Anda di halaman 1dari 226

REKAPITULASI DAFTAR HARGA SATUAN PEKERJAAN

TAHUN 2017

NO URAIAN PEKERJAAN HARGA


1 2 3
I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)
1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER Rp. 671,506.37
2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK Rp. 144,180.96
3 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN Rp. 2,252,518.86
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT Rp. 1,873,614.33
5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU Rp. 2,214,193.44
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN Rp. 8,125.00
7 1 M2 PEMBUATAN BEDENG BURUH Rp. 1,893,871.83
8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM Rp. 356,703.82
9 1 M2 PEMBUATAN STEGGER DARI BAMBU Rp. 40,167.50
10 1 M2 PEMBUATAN STEGGER DENGAN SCAFHOLDING Rp. 137,328.18
11 1 M2 PEMBUATAN JALAN SEMENTARA Rp. 379,422.50
12 1 M3 BONGKARAN BETON BERTULANG Rp. 541,650.00

II PEKERJAAN TANAH (SNI 2835 : 2008)


1 1 M3 GALIAN TANAH BIASA DALAM 1 METER Rp. 59,375.00
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER Rp. 73,125.00
3 1 M3 GALIAN TANAH BIASA DALAM 3 METER Rp. 87,125.00
4 1 M3 GALIAN TANAH KERAS DALAM 1METER Rp. 79,000.00
5 1 M3 GALIAN TANAH CADAS DALAM 1 METER Rp. 120,000.00
6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER Rp. 95,625.00
7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER Rp. 4,375.00
8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER Rp. 26,000.00
9 1 M3 URUGAN KEMBALI Rp. -
10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) Rp. 43,750.00
11 1 M3 URUGAN PASIR Rp. 244,250.00
12 1 M2 PEMASANGAN LAPISAN IJUK TEBAL 10 CM Rp. 25,005.00
13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan Rp. 170,375.00

III PEKERJAAN PONDASI (SNI 2836 : 2008)


1 1 M3 BATU BELAH CAMP. 1 PC : 3 PS Rp. 947,825.00
2 1 M3 BATU BELAH CAMP. 1 PC : 5 PS Rp. 865,695.00
3 1 M3 BATU BELAH CAMP. 1 PC : 6 PS Rp. 842,055.00
4 1 M3 BATU BELAH CAMP. 1 PC : 8 PS Rp. 809,645.00
5 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU BELAH Rp. 2,119,654.00
6 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M Rp. 894,209.00
7 1 M3 PASANGAN BATU KOSONG Rp. 526,095.00
8 1 M' PONDASI BORED PILE DIAMETER 30 CM Rp. 398,336.75

IV PEKERJAAN DINDING (SNI 6897 : 2008)


1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS Rp. 172,692.50
NO URAIAN PEKERJAAN HARGA
1 2 3
2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS Rp. 166,511.50
3 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS Rp. 160,861.00
4 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS Rp. 159,809.00
1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10),
5 Rp. 93,404.00
campuran spesi 1 pc : 3 ps
6 1 M2 PASANGAN DINDING BATA RINGAN Rp. 169,005.00
7 1 M2 PAS. DINDING Terawang/Roster (12 x 11 x 24) CM camp 1 Pc : 3 Ps Rp. 1,448,635.00

V PEKERJAAN PLESTERAN (SNI 2837 : 2008)


1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM Rp. 66,435.80
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM Rp. 59,699.80
3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM Rp. 56,840.20
4 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM Rp. 53,771.80
5 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM Rp. 52,888.20
6 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM Rp. 51,956.20
7 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM Rp. 79,926.40
8 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM Rp. 74,988.60
9 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM Rp. 72,022.40
10 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM Rp. 70,767.60
11 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM Rp. 52,615.00
12 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS Rp. 42,619.00
13 1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH Rp. 24,761.60
14 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE Rp. 11,835.00
15 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS Rp. 52,228.00
16 1 M2 PLESTERAN MENGGUNAKAN SEMEN MU - 301, TEBAL 10 MM Rp. 97,210.00
17 1 M2 ACIAN MENGGUNAKAN SEMEN MU - 200,TEBAL 1,5MM Rp. 65,948.88
18 1 M2 PEKERJAAN ACIAN Rp. 31,562.50

VI PEKERJAAN KAYU (SNI 3434 : 2008)


1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I Rp. 37,695,272.22
2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS III Rp. 10,176,022.22
3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II Rp. 550,164.89
4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III Rp. 466,164.89
5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II Rp. 837,700.00
6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS II Rp. 588,470.00
7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS II Rp. 1,077,100.00
8 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar SampRp. 629,393.93
9 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS II Rp. 678,303.93
10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS II Rp. 925,219.67
11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I Rp. 1,353,038.93
12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II Rp. 1,426,363.93
13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II Bentang 6 M' Rp. 11,810,767.56
14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I Rp. 40,952,242.56
15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II Rp. 11,078,993.33
16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II Rp. 140,599.44
17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II Rp. 168,949.44
18 MEMASANG 1 M2 USUK EXPOSE KAYU KLS I KAMPER Rp. 106,736.94
NO URAIAN PEKERJAAN HARGA
1 2 3
19 MEMASANG 1 M2 RENG KAYU KLS I KAMPER Rp. 52,399.44
20 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II Rp. 1,499,754.56
21 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II Rp. 155,904.56
22 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II Rp. 158,064.44
23 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS II Rp. 140,784.78
24 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS II Rp. 141,914.89
25 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II Rp. 316,944.67
26 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II Rp. 400,370.67
27 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II Rp. 408,763.17
28 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA HOLO Rp. 183,470.67
29 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA HOLO Rp. 191,863.17
30 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I Rp. 331,699.44
31 MEMASANG 1 M2 LAMBRIZIRING DARI CONWOOD UKURAN (100 x 3050 x 11 mm) Rp. 258,633.75
32 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM Rp. 39,348.58

VII PEKERJAAN BETON ( SNI 7394:2008)


1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87 Rp. 878,800.00
2 MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c = 0,78 Rp. 917,569.63
3 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72 Rp. 947,673.33
4 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66 Rp. 983,622.22
5 MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61 Rp. 1,017,413.70
6 MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58 Rp. 1,043,545.56
7 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56 Rp. 1,059,729.63
8 MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53 Rp. 1,087,560.00
9 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52 Rp. 1,096,156.30
10 MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49 Rp. 1,173,290.19
11 MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48 Rp. 1,184,565.74
12 Beton Readymix K-175 Rp. 836,000.00
13 Beton Readymix K-225 Rp. 880,000.00
14 Beton Readymix K-250 Rp. 896,500.00
15 Beton Readymix K-275 Rp. 918,500.00
16 Beton Readymix K-300 Rp. 940,500.00
17 Beton Readymix K-350 Rp. 990,000.00
18 Sewa concrete pump/m3 Rp. 30,000.00
19 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 107,705.00
PEMBESIAN 1 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 10,770.50
20 1 M2 PEMBESIAN DENGAN WIRE MESH M6 Rp. 38,363.33
21 1 M2 PEMBESIAN DENGAN WIRE MESH M7 Rp. 46,630.00
22 1 M2 PEMBESIAN DENGAN WIRE MESH M8 Rp. 58,290.00
23 1 M2 PASANG BEKISTING UNTUK PONDASI Rp. 200,858.83
24 1 M2 PASANG BEKISTING UNTUK SLOOF Rp. 362,262.21
25 1 M2 PASANG BEKISTING UNTUK KOLOM Rp. 393,391.11
26 1 M2 PASANG BEKISTING UNTUK BALOK Rp. 412,291.11
27 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI Rp. 435,391.11
28 1 M2 PASANG BEKISTING UNTUK DINDING Rp. 413,534.36
NO URAIAN PEKERJAAN HARGA
1 2 3
29 1 M2 PASANG BEKISTING UNTUK TANGGA Rp. 361,618.11
30 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON Rp. 112,500.49
38 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM) Rp. 70,175.83
39 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM) Rp. 98,331.78

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG Rp. 76,005.00
2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT Rp. 81,505.00
3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG Rp. 158,970.00
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM Rp. 77,590.00
5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M Rp. 204,955.00
6 1 M2 PEKERJAAN ATAP SIRAP 8 X 60 CM Rp. 342,504.33
7 1 M2 PEKERJAAN ATAP SENG GELOMBANG Rp. 127,276.33
8 1 M2 PASANGAN LAPISAN ALUMINIUM FOIL Rp. 276,350.00
9 1 M1 PASANG NOK SENG GELOMBANG Rp. 40,805.87
10 1 BH PEKERJAAN PASANGAN MURDA/BETALA/IKUT CELEDU Rp. 127,893.85

IX PEKERJAAN PLAFOND / LANGIT - LANGIT (SNI 2839-2008)


1 MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN 6 MM Rp. 30,987.72
2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/3 MM, 4MM, 6MM Rp. 65,970.65
3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING Rp. 307,577.72
4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL Rp. 49,767.72
5 1 M2 PASANG LANGIT-LANGIT AKUSTIK UKURAN (60 x 120) CM + RANGKA ALUMINIUM Rp. 996,266.00
6 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA Rp. 217,526.30
7 1 M2 PLAFOND GYPSUM, RANGKA KAYU Rp. 242,674.43
8 1 M2 PLAFOND GYPSUM, RANGKA HOLO Rp. 117,483.68
9 1 M2 PLAFOND KALSIBOARD, RANGKA KAYU Rp. 255,006.75
10 1 M2 PLAFOND KALSIBOARD, RANGKA HOLO Rp. 129,816.00

X PEKERJAAN SANITASI
1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK Rp. 2,412,610.00
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN Rp. 588,950.00
3 MEMASANG 1 BUAH URINOIR Rp. 3,941,948.00
4 MEMASANG 1 BUAH WASHTAFEL KIA Rp. 495,670.00
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 Rp. 825,883.40
6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 " Rp. 146,715.00
7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3" Rp. 307,505.00
8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" Rp. 43,085.00
9 MEMASANG 1 M1 PIPA PVC TYPE AW f 2" Rp. 63,077.50
10 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4" Rp. 151,972.50
11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5" Rp. 65,182.50

XI PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)


1 1 KG MEMASANG RANGKA BAJA IWF Rp. 19,165.00
2 1 M2 PASANG ROLLING DOOR ALLUMINIUM Rp. 478,250.00
NO URAIAN PEKERJAAN HARGA
1 2 3
3 1 M2 MEMASANG RANGKA KUDA - KUDA BAJA RINGAN C 75 Rp. 193,499.60
4 1 M' PASANG KUSEN PINTU ALLUMINIUM Rp. 84,138.50
5 1 M2 PASANG PINTU KACA RANGKA ALLUMINIUM Rp. 361,241.00
6 1 M2 PASANG TERALI BESI STRIP (2 x 3 ) mm Rp. 816,117.10
7 1 M2 KAWAT NYAMUK Rp. 235,476.20
8 1 M2 PASANG JENDELA NAKO & TRALIS Rp. 316,111.67
9 1 M1 PASANG TALANG DATAR, SENG BJLS 28 Rp. 318,631.58

XII PEKERJAAN KUNCI DAN KACA (SNI 2002)


1 1 BH PASANG KUNCI TANAM BIASA Rp. 221,600.00
2 1 PS PASANG ENGSEL PINTU Rp. 87,080.00
3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU Rp. 76,000.00
4 1 BH PASANG KAIT ANGIN Rp. 65,110.00
5 1 BH PASANG KUNCI SLOT Rp. 271,950.00
6 1 M2 PASANG KACA, TEBAL5 MM Rp. 203,900.00
7 1 M2 PASANG KACA TEMPERED TEBAL 5 MM Rp. 293,550.00
8 1 M2 PASANG KACA TEMPERED TEBAL 6 MM Rp. 376,050.00
9 1 M2 PASANG KACA TEMPERED TEBAL 12 MM Rp. 668,100.00

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING (SNI 7395:2008)


1 1 M2 PASANG LANTAI UBIN GRANIT UKURAN (40 X 40) CM Rp. 476,251.75
2 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM Rp. 218,979.00
3 1 M2 PASANG LANTAI KERAMIK 60 X 60 CM Rp. 253,886.94
4 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM Rp. 236,699.40
5 1 M1 PASANG PLIN KERAMIK 10 X 30 CM Rp. 47,458.50
6 1 M1 PASANG PLIN KERAMIK 10 X 20 CM Rp. 35,056.50
7 1 M2 PASANG LANTAI MARMER 30 X 30 CM Rp. 459,333.50
10 MEMASANG 1 M2 LANTAI KAYU BANGKIRAI Rp. 707,494.44
11 1 M2 PASANG DINDING KERAMIK 20 X 20 CM Rp. 263,942.80
12 1 M2 PASANG DINDING MARMER 30 X 30 CM Rp. 541,446.00
14 1 M2 PASANG DINDING BATA PELAPIS UKURAN (3 x 7 x 24) cm Rp. 597,043.00
15 1 M2 PASANG DINDING BATU PARAS (30 X 15) Rp. 146,562.50
16 1 M2 PASANG DINDING BATU CANDI HITAM (20 x 20 x 3) Rp. 218,062.50

XIV PEKERJAAN PENGECATAN (SNI 2002)


1 1 M2 PEKERJAAN MENGIKIS ATAU MENGEROK CAT TEMBOK CARA MANUAL Rp. 12,690.00
2 1 M2 PEKERJAAN LAPIS PLAMIR Rp. 24,495.00
3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 CAT DASAR, 2 CAT PENUTUP) Rp. 49,342.30
4 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN KUAS Rp. 19,956.20
5 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN ROLL Rp. 25,582.10
6 1 M2 PEKERJAAN PENGECATAN LANGIT -LANGIT 2 LAPIS DENGAN Rp. 42,331.20
1 M2 PEK. PENGECATAN PLAFOND 2 LAPIS DENGAN CAT
7 Rp. 47,957.10
TEMBOK MENGGUNAKAN ROLL
8 1 M2 WATERPROOFING Rp. 38,943.77
9 1 M2 PEKERJAAN PASANG WALL PAPER DENGAN PEREKAT SETARA SILK HOUSE Rp. 743,475.00
NO URAIAN PEKERJAAN HARGA
1 2 3
10 1 M2 PEKERJAAN MELAPIS MENI KAYU Rp. 19,391.00
11 1 M2 PEKERJAAN MENDEMPUL ATAU MEMPLAMIR DAN MENGGOSOK KAYU Rp. 30,932.00
12 1 M2 PEKERJAAN PENGECATAN DASAR 1 LAPIS PADA KAYU Rp. 27,871.00
13 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA KAYU Rp. 52,570.00
14 1 M2 PEKERJAAN MENGEROK KARAT ATAU CAT PADA PERMUKAAN BAJA DENGAN SODA API Rp. 30,546.00
15 1 M2 PEKERJAAN MELAPIS MENI PADA PERMUKAAN BAJA Rp. 19,226.00
16 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA SECARA MANUAL Rp. 54,935.00
17 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN Rp. 48,888.00
18 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN TEAK OIL Rp. 34,063.00
19 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN POLITUR 2 LAPIS Rp. 74,969.00
20 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN VERNIS 2 LAPIS Rp. 32,314.00
21 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN RESIDU/TER Rp. 20,579.00

XV PEKERJAAN STYLE BALI


1 1 M2 PASANGAN BATA GOSOK 2 MUKA Rp. 719,680.00
2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA Rp. 401,242.50
3 1 M2 PASANGAN BATA PRESS 1 MUKA Rp. 384,840.00
4 1 M2 PASANGAN PARAS 1 MUKA Rp. 420,360.83
5 1 M2 PASANGAN BATU PALIMANAN TEBAL 3 CM Rp. 349,840.00
6 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA Rp. 438,858.85
7 1 M2 PASANGAN BATA GOSOK DIUKIR Rp. 539,840.00
8 1 M2 PASANGAN BATU TABAS KARANGASEM DIUKIR Rp. 562,756.67
9 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR Rp. 518,858.85
10 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP IJUK Rp. 3,629,450.00
11 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP GENTENG Rp. 3,214,250.00
12 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP IJUK Rp. 6,725,790.00
13 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP GENTENG Rp. 5,752,400.00
14 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP IJUK 190cmX190cm Rp. 7,309,940.00
15 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP GENTENG 190cmx190cm Rp. 6,093,440.00
16 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP IJUK 190cmx190cm Rp. 13,786,490.00
17 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP GENTENG 190cmx190cm Rp. 12,668,250.00
18 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP IJUK 200CMX200CM Rp. 13,979,800.00
19 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP GENTENG 200CMX200CM Rp. 13,897,300.00
20 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP IJUK 200CMX200CM Rp. 23,526,225.00
21 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP GENTENG 200CMX200CM Rp. 23,443,725.00
22 1 UNIT SANGGAH TAKSU BATU HITAM ATAP IJUK 40cmx40cm Rp. 2,449,387.50
23 1 UNIT SANGGAH TAKSU BATU HITAM ATAP GENTENG 40cmx40cm Rp. 2,703,487.50
24 1 UNIT SANGGAH TAKSU PARAS BATA ATAP IJUK 40cmx40cm Rp. 4,668,632.50
25 1 UNIT SANGGAH TAKSU PARAS BATA ATAP GENTENG 40cmx40cm Rp. 4,857,832.50

XVI PEKERJAAN HARDDSCAPE


1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225 Rp. 165,332.50
2 1 M2 PASANGAN Paving 10 x 20 cm tebal 6 cm K350 Rp. 178,037.50
3 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K225 Rp. 166,603.00
4 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K350 Rp. 187,277.50
NO URAIAN PEKERJAAN HARGA
1 2 3
5 1 M2 PASANGAN Paving 20 x 20 cm tebal 6 cm K350 Rp. 178,037.50
6 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225 Rp. 166,603.00
7 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K350 Rp. 187,508.50
8 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 pc Rp. 156,670.00
9 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 merah Rp. 179,350.00
10 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 hitam Rp. 177,250.00
11 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 pc Rp. 159,400.00
12 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 merah Rp. 185,650.00
13 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 hitam Rp. 184,600.00
14 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 pc Rp. 162,550.00
15 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 merah Rp. 188,800.00
16 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 hitam Rp. 187,750.00
17 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 pc Rp. 170,950.00
18 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 merah Rp. 197,200.00
19 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 hitam Rp. 196,150.00
20 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 pc Rp. 152,050.00
21 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 merah Rp. 176,200.00
22 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 hitam Rp. 174,100.00
23 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 pc Rp. 158,350.00
24 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 merah Rp. 194,050.00
25 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 hitam Rp. 191,950.00
26 1 M2 PASANGAN Paving Tiga Berlian tebal 6 cm K225 pc Rp. 161,983.00
27 1 M2 PASANGAN GRASS BLOCK Rp. 207,928.75
28 1 M2 PASANGAN KORAL SIKAT Rp. 189,056.00
29 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225 Rp. 168,972.50
30 Kanstein Jumbo (P:50,L:15,T:30 cm K225) Rp. 180,672.50
31 Kanstein kotak (P:50,t.20,La.10,Lb.16cm) K225 Rp. 164,672.50
32 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) Rp. 202,672.50
33 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) Rp. 209,672.50
34 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) Rp. 160,672.50
35 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) Rp. 150,672.50
36 1 Buah Pasangan Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) Rp. 182,172.50
37 1 M2 PENGECATAN KANSTEIN Rp. 36,564.14

XVII PEKERJAAN ELEKTRIKAL


1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN Rp. 325,070.00
2 1 TITIK INSTALASI AC Rp. 378,890.00
3 1 TITIK INSTALASI TELEPHONE Rp. 800,002.50
4 1 TITIK INSTALASI MATV Rp. 685,995.00

Denpasar, 20 Pebruari 2017

Kepala Bidang Penataan Bangunan dan


NO URAIAN PEKERJAAN HARGA
1 2 3
Pengembangan Kawasan Permukiman
Dinas Pekerjaan Umum dan Penataan Ruang
Kota Denpasar

Agus Sudarmo, ST.


Penata Tk. I
NIP. 19700907 199903 1 006
DAFTAR ANALISA PEKERJAAN
TAHUN 2017

HARGA HARGA HARGA HARGA


NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
I PEKERJAAN PERSIAPAN (SNI 03-2835-2002)
1 1 M1 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER
1.2500 btg Bambu Sedang 9,450.00 11,812.50
2.5000 kg Semen Portland 1,450.00 3,625.00
1.2000 lbr Seng gelombang 3" - 5" 99,770.00 119,724.00
0.0050 m3 Pasir Beton 210,000.00 1,050.00
0.0090 m3 Koral beton 298,000.00 2,682.00
0.0720 m3 Kayu Meranti Usuk 5/7 6,300,000.00 453,600.00
0.0600 kg Paku biasa 2" - 5" 17,297.78 1,037.87
0.4500 kg Meni Besi 49,500.00 22,275.00
0.2000 oh Tukang Kayu 105,000.00 21,000.00
0.4000 oh Pekerja 75,000.00 30,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0200 oh Mandor 125,000.00 2,500.00
Total : 55,700.00 615,806.37 671,506.37
2 1 M1 PENGUKURAN DAN PEMASANGAN BOWPLANK
0.0120 m3 Kayu Usuk Meranti 5/7 6,300,000.00 75,600.00
0.0200 kg Paku Biasa 2" - 5" 17,297.78 345.96
0.0070 m3 Kayu Papan Meranti 3/20 6,930,000.00 48,510.00
0.1000 oh Tukang Kayu 105,000.00 10,500.00
0.1000 oh Pekerja 75,000.00 7,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 19,725.00 124,455.96 144,180.96
3 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN
1.2500 btg Dolken Kayu Ø 8 - 10/4m 171,465.00 214,331.25
0.1800 m3 Kayu Meranti 6,300,000.00 1,134,000.00
0.8500 kg Paku Biasa 2" - 5" 17,297.78 14,703.11
1.1000 kg Besi Strip 11,960.00 13,156.00
35.0000 kg Semen Portland 1,450.00 50,750.00
0.1500 m3 Pasir Pasang 230,000.00 34,500.00
0.1000 m3 Pasir Beton 210,000.00 21,000.00
0.1500 m3 Koral Beton 298,000.00 44,700.00
30.0000 bh Bata Merah 2,500.00 75,000.00
0.2500 lbr Seng Plat 66,550.00 16,637.50
2.0000 bh Jendela Nako 38,500.00 77,000.00
0.0800 m2 Kaca Polos 143,000.00 11,440.00
0.1500 bh Kunci Tanam 291,500.00 43,725.00
0.0600 lbr Plywood 4 mm 122,100.00 7,326.00
2.0000 oh Tukang Kayu 105,000.00 210,000.00
1.0000 oh Tukang Batu 95,000.00 95,000.00
2.0000 oh Pekerja 75,000.00 150,000.00
0.3000 oh Kepala Tukang 110,000.00 33,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 494,250.00 1,758,268.86 2,252,518.86
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT
1.7000 btg Bambu Sedang 9,450.00 16,065.00
0.2100 m3 Kayu Meranti 6,300,000.00 1,323,000.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.3000 kg Paku Biasa 2" - 5" 17,297.78 5,189.33
10.5000 kg Semen Portland 1,450.00 15,225.00
0.0300 m3 Pasir Beton 210,000.00 6,300.00
0.0500 m3 Koral Beton 298,000.00 14,900.00
1.5000 lbr Seng gelombang BJLS 30 119,790.00 179,685.00
2.0000 oh Tukang Kayu 105,000.00 210,000.00
1.0000 oh Pekerja 75,000.00 75,000.00
0.2000 oh Kepala Tukang 110,000.00 22,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 313,250.00 1,560,364.33 1,873,614.33
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
5 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU
3.0000 btg Bambu Sedang 9,450.00 28,350.00
0.2760 m3 Kayu Meranti 6,300,000.00 1,738,800.00
0.7000 kg Paku biasa 2" - 5" 17,297.78 12,108.44
1.5000 lbr Seng gelombang BJLS 28 119,790.00 179,685.00
1.5000 oh Tukang Kayu 105,000.00 157,500.00
1.0000 oh Pekerja 75,000.00 75,000.00
0.1500 oh Kepala Tukang 110,000.00 16,500.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 255,250.00 1,958,943.44 2,214,193.44
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN
0.1000 oh Pekerja 75,000.00 7,500.00
0.0050 oh Mandor 125,000.00 625.00
Total : 8,125.00 8,125.00

7 1 M2 PEMBUATAN BEDENG BURUH


1.2500 btg Bambu Sedang 9,450.00 11,812.50
0.1860 m3 Kayu Meranti 6,300,000.00 1,171,800.00
0.3000 kg Paku Biasa 2" - 5" 17,297.78 5,189.33
18.0000 kg Semen Portland 1,450.00 26,100.00
0.0300 m3 Pasir Beton 210,000.00 6,300.00
0.0500 m3 Koral Beton 298,000.00 14,900.00
1.5000 lbr Seng gelombang BJLS 28 119,790.00 179,685.00
1.3500 lbr Plywood 4 mm 122,100.00 164,835.00
2.0000 oh Tukang Kayu 105,000.00 210,000.00
1.0000 oh Pekerja 75,000.00 75,000.00
0.2000 oh Kepala Tukang 110,000.00 22,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 313,250.00 1,580,621.83 1,893,871.83

8 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X20) CM


0.0360 m3 Kayu Terentang 6,300,000.00 226,800.00
0.0800 kg Paku Biasa 2" - 5" 17,297.78 1,383.82
1.0000 btg Kaso 5/7 97,020.00 97,020.00
0.3000 oh Tukang kayu 105,000.00 31,500.00
Total : 31,500.00 325,203.82 356,703.82
9 1 M2 PEMBUATAN STEGGER DARI BAMBU
1.0000 btg Bambu 9,450.00 9,450.00
0.2500 kg Tali Ijuk 5,390.00 1,347.50
0.2500 oh Tukang Kayu 105,000.00 26,250.00
0.0170 oh Pekerja 75,000.00 1,275.00
0.0020 oh Kepala Tukang 110,000.00 220.00
0.0130 oh Mandor 125,000.00 1,625.00
29,370.00 10,797.50 40,167.50
10 1 M2 PEMBUATAN STEGGER DENGAN SCAFHOLDING
0.0350 btg Kayu Balok Seseh 2,985,675.00 104,498.63
0.2000 kg Paku 10 17,297.78 3,459.56
0.2500 oh Tukang Kayu 105,000.00 26,250.00
0.0170 oh Pekerja 75,000.00 1,275.00
0.0020 oh Kepala Tukang 110,000.00 220.00
0.0130 oh Mandor 125,000.00 1,625.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
29,370.00 107,958.18 137,328.18
11 1 M2 PEMBUATAN JALAN SEMENTARA
0.1500 m3 Batu Kali 265,000.00 39,750.00
0.0900 m3 Batu Pecah 5 - 7 290,250.00 26,122.50
1.0100 m3 Pasir Pasang 230,000.00 232,300.00
1.0000 oh Pekerja 75,000.00 75,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 81,250.00 298,172.50 379,422.50
12 1 M3 BONGKARAN BETON BERTULANG
6.6670 oh Pekerja 75,000.00 500,025.00
0.3330 oh Mandor 125,000.00 41,625.00
Total : 541,650.00 541,650.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
II PEKERJAAN TANAH (SNI 2835 : 2008)
1 1 M3 GALIAN TANAH BIASA DALAM 1 METER
0.7500 oh Pekerja 75,000.00 56,250.00
0.0250 oh Mandor 125,000.00 3,125.00
Total : 59,375.00 59,375.00
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER
0.9000 oh Pekerja 75,000.00 67,500.00
0.0450 oh Mandor 125,000.00 5,625.00
Total : 73,125.00 73,125.00
3 1 M3 GALIAN TANAH BIASA DALAM 3 METER
1.0500 oh Pekerja 75,000.00 78,750.00
0.0670 oh Mandor 125,000.00 8,375.00
Total : 87,125.00 87,125.00
4 1 M3 GALIAN TANAH KERAS DALAM 1METER
1.0000 oh Pekerja 75,000.00 75,000.00
0.0320 oh Mandor 125,000.00 4,000.00
Total : 79,000.00 79,000.00
5 1 M3 GALIAN TANAH CADAS DALAM 1 METER
1.5000 oh Pekerja 75,000.00 112,500.00
0.0600 oh Mandor 125,000.00 7,500.00
Total : 120,000.00 120,000.00
6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER
1.2000 oh Pekerja 75,000.00 90,000.00
0.0450 oh Mandor 125,000.00 5,625.00
Total : 95,625.00 95,625.00

7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER


0.0500 oh Pekerja 75,000.00 3,750.00
0.0050 oh Mandor 125,000.00 625.00
Total : 4,375.00 4,375.00

8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER


0.3300 oh Pekerja 75,000.00 24,750.00
0.0100 oh Mandor 125,000.00 1,250.00
Total : 26,000.00 26,000.00

9 1 M3 URUGAN KEMBALI
Mengurug Kembali 1 m3 galian dihitung dari 1/3 kali dari indeks pekerjaan
galian

10 1 M3 PEMADATAN TANAH ( Per 20 Cm )


0.5000 oh Pekerja 75,000.00 37,500.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 43,750.00 43,750.00

11 1 M3 URUGAN PASIR
1.2000 m3 Pasir Urug 183,750.00 220,500.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.0100 oh Mandor 125,000.00 1,250.00
Total : 23,750.00 220,500.00 244,250.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6

12 1 M2 PEMASANGAN LAPISAN IJUK TEBAL 10 CM


6.0000 m3 Ijuk 1,980.00 11,880.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 13,125.00 11,880.00 25,005.00

