Anda di halaman 1dari 38

PEKERJAAN : PEMBANGUNAN RUMAH TYPE 80

LOKASI : JL. POROS KOTA WAISAI - KABUPATEN RAJA AMPAT

SATUAN TOTAL
NO. URAIAN KEGIATAN SAT. VOL. HARGA HARGA
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN PENDAHULUAN

1 Pembersihan dan Perataan tanah lokasi M2 85.00 Rp 14,750.00 Rp 1,253,750.00


2 Basecamp Ls 1.00 Rp 3,600,000.00 Rp 3,600,000.00
3 Pengukuran dan pasangan bouwplank M' 104.00 Rp 44,245.00 Rp 4,601,480.00
Sub Total Rp 9,455,230.00
II PEKERJAAN TANAH DAN PASIR
1 Galian tanah pondasi M3 47.31 Rp 34,400.00 Rp 1,627,464.00
2 Urugan tanah kembali M3 15.77 Rp 16,490.00 Rp 260,047.30
3 Urugan tanah peninggian lantai M3 9.20 Rp 165,500.00 Rp 1,522,600.00
4 Urugan pasir dibawah pondasi M3 2.49 Rp 419,600.00 Rp 1,044,804.00
5 Urugan Pasir dibawah Lantai M3 4.92 Rp 419,600.00 Rp 2,064,432.00
Sub Total Rp 6,519,347.30
III PEKERJAAN PASANGAN DAN BETON
1 Pasangan batu kosong M3 9.96 Rp 680,790.00 Rp 6,780,668.40
2 Pasangan pondasi batu kali campuran 1: 4 M3 19.61 Rp 1,291,250.00 Rp 25,319,798.44
3 Cor sloof beton 15/20 camp: 1:2:3 M3 1.87 Rp 4,478,201.25 Rp 8,363,040.83
4 Cor Kolom beton Praktis 12/12 camp: 1:2:3 M3 0.81 Rp 6,326,844.58 Rp 5,101,967.47
5 Cor Ring Balok beton 15/20 camp: 1:2:3 M3 1.87 Rp 4,478,201.25 Rp 8,363,040.83
6 Pasangan Kolom Kayu 10x10 ky klass 1 M3 0.07 Rp 3,552,907.50 Rp 248,703.53
7 Ring balok 10x10 Kayu Kelas 1 M3 0.11 Rp 4,379,800.00 Rp 481,778.00
Sub Total Rp 54,658,997.50
IV PEKERJAAN DINDING DAN LANTAI
1 Pasangan dinding batu tela 1 : 4 M2 205.43 Rp 260,000.00 Rp 53,410,500.00
2 Plesteran 1 : 4 M2 410.85 Rp 52,100.00 Rp 21,405,285.00
3 Acian dinding dan lantai M2 441.75 Rp 19,475.00 Rp 8,603,081.25
4 Pasangan Keramik 30 x 30 Polos M2 46.00 Rp 232,300.00 Rp 10,685,800.00
5 Pasangan keramik 20 x 20 M2 3.06 Rp 215,760.00 Rp 660,765.00
6 Cor Lantai 1 : 3 : 5 tebal 5 cm M3 42.90 Rp 1,532,600.00 Rp 65,748,540.00
Sub Total Rp 160,513,971.25
V PEKERJAAN KAYU,KUSEN,PINTU DAN JENDELA
1 Pas. Kusen pintu, jendela dan ventilasi M3 0.44 Rp 5,051,500.00 Rp 2,197,402.50
2 Pas. Pintu paneil papan kayu besi M2 12.39 Rp 431,700.00 Rp 5,348,763.00
3 Pas. Jalusi papan kayu besi 2/10 M2 3.50 Rp 420,925.00 Rp 1,473,237.50
4 Pas.Jendela Kaca Ugkit M2 11.34 Rp 395,295.00 Rp 4,482,645.30
Sub Total Rp 13,502,048.30
VI PEKERJAAN ATAP DAN PLAFOND
1 Pasangan kuda-kuda 5/10 kayu besi M3 1.10 Rp 4,313,800.00 Rp 4,745,180.00
2 Pasangan gording 5/10 kayu besi M3 1.88 Rp 4,142,200.00 Rp 7,766,625.00
3 Pasangan skor angin 5/10 kayu besi M3 0.08 Rp 4,142,200.00 Rp 331,376.00
4 Pas. Atap Seng bjls 20 M2 68.80 Rp 61,265.00 Rp 4,215,032.00
5 Nok Seng Plat M' 15.00 Rp 29,185.00 Rp 437,775.00
6 Pasangan lisplank papan kayu besi 2/20 M' 169.00 Rp 57,750.00 Rp 9,759,750.00
7 Plafond tripleks 3mm dan rangka plafon kayu klas II M2 116.00 Rp 109,701.50 Rp 12,725,374.00
8 List Plafond M' 124.50 Rp 14,882.50 Rp 1,852,871.25
Sub Total Rp 41,833,983.25
VII PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Pasang kunci tanam 2 slag ( setara yalle) Bh 7.00 Rp 247,300.00 Rp 1,731,100.00
2 Pasang engsel pintu 4" Bh 21.00 Rp 55,807.50 Rp 1,171,957.50
3 Pasang engsel jendela 3" Bh 24.00 Rp 35,555.00 Rp 853,320.00
4 Pasang grendel jendela Bh 12.00 Rp 39,210.00 Rp 470,520.00
5 Pasang grendel pintu Bh 7.00 Rp 44,710.00 Rp 312,970.00
6 Pasang hak angin jendela Bh 10.00 Rp 29,957.50 Rp 299,575.00
Sub Total Rp 4,839,442.50
VIII PEKERJAAN PENGECATAN DAN LABURAN
1 Cat kusen M2 17.40 Rp 39,580.00 Rp 688,692.00
2 Cat kilap kayu pintu dan jendela dan Jalusi M2 54.46 Rp 54,586.00 Rp 2,972,753.56
3 Cat dinding Tembok M2 410.85 Rp 14,983.30 Rp 6,155,888.81
4 Cat Atap Seng M2 68.80 Rp 27,567.00 Rp 1,896,609.60
5 Cat Plafon M2 116.00 Rp 17,363.30 Rp 2,014,142.80
Sub Total Rp 13,728,086.77
SATUAN TOTAL
NO. URAIAN KEGIATAN SAT. VOL. HARGA HARGA
1 2 3 4 5 6
IX PEKERJAAN SANITAIR
1 Pemasangan kloset jongkok Bh 1.00 Rp 462,900.00 Rp 462,900.00
2 Pembuatan Septictank Unit 1.00 Rp 6,407,892.64 Rp 6,407,892.64
3 Pemas. Instalasi air kotor pipa Ø 4" M' 6.00 Rp 101,013.50 Rp 606,081.00
4 Pemas. Instalasi air bersih pipa Ø 1/2" M' 25.00 Rp 72,711.25 Rp 1,817,781.25
5 Pemasangan Kran Air 1/2" Bh 1.00 Rp 66,475.00 Rp 66,475.00
Sub Total Rp 9,361,129.89
X PEKERJAAN ELEKTRIKAL
1 Pemasangan Lampu SL 18 Watt Bh 9.00 Rp 87,750.00 Rp 789,750.00
2 Pemasangan stop kontak Titik 5.00 Rp 59,150.00 Rp 295,750.00
3 pemasangan saklar tunggal Titik 6.00 Rp 60,525.00 Rp 363,150.00
4 pemasangan saklar ganda Titik 2.00 Rp 64,650.00 Rp 129,300.00
5 pemasangan box sekring Unit 1.00 Rp 108,100.00 Rp 108,100.00
6 pemasangan box MCB Unit 1.00 Rp 2,000,000.00 Rp 2,000,000.00
7 Instalasi Kabel NYM 2x2.5mm M' 60.00 Rp 52,440.00 Rp 3,146,400.00
Sub Total Rp 6,832,450.00

XI PEKERJAAN AKHIR
1 Finishng / pembersihan akhir LS 1.00 Rp 1,000,000.00 Rp 1,000,000.00
Sub Total Rp 1,000,000.00
PEKERJAAN : PEMBANGUNAN RUMAH TYPE 80
LOKASI : JL. POROS KOTA WAISAI - KABUPATEN RAJA AMPAT

NO. URAIAN PEKERJAAN TOTAL HARGA

I PEKERJAAN PERSIAPAN PENDAHULUAN Rp 9,455,230.00


II PEKERJAAN TANAH DAN PASIR Rp 6,519,347.30
III PEKERJAAN PASANGAN DAN BETON Rp 54,658,997.50
IV PEKERJAAN DINDING DAN LANTAI Rp 160,513,971.25
V PEKERJAAN KAYU,KUSEN,PINTU DAN JENDELA Rp 13,502,048.30
VI PEKERJAAN ATAP DAN PLAFOND Rp 41,833,983.25
VII PEKERJAAN PENGUNCI DAN PENGGANTUNG Rp 4,839,442.50
VIII PEKERJAAN PENGECATAN DAN LABURAN Rp 13,728,086.77
IX PEKERJAAN SANITAIR Rp 9,361,129.89
X PEKERJAAN ELEKTRIKAL Rp 6,832,450.00
XI PEKERJAAN AKHIR Rp 1,000,000.00

REAL COAST Rp 322,244,686.76


DIBULATKAN Rp 322,240,000.00

Terbilang : ( Tiga Ratus Dua Puluh Dua Juta Dua Ratus Empat Puluh Ribu Rupiah )

WAISAI, 08 Maret 2013


Dibuat Oleh :
PEMILIK BANGUNAN

Ir. H. SUDIRMAN
DAFTAR ANALISA PEKERJAAN
ANALISA BIAYA KONSTRUKSI BANGUNAN GEDUNG
Badan stadarisasi nasional ( BSN )

HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5

@ PEKERJAAN PENDAHULUAN

M2 PEMBERSIHAN LOKASI
Tenaga Kerja
0.1000 Hr Mandor 110,000.00 11,000.00
0.0500 Hr Pekerja 75,000.00 3,750.00
Total 14,750.00

PASANGAN BOUWPLANK / M'


0.007 M3 Papan kayu klas III 1,400,000.00 9,800.00
0.012 M3 Balok kayu klas III 1,400,000.00 16,800.00
0.020 Kg Paku campuran 24,750.00 495.00
0.100 OH Pekerja 75,000.00 7,500.00
0.100 OH Tukang kayu 90,000.00 9,000.00
0.001 OH Kepala tukang kayu 100,000.00 100.00
0.005 OH Mandor 110,000.00 550.00
Total 44,245.00

