Terbilang : DUA BELAS MILYAR SEMBILAN BELAS JUTA TUJUH RATUS TUJUH PULUH DUA RIBU RUPIAH
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RUKO
LOKASI : INDONESIA
T. ANGGARAN : 2015
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA
1 2 3 4 5 6
A PEKERJAAN PERSIAPAN
1 Pek. Administrasi dan Dokumentasi 1 Ls 10,000,000 10,000,000
2 Pek. Pengadaan air kerja 1 Ls 1,500,000 1,500,000
3 Pek. Pengadaan listrik kerja 1 Ls 2,600,000 2,600,000
4 Pek. Pasangan bouwplank 216 m1 66,389 14,339,929
5 Pek. Papan nama proyek 1 ls 180,000 180,000
6 Pek. Pengukuran/setting out 1 Ls 5,000,000 5,000,000
7 Pek. Mob dan Demob 1 Ls 12,000,000 12,000,000
8 Pek. Direksi keet 12 m2 450,000 5,400,000
9 Pek. Gudang dan barak kerja 36 m2 481,632 17,338,741
SUB TOTAL 68,358,670
B PEK. TANAH, PASIR & PAS. BATU KALI
1 Pek. Galian tanah pile cap 187 m3 41,125 7,698,600
2 Pek. Galian tanah pondasi tiang pancang 9 m3 41,125 353,307
3 Pek. Galian tanah pondasi batu kali 5 m3 41,125 192,465
4 Pek. Urugan tanah kembali 128 m3 13,708 1,750,445
5 Pek. Urugan pasir 11 m3 143,170 1,600,068
6 Pek. Pasangan pondasi batu kali 27 m3 619,090 16,901,157
SUB TOTAL 28,496,041
C PEKERJAAN BETON
C.1. BETON SUB STRUCTURE (Elv < +0.00)
1 Pek. Lantai kerja pile cap dan tie beam 37 m3 758,219 27,989,823
2 Pek. Lantai kerja sloof 8 m3 758,219 5,871,651
3 Pek. Bore Pile Dia. 40 cm 274 m1 285,000 77,976,000
4 Pek. Beton Bored Pile 34 m3 2,556,479 87,851,254
5 Pek. Beton Pile Cap PC1 20 unit 3,281,457 65,629,130
6 Pek. Pondasi tiang 2 unit 644,944 1,289,888
7 Pek. Pondasi tiang 1 unit 615,941 615,941
8 Pek. Kolom K1=60/60 11 m3 5,598,369 60,462,389
9 Pek. Balok Sloof TB1=20/25 cm 7 m3 4,903,522 32,216,142
10 Pek. Rabat beton di bawah lantai 1 23 m3 758,219 17,412,737
SUB TOTAL 377,314,956
C.2. BETON UPPER STRUCTURE (Elv +0.00 - +3.25)
1 Pek. Kolom K1 = 60/60 23 m3 5,598,369 131,001,842
2 Pek. Kolom Praktis 20/20 2 m3 6,258,129 10,576,238
3 Pek. Balok Lantai 4 m3 5,584,493 20,003,652
4 Pek. Balok Lantai B1 46 m3 5,174,432 240,145,367
5 Pek. Balok Lantai B2 18 m3 5,967,861 105,410,330
6 Pek. Balok Lantai B3 5 m3 7,501,101 36,005,284
7 Pek. Balok Lantai B4 3 m3 5,525,342 17,957,362
8 Pek. Balok Lantai B5 10 m3 6,557,676 66,101,378
9 Pek. Balok Lantai B6 24 m3 5,863,465 140,107,484
10 Pek. Beton Plat Lantai 23 m3 4,954,563 114,793,762
11 Pek. Plat Topian 2 m3 4,957,070 9,279,635
SUB TOTAL 891,382,336
C.3. BETON UPPER STRUCTURE (Elv +3.25 - + 16.25)
1 Pek. Kolom K1 = 60/60 94 m3 5,598,369 524,007,368
2 Pek. Kolom Praktis 20/20 7 m3 6,258,129 42,304,951
3 Pek. Balok Lantai 4 m3 5,584,493 20,003,652
4 Pek. Balok Lantai B1 46 m3 5,174,432 240,145,367
5 Pek. Balok Lantai B2 18 m3 5,967,861 105,410,330
6 Pek. Balok Lantai B3 5 m3 7,501,101 36,005,284
7 Pek. Balok Lantai B4 3 m3 5,525,342 17,957,362