13 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan


1.2000 m3 Sirtu 123,750.00 148,500.00
0.2500 oh Pekerja 75,000.00 18,750.00
0.0250 oh Mandor 125,000.00 3,125.00
Total : 21,875.00 148,500.00 170,375.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
III PEKERJAAN PONDASI (SNI 2836 : 2008)
1 1 M3 BATU BELAH CAMP. 1 PC : 3 PS
1.2000 m3 Batu Belah 15 cm / 20 cm 285,000.00 342,000.00
202.0000 kg Semen Portland 1,450.00 292,900.00
0.4850 m3 Pasir Pasang 230,000.00 111,550.00
1.5000 oh Pekerja 75,000.00 112,500.00
0.7500 oh Tukang Batu 95,000.00 71,250.00
0.0750 oh Kepala Tukang 110,000.00 8,250.00
0.0750 oh Mandor 125,000.00 9,375.00
Total : 201,375.00 746,450.00 947,825.00
2 1 M3 BATU BELAH CAMP. 1 PC : 4 PS
1.2000 m3 Batu Belah 15 cm / 20 cm 285,000.00 342,000.00
163.0000 kg Semen Portland 1,450.00 236,350.00
0.5200 m3 Pasir Pasang 230,000.00 119,600.00
1.5000 oh Pekerja 75,000.00 112,500.00
0.7500 oh Tukang Batu 95,000.00 71,250.00
0.0750 oh Kepala Tukang 110,000.00 8,250.00
0.0750 oh Mandor 125,000.00 9,375.00
Total : 201,375.00 697,950.00 899,325.00
3 1 M3 BATU BELAH CAMP. 1 PC : 5 PS
1.2000 m3 Batu Belah 15 cm / 20 cm 285,000.00 342,000.00
136.0000 kg Semen Portland 1,450.00 197,200.00
0.5440 m3 Pasir Pasang 230,000.00 125,120.00
1.5000 oh Pekerja 75,000.00 112,500.00
0.7500 oh Tukang Batu 95,000.00 71,250.00
0.0750 oh Kepala Tukang 110,000.00 8,250.00
0.0750 oh Mandor 125,000.00 9,375.00
Total : 201,375.00 664,320.00 865,695.00
4 1 M3 BATU BELAH CAMP. 1 PC : 6 PS
1.2000 m3 Batu Belah 15 cm / 20 cm 285,000.00 342,000.00
117.0000 kg Semen Portland 1,450.00 169,650.00
0.5610 m3 Pasir Pasang 230,000.00 129,030.00
1.5000 oh Pekerja 75,000.00 112,500.00
0.7500 oh Tukang Batu 95,000.00 71,250.00
0.0750 oh Kepala Tukang 110,000.00 8,250.00
0.0750 oh Mandor 125,000.00 9,375.00
Total : 201,375.00 640,680.00 842,055.00
5 1 M3 BATU BELAH CAMP. 1 PC : 8 PS
1.2000 m3 Batu Belah 15 cm / 20 cm 285,000.00 342,000.00
91.0000 kg Semen Portland 1,450.00 131,950.00
0.5840 m3 Pasir Pasang 230,000.00 134,320.00
1.5000 oh Pekerja 75,000.00 112,500.00
0.7500 oh Tukang Batu 95,000.00 71,250.00
0.0750 oh Kepala Tukang 110,000.00 8,250.00
0.0750 oh Mandor 125,000.00 9,375.00
Total : 201,375.00 608,270.00 809,645.00
6 1 M3 PASANGAN PONDASI SIKLOP, 40% BATU BELAH
0.4800 m3 Batu Belah 15 cm / 20 cm 285,000.00 136,800.00
194.0000 kg Semen Portland 1,450.00 281,300.00
0.3120 m3 Pasir Beton 210,000.00 65,520.00
0.4680 m3 Koral Beton 298,000.00 139,464.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
126.0000 kg Besi Beton 8,750.00 1,102,500.00
1.8000 kg Kawat Beton 15,400.00 27,720.00
3.4000 oh Pekerja 75,000.00 255,000.00
0.8500 oh Tukang Batu 95,000.00 80,750.00
0.0850 oh Kepala Tukang 110,000.00 9,350.00
0.1700 oh Mandor 125,000.00 21,250.00
366,350.00 1,753,304.00 2,119,654.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
7 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M
0.4500 m3 Batu Belah 15 cm / 20 cm 285,000.00 128,250.00
194.0000 kg Semen Portland 1,450.00 281,300.00
0.3120 m3 Pasir Beton 210,000.00 65,520.00
0.4680 m3 Koral Beton 298,000.00 139,464.00
2.4000 oh Pekerja 75,000.00 180,000.00
0.8000 oh Tukang Batu 95,000.00 76,000.00
0.0800 oh Kepala Tukang 110,000.00 8,800.00
0.1190 oh Mandor 125,000.00 14,875.00
Total : 279,675.00 614,534.00 894,209.00
8 1 M3 PASANGAN BATU KOSONG
1.2000 m3 Batu Belah 15 cm / 20 cm 285,000.00 342,000.00
0.4320 m3 Pasir Urug 183,750.00 79,380.00
0.7800 oh Pekerja 75,000.00 58,500.00
0.3900 oh Tukang Batu 95,000.00 37,050.00
0.0390 oh Kepala Tukang 110,000.00 4,290.00
0.0390 oh Mandor 125,000.00 4,875.00
Total : 104,715.00 421,380.00 526,095.00
9 1 M' PONDASI BORED PILE DIAMETER 30 CM
A. Pengeboran O 13/m' Bored pile
0.1550 Jam Crawler Crane -
0.1550 Jam Mesin Bor 50,000.00 7,750.00
0.1800 oh Tukang Gali 95,000.00 17,100.00
0.0090 oh Mandor 125,000.00 1,125.00
1.0000 Ls Oli + Solar 35,850.00 35,850.00
0.2200 Alat Bantu 20,000.00 4,400.00
Total A : 54,075.00 12,150.00 66,225.00
B. Beton K-300, Bored Pile
0.0707 m3 Beton K-300 1,096,156.30 77,498.25
0.4250 oh Tukang batu 95,000.00 40,375.00
0.0210 oh Mandor 285,000.00 5,985.00
1.0000 Ls Pipa Tremi dan Casing pelindung 121,000.00 121,000.00
Total B : 46,360.00 198,498.25 244,858.25
C. Pembesian 6 O 13 Beugel O 8 Spiral
7.2936 Kg Besi Ulir u23 9,375.00 68,377.50
1.5600 Kg Beugel Besi O8 12,100.00 18,876.00
Total C : - 87,253.50 87,253.50
Total A + B + C : 100,435.00 297,901.75 398,336.75
IV PEKERJAAN DINDING (SNI 6897 : 2008)
1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 2 PS
140.0000 bh Bata Merah 5 x 11 x 22 cm 2,500.00 350,000.00
43.5000 kg Semen Portland 1,450.00 63,075.00
0.0800 m3 Pasir Pasang 230,000.00 18,400.00
0.6000 oh Pekerja 75,000.00 45,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0300 oh Mandor 125,000.00 3,750.00
69,950.00 431,475.00 501,425.00
2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 PC : 3 PS
140.0000 bh Bata Merah 5 x 11 x 22 cm 2,500.00 350,000.00
32.9500 kg Semen Portland 1,450.00 47,777.50
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.0910 m3 Pasir Pasang 230,000.00 20,930.00
0.6000 oh Pekerja 75,000.00 45,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0300 oh Mandor 125,000.00 3,750.00
69,950.00 418,707.50 488,657.50
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS
70.0000 bh Bata Merah 5 x 11 x 22 cm 1,450.00 101,500.00
18.9500 kg Semen Portland 1,450.00 27,477.50
0.0380 m3 Pasir Pasang 230,000.00 8,740.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
34,975.00 137,717.50 172,692.50
2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS
70.0000 bh Bata Merah 5 x 11 x 22 cm 1,450.00 101,500.00
14.3700 kg Semen Portland 1,450.00 20,836.50
0.0400 m3 Pasir Pasang 230,000.00 9,200.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 34,975.00 131,536.50 166,511.50
3 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS
70.0000 bh Bata Merah 5 x 11 x 22 cm 1,450.00 101,500.00
9.6800 kg Semen Portland 1,450.00 14,036.00
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 34,975.00 125,886.00 160,861.00
4 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS
70.0000 bh Bata Merah 5 x 11 x 22 cm 1,450.00 101,500.00
8.3200 kg Semen Portland 1,450.00 12,064.00
0.0490 m3 Pasir Pasang 230,000.00 11,270.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 34,975.00 124,834.00 159,809.00
1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran
5
spesi 1 pc : 3 ps
12.5000 bh Batako Lubang 2,050.00 25,625.00
15.1600 kg Semen Portland 1,450.00 21,982.00
0.0364 m3 Pasir Pasang 230,000.00 8,372.00
0.2800 kg Besi Beton 8 mm 8,750.00 2,450.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 34,975.00 58,429.00 93,404.00
6 1 M2 PASANGAN DINDING BATA RINGAN
0.1000 m3 Bata Ringan 935,000.00 93,500.00
0.1000 Zak Perekat Bata ringan/ Dry mix 128,100.00 12,810.00
0.2800 kg Besi Beton 8 mm 99,000.00 27,720.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 34,975.00 134,030.00 169,005.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
7 1 M2 PAS. DINDING Terawang/Roster (12 x 11 x 24) CM camp 1 Pc : 3 Ps
30.0000 bh Roster Keramik 46,200.00 1,386,000.00
14.0000 kg Semen Portland 1,450.00 20,300.00
0.0320 m3 Pasir Pasang 230,000.00 7,360.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 34,975.00 1,413,660.00 1,448,635.00
V PEKERJAAN PLESTERAN (SNI 2837 : 2008)
1 1 M2 PLESTERAN CAMP. 1 PC : 1 PS TEBAL 15 MM
15.5040 kg Semen Portland 1,450.00 22,480.80
0.0160 m3 Pasir Pasang 230,000.00 3,680.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 26,160.80 66,435.80
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM
10.2240 kg Semen Portland 1,450.00 14,824.80
0.0200 m3 Pasir Pasang 230,000.00 4,600.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 19,424.80 59,699.80
3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM
7.7760 kg Semen Portland 1,450.00 11,275.20
0.0230 m3 Pasir Pasang 230,000.00 5,290.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 16,565.20 56,840.20
4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM
6.2400 kg Semen Portland 1,450.00 9,048.00
0.0240 m3 Pasir Pasang 230,000.00 5,520.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 14,568.00 54,843.00
4 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM
5.1840 kg Semen Portland 1,450.00 7,516.80
0.0260 m3 Pasir Pasang 230,000.00 5,980.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 13,496.80 53,771.80
5 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
4.4160 kg Semen Portland 1,450.00 6,403.20
0.0270 m3 Pasir Pasang 230,000.00 6,210.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 12,613.20 52,888.20
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
6 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM
3.4560 kg Semen Portland 1,450.00 5,011.20
0.0290 m3 Pasir Pasang 230,000.00 6,670.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 11,681.20 51,956.20
7 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 20 MM
13.6320 kg Semen Portland 1,450.00 19,766.40
0.0270 m3 Pasir Pasang 230,000.00 6,210.00
0.4000 oh Pekerja 75,000.00 30,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0220 oh Mandor 125,000.00 2,750.00
Total : 53,950.00 25,976.40 79,926.40
8 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM
10.3680 kg Semen Portland 1,450.00 15,033.60
0.0310 m3 Pasir Pasang 230,000.00 7,130.00
0.4000 oh Pekerja 75,000.00 30,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0130 oh Mandor 125,000.00 1,625.00
Total : 52,825.00 22,163.60 74,988.60
9 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM
6.9120 kg Semen Portland 1,450.00 10,022.40
0.0350 m3 Pasir Pasang 230,000.00 8,050.00
0.4000 oh Pekerja 75,000.00 30,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0220 oh Mandor 125,000.00 2,750.00
Total : 53,950.00 18,072.40 72,022.40
10 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM
5.8880 kg Semen Portland 1,450.00 8,537.60
0.0360 m3 Pasir Pasang 230,000.00 8,280.00
0.4000 oh Pekerja 75,000.00 30,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0220 oh Mandor 125,000.00 2,750.00
Total : 53,950.00 16,817.60 70,767.60
11 1 M2 PLESTERAN SKONING 1 PC : 2 PS, TEBAL 10 MM
0.5000 kg Semen Portland 1,450.00 725.00
0.0130 m3 Pasir Pasang 230,000.00 2,990.00
0.0800 oh Pekerja 75,000.00 6,000.00
0.4000 oh Tukang Batu 95,000.00 38,000.00
0.0400 oh Kepala Tukang 110,000.00 4,400.00
0.0040 oh Mandor 125,000.00 500.00
Total : 48,900.00 3,715.00 52,615.00
12 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS
4.3200 kg Semen Portland 1,450.00 6,264.00
0.0060 m3 Pasir Pasang 230,000.00 1,380.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.3000 oh Pekerja 75,000.00 22,500.00
0.1000 oh Tukang Batu 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 34,975.00 7,644.00 42,619.00
13 1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH
3.1080 kg Semen Portland 1,450.00 4,506.60
0.1500 oh Pekerja 75,000.00 11,250.00
0.0750 oh Tukang Batu 95,000.00 7,125.00
0.0080 oh Kepala Tukang 110,000.00 880.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 20,255.00 4,506.60 24,761.60
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
14 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE
1.6000 kg Semen Portland 1,450.00 2,320.00
0.0700 oh Pekerja 75,000.00 5,250.00
0.0350 oh Tukang Batu 95,000.00 3,325.00
0.0040 oh Kepala Tukang 110,000.00 440.00
0.0040 oh Mandor 125,000.00 500.00
Total : 9,515.00 2,320.00 11,835.00
15 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS
6.3400 kg Semen Portland 1,450.00 9,193.00
0.0120 m3 Pasir Pasang 230,000.00 2,760.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.1500 oh Tukang Batu 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 40,275.00 11,953.00 52,228.00
16 1 M2 PLESTERAN MENGGUNAKAN SEMEN MU - 301, TEBAL 10 MM
20.0000 kg Semen MU-301 2,163.00 43,260.00
0.4000 oh Pekerja 75,000.00 30,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0220 oh Mandor 125,000.00 2,750.00
Total : 53,950.00 43,260.00 97,210.00
17 1 M2 ACIAN MENGGUNAKAN SEMEN MU - 200,TEBAL 1,5MM
3.5000 kg Semen MU-200 3,428.25 11,998.88
0.4000 oh Pekerja 75,000.00 30,000.00
0.2000 oh Tukang Batu 95,000.00 19,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0220 oh Mandor 125,000.00 2,750.00
Total : 53,950.00 11,998.88 65,948.88
18 1 M2 PEKERJAAN ACIAN
3.2500 zak Semen Portland 50 Kg 1,450.00 4,712.50
0.2000 oh Pekerja 75,000.00 15,000.00
0.1000 oh Tukang Labur/Cat 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0100 oh Mandor 125,000.00 1,250.00
Total : 26,850.00 4,712.50 31,562.50
VI PEKERJAAN KAYU (SNI 3434 : 2008)
MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU
1
KELAS I
1.1000 m3 Balok Kayu Jati 31,500,000.00 34,650,000.00
1.2500 Kg Paku 10 Cm 17,297.78 21,622.22
1.0000 Kg Lem Kayu 18,900.00 18,900.00
7.0000 oh Pekerja 75,000.00 525,000.00
21.0000 oh Tukang Kayu 105,000.00 2,205,000.00
2.1000 oh Kepala Tukang 110,000.00 231,000.00
0.3500 oh Mandor 125,000.00 43,750.00
Total : 3,004,750.00 34,690,522.22 37,695,272.22
MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU
2
KELAS III
1.2000 m3 Balok Kayu kruing 6,300,000.00 7,560,000.00
1.2500 Kg Paku 10 Cm 17,297.78 21,622.22
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
1.0000 Kg Lem Kayu 18,900.00 18,900.00
6.0000 oh Pekerja 75,000.00 450,000.00
18.0000 oh Tukang Kayu 105,000.00 1,890,000.00
1.8000 oh Kepala Tukang 110,000.00 198,000.00
0.3000 oh Mandor 125,000.00 37,500.00
Total : 2,575,500.00 7,600,522.22 10,176,022.22
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II
0.0400 m3 Papan Kayu Kamper 9,975,000.00 399,000.00
0.0500 Kg Paku 5-7 Cm 17,297.78 864.89
0.3500 oh Pekerja 75,000.00 26,250.00
1.0500 oh Tukang Kayu 105,000.00 110,250.00
0.1050 oh Kepala Tukang 110,000.00 11,550.00
0.0180 oh Mandor 125,000.00 2,250.00
Total : 150,300.00 399,864.89 550,164.89
MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS
4
III
0.0400 m3 Papan Kayu Kruing 7,875,000.00 315,000.00
0.0500 Kg Paku 5-7 Cm 17,297.78 864.89
0.3500 oh Pekerja 75,000.00 26,250.00
1.0500 oh Tukang Kayu 105,000.00 110,250.00
0.1050 oh Kepala Tukang 110,000.00 11,550.00
0.0180 oh Mandor 125,000.00 2,250.00
Total : 150,300.00 315,864.89 466,164.89
5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II
0.0400 m3 Papan Kayu Kamper 9,975,000.00 399,000.00
0.5000 Kg Lem Kayu 18,900.00 9,450.00
1.0000 oh Pekerja 75,000.00 75,000.00
3.0000 oh Tukang Kayu 105,000.00 315,000.00
0.3000 oh Kepala Tukang 110,000.00 33,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 429,250.00 408,450.00 837,700.00
MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS
6
II
0.0240 m3 Papan Kayu Kamper 9,975,000.00 239,400.00
0.3000 Kg Lem Kayu 18,900.00 5,670.00
0.8000 oh Pekerja 75,000.00 60,000.00
2.4000 oh Tukang Kayu 105,000.00 252,000.00
0.2400 oh Kepala Tukang 110,000.00 26,400.00
0.0400 oh Mandor 125,000.00 5,000.00
Total : 343,400.00 245,070.00 588,470.00
MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU
7
KELAS II
0.0640 m3 Papan Kayu Kamper 9,975,000.00 638,400.00
0.5000 Kg Lem Kayu 18,900.00 9,450.00
1.0000 oh Pekerja 75,000.00 75,000.00
3.0000 oh Tukang Kayu 105,000.00 315,000.00
0.3000 oh Kepala Tukang 110,000.00 33,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 429,250.00 647,850.00 1,077,100.00
MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP,
8
KAYU KELAS II (Lebar Sampai 90 Cm)
0.0250 m3 Papan Kayu Kamper 9,975,000.00 249,375.00
0.0300 Kg Paku 1-2,5 Cm 17,297.78 518.93
0.5000 Kg Lem Kayu 18,900.00 9,450.00
1.0000 Lbr Plywood 4 mm 69,575.00 69,575.00
0.7000 oh Pekerja 75,000.00 52,500.00
2.1000 oh Tukang Kayu 105,000.00 220,500.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.2100 oh Kepala Tukang 110,000.00 23,100.00
0.0350 oh Mandor 125,000.00 4,375.00
Total : 300,475.00 328,918.93 629,393.93
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU
9
KELAS II
0.0256 m3 Papan Kayu Kamper 9,975,000.00 255,360.00
0.0300 Kg Paku 1-2,5 Cm 17,297.78 518.93
0.5000 Kg Lem Kayu 18,900.00 9,450.00
1.0000 Lbr Plywood 4 mm 69,575.00 69,575.00
0.8000 oh Pekerja 75,000.00 60,000.00
2.4000 oh Tukang Kayu 105,000.00 252,000.00
0.2400 oh Kepala Tukang 110,000.00 26,400.00
0.0400 oh Mandor 125,000.00 5,000.00
Total : 343,400.00 334,903.93 678,303.93
10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS II
0.0600 m3 Papan Kayu Kamper 9,975,000.00 598,500.00
0.1500 Kg Paku 1-2,5 Cm 17,297.78 2,594.67
0.6700 oh Pekerja 75,000.00 50,250.00
2.0000 oh Tukang Kayu 105,000.00 210,000.00
0.2000 oh Kepala Tukang 110,000.00 22,000.00
0.3350 oh Mandor 125,000.00 41,875.00
Total : 324,125.00 601,094.67 925,219.67
11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I
0.0250 m3 Papan Kayu Jati 36,750,000.00 918,750.00
0.0300 Kg Paku 1-2,5 Cm 17,297.78 518.93
0.3000 Kg Lem Kayu 18,900.00 5,670.00
1.0000 Lbr Teakwood 4 mm uk 90x220 cm 84,700.00 84,700.00
0.8000 oh Pekerja 75,000.00 60,000.00
2.4000 oh Tukang Kayu 105,000.00 252,000.00
0.2400 oh Kepala Tukang 110,000.00 26,400.00
0.0400 oh Mandor 125,000.00 5,000.00
Total : 343,400.00 1,009,638.93 1,353,038.93
MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE,
12
KAYU KELAS II
0.0250 m3 Papan Kayu Kamper 36,750,000.00 918,750.00
0.0300 Kg Paku 1-2,5 Cm 17,297.78 518.93
0.8000 Kg Lem Kayu 18,900.00 15,120.00
1.0000 Lbr Teakwood 4 mm uk 90x220 cm 84,700.00 84,700.00
0.5000 Lbr Formika 84,700.00 42,350.00
0.8500 oh Pekerja 75,000.00 63,750.00
2.5500 oh Tukang Kayu 105,000.00 267,750.00
0.2550 oh Kepala Tukang 110,000.00 28,050.00
0.0430 oh Mandor 125,000.00 5,375.00
Total : 364,925.00 1,061,438.93 1,426,363.93
MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS
13
II Bentang 6 M'
1.1000 m3 Balok Kayu Kamper 8,925,000.00 9,817,500.00
15.0000 Kg Besi Strip Tebal 5 cm 11,960.00 179,400.00
5.6000 Kg Paku 12 Cm 17,297.78 96,867.56
4.0000 oh Pekerja 75,000.00 300,000.00
12.0000 oh Tukang Kayu 105,000.00 1,260,000.00
1.2000 oh Kepala Tukang 110,000.00 132,000.00
0.2000 oh Mandor 125,000.00 25,000.00
Total : 1,717,000.00 10,093,767.56 11,810,767.56
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I
1.2000 m3 Balok Kayu Jati 31,500,000.00 37,800,000.00
15.0000 Kg Besi Strip Tebal 5 cm 11,960.00 179,400.00
5.6000 Kg Paku 12 Cm 17,297.78 96,867.56
6.7000 oh Pekerja 75,000.00 502,500.00
20.1000 oh Tukang Kayu 105,000.00 2,110,500.00
2.0100 oh Kepala Tukang 110,000.00 221,100.00
0.3350 oh Mandor 125,000.00 41,875.00
Total : 2,875,975.00 38,076,267.56 40,952,242.56
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II
1.1000 m3 Balok Kayu Kamper 8,925,000.00 9,817,500.00
15.0000 Kg Besi Strip Tebal 5 cm 11,960.00 179,400.00
3.0000 Kg Paku 12 Cm 17,297.78 51,893.33
2.4000 oh Pekerja 75,000.00 180,000.00
7.2000 oh Tukang Kayu 105,000.00 756,000.00
0.7200 oh Kepala Tukang 110,000.00 79,200.00
0.1200 oh Mandor 125,000.00 15,000.00
Total : 1,030,200.00 10,048,793.33 11,078,993.33
16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II
0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 6,300,000.00 88,200.00
0.0036 m3 Reng ( 2 x 3 ) Cm 7,875,000.00 28,350.00
0.2500 Kg Paku 5 Cm dan 10 Cm 17,297.78 4,324.44
0.1000 oh Pekerja 75,000.00 7,500.00
0.1000 oh Tukang Kayu 105,000.00 10,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 19,725.00 120,874.44 140,599.44
17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II
0.0140 m3 Kaso-Kaso ( 5 x 7 ) Cm 6,300,000.00 88,200.00
0.0072 m3 Reng ( 2 x 3 ) Cm 7,875,000.00 56,700.00
0.2500 Kg Paku 5 Cm dan 10 Cm 17,297.78 4,324.44
0.1000 oh Pekerja 75,000.00 7,500.00
0.1000 oh Tukang Kayu 105,000.00 10,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 19,725.00 149,224.44 168,949.44
18 MEMASANG 1 M2 USUK EXPOSE KAYU KLS I KAMPER
0.0105 m3 Usuk ( 5 x 7 ) Cm 7,875,000.00 82,687.50
0.2500 Kg Paku 5 Cm dan 10 Cm 17,297.78 4,324.44
0.1000 oh Pekerja 75,000.00 7,500.00
0.1000 oh Tukang Kayu 105,000.00 10,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 19,725.00 87,011.94 106,736.94
19 MEMASANG 1 M2 RENG KAYU KLS I KAMPER
0.0036 m3 Reng ( 2 x 3 ) Cm 7,875,000.00 28,350.00
0.2500 Kg Paku 5 Cm dan 10 Cm 17,297.78 4,324.44
0.1000 oh Pekerja 75,000.00 7,500.00
0.1000 oh Tukang Kayu 105,000.00 10,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 19,725.00 32,674.44 52,399.44
20 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II
0.1650 m3 Balok Kayu Kamper 8,925,000.00 1,472,625.00
0.2000 Kg Paku 5 Cm dan 10 Cm 17,297.78 3,459.56
0.1200 oh Pekerja 75,000.00 9,000.00
0.1200 oh Tukang Kayu 105,000.00 12,600.00
0.0120 oh Kepala Tukang 110,000.00 1,320.00
0.0060 oh Mandor 125,000.00 750.00
Total : 23,670.00 1,476,084.56 1,499,754.56
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
21 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II
0.0154 m3 Kaso-Kaso ( 5 x 7 ) Cm 6,300,000.00 97,020.00
0.2000 Kg Paku 7 Cm dan 10 Cm 17,297.78 3,459.56
0.1500 oh Pekerja 75,000.00 11,250.00
0.3000 oh Tukang Kayu 105,000.00 31,500.00
0.0300 oh Kepala Tukang 110,000.00 3,300.00
0.0750 oh Mandor 125,000.00 9,375.00
Total : 55,425.00 100,479.56 155,904.56
22 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II
0.0163 m3 Kaso-Kaso ( 5 x 7 ) Cm 6,300,000.00 102,690.00
0.2500 Kg Paku 7 Cm dan 10 Cm 17,297.78 4,324.44
0.2000 oh Pekerja 75,000.00 15,000.00
0.3000 oh Tukang Kayu 105,000.00 31,500.00
0.0300 oh Kepala Tukang 110,000.00 3,300.00
0.0100 oh Mandor 125,000.00 1,250.00
Total : 51,050.00 107,014.44 158,064.44
23 MEMASANG 1 M' LISPLANK UKURAN (3 X 20) CM, KAYU KELAS II
0.0108 m3 Papan Kayu Kamper 9,975,000.00 107,730.00
0.1000 Kg Paku 5 Cm dan 7 Cm 17,297.78 1,729.78
0.1000 oh Pekerja 75,000.00 7,500.00
0.2000 oh Tukang Kayu 105,000.00 21,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0050 oh Mandor 125,000.00 625.00
Total : 31,325.00 109,459.78 140,784.78
24 MEMASANG 1 M' LISPLANK UKURAN (3 X 30) CM, KAYU KELAS II
0.0110 m3 Papan Kayu Kamper 9,975,000.00 109,725.00
0.0500 Kg Paku 5 Cm dan 7 Cm 17,297.78 864.89
0.1000 oh Pekerja 75,000.00 7,500.00
0.2000 oh Tukang Kayu 105,000.00 21,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0050 oh Mandor 125,000.00 625.00
Total : 31,325.00 110,589.89 141,914.89
MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS
25
II
0.0280 m3 Balok Kayu Kamper 8,925,000.00 249,900.00
0.1500 Kg Paku 5 Cm dan 7 Cm 17,297.78 2,594.67
0.1500 oh Pekerja 75,000.00 11,250.00
0.4500 oh Tukang Kayu 105,000.00 47,250.00
0.0450 oh Kepala Tukang 110,000.00 4,950.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 64,450.00 252,494.67 316,944.67
MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP,
26
RANGKA KAYU KELAS II
0.0280 m3 Balok Kayu Kamper 8,925,000.00 249,900.00
0.1500 Kg Paku 5 Cm dan 7 Cm 17,297.78 2,594.67
0.8600 Lbr Teakwood 4 mm uk 90x220 cm 84,700.00 72,842.00
0.5600 Kg Lem Kayu 18,900.00 10,584.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.4500 oh Tukang Kayu 105,000.00 47,250.00
0.0450 oh Kepala Tukang 110,000.00 4,950.00
0.0080 oh Mandor 125,000.00 1,000.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
Total : 64,450.00 335,920.67 400,370.67
MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP,
27
RANGKA KAYU KELAS II
0.0280 m3 Balok Kayu Kamper 8,925,000.00 249,900.00
0.1500 Kg Paku 5 Cm dan 7 Cm 17,297.78 2,594.67
0.8600 Lbr Plywood tebal 4 mm uk 120 x 240 cm 69,575.00 59,834.50
0.5600 Kg Lem Kayu 18,900.00 10,584.00
0.2000 oh Pekerja 75,000.00 15,000.00
0.6000 oh Tukang Kayu 105,000.00 63,000.00
0.0600 oh Kepala Tukang 110,000.00 6,600.00
0.0100 oh Mandor 125,000.00 1,250.00
Total : 85,850.00 322,913.17 408,763.17
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP,
28
RANGKA HOLO
1.5000 Btg Rangka Holo 22,000.00 33,000.00
0.1500 Kg Paku 5 Cm dan 7 Cm 17,297.78 2,594.67
0.8600 Lbr Teakwood 4 mm uk 90x220 cm 84,700.00 72,842.00
0.5600 Kg Lem Kayu 18,900.00 10,584.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.4500 oh Tukang Kayu 105,000.00 47,250.00
0.0450 oh Kepala Tukang 110,000.00 4,950.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 64,450.00 119,020.67 183,470.67
MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP,
29
RANGKA HOLO
1.5000 Btg Rangka Holo 22,000.00 33,000.00
0.1500 Kg Paku 5 Cm dan 7 Cm 17,297.78 2,594.67
0.8600 Lbr Plywood tebal 4 mm uk 120 x 240 cm 69,575.00 59,834.50
0.5600 Kg Lem Kayu 18,900.00 10,584.00
0.2000 oh Pekerja 75,000.00 15,000.00
0.6000 oh Tukang Kayu 105,000.00 63,000.00
0.0600 oh Kepala Tukang 110,000.00 6,600.00
0.0100 oh Mandor 125,000.00 1,250.00
Total : 85,850.00 106,013.17 191,863.17
30 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I
0.0070 m3 Papan Kayu Kamper 9,975,000.00 69,825.00
0.1000 Kg Paku 5 Cm dan 10 Cm 17,297.78 1,729.78
0.1500 Kg Paku Skrup 10 cm 17,297.78 2,594.67
0.6000 oh Pekerja 75,000.00 45,000.00
1.8000 oh Tukang Kayu 105,000.00 189,000.00
0.1800 oh Kepala Tukang 110,000.00 19,800.00
0.0300 oh Mandor 125,000.00 3,750.00
Total : 257,550.00 74,149.44 331,699.44
MEMASANG 1 M2 LAMBRIZIRING DARI CONWOOD UKURAN (100 x 3050 x
31
11 mm)
4.0000 Lbr Conwood Lath 4" Cut (100 x 3050 x 11 mm) 61,100.00 244,400.00
0.0500 Kg Paku 1 Cm dan 2.5 Cm 69,575.00 3,478.75
0.0250 oh Pekerja 75,000.00 1,875.00
0.0750 oh Tukang Kayu 105,000.00 7,875.00
0.0080 oh Kepala Tukang 110,000.00 880.00
0.0010 oh Mandor 125,000.00 125.00
Total : 10,755.00 247,878.75 258,633.75
32 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM
0.4000 Lbr Plywood tebal 4 mm uk 120 x 240 cm 69,575.00 27,830.00
0.0500 Kg Paku 1 Cm dan 2.5 Cm 15,271.67 763.58
0.0250 oh Pekerja 75,000.00 1,875.00
0.0750 oh Tukang Kayu 105,000.00 7,875.00
0.0080 oh Kepala Tukang 110,000.00 880.00
0.0010 oh Mandor 125,000.00 125.00
Total : 10,755.00 28,593.58 39,348.58
VII PEKERJAAN BETON ( SNI 7394:2008)
MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c =
1
0,87
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
247.0000 kg Semen Portland 1,450.00 358,150.00
0.6207 m3 Pasir Beton 210,000.00 130,350.00
0.7400 m3 Koral Beton 298,000.00 220,520.00
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
163,330.00 715,470.00 878,800.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c =
2
0,78
276.0000 kg Semen Portland 1,450.00 400,200.00
0.5914 m3 Pasir Beton 210,000.00 124,200.00
0.7496 m3 Koral Beton 298,000.00 223,389.63
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 754,239.63 917,569.63
MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c =
3
0,72
299.0000 kg Semen Portland 1,450.00 433,550.00
0.5707 m3 Pasir Beton 210,000.00 119,850.00
0.7533 m3 Koral Beton 298,000.00 224,493.33
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 784,343.33 947,673.33
MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c =
4
0,66
326.0000 kg Semen Portland 1,450.00 472,700.00
0.5429 m3 Pasir Beton 210,000.00 114,000.00
0.7622 m3 Koral Beton 298,000.00 227,142.22
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 820,292.22 983,622.22
MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c =
5
0,61
352.0000 kg Semen Portland 1,450.00 510,400.00
0.5221 m3 Pasir Beton 210,000.00 109,650.00
0.7637 m3 Koral Beton 298,000.00 227,583.70
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 854,083.70 1,017,413.70
MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c =
6
0,58
371.0000 kg Semen Portland 1,450.00 537,950.00
0.4986 m3 Pasir Beton 210,000.00 104,700.00
0.7756 m3 Koral Beton 298,000.00 231,115.56
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 880,215.56 1,043,545.56
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c
7
=0,56
384.0000 kg Semen Portland 1,450.00 556,800.00
0.4943 m3 Pasir Beton 210,000.00 103,800.00
0.7696 m3 Koral Beton 298,000.00 229,349.63
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 896,399.63 1,059,729.63
MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c
8
=0,53
406.0000 kg Semen Portland 1,450.00 588,700.00
0.4886 m3 Pasir Beton 210,000.00 102,600.00
0.7600 m3 Koral Beton 298,000.00 226,480.00
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 924,230.00 1,087,560.00
MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c
9
=0,52
413.0000 kg Semen Portland 1,450.00 598,850.00
0.4864 m3 Pasir Beton 210,000.00 102,150.00
0.7563 m3 Koral Beton 298,000.00 225,376.30
215.0000 lt Air 30.00 6,450.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2750 oh Tukang Batu 95,000.00 26,125.00
0.0280 oh Kepala Tukang 110,000.00 3,080.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 163,330.00 932,826.30 1,096,156.30
MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c
10
=0,49
439.0000 kg Semen Portland 1,450.00 636,550.00
0.4786 m3 Pasir Beton 210,000.00 100,500.00
0.7452 m3 Koral Beton 298,000.00 222,065.19
215.0000 lt Air 30.00 6,450.00
2.1000 oh Pekerja 75,000.00 157,500.00
0.3500 oh Tukang Batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.1050 oh Mandor 125,000.00 13,125.00
Total : 207,725.00 965,565.19 1,173,290.19
MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c
11
=0,48
448.0000 kg Semen Portland 1,450.00 649,600.00
0.4764 m3 Pasir Beton 210,000.00 100,050.00
0.7407 m3 Koral Beton 298,000.00 220,740.74
215.0000 lt Air 30.00 6,450.00
2.1000 oh Pekerja 75,000.00 157,500.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.3500 oh Tukang Batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.1050 oh Mandor 125,000.00 13,125.00
Total : 207,725.00 976,840.74 1,184,565.74
12 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR
10.5000 kg Besi Beton (Polos/ Ulir) 8,750.00 91,875.00
0.1500 kg Kawat Beton 15,400.00 2,310.00
0.0700 oh Pekerja 75,000.00 5,250.00
0.0700 oh Tukang Besi 100,000.00 7,000.00
0.0070 oh Kepala Tukang 110,000.00 770.00
0.0040 oh Mandor 125,000.00 500.00
Total : 13,520.00 94,185.00 107,705.00
Total Untuk 1 Kg : 10,770.50
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
13 1 M2 PEMBESIAN DENGAN WIRE MESH M6
0.1000 lbr Besi Wire mesh M6 225,333.33 22,533.33
0.1500 kg Kawat Beton 15,400.00 2,310.00
0.0700 oh Pekerja 75,000.00 5,250.00
0.0700 oh Tukang Besi 100,000.00 7,000.00
0.0070 oh Kepala Tukang 110,000.00 770.00
0.0040 oh Mandor 125,000.00 500.00
Total : 13,520.00 24,843.33 38,363.33
14 1 M2 PEMBESIAN DENGAN WIRE MESH M7
0.1000 lbr Besi Wire mesh M7 308,000.00 30,800.00
0.1500 kg Kawat Beton 15,400.00 2,310.00
0.0700 oh Pekerja 75,000.00 5,250.00
0.0700 oh Tukang Besi 100,000.00 7,000.00
0.0070 oh Kepala Tukang 110,000.00 770.00
0.0040 oh Mandor 125,000.00 500.00
Total : 13,520.00 33,110.00 46,630.00
15 1 M2 PEMBESIAN DENGAN WIRE MESH M8
0.1000 lbr Besi Wire mesh M8 424,600.00 42,460.00
0.1500 kg Kawat Beton 15,400.00 2,310.00
0.0700 oh Pekerja 75,000.00 5,250.00
0.0700 oh Tukang Besi 100,000.00 7,000.00
0.0070 oh Kepala Tukang 110,000.00 770.00
0.0040 oh Mandor 125,000.00 500.00
Total : 13,520.00 44,770.00 58,290.00
16 Beton Readymix K-175 836,000.00
17 Beton Readymix K-225 880,000.00
18 Beton Readymix K-250 896,500.00
19 Beton Readymix K-275 918,500.00
20 Beton Readymix K-300 940,500.00
21 Beton Readymix K-350 990,000.00
22 Sewa concrete pump/m3 30,000.00
23 1 M2 PASANG BEKISTING UNTUK PONDASI
0.0400 m3 Kayu Kelas III 2,985,675.00 119,427.00
0.3000 kg Paku Biasa 5' - 10' 17,297.78 5,189.33
0.1000 ltr Minyak Bekisting 38,325.00 3,832.50
0.5200 oh Pekerja 75,000.00 39,000.00
0.2600 oh Tukang Kayu 105,000.00 27,300.00
0.0260 oh Kepala Tukang 110,000.00 2,860.00
0.0260 oh Mandor 125,000.00 3,250.00
Total : 72,410.00 128,448.83 200,858.83
24 1 M2 PASANG BEKISTING UNTUK SLOOF
0.0450 m3 Kayu Kelas III 2,985,675.00 134,355.38
0.3000 kg Paku Biasa 5' - 10' 17,297.78 5,189.33
0.1000 ltr Minyak Bekisting 38,325.00 3,832.50
0.0150 m3 Kayu Usuk 4/6 6,300,000.00 94,500.00
0.3500 lbr Plywood 9 mm 148,500.00 51,975.00
0.5200 oh Pekerja 75,000.00 39,000.00
0.2600 oh Tukang Kayu 105,000.00 27,300.00
0.0260 oh Kepala Tukang 110,000.00 2,860.00
0.0260 oh Mandor 125,000.00 3,250.00
Total : 72,410.00 289,852.21 362,262.21
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
25 1 M2 PASANG BEKISTING UNTUK KOLOM
0.0400 m3 Kayu Kelas III 2,985,675.00 119,427.00
0.4000 kg Paku Biasa 5' - 12' 17,297.78 6,919.11
0.2000 ltr Minyak Bekisting 38,325.00 7,665.00
0.0150 m3 Kayu Usuk 4/6 6,300,000.00 94,500.00
0.3500 lbr Plywood 9 mm 148,500.00 51,975.00
2.0000 btg Dolken Kayu 8" - 10"/4 m / Bambu Besar Ukuran 4 m 10,500.00 21,000.00
0.6600 oh Pekerja 75,000.00 49,500.00
0.3300 oh Tukang Kayu 105,000.00 34,650.00
0.0330 oh Kepala Tukang 110,000.00 3,630.00
0.0330 oh Mandor 125,000.00 4,125.00
Total : 91,905.00 301,486.11 393,391.11
26 1 M2 PASANG BEKISTING UNTUK BALOK
0.0400 m3 Kayu Kelas III 2,985,675.00 119,427.00
0.4000 kg Paku Biasa 5' - 12' 17,297.78 6,919.11
0.2000 ltr Minyak Bekisting 38,325.00 7,665.00
0.0180 m3 Kayu Usuk 4/6 6,300,000.00 113,400.00
0.3500 lbr Plywood 9 mm 148,500.00 51,975.00
2.0000 btg Dolken Kayu 8" - 10"/4 m / Bambu Besar Ukuran 4 m 10,500.00 21,000.00
0.6600 oh Pekerja 75,000.00 49,500.00
0.3300 oh Tukang Kayu 105,000.00 34,650.00
0.0330 oh Kepala Tukang 110,000.00 3,630.00
0.0330 oh Mandor 125,000.00 4,125.00
Total : 91,905.00 320,386.11 412,291.11
27 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI
0.0400 m3 Kayu Kelas III 2,985,675.00 119,427.00
0.4000 kg Paku Biasa 5' - 12' 17,297.78 6,919.11
0.2000 ltr Minyak Bekisting 38,325.00 7,665.00
0.0150 m3 Kayu Usuk 4/6 6,300,000.00 94,500.00
0.3500 lbr Plywood 9 mm 148,500.00 51,975.00
6.0000 btg Dolken Kayu 8" - 10"/4 m / Bambu Besar Ukuran 4 m 10,500.00 63,000.00
0.6600 oh Pekerja 75,000.00 49,500.00
0.3300 oh Tukang Kayu 105,000.00 34,650.00
0.0330 oh Kepala Tukang 110,000.00 3,630.00
0.0330 oh Mandor 125,000.00 4,125.00
Total : 91,905.00 343,486.11 435,391.11
28 1 M2 PASANG BEKISTING UNTUK DINDING
0.0300 M3 Kayu Kelas III 2,985,675.00 89,570.25
0.4000 Kg Paku Biasa 5' - 12' 17,297.78 6,919.11
0.2000 Ltr Minyak Bekisting 38,325.00 7,665.00
0.0200 M3 Kayu Usuk 4/6 6,300,000.00 126,000.00
0.3500 Lbr Plywood 9 mm 148,500.00 51,975.00
3.0000 Btng Dolken Kayu 8" - 10"/4 m / Bambu Besar Ukuran 4 m 10,500.00 31,500.00
4.0000 Bh Formite/penjaga jarak bekisting/spacer 2,000.00 8,000.00
0.6600 Oh Pekerja 75,000.00 49,500.00
0.3300 Oh Tukang Kayu 105,000.00 34,650.00
0.0330 Oh Kepala Tukang 110,000.00 3,630.00
0.0330 Oh Mandor 125,000.00 4,125.00
91,905.00 321,629.36 413,534.36
29 1 M2 PASANG BEKISTING UNTUK TANGGA
0.0300 m3 Kayu Kelas III 2,985,675.00 89,570.25
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.4000 kg Paku Biasa 5' - 12' 17,297.78 6,919.11
0.1500 ltr Minyak Bekisting 38,325.00 5,748.75
0.0150 m3 Kayu Usuk 4/6 6,300,000.00 94,500.00
0.3500 lbr Plywood 9 mm 148,500.00 51,975.00
2.0000 btg Dolken Kayu 8" - 10"/4 m / Bambu Besar Ukuran 4 m 10,500.00 21,000.00
0.6600 oh Pekerja 75,000.00 49,500.00
0.3300 oh Tukang Kayu 105,000.00 34,650.00
0.0330 oh Kepala Tukang 110,000.00 3,630.00
0.0330 oh Mandor 125,000.00 4,125.00
Total : 91,905.00 269,713.11 361,618.11
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
30 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON
0.0264 m3 Kayu Kelas III (Papan) 2,985,675.00 78,821.82
0.6000 kg Paku Biasa 5' - 12' 17,297.78 10,378.67
0.5000 btg Dolken Kayu 8" - 10"/4 m / Bambu Besar Ukuran 4 m 10,500.00 5,250.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.0500 oh Tukang Kayu 105,000.00 5,250.00
0.0050 oh Kepala Tukang 110,000.00 550.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 18,050.00 94,450.49 112,500.49
31 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM)
0.0020 m3 Kayu Kelas III 2,985,675.00 5,971.35
0.0100 kg Paku Biasa 5' - 12' 17,297.78 172.98
3.0000 kg Besi Beton 10,770.50 32,311.50
0.0450 kg Kawat Beton 15,400.00 693.00
4.0000 kg Semen Portland 1,450.00 5,800.00
0.0060 m3 Pasir Beton 210,000.00 1,260.00
0.0090 m3 Koral Beton 298,000.00 2,682.00
0.1800 oh Pekerja 75,000.00 13,500.00
0.0200 oh Tukang Batu 95,000.00 1,900.00
0.0200 oh Tukang Kayu 105,000.00 2,100.00
0.0200 oh Tukang Besi 100,000.00 2,000.00
0.0060 oh Kepala Tukang 110,000.00 660.00
0.0090 oh Mandor 125,000.00 1,125.00
Total : 21,285.00 48,890.83 70,175.83
30 MEMBUAT 1 M³ BETON TUMBUK (1 PC : 3 PS : 5 KR)
218.0000 kg Semen Portland 1,450.00 316,100.00
0.5200 m3 Pasir Beton 210,000.00 109,200.00
0.8700 m3 Koral Beton 298,000.00 259,260.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2500 oh Tukang Batu 95,000.00 23,750.00
0.0250 oh Kepala Tukang 110,000.00 2,750.00
0.0800 oh Mandor 125,000.00 10,000.00
Total : 160,250.00 684,560.00 844,810.00
31 MEMBUAT 1 M³ BETON CAMPURAN (1 PC : 2 PS : 3 KR)
232.0000 kg Semen Portland 1,450.00 336,400.00
0.5200 m3 Pasir Beton 210,000.00 109,200.00
0.7800 m3 Koral Beton 298,000.00 232,440.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2500 oh Tukang Batu 95,000.00 23,750.00
0.0250 oh Kepala Tukang 110,000.00 2,750.00
0.0800 oh Mandor 125,000.00 10,000.00
Total : 160,250.00 678,040.00 838,290.00
32 MEMBUAT 1 M³ BETON BERTULANG CAMPURAN (1 PC : 1,5 PS : 2,5 KR)
386.0000 kg Semen Portland 1,450.00 559,700.00
0.4700 m3 Pasir Beton 210,000.00 98,700.00
0.7800 m3 Koral Beton 298,000.00 232,440.00
1.6500 oh Pekerja 75,000.00 123,750.00
0.2500 oh Tukang Batu 95,000.00 23,750.00
0.0250 oh Kepala Tukang 110,000.00 2,750.00
0.0800 oh Mandor 125,000.00 10,000.00
Total : 160,250.00 890,840.00 1,051,090.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
33 MEMBUAT 1 M3 TIANG PANCANG PRESTRESSED BETON
440.0000 Kg Semen Portland 1,450.00 638,000.00
0.5000 m3 Pasir Beton 210,000.00 105,000.00
0.8000 m3 Koral Beton 298,000.00 238,400.00
2.4600 Gln Rapidrant - -
0.2000 oh Pekerja 75,000.00 15,000.00
0.0750 oh Tukang Batu 95,000.00 7,125.00
0.0075 oh Kepala Tukang 110,000.00 825.00
0.0200 oh Mandor 125,000.00 2,500.00
Total : 25,450.00 981,400.00 1,006,850.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
33 MEMBUAT 1 M' PASANG BUIS BETON 1/2 DIAMETRE 50 CM
1.0000 Bj Buis Beton 1/2 Diameter 50 cm 99,000.00 99,000.00
0.1200 Kg Semen 1,450.00 174.00
0.0130 m3 Pasir Pasangan 230,000.00 2,990.00
0.2000 oh Pekerja 75,000.00 15,000.00
0.0750 oh Tukang Batu 95,000.00 7,125.00
0.0075 oh Kepala Tukang 110,000.00 825.00
0.0200 oh Mandor 125,000.00 2,500.00
Total : 25,450.00 102,164.00 127,614.00
34 MEMBUAT 1 M' PASANG BUIS BETON 1/2 DIAMETRE 25 CM
1.0000 Bj Buis Beton 1/2 Diameter 25 cm 56,650.00 56,650.00
0.1200 Kg Semen 1,450.00 174.00
0.0130 m3 Pasir Pasangan 230,000.00 2,990.00
0.2000 oh Pekerja 75,000.00 15,000.00
0.0750 oh Tukang Batu 95,000.00 7,125.00
0.0075 oh Kepala Tukang 110,000.00 825.00
0.0200 oh Mandor 125,000.00 2,500.00
Total : 25,450.00 59,814.00 85,264.00
32 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM)
0.0030 m3 Kayu Kelas III 2,985,675.00 8,957.03
0.0200 kg Paku Biasa 5' - 12' 17,297.78 345.96
3.6000 kg Besi Beton 10,770.50 38,773.80
0.0500 kg Kawat Beton 15,400.00 770.00
5.5000 kg Semen Portland 1,450.00 7,975.00
0.0090 m3 Pasir Beton 210,000.00 1,890.00
0.0150 m3 Koral Beton 298,000.00 4,470.00
0.2970 oh Pekerja 75,000.00 22,275.00
0.0330 oh Tukang Batu 95,000.00 3,135.00
0.0330 oh Tukang Kayu 105,000.00 3,465.00
0.0330 oh Tukang Besi 100,000.00 3,300.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 35,150.00 63,181.78 98,331.78

VIII PEKERJAAN PENUTUP ATAP (SNI 03-3436-2002)


1 1 M2 PEKERJAAN ATAP GENTENG PLENTONG
25.0000 bh Genteng Plentong 2,200.00 55,000.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.0750 oh Tukang Kayu 105,000.00 7,875.00
0.0080 oh Kepala Tukang 110,000.00 880.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 21,005.00 55,000.00 76,005.00
2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT
25.0000 bh Genteng Plentong Dicat 2,420.00 60,500.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.0750 oh Tukang Kayu 105,000.00 7,875.00
0.0080 oh Kepala Tukang 110,000.00 880.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 21,005.00 60,500.00 81,505.00
3 1 M1 PASANG BUBUNGAN GENTENG PLENTONG
5.0000 bh Bubungan Plentong 16,500.00 82,500.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
10.8000 kg Semen Portland 1,450.00 15,660.00
0.0320 m3 Pasir Pasang 230,000.00 7,360.00
0.4000 oh Pekerja 75,000.00 30,000.00
0.2000 oh Tukang Kayu 105,000.00 21,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0020 oh Mandor 125,000.00 250.00
Total : 53,450.00 105,520.00 158,970.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM
0.6600 lbr Asbes Gelombang 1.8 mx0.92mx5mm 38,500.00 25,410.00
2.0000 kg Paku Pancing 60 x 230 16,500.00 33,000.00
0.1400 oh Pekerja 75,000.00 10,500.00
0.0670 oh Tukang Kayu 105,000.00 7,035.00
0.0070 oh Kepala Tukang Kayu 110,000.00 770.00
0.0070 oh Mandor 125,000.00 875.00
Total : 19,180.00 58,410.00 77,590.00
5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M
2.4000 lbr Bubungan Stel Gelombang 49,000.00 117,600.00
4.0000 kg Paku Skrup 3,5" 16,500.00 66,000.00
0.0840 oh Pekerja 75,000.00 6,300.00
0.1250 oh Tukang Kayu 105,000.00 13,125.00
0.0130 oh Kepala Tukang 110,000.00 1,430.00
0.0040 oh Mandor 125,000.00 500.00
Total : 21,355.00 183,600.00 204,955.00
6 1 M2 PEKERJAAN ATAP SIRAP 8 X 60 CM
60.0000 Lbr Sirap 4,950.00 297,000.00
0.2000 kg Paku Biasa 1/2" - 1" 15,271.67 3,054.33
0.1660 oh Pekerja 75,000.00 12,450.00
0.2500 oh Tukang Kayu 105,000.00 26,250.00
0.0250 oh Kepala Tukang 110,000.00 2,750.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 42,450.00 300,054.33 342,504.33
8 1 M2 PASANG ATAP ALANG-ALANG 3 M1
6.5000 lbr Alang - alang 16,500.00 107,250.00
0.5000 glg Tali pengikat 19,800.00 9,900.00
0.2000 oh Pekerja 75,000.00 15,000.00
0.0050 oh Mandor 125,000.00 625.00
Total : 15,625.00 117,150.00 132,775.00
7 1 M2 PEKERJAAN ATAP SENG GELOMBANG
0.7000 lbr Seng Gelombang 3" x 6" BJLS 28 119,790.00 83,853.00
2.0000 kg Paku Biasa 1/2" - 1" 15,271.67 30,543.33
0.1400 oh Pekerja 75,000.00 10,500.00
0.0070 oh Tukang Kayu 105,000.00 735.00
0.0070 oh Kepala Tukang 110,000.00 770.00
0.0070 oh Mandor 125,000.00 875.00
Total : 12,880.00 114,396.33 127,276.33
13 1 M' PKERJAAN TALANG PATAHAN ATAP
0.5000 Lbr Seng Plat 53,240.00 26,620.00
0.0150 kg Paku 15,271.67 229.08
0.0190 M3 Kayu Papan Kruing 7,875,000.00 149,625.00
0.4000 oh Tukang Kayu 105,000.00 42,000.00
0.0250 oh Kepala Tukang Kayu 110,000.00 2,750.00
0.0400 oh Pekerja / Pekerja Tak Terlatih 75,000.00 3,000.00
0.0013 oh Mandor 125,000.00 162.50
Total : 47,912.50 176,474.08 224,386.58
13 1 M' PASANGAN LIST PLAFOND
1.0500 M List Kayu Profit 37,800.00 39,690.00
0.0100 kg Paku 15,271.67 152.72
0.0210 oh Tukang Kayu 105,000.00 2,205.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.0020 oh Kepala Tukang Kayu 110,000.00 220.00
0.0210 oh Pekerja / Pekerja Tak Terlatih 75,000.00 1,575.00
0.0010 oh Mandor 125,000.00 125.00
Total : 4,125.00 39,842.72 43,967.72
14 1 M2 PASANGAN KREPYAK JARO
0.0225 M3 Kayu Kamper Papan 9,975,000.00 224,437.50
2.2500 oh Tukang Kayu 105,000.00 236,250.00
0.2250 oh Kepala Tukang Kayu 110,000.00 24,750.00
0.7500 oh Pekerja / Pekerja Tak Terlatih 75,000.00 56,250.00
0.0375 oh Mandor 125,000.00 4,687.50
Total : 4,687.50 224,437.50 229,125.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
6 1 M2 PASANGAN LAPISAN ALUMINIUM FOIL
1.1000 m2 Aluminium Foil 245,300.00 269,830.00
0.0330 oh Pekerja 75,000.00 2,475.00
0.0330 oh Tukang Kayu 105,000.00 3,465.00
0.0030 oh Kepala Tukang 110,000.00 330.00
0.0020 oh Mandor 125,000.00 250.00
Total : 6,520.00 269,830.00 276,350.00
7 1 M1 PASANG NOK SENG GELOMBANG
0.3000 lbr Seng Plat 3" x 6" BJLS 28 66,550.00 19,965.00
0.0400 kg Paku biasa 1/2" - 1" 15,271.67 610.87
0.1500 oh Pekerja 75,000.00 11,250.00
0.0700 oh Tukang Kayu 105,000.00 7,350.00
0.0080 oh Kepala Tukang 110,000.00 880.00
0.0060 oh Mandor 125,000.00 750.00
Total : 20,230.00 20,575.87 40,805.87
8 1 BH PEKERJAAN PASANGAN MURDA/BETALA/IKUT CELEDU
1.0000 BH Murda / Puntal Paras 121,000.00 121,000.00
0.0130 kg Semen 1,450.00 18.85
0.0500 oh Pekerja / Pekerja Tak Terlatih 75,000.00 3,750.00
0.0250 oh Mandor 125,000.00 3,125.00
Total : 6,875.00 121,018.85 127,893.85

IX PEKERJAAN PLAFOND / LANGIT - LANGIT (SNI 2839-2008)


MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN
1
6 MM
1.1000 lbr Asbes semen 18,150.00 19,965.00
0.0100 kg Paku Biasa 1/2" - 1" 15,271.67 152.72
0.0300 oh Pekerja 75,000.00 2,250.00
0.0700 oh Tukang Kayu 105,000.00 7,350.00
0.0070 oh Kepala Tukang 110,000.00 770.00
0.0040 oh Mandor 125,000.00 500.00
Total : 10,870.00 20,117.72 30,987.72
2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/3 MM, 4MM, 6MM
0.3750 lbr TRIPLEKS 122,100.00 45,787.50
0.0300 kg Paku Biasa 1/2" - 1" 15,271.67 458.15
0.1000 oh Pekerja 75,000.00 7,500.00
0.1000 oh Tukang Kayu 105,000.00 10,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 19,725.00 46,245.65 65,970.65
3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING
0.0150 m3 Kayu Papan kamper 9,975,000.00 149,625.00
0.0100 kg Paku Biasa 1/2" - 1" 15,271.67 152.72
0.8000 oh Pekerja 75,000.00 60,000.00
0.8000 oh Tukang Kayu 105,000.00 84,000.00
0.0800 oh Kepala Tukang 110,000.00 8,800.00
0.0400 oh Mandor 125,000.00 5,000.00
Total : 157,800.00 149,777.72 307,577.72
4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL
1.0500 m1 List Kayu Profil 4/5 cm 37,800.00 39,690.00
0.0100 kg Paku list 15,271.67 152.72
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.0500 oh Pekerja 75,000.00 3,750.00
0.0500 oh Tukang Kayu 105,000.00 5,250.00
0.0050 oh Kepala Tukang 110,000.00 550.00
0.0030 oh Mandor 125,000.00 375.00
Total : 9,925.00 39,842.72 49,767.72
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
1 M2 PASANG LANGIT-LANGIT AKUSTIK UKURAN (60 x 120) CM + RANGKA
5
ALUMINIUM
3.6000 m1 Profil Aluminium "T" 219,450.00 790,020.00
0.1500 kg Kawat Diameter 4 mm 88,000.00 13,200.00
1.0500 m1 Ramset 14,520.00 15,246.00
1.5000 Lemb Akustik 60 cm x 120 cm 54,450.00 81,675.00
0.5000 oh Pekerja 75,000.00 37,500.00
0.5000 oh Tukang Besi 100,000.00 50,000.00
0.0500 oh Kepala Tukang 110,000.00 5,500.00
0.0250 oh Mandor 125,000.00 3,125.00
Total : 96,125.00 900,141.00 996,266.00
6 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA
0.0230 m3 Kamper Usuk 4/6 cm 6,300,000.00 144,900.00
0.0600 kg Paku Biasa 2" - 5" 15,271.67 916.30
1.1000 lbr Asbes 18,150.00 19,965.00
0.1800 oh Pekerja 75,000.00 13,500.00
0.3200 oh Tukang Kayu 105,000.00 33,600.00
0.0320 oh Kepala Tukang 110,000.00 3,520.00
0.0090 oh Mandor 125,000.00 1,125.00
Total : 51,745.00 165,781.30 217,526.30
1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200X2400X9)
7
MM
0.1100 kg Paku Sekrup 10,000.00 1,100.00
0.3640 lbr Gypsum Board (120x240x9) 79,200.00 28,828.80
0.1000 oh Pekerja 75,000.00 7,500.00
0.0500 oh Tukang Kayu 105,000.00 5,250.00
0.0050 oh Kepala Tukang 110,000.00 550.00
0.0050 oh Mandor 125,000.00 625.00
Total : 13,925.00 29,928.80 43,853.80
8 1 M2 PASANG LANGIT-LANGIT KALSIBOARD 4.5 MM
0.1100 kg Paku Kalsiboard 15,271.67 1,679.88
0.3640 lbr Kalsiboard 4.5 mm 79,200.00 28,828.80
0.1000 oh Pekerja 75,000.00 7,500.00
0.0500 oh Tukang Kayu 105,000.00 5,250.00
0.0050 oh Kepala Tukang 110,000.00 550.00
0.0050 oh Mandor 125,000.00 625.00
Total : 13,925.00 30,508.68 44,433.68
7 1 M2 PLAFOND GYPSUM, RANGKA KAYU
0.364 Lbr Gypsum Board (120x240x9) 79,200.00 28,828.80
0.023 M3 Kayu Kruing Usuk 6,300,000.00 144,900.00
0.260 Kg Paku Kalsiboard 15,271.67 3,970.63
0.300 OH Pekerja 75,000.00 22,500.00
0.350 OH Tukang Kayu 105,000.00 36,750.00
0.035 OH Kepala Tukang Kayu 110,000.00 3,850.00
0.0150 OH Mandor 125,000.00 1,875.00
Total : 64,975.00 177,699.43 242,674.43
8 1 M2 PLAFOND GYPSUM, RANGKA HOLO
0.364 Lbr Gypsum Board (120x240x9) 79,200.00 28,828.80
1.000 Btg Rangka Metal Furing (2 x 4 cm) panjang 4 m 22,000.00 22,000.00
0.110 Kg Paku Kalsiboard 15,271.67 1,679.88
0.300 OH Pekerja 75,000.00 22,500.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.350 OH Tukang Kayu 105,000.00 36,750.00
0.035 OH Kepala Tukang Kayu 110,000.00 3,850.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 64,975.00 52,508.68 117,483.68
9 1 M2 PLAFOND KALSIBOARD, RANGKA KAYU
0.364 Lbr Kalsiboard (4,5 x 1220 x 2420) mm 113,080.00 41,161.12
0.023 M3 Kayu Kruing Usuk 6,300,000.00 144,900.00
0.260 Kg Paku Kalsiboard 15,271.67 3,970.63
0.300 OH Pekerja 75,000.00 22,500.00
0.350 OH Tukang Kayu 105,000.00 36,750.00
0.035 OH Kepala Tukang Kayu 110,000.00 3,850.00
0.0150 OH Mandor 125,000.00 1,875.00
Total : 64,975.00 190,031.75 255,006.75
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
10 1 M2 PLAFOND KALSIBOARD, RANGKA HOLO
0.364 Lbr Kalsiboard (4,5 x 1220 x 2420) mm 113,080.00 41,161.12
1.000 Btg Rangka Metal Furing (2 x 4 cm) panjang 4 m 22,000.00 22,000.00
0.110 Kg Paku Kalsiboard 15,271.67 1,679.88
0.300 OH Pekerja 75,000.00 22,500.00
0.350 OH Tukang Kayu 105,000.00 36,750.00
0.035 OH Kepala Tukang Kayu 110,000.00 3,850.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 64,975.00 64,841.00 129,816.00
X PEKERJAAN SANITASI
1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK
1.0000 bh Kloset duduk/ monoblok 1,925,000.00 1,925,000.00
6% x harga kloset Perlengkapan 115,500.00
3.3000 oh Pekerja 75,000.00 247,500.00
1.1000 oh Tukang batu 95,000.00 104,500.00
0.0010 oh Kepala Tukang 110,000.00 110.00
0.1600 oh Mandor 125,000.00 20,000.00
Total : 372,110.00 2,040,500.00 2,412,610.00
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN
1.0000 bh Kloset jongkok porselen 175,450.00 175,450.00
6.0000 kg Semen Portland 1,450.00 8,700.00
0.0100 m3 Pasir Pasang 230,000.00 2,300.00
1.0000 oh Pekerja 75,000.00 75,000.00
1.5000 oh Tukang batu 95,000.00 142,500.00
1.5000 oh Kepala Tukang 110,000.00 165,000.00
0.1600 oh Mandor 125,000.00 20,000.00
Total : 402,500.00 186,450.00 588,950.00
3 MEMASANG 1 BUAH URINOIR
1.0000 bh Urinoir 2,874,960.00 2,874,960.00
30% x harga Urin Perlengkapan 862,488.00
6.0000 kg Semen Portland 1,450.00 8,700.00
0.0100 m3 Pasir Pasang 230,000.00 2,300.00
1.0000 oh Pekerja 75,000.00 75,000.00
1.0000 oh Tukang batu 95,000.00 95,000.00
0.1000 oh Kepala Tukang 110,000.00 11,000.00
0.1000 oh Mandor 125,000.00 12,500.00
Total : 193,500.00 3,748,448.00 3,941,948.00
4 MEMASANG 1 BUAH WASHTAFEL KIA
1.0000 bh Washtafel 203,500.00 203,500.00
12% x harga wast Perlengkapan 24,420.00
6.0000 kg Semen Portland 1,450.00 8,700.00
0.0100 m3 Pasir Pasang 230,000.00 2,300.00
1.2000 oh Pekerja 75,000.00 90,000.00
1.4500 oh Tukang batu 95,000.00 137,750.00
0.1500 oh Kepala Tukang 110,000.00 16,500.00
0.1000 oh Mandor 125,000.00 12,500.00
Total : 256,750.00 238,920.00 495,670.00
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3
1.0000 bh Bak Fibreglass 306,130.00 306,130.00
18% x harga wast Perlengkapan 55,103.40
1.8000 oh Pekerja 75,000.00 135,000.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
2.7000 oh Tukang batu 95,000.00 256,500.00
0.5400 oh Kepala Tukang 110,000.00 59,400.00
0.1100 oh Mandor 125,000.00 13,750.00
Total : 464,650.00 361,233.40 825,883.40
6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 "
1.2000 m1 Pipa galvanis 84,000.00 100,800.00
35% x harga pipa Perlengkapan 29,400.00
0.0540 oh Pekerja 75,000.00 4,050.00
0.0900 oh Tukang Pipa 90,000.00 8,100.00
0.0090 oh Kepala Tukang 110,000.00 990.00
0.0270 oh Mandor 125,000.00 3,375.00
Total : 16,515.00 130,200.00 146,715.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3"
1.2000 M' Pipa galvanis 181,000.00 217,200.00
35% x harga pipa Perlengkapan 63,350.00
0.1080 Oh Pekerja 75,000.00 8,100.00
0.1800 Oh Tukang Pipa 90,000.00 16,200.00
0.0180 Oh Kepala Tukang 110,000.00 1,980.00
0.0054 Oh Mandor 125,000.00 675.00
Total : 26,955.00 280,550.00 307,505.00
8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"
1.2000 m1 Pipa PVC 22,000.00 26,400.00
35% x harga pipa Perlengkapan 7,700.00
0.0360 oh Pekerja 75,000.00 2,700.00
0.0600 oh Tukang Pipa 90,000.00 5,400.00
0.0060 oh Kepala Tukang 110,000.00 660.00
0.0018 oh Mandor 125,000.00 225.00
Total : 8,985.00 34,100.00 43,085.00
9 MEMASANG 1 M1 PIPA PVC TYPE AW f 2"
1.2000 m1 Pipa PVC 32,000.00 38,400.00
35% x harga pipa Perlengkapan 11,200.00
0.0540 oh Pekerja 75,000.00 4,050.00
0.0900 oh Tukang Pipa 90,000.00 8,100.00
0.0090 oh Kepala Tukang 110,000.00 990.00
0.0027 oh Mandor 125,000.00 337.50
Total : 13,477.50 49,600.00 63,077.50
10 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4"
1.2000 m1 Pipa PVC 85,000.00 102,000.00
35% x harga pipa Perlengkapan 29,750.00
0.0810 oh Pekerja 75,000.00 6,075.00
0.1350 oh Tukang Pipa 90,000.00 12,150.00
0.0135 oh Kepala Tukang 110,000.00 1,485.00
0.0041 oh Mandor 125,000.00 512.50
Total : 20,222.50 131,750.00 151,972.50
11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5"
1.0000 bh Kran air 55,000.00 55,000.00
0.0250 bh Seal tape 3,300.00 82.50
- oh Pekerja 75,000.00 -
0.1000 oh Tukang Pipa 90,000.00 9,000.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
- oh Mandor 125,000.00 -
Total : 10,100.00 55,082.50 65,182.50
XI PEKERJAAN BESI DAN ALUMINIUM (SNI 7393:2008)
1 1 KG MEMASANG RANGKA BAJA IWF
1.1500 kg Besi Baja IWF 10,450.00 12,017.50
0.0060 oh Pekerja 75,000.00 450.00
0.0600 oh Tukang besi 100,000.00 6,000.00
0.0060 oh Kepala Tukang 110,000.00 660.00
0.0003 oh Mandor 125,000.00 37.50
Total : 7,147.50 12,017.50 19,165.00
2 1 M2 PASANG ROLLING DOOR ALLUMINIUM
1.0000 m2 Rolling Door Alluminium 286,000.00 286,000.00
1.0000 oh Pekerja 75,000.00 75,000.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
1.0000 oh Tukang Aluminium 100,000.00 100,000.00
0.1000 oh Kepala Tukang 110,000.00 11,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 192,250.00 286,000.00 478,250.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
3 1 M2 MEMASANG RANGKA KUDA - KUDA BAJA RINGAN C 75
1.4880 m' C-75, 0.8 15,950.00 23,733.60
2.2320 m' C-75, 0.6 13,750.00 30,690.00
28.0000 bh Baut 550.00 15,400.00
1.6000 bh Dynabolt 3,675.00 5,880.00
5.4000 m' Reng 7,700.00 41,580.00
0.1240 m' Talang Jurai 71,500.00 8,866.00
0.2000 oh Pekerja 75,000.00 15,000.00
0.4500 oh Tukang besi 100,000.00 45,000.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 67,350.00 126,149.60 193,499.60
4 1 M' PASANG KUSEN PINTU ALLUMINIUM
1.1000 m Profil Aluminium 4" 66,000.00 72,600.00
2.0000 bh Sekruf fixer 550.00 1,100.00
0.0600 Tube Sealant 36,300.00 2,178.00
0.0430 oh Pekerja 75,000.00 3,225.00
0.0430 oh Tukang Alumium 100,000.00 4,300.00
0.0043 oh Kepala Tukang 110,000.00 473.00
0.0021 oh Mandor 125,000.00 262.50
Total : 8,260.50 75,878.00 84,138.50
5 1 M2 PASANG PINTU KACA RANGKA ALLUMINIUM
4.4000 m Profil Aluminium 4" 66,000.00 290,400.00
4.5000 m Profil Kaca 9,900.00 44,550.00
0.2700 Tube Sealant 36,300.00 9,801.00
0.0850 oh Pekerja 75,000.00 6,375.00
0.0850 oh Tukang Alumium 100,000.00 8,500.00
0.0090 oh Kepala Tukang 110,000.00 990.00
0.0050 oh Mandor 125,000.00 625.00
Total : 16,490.00 344,751.00 361,241.00
6 1 M2 PASANG TERALI BESI STRIP (2 x 3 ) mm
6.1770 kg Besi strip 16,500.00 101,920.50
27.0800 cm Pengelasan 14,520.00 393,201.60
1.6700 oh Pekerja 75,000.00 125,250.00
1.6700 oh Tukang Las 100,000.00 167,000.00
0.1670 oh Kepala Tukang 110,000.00 18,370.00
0.0830 oh Mandor 125,000.00 10,375.00
Total : 320,995.00 495,122.10 816,117.10
7 1 M2 KAWAT NYAMUK
1.1000 m2 Kawat Nyamuk 24,200.00 26,620.00
11.1100 cm Pengelasan 14,520.00 161,317.20
1.7160 kg Baja Strip (0,2 x 2) cm 16,500.00 28,314.00
0.1000 oh Pekerja 75,000.00 7,500.00
0.1000 oh Tukang Besi 100,000.00 10,000.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 19,225.00 216,251.20 235,476.20
8 1 M2 PASANG JENDELA NAKO & TRALIS
1.1000 m2 Rangka + Kaca Nako 38,500.00 42,350.00
10.0000 bh Paku biasa 1 cm - 2,5 cm 15,271.67 152,716.67
7.0000 m' Besi strip 11,960.00 83,720.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.2000 oh Pekerja 75,000.00 15,000.00
0.2000 oh Tukang besi 100,000.00 20,000.00
0.0200 oh Kepala Tukang 110,000.00 2,200.00
0.0010 oh Mandor 125,000.00 125.00
Total : 37,325.00 278,786.67 316,111.67
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
9 1 M1 PASANG TALANG DATAR, SENG BJLS 28
1.0500 lbr Seng plat 66,550.00 69,877.50
0.0150 kg Paku biasa 0,5" - 1" 15,271.67 229.08
0.0190 m3 Kayu papan kelas II/III 9,975,000.00 189,525.00
0.2000 oh Pekerja 75,000.00 15,000.00
0.4000 oh Tukang besi 100,000.00 40,000.00
0.0250 oh Kepala Tukang 110,000.00 2,750.00
0.0100 oh Mandor 125,000.00 1,250.00
Total : 59,000.00 259,631.58 318,631.58
XII PEKERJAAN KUNCI DAN KACA (SNI 2002)
1 1 BH PASANG KUNCI TANAM BIASA
1.0000 bh Kunci tanam biasa 166,100.00 166,100.00
- oh Pekerja 75,000.00 -
0.5000 oh Tukang besi 100,000.00 50,000.00
0.0500 oh Kepala Tukang 110,000.00 5,500.00
- oh Mandor 125,000.00 -
Total : 55,500.00 166,100.00 221,600.00
2 1 PS PASANG ENGSEL PINTU
1.0000 ps Engsel pintu 73,150.00 73,150.00
- oh Pekerja 75,000.00 -
0.1250 oh Tukang besi 100,000.00 12,500.00
0.0130 oh Kepala Tukang 110,000.00 1,430.00
- oh Mandor 125,000.00 -
Total : 13,930.00 73,150.00 87,080.00

