
4 Pek. Galian tanah ground tank 24.51 M3
5 Pek. Urugan kembali pondasi 20.48 M3
6 Pek. Urugan pasir bawah pondasi, sloof dan saluran 28.98 M3
7 Pek. Urugan pasir bawah lantai dan ground tank 139.48 M3
8 Pek. Urugan limestone peninggian lantai 272.82 M3
9 Pek. Urugan tanah subur 29.48 M3

III. PEKERJAAN PONDASI


1 Pek. Pasangan Batu kosong 1.80 M3
2 Pek. Pasangan Pondasi batu karang 1 : 5 7.32 M3

IV. PEKERJAAN BETON


1 Pekerjaan beton lantai kerja K-100 86.25 M3
2 Pekerjaan beton pondasi setempat 150/150
- Pek. Bekisting batako 27.00 M2
- Pek. Pembesian 1,978.11 Kg
- Pek. Beton K-250 16.20 M3
3 Pekerjaan beton pondasi setempat tower
- Pek. Bekisting batako 3.00 M2
- Pek. Pembesian 378.16 Kg
- Pek. Beton K-250 3.60 M3
4 Pekerjaan beton kolom pedestal 50/50
- Pek. Bekisting kayu 2 kali pakai 46.20 M2
- Pek. Pembesian 842.87 Kg
- Pek. Beton K-250 5.78 M3
5 Pekerjaan beton kolom pedestal dan tower 30/30
- Pek. Bekisting kayu 2 kali pakai 54.72 M2
- Pek. Pembesian 834.26 Kg
- Pek. Beton K-250 4.10 M3
6 Pekerjaan beton sloof 25/40
- Pek. Bekisting 2 kali pakai 362.82 M2
- Pek. Pembesian 9,519.58 Kg
- Pek. Beton K-250 45.35 M3
7 Pekerjaan beton sloof 20/30
- Pek. Bekisting 2 kali pakai 226.91 M2
- Pek. Pembesian 4,884.74 Kg
- Pek. Beton K-250 22.69 M3
8 Pekerjaan beton balok 20/30
- Pek. Bekisting 9.60 M2
- Pek. Pembesian 143.94 Kg
- Pek. Beton K-250 0.72 M3
9 Pekerjaan beton plat lantai 1
- Pek. Pembesian Wiremesh M-8 1,530.00 M2
- Pek. Beton K-250 163.69 M3
10 Pekerjaan beton tangga
- Pek. Bekisting 17.00 M2
- Pek. Pembesian 289.64 Kg
- Pek. Beton K-250 2.25 M3
11 Pekerjaan beton plat lantai 2
- Pek. Bekisting floor deck 59.50 M2
- Pek. Pembesian Wiremesh M-8 59.50 M2
- Pek. Beton K-250 7.90 M3
12 Pekerjaan beton plat lantai tower dan atap rumah pompa
- Pek. Bekisting 10.11 M2
- Pek. Pembesian Wiremesh M-8 8.07 M2
- Pek. Beton K-250 0.90 M3
13 Pekerjaan beton RAMP
- Pek. Pembesian Wiremesh M-8 97.20 M2
- Pek. Beton K-250 4.86 M3
14 Pekerjaan beton lantai ground tank
- Pek. Pembesian Wiremesh M-8 8.41 M2
- Pek. Beton K-250 0.84 M3
15 Pekerjaan beton saluran dan plat penutup saluran
- Pek. Bekisting 2 kali pakai 171.93 M2
- Pek. Pembesian (saluran) 968.84 Kg
- Pek. Pembesian Wiremesh M-8 (penutup saluran) 22.87 M2
- Pek. Beton K-150 21.16 M3
16 Pekerjaan beton kolom praktis 446.50 M1
17 Pekerjaan beton ring praktis 183.20 M1

V. PEKERJAAN PASANGAN, PLESTERAN DAN ACIAN


1 Pas. Dinding Batako 1 : 5 1,082.78 M2
2 Pek. Pasang glass block 405.00 Bh
3 Pek. Plesteran 1 : 5 2,134.37 M2
4 Pek. Acian 2,180.03 M2

VI. PEKERJAAN PLAFOND LANTAI DAN DINDING


1 Pek. Finish epoxy lantai gudang tebal 1500 micron 1,505.16 M2
2 Pek. Pasang dinding kalsiboard rangka hollow 313.76 M2
3 Pek. Pasang plafond gypsum rangka hollow 44.54 M2
4 Pek. Pasang list plafond gypsum 7/7 cm 33.80 M2
5 Pek. Pasang list plafond gypsum 5/5 cm 12.80 M2
6 Pek. Pasang granite tile 60/60 cm 81.95 M2
7 Pek. Pasang plin granite 10/60 cm 29.20 M1
8 Pek. Pasang keramik lantai KM 50/50 cm 5.00 M2
9 Pek. Pasang keramik dinding KM 25/40 cm 34.31 M2