8 Pek. Balok Lantai B5 10 m3 6,557,676 66,101,378
9 Pek. Balok Lantai B6 24 m3 5,863,465 140,107,484
10 Pek. Beton Plat Lantai 93 m3 4,954,563 459,175,050
11 Pek. Plat Topian 2 m3 4,957,070 9,279,635
SUB TOTAL 1,660,497,862
C.4. BETON UPPER STRUCTURE (Elv +16.25 - +19.50)
1 Pek. Kolom K1' = 60/60 23 m3 5,120,407 119,817,524
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RUKO
LOKASI : INDONESIA
T. ANGGARAN : 2015
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA
1 2 3 4 5 6
2 Pek. Kolom Praktis 20/20 2 m3 6,258,129 10,576,238
3 Pek. Balok Lantai 4 m3 5,584,493 20,003,652
4 Pek. Balok Dak B7 8 m3 6,824,422 51,319,657
5 Pek. Balok Dak B8 1 m3 7,694,860 5,540,299
6 Pek. Balok R1 25 m3 6,185,115 153,390,859
7 Pek. Balok R2 3 m3 5,659,028 18,335,251
8 Pek. Beton Plat Dak 12 m3 4,954,563 60,643,854
9 Pek. Plat Topian 1 m3 4,957,070 5,710,545
SUB TOTAL 445,337,879
C.5. BETON TANGGA
1 Pek. Plat tangga 12 m3 4,741,493 56,584,983
2 Pek. Balok bordes B8 1 m3 7,694,860 9,233,832
3 Pek. Plat bordes 9 m3 4,954,563 44,591,069
SUB TOTAL 110,409,884
PEKERJAAN ATAP
1 Pek. Rangka atap dan perakitan 15,578 kg 30,801 479,826,935
D 2 Pek. Pasangan Listplank 415 m1 61,568 25,562,888
3 Pek. Pasangan Atap 2,225 m2 39,291 87,440,771
4 Pek. Pasangan Nok/Bubungan 238 m1 64,178 15,293,534
SUB TOTAL 608,124,129
PEKERJAAN PASANGAN DINDING
1 Pasangan 1/2 bata 1:4 lantai 1-2 1,583 m2 101,521 160,720,149
E 2 Pasangan 1/2 bata 1:4 lantai 3-4 1,445 m2 101,521 146,694,077
3 Pasangan 1/2 bata 1:4 lantai 4-5 1,306 m2 101,521 132,567,499
4 Pasangan plesteran dinding dan beton lantai 1-2 3,230 m2 54,395 175,673,004
5 Pasangan plesteran dinding dan beton lantai 3-4 2,948 m2 54,395 160,342,317
6 Pasangan plesteran dinding dan beton lantai 5-6 2,664 m2 54,395 144,901,753
7 Pasangan acian dinding dan beton lantai 1-2 3,230 m2 23,683 76,484,528
8 Pasangan acian dinding dan beton lantai 3-4 2,948 m2 23,683 69,809,853
9 Pasangan acian dinding dan beton lantai 5-6 2,664 m2 23,683 63,087,338
SUB TOTAL 1,130,280,518
PEKERJAAN PLAFOND
1 Pasangan plafond + rangka kayu lantai 1-2 1,256 m2 125,532 157,614,314
F 2 Pasangan plafond + rangka kayu lantai 3-4 1,292 m2 125,532 162,137,235
3 Pasangan plafond + rangka kayu lantai 5-6 1,634 m2 125,532 205,159,589
4 Pasangan list plafond lantai 1-2 879 m1 18,575 16,317,698
5 Pasangan list plafond lantai 3-4 832 m1 18,575 15,453,984
6 Pasangan list plafond lantai 5-6 1,094 m1 18,575 20,327,933
SUB TOTAL 577,010,752
PEK. KUSEN, PINTU, JENDELA & KACA
Lantai 1-2
G 1 Kusen dan Pintu Type PD1 1 Unit 6,287,326 6,287,326
2 Kusen dan Pintu Type P1 12 Unit 3,783,533 45,402,391
3 Kusen dan Pintu Type P2 2 Unit 3,298,104 6,596,207
4 Kusen dan Pintu Type P3 2 Unit 2,770,095 5,540,190
5 Kusen dan Pintu Type P4 13 Unit 2,474,430 32,167,584