3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU


1.0000 ps Engsel jendela 64,900.00 64,900.00
- oh Pekerja 75,000.00 -
0.1000 oh Tukang besi 100,000.00 10,000.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
- oh Mandor 125,000.00 -
Total : 11,100.00 64,900.00 76,000.00
4 1 BH PASANG KAIT ANGIN
1.0000 ps Kait angin 55,000.00 55,000.00
- oh Pekerja 75,000.00 -
0.1000 oh Tukang besi 100,000.00 10,000.00
0.0010 oh Kepala Tukang 110,000.00 110.00
- oh Mandor 125,000.00 -
Total : 10,110.00 55,000.00 65,110.00
5 1 BH PASANG KUNCI SLOT
1.0000 bh Kunci slot 244,200.00 244,200.00
- oh Pekerja 75,000.00 -
0.2500 oh Tukang besi 100,000.00 25,000.00
0.0250 oh Kepala Tukang 110,000.00 2,750.00
- oh Mandor 125,000.00 -
Total : 27,750.00 244,200.00 271,950.00
6 1 M2 PASANG KACA, TEBAL5 MM
1.1000 bh Kaca 143,000.00 157,300.00
0.1600 oh Pekerja 75,000.00 12,000.00
0.1600 oh Tukang besi 100,000.00 16,000.00
0.1600 oh Kepala Tukang 110,000.00 17,600.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.0080 oh Mandor 125,000.00 1,000.00
Total : 46,600.00 157,300.00 203,900.00
7 1 M2 PASANG KACA TEMPERED TEBAL 5 MM
1.1000 bh Kaca 224,500.00 246,950.00
0.1600 oh Pekerja 75,000.00 12,000.00
0.1600 oh Tukang besi 100,000.00 16,000.00
0.1600 oh Kepala Tukang 110,000.00 17,600.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 46,600.00 246,950.00 293,550.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
8 1 M2 PASANG KACA TEMPERED TEBAL 6 MM
1.1000 bh Kaca 299,500.00 329,450.00
0.1600 oh Pekerja 75,000.00 12,000.00
0.1600 oh Tukang besi 100,000.00 16,000.00
0.1600 oh Kepala Tukang 110,000.00 17,600.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 46,600.00 329,450.00 376,050.00
9 1 M2 PASANG KACA TEMPERED TEBAL 12 MM
1.1000 bh Kaca 565,000.00 621,500.00
0.1600 oh Pekerja 75,000.00 12,000.00
0.1600 oh Tukang besi 100,000.00 16,000.00
0.1600 oh Kepala Tukang 110,000.00 17,600.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 46,600.00 621,500.00 668,100.00
XIII PEKERJAAN PENUTUP LANTAI DAN DINDING (SNI 7395:2008)
1 1 M2 PASANG LANTAI UBIN TERASO UKURAN (40 X 40) CM
6.6300 bh Ubin Teraso - -
9.8000 kg Semen Portland 1,450.00 14,210.00
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
1.3000 kg Semen warna/semen grouting 25,620.00 33,306.00
0.2500 oh Pekerja 75,000.00 18,750.00
0.1250 oh Tukang batu 95,000.00 11,875.00
0.0130 oh Kepala Tukang 110,000.00 1,430.00
0.0130 oh Mandor 125,000.00 1,625.00
Total : 33,680.00 57,866.00 91,546.00
2 1 M2 PASANG LANTAI UBIN TERASO UKURAN (30 X 30) CM
11.8700 bh Ubin Teraso - -
10.0000 kg Semen Portland 1,450.00 14,500.00
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
1.5000 kg Semen warna/semen grouting 25,620.00 38,430.00
0.2600 oh Pekerja 75,000.00 19,500.00
0.1300 oh Tukang batu 95,000.00 12,350.00
0.0130 oh Kepala Tukang 110,000.00 1,430.00
0.0130 oh Mandor 125,000.00 1,625.00
Total : 34,905.00 63,280.00 98,185.00
3 1 M2 PASANG LANTAI UBIN GRANIT UKURAN (40 X 40) CM
6.6300 bh Ubin Granit 58,025.00 384,705.75
9.8000 kg Semen Portland 1,450.00 14,210.00
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
1.3000 kg Semen warna/semen grouting 25,620.00 33,306.00
0.2500 oh Pekerja 75,000.00 18,750.00
0.1250 oh Tukang batu 95,000.00 11,875.00
0.0130 oh Kepala Tukang 110,000.00 1,430.00
0.0130 oh Mandor 125,000.00 1,625.00
Total : 33,680.00 442,571.75 476,251.75
4 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM
11.8700 bh Keramik 30 x 30 cm 5,200.00 61,724.00
10.0000 kg Semen Portland 1,450.00 14,500.00
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
1.5000 kg Semen warna/semen grouting 25,620.00 38,430.00
0.7000 oh Pekerja 75,000.00 52,500.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.3500 oh Tukang batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.0350 oh Mandor 125,000.00 4,375.00
Total : 93,975.00 125,004.00 218,979.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
5 1 M2 PASANG LANTAI KERAMIK 60 X 60 CM
3.0556 bh Keramik 60 x 60 cm 31,625.00 96,631.94
10.0000 kg Semen Portland 1,450.00 14,500.00
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
1.5000 kg Semen warna/semen grouting 25,620.00 38,430.00
0.7000 oh Pekerja 75,000.00 52,500.00
0.3500 oh Tukang batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.0350 oh Mandor 125,000.00 4,375.00
Total : 93,975.00 159,911.94 253,886.94
6 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM
26.5000 bh Keramik 20 x 20 cm 2,860.00 75,790.00
10.4000 kg Semen Portland 1,450.00 15,080.00
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
1.6200 kg Semen warna/semen grouting 25,620.00 41,504.40
0.7000 oh Pekerja 75,000.00 52,500.00
0.3500 oh Tukang batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.0350 oh Mandor 125,000.00 4,375.00
Total : 93,975.00 142,724.40 236,699.40
7 1 M1 PASANG PLIN KERAMIK 10 X 30 CM
5.3000 bh Keramik 30 x 30 cm 5,200.00 27,560.00
1.1400 kg Semen Portland 1,450.00 1,653.00
0.0030 m3 Pasir Pasang 230,000.00 690.00
0.0250 kg Semen warna/semen grouting 25,620.00 640.50
0.0900 oh Pekerja 75,000.00 6,750.00
0.0900 oh Tukang batu 95,000.00 8,550.00
0.0090 oh Kepala Tukang 110,000.00 990.00
0.0050 oh Mandor 125,000.00 625.00
Total : 16,915.00 30,543.50 47,458.50
8 1 M1 PASANG PLIN KERAMIK 10 X 20 CM
5.3000 bh Plint Keramik 10 x 20 cm 2,860.00 15,158.00
1.1400 kg Semen Portland 1,450.00 1,653.00
0.0030 m3 Pasir Pasang 230,000.00 690.00
0.0250 kg Semen warna/semen grouting 25,620.00 640.50
0.0900 oh Pekerja 75,000.00 6,750.00
0.0900 oh Tukang batu 95,000.00 8,550.00
0.0090 oh Kepala Tukang 110,000.00 990.00
0.0050 oh Mandor 125,000.00 625.00
Total : 16,915.00 18,141.50 35,056.50
9 1 M2 PASANG LANTAI MARMER 30 X 30 CM
1.0600 m2 Marmer 308,000.00 326,480.00
8.1900 kg Semen Portland 1,450.00 11,875.50
0.0450 m3 Pasir Pasang 230,000.00 10,350.00
0.6500 kg Semen warna/semen grouting 25,620.00 16,653.00
0.7000 oh Pekerja 75,000.00 52,500.00
0.3500 oh Tukang batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.0350 oh Mandor 125,000.00 4,375.00
Total : 93,975.00 365,358.50 459,333.50
10 MEMASANG 1 M2 LANTAI KAYU BANGKIRAI
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.0260 m3 Papan Kayu Bangkirai 13,650,000.00 354,900.00
0.0080 m3 Kayu Kaso Bangkirai 4/6 11,340,000.00 90,720.00
0.1000 Kg Paku 5 Cm dan 10 Cm 17,297.78 1,729.78
0.1500 Kg Paku Skrup 10 cm 17,297.78 2,594.67
0.6000 oh Pekerja 75,000.00 45,000.00
1.8000 oh Tukang Kayu 105,000.00 189,000.00
0.1800 oh Kepala Tukang 110,000.00 19,800.00
0.0300 oh Mandor 125,000.00 3,750.00
Total : 257,550.00 449,944.44 707,494.44
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
11 1 M2 PASANG DINDING KERAMIK 20 X 20 CM
26.5000 bh Keramik 20 x 20 cm 2,860.00 75,790.00
9.3000 kg Semen Portland 1,450.00 13,485.00
0.0180 m3 Pasir Pasang 230,000.00 4,140.00
1.9400 kg Semen warna/semen grouting 25,620.00 49,702.80
0.9000 oh Pekerja 75,000.00 67,500.00
0.4500 oh Tukang batu 95,000.00 42,750.00
0.0450 oh Kepala Tukang 110,000.00 4,950.00
0.0450 oh Mandor 125,000.00 5,625.00
Total : 120,825.00 143,117.80 263,942.80
12 1 M2 PASANG DINDING MARMER 30 X 30 CM
1.0600 m2 Marmer 308,000.00 326,480.00
3.0030 bh Paku 10 cm 17,297.78
12.4400 kg Semen Portland 1,450.00 18,038.00
0.0250 m3 Pasir Pasang 230,000.00 5,750.00
0.6500 kg Semen warna/semen grouting 25,620.00 16,653.00
1.3000 oh Pekerja 75,000.00 97,500.00
0.6500 oh Tukang batu 95,000.00 61,750.00
0.0650 oh Kepala Tukang 110,000.00 7,150.00
0.0650 oh Mandor 125,000.00 8,125.00
Total : 174,525.00 366,921.00 541,446.00
13 1 M1 PASANG PLIN KAYU 2 X 10 CM
0.0030 m3 Papan Kayu Kelas II 9,975,000.00 29,925.00
0.0500 kg Paku sekrup 3,5' 17,297.78 864.89
0.1200 oh Pekerja 75,000.00 9,000.00
0.1200 oh Tukang kayu 105,000.00 12,600.00
0.0120 oh Kepala Tukang 110,000.00 1,320.00
0.0060 oh Mandor 125,000.00 750.00
Total : 23,670.00 30,789.89 54,459.89
13 1 M2 PASANG DINDING BATA PELAPIS UKURAN (3 x 7 x 24) cm
63.0000 bh Bata Pelapis Dinding 5,850.00 368,550.00
12.4400 kg Semen Portland 1,450.00 18,038.00
0.0250 m3 Pasir Pasang 230,000.00 5,750.00
2.7500 kg Semen warna/semen grouting 25,620.00 70,455.00
1.0000 oh Pekerja 75,000.00 75,000.00
0.5000 oh Tukang batu 95,000.00 47,500.00
0.0500 oh Kepala Tukang 110,000.00 5,500.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 134,250.00 462,793.00 597,043.00
14 1 M2 PASANG DINDING BATU PARAS (30 X 15)
1.1000 m2 Batu Paras 25,000.00 27,500.00
11.7500 kg Semen Portland 1,450.00 17,037.50
0.0350 m3 Pasir Pasang 230,000.00 8,050.00
0.7000 oh Pekerja 75,000.00 52,500.00
0.3500 oh Tukang batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.0350 oh Mandor 125,000.00 4,375.00
Total : 93,975.00 52,587.50 146,562.50
15 1 M2 PASANG DINDING BATU CANDI HITAM (20 x 20 x 3)
1.1000 m2 Batu Candi Hitam (20 x 20 x 3 Cm) 90,000.00 99,000.00
11.7500 kg Semen Portland 1,450.00 17,037.50
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.0350 m3 Pasir Pasang 230,000.00 8,050.00
0.7000 oh Pekerja 75,000.00 52,500.00
0.3500 oh Tukang batu 95,000.00 33,250.00
0.0350 oh Kepala Tukang 110,000.00 3,850.00
0.0350 oh Mandor 125,000.00 4,375.00
Total : 93,975.00 124,087.50 218,062.50
XIV PEKERJAAN PENGECATAN (SNI 2002)
1 M2 PEKERJAAN MENGIKIS ATAU MENGEROK CAT TEMBOK CARA
1
MANUAL
0.0500 Bh Kapi 8,800.00 440.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 12,250.00 440.00 12,690.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
2 1 M2 PEKERJAAN LAPIS PLAMIR
0.1000 kg Plamir Tembok 159,500.00 15,950.00
0.5000 Lbr Amplas 6,600.00 3,300.00
0.0500 Bh Kapi 8,800.00 440.00
0.0200 oh Pekerja 75,000.00 1,500.00
0.0300 oh Tukang cat 95,000.00 2,850.00
0.0030 oh Kepala Tukang 110,000.00 330.00
0.0010 oh Mandor 125,000.00 125.00
Total : 4,805.00 19,690.00 24,495.00
1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR,
3
2 LAPIS CAT PENUTUP)
0.1000 kg Plamir 159,500.00 15,950.00
0.1000 kg Cat dasar 59,400.00 5,940.00
0.2600 kg Cat Penutup 2x 72,930.00 18,961.80
0.0200 oh Pekerja 75,000.00 1,500.00
0.0630 oh Tukang cat 95,000.00 5,985.00
0.0063 oh Kepala Tukang 110,000.00 693.00
0.0025 oh Mandor 125,000.00 312.50
Total : 8,490.50 40,851.80 49,342.30
1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN
4
KUAS
0.2400 kg Cat Tembok setara Vinilex 39,930.00 9,583.20
0.0150 Bh Kuas 13,200.00 198.00
0.0600 oh Pekerja 75,000.00 4,500.00
0.0500 oh Tukang cat 95,000.00 4,750.00
0.0050 oh Kepala Tukang 110,000.00 550.00
0.0030 oh Mandor 125,000.00 375.00
Total : 10,175.00 9,781.20 19,956.20
1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN
5
ROLL
0.4700 kg Cat Tembok setara Vinilex 39,930.00 18,767.10
0.0100 Bh Roll 38,500.00 385.00
0.0400 oh Pekerja 75,000.00 3,000.00
0.0300 oh Tukang cat 95,000.00 2,850.00
0.0030 oh Kepala Tukang 110,000.00 330.00
0.0020 oh Mandor 125,000.00 250.00
Total : 6,430.00 19,152.10 25,582.10
6 1 M2 PEKERJAAN PENGECATAN LANGIT -LANGIT 2 LAPIS DENGAN
CAT TEMBOK MENGGUNAKAN KUAS TERMASUK PLAMUR
0.1000 kg Plamur Tembok 159,500.00 15,950.00
0.2400 Kg Cat Tembok setara Vinilex 39,930.00 9,583.20
0.5000 Lbr Amplas 6,600.00 3,300.00
0.0150 Bh Kuas 13,200.00 198.00
0.0500 Bh Kapi 8,800.00 440.00
0.0800 oh Pekerja 75,000.00 6,000.00
0.0600 oh Tukang cat 95,000.00 5,700.00
0.0060 oh Kepala Tukang 110,000.00 660.00
0.0040 oh Mandor 125,000.00 500.00
Total : 12,860.00 29,471.20 42,331.20
1 M2 PEK. PENGECATAN PLAFOND 2 LAPIS DENGAN CAT TEMBOK
7
MENGGUNAKAN ROLL
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
0.1000 kg Plamur Tembok 159,500.00 15,950.00
0.4700 Kg Cat Tembok setara Vinilex 39,930.00 18,767.10
0.5000 Lbr Amplas 6,600.00 3,300.00
0.0100 Bh Roll 38,500.00 385.00
0.0500 Bh Kapi 8,800.00 440.00
0.0600 oh Pekerja 75,000.00 4,500.00
0.0400 oh Tukang cat 95,000.00 3,800.00
0.0040 oh Kepala Tukang 110,000.00 440.00
0.0030 oh Mandor 125,000.00 375.00
Total : 9,115.00 38,842.10 47,957.10
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
8 1 M2 WATERPROOFING
0.4500 kg waterproofing damplix 3 45,452.82 20,453.77
0.0150 oh Pekerja 75,000.00 1,125.00
0.1600 oh Tukang cat 95,000.00 15,200.00
0.0140 oh Kepala Tukang 110,000.00 1,540.00
0.0050 oh Mandor 125,000.00 625.00
Total : 18,490.00 20,453.77 38,943.77
1 M2 PEKERJAAN PASANG WALL PAPER DENGAN PEREKAT SETARA SILK
9
HOUSE
1.1000 m2 Wall Paper 660,000.00 726,000.00
0.2000 Kg Perekat 27,500.00 5,500.00
0.0100 oh Pekerja 75,000.00 750.00
0.1000 oh Tukang cat 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.0050 oh Mandor 125,000.00 625.00
Total : 11,975.00 731,500.00 743,475.00
10 1 M2 PEKERJAAN MELAPIS MENI KAYU
0.1700 kg Meni 49,500.00 8,415.00
0.1000 ltr Minyak Cat 46,530.00 4,653.00
0.0150 bh Kuas 13,200.00 198.00
0.0750 oh Pekerja 75,000.00 5,625.00
0.0040 oh Mandor 125,000.00 500.00
Total : 6,125.00 13,266.00 19,391.00
1 M2 PEKERJAAN MENDEMPUL ATAU MEMPLAMIR DAN MENGGOSOK
11
KAYU
0.1500 kg Dempul kayu 49,500.00 7,425.00
0.0080 Kg Plamir Kayu 49,500.00 396.00
0.1000 Ltr Minyak Cat 46,530.00 4,653.00
1.0000 Lbr Amplas 6,600.00 6,600.00
0.0150 Bh Kuas 13,200.00 198.00
0.1100 oh Tukang cat 95,000.00 10,450.00
0.0110 oh Kepala Tukang 110,000.00 1,210.00
Total : 11,660.00 19,272.00 30,932.00
12 1 M2 PEKERJAAN PENGECATAN DASAR 1 LAPIS PADA KAYU
0.1700 kg Cat Dasar 49,500.00 8,415.00
0.1000 Ltr Minyak Cat 46,530.00 4,653.00
1.0000 Lbr Amplas 6,600.00 6,600.00
0.0150 Bh Kuas 13,200.00 198.00
0.0750 oh Tukang cat 95,000.00 7,125.00
0.0080 oh Kepala Tukang 110,000.00 880.00
Total : 8,005.00 19,866.00 27,871.00
13 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA KAYU
0.3000 kg Cat Tembok setara Vinilex 49,500.00 14,850.00
0.2000 Ltr Minyak Cat 46,530.00 9,306.00
0.0200 Bh Kuas 13,200.00 264.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.1500 oh Tukang cat 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 28,150.00 24,420.00 52,570.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
1 M2 PEKERJAAN MENGEROK KARAT ATAU CAT PADA PERMUKAAN BAJA
14
DENGAN SODA API
0.5000 Lbr Amplas 6,600.00 3,300.00
0.0500 Bh Sikat Baja 33,220.00 1,661.00
0.0500 Kg Soda Api 24,200.00 1,210.00
0.3000 oh Pekerja 75,000.00 22,500.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 24,375.00 6,171.00 30,546.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
15 1 M2 PEKERJAAN MELAPIS MENI PADA PERMUKAAN BAJA
0.1000 kg Meni 49,500.00 4,950.00
0.1000 Kg Minyak Cat 46,530.00 4,653.00
0.5000 Bh Amplas 6,600.00 3,300.00
0.0150 Bh Kuas 13,200.00 198.00
0.0750 oh Pekerja 75,000.00 5,625.00
0.0040 oh Mandor 125,000.00 500.00
Total : 6,125.00 13,101.00 19,226.00
1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA
16
SECARA MANUAL
0.2000 Kg Cat Warna Zingkronasi 110,000.00 22,000.00
0.1000 Kg Minyak Cat 46,530.00 4,653.00
0.0200 Bh Kuas 6,600.00 132.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.1500 oh Tukang cat 95,000.00 14,250.00
0.0150 oh Kepala Tukang 110,000.00 1,650.00
0.0080 oh Mandor 125,000.00 1,000.00
Total : 28,150.00 26,785.00 54,935.00
17 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN
BAJA/KAYU DENGAN SEMPROT
0.4000 kg Cat Warna Zingkronasi 110,000.00 44,000.00
0.1000 Ltr Minyak Cat 46,530.00 4,653.00
0.0200 oh Pekerja 75,000.00 1,500.00
0.1500 oh Tukang cat 95,000.00 14,250.00
0.0010 oh Kepala Tukang 110,000.00 110.00
0.0010 oh Mandor 125,000.00 125.00
Total : 235.00 48,653.00 48,888.00
18 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN TEAK OIL
0.3000 Ltr Teak Oil 66,550.00 19,965.00
0.5000 Lbr Amplas 6,600.00 3,300.00
0.0150 Bh Kuas 13,200.00 198.00
0.1000 oh Tukang cat 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
Total : 10,600.00 23,463.00 34,063.00
19 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN POLITUR 2 LAPIS
0.1000 Kg Wood Filler 60,500.00 6,050.00
0.2000 Ltr Politur Jadi 75,900.00 15,180.00
1.0000 Lbr Amplas 6,600.00 6,600.00
0.0200 Bh Kuas 13,200.00 264.00
0.2500 oh Pekerja 75,000.00 18,750.00
0.2500 oh Tukang cat 95,000.00 23,750.00
0.0250 oh Kepala Tukang 110,000.00 2,750.00
0.0130 oh Mandor 125,000.00 1,625.00
Total : 46,875.00 28,094.00 74,969.00
20 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN VERNIS 2 LAPIS
0.3000 Ltr Vernis 60,500.00 18,150.00
0.5000 Lbr Amplas 6,600.00 3,300.00
0.0200 Bh Kuas 13,200.00 264.00
0.1000 oh Tukang cat 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
Total : 10,600.00 21,714.00 32,314.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
21 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN RESIDU/TER
0.3500 Ltr Residu / Ter 27,500.00 9,625.00
0.0300 Ltr Minyak Tanah 3,000.00 90.00
0.0200 Bh Kuas 13,200.00 264.00
0.1000 oh Tukang cat 95,000.00 9,500.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
Total : 10,600.00 9,979.00 20,579.00
XV PEKERJAAN STYLE BALI
1 1 M2 PASANGAN BATA GOSOK 2 MUKA
110.0000 bh Bata Gosok 3,250.00 357,500.00
8.4000 kg Semen 50 Kg 1,450.00 12,180.00
Upah Kerja ( Lumpsum) 350,000.00 350,000.00
Total : 350,000.00 369,680.00 719,680.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA
13.7500 bh Paras Kerobokan 13,750.00 189,062.50
8.4000 kg Semen 50 Kg 1,450.00 12,180.00
Upah Kerja ( Lumpsum) 200,000.00 200,000.00
Total : 200,000.00 201,242.50 401,242.50
3 1 M2 PASANGAN BATA PRESS 1 MUKA
55.0000 bh Bata Press 3,250.00 178,750.00
4.2000 kg Semen 50 Kg 1,450.00 6,090.00
Upah Kerja ( Lumpsum) 200,000.00 200,000.00
Total : 200,000.00 184,840.00 384,840.00
4 1 M2 PASANGAN PARAS 1 MUKA
18.3333 bh Batu paras 11,687.50 214,270.83
4.2000 kg Semen 50 Kg 1,450.00 6,090.00
Upah Kerja ( Lumpsum) 200,000.00 200,000.00
Total : 200,000.00 220,360.83 420,360.83
5 1 M2 PASANGAN BATU PALIMANAN TEBAL 3 CM
12.5000 bh Batu Palimanan 11,500.00 143,750.00
4.2000 kg Semen 50 Kg 1,450.00 6,090.00
Upah Kerja ( Lumpsum) 200,000.00 200,000.00
Total : 200,000.00 149,840.00 349,840.00
6 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA
55.0000 bh Bata gosok 3,250.00 178,750.00
4.4917 bh Batu paras 11,687.50 52,496.35
5.2500 kg Semen 50 Kg 1,450.00 7,612.50
Upah Kerja ( Lumpsum) 200,000.00 200,000.00
Total : 200,000.00 238,858.85 438,858.85
7 1 M2 PASANGAN BATA GOSOK DIUKIR
55.0000 bh Bata gosok 3,250.00 178,750.00
4.2000 kg Semen 50 Kg 1,450.00 6,090.00
Upah Kerja ( Lumpsum) 355,000.00 355,000.00
Total : 355,000.00 184,840.00 539,840.00
8 1 M2 PASANGAN BATU TABAS KARANGASEM DIUKIR
18.3333 bh Batu tabas 11,000.00 201,666.67
4.2000 kg Semen 50 Kg 1,450.00 6,090.00
Upah Kerja ( Lumpsum) 355,000.00 355,000.00
Total : 355,000.00 207,756.67 562,756.67
9 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR
55.0000 bh Bata gosok 3,250.00 178,750.00
4.4917 bh Batu paras 11,687.50 52,496.35
5.2500 kg Semen 50 Kg 1,450.00 7,612.50
Upah Kerja ( Lumpsum) 280,000.00 280,000.00
Total : 280,000.00 238,858.85 518,858.85
10 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP IJUK
30.0000 bh Batu hitam singaraja 20 x 40 9,900.00 297,000.00
1.0000 kg Semen 40 kg gresik 1,450.00 1,450.00
0.9800 m3 kayu cempaka 2,860,000.00 2,802,800.00
90.0000 kg ijuk 1,980.00 178,200.00
Upah Kerja ( Lumpsum) 350,000.00 350,000.00
Total : 350,000.00 3,279,450.00 3,629,450.00
11 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP GENTENG
26.0000 bh Batu hitam singaraja 20 x 40 9,900.00 257,400.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
1.0000 kg Semen 40 kg gresik 1,450.00 1,450.00
0.7600 m3 kayu cempaka 2,860,000.00 2,173,600.00
90.0000 bh genteng plentong 2,420.00 217,800.00
20.0000 bh bubungan mini 13,200.00 264,000.00
Upah Kerja ( Lumpsum) 300,000.00 300,000.00
Total : 300,000.00 2,914,250.00 3,214,250.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
12 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP IJUK
150.0000 bh Bata gosok ex tulikup 5,850.00 877,500.00
100.0000 bh paras silakarang 25,000.00 2,500,000.00
1.0000 sak Semen 40 kg gresik 1,450.00 1,450.00
0.9800 m3 kayu cempaka 2,860,000.00 2,802,800.00
98.0000 kg ijuk 1,980.00 194,040.00
Upah Kerja ( Lumpsum) 350,000.00 350,000.00
Total : 350,000.00 6,375,790.00 6,725,790.00
13 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP GENTENG
125.0000 bh Bata gosok ex tulikup 5,850.00 731,250.00
82.0000 bh paras silakarang 25,000.00 2,050,000.00
0.7650 m3 kayu cempaka 2,860,000.00 2,187,900.00
1.0000 sak Semen 40 kg gresik 1,450.00 1,450.00
90.0000 bh genteng plentong 2,420.00 217,800.00
20.0000 bh bubungan mini 13,200.00 264,000.00
Upah Kerja ( Lumpsum) 300,000.00 300,000.00
Total : 300,000.00 5,452,400.00 5,752,400.00
14 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP IJUK 190cmX190cm
65.0000 bh Batu hitam singaraja 20 x 40 9,900.00 643,500.00
1.2000 sak Semen 40 kg gresik 1,450.00 1,740.00
1.8500 m3 kayu cempaka 2,860,000.00 5,291,000.00
315.0000 kg ijuk 1,980.00 623,700.00
Upah Kerja ( Lumpsum) 750,000.00 750,000.00
Total : 750,000.00 6,559,940.00 7,309,940.00
15 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP GENTENG 190cmx190cm
65.0000 bh Batu hitam singaraja 20 x 40 9,900.00 643,500.00
1.2000 sak Semen 40 kg gresik 1,450.00 1,740.00
1.4000 m3 kayu cempaka 2,860,000.00 4,004,000.00
110.0000 bh genteng plentong 2,420.00 266,200.00
40.0000 bh bubungan mini 13,200.00 528,000.00
Upah Kerja ( Lumpsum) 650,000.00 650,000.00
Total : 650,000.00 5,443,440.00 6,093,440.00
16 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP IJUK 190cmx190cm
305.0000 bh Bata ex tulikup 5,850.00 1,784,250.00
210.0000 bh paras silakarang 25,000.00 5,250,000.00
1.2000 sak Semen 40 kg gresik 1,450.00 1,740.00
1.8800 m3 kayu cempaka 2,860,000.00 5,376,800.00
315.0000 kg ijuk 1,980.00 623,700.00
Upah Kerja ( Lumpsum) 750,000.00 750,000.00
Total : 750,000.00 13,036,490.00 13,786,490.00
17 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP GENTENG 190cmx190cm
305.0000 bh Bata ex tulikup 5,850.00 1,784,250.00
210.0000 bh paras silakarang 25,000.00 5,250,000.00
1.4300 m3 kayu cempaka 2,860,000.00 4,089,800.00
110.0000 bh genteng plentong 2,420.00 266,200.00
40.0000 bh bubungan mini 13,200.00 528,000.00
Upah Kerja ( Lumpsum) 750,000.00 750,000.00
Total : 750,000.00 11,918,250.00 12,668,250.00
18 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP IJUK 200CMX200CM
230.0000 bh Batu hitam singaraja 20 x 40 9,900.00 2,277,000.00
4.0000 sak Semen 40 kg gresik 1,450.00 5,800.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
3.2400 m3 kayu cempaka 2,860,000.00 9,266,400.00
470.0000 kg ijuk 1,980.00 930,600.00
Upah Kerja ( Lumpsum) 1,500,000.00 1,500,000.00
Total : 1,500,000.00 12,479,800.00 13,979,800.00
19 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP GENTENG 200CMX200CM
230.0000 bh Batu hitam singaraja 20 x 40 9,900.00 2,277,000.00
4.0000 sak Semen 40 kg gresik 1,450.00 5,800.00
3.0000 m3 kayu cempaka 2,860,000.00 8,580,000.00
225.0000 bh genteng plentong 2,420.00 544,500.00
75.0000 bh bubungan mini 13,200.00 990,000.00
Upah Kerja ( Lumpsum) 1,500,000.00 1,500,000.00
Total : 1,500,000.00 12,397,300.00 13,897,300.00
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
20 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP IJUK 200CMX200CM
525.0000 bh Bata ex tulikup 5,850.00 3,071,250.00
350.0000 bh paras silakarang 25,000.00 8,750,000.00
5.5000 sak Semen 40 kg gresik 1,450.00 7,975.00
3.2400 m3 kayu cempaka 2,860,000.00 9,266,400.00
470.0000 kg ijuk 1,980.00 930,600.00
Upah Kerja ( Lumpsum) 1,500,000.00 1,500,000.00
Total : 1,500,000.00 22,026,225.00 23,526,225.00

21 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP GENTENG 200CMX200CM

525.0000 bh Bata ex tulikup 5,850.00 3,071,250.00


350.0000 bh paras silakarang 25,000.00 8,750,000.00
5.5000 sak Semen 40 kg gresik 1,450.00 7,975.00
3.0000 m3 kayu cempaka 2,860,000.00 8,580,000.00
225.0000 bh genteng plentong 2,420.00 544,500.00
75.0000 bh bubungan mini 13,200.00 990,000.00
Upah Kerja ( Lumpsum) 1,500,000.00 1,500,000.00
Total : 1,500,000.00 21,943,725.00 23,443,725.00
26 1 UNIT SANGGAH TAKSU BATU HITAM ATAP IJUK 40cmx40cm
20.0000 bh Batu hitam singaraja 20 x 40 9,900.00 198,000.00
0.7500 sak Semen 40 kg gresik 1,450.00 1,087.50
0.6300 m3 kayu cempaka 2,860,000.00 1,801,800.00
75.0000 kg ijuk 1,980.00 148,500.00
Upah Kerja ( Lumpsum) 300,000.00 300,000.00
Total : 300,000.00 2,149,387.50 2,449,387.50
27 1 UNIT SANGGAH TAKSU BATU HITAM ATAP GENTENG 40cmx40cm
21.0000 bh Batu hitam singaraja 20 x 40 9,900.00 207,900.00
0.7500 sak Semen 40 kg gresik 1,450.00 1,087.50
0.6300 m3 kayu cempaka 2,860,000.00 1,801,800.00
75.0000 bh genteng plentong 2,420.00 181,500.00
16.0000 bh bubungan mini 13,200.00 211,200.00
Upah Kerja ( Lumpsum) 300,000.00 300,000.00 -
Total : 300,000.00 2,403,487.50 2,703,487.50
28 1 UNIT SANGGAH TAKSU PARAS BATA ATAP IJUK 40cmx40cm
100.0000 bh Bata gosok ex tulikup 5,850.00 585,000.00
75.0000 bh paras silakarang 25,000.00 1,875,000.00
0.8500 sak Semen 40 kg gresik 1,450.00 1,232.50
0.6150 m3 kayu cempaka 2,860,000.00 1,758,900.00
75.0000 kg ijuk 1,980.00 148,500.00
Upah Kerja ( Lumpsum) 300,000.00 300,000.00 -
Total : 300,000.00 4,368,632.50 4,668,632.50
29 1 UNIT SANGGAH TAKSU PARAS BATA ATAP GENTENG 40cmx40cm
100.0000 bh Bata gosok ex tulikup 5,850.00 585,000.00
75.0000 bh paras silakarang 25,000.00 1,875,000.00
0.8500 sak Semen 40 kg gresik 1,450.00 1,232.50
0.6000 m3 kayu cempaka 2,860,000.00 1,716,000.00
70.0000 bh genteng plentong 2,420.00 169,400.00
16.0000 bh bubungan mini 13,200.00 211,200.00
Upah Kerja ( Lumpsum) 300,000.00 300,000.00 -
Total : 300,000.00 4,557,832.50 4,857,832.50
XVI PEKERJAAN HARDDSCAPE
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225
1.0500 m2 Paving 10 x 20 cm tebal 6 cm K225 78,650.00 82,582.50
0.1000 m3 Pasir Urug 183,750.00 18,375.00
0.2500 oh Tukang Batu 95,000.00 23,750.00
0.5000 oh Pekerja 75,000.00 37,500.00
0.0250 oh Mandor 125,000.00 3,125.00
Total : 64,375.00 100,957.50 165,332.50
2 1 M2 PASANGAN Paving 10 x 20 cm tebal 6 cm K350 90,750.00 64,375.00 113,662.50 178,037.50
3 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K225 79,860.00 64,375.00 102,228.00 166,603.00
4 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K350 99,550.00 64,375.00 122,902.50 187,277.50
5 1 M2 PASANGAN Paving 20 x 20 cm tebal 6 cm K350 90,750.00 64,375.00 113,662.50 178,037.50
6 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225 79,860.00 64,375.00 102,228.00 166,603.00
7 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K350 99,770.00 64,375.00 123,133.50 187,508.50
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
8 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 pc 70,400.00 64,375.00 92,295.00 156,670.00
9 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 merah 92,000.00 64,375.00 114,975.00 179,350.00
10 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 hitam 90,000.00 64,375.00 112,875.00 177,250.00
11 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 pc 73,000.00 64,375.00 95,025.00 159,400.00
12 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 merah 98,000.00 64,375.00 121,275.00 185,650.00
13 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 hitam 97,000.00 64,375.00 120,225.00 184,600.00
14 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 pc 76,000.00 64,375.00 98,175.00 162,550.00
15 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 merah 101,000.00 64,375.00 124,425.00 188,800.00
16 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 hitam 100,000.00 64,375.00 123,375.00 187,750.00
17 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 pc 84,000.00 64,375.00 106,575.00 170,950.00
18 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 merah 109,000.00 64,375.00 132,825.00 197,200.00
19 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 hitam 108,000.00 64,375.00 131,775.00 196,150.00
20 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 pc 66,000.00 64,375.00 87,675.00 152,050.00
21 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 merah 89,000.00 64,375.00 111,825.00 176,200.00
22 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 hitam 87,000.00 64,375.00 109,725.00 174,100.00
23 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 pc 72,000.00 64,375.00 93,975.00 158,350.00
24 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 merah 106,000.00 64,375.00 129,675.00 194,050.00
25 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 hitam 104,000.00 64,375.00 127,575.00 191,950.00
26 1 M2 PASANGAN Paving Tiga Berlian tebal 6 cm K225 pc 75,460.00 64,375.00 97,608.00 161,983.00
27 1 M2 PASANGAN GRASS BLOCK
1.0000 m2 Grass Block 61,000.00 61,000.00
0.0690 m3 Pasir Urug 183,750.00 12,678.75
0.5000 oh Tukang Batu 95,000.00 47,500.00
0.0500 oh Kepala Tukang 110,000.00 5,500.00
1.0000 oh Pekerja 75,000.00 75,000.00
0.0500 oh Mandor 125,000.00 6,250.00
Total : 134,250.00 73,678.75 207,928.75
28 1 M2 PASANGAN KORAL SIKAT
1.2000 zak Koral Sikat 45,000.00 54,000.00
9.2800 zak Semen 1,450.00 13,456.00
0.2000 m3 Pasir pasang 230,000.00 46,000.00
0.2500 oh Tukang Batu 95,000.00 23,750.00
0.0100 oh Kepala Tukang 110,000.00 1,100.00
0.6250 oh Pekerja 75,000.00 46,875.00
0.0310 oh Mandor 125,000.00 3,875.00
Total : 75,600.00 113,456.00 189,056.00
29 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225
2.0000 bh Kanstein Bulat(P:50,T:30,La:10,Lb:16 cm K225 29,150.00 58,300.00
2.1000 Kg Semen 50 Kg 1,450.00 3,045.00
0.0060 m3 Pasir Urug 183,750.00 1,102.50
0.3500 oh Tukang Batu 95,000.00 33,250.00
0.9500 oh Pekerja 75,000.00 71,250.00
0.0162 oh Mandor 125,000.00 2,025.00
Total : 106,525.00 62,447.50 168,972.50
30 Kanstein Jumbo (P:50,L:15,T:30 cm K225) 35,000.00 106,525.00 74,147.50 180,672.50
31 Kanstein kotak (P:50,t.20,La.10,Lb.16cm) K225 27,000.00 106,525.00 58,147.50 164,672.50
32 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) 46,000.00 106,525.00 96,147.50 202,672.50
33 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) 49,500.00 106,525.00 103,147.50 209,672.50
34 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) 25,000.00 106,525.00 54,147.50 160,672.50
35 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) 20,000.00 106,525.00 44,147.50 150,672.50
36 1 Buah Pasangan Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) 35,750.00 106,525.00 75,647.50 182,172.50
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
37 1 M2 PENGECATAN KANSTEIN
0.2840 kg Cat 64,460.00 18,306.64
0.0710 kg Thiner 27,500.00 1,952.50
0.0300 oh Tukang Cat 95,000.00 2,850.00
0.0030 oh Kep. Tukang 110,000.00 330.00
0.1500 oh Pekerja 75,000.00 11,250.00
0.0150 oh Mandor 125,000.00 1,875.00
Total : 16,305.00 20,259.14 36,564.14
HARGA HARGA HARGA HARGA
NO URAIAN
SATUAN (Rp) UPAH (Rp) BAHAN (Rp) JUMLAH (Rp)

1 2 3 4 5 6
XVII PEKERJAAN ELEKTRIKAL
1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN
8.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 11,000.00 88,000.00
3.0000 bt Pipa Clipsal 20 mm hitam 3,300.00 9,900.00
2.0000 bh Tee dos clipsal 20 mm hitam 7,480.00 14,960.00
15.0000 bj Klem clipsal 20 mm hitam 11,025.00 165,375.00
3.0000 bj Sock clipsal 20 mm hitam 3,300.00 9,900.00
1.0000 bj Inbow dos plastik clipsal E 157 P 11,935.00 11,935.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00
Total : 25,000.00 300,070.00 325,070.00
2 1 TITIK INSTALASI AC
10.0000 m1 Kabel NYM 3 x 2.5 mm ex. Supreme 11,000.00 110,000.00
3.0000 bt Pipa Clipsal 20 mm hitam 3,300.00 9,900.00
1.0000 bh Tee dos clipsal 20 mm hitam 7,480.00 7,480.00
15.0000 bj Klem clipsal 20 mm hitam 11,025.00 165,375.00
4.0000 bj Sock clipsal 20 mm hitam 3,300.00 13,200.00
1.0000 bj Inbow dos plastik clipsal E 157 P 11,935.00 11,935.00
1.0000 m1 Pipa flexible clipsal 20 mm hitam 11,000.00 11,000.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00 25,000.00
Total : 25,000.00 353,890.00 378,890.00
3 1 TITIK INSTALASI TELEPHONE
25.0000 m1 Kabel telephone 17,482.50 437,062.50
8.0000 bt Pipa Clipsal 20 mm putih 3,300.00 26,400.00
1.0000 bh Tee dos clipsal 20 mm putih 7,480.00 7,480.00
25.0000 bj Klem clipsal 20 mm putih 11,025.00 275,625.00
5.0000 bj Sock clipsal 20 mm putih 3,300.00 16,500.00
1.0000 bj Inbow dos plastik clipsal E 157 P 11,935.00 11,935.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00
Total : 25,000.00 775,002.50 800,002.50
4 1 TITIK INSTALASI MATV
20.0000 m1 Coaxial cable 5C-75 ohm commscof 18,700.00 374,000.00
6.0000 bt Pipa Clipsal 20 mm putih 3,300.00 19,800.00
2.0000 bh Tee dos clipsal 20 mm putih 7,480.00 14,960.00
20.0000 bj Klem clipsal 20 mm putih 11,025.00 220,500.00
6.0000 bj Sock clipsal 20 mm putih 3,300.00 19,800.00
1.0000 bj Inbow dos plastik clipsal E 157 P 11,935.00 11,935.00
1.0000 ttk Biaya pasang 25,000.00 25,000.00
Total : 25,000.00 660,995.00 685,995.00
1 1 M2 Finishing lantai Epoxy Floor Coating Setara Polyfloor PU Concrete PFT - 253 MF Propan Multipox (3000 Micron)
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja OH 0.1200 75,000.00 9,000.00
Tukang batu OH 0.1200 95,000.00 11,400.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0060 125,000.00 750.00
JUMLAH TENAGA KERJA 22,470.00
B. BAHAN
Primer Coat - Polyfloor PU Concrete PFT - 253 MF (1000 Micron) m2 1.0000 132,000.00 132,000.00
Top Coat - Polyfloor PU Concrete PFT - 253 MF (2000 Micron) m2 1.0000 270,000.00 270,000.00

JUMLAH HARGA BAHAN 402,000.00

C. PERALATAN
Alat Bantu ls 1.0000 5,000.00 5,000.00
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 429,470.00
E. Overhead & Profit %xD -
F. Harga Satuan Pekerjaan (D+E) 429,470.00

2 1 M2 Finishing lantai Epoxy Floor Coating Setara Polyfloor PFT - 253 MF Propan Multipox (2000 Micron)
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja OH 0.1200 75,000.00 9,000.00
Tukang batu OH 0.1200 95,000.00 11,400.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0060 125,000.00 750.00
JUMLAH TENAGA KERJA 22,470.00
B. BAHAN
Primer Coat - Polyfloor Epoxy Primer PFP 241 (50 Micron) m2 1.0000 9,800.00 9,800.00
First Coat - Polyfloor PFT - 253 (500 Micron) m2 1.0000 98,000.00 98,000.00
Top Coat - Polyfloor PFT - 253 (1500 Micron) m2 1.0000 294,000.00 294,000.00
JUMLAH HARGA BAHAN 401,800.00

C. PERALATAN
Alat Bantu ls 1.0000 5,000.00 5,000.00
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 429,270.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 429,270.00

3 1 M2 Finishing lantai Epoxy Floor Coating + Pasir Silica Setara Polyfloor PFT - 253 Propan Multipox (2000 Micron)
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja OH 0.1200 75,000.00 9,000.00
Tukang batu OH 0.1200 95,000.00 11,400.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0060 125,000.00 750.00
JUMLAH TENAGA KERJA 22,470.00
B. BAHAN
Primer Coat - Polyfloor Epoxy Primer PFP 241 (50 Micron) m2 1.0000 9,185.00 9,185.00
First Coat - Polyfloor PFT - 253 (500 Micron) m2 1.0000 91,850.00 91,850.00
Broadcast Layer (Tabur Pasir Silica)
Top Coat - Polyfloor PFT - 253 (1500 Micron) m2 1.0000 275,550.00 275,550.00
JUMLAH HARGA BAHAN 376,585.00

C. PERALATAN
Alat Bantu ls 1.0000 5,000.00 5,000.00
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 404,055.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 404,055.00
4 1 M2 Finishing lantai Floor Hardener Setara Propan Multipox
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja OH 0.1200 75,000.00 9,000.00
Tukang batu OH 0.1200 95,000.00 11,400.00
Kepala Tukang OH 0.0120 110,000.00 1,320.00
Mandor OH 0.0060 125,000.00 750.00
JUMLAH TENAGA KERJA 22,470.00
B. BAHAN
First Layer - Silikat Penetran LD-201 m2 1.0000 85,000.00 85,000.00
Second Layer - Silikat Toping CC-203 m2 1.0000 91,900.00 91,900.00
JUMLAH HARGA BAHAN 176,900.00

C. PERALATAN
Alat Bantu ls 1.0000 5,000.00 5,000.00
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 204,370.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 204,370.00

5 1 M2 Semen Base Setara Sika Top Seal 107


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang cat OH 0.1000 95,000.00 9,500.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0100 125,000.00 1,250.00
JUMLAH TENAGA KERJA 19,350.00
B. BAHAN
Waterproofing sika kg 1.0000 17,500.00 17,500.00
JUMLAH HARGA BAHAN 17,500.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 36,850.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 36,850.00

6 1 M2 Pasangan Granite Tile 60x60 Setara Niro Granite Regal GMR81 Series Polished
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000 75,000.00 52,500.00
Tukang batu OH 0.3500 95,000.00 33,250.00
Kepala Tukang OH 0.0350 110,000.00 3,850.00
Mandor OH 0.0350 125,000.00 4,375.00
JUMLAH TENAGA KERJA 93,975.00
B. BAHAN
Granite Tile 60x60 m2 1.1000 345,000.00 379,500.00
Semen Portland kg 10.0000 1,450.00 14,500.00
Pasir Pasang m3 0.0450 230,000.00 10,350.00
Semen warna/semen grouting kg 1.0000 25,620.00 25,620.00
JUMLAH HARGA BAHAN 429,970.00

C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 523,945.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 523,945.00
7 1 M2 Pasangan Granite Tile 30x30 Setara Niro Granite Nordik Stone GSN02 Series Structured
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000 75,000.00 52,500.00
Tukang batu OH 0.3500 95,000.00 33,250.00
Kepala Tukang OH 0.0350 110,000.00 3,850.00
Mandor OH 0.0350 125,000.00 4,375.00
JUMLAH TENAGA KERJA 93,975.00
B. BAHAN
Granite Tile 30x30 m2 1.1000 180,000.00 198,000.00
Semen Portland kg 10.0000 1,450.00 14,500.00
Pasir Pasang m3 0.0450 230,000.00 10,350.00
Semen warna/semen grouting kg 1.3000 25,620.00 33,306.00
JUMLAH HARGA BAHAN 256,156.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 350,131.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 350,131.00

8 1 M2 Pasangan Lantai Keramik 30x30 Setara Platinum


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000 75,000.00 52,500.00
Tukang batu OH 0.3500 95,000.00 33,250.00
Kepala Tukang OH 0.0350 110,000.00 3,850.00
Mandor OH 0.0350 125,000.00 4,375.00
JUMLAH TENAGA KERJA 93,975.00
B. BAHAN
Keramik 30x30 m2 1.1000 65,000.00 71,500.00
Semen Portland kg 10.0000 1,450.00 14,500.00
Pasir Pasang m3 0.0450 230,000.00 10,350.00
Semen warna/semen grouting kg 1.3000 25,620.00 33,306.00
JUMLAH HARGA BAHAN 129,656.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 223,631.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 223,631.00

9 1 M2 Pasangan Lantai Keramik 30x30 Setara Platinum, Anti Slip


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000 75,000.00 52,500.00
Tukang batu OH 0.3500 95,000.00 33,250.00
Kepala Tukang OH 0.0350 110,000.00 3,850.00
Mandor OH 0.0350 125,000.00 4,375.00
JUMLAH TENAGA KERJA 93,975.00
B. BAHAN
Keramik 30x30 m2 1.1000 70,000.00 77,000.00
Semen Portland kg 10.0000 1,450.00 14,500.00
Pasir Pasang m3 0.0450 230,000.00 10,350.00
Semen warna/semen grouting kg 1.3000 25,620.00 33,306.00
JUMLAH HARGA BAHAN 135,156.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 229,131.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 229,131.00
10 1 M1 Pasangan Plint Granit Tile 10 X 60 CM Setara Niro Granite Regal GMR81 Series Polished
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0900 75,000.00 6,750.00
Tukang batu OH 0.0900 95,000.00 8,550.00
Kepala Tukang OH 0.0090 110,000.00 990.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 16,915.00
B. BAHAN
Grinte Tile 10 x 60 cm bh 1.6667 115,000.00 191,666.67
Semen Portland kg 1.1400 1,450.00 1,653.00
Pasir Pasang m3 0.0030 230,000.00 690.00
Semen warna/semen grouting kg 0.1000 25,620.00 2,562.00
JUMLAH HARGA BAHAN 196,571.67

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 213,486.67
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 213,486.67

11 1 M1 Pasangan Plint Keramik 10x30 cm Setara Platinum


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0900 75,000.00 6,750.00
Tukang batu OH 0.0900 95,000.00 8,550.00
Kepala Tukang OH 0.0090 110,000.00 990.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 16,915.00
B. BAHAN
Keramik 10 x 30 cm bh 3.3333 5,909.09 19,696.97
Semen Portland kg 1.1400 1,450.00 1,653.00
Pasir Pasang m3 0.0030 230,000.00 690.00
Semen warna/semen grouting kg 0.1000 25,620.00 2,562.00
JUMLAH HARGA BAHAN 24,601.97

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 41,516.97
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 41,516.97

12 1 M2 Pasangan Granit Tile Dinding 30x60 Setara Niro Granite Nordik Stone GSN02 Series Structured
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.9000 75,000.00 67,500.00
Tukang batu OH 0.4500 95,000.00 42,750.00
Kepala Tukang OH 0.0450 110,000.00 4,950.00
Mandor OH 0.0450 125,000.00 5,625.00
JUMLAH TENAGA KERJA 120,825.00
B. BAHAN
Keramik 20x25 m2 1.1000 315,000.00 346,500.00
Semen Portland kg 9.3000 1,450.00 13,485.00
Pasir Pasang m3 0.0180 230,000.00 4,140.00
Semen warna/semen grouting kg 1.9400 25,620.00 49,702.80
JUMLAH HARGA BAHAN 413,827.80

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 534,652.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 534,652.80
13 1 M2 Pasangan Keramik Dinding 30x30 Setara Platinum
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.9000 75,000.00 67,500.00
Tukang batu OH 0.4500 95,000.00 42,750.00
Kepala Tukang OH 0.0450 110,000.00 4,950.00
Mandor OH 0.0450 125,000.00 5,625.00
JUMLAH TENAGA KERJA 120,825.00
B. BAHAN
Keramik 20x25 m2 1.1000 65,000.00 71,500.00
Semen Portland kg 9.3000 1,450.00 13,485.00
Pasir Pasang m3 0.0180 230,000.00 4,140.00
Semen warna/semen grouting kg 1.9400 25,620.00 49,702.80
JUMLAH HARGA BAHAN 138,827.80

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 259,652.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 259,652.80

14 1 M1 Pasang List Gypsum 7 cm


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0150 75,000.00 1,125.00
Tukang Kayu OH 0.0250 105,000.00 2,625.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 9,875.00
B. BAHAN
List gypsum 7cm m2 1.1000 22,800.00 25,080.00
Cornice kg 1.0000 3,250.00 3,250.00
JUMLAH HARGA BAHAN 28,330.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 38,205.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 38,205.00

15 1 M1 Kusen Aluminium 4'' Motif Kayu


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0600 75,000.00 4,500.00
Tukang Aluminium OH 0.0700 100,000.00 7,000.00
Kepala Tukang OH 0.0043 110,000.00 473.00
Mandor OH 0.0021 125,000.00 262.50
JUMLAH TENAGA KERJA 12,235.50
B. BAHAN
Kusen aluminium 4" motif kayu m1 1.1000 185,000.00 203,500.00
Material bantu ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA BAHAN 213,500.00
C. PERALATAN -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 225,735.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 225,735.50
16 1 UnitPasang Engsel Pivot Setara Solid
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0150 75,000.00 1,125.00
Tukang Kayu OH 0.2000 105,000.00 21,000.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 28,250.00
B. BAHAN
Engsel Pivot BH 1.0000 450,000.00 450,000.00
JUMLAH HARGA BAHAN 450,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 478,250.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 478,250.00

17 1 PS Pasang Handel Pintu Kaca Setara Solid


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0150 75,000.00 1,125.00
Tukang Kayu OH 0.2000 105,000.00 21,000.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 28,250.00
B. BAHAN
Handle Pintu Kaca BH 1.0000 620,000.00 620,000.00
JUMLAH HARGA BAHAN 620,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 648,250.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 648,250.00

18 1 PS Pasang Handel Pintu Biasa Setara Solid


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0150 75,000.00 1,125.00
Tukang Kayu OH 0.2000 105,000.00 21,000.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 28,250.00
B. BAHAN
Handle Pintu BH 1.0000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 278,250.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 278,250.00

