Anda di halaman 1dari 32

REKAPITULASI ANGGARAN

SATUAN KERJA : BAGIAN ADMINISTRASI PEMERINTAHAN UMUM SETDA KAB. KONAWE UTARA
PEKERJAAN : PEMBANGUNAN TAPAL BATAS KECAMATAN ASERA DAN OHEO
LOKASI : KAB. KONAWE UTARA
TAHUN ANGGARAN : 2012

NO URAIAN PEKERJAAN JUMLAH HARGA

A PEKERJAAN PENDAHULUAN Rp 5,673,000.00


B PEKERJAAN TANAH DAN PASIR Rp 469,324.80
C PEKERJAAN BETON Rp 62,551,550.75
D PEKERJAAN PLESTERAN Rp 2,669,629.92
E PEKERJAAN PENGECATAN DAN PAS. HURUF & LOGO Rp 13,189,282.92
F PEKERJAAN PAGAR STAENLESS STEEL Rp 26,554,643.76
G PEKERJAAN LAIN-LAIN Rp 500,000.00

REAL COST Rp 111,607,432.15


IMB 2 % x REAL COST Rp 2,232,148.64
PPN 10 % x REAL COST Rp 11,160,743.22
TOTAL COST Rp 125,000,324.01
DIBULATKAN Rp 125,000,000.00

Terbilang :
( Seratus Dua Puluh Lima Juta Rupiah )

Wanggudu, April 2012


Disetujui Oleh : Dibuat Oleh,-
PEJABAT PEMBUAT KOMITMEN (PPK) : Konsultan Perencana :
BAGIAN ADMINISTRASI PEMERINTAHAN UMUM CV. FATNA ARISINDO
SETDA KAB. KONAWE UTARA

SAMSUL M, S.STP, M.Si MUHAMMAD ROFIQ, ST


NIP. 19780709199810 1 003 Diektur
RENCANA ANGGARAN BIAYA ( RAB )
SATUAN KERJA : BAGIAN ADMINISTRASI PEMERINTAHAN UMUM SETDA KAB. KONAWE UTARA
PEKERJAAN : PEMBANGUNAN TAPAL BATAS KECAMATAN ASERA DAN OHEO
LOKASI : KAB. KONAWE UTARA
TAHUN ANGGARAN : 2012

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6 ( 3 x 5)
A PEKERJAAN PENDAHULUAN
1 Bangsal Kerja 1.00 Ls 2,250,000.00 Rp 2,250,000.00
2 Pengukuran & Pemasangan Bowplank 12.50 M1 45,840.00 Rp 573,000.00
3 Penyediaan Air Kerja 1.00 LS 750,000.00 Rp 750,000.00
4 Pembuatan Laporan & Dokumentasi 1.00 LS 1,500,000.00 Rp 1,500,000.00
5 Penyediaan P3K 1.00 LS 250,000.00 Rp 250,000.00
6 Papan Nama Proyek 1.00 LS 350,000.00 Rp 350,000.00
JUMLAH Rp 5,673,000.00
B PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi Poor plat 10.08 M3 Rp 29,456.00 Rp 296,916.48
2 Pek. Urugan kembali bekas Galian tanah 7.56 M3 Rp 10,752.00 Rp 81,285.12
3 Pek. Urugan pasir alas Pondasi Poer plat 0.67 M3 Rp 135,600.00 Rp 91,123.20
JUMLAH Rp 469,324.80
C PEKERJAAN BETON
1 Pek. Pond.Poor Plat + Steak Kolom 1 Pc : 2 Psr : 3 Krl 2.88 M3 Rp 5,177,950.00 Rp 14,912,496.00
2 Pek. Kolom 50/100 cm camp. 1 Pc : 2 Psr : 3 Krl 6.00 M3 Rp 6,206,050.00 Rp 37,236,300.00
3 Pek. Sirip Beton t. 10 cm camp. 1 Pc : 2 Psr : 3 Krl 0.60 M3 Rp 4,772,120.00 Rp 2,863,272.00
4 Pek. Lantai Kerja 1 Pc : 2 Psr : 3 Krl 0.67 M3 Rp 822,800.00 Rp 551,276.00
5 Pek. Profil Beton 46.60 Ls Rp 120,000.00 Rp 5,592,000.00
6 Pek. Nat / Tali Air Jarak 4cm 16.46 Ls Rp 84,850.00 Rp 1,396,206.75
JUMLAH Rp 62,551,550.75
D PEKERJAAN PLESTERAN
1 Pek. Plesteran Kolom & Plat Beton camp. 1 Pc : 3 Psr 47.22 M2 Rp 37,132.00 Rp 1,753,373.04
2 Pek. Acian Pasta PC semua Plesteran 47.22 M2 Rp 19,404.00 Rp 916,256.88
JUMLAH Rp 2,669,629.92
E PEKERJAAN PENGECATAN DAN PAS. HURUF & LOGO
1 Pengecatan Kolom & Plat Beton 3 x sapu 47.22 M2 Rp 25,186.00 Rp 1,189,282.92
2 Pek. Pemasangan Huruf 2 (dua) nama Kecamatan 2.00 Set Rp 4,600,000.00 Rp 9,200,000.00
3 Pek. Pemasangan Logo Prov. SULTRA & Kab. KONUT 4.00 Bh Rp 700,000.00 Rp 2,800,000.00
JUMLAH Rp 13,189,282.92
F PEKERJAAN PAGAR STAENLESS STEEL
1 Pek. Pas. Staenless steel dia 2" & 1" 15.92 M1 Rp 1,352,075.00 Rp 21,525,034.00
2 Pek. Galian Tanah Pondasi Batu Gunung 2.52 M3 Rp 29,456.00 Rp 74,229.12
3 Pek. Urugan pasir alas Pondasi Batu Gunung 0.32 M3 Rp 135,600.00 Rp 43,392.00
4 Pek. Pas. Batu Kosong 0.95 M3 Rp 310,620.00 Rp 295,089.00
5 Pek. Pondasi Batu Gunung 3.78 M3 Rp 687,820.00 Rp 2,599,959.60
6 Pek. Sloef Beton 0.38 M3 Rp 4,277,950.00 Rp 1,625,621.00
7 Pek. Urugan kembali bekas Galian tanah 0.63 M3 Rp 10,752.00 Rp 6,773.76
8 Pek. Rabat Beton 1 Pc : 2 Psr : 3 Krl 0.24 M3 Rp 822,500.00 Rp 197,400.00
9 Pek. Plesteran Beton & Pondasi camp. 1 Pc : 3 Psr 5.04 M2 Rp 37,132.00 Rp 187,145.28
JUMLAH Rp 26,554,643.76
G PEKERJAAN LAIN-LAIN
1 Pekerjaan Pembersihan Akhir 1.00 LS Rp 500,000.00 Rp 500,000.00
JUMLAH Rp 500,000.00

