Kebutuhan pintu pekerjaan Sungai Cimanuk

Struktur Inlet Struktur Outlet


No Sub-Proyek Pekerjaan
Trashrack Saluran Pintu klep

1 CM-4a Detention Basin Side weir Tanpa trashrack Gambar terlampir Box culvert 1,0x1,0 m (2 buah) 100x100 cm (2 buah)

2 CM-4b Detention Basin Side weir Tanpa trashrack Gambar terlampir Box culvert 1,0x1,0 m (2 buah) 100x100 cm (2 buah)

3 CM-4c Detention Basin Side weir Tanpa trashrack Gambar terlampir Box culvert 1,0x1,0 m (2 buah) 100x100 cm (2 buah)
Saluran Struktur Pengambilan Struktur Inlet Struktur Outlet
Sub Proyek Pekerjaan
Dari Warga Pelimpah Pintu Saluran Trashrack Saluran Trashrack Flap gate
Perkuatan Tebing dan
BB-2 0,4 x 0,4 m
Peninggian Tanggul

BB-4a Kolam Detention Sal. Irigasi √ U-ditch B=1,0 m 1,0 x 1,4 m Box Culvert B=1,0; H=1,0 1,0 x 1,4 m 1,0 x 1,0 m

BB-4c Kolam Detention Sal. Irigasi √ B=1,0 m U-ditch B=1,0 m 1,0 x 2,1 m Box Culvert B=1,0; H=1,4 1,0 x 2,0 m 1,0 x 1,0 m

BB-4e Kolam Detention Sal. Drainase U-ditch B=1,0 m 1,0 x 1,4 m Box Culvert B=1,0; H=1,4 1,0 x 2,0 m 1,0 x 1,0 m

BB-4g Drainase Sal. Irigasi B=1,0 m 1,85 x 2,55 m 0,3 x 0,3 m

BB-5a Kolam Detention √ 1,0 x 1,0 m


REKAPITULASI PEKERJAAN HIDROMEKANIKAL PROYEK PENGENDALIAN BANJIR
BALAI BESAR WILYAH SUNGAI CIMANUK - CISANGGARUM
TAHUN ANGGARAN 2021/2022

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH


I SUNGAI CIMANUK
I.A Sub Proyek CM-4a
1 Fabrikasi Trashrack Galvanis & Frame Set 1 Rp 99,854,916.00 Rp 99,854,916.00
- PemasanganTrashrack & Frame set Set 1 Rp 11,692,955.00 Rp 11,692,955.00
2 Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m) Set 2 Rp 34,378,000.00 Rp 68,756,000.00
- Pemasangan Pintu Flap Gate (1 m x 1 m) Set 2 Rp 3,422,000.00 Rp 6,844,000.00
Jumlah Rp 187,147,871.00
I.B Sub Proyek CM - 4b
1 Fabrikasi Trashrack Galvanis & Frame Set 1 Rp 99,854,916.00 Rp 99,854,916.00
- PemasanganTrashrack & Frame set Set 1 Rp 11,692,955.00 Rp 11,692,955.00
2 Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m) Set 2 Rp 34,378,000.00 Rp 68,756,000.00
- Pemasangan Pintu Flap Gate (1 m x 1 m) Set 2 Rp 3,422,000.00 Rp 6,844,000.00
Jumlah Rp 187,147,871.00
I.C Sub Proyek CM - 4c Outlet
1 Fabrikasi Trashrack Galvanis & Frame Set 1 Rp 99,854,916.00 Rp 99,854,916.00
- PemasanganTrashrack & Frame set Set 1 Rp 11,692,955.00 Rp 11,692,955.00
2 Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m) Set 2 Rp 34,378,000.00 Rp 68,756,000.00
- Pemasangan Pintu Flap Gate (1 m x 1 m) Set 2 Rp 3,422,000.00 Rp 6,844,000.00
Jumlah Rp 187,147,871.00
Total Jumlah Sungai Cimanuk Jumlah IA+IB+IC Rp 561,443,613.00