19 1 PS Pasang Door Closer Setara Solid


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 75,000.00 30,000.00
Tukang Kayu OH 0.7000 105,000.00 73,500.00
Kepala Tukang OH 0.2000 110,000.00 22,000.00
Mandor OH 0.0200 125,000.00 2,500.00
JUMLAH TENAGA KERJA 128,000.00
B. BAHAN
Door Closer BH 1.0000 350,000.00 350,000.00
JUMLAH HARGA BAHAN 350,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 478,000.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 478,000.00
20 1 PS Pasang Door Stopper Setara Solid
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.0150 75,000.00 1,125.00
Tukang Kayu OH 0.2000 105,000.00 21,000.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 28,250.00
B. BAHAN
Door stoper BH 1.0000 85,000.00 85,000.00
JUMLAH HARGA BAHAN 85,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 113,250.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 113,250.00

21 1 BH Pasang Grendel Setara Solid


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.0150 75,000.00 1,125.00
Tukang Kayu OH 0.1000 105,000.00 10,500.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 17,750.00
B. BAHAN
Grendel BH 1.0000 135,000.00 135,000.00
JUMLAH HARGA BAHAN 135,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 152,750.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 152,750.00

22 1 M1 Railing Tangga Pipa Schedule sch 80 diameter 2 inch Stainless Steel


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.6000 75,000.00 45,000.00
Tukang besi OH 1.0000 100,000.00 100,000.00
Kepala Tukang OH 0.2000 110,000.00 22,000.00
Mandor OH 0.0200 125,000.00 2,500.00
JUMLAH TENAGA KERJA 169,500.00
B. BAHAN
Pipa Schedule sch 80 diameter 2 inch Stainless Steel M1 1.1000 151,333.33 166,466.67
Bahan las ls 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 216,466.67

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 385,966.67
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 385,966.67

23 1 M1 Railing Tangga Besi Hollow Galvanis Kom. 40x40x2mm Dan 20x20x1,7mm


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.6000 75,000.00 45,000.00
Tukang besi OH 1.0000 100,000.00 100,000.00
Kepala Tukang OH 0.2000 110,000.00 22,000.00
Mandor OH 0.0200 125,000.00 2,500.00
JUMLAH TENAGA KERJA 169,500.00
B. BAHAN
Besi hollow Galvanis 40x40x2mm M1 5.5000 67,500.00 371,250.00
Besi hollow Galvanis 20x20x1,7mm M1 3.5000 24,833.33 86,916.67
Bahan las ls 1.0000 100,000.00 100,000.00
Cat avian ltr 0.4000 55,000.00 22,000.00
tiner ltr 0.2000 35,000.00 7,000.00
JUMLAH HARGA BAHAN 587,166.67
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 756,666.67
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 756,666.67
24 1 M1 Grill Kios Besi Hollow Galvanis Kom. 40x40x2mm Dan 20x20x1,7mm
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 75,000.00 22,500.00
Tukang besi OH 0.5000 100,000.00 50,000.00
Kepala Tukang OH 0.1000 110,000.00 11,000.00
Mandor OH 0.0100 125,000.00 1,250.00
JUMLAH TENAGA KERJA 84,750.00
B. BAHAN
Besi hollow Galvanis 40x40x2mm M1 2.7500 67,500.00 185,625.00
Besi hollow Galvanis 20x20x1,7mm M1 1.7500 24,833.33 43,458.33
Bahan las ls 0.5000 100,000.00 50,000.00
Cat avian ltr 0.2000 55,000.00 11,000.00
tiner ltr 0.1000 35,000.00 3,500.00
JUMLAH HARGA BAHAN 293,583.33

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 378,333.33
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 378,333.33

25 1 M1 Grill Besi Drainase


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 75,000.00 22,500.00
Tukang besi OH 0.5000 100,000.00 50,000.00
Kepala Tukang OH 0.0200 110,000.00 2,200.00
Mandor OH 0.0010 125,000.00 125.00
JUMLAH TENAGA KERJA 74,825.00
B. BAHAN
besi siku 5cm m 3.2000 20,000.00 64,000.00
Besi strip m 6.0000 20,000.00 120,000.00
Bahan las ls 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 209,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 283,825.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 283,825.00

26 1 M2 Pemasangan Plat Stainless Steel 304 Tebal 15 mm


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6000 75,000.00 45,000.00
Tukang besi OH 1.0000 100,000.00 100,000.00
Kepala Tukang OH 0.2000 110,000.00 22,000.00
Mandor OH 0.0200 125,000.00 2,500.00
JUMLAH TENAGA KERJA 169,500.00
B. BAHAN
Plat Stainless Steel 304 Tebal 15 mm lbr 0.3359 1,627,920.00 546,869.12
Plywood 9 mm Setara Meranti m2 0.3359 148,500.00 49,885.78
Bahan las ls 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 646,754.90

C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 816,254.90
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 816,254.90
27 1 M2 Pengecatan Tembok Eksterior Setara Dulux Weathershield
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang cat OH 0.0630 95,000.00 5,985.00
Kepala Tukang OH 0.0063 110,000.00 693.00
Mandor OH 0.0025 125,000.00 312.50
JUMLAH TENAGA KERJA 14,490.50
B. BAHAN
Plamir kg 0.1000 159,500.00 15,950.00
Cat Penutup 2x kg 0.5000 126,500.00 63,250.00
JUMLAH HARGA BAHAN 79,200.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 93,690.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 93,690.50

28 1 M2 Pengecatan Tembok Interior Setara Dulux


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang cat OH 0.0630 95,000.00 5,985.00
Kepala Tukang OH 0.0063 110,000.00 693.00
Mandor OH 0.0025 125,000.00 312.50
JUMLAH TENAGA KERJA 14,490.50
B. BAHAN
Plamir kg 0.1000 159,500.00 15,950.00
Cat Penutup 2x kg 0.5000 93,500.00 46,750.00
JUMLAH HARGA BAHAN 62,700.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,190.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 77,190.50

29 1 M2 Pengecatan Tembok Dengan Waterproofing Setara Aquaproof


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang cat OH 0.1000 95,000.00 9,500.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0100 125,000.00 1,250.00
JUMLAH TENAGA KERJA 19,350.00
B. BAHAN
Plamir kg 0.1000 159,500.00 15,950.00
Cat Penutup 2x kg 0.8000 42,500.00 34,000.00
JUMLAH HARGA BAHAN 49,950.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 69,300.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 69,300.00

30 1 M2 Coating Batu Alam


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang cat OH 0.0630 95,000.00 5,985.00
Kepala Tukang OH 0.0063 110,000.00 693.00
Mandor OH 0.0025 125,000.00 312.50
JUMLAH TENAGA KERJA 14,490.50
B. BAHAN
Coaitng ltr 0.3000 53,000.00 15,900.00
Tinner ltr 0.3000 27,500.00 8,250.00
JUMLAH HARGA BAHAN 24,150.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 38,640.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 38,640.50
31 1 M2 Pasangan Kaca 8mm
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0630 75,000.00 4,725.00
Tukang besi OH 0.0730 100,000.00 7,300.00
Kepala Tukang OH 0.0650 110,000.00 7,150.00
Mandor OH 0.0800 125,000.00 10,000.00
JUMLAH TENAGA KERJA 29,175.00
B. BAHAN
Kaca bening 8mm M2 1.1000 317,900.00 349,690.00
Sealant Btl 3.5000 20,000.00 70,000.00
JUMLAH HARGA BAHAN 419,690.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 448,865.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 448,865.00

32 1 M2 Pasangan Partisi Toilet Setara Toilet Archi Cubicle Partition


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 75,000.00 11,250.00
Tukang besi OH 0.4500 100,000.00 45,000.00
Kepala Tukang OH 0.0450 110,000.00 4,950.00
Mandor OH 0.0080 125,000.00 1,000.00
JUMLAH TENAGA KERJA 62,200.00
B. BAHAN
- PanelPenolid Board Thick 12 mm, Hight 1,95 m M2 1.1000 1,510,000.00 1,661,000.00
- Finishing High Pressure Laminates (HPL)
- Pedestal A201 SS Adjustable Support
- Lock P166 Thum Turn Indicator Latch
- Hinge P150 Gravity Hinge
- Door Handle P155 Door Knops
- Dress Hook P152 Coat Hook
JUMLAH HARGA BAHAN 1,661,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,723,200.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,723,200.00

33 1 M2 Pemasangan Pembatas Los Besi Hollow Galvanis 40x40x2mm Kombinasi Kawat Besi Kotak
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja OH 0.1500 75,000.00 11,250.00
Tukang Besi OH 0.4500 100,000.00 45,000.00
Kepala Tukang OH 0.0450 110,000.00 4,950.00
Mandor OH 0.0080 125,000.00 1,000.00
JUMLAH TENAGA KERJA 62,200.00
B. BAHAN
Besi Hollow 4x4 Tebal 2 mm m' 2.1000 37,465.00 78,676.50
Stainless Steel Wire Mesh M5 m2 1.1000 220,000.00 242,000.00
Asesoris Ls 1.0000 35,000.00 35,000.00
Finishing Dan Material Bantu Ls 1.0000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 370,676.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 432,876.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 432,876.50
34 1 UNIT Wastafel Setara TOTO
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.5000 75,000.00 37,500.00
Tukang batu OH 1.0000 95,000.00 95,000.00
Kepala Tukang OH 0.2000 110,000.00 22,000.00
Mandor OH 0.0200 125,000.00 2,500.00
JUMLAH TENAGA KERJA 157,000.00
B. BAHAN
Wastafel Toto unit 1.0000 808,500.00 808,500.00
JUMLAH HARGA BAHAN 808,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 965,500.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 965,500.00

35 1 UNIT Floor Drain Setara TOTO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0800 75,000.00 6,000.00
Tukang batu OH 0.3000 95,000.00 28,500.00
Kepala Tukang OH 0.0300 110,000.00 3,300.00
Mandor OH 0.0030 125,000.00 375.00
JUMLAH TENAGA KERJA 38,175.00
B. BAHAN
Floor drainToto unit 1.0000 341,000.00 341,000.00
JUMLAH HARGA BAHAN 341,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 379,175.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 379,175.00

36 1 UNIT Bak Zink Setara Modena


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang batu OH 0.2000 95,000.00 19,000.00
Kepala Tukang OH 0.1000 110,000.00 11,000.00
Mandor OH 0.0025 125,000.00 312.50
JUMLAH TENAGA KERJA 37,812.50
B. BAHAN
Zink Satainless Steel unit 1.0000 450,000.00 450,000.00
JUMLAH HARGA BAHAN 450,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 487,812.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 487,812.50

37 1 M2 Pemasangan Atap Genteng Kodok Setara Goodyear


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 75,000.00 11,250.00
Tukang Kayu OH 0.0750 105,000.00 7,875.00
Kepala Tukang OH 0.0080 110,000.00 880.00
Mandor OH 0.0080 125,000.00 1,000.00
JUMLAH TENAGA KERJA 21,005.00
B. BAHAN
Genteng Kodok bh 25.0000 5,500.00 137,500.00
JUMLAH HARGA BAHAN 137,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 158,505.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 158,505.00
38 1 M1 Pemasangan Bubungan Denteng Kodok Setara Goodyear
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 75,000.00 30,000.00
Tukang cat OH 0.2000 105,000.00 21,000.00
Kepala Tukang OH 0.0200 110,000.00 2,200.00
Mandor OH 0.0020 125,000.00 250.00
JUMLAH TENAGA KERJA 53,450.00
B. BAHAN
Bubungan gemini bh 5.0000 17,600.00 88,000.00
Semen Portland kg 10.0000 1,450.00 14,500.00
Pasir pasang m3 0.0320 230,000.00 7,360.00
JUMLAH HARGA BAHAN 109,860.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 163,310.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 163,310.00

39 1 M1 Pemasangan Listplank Kayu Kamper Double


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 75,000.00 11,250.00
Tukang kayu OH 0.3000 105,000.00 31,500.00
Kepala Tukang OH 0.0300 110,000.00 3,300.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 46,675.00
B. BAHAN
Kayu kamper profil M3 0.0220 9,975,000.00 219,450.00
Paku KG 0.1000 18,000.00 1,800.00
JUMLAH HARGA BAHAN 221,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 267,925.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 267,925.00

40 1 M1 Pemasangan Tatab
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang kayu OH 0.1500 105,000.00 15,750.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0050 125,000.00 625.00
JUMLAH TENAGA KERJA 24,975.00
B. BAHAN
Kayu kamper profil m1 1.0000 35,000.00 35,000.00
Paku ls 0.1000 14,500.00 1,450.00
JUMLAH HARGA BAHAN 36,450.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 61,425.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 61,425.00

41 1 BH Pekerjaan Pasangan Murda Dan Ikut Celedu


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja / Pekerja Tak Terlatih OH 0.0500 75,000.00 3,750.00
Mandor OH 0.0250 125,000.00 3,125.00
JUMLAH TENAGA KERJA 6,875.00
B. BAHAN
Murda / Puntal Paras BH 1.0000 350,000.00 350,000.00
Semen kg 0.0130 1,450.00 18.85
JUMLAH HARGA BAHAN 350,018.85
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 356,893.85
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 356,893.85
42 1 BH Pekerjaan Pasangan Delineator Steel Pipa 3 ''
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja / Pekerja Tak Terlatih OH 0.0500 75,000.00 3,750.00
Mandor OH 0.0250 125,000.00 3,125.00
JUMLAH TENAGA KERJA 6,875.00
B. BAHAN
- Delineator Steel Pipa 3 '' BH 1.0000 290,000.00 290,000.00
- Tinggi 1100 mm
- Diameter 100 mm
- Reflector : Sticker standard ASTM Tipe IV
- Uk. Reflektor : 181 x 50 mm
- Finishing : Cat Duco Oven
JUMLAH HARGA BAHAN 290,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 296,875.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 296,875.00

43 1 Unit Swing Fire Door Double


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 75,000.00 22,500.00
Mandor OH 0.1000 125,000.00 12,500.00
JUMLAH TENAGA KERJA 35,000.00
B. BAHAN
Swing Fire Door Double Unit 1.0000 36,549,331.00 36,549,331.00
- Uk. Clear Opening : L: 1400 mm, T:2150 mm
Consist of :
- Kusen : Steel Plate 2mm
- Pintu : Steel Plate 1,6 mm (Tebal 55 mm)
- Isolasi : Rockwool Density 100kg/m3
- 3 Prs : Hinge
- 2 Set : Panic Device Palmo + Mortise Iseo
- 1 Set : Door Closer
- 1 Set : Flush Bolt FB SQ 501 - 270mm & 370mm
JUMLAH HARGA BAHAN 36,549,331.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 36,584,331.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 36,584,331.00

44 1 M3 Waterproofing Integral Crystallin Setara Pentent T-308


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang cat OH 0.1000 105,000.00 10,500.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0100 125,000.00 1,250.00
JUMLAH TENAGA KERJA 20,350.00
B. BAHAN
Waterproofing Integral Crystallin Setara Pentent T-308 m3 1.0000 140,000.00 140,000.00
JUMLAH HARGA BAHAN 140,000.00

C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 160,350.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 160,350.00
45 1 M2 Waterproofing Membrane Bakar Profextorcseal 3pv Setara Fosroc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang cat OH 0.1000 105,000.00 10,500.00
Kepala Tukang OH 0.0100 110,000.00 1,100.00
Mandor OH 0.0100 125,000.00 1,250.00
JUMLAH TENAGA KERJA 20,350.00
B. BAHAN
Waterproofing Membrane Bakar Profextorcseal 3pv Setara Fosroc m3 1.0000 100,000.00 100,000.00
JUMLAH HARGA BAHAN 100,000.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 120,350.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 120,350.00

46 1 BH Pemasangan Huruf Stainless Steel 304 T=1,5mm, Tinggi Huruf 1 m, Tebal huruf 10 cm
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.5300 75,000.00 39,750.00
Tukang Besi OH 0.5300 100,000.00 53,000.00
Kepala Tukang OH 0.5300 110,000.00 58,300.00
Mandor OH 0.0530 125,000.00 6,625.00
JUMLAH TENAGA KERJA 157,675.00
B. BAHAN
Stainless Steel 304 T=1,5 mm cm2 100.0000 12,000.00 1,200,000.00
Asesoris dan kelengkapan Ls 1.0000 250,000.00 250,000.00
JUMLAH HARGA BAHAN 1,450,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,607,675.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,607,675.00

47 1 M1 Tiang Sarana Upacara Besi Hollow Galvanis Kom. 40x40x2mm


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.0750 75,000.00 5,625.00
Tukang besi OH 0.1250 100,000.00 12,500.00
Kepala Tukang OH 0.0250 110,000.00 2,750.00
Mandor OH 0.0025 125,000.00 312.50
JUMLAH TENAGA KERJA 21,187.50
B. BAHAN
Besi hollow Galvanis 40x40x2mm M1 1.1000 67,500.00 74,250.00
Bahan las ls 1.0000 12,500.00 12,500.00
Cat avian ltr 0.1250 55,000.00 6,875.00
tiner ltr 0.1000 35,000.00 3,500.00
JUMLAH HARGA BAHAN 97,125.00

C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 118,312.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 118,312.50

48 1 M1 Pekerjaan Pasangan List Stepnosing Karet Tangga


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja / Pekerja Tak Terlatih OH 0.0500 75,000.00 3,750.00
Mandor OH 0.0250 125,000.00 3,125.00
JUMLAH TENAGA KERJA 6,875.00
B. BAHAN
List Stepnosing Karet Tangga m1 1.0000 30,000.00 30,000.00
JUMLAH HARGA BAHAN 30,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 36,875.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 36,875.00
49 1 M2 Pekerjaan Pasangan Usuk Profil C 75
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang Kayu OH 0.1000 105,000.00 10,500.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0500 125,000.00 6,250.00
JUMLAH TENAGA KERJA 29,750.00
B. BAHAN
Baja ringan profil C 75 btg 0.5833 90,000.00 52,500.00
Sekrup ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA BAHAN 62,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 92,250.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 92,250.00

50 1 M2 Pekerjaan Pasangan Reng Profil UK 30


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang Kayu OH 0.1000 105,000.00 10,500.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0500 125,000.00 6,250.00
JUMLAH TENAGA KERJA 29,750.00
B. BAHAN
Baja ringan profil Uk btg 0.9242 36,000.00 33,271.20
Sekrup ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA BAHAN 43,271.20
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 73,021.20
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 73,021.20

51 1 M2 Pekerjaan Pasangan Reng Profil UK 30


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1000 75,000.00 7,500.00
Tukang Kayu OH 0.1000 105,000.00 10,500.00
Kepala Tukang OH 0.0500 110,000.00 5,500.00
Mandor OH 0.0500 125,000.00 6,250.00
JUMLAH TENAGA KERJA 29,750.00
B. BAHAN
Baja ringan profil Uk btg 0.9242 36,000.00 33,271.20
Sekrup ls 1.0000 10,000.00 10,000.00
JUMLAH HARGA BAHAN 43,271.20
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 73,021.20
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 73,021.20

52 1 BH Pemasangan Angkur Diameter 16


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.0100 75,000.00 750.00
Tukang kayu OH 0.0080 105,000.00 840.00
Kepala Tukang OH 0.0020 110,000.00 220.00
Mandor OH 0.0020 125,000.00 250.00
JUMLAH TENAGA KERJA 2,060.00
B. BAHAN
Angkur diameter 16 bh 1.0000 55,000.00 55,000.00
Alat dan material bantu ls 1.0000 1,000.00 1,000.00
JUMLAH HARGA BAHAN 56,000.00

C. PERALATAN -
JUMLAH HARGA ALAT -
D. Jumlah (A + B + C) 58,060.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 58,060.00
53 1 BH Pemasangan Baut Diameter 16
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0100 75,000.00 750.00
Tukang kayu OH 0.0080 105,000.00 840.00
Kepala Tukang OH 0.0020 110,000.00 220.00
Mandor OH 0.0020 125,000.00 250.00
JUMLAH TENAGA KERJA 2,060.00
B. BAHAN
Baut diameter 16 bh 1.0000 9,000.00 9,000.00
Alat dan material bantu ls 1.0000 1,000.00 1,000.00
JUMLAH HARGA BAHAN 10,000.00

C. PERALATAN -

JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 12,060.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 12,060.00

54 1 KG Cat Zincromate
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0100 75,000.00 750.00
Tukang Cat OH 0.0080 95,000.00 760.00
Kepala Tukang OH 0.0020 110,000.00 220.00
Mandor OH 0.0020 125,000.00 250.00
JUMLAH TENAGA KERJA 1,980.00
B. BAHAN
Cat Zincromate kg 1.0000 50,000.00 50,000.00
Alat dan material bantu ls 1.0000 1,000.00 1,000.00
JUMLAH HARGA BAHAN 51,000.00

C. PERALATAN -

JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 52,980.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 52,980.00

55 1 M2 Pasangan Kaca Tempered 12 mm Dengan Spider Fitting


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0800 75,000.00 6,000.00
Tukang Besi OH 0.0800 100,000.00 8,000.00
Kepala Tukang OH 0.0650 110,000.00 7,150.00
Mandor OH 0.0800 125,000.00 10,000.00
JUMLAH TENAGA KERJA 31,150.00
B. BAHAN
Kaca Tempered 12 mm m2 1.1000 1,962,500.00 2,158,750.00
Sipder Fitting ls 1.0000 900,000.00 900,000.00
Sealent btl 3.5000 35,000.00 122,500.00
JUMLAH HARGA BAHAN 3,181,250.00

C. PERALATAN -

JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 3,212,400.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 3,212,400.00
56 1 M3 Pekerjaan Beton K300
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 0.3515 75,000.00 26,358.75
Tukang Batu Hari 1.4157 95,000.00 134,491.50
Kepala Tukang Hari 0.0299 110,000.00 3,288.78
Mandor Hari 0.0166 125,000.00 2,079.00
JUMLAH TENAGA KERJA 166,218.03
B. BAHAN
Beton Ready Mix K 300, Slump 12 +/- 2 cm M3 1.0500 1,130,040.00 1,186,542.00
Additive/Bonding Agent Ltr 0.2500 132,950.00 33,237.50
JUMLAH HARGA BAHAN 1,219,779.50

C. PERALATAN
Concrete Pump Lot 1.0000 46,540.00 46,540.00
Alat Alat lain Lot 1.0000 33,236.45 33,236.45
JUMLAH HARGA ALAT 79,776.45

D. Jumlah (A + B + C) 1,465,773.98
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,465,773.98

57 1 M3 Pekerjaan Beton K300 Untuk Bore Pile


SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 0.3195 75,000.00 23,962.50
Tukang Bor Hari 1.2870 95,000.00 122,265.00
Kepala Tukang Hari 0.0272 110,000.00 2,989.80
Mandor Hari 0.0151 125,000.00 1,890.00
JUMLAH TENAGA KERJA 151,107.30
B. BAHAN
Beton Ready Mix K 300, Slump 12 +/- 2 cm M3 1.2000 1,130,040.00 1,356,048.00
Additive/Bonding Agent Ltr 0.2500 132,950.00 33,237.50
JUMLAH HARGA BAHAN 1,389,285.50

C. PERALATAN
Pipa Tremi Lot 1.0000 19,941.87 19,941.87
Alat Alat lain Lot 1.0000 19,941.87 19,941.87
JUMLAH HARGA ALAT 39,883.74

D. Jumlah (A + B + C) 1,580,276.54
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,580,276.54

58 1 M' SCAFOLDING Penahan BALOK PRESTRESS, Tinggi kl..3,00 Mt (Sewa)


SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 0.0799 75,000.00 5,990.63
Tukang Batu Hari 0.3218 95,000.00 30,566.25
Kepala Tukang Hari 0.0068 110,000.00 747.45
Mandor Hari 0.0038 125,000.00 472.50
JUMLAH TENAGA KERJA 37,776.83
B. BAHAN Per 6,00 Mtr.
Main Frame MF 170 Bh 6.0000 9,310.00 55,860.00
End Frame EF 90 Bh 6.0000 6,650.00 39,900.00
Bracing 193 Bh 12.0000 4,330.00 51,960.00
Bracing 185 Bh 12.0000 4,330.00 51,960.00
Base Plate Bh 12.0000 3,990.00 47,880.00
Joint Pin Bh 12.0000 5,320.00 63,840.00
U Head Jack Bh 12.0000 5,320.00 63,840.00
Main Beam (Gelagar) 5 Mtr Bh 2.0000 13,300.00 26,600.00
Rail Beam (Suri-Suri) Bh 10.0000 13,300.00 133,000.00
JUMLAH HARGA BAHAN 534,840.00
JUMLAH HARGA PER METER 89,140.00
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 126,916.83
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 126,916.83
59 1 Kg Pemasangan Besi WIRE MESH (M6-150)
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 0.0027 75,000.00 199.69
Tukang Besi Hari 0.0143 100,000.00 1,430.00
Kepala Tukang Hari 0.0030 110,000.00 332.20
Mandor Hari 0.0017 125,000.00 210.00
JUMLAH TENAGA KERJA 2,171.89
B. BAHAN
Wire Mesh U50 m2 1.1000 11,170.00 12,287.00
Kawat Beton Kg 0.0150 15,400.00 231.00
JUMLAH HARGA BAHAN 12,518.00

C. PERALATAN
Alat Kerja Lot 1.0000 997.09 997.09
JUMLAH HARGA ALAT 997.09

D. Jumlah (A + B + C) 15,686.98
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 15,686.98

60 1 Kg Pemasangan Besi Ulir U40


SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 0.0043 75,000.00 319.50
Tukang Besi Hari 0.0172 100,000.00 1,716.00
Kepala Tukang Hari 0.0036 110,000.00 398.64
Mandor Hari 0.0020 125,000.00 252.00
JUMLAH TENAGA KERJA 2,686.14
B. BAHAN
Besi Beton Kg 1.1000 8,750.00 9,625.00
Kawat Beton Kg 0.0150 15,400.00 231.00
JUMLAH HARGA BAHAN 9,856.00

C. PERALATAN
Alat Kerja Lot 1.0000 997.09 997.09
JUMLAH HARGA ALAT 997.09

D. Jumlah (A + B + C) 13,539.23
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 13,539.23

61 1 m3 Pekerjaan BETON B-0 untuk BORE PILE


SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 0.3195 75,000.00 23,962.50
Tukang Batu Hari 1.2870 95,000.00 122,265.00
Kepala Tukang Hari 0.0272 110,000.00 2,989.80
Mandor Hari 0.0151 125,000.00 1,890.00
JUMLAH TENAGA KERJA 151,107.30
B. BAHAN
Beton Ready Mix B-0 Kg 1.2000 897,390.00 1,076,868.00
Additive/Plasticicer Kg 2.5000 19,950.00 49,875.00
JUMLAH HARGA BAHAN 1,126,743.00

C. PERALATAN
Pipa Tremi Lot 1.0000 19,941.87 19,941.87
Alat Alat lain Lot 1.0000 19,941.87 19,941.87
JUMLAH HARGA ALAT 39,883.74
D. Jumlah (A + B + C) 1,317,734.04
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,317,734.04
62 1 M3 Lantai Kerja sp. 1:3:5
SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 5.1546 75,000.00 386,595.00
Tukang Batu Hari 0.7865 95,000.00 74,717.50
Kepala Tukang Hari 0.0831 110,000.00 9,135.50
Mandor Hari 0.2957 125,000.00 36,960.00
JUMLAH TENAGA KERJA 507,408.00
B. BAHAN
Semen Portland Zak 4.3600 66,480.00 289,852.80
Pasir Pasang M3 0.5200 265,900.00 138,268.00
Kerikil / Split M3 0.8700 252,600.00 219,762.00
JUMLAH HARGA BAHAN 647,882.80

C. PERALATAN
Alat Kerja Lot 1.0000 66,472.89 66,472.89
JUMLAH HARGA ALAT 66,472.89

D. Jumlah (A + B + C) 1,221,763.69
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,221,763.69

63 1 M2 Pasangan Begisting Pilecap Batako sp. 1:3


SATUAN KOEFISIEN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A. TENAGA
Pekerja Hari 0.4544 75,000.00 34,080.00
Tukang Batu Hari 0.1430 95,000.00 13,585.00
Kepala Tukang Hari 0.0151 110,000.00 1,661.00
Mandor Hari 0.0252 125,000.00 3,150.00
JUMLAH TENAGA KERJA 52,476.00
B. BAHAN
Batako Buah 14.0000 3,330.00 46,620.00
Pasir Pasang M3 0.0470 265,900.00 12,497.30
Semen Portland Zak 0.2874 66,480.00 19,106.35
JUMLAH HARGA BAHAN 78,223.65

C. PERALATAN
Alat Kerja Lot 1.0000 14,624.04 14,624.04
JUMLAH HARGA ALAT 14,624.04

D. Jumlah (A + B + C) 145,323.69
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 145,323.69

64 1 UNIT Sewa TC KAP 2,5 TON LENGTH 60 M1 Selama 9 Bulan


KOEFISIEN HARGA SATUAN HARGA SATUAN
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA

JUMLAH TENAGA KERJA -


B. BAHAN

JUMLAH HARGA BAHAN -


C. PERALATAN
Sewa TC Kap 2,5 Ton Length 60 m/Bulan/ 200 jam Bulan 7 120,000,000.00 840,000,000.00
Jaminan Angkur Set 1 65,000,000.00 65,000,000.00
Pasang Angkur Set 1 7,500,000.00 7,500,000.00
Erexsion Set 1 55,000,000.00 55,000,000.00
Dismantling Normal Set 1 55,000,000.00 55,000,000.00
Mob-Demob TC Set 1 175,000,000.00 175,000,000.00
Transportasi Crew TC 6 Orang Ls 1 25,000,000.00 25,000,000.00
Gaji Operator Set 1 7,500,000.00 7,500,000.00
Mess Crew dan Operator Ditanggung Penyewa
Genzet/ Power Listrik Ditanggung Penyewa
Alat bantu Bongkar Pasang Ditanggung Penyewa
Asuransi Ditanggung Penyewa
JUMLAH HARGA ALAT 1,230,000,000.00

D. Jumlah (A + B + C) 1,230,000,000.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,230,000,000.00
65 1 M3 Urugan Tanah Subur
SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.5000 75,000.00 37,500.00
Mandor OH 0.0500 125,000.00 6,250.00
JUMLAH TENAGA KERJA 43,750.00
B. BAHAN
Tanah Subur M3 1.2000 65,000.00 78,000.00
JUMLAH HARGA BAHAN 78,000.00

C. PERALATAN -

JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 121,750.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 121,750.00

66 1 M2 Penanaman Tanaman Hias Kacang Kacangan


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 75,000.00 11,250.00
Mandor OH 0.0150 125,000.00 1,875.00
JUMLAH TENAGA KERJA 13,125.00
B. BAHAN
Tanaman Hias Btg 50.0000 500.00 25,000.00
JUMLAH HARGA BAHAN 25,000.00

C. PERALATAN -

JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 38,125.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 38,125.00

67 1 M3 Pekerjaan Lapisan Aspal


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1406 75,000.00 10,545.00
Mandor OH 0.0201 125,000.00 2,512.50
JUMLAH TENAGA KERJA 13,057.50
B. BAHAN
Pasir Kasar m3 0.0139 230,000.00 3,197.00
Pasir Halus m3 0.0139 267,000.00 3,711.30
Semen kg 31.5000 1,450.00 45,675.00
Aspal kg 92.7000 12,000.00 1,112,400.00
JUMLAH HARGA BAHAN 1,164,983.30
C. PERALATAN
Wheel Loader Jam 0.0096 330,000.00 3,168.00
AMP Jam 0.0201 5,018,600.00 100,873.86
Genzet Jam 0.0201 416,800.00 8,377.68
Dump Truck Jam 0.0384 248,157.27 9,529.24
Asphalt Finishir Jam 0.0290 507,700.00 14,723.30
Tandem Roller Jam 0.0238 318,300.00 7,575.54
P. Tyre Roller Jam 0.0082 292,100.00 2,395.22
Alat Bantu Ls 1.0000 20,000.00 20,000.00
JUMLAH HARGA ALAT 166,642.84

D. Jumlah (A + B + C) 1,344,683.64
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,344,683.64
68 1 M3 Pekerjaan Beton K-450
SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1815 87,550.00 15,890.33
Tukang Cor/Batu OH 0.7260 105,060.00 76,273.56
Kepala Tukang OH 0.0145 128,410.00 1,864.51
Mandor OH 0.0073 175,100.00 1,271.23
JUMLAH TENAGA KERJA 95,299.62
B. BAHAN
Beton Ready Mix K 500 m3 1.0500 1,229,200.00 1,290,660.00
Additive m3 2.5000 17,510.00 43,775.00
JUMLAH HARGA BAHAN 1,334,435.00
C. PERALATAN
Concrete Pump Lot 1.0000 46,700.00 46,700.00
Alat Alat lain Lot 1.0000 58,366.44 58,366.44
JUMLAH HARGA ALAT 105,066.44

D. Jumlah (A + B + C) 1,534,801.06
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,534,801.06

69 1 M3 Beton Balok Precast Prestress B1, B2, BR1 dan BS1


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

Ukuran m 0.4000 1.5240 2.9839


m 0.5000 1.4319 1.5782
m 5.5600

A. TENAGA
Pekerja erection Hari 2.0000 96,305.00 192,610.00
Tukang erection Hari 1.5000 115,566.00 173,349.00
Kepala Tukang erection Hari 0.5000 141,251.00 70,625.50
Mandor erection Hari 0.2500 192,610.00 48,152.50
JUMLAH TENAGA KERJA 484,737.00
B. BAHAN
Beton Ready Mix K-450 M3 1.0500 1,534,801.06 1,611,541.11
Pembesian PC Strand Kg 35.7967 24,310.00 870,217.84
Pembesian U40 Kg 197.6418 12,970.05 2,563,424.19
Cetakan/Formwork M2 5.0000 131,250.00 656,250.00
JUMLAH HARGA BAHAN 5,701,433.14
C. ALAT PRODUKSI DAN FINISHING
Upah Jacking Strands dll m3 1.0000 1,700,000.00 1,700,000.00
Peralatan Gantry Crane dll m3 1.0000 275,000.00 275,000.00
Aksesoris Produksi Ls 1.0000 750,000.00 750,000.00
Material testing m3 1.0000 130,000.00 130,000.00
QC,Grouting/finshing Lot 1.0000 175,000.00 175,000.00
JUMLAH HARGA ALAT 3,030,000.00
D. STOCKING, LOADING TRUCKING & UNLOADING
Upah Curing & Stocking m3 1.0000 275,000.00 275,000.00
Loading di Pabrik Kg 2,500.0000 20.00 50,000.00
Biaya Transport Pabrik (Bandung) - Site (Dps) Kg 2,500.0000 825.00 2,062,500.00
Turunkan di Site Proyek ( Crane ) Ls 2,500.0000 20.00 50,000.00
Bahan bantu ( kayu ) landasan m3 1.0000 55,000.00 55,000.00
JUMLAH HARGA ALAT 2,492,500.00

D. Jumlah (A + B + C) 11,708,670.14
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 11,708,670.14
G. Harga per balok B1, B2, BR1 dan BS1 13,020,041.20
70 1 M3 Beton Balok Precast Prestress B3 dan B4
SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)
Ukuran m 0.4000 1.5240 2.9839
m 0.4000 1.4319 1.5782
m 5.5600

A. TENAGA
Pekerja erection Hari 2.0000 96,305.00 192,610.00
Tukang erection Hari 1.5000 115,566.00 173,349.00
Kepala Tukang erection Hari 0.5000 141,251.00 70,625.50
Mandor erection Hari 0.2500 192,610.00 48,152.50
JUMLAH TENAGA KERJA 484,737.00
B. BAHAN
Beton Ready Mix K-450 M3 1.0500 1,534,801.06 1,611,541.11
Pembesian PC Strand Kg 35.7967 24,310.00 870,217.84
Pembesian U40 Kg 206.0139 12,970.05 2,672,010.54
Cetakan/Formwork M2 5.0000 131,250.00 656,250.00
JUMLAH HARGA BAHAN 5,810,019.49
C. ALAT PRODUKSI DAN FINISHING
Upah Jacking Strands dll m3 1.0000 1,700,000.00 1,700,000.00
Peralatan Gantry Crane dll m3 1.0000 275,000.00 275,000.00
Aksesoris Produksi Ls 1.0000 750,000.00 750,000.00
Material testing m3 1.0000 130,000.00 130,000.00
QC,Grouting/finshing Lot 1.0000 175,000.00 175,000.00
JUMLAH HARGA ALAT 3,030,000.00
D. STOCKING, LOADING TRUCKING & UNLOADING
Upah Curing & Stocking m3 1.0000 275,000.00 275,000.00
Loading di Pabrik Kg 2,500.0000 20.00 50,000.00
Biaya Transport Pabrik (Bandung) - Site (Dps) Kg 2,500.0000 825.00 2,062,500.00
Turunkan di Site Proyek ( Crane ) Ls 2,500.0000 20.00 50,000.00
Bahan bantu ( kayu ) landasan m3 1.0000 55,000.00 55,000.00
JUMLAH HARGA ALAT 2,492,500.00

D. Jumlah (A + B + C) 11,817,256.49
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 11,817,256.49
G. Harga per balok B3 dan B4 10,512,631.38

71 1 M3 Beton Balok Precast Prestress RB1 dan RB2


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)
Ukuran m 0.3000 1.5240 1.5782
m 0.5000 1.4319 0.6165
m 5.5600

A. TENAGA
Pekerja erection Hari 2.0000 96,305.00 192,610.00
Tukang erection Hari 1.5000 115,566.00 173,349.00
Kepala Tukang erection Hari 0.5000 141,251.00 70,625.50
Mandor erection Hari 0.2500 192,610.00 48,152.50
JUMLAH TENAGA KERJA 484,737.00
B. BAHAN
Beton Ready Mix K-450 M3 1.0500 1,534,801.06 1,611,541.11
Pembesian PC Strand Kg 23.7054 24,310.00 576,277.59
Pembesian U40 Kg 143.6478 12,970.05 1,863,118.52
Cetakan/Formwork M2 5.0000 131,250.00 656,250.00
JUMLAH HARGA BAHAN 4,707,187.23
C. ALAT PRODUKSI DAN FINISHING
Upah Jacking Strands dll m3 1.0000 1,700,000.00 1,700,000.00
Peralatan Gantry Crane dll m3 1.0000 275,000.00 275,000.00
Aksesoris Produksi Ls 1.0000 750,000.00 750,000.00
Material testing m3 1.0000 130,000.00 130,000.00
QC,Grouting/finshing Lot 1.0000 175,000.00 175,000.00
JUMLAH HARGA ALAT 3,030,000.00
D. STOCKING, LOADING TRUCKING & UNLOADING
Upah Curing & Stocking m3 1.0000 275,000.00 275,000.00
Loading di Pabrik Kg 2,500.0000 20.00 50,000.00
Biaya Transport Pabrik (Bandung) - Site (Dps) Kg 2,500.0000 825.00 2,062,500.00
Turunkan di Site Proyek ( Crane ) Ls 2,500.0000 20.00 50,000.00
Bahan bantu ( kayu ) landasan m3 1.0000 55,000.00 55,000.00
JUMLAH HARGA ALAT 2,492,500.00
D. Jumlah (A + B + C) 10,714,424.23
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 10,714,424.23
G. Harga per Balok RB1 dan RB2 8,935,829.81

72 1 M2 Beton Plat Lantai HCS TYPE 200.07.14


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)
A. TENAGA
Pekerja erection Hari 0.2000 96,305.00 19,261.00
Tukang erection Hari 0.2000 115,566.00 23,113.20
Kepala Tukang erection Hari 0.1000 141,251.00 14,125.10
Mandor erection Hari 0.0500 192,610.00 9,630.50
JUMLAH TENAGA KERJA 66,129.80
B. BAHAN
Beton Ready Mix K-450 M3 0.1385 1,534,801.06 212,569.95
Pembesian PC Wire Kg 5.6800 22,310.00 126,720.80
Cetakan/Formwork M2 0.9960 131,250.00 130,725.00
JUMLAH HARGA BAHAN 470,015.75
C. STOCKING, LOADING TRUCKING & UNLOADING
Upah Curing & Stocking m3 0.0600 275,000.00 16,500.00
Loading di Pabrik Kg 334.1700 20.00 6,683.40
Biaya Transport Pabrik (Bandung) - Site (Dps) Kg 334.1700 825.00 275,690.25
Turunkan di Site Proyek ( Crane ) Ls 334.1700 20.00 6,683.40
Bahan bantu ( kayu ) landasan m3 0.1385 55,000.00 7,617.50
JUMLAH HARGA ALAT 313,174.55

D. Jumlah (A + B + C) 849,320.10
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 849,320.10

73 1 M2 Beton Plat Lantai HCS TYPE 150.07.14


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)
A. TENAGA
Pekerja erection Hari 0.2000 96,305.00 19,261.00
Tukang erection Hari 0.2000 115,566.00 23,113.20
Kepala Tukang erection Hari 0.1000 141,251.00 14,125.10
Mandor erection Hari 0.0500 192,610.00 9,630.50
JUMLAH TENAGA KERJA 66,129.80
B. BAHAN
Beton Ready Mix K-450 M3 0.1100 1,534,801.06 168,828.12
Pembesian PC Wire Kg 5.6800 22,310.00 126,720.80
Cetakan/Formwork M2
0.9960 131,250.00 130,725.00
JUMLAH HARGA BAHAN 426,273.92
C. STOCKING, LOADING TRUCKING & UNLOADING
Upah Curing & Stocking m3 0.0549 275,000.00 15,097.50
Loading di Pabrik Kg 314.4000 20.00 6,288.00
Biaya Transport Pabrik (Bandung) - Site (Dps) Kg 314.4000 825.00 259,380.00
Turunkan di Site Proyek ( Crane ) Ls 314.4000 20.00 6,288.00
Bahan bantu ( kayu ) landasan m3 0.1100 55,000.00 6,050.00
JUMLAH HARGA ALAT 293,103.50
D. Jumlah (A + B + C) 785,507.22
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 785,507.22

74 1 M' Pekerjaan Tiang Pancang Precast Prestress Ukuran 40cm x 40cm


NO. URAIAN SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
Ukuran m 0.4000 1.5240
m 12.0000 1.4319
A. BAHAN
Beton Ready Mix K-450 M3 1.9200 1,534,801.06 2,946,818.04
Pembesian PC Strand Kg 12.6004 24,310.00 306,316.68
Pembesian U50 Kg 51.7818 13,970.05 723,394.80
Cetakan Tiang Pancang M2 14.4000 131,250.00 1,890,000.00
JUMLAH HARGA BAHAN 5,866,529.52
C. ALAT PRODUKSI DAN FINISHING
Upah Jacking Strands dll Lot 8.0000 50,000.00 400,000.00
Peralatan Gantry Crane dll Lot 1.0000 125,000.00 125,000.00
QC,Grouting/finshing Lot 1.0000 50,000.00 50,000.00
JUMLAH HARGA ALAT 575,000.00
D. STOCKING, LOADING TRUCKING & UNLOADING
Upah Curing & Stocking Ls 1.0000 12,500.00 12,500.00
Loading di Pabrik Kg 4,800.0000 20.00 96,000.00
Biaya Transport Pabrik - Site Kg 4,800.0000 100.00 480,000.00
Turunkan di Site Proyek ( Crane ) Ls 4,800.0000 20.00 96,000.00
Bahan bantu ( kayu ) landasan Ls 1.0000 25,000.00 25,000.00
Material testing Ls 1.0000 50,000.00 50,000.00
JUMLAH HARGA ALAT 759,500.00
D. Jumlah (A + B + C) 7,201,029.52
E. Overhead & Profit 10 % x D 720,102.95
F. Harga Satuan Pekerjaan (D+E) 7,921,132.47
G. Harga Per Meter 660,094.37

75 1 M' Pekerjaan Pre Boring


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

Penggunaan Alat Bore 1.0000 125,000.00 125,000.00


Alat Bantu, Listrik dll 1.0000 35,000.00 35,000.00
Penggunaan Casing selama Bore-Cor - - -
Material Bentonite - - -
Material Clay 1.0000 50,000.00 50,000.00
Upah Boring & Flushing 1.0000 175,000.00 175,000.00
Handling pemasangan Besi 1.0000 50,000.00 50,000.00
Lain Lain - 20,000.00 -
JUMLAH HARGA 435,000.00

D. Jumlah (A + B + C) 435,000.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 435,000.00

76 1 M' Pekerjaan PEMANCANGAN DENGAN ALAT HSPD 240 Ton.


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

Alat pancang HSPD 240 0.0833 1,450,000.00 120,833.33


Alat Bantu, Listrik, BBM dll 1.2000 9,500.00 11,400.00
Pekerja Pancang 0.0700 96,305.00 6,741.35
Kepala tukang Pancang 0.0250 141,251.00 3,531.28
Mandor Pancang 0.0150 192,610.00 2,889.15
JUMLAH HARGA 145,395.11
D. Jumlah (A + B + C) 145,395.11
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 145,395.11

77 1 M3 Galian Tanah Dengan Excavator, Termasuk Perapihan Kembali


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0870 100,000.00 8,700.00
Mandor OH 0.0435 125,000.00 5,437.50
JUMLAH TENAGA KERJA 14,137.50
B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN
Excavator Jam 0.0694 460,000.00 31,924.00
JUMLAH HARGA ALAT 31,924.00

D. Jumlah (A + B + C) 46,061.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 46,061.50

78 1 Unit Sewa Crane Tadano 50 Ton Selama 3 Bulan


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

A. TENAGA

JUMLAH TENAGA KERJA -


B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN
Crane 50 Ton Bulan 3.0000 110,000,000.00 330,000,000.00
JUMLAH HARGA ALAT 330,000,000.00

D. Jumlah (A + B + C) 330,000,000.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 330,000,000.00

79 1 Unit Sewa Pompa Pengeringan Air (Dewatering) Selama 2 bulan


SATUAN KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN
(Rp.) (Rp.)

A. TENAGA

JUMLAH TENAGA KERJA -


B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN
Pompa Air Hari 60.0000 200,000.00 12,000,000.00
JUMLAH HARGA ALAT 12,000,000.00
D. Jumlah (A + B + C) 12,000,000.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 12,000,000.00

Denpasar, 20 Pebruari 2017


Mengetahui, Kepala Bidang Penataan Bangunan dan
Kepala Dinas Pekerjaan Umum dan Pengembangan Kawasan Permukiman
Penataan Ruang Kota Denpasar Dinas Pekerjaan Umum dan Penataan Ruang
Kota Denpasar

Ir. I Ketut Winarta Agus Sudarmo, ST.