BONGKARAN DINDING TEMBOK BATA/M3


6.667 OH Pekerja 75,000.00 500,025.00
0.033 OH Mandor 110,000.00 3,630.00
Total 503,655.00
UNTUK 1 M2 40,292.40

BONGKARAN BETON BERTULANG/M3


6.667 OH Pekerja 75,000.00 500,025.00
0.333 OH Mandor 110,000.00 36,630.00
Total 536,655.00
UNTUK 1 M2 42,932.40

BONGKARAN ATAP SENG /M2


0.05 OH Pekerja 75,000.00 3,750.00
0.025 OH Mandor 110,000.00 2,750.00
Total 6,500.00

@ PEKERJAAN GALIAN DAN URUGAN

GALIAN TANAH BIASA / M3

0.400 OH Pekerja 75,000.00 30,000.00


0.040 OH Mandor 110,000.00 4,400.00
Total 34,400.00

URUGAN TANAH KEMBALI / M3

0.192 OH Pekerja 75,000.00 14,400.00


0.019 OH Mandor 110,000.00 2,090.00
Total 16,490.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5

URUGAN PASIR / M3
1.200 M3 Pasir urug 330,000.00 396,000.00
0.300 OH Pekerja 75,000.00 22,500.00
0.010 OH Mandor 110,000.00 1,100.00
Total 419,600.00

URUGAN TANAH / SIRTU / M3


1.200 M3 Tanah urug 120,000.00 144,000.00
0.250 OH Pekerja 75,000.00 18,750.00
0.025 OH Mandor 110,000.00 2,750.00
Total 165,500.00

@ PEKERJAAN PASANGAN DAN BETON

AANSTAMPING BATU KOSONG / M3


1.200 M3 Batu kali 400,000.00 480,000.00
0.300 M3 Pasir Urug 330,000.00 99,000.00
0.780 OH Pekerja 75,000.00 58,500.00
0.390 OH Tukang 90,000.00 35,100.00
0.039 OH Kepala Tukang 100,000.00 3,900.00
0.039 OH Mandor 110,000.00 4,290.00
Total 680,790.00

PASANGAN BATU KALI/GUNUNG 1 : 4 / M3


1.200 M3 Batu kali 400,000.00 480,000.00
3.260 Zak Semen PC 125,000.00 407,500.00
0.520 M3 Pasir pasang 400,000.00 208,000.00
1.500 OH Pekerja 75,000.00 112,500.00
0.750 OH Tukang batu 90,000.00 67,500.00
0.075 OH Kepala tukang batu 100,000.00 7,500.00
0.075 OH Mandor 110,000.00 8,250.00
Total 1,291,250.00

PEKERJAAN BETON TUMBUK CAMP. 1 : 3 : 5 / M3


0.870 M3 Batu pecah 715,000.00 622,050.00
4.360 Zak Semen PC 125,000.00 545,000.00
0.520 M3 Pasir beton 400,000.00 208,000.00
1.650 OH Pekerja 75,000.00 123,750.00
0.250 OH Tukang batu 90,000.00 22,500.00
0.025 OH Kepala tukang batu 100,000.00 2,500.00
0.080 OH Mandor 110,000.00 8,800.00
Total 1,532,600.00

PEKERJAAN BETON 1 : 2 : 3 Beton Bertulang / M3


0.780 M3 Batu pecah 715,000.00 557,700.00
4.640 Zak Semen PC 125,000.00 580,000.00
0.520 M3 Pasir beton 400,000.00 208,000.00
1.650 OH Pekerja 75,000.00 123,750.00
0.250 OH Tukang batu 90,000.00 22,500.00
0.025 OH Kepala tukang batu 100,000.00 2,500.00
0.080 OH Mandor 110,000.00 8,800.00
Total 1,503,250.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5

PEKERJAAN PEMBESIAN (BESI POLOS) / Kg


1.050 Kg Besi beton 8,662.50 9,095.63
0.015 Kg Kawat beton 33,000.00 495.00
0.007 OH Pekerja 75,000.00 525.00
0.007 OH Tukang besi 90,000.00 630.00
0.0007 OH Kepala tukang 100,000.00 70.00
0.0003 OH Mandor 110,000.00 33.00
Total 10,848.63

PEKERJAAN BEGESTING UNTUK SLOOF / M2


0.045 M3 Kayu terentang 66,000.00 2,970.00
0.100 M3 kayu bekesting 1,400,000.00 140,000.00
0.300 Kg Paku biasa 24,750.00 7,425.00
0.100 Lt Minyak Bekesting 138,600.00 13,860.00
0.300 OH Pekerja 75,000.00 22,500.00
0.260 OH Tukang 90,000.00 23,400.00
0.026 OH Kepala tukang 100,000.00 2,600.00
0.005 OH Mandor 110,000.00 550.00
Total 213,305.00

PEKERJAAN BEGESTING UNTUK KOLOM / M2


0.040 M3 Kayu terentang 66,000.00 2,640.00
0.015 M3 kayu bekesting 1,450,000.00 21,750.00
0.400 Kg Paku biasa 24,750.00 9,900.00
0.200 Lt Minyak bekesing 138,600.00 27,720.00
0.350 Lbr Triplek 64,350.00 22,522.50
2.000 Btg Dolken katu mangi-mangi 55,000.00 110,000.00
0.300 OH Pekerja 75,000.00 22,500.00
0.330 OH Tukang 90,000.00 29,700.00
0.033 OH Kepala tukang 100,000.00 3,300.00
0.006 OH Mandor 110,000.00 660.00
Total 250,692.50

PEKERJAAN SLOOF BETON 25/30 /m3


1.05 M3 Beton camp. 1:2:3 1,503,250.00 1,578,412.50
8.000 M2 Bekesting 213,305.00 1,706,440.00
110.00 Kg Pembesian 10,848.63 1,193,348.75
Total 4,478,201.25

PEKERJAAN KOLOM PRAKTIS /m3


1.050 M3 Beton camp. 1:2:3 1,503,250.00 1,578,412.50
16.667 M2 Bekesting 213,305.00 3,555,083.33
110.00 Kg Pembesian 10,848.63 1,193,348.75

Total 6,326,844.58

PEKERJAAN KOLOM 20 X 20 /m3


1.050 M3 Beton camp. 1:2:3 1,503,250.00 1,578,412.50
10.000 M2 Bekesting 213,305.00 2,133,050.00
110.00 Kg Pembesian 10,848.63 1,193,348.75

Total 4,904,811.25
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
PEKERJAAN RING BALK
1.050 M3 Cor beton 1:2:3 1,503,250.00 1,578,412.50
8.000 M3 Begesting 213,305.00 1,706,440.00
110.00 Kg Pembesian 10,848.63 1,193,348.75
Total 4,478,201.25
@ PEKERJAAN DINDING DAN LANTAI

PASANGAN BATU TELA 1 : 2 / M2


24.000 Bh Batu tela 6,000.00 144,000.00
0.531 Zak Semen PC 125,000.00 66,375.00
0.093 M3 Pasir pasang 400,000.00 37,200.00
0.650 OH Pekerja 75,000.00 48,750.00
0.200 OH Tukang batu 90,000.00 18,000.00
0.020 OH Kepala tukang batu 100,000.00 2,000.00
0.030 OH Mandor 110,000.00 3,300.00
Total 319,625.00
untuk 1 M3 3,995,312.50

PASANGAN BATU TELA 1 : 3 / M2


24.000 Bh Batu tela 6,000.00 144,000.00
0.287 Zak Semen PC 125,000.00 35,925.00
0.040 M3 Pasir pasang 400,000.00 16,000.00
0.650 OH Pekerja 75,000.00 48,750.00
0.200 OH Tukang batu 90,000.00 18,000.00
0.020 OH Kepala tukang batu 100,000.00 2,000.00
0.030 OH Mandor 110,000.00 3,300.00
Total 267,975.00
untuk 1 M3 3,349,687.50

PASANGAN BATU TELA 1 : 4 / M2


24.000 Bh Batu tela 6,000.00 144,000.00
0.230 Zak Semen PC 125,000.00 28,750.00
0.038 M3 Pasir pasang 400,000.00 15,200.00
0.650 OH Pekerja 75,000.00 48,750.00
0.200 OH Tukang batu 90,000.00 18,000.00
0.020 OH Kepala tukang batu 100,000.00 2,000.00
0.030 OH Mandor 110,000.00 3,300.00
Total 260,000.00
untuk 1 M3 3,250,000.00

PAS. DINDING PEMISAH Tripleks RANGKAP, RANGKA KAYU MATOA

0.020 Bh Kayu matoa balok 1,450,000.00 28,275.00


0.007 Zak Kayu matoa papan 1,450,000.00 10,150.00
0.100 M3 Paku Biasa 24,750.00 2,475.00
0.560 Kg Lem kayu 24,750.00 13,860.00
0.336 Lbr Tripleks 3mm 64,350.00 21,617.17
0.200 OH Pekerja 75,000.00 15,000.00
0.600 OH Tukang batu 90,000.00 54,000.00
0.060 OH Kepala tukang batu 100,000.00 6,000.00
0.010 OH Mandor 110,000.00 1,100.00
Total 152,477.17
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
PASANG MOTIF PADA DINDING /M2
0.256 Zak Semen 125,000.00 32,000.00
0.035 M3 Pasir Pasang 400,000.00 14,000.00
0.3 OH Pekerja 75,000.00 22,500.00
0.1 OH Tukang Batu 90,000.00 9,000.00
0.01 OH Kepala Tukang 100,000.00 1,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 80,150.00

PASANG GLASS BLOCK/M2


23 Bh Glass Block 20x20x7 30,000.00 690,000.00
0.101 Zak Semen 125,000.00 12,625.00
0.013 M3 Pasir Pasang 400,000.00 5,200.00
0.3 OH Pekerja 75,000.00 22,500.00
0.1 OH Tukang Batu 90,000.00 9,000.00
0.01 OH Kepala Tukang 100,000.00 1,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 741,975.00

PLESTERAN Tebal = 15 mm 1 PC : 2 PSR


0.170 Zak Semen PC 125,000.00 21,300.00
0.017 M3 Pasir plester 400,000.00 6,800.00
0.200 OH Pekerja 75,000.00 15,000.00
0.150 OH Tukang batu 90,000.00 13,500.00
0.015 OH Kepala tukang batu 100,000.00 1,500.00
0.0100 OH Mandor 110,000.00 1,100.00
Total 59,200.00