VII. PEKERJAAN KUSEN DAN PENGGANTUNG


1 Pek. Pasang kusen aluminium 39.06 M2
2 Pek. Pasang daun pintu aluminium KM 2.94 M2
3 Pek. Pasang daun pintu multiplek lapis HPL 3.15 M2
4 Pek. Pasang daun jendela aluminium kaca 3.36 M2
5 Pek. Pasang kaca 5 mm 4.95 M2
6 Pek. Pasang engsel pintu 10.00 Bh
7 Pek. Pasang engsel jendela 8.00 Bh
8 Pek. Pasang grendel jendela 4.00 Bh
9 Pek. Pasang kait angin jendela 8.00 Bh
10 Pek. Pasang door closer 1.00 Bh
11 Pek. Pasang kunci+hendle pintu 3.00 Bh
12 Pek. Pasang reiling hollow tangga dan teras 29.79 M2
13 Pek. Pasang pintu hollow rumah pompa 0.85 M2
14 Pek. Pasang baja penutup ground tank 8.41 M2

VIII. PEKERJAAN BAJA DAN ATAP


1 Pek. Baja H-beam 400x400x13x21 mm (kolom) 17,578.40 Kg
2 Pek.
Pek.Baja
BajaIWF
H-beam 250X250x9x14
600x200x8x13 mm (kolom)
mm (castellated) 941.20 Kg
3 Pek. Baja IWF 450X150X6.5X9 mm (castellated) 3,907.20 Kg
4 3,739.00 Kg
5 Pek.
Pek.Baja
BajaIWF
IWF396X199x6x11
450x200x9x14 mm
mm (plat
(kuda-kuda)
lantai) 19,152.00 Kg
6 Pek. Baja IWF 298X149X5.5X8 mm (top ring) 1,847.33 Kg
7 Pek. Baja IWF 298X149x5.5x8 mm (skur) 1,632.00 Kg
8 Pek. Baja IWF 198X99x4.5x7 mm (plat lantai) 1,129.60 Kg
9 282.10 Kg
10 Pek.
Pek.Baja
Bajagording
IWF 198X99x4.5x7 mm (tangga)
CNP 200x75x20X3.2 mm 411.32 Kg
11 Pek. Trekstang ∅10 mm 11,094.34 Kg
12 Pek. Kait angin ∅10 mm 432.78 Kg
13 Pek. Baja plate 6 mm 251.53 Kg
14 Pek. Baja plate 9 mm 2,630.01 Kg
15 Pek. Baja plate 13 mm 716.54 Kg
16 368.26 Kg
17 Pek. Baja plate 15 mm 115.87 Kg
18 Pek.
Pek.Anchor
Baja plate
D 2525P=800
mm mm 1,020.50 Kg
19 Pek. Bolt D 19 HTB A325N 240.00 Bh
20 1,416.00 Bh
21 Pek. Pasang pintu baja gudang 83.00 M2
22 Pek. Pasang tangga besi tower 10.50 M1
23 Pek. Pasang tangga besi groundtank 8.00 M1
24 Pek. Kuda-kuda baja ringan profil C 5.29 M2
25 Pek. Penutup atap spandek 2,009.42 M2
26 Pek. Bubungan atap spandek 60.40 M1
27 Pek. Lapisan aluminium foil 2,001.92 M2
28 Pek. Lapisan kawat wiremesh bawah aluminium foil 2,001.92 M2

IX. PEKERJAAN LISTRIK


1 Pek. Pasang kabel power udara 200.00 M1
2 Pek. Pasang tiang listrik kabel power 4.00 Unt
3 Pek. Pasang panel MCB 1.00 Unt
4 Pek. Pasang intalasi titik lampu 45.00 Ttk
5 Pek. Pasang intalasi stop kontak 4.00 Ttk
6 Pek. Pasang intalasi stop kontak AC 2.00 Ttk
7 Pek. Pasang lampu LED ceiling plafond 20 Watt 8.00 Bh
8 Pek. Pasang lampu LED 10 Watt+fitting 2.00 Bh
9 Pek. Pasang lampu gudang Mercury 400 watt 18.00 Bh
10 Pek. Pasang lampu baret LED 20 watt 2.00 Bh
11 Pek. Pasang lampu dinding LED 16 watt 2.00 Bh
12 Pek. Pasang lampu sorot LED 100 watt 5.00 Bh
13 Pek. Pasang lampu taman LED 33 Watt +rumah+tiang 8.00 Set
14 Pek. Pasang kabel tambahan lampu gudang 90.00 M1
15 Pek. Pasang sling dan katrol lampu gudang 18.00 Unt
16 Pek. Pasang saklar tunggal 2.00 Bh
17 Pek. Pasang saklar ganda 8.00 Bh
18 Pek. Pasang saklar 3 7.00 Bh
19 Pek. Pasang stop kontak 4.00 Bh
20 Pek. Pasang stop kontak AC 2.00 Bh
21 Pek. Pasang kamera CCTV 1.00 Set
22 Pek. Pasang turbine ventilator cyclone 20.00 Bh
23 Pek. Pasang penangkal petir (3 tombak) 1.00 Unt