Pembina Utama Muda Penata Tk. I
NIP. 19571231 198803 1 103 NIP. 19700907 199903 1 006
DAFTAR HARGA SATUAN BAHAN
TAHUN 2017
A. Harga Satuan Bahan

HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4

BATU, PASIR DAN TANAH


1 Batu Kali/batu bulat 15-30 cm m3 265,000.00
2 Batu Karang Bukit m3 179,000.00
3 Batu Belah Diameter 15-30 cm m3 285,000.00
4 Batu Pecah diameter 5-7 cm m3 290,250.00
5 Batu Pecah diameter 3-5 cm m3 292,500.00
6 Batu Pecah diameter 2-3 cm m3 294,500.00
7 Koral Beton diameter 1 - 2 cm m3 298,000.00
8 Koral Sikat (Lokal) zak 45,000.00
9 Batu Candi Hitam (Ukuran 30 x 30 x 2 Cm) Cirebon m2 105,600.00
10 Batu Candi Hitam (Ukuran 30 x 30 x 3 Cm) Cirebon m2 156,000.00
11 Batu Candi Hitam (Ukuran 30 x 30 x 5 Cm) Cirebon m2 228,000.00
12 Batu Candi Hitam (Ukuran 20 x 20 x 2 Cm) Cirebon m2 90,000.00
13 Batu Candi Hitam (Ukuran 20 x 30 x 5 Cm) Cirebon m2 216,000.00
14 Batu Putih Jogya / Palimanan (30 x 30 x 2 Cm) m2 96,000.00
15 Batu Putih Jogya / Palimanan (30 x 30 x 3 Cm) m2 138,000.00
16 Batu Putih Jogya / Palimanan (30 x 30 x 5 Cm) m2 204,000.00
17 Batu pilah Singaraja 30 x 30 m2 89,100.00
18 Batu pilah Singaraja 20 x 20 m2 83,600.00
19 Batu hitam Jember 5 x 20 halus m2 83,600.00
20 Batu hitam Jember 20 x 40 halus m2 89,100.00
21 Batu hitam Jember 15 x 30 halus m2 83,600.00
22 Batu hitam Singaraja 15 x 30 halus m2 83,600.00
23 Batu hitam Singaraja 20 x 40 halus m2 89,100.00
24 Batu hitam karangasem/Batu Tabas m2 99,000.00
25 Paras Silakarang Tipis (Ukuran 15 x 30 x 5 Cm) m2 25,000.00
26 Paras Silakarang Tebal (Ukuran 15 x 30 x 8 Cm) m2 33,000.00
27 Batu Paras Bali/Pawon (Abu - Abu Terang) m2 93,500.00
28 Paras Kelating / Kerobokan (Ukuran 3 x 20 x 40 Cm) bh 13,750.00
29 Batako Lubang bj 2,050.00
30 Batako Buntu bj 2,250.00
32 Bata Ringan setara falcon uk. 75 x 200 x 500 mm m3 935,000.00
33 Bata Ringan setara falcon uk. 100 x 200 x 600 mm m3 935,000.00
34 Bata Ringan setara falcon uk. 125 x 200 x 600 mm m3 935,000.00
35 Bata Ringan setara falcon uk. 150 x 200 x 600 mm m3 935,000.00
36 Bata Merah Klas I bj 2,500.00
37 Bata Merah Klas II bj 2,150.00
38 Bata Merah Klas III bj 1,450.00
39 Bata Merah Super (Pripian) ex tulikup bj 5,850.00
40 Bata Pres 22x10x6cm bj 3,250.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
41 Bata Pres 22x10x5cm bj 3,120.00
42 Limestone m3 158,000.00
43 Pasir Halus m3 267,000.00
44 Pasir pasang m3 230,000.00
45 Pasir cor m3 210,000.00
46 Pasir urug m3 183,750.00
47 Sirtu m3 123,750.00
48 Split Kasar M3 264,000.00
49 Split Halus M3 285,000.00
50 Tanah urug m3 140,000.00

SEMEN & PEREKAT


51 Semen Setara Gresik kg 1,450.00
52 Semen Setara Tiga Roda kg 1,425.00
53 Semen Setara Tonasa kg 1,375.00
54 Semen Setara Bosowa kg 1,375.00
55 Semen Setara Holcim kg 1,375.00
56 Semen warna setara MU 408/ Nat kg 25,620.00

Mortar Utama
57 ThinBedMAX/Perekat Bata Ringan (MU 380) @40 Kg Zak 128,100.00
58 PlasterPlus/Pas. Bata & Plester (MU-301) @40 kg Zak 86,520.00
59 Plester premium (MU-100)@ 40 kg Zak 91,350.00
60 Finish Plesteran/ Render (MU 290)@ 40 kg Zak 160,230.00
61 SkimWall/Acian Plesteran & Beton (Skimcoat) 20 kg (MU-200) Zak 72,187.50
62 SkimWall/Acian Plesteran & Beton (Skimcoat) 40 kg (MU-200) Zak 137,130.00
63 Acian Putih (MU-270)@25 kg Zak 152,460.00
64 Perata Lantai (MU-440)@40kg Zak 87,360.00
65 Perata Lantai Expose (MU 445) 40 kg Zak 169,890.00
66 Self Leveling Floor /Underlayment (MU-410) @25kg Zak 270,900.00
67 Primer Self Leveling Floor (MU-L410) @ 5lt Set 302,925.00
68 Floor Hardener (MU 700) 25 kg Zak 138,180.00
69 Granitfix/Perekat Granite Tile & Batu Alam (MU-400) @25kg Zak 117,442.50
70 Cerafix/Perekat Keramik (MU-420)@25 kg Zak 82,162.50
71 Poolfix White/Perekat keramik area terendam (MU-460)@25 kg Zak 392,070.00
72 Renofix/Perekat keramik diatas keramik (MU-480)@25 kg Zak 235,095.00
73 Powerfix Flex/Perekat keramik serba guna (MU-485)@25 kg Zak 299,250.00
74 Rapidfix Flex/Perekat keramik Fast Setting (MU-490)@25 kg Zak 324,660.00
75 Colorfill/ Pengisi nat interior & eksterior (MU-408C) kg 11,340.00
76 ColorPlus/Pengisi nat interior,eksterior,area basah(MU-408P) kg 16,800.00
77 Glliter/Pengisi nat dengan efek Glliter (MU-408G)@ 2kg set 154,875.00
78 PowerPool/Pengisi nat area terendam(MU-408PP)@2kg set 82,950.00
79 FixGrout/Perbaikan struktur beton (MU-800)@20kg Zak 77,490.00
80 PatchCrete/Perbaikan permukaan beton(MU-830)@40kg Zak 249,270.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
81 SkimRep/Perbaikan permukaan acian(MU-840)@25kg Zak 308,910.00
82 DryShield/Pelapis kedap air (MU-600)@3kg Set 101,535.00
83 ArcyBond/Perekat Mortar & Beton akrilik (MU-L500)@900ml Set 31,500.00

Uzin
84 Beton Instan (UZ K300) 50 kg Zak 78,750.00
85 Plester dinding instan (UZ Plester) 50 Kg Zak 78,750.00
86 Plester Finish tanpa Aci (UZ Render) 50 kg Zak 99,750.00
87 Acian diatas beton (UZ SC100) 40 kg Zak 111,300.00
88 Acian dinding instan interior (UZ SC 50) 40 kg Zak 102,900.00
89 Acian dinding instan eksterior (UZ SC 75) 40 kg Zak 105,000.00
90 Perekat Bata Ringan (UZ TB20) 50 kg Zak 112,875.00

Bostik
Perekat Keramik & Batu Alam
91 Fix Crete Zak 133,185.15
92 Fix all Zak 149,694.30
93 Super Fix all Zak 213,064.95
94 Super Fix all trade/white Zak 258,667.50
95 Asaflex 45 kg (15lt +30 kgp) Set 1,292,834.55
96 Mortar Fix 100kg Set 1,431,696.00
97 Mortar Fix 50 kg Set 829,256.40
98 Mortar Fix 5 kg Set 87,445.05
99 Grout ( Semen Nat) 20 kg Zak 386,742.30
100 Grout ( Semen Nat) 1 kg Zak 16,420.95
101 Liquid Grout Adictive (LGA) 20 Lt Pail 931,728.00
102 Mega Lastic Acrilic Base 20Lt Pail 931,728.00

Wall System
103 Skim Plas 25 Kg Zak 111,612.90
104 Skim Crete 25 Kg Zak 145,828.20
105 Fix. Plas 40 kg Zak 100,101.75
106 Fix T. 40 kg Zak 147,909.30

Waterproofing
107 Ultra Coat RC2 20 Lt Pail 1,179,487.05
108 Boscosem Slury 33 Kg Set 494,182.50
109 Damplix 2 20 kg Set 1,541,675.10
110 Damplix 3 45 kg Set 2,045,376.90
111 Damplix 3E 35 kg Set 1,133,574.75
112 Boscoseal Tom (Wp membran Bakar) Uk. 1m x 10 m Rol 897,871.80
113 Indo primer ( lapisan primer WP membran) 20 Lt Pail 734,801.55
114 Integral Kristalisasi (Waterproofing kristal) 20 kg Pail 1,577,668.05
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
Sealent
115 No More Nail (320 GR) Pcs 71,695.05
116 Seal n Flex 1 (600 ML) Pcs 111,692.70
117 Boscosil 313 (300 ML) Pcs 57,016.05
118 Boscosil 616 (300 ML) Pcs 57,862.35
119 Fil A Gap (300 ML) Pcs 37,076.55
120 Boscosil Mastic (300 ML) khusus R. Pendingin Pcs 48,769.35
121 Bostik Z Bond 6S (300 ML) Pcs 139,258.35
122 Bostik Z PU Contrcuction (600 ML) Pcs 121,796.85
123 Quelyd Super Express (250 GR) Pcs 35,833.35
124 Expanda Foam (340 GR) Pcs 171,652.95
125 Barel Gun Bh 523,805.10
126 Flash Band Rol 164,872.05

BAMBU
127 Bambu Ukuran 8"- 10" panjang 4 m btg 10,500.00
128 Bambu Ukuran 3"-6" panjang 4 m btg 9,450.00
129 Gedeg kulit kelas I m2 36,750.00
130 Gedeg kulit kelas II m2 34,125.00
131 Gedeg Biasa m2 35,000.00
`
KAYU
132 Kayu bingkirai Balok m3 11,340,000.00
133 Kayu bingkirai papan m3 13,650,000.00
134 Kayu Cempaka lokal m3 2,860,000.00
135 Kayu jati Balok Ex Bojonegoro m3 31,500,000.00
136 Kayu jati papan Ex. Bojonegoro m3 36,750,000.00
137 Kayu kamper balok m3 8,925,000.00
138 Kayu kamper usuk/reng m3 7,875,000.00
139 Kayu kamper papan m3 9,975,000.00
140 Kayu kruing balok m3 6,300,000.00
141 Kayu kruing usuk/reng m3 6,300,000.00
142 Kayu kruing papan m3 7,875,000.00
143 Kayu Reng mekanis Uk 2 x 3 x 400 cm m3 4,510,000.00
144 Kayu Reng mekanis Uk 3 x 5 x 400 cm m3 4,510,000.00
145 Kayu Usuk mekanis Uk 4 x 6 x 400 cm m3 4,510,000.00
146 Kayu Usuk mekanis Uk 5 x 7 x 400 cm m3 4,510,000.00
147 Kayu Balok mekanis Uk. 6 x 12 x 400 cm m3 5,390,000.00
148 Kayu Balok mekanis Uk. 6 x 15 x 400 cm m3 5,500,000.00
149 Kayu Balok mekanis Uk. 6 x 20 x 400 cm m3 5,500,000.00
150 Kayu meranti balok m3 6,300,000.00
151 Kayu meranti usuk/reng m3 6,300,000.00
152 Kayu meranti papan m3 6,930,000.00
153 Kayu merbau Balok m3 16,800,000.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
154 Kayu merbau papan m3 17,850,000.00
155 Kayu Profil 4/5 kamper m1 37,800.00
156 List profil 2/4 kamper M1 30,450.00
157 Kayu seseh balok m3 2,985,675.00
158 Kayu seseh dolken D 20 Panjang 3 m Batang 171,465.00
159 Kayu seseh dolken D 10 Panjang 4 m Batang 99,750.00
160 Kayu Usuk Albesia 5/7 Panjang 4 m Batang 52,500.00
161 Lem Aica Aibond kg 53,000.00
162 Lem Kayu setara Fox ltr 18,900.00
163 Minyak bekisting setara Calform NX*R ltr 38,325.00

Flooring/ Lantai
164 Parket Jati lokal Uk. 1,2 x 5 x 20 cm m2 220,000.00
165 Parket Jati lokal Uk. 1,2 x 5 x 25 cm m2 230,000.00
166 Parket Jati lokal Uk. 1,2 x 5 x 30 cm m2 250,000.00
167 Jati Eksport Uk. 1,2 x 5 x 20 cm m2 240,000.00
168 Jati Eksport Uk. 1,2 x 5 x 25 cm m2 265,000.00
169 Jati Eksport Uk. 1,2 x 5 x 30 cm m2 290,000.00
170 Jati Eksport Uk. 1,5 x 9 x 30 - 120 cm m2 460,000.00
171 Jati Eksport Uk. 1,5 x 12 x 30 - 120 cm m2 625,000.00
172 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 20 cm m2 190,000.00
173 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 30 cm m2 220,000.00
174 Parket Kayu Merbau Kelas I Uk. 1 x 9 x 30 - 120 cm m2 450,000.00
175 Parket Kayu Merbau Export Uk. 1 x 9 x 30 - 120 cm m2 490,000.00
176 Parket Kayu Merbau Export Uk. 1 x 9 x 60 - 120 cm m2 475,000.00
177 Decking Bangkirai Uk. 1,9 x 9 x 180 - 390 cm m2 440,000.00
178 Decking Krewing Uk. 1,9 x 9 x 180 - 400 cm m2 450,000.00
179 Decking Merbau Uk. 1,9 x 9 x 180 - 400 cm m2 520,000.00
180 Decking Ulin Sulawesi Uk. 1,9 x 9 x 200 cm m2 690,000.00

Lambersering
181 Lambersering Bangkirai Uk. 1 x 9 x 200 cm m2 420,000.00
182 Lambersering Kruing Uk. 2 x 9 x 200 cm m2 320,000.00

Lis Kayu
183 Lis plapond kayu mekanis Uk. 1 x 5 x 400 cm btg 15,000.00
184 Lis Plapond dobel kayu mekanis Uk. 1 x 5 x 400 cm btg 16,000.00
185 Lis Plapond Uk. 0,8 x 5 x 400 cm btg 13,000.00
186 Lis Plapond Uk.1 x 3 x 400 cm btg 11,000.00
187 Lis Plapond tanpa profil Uk. 1 x 5 x 400 cm btg 14,000.00
188 Lisplang kayu mekanis Uk. 2 x 6 x 400 cm btg 35,500.00
189 Lisplang kayu mekanis Uk. 2 x 7 x 400 cm btg 40,000.00
190 Lisplang kayu mekanis Uk. 2 x 8 x 400 cm btg 44,000.00
191 Lisplang kayu mekanis Uk. 2 x 10 x 400 cm btg 51,500.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
192 Lisplang kayu mekanis Uk. 2 x 12 x 400 cm btg 63,000.00
193 Lisplang kayu mekanis Uk. 2 x 15 x 400 cm btg 79,000.00
194 Lisplang kayu mekanis Uk. 2 x 20 x 400 cm btg 115,000.00
195 Lis Kaca Uk. 1,5 x 3 cm m' 6,500.00
196 Lis Dowel Kecil Uk. 1 x 2 cm m' 3,200.00
197 Lis Dowel Besar Uk. 1,3 x 3 cm m' 4,000.00
198 Lis Kusen m' 3,300.00

CONWOOD
Flooring/Deck Application
199 Conwood Deck 4" ( 102 x 3050 x 14 mm) Pcs 67,100.00
200 Conwood Deck 6" ( 152 x 3050 x 14 mm) Pcs 105,400.00
201 Conwood Deck 8" ( 203 x 3050 x 14 mm) Pcs 140,500.00
202 Conwood Deck 4" ( 102 x 3050 x 25 mm) Pcs 140,900.00
203 Conwood Deck 6" ( 152 x 3050 x 25 mm) Pcs 211,400.00
204 Conwood Deck 8" ( 203 x 3050 x 25 mm) Pcs 281,700.00
205 Conwood Deck 12"( 300 x 3050 x 25 mm) Pcs 414,700.00

Decorative Stair
206 Conwood Stair 8" (Vertical) (200 x 1200 x 16 mm) Pcs 74,500.00
207 Conwood Stair 12" (Horisontal) (300 x 1200 x 25 mm) Pcs 163,200.00
208 Conwood Handrail (85 x 3050 x 30 mm) Pcs 130,200.00

Ceiling Application
209 Celling Border (50 X 3050 X 11 mm) Pcs 33,100.00
210 Conwood Lath 3" Cut (76 x 3050 x 11 mm) Pcs 49,900.00
211 Conwood Lath 4" Cut (100 x 3050 x 11 mm) Pcs 61,100.00
212 Conwood Lath 3"(UG)(600 x 1200 x 8 mm) Pcs 105,300.00
213 Conwood Lath 3"(UG)(1200 x 2400 x 8 mm) Pcs 447,700.00

Eave/lisplank
214 Conwood Eave 2 IN 1 (235 x 3050 x 16 mm) Pcs 149,200.00

Wall Application
215 Conwood Lap Siding 6" BG (152 x 3050 x 11mm) Pcs 63,900.00
216 Conwood Lap Siding 8" GO (200 x 3050 x 11mm) Pcs 83,300.00
217 Conwood Decorative Panel (600 x 1200 x 11mm) Pcs 151,600.00
218 Conwood Decorative Panel " V-Groove" (305 x 3050 x 14mm) Pcs 185,400.00

Moulding Application
219 Conwood Floor Mould 4" (Louis) (102 x 3050 x 11mm) Pcs 46,900.00
220 Conwood Floor Mould 4" (Louis) (102 x 3050 x 14mm) Pcs 55,500.00
221 Conwood Floor Mould 4" (Classic) (102 x 3050 x 11mm) Pcs 46,900.00
222 Conwood Floor Mould 4" (Classic) (102 x 3050 x 14mm) Pcs 55,500.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4

Decorative Application
223 Conwood Plank 1" (100 x 3050 x 25 mm) Pcs 90,300.00
224 Conwood Plank 2" (50 x 3050 x 16 mm) Pcs 34,200.00
225 Conwood Plank 2" (50 x 3050 x 25 mm) Pcs 53,000.00
226 Conwood Sun Shade 3" (76 x 3050 x 14 mm) Pcs 45,300.00
227 Conwood Fence 4" Arrow - 1M (100x 1000 x 16 mm) Pcs 28,500.00
228 Conwood Fence 4" Arrow - 1,5M (100x 1500 x 16 mm) Pcs 42,800.00
229 Conwood Fence 4" Botany - 1M (100x 1000 x 16 mm) Pcs 28,500.00
230 Conwood Fence 4" Botany - 1,5M (100x 1500 x 16 mm) Pcs 42,800.00
231 Conwood Fence 4" Classic - 1,5M (100x 1500 x 16 mm) Pcs 44,600.00
232 Conwood Fence 4" Branch - 1M (100x 1000 x 16 mm) Pcs 29,500.00

Planks
233 Conwood Plank 8" Textured (200 x 3050 x 8 mm) Pcs 47,000.00
234 Conwood Plank 8" Plain (200 x 3050 x 8 mm) Pcs 47,000.00

BESI BETON DAN PAGAR


235 Baja Strip (0,2 x 2) cm / Plat Strip Kg 16,500.00
236 Besi Beton U 24 (Polos) kg 8,750.00
237 Besi Beton U 32 (Ulir) Kg 9,375.00
238 Besi Ø5 (3,8 x 6,0) btg 4,200.00
239 Besi Ø6 (5,0 x 12) btg 11,850.00
240 Besi Ø6 (5,2 x 12) btg 12,450.00
241 Besi Ø6 (5,7 x 12) btg 14,750.00
242 Besi Ø8 (6,5 x 12) btg 19,550.00
243 Besi Ø8 (6,7 x 12) btg 20,700.00
244 Besi Ø8 (6,9 x 12) SNI btg 23,900.00
245 Besi Ø8 (7,1 x 12) SNI btg 24,700.00
246 Besi Ø8 (7,4 x 12) SNI btg 26,500.00
247 Besi Ø8 (7,6 x 12) SNI btg 27,200.00
248 Besi Ø8 (7,7 x 12) SNI btg 27,700.00
249 Besi Ø8 (7,8 x 12) SNI btg 28,400.00
250 Besi Ø8 SNI U 24 btg 28,900.00
251 Besi Ø10 (8,4 x 12) SNI btg 33,600.00
252 Besi Ø10 (8,6 x 12) SNI btg 34,800.00
253 Besi Ø10 (8,9 x 12) SNI btg 37,500.00
254 Besi Ø10 (9,2 x 12) SNI btg 39,400.00
255 Besi Ø10 (9,4 x 12) SNI btg 41,500.00
256 Besi Ø10 (9,6 x 12) SNI btg 43,200.00
257 Besi Ø10 (9,8 x 12) SNI btg 44,400.00
258 Besi Ø10 SNI U 24 btg 45,500.00
259 Besi Ø10 Ulir (9,5 x 12) SNI btg 42,700.00
260 Besi Ø10 Ulir (9,7 x 12) SNI btg 44,400.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
261 Besi Ø12 (11,5 x 12) SNI btg 62,700.00
262 Besi Ø13 Ulir (11,5 x 12) SNI btg 64,300.00
263 Besi Ø13 Ulir (11,7 x 12) SNI btg 66,000.00
264 Besi Ø13 Ulir (12,0 x 12) SNI btg 69,200.00
265 Besi Ø13 Ulir (12,5 x 12) SNI btg 74,300.00
266 Besi Ø13 Ulir (12,7 x 12) SNI btg 76,800.00
267 Besi Ø16 Ulir (14 x 12) SNI btg 94,400.00
268 Besi Ø16 Ulir (14,5 x 12) SNI btg 101,200.00
269 Besi Ø16 Ulir (15,0 x 12) SNI btg 108,000.00
270 Besi Ø16 Ulir (15,5 x 12) SNI btg 115,300.00
271 Besi Ø16 Ulir (15,7 x 12) SNI btg 117,500.00
272 Wiremesh M6@50m Rol 2,028,000.00
273 Wiremesh M7 (D6,5mm) Uk. 2,1 x 5,4 m lbr 308,000.00
274 Wiremesh M8 (D7,5mm) Uk. 2,1 x 5,4 m lbr 424,600.00
275 Beugel Besi O8 Kg 12,100.00
276 Beugel penguat /plaat Buah 70,950.00
277 Besi / Baja profil Kg 10,450.00
278 Besi Baja WF 200 x 100 x 4,5 x 7 Kg 11,500.00
279 Besi Baja WF 250 x 125 x 5 x 7 Kg 11,500.00
280 Besi Baja C 100 x 50 x 3,2 Kg 11,500.00
281 Baja Ringan Type C- 75, 0.8 m' 15,950.00
282 Baja Ringan Type C- 75, 0.6 m' 13,750.00
283 Reng Baja m' 7,700.00
284 Profil Canal "C" Tipe C71.075 Batang 16,280.00
285 Profil Canal "C" Tipe C81.075 Batang 94,380.00
286 Profil Canal "C" Tipe C81.065 Batang 90,750.00
287 Profil "Omega / reng Tipe AA Batang 52,800.00
288 Profil "Omega / reng Tipe A Batang 49,500.00
289 Besi Baja L60 X 60 X 6 / L50 x 50 x 5 Kg 13,200.00
290 Profil "Omega / reng Tipe AB Batang 46,200.00
291 Besi Siku L.30.30.3 mm Batang 45,100.00
292 Besi Plat Kg 24,860.00
293 Besi plat 3 X 6 tebal 1,2 mm Bt 215,600.00
294 Besi plat 4 X 8 tebal 1,8 mm Bt 486,200.00
295 Elektrode 2 % Bh 203,500.00
296 Kawat berduri kg 99,000.00
297 Kawat beton RRT kg 15,400.00
298 Kawat Ayak /Kuasa 5 X 5 cm M2 26,400.00
299 Kawat Harmonika 3 X 3 cm M2 33,000.00
300 Kawat Nyamuk M2 24,200.00
301 Pagar Setara BRC T.90 diameter 6mm m' 181,500.00
302 Pagar Setara BRC T.120 diameter 6mm m' 225,500.00
303 Pagar Setara BRC T.150 diameter 6mm m' 236,500.00
304 Pagar Setara BRC T.175 diameter 7mm m' 356,400.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
305 Pagar Setara BRC T.190 diameter 7mm m' 533,500.00
306 Pagar HotDip Galvanized T.90 diameter 6mm m' 168,300.00
307 Pagar HotDip Galvanized T.120 diameter 6mm m' 169,400.00
308 Pagar HotDip Galvanized T.150 diameter 7mm m' 231,000.00
309 Pagar HotDip Galvanized T.175 diameter 7mm m' 251,900.00
310 Pagar HotDip Galvanized T.190 diameter 7mm m' 266,200.00
312 Profil Aluminium Kaca 3/4 m 9,900.00
313 Profil Aluminium L 3 cm lis Kaca m 12,650.00
314 Profil Aluminium 4" m 66,000.00
315 Skruf Fixer 5 cm bh 550.00
316 Dynabolt bh 3,675.00
317 Sealant Tube 36,300.00
318 Rolling Door Aluminium M2 286,000.00
319 Silicon Kg 73,700.00

FINISHING
320 Amplas lbr 6,600.00
321 Cat besi kg 93,170.00
322 Cat dasar Tembok Setara Emco kg 59,400.00
323 Cat Setara emco Lux Biasa kg 59,400.00
324 Cat Setara emco Lux Warna kg 64,460.00
325 Cat Setara emco Lux Warna Tua kg 72,930.00
326 Cat Galvanis kg 87,780.00
327 Cat Kayu Emco kg 63,800.00
328 Cat Baja Chromate (anti karat) Kg 110,000.00
329 Cat Marka Jalan kg 43,890.00
330 Cat menie besi kg 49,500.00
331 Cat menie Kayu kg 49,500.00
332 Cat tembok Setara Decolith kg 39,930.00
333 Cat tembok Setara Dulux Exterior kg 126,500.00
334 Cat tembok Setara Dulux Interior kg 93,500.00
335 Cat tembok Setara Vinilex kg 39,930.00

Cat KCA
336 Cat Natural@25 kg Pail 399,000.00
337 Cat Flakes@25 kg Pail 683,000.00
338 Cat Genteng @25kg Pail 519,000.00
339 Stone Coating :
340 Clear gloss air kg 48,000.00
341 Black gloss air kg 46,000.00
342 Clear gloss solvent kg 50,500.00
343 Black gloss solvent kg 54,000.00
344 Clear doft solvent kg 53,000.00
345 Black doft solvent kg 54,000.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
346 Dempul / Plamir ltr 52,800.00
347 Dempul / Plamir Altik ltr 46,530.00
348 Dempul Impra Kayu ltr 49,500.00
349 Kuas untuk mengecat bh 13,200.00
350 Lem Fox (Rajawali Kuning) Gln 159,500.00
351 Lem Wall Paper Kg 27,500.00
352 Mild zak 13,200.00
353 Minyak cat ltr 46,530.00
354 Melamine Lack / Imfra ltr 77,000.00
355 Okear / Veap Kg 82,500.00
356 Plamir kayu kg 49,500.00
357 Plamir tembok setara wall Putty kg 159,500.00
358 Politur ultra ltr 75,130.00
359 Politur Jadi ltr 75,900.00
360 vernis ltr 60,500.00
361 Residu / Teer Ltr 27,500.00
362 Roll Buah 38,500.00
363 Sending Seaker ltr 61,050.00
364 Soda Api Kg 24,200.00
365 Thiner A Spesial ltr 27,500.00
366 Thiner B ltr 27,500.00
367 Teack Oil ltr 66,550.00
368 Wall Paper Setara Silk House m2 660,000.00
369 Wood Filler ltr 60,500.00
370 Cat Scotlight Ltr 166,100.00

KACA
371 Bingkai Nako Silver daun 38,500.00
372 Bingkai Nako Coklat daun 33,000.00
373 Glass Block bh 40,700.00
374 Kaca 3 mm bening m2 82,500.00
375 Kaca 5 mm bening m2 143,000.00
376 Kaca 6 mm bening m2 187,000.00
377 Kaca 8 mm bening m2 317,900.00
378 Kaca 10 mm bening m2 385,000.00
379 Kaca 12 mm bening m2 495,000.00
380 Kaca Cermin 3 mm m2 165,000.00
381 Kaca Cermin 5 mm m2 308,000.00
382 Kaca Es/Kapur 3 mm m2 198,000.00
383 Kaca Es/Kapur 5 mm m2 253,000.00
384 Kaca ryben 3 mm m2 99,000.00
385 Kaca ryben 5 mm m2 154,000.00
386 Kaca asahi tebal 3 mm polos clear m2 63,000.00
387 Kaca asahi tebal 3 mm ryben dark grey m2 89,000.00
388 Kaca asahi tebal 3 mm cermin mirror m2 140,000.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
389 Kaca asahi tebal 3 mm es mislet m2 145,500.00
390 Kaca asahi tebal 3 mm biru dark blue m2 235,500.00
391 Kaca asahi tebal 3 mm one way m2 350,000.00
392 Kaca asahi tebal 5 mm polos clear m2 92,500.00
393 Kaca asahi tebal 5 mm ryben dark grey m2 113,500.00
394 Kaca asahi tebal 5 mm cermin mirror m2 200,000.00
395 Kaca asahi tebal 5 mm es mislet m2 190,000.00
396 Kaca asahi tebal 6 mm polos clear m2 145,000.00
397 Kaca asahi tebal 8 mm polos clear m2 289,000.00
398 Kaca asahi tebal 10 mm polos clear m2 350,000.00
399 Kaca asahi tebal 12 mm polos clear m2 362,500.00
400 Kaca tempered asahimas tebal 3mm polos clear m2 203,500.00
401 Kaca tempered asahimas tebal 3mm ryben dark grey m2 242,000.00
402 Kaca tempered asahimas tebal 3mm sanergy clear m2 604,000.00
403 Kaca tempered asahimas tebal 4mm polos clear m2 200,500.00
404 Kaca tempered asahimas tebal 4mm sanergy clear m2 692,000.00
405 Kaca tempered asahimas tebal 5mm polos clear m2 224,500.00
406 Kaca tempered asahimas tebal 5mm ryben dark grey m2 278,000.00
407 Kaca tempered asahimas tebal 5mm stopsol m2 436,000.00
408 Kaca tempered asahimas tebal 5mm warna m2 372,000.00
409 Kaca tempered asahimas tebal 5mm sanergy clear m2 812,000.00
410 Kaca tempered asahimas tebal 6mm polos clear m2 299,500.00
411 Kaca tempered asahimas tebal 6mm ryben dark grey m2 406,000.00
412 Kaca tempered asahimas tebal 6mm stopsol m2 825,000.00
413 Kaca tempered asahimas tebal 6mm warna m2 466,500.00
414 Kaca tempered asahimas tebal 6mm diamon m2 621,500.00
415 Kaca tempered asahimas tebal 6mm sanergy clear m2 1,001,000.00
416 Kaca tempered asahimas tebal 8mm polos clear m2 391,500.00
417 Kaca tempered asahimas tebal 8mm stopsol m2 1,132,000.00
418 Kaca tempered asahimas tebal 8mm warna m2 731,500.00
419 Kaca tempered asahimas tebal 8mm diamon m2 1,078,000.00
420 Kaca tempered asahimas tebal 8mm sanergy clear m2 1,375,000.00
421 Kaca tempered asahimas tebal 10mm polos clear m2 482,000.00
422 Kaca tempered asahimas tebal 10mm diamon m2 1,540,000.00
423 Kaca tempered asahimas tebal 12mm polos clear m2 565,000.00
424 Kaca tempered asahimas tebal 12mm diamon m2 1,962,500.00
425 Kaca tempered asahimas tebal 15mm polos clear m2 4,616,500.00
426 Kaca tempered asahimas tebal 15mm diamon m2 6,000,000.00
427 Kaca tempered asahimas tebal 19mm polos clear m2 5,313,000.00
428 Kaca tempered asahimas tebal 19mm diamon m2 7,309,500.00
429 Kaca tebal 3+3 mm laminet biasa m2 345,000.00
430 Kaca tebal 4+4 mm laminet biasa m2 422,000.00
431 Kaca tebal 5+5 mm laminet biasa m2 475,000.00
432 Kaca tebal 6+6 mm laminet biasa m2 566,000.00
433 Kaca tebal 8+8 mm laminet biasa m2 846,000.00
434 Kaca tebal 10+10 mm laminet biasa m2 1,041,000.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
435 Kaca tebal 12+12 mm laminet biasa m2 1,184,000.00
436 Kaca tebal 3+3 mm laminet tempered m2 957,000.00
437 Kaca tebal 4+4 mm laminet tempered m2 1,056,000.00
438 Kaca tebal 5+5 mm laminet tempered m2 1,083,000.00
439 Kaca tebal 6+6 mm laminet tempered m2 1,375,000.00
440 Kaca tebal 8+8 mm laminet tempered m2 1,670,000.00
441 Kaca tebal 10+10 mm laminet tempered m2 1,938,000.00
442 Kaca tebal 12+12 mm laminet tempered m2 2,134,000.00
443 Ongkos polin kaca tempered tebal 5mm m' 15,000.00
444 Ongkos polin kaca tempered tebal 6mm m' 15,000.00
445 Ongkos polin kaca tempered tebal 8mm m' 25,000.00
446 Ongkos polin kaca tempered tebal 10mm m' 25,000.00
447 Ongkos polin kaca tempered tebal 12mm m' 27,500.00
448 Ongkos polin kaca tempered tebal 19mm m' 90,000.00

PIPA
449 Pipa Galvanis 1" M1 55,650.00
450 Pipa Galvanis 1,5 BSA M1 84,000.00
451 Pipa Galvanis 2" M1 118,000.00
452 Pipa Galvanis 3" M1 181,000.00
453 Pipa Setara Maspion AW 1/2 M1 7,560.00
454 Pipa Setara Maspion AW 3/4 M1 10,000.00
455 Pipa Setara Maspion AW 1 M1 11,550.00
456 Pipa Setara Maspion AW 1-1/2 M1 22,000.00
457 Pipa Setara Maspion AW 1-1/4 M1 17,000.00
458 Pipa Setara Maspion AW 2 M1 32,000.00
459 Pipa Setara Maspion AW 2-1/2 M1 41,000.00
460 Pipa Setara Maspion AW 3 M1 58,275.00
461 Pipa Setara Maspion AW 4 M1 85,000.00
462 Pipa Setara Maspion AW 5 M1 134,000.00
463 Pipa Setara Maspion AW 6 M1 176,400.00
464 Pipa Setara Maspion AW 8 M1 275,000.00
465 Pipa Setara Maspion AW 10 M1 390,000.00
466 Pipa Setara Maspion AW 12 M1 630,000.00
467 Pipa Setara Maspion AW 14 M1 800,625.00
468 Pipa Setara Maspion AW 16 M1 979,125.00
469 Pipa Setara Maspion C 3/4 M1 3,675.00
470 Pipa Setara Maspion C 5/8 M1 2,100.00
471 Pipa Setara Maspion C 1 M1 7,000.00
472 Pipa Setara Maspion C 1-1/2 M1 9,000.00
473 Pipa Setara Maspion C 1-1/4 M1 10,000.00
474 Pipa Setara Maspion C 2 M1 13,000.00
475 Pipa Setara Maspion C 2-1/2 M1 17,000.00
476 Pipa Setara Maspion C 3 M1 19,000.00
477 Pipa Setara Maspion C 4 M1 25,000.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
478 Pipa Setara Maspion D 1/2 M1 7,000.00
479 Pipa Setara Maspion D 1-1/2 M1 12,000.00
480 Pipa Setara Maspion D 1-1/4 M1 11,000.00
481 Pipa Setara Maspion D 2 M1 15,225.00
482 Pipa Setara Maspion D 2-1/2 M1 23,000.00
483 Pipa Setara Maspion D 3 M1 32,550.00
484 Pipa Setara Maspion D 4 M1 46,000.00
485 Pipa Setara Maspion D 5 M1 75,000.00
486 Pipa Setara Maspion D 6 M1 90,825.00
487 Pipa Setara Maspion D 8 M1 161,000.00
488 Pipa Setara Maspion D 10 M1 280,000.00
489 Pipa Setara Maspion D 12 M1 381,675.00
490 Pipa Setara Maspion D 14 M1 499,800.00
491 Pipa Setara Maspion D 16 M1 646,800.00
492 Pipa / selang spiral sel kran M1 34,650.00
490 Pipa setara langgeng warna abu - abu AW 1/2 M1 6,442.50
491 Pipa setara langgeng warna abu - abu AW 3/4 M1 7,847.50
492 Pipa setara langgeng warna abu - abu AW 1 M1 9,880.00
493 Pipa setara langgeng warna abu - abu AW 1 1/4 M1 13,985.00
494 Pipa setara langgeng warna abu - abu AW 1 1/2 M1 18,212.50
493 Pipa setara langgeng warna abu - abu AW 2 M1 27,047.50
490 Pipa setara langgeng warna abu - abu AW 2 1/2 M1 34,722.50
491 Pipa setara langgeng warna abu - abu AW 3 M1 49,525.00
492 Pipa setara langgeng warna abu - abu AW 4 M1 72,182.50
493 Pipa setara langgeng warna abu - abu AW 5 M1 113,850.00
494 Pipa setara langgeng warna abu - abu AW 6 M1 150,472.50
495 Pipa setara langgeng warna abu - abu AW 8 M1 234,032.50
494 Pipa setara langgeng warna abu - abu AW 10 M1 332,500.00
491 Pipa setara langgeng warna abu - abu AW 12 M1 475,115.00
492 Pipa setara langgeng warna abu - abu AW 16 M1 835,555.00
493 Pipa setara langgeng warna abu - abu D 1 1/4 M1 8,712.50
494 Pipa setara langgeng warna abu - abu D 1 1/2 M1 9,880.00
495 Pipa setara langgeng warna abu - abu D 2 M1 12,912.50
496 Pipa setara langgeng warna abu - abu D 2 1/2 M1 19,125.00
495 Pipa setara langgeng warna abu - abu D 3 M1 27,740.00
492 Pipa setara langgeng warna abu - abu D 4 M1 39,007.50
493 Pipa setara langgeng warna abu - abu D 5 M1 63,717.50
494 Pipa setara langgeng warna abu - abu D 6 M1 77,397.50
495 Pipa setara langgeng warna abu - abu D 8 M1 136,877.50
496 Pipa setara langgeng warna abu - abu D 10 M1 238,877.50
497 Pipa setara langgeng warna abu - abu D 12 M1 325,575.00
496 Pipa setara langgeng warna abu - abu D 14 M1 426,405.00
493 Pipa setara langgeng warna abu - abu D 16 M1 551,932.50
494 Pipa setara langgeng warna abu - abu D 20 M1 953,412.50
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
495 Pipa setara langgeng warna abu - abu C 5/8 M1 1,770.00
496 Pipa setara langgeng warna abu - abu C 1/2 M1 2,965.00
497 Pipa setara langgeng warna abu - abu C 3/4 M1 3,220.00
498 Pipa setara langgeng warna abu - abu C 1 M1 4,505.00
497 Pipa setara langgeng warna abu - abu C 1 1/4 M1 5,980.00
494 Pipa setara langgeng warna abu - abu C 1 1/2 M1 7,170.00
495 Pipa setara langgeng warna abu - abu C 2 M1 10,822.50
496 Pipa setara langgeng warna abu - abu C 2 1/2 M1 13,710.00
497 Pipa setara langgeng warna abu - abu C 3 M1 16,707.50
498 Pipa setara langgeng warna abu - abu C 4 M1 21,525.00
499 Pipa setara langgeng warna abu - abu C 5 M1 29,120.00
498 Pipa setara winlon warna abu - abu AW 1/2 M1 5,527.50
495 Pipa setara winlon warna abu - abu AW 3/4 M1 7,067.50
496 Pipa setara winlon warna abu - abu AW 1 M1 9,212.50
497 Pipa setara winlon warna abu - abu AW 1 1/4 M1 13,475.00
498 Pipa setara winlon warna abu - abu AW 1 1/2 M1 15,867.50
499 Pipa setara winlon warna abu - abu AW 2 M1 22,797.50
500 Pipa setara winlon warna abu - abu AW 2 1/2 M1 29,727.50
499 Pipa setara winlon warna abu - abu AW 3 M1 41,772.50
496 Pipa setara winlon warna abu - abu AW 4 M1 64,322.50
497 Pipa setara winlon warna abu - abu AW 5 M1 102,052.50
498 Pipa setara winlon warna abu - abu AW 6 M1 128,975.00
499 Pipa setara winlon warna abu - abu AW 8 M1 204,737.50
500 Pipa setara winlon warna abu - abu AW 10 M1 291,362.50
501 Pipa setara winlon warna abu - abu AW 12 M1 489,912.50
500 Pipa setara winlon warna abu - abu D 1 1/4 M1 7,782.50
497 Pipa setara winlon warna abu - abu D 1 1/2 M1 8,772.50
498 Pipa setara winlon warna abu - abu D 2 M1 11,467.50
499 Pipa setara winlon warna abu - abu D 2 1/2 M1 16,335.00
500 Pipa setara winlon warna abu - abu D 3 M1 23,732.50
501 Pipa setara winlon warna abu - abu D 4 M1 33,687.50
502 Pipa setara winlon warna abu - abu D 6 M1 66,660.00
501 Pipa setara winlon warna abu - abu D 8 M1 117,727.50
498 Pipa setara winlon warna abu - abu D 10 M1 218,405.00
499 Pipa setara winlon warna abu - abu D 12 M1 297,220.00
500 Pipa setara winlon warna abu - abu C 5/8 M1 1,485.00
501 Pipa setara winlon warna abu - abu C 1/2 M1 2,722.50
502 Pipa setara winlon warna abu - abu C 3/4 M1 2,887.50
503 Pipa setara winlon warna abu - abu C 1 M1 4,042.50
502 Pipa setara winlon warna abu - abu C 1 1/4 M1 5,362.50
499 Pipa setara winlon warna abu - abu C 1 1/2 M1 6,737.50
500 Pipa setara winlon warna abu - abu C 2 M1 9,212.50
501 Pipa setara winlon warna abu - abu C 2 1/2 M1 11,605.00
502 Pipa setara winlon warna abu - abu C 3 M1 14,355.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
503 Pipa setara winlon warna abu - abu C 4 M1 19,855.00
504 Pipa setara wavin warna putih AW 1/2 M1 4,757.50
503 Pipa setara wavin warna putih AW 3/4 M1 6,517.50
500 Pipa setara wavin warna putih AW 1 M1 8,910.00
501 Pipa setara wavin warna putih AW 1 1/4 M1 13,365.00
502 Pipa setara wavin warna putih AW 1 1/2 M1 15,345.00
503 Pipa setara wavin warna putih AW 2 M1 19,635.00
504 Pipa setara wavin warna putih AW 2 1/2 M1 28,655.00
505 Pipa setara wavin warna putih AW 3 M1 38,637.50
504 Pipa setara wavin warna putih AW 4 M1 64,020.00
501 Pipa setara wavin warna putih AW 5 M1 106,067.50
502 Pipa setara wavin warna putih AW 6 M1 148,775.00
503 Pipa setara wavin warna putih AW 8 M1 249,700.00
504 Pipa setara wavin warna putih AW 10 M1 386,100.00
505 Pipa setara wavin warna putih AW 12 M1 544,390.00
506 Pipa setara wavin warna putih D 1 1/4 M1 8,387.50
505 Pipa setara wavin warna putih D 1 1/2 M1 9,487.50
502 Pipa setara wavin warna putih D 2 M1 12,155.00
503 Pipa setara wavin warna putih D 2 1/2 M1 16,445.00
504 Pipa setara wavin warna putih D 3 M1 20,872.50
505 Pipa setara wavin warna putih D 4 M1 32,835.00
506 Pipa setara wavin warna putih D 5 M1 52,937.50
507 Pipa setara wavin warna putih D 6 M1 69,822.50
506 Pipa setara wavin warna putih D 8 M1 122,815.00
503 Pipa setara wavin warna putih D 10 M1 202,317.50
504 Pipa setara wavin warna putih D 12 M1 284,020.00
505 Pipa setara langgeng warna putih AW 1/2 M1 4,520.00
506 Pipa setara langgeng warna putih AW 3/4 M1 12,385.00
507 Pipa setara langgeng warna putih AW 1 M1 8,465.00
508 Pipa setara langgeng warna putih AW 1 1/4 M1 12,697.50
507 Pipa setara langgeng warna putih AW 1 1/2 M1 14,697.50
504 Pipa setara langgeng warna putih AW 2 M1 18,655.00
505 Pipa setara langgeng warna putih AW 2 1/2 M1 27,222.50
506 Pipa setara langgeng warna putih AW 3 M1 36,707.50
507 Pipa setara langgeng warna putih AW 4 M1 60,812.50
508 Pipa setara langgeng warna putih AW 5 M1 100,765.00
509 Pipa setara langgeng warna putih AW 6 M1 141,337.50
508 Pipa setara langgeng warna putih AW 8 M1 237,215.00
505 Pipa setara langgeng warna putih AW 10 M1 366,795.00
506 Pipa setara langgeng warna putih AW 12 M1 517,172.50
507 Pipa setara langgeng warna putih AW 14 M1 708,120.00
508 Pipa setara langgeng warna putih AW 16 M1 885,117.50
509 Pipa setara langgeng warna putih D 1 1/4 M1 7,970.00
510 Pipa setara langgeng warna putih D 1 1/2 M1 9,015.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
509 Pipa setara langgeng warna putih D 2 M1 11,547.50
506 Pipa setara langgeng warna putih D 2 1/2 M1 15,625.00
507 Pipa setara langgeng warna putih D 3 M1 19,830.00
508 Pipa setara langgeng warna putih D 4 M1 31,195.00
509 Pipa setara langgeng warna putih D 5 M1 50,292.50
510 Pipa setara langgeng warna putih D 6 M1 66,332.50
511 Pipa setara langgeng warna putih D 8 M1 116,675.00
510 Pipa setara langgeng warna putih D 10 M1 192,202.50
507 Pipa setara langgeng warna putih D 12 M1 269,820.00
508 Pipa setara langgeng warna putih D 14 M1 451,702.50
509 Pipa setara langgeng warna putih D 16 M1 584,677.50
510 Pipa setara langgeng warna putih D 20 M1 925,642.50
511 Pipa setara langgeng warna putih C 5/8 M1 1,770.00
512 Pipa setara langgeng warna putih C 1/2 M1 2,880.00
511 Pipa setara langgeng warna putih C 3/4 M1 3,220.00
508 Pipa setara langgeng warna putih C 1 M1 4,370.00
509 Pipa setara langgeng warna putih C 1 1/4 M1 5,805.00
510 Pipa setara langgeng warna putih C 1 1/2 M1 7,170.00
511 Pipa setara langgeng warna putih C 2 M1 10,507.50
512 Pipa setara langgeng warna putih C 2 1/2 M1 13,310.00
513 Pipa setara langgeng warna putih C 3 M1 16,220.00
512 Pipa setara langgeng warna putih C 4 M1 16,220.00
509 Pipa setara winlon warna putih AW 1/2 M1 3,822.50
510 Pipa setara winlon warna putih AW 3/4 M1 5,142.50
511 Pipa setara winlon warna putih AW 1 M1 7,150.00
512 Pipa setara winlon warna putih AW 1 1/4 M1 9,955.00
513 Pipa setara winlon warna putih AW 1 1/2 M1 12,925.00
514 Pipa setara winlon warna putih AW 2 M1 17,820.00
513 Pipa setara winlon warna putih AW 2 1/2 M1 23,925.00
510 Pipa setara winlon warna putih AW 3 M1 32,972.50
511 Pipa setara winlon warna putih AW 4 M1 54,587.50
512 Pipa setara winlon warna putih AW 5 M1 81,262.50
513 Pipa setara winlon warna putih AW 6 M1 116,792.50
514 Pipa setara winlon warna putih AW 8 M1 183,067.50
515 Pipa setara winlon warna putih AW 10 M1 263,917.50
514 Pipa setara winlon warna putih D 1 1/4 M1 6,160.00
511 Pipa setara winlon warna putih D 1 1/2 M1 7,480.00
512 Pipa setara winlon warna putih D 2 M1 10,065.00
513 Pipa setara winlon warna putih D 2 1/2 M1 13,612.50
514 Pipa setara winlon warna putih D 3 M1 16,967.50
515 Pipa setara winlon warna putih D 4 M1 27,610.00
516 Pipa setara winlon warna putih D 5 M1 40,590.00
515 Pipa setara winlon warna putih D 6 M1 57,945.00
512 Pipa setara winlon warna putih D 8 M1 98,945.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
513 Pipa setara winlon warna putih D 10 M1 186,367.50
514 Pipa setara winlon warna putih C 5/8 M1 1,402.50
515 Pipa setara winlon warna putih C 1/2 M1 2,612.50
516 Pipa setara winlon warna putih C 3/4 M1 2,832.50
517 Pipa setara winlon warna putih C 1 M1 4,207.50
516 Pipa setara winlon warna putih C 1 1/4 M1 4,922.50
513 Pipa setara winlon warna putih C 1 1/2 M1 6,160.00
514 Pipa setara winlon warna putih C 2 M1 8,662.50
515 Pipa setara winlon warna putih C 2 1/2 M1 10,917.50
516 Pipa setara winlon warna putih C 3 M1 13,585.00
517 Pipa setara winlon warna putih C 4 M1 18,122.50
518 Pipa setara vilano warna putih AW 1/2 M1 3,482.50
517 Pipa setara vilano warna putih AW 3/4 M1 4,870.00
514 Pipa setara vilano warna putih AW 1 M1 6,382.50
515 Pipa setara vilano warna putih AW 1 1/4 M1 9,287.50
516 Pipa setara vilano warna putih AW 3 M1 29,035.00
517 Pipa setara vilano warna putih AW 4 M1 41,785.00
518 Pipa setara vilano warna putih AW 5 M1 69,670.00
519 Pipa setara vilano warna putih AW 6 M1 99,282.50
518 Pipa setara vilano warna putih D 1 1/4 M1 5,805.00
515 Pipa setara vilano warna putih D 1 1/2 M1 6,967.50
516 Pipa setara vilano warna putih D 2 M1 8,707.50
517 Pipa setara vilano warna putih D 2 1/2 M1 12,190.00
518 Pipa setara vilano warna putih D 3 M1 15,675.00
519 Pipa setara vilano warna putih D 4 M1 24,382.50
520 Pipa setara vilano warna putih D 5 M1 31,930.00
519 Pipa setara vilano warna putih D 6 M1 55,157.50

BAHAN LISTRIK
520 Coaxial cable 5C - 75 ohm commscof m1 18,700.00
521 Box Panel (3 mm) (400 x 600) Bh 598,400.00
522 Figting lampu Broco Bh 22,000.00
523 Inbow dos plastik clipsal E 157 P OB bj 11,935.00
524 Kabel NYM 2 x 1.5 mm Suprime NYM m1 11,000.00
525 Kabel NYY 2 x 1.5 mm m1 15,950.00
526 Kabel NYM 2 x 2.5 mm m1 16,500.00
527 Kabel NYY 3 x 1.5 mm m1 19,800.00
528 Kabel NYM 3 x 2.5 mm m1 20,900.00
529 Kabel NYY 3 x 2.5 mm m1 27,500.00
530 Kabel NYM 4 mm m1 39,900.00
531 Kabel NYY 2 x 2,5 mm m1 21,450.00
532 Kabel Twisteed 2 x 16 mm m1 16,500.00
533 Kabel telephone m1 17,482.50
534 Klem clipsal 20 mm bj 11,025.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
535 Lampu Son 150 Watt Setara Philips Set 1,438,500.00
536 Lampu Mercury 125 Watt Setara Philips Set 1,403,850.00
537 Lampu Mercury 250 Watt Setara Philips Set 2,977,800.00
538 Lampu Mercury 400 Watt Setara Philips Set 11,118,450.00
539 Lampu pijar 10 Watt Setara Philips bh 7,150.00
540 Lampu pijar 15 Watt Setara Philips bh 7,700.00
541 Lampu pijar 25 Watt Setara Philips bh 8,030.00
542 Lampu pijar 40 Watt Setara Philips bh 9,130.00
543 Lampu TL 20 Watt Komplit (Ballast Philips) bh 115,500.00
544 Lampu TL 25 Watt Komplit (Ballast Philips) bh 126,000.00
545 Lampu LED (5 Watt) Setara Philips Bh 55,000.00
546 Lampu LED (7 Watt) Setara Philips Bh 82,500.00
547 Lampu LED (10 Setara Philips Bh 113,850.00
548 Lampu LED (13 Watt) Setara Philips Bh 148,500.00
549 Lampu Sorot LED (5 Watt) Setara Philips Bh 209,000.00
550 Lampu Sorot LED (7 Watt) Setara Philips Bh 239,800.00
551 Lampu Sorot LED (10 Watt) Setara Philips Bh 278,250.00
552 Lampu Sorot LED (13 Watt) Setara Philips Bh 363,000.00
553 Lampu Esensial (5 Watt) Setara Philips Bh 30,800.00
554 Lampu Esensial (8 Watt) Setara Philips Bh 38,500.00
555 Lampu Esensial (11 Watt) Setara Philips Bh 44,000.00
556 Lampu Esensial (14 Watt) Setara Philips Bh 52,800.00
557 Lampu Esensial (18 Watt) Setara Philips Bh 58,300.00
558 Magnet Contactor 80 A SN - 50 Bh 1,225,224.00
559 MCB 3 phase 40 A MG Bh 347,550.00
560 MCB 3 phase 63 A MG Bh 660,450.00
561 Panel MDP Unit 33,206,250.00
562 Panel SDP Unit 14,437,500.00
563 Pipa clipsal 20 mm bt 15,400.00
564 Pipa flexible clipsal 20 mm m1 11,000.00
565 Saklar ganda Setara Broco Bh 30,800.00
566 Saklar tunggal Setara Broco Bh 19,800.00
567 SL 18 Watt Komplit bh 81,675.00
568 Sock clipsal 20 mm bj 3,300.00
569 Steker bh 14,740.00
570 Stop Kontak bh 27,500.00
571 Stop Kontak Khusus (Kedap Air) bh 49,500.00
572 Tee dos clipsal 20 mm bh 7,480.00
573 Time Switch Bh 472,500.00
574 T Foring Bh 46,200.00

MARMER / GRANIT
575 Marmer (30 x 30) m2 308,000.00
576 Granit (30 x 30) Tekstur Kasar Tebal 3 cm m2 715,000.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
577 Batu Andesit (30 x 30 x 5 cm) m2 385,000.00
578 Roster Keramik (12 x 11 x 24) bh 46,200.00

GRANIT TILE
579 Setara Essenza 40 x 40 m2 315,150.00
580 Setara Essenza 60 x 60 m2 387,200.00
581 Setara Granito 40 x 40 cm m2 348,150.00
582 Setara Nero Granito 30 x 60 cm m2 305,800.00
583 Setara Nero Granito 40 x 40 cm m2 348,150.00
584 Setara Nero Granito 60 x 60 cm m2 345,950.00
585 Setara Ex Cina 60 x 60 cm m2 181,500.00
586 Setara Ex Cina 80 x 80 cm m2 231,000.00

KERAMIK
587 Keramik Setara Asia Tile 20 x 20 kelas I warna muda m2 71,500.00
588 Keramik Setara Asia Tile 20 x 20 kelas I warna tua m2 74,800.00
589 Keramik Setara Asia Tile 20 x 25 kelas I m2 77,000.00
590 Keramik Setara Asia Tile 30 x 30 kelas I warna muda m2 55,000.00
591 Keramik Setara Asia Tile 30 x 30 kelas I warna tua m2 57,200.00
592 Keramik Setara Asia Tile 40 x 40 kelas I m2 74,800.00
593 Keramik Setara Asia Tile 60 x 60 kelas I Setara Platinum m2 126,500.00
594 Keramik Setara ARWANA ( warna putih) 40 X 40 M2 51,700.00
595 Keramik Setara ARWANA ( warna tua) M2 66,000.00
587 Keramik Setara Ikad (Keramik) Kw. I 20 x 20 cm m2 63,800.00
588 Keramik Setara Ikad (Keramik) Kw. I 30 x 30 cm m2 68,200.00
589 Keramik Setara Ikad (Keramik) Kw. I 40 x 40 cm m2 77,000.00
590 Keramik Setara Ikad (Keramik) Kw. I 50 x 50 cm m2 88,550.00
591 Keramik Setara KIA 20/20 cm warna muda m2 71,500.00
592 Keramik Setara KIA 30/30 cm warna muda m2 72,600.00
593 Keramik Setara KIA 20/20 cm warna tua m2 77,550.00
594 Keramik Setara KIA 30/30 cm warna tua m2 77,550.00
595 Keramik Setara Mulia 20 x 20 cm Warna Tua m2 51,700.00
596 Keramik Setara Mulia 20 x 20 cm Warna Muda m2 48,950.00
597 Keramik Setara Mulia 30 x 30 cm Warna Putih m2 47,410.00
598 Keramik Setara Mulia 30 x 30 Warna Marbel m2 55,550.00
599 Keramik Setara Mulia 30 x 30 Warna Impresso m2 57,090.00
600 Keramik Setara Mulia 40 x 40 cm kelas I m2 69,850.00
601 Keramik Setara ROMAN 20/20 cm m2 102,850.00
602 Keramik Setara ROMAN 30/30 cm m2 143,000.00
603 Tegel Bata 20 x 20 Pc m2 86,350.00
604 Tegel B/TB 20 x 20 Kuning m2 86,350.00
605 Tegel 20 x 20 TB Merah m2 86,350.00
606 Tegel 30 x 30 TB PC m2 86,350.00
607 Tegel 30 x 30 TB PC Kuning m2 86,350.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
608 Tegel 30 x 30 Warna Merah m2 86,350.00
609 Tegel PC Abu - Abu 20/20 cm m2 86,350.00
610 Tegel PC Warna 20/20 cm m2 86,350.00
611 Tegel PC Warna 30/30 cm m2 86,350.00