Wanggudu, April 2012


Disetujui Oleh : Dibuat Oleh,-
PEJABAT PEMBUAT KOMITMEN (PPK) : Konsultan Perencana :
BAGIAN ADMINISTRASI PEMERINTAHAN UMUM CV. FATNA ARISINDO
SETDA KAB. KONAWE UTARA

SAMSUL M, S.STP, M.Si MUHAMMAD ROFIQ, ST


NIP. 19780709199810 1 003 Diektur
ANALISA HARGA SATUAN PEKERJAAN

SATUAN KERJA : BAGIAN ADMINISTRASI PEMERINTAHAN UMUM SETDA KAB. KONAWE UTARA
PEKERJAAN : PEMBANGUNAN TAPAL BATAS KECAMATAN ASERA DAN OHEO
LOKASI : KAB. KONAWE UTARA
TAHUN ANGGARAN : 2012

1 Anl 1 M' PENGUKURAN DAN PASANGAN BOWPLANK


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 65,000.00 0.1000 6,500.00
2 Kepala Tukang Org/Hari 70,000.00 0.0100 700.00
3 Pekerja Org/Hari 50,000.00 0.1000 5,000.00
4 Mandor Org/Hari 60,000.00 0.0050 300.00
Jumlah 12,500.00
B BAHAN
1 Kayu 5/7 M3 2,100,000.00 0.0120 25,200.00
2 Paku biasa 2" - 5" Kg 22,000.00 0.0200 440.00
3 Kayu papan 3/20 M3 1,100,000.00 0.0070 7,700.00
Jumlah 33,340.00
Harga Satuan A + B 45,840.00

2 Anl 1 M2 PEMBUATAN BARAK KERJA


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 65,000.00 0.4900 31,850.00
2 Kepala Tukang Org/Hari 70,000.00 0.0500 3,500.00
3 Pekerja Org/Hari 50,000.00 0.2500 12,500.00
4 Mandor Org/Hari 60,000.00 0.0100 600.00
Jumlah 48,450.00
B BAHAN
1 Kayu Klas II Papan M3 1,300,000.00 1.2000 1,560,000.00
2 Kayu Klas II Balok M3 1,300,000.00 1.2000 1,560,000.00
3 Paku campuran Kg 22,000.00 1.2000 26,400.00
4 Seng Gelombang Lbr 6,000.00 1.2000 7,200.00
5 Tripleks tebal 3 mm Lbr 48,000.00 1.2000 57,600.00
Jumlah 3,211,200.00
Harga Satuan A + B 3,259,650.00

3 Anl 1 m2 Membersihkan lapangan dan peralatan/ Land Clearing ( Dengan Alat )


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 50,000.00 0.010 500.00
2 Mandor Org/Hari 60,000.00 0.005 300.00
Jumlah 800.00
B BAHAN
1 Buldozer M3 318,732.96 0.0070 2,223.16
2 Excavator M3 347,535.36 0.0070 2,424.06
3 Dump Truck Kg 171,896.96 0.0139 2,385.07
Jumlah 7,032.29
Harga Satuan A + B 7,832.29
4 Anl 1 M3 PEK. GALIAN TANAH
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 50,000.00 0.5260 26,300.00
2 Mandor Org/Hari 60,000.00 0.0526 3,156.00
Jumlah 29,456.00
B BAHAN
Jumlah
Harga Satuan A + B 29,456.00

5 Anl 1 M3 PEK. URUGAN KEMBALI


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 50,000.00 0.1920 9,600.00
2 Mandor Org/Hari 60,000.00 0.0192 1,152.00
Jumlah 10,752.00

Jumlah
Harga Satuan A 10,752.00

6 Anl 1 M3 PEK. URUGAN TANAH


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 50,000.00 0.3000 15,000.00
2 Mandor Org/Hari 60,000.00 0.0100 600.00
Jumlah 15,600.00
B BAHAN
1 Tanah Urug M3 80,000.00 1.2000 96,000.00
Jumlah 96,000.00
Harga Satuan A + B 111,600.00

7 Anl 1 M3 PEK. URUGAN PASIR


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 50,000.00 0.3000 15,000.00
2 Mandor Org/Hari 60,000.00 0.0100 600.00
Jumlah 15,600.00
B BAHAN
1 Pasir Urug M3 100,000.00 1.2000 120,000.00
Jumlah 120,000.00
Harga Satuan A + B 135,600.00

8 Anl 1 M2 PEK. PLESTER 1 PC: 3 PSR, TEBAL 15 MM


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 65,000.00 0.1500 9,750.00
2 Kepala Tukang Org/Hari 70,000.00 0.0150 1,050.00
3 Pekerja Org/Hari 50,000.00 0.2000 10,000.00
4 Mandor Org/Hari 60,000.00 0.0100 600.00
Jumlah 21,400.00
B BAHAN
1 Semen Kg 1,900.00 6.4800 12,312.00
2 Pasir Pasang M3 180,000.00 0.0190 3,420.00
Jumlah 15,732.00
Harga Satuan A + B 37,132.00

