NO PEKERJAAN VOLUME SAT JUMLAH
SATUAN
1 2 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Boupla 1 Ls Rp 70,375.0 Rp 70,375.0
JUMLAH Rp 70,375.0
V PEKERJAAN BETON
1 Pondasi Strous Pile 2 27 M1 Rp 114,655.0 Rp 3,095,685.0
Sloof 20/40 3.277 M3 Rp 3,692,906.3 Rp 12,100,915.2
3 Sloof 20/30 0.360 M3 Rp 3,692,906.3 Rp 1,329,446
4 Kolom 20/40 Lt-1 1.728 M3 Rp 3,713,637.5 Rp 6,417,165.6
5 Kolom praktis 15/20 1.404 M3 Rp 114,655.0 Rp 160,976
6 Balok 20/40 3.277 M3 Rp 4,244,000.0 Rp 13,906,739
7 Balok 20/30 0.360 M3 Rp 4,244,000.0 Rp 1,527,840
8 Plat Tebal 12 cm Lt-2 9 6.931 M3 Rp 3,494,592.5 Rp 24,221,720
Kolom 20/40 Lt-2 1.680 M3 Rp 3,713,637.5 Rp 6,238,911
10 Kolom praktis 15/20 Lt-2 11 0.315 M3 Rp 114,655.0 Rp 36,116
Balok 20/30 Lt-2 1.886 M3 Rp 4,244,000.0 Rp 8,005,882
12 Rink Balk Lt-2 15/15 9.200 M3 Rp 138,542.5 Rp 1,274,591
13 Plat Kanopi Tebal 12 cm Lt-atap 2.560 M3 Rp 3,494,592.5 Rp 8,944,759
14 Plat Tangga 1.962 M3 Rp 3,494,592.5 Rp 6,856,390
JUMLAH Rp 94,117,136
NO PEKERJAAN HAFRGA
VOLUME SAT JUMLAH
SATUAN
1 2 4 5 6 7
X PEKERJAAN PENGECATAN
1 Pengecatan tembok baru ( 1lapis 91.912 M2 Rp 18,947.3 Rp 1,741,479.7
plamuur, 1 lapis cat dasar, 2 lapis cat
2 Pengecatan tembok baru exterior 137.868 M2 Rp 96,433.0 Rp 13,295,024.9
JUMLAH Rp 15,036,504.5
XIV BOP
(Perencanaan,Pengawasan Pekerjaan dan 6% Rp 21,747,132,- Rp 21,747,132,-
Pelaporan)
Pajak (PPN dan PPH)
Rp 45,306,525,- Rp 45,306,525,-
JUMLAH Rp 67,053,657,-