ATAP
612 Alang-alang panjang 2,4 meter lbr 16,500.00
613 Alluminium foil M2 Double Roll 245,300.00
614 Akustik 60 cm x 120 cm lembar 54,450.00
615 Asbes Bubungan lbr 49,000.00
616 Asbes Gelombang 1,80 m x 0,80 m lbr 38,500.00
617 Asbes Gelombang 1,80 m x 1,05 m lbr 41,800.00
618 Asbes Gelombang 2,10 m x 1,05 m lbr 45,100.00
619 Asbes Gelombang 2,4 m x 1,05 m lbr 53,900.00
620 Asbes Rata 2 m x 1 m x 4 mm lbr 60,500.00
621 Bentala tanah liat Ex Pejaten bh 93,500.00
622 Bentala Besar polos Lubang 25 cm bj 82,500.00
623 Bentala Besar Warna Lubang 25 cm bj 110,000.00
624 Bentala Besar polos Lubang 90 cm bj 143,000.00
625 Bentala Besar Warna Lubang 90 cm bj 165,000.00
626 Bubungan Besar bj 17,600.00
627 Bubungan Kecil bj 13,200.00
628 Bubungan Bambe Kecil bj 19,250.00
629 Bubungan Bulat Karang Pilang bj 19,250.00
630 Bubungan Bulat Jati Wangi bj 17,050.00
631 Bubungan Bulat Ngalayur isi 3,5/m bj 9,900.00
632 Bubungan Besar Good Year bj 17,600.00
633 Bubungan Beton Cisangkan bj 21,450.00
634 Bubungan Karang Pilang isi 3,5/m bj 19,250.00
635 Bubungan Pletong Jatiwangi bj 16,500.00
636 Bubungan SL Utama Bj 16,500.00
637 Bubungan SL Ngalayur bj 9,350.00
638 Bubungan Segi Tiga Karang Pilang bj 19,250.00
639 Bubungan Utama isi 3,5/m bj 16,500.00
640 Genteng Bambe bj 5,390.00
641 Genteng Bambe Karang Pilang bj 5,390.00
642 Genteng Bambe Kecil bj 5,170.00
643 Genteng Beton Cisangkan bj 13,750.00
644 Genteng Gemini bj 6,600.00
645 Genteng Kanmuri (glazur) isi 14/m2 bj 11,550.00
646 Genteng Kodok Lokal bj 3,740.00
647 Genteng Kodok Kamulan bj 3,850.00
648 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj 5,500.00
649 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj 5,170.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
650 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj 5,500.00
651 Genteng Kodok Soka bj 2,420.00
652 Genteng Lestari bj 3,080.00
653 Genteng Metal 80 x 77,6 (Polos) lembar 40,590.00
654 Genteng Metal 80 x 77,6 (Pasir) lembar 65,340.00
655 Genteng Morando Abadi isi 18/m2 bj 9,240.00
656 Genteng Morando Jatiwangi isi 18/m2 bj 4,950.00
657 Genteng Morando Ngalayur isi 20/m2 bj 4,070.00
658 Genteng Morando Metal bj 63,800.00
659 Genteng Pejaten Mini bj 3,080.00
660 Genteng Plentong bj 2,200.00
661 Genteng plentong dicat bj 2,420.00
662 Genteng Plentong Mantili bj 2,200.00
663 Genteng Pres Besar bj 1,980.00
664 Genteng Pres Besar Cat bj 2,090.00
665 Genteng Pres Mini bj 1,760.00
666 Genteng Pres Mini Cat bj 1,980.00
667 Genteng Besar polos Lubang 35 cm bj 1,980.00
668 Genteng Besar Warna Lubang 35 cm bj 2,090.00
669 Fiberglas (1.80 x 0.80) M2 lbr 1,760.00
670 Ijuk kg 1,980.00
671 Ikut Celedu Besar Polos bh 88,000.00
672 Ikut Celedu Besar Warna bh 99,000.00
673 Ikut Celedu Kecil Polos bh 66,000.00
674 Ikut Celedu Kecil Warna bh 88,000.00
675 Kawat las Kg 80,300.00
676 Kawat Diameter 4 mm Kg 88,000.00
677 Murda tanah liat Ex Pejaten bh 121,000.00
678 Murda Kecil Polos Lubang 25 cm bh 88,000.00
679 Murda Kecil Warna Lubang 25 cm bh 104,500.00
680 Profil Aluminium "T" m3 219,450.00
681 Seng BJLS 0,18 gelombang lbr 99,770.00
682 Seng BJLS 0,22 gelombang lbr 106,480.00
683 Seng BJLS 0,30 gelombang lbr 119,790.00
684 Seng Zincalume Panjang 6m Tebal 0,5 mm lbr 93,500.00
685 Seng Plat Lebar 0,90 M lbr 53,240.00
686 Seng Plat 3" x 6" BJLS 28 lbr 66,550.00
687 Seng Plat Aluminium lbr 53,240.00
688 Sirap Lbr 4,950.00
689 Subeng Besar Polos lbr 9,240.00
690 Subeng Besar Warna lbr 5,390.00
691 Subeng Kecil Polos lbr 6,600.00
692 Subeng Kecil Warna bh 4,180.00
693 Tali Ijuk kg 5,390.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
694 Tali pengikat alang-alang ikat 19,800.00
495 Besi strip kg 11,960.00

SANITAIR
695 Bak mandi fibre glass 70x70x66 cm bh 306,130.00
696 Bak mandi keramik 50x50 bh 187,000.00
697 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 341,000.00
698 Floor drain plastik Setara Alianco bh 27,500.00
699 Floor drain stainless Setara Wasser bh 49,500.00
700 Kloset duduk INA Komplit bh 1,650,000.00
701 Kloset duduk Amerika Standar Winplus bh 1,430,000.00
702 Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP COMPLIT bh 1,815,000.00
703 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh 5,699,100.00
704 Kloset duduk " TOTO Type AVANTE CW 823 J bh 8,457,900.00
705 Kloset duduk " TOTO Type CW 660J bh 738,100.00
706 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 1,925,000.00
707 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh 2,589,400.00
708 Kloset duduk " TOTO Type CW 660J WARNA COMPLIT bh 810,700.00
709 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 3,388,000.00
710 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 3,763,100.00
711 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 3,908,300.00
712 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 469,150.00
713 Kloset jongkok " TOTO Type CE 7 COMPLIT bh 246,950.00
714 Kloset porselin jongkok TOTO (standar) bh 374,000.00
715 Kloset porselin jongkok Ina (standar) bh 175,450.00
716 Kran biasa Setara Onda bh 55,000.00
717 Kran SunEi PI/3 JHR bh 76,000.00
718 Kran TOTO T 205 LCSC bh 242,550.00
719 Kran TOTO T 205 MC bh 330,000.00
720 Kran TOTO T 23 B13 bh 271,700.00
721 Kran TOTO T 23 B13V7NB bh 280,500.00
722 Kran TOTO T 26 - 13 bh 367,400.00
723 Kran TOTO TX 109 LH bh 775,500.00
724 Penyekat Urinoir " TOTO " Type A 100 " bh 1,364,000.00
725 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 459,800.00
726 Soap holder " TOTO " Type S 6 N " bh 121,000.00
727 Seal tape bh 3,300.00
728 Urinoir " TOTO U 57 M bh 2,874,960.00
729 Urinoir " TOTO U 57 M BODI bh 1,414,600.00
730 Wastagel KIA Standard bh 203,500.00
731 Wastagel KIA Warna bh 258,500.00
732 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh 1,248,500.00
733 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh 808,500.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
KUNCI DAN PENGGANTUNG
734 Engsel H ( 80 x 50) Ps 11,000.00
735 Engsel kupu-kupu Rafes 4' 304 ps 64,900.00
736 Engsel pintu Setara ECOLING Ps 73,150.00
737 Engsel jendela Setara ECOLING Ps 46,310.00
738 Engsel jendela Setara CAMEL Ps 39,600.00
739 Espagnoleth Setara Rafes 60 cm Ps 51,700.00
740 Grendel Setara ESBELA Bh 133,100.00
741 Grendel tanam Setara CAMEL Bh 218,350.00
742 Kait angin biasa Setara CAMEL Bh 55,000.00
743 Kait angin lipat Setara ESBELA Bh 86,460.00
744 Kait angin tarik Setara ESBELA Bh 59,950.00
745 Kunci lif 1 x putar Setara BELLEZA Bh 146,300.00
746 Kunci lif 2 x putar Bh 166,100.00
747 Kunci pintu TOP Setara ESBELA bh 330,000.00
748 Kunci pintu Vanesa Setara CAMEL bh 199,650.00
749 Kunci pintu Setara ESBELLA bh 286,000.00
750 Kunci Pintu 2 x putar Setara SES Bh 226,270.00
751 Kunci pintu Setara DELWIN) bh 198,000.00
752 Kunci shang hae 2 x putar Bh 185,900.00
753 Kunci slot / Grendel Pintu Setara DELLWYN bh 244,200.00
754 Kunci tanam 2 slag Setara Dexon bh 291,500.00
755 Rolling door plaat M2 133,100.00

PAKU
756 Paku Beton Kg 33,000.00
757 Paku 2-4 cm kg 15,271.67
758 Paku Pancing 60 x 230 Kg 16,500.00
759 Paku 5-12 cm kg 17,297.78
760 Paku 2 cm (30 kg) 3/4 inch SQ dus 471,800.00
761 Paku 2,5 cm (30 kg) 1 inch SQ dus 466,200.00
762 Paku 3 cm (30 kg) 1 1/4 inch SQ dus 457,800.00
763 Paku 4 cm (30 kg) 1 1/2 inch SQ dus 436,800.00
764 Paku 5 cm (30 kg) 2 inch SQ dus 393,400.00
765 Paku 7,10,12 cm (3,4,5) inch SQ dus 389,200.00
766 Paku 5 -12 cm (27kg) 2,3,4,5 inch dus 306,600.00
767 Bendrat 20 kg rol 250,600.00
768 Sekrup Kalisiboard buah 220.00

PAVING
769 Paving 10 x 20 cm tebal 6 cm K225 (Polos) m2 78,650.00
770 Paving 10 x 20 cm tebal 6 cm K225 (Warna) m2 125,400.00
771 Paving 20 x 20 cm tebal 6 cm K225 (Polos) m2 78,650.00
772 Paving 20 x 20 cm tebal 6 cm K225 (Warna) m2 125,400.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
773 Paving 10 x 20 cm tebal 6 cm K350 (Polos) m2 90,750.00
774 Paving 10 x 20 cm tebal 6 cm K350 (Warna) m2 136,400.00
775 Paving 20 x 20 cm tebal 6 cm K350 (Polos) m2 90,750.00
776 Paving 20 x 20 cm tebal 6 cm K350 (Warna) m2 136,950.00
777 Paving 10 x 20 cm tebal 8 cm K225 (Polos) m2 79,860.00
778 Paving 10 x 20 cm tebal 8 cm K225 (Warna)) m2 136,950.00
779 Paving 20 x 20 cm tebal 8 cm K225 (Polos) m2 79,860.00
780 Paving 20 x 20 cm tebal 8 cm K225 (Warna) m2 137,280.00
781 Paving 10 x 20 cm tebal 8 cm K350 (Polos) m2 99,550.00
782 Paving 10 x 20 cm tebal 8 cm K350 (Warna)) m2 146,850.00
783 Paving 20 x 20 cm tebal 8 cm K350 (Polos) m2 99,770.00
784 Paving 20 x 20 cm tebal 8 cm K350 (Warna)) m2 146,300.00
785 Paving 20 x 20 cm tebal 8 cm K400 (Polos) m2 117,700.00
786 Paving 20 x 20 cm tebal 8 cm K400 (Warna)) m2 156,200.00
787 Paving Tiga Berlian tebal 6 cm K225 (Polos) m2 75,460.00
788 Paving Tiga Berlian tebal 6 cm K225 (Warna) m2 122,100.00
789 Kanstein Segi Lima P40 Buah 29,150.00
790 Kanstein Segi Lima P50 Buah 35,750.00
791 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 78,430.00
792 Grass Block lobang 5, 30 X 30 cm tebal 7 cm K 225 m2 61,000.00

PLAFOND & TIRPLEK


792 Acustik 30/30 lbr 84,700.00
793 Celling teak (0,62 x 2,40) m2 lbr 105,600.00
794 Eternit lbr 18,150.00
795 Plywood 4 mm Setara Meranti lbr 69,575.00
796 Plywood 5 mm lbr 122,100.00
797 Plywood 9 mm Setara Meranti lbr 148,500.00
798 Plywood aluminium lbr 118,800.00
799 Gypsum Board (120x240x9) lbr 79,200.00
800 Kalsiboard (4,5 x 1220 x 2420) mm lbr 113,080.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
801 Hard board MDF lbr 141,900.00
802 Multiplek 6 mm lbr 74,800.00
803 Multiplek 9 mm lbr 115,500.00
804 Triplek tebal 3mm (2,7mm) kayu sengon lbr 44,300.00
805 Triplek tebal 3mm (2,7mm) kayu semi meranti lbr 52,500.00
806 Triplek tebal 4mm (3,6mm) kayu sengon lbr 54,000.00
807 Triplek tebal 4mm (3,6mm) kayu semi meranti lbr 64,500.00
808 Triplek tebal 6mm (5,2mm) kayu sengon I lbr 65,800.00
809 Triplek tebal 6mm (5,2mm) kayu sengon II lbr 59,000.00
810 Triplek tebal 6mm (5,2mm) kayu semi meranti lbr 76,500.00
811 Triplek tebal 6mm (5,2mm) kayu semi meranti II lbr 61,500.00
812 Triplek tebal 8,0mm kayu sengon I lbr 97,000.00
813 Triplek tebal 8,0mm kayu sengon II lbr 89,000.00
814 Triplek tebal 8,0mm kayu semi meranti lbr 107,500.00
815 Triplek tebal 9,0mm kayu semi meranti II lbr 94,500.00
816 Triplek tebal 12 mm kayu sengon I lbr 129,500.00
817 Triplek tebal 12 mm kayu semi meranti lbr 178,000.00
818 Triplek tebal 15 mm kayu semi meranti lbr 210,000.00
819 Triplek tebal 18 mm kayu semi meranti lbr 232,000.00
820 Teakwood 122 x 244 x 2,7 mm lbr 72,500.00
821 Melamine Putih/Biru 2,7 lbr 87,500.00
822 Triplek aluminium jruk asli lbr 106,500.00
823 Triplek aluminium jruk standar lbr 69,500.00
824 Blocbord 18 mm sengon lbr 167,500.00
825 Blocbord 18 mm meranti super lbr 205,000.00
826 Teak block lbr 207,500.00
804 Rangka Aluminium m1 19,360.00
805 Rangka Metal Furing (2 x 4 cm) panjang 4 m Batang 22,000.00
806 Rangka Metal Furing (4 x 4 cm) panjang 4 m Batang 27,500.00
807 Teak wood (1,20x2,40x 0,4) lbr 84,700.00
808 Teak wood (0,90x2,00 x 0,4) lbr 72,600.00

BUIS BETON
809 Buis beton Diameter 25 x 75 bh 56,650.00
810 Buis beton Diameter 30 x 75 bh 72,600.00
811 Buis beton Diameter 50 x 75 bh 99,000.00

TALANG
812 Talang Karet L = 0.50 m' 99,000.00
813 Talang Karet L = 0.90 m' 126,500.00
814 Pipa Talang PVC Setara Maspion 6" Setengah Lingkaran m' 71,500.00
815 Pipa Talang PVC Setara Maspion 6" Kotak m' 93,500.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
LAIN-LAIN
816 Air Bersih Ltr 30.00
817 Bak Cuci Aluminium Bh 225,500.00
818 Cangkul Bh 72,600.00
819 Cangkul Gigi Bh 159,500.00
820 Ember Bh 26,400.00
821 Gerinding bh 506,000.00
822 Helm Proyek Bh 80,300.00
823 Hammer 3 kg Bh 92,950.00
824 Instalasi Tata Suara Titik 399,300.00
825 Kapi Bh 8,800.00
826 Keni 2" Bh 15,950.00
827 Keranjang Sampah Bh 39,600.00
828 Linggis bh 79,200.00
829 Masker Bh 52,800.00
830 Ompreng Besar (bak Adonan) Bh 485,100.00
831 Panyong Bh 88,000.00
832 Pengelasan cm 14,520.00
833 Sabit Bh 66,000.00
834 Sapu lidi Ikat 6,600.00
835 Sepatu Karet Bh 133,100.00
836 Sikat baja Bh 33,220.00
837 Skop Bh 59,950.00
838 Water mur Bh 35,000.00
839 Pipa Tremi dan Casing pelindung Ls 121,000.00
840 Pelumas (olie) Ltr 28,350.00
841 Solar Ltr 7,500.00
842 Ramset M' 14,520.00
843 Minyak Tanah Ltr 3,000.00
844 Pembuangan lumpur eks. Bor M3 95,000.00
845 Mobilisasi dan demobilisasi alat pancang HSPD240 ton unit 132,000,000.00
846 Mobilisasi dan demobilisasi alat bor auger ZKL28 unit 135,000,000.00
847 Service Crane kapasitas 2,5 ton bln 132,500,000.00
848 Excavator PC200 bln 93,500,000.00
849 Pengadaan rail beam untuk pemancangan ls 17,000,000.00
850 Pemotongan kepala tiang pancang turap m' 95,000.00
851 Galian tanah untuk capping beam m3 105,000.00
852 Pembuangan tanah galian m3 95,000.00
853 Pekerjaan Cetakan/Tutup Kepala Kolom Bh 250,000.00
854 Pek. Pembuatan papan nama proyek Ls 1,000,000.00

ALAT PEMADAM KEBAKARAN ###


855 Instalasi pipa induk BS 3" Sch M' 203,500.00
856 Intalasi pipa distribusi BS 2" Sch M' 137,500.00
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
857 Seamesi conection Bh 1,980,000.00
858 Box hidran dengan kelengkapannya Bh 2,750,000.00
859 Selang pemadam 30 m Bh 3,520,000.00
860 Pemadam api ringan 6 kg Bh 121,000.00

BETON READY MIX


861 Beton Ready Mix K-175 M3 836,000.00
862 Beton Ready Mix K-225 M3 880,000.00
863 Beton Ready Mix K-250 M3 896,500.00
864 Beton Ready Mix K-275 M3 918,500.00
865 Beton Ready Mix K-300 M3 940,500.00
866 Beton Ready Mix K-350 M3 990,000.00
867 Sewa Concrete pump/M3 Ls 30,000.00

868 Formite/penjaga jarak bekisting/spacer Bh 2,000.00

869 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 pc M2 70,400.00


870 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 merah M2 92,000.00
871 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 hitam M2 90,000.00
872 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 pc M2 73,000.00
873 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 merah M2 98,000.00
874 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 hitam M2 97,000.00
875 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 pc M2 76,000.00
876 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 merah M2 101,000.00
877 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 hitam M2 100,000.00
878 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 pc M2 84,000.00
879 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 merah M2 109,000.00
880 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 hitam M2 108,000.00
881 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 pc M2 66,000.00
882 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 merah M2 89,000.00
883 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 hitam M2 87,000.00
884 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 pc M2 72,000.00
885 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 merah M2 106,000.00
886 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 hitam M2 104,000.00
Konsultan
HARGA
NO NAMA BARANG SATUAN
SATUAN (Rp)

1 2 3 4
887 Kanstein Jumbo (P:50,L:15,T:30 cm K225) M1 35,000.00
888 Kanstein kotak (P:50,t.20,La.10,Lb.16cm) K225 M1 27,000.00
889 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) M1 46,000.00
890 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) M1 49,500.00
891 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) M1 25,000.00
892 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) M1 20,000.00

Denpasar, 17 Pebruari 2017

Pejabat Pembuat Komitmen (PPK)


Kegiatan Pembangunan Pasar Badung
Kota Denpasar

Agus Sudarmo, ST.


Penata Tk. I
NIP. 19700907 199903 1 006
DAFTAR HARGA SATUAN UPAH
TAHUN 2017

NO NAMA BARANG SATUAN HARGA (Rp)


1 2 3 4

1 Mandor Hari 125,000.00


2 Kepala Tukang Lapangan Hari 110,000.00
3 Kepala Tukang Besi Hari 110,000.00
4 Kepala Tukang Batu Hari 110,000.00
5 Kepala Tukang Kayu Hari 110,000.00
6 Kepala Tukang Cat Hari 110,000.00
7 Kepala Tukang Paras Bali Hari 165,000.00
8 Kepala Tukang Ukir Hari 185,000.00
9 Tukang Aluminium Hari 100,000.00
10 Tukang Batu Hari 95,000.00
11 Tukang Besi Hari 100,000.00
12 Tukang Kayu Hari 105,000.00
13 Tukang Cat Hari 95,000.00
14 Tukang Politur Hari 95,000.00
15 Tukang Ukir Hari 120,000.00
16 Tukang Paras Bali Hari 165,000.00
17 Pekerja Terlatih Hari 90,000.00
18 Pekerja Semi Terlatih Hari 85,000.00
19 Pekerja / Pekerja Tidak Terlatih Hari 75,000.00
21 Tukang Listrik Hari 90,000.00
22 Tukang Pipa/ Tukang Ledeng Hari 90,000.00
23 Kepala Tukang Pipa/ Tukang Ledeng Hari 100,000.00
24 Tukang Las Hari 100,000.00
25 Tukang Masak Aspal Hari 95,000.00
26 Tukang Cor Aspal Hari 95,000.00
27 Pekerja Pembantu Tukang Aspal Hari 60,000.00
28 Penjaga Api Hari 65,000.00
29 Sopir SIM A Hari 70,000.00
30 Sopir SIM B1 Hari 75,000.00
31 Sopir SIM B2 Hari 80,000.00
32 Operator Hari 100,000.00
33 Operator Semi Terampil Hari 85,000.00
34 Pembantu Operator Hari 80,000.00
35 Pembantu Sopir Hari 60,000.00
36 Mekanik Terampil Hari 95,000.00
39 Sewa Wales Jam 495,000.00
42 Sewa Wheel Loader Jam 330,000.00
43 Sewa Dump Truck Jam 248,157.27
44 Sewa Aspal Apayer Jam 80,000.00
45 Sewa Alat Bantu Set 55,000.00
54 Sewa Mesin Bor Jam 50,000.00
55 Alat Bantu Ls 20,000.00
NO NAMA BARANG SATUAN HARGA (Rp)
1 2 3 4
56 Ongkos Ngebor O 30 cm m' 75,000.00

UPAH KERJA UNTUK :


57 1 M2 PASANGAN BATA GOSOK 2 MUKA Ls 350,000.00
58 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA Ls 200,000.00
59 1 M2 PASANGAN BATA PRESS 1 MUKA Ls 200,000.00
60 1 M2 PASANGAN PARAS 1 MUKA Ls 200,000.00
61 1 M2 PASANGAN BATU PALIMANAN TEBAL 3 CM Ls 200,000.00
62 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA Ls 200,000.00
63 1 M2 PASANGAN BATA GOSOK DIUKIR Ls 355,000.00
64 1 M2 PASANGAN BATU TABAS KARANGASEM DIUKIR Ls 355,000.00
65 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR Ls 280,000.00
66 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP IJUK Ls 350,000.00
67 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP GENTENG Ls 300,000.00
68 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP IJUK Ls 350,000.00
69 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP GENTENG Ls 300,000.00
70 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP IJUK 190cmX190cm Ls 750,000.00
71 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP GENTENG 190cmx190cm Ls 650,000.00
72 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP IJUK 190cmx190cm Ls 750,000.00
73 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP GENTENG 190cmx190cm Ls 750,000.00
74 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP IJUK 200CMX200CM Ls 1,500,000.00
75 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP GENTENG 200X200 Ls 1,500,000.00
76 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP IJUK 200CMX200CM Ls 1,500,000.00
77 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP GENTENG 200X200 Ls 1,500,000.00
78 1 UNIT SANGGAH TAKSU BATU HITAM ATAP IJUK 40cmx40cm Ls 300,000.00
79 1 UNIT SANGGAH TAKSU BATU HITAM ATAP GENTENG 40cmx40cm Ls 300,000.00
80 1 UNIT SANGGAH TAKSU PARAS BATA ATAP IJUK 40cmx40cm Ls 300,000.00
81 1 UNIT SANGGAH TAKSU PARAS BATA ATAP GENTENG 40cmx40cm Ls 300,000.00

82 1 TTK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN & CEILING FAN Titik 25,000.00
83 1 TITIK INSTALASI AC Titik 25,000.00
84 1 TITIK INSTALASI TELEPHONE Titik 25,000.00
85 1 TITIK INSTALASI MATV Titik 25,000.00

Denpasar,17 Pebruari 2017


Pejabat Pembuat Komitmen (PPK)
Kegiatan Pembangunan Pasar Badung
Kota Denpasar

Agus Sudarmo, ST.


Penata Tk. I
NIP. 19700907 199903 1 006
DAFTAR HARGA BAHAN, UPAH DAN ALAT - TAMBAHAN
TAHUN 2017
Untuk analisa tambahan
HARGA SATUAN
NO NAMA BARANG SATUAN
(Rp)
1 2 3 4
HARGA SATUAN BAHAN
1 Primer Coat - Polyfloor PU Concrete PFT - 253 MF (1000 Micron) M2 132,000.00
2 Top Coat - Polyfloor PU Concrete PFT - 253 MF (2000 Micron) M2 270,000.00
3 Primer Coat - Polyfloor Epoxy Primer PFP 241 (50 Micron) M2 9,800.00
4 Primer Coat - Polyfloor Epoxy Primer PFP 241 (50 Micron) + pasir silika M2 9,185.00
5 First Layer - Silikat Penetran LD-201 M2 85,000.00
6 Second Layer - Silikat Toping CC-203 M2 91,900.00
7 Waterproofing sika Kg 17,500.00
8 Granite Tile 60x60 M2 345,000.00
9 Granite Tile 30x30 M2 180,000.00
10 Keramik 30x30 M2 65,000.00
11 Keramik 30x30 anti slip M2 70,000.00
12 Grinte Tile 10 x 60 cm M2 115,000.00
13 Keramik 10 x 30 cm Bh 5,909.09
14 Granite 30 x 60 nordik stone GSN02 M2 315,000.00
15 Keramik 20x25 M2 65,000.00
16 List gypsum 7cm M2 22,800.00
17 Cornice Kg 3,250.00
18 Kusen aluminium 4" motif kayu M1 185,000.00
19 Engsel Pivot Bh 450,000.00
20 Handle Pintu Kaca Bh 620,000.00
21 Handle Pintu Bh 250,000.00
22 Door Closer Bh 350,000.00
23 Door stoper Bh 85,000.00
24 Grendel Bh 135,000.00
25 Pipa Schedule sch 80 diameter 2 inch Stainless Steel Btg 908,000.00
26 Besi hollow Galvanis 40x40x2mm M1 405,000.00
27 Besi hollow Galvanis 20x20x1,7mm M1 149,000.00
28 Cat avian Liter 55,000.00
29 Thinner Liter 35,000.00
30 besi siku 5cm M1 20,000.00
31 Besi strip M1 20,000.00
32 Plat Stainless Steel 304 Tebal 15 mm Lbr 1,627,920.00
33 Cat Penutup 2x dgn waterpoffing aquaproof Kg 850,000.00
34 Sealant Botol 20,000.00
35 PanelPenolid Board Thick 12 mm, Hight 1,95 m M2 1,510,000.00
36 Besi Hollow 4x4 Tebal 2 mm M1 149,860.00
37 Stainless Steel Wire Mesh M5 M2 220,000.00
38 Zink Satainless Steel Unit 450,000.00
39 Paku lisplank Kg 18,000.00
40 Kayu kamfer profil M1 35,000.00
41 Murda / Puntal Paras Bh 350,000.00
42 Delineator Steel Pipa 3 '' Bh 290,000.00
43 Swing Fire Door Double Unit 36,549,331.00
44 Waterproofing Integral Crystallin Setara Pentent T-308 M2 140,000.00
45 Waterproofing Membrane Bakar Profextorcseal 3pv Setara Fosroc M2 100,000.00
46 Stainless Steel 304 T=1,5 mm Cm2 12,000.00
47 Aksesoris pasangan huruf stainless steel Cm2 250,000.00
48 List Stepnosing Karet Tangga M1 30,000.00
49 Baja ringan profil C 75 Btg 90,000.00
50 Baja ringan profil Uk Btg 36,000.00
51 Angkur diameter 16 Bh 55,000.00
52 Baut diameter 16 Bh 9,000.00
53 Cat Zincromate Kg 50,000.00
54 Sipder Fitting Ls 900,000.00
55 Sealent kaca tempered Botol 35,000.00
56 Beton Ready Mix K 300, Slump 12 +/- 2 cm M3 1,130,040.00
57 Additive/Bonding Agent Ltr 132,950.00
58 Main Frame MF 170 Bh 9,310.00
59 End Frame EF 90 Bh 6,650.00
60 Bracing 193 Bh 4,330.00
61 Bracing 185 Bh 4,330.00
62 Base Plate Bh 3,990.00
63 Joint Pin Bh 5,320.00
64 U Head Jack Bh 5,320.00
65 Main Beam (Gelagar) 5 Mtr Bh 13,300.00
66 Rail Beam (Suri-Suri) Bh 13,300.00
67 Wire Mesh U50 M2 11,170.00
68 Beton Ready Mix B-0 Kg 897,390.00
69 Additive/Plasticicer Kg 19,950.00
70 Semen Portland Zak 66,480.00
71 Pasir Pasang M3 265,900.00
72 Kerikil / Split M3 252,600.00
73 Batako Bh 3,330.00
74 Pasir Pasang M3 265,900.00
75 Sewa TC Kap 2,5 Ton Length 60 m/Bulan/ 200 jam Bulan 120,000,000.00
76 Jaminan Angkur Set 65,000,000.00
77 Pasang Angkur Set 7,500,000.00
78 Erexsion Set 55,000,000.00
79 Dismantling Normal Set 55,000,000.00
80 Mob-Demob TC Set 175,000,000.00
81 Transportasi Crew TC 6 Orang Ls 25,000,000.00
82 Gaji Operator Set 7,500,000.00
83 Tanah Subur M3 65,000.00
84 Tanaman Hias Btg 500.00
85 Aspal Kg 12,000.00
86 Wheel Loader Jam 330,000.00
87 AMP Jam 5,018,600.00
88 Genzet Jam 416,800.00
89 Dump Truck Jam 248,157.27
90 Asphalt Finishir Jam 507,700.00
91 Tandem Roller Jam 318,300.00
92 P. Tyre Roller Jam 292,100.00
93 Beton Ready Mix K 500 M3 1,229,200.00
94 Additive Beton K-500 M3 17,510.00
95 Beton Ready Mix K-450 M3 1,534,801.06
96 Pembesian PC Strand Kg 24,310.00
97 Pembesian U40 Kg 12,970.05
98 Cetakan/Formwork M2 131,250.00
99 Beton Ready Mix K-450 M3 1,534,801.06
100 Pembesian PC Strand Kg 24,310.00
101 Pembesian U40 Kg 12,970.05
102 Cetakan/Formwork M2 131,250.00
103 Upah Jacking Strands dll m3 1,700,000.00
104 Peralatan Gantry Crane dll m3 275,000.00
105 Material testing m3 130,000.00
106 Pembesian PC Wire Kg 22,310.00
107 Pembesian U 50 Kg 13,970.05
ALAT BANTU
1 Finishing lantai epoxy floor coating setara polyfloor Ls 5,000.00
2 Finishing lantai floor hardener setara propan mulipox Ls 5,000.00
3 Kusen Aluminium 4" motif kayu Ls 10,000.00
4 Bahan las railling tangga pipa schedule sch 2" Ls 50,000.00
5 Bahan las railling tangga besi hollow Ls 100,000.00
6 Bahan las grill besi drainase Ls 25,000.00
7 Bahan las pasang plat stainless 304 - 15 mm Ls 50,000.00
8 Alsesoris pembatas los besi hollow galvanis 40x40x2 Ls 35,000.00
9 Finishing dan material bantu pembatas los besi hollow Ls 15,000.00
10 Paku pasang tatab Ls 14,500.00
11 Sekrup pasangan usuk profil C 75 Ls 10,000.00
12 Pemasangan angkur diameter 16 Ls 1,000.00
13 Alat dan material cat zincromate Ls 1,000.00
14 Concrete Pump Lot 46,540.00
15 Alat Alat lain pek. Beton K-300 Lot 33,236.45
16 Pipa Tremi Lot 19,941.87
17 Alat Alat lain pek. Beton K-300 untuk bore pile Lot 19,941.87
18 Alat kerja pasang besi wire mesh Lot 997.09
19 Alat kerja lantai kerja sp 1:3:5 Lot 66,472.89
20 Alat kerja begesting pilecap batako Lot 14,624.04
21 Alat bantu pekerjaan lapisan aspal Ls 20,000.00
22 Concrete Pump Pek. Beton K-500 Lot 46,700.00
23 Alat Alat lain pek. Beton K-500 Lot 58,366.44
24 Upah Jacking Strands dll (balok prstress) m3 1,700,000.00
25 Peralatan Gantry Crane dll (balok prestress) m3 275,000.00
26 Aksesoris Produksi (balok prestress) Ls 750,000.00
27 Material testing (balok prestress) m3 130,000.00
28 QC,Grouting/finshing (balok prestress) Lot 175,000.00
29 Upah Curing & Stocking (balok prestress) m3 275,000.00
30 Loading di Pabrik (balok prestress) Kg 20.00
31 Biaya Transport Pabrik (balok prestress) Kg 825.00
32 Turunkan di Site Proyek ( Crane ) (balok prestress) Ls 20.00
33 Bahan bantu ( kayu ) landasan (balok prestress) m3 55,000.00
34 Aksesoris Produksi (balok prestress) B1, B2, BR1 dan BS1 Ls 750,000.00
35 QC, Groutiing/Finishing (balok prestress) B1, B2, BR1 dan BS1 Lot 175,000.00
36 Upah Jacking Strands dll (tiang pancang prestress) Lot 50,000.00
37 Peralatan Gantry Crane dll (tiang pancang prestress) Lot 125,000.00
38 QC,Grouting/finshing (tiang pancang prestress) Lot 50,000.00
39 Upah Curing & Stocking (tiang pancang prestress) Ls 12,500.00
40 Biaya Transport Pabrik (tiang pancang prestress) Kg 100.00
41 Bahan bantu ( kayu ) landasan (tiangpancang prestress) Ls 25,000.00
42 Material testing tiang pancang prestress) Ls 50,000.00

43 Penggunaan Alat Bore (pek. Pre boring) 125,000.00


44 Alat Bantu, Listrik dll (pek.boring) 35,000.00
45 Material Clay (pek.boring) 50,000.00
46 Upah Boring & Flushing (pek.boring) 175,000.00
47 Handling pemasangan Besi (pek.pre boring) 50,000.00
48 Lain Lain 20,000.00
49 Upah las Besi Hollow Galvanis Kom. 40x40x2mm 12,500.00
50 Alat pancang HSPD 240 1,450,000.00
51 Alat Bantu, Listrik, BBM dll 9,500.00
52 Pekerja Pancang 96,305.00
53 Kepala tukang Pancang 141,251.00
54 Mandor Pancang 192,610.00

55 Excavator Jam 460,000.00


56 Crawler Crane 50 Ton Bulan 110,000,000.00
57 Pompa Air Hari 200,000.00

UPAH KERJA
1 Pekerja OH 87,550.00
2 Tukang Cor/Batu OH 105,060.00
3 Kepala Tukang OH 128,410.00
4 Mandor OH 175,100.00
5 Pekerja erection OH 96,305.00
6 Tukang erection OH 115,566.00
7 Kepala Tukang erection OH 141,251.00
8 Mandor erection OH 192,610.00
9 Pekerja (galian dengan excavator) OH 100,000.00
10 Mandor (galian dengan excavator) OH 125,000.00
Denpasar, 17 Pebruari 2017

Pejabat Pembuat Komitmen (PPK)


Kegiatan Pembangunan Pasar Badung
Kota Denpasar

Agus Sudarmo, ST.


Penata Tk. I
NIP. 19700907 199903 1 006
DAFTAR HARGA BAHAN
PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KOTA DENPASAR TAHUN 2017

HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
BATU KALI DAN BATU ALAM
1 Batu Kali/batu bulat 15-30 cm M3 265,000.00
2 Batu Pecah Besar 15/30 cm M3 285,000.00
3 Batu Pecah 5/7 cm M3 290,250.00
4 Batu Pecah 3/5 cm M3 294,500.00
5 Batu Pecah 3-4 cm M3 205,500.00
6 Batu Pecah 2/3 cm M3 294,500.00
7 Batu Pecah Mesin 1 - 2 cm M3 253,066.67
8 Batu Pecah 0,5 - 1 Cm M3 290,400.00
9 Batu Alam Andesit Bintik Bakar m2 155,000.00
10 Batu Alam Andesit Alur m2 167,900.00
11 Batu Alam Live Grendia m2 115,000.00
12 Batu Candi 105,000.00
13 Batu Candi Hitam (Ukuran 30 x 30 x 2 Cm) Cirebon m2 105,600.00
14 Batu Candi Hitam (Ukuran 30 x 30 x 3 Cm) Cirebon m2 156,000.00
15 Batu Candi Hitam (Ukuran 30 x 30 x 5 Cm) Cirebon m2 228,000.00
16 Batu Candi Hitam (Ukuran 20 x 20 x 2 Cm) Cirebon m2 90,000.00
17 Batu Candi Hitam (Ukuran 20 x 30 x 5 Cm) Cirebon m2 216,000.00
18 Batu Putih Jogya / Palimanan (30 x 30 x 2 Cm) m2 96,000.00
19 Batu Putih Jogya / Palimanan (30 x 30 x 3 Cm) m2 138,000.00
20 Batu Putih Jogya / Palimanan (30 x 30 x 5 Cm) m2 204,000.00
21 Batu Alam Palimanan Putih Super m2 115,000.00
22 Batu hitam Jember 5 x 20 halus m2 83,600.00
23 Batu hitam Jember 20 x 40 halus m2 89,100.00
24 Batu hitam Jember 15 x 30 halus m2 83,600.00
25 Batu hitam Singaraja 15 x 30 halus m2 83,600.00
26 Batu hitam Singaraja 20 x 40 halus m2 89,100.00
27 Batu hitam karangasem/Batu Tabas (20 x 40 x 3) m2 99,000.00
28 Paras Silakarang Tipis (Ukuran 15 x 30 x 5 Cm) m2 25,000.00
29 Paras Silakarang Tebal (Ukuran 15 x 30 x 8 Cm) m2 33,000.00
30 Batu Paras Bali/Pawon (Abu - Abu Terang) m2 93,500.00
31 Paras Kelating / Kerobokan (Ukuran 3 x 20 x 40 Cm) bh 13,750.00
32 Batu Pilah M2 75,000.00
33 Batu pilah Singaraja 30 x 30 m2 89,100.00
34 Batu pilah Singaraja 20 x 20 m2 83,600.00
35 Split Kasar M3 264,000.00
36 Split Halus M3 285,000.00
37 Koral Beton / Kerikil diameter 1 - 2 cm M3 298,000.00
38 Batu Sikat Hitam Lokal Super kampil 103,500.00
39 Batu Sikat Akik Merah kampil 25,300.00
40 Batu Sikat Putih Salju kampil 40,250.00
41 Koral Sikat (Lokal) Zak 45,000.00
42 Pasir Halus m3 267,000.00
43 Pasir Pasang M3 230,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
44 Pasir Beton/cor M3 210,000.00
45 Pasir Urug M3 183,750.00
46 Tanah Urug M3 140,000.00
47 Tanah Lempung 80,000.00
48 Sirtu M3 123,750.00
49 Batu Karang Bukit M3 179,000.00
50 Tanah Urug M3 140,000.00
51 Limestone M3 158,000.00
52 Batako bj 2,700.00
53 Batako Lubang bj 2,050.00
54 Batako Buntu bj 2,250.00
55 Batu Bata bh 2,200.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
56 Bata Ringan setara falcon uk. 75 x 200 x 500 mm m3 935,000.00
57 Bata Ringan setara falcon uk. 100 x 200 x 600 mm m3 935,000.00
58 Bata Ringan setara falcon uk. 125 x 200 x 600 mm m3 935,000.00
59 Bata Ringan setara falcon uk. 150 x 200 x 600 mm m3 935,000.00
60 Bata Merah Klas I bj 2,500.00
61 Bata Merah Klas II bj 2,150.00
62 Bata Merah Klas III bj 1,450.00
63 Bata Merah Super (Pripian) ex tulikup bj 5,850.00
64 Bata Pres 22x10x6cm bj 3,250.00
65 Bata Pres 22x10x5cm bj 3,120.00
66 Batu Gosok Bh 8,000.00
67 Filler Kg 16,500.00
68 Agregat M3 175,000.00
69 Closeter bh 74,750.00
70 Lis Batu Alam L=7, T=40 bj 25,300.00
71 Lem Batu Alam kaleng 51,750.00
72 Coating (CP.27) kaleng 51,750.00

SEMEN
73 PC. Tiga Roda 50 Kg Zak 71,250.00
74 PC Tiga Roda 40 Kg Zak 57,000.00
75 PC. Tonasa 50 Kg / Busoa 50 Kg Zak 68,750.00
76 PC. Gresik 40 Kg Zak 58,000.00
77 PC. Gresik 50 Kg Zak 72,500.00
78 PC Tonasa 40 Kg Zak 55,000.00
79 PC Holcim 40 Kg Zak 49,000.00
80 Semen Setara Gresik kg 1,450.00
81 Semen Setara Tiga Roda kg 1,425.00
82 Semen Setara Tonasa kg 1,375.00
83 Semen Setara Bosowa kg 1,375.00
84 Semen Setara Holcim kg 1,375.00
85 Semen Warna setara MU 408/ Nat kg 25,620.00
86 Semen Tipe V kg 2,250.00
87 Semen Portland kg 1,591.67

Mortar Utama
88 ThinBedMAX/Perekat Bata Ringan (MU 380) @40 Kg Zak 128,100.00
89 PlasterPlus/Pas. Bata & Plester (MU-301) @40 kg Zak 86,520.00
90 Plester premium (MU-100)@ 40 kg Zak 91,350.00
91 Finish Plesteran/ Render (MU 290)@ 40 kg Zak 160,230.00
92 SkimWall/Acian Plesteran & Beton (Skimcoat) 20 kg (MU-200) Zak 72,187.50
93 SkimWall/Acian Plesteran & Beton (Skimcoat) 40 kg (MU-200) Zak 137,130.00
94 Acian Putih (MU-270)@25 kg Zak 152,460.00
95 Perata Lantai (MU-440)@40kg Zak 87,360.00
96 Perata Lantai Expose (MU 445) 40 kg Zak 169,890.00
97 Self Leveling Floor /Underlayment (MU-410) @25kg Zak 270,900.00
98 Primer Self Leveling Floor (MU-L410) @ 5lt Set 302,925.00
99 Floor Hardener (MU 700) 25 kg Zak 138,180.00
100 Granitfix/Perekat Granite Tile & Batu Alam (MU-400) @25kg Zak 117,442.50
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
101 Cerafix/Perekat Keramik (MU-420)@25 kg Zak 82,162.50
102 Poolfix White/Perekat keramik area terendam (MU-460)@25 kg Zak 392,070.00
103 Renofix/Perekat keramik diatas keramik (MU-480)@25 kg Zak 235,095.00
104 Powerfix Flex/Perekat keramik serba guna (MU-485)@25 kg Zak 299,250.00
105 Rapidfix Flex/Perekat keramik Fast Setting (MU-490)@25 kg Zak 324,660.00
106 Colorfill/ Pengisi nat interior & eksterior (MU-408C) kg 11,340.00
107 ColorPlus/Pengisi nat interior,eksterior,area basah(MU-408P) kg 16,800.00
108 Glliter/Pengisi nat dengan efek Glliter (MU-408G)@ 2kg set 154,875.00
109 PowerPool/Pengisi nat area terendam(MU-408PP)@2kg set 82,950.00
110 FixGrout/Perbaikan struktur beton (MU-800)@20kg Zak 77,490.00
111 PatchCrete/Perbaikan permukaan beton(MU-830)@40kg Zak 249,270.00
112 SkimRep/Perbaikan permukaan acian(MU-840)@25kg Zak 308,910.00
113 DryShield/Pelapis kedap air (MU-600)@3kg Set 101,535.00
114 ArcyBond/Perekat Mortar & Beton akrilik (MU-L500)@900ml Set 31,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4

Uzin
115 Beton Instan (UZ K300) 50 kg Zak 78,750.00
116 Plester dinding instan (UZ Plester) 50 Kg Zak 78,750.00
117 Plester Finish tanpa Aci (UZ Render) 50 kg Zak 99,750.00
118 Acian diatas beton (UZ SC100) 40 kg Zak 111,300.00
119 Acian dinding instan interior (UZ SC 50) 40 kg Zak 102,900.00
120 Acian dinding instan eksterior (UZ SC 75) 40 kg Zak 105,000.00
121 Perekat Bata Ringan (UZ TB20) 50 kg Zak 112,875.00

Bostik
Perekat Keramik & Batu Alam
122 Fix Crete 25kg Zak 133,185.15
123 Fix all 20kg Zak 149,694.30
124 Super Fix all 20kg Zak 213,064.95
125 Super Fix all trade/white 20kg Zak 258,667.50
126 Asaflex 45 kg (15lt +30 kgp) Set 1,292,834.55
127 Mortar Fix 100kg Set 1,431,696.00
128 Mortar Fix 50 kg Set 829,256.40
129 Mortar Fix 5 kg Set 87,445.05
130 Grout ( Semen Nat) 20 kg Zak 386,742.30
131 Grout ( Semen Nat) 1 kg Zak 16,420.95
132 Liquid Grout Adictive (LGA) 20 Lt Pail 931,728.00
133 Mega Lastic Acrilic Base 20Lt Pail 931,728.00

Wall System
134 Skim Plas 25 Kg Zak 111,612.90
135 Skim Crete 25 Kg Zak 145,828.20
136 Fix. Plas 40 kg Zak 100,101.75
137 Fix T. 40 kg Zak 147,909.30

Waterproofing
138 Ultra Coat RC2 20 Lt Pail 1,179,487.05
139 Boscosem Slury 33 Kg Set 494,182.50
140 Damplix 2 20 kg Set 1,541,675.10
141 Damplix 3 45 kg Set 2,045,376.90
142 Damplix 3E 35 kg Set 1,133,574.75
143 Boscoseal Tom (Wp membran Bakar) Uk. 1m x 10 m Rol 897,871.80
144 Indo primer ( lapisan primer WP membran) 20 Lt Pail 734,801.55
145 Integral Kristalisasi (Waterproofing kristal) 20 kg Pail 1,577,668.05

Sealent
146 No More Nail (320 GR) Pcs 71,695.05
147 Seal n Flex 1 (600 ML) Pcs 111,692.70
148 Boscosil 313 (300 ML) Pcs 57,016.05
149 Boscosil 616 (300 ML) Pcs 57,862.35
150 Fil A Gap (300 ML) Pcs 37,076.55
151 Boscosil Mastic (300 ML) khusus R. Pendingin Pcs 48,769.35
152 Bostik Z Bond 6S (300 ML) Pcs 139,258.35
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
153 Bostik Z PU Contrcuction (600 ML) Pcs 121,796.85
154 Quelyd Super Express (250 GR) Pcs 35,833.35
155 Expanda Foam (340 GR) Pcs 171,652.95
156 Barel Gun Bh 523,805.10
157 Flash Band Rol 164,872.05

BAMBU
158 Bambu btg 11,000.00
159 Bambu Ukuran 8"- 10" panjang 4 m btg 10,500.00
160 Bambu Ukuran 3"-6" panjang 4 m btg 9,450.00
161 Gedeg kulit kelas I m2 36,750.00
162 Gedeg kulit kelas II m2 34,125.00
163 Gedeg Biasa m2 35,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4

KAYU
164 Kayu jati Balok m3 31,500,000.00
165 Kayu jati papan m3 36,750,000.00
166 Kayu jati Usuk m3 14,500,000.00
167 Kayu jati Reng m3 14,500,000.00
168 Kayu merbau Balok m3 16,800,000.00
169 Kayu merbau papan m3 17,850,000.00
170 Kayu kamper balok m3 8,925,000.00
171 Kayu kamper usuk/reng m3 7,875,000.00
172 Kayu kamper papan m3 9,975,000.00
173 Kayu Profil 4/5 kamper m1 37,800.00
174 List Kayu m1 33,000.00
175 List profil 2/4 kamper M1 30,450.00
176 Kayu kruing balok m3 6,300,000.00
177 Kayu kruing papan m3 7,875,000.00
178 Kayu Usuk Kruing M3 6,300,000.00
179 Kayu Reng Kruing M3 6,300,000.00
180 Kayu Papan Meranti M3 6,930,000.00
181 Kayu Balok Meranti M3 6,300,000.00
182 Kayu Usuk Meranti M3 6,300,000.00
183 Kayu Reng Meranti M3 6,300,000.00
184 Kayu Bangkirai Papan M3 13,650,000.00
185 Kayu Bangkirai Balok M3 11,340,000.00
186 Kayu Seseh Balok m3 2,985,675.00
187 Kayu Dolken / Skapolding Ls 20,000.00
188 Kayu Seseh Dolken D 20 Panjang 3 m Btg 171,465.00
189 Kayu Seseh Dolken D 8-10 Panjang 4m Btg 99,750.00
190 Kayu Usuk Albesia 5/7 Panjang 4 m Btg 52,500.00
191 Kayu Reng mekanis Uk 2 x 3 x 400 cm m3 4,510,000.00
192 Kayu Reng mekanis Uk 3 x 5 x 400 cm m3 4,510,000.00
193 Kayu Usuk mekanis Uk 4 x 6 x 400 cm m3 4,510,000.00
194 Kayu Usuk mekanis Uk 5 x 7 x 400 cm m3 4,510,000.00
195 Kayu Balok mekanis Uk. 6 x 12 x 400 cm m3 5,390,000.00
196 Kayu Balok mekanis Uk. 6 x 15 x 400 cm m3 5,500,000.00
197 Kayu Balok mekanis Uk. 6 x 20 x 400 cm m3 5,500,000.00
198 Kayu lokal m3 2,843,000.00
199 Kayu Cempaka lokal m3 2,860,000.00
200 Kayu Bakar M3 700,000.00
201 Papan Bakesting M3 3,306,000.00
202 Papan Kayu Ulin M3 15,000,000.00
203 Balok Kayu Ulin M3 15,000,000.00
204 Lem Aica Aibond kg 53,000.00
205 Lem Kayu setara Fox ltr 18,900.00
206 Minyak bekisting setara Calform NX*R ltr 38,325.00

Flooring/ Lantai
207 Parket Jati lokal Uk. 1,2 x 5 x 20 cm m2 220,000.00
208 Parket Jati lokal Uk. 1,2 x 5 x 25 cm m2 230,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
209 Parket Jati lokal Uk. 1,2 x 5 x 30 cm m2 250,000.00
210 Jati Eksport Uk. 1,2 x 5 x 20 cm m2 240,000.00
211 Jati Eksport Uk. 1,2 x 5 x 25 cm m2 265,000.00
212 Jati Eksport Uk. 1,2 x 5 x 30 cm m2 290,000.00
213 Jati Eksport Uk. 1,5 x 9 x 30 - 120 cm m2 460,000.00
214 Jati Eksport Uk. 1,5 x 12 x 30 - 120 cm m2 625,000.00
215 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 20 cm m2 190,000.00
216 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 30 cm m2 220,000.00
217 Parket Kayu Merbau Kelas I Uk. 1 x 9 x 30 - 120 cm m2 450,000.00
218 Parket Kayu Merbau Export Uk. 1 x 9 x 30 - 120 cm m2 490,000.00
219 Parket Kayu Merbau Export Uk. 1 x 9 x 60 - 120 cm m2 475,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
220 Decking Bangkirai Uk. 1,9 x 9 x 180 - 390 cm m2 440,000.00
221 Decking Krewing Uk. 1,9 x 9 x 180 - 400 cm m2 450,000.00
222 Decking Merbau Uk. 1,9 x 9 x 180 - 400 cm m2 520,000.00
223 Decking Ulin Sulawesi Uk. 1,9 x 9 x 200 cm m2 690,000.00

Lambersering
224 Lambersering Bangkirai Uk. 1 x 9 x 200 cm m2 420,000.00
225 Lambersering Kruing Uk. 2 x 9 x 200 cm m2 320,000.00