X. PEKERJAAN SANITAIR
1 Pek. Pasang intalasi air pipa PVC AW 1/2" 16.00 M1
2 Pek. Pasang intalasi air pipa PVC AW 1" 24.00 M1
3 Pek. Pasang intalasi air pipa PVC AW 2" 28.00 M1
4 Pek. Pasang intalasi air pipa PVC AW 3" 24.00 M1
5 Pek. Pasang washtafel gantung+kran 1.00 Set
6 Pek. Pasang kloset duduk 2.00 Bh
7 Pek. Pasang jetwhaser 2.00 Bh
8 Pek. Pasang kran air 3.00 Bh
9 Pek. Pasang floor drain 2.00 Bh
10 Pek. Septictank 1.00 Unt

XI. PEKERJAAN PENGECATAN


1 Pek. Pengecatan baja Zinchromate 2,196.38 M2
2 Pek. Pengecatan dinding baru Dulux Interior 1,213.66 M2
3 Pek. Pengecatan dinding baru Dulux Weathershield 1,437.00 M2
4 Pek. Pengecatan plafond baru Dulux Interior 44.54 M2

XII. PEKERJAAN LANDSCAPE


1 Pek. Paving 20x20 tebal 8 cm K-300 683.85 M2
2 Pek. Pasang kanstin beton 116.00 M1
3 Pek. Penanaman Pohon Tabebuya/Chrysotricha sp 5.00 Pohon
4 Pek. Penanaman Pohon Jepun/Plumeria Rubra 4.00 Pohon
5 Pek. Penanaman Jempiring/Gardenia jasminioides 25.00 Pohon
6 Pek. Penanaman Kembang Kertas Daun Kecil/Bogenvile small le 14.00 Pohon
7 Pek. Penanaman Rumput Jepang 35.00 M2

XIII. PEKERJAAN TANGKI AIR, SUMUR BOR DAN POMPA AIR


1 Pek. Pasang tangki air plastik kapasitas 3600 ltr (ground tank) 1.00 Unt
2 Pek. Pasang stainless stell kapasitas 1500 ltr (tower) 1.00 Unt
3 Pek. Pasang instalasi air bersih pipa PVC AW 2" 32.00 M1
4 Pek. Pasang instalasi listrik pompa air Kabel NYM 3 x 2,5 mm 90.00 M1
5 Pek. Sumur bor + cassing pipa PVC AW 6" 85.00 M1
6 Pek. Pasang pompa submersible Grundfos 1.00 Unt
7 Pek. Pasang pompa air pendorong 1.00 Unt

TOTAL PEKERJAAN GUDANG -


REKAPITULASI
BILL OF QUANTITY ( BQ )

JUMLAH HARGA
NO. URAIAN PEKERJAAN
(Rp.)

I. PEKERJAAN PERSIAPAN Rp -

II. PEKERJAAN TANAH DAN PASIR Rp -

III. PEKERJAAN PONDASI Rp -

IV. PEKERJAAN BETON Rp -

V. PEKERJAAN PASANGAN, PLESTERAN DAN ACIAN Rp -

VI. PEKERJAAN PLAFOND LANTAI DAN DINDING Rp -

VII. PEKERJAAN KUSEN DAN PENGGANTUNG Rp -

VIII. PEKERJAAN BAJA DAN ATAP Rp -

IX. PEKERJAAN LISTRIK Rp -

X. PEKERJAAN SANITAIR Rp -

XI. PEKERJAAN PENGECATAN Rp -

XII. PEKERJAAN LANDSCAPE Rp -

XIII. PEKERJAAN TANGKI AIR, SUMUR BOR DAN POMPA AIR Rp -

JUMLAH HARGA Rp -
PPN 11% Rp -
JUMLAH HARGA Rp -
DIBULATKAN Rp -
Terbilang :
Empat Belas milyar lima enam ratus enam puluh enam juta lima ratus dua puluh satu ribu rupiah