PLESTERAN Tebal = 15 mm 1 PC : 4 PSR


0.104 Zak Semen PC 125,000.00 13,000.00
0.020 M3 Pasir plester 400,000.00 8,000.00
0.200 OH Pekerja 75,000.00 15,000.00
0.150 OH Tukang batu 90,000.00 13,500.00
0.015 OH Kepala tukang batu 100,000.00 1,500.00
0.0100 OH Mandor 110,000.00 1,100.00
Total 52,100.00

KERAMIK 40/40 / M2
1.000 M2 Keramik 40/40 88,000.00 88,000.00
0.228 Zak Semen (PC) 125,000.00 28,450.00
0.042 M3 Pasir pasang 400,000.00 16,800.00
1.500 Kg Semen warna 5,500.00 8,250.00
0.700 OH Pekerja 75,000.00 52,500.00
0.350 OH Tukang 90,000.00 31,500.00
0.035 OH Kepala Tukang 100,000.00 3,500.00
0.030 OH Mandor 110,000.00 3300
Total 232,300.00

KERAMIK 30/30 / M2
1.000 M2 Keramik 30/30 75,000.00 75,000.00
0.200 Zak Semen PC 125,000.00 25,000.00
0.045 M3 Pasir pasang 400,000.00 18,000.00
1.500 Kg Semen Warna 5,500.00 8,250.00
0.700 OH Pekerja 75,000.00 52,500.00
0.350 OH Tukang 90,000.00 31,500.00
0.035 OH Kepala tukang 100,000.00 3,500.00
0.030 OH Mandor 110,000.00 3300
Total 217,050.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
KERAMIK 20/20 / M2
1.000 M2 Keramik 20/20 71,500.00 71,500.00
0.208 Zak Semen PC 125,000.00 26,000.00
0.045 M3 Pasir pasang 400,000.00 18,000.00
1.620 Kg Semen Warna 5,500.00 8,910.00
0.700 OH Pekerja 75,000.00 52,500.00
0.350 OH Tukang 90,000.00 31,500.00
0.035 OH Kepala tukang 100,000.00 3,500.00
0.035 OH Mandor 110,000.00 3,850.00
Total 215,760.00

KERAMIK PLINT 10/20 / M'


1.000 Bh Keramik Plint 10/20 65,000.00 65,000.00
0.033 Zak Semen PC 125,000.00 4,125.00
0.0032 M3 Pasir pasang 400,000.00 1,280.00
0.100 Kg Semen Warna 5,500.00 550.00
0.090 OH Pekerja 75,000.00 6,750.00
0.090 OH Tukang 90,000.00 8,100.00
0.009 OH Kepala tukang 100,000.00 900.00
0.005 OH Mandor 110,000.00 495.00
Total 87,200.00

PEK KOLOM KAYU /M3


1.1000 Bh Balok kayu klas I 2,310,000.00 2,541,000.00
0.2500 Zak Paku campuran 24,750.00 6,187.50
4.0000 M3 Pekerja 75,000.00 300,000.00
7.2000 Kg Tukang kayu 90,000.00 648,000.00
0.5200 OH Kepala tukang kayu 100,000.00 52,000.00
0.0520 OH Mandor 110,000.00 5,720.00
Total 3,552,907.50
@ PEKERJAAN ATAP

PEKERJAAN KUDA-KUDA KAYU / M3


1.200 M3 Balok kayu klas I 2,310,000.00 2,772,000.00
15.000 Kg Besi strip 0.00 0.00
0.800 Kg Paku campuran 24,750.00 19,800.00
4.000 OH Pekerja 75,000.00 300,000.00
12.000 OH Tukang kayu 90,000.00 1,080,000.00
1.200 OH Kepala tukang kayu 100,000.00 120,000.00
0.200 OH Mandor 110,000.00 22,000.00

Total 4,313,800.00

PEK. GORDING DAN BALOK NOK KAYU / M3


1.100 M3 Balok kayu klas I 2,310,000.00 2,541,000.00
3.200 Kg Paku campuran 24,750.00 79,200.00
4.000 OH Pekerja 75,000.00 300,000.00
12.000 OH Tukang kayu 90,000.00 1,080,000.00
1.200 OH Kepala tukang kayu 100,000.00 120,000.00
0.200 OH Mandor 110,000.00 22,000.00
Total 4,142,200.00

PEKERJAAN BALOK IKATAN ANGIN KAYU /M3


1.100 M3 Balok kayu klas I 2,310,000.00 2,541,000.00
3.200 Kg Paku campuran 24,750.00 79,200.00
4.000 OH Pekerja 75,000.00 300,000.00
12.000 OH Tukang kayu 90,000.00 1,080,000.00
1.200 OH Kepala tukang kayu 100,000.00 120,000.00
0.200 OH Mandor 110,000.00 22,000.00
Total 4,142,200.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5

PEKERJAAN KOLOM/RING BALOK KAYU /M3


1.100 M3 Balok kayu klas I 2,310,000.00 2,541,000.00
12.800 Kg Paku campuran 24,750.00 316,800.00
4.000 OH Pekerja 75,000.00 300,000.00
12.000 OH Tukang kayu 90,000.00 1,080,000.00
1.200 OH Kepala tukang kayu 100,000.00 120,000.00
0.200 OH Mandor 110,000.00 22,000.00
Total 4,379,800.00

PAS. KASAU + RENG/M2


0.014 m3 Balok Kayu 2,310,000.00 32,340.00
0.150 kg Paku Biasa 24,750.00 3,712.50
0.100 OH Pekerja 75,000.00 7,500.00
0.100 OH Tukang 90,000.00 9,000.00
0.010 OH Kepala Tukang 100,000.00 1,000.00
0.005 OH Mandor 110,000.00 550.00
Total 54,102.50

PEKERJAAN RESIDU KAYU / M2


0.350 Ltr Residu 138,600.00 48,510.00
0.100 OH Pekerja 75,000.00 7,500.00
0.006 OH Mandor 110,000.00 660.00
Total 56,670.00

PASANG ATAP SENG BJLS 0.20 / M2


0.700 Lbr Atap Seng Gelombang 3"X7" 56,650.00 39,655.00
0.020 Kg Paku seng 27,500.00 550.00
0.120 OH Pekerja 75,000.00 9,000.00
0.060 OH Tukang kayu 90,000.00 5,400.00
0.060 OH Kepala tukang kayu 100,000.00 6,000.00
0.006 OH Mandor 110,000.00 660.00
Total 61,265.00

BUBUNGAN SENG PLAT BJLS 0.30 / M'


0.300 m' Seng Plat 3"X6" 30,250.00 9,075.00
0.040 Kg Paku seng 27,500.00 1,100.00
0.150 OH Pekerja 75,000.00 11,250.00
0.070 OH Tukang 90,000.00 6,300.00
0.008 OH Kepala tukang kayu 100,000.00 800.00
0.006 OH Mandor 110,000.00 660.00
Total 29,185.00
PENUTUP ATAP METAL ROOF/M2
1.02 lbr multiroof 65,000.00 66,300.00
0.2 kg Paku 44,000.00 8,800.00
0.2 OH Pekerja 75,000.00 15,000.00
0.1 OH Tukang 90,000.00 9,000.00
0.01 OH Kepala Tukang 100,000.00 1,000.00
0.001 OH Mandor 110,000.00 110.00
Total 100,210.00

BUBUNGAN ATAP MULTIROOF/M'


1.1 bh Nok multiroof 38,500.00 42,350.00
0.05 kg Paku 44,000.00 2,200.00
0.25 OH Pekerja 75,000.00 18,750.00
0.15 OH Tukang 90,000.00 13,500.00
0.015 OH Kepala Tukang 100,000.00 1,500.00
0.013 OH Mandor 110,000.00 1,430.00
Total 79,730.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5

PASANG LISTPLANK PAPAN / M'


0.010 M3 Papan kayu klas I 2,530,000.00 25,300.00
0.050 Kg Paku campuran 33,000.00 1,650.00
0.110 OH Pekerja 75,000.00 8,250.00
0.220 OH Tukang kayu 90,000.00 19,800.00
0.022 OH Kepala tukang kayu 100,000.00 2,200.00
0.005 OH Mandor 110,000.00 550.00
Total 57,750.00

@ PEKERJAAN KUSEN, PINTU DAN JENDELA

PAS. DINDING PAPAN KAYU Kelas II / M2


0.020 M3 Papan kayu klas II 1,450,000.00 29,000.00
0.250 Kg Paku 33,000.00 8,250.00
0.600 OH Pekerja 75,000.00 45,000.00
1.800 OH Tukang kayu 90,000.00 162,000.00
0.180 OH Kepala tukang kayu 100,000.00 18,000.00
0.030 OH Mandor 110,000.00 3,300.00
Total 265,550.00

PAS. PINTU TRIPLEK / M2


0.700 Lbr Triplek 3 mm 64,350.00 45,045.00
0.020 M3 Balok kayu klas I 2,310,000.00 46,200.00
0.050 Kg Paku 1/2 " - 1" 23,650.00 1,182.50
1.000 OH Pekerja 75,000.00 75,000.00
1.500 OH Tukang kayu 90,000.00 135,000.00
0.250 OH Kepala tukang kayu 100,000.00 25,000.00
0.050 OH Mandor 110,000.00 5,500.00
Total 332,927.50
PEKERJAAN KUSEN KAYU KLAS I / M3
1.100 M3 Balok kayu klas I 2,310,000.00 2,541,000.00
1.000 Kg Paku 27,500.00 27,500.00
6.000 OH Pekerja 75,000.00 450,000.00
20.000 OH Tukang kayu 90,000.00 1,800,000.00
2.000 OH Kepala tukang kayu 100,000.00 200,000.00
0.300 OH Mandor 110,000.00 33,000.00
Total 5,051,500.00

PINTU PANIL PAPAN KAYU BESI / M2


0.040 M3 Kayu klas I 2,530,000.00 101,200.00
1.000 OH Pekerja 75,000.00 75,000.00
2.500 OH Tukang kayu 90,000.00 225,000.00
0.250 OH Kepala tukang kayu 100,000.00 25,000.00
0.050 OH Mandor 110,000.00 5,500.00
Total 431,700.00

PINTU PANIL PAPAN KAYU BESI LAPIS SENG PLAT / M2


0.040 M3 Papan Kayu Besi 2,530,000.00 101,200.00
0.655 M2 Seng Plat BJLS. 30 30,250.00 19,813.75
1.000 OH Pekerja 75,000.00 75,000.00
2.500 OH Tukang 90,000.00 225,000.00
0.250 OH Kepala Tukang 100,000.00 25,000.00
0.050 OH Mandor 110,000.00 5,500.00
Total 451,513.75
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5