Lis Kayu
226 Lis plapond kayu mekanis Uk. 1 x 5 x 400 cm btg 15,000.00
227 Lis Plapond dobel kayu mekanis Uk. 1 x 5 x 400 cm btg 16,000.00
228 Lis Plapond Uk. 0,8 x 5 x 400 cm btg 13,000.00
229 Lis Plapond Uk.1 x 3 x 400 cm btg 11,000.00
230 Lis Plapond tanpa profil Uk. 1 x 5 x 400 cm btg 14,000.00
231 Lisplang kayu mekanis Uk. 2 x 6 x 400 cm btg 35,500.00
232 Lisplang kayu mekanis Uk. 2 x 7 x 400 cm btg 40,000.00
233 Lisplang kayu mekanis Uk. 2 x 8 x 400 cm btg 44,000.00
234 Lisplang kayu mekanis Uk. 2 x 10 x 400 cm btg 51,500.00
235 Lisplang kayu mekanis Uk. 2 x 12 x 400 cm btg 63,000.00
236 Lisplang kayu mekanis Uk. 2 x 15 x 400 cm btg 79,000.00
237 Lisplang kayu mekanis Uk. 2 x 20 x 400 cm btg 115,000.00
238 Lis Kaca Uk. 1,5 x 3 cm m' 6,500.00
239 Lis Dowel Kecil Uk. 1 x 2 cm m' 3,200.00
240 Lis Dowel Besar Uk. 1,3 x 3 cm m' 4,000.00
241 Lis Kusen m' 3,300.00

CONWOOD
Flooring/Deck Application
242 Conwood Deck 4" ( 102 x 3050 x 14 mm) Pcs 67,100.00
243 Conwood Deck 6" ( 152 x 3050 x 14 mm) Pcs 105,400.00
244 Conwood Deck 8" ( 203 x 3050 x 14 mm) Pcs 140,500.00
245 Conwood Deck 4" ( 102 x 3050 x 25 mm) Pcs 140,900.00
246 Conwood Deck 6" ( 152 x 3050 x 25 mm) Pcs 211,400.00
247 Conwood Deck 8" ( 203 x 3050 x 25 mm) Pcs 281,700.00
248 Conwood Deck 12"( 300 x 3050 x 25 mm) Pcs 414,700.00

Decorative Stair
249 Conwood Stair 8" (Vertical) (200 x 1200 x 16 mm) Pcs 74,500.00
250 Conwood Stair 12" (Horisontal) (300 x 1200 x 25 mm) Pcs 163,200.00
251 Conwood Handrail (85 x 3050 x 30 mm) Pcs 130,200.00

Ceiling Application
252 Celling Border (50 X 3050 X 11 mm) Pcs 33,100.00
253 Conwood Lath 3" Cut (76 x 3050 x 11 mm) Pcs 49,900.00
254 Conwood Lath 4" Cut (100 x 3050 x 11 mm) Pcs 61,100.00
255 Conwood Lath 3"(UG)(600 x 1200 x 8 mm) Pcs 105,300.00
256 Conwood Lath 3"(UG)(1200 x 2400 x 8 mm) Pcs 447,700.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
Eave/lisplank
257 Conwood Eave 2 IN 1 (235 x 3050 x 16 mm) Pcs 149,200.00

Wall Application
258 Conwood Lap Siding 6" BG (152 x 3050 x 11mm) Pcs 63,900.00
259 Conwood Lap Siding 8" GO (200 x 3050 x 11mm) Pcs 83,300.00
260 Conwood Decorative Panel (600 x 1200 x 11mm) Pcs 151,600.00
261 Conwood Decorative Panel " V-Groove" (305 x 3050 x 14mm) Pcs 185,400.00

Moulding Application
262 Conwood Floor Mould 4" (Louis) (102 x 3050 x 11mm) Pcs 46,900.00
263 Conwood Floor Mould 4" (Louis) (102 x 3050 x 14mm) Pcs 55,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
264 Conwood Floor Mould 4" (Classic) (102 x 3050 x 11mm) Pcs 46,900.00
265 Conwood Floor Mould 4" (Classic) (102 x 3050 x 14mm) Pcs 55,500.00

Decorative Application
266 Conwood Plank 1" (100 x 3050 x 25 mm) Pcs 90,300.00
267 Conwood Plank 2" (50 x 3050 x 16 mm) Pcs 34,200.00
268 Conwood Plank 2" (50 x 3050 x 25 mm) Pcs 53,000.00
269 Conwood Sun Shade 3" (76 x 3050 x 14 mm) Pcs 45,300.00
270 Conwood Fence 4" Arrow - 1M (100x 1000 x 16 mm) Pcs 28,500.00
271 Conwood Fence 4" Arrow - 1,5M (100x 1500 x 16 mm) Pcs 42,800.00
272 Conwood Fence 4" Botany - 1M (100x 1000 x 16 mm) Pcs 28,500.00
273 Conwood Fence 4" Botany - 1,5M (100x 1500 x 16 mm) Pcs 42,800.00
274 Conwood Fence 4" Classic - 1,5M (100x 1500 x 16 mm) Pcs 44,600.00
275 Conwood Fence 4" Branch - 1M (100x 1000 x 16 mm) Pcs 29,500.00

Planks
276 Conwood Plank 8" Textured (200 x 3050 x 8 mm) Pcs 47,000.00
277 Conwood Plank 8" Plain (200 x 3050 x 8 mm) Pcs 47,000.00

BESI
278 Mour + Bout bh 7,550.00
279 Besi strip kg 11,960.00
280 Besi strip 30x3 mm m' 20,000.00
281 Baja Strip (0,2 x 2) cm / Plat Strip Kg 16,500.00
282 Besi Beton U24 (Polos) Kg 8,750.00
283 Besi Beton Ulir U 32 Kg 9,375.00
284 Besi Ø5 (3,8 x 6,0) btg 4,200.00
285 Besi Ø6 (5,0 x 12) btg 11,850.00
286 Besi Ø6 (5,2 x 12) btg 12,450.00
287 Besi Ø6 (5,7 x 12) btg 14,750.00
288 Besi Ø8 (6,5 x 12) btg 19,550.00
289 Besi Ø8 (6,7 x 12) btg 20,700.00
290 Besi Ø8 (6,9 x 12) SNI btg 23,900.00
291 Besi Ø8 (7,1 x 12) SNI btg 24,700.00
292 Besi Ø8 (7,4 x 12) SNI btg 26,500.00
293 Besi Ø8 (7,6 x 12) SNI btg 27,200.00
294 Besi Ø8 (7,7 x 12) SNI btg 27,700.00
295 Besi Ø8 (7,8 x 12) SNI btg 28,400.00
296 Besi Ø8 SNI U 24 btg 28,900.00
297 Besi Ø10 (8,4 x 12) SNI btg 33,600.00
298 Besi Ø10 (8,6 x 12) SNI btg 34,800.00
299 Besi Ø10 (8,9 x 12) SNI btg 37,500.00
300 Besi Ø10 (9,2 x 12) SNI btg 39,400.00
301 Besi Ø10 (9,4 x 12) SNI btg 41,500.00
302 Besi Ø10 (9,6 x 12) SNI btg 43,200.00
303 Besi Ø10 (9,8 x 12) SNI btg 44,400.00
304 Besi Ø10 SNI U 24 btg 45,500.00
305 Besi Ø10 Ulir (9,5 x 12) SNI btg 42,700.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
306 Besi Ø10 Ulir (9,7 x 12) SNI btg 44,400.00
307 Besi Ø12 (11,5 x 12) SNI btg 62,700.00
308 Besi Ø13 Ulir (11,5 x 12) SNI btg 64,300.00
309 Besi Ø13 Ulir (11,7 x 12) SNI btg 66,000.00
310 Besi Ø13 Ulir (12,0 x 12) SNI btg 69,200.00
311 Besi Ø13 Ulir (12,5 x 12) SNI btg 74,300.00
312 Besi Ø13 Ulir (12,7 x 12) SNI btg 76,800.00
313 Besi Ø16 Ulir (14 x 12) SNI btg 94,400.00
314 Besi Ø16 Ulir (14,5 x 12) SNI btg 101,200.00
315 Besi Ø16 Ulir (15,0 x 12) SNI btg 108,000.00
316 Besi Ø16 Ulir (15,5 x 12) SNI btg 115,300.00
317 Besi Ø16 Ulir (15,7 x 12) SNI btg 117,500.00
318 Wiremesh M6@50m Rol 2,028,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
319 Wiremesh M7 (D6,5mm) Uk. 2,1 x 5,4 m lbr 308,000.00
320 Wiremesh M8 (D7,5mm) Uk. 2,1 x 5,4 m lbr 424,600.00
321 Wermes Diameter 8 (U 50) lbr 489,900.00
322 Beugel Besi O8 Kg 12,100.00
323 Beugel penguat /plaat kg 70,950.00
324 Kawat Beton RRT Kg 15,400.00
325 Kawat berduri kg 99,000.00
326 Kawat Ayak M2 14,000.00
327 Kawat Harmonika 3 X 3 cm M2 33,000.00
328 Kawat Nyamuk M2 24,200.00
329 Kawat Jaring M2 25,000.00
330 Kawat Bronjong Kg 44,000.00
331 Besi / Baja profil Kg 10,450.00
332 Besi Baja L60 X 60 X 6 / L50 x 50 x 5 Kg 13,200.00
333 Baja WF (150 x 12 GG) btg 1,512,000.00
334 Baja WF (2000 x 12 GG) btg 2,304,000.00
335 Besi Baja WF 200 x 100 x 4,5 x 7 Kg 11,500.00
336 Besi Baja WF 250 x 125 x 5 x 7 Kg 11,500.00
337 Besi Baja C 100 x 50 x 3,2 Kg 11,500.00
338 Baja Ringan Type C- 75, 0.8 m' 15,950.00
339 Baja Ringan Type C- 75, 0.6 m' 13,750.00
340 Reng Baja m' 7,700.00
341 Profil Canal "C" Tipe C71.075 Btg 16,280.00
342 Profil Canal "C" Tipe C81.075 Btg 94,380.00
343 Profil Canal "C" Tipe C81.065 Btg 90,750.00
344 Profil "Omega / reng Tipe AA Btg 52,800.00
345 Profil "Omega / reng Tipe A Btg 49,500.00
346 Profil "Omega / reng Tipe AB btg 46,200.00
347 Profil Aluminium Kaca 3/4 m 9,900.00
348 Profil Aluminium L 3 cm lis Kaca m 12,650.00
349 Profil Aluminium 4" m 66,000.00
350 Besi Plat Kg 24,860.00
351 Besi plat 3 X 6 tebal 1,2 mm Btg 215,600.00
352 Besi plat 4 X 8 tebal 1,8 mm Btg 486,200.00
353 Baja Plat Hitam L = 10 lbr 1,805,000.00
354 Baja Plat Hitam L = 8 lbr 1,449,000.00
355 Baut Galvanis 3/4 x 2 " Bj 6,775.00
356 Baut Galvanis 3/4 x 2 1/2 " Bj 7,790.00
357 Baut Galvanis 3/4 x 3 " Bj 8,475.00
358 Baut Galvanis 3/4 x 3 1/2 " Bj 9,475.00
359 Baut Galvanis 3/4 x 4 " Bj 10,125.00
360 Baut Galvanis 3/4 x 4 1/2 " Bj 11,100.00
361 Baut Galvanis 3/4 x 5 " Bj 11,800.00
362 Baut Galvanis 3/4 x 5 1/2 " Bj 7,031.25
363 Baut Galvanis 3/4 x 6 " Bj 13,800.00
364 Plat Siku Panjang 30 cm Bj 24,000.00
365 Plat Siku Panjang 40 cm Bj 26,000.00
366 Plat Siku Panjang 50 cm Bj 30,000.00
367 Plat Siku Panjang 60 cm Bj 35,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
368 Plat Aluminium 2mm m2 275,000.00
369 Besi Siku L.30.30.3 mm btg 74,033.33
370 Baut UNC 5/8 x 2" Bj 3,000.00
371 Baut UNC 5/8 x 2 1/2" Bj 3,200.00
372 Baut UNC 5/8 x 3" Bj 3,650.00
373 Baut UNC 5/8 x 3 1/2" Bj 3,900.00
374 Baut UNC 5/8 x 4" Bj 4,350.00
375 Baut UNC 5/8 x 4 1/2" Bj 4,700.00
376 Baut UNC 5/8 x 5" Bj 5,075.00
377 Baut UNC 5/8 x 5 1/2" Bj 5,440.00
378 Baut UNC 5/8 x 6" Bj 5,800.00
379 Baut UNC 3/4 x 2" Bj 5,300.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
380 Baut UNC 3/4 x 2 1/2" Bj 5,750.00
381 Baut UNC 3/4 x 3" Bj 6,300.00
382 Baut UNC 3/4 x 3 1/2" Bj 6,900.00
383 Baut UNC 3/4 x 4" Bj 7,450.00
384 Baut UNC 3/4 x 4 1/2" Bj 8,000.00
385 Baut UNC 3/4 x 5" Bj 8,650.00
386 Baut UNC 3/4 x 5 1/2" Bj 9,200.00
387 Baut UNC 3/4 x 6" Bj 9,800.00
388 Baut CB 3/8 x 5" Bj 1,600.00
389 Baut CB 3/8 x 3" Bj 1,100.00
390 Baut CB 3/8 x 2" Bj 900.00
391 Behel 7/8 Bj 119,000.00
392 Baut Baja A325 16 x 50 Bj 6,000.00
393 Baut Baja A325 16 x 60 Bj 6,700.00
394 Baut Baja A325 16 x 70 Bj 7,000.00
395 Baut Baja A325 16 x 80 Bj 8,000.00
396 Baut Baja A325 16 x 90 Bj 8,750.00
397 Baut Baja A325 16 x 100 Bj 9,550.00
398 Baut Baja A325 16 x 110 Bj 11,000.00
399 Baut Baja A325 16 x 120 Bj 12,000.00
400 Baut Baja A325 16 x 130 Bj 13,000.00
401 Baut Baja A325 16 x 140 Bj 14,000.00
402 Baut Baja A325 16 x 150 Bj 14,500.00
403 Baut Baja A325 19 x 50 Bj 9,600.00
404 Baut Baja A325 19 x 60 Bj 10,550.00
405 Baut Baja A325 19 x 70 Bj 11,425.00
406 Baut Baja A325 19 x 80 Bj 12,000.00
407 Baut Baja A325 19 x 90 Bj 13,850.00
408 Baut Baja A325 19 x 100 Bj 14,700.00
409 Baut Baja A325 19 x 110 Bj 16,000.00
410 Baut Baja A325 19 x 120 Bj 17,000.00
411 Baut Baja A325 19 x 130 Bj 18,850.00
412 Baut Baja A325 19 x 140 Bj 18,800.00
413 Baut Baja A325 19 x 150 Bj 20,000.00
414 Baut Galvanis 3/8 x 2 " Bj 1,300.00
415 Baut Galvanis 3/8 x 2 1/2 " Bj 1,400.00
416 Baut Galvanis 3/8 x 3 " Bj 1,550.00
417 Baut Galvanis 3/8 x 3 1/2 " Bj 1,695.00
418 Baut Galvanis 3/8 x 4 " Bj 1,840.00
419 Baut Galvanis 3/8 x 4 1/2 " Bj 2,045.00
420 Baut Galvanis 3/8 x 5 " Bj 2,150.00
421 Baut Galvanis 3/8 x 5 1/2 " Bj 2,400.00
422 Baut Galvanis 3/8 x 6 " Bj 2,500.00
423 Baut Galvanis 5/8 x 2 " Bj 3,550.00
424 Baut Galvanis 5/8 x 2 1/2 " Bj 4,025.00
425 Baut Galvanis 5/8 x 3 " Bj 4,375.00
426 Baut Galvanis 5/8 x 3 1/2 " Bj 4,900.00
427 Baut Galvanis 5/8 x 4 " Bj 5,250.00
428 Baut Galvanis 5/8 x 4 1/2 " Bj 5,650.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
429 Baut Galvanis 5/8 x 5 " Bj 5,980.00
430 Baut Galvanis 5/8 x 5 1/2 " Bj 6,750.00
431 Baut Galvanis 5/8 x 6 " Bj 7,100.00
432 Besi Pipa Galvanis lonjor 770,000.00
433 Angker diameter 12mm bh 14,800.00
434 Skruf Fixer 5 cm bh 550.00
435 Dynabolt bh 3,675.00
436 Sealant Tube 36,300.00
437 Silicon Kg 73,700.00
438 Elektrode 0,6 % bh 137,500.00
439 Elektrode 2 % Bh 203,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
CAT
440 Cat Marka Jalan Kg 43,890.00
441 Glas Bit Kg 27,500.00
442 Cat besi kg 93,170.00
443 Cat Menie besi / Galvanis Kg 49,500.00
444 Cat menie Kayu kg 49,500.00
445 Cat Dasar Tembok Setara Emco Kg 59,400.00
446 Cat Setara emco Lux Biasa kg 59,400.00
447 Cat Setara emco Lux Warna kg 64,460.00
448 Cat Setara emco Lux Warna Tua kg 72,930.00
449 Cat tembok Setara Decolith kg 39,930.00
450 Cat tembok Setara Dulux Exterior kg 126,500.00
451 Cat tembok Setara Dulux Interior kg 93,500.00
452 Cat tembok Setara Vinilex kg 39,930.00
453 Cat Galvanis kg 87,780.00
454 Cat Kayu Emco kg 63,800.00
455 Cat Baja Chromate (anti karat) Kg 110,000.00
456 Cat Kansteen Kg 57,875.00
457 Amplas lbr 6,600.00
458 Kuas Bh 13,200.00

Cat KCA
459 Cat Natural@25 kg Pail 399,000.00
460 Cat Flakes@25 kg Pail 683,000.00
461 Cat Genteng @25kg Pail 519,000.00

Stone Coating :
462 Clear gloss air kg 48,000.00
463 Black gloss air kg 46,000.00
464 Clear gloss solvent kg 50,500.00
465 Black gloss solvent kg 54,000.00
466 Clear doft solvent kg 53,000.00
467 Black doft solvent kg 54,000.00
468 Dempul / Plamir ltr 52,800.00
469 Dempul / Plamir Altik ltr 46,530.00
470 Dempul Impra Kayu ltr 49,500.00
471 Kuas untuk mengecat bh 13,200.00
472 Lem Fox (Rajawali Kuning) Gln 159,500.00
473 Lem Wall Paper Kg 27,500.00
474 Mild zak 13,200.00
475 Minyak cat ltr 46,530.00
476 Melamine Lack / Imfra ltr 77,000.00
477 Okear / Veap Kg 82,500.00
478 Plamir kayu kg 49,500.00
479 Plamir tembok setara wall Putty kg 159,500.00
480 Politur ultra ltr 75,130.00
481 Politur Jadi ltr 75,900.00
482 vernis ltr 60,500.00
483 Residu / Teer Ltr 27,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
484 Roll Buah 38,500.00
485 Sending Seaker ltr 61,050.00
486 Soda Api Kg 24,200.00
487 Thiner A Spesial ltr 27,500.00
488 Thiner B ltr 27,500.00
489 Teack Oil ltr 66,550.00
490 Wall Paper Setara Silk House m2 660,000.00
491 Wood Filler ltr 60,500.00
492 Cat Scotlight Ltr 166,100.00

KACA
493 Bingkai Nako Silver daun 38,500.00
494 Bingkai Nako Coklat daun 33,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
495 Glass Block bh 40,700.00
496 Kaca 2 mm bening m2 77,000.00
497 Kaca 3 mm bening m2 82,500.00
498 Kaca 5 mm bening m2 143,000.00
499 Kaca 6 mm bening m2 187,000.00
500 Kaca 8 mm bening m2 317,900.00
501 Kaca 10 mm bening m2 385,000.00
502 Kaca 12 mm bening m2 495,000.00
503 Kaca Cermin 3 mm m2 165,000.00
504 Kaca Cermin 5 mm m2 308,000.00
505 Kaca Es/Kapur 3 mm m2 198,000.00
506 Kaca Es/Kapur 5 mm m2 253,000.00
507 Kaca Nako Bening m2 99,000.00
508 Kaca Nako Rayben m2 132,000.00
509 Kaca ryben 3 mm m2 99,000.00
510 Kaca ryben 5 mm m2 154,000.00
511 Kaca asahi tebal 3 mm polos clear m2 63,000.00
512 Kaca asahi tebal 3 mm ryben dark grey m2 89,000.00
513 Kaca asahi tebal 3 mm cermin mirror m2 140,000.00
514 Kaca asahi tebal 3 mm es mislet m2 145,500.00
515 Kaca asahi tebal 3 mm biru dark blue m2 235,500.00
516 Kaca asahi tebal 3 mm one way m2 350,000.00
517 Kaca asahi tebal 5 mm polos clear m2 92,500.00
518 Kaca asahi tebal 5 mm ryben dark grey m2 113,500.00
519 Kaca asahi tebal 5 mm cermin mirror m2 200,000.00
520 Kaca asahi tebal 5 mm es mislet m2 190,000.00
521 Kaca asahi tebal 6 mm polos clear m2 145,000.00
522 Kaca asahi tebal 8 mm polos clear m2 289,000.00
523 Kaca asahi tebal 10 mm polos clear m2 350,000.00
524 Kaca asahi tebal 12 mm polos clear m2 362,500.00
525 Kaca tempered asahimas tebal 3mm polos clear m2 203,500.00
526 Kaca tempered asahimas tebal 3mm ryben dark grey m2 242,000.00
527 Kaca tempered asahimas tebal 3mm sanergy clear m2 604,000.00
528 Kaca tempered asahimas tebal 4mm polos clear m2 200,500.00
529 Kaca tempered asahimas tebal 4mm sanergy clear m2 692,000.00
530 Kaca tempered asahimas tebal 5mm polos clear m2 224,500.00
531 Kaca tempered asahimas tebal 5mm ryben dark grey m2 278,000.00
532 Kaca tempered asahimas tebal 5mm stopsol m2 436,000.00
533 Kaca tempered asahimas tebal 5mm warna m2 372,000.00
534 Kaca tempered asahimas tebal 5mm sanergy clear m2 812,000.00
535 Kaca tempered asahimas tebal 6mm polos clear m2 299,500.00
536 Kaca tempered asahimas tebal 6mm ryben dark grey m2 406,000.00
537 Kaca tempered asahimas tebal 6mm stopsol m2 825,000.00
538 Kaca tempered asahimas tebal 6mm warna m2 466,500.00
539 Kaca tempered asahimas tebal 6mm diamon m2 621,500.00
540 Kaca tempered asahimas tebal 6mm sanergy clear m2 1,001,000.00
541 Kaca tempered asahimas tebal 8mm polos clear m2 391,500.00
542 Kaca tempered asahimas tebal 8mm stopsol m2 1,132,000.00
543 Kaca tempered asahimas tebal 8mm warna m2 731,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
544 Kaca tempered asahimas tebal 8mm diamon m2 1,078,000.00
545 Kaca tempered asahimas tebal 8mm sanergy clear m2 1,375,000.00
546 Kaca tempered asahimas tebal 10mm polos clear m2 482,000.00
547 Kaca tempered asahimas tebal 10mm diamon m2 1,540,000.00
548 Kaca tempered asahimas tebal 12mm polos clear m2 565,000.00
549 Kaca tempered asahimas tebal 12mm diamon m2 1,962,500.00
550 Kaca tempered asahimas tebal 15mm polos clear m2 4,616,500.00
551 Kaca tempered asahimas tebal 15mm diamon m2 6,000,000.00
552 Kaca tempered asahimas tebal 19mm polos clear m2 5,313,000.00
553 Kaca tempered asahimas tebal 19mm diamon m2 7,309,500.00
554 Kaca tebal 3+3 mm laminet biasa m2 345,000.00
555 Kaca tebal 4+4 mm laminet biasa m2 422,000.00
556 Kaca tebal 5+5 mm laminet biasa m2 475,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
557 Kaca tebal 6+6 mm laminet biasa m2 566,000.00
558 Kaca tebal 8+8 mm laminet biasa m2 846,000.00
559 Kaca tebal 10+10 mm laminet biasa m2 1,041,000.00
560 Kaca tebal 12+12 mm laminet biasa m2 1,184,000.00
561 Kaca tebal 3+3 mm laminet tempered m2 957,000.00
562 Kaca tebal 4+4 mm laminet tempered m2 1,056,000.00
563 Kaca tebal 5+5 mm laminet tempered m2 1,083,000.00
564 Kaca tebal 6+6 mm laminet tempered m2 1,375,000.00
565 Kaca tebal 8+8 mm laminet tempered m2 1,670,000.00
566 Kaca tebal 10+10 mm laminet tempered m2 1,938,000.00
567 Kaca tebal 12+12 mm laminet tempered m2 2,134,000.00
568 Ongkos polin kaca tempered tebal 5mm m' 15,000.00
569 Ongkos polin kaca tempered tebal 6mm m' 15,000.00
570 Ongkos polin kaca tempered tebal 8mm m' 25,000.00
571 Ongkos polin kaca tempered tebal 10mm m' 25,000.00
572 Ongkos polin kaca tempered tebal 12mm m' 27,500.00
573 Ongkos polin kaca tempered tebal 19mm m' 90,000.00

PI PA
574 Pipa Galvanis 1" M1 55,650.00
575 Pipa Galvanis 1,5 BSA M1 84,000.00
576 Pipa Galvanis 2" M1 118,000.00
577 Pipa Galvanis 3" M1 181,000.00
578 Pipa Setara Maspion AW 1/2 M1 7,560.00
579 Pipa Setara Maspion AW 3/4 M1 10,000.00
580 Pipa Setara Maspion AW 1 M1 11,550.00
581 Pipa Setara Maspion AW 1-1/2 M1 22,000.00
582 Pipa Setara Maspion AW 1-1/4 M1 17,000.00
583 Pipa Setara Maspion AW 2 M1 32,000.00
584 Pipa Setara Maspion AW 2-1/2 M1 41,000.00
585 Pipa Setara Maspion AW 3 M1 58,275.00
586 Pipa Setara Maspion AW 4 M1 85,000.00
587 Pipa Setara Maspion AW 5 M1 134,000.00
588 Pipa Setara Maspion AW 6 M1 176,400.00
589 Pipa Setara Maspion AW 8 M1 275,000.00
590 Pipa Setara Maspion AW 10 M1 390,000.00
591 Pipa Setara Maspion AW 12 M1 630,000.00
592 Pipa Setara Maspion AW 14 M1 800,625.00
593 Pipa Setara Maspion AW 16 M1 979,125.00
594 Pipa Setara Maspion C 3/4 M1 3,675.00
595 Pipa Setara Maspion C 5/8 M1 2,100.00
596 Pipa Setara Maspion C 1 M1 7,000.00
597 Pipa Setara Maspion C 1-1/2 M1 9,000.00
598 Pipa Setara Maspion C 1-1/4 M1 10,000.00
599 Pipa Setara Maspion C 2 M1 13,000.00
600 Pipa Setara Maspion C 2-1/2 M1 17,000.00
601 Pipa Setara Maspion C 3 M1 19,000.00
602 Pipa Setara Maspion C 4 M1 25,000.00
603 Pipa Setara Maspion D 1/2 M1 7,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
604 Pipa Setara Maspion D 1-1/2 M1 12,000.00
605 Pipa Setara Maspion D 1-1/4 M1 11,000.00
606 Pipa Setara Maspion D 2 M1 15,225.00
607 Pipa Setara Maspion D 2-1/2 M1 23,000.00
608 Pipa Setara Maspion D 3 M1 32,550.00
609 Pipa Setara Maspion D 4 M1 46,000.00
610 Pipa Setara Maspion D 5 M1 75,000.00
611 Pipa Setara Maspion D 6 M1 90,825.00
612 Pipa Setara Maspion D 8 M1 161,000.00
613 Pipa Setara Maspion D 10 M1 280,000.00
614 Pipa Setara Maspion D 12 M1 381,675.00
615 Pipa Setara Maspion D 14 M1 499,800.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
616 Pipa Setara Maspion D 16 M1 646,800.00
617 Pipa / selang spiral sel kran M1 34,650.00
618 Pipa setara langgeng warna abu - abu AW 1/2 M1 6,442.50
619 Pipa setara langgeng warna abu - abu AW 3/4 M1 7,847.50
620 Pipa setara langgeng warna abu - abu AW 1 M1 9,880.00
621 Pipa setara langgeng warna abu - abu AW 1 1/4 M1 13,985.00
622 Pipa setara langgeng warna abu - abu AW 1 1/2 M1 18,212.50
623 Pipa setara langgeng warna abu - abu AW 2 M1 27,047.50
624 Pipa setara langgeng warna abu - abu AW 2 1/2 M1 34,722.50
625 Pipa setara langgeng warna abu - abu AW 3 M1 49,525.00
626 Pipa setara langgeng warna abu - abu AW 4 M1 72,182.50
627 Pipa setara langgeng warna abu - abu AW 5 M1 113,850.00
628 Pipa setara langgeng warna abu - abu AW 6 M1 150,472.50
629 Pipa setara langgeng warna abu - abu AW 8 M1 234,032.50
630 Pipa setara langgeng warna abu - abu AW 10 M1 332,500.00
631 Pipa setara langgeng warna abu - abu AW 12 M1 475,115.00
632 Pipa setara langgeng warna abu - abu AW 16 M1 835,555.00
633 Pipa setara langgeng warna abu - abu D 1 1/4 M1 8,712.50
634 Pipa setara langgeng warna abu - abu D 1 1/2 M1 9,880.00
635 Pipa setara langgeng warna abu - abu D 2 M1 12,912.50
636 Pipa setara langgeng warna abu - abu D 2 1/2 M1 19,125.00
637 Pipa setara langgeng warna abu - abu D 3 M1 27,740.00
638 Pipa setara langgeng warna abu - abu D 4 M1 39,007.50
639 Pipa setara langgeng warna abu - abu D 5 M1 63,717.50
640 Pipa setara langgeng warna abu - abu D 6 M1 77,397.50
641 Pipa setara langgeng warna abu - abu D 8 M1 136,877.50
642 Pipa setara langgeng warna abu - abu D 10 M1 238,877.50
643 Pipa setara langgeng warna abu - abu D 12 M1 325,575.00
644 Pipa setara langgeng warna abu - abu D 14 M1 426,405.00
645 Pipa setara langgeng warna abu - abu D 16 M1 551,932.50
646 Pipa setara langgeng warna abu - abu D 20 M1 953,412.50
647 Pipa setara langgeng warna abu - abu C 5/8 M1 1,770.00
648 Pipa setara langgeng warna abu - abu C 1/2 M1 2,965.00
649 Pipa setara langgeng warna abu - abu C 3/4 M1 3,220.00
650 Pipa setara langgeng warna abu - abu C 1 M1 4,505.00
651 Pipa setara langgeng warna abu - abu C 1 1/4 M1 5,980.00
652 Pipa setara langgeng warna abu - abu C 1 1/2 M1 7,170.00
653 Pipa setara langgeng warna abu - abu C 2 M1 10,822.50
654 Pipa setara langgeng warna abu - abu C 2 1/2 M1 13,710.00
655 Pipa setara langgeng warna abu - abu C 3 M1 16,707.50
656 Pipa setara langgeng warna abu - abu C 4 M1 21,525.00
657 Pipa setara langgeng warna abu - abu C 5 M1 29,120.00
658 Pipa setara winlon warna abu - abu AW 1/2 M1 5,527.50
659 Pipa setara winlon warna abu - abu AW 3/4 M1 7,067.50
660 Pipa setara winlon warna abu - abu AW 1 M1 9,212.50
661 Pipa setara winlon warna abu - abu AW 1 1/4 M1 13,475.00
662 Pipa setara winlon warna abu - abu AW 1 1/2 M1 15,867.50
663 Pipa setara winlon warna abu - abu AW 2 M1 22,797.50
664 Pipa setara winlon warna abu - abu AW 2 1/2 M1 29,727.50
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
665 Pipa setara winlon warna abu - abu AW 3 M1 41,772.50
666 Pipa setara winlon warna abu - abu AW 4 M1 64,322.50
667 Pipa setara winlon warna abu - abu AW 5 M1 102,052.50
668 Pipa setara winlon warna abu - abu AW 6 M1 128,975.00
669 Pipa setara winlon warna abu - abu AW 8 M1 204,737.50
670 Pipa setara winlon warna abu - abu AW 10 M1 291,362.50
671 Pipa setara winlon warna abu - abu AW 12 M1 489,912.50
672 Pipa setara winlon warna abu - abu D 1 1/4 M1 7,782.50
673 Pipa setara winlon warna abu - abu D 1 1/2 M1 8,772.50
674 Pipa setara winlon warna abu - abu D 2 M1 11,467.50
675 Pipa setara winlon warna abu - abu D 2 1/2 M1 16,335.00
676 Pipa setara winlon warna abu - abu D 3 M1 23,732.50
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
677 Pipa setara winlon warna abu - abu D 4 M1 33,687.50
678 Pipa setara winlon warna abu - abu D 6 M1 66,660.00
679 Pipa setara winlon warna abu - abu D 8 M1 117,727.50
680 Pipa setara winlon warna abu - abu D 10 M1 218,405.00
681 Pipa setara winlon warna abu - abu D 12 M1 297,220.00
682 Pipa setara winlon warna abu - abu C 5/8 M1 1,485.00
683 Pipa setara winlon warna abu - abu C 1/2 M1 2,722.50
684 Pipa setara winlon warna abu - abu C 3/4 M1 2,887.50
685 Pipa setara winlon warna abu - abu C 1 M1 4,042.50
686 Pipa setara winlon warna abu - abu C 1 1/4 M1 5,362.50
687 Pipa setara winlon warna abu - abu C 1 1/2 M1 6,737.50
688 Pipa setara winlon warna abu - abu C 2 M1 9,212.50
689 Pipa setara winlon warna abu - abu C 2 1/2 M1 11,605.00
690 Pipa setara winlon warna abu - abu C 3 M1 14,355.00
691 Pipa setara winlon warna abu - abu C 4 M1 19,855.00
692 Pipa setara wavin warna putih AW 1/2 M1 4,757.50
693 Pipa setara wavin warna putih AW 3/4 M1 6,517.50
694 Pipa setara wavin warna putih AW 1 M1 8,910.00
695 Pipa setara wavin warna putih AW 1 1/4 M1 13,365.00
696 Pipa setara wavin warna putih AW 1 1/2 M1 15,345.00
697 Pipa setara wavin warna putih AW 2 M1 19,635.00
698 Pipa setara wavin warna putih AW 2 1/2 M1 28,655.00
699 Pipa setara wavin warna putih AW 3 M1 38,637.50
700 Pipa setara wavin warna putih AW 4 M1 64,020.00
701 Pipa setara wavin warna putih AW 5 M1 106,067.50
702 Pipa setara wavin warna putih AW 6 M1 148,775.00
703 Pipa setara wavin warna putih AW 8 M1 249,700.00
704 Pipa setara wavin warna putih AW 10 M1 386,100.00
705 Pipa setara wavin warna putih AW 12 M1 544,390.00
706 Pipa setara wavin warna putih D 1 1/4 M1 8,387.50
707 Pipa setara wavin warna putih D 1 1/2 M1 9,487.50
708 Pipa setara wavin warna putih D 2 M1 12,155.00
709 Pipa setara wavin warna putih D 2 1/2 M1 16,445.00
710 Pipa setara wavin warna putih D 3 M1 20,872.50
711 Pipa setara wavin warna putih D 4 M1 32,835.00
712 Pipa setara wavin warna putih D 5 M1 52,937.50
713 Pipa setara wavin warna putih D 6 M1 69,822.50
714 Pipa setara wavin warna putih D 8 M1 122,815.00
715 Pipa setara wavin warna putih D 10 M1 202,317.50
716 Pipa setara wavin warna putih D 12 M1 284,020.00
717 Pipa setara langgeng warna putih AW 1/2 M1 4,520.00
718 Pipa setara langgeng warna putih AW 3/4 M1 12,385.00
719 Pipa setara langgeng warna putih AW 1 M1 8,465.00
720 Pipa setara langgeng warna putih AW 1 1/4 M1 12,697.50
721 Pipa setara langgeng warna putih AW 1 1/2 M1 14,697.50
722 Pipa setara langgeng warna putih AW 2 M1 18,655.00
723 Pipa setara langgeng warna putih AW 2 1/2 M1 27,222.50
724 Pipa setara langgeng warna putih AW 3 M1 36,707.50
725 Pipa setara langgeng warna putih AW 4 M1 60,812.50
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
726 Pipa setara langgeng warna putih AW 5 M1 100,765.00
727 Pipa setara langgeng warna putih AW 6 M1 141,337.50
728 Pipa setara langgeng warna putih AW 8 M1 237,215.00
729 Pipa setara langgeng warna putih AW 10 M1 366,795.00
730 Pipa setara langgeng warna putih AW 12 M1 517,172.50
731 Pipa setara langgeng warna putih AW 14 M1 708,120.00
732 Pipa setara langgeng warna putih AW 16 M1 885,117.50
733 Pipa setara langgeng warna putih D 1 1/4 M1 7,970.00
734 Pipa setara langgeng warna putih D 1 1/2 M1 9,015.00
735 Pipa setara langgeng warna putih D 2 M1 11,547.50
736 Pipa setara langgeng warna putih D 2 1/2 M1 15,625.00
737 Pipa setara langgeng warna putih D 3 M1 19,830.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
738 Pipa setara langgeng warna putih D 4 M1 31,195.00
739 Pipa setara langgeng warna putih D 5 M1 50,292.50
740 Pipa setara langgeng warna putih D 6 M1 66,332.50
741 Pipa setara langgeng warna putih D 8 M1 116,675.00
742 Pipa setara langgeng warna putih D 10 M1 192,202.50
743 Pipa setara langgeng warna putih D 12 M1 269,820.00
744 Pipa setara langgeng warna putih D 14 M1 451,702.50
745 Pipa setara langgeng warna putih D 16 M1 584,677.50
746 Pipa setara langgeng warna putih D 20 M1 925,642.50
747 Pipa setara langgeng warna putih C 5/8 M1 1,770.00
748 Pipa setara langgeng warna putih C 1/2 M1 2,880.00
749 Pipa setara langgeng warna putih C 3/4 M1 3,220.00
750 Pipa setara langgeng warna putih C 1 M1 4,370.00
751 Pipa setara langgeng warna putih C 1 1/4 M1 5,805.00
752 Pipa setara langgeng warna putih C 1 1/2 M1 7,170.00
753 Pipa setara langgeng warna putih C 2 M1 10,507.50
754 Pipa setara langgeng warna putih C 2 1/2 M1 13,310.00
755 Pipa setara langgeng warna putih C 3 M1 16,220.00
756 Pipa setara langgeng warna putih C 4 M1 16,220.00
757 Pipa setara winlon warna putih AW 1/2 M1 3,822.50
758 Pipa setara winlon warna putih AW 3/4 M1 5,142.50
759 Pipa setara winlon warna putih AW 1 M1 7,150.00
760 Pipa setara winlon warna putih AW 1 1/4 M1 9,955.00
761 Pipa setara winlon warna putih AW 1 1/2 M1 12,925.00
762 Pipa setara winlon warna putih AW 2 M1 17,820.00
763 Pipa setara winlon warna putih AW 2 1/2 M1 23,925.00
764 Pipa setara winlon warna putih AW 3 M1 32,972.50
765 Pipa setara winlon warna putih AW 4 M1 54,587.50
766 Pipa setara winlon warna putih AW 5 M1 81,262.50
767 Pipa setara winlon warna putih AW 6 M1 116,792.50
768 Pipa setara winlon warna putih AW 8 M1 183,067.50
769 Pipa setara winlon warna putih AW 10 M1 263,917.50
770 Pipa setara winlon warna putih D 1 1/4 M1 6,160.00
771 Pipa setara winlon warna putih D 1 1/2 M1 7,480.00
772 Pipa setara winlon warna putih D 2 M1 10,065.00
773 Pipa setara winlon warna putih D 2 1/2 M1 13,612.50
774 Pipa setara winlon warna putih D 3 M1 16,967.50
775 Pipa setara winlon warna putih D 4 M1 27,610.00
776 Pipa setara winlon warna putih D 5 M1 40,590.00
777 Pipa setara winlon warna putih D 6 M1 57,945.00
778 Pipa setara winlon warna putih D 8 M1 98,945.00
779 Pipa setara winlon warna putih D 10 M1 186,367.50
780 Pipa setara winlon warna putih C 5/8 M1 1,402.50
781 Pipa setara winlon warna putih C 1/2 M1 2,612.50
782 Pipa setara winlon warna putih C 3/4 M1 2,832.50
783 Pipa setara winlon warna putih C 1 M1 4,207.50
784 Pipa setara winlon warna putih C 1 1/4 M1 4,922.50
785 Pipa setara winlon warna putih C 1 1/2 M1 6,160.00
786 Pipa setara winlon warna putih C 2 M1 8,662.50
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
787 Pipa setara winlon warna putih C 2 1/2 M1 10,917.50
788 Pipa setara winlon warna putih C 3 M1 13,585.00
789 Pipa setara winlon warna putih C 4 M1 18,122.50
790 Pipa setara vilano warna putih AW 1/2 M1 3,482.50
791 Pipa setara vilano warna putih AW 3/4 M1 4,870.00
792 Pipa setara vilano warna putih AW 1 M1 6,382.50
793 Pipa setara vilano warna putih AW 1 1/4 M1 9,287.50
794 Pipa setara vilano warna putih AW 3 M1 29,035.00
795 Pipa setara vilano warna putih AW 4 M1 41,785.00
796 Pipa setara vilano warna putih AW 5 M1 69,670.00
797 Pipa setara vilano warna putih AW 6 M1 99,282.50
798 Pipa setara vilano warna putih D 1 1/4 M1 5,805.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
799 Pipa setara vilano warna putih D 1 1/2 M1 6,967.50
800 Pipa setara vilano warna putih D 2 M1 8,707.50
801 Pipa setara vilano warna putih D 2 1/2 M1 12,190.00
802 Pipa setara vilano warna putih D 3 M1 15,675.00
803 Pipa setara vilano warna putih D 4 M1 24,382.50
804 Pipa setara vilano warna putih D 5 M1 31,930.00
805 Pipa setara vilano warna putih D 6 M1 55,157.50

806 Pipa PVC (class VU)


PVC Pipe dia. 150 mm m 153,950.00
Elbow 900̊, dia 150 mm bh 143,250.00
Elbow 45, dia 150 mm bh 125,000.00
Sochet dia. 150 bh 66,000.00
shortpipe ke HI dan pipa bh 275,000.00
saddle branch bh 330,000.00
solvent cement kg 45,000.00
PVC Pipe dia. 200 mm m 217,800.00
Sochet dia. 200 bh 137,500.00
Tee dia 200 x 150 mm bh 530,200.00

807 Pipa PVC ( class D ) dia 150 mm M 76,200.00


Bend dia 150, 90 (DV) bh 33,000.00
Bend dia 150, 45 (DV) bh 33,000.00
sochet dia 150 mm (DV) bh 26,500.00

808 Pipa PVC ( class D ) dia 4"


dia 100 mm, length = 4 m M 35,175.00
Sochet dia. 100 mm bh 11,880.00
Bend dia 100, 90 bh 37,560.00
Bend dia 100, 45 bh 18,830.00
Tee Y 45 ; 4" x 2" bh 26,120.00
Tee Y 45 ; 4" x 3" bh 35,880.00
Tee Y 45 ; 4" x 4" bh 40,430.00
Dop PVC 4" bh 14,920.00

809 Pipa PVC ( class D ) dia 3"


dia 75 mm, length = 4 m m 22,462.00
Bend dia 75, 90 bh 18,060.00
Bend dia 75, 45 bh 10,470.00
Sochet dia. 75 mm bh 6,530.00
Dop PVC 3" bh 7,930.00

810 Pipa PVC ( class D ) dia 2" m 13,400.00


Sochet dia. 50 mm bh 4,550.00
Bend dia 50, 90 bh 7,960.00
Bend dia 50, 45 bh 4,690.00
Dop PVC 2" bh 7,000.00
Sifon Crom Leher Angsa bh 132,860.00
811 Pipa PVC Ø 6" M 210,850.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
812 Pipa PVC Ø 4" M 98,700.00
813 Pipa PVC Ø 3" M 67,450.00
814 Pipa PVC Ø 2" M 31,600.00
815 Pipa GI Ø 4" M 399,600.00
816 Pipa GI Ø 3" M 290,000.00
817 Pipa GI Ø 2" M 182,300.00
818 PVC Tee R-R Ø 10" x 3" bh 5,184,700.00
819 PVC Tee R-R Ø 6" x 4" bh 1,230,000.00
820 PVC Tee R-R Ø 6" x 3" bh 1,300,000.00
821 PVC Tee R-R Ø 4" x 4" bh 680,000.00
822 PVC Tee R-R Ø 4" x 3" bh 595,000.00
823 PVC Tee R-R Ø 3" x 3" bh 301,800.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
824 PVC Tee R-R Ø 2" x 3" bh 315,000.00
825 PVC Tee R-SC Ø 4" x 2" bh 475,000.00
826 PVC Tee R-SC Ø 3" x 2" bh 300,000.00
827 PVC Tee SC-SC Ø 2" x 2" bh 66,000.00
828 CI Giboult Joint Std Jis Ø 10" bh 1,588,290.00
829 CI Giboult Joint Std SII Ø 6" bh 699,000.00
830 CI Giboult Joint Std SII Ø 4" bh 545,000.00
831 CI Giboult Joint Std SII Ø 3" bh 396,000.00
832 CI Gate Valve FL- FL Ø 4" bh 4,200,000.00
833 CI Plat Cap Ø 4" bh 201,250.00
834 PVC Tapper Core Ø 4" bh 605,000.00
835 PVC Tapper Core Ø 3" bh 460,000.00
836 BS Bend FL- FL Ø 4" x 45 0̊ bh 719,000.00
837 BS Bend FL- FL Ø 3" x 45 0̊ bh 518,000.00
838 BS Flenge Ø 4" bh 155,400.00
839 BS Flange Ø 3" bh 124,800.00
840 Karet Packing Ø 4" bh 21,000.00
841 Karet Packing Ø 3" bh 18,000.00
842 Bronze Gate Valve Ø 3" bh 1,400,000.00
843 Bronze Gate Valve Ø 2" bh 511,000.00
844 PVC Valve Sochet Ø 3" bh 41,600.00
845 PVC Valve Sochet Ø 2" bh 19,300.00
846 GI Cap Ø 3" bh 66,200.00
847 GI Cap Ø 2" bh 23,650.00
848 GI Elbow Ø 2" bh 35,650.00
849 PVC Bend R- R Ø 4" x 90 0̊ bh 205,200.00
850 PVC Bend R- R Ø 4" x 45 0̊ bh 129,100.00
851 PVC Bend R- R Ø 3" x 45 0̊ bh 93,900.00
852 PVC Bend R- R Ø 3" x 90 0̊ bh 99,700.00
853 PVC Elbow Ø 2" bh 37,000.00
854 PVC Reducer R-R Ø 4" x 3" bh 98,000.00
855 PVC Reducer R-R Ø 3" x 2" bh 47,000.00
856 Beton Path box bh 275,000.00
857 Beton KS bh 49,610.00
858 Pipa Selubung Valve M 70,725.00
859 Penutup Pipa bh 15,700.00
860 Patok UP bh 2,500.00
861 Beton Penahan Ø 10" bh 668,660.00
862 Beton Penahan Ø 6" bh 143,290.00
863 Beton Penahan Ø 4" bh 49,760.00
864 Beton Penahan Ø 3" bh 114,600.00
865 Beton Penahan Ø 2" bh 19,105.00
866 Baut Dynabol bh 40,000.00

BAHAN LISTRIK
867 Coaxial cable 5C - 75 ohm commscof m1 18,700.00
868 Box Panel (3 mm) (400 x 600) Bh 598,400.00
869 Figting lampu Broco Bh 22,000.00
870 Inbow dos plastik clipsal E 157 P OB bj 11,935.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
871 Kabel NYM 2 x 1.5 mm Suprime NYM m1 11,000.00
872 Kabel NYY 2 x 1.5 mm m1 15,950.00
873 Kabel NYM 2 x 2.5 mm m1 16,500.00
874 Kabel NYY 3 x 1.5 mm m1 19,800.00
875 Kabel NYM 3 x 2.5 mm m1 20,900.00
876 Kabel NYY 3 x 2.5 mm m1 27,500.00
877 Kabel NYM 4 mm m1 39,900.00
878 Kabel NYY 2 x 2,5 mm m1 21,450.00
879 Kabel Twisteed 2 x 16 mm m1 16,500.00
880 Kabel telephone m1 17,482.50
881 Klem clipsal 20 mm bj 11,025.00
882 Casing Lampu Bawah Air bh 64,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
883 Casing Lampu Tangga bh 66,500.00
884 Kap Lampu 14 Inchi Aluminium bh 90,000.00
885 Fitting Gantung E27 bh 15,000.00
886 Lampu Son 150 Watt Setara Philips Set 1,438,500.00
887 Lampu Mercury (halaman) bh 462,000.00
888 Lampu Mercury 125 Watt Setara Philips Set 1,403,850.00
889 Lampu Mercury 250 Watt Setara Philips Set 2,977,800.00
890 Lampu Mercury 400 Watt Setara Philips Set 11,118,450.00
891 Lampu pijar 10 Watt Setara Philips bh 7,150.00
892 Lampu pijar 15 Watt Setara Philips bh 7,700.00
893 Lampu pijar 25 Watt Setara Philips bh 8,030.00
894 Lampu pijar 40 Watt Setara Philips bh 9,130.00
895 Lampu TL 20 Watt Komplit (Ballast Philips) bh 115,500.00
896 Lampu TL 25 Watt Komplit (Ballast Philips) bh 126,000.00
897 Lampu LED (5 Watt) Setara Philips Bh 55,000.00
898 Lampu LED (7 Watt) Setara Philips Bh 82,500.00
899 Lampu LED (10) Setara Philips Bh 113,850.00
900 Lampu LED (13 Watt) Setara Philips Bh 148,500.00
901 Lampu Sorot LED (5 Watt) Setara Philips Bh 209,000.00
902 Lampu Sorot LED (7 Watt) Setara Philips Bh 239,800.00
903 Lampu Sorot LED (10 Watt) Setara Philips Bh 278,250.00
904 Lampu Sorot LED (13 Watt) Setara Philips Bh 363,000.00
905 Lampu Sorot LED (25 Watt) Setara Philips Bh 757,000.00
906 Lampu Sorot LED (100 Watt) Setara Philips (ip65) Bh 1,450,000.00
907 Lampu Sorot Cahaya RGB (LED) 100 watt setara Philips (ip65) Bh 2,400,000.00
908 Lampu Sorot Bawah Cahaya Warm White (bolam) 400 watt setara Philips Bh 3,200,000.00
909 Lampu Sorot Bawah Cahaya Warm White (LED) 10 watt setara Philips (ip65) Bh 275,000.00
910 Lampu Sorot Bawah Cahaya Warm White (LED) 30 watt setara Philips (ip65) Bh 380,000.00
911 Lampu Esensial (5 Watt) Setara Philips Bh 30,800.00
912 Lampu Esensial (8 Watt) Setara Philips Bh 38,500.00
913 Lampu Esensial (11 Watt) Setara Philips Bh 44,000.00
914 Lampu Esensial (14 Watt) Setara Philips Bh 52,800.00
915 Lampu Esensial (18 Watt) Setara Philips Bh 58,300.00
916 Scot Light m2 89,000.00
917 Magnet Contactor 80 A SN - 50 Bh 1,225,224.00
918 MCB 3 phase 40 A MG Bh 347,550.00
919 MCB 3 phase 63 A MG Bh 660,450.00
920 Panel MDP Unit 33,206,250.00
921 Panel SDP Unit 14,437,500.00
922 Pipa clipsal 20 mm bt 15,400.00
923 Pipa flexible clipsal 20 mm m1 11,000.00
924 Saklar ganda Setara Broco Bh 30,800.00
925 Saklar tunggal Setara Broco Bh 19,800.00
926 SL 18 Watt Komplit bh 81,675.00
927 Sock clipsal 20 mm bj 3,300.00
928 Steker bh 14,740.00
929 Stop Kontak bh 27,500.00
930 Stop Kontak Khusus (Kedap Air) bh 49,500.00
931 Travo max 50 watt bh 750,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
932 Tee dos clipsal 20 mm bh 7,480.00
933 Time Switch Bh 472,500.00
934 T Foring Bh 46,200.00

