TAMBAHAN C-29
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5
IV PEKERJAAN PLESTERAN
1 Plesteran Biasa ( 0.5:0.5 : 10 ) 224.35 M² Rp 48,000.00 Rp 10,768,896
2 Benangan Sudut 20 M Rp 27,500.00 Rp 550,000
SUB TOTAL Rp 11,318,896
VI PEKERJAAN PLAFON
1 Pasang Rangka Plafond 17.96 M² Rp 98,000.00 Rp 1,760,080
2 Pasang Plafond Gypsum 17.96 M² Rp 105,000.00 Rp 1,885,800
3 Pasang Listplank 20cm 6.00 M Rp 45,000.00 Rp 270,000
SUB TOTAL Rp 3,915,880