I. UPAH KERJA
1 Pekerja Orang / Hari Rp 75,000.00
2 Tukang Batu / Kayu / Besi / Cat / Listrik Orang / Hari Rp 90,000.00
3 Kepala Tukang Orang / Hari Rp 100,000.00
4 Mandor Orang / Hari Rp 95,000.00
II. BAHAN-BAHAN
1 Batu Kali M³ Rp 155,000.00
2 Kerikil Sungai M³ Rp 200,000.00
3 Pasir Pasang M³ Rp 124,000.00
4 Pasir Urug M³ Rp 124,000.00
5 Sirtu M³ Rp 110,000.00
6 Pasir Beton M³ Rp 124,000.00
7 Batu Bata Bh. Rp 1,100.00
8 Semen / PC Kg Rp 1,450.00
9 Kayu Kelas II M³ Rp 2,500,000.00
10 Kayu Kelas III ( Campuran ) M³ Rp 1,900,000.00
11 Dolken Kayu Ø 8-10 cm –Panjang 4 m Btg Rp 24,000.00
12 Plywood tebal 9 mm Lbr Rp 145,000.00
13 Besi Beton Kg Rp 12,000.00
14 Kawat Beton Kg Rp 25,000.00
15 Minyak Bekisting Ltr Rp 27,500.00
16 Paku Biasa Kg Rp 22,000.00
17 Atap Genteng Metal M2 Rp 60,000.00
18 Nok Genteng Metal Lbr Rp 34,000.00
19 Cat Meni Kayu Kg Rp 31,000.00
20 Cat Kayu Kg Rp 61,500.00
21 Cat Tembok (Ex.Jotun) Kg Rp 85,000.00
22 Cat Besi Kg Rp 65,000.00
23 Plamir Kg Rp 25,500.00
24 Minyak cat Ltr Rp 25,000.00
25 Kertas Pasir Lbr Rp 7,500.00
26 Kuas Cat Bh Rp 18,000.00
27 Smartruss C 75.65 M' Rp 14,000.00
28 Reng R 33-0,45 M' Rp 7,000.00
29 Self Drilling Screw Bh Rp 650.00
30 Rangka Metal Hollow 2x4 M' Rp 12,000.00
31 Rangka Metal Hollow 4x4 M' Rp 15,000.00
32 Besi Hollow 4x4 Galvanis M' Rp 20,000.00
33 Ramset Bh Rp 4,000.00
34 Screw Bremick Bh Rp 550.00
35 Self Drilling Screw dia-6x20mm (truss screw) Bh Rp 650.00
36 Self Drilling Screw dia-4x16mm (Roof Button Screw) Bh Rp 650.00
37 Kawat Diameter 4 mm Kg Rp 16,000.00
38 Gypsum board 120x240 cm, tebal 9mm Lbr Rp 70,000.00
39 Saklar Ganda Bh Rp 33,000.00
HARGA SATUAN UPAH KERJA DAN BAHAN
A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah (1/3 kali dari pekerjaan galian)
A TENAGA
Pekerja 0.250 OH Rp 75,000.00 Rp 18,750.00
Mandor 0.008 OH Rp 95,000.00 Rp 791.67
B BAHAN
C PERALATAN
D Jumlah (A+B+C) Rp 19,541.67
E Overhead & Profit 10.00 % Rp 19,541.67 Rp 1,954.17
F Harga Satuan Pekerjaan (D+E) Rp 21,495.83
A.4.4.1.9. Pemasangan 1m2 Dinding Bata Merah (5x11x22) cm tebal ½ Batu Camp. 1 : 4
A TENAGA
Pekerja 0.300 OH Rp 75,000.00 Rp 22,500.00
Tukang 0.100 OH Rp 90,000.00 Rp 9,000.00
Kepala Tukang 0.010 OH Rp 100,000.00 Rp 1,000.00
Mandor 0.015 OH Rp 95,000.00 Rp 1,425.00
B BAHAN
Bata Merah 70.00 Bh Rp 1,100.00 Rp 77,000.00
Semen Portland 11.500 Kg Rp 1,450.00 Rp 16,675.00
