KAJIAN TEKNIS
KEUNTUNGAN PEMASANGAN SSVT DI GITET 500 KV PERANAP
Kontrak No : 0740.PJ/DAN.02.02/DIR/2017
PR.SMT.PUSMANPRO.37
GITET 500 KV PERANAP PT PLN (PERSERO) PUSMANPRO UPMK IV
DAFTAR ISI
BAGIAN 1
PENDAHULUAN
Progress
BOBOT
NO ITEM PEKERJAAN s/d saat Deviasi
(%)
ini
A GARDU INDUK
A.1 GI Tegangan Ekstra Tinggi 500 kV Peranap
Pengadaan Material Termasuk Transportasi,
1. 75,0023 71,2767
Pemasangan Commisioning Dan Asuransi
2. Installation Services For Civil Works 24,9977 22,1731
TOTAL SEMUA 100,000 93,4498
Gambar 1. Tabel pencapaian progres hingga bulan Juni 2022.
SSVT memiliki koneksi fase langsung ke ground dengan insulasi galvanik antara
belitan primer dan sekunder, yang digulung di atas inti magnet yang sama dengan insulasi
independen. Mereka menyajikan kerugian rendah dengan perlindungan impedansi untuk
membatasi arus gangguan trafo tegangan ini dapat berupa kertas minyak atau isolasi
SF6.
SSVT dengan insulasi kertas minyak (Gambar 3 kiri) dibuat dengan inti magnetik
di dalam tangki logam dengan gulungan primer dan sekunder di sekitarnya. Konduktor
utama tertutup oleh bushing kapasitif yang terdiri dari pelindung dan lapisan kertas isolasi
yang diisi dengan minyak. Untuk mengontrol perubahan level oli, mereka dilengkapi
dengan bellow metalik.
SSVT dengan insulasi gas (Gambar 3 kanan) dibuat dengan inti magnetik di
dalam tangki logam dengan gulungan primer dan sekunder di sekitarnya. Gulungan ini
terbuat dari kabel listrik tahan panas yang dilapisi resin sintetis dan lapisan plastik dengan
ketahanan dielektrik yang tinggi dan kinerja termal dan mekanik yang sangat baik. SF6
dan lapisan plastik ini membentuk isolasi listrik. Katup input untuk gas SF6 disediakan di
sisi tangki bersama dengan manometer untuk memantau tekanan gas.
BAGIAN II
PERMASALAHAN
2.1. KRONOLOGIS
Kronologis singkat Pekerjaan Pembangunan GI Tegangan Ekstra Tinggi 500 kV
Peranap secara umum dijabarkan berikut :
No Tanggal Deskripsi
BAGIAN III
HASIL EVALUASI / KAJIAN
C. Minutes of meeting
- MOM tanggal 13 Maret 2020 pembahasan Atk & Eot Gitet 500 Kv Peranap
Gardu Induk Peranap merupakan salah satu Gardu Tegangan Ekstra Tinggi yang
terkoneksi melalui Jaringan Tegangan Tinggi 500kV di Sumatera. Detail status
saat ini dapat diketahui dari gambar di bawah ini, sesuai rilis oleh PLN.
Catu/sumber daya yang sangat andal, karena daya diambil langsung dari saluran
HV/transmisi, yang memiliki tingkat keandalan yang jauh lebih tinggi dari pada
saluran distribusi.
2. Hemat biaya.
Biaya pemasangan umumnya lebih rendah, dan biaya hidup pasti lebih rendah,
karena tidak perlu membayar energi ke pihak ke-3.
3. Desain bebas perawatan dan umur panjang
SSVT hanya membutuhkan lebih sedikit perawatan. Ini adalah salah satu
keuntungan menggunakan SSVT untuk daya bantu. .
4. Pasokan layanan bantu independen.
Pengguna tidak harus bergantung pada pihak ketiga, seperti utilitas
distribusi,pemasok bahan bakar, dll. Mengambil daya langsung dari saluran HV di
switchyard dapat menyebabkan ketergantungan yang lebih sedikit. Selama garis
HV diberi energi, daya tersedia. Tidak perlu koordinasi antar pihak karena kekuatan
tambahan dimiliki oleh P3BS atau unit distribusi. Pemilik dapat dengan mudah
melakukan penutupan dan pembukaan saklar tanpa campur tangan dari pihak lain.
BAGIAN IV
KESIMPULAN
Station Service Voltage Transformers (SSVT) juga dikenal sebagai Power Voltage
Transformers (PVT) digunakan untuk memasok daya Tegangan Rendah langsung dari
saluran Tegangan Tinggi hingga 550kV. Terletak di dalam gardu induk sendiri,
mereka dapat menyediakan daya hingga 333kVA per fase dengan cara yang andal
dan hemat biaya. Dengan semua pertimbangan yang disebutkan, solusi untuk memasok
layanan tambahan dengan SSVT adalah solusi terbaik sebagai sumber utama layanan
tambahan gardu induk, dengan generator diesel sebagai cadangan. Dan memiliki
beberapa keunggulan mendasar dibadingkan penggunaan sumber daya dari saluran
distribusi atau LV line, yaitu :
Selanjutnya proses persiapan dan administrasi amandemen dapat dilakukan setelah ada
pembahasan dan kesepakatan para pihak sebagai tindak lanjut penyelesaian progress
pekerjaan Pembangunan GITET 500 KV Peranap bersama Direksi Pekerjaan dan/atau
pihak terkait lainnya yang mewakili. Selanjutnya pelaksana juga harus memastikan dan
melakukan perubahan terkait waktu jaminan pelaksanaan sesuai dengan kesepakatan
perubahan waktu dari para pihak.
DAFTAR
LAMPIRAN
C As commented 05.06.2021 RY UA UA
B Re-Issued For Approval 14.12.2020 RY UA UA
A For Approval 17.07.2020 RY UA UA
Rev. Description Date Designed Checked Approved
Owner :
PT PLN ENJINIRING
Project :
Title :
PLN Dwg. No. :
Responsible Dept. : Created by : Checked by : Approved by : Format :
RY UA UA
PGGI 17th-Jul, 2020 17th-Jul, 2020 17th-Jul, 2020 A4 size
Doc. Type : ☑ For Approval □ For Information □ Other
Doc. Status: □ Approved □ Approved on Condition □ Not Approved
PT ABB Sakti Industri Contractor
Dwg/Doc. No. 1HID1-1-8055-B755-1 Rev. C
Total __ Pages (including this cover Sheet)
TECHNICAL PARTICULAR AND GUARANTEE
System Voltage
1. Rated frequency (Fr) Hz 50 50
2. Highest Voltage for equipment (Um) kVrms 550 550
3. Insulation Class :
- Power frequency withstand voltage kVrms 680 680 (primary); 3 (secondary)
- Lightning impulse withstand voltage kVp 1550 1550
- Switching impulse withstand voltage kVp 1175 1175
Operating Conditions
4. Rated primary voltage (Upr) kV 500/√3 500/√3
5. Rated secondary voltage (Usr) kV 0.4/√3 0.4/√3
6. Rated overvoltage factor to be mentioned 1.2Un for cont.; 1.5Un for 30s
7. Windings power kVA 100 100
8. Rated secondary current A to be mentioned 433
9. Rated short circuit current (1s) kA to be mentioned N/A
10. Rated dynamic current kA to be mentioned N/A
Environmental Conditions
11. Min. operating temperature ᵒC to be mentioned -10
12. Max operating temperature (shade conditions) ᵒC to be mentioned +45
13. Relative humidity % to be mentioned As per IEC
14. Altitude above sea level m to be mentioned ≤1000
2 of 4
TECHNICAL PARTICULAR AND GUARANTEE
Insulator
21. Material - Color to be mentioned Polimeric
22. Creepage distance mm/kV 25 25
23. Min. flashover distance mm to be mentioned 5050
24. Static withstand loads N to be mentioned 2100
25. Insulation fluid to be mentioned 100% SF6
Others
26. Impedance % to be mentioned <9
27. Type of tapping to be mentioned N/A
28. Number of taps to be mentioned 0
29 Maximum losses for:
No load losses (at rated voltage) W to be mentioned 642
Load losses at rated load W to be mentioned 703
30. Gas pressure indicator to be provided Yes, provided (2 alarm)
31. Leakage rate of gas per Annum % to be mentioned <0.5%
32. Total height mm to be mentioned 7400
33. Type Test Report to be provided Yes, provided
3 of 4
PT PLN (Persero) Unit Induk Pembangunan KSO PT ABB Sakti Industri - PT Waskita Karya (Persero) Tbk. PT PLN Enjiniring
Sumatera Bagian Tengah
CONTRACTOR'S REPLY
No. No. Gambar Title Rev. Status Tanggapan PLN Jawaban Kontraktor
2. Pada TPG impedance < 8 % namun pada type test 2. Nilai aktual adalah < 9 %. Nilai < 8 % merupakan teori
impedance < 9 %. Mohon dikoreksi perhitungan.