II SUNGAI BABAKAN
II.A Sub Proyek BB - 2
1 Fabrikasi Flap Gate Fiberglass ( 0,4 m x 0,4 m) Set 1 Rp 17,052,000.00 Rp 17,052,000.00
- Pemasangan Pintu Flap Gate (0,4 m x 0,4 m) Set 1 Rp 1,848,000.00 Rp 1,848,000.00
Jumlah Rp 18,900,000.00
II.B Sub Proyek BB - 4a
1 Fabrikasi Trashrack Galvanis B= 1 m, H= 1,4 m Set 2 Rp 6,122,465.00 Rp 12,244,930.00
- Pemasangan Trashrack (B= 1m, H= 1,4 m) Set 2 Rp 1,168,667.00 Rp 2,337,334.00
2 Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m) Set 1 Rp 34,378,000.00 Rp 34,378,000.00
- Pemasangan Pintu Flap Gate (1 m x 1 m) Set 1 Rp 3,422,000.00 Rp 3,422,000.00
Jumlah Rp 52,382,264.00
II.C Sub Proyek BB - 4c
1 Fabrikasi Pintu Sorong Spindle Tunggal B= 1m, H= 1 m Set 1 Rp 37,214,111.00 Rp 37,214,111.00
- Pemasangan Pintu Sorong Spindle Tunggal (B= 1m, H= 1 m) Set 1 Rp 3,640,230.00 Rp 3,640,230.00
2 Fabrikasi Trashrack Galvanis B= 1 m, H= 2,1 m Set 1 Rp 8,456,530.00 Rp 8,456,530.00
- Pemasangan Trashrack (B= 1m, H= 2,1 m) Set 1 Rp 1,632,877.00 Rp 1,632,877.00
3 Fabrikasi Trashrack Galvanis B= 1 m, H= 2,0 m Set 1 Rp 8,420,230.00 Rp 8,420,230.00
- Pemasangan Trashrack (B= 1 m, H= 2,0 m) Set 1 Rp 1,630,082.00 Rp 1,630,082.00
4 Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m) Set 1 Rp 34,378,000.00 Rp 34,378,000.00
- Pemasangan Pintu Flap Gate (1 m x 1 m) Set 1 Rp 3,422,000.00 Rp 3,422,000.00
Jumlah Rp 98,794,060.00
II. D Sub Proyek BB - 4e
1 Fabrikasi Trashrack Galvanis B= 1 m, H= 1,4 m Set 1 Rp 6,122,463.00 Rp 6,122,463.00
- Pemasangan Trashrack (B= 1m, H= 1,4 m) Set 1 Rp 1,168,667.00 Rp 1,168,667.00
2 Fabrikasi Trashrack Galvanis B= 1 m, H= 2,0 m Set 1 Rp 8,420,229.00 Rp 8,420,229.00
- Pemasangan Trashrack (B= 1m, H= 2,0 m) Set 1 Rp 1,630,082.00 Rp 1,630,082.00
3 Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m) Set 1 Rp 34,378,245.00 Rp 34,378,245.00
- Pemasangan Pintu Flap Gate (1 m x 1 m) Set 1 Rp 3,421,915.00 Rp 3,421,915.00
Jumlah Rp 55,141,601.00
II.E Sub Proyek BB - 4g
1 Fabrikasi Pintu Sorong Spindle Tunggal B= 1m, H= 1 m Set 1 Rp 37,214,111.00 Rp 37,214,111.00
- Pemasangan Pintu Sorong Spindle Tunggal (B= 1m, H= 1 m) Set 1 Rp 3,640,233.00 Rp 3,640,233.00
2 Fabrikasi Trashrack Galvanis B= 1,85 m, H= 2,55 m Set 1 Rp 15,038,600.00 Rp 15,038,600.00
- Pemasangan ,Trashrack (B= 1,85 m, H= 2,55 m) Set 1 Rp 2,555,943.00 Rp 2,555,943.00
3 Fabrikasi Flap Gate Fiberglass ( 0,3 m x 0,3 m) Set 1 Rp 12,651,408.00 Rp 12,651,408.00
- Pemasangan Pintu Flap Gate (0,3 m x 0,3 m) Set 1 Rp 1,598,500.00 Rp 1,598,500.00
Jumlah Rp 72,698,795.00
II.F Sub Proyek BB - 5a
1 Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m) Set 1 Rp 34,378,245.00 Rp 34,378,245.00
- Pemasangan Pintu Flap Gate (1 m x 1 m) Set 1 Rp 3,421,915.00 Rp 3,421,915.00
Jumlah Rp 37,800,160.00
Jumlah Sungai Babakan (IIA+IIB+IIC+IID+IIE+IIF) Rp 335,716,880.00