9 Anl 1 M2 PEK. PLESTERAN 1 PC : 5 PSR TEBAL 15 MM


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 65,000.00 0.1500 9,750.00
2 Kepala Tukang Org/Hari 70,000.00 0.0150 1,050.00
3 Pekerja Org/Hari 50,000.00 0.2000 10,000.00
4 Mandor Org/Hari 60,000.00 0.0100 600.00
Jumlah 21,400.00
B BAHAN
1 Semen Kg 1,900.00 4.3200 8,208.00
2 Pasir Pasang M3 180,000.00 0.0220 3,960.00
Jumlah 12,168.00
Harga Satuan A + B 33,568.00

10 1 M3 MEMBUAT KOLOM BETON BERTULANG (200 Kg BESI + BEKISTING)


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang batu Org/Hari 65,000.00 0.3500 22,750.00
2 Tukang kayu Org/Hari 65,000.00 3.3000 214,500.00
3 Tukang besi Org/Hari 65,000.00 2.1000 136,500.00
4 Kepala tukang Org/Hari 70,000.00 0.5700 39,900.00
5 Pekerja Org/Hari 50,000.00 7.3000 365,000.00
6 Mandor Org/Hari 60,000.00 0.2500 15,000.00
Jumlah 793,650.00
B BAHAN
1 Paku campur Kg 22,000.00 4.0000 88,000.00
2 Minyak bekisting Ltr 12,000.00 2.0000 24,000.00
3 Besi Beton Kg 18,000.00 200.0000 3,600,000.00
4 Kawat beton Kg 20,000.00 4.5000 90,000.00
5 Semen Portland Kg 1,900.00 323.0000 613,700.00
6 Pasir beton M3 165,000.00 0.5200 85,800.00
7 Batu Pecah/Suplit M3 250,000.00 0.7800 195,000.00
8 Balok kayu M3 1,100,000.00 0.1500 165,000.00
9 Papan bekisting M3 1,100,000.00 0.3190 350,900.00
10 Dolken dia 10 cm/4 m Btg 10,000.00 20.0000 200,000.00
Jumlah 5,412,400.00
Harga Satuan A + B 6,206,050.00

11 1 M3 MEMBUAT BALOK BETON BERTULANG (150 Kg BESI + BEKISTING)


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang batu Org/Hari 65,000.00 0.3500 22,750.00
2 Tukang kayu Org/Hari 65,000.00 2.8000 182,000.00
3 Tukang besi Org/Hari 65,000.00 1.4000 91,000.00
4 Kepala tukang Org/Hari 70,000.00 0.4550 31,850.00
5 Pekerja Org/Hari 50,000.00 5.9600 298,000.00
6 Mandor Org/Hari 60,000.00 0.2080 12,480.00
Jumlah 638,080.00
B BAHAN
1 Paku campur Kg 22,000.00 3.2000 70,400.00
2 Minyak bekisting Ltr 12,000.00 1.6000 19,200.00
3 Besi Beton Kg 18,000.00 150.0000 2,700,000.00
4 Kawat beton Kg 20,000.00 3.0000 60,000.00
5 Semen Portland Kg 1,900.00 323.0000 613,700.00
6 Pasir beton M3 165,000.00 0.5200 85,800.00
7 Batu Pecah/Suplit M3 250,000.00 0.7800 195,000.00
8 Balok kayu M3 1,100,000.00 0.1400 154,000.00
9 Papan bekisting M3 1,100,000.00 0.3350 368,500.00
10 Dolken dia 10 cm/4 m Btg 10,000.00 16.0000 160,000.00
Jumlah 4,426,600.00
Harga Satuan A + B 5,064,680.00

12 1 M3 MEMBUAT PLAT BETON BERTULANG (150 Kg BESI + BEKISTING)


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang batu Org/Hari 65,000.00 0.3500 22,750.00
2 Tukang kayu Org/Hari 65,000.00 2.3000 149,500.00
3 Tukang besi Org/Hari 65,000.00 1.4000 91,000.00
4 Kepala tukang Org/Hari 70,000.00 0.4050 28,350.00
5 Pekerja Org/Hari 50,000.00 5.6000 280,000.00
6 Mandor Org/Hari 60,000.00 0.2020 12,120.00
Jumlah 583,720.00
B BAHAN
1 Paku campur Kg 22,000.00 3.0000 66,000.00
2 Minyak bekisting Ltr 12,000.00 1.2000 14,400.00
3 Besi Beton Kg 18,000.00 150.0000 2,700,000.00
4 Kawat beton Kg 20,000.00 3.0000 60,000.00
5 Semen Portland Kg 1,900.00 323.0000 613,700.00
6 Pasir beton M3 165,000.00 0.5200 85,800.00
7 Batu Pecah/Suplit M3 250,000.00 0.7800 195,000.00
8 Balok kayu M3 1,100,000.00 0.1050 115,500.00
9 Papan bekisting M3 1,100,000.00 0.1800 198,000.00
10 Dolken dia 10 cm/4 m Btg 10,000.00 14.0000 140,000.00
Jumlah 4,188,400.00
Harga Satuan A + B 4,772,120.00

13 1 M3 MEMBUAT PONDASI BETON BERTULANG (200 Kg BESI + BEKISTING)


