I. PEKERJAAN PERSIAPAN
A. PEKERJAAN PERSIAPAN Rp 97,260,000.00
II. PEKERJAAN STRUKTUR
A. PEKERJAAN GALIAN DAN URUGAN Rp 112,355,442.00
B. PEKERJAAN BETON Rp 1,289,572,556.00
C. PEKERJAAN BAJA Rp 1,134,916,104.00
III. PEKERJAAN ARSlTEKTUR
A. PEKERJAAN PASANGAN Rp 500,811,840.00
B. PEKERJAAN PENGECATAN DAN FINISHING Rp 206,468,200.00
C. PEKERJAAN PENUTUP ATAP dan TALANG Rp 299,231,800.00
D. PEKERJAAN PINTU & JENDELA Rp 137,000,000.00
E. PEKERJAAN LINGKUNGAN Rp 222,500,000.00
JUMLAH Rp 4,000,115,942.00
PPN 11% Rp 440,012,753.62
JUMLAH Rp 4,440,128,695.62
DIBULATKAN Rp 4,440,128,000.00
TERBILANG : Empat milyar seratus lima belas ribu rupiah
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
I. PEKERJAAN PERSIAPAN
1 Pek. Bongkaran bangunan eksisting 1 ls Rp 20,000,000.00 Rp 20,000,000.00
2 Pek. Cut N Fill 1 ls Rp 45,000,000.00 Rp 45,000,000.00
3 Mobilisasi dan demobilisasi 1 ls Rp 10,000,000.00 Rp 10,000,000.00
4 Pek. Pasangan bowplank 212 m' Rp 105,000.00 Rp 22,260,000.00
B. PEKERJAAN BETON
1 Pek. Pondasi beton setempat 7.17 m3 Rp 3,275,000.00 Rp 23,475,200.00
2 Pek. Kolom pedestal 40/40 5.12 m3 Rp 4,550,000.00 Rp 23,296,000.00
3 Pek. Tiebeam 20/30 11.64 m3 Rp 5,220,000.00 Rp 60,760,800.00
4 Pek Kolom praktis 15/15 4.05 m3 Rp 6,850,000.00 Rp 27,742,500.00
5 Pek. Balok beton 15/20 2.31 m3 Rp 7,525,000.00 Rp 17,382,750.00
6 Pek. Balok lintel 13/13 1.98 m3 Rp 5,220,000.00 Rp 10,321,506.00
7 Pek Plat Lantai Beton tbl. 8cm 84.8 m3 Rp 2,450,000.00 Rp 207,760,000.00
8 Pek. Wiremesh M-8 untuk lantai 1 lapis 6,394.60 kg Rp 19,500.00 Rp 124,694,700.00
9 Pek Plat Lantai Beton tbl. 20cm area bongkar muat 6.4 m3 Rp 2,450,000.00 Rp 15,680,000.00
10 Pek. Wiremesh M-8 untuk lantai 2 lapis area bongkar muat 174.4 kg Rp 19,500.00 Rp 3,400,800.00
11 Pek. Lantai kerja beton bawah pobdasi 2.5 m3 Rp 1,050,000.00 Rp 2,620,800.00
12 Pek Beton Rabat 1 : 3 : 5 (tebal 5 cm) 22 m3 Rp 1,850,000.00 Rp 40,700,000.00
13 Pek. Floor hardenner finish epoxy 1,125.75 m2 Rp 650,000.00 Rp 731,737,500.00
JUMLAH B. Rp 1,289,572,556.00
C. PEKERJAAN BAJA
1 Pek. Pasang Baud angkur M-19 panjang 60cm 128 set Rp 96,000.00 Rp 12,288,000.00
2 Pek. Pasang Baseplate tbl. 15mm 280 kg Rp 33,800.00 Rp 9,464,000.00
3 Pek. Pasang Kolom IWF 300.150 7,480.00 kg Rp 33,800.00 Rp 252,824,000.00
4 Pek. Pasang balok IWF 200.100 2,483.30 kg Rp 33,800.00 Rp 83,935,540.00
5 Pek. Pasang rafter IWF 250.125 7,859.70 kg Rp 33,800.00 Rp 265,657,860.00
6 Pek. Voute IWF 250.125 710 kg Rp 33,800.00 Rp 23,998,000.00
7 Pek. Plat stiff tbl. 15mm 694 kg Rp 33,800.00 Rp 23,457,200.00
8 Pek. Plat stiff tbl. 10mm 359.4 kg Rp 33,800.00 Rp 12,147,720.00
9 Pek. Pasang Gording CNP 125.3,2 11,017.92 kg Rp 33,800.00 Rp 372,405,696.00
10 Pek. Pasang siku dudukan Gording 5.5 158.76 kg Rp 33,800.00 Rp 5,366,088.00
11 Pek. Pasang trekstang Ø 12mm 260 set Rp 65,000.00 Rp 16,900,000.00
12 Pek. Pasang spand mur kait angin Ø 16mm 40 set Rp 360,000.00 Rp 14,400,000.00
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
E. PEKERJAAN LINGKUNGAN
1 Pek. Saluran Uditch 210 m' Rp 750,000.00 Rp 157,500,000.00
2 Pek. Jalan lingkungan 1 ls Rp 45,000,000.00 Rp 45,000,000.00
3 Pek. IPAL 2 unit Rp 10,000,000.00 Rp 20,000,000.00
JUMLAH E. Rp 222,500,000.00
I. PEKERJAAN PERSIAPAN
A. PEKERJAAN PERSIAPAN Rp 97,260,000.00 Rp 63,100,000.00 Rp 34,160,000.00
II. PEKERJAAN STRUKTUR
A. PEKERJAAN GALIAN DAN URUGAN Rp 112,361,760.00 Rp 78,653,232.00 Rp 33,708,528.00
B. PEKERJAAN BETON Rp 1,289,597,400.00 Rp 905,017,330.00 Rp 384,580,070.00
C. PEKERJAAN BAJA Rp 1,134,916,104.00 Rp 882,603,620.00 Rp 252,312,484.00
III. PEKERJAAN ARSlTEKTUR
A. PEKERJAAN PASANGAN Rp 500,811,840.00 Rp 346,670,460.00 Rp 154,141,380.00
B. PEKERJAAN PENGECATAN DAN FINISHING Rp 206,468,200.00 Rp 119,132,800.00 Rp 87,335,400.00
C. PEKERJAAN PENUTUP ATAP dan TALANG Rp 299,231,800.00 Rp 209,462,260.00 Rp 89,769,540.00
D. PEKERJAAN PINTU & JENDELA Rp 137,000,000.00 Rp 95,900,000.00 Rp 41,100,000.00
E. PEKERJAAN LINGKUNGAN Rp 222,500,000.00 Rp 155,750,000.00 Rp 66,750,000.00
TOTAL Rp 1,143,857,402.00
TOTAL Rp 1,269,681,634.60
PROYEK PEMBANGUNAN PABRIK TAHU - CIBUBUR
RENCANA ANGGARAN PELAKSANAAN
RENCANA ANGGARAN BIAYA PROFIT
( RAB )
( RAP )
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH
I. PEKERJAAN PERSIAPAN
1 Pek. Bongkaran bangunan eksisting 1 ls Rp 20,000,000.00 Rp 20,000,000.00 Rp 14,000,000.00 Rp 14,000,000.00 Rp 6,000,000.00 Rp 6,000,000.00
2 Pek. Cut N Fill 1 ls Rp 45,000,000.00 Rp 45,000,000.00 Rp 31,500,000.00 Rp 31,500,000.00 Rp 13,500,000.00 Rp 13,500,000.00