6 Kusen dan Pintu Type P5 2 Unit 844,391 1,688,782
7 Kusen Jendela Type J1 29 Unit 2,859,949 82,938,520
8 Kusen Jendela Type J2 18 Unit 1,446,318 26,033,730
9 Kusen Jendela Type J4 40 Unit 487,860 19,514,400
10 Kusen Jendela Type J6 8 Unit 898,247 7,185,974
11 Kusen Jendela Type J7 6 Unit 365,281 2,191,688
12 Pasangan GB 4 Unit 820,000 3,280,000
13 Pasangan pintu teralis (PR) 17 m2 580,913 9,939,421
14 Pasangan R2 12 m2 580,913 7,214,939
15 Railing tangga type 1 18 m1 720,000 12,672,000
16 Railing tangga type 2 17 m1 720,000 12,528,000
Lantai 3-4
1 Kusen dan Pintu Type P1 14 Unit 3,783,533 52,969,456
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RUKO
LOKASI : INDONESIA
T. ANGGARAN : 2015
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA
1 2 3 4 5 6
2 Kusen dan Pintu Type P3 4 Unit 2,770,095 11,080,379
3 Kusen dan Pintu Type P4 8 Unit 2,474,430 19,795,436
4 Kusen dan Pintu Type P5 2 Unit 844,391 1,688,782
5 Kusen Jendela Type J1 32 Unit 2,859,949 91,518,367
6 Kusen Jendela Type J2 18 Unit 1,446,318 26,033,730
7 Kusen Jendela Type J3 4 Unit 2,952,831 11,811,324
8 Kusen Jendela Type J4 52 Unit 487,860 25,368,720
9 Kusen Jendela Type J5 4 Unit 1,139,401 4,557,604
10 Kusen Jendela Type J6 8 Unit 898,247 7,185,974
11 Pasangan GB 4 Unit 820,000 3,280,000
12 Pasangan R1 6 Unit 580,913 3,607,470
13 Railing tangga type 1 18 m1 720,000 12,672,000
14 Railing tangga type 2 17 m1 720,000 12,528,000
Lantai 5-6
1 Kusen dan Pintu Type PD2 1 Unit 5,869,294 5,869,294
2 Kusen dan Pintu Type P1 10 Unit 3,783,533 37,835,326
3 Kusen dan Pintu Type P3 2 Unit 2,770,095 5,540,190
4 Kusen dan Pintu Type P4 4 Unit 2,474,430 9,897,718
5 Kusen dan Pintu Type P5 2 Unit 844,391 1,688,782
6 Kusen Jendela Type J1 32 Unit 2,859,949 91,518,367
7 Kusen Jendela Type J2 24 Unit 1,446,318 34,711,640
8 Kusen Jendela Type J3 4 Unit 2,952,831 11,811,324
9 Kusen Jendela Type J4 36 Unit 487,860 17,562,960
10 Kusen Jendela Type J5 10 Unit 1,139,401 11,394,009
11 Kusen Jendela Type J6 15 Unit 898,247 13,473,701
SUB TOTAL 806,581,706
PEKERJAAN LANTAI
1 Pas. Keramik lantai 40/40 elv +0.00 1,146 m2 180,070 206,360,220
H 2 Pas. Keramik lantai 20/20 84 m2 184,785 15,516,396
3 Pas. Keramik dinding 20/25 216 m2 154,477 33,319,809
4 Pas. Batu tempel 65 m2 335,243 21,723,714
5 Pas. Keramik lantai 40/40 elv +4.00 1,134 m2 180,070 204,199,380
6 Pas. Keramik lantai 20/20 36 m2 184,785 6,652,260
7 Pas. Keramik dinding 20/25 117 m2 154,477 18,120,093
8 Pas. Keramik lantai 40/40 elv +8.00 1,119 m2 180,070 201,498,330
9 Pas. Keramik lantai 20/20 12 m2 184,785 2,217,420
10 Pas. Keramik dinding 20/25 44 m2 154,477 6,719,728
11 Pas. Keramik tangga elv +0.00 s/d +8.00 192 m2 166,480 31,964,160
SUB TOTAL 748,291,510
PEKERJAAN SANITAIR
Lantai Dasar
I 1 Pas. Closet duduk 2 Unit 3,302,534 6,605,068
