SATUAN KERJA BALAI WILAYAH SUNGAI KALIMANTAN III PENGELOLAAN ASET BENDUNGAN
REHABILITASI RUMAH DINAS JABATAN KEPALA BWS KALIMANTAN III KOTA SAMARINDA
NOMOR KONTRAK : HK.02.03/BMN-BWS-K.III/34/II/2017
TANGGAL KONTRAK : 13 Februari 2017
1. Pekerjaan Pondasi
a. Galian Tanah (Manual) M3 20.00 23,862.50 477,250.00
b. Tiang Pancang Kayu Ulin 10/10 M1 88.00 50,140.00 4,412,320.00
4,889,570.00
2. Pekerjaan Beton
2.a Pekerjaan Sloof
a. Cor Beton M3 3.72 1,332,045.00 4,955,207.40
b. Pembesian Kg 304.52 27,335.50 8,324,206.46
c. Bekisting dan Pembongkaran M2 16.80 121,133.33 2,035,039.94
15,314,453.80
2.b Pekerjaan Kolom
a. Cor Beton M3 1.53 1,332,045.00 2,038,028.85
b. Pembesian Kg 125.25 27,335.50 3,423,771.38
c. Bekisting dan Pembongkaran M2 6.91 121,133.33 837,031.31
6,298,831.54
2.c Pekerjaan Ring Balk
a. Cor Beton M3 2.89 1,332,045.00 3,849,610.05
b. Pembesian Kg 236.59 27,335.50 6,467,305.95
c. Bekisting dan Pembongkaran M2 13.04 121,133.33 1,579,578.62
11,896,494.62
3. Pekerjaan Dinding
a. Pasangan Batu Bata Camp. 1 pc : 4 psr M2 111.60 104,149.75 11,623,112.10
b. Plesteran Camp. 1 pc : 2 psr M2 223.20 39,015.67 8,708,297.54
c. Rooster 20/20 M2 0.80 121,049.00 96,839.20
20,428,248.84
4. Pekerjaan Lantai
a. Timbunan Tanah M3 24.73 63,537.50 1,571,282.38
b. Timbunan Pasir Urug M3 4.12 137,425.00 566,191.00
c. Cor Beton B0 M3 5.77 1,003,662.50 5,791,132.63
d. Keramik Lantai Uk. 30 x 30 cm M2 37.20 132,604.58 4,932,890.38
12,861,496.38
5. Pekerjaan Atap dan Kuda-Kuda
a. Kuda-Kuda M3 5.82 2,741,216.67 15,953,881.02
b. Rangka Atap M2 58.40 163,371.88 9,540,917.79
c. Lisplank M2 9.48 100,993.00 957,413.64
d. Bubungan M1 7.30 47,552.50 347,133.25
e. Atap M2 58.40 117,586.35 6,867,042.84
33,666,388.54
6. Pekerjaan Plafond
a. Rangka Plafond M2 82.49 189,821.88 15,658,406.88
b. Plafond M2 82.49 84,977.33 7,009,779.95
22,668,186.83
7. Pekerjaan Pengecatan
a. Cat Tembok M2 223.20 48,872.70 10,908,386.64
b. Cat Tembok Batas Pagar Rumah M2 62.62 48,872.70 3,060,261.86
13,968,648.50
TOTAL PEKERJAAN GUDANG 141,992,319.05
II. PEKERJAAN LAIN-LAIN
X.1. 1 Bahan
- Polycarbonate t: 5mm 1.000 m2 x Rp 141,242.94 = Rp 141,242.94
- Rangka Hollow Galvanis 1.000 m2 x Rp 400,000.00 = Rp 400,000.00
- Perlengkapan 6% dari Harga Bahan 0.060 Ls x Rp 32,474.58 = Rp 1,948.47
= Rp 543,191.41
X.1. 2 Tenaga
- Pekerja 0.700 Oh x Rp 75,000.00 = Rp 52,500.00
- Tukang batu 0.350 Oh x Rp 90,000.00 = Rp 31,500.00
- Kepala tukang 0.035 Oh x Rp 100,000.00 = Rp 3,500.00
- Mandor 0.070 Oh x Rp 120,000.00 = Rp 8,400.00
= Rp 95,900.00
Total = Rp 639,091.41
Profit 15% = Rp 95,863.71
Total + Profit = Rp 734,955.12
X.2. 1 Bahan
- Tandon Air 1.200 Ltr 1.000 m x Rp 2,000,000.00 = Rp 2,000,000.00
- Perlengkapan 6% dari Harga Bahan 0.060 Ls x Rp 120,000.00 = Rp 7,200.00
= Rp 2,007,200.00
X.2. 2 Tenaga
- Pekerja 3.300 Oh x Rp 75,000.00 = Rp 247,500.00
- Tukang batu 1.100 Oh x Rp 90,000.00 = Rp 99,000.00
- Kepala tukang 0.001 Oh x Rp 100,000.00 = Rp 100.00
- Mandor 0.160 Oh x Rp 120,000.00 = Rp 19,200.00
= Rp 365,800.00
Total = Rp 2,373,000.00
Profit 15% = Rp 355,950.00
Total + Profit = Rp 2,728,950.00