1
SSVT
OUTLINE DRAWING
DESCRIPCION
DESCRIPTION
Terminal primario
2.-
Primary terminal
Toma de tierra
3.-
Earthing terminal
5360
Caja bornes
4.-
Terminal box
7400
Cáncamo elevación
5.-
Lifting eyebolt
Valvula de llenado
GC 6.-
Filling valve
Anillo Deflector
8.-
1075
Deflector ring
Detalle "X"
Ver Detalle "X" Detail "X"
See detail "X"
5
4-Ø38
7
R
45
Ø
909
50
790
25
14
Ho
1 2 34 1 3
6 0 8
© Copyright by ARTECHE G.I.T. S.L.U. Vitoria-Gasteiz. En "Fecha creación". Todos los derechos reservados, estando prohibida la reproducción total o parcial del plano, sin autorización del titular.
X1 X3 X2 X4
SZ 11/12/2020 JRG
PLANO Nº
20026423_4216631
CHARACTERISTICS SHEET SERIAL N 20026423
Mechanic features 1500 (N) Seismics 0.5 (g) / (g) Wind speed (km/h)
Painted: RAL 9002
PT PLN ENJINIRING
Project :
Title :
PLN Dwg. No. :
Responsible Dept. : Created by : Checked by : Approved by : Format :
RY UA UA
PGGI 17th-Jul, 2020 17th-Jul, 2020 17th-Jul, 2020 A4 size
Doc. Type : ☑ For Approval □ For Information □ Other
Doc. Status: □ Approved □ Approved on Condition □ Not Approved
PT ABB Sakti Industri Contractor
Dwg/Doc. No. 1HID1-2-8055-B737-4 Rev. C
Total __ Pages (including this cover Sheet)
TECHNICAL PARTICULAR AND GUARANTEE
1 Manufacturer - ABB
2 Type - Outdoor
7 Front cover : door with glass window - No, front cover with lamp indication
9 Dimension :
- depth mm 700
- width mm 800
- height mm 1950
15 Built-in sockets :
- 2 pole AC 220 V 16 A - Yes
- 3 pole AC 380 V 25 A - Yes
protected by MCBs
18 Built-in switches - No
19 Built-in fuses - No
THERMOSTAT DIODE
OUTLET
HEATING RESISTOR
SYMBOL LEGENDS
EARTH TITLE: Schematic SSVT Peranap r1
INCOMING
L1 L2 L3 L1 L2 L3
NEUTRAL NEUTRAL NEUTRAL
-L3:X2
-F92:1
-F92:3
-F92:5
MCCB
F90 1 3 5
I>
800A 2 4 6
-XAC1:5
-XAC1:3
-XAC1:1
-XAC1:7
NEUTRAL L1 L2 L3
OUTGOING
-F90:2
-F90:4
-F90:6
-F90:1
-F90:3
-F90:5
-BB:N
-BB:N
1 2 3 4 5 6 7 8 9
XAC1
Red 4.0mm
Yellow 4.0mm
Black 4.0mm
I> I>
25A 2 4 6 8 6A 2 4 6
4.0mm
4.0mm
4.0mm
4.0mm
1.5mm
1.5mm
1.5mm
1.5mm
Yellow
Yellow
Black
Black
Blue
Blue
Red
Red
1 2 3 4 5 6 7 8 9 10 11 12
X1 X1 X1
XAC2
1.5mm
1.5mm
4.0mm
4.0mm
4.0mm
4.0mm
L1 L2 L3
Yellow
Black
Blue
Red
Red
Red
X2 X2 X2
XG91
B91
21 21 11 4
<φ PH N
22 22
3
S91 S92 12 PH T
2
XG1 PH S
L X1 X1 L 1
Gn/Ye
4.0mm PE
E91 E92 E93 PE Gn/Ye
PH R
5
4.0mm
4.0mm
Gn/Ye
N X2 X2 PE
PE1 N PE2 PE3 AC SUPPLY DIAGRAM
1.5mm
1.5mm
1.5mm
Blue
Blue
Blue
10 11 12
TITLE: Schematic SSVT Peranap r1
XAC1 Document Number: REV:
01
Date: 1/13/2021 11:26 AM Sheet: 3/7
MCCB / MCB TRIP INDICATION CB OPEN CB CLOSE
110V DC Distribution Board
+DC -DC
MK SSVT
1 2 3 4
XDC
12 14 12 14 12 14 22 24 12 14 22 24
11 11 11 21 11 21
X1 X1
A1 A1
KACTR KCO LOP LCL
A2 A2 X2 Green X2 Red
12 14 22 24 32 34 42 44
11 21 31 41
1 2 3 4 5 6 7 8 9 10 11 12
XACTR
SAS PANEL
1 2 3 4 5 6 7 8 9 10 11 12
TRIP STATUS
CLOSE OPEN CB
TRIP SIGNAL TRIP SIGNAL MCCB MCCB MCCB MCCB TITLE: Schematic SSVT Peranap r1
MCCB / MCB MCCB / MCB OPEN CLOSE OPEN CLOSE Document Number: REV:
01
Date: 1/13/2021 11:26 AM Sheet: 4/7
1 2 3 4 5 6
XSSVT
7 8 9 10 11 12
13 14 15 16 17 18
TERMINAL SPARE
MATERIAL LIST
No. No. Gambar Title Rev. Status Tanggapan PLN Jawaban Kontraktor
1
SSVT
TYPE TEST
T E S T S
Nº: 3/LE130 ‘
LCOE
FUNDACIÓN PARA EL FOMENTO DE LA INNOVACIÓN INDUSTRIAL
Centro Tecnológico UPM – Tecnogetafe
C/ Eric Kandel, 1 – 28906 Getafe (Madrid)
Teléfono: +34 91 491 81 68
www.f2i2.net
MANUFACTURER Arteche
TYPE UG-550
Authorized signatory/s
• The results of the tests refer exclusively to the sample which was tested.