3 Mobilisasi dan demobilisasi 1 ls Rp 10,000,000.00 Rp 10,000,000.00 Rp 7,000,000.00 Rp 7,000,000.00 Rp 3,000,000.00 Rp 3,000,000.00
4 Pek. Pasangan bowplank 212 m' Rp 105,000.00 Rp 22,260,000.00 Rp 50,000.00 Rp 10,600,000.00 Rp 55,000.00 Rp 11,660,000.00
B. PEKERJAAN BETON
1 Pek. Pondasi beton setempat 7.17 m3 Rp 3,275,000.00 Rp 23,481,750.00 Rp 2,292,500.00 Rp 16,437,225.00 Rp 982,500.00 Rp 7,044,525.00
2 Pek. Kolom pedestal 40/40 5.12 m3 Rp 4,550,000.00 Rp 23,296,000.00 Rp 3,185,000.00 Rp 16,307,200.00 Rp 1,365,000.00 Rp 6,988,800.00
3 Pek. Tiebeam 20/30 11.64 m3 Rp 5,220,000.00 Rp 60,760,800.00 Rp 3,654,000.00 Rp 42,532,560.00 Rp 1,566,000.00 Rp 18,228,240.00
4 Pek Kolom praktis 15/15 4.05 m3 Rp 6,850,000.00 Rp 27,742,500.00 Rp 4,795,000.00 Rp 19,419,750.00 Rp 2,055,000.00 Rp 8,322,750.00
5 Pek. Balok beton 15/20 2.31 m3 Rp 7,525,000.00 Rp 17,382,750.00 Rp 5,267,500.00 Rp 12,167,925.00 Rp 2,257,500.00 Rp 5,214,825.00
6 Pek. Balok lintel 13/13 1.98 m3 Rp 5,220,000.00 Rp 10,335,600.00 Rp 3,654,000.00 Rp 7,234,920.00 Rp 1,566,000.00 Rp 3,100,680.00
7 Pek Plat Lantai Beton tbl. 8cm 84.8 m3 Rp 2,450,000.00 Rp 207,760,000.00 Rp 1,715,000.00 Rp 145,432,000.00 Rp 735,000.00 Rp 62,328,000.00
8 Pek. Wiremesh M-8 untuk lantai 1 lapis 6,394.60 kg Rp 19,500.00 Rp 124,694,700.00 Rp 14,000.00 Rp 89,524,400.00 Rp 5,500.00 Rp 35,170,300.00
9 Pek Plat Lantai Beton tbl. 20cm area bongkar muat 6.4 m3 Rp 2,450,000.00 Rp 15,680,000.00 Rp 1,715,000.00 Rp 10,976,000.00 Rp 735,000.00 Rp 4,704,000.00
10 Pek. Wiremesh M-8 untuk lantai 2 lapis area bongkar muat 174.4 kg Rp 19,500.00 Rp 3,400,800.00 Rp 14,000.00 Rp 2,441,600.00 Rp 5,500.00 Rp 959,200.00
11 Pek. Lantai kerja beton bawah pobdasi 2.5 m3 Rp 1,050,000.00 Rp 2,625,000.00 Rp 735,000.00 Rp 1,837,500.00 Rp 315,000.00 Rp 787,500.00
12 Pek Beton Rabat 1 : 3 : 5 (tebal 5 cm) 22 m3 Rp 1,850,000.00 Rp 40,700,000.00 Rp 1,295,000.00 Rp 28,490,000.00 Rp 555,000.00 Rp 12,210,000.00
13 Pek. Floor hardenner finish epoxy 1,125.75 m2 Rp 650,000.00 Rp 731,737,500.00 Rp 455,000.00 Rp 512,216,250.00 Rp 195,000.00 Rp 219,521,250.00
JUMLAH B. Rp 1,289,597,400.00 Rp 905,017,330.00 Rp 384,580,070.00
C. PEKERJAAN BAJA
1 Pek. Pasang Baud angkur M-19 panjang 60cm 128 set Rp 96,000.00 Rp 12,288,000.00 Rp 67,200.00 Rp 8,601,600.00 Rp 28,800.00 Rp 3,686,400.00
2 Pek. Pasang Baseplate tbl. 15mm 280 kg Rp 33,800.00 Rp 9,464,000.00 Rp 26,500.00 Rp 7,420,000.00 Rp 7,300.00 Rp 2,044,000.00
PROYEK PEMBANGUNAN PABRIK TAHU - CIBUBUR
RENCANA ANGGARAN PELAKSANAAN
RENCANA ANGGARAN BIAYA PROFIT
( RAB )
( RAP )
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH
3 Pek. Pasang Kolom IWF 300.150 7,480.00 kg Rp 33,800.00 Rp 252,824,000.00 Rp 26,500.00 Rp 198,220,000.00 Rp 7,300.00 Rp 54,604,000.00
4 Pek. Pasang balok IWF 200.100 2,483.30 kg Rp 33,800.00 Rp 83,935,540.00 Rp 26,500.00 Rp 65,807,450.00 Rp 7,300.00 Rp 18,128,090.00
5 Pek. Pasang rafter IWF 250.125 7,859.70 kg Rp 33,800.00 Rp 265,657,860.00 Rp 26,500.00 Rp 208,282,050.00 Rp 7,300.00 Rp 57,375,810.00
6 Pek. Voute IWF 250.125 710 kg Rp 33,800.00 Rp 23,998,000.00 Rp 26,500.00 Rp 18,815,000.00 Rp 7,300.00 Rp 5,183,000.00
7 Pek. Plat stiff tbl. 15mm 694 kg Rp 33,800.00 Rp 23,457,200.00 Rp 26,500.00 Rp 18,391,000.00 Rp 7,300.00 Rp 5,066,200.00
8 Pek. Plat stiff tbl. 10mm 359.4 kg Rp 33,800.00 Rp 12,147,720.00 Rp 26,500.00 Rp 9,524,100.00 Rp 7,300.00 Rp 2,623,620.00
9 Pek. Pasang Gording CNP 125.3,2 11,017.92 kg Rp 33,800.00 Rp 372,405,696.00 Rp 26,500.00 Rp 291,974,880.00 Rp 7,300.00 Rp 80,430,816.00
10 Pek. Pasang siku dudukan Gording 5.5 158.76 kg Rp 33,800.00 Rp 5,366,088.00 Rp 26,500.00 Rp 4,207,140.00 Rp 7,300.00 Rp 1,158,948.00
11 Pek. Pasang trekstang Ø 12mm 260 set Rp 65,000.00 Rp 16,900,000.00 Rp 45,500.00 Rp 11,830,000.00 Rp 19,500.00 Rp 5,070,000.00
12 Pek. Pasang spand mur kait angin Ø 16mm 40 set Rp 360,000.00 Rp 14,400,000.00 Rp 252,000.00 Rp 10,080,000.00 Rp 108,000.00 Rp 4,320,000.00
13 Pek. Baud HTB M-16 552 bh Rp 37,000.00 Rp 20,424,000.00 Rp 25,900.00 Rp 14,296,800.00 Rp 11,100.00 Rp 6,127,200.00
14 Pek. Baud HTB M-14 144 bh Rp 29,000.00 Rp 4,176,000.00 Rp 20,300.00 Rp 2,923,200.00 Rp 8,700.00 Rp 1,252,800.00
15 Pek. Baud HTB M-12 672 bh Rp 26,000.00 Rp 17,472,000.00 Rp 18,200.00 Rp 12,230,400.00 Rp 7,800.00 Rp 5,241,600.00
JUMLAH C. Rp 1,134,916,104.00 Rp 882,603,620.00 Rp 252,312,484.00
3 Pek. Exhaust fan Industri 8 set Rp 6,250,000.00 Rp 50,000,000.00 Rp 4,375,000.00 Rp 35,000,000.00 Rp 1,875,000.00 Rp 15,000,000.00