PEK. PINTU/JENDELA KACA BENING BINGKAI 5 MM / M2


1.100 M2 Kaca tebal 5 mm 275,000.00 302,500.00
0.030 M3 Kayu klas I 2,530,000.00 75,900.00
0.015 OH Pekerja 75,000.00 1,125.00
0.150 OH Tukang kayu 90,000.00 13,500.00
0.015 OH Kepala tukang kayu 100,000.00 1,500.00
0.007 OH Mandor 110,000.00 770.00
Total 395,295.00

PASANG KACA MATI RIBEN 5 MM / M2


1.100 M2 Kaca tebal 5 mm 302,500.00 332,750.00
0.020 M3 Kayu List 2,530,000.00 50,600.00
0.005 Kg Paku 27,500.00 137.50
0.015 OH Pekerja 75,000.00 1,125.00
0.150 OH Tukang kayu 90,000.00 13,500.00
0.015 OH Kepala tukang kayu 100,000.00 1,500.00
0.007 OH Mandor 110,000.00 770.00
Total 400,382.50

PASANG JALUSI PAPAN KAYU KLAS I / M2


0.060 M3 Papan Kayu Besi 2,530,000.00 151,800.00
0.150 Kg Paku campuran 27,500.00 4,125.00
0.500 OH Pekerja 75,000.00 37,500.00
2.000 OH Tukang kayu 90,000.00 180,000.00
0.200 OH Kepala tukang kayu 100,000.00 20,000.00
0.250 OH Mandor 110,000.00 27,500.00
Total 420,925.00
@ PEKERJAAN PLAFOND

PLAFOND TRIPLEKS t = 3 mm + RANGKA KAYU / M2


0.390 Lbr Tripleks 3 mm 64,350.00 25,096.50
0.060 Kg Paku Biasa 30,250.00 1,815.00
0.024 M3 Balok Kayu kls II 5 / 5 1,450,000.00 34,800.00
0.200 OH Pekerja 75,000.00 15,000.00
0.320 OH Tukang kayu 90,000.00 28,800.00
0.032 OH Kepala tukang kayu 100,000.00 3,200.00
0.009 OH Mandor 110,000.00 990.00
Total 109,701.50

PASANG LIS TEPI PLAFOND Tripleks / M'


1.1000 M Lis Tripleks 5,000.00 5,500.00
0.0100 Kg Paku 30,250.00 302.50
0.0500 OH Pekerja 75,000.00 3,750.00
0.0500 OH Tukang kayu 90,000.00 4,500.00
0.0050 OH Kepala tukang kayu 100,000.00 500.00
0.0030 OH Mandor 110,000.00 330.00
Total 14,882.50

@ PEKERJAAN PENGUNCI DAN PENGGANTUNG


PASANG KUNCI TANAM UNION 2 SLAAG / BH
1.000 Bh Kunci tanam 2 slaag 200,000.00 200,000.00
0.0100 OH Pekerja 75,000.00 750.00
0.5000 OH Tukang kayu 90,000.00 45,000.00
0.0100 OH Kepala tukang kayu 100,000.00 1,000.00
0.0050 OH Mandor 110,000.00 550.00
Total 247,300.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5

PASANG ENGSEL PINTU / BH


1.000 Psg Engsel pintu 4 " 39,600.00 39,600.00
0.015 OH Pekerja 75,000.00 1,125.00
0.150 OH Tukang kayu 90,000.00 13,500.00
0.015 OH Kepala tukang kayu 100,000.00 1,500.00
0.00075 OH Mandor 110,000.00 82.50
Total 55,807.50

PASANG ENGSEL JENDELA / BH


1.000 Psg Engsel jendela 3 " 24,750.00 24,750.00
0.010 OH Pekerja 75,000.00 750.00
0.100 OH Tukang kayu 90,000.00 9,000.00
0.010 OH Kepala tukang kayu 100,000.00 1,000.00
0.0005 OH Mandor 110,000.00 55.00
Total 35,555.00
PASANG GRENDEL PINTU / BH
1.000 Bh Grendel 23,100.00 23,100.00
0.020 OH Pekerja 75,000.00 1,500.00
0.200 OH Tukang kayu 90,000.00 18,000.00
0.020 OH Kepala tukang kayu 100,000.00 2,000.00
0.0010 OH Mandor 110,000.00 110.00
Total 44,710.00
PASANG GRENDEL JENDELA / BH
1.000 Bh Grendel 17,600.00 17,600.00
0.020 OH Pekerja 75,000.00 1,500.00
0.200 OH Tukang kayu 90,000.00 18,000.00
0.020 OH Kepala tukang kayu 100,000.00 2,000.00
0.001 OH Mandor 110,000.00 110.00
Total 39,210.00
PASANG KAIT PENGIKAT / BH
1.000 Bh Kait pengikat 22,000.00 22,000.00
0.015 OH Pekerja 75,000.00 1,125.00
0.150 OH Tukang kayu 90,000.00 13,500.00
0.015 OH Kepala tukang kayu 100,000.00 1,500.00
0.00075 OH Mandor 110,000.00 82.50
Total 38,207.50

PASANG HANDEL/TARIKAN JENDELA / BH


1.000 Bh Tarikan jendela 13,750.00 13,750.00
0.0150 OH Pekerja 75,000.00 1,125.00
0.1500 OH Tukang kayu 90,000.00 13,500.00
0.0150 OH Kepala tukang kayu 100,000.00 1,500.00
0.0008 OH Mandor 110,000.00 82.50
Total 29,957.50

@ PEKERJAAN ELEKTRIKAL
INSTALASI KABEL NYM/NYA 2 X 2.5 / M'
1.000 M' Kabel NYM/NYA 2 X 2.5 12,540.00 12,540.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 52,440.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
PASANG LAMPU TL 2 x 40 WATT / BH
1.000 Bh Lampu TL 40 Watt 71,500.00 71,500.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 111,400.00

PASANG LAMPU SL 20 WATT / BH


1.000 Bh Lampu SL 20 Watt 47,850.00 47,850.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 87,750.00
PASANG LAMPU PIJAR 40 WATT / BH
1.000 Bh Lampu Pijar 40 Watt 5,500.00 5,500.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 45,400.00

PASANG SAKLAR DOUBLE / BH


1.000 Bh Saklar double 24,750.00 24,750.00
0.750 Btg Cundult pipa PVC dia 5/8" - 0.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 64,650.00

PASANG SAKLAR TUNGGAL / BH


1.000 Bh Saklar tunggal 20,625.00 20,625.00
0.750 Btg Cundult pipa PVC dia 5/8" 0.00 0.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 60,525.00

PASANG STOP KONTAK / BH


1.000 Bh Stop Kontak 19,250.00 19,250.00
0.750 Btg Cundult pipa PVC dia 5/8" 0.00 0.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 59,150.00
PASANG BOX SEKRING / BH
1.000 Bh Sekring kast 68,200.00 68,200.00
0.750 Btg Cundult pipa PVC dia 5/8" 0.00 0.00
0.150 OH Pekerja 75,000.00 11,250.00
0.300 OH Instalator / Tukang listrik 90,000.00 27,000.00
0.015 OH Mandor 110,000.00 1,650.00
Total 108,100.00

PINTU TRIPLEK / M2
0.019 M3 Kayu klas I 2,530,000.00 48,070.00
0.300 Kg Paku 27,500.00 8,250.00
1.000 Lb Triplek 64,350.00 64,350.00
0.600 OH Pekerja 75,000.00 45,000.00
2.000 OH Tukang kayu 90,000.00 180,000.00
0.200 OH Kepala tukang kayu 100,000.00 20,000.00
0.030 OH Mandor 110,000.00 3,300.00
Total 368,970.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
@ PEKERJAAN INSTALASI AIR DAN SANITASI

PEK. INSTALASI AIR KOTOR PIPA PVC. DIA. 4" / M'


1.200 M' Pipa PVC. Dia. 4" 52,250.00 62,700.00
1.000 set Perlengkapan 18,287.50 18,287.50
0.081 OH Pekerja 75,000.00 6,075.00
0.135 OH Tukang 90,000.00 12,150.00
0.014 OH Kepala Tukang 100,000.00 1,350.00
0.004 OH Mandor 110,000.00 451.00
Total 101,013.50

PEK. INSTALASI AIR BERSIH PIPA GIV DIA. 1/2" / M'


1.2000 Btg Pipa . Dia. 1/2" 36,575.00 43,890.00
1.000 set Perlengkapan 12,801.25 12,801.25
0.054 OH Pekerja 75,000.00 4,050.00
0.090 OH Tukang 90,000.00 8,100.00
0.009 OH Kepala Tukang 100,000.00 900.00
0.027 OH Mandor 110,000.00 2,970.00
Total 72,711.25

PEK. PASANG KRANT AIR / BH


1.000 bh Kran air 55,000.00 55,000.00
0.025 bh Seal tape 7,000.00 175.00
0.010 OH Pekerja 75,000.00 750.00
0.100 OH Tukang 90,000.00 9,000.00
0.010 OH Kepala Tukang 100,000.00 1,000.00
0.005 OH Mandor 110,000.00 550.00
Total 66,475.00

PASANG FLOoR DRAIN / BH


1 bh Floor drain 16,500.00 16,500.00
0.01 OH Pekerja 75,000.00 750.00
0.1 OH Tukang 90,000.00 9,000.00
0.01 OH Kepala Tukang 100,000.00 1,000.00
0.005 OH Mandor 110,000.00 550.00
Total 27,800.00

PASANG KOLOM KAYU BALOK 10 X 10 / M3


1.100 M3 Kayu Balok 2,310,000.00 2,541,000.00
0.800 Kg Paku campuran 27,500.00 22,000.00
4.000 OH Pekerja 75,000.00 300,000.00
12.000 OH Tukang kayu 90,000.00 1,080,000.00
1.200 OH Kepala tukang kayu 100,000.00 120,000.00
0.200 OH Mandor 110,000.00 22,000.00
Total 4,085,000.00
PASANG WASHTAFEL + KRANT / BH
1.000 bh Westafel 825,000.00 825,000.00
1.000 set Kran air 55,000.00 55,000.00
1.000 set Perlengkapan 99,000.00 99,000.00
6.000 Kg Semen abu-abu 22,000.00 132,000.00
0.010 M3 Pasir pasang 400,000.00 4,000.00
1.200 OH Pekerja 75,000.00 90,000.00
1.450 OH Tukang 90,000.00 130,500.00
0.150 OH Kepala Tukang 100,000.00 15,000.00
0.100 OH Mandor 110,000.00 11,000.00
Total 1,361,500.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
BAK MANDI 0.3 m3 / BH
72.000 bh Batu Tela 6,000.00 432,000.00
0.801 Zak semen 125,000.00 100,150.00
0.090 M3 Pasir pasang 400,000.00 36,000.00
68.000 Bh Ubin keramik 6,500.00 442,000.00
4.080 Kg semen warna 22,000.00 89,760.00
1.960 OH Pekerja 75,000.00 147,000.00
1.330 OH Tukang 90,000.00 119,700.00
0.133 OH Kepala Tukang 100,000.00 13,300.00
0.097 OH Mandor 110,000.00 10,670.00
Total 1,390,580.00

