Anda di halaman 1dari 2

NOMOR HARGA SATUAN

NO URAIAN PEKERJAAN SAT VOLUME TOTAL HARGA


ANALISA (RP)
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pasang Bouwplank m1 184,0 1.4 Rp 29.350,00 Rp 5.400.400,00
SUBTOTAL (I) PEKERJAAN PESIAPAN Rp 5.400.400,00
II PEKERJAAN TANAH DAN PASIR
1 Galian tanah pondasi m3 91,0 2.1 Rp 39.750,00 Rp 3.617.250,00
2 Mengurug kembali galian pondasi m3 30,0 2.9 Rp 13.220,00 Rp 396.600,00
3 Urugan pasir bawah pondasi m3 12,0 2.11 Rp 117.900,00 Rp 1.414.800,00
4 Urugan tanah peninggian lantai disiram m3 57,0 2.15 Rp 91.550,00 Rp 5.218.350,00
5 Pemadatan tanah m3 57,0 2.10 Rp 29.500,0 Rp 1.681.500,00
SUBTOTAL (II) PEKERJAAN TANAH DAN PASIR Rp 12.328.500,00
III PEKERJAAN PASANGAN
1 Pasangan batu kosong m3 24,0 3.1 Rp 298.600,00 Rp 7.166.400,00
2 Pasangan pondasi batu 1 pc : 5 ps m3 37,0 3.7 Rp 518.140,00 Rp 19.171.180,00
3 Pasangan dinding 1/2 bata 1 pc : 5 ps m2 385,0 4.12 Rp 87.684,00 Rp 33.758.340,00
4 Pasangan dinding 1/2 bata 1 pc : 3 ps m2 40,0 4.10 Rp 93.231,00 Rp 3.729.240,00
SUB TOTAL (III) PEKERJAAN PASANGAN Rp 63.825.160,00
IV PEKEJAAN BETON
1 Sloop 13/20 m3 3,3 7.38 Rp 3.547.293,57 Rp 11.706.068,78
3 Balok 13/20 m3 1,2 7.55 Rp 4.468.325,79 Rp 5.361.990,95
4 Kolom praktis 10/10 m3 0,4 7.45 Rp 6.936.237,76 Rp 2.774.495,10
5 Kolom struktur 15/15 (selasar) m3 1,0 7.44 Rp 4.793.455,69 Rp 4.793.455,69
6 Balok ring, geuvel 10/15 m3 4,0 7.59 Rp 6.918.469,95 Rp 27.673.879,80
SUB TOTAL (IV) PEKERJAAN BETON Rp 52.309.890,32
V PEKERJAAN PLESTERAN DAN LANTAI
1 Pek. Lantai keramik 40x40 m2 180,0 13.2 Rp 144.564,00 Rp 26.021.520,00
2 Plesteran m2 713,0 5.8 Rp 42.271,00 Rp 30.139.223,00
3 Acian plesteran m2 713,0 5.32 Rp 23.425,00 Rp 16.702.025,00
SUB TOTAL (V) PEKERJAAN PLESTERAN DAN LANTAI Rp 72.862.768,00
VI PEKERJAAN KAYU DAN ALUMINIUM
1 Listplank kayu klas II m' 152,0 6.40 Rp 61.750,00 Rp 9.386.000,00
2 Kusen kayu klas II m3 2,1 6.2 Rp 6.103.562,50 Rp 13.061.623,75
3 Daun jendela kaca m2 21,0 6.10 Rp 332.100,00 Rp 6.974.100,00
4 Daun pintu panil m2 6,5 6.6 Rp 466.640,00 Rp 3.033.160,00
5 Pek. Ventilasi krepyek m2 23,0 6.18 Rp 268.450,00 Rp 6.174.350,00
6 Kaca polos 3 mm m2 41,0 12.7 Rp 138.667,50 Rp 5.685.367,50
SUB TOTAL (VI) PEKERJAAN KAYU DAN ALUMINIUM Rp 44.314.601,25
VII PEKERJAAN ATAP / PLAFOND
1 Pek. Rangka baja ringan m2 468,0 LS Rp 225.000,00 Rp 105.300.000,00
2 Atap genteng pejaten lokal m2 517,0 8.4 Rp 61.835,00 Rp 31.968.695,00
3 Bubungan genteng pejaten m' 40,0 8.5 Rp 37.280,00 Rp 1.491.200,00
4 Plafond calsiboard 3,5 mm rangka kayu m2 400,0 9.21 Rp 80.620,00 Rp 32.248.000,00
SUB TOTAL (VII) PEKERJAAN ATAP / PLAFOND Rp 171.007.895,00
VIII PEKERJAAN BESI
1 Kunci pintu 2 slang besar bh 4,0 12.1 Rp 161.070,00 Rp 644.280,00
2 Engsel pintu bh 12,0 12.4 Rp 39.722,50 Rp 476.670,00
3 Engsel jendela bh 88,0 12.5 Rp 23.200,00 Rp 2.041.600,00
5 Grendel kecil bh 88,0 12.6 Rp 21.545,00 Rp 1.895.960,00
SUB TOTAL (VIII) PEKEJAAN BESI Rp 5.058.510,00
IX PEKERJAAN INSTALASI LISTRIK
1 Titik lampu + instalasi bh 16,0 16.1 Rp 173.500,00 Rp 2.776.000,00
2 Lampu SL 18 watt bh 16,0 16.6 Rp 39.900,00 Rp 638.400,00
4 Saklar tunggal bh 8,0 16.3 Rp 55.000,00 Rp 440.000,00
5 Stop kontak bh 4,0 16.2 Rp 56.000,00 Rp 224.000,00
SUB TOTAL (IX) PEKERJAAN INSTALASI LISTRIK Rp 4.078.400,00
X PEKERJAAN PENGECATAN
1 Cat tembok m2 578,0 14.14 Rp 20.644,00 Rp 11.932.232,00
2 Cat plapond m2 438,0 14.14 Rp 20.644,00 Rp 9.042.072,00
3 Cat kayu m2 155,0 14.8 Rp 27.950,00 Rp 4.332.250,00
SUB TOTAL (X) PEKERJAAN PENGECATAN Rp 25.306.554,00
SUB TOTAL Rp 456.492.678,57
DIBULATKAN Rp 456.492.000,00

Anda mungkin juga menyukai