2 Pas. Urinoir 3 Unit 3,847,060 11,541,180
3 Pas. Kran Air 2 Buah 83,180 166,360
4 Pas. Wastavel 3 Unit 1,423,190 4,269,570
Lantai 1-4
1 Pas. Closet duduk 2 Unit 3,302,534 6,605,068
2 Pas. Urinoir 3 Unit
3 Pas. Kran Air 2 Buah 83,180 166,360
4 Pas. Wastavel 3 Unit 1,423,190 4,269,570
Lantai 5
1 Pas. Closet duduk 2 Unit 3,302,534 6,605,068
2 Pas. Urinoir 3 Unit
3 Pas. Kran Air 2 Buah 83,180 166,360
4 Pas. Wastavel 3 Unit 1,423,190 4,269,570
SUB TOTAL 44,664,175
PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dan beton lantai 1-2 luar 1,111 m2 39,931 44,378,449
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RUKO
LOKASI : INDONESIA
T. ANGGARAN : 2015
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA
1 2 3 4 5 6
J 2 Pek. Pengecatan dinding dan beton lantai 3-4 luar 1,078 m2 39,931 43,065,108
3 Pek. Pengecatan dinding dan beton lantai 5-6 luar 1,086 m2 39,931 43,349,419
4 Pek. Pengecatan dinding dan beton lantai 1-2 dalam 2,201 m2 13,413 29,521,889
5 Pek. Pengecatan dinding dan beton lantai 3-4 dalam 2,061 m2 13,413 27,640,199
6 Pek. Pengecatan dinding dan beton lantai 5-6 dalam 1,867 m2 13,413 25,043,350
7 Pek. Pengecatan plafond dan list lantai 1-2 1,256 m2 9,538 11,976,066
8 Pek. Pengecatan plafond dan list lantai 3-4 1,292 m2 9,538 12,319,733
9 Pek. Pengecatan plafond dan list lantai 5-6 1,634 m2 9,538 15,588,716
SUB TOTAL 252,882,930
MEKANIKAL
K.1. PENYEDIAAN DAN SUPLAI AIR BERSIH
K Instalasi pompa suplai dari sumur ke groundtank
1 Pompa hisap kap. Min 65 ltr/mnt 1 unit 15,250,000 15,250,000
2 Gate valve dia.32mm 2 unit 150,000 300,000
3 Fleksible joint dia.32mm 4 bh 150,000 600,000
4 Strainer dia.32mm 2 bh 150,000 300,000
5 Check valve dia.32mm 2 bh 180,000 360,000
6 Foot valve dia.32mm 1 bh 205,000 205,000
7 Pemipaan 1 ls 320,000 320,000
8 Fiting & aksesoris 1 ls 125,000 125,000
9 Pemasangan, instalasi dan alat bantu 1 ls 75,000 75,000
5 Panel Pompa
- Panel Box Wall Mounted 40 X 30 X 20 CM 1 bh 625,000 625,000
- MCB 4.5 kA 1P 10 A 1 bh 75,000 75,000
- MCB 4.5 kA 1P 6 A 2 bh 75,000 150,000
- Busbar RSTN-GND 1 ls 95,000 95,000
- Grounding panel BC 2.5 MM2 1 ls 120,000 120,000
- Kabel, Wiring & Pemasangan 1 ls 120,000 120,000
- Material Bantu 1 ls 75,000 75,000
SUB TOTAL 32,675,000
L.3. INSTALASI KABEL TOEVOER
1 Kabel dr Panel SDP LP ke Panel LP.1 Lt 1 NYY 4 X 16 MM 12 m1 195,000 2,340,000
2 Kabel dr Panel SDP LP ke Panel LP.1 Lt 2 NYY 4 X 16 MM 12 m1 195,000 2,340,000
3 Kabel dr Panel SDP LP ke Panel LP.1 Lt 3 NYY 4 X 16 MM 12 m1 195,000 2,340,000
4 Kabel dr P. SDP ke Panel Pompa NYY 3 X 2.5 MM 40 m1 27,500 1,100,000
SUB TOTAL 8,120,000
L.4. INSTALASI PENERANGAN
Lantai 1
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RUKO
LOKASI : INDONESIA
T. ANGGARAN : 2015
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA