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang batu Org/Hari 65,000.00 0.3500 22,750.00
2 Tukang kayu Org/Hari 65,000.00 1.0400 67,600.00
3 Tukang besi Org/Hari 65,000.00 1.0500 68,250.00
4 Kepala tukang Org/Hari 70,000.00 0.2450 17,150.00
5 Pekerja Org/Hari 50,000.00 3.9000 195,000.00
6 Mandor Org/Hari 60,000.00 0.1650 9,900.00
Jumlah 380,650.00
B BAHAN
1 Paku biasa 2 - 5 inc. Kg 22,000.00 1.5000 33,000.00
2 Minyak bekisting Ltr 12,000.00 0.4000 4,800.00
3 Besi Beton Kg 18,000.00 200.0000 3,600,000.00
4 Kawat beton Kg 20,000.00 2.2500 45,000.00
5 Semen Portland Kg 1,900.00 323.0000 613,700.00
6 Pasir beton M3 165,000.00 0.5200 85,800.00
7 Batu Pecah/Suplit M3 250,000.00 0.7800 195,000.00
8 Balok Kayu M3 1,100,000.00 0.2000 220,000.00
Jumlah 4,797,300.00
Harga Satuan A + B 5,177,950.00
14 Anl. 1 M2 PEKERJAAN ACIAN TEMBOK 1 PC : 8 KAPUR
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Cat Hari/Org 65,000.00 0.0500 3,250.00
2 Kepala Tukang Hari/Org 70,000.00 0.0050 350.00
3 Pekerja Hari/Org 50,000.00 0.0600 3,000.00
Jumlah 6,600.00
B BAHAN
1 Semen Kg 1,900.00 4.0000 7,600.00
2 Kapur Tonasa Kg 10,200.00 0.0200 204.00
3 Amplas Lbr 10,000.00 0.5000 5,000.00
Jumlah 12,804.00
Harga Satuan A + B 19,404.00

15 Anl 1 M2 PEK. CAT TEMBOK (1 x PLAMIR, 1 X CAT DASAR, 2 X CAT PENUTUP)


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Cat Org/Hari 65,000.00 0.0630 4,095.00
2 Kepala Tukang Org/Hari 70,000.00 0.0063 441.00
3 Pekerja Org/Hari 50,000.00 0.0200 1,000.00
4 Mandor Org/Hari 60,000.00 0.0025 150.00
Jumlah 5,686.00

B BAHAN
1 Plamir Kg 15,000.00 0.1000 1,500.00
2 Cat dasar Kg 50,000.00 0.1000 5,000.00
3 Cat tembok/penutup 2 X Kg 50,000.00 0.2600 13,000.00
Jumlah 19,500.00
Harga Satuan A + B 25,186.00

16 Anl. 1 M1 PEKERJAAN STAINLESS STEEL


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Besi Org/Hari 65,000.00 0.5500 35,750.00 ###
2 Pekerja Org/Hari 50,000.00 1.0000 50,000.00 ###
3 Kepala tukang Org/Hari 70,000.00 0.0550 3,850.00 ###
4 Mandor Org/Hari 60,000.00 0.0500 3,000.00 ###
Jumlah 92,600.00

B BAHAN
1 Pipa Steanless steal Dia 2" M1 160,000.00 4.8000 768,000.00
2 Pipa Steanless steal Dia 1" M1 80,000.00 4.2000 336,000.00 ###
3 Besi Plat T = 5 mm Kg 14,750.00 0.5000 7,375.00
4 Cat Kg 50,000.00 1.5000 75,000.00
5 Dynabolt dia. 12 mm / Fishe Bh 6,600.00 3.5000 23,100.00
6 Fabrikasi & Erection Ls 50,000.00 1.0000 50,000.00
Jumlah 1,259,475.00
Harga Satuan A + B 1,352,075.00
27 Anl 1 KG PASANG PLAT BESI HURUF
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Besi Org/Hari 65,000.00 0.0600 3,900.00
2 Kepala Tukang Org/Hari 70,000.00 0.0060 420.00
3 Pekerja Org/Hari 50,000.00 0.6000 30,000.00
4 Mandor Org/Hari 60,000.00 0.3000 18,000.00
Jumlah 52,320.00
B BAHAN
1 Besi plat Kg 14,750.00 1.1000 16,225.00
2 Meni Besi Kg 70,000.00 0.0800 5,600.00
Jumlah 21,825.00
Harga Satuan A + B 74,145.00

28 1 M3 Membuat Beton Tumbuk, 1 Pc : 2 Ps : 3 Split


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Portland Semen KG 1,900.00 218.000 414,200.00
2 Pasir Beton M3 165,000.00 0.5200 85,800.00
3 Split / Kerikil M3 250,000.00 0.8700 217,500.00
Jumlah 717,500.00
B BAHAN
1 Pekerja OH 50,000.00 1.6500 82,500.00
2 Tukang OH 65,000.00 0.2500 16,250.00
3 Kepala Tukang OH 70,000.00 0.0250 1,750.00
4 Mandor OH 60,000.00 0.0800 4,800.00
Jumlah 105,300.00
Harga Satuan A + B 822,800.00

29 Anl 1M3 PONDASI BATU BELAH 1 : 5


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Org/Hari 65,000.00 0.7500 48,750.00
2 Kepala Tukang Org/Hari 70,000.00 0.0750 5,250.00
3 Pekerja Org/Hari 50,000.00 1.5000 75,000.00
4 Mandor Org/Hari 60,000.00 0.0750 4,500.00
Jumlah 133,500.00
B BAHAN
1 Batu Belah 15cm/20cm m3 165,000.00 1.2000 198,000.00
2 Portland Cement Kg 1,900.00 136.0000 258,400.00
3 Pasir Pasang m3 180,000.00 0.5440 97,920.00
Jumlah 554,320.00
Harga Satuan A + B 687,820.00

30 Anl 1M3 BATU KOSONG


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Org/Hari 65,000.00 0.3900 25,350.00
2 Kepala Tukang Org/Hari 70,000.00 0.0390 2,730.00
3 Pekerja Org/Hari 50,000.00 0.7800 39,000.00
4 Mandor Org/Hari 60,000.00 0.0390 2,340.00
Jumlah 69,420.00
B BAHAN
1 Batu Belah 15cm/20cm m3 165,000.00 1.2000 198,000.00
2 Pasir Urug m3 100,000.00 0.4320 43,200.00
Jumlah 241,200.00
Harga Satuan A + B 310,620.00
31 1 M3 MEMBUAT SLOOF BETON BERTULANG (150 Kg BESI + BEKISTING)
No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang batu Org/Hari 65,000.00 0.3500 22,750.00
2 Tukang kayu Org/Hari 65,000.00 1.0400 67,600.00
3 Tukang besi Org/Hari 65,000.00 1.0500 68,250.00
4 Kepala tukang Org/Hari 70,000.00 0.2450 17,150.00
5 Pekerja Org/Hari 50,000.00 3.9000 195,000.00
6 Mandor Org/Hari 60,000.00 0.1650 9,900.00
Jumlah 380,650.00
B BAHAN
1 Paku biasa 2 - 5 inc. Kg 22,000.00 1.5000 33,000.00
2 Minyak bekisting Ltr 12,000.00 0.4000 4,800.00
3 Besi Beton Kg 18,000.00 150.0000 2,700,000.00
4 Kawat beton Kg 20,000.00 2.2500 45,000.00
5 Semen Portland Kg 1,900.00 323.0000 613,700.00
6 Pasir beton M3 165,000.00 0.5200 85,800.00
7 Batu Pecah/Suplit M3 250,000.00 0.7800 195,000.00
8 Balok Kayu M3 1,100,000.00 0.2000 220,000.00
Jumlah 3,897,300.00
Harga Satuan A + B 4,277,950.00