JUMLAH D. Rp 137,000,000.00 Rp 95,900,000.00 Rp 41,100,000.00
E. PEKERJAAN LINGKUNGAN
1 Pek. Saluran Uditch 210 m' Rp 750,000.00 Rp 157,500,000.00 Rp 525,000.00 Rp 110,250,000.00 Rp 225,000.00 Rp 47,250,000.00
2 Pek. Jalan lingkungan 1 ls Rp 45,000,000.00 Rp 45,000,000.00 Rp 31,500,000.00 Rp 31,500,000.00 Rp 13,500,000.00 Rp 13,500,000.00
3 Pek. IPAL 2 unit Rp 10,000,000.00 Rp 20,000,000.00 Rp 7,000,000.00 Rp 14,000,000.00 Rp 3,000,000.00 Rp 6,000,000.00
JUMLAH E. Rp 222,500,000.00 Rp 155,750,000.00 Rp 66,750,000.00
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
REKAPITULASI
PROYEK PEMBANGUNAN PABRIK TAHU - CIBUBUR
I. PEKERJAAN PERSIAPAN
A. PEKERJAAN PERSIAPAN Rp 63,100,000.00 Rp 57,490,000.00 Rp 5,610,000.00
II. PEKERJAAN STRUKTUR
A. PEKERJAAN GALIAN DAN URUGAN Rp 78,653,232.00 Rp 66,855,247.20 Rp 11,797,984.80
B. PEKERJAAN BETON Rp 905,017,330.00 Rp 654,532,931.00 Rp 250,484,399.00
C. PEKERJAAN BAJA Rp 882,603,620.00 Rp 838,473,439.00 Rp 44,130,181.00
III. PEKERJAAN ARSlTEKTUR
A. PEKERJAAN PASANGAN Rp 346,670,460.00 Rp 305,554,280.40 Rp 41,116,179.60
B. PEKERJAAN PENGECATAN DAN FINISHING Rp 119,132,800.00 Rp 107,219,520.00 Rp 11,913,280.00
C. PEKERJAAN PENUTUP ATAP dan TALANG Rp 209,462,260.00 Rp 188,516,034.00 Rp 20,946,226.00
D. PEKERJAAN PINTU & JENDELA Rp 95,900,000.00 Rp 81,515,000.00 Rp 14,385,000.00
E. PEKERJAAN LINGKUNGAN Rp 155,750,000.00 Rp 132,387,500.00 Rp 23,362,500.00
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH
I. PEKERJAAN PERSIAPAN
1 Pek. Bongkaran bangunan eksisting 1 ls Rp 14,000,000.00 Rp 14,000,000.00 Rp 12,600,000.00 Rp 12,600,000.00 Rp 1,400,000.00 Rp 1,400,000.00
2 Pek. Cut N Fill 1 ls Rp 31,500,000.00 Rp 31,500,000.00 Rp 28,350,000.00 Rp 28,350,000.00 Rp 3,150,000.00 Rp 3,150,000.00
3 Mobilisasi dan demobilisasi 1 ls Rp 7,000,000.00 Rp 7,000,000.00 Rp 7,000,000.00 Rp 7,000,000.00 Rp - Rp -
4 Pek. Pasangan bowplank 212 m' Rp 50,000.00 Rp 10,600,000.00 Rp 45,000.00 Rp 9,540,000.00 Rp 5,000.00 Rp 1,060,000.00
B. PEKERJAAN BETON
1 Pek. Pondasi beton setempat 7.17 m3 Rp 2,292,500.00 Rp 16,437,225.00 Rp 1,604,750.00 Rp 11,506,057.50 Rp 687,750.00 Rp 4,931,167.50
2 Pek. Kolom pedestal 40/40 5.12 m3 Rp 3,185,000.00 Rp 16,307,200.00 Rp 2,229,500.00 Rp 11,415,040.00 Rp 955,500.00 Rp 4,892,160.00
3 Pek. Tiebeam 20/30 11.64 m3 Rp 3,654,000.00 Rp 42,532,560.00 Rp 2,557,800.00 Rp 29,772,792.00 Rp 1,096,200.00 Rp 12,759,768.00
4 Pek Kolom praktis 15/15 4.05 m3 Rp 4,795,000.00 Rp 19,419,750.00 Rp 3,356,500.00 Rp 13,593,825.00 Rp 1,438,500.00 Rp 5,825,925.00
5 Pek. Balok beton 15/20 2.31 m3 Rp 5,267,500.00 Rp 12,167,925.00 Rp 3,687,250.00 Rp 8,517,547.50 Rp 1,580,250.00 Rp 3,650,377.50
6 Pek. Balok lintel 13/13 1.98 m3 Rp 3,654,000.00 Rp 7,234,920.00 Rp 2,557,800.00 Rp 5,064,444.00 Rp 1,096,200.00 Rp 2,170,476.00
7 Pek Plat Lantai Beton tbl. 8cm 84.8 m3 Rp 1,715,000.00 Rp 145,432,000.00 Rp 1,200,500.00 Rp 101,802,400.00 Rp 514,500.00 Rp 43,629,600.00
8 Pek. Wiremesh M-8 untuk lantai 1 lapis 6,394.60 kg Rp 14,000.00 Rp 89,524,400.00 Rp 13,000.00 Rp 83,129,800.00 Rp 1,000.00 Rp 6,394,600.00
9 Pek Plat Lantai Beton tbl. 20cm area bongkar muat 6.4 m3 Rp 1,715,000.00 Rp 10,976,000.00 Rp 1,200,500.00 Rp 7,683,200.00 Rp 514,500.00 Rp 3,292,800.00
10 Pek. Wiremesh M-8 untuk lantai 2 lapis area bongkar muat 174.4 kg Rp 14,000.00 Rp 2,441,600.00 Rp 13,000.00 Rp 2,267,200.00 Rp 1,000.00 Rp 174,400.00
11 Pek. Lantai kerja beton bawah pobdasi 2.5 m3 Rp 735,000.00 Rp 1,837,500.00 Rp 514,500.00 Rp 1,286,250.00 Rp 220,500.00 Rp 551,250.00
12 Pek Beton Rabat 1 : 3 : 5 (tebal 5 cm) 22 m3 Rp 1,295,000.00 Rp 28,490,000.00 Rp 906,500.00 Rp 19,943,000.00 Rp 388,500.00 Rp 8,547,000.00
13 Pek. Floor hardenner finish epoxy 1,125.75 m2 Rp 455,000.00 Rp 512,216,250.00 Rp 318,500.00 Rp 358,551,375.00 Rp 136,500.00 Rp 153,664,875.00
JUMLAH B. Rp 905,017,330.00 Rp 654,532,931.00 Rp 250,484,399.00
C. PEKERJAAN BAJA
1 Pek. Pasang Baud angkur M-19 panjang 60cm 128 set Rp 67,200.00 Rp 8,601,600.00 Rp 63,840.00 Rp 8,171,520.00 Rp 3,360.00 Rp 430,080.00
2 Pek. Pasang Baseplate tbl. 15mm 280 kg Rp 26,500.00 Rp 7,420,000.00 Rp 25,175.00 Rp 7,049,000.00 Rp 1,325.00 Rp 371,000.00
PROYEK PEMBANGUNAN PABRIK TAHU - CIBUBUR
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH
3 Pek. Pasang Kolom IWF 300.150 7,480.00 kg Rp 26,500.00 Rp 198,220,000.00 Rp 25,175.00 Rp 188,309,000.00 Rp 1,325.00 Rp 9,911,000.00
