RINCIAN RENCANA ANGGARAN BIAYA

NO NAMA JENIS PEKERJAAN VOLUME SATUAN HARGA SATUAN HARGA PEKERJAAN KETERANGAN
I PEKERJAAN PERSIAPAN Rp 17.727.437,00
1 MEMBERSIHKAN & MERATAKAN TANAH 510,00 M² Rp 15.500,00 Rp 7.905.000,00
2 PASANG BOWPLANK 120,50 M¹ Rp 81.514,00 Rp 9.822.437,00
II PEKERJAAN TANAH Rp 25.910.808,09
1 GALIAN TANAH PONDASI BATU KALI 70,31 M³ Rp 70.750,00 Rp 4.974.432,50
2 GALIAN TANAH PONDASI FOOTPLAT 48,13 M³ Rp 86.850,00 Rp 4.180.264,20
3 URUG KEMBALI GALIAN TANAH 39,48 M³ Rp 17.083,33 Rp 674.461,39
4 URUG TANAH BAWAH LANTAI 163,00 M³ Rp 86.250,00 Rp 14.058.750,00
(MENGGUNAKAN TANAH HASIL GALIAN)
5 URUG PASIR 8,25 M³ Rp 245.200,00 Rp 2.022.900,00
III PEKERJAAN PONDASI Rp 77.238.077,85
1 PEKERJAAN PONDASI FOOTPLAT 1 X 1 1,80 M³ Rp 2.489.065,00 Rp 4.480.317,00
2 PEKERJAAN PONDASI FOOTPLAT 0,8 X 0,8 2,59 M³ Rp 2.517.337,00 Rp 6.524.937,50
3 PEKERJAAN PASANGAN PONDASI BATU 84,39 M³ Rp 745.065,00 Rp 62.876.035,35
KALI 1PC : 8 PP
4 URUG PASIR BAWAH PONDASI 13,69 M³ Rp 245.200,00 Rp 3.356.788,00
IV PEKERJAAN BETON BERTULANG Rp 396.382.185,74
1 SLOOF 20/30 7,29 M³ Rp 3.767.614,33 Rp 27.465.908,49
2 SLOOF 15/20 0,98 M³ Rp 3.733.241,00 Rp 3.662.309,42
3 KOLOM K2 30/30 5,94 M³ Rp 6.341.734,11 Rp 37.669.900,62
4 KOLOM K3 20/30 6,34 M³ Rp 6.415.863,00 Rp 40.650.907,97
5 KOLOM KP 15/15 7,52 M³ Rp 6.428.903,00 Rp 48.313.206,05
6 BALOK BL 15/15 2,01 M³ Rp 5.815.627,00 Rp 11.704.676,29
7 BALOK B1 20/45 6,75 M³ Rp 5.885.980,78 Rp 39.730.370,25
8 BALOK B2 15/30 6,78 M³ Rp 6.618.229,67 Rp 44.891.451,83
9 BALOK BP 15/20 5,84 M³ Rp 5.777.931,00 Rp 33.740.228,07
10 PLAT DAG BETON T12 cm 15,11 M³ Rp 6.069.141,00 Rp 91.728.997,07
11 PLAT DAG BETON T10 cm 2,18 M³ Rp 5.594.901,00 Rp 12.196.884,18
12 RABAT BETON GARASI 10 CM 4,75 M³ Rp 974.178,00 Rp 4.627.345,50
V PEKERJAAN DINDING HEBEL Rp 80.488.260,00
1 PEKERJAAN DINDING BATU BATA 619,20 M² Rp 129.987,50 Rp 80.488.260,00