PASANG KLOSET JONGKOK / BH


1.000 bh Kloset jongkok 201,300.00 201,300.00
0.120 Kg semen 125,000.00 15,000.00
0.010 M3 pasir pasang 400,000.00 4,000.00
1.000 OH Pekerja 75,000.00 75,000.00
1.500 OH Tukang 90,000.00 135,000.00
0.150 OH Kepala Tukang 100,000.00 15,000.00
0.160 OH Mandor 110,000.00 17,600.00
Total 462,900.00

PEK. SEPTICK TANK DAN PERESAPAN / UNIT


450.000 bh Batu tela 6,000.00 2,700,000.00
6.097 Kg Semen 125,000.00 762,150.00
0.589 M3 Pasir pasang 400,000.00 235,600.00
0.200 M3 Batu pecah 715,000.00 143,000.00
31.170 Kg Besi beton polos 10,848.63 338,151.64
0.445 Kg Kawat beton 33,000.00 14,685.00
0.134 M3 Pasir beton 400,000.00 53,600.00
0.138 M3 Pasir Urug 330,000.00 45,540.00
0.043 M3 Kayu Balok 2,530,000.00 108,031.00
0.800 Lbr Tripleks 9mm 80,000.00 64,000.00
0.920 Kg Paku Biasa 2-5" 27,500.00 25,300.00
3.000 M' Pipa PVC dia 2" 29,562.50 88,687.50
1.700 M' Pipa PVC dia 4" 52,250.00 88,825.00
35.000 % Perlengkapan 18,287.50 640,062.50
8.648 OH Pekerja 75,000.00 648,600.00
3.486 OH Tukang batu 90,000.00 313,740.00
0.500 OH Tukang pipa 90,000.00 45,000.00
0.399 OH Kepala Tukang 100,000.00 39,900.00
0.482 OH Mandor 110,000.00 53,020.00
Total 6,407,892.64

@ PEKERJAAN PENGECETAN DAN LABURAN

PEKERJAAN CAT KAYU KUSEN / M2


0.200 kg Cat meni kayu 43,450.00 8,690.00
0.150 1 Amplas 11,000.00 1,650.00
0.260 kg Cat kayu KW2 ( Cat penutup ) 57,750.00 15,015.00
0.070 OH Pekerja 75,000.00 5,250.00
0.090 OH Tukang 90,000.00 8,100.00
0.006 OH Kepala Tukang 100,000.00 600.00
0.003 OH Mandor 110,000.00 275.00
Total 39,580.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
PEKERJAAN CAT POLITUR PINTU DAN JENDELA / M2
0.150 kg Pelitur 35,750.00 5,362.50
0.372 kg Pelitur jadi 53,625.00 19,948.50
2.000 lbr Kertas Amplas 11,000.00 22,000.00
0.060 OH Tukang 90,000.00 5,400.00
0.016 OH Kepala Tukang 100,000.00 1,600.00
0.003 OH Mandor 110,000.00 275.00
Total 54,586.00

PEKERJAAN DINDING BARU / M2


0.100 kg Cat tembok KW 2 (cat dasar ) 8,717.50 871.75
0.260 kg Cat tembok KW 2 (cat penutup ) 8,717.50 2,266.55
0.070 OH Pekerja 75,000.00 5,250.00
0.063 OH Tukang 90,000.00 5,670.00
0.007 OH Kepala Tukang 100,000.00 650.00
0.003 OH Mandor 110,000.00 275.00
Total 14,983.30

PEKERJAAN DINDING LAMA / M2


0.120 kg Cat tembok KW 2 (cat dasar ) 8,717.50 1,046.10
0.180 kg Cat tembok KW 2 (cat penutup ) 8,717.50 1,569.15
0.028 OH Pekerja 75,000.00 2,100.00
0.042 OH Tukang 90,000.00 3,780.00
0.005 OH Kepala Tukang 100,000.00 500.00
0.003 OH Mandor 110,000.00 275.00
Total 9,270.25

PEKERJAAN CAT PLAFON / M2


0.100 kg Cat tembok KW 2 (cat dasar ) 8,717.50 871.75
0.260 kg Cat tembok KW 2 (cat penutup ) 8,717.50 2,266.55
0.070 OH Pekerja 75,000.00 5,250.00
0.090 OH Tukang 90,000.00 8,100.00
0.006 OH Kepala Tukang 100,000.00 600.00
0.003 OH Mandor 110,000.00 275.00
Total 17,363.30

PEKERJAAN CAT LISTPLANK / M2


0.200 kg Cat meni kayu 43,450.00 8,690.00
0.150 kg Plamir kayu 30,250.00 4,537.50
0.170 kg Cat kayu KW2 ( Cat Dasar ) 8,717.50 1,481.98
0.260 kg Cat kayu KW2 ( Cat penutup ) 8,717.50 2,266.55
0.070 OH Pekerja 75,000.00 5,250.00
0.090 OH Tukang 90,000.00 8,100.00
0.006 OH Kepala Tukang 100,000.00 600.00
0.003 OH Mandor 110,000.00 275.00
Total 31,201.03

PEKERJAAN CAT BESI PAGAR M2


0.100 Kg Cat Meni Besi anti karat 27,500.00 2,750.00
0.170 Kg Cat Dasar 51,700.00 8,789.00
0.260 Kg Cat Penutup mengkilat 51,700.00 13,442.00
0.070 OH Pekerja 75,000.00 5,250.00
0.090 OH Tukang cat 90,000.00 8,100.00
0.006 OH Kepala tukang cat 100,000.00 600.00
0.003 OH Mandor 110,000.00 275.00
Total 39,206.00
HARGA TOTAL
NO. KODE URAIAN PEKERJAAN SATUAN HARGA
( Rp. ) ( Rp. )
1 2 3 4 5
PEKERJAAN CAT ATAP SENG / M2
0.100 Kg Cat Meni Besi 27,500.00 2,750.00
0.260 Kg Cat Penutup 51,700.00 13,442.00
0.050 OH Pekerja 75,000.00 3,750.00
0.090 OH Tukang cat 75,000.00 6,750.00
0.006 OH Kepala tukang cat 100,000.00 600.00
0.003 OH Mandor 110,000.00 275.00
Total 27,567.00

ACIAN DINDING/M2
0.042 Zak Semen 125,000.00 5,250.00
0.070 Oh Pekerja 75,000.00 5,250.00
0.090 Oh tukang batu 90,000.00 8,100.00
0.006 Oh Kepala tukang batu 100,000.00 600.00
0.003 Oh Mandor 110,000.00 275.00
Total 19,475.00
PEKERJAAN PENAHAN TIMBUNAN DAN SALURAN/ 10 M'
10.000 Bh Pasangan batu tela 1 : 4 6,000.00 60,000.00
0.020 M3 Pasir Urug 330,000.00 6,600.00
1.230 M2 Plesteran 59,200.00 72,816.00
Total 139,416.00
HARGA SATUAN BAHAN DAN UPAH
KABUPATEN RAJA AMPAT TAHUN 2013
Lokasi : WAISAI, DISTRIK WAIGEO SELATAN

I. BAHAN

No. URAIAN SAT. HARGA SATUAN

1 2 3 4
A. DAFTAR HARGA BAHAN
1. BAHAN BATU

a. Batu Gunung m3 400,000.00


b. Batu Tela bh 6,000.00
c. Batu Bata Merah bh 2,500.00
d. Batu Pecah Mesin (Stone Chruser)
- Abu Batu m3 825,000.00
- Bt 1 - 2 cm' m3 715,000.00
- Bt 2 - 3 cm' m 3
715,000.00
- Bt 3 - 5 cm' m 3
715,000.00
- Bt 5 - 7 cm' m3 715,000.00

2. BAHAN KERIKIL
a. Kerikil Sungai (Bulat) m3 450,000.00
b. Kerikil Pecah Lokal m3 605,000.00

3. BAHAN PASIR
a. Pasir Pasang m3 400,000.00
b. Pasir Urug m 3
330,000.00
c. Pasir Plester m 3
400,000.00
d. Sirtu m3 220,000.00
e. Pasir Cor/Beton (Lokal) m 3
400,000.00
f. Pasir Cor/Beton (Non Lokal) m 3
858,000.00
g. Pasir Cor/Beton (Non Lokal) m3 715,000.00
4. BAHAN TANAH TIMBUNAN
a. Tanah Timbunan/Urugan Pilihan m3 120,000.00

5. BAHAN KARANG
a. Karang Kasar m3 430,000.00

6. BAHAN SEMEN
a. Semen Portland 50 Kg zak 125,000.00
b. Semen Portland 40 Kg zak 107,800.00
c. Semen Putih kg 5,500.00
d. Semen Warna kg 22,000.00

7. BAHAN LANTAI
A. Keramik Polos
a. Keramik 20 x 20 m2 71,500.00
b. Keramik 20 x 25 m 2
71,500.00
c. Keramik 30 x 30 m 2
75,000.00
d. Keramik 40 x 40 m2 82,500.00
B. Keramik Motif
a. Keramik 20 x 20 m2 93,500.00
b. Keramik 30 x 30 m2 80,300.00
c. Keramik 40 x 40 m 2
88,000.00
No. URAIAN SAT. HARGA SATUAN

1 2 3 4
d. Ubin Mozaik/Km 20 x 20 m2 82,500.00
e. Granit Tile m 2
309,100.00
f. Karpet Plastik 120 cm m1 26,400.00
g. Karpet Plastik 180 cm m1 27,500.00
h. Karpet Plastik 200 cm m 1
45,100.00
i. Karpet Bludru m1 55,000.00
j. Terpal Ukuran 3 x 4 m Lbr 93,500.00
k. Terpal Ukuran 4 x 6 m Lbr 187,000.00
l. Terpal Ukuran 6 x 8 m Lbr 374,000.00
m. Terpal Ukuran 8 x 10 m Lbr 621,500.00