4 Pek. Pasang balok IWF 200.100 2,483.30 kg Rp 26,500.00 Rp 65,807,450.00 Rp 25,175.00 Rp 62,517,077.50 Rp 1,325.00 Rp 3,290,372.50
5 Pek. Pasang rafter IWF 250.125 7,859.70 kg Rp 26,500.00 Rp 208,282,050.00 Rp 25,175.00 Rp 197,867,947.50 Rp 1,325.00 Rp 10,414,102.50
6 Pek. Voute IWF 250.125 710 kg Rp 26,500.00 Rp 18,815,000.00 Rp 25,175.00 Rp 17,874,250.00 Rp 1,325.00 Rp 940,750.00
7 Pek. Plat stiff tbl. 15mm 694 kg Rp 26,500.00 Rp 18,391,000.00 Rp 25,175.00 Rp 17,471,450.00 Rp 1,325.00 Rp 919,550.00
8 Pek. Plat stiff tbl. 10mm 359.4 kg Rp 26,500.00 Rp 9,524,100.00 Rp 25,175.00 Rp 9,047,895.00 Rp 1,325.00 Rp 476,205.00
9 Pek. Pasang Gording CNP 125.3,2 11,017.92 kg Rp 26,500.00 Rp 291,974,880.00 Rp 25,175.00 Rp 277,376,136.00 Rp 1,325.00 Rp 14,598,744.00
10 Pek. Pasang siku dudukan Gording 5.5 158.76 kg Rp 26,500.00 Rp 4,207,140.00 Rp 25,175.00 Rp 3,996,783.00 Rp 1,325.00 Rp 210,357.00
11 Pek. Pasang trekstang Ø 12mm 260 set Rp 45,500.00 Rp 11,830,000.00 Rp 43,225.00 Rp 11,238,500.00 Rp 2,275.00 Rp 591,500.00
12 Pek. Pasang spand mur kait angin Ø 16mm 40 set Rp 252,000.00 Rp 10,080,000.00 Rp 239,400.00 Rp 9,576,000.00 Rp 12,600.00 Rp 504,000.00
13 Pek. Baud HTB M-16 552 bh Rp 25,900.00 Rp 14,296,800.00 Rp 24,605.00 Rp 13,581,960.00 Rp 1,295.00 Rp 714,840.00
14 Pek. Baud HTB M-14 144 bh Rp 20,300.00 Rp 2,923,200.00 Rp 19,285.00 Rp 2,777,040.00 Rp 1,015.00 Rp 146,160.00
15 Pek. Baud HTB M-12 672 bh Rp 18,200.00 Rp 12,230,400.00 Rp 17,290.00 Rp 11,618,880.00 Rp 910.00 Rp 611,520.00
JUMLAH C. Rp 882,603,620.00 Rp 838,473,439.00 Rp 44,130,181.00
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH HARGA SATUAN JUMLAH
3 Pek. Exhaust fan Industri 8 set Rp 4,375,000.00 Rp 35,000,000.00 Rp 3,718,750.00 Rp 29,750,000.00 Rp 656,250.00 Rp 5,250,000.00
JUMLAH D. Rp 95,900,000.00 Rp 81,515,000.00 Rp 14,385,000.00
E. PEKERJAAN LINGKUNGAN
1 Pek. Saluran Uditch 210 m' Rp 525,000.00 Rp 110,250,000.00 Rp 446,250.00 Rp 93,712,500.00 Rp 78,750.00 Rp 16,537,500.00
2 Pek. Jalan lingkungan 1 ls Rp 31,500,000.00 Rp 31,500,000.00 Rp 26,775,000.00 Rp 26,775,000.00 Rp 4,725,000.00 Rp 4,725,000.00
3 Pek. IPAL 2 unit Rp 7,000,000.00 Rp 14,000,000.00 Rp 5,950,000.00 Rp 11,900,000.00 Rp 1,050,000.00 Rp 2,100,000.00
JUMLAH E. Rp 155,750,000.00 Rp 132,387,500.00 Rp 23,362,500.00
85%
85%
85%
85%
85%
85%
85%
85%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
70%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
95%
90%
85%
90%
90%
90%
90%
90%
90%
90%
90%
85%
85%
85%
85%
85%
85%
REKAPITULASI
PROYEK PEMBANGUNAN PABRIK TAHU - CIBUBUR
I. PEKERJAAN PERSIAPAN
A. PEKERJAAN PERSIAPAN Rp 97,260,000.00 Rp 63,100,000.00 Rp 34,160,000.00 Rp 63,100,000.00 Rp 57,490,000.00 Rp 5,610,000.00 Rp 39,770,000.00
II. PEKERJAAN STRUKTUR
A. PEKERJAAN GALIAN DAN URUGAN Rp 112,361,760.00 Rp 78,653,232.00 Rp 33,708,528.00 Rp 78,653,232.00 Rp 66,855,247.20 Rp 11,797,984.80 Rp 45,506,512.80
B. PEKERJAAN BETON Rp 1,289,597,400.00 Rp 905,017,330.00 Rp 384,580,070.00 Rp 905,017,330.00 Rp 654,532,931.00 Rp 250,484,399.00 Rp 635,064,469.00
C. PEKERJAAN BAJA Rp 1,134,916,104.00 Rp 882,603,620.00 Rp 252,312,484.00 Rp 882,603,620.00 Rp 838,473,439.00 Rp 44,130,181.00 Rp 296,442,665.00
III. PEKERJAAN ARSlTEKTUR
A. PEKERJAAN PASANGAN Rp 500,811,840.00 Rp 346,670,460.00 Rp 154,141,380.00 Rp 346,670,460.00 Rp 305,554,280.40 Rp 41,116,179.60 Rp 195,257,559.60
B. PEKERJAAN PENGECATAN DAN FINISHING Rp 206,468,200.00 Rp 119,132,800.00 Rp 87,335,400.00 Rp 119,132,800.00 Rp 107,219,520.00 Rp 11,913,280.00 Rp 99,248,680.00
C. PEKERJAAN PENUTUP ATAP dan TALANG Rp 299,231,800.00 Rp 209,462,260.00 Rp 89,769,540.00 Rp 209,462,260.00 Rp 188,516,034.00 Rp 20,946,226.00 Rp 110,715,766.00
D. PEKERJAAN PINTU & JENDELA Rp 137,000,000.00 Rp 95,900,000.00 Rp 41,100,000.00 Rp 95,900,000.00 Rp 81,515,000.00 Rp 14,385,000.00 Rp 55,485,000.00
E. PEKERJAAN LINGKUNGAN Rp 222,500,000.00 Rp 155,750,000.00 Rp 66,750,000.00 Rp 155,750,000.00 Rp 132,387,500.00 Rp 23,362,500.00 Rp 90,112,500.00
CATATAN :
PROFIT 1 PROFIT 2 TOTAL KESELURUHAN
NILAI PROFIT KESELURUHAN Rp 400,014,710.40 Rp 423,745,750.40 Rp 823,760,460.80
PROYEK PEMBANGUNAN PABRIK TAHU - CIBUBUR
I. PEKERJAAN PERSIAPAN
1 Pek. Bongkaran bangunan eksisting 1 ls Rp 20,000,000.00 Rp 20,000,000.00 0.50% Rp 14,000,000.00 Rp 14,000,000.00 0.49% Rp 5,000,000.00
2 Pek. Cut N Fill 1 ls Rp 45,000,000.00 Rp 45,000,000.00 1.12% Rp 31,500,000.00 Rp 31,500,000.00 1.10% Rp 31,500,000.00
3 Mobilisasi dan demobilisasi 1 ls Rp 10,000,000.00 Rp 10,000,000.00 0.25% Rp 7,000,000.00 Rp 7,000,000.00 0.25% Rp 7,000,000.00