• The above-mentioned sample is the one described in the Report and is the sample which was originally received, with any
modifications which may have been produced during the tests, in order that these could be correctly performed. These
modifications are documented in the LCOE files, and are available for inspection by any person or organization authorized to do so.
• Partial reproduction of this document is prohibited.
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA
INDEX
Page Number
1 IDENTIFICATION OF THE TEST OBJECT ............................................................................................ 3
1.1 DESCRIPTION OF THE TEST OBJECT ........................................................................................................... 3
1.2 NOMINAL CHARACTERISTICS ASSIGNED BY THE MANUFACTURER ................................................................... 3
1.3 RATING PLATE OF VOLTAGE TRANSFORMER ............................................................................................... 4
1.4 PICTURES OF TEST OBJECT ...................................................................................................................... 5
2 GENERAL INFORMATION ............................................................................................................... 7
2.1 TESTS CARRIED OUT BY .......................................................................................................................... 7
2.2 MEASUREMENT UNCERTAINTY ................................................................................................................ 7
2.3 STANDARDS APPLIED ............................................................................................................................. 7
2.4 ADDITIONAL INFORMATION .................................................................................................................... 7
3 PERFORMED TESTS ........................................................................................................................ 8
3.1 VERIFICATION OF NAMEPLATE AND TERMINAL MARKINGS ............................................................................ 8
3.2 TEST FOR ACCURACY OF VOLTAGE TRANSFORMER ....................................................................................... 9
3.3 LIGHTNING IMPULSE TEST ON PRIMARY TERMINALS................................................................................... 10
3.4 WET TEST FOR OUTDOOR TYPE TRANSFORMERS. SWITCHING IMPULSE TEST. ................................................ 12
3.5 RADIO INTERFERENCE VOLTAGE MEASUREMENT ....................................................................................... 14
3.6 POWER FREQUENCY WITHSTAND TEST ON SECONDARY TERMINALS .............................................................. 15
3.7 TEMPERATURE-RISE TEST WITH THERMAL LIMITING OUTPUT ...................................................................... 16
3.8 SHORT-CIRCUIT WITHSTAND CAPABILITY TEST .......................................................................................... 18
3.9 TRANSMITTED OVERVOLTAGE TEST........................................................................................................ 19
3.10 MEASUREMENT OF NO-LOAD LOSSES AND EXCITATION CURRENT ................................................................ 20
3.11 MEASUREMENT OF LOAD LOSSES AND IMPEDANCE VOLTAGE ...................................................................... 21
4 SUMMARY AND CONCLUSIONS ................................................................................................... 22
Manufacturer: Arteche
Type: UG-550
Serial number: 1600018/1
According to Standard: IEC 61869-3
Year of manufacture: 2017
2 GENERAL INFORMATION
Tests have been performed in L.C.O.E. High Voltage laboratory place at Tecnogetafe, Eric
Kandel Street, number 1 – 28906 Getafe (Madrid) except short-circuit withstand capability test
was performed at High Power Laboratory, located at Parque Empresarial Boroa, parcel 24 –
48340 Amorebieta (Vizcaya).
Name Company
Name Company
The uncertainty of the test is calculated and at the disposal of the applicant.
In this report, voltage values corresponding to power frequency withstand tests are expressed in
peak value divided by root of two and voltage values corresponding to lightning impulse tests are
expressed in peak value.
3 PERFORMED TESTS
• Results:
Nameplate of voltage transformer includes the minimum information required and satisfies
section 6.13.302 of UNE-EN 61869-3 Standard.
Ratio and phase displacement errors of voltage transformer were measured according to
section 7.2.6 of UNE-EN 61869-3 Standard.
Errors
Voltage
Ratio Burden
(% Un)
Ratio (%) Phase (min)
80 -0.061 +0.1
0 VA
100 -0.059 +0.2
Cos phi 0.8
120 -0.055 +0.1
80 -0.063 +0.2
525000/√3 V 25 VA
100 -0.061 +0.2
/ 400/√3 V Cos phi 0.8
120 -0.056 +0.2
80 -0.066 +0.0
100 VA
100 -0.064 +0.0
Cos phi 0.8
120 -0.060 -0.0
Voltage ratio and phase displacement errors are between the limits specified for
the accuracy class for metering 1.
Errors
Voltage
Ratio Burden
(% Un)
Ratio (%) Phase (min)
Peak value of full impulses was equal to 1550 kV without correction due to local
atmospheric conditions and test wave polarity of the impulses was both positive and
negative.
Terminal N, one terminal of each secondary winding and tank were connected to ground
during the impulse test.
• Test result:
No external flashover or insulation damage was detected during the impulse test.
3.4 Wet test for outdoor type transformers. Switching Impulse Test.
Wet test for outdoor type transformers was performed on voltage transformer according to
sections 7.2.3.3 and 7.2.4 of UNE-EN 61869-1 Standard.
Fifteen switching impulses of peak voltage equal to 1175 kV, corrected due to local
atmospheric conditions, were applied on HV terminal of voltage transformer and ground
under wet condition according to UNE-EN 60060-1 Standard.
Terminal N, one terminal of each secondary winding and tank were connected to ground
during the impulse test.
• Test result:
No external flashover or insulation damage was detected during switching impulse test.
Test voltage of 476.3 kV (1.5 Um/√3), 50 Hz was applied for 30 seconds between high
voltage primary terminal of voltage transformer and ground. Terminal N, one terminal of
each secondary winding and tank were connected to ground during the test.
Then test voltage was reduced to 349.3 kV (1.1 Um/√3) and radio interference voltage was
measured during 30 seconds with measuring frequency equal to 1.26 MHz.
• Test results:
RIV Measurement
Test voltage Level 1 476.3 kV
Test voltage Level 2 349.3 kV
Test frequency 50 Hz
Test duration 30 s (each level)
RIV measuring frequency 1.26 MHz
Ambient Conditions
Ambient temperature 21.4 ºC
Relative Humidity 39.7 %
Atmospheric Pressure 955.7 hPa
476.3 kV 645.7 µV - -
349.3 kV 70.0 µV 2500 µV (IEC) OK
Test voltage equal to 3 kV, 50 Hz was applied during 60 seconds between short-circuited
terminals of each secondary winding and earth with the primary terminals of the
transformer, other secondary terminals and tank connected to ground.
Test voltage of 3 kV, 60 Hz was applied during 60 seconds between terminal N of primary
winding and earth with secondary terminals short-circuited and tank of the transformer
connected to ground.
• Test results:
Temperature rise of primary winding A-N and secondary winding a-n were measured by
the increase-in-resistance method and several thermocouples were placed over the
surface of the transformer tank to control external temperatures.
Three thermocouples were placed around the test object to control the ambient
temperature.
Rated secondary current was applied on voltage transformer for several hours to reach
stable thermal condition and winding resistances were measured again.
Temperature rises of primary winding A-N and secondary winding a-n (two sections) were
lower than limit specified of 60 K (thermal insulation class A) specified by UNE-EN 61869-
1 and UNE-EN 61869-3 Standards.
Temperature rise of external and metallic parts of voltage transformer was lower than limit
specified of 60 K (thermal insulation class A) specified by UNE-EN 61869-1 Standard.
The voltage transformer was energized from the secondary winding with the primary
winding short-circuited. Test voltage equal to rated secondary voltage was applied to
voltage transformer for one second with test frequency equal to 50 Hz.