8. BAHAN KAYU
a. Kayu Besi
- Balok ukuran 6 x 12 m3 2,310,000.00
- Balok ukuran 10 x 10 m 3
2,310,000.00
- Balok ukuran 5 x 10 m 3
2,310,000.00
- Balok ukuran 5 x 5 m3 2,530,000.00
- Papan ukuran 3 x 20 m3 2,530,000.00
- Papan ukuran 2.5 x 25 m 3
2,530,000.00
- Papan ukuran 2.5 x 30 m3 2,530,000.00
- Papan ukuran 3 x 30 m3 2,530,000.00
- Papan ukuran 4 x 25 m 3
2,530,000.00
b. Kayu Matoa/Lombo m 3

- Balok ukuran 10 x 10 m3 1,450,000.00


- Balok ukuran 5 x 10 m 3
1,450,000.00
- Balok ukuran 5 x 5 m 3
1,450,000.00
- Papan ukuran 2.5 x 25 m3 1,450,000.00
- Papan ukuran 3 x 20 m 3
1,450,000.00
c. Kayu untuk Begesting
- Balok ukuran 5 x 10 m3 1,400,000.00
- Balok ukuran 5 x 5 m 3
1,400,000.00
- Papan ukuran 2.5 x 30 m 3
1,400,000.00
d. Kayu mangi-mangi btg 55,000.00
e. Kayu terentang m3 66,000.00
f. Tripleks
- Tripleks ukuran 3 mm lbr 64,350.00
- Tripleks ukuran 4 mm lbr 80,000.00
- Tripleks ukuran 5 mm lbr 93,500.00
g. Multipleks
- Multipleks ukuran 10 mm lbr 111,100.00
- Multipleks ukuran 12 mm lbr 166,100.00
- Multipleks ukuran 20 mm lbr 210,100.00
h. Teak Wood
- Teak Wood ukuran 3 mm lbr 110,000.00
- Teak Wood ukuran 4 mm lbr 177,100.00
- Teak Wood ukuran 5 mm lbr 122,100.00
i. Formika
- Formika Polos lbr 100,100.00
- Formika Kembang lbr 127,600.00
j. Lambersering btg 27,500.00
k. List Profil btg 19,250.00
l. Gypsum Board btg 137,500.00
No. URAIAN SAT. HARGA SATUAN

1 2 3 4
9. BAHAN ATAP
a. Seng Gelombang
- Seng Gelombang 6 kk BJLS 20 lbr 56,650.00
- Seng Gelombang 7 kk BJLS 20 lbr 71,500.00
- Seng Gelombang 6 kk BJLS 30 lbr 74,800.00
- Seng Gelombang 7 kk BJLS 30 lbr 93,500.00
- Seng Gelombang 8 kk BJLS 20 lbr

b. Seng Plat
- Seng Plat BJLS 20 m1 24,200.00
- Seng Plat BJLS 30 m1 30,250.00
- Seng Talang m 1
22,000.00
c. Seng Plastik
- Seng Plastik Gelombang Besar 6 kk lbr 53,350.00
- Seng Plastik Gelombang Besar 7 kk lbr 67,100.00
- Seng Plastik Gelombang Kecil lbr 36,300.00
d. Polycarbonat Tebal roll
d. Metal Roof lbr 65,000.00
Noc Metal Roof lbr 38,500.00

10. BAHAN KACA


a. Kaca Bening 5 mm' lbr 275,000.00
b. Kaca Rayben 5 mm' lbr 302,500.00
c. Kaca Cermin tebal lbr 85,800.00

11. BAHAN JENDELA LOVER


a. Lover/nako 6 klip set 88,000.00
b. Lover/nako 8 klip set 121,000.00
c. Rangka Lover/nako tanpa Trali lbr 181,500.00

12. BAHAN PENGUNCI/PENGGANTUNG


a. Kunci Tanam bh. 200,000.00
b. Gembok besar bh. 49,500.00
c. Gembok kecil bh. 12,925.00
d. Kunci Laci bh. 19,250.00
e. Engsel
- Engsel Jendela pas. 24,750.00
- Engsel Pintu pas. 39,600.00
- Engsel Kupu-kupu ring nilon Pintu pas. 19,800.00
- Engsel Kupu-kupu ring nilon Jendela pas. 15,400.00
- Hak Angin Biasa pas. 13,200.00
- Hak Angin Lipat pas. 22,000.00
- Kunci Gembok bh. 28,600.00
- Grendel Lecil bh. 17,600.00
- Grendel Sedang bh. 23,100.00
- Grendel Besar bh. 31,350.00
- Tarikan jendela bh. 13,750.00
- Grendel rante bh. 27,500.00

13. BAHAN SANITAIR


a. Kloset duduk porselin bh. 550,000.00
b. Kloset jongkok Keramik bh. 201,300.00
c. Wastafel Keramik bh. 825,000.00
d. Was bak/bak cuci logam 1 lobang bh. 385,000.00
No. URAIAN SAT. HARGA SATUAN

1 2 3 4
e. Bak Mandi Feber Kotak bh. 572,000.00
f. Kran air plastik bh. 16,500.00
g. kran air kuningan bh. 55,000.00
h. Hans shower bh. 77,000.00
i. Tandon Air
- Tandon Plastik Profil Tank 400 Liter bh. 748,000.00
- Tandon Plastik Profil Tank 450 Liter bh. 880,000.00
- Tandon Plastik Profil Tank 520 Liter bh. 1,430,000.00
- Tandon Plastik Profil Tank 1100 Liter bh. 1,980,000.00
- Tandon Plastik Profil Tank 1200 Liter bh. 2,200,000.00
- Tandon Plastik Profil Tank 2200 Liter bh. 4,400,000.00
- Tandon Plastik Profil Tank 3300 Liter bh. 10,000,000.00
- Tandon Plastik Profil Tank 5200 Liter bh. 15,000,000.00

j. Bak Air Feber glass


- Bak Air Feber glass bh. 3,012,900.00
k. Pompa Dragon bh. 605,000.00
l. Mesin Pompa Air
- 100 Watt bh. 908,600.00
- 150 Watt bh. 2,228,600.00

14. BAHAN PAKU/BAUT


a. Paku
- Paku Tripleks kg. 30,250.00
- Paku Persegi kg. 33,000.00
- Paku 1/4 - 1/2 kg. 27,500.00
- Paku 1 - 3 kg. 23,650.00
- Paku 2 1/2 - 7 kg. 24,750.00
- Paku Seng Gelombang kg. 27,500.00
- Paku genteng metal kg. 44,000.00
- Paku Tembok/beton dos 37,400.00
- Paku Tembok/beton dos 27,500.00
- Timah Solder roll 46,750.00
b. Baut
- Baut + Mur f 3/8'' - 17,5 bh. 8,470.00
- Baut + Mur f 3/8'' - 15 bh. 10,285.00
- Baut + Mur f 3/8'' - 20 bh. 108,900.00
- Baut + Mur f 3/8'' - 30 bh. 18,150.00
- Baut bh. 12,100.00
- But Mur bh. 18,150.00
- Ring bh. 1,100.00

15. BAHAN KAWAT BAJA


a. Kawat Ikat kg. 33,000.00
b. Kawat Duri
- Kawat Duri Kecil roll 220,000.00
- Kawat Duri Besar roll 330,000.00
c. Kawat Ram m1 24,750.00
d. Kawat Harmonika m 1
27,500.00
e. Kawat Nyamuk Plastik m1 16,584.23
f. Kawat Nyamuk Besi m1 33,074.33
g. Kawat Ayakan m 1
24,750.00
No. URAIAN SAT. HARGA SATUAN

1 2 3 4
16. BAHAN BESI BETON
a. Besi Beton Bulat
- Diamater 6 mm btg. 44,000.00
- Diamater 8 mm btg. 69,300.00
- Diamater 10 mm btg. 103,950.00
- Diamater 12 mm btg. 146,300.00
- Diamater 16 mm btg. 242,000.00
- Diamater 19 mm btg. 301,400.00
- Besi Beton Polos Kg
b. Besi Beton Ulir
- Diamater 13 mm btg. 162,800.00
- Diamater 16 mm btg. 267,300.00
- Diamater 19 mm btg. 345,400.00
- Diamater 19 mm
- Besi Strip Kg

17. BAHAN PIPA UNTUK PEKERJAAN


BANGUNAN
a. Pipa PVC
- Diameter 1/2" btg. 33,000.00
- Diameter 3/4" btg. 41,250.00
- Diameter 1" btg. 49,500.00
- Diameter 1 1/2" btg. 96,250.00
- Diameter 2" btg. 118,250.00
- Diameter 2 1/2" btg. 154,000.00
- Diameter 3" btg. 165,000.00
- Diameter 4" btg. 209,000.00
b. Pipa GIV
- Diameter 1/2" btg. 146,300.00
- Diameter 3/4" btg. 217,800.00
- Diameter 1" btg. 327,800.00
- Diameter 1 1/2" btg. 402,600.00
- Diameter 2" btg. 523,600.00
- Diameter 2 1/2" btg. 627,000.00
- Diameter 3" btg. 847,000.00

18. BAHAN CAT


a. Cat Tembok
- Cat Tembok 5 kg klg. 53,625.00
- Cat Tembok 20 kg klg. 174,350.00
b. Cat Kayu
- Cat Dasar kg. 43,450.00
- Cat Kilap kg. 57,750.00
c. Cat Aluminium kg. 38,500.00
d. Cat genteng kg. 26,125.00
e. Cat Besi
- Cat Besi kg. 51,700.00
- Menie ltr. 27,500.00
f. Plamur Tembok kg. 77,000.00
g. Residu / Minyak Gegisting kg. 138,600.00
h. Teak oil ltr. 34,100.00
i. Plitur kg. 35,750.00
j. Dempul kg. 30,250.00
No. URAIAN SAT. HARGA SATUAN

1 2 3 4
k. Minyak Cat/Thinner ltr. 33,000.00
l. Amplas Kayu m' 11,000.00
m. Lem Kayu kg. 24,750.00
n. Kuas rol bh. 26,400.00
o. Kuas Biasa
- Kuas 1" bh. 4,950.00
- Kuas 2" bh. 9,625.00
- Kuas 2,5" bh. 12,925.00
- Kuas 3" bh. 17,050.00
18. BAHAN INSTALASI LISTRIK
a. Lampu TL Lengkap
- Lampu TL Lengkap 20 watt bh. 60,500.00
- Lampu TL Lengkap 40 watt bh. 71,500.00
- Lampu TL Lengkap 60 watt bh. 82,500.00
b. Lampu SL
- Lampi SL 5 Watt bh. 27,500.00
- Lampi SL 8 Watt bh. 30,800.00
- Lampi SL 11 Watt bh. 33,000.00
- Lampi SL 14 Watt bh. 36,300.00
- Lampi SL 18 Watt bh. 42,075.00
- Lampi SL 23 Watt bh. 47,850.00
- Lampu SL bh.