VI PEKERJAAN PLESTERAN & ACIAN Rp 118.125.712,80


1 PEKERJAAN PLESTERAN , TEBAL 15 MM 1238,40 M² Rp 59.517,00 Rp 73.705.852,80
1PC : 6PS
2 PEKERJAAN ACIAN 1238,40 M² Rp 35.868,75 Rp 44.419.860,00
VII PEKERJAAN CAT & POLITUR Rp 36.646.680,80
1 PEKERJAAN CAT DINDING 1238,40 M² Rp 24.572,00 Rp 30.429.964,80
2 (1 lapis cat dasar, 2 lapis cat penutup)
PEKERJAAN CAT PLAFOND 253,00 M² Rp 24.572,00 Rp 6.216.716,00
VIII PEKERJAAN PINTU JENDELA Rp 66.416.450,00
1 PEKERJAAN PINTU P1 6,18 M² Rp 542.500,00 Rp 3.352.650,00
2 PEKERJAAN PINTU P2 9,90 M² Rp 585.500,00 Rp 5.796.450,00
3 PEKERJAAN PINTU P3 2,74 M² Rp 542.500,00 Rp 1.486.450,00
4 PEKERJAAN PINTU P4 5,28 M² Rp 585.500,00 Rp 3.091.440,00
5 PEKERJAAN PINTU P5 4,32 M² Rp 585.500,00 Rp 2.529.360,00
6 PEKERJAAN PINTU P6 2,40 M² Rp 405.000,00 Rp 972.000,00
7 PEKERJAAN PINTU FG 10,74 M² Rp 577.000,00 Rp 6.196.980,00
8 PEKERJAAN PINTU PG 12,32 M² Rp 577.000,00 Rp 7.108.640,00
9 PEKERJAAN PINTU PL 11,40 M² Rp 577.000,00 Rp 6.577.800,00
10 PEKERJAAN JENDELA J1 2,51 M² Rp 435.000,00 Rp 1.091.850,00
11 PEKERJAAN JENDELA J2 21,12 M² Rp 435.000,00 Rp 9.187.200,00
12 PEKERJAAN JENDELA J3 7,68 M² Rp 435.000,00 Rp 3.340.800,00
13 PEKERJAAN JENDELA J4 7,04 M² Rp 435.000,00 Rp 3.062.400,00
14 PEKERJAAN JENDELA J5 4,10 M² Rp 435.000,00 Rp 1.783.500,00
15 PEKERJAAN JENDELA J6 2,52 M² Rp 435.000,00 Rp 1.096.200,00
16 PEKERJAAN JENDELA J7 1,32 M² Rp 435.000,00 Rp 574.200,00
17 PEKERJAAN JENDELA J8 3,60 M² Rp 435.000,00 Rp 1.566.000,00
18 PEKERJAAN JENDELA J9 3,11 M² Rp 435.000,00 Rp 1.352.850,00
19 PEKERJAAN BOVEN BV1 1,44 M² Rp 450.000,00 Rp 648.000,00
20 PEKERJAAN BOVEN BV2 0,80 M² Rp 435.000,00 Rp 348.000,00
21 PEKERJAAN BOVEN BV3 2,00 M² Rp 435.000,00 Rp 870.000,00
22 PEKERJAAN BOVEN BV4 0,92 M² Rp 435.000,00 Rp 400.200,00
23 PEKERJAAN PINTU PAGAR 10,60 M² Rp 375.800,00 Rp 3.983.480,00
IX PEKERJAAN ATAP & RANGKA ATAP Rp 68.827.527,08
1 PEKERJAAN ATAP GENTENG BETON FLAT 153,25 M² Rp 131.796,00 Rp 20.197.737,00
2 PEKERJAAN RANGKA ATAP BAJA RINGAN 153,25 M² Rp 186.487,64 Rp 28.579.230,08
3 PEK KACA LAMINASI RANGKA BESI HOLLOW 27,00 M² Rp 572.500,00 Rp 15.457.500,00
4 PEKERJAAN LISPLANK (2x20)CM 57 M¹ Rp 80.580,00 Rp 4.593.060,00
X PEKERJAAN PLAFOND / LANGIT - LANGIT Rp 39.235.493,00
1 PLAFOND GYPSUM 253,00 M² Rp 48.891,00 Rp 12.369.423,00
2 RANGKA PLAFOND BESI HOLLOW 253,00 M² Rp 106.190,00 Rp 26.866.070,00
XI PEKERJAAN INSTALASI LISTRIK Rp 44.123.580,00
1 PENYAMBUNGAN PLN 1,00 Bh Rp 3.500.000,00 Rp 3.500.000,00
2 TITIK STOP KONTAK 31,00 Bh Rp 93.350,00 Rp 2.893.850,00
2 LAMPU DOWNLIGHT 57,00 Bh Rp 38.150,00 Rp 2.174.550,00
3 LAMPU SL 10,00 Bh Rp 38.150,00 Rp 381.500,00
4 LAMPU TEMPEL DINDING 4,00 Bh Rp 315.045,00 Rp 1.260.180,00
4 LAMPU HIAS GANTUNG 10,00 Bh Rp 553.650,00 Rp 5.536.500,00
4 LAMPU LED Strip 115,00 M Rp 53.500,00 Rp 6.152.500,00
5 AC SET 4,00 Bh Rp 4.250.000,00 Rp 17.000.000,00
6 Saklar Tunggal 8,00 Bh Rp 86.300,00 Rp 690.400,00
7 Saklar Ganda 17,00 Bh Rp 91.300,00 Rp 1.552.100,00
8 Kabel 12,00 roll Rp 248.500,00 Rp 2.982.000,00
XII PEKERJAAN PENUTUP LANTAI Rp 114.324.440,88
1 PEKERJAAN GRANITE 60×60 POLISHED 218,50 M² Rp 378.936,25 Rp 82.797.570,63
2 PEKERJAAN GRANITE 60×60 UNPOLISHED 49,80 M² Rp 378.936,25 Rp 18.871.025,25
3 PEKERJAAN KERAMIK 30 X 60 UNPOLISHED 16,20 M² Rp 308.725,00 Rp 5.001.345,00
4 LANTAI KAYU PARQUET 21,00 M² Rp 364.500,00 Rp 7.654.500,00
XIII INSTALASI AIR Rp 60.451.081,25
PEKERJAAN INSTALASI AIR BERSIH
1 PEKERJAAN SUMUR AIR BERSIH 12 M¹ Rp 450.000,00 Rp 5.400.000,00
2 PEKERJAAN PASANG POMPA AIR 1 Bh Rp 1.550.000,00 Rp 1.550.000,00
3 PEKERJAAN PASANG PIPA 3/4' TIPE AW 132 M¹ Rp 25.485,00 Rp 3.364.020,00
4 PEKERJAAN PASANG TANDON AIR (SET) 1 Bh Rp 1.850.000,00 Rp 1.850.000,00
5 PEKERJAAN PASANG KRAN AIR 3/4 3 Bh Rp 78.062,50 Rp 234.187,50
6 PEKERAJAAN PASANG ZINK 2 Bh Rp 1.455.000,00 Rp 2.910.000,00
7 PEKERAJAAN PASANG WASTAFEL 3 Bh Rp 1.056.000,00 Rp 3.168.000,00
PEKERJAAN INSTALASI AIR KOTOR
8 PEMBUATAN SEPTICTANK 1 Bh Rp 2.850.000,00 Rp 2.850.000,00
9 PEKERJAAN SUMUR RESAPAN 3 Bh Rp 2.250.000,00 Rp 6.750.000,00
10 PEKERJAAN SUMUR RESAPAN AIR HUJAN 2 Bh Rp 2.050.000,00 Rp 4.100.000,00
11 PEKERJAAN PEMBUATAN BAK LEMAK 1 Bh Rp 1.400.000,00 Rp 1.400.000,00
12 PEKERJAAN PASANG KLOSET DUDUK TOTO 3 Bh Rp 1.680.100,00 Rp 5.040.300,00
13 PEKERJAAN PEMBUATAN SHOWER TOTO 3 Bh Rp 900.110,00 Rp 2.700.330,00
14 PEKERJAAN PASANG FLOOR DRAINE 4 Bh Rp 73.650,00 Rp 294.600,00
15 PEKERJAAN PASANG PIPA 3' TIPE AW 112 Bh Rp 60.957,50 Rp 6.827.240,00
16 PEKERJAAN PASANG PIPA 4' TIPE AW 165,5 M¹ Rp 72.582,50 Rp 12.012.403,75
XIV PEKERJAAN TAMAN Rp 27.400.000,00
1 LANDSCAPE TANAMAN HIJAU 274 M² Rp 100.000,00 Rp 27.400.000,00
REKAPITULASI ANGGARAN BIAYA
NAMA PROYEK : PEMBANGUNAN RUMAH 2 LANTAI
LUAS : 305 M2
LOKASI : Medan, Sumatera Utara
TAHUN : 2023