• Results of test:
After short-circuit test voltage transformer is not visibly damaged and the insulation next to
the surface of both the primary and the secondary windings does not show significant
deterioration.
Accuracy test and routine dielectric tests were performed on voltage transformer after
short-circuit test at manufacturer Lab and witnessed by LCOE technician. All tests
performed passed successfully.
• Procedure:
Ten reduced impulse with a peak value (Up) of around 5.56 kV were applied to terminal A
of primary winding. Test wave polarity was positive, front time around 500 ns and time to
half value above 50 µs.
The transmitted voltage at the open secondary terminals (Us) was measured by using an
oscilloscope having a bandwidth of 500 MHz and input impedance equal to 50 Ω.
Terminal N, one terminal of each secondary winding and tank were connected to ground
during the impulse test.
Transmitted peak voltage measured on secondary winding was lower than limit value
specified by UNE-EN 61869-1 Standard.
• Procedure:
• Test results:
Then test voltage was applied on primary winding of voltage transformer up to 1.2 Ur and
test current from N terminal to ground was measured.
• Procedure:
Test voltage was applied to secondary winding of voltage transformer with high voltage
winding short-circuited, up to secondary current was equal to rated current Ir 433 A. Load
losses and impedance voltage were measured during the test.
• Test results:
The following tests according to IEC 61869-1 and IEC 61869-3 Standards have been performed
on voltage transformer manufactured by Arteche Nissin, type UG-550 and identification
1600018/1.
Measurement of no-load losses, excitation current, load-losses and impedance voltage of voltage
transformer have been performed according to specification of the manufacturer.
Annex 1
Drawing of voltage transformer
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 1 to Test Report 2017 03 3D 0097
Page 2 of 2
Annex 2
Lightning impulse test
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 2 to Test Report 2017 03 3D 0097
Page 2 of 3
Annex 3
Switching Impulse Test
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 3 to Test Report 2017 03 3D 0097
Page 2 of 2
Annex 4
Temperature-rise test
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 4 to Test Report 2017 03 3D 0097
Page 2 of 3
Annex 5
Short-circuit withstand capability test
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 5 to Test Report 2017 03 3D 0097
Page 2 of 2
Annex 6
Transmitted overvoltage test
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 6 to Test Report 2017 03 3D 0097
Page 2 of 2
Annex 7
Routine tests performed at Arteche factory
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 7 to Test Report 2017 03 3D 0097
Page 2 of 9
A GENERAL INFORMATION
Tests were performed at Arteche factory located at Derio Bidea, number 28 - 48100 Munguía
(Vizcaya) by Arteche technicians and by using manufacturer equipment. Tests have been
witnessed by:
Name Company
In this report, voltage values corresponding to power frequency withstand tests are expressed in
peak value divided by root of two and voltage values corresponding to lightning impulse tests are
expressed in peak value.
B PERFORMED TESTS
Power frequency withstand tests was performed on primary terminals of voltage transformer
after short-circuit withstand capability test according to section 7.3.1 of UNE-EN 61869-3
Standard.
Test voltage of 680 kV, 120 Hz was applied during 50 seconds between high voltage
terminal of primary winding and earth with terminal N, one terminal of each secondary
winding and tank of the transformer connected to ground.
Test voltage of 3 kV, 50 Hz was applied during 60 seconds between terminal N of primary
winding and earth with secondary terminals short-circuited and tank of the transformer
connected to ground.
• Test Parameters:
• Results:
Test voltage of 550 kV (higher than 80 % of rated power-frequency test voltage) , 120 Hz
was applied during 60 seconds between high voltage terminal of primary winding and earth
with terminal N, one terminal of the secondary winding and tank of the transformer
connected to ground.
Partial discharges were measured while test voltage applied on primary terminal was equal
to 550 kV (Um) and 381 kV (1.2 Um/√3).
• Test results:
Partial discharges measured at test voltage equal to Um and 1.2 Um/√3 were lower than limit
specified by UNE-EN 61869-3 Standard.
Ratio and phase displacement errors of voltage transformer were measured after short-
circuit withstand capability test according to section 7.2.6 of UNE-EN 61869-3 Standard.
Errors
Voltage
Ratio Burden
(% Un)
Ratio (%) Phase (min)
80 -0.019 -1.2
100 0 VA -0.020 -1.2
120 -0.018 -1.2
80 -0.021 -1.2
525000/√3 V 25 VA
100 -0.022 -1.2
/ 400/√3 V Cos phi 0.8
120 -0.020 -1.2
80 -0.026 -1.3
100 VA
100 -0.027 -1.3
Cos phi 0.8
120 -0.025 -1.3
Voltage ratio and phase displacement errors are between the limits specified for the
accuracy class for metering 1.
Test voltage equal to 3 kV, 50 Hz was applied during 60 seconds between short-circuited
terminals of secondary winding and earth with the primary terminals of the transformer and
tank connected to ground.
• Test results:
All equipment used during the performed tests was calibrated and satisfied technical requirements
according to UNE-EN 61869-3 and UNE-EN 60060-1 Standard.
Manufacturer: YANGZHOU
Internal Code: 424
Last calibration date: June 2015
Calibration interval: 2 years
Certificate of Calibration: ENAC / ILAC 201506600855
Calibration Laboratory: LCOE
Manufacturer: OMICRON
Internal Code: 534
Last calibration date: October 2016
Calibration interval: 2 years
Certificate of Calibration: ENAC / ILAC 2016103B0448
Calibration Laboratory: LCOE
Manufacturer: ZERA
Internal Code: 514
Last calibration date: January 2017
Calibration interval: 2 years
Certificate of Calibration: ENAC / ILAC 201701600040
Calibration Laboratory: LCOE
LABORATORIO CENTRAL OFICIAL DE ELECTROTECNIA Annex 7 to Test Report 2017 03 3D 0097
Page 8 of 9
Manufacturer: SEFELEC
Internal Code: 523
Last calibration date: October 2016
Calibration interval: 2 years
Certificate of Calibration: ENAC / ILAC 2016103C0467
Calibration Laboratory: LCOE
The following tests according to IEC 61869-1 and IEC 61869-3 Standards have been performed
after type tests on voltage transformer manufactured by Arteche, type UG-550 and identification
1600018/1.
› 245 kV Transformer
for substation auxiliary
services, model UTP.
Coyote Switch (USA).
INTRODUCTION
This type of voltage transformer can supply
several kVA low voltage power directly from a
high voltage transmission line.
Gas insulation:
model UG up to 550 kV and
100 kVA.
APPLICATIONS
1. Substations auxiliary services power 3. Rural electrification of isolated popula-
supply: tions:
Power supply in conventional substations As a power source for supplying reliable
where low voltage power is needed as a power to rural populations in isolated
primary or back-up supply; or in remote areas where there are no distribution lines
areas where building distribution lines nearby, but there are transmission lines.
is unsafe and with unreliable supply that This particular application supplies low
requires frequent maintenance and high voltage power directly from HV line in an
costs. economical and practical way.
It can also be used as a primary power 4. Temporary power supply when building
source in switching substations without substations, wind farms, etc., and emer-
power transformers to supply the gency supply during natural disasters.
substation and SCADA control systems.
2. Power supply for telecommunication 5. Voltage elevator for High Voltage electrical
and monitoring systems: test laboratories, wind and solar farms.
High quality electrical supply for booster
antennas in remote locations using a
voltage transformer connected to a nearby
transmission line.
› UTP-245 Voltage
transformer for
rural electrification.