c. Lampu Pijar
- Lampu Pijar Merah bh. 5,500.00
- Lampu Pijar Kuning bh. 5,500.00
- Lampu Pijar Hijau bh. 5,500.00
d. Sekering Otomat Unit 79,200.00
e. Sekering Box bh. 68,200.00
f. Kabel NYM
- Kabel NYM 1 x 2,5 mm m1 7,700.00
- Kabel NYM 2 x 2,5 mm m 1
12,540.00
- Kabel NYM 3 x 2,6 mm m1 16,500.00
g. Kabel NYA
- Kabel NYA 1 x 1,5 mm Merah m1 3,850.00
- Kabel NYM 1 x 1,5 mm Hitam m1 3,850.00
- Kabel NYM 1 x 2,5 mm Merah m 1
4,950.00
- Kabel NYM 3 x 2,5 mm Hitam m1 4,950.00
h. Saklar Tunggal bh. 20,625.00
i. Saklar Ganda bh. 24,750.00
j. Stop Kontak bh. 19,250.00
Cundult pipa PVC dia 5/8" btg
19. BAHAN ASPAL kg 11,220.00

20. BAHAN BAHAN BAKAR DAN OLIE


a. Minyak Tanah ltr 6,600.00
b. Bensin ltr 7,150.00
c. Solar ltr 8,800.00
d. Minyak Pelumas ltr 44,000.00
HARGA SATUAN BAHAN DAN UPAH
KABUPATEN RAJA AMPAT TAHUN 2013
Lokasi : WAISAI, DISTRIK WAIGEO SELATAN

II. UPAH

No. URAIAN SAT. HARGA SATUAN

1 2 3 4

B. DAFTAR HARGA UPAH


1. Mandor Lapangan H/O 110,000.00
2. Mekanik H/O 105,000.00
3. Mekanik Pembantu H/O 80,000.00
4. Tukang Kepala H/O 100,000.00
5. Tukang Kayu H/O 90,000.00
6 Tukang Batu H/O 90,000.00
7 Tukang Besi H/O 90,000.00
8 Tukang Cat H/O 80,000.00
9 Tukang Gali H/O 80,000.00
10 Tukang Las H/O 90,000.00
11 Tukang Listrik H/O 90,000.00
12 Tukang pipa H/O 90,000.00
13 Operator Terlatih H/O 100,000.00
14 Pembantu Operator H/O 80,000.00
15 Supir H/O 90,000.00
16 Pembantu Supir / Kenek H/O 80,000.00
17 Pekerja H/O 75,000.00
TIME SCEDULLE
PEKERJAAN : PEMBANGUNAN SANGGAR PKK
LOKASI : di 30 KABUPATEN RAJA AMPAT
T.A : 2012

KUANTITAS RENCANA KERJA


NO. URAIAN PEKERJAAN BOBOT BULAN I BULAN II BULAN III BULAN IV BULAN III BULAN IV
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

I PEKERJAAN PERSIAPAN PENDAHULUAN 5.84 0.97 0.97 0.97 0.97 0.97 0.97 - - - -

II PEKERJAAN TANAH DAN PASIR 5.04 1.26 1.26 1.26 1.26

III PEKERJAAN PASANGAN DAN BETON 12.39 2.06 2.06 2.06 2.06 2.06 2.06 - -

IV PEKERJAAN DINDING DAN LANTAI 17.45 3.49 3.49 3.49 3.49 3.49 - - - - - - - -

V PEKERJAAN KAYU,KUSEN,PINTU DAN JENDELA 19.99 4.00 4.00 4.00 4.00 4.00 - - - - - -

VI PEKERJAAN ATAP DAN PLAFOND 21.96 4.39 4.39 4.39 4.39 4.39 - - - - 0.88 0.88 0.88 0.88

VII PEKERJAAN PENGUNCI DAN PENGGANTUNG 3.14 1.57 1.57 - - - -

VIII PEKERJAAN PENGECATAN DAN LABURAN 9.96 3.32 3.32 3.32 - - - - - -

IX #REF! #REF! #REF! #REF! - - - -

X PEKERJAAN SANITAIR 3.25 0.65 0.65 0.65 0.65 0.65 - - - - 0.13 0.13 0.13 0.13 0.13

XI PEKERJAAN AKHIR 0.99 0.99 -

(A) RENCANA BOBOT MINGGUAN 0.97 2.23 1.26 3.33 3.33 6.06 7.04 10.92 14.59 15.85 #REF! #REF! 1.64 - - - - 1.01 1.01 1.01 1.01 0.13

(B) JUMLAH BOBOT MINGGUAN 0.97 3.21 4.47 7.79 11.12 17.18 24.22 35.13 49.73 65.58 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

Waisai, 1 juni 2011 Waisai, 1 juni 2011 Waisai, 1 juni 2011


penawar penawar penawar
CV. SUMBER REJEKI BERSAMA CV. SUMBER REJEKI BERSAMA CV. SUMBER REJEKI BERSAMA

H. HIKMAT RAHIM H. HIKMAT RAHIM H. HIKMAT RAHIM


Direktur Direktur Direktur
TIME SCEDULE
PEKERJAAN : PEMBANGUNAN SANGGAR PKK
LOKASI : di 30 KABUPATEN RAJA AMPAT
T.A : 2012

REALISASI
NO. URAIAN PEKERJAAN TOTAL HARGA BOBOT BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5 BULAN 6 KET
MG 1 MG 2 MG 3 MG 4 MG 1 MG 2 MG 3 MG 4 MG 1 MG 2 MG 3 MG 4 MG 1 MG 2 MG 3 MG 4 MG 1 MG 2 MG 3 MG 4 MG 1 MG 2 MG 3 MG 4

I PEKERJAAN PERSIAPAN PENDAHULUAN Rp 7,378,290.00 5.84 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58 0.58

II PEKERJAAN TANAH DAN PASIR Rp 6,376,935.00 5.04 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36

III PEKERJAAN PASANGAN DAN BETON Rp 15,660,966.00 12.39 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24 1.24

IV PEKERJAAN DINDING DAN LANTAI Rp 22,062,107.00 17.45 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87 0.87

V PEKERJAAN KAYU,KUSEN,PINTU DAN JENDELA Rp 25,276,294.95 19.99 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33 1.33

VI PEKERJAAN ATAP DAN PLAFOND Rp 27,760,310.25 21.96 1.46 1.46 1.46 1.46 1.46 1.46 1.46 1.46 1.46 1.46 1.46 1.46 1.46 1.46

VII PEKERJAAN PENGUNCI DAN PENGGANTUNG Rp 3,973,610.00 3.14 0.16 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31

VIII PEKERJAAN PENGECATAN DAN LABURAN Rp 12,588,341.40 9.96 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

IX PEKERJAAN SANITAIR Rp 4,110,541.50 3.25 0.65 0.65 0.65 0.65 0.65 0.65 0.65 0.65

X PEKERJAAN AKHIR Rp 1,250,000.00 0.99 0.25 0.25 0.25 0.25

Rp 126,437,396.10 100
Bobot/mingggu Rp 12,643,739.61 0.58 0.94 0.36 1.60 4.39 3.80 5.27 5.27 6.01 5.58 5.58 5.58 6.80 4.98 4.98 5.63 6.21 5.63 5.31 5.31 4.68 3.23 1.48 0.83
Bobot Komulatif Rp 139,081,135.71 0.58 1.53 1.89 3.49 7.87 11.68 16.95 22.21 28.22 33.80 39.39 44.97 51.77 56.75 61.73 67.36 73.57 79.20 84.51 89.83 94.51 97.73 99.22 100

Waisai, 08 Mei 2012


Penwar
PT. CAHAYA SAWITTO

H. ANDI SAU
Direktur Utama
DAFTAR BERAT BESI BETON POLOS

NO UKURAN BERAT SAT

1 Besi Beton 6 mm x 12 m 2.66 Kg


2 Besi Beton 7 mm x 12 m 3.63 Kg
3 Besi Beton 8 mm x 12 m 4.47 Kg
4 Besi Beton 9 mm x 12 m 6.00 Kg
5 Besi Beton 10 mm x 12 m 7.40 Kg
6 Besi Beton 11 mm x 12 m 8.95 Kg
7 Besi Beton 12 mm x 12 m 10.70 Kg
8 Besi Beton 16 mm x 12 m 19.00 Kg
9 Besi Beton 19 mm x 12 m 26.80 Kg
10 Besi Beton 22 mm x 12 m 35.80 Kg
11 Besi Beton 25 mm x 12 m 46.20 Kg
12 Besi Beton 28 mm x 12 m 58.00 Kg
13 Besi Beton 32 mm x 12 m 75.72 Kg

DAFTAR BERAT BESI STRIP/ FLAT BARS

NO UKURAN BERAT SAT

1 1/4'' X 4 '' X 6 m 29.50 Kg


2 5/16'' X 1 '' X 6 m 9.50 Kg
3 5/16'' X 1 '' X 1/2 x 6 m 12.20 Kg
4 5/16'' X 2 '' X 6 m 18.40 Kg
5 3/8'' X 1 '' X 6 m 10.60 Kg
6 3/8'' X 1 1/4 '' X 6 m 14.50 Kg
7 3/8'' X 1 1/2 '' X 6 m 16.00 Kg
8 3/8'' X 2 '' X 6 m 21.20 Kg
9 3/8'' X 2 1/2 '' X 6 m 27.60 Kg
10 3/8'' X 3 '' X 6 m 32.00 Kg
11 3/8'' X 4 '' X 6 m 42.50 Kg
12 3/8'' X 6 '' X 6 m 64.00 Kg
13 1/2'' X 1 1/2 '' X 6 m 21.50 Kg
14 1/2'' X 2 '' X 6 m 31.50 Kg
15 1/2'' X 3 '' X 6 m 42.40 Kg
16 1/2'' X 4 '' X 6 m 56.50 Kg
17 1/2'' X 6 '' X 6 m 85.00 Kg
18 1/2'' X 2 '' X 6 m 37.80 Kg
DAFTAR BERAT BESI BETON ULIR