4 Pek. Pasangan bowplank 212 m' Rp 105,000.00 Rp 22,260,000.00 0.56% Rp 50,000.00 Rp 10,600,000.00 0.37% Rp 50,000.00
B. PEKERJAAN BETON
1 Pek. Pondasi beton setempat 7.17 m3 Rp 3,275,000.00 Rp 23,481,750.00 0.59% Rp 2,292,500.00 Rp 16,437,225.00 0.58% Rp 2,292,500.00
2 Pek. Kolom pedestal 40/40 5.12 m3 Rp 4,550,000.00 Rp 23,296,000.00 0.58% Rp 3,185,000.00 Rp 16,307,200.00 0.57% Rp 3,185,000.00
3 Pek. Tiebeam 20/30 11.64 m3 Rp 5,220,000.00 Rp 60,760,800.00 1.52% Rp 3,654,000.00 Rp 42,532,560.00 1.49% Rp 3,654,000.00
4 Pek Kolom praktis 15/15 4.05 m3 Rp 6,850,000.00 Rp 27,742,500.00 0.69% Rp 4,795,000.00 Rp 19,419,750.00 0.68% Rp 4,795,000.00
5 Pek. Balok beton 15/20 2.31 m3 Rp 7,525,000.00 Rp 17,382,750.00 0.43% Rp 5,267,500.00 Rp 12,167,925.00 0.43% Rp 5,267,500.00
6 Pek. Balok lintel 13/13 1.98 m3 Rp 5,220,000.00 Rp 10,335,600.00 0.26% Rp 3,654,000.00 Rp 7,234,920.00 0.25% Rp 3,654,000.00
7 Pek Plat Lantai Beton tbl. 8cm 84.8 m3 Rp 2,450,000.00 Rp 207,760,000.00 5.19% Rp 1,715,000.00 Rp 145,432,000.00 5.09% Rp 1,715,000.00
8 Pek. Wiremesh M-8 untuk lantai 1 lapis 6,394.60 kg Rp 19,500.00 Rp 124,694,700.00 3.12% Rp 14,000.00 Rp 89,524,400.00 3.13% Rp 14,000.00
9 Pek Plat Lantai Beton tbl. 20cm area bongkar muat 6.4 m3 Rp 2,450,000.00 Rp 15,680,000.00 0.39% Rp 1,715,000.00 Rp 10,976,000.00 0.38% Rp 1,715,000.00
10 Pek. Wiremesh M-8 untuk lantai 2 lapis area bongkar muat 174.4 kg Rp 19,500.00 Rp 3,400,800.00 0.09% Rp 14,000.00 Rp 2,441,600.00 0.09% Rp 14,000.00
11 Pek. Lantai kerja beton bawah pobdasi 2.5 m3 Rp 1,050,000.00 Rp 2,625,000.00 0.07% Rp 735,000.00 Rp 1,837,500.00 0.06% Rp 735,000.00
12 Pek Beton Rabat 1 : 3 : 5 (tebal 5 cm) 22 m3 Rp 1,850,000.00 Rp 40,700,000.00 1.02% Rp 1,295,000.00 Rp 28,490,000.00 1.00% Rp 1,295,000.00
13 Pek. Floor hardenner finish epoxy 1,125.75 m2 Rp 650,000.00 Rp 731,737,500.00 18.29% Rp 455,000.00 Rp 512,216,250.00 17.93% Rp 455,000.00
JUMLAH B. Rp 1,289,597,400.00 32.24% Rp 905,017,330.00 31.69%
C. PEKERJAAN BAJA
PROYEK PEMBANGUNAN PABRIK TAHU - CIBUBUR
1 Pek. Pasang Baud angkur M-19 panjang 60cm 128 set Rp 96,000.00 Rp 12,288,000.00 0.31% Rp 67,200.00 Rp 8,601,600.00 0.30% Rp 67,200.00
2 Pek. Pasang Baseplate tbl. 15mm 280 kg Rp 33,800.00 Rp 9,464,000.00 0.24% Rp 26,500.00 Rp 7,420,000.00 0.26% Rp 26,500.00
3 Pek. Pasang Kolom IWF 300.150 7,480.00 kg Rp 33,800.00 Rp 252,824,000.00 6.32% Rp 26,500.00 Rp 198,220,000.00 6.94% Rp 26,500.00
4 Pek. Pasang balok IWF 200.100 2,483.30 kg Rp 33,800.00 Rp 83,935,540.00 2.10% Rp 26,500.00 Rp 65,807,450.00 2.30% Rp 26,500.00
5 Pek. Pasang rafter IWF 250.125 7,859.70 kg Rp 33,800.00 Rp 265,657,860.00 6.64% Rp 26,500.00 Rp 208,282,050.00 7.29% Rp 26,500.00
6 Pek. Voute IWF 250.125 710 kg Rp 33,800.00 Rp 23,998,000.00 0.60% Rp 26,500.00 Rp 18,815,000.00 0.66% Rp 26,500.00
7 Pek. Plat stiff tbl. 15mm 694 kg Rp 33,800.00 Rp 23,457,200.00 0.59% Rp 26,500.00 Rp 18,391,000.00 0.64% Rp 26,500.00
8 Pek. Plat stiff tbl. 10mm 359.4 kg Rp 33,800.00 Rp 12,147,720.00 0.30% Rp 26,500.00 Rp 9,524,100.00 0.33% Rp 26,500.00
9 Pek. Pasang Gording CNP 125.3,2 11,017.92 kg Rp 33,800.00 Rp 372,405,696.00 9.31% Rp 26,500.00 Rp 291,974,880.00 10.22% Rp 26,500.00
10 Pek. Pasang siku dudukan Gording 5.5 158.76 kg Rp 33,800.00 Rp 5,366,088.00 0.13% Rp 26,500.00 Rp 4,207,140.00 0.15% Rp 26,500.00
11 Pek. Pasang trekstang Ø 12mm 260 set Rp 65,000.00 Rp 16,900,000.00 0.42% Rp 45,500.00 Rp 11,830,000.00 0.41% Rp 45,500.00
12 Pek. Pasang spand mur kait angin Ø 16mm 40 set Rp 360,000.00 Rp 14,400,000.00 0.36% Rp 252,000.00 Rp 10,080,000.00 0.35% Rp 252,000.00
13 Pek. Baud HTB M-16 552 bh Rp 37,000.00 Rp 20,424,000.00 0.51% Rp 25,900.00 Rp 14,296,800.00 0.50% Rp 25,900.00
14 Pek. Baud HTB M-14 144 bh Rp 29,000.00 Rp 4,176,000.00 0.10% Rp 20,300.00 Rp 2,923,200.00 0.10% Rp 20,300.00
15 Pek. Baud HTB M-12 672 bh Rp 26,000.00 Rp 17,472,000.00 0.44% Rp 18,200.00 Rp 12,230,400.00 0.43% Rp 18,200.00
JUMLAH C. Rp 1,134,916,104.00 28.37% Rp 882,603,620.00 30.90%
E. PEKERJAAN LINGKUNGAN
1 Pek. Saluran Uditch 210 m' Rp 750,000.00 Rp 157,500,000.00 3.94% Rp 525,000.00 Rp 110,250,000.00 3.86% Rp 525,000.00
2 Pek. Jalan lingkungan 1 ls Rp 45,000,000.00 Rp 45,000,000.00 1.12% Rp 31,500,000.00 Rp 31,500,000.00 1.10% Rp 31,500,000.00
3 Pek. IPAL 2 unit Rp 10,000,000.00 Rp 20,000,000.00 0.50% Rp 7,000,000.00 Rp 14,000,000.00 0.49% Rp 7,000,000.00
JUMLAH E. Rp 222,500,000.00 5.56% Rp 155,750,000.00 5.45%