Chihuahua State
(Mexico).
› Oil-paper insulated
power voltage
transformers.
ADVANTAGES
RANGE
Auxiliary service inductive voltage trans-
formers are named using different letters
(UT followed by a third letter to indicate the
model for oil-paper insulation and UG for gas
insulation) followed by 2 or 3 numbers to
indicate their service voltages.
B
B
B
A A A
› 420 kV UG Power
voltage transformer.
Routine tested in
ARTECHE’s laboratory.
Dengan hormat,
Menunjuk :
a. Surat Perjanjian Pembangunan Gardu Induk Tegangan Ekstra Tinggi 500 KV Peranap,
No. 0740.PJ/DAN.02.02/DIR/2017, tanggal 28 Desember 2017.
b. Kesepakatan Diskusi Kontrak Pekerjaan Pembangunan Gardu Induk Tegangan Ekstra
Tinggi 500 KV Peranap, tanggal 15 Desember 2017
c. Surat KSO ABB Waskita No. 045/ABB-WSKT/V/2020 tanggal 6 Mei 2020, perihal :
Surat Penyampaian Amandemen Kerja Tambah Kurang dalam Proyek Pembangunan
GITET 500 kV Peranap
d. Surat KSO ABB Waskita No. 078/ABB-WSKT/IX/2020 tanggal 21 Juli 2020, Perihal : Permohonan
Pembahasan Amandemen Kerja Tambah Kurang Pekerjaan Pembangunan Gardu Induk Tegangan
Ekstra Tinggi 500 KV Peranap
e. Risalah Rapat (MOM) tanggal 7 Agustus 2020, agenda Rapat Pembahasan Progress Pekerjaan dan
Rencana Amandemen GITET 500 KV Peranap
f. Surat KSO ABB Waskita No. 096/ABB-WSKT/IX/2020 tanggal 11 September 2020, perihal Permohonan
Pembahasan Amandemen Kerja Tambah Kurang Pekerjaan Pembangunan
Gardu Induk Tegangan Ekstra Tinggi 500 kV Peranap
Bersama ini kami sampaikan beberapa hal sebagai berikut :
1. Berdasarkan Laporan Kemajuan Pekerjaan (LKP) bulan Agustus 2020, progress pada Proyek
Pembangunan GITET 500 KV Peranap adalah 79,995% dengan rincian:
- Pekerjaan Sipil : 87.292 %
- Pekerjaan Elektrikal Mekanikal : 77,563 %
2. Kami telah melaksanakan dan menyelesaikan beberapa pekerjaan tambah (daftar terlampir)
berdasarkan Berita Acara Lapangan dan Risalah Rapat (Minute of Meeting) yang
ditandatangani oleh Pusmanpro dan UPPJ Jambi, akan tetapi kami tidak dapat memasukkan
item pekerjaan tersebut dalam Laporan Kemajuan Proyek karena belum masuk dalam
Amandemen Kontrak.
3. Berdasarkan poin 2 di atas kami sampaikan Usulan Amandemen Tambah Kurang Pekerjaan
Pembangunan Gardu Induk Tegangan Ekstra Tinggi 500 KV Peranap sebagai berikut :
Muhamad Sidik
Tembusan:
1. General Manager UIP SUMBAGTENG – PT. PLN (Persero), Up. Bpk. Henvry Setijabudi
2. Senior Manager Bidang Operasi dan Konstruksi UIP SUMBAGTENG - PT. PLN (Persero), Up. Bpk. Teddy Finzar
3. Manager PLN PUSMANPRO UPMK III dan IV
4. LBU Manager PGGI – PT. ABB Power Grids Indonesia
5. SVP EPC Division PT. Waskita Karya (Perero) Tbk
6. PLN Engineering
7. Arsip.
LAMPIRAN
REKAPITULASI BIAYA ADDENDUM PEKERJAAN TAMBAH - KURANG
PEMBANGUNAN GARDU INDUK TEGANGAN EKSTRA TINGGI 500 KV PERANAP
GRAND REKAPITULASI BIAYA
ADDENDUM PEKERJAAN TAMBAH - KURANG
PEMBANGUNAN GARDU INDUK TEGANGAN EKSTRA TINGGI 500 KV PERANAP
( Rp ) ( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6
1,1 PENGADAAN MATERIAL TERMASUK TRANSPORTASI, PEMASANGAN 221.629.371.371 222.460.223.179 21.154.899.102 20.324.047.294,58
COMMISSIONING DAN ASURANSI ( FOR SUBSTATION ) 500 kV SUBSTATION
1
1 1,2 INSTALATION SERVICE FOR CIVIL WORKS 73.867.280.344 88.048.373.510 21.244.450.483 7.063.357.317
1
1,3 SUBSTATION SERVICE VOLTAGE TRANSFORMER (SSVT) 0 14.161.534.108 14.161.534.108 -
( Rp ) ( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6
500 KV OUTDOOR EQUIPMENT FOR NEW AUR DURI OHL FEEDER No. 1 & FUTURE OHL
1 1 20.468.843.060 20.198.498.191 0 270.344.870
FEEDER
500 KV OUTDOOR EQUIPMENT FOR NEW AUR DURI OHL FEEDER No. 2 & FUTURE OHL
1 2 20.587.546.820 20.317.201.951 0 270.344.870
FEEDER
500 KV OUTDOOR EQUIPMENT FOR PERAWANG OHL FEEDER No. 3 WITH SHUNT
1 3 24.654.966.822 24.047.810.544 114.373.504 721.529.782
REACTOR & FUTURE OHL FEEDER
500 KV OUTDOOR EQUIPMENT FOR PERAWANG OHL FEEDER No. 4 WITH SHUNT
1 4 24.490.302.770 23.883.146.492 114.373.504 721.529.782
REACTOR & FUTURE OHL FEEDER
2 5 500 KV BUSBARS AND CONNECTIONS 4.756.444.169 4.756.444.169 0 0
2 6 500 KV SUBSTATION EARTING SYSTEM 4.523.022.851 4.523.022.851 0 0
2 7 500 KV SUBSTATIONS MULTICORE AND AUXILIARY CABLES 3.076.798.371 3.076.798.371 0 0
2 8 500 KV SUBSTATION STRUCTURES 18.866.676.598 16.922.763.794 62.196.400 2.006.109.204
2 9 500 kV SUBSTATION CONTROL PANELS 6.518.213.204 7.062.604.913 2.698.823.150 2.154.431.440
1.10 10 500 KV SUBSTATION PROTECTION PANELS 25.276.747.268 30.565.546.833 18.165.132.544 12.876.332.979
1 11 INVERTER FOR SUBSTATION AUTOMATION 628.265.838 628.265.838 0 0
1 12 DFR 6.542.286.523 6.542.286.523 0 0
1 13 110 VOLT DC EQUIPMENT 3.260.988.299 3.260.988.299 0 0
1 14 48 VOLT DC EQUIPMENT 1.574.817.338 1.574.817.338 0 0
1 15 LVAC EQUIPMENT 3.043.598.296 1.740.173.928 0 1.303.424.368
1 16 500 KV SHUNT REACTOR 40.940.319.372 40.940.319.372 0 0
1 17 SUBSTATION AUTOMATION HARDWARE 6.633.615.519 6.633.615.519 0 0
1 18 SUBSTATION AUTOMATION SOFTWARE 0 0 0 0
1 19 POWER LINE CARRIER SYSTEM 0 0 0 0
1.20 20 MISCELLANEOUS 1.770.708.406 1.770.708.406 0 0
1 21 TRAINING 892.467.807 892.467.807 0 0
1 22 TEST AND COMISSIONING 2.928.314.432 2.928.314.432 0 0
1 23 JASA SERTIFIKASI 0 0 0 0
1 24 AS BUILT DRAWING 194.427.608 194.427.608 0 0
SUB TOTAL I PENGADAAN MATERIAl, TRANSPORTASI DAN PEMASANGAN 221.629.371.371 222.460.223.179 21.154.899.102 20.324.047.295
NO URAIAN PEKERJAAN HARGA KONTRAK USULAN AMANDEMEN TAMBAH KURANG
( Rp ) ( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6
CONTROL BUILDING
3 1 CONTROL BUILDING SAS 11.680.052.564 11.048.689.154 2.593.944.326 3.225.307.736
SWITCHYARD
4 1 PREPARATION WORK FOR CONTROL BUILDING 4.279.109.011 6.605.455.336 2.326.346.325 0
4 2 SITE WORKS 38.775.493.082 51.578.242.148 16.200.283.745 3.397.534.679
4 3 FOUNDATION 500 KV 19.132.625.687 18.815.986.872 123.876.087 440.514.902
NEW
Protection Cubicle 2 for OHL Comprising: set - 4,0 4,0 - - 1.619.421.262 6.477.685.048 - 6.477.685.048
10.2.1
Ethernet switch for inter-bay level system
IED Main 2 line protection (MPU 2) - Differential, DEF, Over
Current, Autoreclose, etc.