Pasir Pasang 0.043 M3 Rp 124,000.00 Rp 5,332.00
C PERALATAN
D Jumlah (A+B+C) Rp 132,932.00
E Overhead & Profit 10.00 % Rp 132,932.00 Rp 13,293.20
F Harga Satuan Pekerjaan (D+E) Rp 146,225.20
A.A.4.1.1.2. Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K-125), slump (12 ± 2), wc = 0,78
Catatan : Berat isi pasir = 1400 Kg/m3, Berat isi kerikil = 1350 Kg/m3, Buckling factor pasir = 20 %
A TENAGA
Pekerja 1.650 OH Rp 75,000.00 Rp 123,750.00
Tukang 0.275 OH Rp 90,000.00 Rp 24,750.00
Kepala Tukang 0.028 OH Rp 100,000.00 Rp 2,800.00
Mandor 0.083 OH Rp 95,000.00 Rp 7,885.00
B BAHAN
Semen Portland 276.00 Kg Rp 1,450.00 Rp 400,200.00
Pasir Beton 828.00 Kg Rp 88.57 Rp 73,337.14
Kerikil (maks 30 mm) 1012.00 Kg Rp 148.15 Rp 149,925.93
Air 215.00 Ltr Rp 100.00 Rp 21,500.00
C PERALATAN
D Jumlah (A+B+C) Rp 804,148.07
E Overhead & Profit 10.00 % Rp 804,148.07 Rp 80,414.81
F Harga Satuan Pekerjaan (D+E) Rp 884,562.88
A.4.7.1.10. Pengecatan 1 M2 Tembok Baru (1 Lapis Plamuur, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
A TENAGA
Pekerja 0.020 OH Rp 75,000.00 Rp 1,500.00
Tukang 0.063 OH Rp 90,000.00 Rp 5,670.00
Kepala Tukang 0.0063 OH Rp 100,000.00 Rp 630.00
Mandor 0.003 OH Rp 95,000.00 Rp 285.00
B BAHAN
Plamur 0.10 Kg Rp 25,500.00 Rp 2,550.00
Cat dasar (Cat Tembok) 0.10 Kg Rp 85,000.00 Rp 8,500.00
Cat penutup (Cat Tembok) 0.26 Kg Rp 85,000.00 Rp 22,100.00
C PERALATAN
D Jumlah (A+B+C) Rp 41,235.00
E Overhead & Profit 10.00 % Rp 41,235.00 Rp 4,123.50
F Harga Satuan Pekerjaan (D+E) Rp 45,358.50
Pengecatan 1 M2 Langit - langit / Plafond (1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
A TENAGA
Pekerja 0.020 OH Rp 75,000.00 Rp 1,500.00
Tukang 0.063 OH Rp 90,000.00 Rp 5,670.00
Kepala Tukang 0.0063 OH Rp 100,000.00 Rp 630.00
Mandor 0.003 OH Rp 95,000.00 Rp 285.00
B BAHAN
Cat dasar (Cat Tembok) 0.10 Kg Rp 85,000.00 Rp 8,500.00
Cat penutup (Cat Tembok) 0.26 Kg Rp 85,000.00 Rp 22,100.00
C PERALATAN
D Jumlah (A+B+C) Rp 38,685.00
E Overhead & Profit 10.00 % Rp 38,685.00 Rp 3,868.50
F Harga Satuan Pekerjaan (D+E) Rp 42,553.50
Alamat : Jl. Pandanjakaya Gang Asam BTN Harmoni II No. 18
Pengawu, Kec. Tatanga Kota Palu – Sulawesi Tengah
Gmail : digitasi.consultant@gmail.com
DAFTAR ANALISA UPAH DAN BAHAN
SATUAN KERJA : DINAS KESEHATAN KABUPATEN SIGI
PEKERJAAN : PEMBANGUNAN PARKIR PUSKESMAS NOKILALAKI
LOKASI : DESA KAMARORA A KEC. NOKILALAKI KAB. SIGI
TAHUN ANGGARAN : 2017