TAHAPAN PENGELUARAN
Presentase
%
JUMLAH
Rp 54,100,000.00 1.90%
TAHAPAN PENGELUARAN
Presentase
%
JUMLAH
Rp 1,866,274,182.00
TAHAPAN PENGELUARAN
Presentase
%
JUMLAH
Rp 209,462,260.00 7.36%
Rp 926,915,520.00
Rp 54,100,000.00 1.90%
Rp 1,866,274,182.00 65.55%
Rp 926,915,520.00 32.55%
Rp 2,847,289,702.00 100%
PT. BERKAH KEDELAI MANDIRI
Kampung Kaum, Kel. Cileungsi Kec. Cileungsi
Kabupaten Bogor – Provinsi Jawa Barat 16820
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
I. PEKERJAAN PERSIAPAN
PEKERJAAN PERSIAPAN Rp 62,260,000.00
II. PEKERJAAN STRUKTUR
PEKERJAAN GALIAN DAN URUGAN Rp 112,361,760.00
PEKERJAAN BETON Rp 1,069,649,700.00
PEKERJAAN BAJA Rp 1,024,506,250.00
III. PEKERJAAN ARSlTEKTUR
PEKERJAAN PASANGAN Rp 500,811,840.00
PEKERJAAN PENGECATAN DAN FINISHING Rp 182,845,000.00
PEKERJAAN PENUTUP ATAP dan TALANG Rp 291,758,800.00
PEKERJAAN PINTU & JENDELA Rp 137,000,000.00
PEKERJAAN LINGKUNGAN Rp 222,500,000.00
IV. PEKERJAAN MEKANICAL, ELECTRIKAL & PLUMBING
PEKERJAAN ME PERSIAPAN Rp 207,574,467.64
PEKERJAAN MEP AREA LANDSCAPE Rp 42,170,417.47
PEKERJAAN BANGUNAN UTAMA (AREA RUANG CONTROL INDOOR) Rp 70,340,562.56
PEKERJAAN LOADING AREA Rp 56,286,078.54
PEKERJAAN SEMI OUTDOOR Rp 19,464,788.28
PEKERJAAN OUTDOOR Rp 19,345,736.76
PEKERJAAN BANGUNAN PENUNJANG Rp 103,933,655.83
JUMLAH Rp 4,122,809,057.07
PPN 11% Rp -
JUMLAH Rp 4,122,809,057.07
DIBULATKAN Rp 4,122,809,000.00
TERBILANG : ….................................................................................... rupiah
( …................................................... )
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
1 2 3 4 5 6
I. PEKERJAAN PERSIAPAN
1 Pagar Keliling Dan Gudang 1 ls Rp 20,000,000.00 Rp 20,000,000.00
2 Perapihan Puing Existing 1 ls Rp 10,000,000.00 Rp 10,000,000.00
3 Mobilisasi dan demobilisasi 1 ls Rp 10,000,000.00 Rp 10,000,000.00
4 Pek. Pasangan bowplank 212 m' Rp 105,000.00 Rp 22,260,000.00
B. PEKERJAAN BETON
1 Pek. Pondasi beton setempat 7.17 m3 Rp 3,275,000.00 Rp 23,481,750.00
2 Pek. Kolom pedestal 40/40 5.12 m3 Rp 4,150,000.00 Rp 21,248,000.00
3 Pek. Tiebeam 20/30 11.64 m3 Rp 5,020,000.00 Rp 58,432,800.00
4 Pek Kolom praktis 15/15 4.05 m3 Rp 6,850,000.00 Rp 27,742,500.00
5 Pek. Balok beton 15/20 2.31 m3 Rp 7,525,000.00 Rp 17,382,750.00
6 Pek. Balok lintel 13/13 1.98 m3 Rp 5,220,000.00 Rp 10,335,600.00
7 Pek Plat Lantai Beton tbl. 8cm 84.8 m3 Rp 2,050,000.00 Rp 173,840,000.00
8 Pek. Wiremesh M-8 untuk lantai 1 lapis 6,394.60 kg Rp 17,500.00 Rp 111,905,500.00
9 Pek Plat Lantai Beton tbl. 20cm area bongkar muat 6.4 m3 Rp 2,450,000.00 Rp 15,680,000.00
10 Pek. Wiremesh M-8 untuk lantai 2 lapis area bongkar muat 174.4 kg Rp 19,500.00 Rp 3,400,800.00
11 Pek. Lantai kerja beton bawah pobdasi 2.5 m3 Rp 1,050,000.00 Rp 2,625,000.00
12 Pek Beton Rabat 1 : 3 : 5 (tebal 5 cm) 22 m3 Rp 1,850,000.00 Rp 40,700,000.00
13 Pek. Floor hardenner finish epoxy 1,125.75 m2 Rp 500,000.00 Rp 562,875,000.00
JUMLAH B. Rp 1,069,649,700.00
C. PEKERJAAN BAJA
1 Pek. Pasang Baud angkur M-19 panjang 60cm 128 set Rp 96,000.00 Rp 12,288,000.00
2 Pek. Pasang Baseplate tbl. 15mm 280 kg Rp 31,250.00 Rp 8,750,000.00
3 Pek. Pasang Kolom IWF 300.150 7,480.00 kg Rp 31,250.00 Rp 233,750,000.00
4 Pek. Pasang balok IWF 200.100 2,483.30 kg Rp 31,250.00 Rp 77,603,125.00
5 Pek. Pasang rafter IWF 250.125 7,859.70 kg Rp 31,250.00 Rp 245,615,625.00
6 Pek. Voute IWF 250.125 710 kg Rp 31,250.00 Rp 22,187,500.00
7 Pek. Plat stiff tbl. 15mm 694 kg Rp 31,250.00 Rp 21,687,500.00
8 Pek. Plat stiff tbl. 10mm 359.4 kg Rp 31,250.00 Rp 11,231,250.00
9 Pek. Pasang Gording CNP 125.3,2 10,017.92 kg Rp 31,250.00 Rp 313,060,000.00
10 Pek. Pasang siku dudukan Gording 5.5 158.76 kg Rp 31,250.00 Rp 4,961,250.00
11 Pek. Pasang trekstang Ø 12mm 260 set Rp 65,000.00 Rp 16,900,000.00
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
12 Pek. Pasang spand mur kait angin Ø 16mm 40 set Rp 360,000.00 Rp 14,400,000.00
13 Pek. Baud HTB M-16 552 bh Rp 37,000.00 Rp 20,424,000.00
14 Pek. Baud HTB M-14 144 bh Rp 29,000.00 Rp 4,176,000.00
15 Pek. Baud HTB M-12 672 bh Rp 26,000.00 Rp 17,472,000.00
JUMLAH C. Rp 1,024,506,250.00
E. PEKERJAAN LINGKUNGAN
1 Pek. Saluran Uditch 210 m' Rp 750,000.00 Rp 157,500,000.00
2 Pek. Jalan lingkungan 1 ls Rp 45,000,000.00 Rp 45,000,000.00
3 Pek. IPAL 2 unit Rp 10,000,000.00 Rp 20,000,000.00
JUMLAH E. Rp 222,500,000.00
( …................................................... )
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
Nama Proyek : Pembangunan Pabrik Tahu