IED Main 2 Circulating Current Protection (CCP 2)
Miscellaneous equipment, test block, rack cabinet, optical cables
and cord, control control cables, clamps, connectors, connection
to individual item of equipment, terminals, auxiliary relay,
interior lamp, heater,.. etc to complete the scope of works.
Note : - If Main 1 and Main 2 are the same algorithm, protection
relay must be different manufacturer
- IED Main 2 Line Protection changes from ABB to Toshiba
10.3 Protection Cubicle 1 for 500/275 kV Interbus Transformer set - -
10.4 Protection Cubicle 2 for 500/275 kV Interbus Transformer set - -
10.5 Protection Cubicle 1 for 500 kV Reactor comprising: sets 2,0 (2,0) - 1.094.959.307 - 9.715.855 - 2.209.350.323 -
Ethernet switch for inter-bay level system
IED Main 1 Reactor Protection (MPU 1) - Restricted Earth Fault
low impedance type, Over Current, 3-phase under/over voltage,
etc.
IED Main 1 Circulating Current Protection (CCP 1)
Miscellaneous equipment, test block, rack cabinet, optical cables
and cord, control control cables, clamps, connectors, connection
to individual item of equipment, terminals, auxiliary relay,
interior lamp, heater,.. etc to complete the scope of works.
NEW
Protection Cubicle 1 for 500 kV Reactor comprising: set - 2,0 2,0 - - 913.219.331 1.826.438.662 - 1.826.438.662
10.5.1
Ethernet switch for inter-bay level system
IED Main 1 Reactor Protection (MPU 1) - Restricted Earth Fault
low impedance type, Over Current, 3-phase under/over voltage,
etc.
Miscellaneous equipment, test block, rack cabinet, optical cables
and cord, control control cables, clamps, connectors, connection
to individual item of equipment, terminals, auxiliary relay,
interior lamp, heater,.. etc to complete the scope of works.
10.6 Protection Cubicle 2 for 500 kV Reactor comprising: sets 2,0 - 2,0 1.094.959.307 2.189.918.613 9.715.855 19.431.710 - -
Ethernet switch for inter-bay level system
IED Main 1 Reactor Protection (MPU 1) - Restricted Earth Fault
IED Main 2 Circulating Current Protection (CCP 2)
Miscellaneous equipment, test block, rack cabinet, optical cables
and cord, control control cables, clamps, connectors, connection
to individual item of equipment, terminals, auxiliary relay,
interior lamp, heater,.. etc to complete the scope of works.
Note : Main 1 and Main 2 Protection must be different
manufacturer
NEW
Protection Cubicle 2 for 500 kV Reactor comprising: set - 2,0 2,0 - - 913.219.331 1.826.438.662 - 1.826.438.662
10.6.1
Ethernet switch for inter-bay level system
IED Main 1 Reactor Protection (MPU 1) - Restricted Earth Fault
low impedance type, Over Current, 3-phase under/over voltage,
etc.
Miscellaneous equipment, test block, rack cabinet, optical cables
and cord, control control cables, clamps, connectors, connection
to individual item of equipment, terminals, auxiliary relay,
interior lamp, heater,.. etc to complete the scope of works.
Note : Main 1 and Main 2 Protection must be different
manufacturer
10.7 Protection Cubicle 1 for Busbar comprising: set 1,0 - 1,0 3.870.834.299 3.870.834.299 9.715.855 9.715.855 - -
10.8 Protection Cubicle 2 for Busbar comprising: set 1,0 - 1,0 3.870.834.299 3.870.834.299 9.715.855 9.715.855 - -
VOLUME HARGA SATUAN USULAN TOTAL
VOLUME VOLUME PERUBAHAN SETELAH HARGA PENGADAAN HARGA JASA
NO. URAIAN PEKERJAAN SATUAN PENGURANGAN PENAMBAHAN
BOQ Pengurangan / PERUBAHAN SATUAN TOTAL SATUAN TOTAL
KONTRAK Penambahan (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(1) (2) (3) (4) (4') (4'') (5) (6) = (4'') x (5) (7) (8) = (4'') x (7) (9) = -[(6) + (8)] (10) = (6) + (8)
10.9 Protection Cubicle for Diameter comprising: set - 2,0 2,0 1.234.414.773 2.468.829.546 9.715.855 19.431.710 - 2.488.261.256
Ethernet switch for inter-bay level system
IED Circuit Breaker Failure & Short Zone Protection for CB A (CBF
& SZP A)
IED Circuit Breaker Failure & Short Zone Protection for CB AB
(CBF & SZP AB)
IED Circuit Breaker Failure & Short Zone Protection for CB B (CBF
& SZP B)
Miscellaneous equipment, test block, rack cabinet, optical cables
and cord, control control cables, clamps, connectors, connection
to individual item of equipment, terminals, auxiliary relay,
interior lamp, heater,.. etc to complete the scope of works.
10.10 Protection Cubicle for Diameter comprising: sets 4,0 (2,0) 2,0 1.006.095.350 2.012.190.700 9.715.855 19.431.710 2.031.622.410 -
Ethernet switch for inter-bay level system
IED Circuit Breaker Failure & Short Zone Protection for CB A (CBF
& SZP A)
IED Circuit Breaker Failure & Short Zone Protection for CB AB
(CBF & SZP AB)
Miscellaneous equipment, test block, rack cabinet, optical cables
and cord, control control cables, clamps, connectors, connection
to individual item of equipment, terminals, auxiliary relay,
interior lamp, heater,.. etc to complete the scope of works.