NO UKURAN BERAT SAT

1 D 10 mm x 12 m 7.40 Kg
2 D 13 mm x 12 m 12.48 Kg
3 D 16 mm x 12 m 18.96 Kg
4 D 19 mm x 12 m 26.76 Kg
5 D 22 mm x 12 m 35.76 Kg
6 D 25 mm x 12 m 46.20 Kg
7 D 29 mm x 12 m 62.28 Kg
8 D 32 mm x 12 m 75.72 Kg
44,000 16,541.35

69,300 15,503.36

103,950 14,047.30

146,300 13,672.90
14,941.23
METODE PELAKSANAAN PEKERJAAN

PEMBANGUNAN SANGGAR PKK


30 KAMPUNG KAB. RAJA AMPAT
DISTRIK WAIGEO SELATAN
TAHUN ANGGARAN 2012

A. Methode Pelaksanaan / Rencana Kerja

Untuk Melaksanakan pekerjaan mengacu dari syarat dan spesifikasi teknis yang tertuang dalam dokumen lelang, ada pun
point utama pekerjaan yaitu sebagai berikut :

I PEKERJAAN PERSIAPAN PENDAHULUAN


II PEKERJAAN TANAH DAN PASIR
III PEKERJAAN PASANGAN DAN BETON
IV PEKERJAAN DINDING DAN LANTAI
V PEKERJAAN KAYU,KUSEN,PINTU DAN JENDELA
VI PEKERJAAN ATAP DAN PLAFOND
VII PEKERJAAN PENGUNCI DAN PENGGANTUNG
VIII PEKERJAAN PENGECATAN DAN LABURAN
IX PEKERJAAN SANITAIR
X PEKERJAAN AKHIR

Dari Point Pekerjaan tersebut akan di koordinir oleh Kepala Proyek dan 2 (dua) orang Pelaksana dibantu Surveyor dan tenga
Bantu lainnya :

B. URUTAN KERJA

Seperti diuraikan dalam rencana kerja, urutan pelaksanaan pekerjaan adalah sebagai berikut :

Pekerjaan Utama Meliputi :

I PEKERJAAN PERSIAPAN PENDAHULUAN

Pekerjaan Pembangunan Sanggar PKK yang meliputi :

1. Mobilisasi dan Demobilisasi


Memobilisasi alat yang diperlukan dlm pekerjaan, Tenaga Kerja Dan Bahan Ke 30 Kampung.

2. Pembersihan dan Perataan Tanah


Pembersihan dan Perataan Tanah Pada posisi bangunan Lengkap

3. Direksi Keet/Gudang Barang


Pembangunan Direksi Keet Dan gudang Barang Dan Peralatan.

4. Penguran Dan Pemasangan


Melaksanakan Pengukuran Lapangan dan pemasangan patok dengan menggunakan meter dan
waterpas atau thedolit guna pembuatan gambar kerja (shop drawing) dan selanjutnya dasar untuk
pembuatan gambar setelah selesai pekerjaan atau (As Build Drawing) serta pengambilan Dokumentasi
(Fhoto 0%).
II PEKERJAAN TANAH DAN PASIR

Pekerjaan Tanah Dan Pasir sesuai rencana dengan langkah kerja sebagai berikut :
1. Galian Tanah Pondasi
Galian Tanah Untuk Pondasi Dikerjakan Secara Manual Dan menggunakan Pekerja diawasi Oleh Satu
orang mandor.

2. Urugan Tanah Kembali


Urugan Tanah Kembali Ini Dilaksanakan Oleh Pekerja dan Diawasi Satu Orang Mandor, Pekerjaan
Ini dilaksanakan Pada saat Pemasangan Pondasi selesai dilaksanakan.

3. Urugan Tanah Peninggian Lantai


Urugan Tanah Peninggian Lantai dilakukan guna mendapatkan elevasi lantai, yang dilaksanakan oleh
Beberapa orang Pekerja dan diawasi oleh satu orang mandor.

4. Urugan Pasir Bawah Lantai


Pekerjaan Ini Sama Funsi Dan Pelaksanaannya Dengan item sebelumnya tapi menggunakan Pasir
Urug sesuai spesifikasi Tehnik.

III PEKERJAAN PASANGAN DAN BETON


Pekerjaan ini Meliputi pekerjaan sebagai berikut :
1. Pasangan pondasi batu kali campuran 1: 4
Pasangan pondasi batu kali campuran 1: 4 dilaksanakan oleh : beberapa pekerja, Tukang Batu, Kepala
Tukang batu Dan Mandor komposisi adukan Disesuaikan dengan Sepesifikasi Tehnik sesuai BSN
SNI.
2. Pasangan Kolom Kayu 10x10 ky klass 1
Pasangan Kolom Kayu 10x10 ky klass 1 ini dilaksanakan setelah Pemasangan pondasi, Pemasangan
Klom kayu Dikerjakan Oleh Beberapa Pekerja, Tukang Kayu, Kepala Tukang Kayu, Dan mandor.
Bahan Dan Ukuran Sesuai Dengan Yang Ditentukan.

3. Ring balok 5x10 Kayu Kelas 1

IV PEKERJAAN DINDING DAN LANTAI

Pekerjaan Tanah Meliputi Beberapa Item Pekerjaan sebagai berikut :

1. Pasangan Dinding Batu


Pasangan Dinding Batu Ini dilaksanakan Oleh Berapa Pekerja, Tukang batu, Kepala Tukang Batu dan
Mandor. Kompisisi Adukan Sesuai spesifikasi tehnik sebagai pedoman pekerjaan.
2. Plesteran dan Acian
Plesteran Ini dilakukan setelah Pekerjaan Pemasangan Dinding Batu bata.

3. Cor Lantai Dengan Beton Tanpa Tulangan.


V PEKERJAAN KAYU,KUSEN,PINTU DAN JENDELA

Pekerjaan Kayu, Kusen, Pintu Dan Jendela Beberapa Item Pekerjaan sebagai berikut :

─ Pas. Kusen pintu, jendela dan ventilasi


─ Pas. Pintu paneil papan kayu besi
─ Pas. Pintu Double Tripleks
─ Pas. Jalusi papan kayu besi 2/10
─ Pas.Jendela Kaca Ugkit
─ Pas. Dinding kayu Kelas II
─ Pas. Dinding Partisi Tripleks 3mm

Semua Item Pekerjaan Pelaksanaan, dan bahan Sesuai dengan spesifikasi yang telah
ditentukan

VI PEKERJAAN ATAP DAN PLAFOND

Pekerjaan Kayu, Kusen, Pintu Dan Jendela Beberapa Item Pekerjaan sebagai berikut :

─ Pasangan kuda-kuda 5/10 kayu besi


─ Pasangan gording 5/10 kayu besi
─ Pasangan skor angin 5/10 kayu besi
─ Pas. Atap Seng bjls 20
─ Nok Seng Plat
─ Pasangan lisplank papan kayu besi 2/20
─ Plafond tripleks 3mm dan rangka plafon kayu klas II
─ List Plafond

Semua Item Pekerjaan Pelaksanaan, dan bahan Sesuai dengan spesifikasi yang telah
ditentukan

VII PEKERJAAN PENGUNCI DAN PENGGANTUNG

Pekerjaan Kayu, Kusen, Pintu Dan Jendela Beberapa Item Pekerjaan sebagai berikut :

─ Pasang kunci tanam 2 slag ( setara yalle)


─ Pasang engsel pintu 4"
─ Pasang engsel jendela 3"
─ Pasang grendel jendela
─ Pasang hak angin jendela

Semua Item Pekerjaan Pelaksanaan, dan bahan Sesuai dengan spesifikasi yang telah
ditentukan
VIII PEKERJAAN PENGECATAN DAN LABURAN

Pekerjaan Kayu, Kusen, Pintu Dan Jendela Beberapa Item Pekerjaan sebagai berikut :

─ Cat Meni Kayu


─ Cat kusen
─ Cat kilap kayu pintu dan jendela dan Jalusi
─ Cat dinding Tembok dan Papan Luar dalam
─ Cat Atap Seng
─ Cat Plafon

Semua Item Pekerjaan Pelaksanaan, dan bahan Sesuai dengan spesifikasi yang telah
ditentukan

IX PEKERJAAN SANITAIR

Pekerjaan Kayu, Kusen, Pintu Dan Jendela Beberapa Item Pekerjaan sebagai berikut :

─ Pemasangan kloset jongkok


─ Pembuatan Septictank
─ Pemas. Instalasi air kotor pipa Ø 4"
─ Pemas. Instalasi air bersih pipa Ø 2"
─ Pemasangan Kran Air 1/2"

Semua Item Pekerjaan Pelaksanaan, dan bahan Sesuai dengan spesifikasi yang telah
ditentukan

X PEKERJAAN AKHIR

Pekerjaan yang di maksud adalah pembuatan laporan dan dokumentasi selama pekerjaan dilakukan/ berlangsung
mulai dari nol sampai selesai kemudian laporan dan dokumentasi tersebut diserahkan pada Direksi pelaksanaan

Dokumentasi dan laporan yang diserahkan adalah :


Foto-foto Dokumentasi pelaksanaan pekerjaan, dalam bentuk album mulai dari :
- Fhoto 0 %
- Fhoto 25 %
- Fhoto 50 %
- Fhoto 75 % dan
- Fhoto 100 %
Laporan –laporan kegiatan, berupa Lap. Harian, Mingguan, Bulanan.
Berita Acara sehubungan dengan pelaksanaan pekerjaan dilengkap dgn MC
Gambar – gambar kerja dibuat atas petunjuk Direksi Pelaksanaan
Gambar As-Built drawing sudah harus diserahkan paling lambat sebelum pemeriksaan PHO/FHO.

Dari uraian pokok pekerjaan tersebut diatas waktu pelaksanaan dapat dilaksanakan secara bersamaan atau
berurutan sesuai dan tidak saling mendahului, dengan keadaan dan tersedianya bahan–bahan, alat kerja dan
tenaga kerja. Sehingga pekerjaan tersebut bisa dipacu dan diselesaikan sesuai dengan waktu yang telah
ditentukan.

Demikan metode pekerjaan ini kami buat hanya sebagai penuntun dan petunuk kelak jika kami dipercaya

sebagai pelaksana. Dari keseluruhan pekerjaan-pekerjaan tersebut di atas di rencanakan selesai dalam waktu 180

(Seratus Delapan Puluh) Hari Kalender berdasarkan rencana kerja Time Schedule yang ada.

WAISAI, 08 Maret 2013


Dibuat Oleh :
PEMILIK BANGUNAN

Ir. H. SUDIRMAN
0