Lokasi : Cibubur - Jawa Barat
Pekerjaan : Mechanikal & Electrikal
Tahun Anggaran : 2024
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
A. PEKERJAAN ME PERSIAPAN
a. Pengadaan Sumber Air Bersih
1 Jasa Pengurusan geser meteran dan upgrade kelas PDAM (ke tarif Niaga Kecil 1'') 1.00 Ls Rp 12,500,000.00 Rp 12,500,000.00
Note : (Pengurusan sampai dengan air menyala)
- Biaya penyambungan resmi dari PDAM menjadi tanggungan Owner
2 Sumur bor + pipa casing PVC AW Ø 4", debit minimal 0,5 liter /detik 1.00 Ls Rp 31,667,713.00 Rp 31,667,713.00
- include hasil tes lab. kondisi air layak konsumsi
- include metode analisa penentuan tittik sumur bor yang dikeluarkan oleh lembaga resmi
3 Panel pompa otomatis (Water level control) ex. Omron 61F-G1-AP 1.00 set Rp 3,450,000.00 Rp 3,450,000.00
4 Pelampung dan pipa sambungan PDAM ex. Onda 1.00 unit Rp 1,500,000.00 Rp 1,500,000.00
5 Test & Commissioning 1.00 Ls Rp 5,000,000.00 Rp 5,000,000.00
- Test tekan air bersih kapasitas 4 bar min. 4 jam
- Tes glontor
- Merger
b. Jasa Pengurusan Pasang Baru Listrik PLN ke Cap. 33000 VA 1.00 Ls Rp 92,500,000.00 Rp 92,500,000.00
- Include SLO & NIDI
catatan : untuk biaya penyambungan resmi dari PLN menjadi tanggungan owner
c. Pompa Distribusi
1 Pompa distribusi jet pump untuk ke toilet atas ex. Wasser PW 381-EA (Automatic) 1.00 Ls Rp 9,047,918.00 Rp 9,047,918.00
2 Pompa distribusi jet pump untuk area penunjang ex. Wasser PW 381-EA (Automatic) 1.00 Ls Rp 2,035,781.55 Rp 2,035,781.55
3 Pompa hisap tipe submersible 3" ex. Grundfos SQ3-80 2Pk 1.00 Ls Rp 18,095,836.00 Rp 18,095,836.00
4 Instalasi perpipaan termasuk fitting pipa dan valve untuk pompa 1.00 Ls Rp 1,809,583.60 Rp 1,809,583.60
5 Titik instalasi stopkontak (Kabel NYM 3x2.5 mm + Conduit Pipa 20 mm) ex. Supreme NYM 3x2,5mm + HIC 20mm 2.00 titik Rp 248,817.75 Rp 497,635.49
6 Stop kontak dinding outbow ex. Broco Atlantic IP44 2.00 titik Rp 185,000.00 Rp 370,000.00
d. CCTV Kerja
CCTV (IP Camera merk HIK-Vision Multi view online 5 MP, dengan perangkat NVR, Aksesories dan Type Camera Muti View +
1 6.00 titik Rp 4,850,000.00 Rp 29,100,000.00
instalasi pendukung 4 Titik) Monitor
JUMLAH A. Rp 207,574,467.64
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
Nama Proyek : Pembangunan Pabrik Tahu
Lokasi : Cibubur - Jawa Barat
Pekerjaan : Mechanikal & Electrikal
Tahun Anggaran : 2024
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
JUMLAH B. Rp 42,170,417.47
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
JUMLAH C. Rp 70,340,562.56
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
JUMLAH D. Rp 56,286,078.54
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
1 Titik instalasi lampu (Kabel NYM 2x2.5 mm + Conduit Pipa 20 mm) ex. Eterna NYM 2x2,5mm + HIC 20mm 35.00 titik Rp 248,817.75 Rp 8,708,621.08
2 Titik instalasi stopkontak (Kabel NYM 3x2.5 mm + Conduit Pipa 20 mm) ex. Eterna NYM 3x2,5mm + HIC 20mm 8.00 titik Rp 248,817.75 Rp 1,990,541.96
3 Stop kontak Dinding Outbow untuk Wall fan dan hand drayer ex. Broco Atlantic IP44 8.00 titik Rp 40,715.63 Rp 325,725.05
4 Saklar ganda ex. Panasonic 2x WEJ5531, WEJ78029W 2.00 titik Rp 40,715.63 Rp 81,431.26
5 Armature lampu gantung + lampu LED 30.00 titik Rp 155,400.00 Rp 4,662,000.00
Spesifikasi :
- Lampu LED 14 Watt warm wite ex. Philips 14,5w warm white
- Pipa conduit 20mm + Accessories finish cat hitam doff
6 Downlight outbow LED slim 14 Watt 4'' nyala white armature hitam doff untuk tritisan samping ex. Philips DN027C cooldaylight white 5.00 titik Rp 203,578.16 Rp 1,017,890.78
7 Wall fan 20" c/w Instalasi ex. Sekai WF-FSB50-GS 6.00 unit Rp 412,500.00 Rp 2,475,000.00
8 Hand dryer c/w Instalasi ex. Krisbow Putih 1.00 unit Rp 203,578.16 Rp 203,578.16
JUMLAH E. Rp 19,464,788.28
F. PEKERJAAN OUTDOOR
I. PEKERJAAN INSTALASI LISTRIK
1 Titik instalasi lampu (Kabel NYM 2x2.5 mm + Conduit Pipa 20 mm) ex. Eterna NYM 2x2,5mm + HIC 20mm 4.00 titik Rp 248,817.75 Rp 995,270.98
2 Titik instalasi stopkontak (Kabel NYM 3x2.5 mm + Conduit Pipa 20 mm) ex. Eterna NYM 3x2,5mm + HIC 20mm 4.00 titik Rp 248,817.75 Rp 995,270.98
3 Saklar ganda ex. Panasonic 2x WEJ5531, WEJ78029W 1.00 bh Rp 38,001.26 Rp 38,001.26
4 Stopkontak outbow untuk stage ex. Broco Atlantic IP44 4.00 bh Rp 38,001.26 Rp 152,005.02
5 Lampu gantung cafe (renceng) fitting setiap 100cm
Spesifikasi :
- Kabel lampu renceng include acesoris 88.00 m Rp 31,667.71 Rp 2,786,758.74
- Seling baja 6mm 88.00 m Rp 4,523.96 Rp 398,108.39