32 Anl 1M3 RABAT BETON 1 : 2 : 3


No. Uraian Satuan Harga Kwantitas Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Org/Hari 65,000.00 0.2500 16,250.00
2 Kepala Tukang Org/Hari 70,000.00 0.0250 1,750.00
3 Pekerja Org/Hari 50,000.00 1.6500 82,500.00
4 Mandor Org/Hari 60,000.00 0.0750 4,500.00
Jumlah 105,000.00
B BAHAN
1 Kerikil m3 250,000.00 0.8700 217,500.00
2 Portland Cement Kg 1,900.00 218.0000 414,200.00
3 Pasir Pasang m3 165,000.00 0.5200 85,800.00
Jumlah 717,500.00
Harga Satuan A + B 822,500.00

Wanggudu, April 2012


Disetujui Oleh : Dibuat Oleh,-
PEJABAT PEMBUAT KOMITMEN (PPK) : Konsultan Perencana :
BAGIAN ADMINISTRASI PEMERINTAHAN UMUM CV. FATNA ARISINDO
SETDA KAB. KONAWE UTARA

SAMSUL M, S.STP, M.Si MUHAMMAD ROFIQ, ST


NIP. 19780709199810 1 003 Diektur
DAFTAR HARGA BAHAN DAN UPAH KERJA
SATUAN KERJA : BAGIAN ADMINISTRASI PEMERINTAHAN UMUM SETDA KAB. KONAWE UTARA
PEKERJAAN : PEMBANGUNAN TAPAL BATAS KECAMATAN ASERA DAN OHEO
LOKASI : KAB. KONAWE UTARA
TAHUN ANGGARAN : 2012

HARGA
NO. URAIAN JENIS TENAGA / BAHAN SATUAN
(Rp.)
1 2 3 4

A. UPAH KERJA
1 Mandor OH Rp 60,000.00
2 Kepala tukang OH Rp 70,000.00
3 Tukang Listrik OH Rp 65,000.00
4 Tukang kayu OH Rp 65,000.00
5 Tukang batu OH Rp 65,000.00
6 Tukang besi OH Rp 65,000.00
7 Tukang Cat OH Rp 65,000.00
8 Tukang Gypsum OH Rp 65,000.00
9 Pekerja OH Rp 50,000.00

B. BAHAN DASAR
1 Tanah urug M3 Rp 80,000.00
2 Pasir urug M3 Rp 100,000.00
3 Pasir pasangan M3 Rp 180,000.00
4 Pasir beton M3 Rp 165,000.00
5 Batu belah gunung M3 Rp 165,000.00
6 Koral beton/Split M3 Rp 250,000.00
7 Buis beton dia 20 m panjang 1 meter M1 Rp 54,000.00
8 Semen Portland Kg Rp 1,900.00
9 Semen warna Kg Rp 2,500.00
10 Semen putih Kg Rp 2,500.00
11 Oli ( Pelumas ) Ltr Rp 25,000.00
12 Bahan Bakar solar Ltr Rp 8,000.00
13 Profil Beton m1 Rp 120,000.00
14 Nat / Tali Air Jarak 4cm M2 Rp 84,850.00

D. BAHAN KAYU
1 Dolken kayu dia 10 / 400 Cm Btg. Rp 10,000.00
2 Papan kayu Kls. I Bayam / jati M3 Rp 4,000,000.00
3 Balok kayu Kls. I Bayam / jati M3 Rp 4,000,000.00
4 Papan kayu Kls. II kalapi M3 Rp 2,100,000.00
5 Balok kayu Kls. II kalapi M3 Rp 2,100,000.00
6 Papan kayu Kls. III M3 Rp 1,300,000.00
7 Balok kayu Kls. III M3 Rp 1,300,000.00
8 Papan/balok kayu meranti kelas III (bekisting) M3 Rp 1,100,000.00
G. BAHAN BESI
1 Kawat beton Kg Rp 20,000.00
2 Besi Beton polos Kg Rp 18,000.00
3 Paku biasa 2"-5" Kg Rp 22,000.00
4 Paku sekrup Dos Rp 28,000.00
5 Besi strip Kg Rp 28,600.00
6 Steanless stell Dia 2" M1 Rp 160,000.00
7 Steanless stell Dia 4" M1 Rp 300,000.00
8 Steanless stell Dia 1" M1 Rp 80,000.00
9 Besi Plat Kg Rp 14,750.00
10 Dynabolt dia. 12 mm / Fisher Bh Rp 6,600.00
11 Huruf Stanless stell Kuningan T. 16 cm Set Rp 4,600,000.00
12 Logo Fiberglass Bh Rp 700,000.00

H BAHAN CAT
1 Plamur tembok boyo 23 Kg. Kg. Rp 15,000.00
2 Cat dasar tembok Kg. Rp 50,000.00
3 Cat penutup tembok (anti lumut) Kg. Rp 50,000.00
4 Minyak cat Ltr Rp 37,500.00
5 Kalsium Kg. Rp 6,000.00
6 Soda api Kg Rp 6,000.00
7 Kuas biasa 3 cm Bh. Rp 10,000.00
8 Kuas biasa 4" Bh. Rp 15,000.00
9 Kuas Roll Bh. Rp 25,000.00
10 Ampelas halus Lbr Rp 10,000.00
11 Ampelas kasar Lbr Rp 6,000.00
12 Minyak bekisting Ltr Rp 12,000.00
13 Cat Besi Kg Rp 50,000.00
14 Meni Besi Kg Rp 70,000.00
15 Kapur Tonasa Kg Rp 10,200.00