III Total Jumlah (Sungai Babakan+Sungai Cimanuk)


Total Jumlah Rp 897,160,493.00
PPN 10% Rp 89,716,049.30
GRAND TOTAL Rp 986,876,542.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan : Fabrikasi Trashrack Galvanis & Frame
Satuan / Unit : 1 Set
Harga Satuan : Rp 99,854,916.00
Lokasi : Sungai Cimanuk (CM -4a)
No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 10 103,000.00 1,030,000.00
3 Tukang Las Listrik/Welder OH 10 100,000.00 1,000,000.00
4 Operator Gerinda OH 10 126,000.00 1,260,000.00
9 Helper /Pekerja OH 30 75,000.00 2,250,000.00
Jumlah Harga Tenaga Kerja 5,540,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
i Rangka Trashrack : -
1 Baja UNP SS400 150x75x6,5 (59 meter) Kg 766.97 16,300.00 12,501,676.20
2 Baja Siku SS400 150x150x12 ( 30 meter) Kg 820.00 16,300.00 13,366,000.00

ii Trashrack depan uk (1,5m x 2,5m) 4 unit


1 Plate strip Galvanis 5mmx38mmx6m m 83.48 53,333.33 4,452,266.67
2 Plate strip Galvanis 3mmx30mmx6m m 236.26 33,000.00 7,796,580.00

iii Trashrack sisi atas: 34 m²


1 Plate strip Galvanis 5mmx38mmx6m m 192.1 53,333.33 10,245,333.33
2 Plate strip Galvanis 3mmx30mmx6m m 535.5 33,000.00 17,671,500.00

iv Trashrack sisi kanan & kiri 10,8 m²


1 Plate strip Galvanis 5mmx38mmx6m m 60.1 53,333.33 3,205,440.00
2 Plate strip Galvanis 3mmx30mmx6m m 170.1 33,000.00 5,613,300.00
Jumlah Harga Bahan Utama 74,852,096.20
C Bahan Bantu
1 Kawat Las RD 26 Kg 45.0 27,500.00 1,237,500.00
2 Sarung Tangan Pendek Stl 16.0 16,000.00 256,000.00
3 Batu Gerinda 4" Bh 50.0 5,500.00 275,000.00
4 Batu Gerinda Cutting 4" Bh 50.0 4,000.00 200,000.00
5 Olie Bor Ltr 1.0 35,000.00 35,000.00
6 Bensin Ltr 30.0 7,600.00 228,000.00
7 Cat anti karat utk Rangka Kg 1.0 63,500.00 63,500.00
8 Cat Finishing utk Rangka Kg 1.0 40,000.00 40,000.00
8 Kwas Kecil Bh 4.0 8,000.00 32,000.00
7 Sikat Kawat Bh 4.0 41,300.00 165,200.00
8 Kain Majun Kg 2.0 6,250.00 12,500.00
Jumlah Harga Bahan Bantu 2,544,700.00

D Peralatan Satuan Koef. Harga Satuan (Rp) Jumlah (Rp)


1 Mesin Las 500 A Sewa / Hari 12 150,000.00 1,800,000.00
2 Mesin Gerinda 4" Sewa / Hari 12 50,000.00 600,000.00
3 Lever Block 1 - 3 ton Sewa / Hari 28 50,000.00 1,400,000.00
4 Mesin Bor Tangan Sewa / Hari 6 10,500.00 63,000.00
5 Peralatan Painting Sewa / Hari 3 120,400.00 361,200.00
6 Mesin Genset Sewa / Hari 6 602,700.00 3,616,200.00
Jumlah Harga Peralatan 7,840,400.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 90,777,196.20