1 2 3 4 5 6
1 Lampu TL 2x36 Watt Inbow RM 300 16 bh 225,000 3,600,000
2 Lampu TL 2x18 Watt Inbow RM 300 48 bh 190,000 9,120,000
3 Lampu Downlight 1x 11 W E27 15 bh 105,000 1,575,000
4 Lampu Downlight 1x 18 W E27 65 bh 110,000 7,150,000
5 Saklar Tunggal 30 bh 108,590 3,257,700
6 Saklar Ganda 23 bh 142,790 3,284,170
7 Saklar Tukar 4 bh 108,590 434,360
8 Instalasi penerangan 144 ttk 195,000 28,080,000
9 Outlet stopkontak, tunggal, 1ph, 10A/250VA 16 bh 199,788 3,196,600
10 Outlet stopkontak, ganda, 1ph, 16A/250VA 12 bh 199,788 2,397,450
11 Instalasi stopkontak 28 ttk 265,000 7,420,000
Lantai 2
1 Lampu TL 2x36 Watt Inbow RM 300 16 bh 225,000 3,600,000
2 Lampu TL 2x18 Watt Inbow RM 300 60 bh 190,000 11,400,000
3 Lampu Baret Square 1x22 W 4 bh 269,800 1,079,200
4 Lampu Downlight 1x 11 W E27 8 bh 105,000 840,000
5 Lampu Downlight 1x 18 W E27 51 bh 110,000 5,610,000
6 Saklar Tunggal 26 bh 108,590 2,823,340
7 Saklar Ganda 21 bh 142,790 2,998,590
8 Saklar Tukar 12 bh 108,590 1,303,080
9 Instalasi penerangan 139 ttk 195,000 27,105,000
10 Outlet stopkontak, tunggal, 1ph, 10A/250VA 16 bh 199,788 3,196,600
11 Outlet stopkontak, ganda, 1ph, 16A/250VA 14 bh 199,788 2,797,025
12 Instalasi stopkontak 30 ttk 265,000 7,950,000
Lantai 3
1 Lampu TL 2x36 Watt Inbow RM 300 36 bh 225,000 8,100,000
2 Lampu TL 2x18 Watt Inbow RM 300 24 bh 190,000 4,560,000
3 Lampu Baret Square 1x22 W 4 bh 269,800 1,079,200
4 Lampu Downlight 1x 11 W E27 8 bh 105,000 840,000
5 Lampu Downlight 1x 18 W E27 49 bh 110,000 5,390,000
6 Saklar Tunggal 22 bh 108,590 2,388,980
7 Saklar Ganda 19 bh 142,790 2,713,010
8 Saklar Tukar 4 bh 108,590 434,360
9 Instalasi penerangan 121 ttk 195,000 23,595,000
10 Outlet stopkontak, tunggal, 1ph, 10A/250VA 12 bh 199,788 2,397,450
11 Outlet stopkontak, ganda, 1ph, 16A/250VA 12 bh 199,788 2,397,450
12 Instalasi stopkontak 24 ttk 265,000 6,360,000
SUB TOTAL 200,473,565
L.5. INSTALASI KABEL TRAY & LADDER
Instalasi kabel tray lantai 1
1 Kabel Tray uk.300x100mm 62 m1 105,000 6,510,000
2 Kabel Ladder di shaft listrik uk. 300cmm 6 m1 105,000 630,000
3 Aksesoris (Hanger, Elbow & Tee) 1 ls 130,000 130,000
PEKERJAAN LAIN-LAIN/PENDUKUNG
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEMBANGUNAN RUKO
LOKASI : INDONESIA
T. ANGGARAN : 2015
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT
SATUAN HARGA
1 2 3 4 5 6
M.1. PEK. SALURAN KELILING
M 1 Pek. Galian tanah 114 m3 41,125 4,684,302
2 Pek. Urugan tanah kembali 30 m3 13,708 405,767
3 Pek. Pasangan buis beton U dia 30 cm 181 m1 91,066 16,464,774
4 Pek. Pasangan dinding batu bata 181 m2 101,521 18,354,906
5 Pek. Pasangan Plesteran 217 m2 54,395 11,801,539
6 Pek. Pasangan acian 217 m2 23,683 5,138,155
SUB TOTAL 56,849,444
M.2. PEK. GROUND TANK KAP ±15 M3