Wanggudu, April 2012


Disetujui Oleh : Dibuat Oleh,-
PEJABAT PEMBUAT KOMITMEN (PPK) : Konsultan Perencana :
BAGIAN ADMINISTRASI PEMERINTAHAN UMUM CV. FATNA ARISINDO
SETDA KAB. KONAWE UTARA

SAMSUL M, S.STP, M.Si MUHAMMAD ROFIQ, ST


NIP. 19780709199810 1 003 Diektur
BUAT KWITANSI : => INDONESIA
Number.: 009
Sudah Terima Uang Dari :
Sudah Terima Uang Dari :

Terbilang
Terbilang/To say
Terbilang
Terbilang/To say LIMA RATUS TIGA PULUH EMPAT RIBU TIGA RATUS ENAM PULUH EMPAT RUP

UNTUK PEMBAYARAN DOKUMEN PREQULIFICATION

Nominal
Nominal Rp. 534,364.000

Number.: 009
Sudah Terima Uang Dari :
Sudah Terima Uang Dari :

Terbilang
Terbilang/To say
Terbilang
Terbilang/To say LIMA RATUS TIGA PULUH EMPAT RIBU TIGA RATUS ENAM PULUH EMPAT RUP

UNTUK PEMBAYARAN DOKUMEN PREQULIFICATION

Nominal
U$D. 534,364.000
Nominal

Number.: 009
Sudah Terima Uang Dari :
Sudah Terima Uang Dari :

Terbilang
Terbilang/To say
Terbilang
Terbilang/To say LIMA RATUS TIGA PULUH EMPAT RIBU TIGA RATUS ENAM PULUH EMPAT RUP

UNTUK PEMBAYARAN DOKUMEN PREQULIFICATION

Nominal
U$D. 534,364.000
Nominal
No AMOUNTH
001 125,000,000.000
002 Err:540
003 Err:540
004 Err:540
005 Err:540
006 Err:540
007
008
009
ISI KATA > INDONESIA atau FOREIGN

KWITANSI PEMBAYARAN/RECIVING OF PEYMENT


PATAR HUTAJULUK

EMPAT RIBU TIGA RATUS ENAM PULUH EMPAT RUPIAH

PREQULIFICATION Yang Menerima


PT PLN PIKITRING SULAWESI
Makassar, 2-Dec-2023

SATTUANG SE.

KWITANSI PEMBAYARAN/RECIVING OF PEYMENT


PATAR HUTAJULUK

EMPAT RIBU TIGA RATUS ENAM PULUH EMPAT RUPIAH

PREQULIFICATION Yang Menerima


PT PLN PIKITRING SULAWESI
Makassar, 2-Dec-2023

SATTUANG SE.

KWITANSI PEMBAYARAN/RECIVING OF PEYMENT


PATAR HUTAJULUK

EMPAT RIBU TIGA RATUS ENAM PULUH EMPAT RUPIAH

PREQULIFICATION Yang Menerima


PT PLN PIKITRING SULAWESI
Makassar, 2-Dec-2023

SATTUANG SE.
TO SAYED
( Seratus Dua Puluh Lima Juta Rupiah )
Err:540
Err:540
Err:540
Err:540
Err:540
Err:540
Err:540
Err:540
KWITANSI No. 1 ( ( Seratus Dua Puluh Lima Juta Rupiah )
125,000,000.000
125000000 0
125000000.000 0 0 0
0 MILYAR

KWITANSI No. 2 ( Err:540


Err:540 ### ### Err:540 Err:540
Err:540 ### Err:540
Err:540 ### ### Err:540 Err:540 Err:540
Err:540 Err:540 Err:540 MILYAR

KWITANSI No. 3 ( Err:540


Err:540 ### ### Err:540 Err:540
Err:540 ### Err:540
Err:540 ### ### Err:540 Err:540 Err:540
Err:540 Err:540 Err:540 MILYAR

KWITANSI No. 4 ( Err:540


Err:540 ### ### Err:540 Err:540
Err:540 ### Err:540
Err:540 ### ### Err:540 Err:540 Err:540
Err:540 Err:540 Err:540 MILYAR
KWITANSI No. 5 ( Err:540
Err:540 ### ### Err:540 Err:540
Err:540 ### Err:540
Err:540 ### ### Err:540 Err:540 Err:540
Err:540 Err:540 Err:540 MILYAR
KWITANSI No. 6 ( Err:540
Err:540 ### ### Err:540 Err:540
Err:540 ### Err:540
Err:540 ### ### Err:540 Err:540 Err:540
Err:540 Err:540 Err:540 MILYAR
KWITANSI No. 1 ( Err:540
Err:540 ### ### Err:540 Err:540
Err:540 ### Err:540
Err:540 ### ### Err:540 Err:540 Err:540
Err:540 Err:540 Err:540 MILYAR
KWITANSI No. 1 ( ( Rupiah )
0.000
0 0
0.000 0 0 0
0 MILYAR
KWITANSI No. 1 ( (
0.000
0 0
125 1 2 5 Seratus Dua Puluh Lima Juta
125000000.000 0
1 2 5 Seratus Dua Puluh
BILLION AND 8 Juta Juta

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
BILLION AND ### Err:540 Juta

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
BILLION AND ### Err:540 Juta

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
BILLION AND ### Err:540 Juta

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
BILLION AND ### Err:540 Juta

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
BILLION AND ### Err:540 Juta

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
BILLION AND ### Err:540 Juta

0.000 0
0 0 0
BILLION AND 0 Juta

0
000 0 0 0
000000.000 0
Lima 0 0 0
MILLION AND 0 Ribu

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
MILLION AND ### Err:540 Ribu