F Overhead + Profit 10% x E 9,077,719.62
Jumlah Harga (Total) 99,854,915.82
G Harga Satuan Pekerjaan per - Unit 99,854,916.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
PemasanganTrashrack & Frame set
Satuan / Unit : 1 Set
Harga Satuan : Rp 12,264,955.00
Lokasi : Sungai Cimanuk (CM -4a)
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 15.36 75,000.00 1,152,000.00
2 Tukang las OH 7.68 100,000.00 768,000.00
3 Tukang OH 0.78 98,000.00 76,440.00
4 Mandor OH 1.56 103,000.00 160,680.00
Jumlah Harga Tenaga Kerja 2,157,120.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 20.00 2,700.00 54,000.00
2 Baut Kuningan 10 x20 mm Bh 40.00 13,000.00 520,000.00
3 Batu Gerinda 4" Bh 20.00 30,000.00 600,000.00
4 Campuran beton fc'= 19,3 Mpa m³ 0.46 1,012,398.10 467,727.92
5 Pasangan bata, mortar tipe N m³ 0.00 - -
Jumlah Harga Bahan 1,641,727.92
C Peralatan
1 Trashrack **) koef 0.07 99,854,916.00 6,989,844.12
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 2.30 36,400.00 83,865.60
3 Mesin las listrik 500A, diesel Sewa/hari 2.30 120,400.00 277,401.60
Jumlah Harga Peralatan 7,351,111.32
D Jumlah Harga (A+B+C) 11,149,959.24
E Overhead + Profit 10% xD 1,114,995.92
F Harga Satuan Pekerjaan (D+E) 12,264,955.16
Dibulatkan 12,264,955.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan : Fabrikasi Trashrack Galvanis & Frame
Satuan / Unit : 1 Set
Harga Satuan : Rp 99,854,916.00
Lokasi : Sungai Cimanuk (CM -4b)
No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 10 103,000.00 1,030,000.00
3 Tukang Las Listrik/Welder OH 10 100,000.00 1,000,000.00
4 Operator Gerinda OH 10 126,000.00 1,260,000.00
9 Helper /Pekerja OH 30 75,000.00 2,250,000.00
Jumlah Harga Tenaga Kerja 5,540,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
i Rangka Trashrack : -
1 Baja UNP SS400 150x75x6,5 (59 meter) Kg 766.97 16,300.00 12,501,676.20
2 Baja Siku SS400 150x150x12 ( 30 meter) Kg 820.00 16,300.00 13,366,000.00

ii Trashrack depan uk (1,5m x 2,5m) 4 unit


1 Plate strip Galvanis 5mmx38mmx6m m 83.48 53,333.33 4,452,266.67
2 Plate strip Galvanis 3mmx30mmx6m m 236.26 33,000.00 7,796,580.00

iii Trashrack sisi atas: 34 m²


1 Plate strip Galvanis 5mmx38mmx6m m 192.1 53,333.33 10,245,333.33
2 Plate strip Galvanis 3mmx30mmx6m m 535.5 33,000.00 17,671,500.00

iv Trashrack sisi kanan & kiri 10,8 m²


1 Plate strip Galvanis 5mmx38mmx6m m 60.1 53,333.33 3,205,440.00
2 Plate strip Galvanis 3mmx30mmx6m m 170.1 33,000.00 5,613,300.00
Jumlah Harga Bahan Utama 74,852,096.20
C Bahan Bantu
1 Kawat Las RD 26 Kg 45.0 27,500.00 1,237,500.00
2 Sarung Tangan Pendek Stl 16.0 16,000.00 256,000.00
3 Batu Gerinda 4" Bh 50.0 5,500.00 275,000.00
4 Batu Gerinda Cutting 4" Bh 50.0 4,000.00 200,000.00
5 Olie Bor Ltr 1.0 35,000.00 35,000.00
6 Bensin Ltr 30.0 7,600.00 228,000.00
7 Cat anti karat utk Rangka Kg 1.0 63,500.00 63,500.00
8 Cat Finishing utk Rangka Kg 1.0 40,000.00 40,000.00
8 Kwas Kecil Bh 4.0 8,000.00 32,000.00
7 Sikat Kawat Bh 4.0 41,300.00 165,200.00
8 Kain Majun Kg 2.0 6,250.00 12,500.00
Jumlah Harga Bahan Bantu 2,544,700.00