1 Pek. Galian tanah groundtank 16 m3 50,513 795,572
2 Pek. Pas. Lantai kerja/rabat beton 1 m3 758,219 545,918
3 Pek. Plat beton dasar 1 m3 4,954,563 5,350,928
4 Pek. Plat beton dinding 3 m3 4,954,563 15,606,874
5 Pek. Plat beton tutup 1 m3 4,954,563 5,350,928
6 Pek. Pasangan tangga besi 11 kg 11,756 129,203
7 Pek. Pasangan keramik 30/30 30 m2 166,480 4,994,400
SUB TOTAL 32,773,824
M.3. PEK. HALAMAN PARKIR
1 Pek. Galian tanah 20 m3 41,125 830,725
2 Pek. Urugan tanah kembali 8 m3 13,708 113,094
3 Pek. Urugan sirtu dipadatkan 45 m3 133,800 6,021,000
4 Pek. Urugan pasir 45 m3 143,170 6,442,650
5 Pek. Pasangan paving 450 m2 68,154 30,669,435
6 Pek. Pemasangan beton kanstin 4 m3 2,198,310 8,793,240
SUB TOTAL 52,870,144
8,310,732,005
ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
BANGUNAN GEDUNG DAN PERUMAHAN
TAHUN 2015
KET KOEF SAT URAIAN HARGA SATUAN JUMLAH
1 m3 Pondasi batu kali 1PC : 4 PP SNI : 2836:2008
1.200 m3 Batu Kali Rp 124,850.00 Rp 149,820.00
BAHAN 163.000 Kg PC Rp 1,650.00 Rp 268,950.00
0.520 m3 Pasir pasang Rp 121,000.00 Rp 62,920.00
1.500 OH Pekerja Rp 52,250.00 Rp 78,375.00
0.750 OH Tukang batu Rp 63,800.00 Rp 47,850.00
TENAGA
0.075 OH Kepala Tukang Rp 71,500.00 Rp 5,362.50
0.075 OH Mandor Rp 77,500.00 Rp 5,812.50
JUMLAH Rp 619,090.00
HARGA SATUAN Rp 619,090.00
1 m3 Pondasi siklop, 60% beton 1PC : 2PB : 3KR & 40% batu belah SNI : 2836:2008
0.480 m3 Batu kali Rp 124,850.00 Rp 59,928.00
194.000 Kg PC Rp 1,650.00 Rp 320,100.00
0.312 m3 Pasir Beton Rp 121,000.00 Rp 37,752.00
BAHAN
0.468 m3 Sirtu Rp 99,000.00 Rp 46,332.00
126.000 kg Besi Beton Rp 10,110.00 Rp 1,273,860.00
1.800 Kg Kawat Beton Rp 16,500.00 Rp 29,700.00
3.400 OH Pekerja Rp 52,250.00 Rp 177,650.00
0.850 OH Tukang batu Rp 63,800.00 Rp 54,230.00
TENAGA
0.085 OH Kepala Tukang Rp 71,500.00 Rp 6,077.50
0.170 OH Mandor Rp 77,500.00 Rp 13,175.00
JUMLAH Rp 2,018,804.50
HARGA SATUAN Rp 2,018,804.50
1 m2 Memasang langit-langit tripleks uk. (120 x 240) cm, tebal 3 mm SNI : 2839:2008
0.3750 lbr Tripleks Rp 72,385.00 Rp 27,144.38
BAHAN
0.0300 kg Paku kecil Rp 19,303.00 Rp 579.09
0.100 OH Pekerja Rp 52,250.00 Rp 5,225.00
0.100 OH Tukang Kayu Rp 63,800.00 Rp 6,380.00
TENAGA
0.010 OH Kepala Tukang Rp 71,500.00 Rp 715.00
0.005 OH Mandor Rp 77,500.00 Rp 387.50
JUMLAH Rp 40,430.97
HARGA SATUAN Rp 40,430.97
1 m2 pasang rangka dinding pemisah teakwood rangkap, rk. kayu SNI : 2006
0.0195 m3 kayu balok Rp 3,025,000.00 Rp 58,987.50
0.007 m3 kayu papan Rp 3,025,000.00 Rp 21,175.00
BAHAN 0.100 kg paku biasa 2" - 5" Rp 19,303.00 Rp 1,930.30
0.560 ltr lem kayu Rp 40,000.00 Rp 22,400.00
1.000 lbr teakwood Rp 72,500.00 Rp 72,500.00
0.150 Oh Pekerja Rp 52,250.00 Rp 7,837.50
0.450 Oh Tukang kayu Rp 63,800.00 Rp 28,710.00
TENAGA 0.045 Oh Kepala tukang Rp 71,500.00 Rp 3,217.50
0.075 Oh Mandor Rp 77,500.00 Rp 5,812.50