10.11 Protection Cubicle for Diameter comprising: set - - -
10.12 Energy Meter Panel. lot 1,0 - 1,0 386.196.429 386.196.429 12.144.819 12.144.819 - -
12,0 DFR
12.1 INTERFACE CUBICLE FOR SCADA set - - -
12.2 FAULT RECORDER sets 4,0 - 4,0 643.153.035 2.572.612.139 7.590.512 30.362.047 - -
12.3 EVENT RECORDER set 1,0 - 1,0 917.390.877 917.390.877 7.590.512 7.590.512 - -
12.4 FAULT LOCATION EQUIPMENT (FAULT LOCATOR) (1 Panel) sets 4,0 - 4,0 745.992.225 2.983.968.902 7.590.512 30.362.047 - -
17.2 Server consist of : - CPU - KEYBOARD - MOUSE, VDU UNIT - 2,0 - 2,0
17.3 Colour Laser Printer. - 1,0 - 1,0
17.4 GPS Time reference clock complete with Antenna. sets 1,0 - 1,0
17.5 Gate Way. Set 1,0 - 1,0
17.6 Modem. Set 2,0 - 2,0
17.7 Router for communication to Sumatera Control Center Set 1,0 - 1,0
17.8 Ethernet Switch for station level (manageable). sets 2,0 - 2,0
17.9 IED Bay Control (BCU) for Common Set 1,0 - 1,0
HMI-Operator Work Station (1 set consist 2 HMI for operator and
17.10 sets
engineer ) consist of :
17.11 Furniture. set 1,0 - 1,0
17.12 Engineering Tools and Test Equipment (Laptop). set 1,0 - 1,0
Integration to the existing SAS Peranap 275 KV Substation,
17.13 set 1,0 - 1,0
Peranap 150 KV substation
Commisioning and point to point test between substation to
17.14 set 1,0 - 1,0
Sumatera control center
Miscelaneous equipment and material including cables, optical
cable, STP cable and cord, clamps, connectors, compression
17.15 lot 1,0 - 1,0
terminal, connection to individual items of equipment ….etc, to
complete the scope of works.
20. MISCELLANEOUS
CCTV SYSTEM COMPLETE AS SPECIFIED IN THE TECHNICAL
20,1 lot 1,0 - 1,0 1.139.967.526 1.139.967.526 212.773.790 212.773.790 - -
SPECIFICATION consist of :
Miscellaneous equipment and material including power cables,
video cable, network cable, patch cord, pig tail, connectors,
20,2 lot 1,0 - 1,0 205.193.300 205.193.300 212.773.790 212.773.790 - -
compression terminal, connection to individual items of
equipment, etc, to complete the scope of works.
21. TRAINING
21,1 Substation Automation Engineer ( 3 trainee, 15 duration) MD 45,0 - 45,0 - - 8.499.693 382.486.203 - -
Substation Automation Operation and Maintenance ( 3 trainee,
21,2 MD 30,0 - 30,0 - - 8.499.693 254.990.802 - -
10 duration)
Substation Telecommunication Operation and Maintenance Staff
21,4 MD 30,0 - 30,0 - - 8.499.693 254.990.802 - -
( 3 trainee, 10 duration)
2 Site Works
2,1 Earth Work
2.1.1 a. Common excavation m3 32.000,0 22.691,9 54.691,9 36.569 2.000.028.091 - - - 829.820.091
2.1.2 b. Back Fill with selected material m3 32.000,0 1.913,6 33.913,6 86.695 2.940.139.552 - - - 165.899.552
2.1.3 c. Import Fill with selected material m3 2.666,7 (2.666,7) - 181.195 - - - 483.187.271 -
2.1.4 d. Soil Disposal m3 - - - 21.651 - - - - -
2.2 Slope Stability
2.2.1 a. Retaining Wall ( Stone Masonry) m3 250,0 413,9 663,9 1.332.168 884.426.335 - - - 551.384.335
2.2.2 b. Gabion m3 320,0 (320,0) - 1.239.970 - - - 396.790.400 -
2.2.3 c. Sodding ( Gebalan Rumput) m3 - - - 28.000 - - - - -
d. Concrete frame ( Concrete K175, Fe: 150kg/m3 ; BJTD-35,
2.2.4 m3 - - - 5.459.235 - - - - -
formwork)
2.3 Road Works ( Rigid Pavement)
2.3.1 a. Prepare Compacted Subgrade (Thickness 15cm) m2 10.092,0 3,0 10.095,0 16.586 167.435.670 - - - 49.758
2.3.2 b. Lean concrete K-100 (Thickness 5cm) m3 504,6 0,1 504,8 2.033.117 1.026.215.806 - - - 304.968
2.3.3 c. Concrete K-225, Fe:150kg/m3, Formwork (thickness 20cm) m3 2.018,4 0,6 2.019,0 5.553.699 11.212.918.281 - - - 3.332.219
2.3.4 d. Joint Sealing & Joint Filler (4mm) m' 800,0 2.141,1 2.941,1 52.540 154.522.767 - - - 112.490.767
2.4 Kerbs (15/30)
2.4.1 a. Precast Concrete Kerbs for Switchyard (15x30x50 cm) m' 694,0 (694,0) - 280.990 - - - 195.007.060 -
2.4.2 b. Precast Concrete Kerbs for Road (20x30x50 cm) m' 804,0 1.478,0 2.282,0 296.490 676.590.180 - - - 438.212.220
2.5 Fence Complete with accessories, and Foundation
2.5.1 a. BRC 1.50 m height For Switchyard m' 560,0 800,0 1.360,0 1.015.079 1.380.507.440 - - - 812.063.200
2.5.2 b. BRC 1.90 m height m' 326,0 (323,0) 3,0 1.197.101 3.591.303 - - 386.663.623 -
c. Brick Wall Fence 2,4 m height (lower part) complete with tie
2.5.3 m' 1.200,0 790,0 1.990,0 2.680.071 5.333.341.290 - - - 2.117.256.090
beam, wall painting and barbed wire 0,60 m height (Upper part)
2.5.4 d. Fabricated Concrete Fence 2.40 m height m' - - - - - - - - -
2.6 Gate Complete with pole, accessories and foundation
2.6.1 a. Sliding gate BRC 1.90 m height, 7 m width ( include Column Unit 1,0 - 1,0 28.175.000 28.175.000 - - - -
2.6.2 b. Single Gate BRC 1.50m hight, 3 m Width Unit 4,0 (1,0) 3,0 9.660.000 28.980.000 - - 9.660.000 -
2.7 Landscaping m2 1.000,0 - 1.000,0 490.000 490.000.000 - - - -
2.8 Gravel (dia 3 - 5 cm); thickness = 20 cm m2 25.500,0 1.885,0 27.385,0 207.713 5.688.220.505 - - - 391.539.005
Cable trench (K225, BJTD 40 incld cover, Galvanized Cable Tray
2.9
L 50.50.5 and PVC Pipe)
2.9.1 a. Cable duct type 1 (Large, Width > 80 cm) m' 137,0 768,5 905,5 4.136.595 3.745.686.773 - - - 3.178.973.258
2.9.2 b. Cable duct type 2 (Medium, Width > 60 cm, < 80 cm) m' 568,0 320,0 888,0 3.282.252 2.914.639.776 - - - 1.050.320.640
2.9.3 c. Cable duct type 3 (Small, Width < 60 cm) m' 760,0 (698,2) 61,8 2.735.075 169.027.635 - - 1.909.629.365 -
2.9.4 d. Cable Duct (Crossing Road) m' 12,0 57,0 69,0 5.136.319 354.406.011 - - - 292.770.183