NO JENIS PEKERJAAN BOBOT (100%) HARGA SATUAN


I PEKERJAAN PERSIAPAN 1,511% Rp 17.727.437,00
II PEKERJAAN TANAH DAN GALIAN 2,208% Rp 25.910.808,09
III PEKERJAAN PONDASI 6,583% Rp 77.238.077,85
IV PEKERJAAN BETON BERTULANG 33,784% Rp 396.382.185,74
V PEKERJAAN DINDING BATA MERAH 6,860% Rp 80.488.260,00
VI PEKERJAAN PLESTERAN & ACIAN 10,068% Rp 118.125.712,80
VII PEKERJAAN CAT DAN POLITUR 3,123% Rp 36.646.680,80
VIII PEKERJAAN PINTU JENDELA 5,661% Rp 66.416.450,00
IX PEKERJAAN ATAP & RANGKA ATAP 5,866% Rp 68.827.527,08
X PEKERJAAN PLAFOND / LANGIT - LANGIT 3,344% Rp 39.235.493,00
XI PEKERJAAN INSTALASI LISTRIK 3,761% Rp 44.123.580,00
XII PEKERJAAN KERAMIK LANTAI 9,744% Rp 114.324.440,88
XIII PEKERJAAN INSTALASI AIR 5,152% Rp 60.451.081,25
XIV PEKERJAAN TAMAN DAN HALAMAN 2,335% Rp 27.400.000,00
TOTAL 100,000% Rp 1.173.297.734

Satu Milyar Seratus Tujuh Puluh Tiga


Juta Dua Ratus Sembilan Puluh Tujuh
TERBILANG =
Ribu Tujuh Ratus Tiga Puluh Empat
Rupiah

HARGA PER 1 M² = 1.173.297.734 / 305 Rp 3.846.877,82