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
MILLION AND ### Err:540 Ribu

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
MILLION AND ### Err:540 Ribu

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
MILLION AND ### Err:540 Ribu

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
MILLION AND ### Err:540 Ribu

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
MILLION AND ### Err:540 Ribu

0.000 0
0 0 0
MILLION AND 0 Ribu

0
000 0 0 0
000.000 0
0 0 0
THOUSAND AND

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
THOUSAND AND

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
THOUSAND AND

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
THOUSAND AND

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
THOUSAND AND

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
THOUSAND AND

Err:540 ### ### ### Err:540


Err:540 ### ###
Err:540 ### ### ### Err:540 Err:540
THOUSAND AND

0 0
0.000 0
0 0 0
THOUSAND AND

0
000 0 0 0
0
0 0 0
0 0

Err:540 ### ### ### Err:540


### ###
Err:540 ### ### ### Err:540 Err:540 Err:540
Err:540 ###

Err:540 ### ### ### Err:540


### ###
Err:540 ### ### ### Err:540 Err:540 Err:540
Err:540 ###

Err:540 ### ### ### Err:540


### ###
Err:540 ### ### ### Err:540 Err:540 Err:540
Err:540 ###

Err:540 ### ### ### Err:540


### ###
Err:540 ### ### ### Err:540 Err:540 Err:540
Err:540 ###

Err:540 ### ### ### Err:540


### ###
Err:540 ### ### ### Err:540 Err:540 Err:540
Err:540 ###

Err:540 ### ### ### Err:540


### ###
Err:540 ### ### ### Err:540 Err:540 Err:540
Err:540 ###

000 0 0 0
0
0 0 0
0 0

0
SATUAN
ANGKA
1
2
3
4
5
6
7
8
9

PULUHAN
ANGKA
1
2
3
4
5
6
7
8
9

BELASAN
ANGKA
10
11
12
13
14
15
16
17
18
19

Koma KOMMA
Rupiah Rupiah ) DOLAR
RATUSAN
ANGKA
1
2
### Koma KOMMA 3
Rupiah Rupiah ) DOLAR 4
5
6
7
8
### Koma KOMMA 9
Rupiah Rupiah ) DOLAR

### Koma KOMMA


Rupiah Rupiah ) DOLAR

### Koma KOMMA


Rupiah Rupiah ) DOLAR

### Koma KOMMA


Rupiah Rupiah ) DOLAR

### Koma KOMMA


Rupiah Rupiah ) DOLAR

Koma KOMMA
Rupiah Rupiah ) DOLAR
Satu Satu ONE
Dua Dua TWO
Tiga Tiga THREE
Empat Empat FOUR
Lima Lima FIVE
Enam Enam SIX
Tujuh Tujuh SEVEN
Delapan Delapan EIGHT
Sembilan Sembilan NINE

Sepuluh Sepuluh TEN


Dua Puluh Dua Puluh TWENTY
Tiga Puluh Tiga Puluh THIRTY
Empat Puluh Empat Puluh FOURTY
Lima Puluh Lima Puluh FIVETY
Enam Puluh Enam Puluh SIXTY
Tujuh Puluh Tujuh Puluh SEVENTY
Delapan Puluh Delapan Puluh EIGHTY
Sembilan Puluh Sembilan Puluh NINETY

Sepuluh Sepuluh TEN


Sebelas Sebelas ELEVEN
Dua Belas Dua Belas TWELVE
Tiga Belas Tiga Belas THIRTEEN
Empat Belas Empat Belas FOURTEEN
Lima Belas Lima Belas FIVETEEN
Enam Belas Enam Belas SIXTEEN
Tujuh Belas Tujuh Belas SEVENTEEN
Delapan Belas Delapan Belas EIGHTEEN
Sembilan Belas Sembilan Belas NINETEEN

Seratus Seratus HUNDRED AND


Dua Ratus Dua Ratus TWO HUNDRED AND
Tiga Ratus Tiga Ratus THREE HUNDRED AND
Empat Ratus Empat Ratus FOUR HUNDRED AND
Lima Ratus Lima Ratus FIVE HUNDRED AND
Enam Ratus Enam Ratus SIX HUNDRED AND
Tujuh Ratus Tujuh Ratus SEVEN HUNDRED AND
Delapan Ratus Delapan Ratus EIGHT HUNDRED AND
Sembilan Ratus Sembilan Ratus NINE HUNDRED AND
HARGA BAHAN DAN UPAH KERJA
SATUAN KERJA : BAGIAN PEMERINTAHAN BUPATI KONAWE UTARA
PEKERJAAN : REHAB GEDUNG KANTOR CAMAT MOLAWE
LOKASI : KEC. MOLAWE KAB. KONAWE UTARA
TAHUN ANGGARAN : 2012