Open Drainage for Switchyard, Control building and substation
2.10 m' 540,0 190,0 730,0 660.168 481.922.640 - - - 125.431.920
area
2.11 Sub soil Drainage PVC dia 6 inc including gravel & Palm Fibre m' 800,0 - 800,0 709.092 567.273.600 - - - -
2.12 Fire wall reinforced concrete grade 225/20 complete with m3 - - -
VOLUME HARGA SATUAN USULAN TOTAL
VOLUME VOLUME PERUBAHAN SETELAH HARGA PENGADAAN HARGA JASA
NO. URAIAN PEKERJAAN SATUAN PENGURANGAN PENAMBAHAN
BOQ Pengurangan / PERUBAHAN SATUAN TOTAL SATUAN TOTAL
KONTRAK Penambahan (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(1) (2) (3) (4) (4') (4'') (5) (6) = (4'') x (5) (7) (8) = (4'') x (7) (9) = -[(6) + (8)] (10) = (6) + (8)
2.13 Post security (4m x 4 m) included toilet 1,5m x 1,5m unit 1,0 - 1,0 12.600.000 12.600.000 - - - -
2.14 Loading test No 1,0 - 1,0 436.679.320 436.679.320 - - - -
2.15 Pilling Foundation
2.15.1 b. Bored Pile dia. 60 cm m' 1.320,0 2.707,5 4.027,5 1.603.966 6.459.892.867 - - - 4.342.657.747
2.15.2 c. Driven Pile dia. 50 cm m' 10,0 (10,0) - 1.659.696 - - - 16.596.960 -
-
Item baru
2.16 Firewall unit - 7,0 7,0 202.611.966 1.418.283.761 - - - 1.418.283.761
2.17 Oil pit unit - 2,0 2,0 109.486.776 218.973.551 - - - 218.973.551
2.18 Ground Reservoir unit - 1,0 1,0 150.520.480 150.520.480 - - - 150.520.480
3 Roof Work
3.1 Steel trusses complete with connection kg 33.600,0 (18.510,3) 15.089,7 33.740 509.127.153 - - 624.536.847 -
3.2 Purlin kg 3.360,0 106,9 3.466,9 33.740 116.973.206 - - - 3.606.806
3.3 Wind Bracing and tie rod kg 10.080,0 (9.728,7) 351,35 33.740 11.854.549 - - 328.244.651 -
PVC Pipe vertical dia 3 inch ( Included bends, tees, albows,
3.4 m' 98,0 199,6 297,6 184.158 54.805.421 - - - 36.757.937
reducers, adaptors, roof drain)
Water proofing membrane type Thickness 3 mm and mortar
3.5 m2 25,0 229,6 254,6 329.447 83.890.384 - - - 75.654.209
screed
3.6 Corrugated metal sheet complete with accessories m2 1.055,0 (352,6) 702,4 260.400 182.894.544 - - 91.827.456 -
3.7 Acrylie Roof complete with Accessories m2 - - - - - - - - -
3.8 Foam Foil Insulation m2 567,0 135,4 702,4 105.996 74.447.351 - - - 14.347.619
Item baru
4.7 Floor hardener m2 - 168,8 168,8 95.000 16.036.000 - - - 16.036.000
7 Ceiling work - -
7.1 Acoustic ceiling complete with hanger, Aluminium frame and m2 1.134,0 (67,5) 1.066,5 420.000 447.930.000 - - 28.350.000 -
7.2 Aluminium ceiling complete with hanger, frame and painting m2 103,0 (1,1) 101,9 672.000 68.476.800 - - 739.200 -
13 Painting works
13.1 Wall Painting exterior (Grade Weathershield) m2 1.980,0 1.876,8 3.856,8 53.912 207.927.802 - - - 101.182.042
13.2 Wall Painting Interior m2 4.252,0 (1.447,5) 2.804,5 47.479 133.156.755 - - 68.723.953 -
Aluminium & Steel Painting ( Lead Primer, Undercoat and Gloss
13.3 m2 1.127,0 (158,6) 968,4 4.900 4.745.209 - - 777.091 -
Paint)
14 Electrical
Balcon And Lobby Room
14.1 Downlight fitting including installation, wiring, switch and LED 9 Sets 20,0 - 20,0 594.550 11.890.992 - - - -
14.2 Stop Contact including installation and wiring Sets 4,0 - 4,0 567.940 2.271.761 - - - -
14.3 Emergency Lighting including installation, wiring and Lamp 30 Sets 2,0 - 2,0 3.739.832 7.479.665 - - - -
16 Lighting Protection -
Cable BC 70 mm including all accessories clamps steel plate,
16.1 Lot 1,0 - 1,0 76.984.136 76.984.136 - - - -
material support and spole, grounding system for control building
17 Fire Alarm
17.1 Alarm bell 6" (150 mm) diameter including installation wiring NO 27,0 (3,0) 24,0 3.756.356 90.152.544 - - 11.269.068 -
17.2 Smoke detector including installation wiring NO 25,0 (3,0) 22,0 4.929.303 108.444.666 - - 14.787.909 -
Fixed and rate of rise temperature detector including installation
17.3 NO 25,0 (3,0) 22,0 4.929.303 108.444.666 - - 14.787.909 -
wiring
MCFA (Master Control Fire Almr) Including indication lamp,
17.4 NO 1,0 - 1,0 196.078.235 196.078.235 - - - -
batttery rectifier and all accessories
19 Crane Manual -
19.1 Crane Manual complete with accessories capacity 1,0 ton NO 1,0 - 1,0 78.948.000 78.948.000 - - - -
SUB TOTAL C.18 DAN C.19 168.318.000 - - -
TOTAL ITEM PEKERJAAN CONTROL BUILDING SAS 11.048.689.154 - 3.225.307.736 2.593.944.326
VOLUME HARGA SATUAN USULAN TOTAL
VOLUME VOLUME PERUBAHAN SETELAH HARGA PENGADAAN HARGA JASA
NO. URAIAN PEKERJAAN SATUAN PENGURANGAN PENAMBAHAN
BOQ Pengurangan / PERUBAHAN SATUAN TOTAL SATUAN TOTAL
KONTRAK Penambahan (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)
(1) (2) (3) (4) (4') (4'') (5) (6) = (4'') x (5) (7) (8) = (4'') x (7) (9) = -[(6) + (8)] (10) = (6) + (8)
2 Civil Material
2.1 Foundation of SSVT units - 6,0 6,0 30.491.590 182.949.540 - - - 182.949.540
2.2 Foundation of Marshaling Kiosk units - 2,0 2,0 12.073.099 24.146.198 - - - 24.146.198
SUB TOTAL D.2 207.095.738 - - 207.095.738
TOTAL ITEM PEKERJAAN SUBSTATION VOLTAGE
13.528.034.108 633.500.000 - 14.161.534.108
TRANFORMER ( SSVT )
TOTAL ITEM A + B + C + D 290.345.586.183 34.324.544.614 27.387.404.612 56.560.883.693
ANALISA HARGA SATUAN PEKERJAAN
NEW ITEM ( CIVIL WORK )
Harga Satuan Jumlah Harga
No Uraian Pekerjaan Sat Vol
Usulan Usulan
(1) (2) (3) (4) (5) (6 = 4 x 5)
HARGA SATUAN
KONTRAK USULAN KONTRAKTOR
NO. URAIAN PEKERJAAN SATUAN
PENGADAAN PENGADAAN
PEMASANGAN JUMLAH PEMASANGAN JUMLAH
MATERIAL MATERIAL
(1) (2) (3) (4) (5) (6) (7) (8) (9)
2 Civil Material