- Lampu LED 4 watt kuning LED Classic Edison ST64 4w 88.00 titik Rp 67,859.39 Rp 5,971,625.88
6 Lampu selang LED strip + list U untuk stage ex. Philips 31087 Warmwhite 12.00 m Rp 75,540.00 Rp 906,480.00
7 Lampu selang LED strip + list U untuk dinding stage ex. Philips 31087 Warmwhite 14.00 m Rp 75,540.00 Rp 1,057,560.00
8 Pembuatan sumur resapan Ø100 cm dalam 150 cm untuk area outdoor (4 unit)
Spesifikasi :
- Galian tanah 6.00 m3 Rp 58,811.47 Rp 352,868.80
- Buis beton bertulang untuk resapan Ø100 cm, tinggi 150 cm Mutu beton buis K-300 12.00 bh Rp 452,395.90 Rp 5,428,750.80
Ready Mix K.250 (Tul.Rangkap
- Penutup plat beton bertulang t= 10 cm 0.31 m3 Rp 836,932.42 Rp 263,035.90
Lx=Ly, Ø10-150 mm)
RENCANA ANGGARAN BIAYA (RAB) - PABRIK TAHU - CIBUBUR
Nama Proyek : Pembangunan Pabrik Tahu
Lokasi : Cibubur - Jawa Barat
Pekerjaan : Mechanikal & Electrikal
Tahun Anggaran : 2024
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
JUMLAH F Rp 19,345,736.76
G. PEKERJAAN BANGUNAN PENUNJANG
I. PEKERJAAN INSTALASI LISTRIK
1 Titik instalasi lampu (Kabel NYM 2x2.5 mm + Conduit Pipa 20 mm) ex. Eterna NYM 2x2,5mm + HIC 20mm 27.00 titik Rp 248,817.75 Rp 6,718,079.12
2 Titik instalasi stopkontak (Kabel NYM 3x2.5 mm + Conduit Pipa 20 mm) ex. Eterna NYM 3x2,5mm + HIC 20mm 7.00 titik Rp 248,817.75 Rp 1,741,724.21
3 Stop kontak dinding ruang crew, janitor dan musholah ex. Panasonic WEJP1121-7 7.00 titik Rp 38,001.26 Rp 266,008.79
4 Downlight inbow LED 14 watt 4" nyala white untuk ruang crew, toilet, dan musholah ex. Philips DN027B cooldylight white 11.00 titik Rp 158,338.57 Rp 1,741,724.22
5 Downlight outbow LED slim 14 Watt 4'' nyala warm white armature hitam doff untuk selasar dan janitor ex. Philips DN027C warm white 9.00 titik Rp 203,578.16 Rp 1,832,203.40
6 Downlight outbow LED slim 14 Watt 4'' nyala white armature hitam doff untuk tritisan belakang ex. Philips DN027C cooldaylight white 6.00 titik Rp 203,578.16 Rp 1,221,468.93
7 Kap lampu waterproof + TL LED 1x16 watt nyala white untuk samping penunjang ex. Philips 1.00 titik Rp 323,500.00 Rp 323,500.00
8 Saklar tunggal ex. Panasonic 1x WEJ5541, WEJ78029W 7.00 titik Rp 40,715.63 Rp 285,009.42
9 Saklar ganda ex. Panasonic 2x WEJ5531, WEJ78029W 3.00 titik Rp 38,001.26 Rp 114,003.77
10 Exhaust fan ceiling 10" untuk toilet ex. KDK 25TGQ2 4.00 unit Rp 407,156.31 Rp 1,628,625.24
11 Kipas Wall fan 16" untuk musholah ex. Sekai WFN 1627 1.00 titik Rp 339,296.93 Rp 339,296.93
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
16 Avor lantai stainless steel untuk area outdoor ex. Mitoyo model paten / tidak bisa dibuka 20.00 titik Rp 135,718.77 Rp 2,714,375.40
17 Clean out stainless steel 4'' ex. Onda 4'' 2.00 bh Rp 135,718.77 Rp 271,437.54
18 Kloset duduk c/w Installation & Accessories ex. Toto CW 420 J 2.00 unit Rp 2,940,573.35 Rp 5,881,146.70
19 Jet flush c/w Installation & Accessories ex. Toto THX240NB (putih) 2.00 unit Rp 226,197.95 Rp 452,395.90
20 Kloset jongkok ex. Toto CE 6 2.00 unit Rp 113,098.98 Rp 226,197.95
21 Wastafel type ex. Toto LW 246 J + acesoris lengkap ex. Toto LW 246 J 2.00 unit Rp 1,130,989.75 Rp 2,261,979.50
22 Kran Wastafel ex. Toto A88Z 2.00 bh Rp 135,718.77 Rp 271,437.54
23 Kaca cermin meja wastafel uk.80x95 cm (tepi dibevel 5 cm) 2.00 unit Rp 412,585.06 Rp 825,170.12
Spesifikasi :
- Galian tanah 9.37 m3 Rp 450,000.00 Rp 4,215,150.00
- Pemasangan Septictank BIO STP 1.00 unit Rp 9,047,918.00 Rp 9,047,918.00
- urugan tanah kembali (compact sand) 6.37 m3 Rp 75,000.00 Rp 477,525.00
- Pasangan Rollag Bata 1.92 m2 Rp 226,197.95 Rp 434,300.06
Ready Mix Mutu K.250
- Cor tutup plat beton bertulang tebal 12cm (Tul.Rangkap Lx=Ly, Ø10-150 1.00 Ls Rp 4,580,000.00 Rp 4,580,000.00
mm)
- Tutup bak kontrol : plat besi bordes finish cat hitam 1.00 Ls Rp 2,500,000.00 Rp 2,500,000.00
- Rabatan lantai beton tebal 5 cm 0.28 m3 Rp 678,593.85 Rp 186,952.61
25 Pembuatan sumur resapan Ø150 cm dalam 150 cm untuk septictank (1 unit)
Spesifikasi :
- Galian tanah 3.38 m3 Rp 450,000.00 Rp 1,518,750.00
- Buis beton bertulang untuk resapan Ø150 cm, dalam 150 cm Mutu beton buis K-300 3.00 bh Rp 1,000,000.00 Rp 3,000,000.00
Ready Mix K.250 (Tul.Rangkap
- Penutup plat beton bertulang t= 12 cm 1.00 Ls Rp 2,850,000.00 Rp 2,850,000.00
Lx=Ly, Ø10-150 mm)
JUMLAH G Rp 103,933,655.83
SPESIFIKASI
( SEMUA PRODUCT YANG DIPAKAI ADALAH
NO URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN JUMLAH
KW1 DAN TEBAL PROFIL ADALAH SKET
LAPANGAN)
1 2 3 4 5 6
( …................................................... )