MARMER / GRANIT
935 Marmer (30 x 30) m2 308,000.00
936 Granit (30 x 30) Tekstur Kasar Tebal 3 cm m2 715,000.00
937 Batu Andesit (30 x 30 x 5 cm) m2 385,000.00
938 Roster Keramik (12 x 11 x 24) bh 46,200.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
GRANIT TILE
939 Setara Essenza 40 x 40 m2 315,150.00
940 Setara Essenza 60 x 60 m2 387,200.00
941 Setara Granito 40 x 40 cm m2 348,150.00
942 Setara Nero Granito 30 x 60 cm m2 305,800.00
943 Setara Nero Granito 40 x 40 cm m2 348,150.00
944 Setara Nero Granito 60 x 60 cm m2 345,950.00
945 Setara Ex Cina 60 x 60 cm m2 181,500.00
946 Setara Ex Cina 80 x 80 cm m2 231,000.00

KERAMIK
947 Keramik Setara Asia Tile 20 x 20 kelas I warna muda m2 71,500.00
948 Keramik Setara Asia Tile 20 x 20 kelas I warna tua m2 74,800.00
949 Keramik Setara Asia Tile 20 x 25 kelas I m2 77,000.00
950 Keramik Setara Asia Tile 30 x 30 kelas I warna muda m2 55,000.00
951 Keramik Setara Asia Tile 30 x 30 kelas I warna tua m2 57,200.00
952 Keramik Setara Asia Tile 40 x 40 kelas I m2 74,800.00
953 Keramik Setara Asia Tile 60 x 60 kelas I Setara Platinum m2 126,500.00
954 Keramik Setara ARWANA ( warna putih) M2 51,700.00
955 Keramik Setara ARWANA ( warna tua) M2 66,000.00
956 Keramik Setara Diamond 10/20 cm (Warna Muda) M2 66,000.00
957 Keramik Setara Diamond 20/20 cm (Kelas I Warna Muda) M2 60,500.00
958 Keramik Setara Diamond 30/30 cm (Kelas I Warna Muda) M2 66,000.00
959 Keramik Setara Diamond 10/20 cm (Warna tua) M2 82,500.00
960 Keramik Setara Diamond 20/20 cm (Kelas I Warna Tua) M2 66,000.00
961 Keramik Setara Diamond 30/30 cm (Kelas I Warna Tua) M2 66,000.00
962 Keramik Setara Ikad (Keramik) Kw. I 10 x 20 cm (DK warna muda) M2 66,000.00
963 Keramik Setara Ikad (Keramik) Kw. I 10 x 20 cm (DK warna tua) M2 82,500.00
964 Keramik Setara Ikad (Keramik) Kw. I 20 x 20 cm (warna tua) m2 63,800.00
965 Keramik Setara Ikad (Keramik) Kw. I 20 x 20 cm (warna muda) m2 55,000.00
966 Keramik Setara Ikad (Keramik) Kw. I 30 x 30 cm m2 68,200.00
967 Keramik Setara Ikad (Keramik) Kw. I 40 x 40 cm m2 77,000.00
968 Keramik Setara Ikad (Keramik) Kw. I 50 x 50 cm m2 88,550.00
969 Keramik Setara KIA 20/20 cm warna muda m2 71,500.00
970 Keramik Setara KIA 30/30 cm warna muda m2 72,600.00
971 Keramik Setara KIA 20/20 cm warna tua m2 77,550.00
972 Keramik Setara KIA 30/30 cm warna tua m2 77,550.00
973 Keramik Setara Mulia Warna Putih m2 49,500.00
974 Keramik Setara Mulia Warna Tua m2 49,500.00
975 Keramik Setara Mulia 20 x 20 cm Warna Tua m2 51,700.00
976 Keramik Setara Mulia 20 x 20 cm Warna Muda m2 48,950.00
977 Keramik Setara Mulia 30 x 30 cm Warna Putih m2 47,410.00
978 Keramik Setara Mulia 30 x 30 Warna Marbel m2 55,550.00
979 Keramik Setara Mulia 30 x 30 Warna Impresso m2 57,090.00
980 Keramik Setara Mulia 40 x 40 cm kelas I m2 69,850.00
981 Keramik Setara ROMAN 20/20 cm m2 102,850.00
982 Keramik Setara ROMAN 30/30 cm m2 143,000.00
983 Tegel PC abu - abu 20/20 cm M2 86,350.00
984 Tegel PC Warna 20/20 cm M2 86,350.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
985 Tegel PC Warna 30/30 cm M2 86,350.00
986 Tegel 30 x 30 TB PC M2 69,500.00
987 Tegel 30 x 30 TB PC Kuning (Tegel Penuntun) M2 86,350.00
988 Tegel 30 x 30 Warna Merah M2 86,350.00
989 Tegel Bata 20 x 20 Merah M2 86,350.00
990 Tegel Bata 20 x 20 PC M2 86,350.00
991 Tegel B/TB 20 x 20 Kuning M2 86,350.00
992 Tegel Mozaik Porselint 30/30 cm M2 82,500.00
993 Tegel Wafel 20/20 cm Warna M2 77,000.00
994 Ubin PC Warna Bj 7,000.00
995 Ubin PC Warna 20 / 20 Cm M2 82,500.00
996 Batu Lahar 30/30 bh 27,500.00
997 Porselint 11/11 cm bj 49,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4

ATAP
998 Alang-alang panjang 2,4 meter lbr 16,500.00
999 Alluminium foil M2 Double Roll 245,300.00
1000 Akustik 60 cm x 120 cm lbr 54,450.00
1001 Asbes Bubungan lbr 49,000.00
1002 Asbes Gelombang 1,80 m x 0,80 m lbr 38,500.00
1003 Asbes Gelombang 1,80 m x 1,05 m lbr 41,800.00
1004 Asbes Gelombang 2,10 m x 1,05 m lbr 45,100.00
1005 Asbes Gelombang 2,4 m x 1,05 m lbr 53,900.00
1006 Asbes Rata 2 m x 1 m x 4 mm lbr 60,500.00
1007 Bentala tanah liat Ex Pejaten bh 93,500.00
1008 Bentala Ex Kapal 70,500.00
1009 Bentala Besar polos Lubang 25 cm bj 82,500.00
1010 Bentala Besar Warna Lubang 25 cm bj 110,000.00
1011 Bentala Besar polos Lubang 90 cm bj 143,000.00
1012 Bentala Besar Warna Lubang 90 cm bj 165,000.00
1013 Bubungan Besar bj 17,600.00
1014 Bubungan Kecil bj 13,200.00
1015 Bubungan Bambe Kecil bj 19,250.00
1016 Bubungan Bulat Karang Pilang bj 19,250.00
1017 Bubungan Bulat Jati Wangi bj 17,050.00
1018 Bubungan Bulat Ngalayur isi 3,5/m bj 9,900.00
1019 Bubungan Besar Good Year bj 17,600.00
1020 Bubungan Beton Cisangkan bj 21,450.00
1021 Bubungan Gerard lbr 68,500.00
1022 Bubungan Karang Pilang isi 3,5/m bj 19,250.00
1023 Bubungan Pletong Jatiwangi bj 16,500.00
1024 Bubungan SL Utama Bj 16,500.00
1025 Bubungan SL Ngalayur bj 9,350.00
1026 Bubungan Segi Tiga Karang Pilang bj 19,250.00
1027 Bubungan Utama isi 3,5/m bj 16,500.00
1028 Genteng Bambe bj 5,390.00
1029 Genteng Bambe Karang Pilang bj 5,390.00
1030 Genteng Bambe Kecil bj 5,170.00
1031 Genteng Beton Cisangkan bj 13,750.00
1032 Genteng Gemini bj 6,600.00
1033 Genteng Gerard Polos m2 254,500.00
1034 Genteng Good Year m2 5,500.00
1035 Genteng Kanmuri (glazur) isi 14/m2 bj 11,550.00
1036 Genteng Kodok Lokal bj 3,740.00
1037 Genteng Kodok Kamulan bj 3,850.00
1038 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bj 5,500.00
1039 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bj 5,170.00
1040 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bj 5,500.00
1041 Genteng Kodok Karang Pilang (Surabaya) bj 7,000.00
1042 Genteng Kodok Soka bj 2,420.00
1043 Genteng Lestari bj 3,080.00
1044 Genteng Metal m2 40,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1045 Genteng Metal 80 x 77,6 (Polos) lbr 40,590.00
1046 Genteng Metal 80 x 77,6 (Pasir) lbr 65,340.00
1047 Genteng Morando Abadi isi 18/m2 bj 9,240.00
1048 Genteng Morando Jatiwangi isi 18/m2 bj 4,950.00
1049 Genteng Morando Ngalayur isi 20/m2 bj 4,070.00
1050 Genteng Morando Metal bj 63,800.00
1051 Genteng Pejaten Mini bj 3,080.00
1052 Genteng Plentong bj 2,200.00
1053 Genteng plentong dicat bj 2,420.00
1054 Genteng Plentong Mantili bj 2,200.00
1055 Genteng Plentong Pejaten / Darmasaba bj 4,000.00
1056 Genteng Plentong Jatiwangi / Surabaya bj 6,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1057 Genteng Portugis bj 6,500.00
1058 Genteng Pres Besar bj 1,980.00
1059 Genteng Pres Besar Cat bj 2,090.00
1060 Genteng Pres Mini bj 1,760.00
1061 Genteng Pres Mini Cat bj 1,980.00
1062 Genteng Terreal bj 8,000.00
1063 Genteng T. Romana bj 8,000.00
1064 Genteng Besar polos Lubang 35 cm bj 1,980.00
1065 Genteng Besar Warna Lubang 35 cm bj 2,090.00
1066 Fiberglas (1.80 x 0.80) M2 lbr 1,760.00
1067 Ijuk kg 1,980.00
1068 Ijuk Bersih kg 11,000.00
1069 Ijuk kg 8,000.00
1070 Ikut Celedu bj 209,000.00
1071 Ikut Celedu Besar Polos bh 88,000.00
1072 Ikut Celedu Besar Warna bh 99,000.00
1073 Ikut Celedu Kecil Polos bh 66,000.00
1074 Ikut Celedu Kecil Warna bh 88,000.00
1075 Kawat las Kg 80,300.00
1076 Kawat Diameter 4 mm Kg 88,000.00
1077 Murda / Puntal Paras Bh 220,000.00
1078 Murda tanah liat Ex Pejaten bh 121,000.00
1079 Murda Kecil Polos Lubang 25 cm bh 88,000.00
1080 Murda Kecil Warna Lubang 25 cm bh 104,500.00
1081 Profil Aluminium "T" m3 219,450.00
1082 Seng BJLS 0,18 gelombang lbr 99,770.00
1083 Seng BJLS 0,22 gelombang lbr 106,480.00
1084 Seng BJLS 0,30 gelombang lbr 119,790.00
1085 Seng Zincalume Panjang 6m Tebal 0,5 mm lbr 93,500.00
1086 Seng Plat Lebar 0,90 M lbr 53,240.00
1087 Seng Plat 3" x 6" BJLS 28 lbr 66,550.00
1088 Seng Plat Aluminium lbr 53,240.00
1089 Sirap Lbr 4,950.00
1090 Subeng Besar Polos lbr 9,240.00
1091 Subeng Besar Warna lbr 5,390.00
1092 Subeng Kecil Polos lbr 6,600.00
1093 Subeng Kecil Warna bh 4,180.00

TALI
1094 Tali Ijuk kg 5,390.00
1095 Tali pengikat ikat 16,500.00
1096 Tali pengikat alang-alang ikat 19,800.00
1097 Tali Rafia Gulung 3,000.00

SANITAIR
1098 Bak mandi fibre glass 70x70x66 cm bh 306,130.00
1099 Bak mandi porselin/ keramik bh 242,500.00
1100 Bak mandi keramik 50x50 bh 187,000.00
1101 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 341,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1102 Floor drain Plastic bh 18,900.00
1103 Floor Drain Stainless bh 65,000.00
1104 Floor drain plastik Setara Alianco bh 27,500.00
1105 Floor drain stainless Setara Wasser bh 49,500.00
1106 Dudukan Kloset dan Perlengkapannya set 2,090,000.00
1107 Kloset duduk INA Komplit bh 1,650,000.00
1108 closet duduk INA (putih) STD bh 1,100,000.00
1109 closet duduk INA (warna) bh 1,320,000.00
1110 Kloset duduk Amerika Standar Winplus bh 1,430,000.00
1111 closet duduk TOTO (putih) STD bh 1,100,000.00
1112 closet duduk TOTO (warna) bh 1,705,000.00
1113 Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP COMPLIT bh 1,815,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1114 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh 5,699,100.00
1115 Kloset duduk " TOTO Type AVANTE CW 823 J bh 8,457,900.00
1116 Kloset duduk " TOTO Type CW 660J bh 738,100.00
1117 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 1,925,000.00
1118 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh 2,589,400.00
1119 Kloset duduk " TOTO Type CW 660J WARNA COMPLIT bh 810,700.00
1120 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 3,388,000.00
1121 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 3,763,100.00
1122 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 3,908,300.00
1123 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 469,150.00
1124 Kloset jongkok " TOTO Type CE 7 COMPLIT bh 246,950.00
1125 closet jongkok porselin/ keramik bh 275,000.00
1126 Kloset porselin jongkok TOTO (standar) bh 374,000.00
1127 Kloset porselin jongkok Ina (standar) bh 175,450.00
1128 Kran biasa Setara Onda bh 55,000.00
1129 Kran SunEi PI/3 JHR bh 76,000.00
1130 Kran TOTO T 205 LCSC bh 242,550.00
1131 Kran TOTO T 205 MC bh 330,000.00
1132 Kran TOTO T 23 B13 bh 271,700.00
1133 Kran TOTO T 23 B13V7NB bh 280,500.00
1134 Kran TOTO T 26 - 13 bh 367,400.00
1135 Kran TOTO TX 109 LH bh 775,500.00
1136 Penyekat Urinoir " TOTO " Type A 100 " bh 1,364,000.00
1137 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 459,800.00
1138 Soap holder " TOTO " Type S 6 N " bh 121,000.00
1139 Seal tape bh 3,300.00
1140 Urinoir TOTO (STD) bh 2,640,000.00
1141 Urinoir " TOTO U 57 M bh 2,874,960.00
1142 Urinoir " TOTO U 57 M BODI bh 1,414,600.00
1143 Urinoir INA (STD) bh 2,530,000.00
1144 Wastagel KIA Standard bh 203,500.00
1145 Wastagel KIA Warna bh 258,500.00
1146 Wastafel TOTO (putih) bh 594,000.00
1147 Wastafel TOTO (warna) bh 1,135,000.00
1148 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh 1,248,500.00
1149 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh 808,500.00
1150 Wastafel INA (putih) bh 770,000.00
1151 Wastafel INA (warna) bh 770,000.00

KUNCI DAN PENGGANTUNG


1152 Engsel H ( 80 x 50) Ps 11,000.00
1153 Engsel kupu-kupu Rafes 4' 304 ps 64,900.00
1154 Engsel pintu Setara ECOLING Ps 73,150.00
1155 Engsel jendela Setara ECOLING Ps 46,310.00
1156 Engsel jendela Setara CAMEL Ps 39,600.00
1157 Espagnoleth Setara Rafes 60 cm Ps 51,700.00
1158 Grendel Setara ESBELA Bh 133,100.00
1159 Grendel tanam Setara CAMEL Bh 218,350.00
1160 Kait angin biasa Setara CAMEL Bh 55,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1161 Kait angin lipat Setara ESBELA Bh 86,460.00
1162 Kait angin tarik Setara ESBELA Bh 59,950.00
1163 Kunci lif 1 x putar Setara BELLEZA Bh 146,300.00
1164 Kunci lif 2 x putar Bh 166,100.00
1165 Kunci pintu TOP Setara ESBELA bh 330,000.00
1166 Kunci pintu Vanesa Setara CAMEL bh 199,650.00
1167 Kunci pintu Setara ESBELLA bh 286,000.00
1168 Kunci Pintu 2 x putar Setara SES Bh 226,270.00
1169 Kunci pintu Setara DELWIN) bh 198,000.00
1170 Kunci shang hae 2 x putar Bh 185,900.00
1171 Kunci slot / Grendel Pintu Setara DELLWYN bh 244,200.00
1172 Kunci tanam 2 slag Setara Dexon bh 291,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1173 Rolling door plaat M2 133,100.00
1174 Rolling Door Aluminium M2 650,000.00
1175 besi tangga D 19, enamel cat bh 15,000.00
1176 Handle Besi Ø 12, enamel cat bh 6,500.00

PAKU
1177 Paku Beton Kg 33,000.00
1178 Paku Usuk Kg 14,625.00
1179 Paku Reng Kg 14,250.00
1180 Paku List Kg 21,191.67
1181 Paku Seng Ulir bh 900.00
1182 Paku 2-4 cm kg 15,271.67
1183 Paku Pancing 60 x 230 Kg 16,500.00
1184 Paku 5-12 cm kg 17,297.78
1185 Paku 2 cm (30 kg) 3/4 inch SQ dus 471,800.00
1186 Paku 2,5 cm (30 kg) 1 inch SQ dus 466,200.00
1187 Paku 3 cm (30 kg) 1 1/4 inch SQ dus 457,800.00
1188 Paku 4 cm (30 kg) 1 1/2 inch SQ dus 436,800.00
1189 Paku 5 cm (30 kg) 2 inch SQ dus 393,400.00
1190 Paku 7,10,12 cm (3,4,5) inch SQ dus 389,200.00
1191 Paku 5 -12 cm (27kg) 2,3,4,5 inch dus 306,600.00
1192 Bendrat 20 kg rol 250,600.00
1193 Sekrup Kalisiboard buah 220.00

BETON CETAK
1194 Paving Arahan 30 x 30 tebal 6 cm (K225) M2 150,000.00
1195 Paving Arahan 20 x 20 tebal 6 cm (K225) M2 150,000.00
1196 Paving stone tebal 6 cm polos 10/20 K225 (Polos) M2 78,650.00
1197 Paving stone tebal 6 cm 10/20 K225 (Warna full colour) M2 125,400.00
1198 Paving stone tebal 6 cm 20/20 K225 (Polos) M2 78,650.00
1199 Paving stone tebal 6 cm 20/20 K225 (Warna full colour) M2 125,400.00
1200 Paving 10 x 20 cm tebal 6 cm K350 (Polos) m2 90,750.00
1201 Paving 10 x 20 cm tebal 6 cm K350 (Warna) m2 136,400.00
1202 Paving 20 x 20 cm tebal 6 cm K350 (Polos) m2 90,750.00
1203 Paving 20 x 20 cm tebal 6 cm K350 (Warna) m2 136,950.00
1204 Paving stone tebal 8 cm 10/20 K225 (Polos) M2 79,860.00
1205 Paving stone tebal 8 cm 10/20 K225 (Warna full Colour) M2 136,950.00
1206 Paving stone tebal 8 cm 20/20 K225 (Polos) M2 79,860.00
1207 Paving stone tebal 8 cm 20/20 K225 (Warna full colour) M2 137,280.00
1208 Paving Stone tebal 8 cm (K300) M2 94,450.00
1209 Paving 10 x 20 cm tebal 8 cm K350 (Polos) m2 99,550.00
1210 Paving 10 x 20 cm tebal 8 cm K350 (Warna)) m2 146,850.00
1211 Paving 20 x 20 cm tebal 8 cm K350 (Polos) m2 99,770.00
1212 Paving 20 x 20 cm tebal 8 cm K350 (Warna)) m2 146,300.00
1213 Paving 20 x 20 cm tebal 8 cm K400 (Polos) m2 117,700.00
1214 Paving 20 x 20 cm tebal 8 cm K400 (Warna)) m2 156,200.00
1215 Paving Tiga Berlian tebal 6 Cm K225 (Polos) M2 75,460.00
1216 Paving Tiga Berlian tebal 6 cm K225 (Warna) m2 122,100.00
1217 Box Culvert Type 600x600x1200 K 350 Bh 2,949,933.33
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1218 Box Culvert Type 800x800x1200 K 350 Bh 3,676,666.67
1219 Box Culvert Type 1000x1000X1200 K 350 Bh 4,315,416.67
1220 Box Culvert Type 1200x1200X1200 K 350 Bh 4,496,000.00
1221 Box Culvert Type 1500x1500x1200 K 350 Bh 10,420,000.00
1222 Box Culvert Type 2000x2000x1200 K 350 Bh 14,331,666.67
1223 Box Culvert Type 3000x2000x1200 K 350 Bh 14,680,000.00
1224 Box Culvert Type 3000x2500x1200 K 350 Bh 15,927,500.00
1225 Box Culvert Type 3000x3000x1200 K 350 Bh 17,220,500.00
1226 Saluran Berbentuk U Type 300x300x1200 K350 Bh 422,000.00
1227 Saluran Berbentuk U Type 300x400x1200 K350 Bh 502,500.00
1228 Saluran Berbentuk U Type 300x500x1200 K350 Bh 583,000.00
1229 Saluran Berbentuk U Type 400x400x1200 K350 Bh 584,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1230 Saluran Berbentuk U Type 400x600x1200 K350 Bh 815,500.00
1231 Saluran Berbentuk U Type 400x700x1200 K350 Bh 1,200,000.00
1232 Saluran Berbentuk U Type 500x500x1200 K350 Bh 1,200,000.00
1233 Saluran Berbentuk U Type 500x600x1200 K350 Bh 1,300,000.00
1234 Saluran Berbentuk U Type 500x700x1200 K350 Bh 1,400,000.00
1235 Saluran Berbentuk U Type 600x600x1200 K350 Bh 1,389,033.33
1236 Saluran Berbentuk U Type 600x700x1200 K350 Bh 1,096,500.00
1237 Saluran Berbentuk U Type 700x700x1200 K350 Bh 1,650,960.00
1238 Saluran Berbentuk U Type 600x800x1200 K350 Bh 1,226,000.00
1239 Saluran Berbentuk U Type 800x800x1200 K350 Bh 1,992,100.00
1240 Saluran Berbentuk U Type 800x1000x1200 K350 Bh 1,752,500.00
1241 Saluran Berbentuk U Type 1000x1000x1200 K350 Bh 1,840,000.00
1242 Bentala Exs Kapal (Paras) bh 68,000.00
1243 Bentala Exs Kapal (Terakota) bh 68,000.00
1244 Kanstein Segi Lima P40 Buah 29,150.00
1245 Kanstein Segi Lima P50 Buah 35,750.00
1246 Kansteen K.250 Bh 60,000.00
1247 Kansteen Pendek K.250 Bh 22,500.00
1248 Kansteen Jalan Masuk K.250 Bj 61,500.00
1249 Kansteen Segilima P.50, T.20, L.15 K.250 Bj 35,750.00
1250 Kansteen Bulat P.50, T.30, LA.10 LB.15 K.250 Bj 60,000.00
1251 Kansteen Jumbo P.50, T.30, L.15 K.250 Bj 43,000.00
1252 Kansteen Jumbo 15x30x50 K.300 Bj 94,000.00
1253 Kansteen Jumbo Mini 15x20x50 K.300 Bj 87,000.00
1254 Kansteen Kursi 15x40x60 K300 Bj 114,000.00
1255 Kansteen Persegi T 15, P50, L 20 K 225 Bj 55,000.00
1256 Kansteen Kursi K 225 Bj 91,500.00
1257 Kansteen Kursi T 15, L 40 . P 50 K 225 Bj 120,000.00
1258 Kansteen Kursi T 10, L 40 . P 50 K 225 Bj 95,000.00
1259 Kansteen Jumbo 15x30x50 K.300 Bh 67,000.00
1260 Kansteen Jumbo mini 15x20x50 K.300 Bh 58,500.00
1261 Kansteen kursi (Jalan Masuk) 15x40x60 K.300 Bh 82,000.00
1262 Tutup Got (Grill) (P:45, L:24, T:9 cm) Bj 57,000.00
1263 Tutup Got (Grill) (P:30, L:24, T:9 cm) Bj 54,000.00
1264 Plat Penutup 600 x 1200 Bh 569,500.00
1265 Plat Penutup 800 x 1200 Bh 791,000.00
1266 Plat Penutup 1000 x 1200 Bh 917,000.00
1267 Frame Manhole 600x600 Bh 700,000.00
1268 Frame Manhole 800x800 Bh 592,000.00
1269 Frame Manhole 1000x1000 Bh 733,000.00
1270 Cover manhole 600x600 Bh 838,000.00
1271 Cover manhole 800x800 Bh 1,032,500.00
1272 Cover manhole 1000x1000 Bh 1,200,000.00
1273 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 78,430.00
1274 Grass Block lobang 5, 30 X 30 cm tebal 7 cm K 225 m2 61,000.00
1275 Beton Cetak Greas Blok K.250 Bj 13,400.00

PLAFOND & TIRPLEK


1276 Acustik 30/30 lbr 84,700.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1277 Celling teak (0,62 x 2,40) m2 lbr 105,600.00
1278 Eternit lbr 18,150.00
1279 Playwood 3 mm Lbr 54,708.33
1280 Playwood 4 mm Setara Meranti Lbr 69,575.00
1281 Plywood 5 mm lbr 122,100.00
1282 Playwood 9 mm Setara Meranti Lbr 148,500.00
1283 Playwood aluminium Lbr 118,800.00
1284 Gypsum Board (120x240x9) lbr 79,200.00
1285 Kalsiboard (4,5 x 1220 x 2420) mm lbr 113,080.00
1286 Hard board MDF lbr 141,900.00
1287 Kayu Acuan / Multiplek 6 mm Lbr 74,800.00
1288 Multiplek 9mm Lbr 115,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1289 Triplek tebal 3mm (2,7mm) kayu sengon lbr 44,300.00
1290 Triplek tebal 3mm (2,7mm) kayu semi meranti lbr 52,500.00
1291 Triplek tebal 4mm (3,6mm) kayu sengon lbr 54,000.00
1292 Triplek tebal 4mm (3,6mm) kayu semi meranti lbr 64,500.00
1293 Triplek tebal 6mm (5,2mm) kayu sengon I lbr 65,800.00
1294 Triplek tebal 6mm (5,2mm) kayu sengon II lbr 59,000.00
1295 Triplek tebal 6mm (5,2mm) kayu semi meranti lbr 76,500.00
1296 Triplek tebal 6mm (5,2mm) kayu semi meranti II lbr 61,500.00
1297 Triplek tebal 8,0mm kayu sengon I lbr 97,000.00
1298 Triplek tebal 8,0mm kayu sengon II lbr 89,000.00
1299 Triplek tebal 8,0mm kayu semi meranti lbr 107,500.00
1300 Triplek tebal 9,0mm kayu semi meranti II lbr 94,500.00
1301 Triplek tebal 12 mm kayu sengon I lbr 129,500.00
1302 Triplek tebal 12 mm kayu semi meranti lbr 178,000.00
1303 Triplek tebal 15 mm kayu semi meranti lbr 210,000.00
1304 Triplek tebal 18 mm kayu semi meranti lbr 232,000.00
1305 Teakwood 122 x 244 x 2,7 mm lbr 72,500.00
1306 Melamine Putih/Biru 2,7 lbr 87,500.00
1307 Triplek aluminium jruk asli lbr 106,500.00
1308 Triplek aluminium jruk standar lbr 69,500.00
1309 Blocbord 18 mm sengon lbr 167,500.00
1310 Blocbord 18 mm meranti super lbr 205,000.00
1311 Teak block lbr 207,500.00
1312 Rangka Aluminium m1 19,360.00
1313 Rangka Metal Furing (2 x 4 cm) panjang 4 m btg 22,000.00
1314 Rangka Metal Furing (4 x 4 cm) panjang 4 m btg 27,500.00
1315 Teak wood (1,20x2,40x 0,4) lbr 84,700.00
1316 Teak wood (0,90x2,00 x 0,4) lbr 72,600.00
1317 Jabar Wood 4 mm lbr 106,000.00

BUIS BETON
1318 Buis beton Diameter 25 x 75 bh 56,650.00
1319 Buis beton Diameter 30 x 75 bh 72,600.00
1320 Buis beton Diameter 50 x 75 bh 99,000.00
1321 Buis Beton diameter 80 cm Bj 113,066.67
1322 Buis Beton diameter 25 cm Bj 55,166.67
1323 Buis Beton diameter 1/2 50 cm Bj 50,333.33

TALANG
1324 Talang Karet L = 0.50 m' 99,000.00
1325 Talang Karet L = 0.90 m' 126,500.00
1326 Pipa Talang PVC Setara Maspion 6" Setengah Lingkaran m' 71,500.00
1327 Pipa Talang PVC Setara Maspion 6" Kotak m' 93,500.00

ASPAL, BBM DAN PELUMAS


1328 Aspal Penetrasi 60/70 Kg 12,000.00
1329 Aspal Curah Kg 12,000.00
1330 Aspal RC Kg 10,000.00
1331 Aspal Emulsi ltr 14,200.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1332 Aspal Emulsi CRS 1 ltr 10,300.00
1333 Aspal Emulsi CRS 1 Modif 10,900.00
1334 Aspal Emulsi CRS 2 ltr 11,650.00
1335 Aspal Emulsi CSS 1 h Modif ltr 10,400.00
1336 Aspal Emulsi CSS 1 h ltr 9,650.00
1337 Aspal Emulsi CSS 1 / PCE ltr 10,200.00
1338 Minyak Aspal ( fluck oil ) Ltr 13,350.00
1339 Minyak Tanah Ltr 3,000.00
1340 Minyak Tanah Industri Ltr 7,625.00
1341 Solar Ltr 7,500.00
1342 Solar Industri Ltr -
1343 Premium (industri) Ltr -
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1344 Pelumas ( olie ) Ltr 28,350.00
1345 Kayu Api M3 385,000.00
1346 Gas elpiji Kg -
1347 Minyak Begesting ( B 115 ) Ltr 30,666.67
1348 Aspal Cold Mix (Readymix) Kg 2,250.00

ALAT PEMADAM KEBAKARAN


1349 Instalasi pipa induk BS 3" Sch M' 203,500.00
1350 Intalasi pipa distribusi BS 2" Sch M' 137,500.00
1351 Seamesi conection Bh 1,980,000.00
1352 Box hidran dengan kelengkapannya Bh 2,750,000.00
1353 Selang pemadam 30 m Bh 3,520,000.00
1354 Pemadam api ringan 6 kg Bh 121,000.00

TANAMAN
1355 Pohon Lianglio / Salix Babylonica pohon 520,000.00
1356 Palem Ekor Tupai / Wodyetia Bifurcata pohon 1,550,000.00
1357 Pohon Jepun / Plumeria Rubra pohon 1,500,000.00
1358 Pohon Pudak / Pandanus Tectorius pohon 2,000,000.00
1359 Pohon Ketapag Kencana / Terminalia Molineti pohon 1,600,000.00
1360 Pohon Sente Batang Hitam / Alokasia 'black' pohon 70,000.00
1361 Pohon Dadap Merah / Erythrina Crista Galli pohon 1,400,000.00
1362 Pohon Jepun Pagoda / Plumeria 'pagoda' pohon 1,600,000.00
1363 Pohon Tabebuya / Chrysotricha sp pohon 1,300,000.00
1364 Semak Jempiring / Gardenia Jasminioides polybag 8,500.00
1365 Semak Spathyphilum / Spathyphylum sp polybag 9,000.00
1366 Semak Reulia Besar / Reulia Malacosperma Giant polybag 4,000.00
1367 Semak Anturium Bunga / Anthurium Andreanum polybag 40,000.00
1368 Semak Hemigrapis / Hemigrapis sp polybag 5,000.00
1369 Semak Puring / Codeaium variegatum polybag 9,000.00
1370 Semak Pakis Bulu / Nephrolepis biserrata polybag 13,000.00
1371 Lili Bangkok / Hymenocalis litoralis polybag 9,000.00
1372 Jempiring / Gardenia jasminioides polybag 7,000.00
1373 Kaki Laba-laba / Oxmosilum Liniare Yellow polybag 16,000.00
1374 Semak Bawang-bawangan / Ornithogalum umbrellatum polybag 4,700.00
1375 Semak Kebang Kertas Daun Kecil / Bogenvile small leave polybag 16,000.00
1376 Semak Lily Paris / Hymenocallis Speciosa polybag 4,000.00
1377 Semak Daun Philodendron / Philodendron sp polybag 13,000.00
1378 Semak Bunga Yolanda / Yolanda white flower polybag 10,000.00
1379 Semak Karembusa Putih / Tebermontana carembusa 'white' polybag 15,000.00
1380 Semak Simbang Darah / Excoecaria Cochinechinensis polybag 8,000.00
1381 Semak Bromelia / Bromelia sp polybag 150,000.00
1382 Pupuk Kandang m3 162,000.00

LAIN - LAIN
1383 Air Bersih Ltr 30.00
1384 Bak Cuci Aluminium Bh 225,500.00
1385 Cangkul Bh 72,600.00
1386 Cangkul Gigi Bh 159,500.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1387 Ember Bh 26,400.00
1388 Gerinding bh 506,000.00
1389 Helm Proyek Bh 80,300.00
1390 Hammer 3 kg Bh 92,950.00
1391 Instalasi Tata Suara Titik 399,300.00
1392 Kapi Bh 8,800.00
1393 Keni 2" Bh 15,950.00
1394 Keranjang Sampah Bh 39,600.00
1395 Linggis bh 79,200.00
1396 Masker Bh 52,800.00
1397 Ompreng Besar (bak Adonan) Bh 485,100.00
1398 Panyong Bh 88,000.00
HARGA
KESEPAKATAN
NO NAMA BAHAN SAT

(RP)
1 2 3 4
1399 Pengelasan cm 14,520.00
1400 Sabit Bh 66,000.00
1401 Sapu lidi Ikat 6,600.00
1402 Sepatu Karet Bh 133,100.00
1403 Sikat baja Bh 33,220.00
1404 Skop Bh 59,950.00
1405 Water mur Bh 35,000.00
1406 Pipa Tremi dan Casing pelindung Ls 121,000.00
1407 Pelumas (olie) Ltr 28,350.00

Apabila dikemudian hari terdapat kekeliruan, akan dilakukan revisi / penyesuaian

Denpasar, 3 Januari 2017


Bidang Penataan Ruang Bidang Penataan Ruang dan Bangkim

I Gede Cipta Sudewa Atmaja, ST., MT. I Ketut Dirga, ST., M.Si.
NIP. 19690426 199803 1 012 NIP. 19670820 199103 1 007

Bidang Air Minum Dan PLP Bidang Sumber Daya Air

I Putu Wisnu Wijaya Kusuma, ST. MT. I Gst. Ngurah Putra Sanjaya, ST.
NIP. 19680314 199703 1 005 NIP. 19660316 199703 1 003

Bidang Bina Marga Bidang Jasa Konstruksi dan Bina Program

I Wayan Dirgayasa, ST. Ir. I Gde Made Bhaju Pravita, MM.


NIP. 19680314 199703 1 005 NIP. 19681114 199803 1 003

Mengetahui,
Kepala Dinas Pekerjaan Umum dan
Penataan Ruang Kota Denpasar

Ir. I Ketut Winarta


Pembina Utama Muda
NIP. 19571231 198803 1 103
DAFTAR HARGA SATUAN UPAH
TAHUN 2017

NO NAMA BARANG SATUAN HARGA (Rp)

1 2 3 4

1 Mandor Hari 125,000.00


2 Kepala Tukang Lapangan Hari 110,000.00
3 Kepala Tukang Besi Hari 110,000.00
4 Kepala Tukang Batu Hari 110,000.00
5 Kepala Tukang Kayu Hari 110,000.00
6 Kepala Tukang Cat Hari 110,000.00
7 Kepala Tukang Paras Bali Hari 165,000.00
8 Kepala Tukang Ukir Hari 185,000.00
9 Tukang Aluminium Hari 100,000.00
10 Tukang Batu Hari 95,000.00
11 Tukang Besi Hari 100,000.00
12 Tukang Kayu Hari 105,000.00
13 Tukang Cat Hari 95,000.00
14 Tukang Politur Hari 95,000.00
15 Tukang Ukir Hari 120,000.00
16 Tukang Paras Bali Hari 165,000.00
17 Pekerja Terlatih Hari 90,000.00
18 Pekerja Semi Terlatih Hari 85,000.00
19 Pekerja / Pekerja Tidak Terlatih Hari 75,000.00
21 Tukang Listrik Hari 90,000.00
22 Tukang Pipa/ Tukang Ledeng Hari 90,000.00
23 Kepala Tukang Pipa/ Tukang Ledeng Hari 100,000.00
24 Tukang Las Hari 100,000.00
25 Tukang Masak Aspal Hari 95,000.00
26 Tukang Cor Aspal Hari 95,000.00
27 Pekerja Pembantu Tukang Aspal Hari 60,000.00
28 Penjaga Api Hari 65,000.00
29 Sopir SIM A Hari 70,000.00
30 Sopir SIM B1 Hari 75,000.00
31 Sopir SIM B2 Hari 80,000.00
32 Operator Hari 100,000.00
33 Operator Semi Terampil Hari 85,000.00
34 Pembantu Operator Hari 80,000.00
NO NAMA BARANG SATUAN HARGA (Rp)

1 2 3 4
35 Pembantu Sopir Hari 60,000.00
36 Mekanik Terampil Hari 95,000.00
37 Masinis Hari 98,000.00
38 Pembantu Masinis Hari 70,000.00
39 Ongkos Kerja Pemasangan dan Pengelasan Hari 30,000.00
40 Ongkos Potong Besi Hari 30,000.00
41 Ongkos Pemasangan Lampu Ls 285,000.00
42 Ongkos Pemasangan Panel Ls 450,000.00
43 Pembantu Mekanik Hari 50,000.00
44 Pasang Atap Alang-Alang Hari 90,000.00
45 Pasang Bata Gosok Dua Muka M2 280,000.00
46 Pasang Bata Gosok Satu Muka M2 150,000.00
47 Pasang Batu Paras Diukir M2 290,000.00
48 Pasang Patu Paras Siap Diukir M2 260,000.00
49 Ongkos Ngebor O 30 cm m' 75,000.00
50 Ongkos Polis Kaca Tempered Tebal 5mm m' 20,000.00
51 Ongkos Polis Kaca Tempered Tebal 6mm m' 20,000.00
52 Ongkos Polis Kaca Tempered Tebal 8mm m' 30,000.00
53 Ongkos Polis Kaca Tempered Tebal 10mm m' 30,000.00
54 Ongkos Polis Kaca Tempered Tebal 12mm m' 35,000.00
55 Ongkos Polis Kaca Tempered Tebal 19mm m' 95,000.00

Denpasar, 3 Januari 2017


Bidang Penataan Ruang Bidang Penataan Ruang dan Bangkim

I Gede Cipta Sudewa Atmaja, ST., MT. I Ketut Dirga, ST., M.Si.
NIP. 19690426 199803 1 012 NIP. 19670820 199103 1 007

Bidang Air Minum Dan PLP Bidang Sumber Daya Air

I Putu Wisnu Wijaya Kusuma, ST. MT. I Gst. Ngurah Putra Sanjaya, ST.
NIP. 19680314 199703 1 005 NIP. 19660316 199703 1 003
Bidang Air Minum Dan PLP Bidang Sumber Daya Air

NO NAMA BARANG SATUAN HARGA (Rp)


I Putu Wisnu Wijaya Kusuma, ST. MT. I Gst. Ngurah Putra Sanjaya, ST.
1 NIP. 19680314 199703 1 005
2 NIP.
3 19660316 1997034 1 003

Bidang Bina Marga Bidang Jasa Konstruksi dan Bina Program

I Wayan Dirgayasa, ST. Ir. I Gde Made Bhaju Pravita, MM.


NIP. 19680314 199703 1 005 NIP. 19681114 199803 1 003

Mengetahui,
Kepala Dinas Pekerjaan Umum dan
Penataan Ruang Kota Denpasar

Ir. I Ketut Winarta


Pembina Utama Muda
NIP. 19571231 198803 1 103
Bidang Penataan Ruang dan Bangkim

I Ketut Dirga, ST., M.Si.


NIP. 19670820 199103 1 007

Bidang Sumber Daya Air

I Gst. Ngurah Putra Sanjaya, ST.


NIP. 19660316 199703 1 003
Bidang Sumber Daya Air

I Gst. Ngurah Putra Sanjaya, ST.


NIP. 19660316 199703 1 003

Bidang Jasa Konstruksi dan Bina Program

Ir. I Gde Made Bhaju Pravita, MM.


NIP. 19681114 199803 1 003
DAFTAR HARGA SEWA ALAT BERAT
TAHUN 2017

NO NAMA BARANG KAPASITAS SATUAN HARGA (Rp)

1 2 3 4 5

1 ASPHALT MIXING PLANT 60 T/Jam Jam 5,046,022.47


2 ASPHALT FINISHER 6 Ton Jam 507,700.00
3 ASPHALT SPRAYER 800 Liter Jam 108,378.92
4 BULLDOZER 100-150 HP - Jam 430,466.00
5 COMPRESSOR 4000-6500 L\M - Jam 167,843.11
6 CONCRETE MIXER 0.3-0.6 M3 500 Liter Jam 83,573.52
7 CRANE 10-15 TON 15 Ton Jam 516,072.38
8 DUMP TRUCK 3-4 M3 6 Ton Jam 248,157.27
9 DUMP TRUCK 8 Ton Jam 388,286.24
10 EXCAVATOR 80-140 HP 0.5 M3 Jam 460,000.00
11 FLAT BED TRUCK 3-4 M3 4 M3 Jam 373,577.89
12 GENERATOR SET 125 KVA Jam 416,800.00
13 MOTOR GRADER >100 HP - - Jam 453,229.95
14 TRACK LOADER 75-100 HP 1.6 M3 Jam 376,324.77
15 WHEEL LOADER 1.0-1.6 M3 1.5 M3 Jam 330,000.00
16 THREE WHEEL ROLLER 6-8 T 8 Ton Jam 259,037.06
17 TANDEM ROLLER 6-8 T. 8 Ton Jam 318,300.00
18 TIRE ROLLER 8-10 T. 10 Ton Jam 292,100.00
19 VIBRATORY ROLLER 5-8 T. 7 Ton Jam 495,000.00
20 CONCRETE VIBRATOR - - Jam 49,291.45
21 STONE CRUSHER 50 T/Jam Jam 734,331.33
22 WATER PUMP 70-100 mm - Jam 45,649.42
23 WATER TANKER 3000-4500 L. 4000 Liter Jam 252,387.09
24 PEDESTRIAN ROLLER 1 Ton Jam 73,338.01
25 TAMPER 0.3 Ton Jam 57,096.01
26 JACK HAMMER - Jam 76,832.84
27 FULVI MIXER - Jam 147,477.18
28 CONCRETE PUMP 8 M3 Jam 307,176.96
29 TRAILER 20 TON 20 Ton Jam 284,292.63
30 PILE DRIVER + HAMMER 2.5 Ton Jam 192,967.43
31 CRANE ON TRACK 35 TON 35 Ton Jam 398,664.11
32 WELDING SET 250 Amp Jam 164,293.99
33 BORE PILE MACHINE 2000 Meter Jam 992,707.11
34 ASPHALT LIQUID MIXER 1000 Liter Jam 84,927.40
35 TRAILLER 15 TON 15 Ton Jam 354,040.00
36 COLD MILLING - Jam 492,443.81
37 ROCK DRILL BREAKER - Jam 58,810.77
38 ALAT STRESSING - Jam 12,500.00
39 ALAT GROUTING - Jam 15,000.00
40 BARO MIXER - Jam 60,000.00
41 BOLE MIXER - Jam 60,000.00
42 PRENATER - Jam 60,000.00
43 ASPHALT CUTER - Jam 61,111.11
44 CONCRETE PAN MIXER 600 Ltr Jam 455,640.00
NO NAMA BARANG KAPASITAS SATUAN HARGA (Rp)

1 2 3 4 5
45 TRUCK MIXER 5 M3 Jam 546,172.06
46 BLENDING EQUIPMENT 30 Ton Jam 191,768.73
47 ASPHALT DISTRIBUTOR 4000 Ltr Jam 347,303.82
48 Crane Tadano 50 Ton Bulan 110,000,000.00
49 Crane Tadano 35 Ton Bulan 95,000,000.00
50 Crane Tadano 30 Ton Bulan 85,000,000.00
51 Crane Tadano 25 Ton Bulan 75,000,000.00
52 Crane Tadano 7.5 Ton Bulan 60,000,000.00
53 Crane Tadano 50 Ton Hari 12,000,000.00
54 Crane Tadano 35 Ton Hari 9,000,000.00
55 Crane Tadano 30 Ton Hari 8,000,000.00
56 Crane Tadano 25 Ton Hari 7,000,000.00
57 Crane Tadano 7.5 Ton Hari 5,000,000.00
58 Excavator PC.200-8 / MO th. 2015 UT (breaker) - Jam 550,000.00
59 Excavator PC.200-8 / MO th. 2015 UT (bucket) - Jam 450,000.00
60 Mobilisasi Excavator PC.200-8 (Denpasar, Kuta, Nusa Dua) - LS 3,500,000.00
61 Excavator PC.78 UU (breaker) - Jam 400,000.00
62 Excavator PC.78 UU (bucket) - Jam 300,000.00
63 Mobilisasi Excavator PC.78 UU (Denpasar, Kuta, Nusa Dua) - LS 1,500,000.00
64 Sewa TC Kap 2,5 Ton Length 60 m/Bulan/ 200 jam - Bulan 110,000,000.00
65 Jaminan Angkur - Set 55,000,000.00
66 Pasang Angkur - Set 5,000,000.00
67 Erexsion - Set 45,000,000.00
68 Dismantling Normal - Set 45,000,000.00
69 Mob-Demob TC - Set 90,000,000.00
70 Sewa Mesin Bor - Jam 50,000.00

Denpasar, 3 Januari 2017


Bidang Penataan Ruang Bidang Penataan Ruang dan Bangkim

I Gede Cipta Sudewa Atmaja, ST., MT. I Ketut Dirga, ST., M.Si.
NIP. 19690426 199803 1 012 NIP. 19670820 199103 1 007

Bidang Air Minum Dan PLP Bidang Sumber Daya Air

I Putu Wisnu Wijaya Kusuma, ST. MT. I Gst. Ngurah Putra Sanjaya, ST.
NIP. 19680314 199703 1 005 NIP. 19660316 199703 1 003

Bidang Bina Marga Bidang Jasa Konstruksi dan Bina Program

I Wayan Dirgayasa, ST. Ir. I Gde Made Bhaju Pravita, MM.


NIP. 19680314 199703 1 005 NIP. 19681114 199803 1 003
Bidang Bina Marga Bidang Jasa Konstruksi dan Bina Program
NO NAMA BARANG KAPASITAS SATUAN HARGA (Rp)

1 2 3 4 5
I Wayan Dirgayasa, ST. Ir. I Gde Made Bhaju Pravita, MM.
NIP. 19680314 199703 1 005 NIP. 19681114 199803 1 003

Mengetahui,
Kepala Dinas Pekerjaan Umum dan Penataan Ruang
Kota Denpasar

Ir. I Ketut Winarta


Pembina Utama Muda
NIP. 19571231 198803 1 103
Bidang Penataan Ruang dan Bangkim

I Ketut Dirga, ST., M.Si.


NIP. 19670820 199103 1 007

Bidang Sumber Daya Air

I Gst. Ngurah Putra Sanjaya, ST.


NIP. 19660316 199703 1 003

Bidang Jasa Konstruksi dan Bina Program

Ir. I Gde Made Bhaju Pravita, MM.


NIP. 19681114 199803 1 003
Bidang Jasa Konstruksi dan Bina Program

Ir. I Gde Made Bhaju Pravita, MM.


NIP. 19681114 199803 1 003
DAFTAR BIAYA LANGSUNG PERSONIL DAN BIAYA TIDAK LANGSUNG PERSONIL
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KOTA DENPASAR TAHUN 2017
BIAYA LANGSUNG PERSONIL

NO BIDANG TAHUN TAHUN 2016 TAHUN 2017


AKADEMIK/KEAHLIAN PENGALAMAN PENDIDIKAN
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA AHLI DENGAN PENDIDIKAN S1
12 S1 14,700,000 14,700,000
11 S1 14,000,000 14,000,000
1 AHLI MADYA 10 S1 13,300,000
13,300,000
9 S1 12,500,000 12,500,000
8 S1 11,800,000 11,800,000
7 S1 11,000,000 11,000,000
2 AHLI MUDA 6 S1 10,700,000 10,700,000
5 S1 9,000,000 9,000,000
4 S1 7,900,000 7,900,000
3 AHLI PRATAMA 3 S1 7,500,000 7,500,000
B SUB PROFESIONAL STAF
ASSISTANT PROFESSIONAL 0-3 S1 4,000,000 4,200,000
1 5 - 10 D3 4,000,000 4,200,000
STAFF
0-3 S1 4,000,000 4,000,000
2 DRAFTER CAD/DRAFTER GIS 5 - 10 D3 4,000,000 4,000,000
0-3 S1 4,000,000 4,000,000
3 LAB. TECHNICIAN 5 - 10 D3 4,000,000 4,000,000
0-3 S1 4,000,000 4,000,000
4 INSPECTOR 5 - 10 D3 4,000,000 4,000,000
0-3 S1 3,500,000 3,500,000
5 SURVEYOR 5 - 10 D3 3,500,000 3,500,000
C TENAGA PENDUKUNG
1 SEKRETARIS 2,057,000 2,200,000
2 TENAGA ADMINISTRASI 2,057,000 2,200,000
3 OPERATOR KOMPUTER 2,057,000 2,200,000
4 SOPIR 2,007,000 2,173,000
5 PEKERJA 2,007,000 2,173,000
6 OFFICE BOY 2,007,000 2,173,000

KETERANGAN
Perhitungan Konversi Minimum Biaya Langsung Personil menurut
- SBOB
- SBOM SBOB/4,1
- SBOH (SBOB/22) x 1,1
- SBOJ (SBOH/8) x 1,3
BIAYA TAK LANGSUNG PERSONIL
SEWA
1 SEWA KENDARAAN RODA EMPAT Rp. 4,550,000 / BULAN
2 SEWA KENDARAAN RODA DUA Rp. 500,000 / BULAN
3 SEWA KOMPUTER DAN PRINTER Rp. 900,000 / BULAN
4 SEWA SCANNER Rp. 400,000 / BULAN
5 SEWA ALAT UKUR DAN GPS,BB Rp. 500,000 / HARI
6 SEWA ALAT BORING (MEKANIS) Rp. 1,250,000 / HARI
7 SEWA ALAT SPT Rp. 400,000 / HARI
8 SEWA ALAT DCP Rp. 375,000 / HARI
9 SEWA TRUK + BEBAN Rp. 3,500,000 / HARI
10 TEST LABORATORIUM Rp. 2,500,000
BIAYA LAPORAN
1 RAB Rp. 75,000 / BUKU
2 GAMBAR Rp. 100,000 / BUKU
3 SPESIFIKASI Rp. 150,000 / BUKU
4 LAPORAN PENDAHULUAN Rp. 100,000 / BUKU
5 LAPORAN ANTARA Rp. 125,000 / BUKU
6 LAPORAN BULANAN Rp. 75,000 / BUKU
7 LAPORAN TRIWULAN Rp. 75,000 / BUKU
8 LAPORAN AKHIR Rp. 150,000 / BUKU
9 LAPORAN TEKNIS/KHUSUS Rp. 300,000 / BUKU
10 DOKUMENTASI Rp. 200,000 / ALBUM
LAINNYA
1 ATK MAKSIMUM Rp. 2,500,000

Denpasar, 3 Januari 2017

Bidang Penataan Ruang Bidang Penataan Ruang dan


Bangkim Bidang Bina Marga

I Gede Cipta Sudewa Atmaja, ST., MT.


NIP. 19690426 199803 1 012 I Ketut Dirga, ST., M.Si.
NIP. 19670820 199103 1 007 I Wayan Dirgayasa, ST.
NIP. 19680314 199703 1 005

Bidang Air Minum Dan PLP Bidang Sumber Daya Air BIdang Jasa Konstruksi dan Bina
Program

I Putu Wisnu Wijaya Kusuma, ST. MT. I Gst. Ngurah Putra Sanjaya, ST. Ir. I Gde Made Bhaju Pravita, MM.
NIP. 19680314 199703 1 005 NIP. 19660316 199703 1 003 NIP. 19681114 199803 1 003

Mengetahui,
Kepala Dinas Pekerjaan Umum dan Penataan Ruang
Kota Denpasar

Ir. I Ketut Winarta


Pembina Utama Muda
NIP. 19571231 198803 1 103