JUMLAH Rp 222,570.30
HARGA SATUAN Rp 222,570.30
1 m2 pasang rangka dinding pemisah mega sungkai rangkap, rk. kayu SNI : 2006
0.0195 m3 kayu balok Rp 3,025,000.00 Rp 58,987.50
0.007 m3 kayu papan Rp 3,025,000.00 Rp 21,175.00
BAHAN 0.100 kg paku biasa 2" - 5" Rp 19,303.00 Rp 1,930.30
0.560 ltr lem kayu Rp 40,000.00 Rp 22,400.00
1.000 lbr mega sungkai Rp 130,000.00 Rp 130,000.00
0.150 Oh Pekerja Rp 52,250.00 Rp 7,837.50
0.450 Oh Tukang kayu Rp 63,800.00 Rp 28,710.00
TENAGA 0.045 Oh Kepala tukang Rp 71,500.00 Rp 3,217.50
0.075 Oh Mandor Rp 77,500.00 Rp 5,812.50
JUMLAH Rp 280,070.30
HARGA SATUAN Rp 280,070.30
ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
BANGUNAN GEDUNG DAN PERUMAHAN
TAHUN 2015
KET KOEF SAT URAIAN HARGA SATUAN JUMLAH
1 buah Pasang kunci tanam biasa (kecil) SNI : 2002
BAHAN 1.0000 bh Kunci tanam kecil Rp 90,000.00 Rp 90,000.00
0.010 OH Pekerja Rp 52,250.00 Rp 522.50
0.500 OH Tukang kayu Rp 63,800.00 Rp 31,900.00
TENAGA
0.010 OH Kepala Tukang Rp 71,500.00 Rp 715.00
0.005 OH Mandor Rp 77,500.00 Rp 387.50
JUMLAH Rp 123,525.00
HARGA SATUAN Rp 123,525.00
JUMLAH :
BIAYA UMUM LAPANGAN
1 Biaya Gaji Karyawan
- Project Manager 8.00 Bln
- Adm keuangan dan proyek 8.00 Bln
- Pelaksana 8.00 Bln
- Asst. Pelaksana 8.00 Bln
- Surveyor 8.00 Bln
- Asst. Surveyor 2 orang 8.00 Bln
- Peralatan dan Logistik 8.00 Bln
- Driver 8.00 Bln
- Office boy 8.00 Bln
2 Uang makan
- Site Manager 8.00 Bln
- Adm keuangan dan proyek 8.00 Bln
- Pelaksana 8.00 Bln
- Asst. Pelaksana 8.00 Bln
- Surveyor 8.00 Bln
- Asst. Surveyor 2 orang 8.00 Bln
- Peralatan dan Logistik 8.00 Bln
- Driver 8.00 Bln
- Office boy 8.00 Bln
3 Operasional dan pulsa
- Operasional site manager 8.00 Bln
- Operasional Lapangan 8.00 Bln
4 Alat tulis kantor 8.00 Bln
5 Biaya fak dan komunikasi untuk kantor 8.00 Bln
6 Jamuan direksi / konsultan 8.00 Bln
7 Biaya rutinitas mess 8.00 Bln
JUMLAH :
BIAYA KARYA TAK LANGSUNG
Biaya Sewa Base Camp/Kantor Lapangan
1 Kantor dan Mess Karyawan dan Ops 8.00 Bln
2 Perabot mess karyawan 1.00 Ls
JUMLAH :
unit 6,500 62,400,000
unit 750,000 12,000,000
unit 6,500 4,875,000
unit 6,500 7,800,000
unit 6,500 19,500,000
30,000,000 30,000,000
10,000,000 600,000
137,175,000
15,000,000 120,000,000
120,000,000
4,500,000 36,000,000
2,250,000 18,000,000
3,000,000 24,000,000
2,500,000 20,000,000
2,000,000 16,000,000
1,750,000 14,000,000
2,500,000 20,000,000
1,500,000 12,000,000
1,500,000 12,000,000
800,000 6,400,000
750,000 6,000,000
750,000 6,000,000
500,000 4,000,000
750,000 6,000,000
1,000,000 8,000,000
500,000 4,000,000
500,000 4,000,000
500,000 4,000,000
5,000,000 40,000,000
5,000,000 40,000,000
1,000,000 8,000,000
600,000 4,800,000
2,000,000 16,000,000
1,000,000 8,000,000
337,200,000
4,500,000 36,000,000
2,000,000 2,000,000
38,000,000
632,375,000