NO URAIAN SAT UPAH/HARGA

A. b c d
1 Mandor OH Rp 65,000.00
2 Kepala tukang OH Rp 75,000.00
3 Tukang Listrik OH Rp 65,000.00
4 Tukang Las OH Rp 65,000.00
5 Tukang kayu OH Rp 65,000.00
6 Tukang batu OH Rp 65,000.00
7 Tukang besi OH Rp 65,000.00
8 Tukang Cat OH Rp 65,000.00
9 Pekerja OH Rp 50,000.00
A. BAHAN DASAR
1 Tanah urug M3 Rp 80,000.00
2 Pasir urug M3 Rp 100,000.00
3 Pasir pasangan M3 Rp 160,000.00
4 Pasir beton M3 Rp 165,000.00
5 Batu belah gunung M3 Rp 160,000.00
6 Batu bata Bh Rp 650.00
7 Koral beton/Split 2 - 3Cm M3 Rp 250,000.00
8 Koral beton/Split 5 - 7Cm M3 Rp 245,000.00
9 Kerikil sungai M3 Rp 200,000.00
10 Sirtu M3 Rp 110,000.00
11 Buis beton dia 20 Cm panjang 1 meter M1 Rp 50,000.00
12 Semen Portland Kg Rp 1,900.00
13 Semen warna Kg Rp 1,800.00
14 Semen putih Kg Rp 1,800.00
B. BAHAN LANTAI
1 Tegel keramik Roman 40x40 cm Bh Rp 11,800.00
2 Tegel keramik Roman 40x40 cm anti slip Bh Rp 11,800.00
3 Tegel keramik 20x20 cm anti slip Bh Rp 5,275.00
4 Tegel keramik 20x25 cm Corak Warna Bh Rp 5,450.00
5 Tegel keramik 10 x 40 cm Bh Rp 5,975.00
C. BAHAN KAYU
1 Dolken kayu dia 10 / 400 Cm Btg. Rp 9,000.00
2 Papan kayu Kls I Bayam / Jati M3 Rp 4,000,000.00
3 Balok kayu Kls I Bayam / Jati M3 Rp 4,000,000.00
4 Papan kayu Kls II M3 Rp 2,100,000.00
5 Balok kayu Kls II M3 Rp 2,100,000.00
6 Papan kayu Kls III M3 Rp 1,300,000.00
7 Balok kayu Kls III M3 Rp 1,300,000.00
8 Papan/balok kayu (bekisting) M3 Rp 1,100,000.00
D. BAHAN LANGIT-LANGIT
1 Tripleks 1220 x 2440 x 0,3 mm Lbr Rp 65,000.00
2 Plywood 9 mm Lbr Rp 120,000.00
3 List Tripleks M' Rp 3,000.00
E. BAHAN ATAP
1 Plastik Bubungan M' Rp 20,000.00
2 Alumunium Voil M' Rp 7,000.00
3 Seng Gelombang Besar BJLS 20 Kaki Rp 8,500.00
4 Seng Gelombang Besar BJLS 20 (6 Kaki) Lembar Rp 51,000.00
5 Seng Plat Bjls 0.22 M' Rp 60,000.00
F. BAHAN BESI
1 Kawat beton Kg Rp 20,000.00
2 Besi Beton polos Kg Rp 18,000.00
3 Besi Siku Kg Rp 18,000.00
4 Paku biasa 5"-10" Kg Rp 22,000.00
5 Paku Sakura Roof Kg Rp 20,000.00
5 Paku seng Kg Rp 22,500.00
6 Paku tripleks Kg Rp 28,000.00
7 Paku Sekrup Kg Rp 28,000.00
8 Besi strip Kg Rp 28,600.00
G. BAHAN CAT
1 Plamur tembok Kg. Rp 15,000.00
2 Plamir kayu Kg. Rp 15,000.00
3 Cat dasar kayu Kg. Rp 40,000.00
4 Cat dasar tembok Kg Rp 30,000.00
5 Cat tembok Metro Lite Kg Rp 30,000.00
6 Cat kayu kilap Avian Kg. Rp 40,000.00
7 Cat Pelitur Kg. Rp 55,000.00
8 Cat atap seng Ex. Aga Kg Rp 70,000.00
9 Minyak cat Ltr Rp 37,000.00
10 Lem fox/ lem kayu Kg. Rp 22,000.00
11 Kuas biasa 5 cm Bh. Rp 17,500.00
12 Kuas Roll Bh. Rp 20,000.00
13 Ampelas halus Lbr Rp 9,500.00
14 Ampelas kasar Lbr Rp 2,500.00
15 Meni besi Kg Rp 70,000.00
16 Meni kayu Kg Rp 13,000.00
17 Minyak bekisting Ltr Rp 12,000.00
18 Residu Ltr Rp 9,000.00
H. BAHAN PENGGANTUNG
1 Kunci Tanam 2x Putar Bh. Rp 105,000.00
2 Grendel Tanam Bh. Rp 11,500.00
3 Engsel Pintu H Kuningan Bh. Rp 18,500.00
4 Engsel jendela Standart Bh. Rp 16,000.00
5 Pengangan Pintu Stainless Stell Bh. Rp 300,000.00
6 Door Closer Bh. Rp 300,000.00
7 Hak Angin Standart Bh. Rp 8,500.00
I. BAHAN KACA
1 Kaca bening 5 mm M2 Rp 120,000.00
2 Kaca Rayban 5 mm M2 Rp 150,000.00
3 Lem sealent Kg Rp 84,500.00
J. BAHAN INSTALASI LISTRIK
1 Lampu SL 20 Watt+philips down light Bh. Rp 85,000.00
2 Lampu Pijar 25 Watt Bh. Rp 29,500.00
3 Instalasi titik lampu Titik Rp 125,000.00
4 Saklar Tunggal Ex. Clipsal Bh. Rp 26,000.00
5 Saklar tunggal Ex.Broco Bh. Rp 23,000.00
6 Stop Kontak Close Ex.Broco Bh. Rp 27,000.00
7 Saklar ganda broco Bh. Rp 13,500.00
8 MCB 63 A 1 o Merlin Gering Bh. Rp 220,000.00
9 Stik Bh. Rp 1,250.00
10 Klem Bh. Rp 2,500.00
11 Panel Box Bh. Rp 300,000.00
12 KWH meter Bh. Rp 550,000.00
K. BAHAN SANITER
1 Kloset jongkok porselin Bh. Rp 130,000.00
2 Pasangan Bak KM / WC (Fiber) Bh. Rp 300,000.00
3 Floor drain Bh. Rp 15,000.00
4 Kran. Dia 1/2" Bh. Rp 17,000.00
5 Seal tape Bh. Rp 6,000.00
6 Stop Kran Btg. Rp 35,000.00
7 Pek. Septick Tank Bh. Rp 2,500,000.00
8 Pipa PVC Æ 1/2'' AW M1 Rp 5,700.00
9 Pipa PVC Æ 2 '' AW M1 Rp 16,250.00
10 Pipa PVC Æ 4 '' AW M1 Rp 35,800.00

-
Dibuat Oleh,-
ULP / PEJABAT PENGADAAN
Dibuat Oleh,-

SUKARJO LADANGKA, S.Sos


Direktur

Anda mungkin juga menyukai