D Peralatan Satuan Koef. Harga Satuan (Rp) Jumlah (Rp)


1 Mesin Las 500 A Sewa / Hari 12 150,000.00 1,800,000.00
2 Mesin Gerinda 4" Sewa / Hari 12 50,000.00 600,000.00
3 Lever Block 1 - 3 ton Sewa / Hari 28 50,000.00 1,400,000.00
4 Mesin Bor Tangan Sewa / Hari 6 10,500.00 63,000.00
5 Peralatan Painting Sewa / Hari 3 120,400.00 361,200.00
6 Mesin Genset Sewa / Hari 6 602,700.00 3,616,200.00
Jumlah Harga Peralatan 7,840,400.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 90,777,196.20


F Overhead + Profit 10% x E 9,077,719.62
Jumlah Harga (Total) 99,854,915.82
G Harga Satuan Pekerjaan per - Unit 99,854,916.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
PemasanganTrashrack & Frame set
Satuan / Unit : 1 Set
Harga Satuan : Rp 12,264,955.00
Lokasi : Sungai Cimanuk (CM -4b)
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 15.36 75,000.00 1,152,000.00
2 Tukang las OH 7.68 100,000.00 768,000.00
3 Tukang OH 0.78 98,000.00 76,440.00
4 Mandor OH 1.56 103,000.00 160,680.00
Jumlah Harga Tenaga Kerja 2,157,120.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 20.00 2,700.00 54,000.00
2 Baut Kuningan 10 x20 mm Bh 40.00 13,000.00 520,000.00
3 Batu Gerinda 4" Bh 20.00 30,000.00 600,000.00
4 Campuran beton fc'= 19,3 Mpa m³ 0.46 1,012,398.10 467,727.92
5 Pasangan bata, mortar tipe N m³ 0.00 - -
Jumlah Harga Bahan 1,641,727.92
C Peralatan
1 Trashrack **) koef 0.07 99,854,916.00 6,989,844.12
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 2.30 36,400.00 83,865.60
3 Mesin las listrik 500A, diesel Sewa/hari 2.30 120,400.00 277,401.60
Jumlah Harga Peralatan 7,351,111.32
D Jumlah Harga (A+B+C) 11,149,959.24
E Overhead + Profit 10% xD 1,114,995.92
F Harga Satuan Pekerjaan (D+E) 12,264,955.16
Dibulatkan 12,264,955.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan : Fabrikasi Trashrack Galvanis & Frame
Satuan / Unit : 1 Set
Harga Satuan : Rp 99,854,916.00
Lokasi : Sungai Cimanuk (CM -4c)
No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 10 103,000.00 1,030,000.00
3 Tukang Las Listrik/Welder OH 10 100,000.00 1,000,000.00
4 Operator Gerinda OH 10 126,000.00 1,260,000.00
9 Helper /Pekerja OH 30 75,000.00 2,250,000.00
Jumlah Harga Tenaga Kerja 5,540,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
i Rangka Trashrack : -
1 Baja UNP SS400 150x75x6,5 (59 meter) Kg 766.97 16,300.00 12,501,676.20
2 Baja Siku SS400 150x150x12 ( 30 meter) Kg 820.00 16,300.00 13,366,000.00

ii Trashrack depan uk (1,5m x 2,5m) 4 unit


1 Plate strip Galvanis 5mmx38mmx6m m 83.48 53,333.33 4,452,266.67
2 Plate strip Galvanis 3mmx30mmx6m m 236.26 33,000.00 7,796,580.00

iii Trashrack sisi atas: 34 m²


1 Plate strip Galvanis 5mmx38mmx6m m 192.1 53,333.33 10,245,333.33
2 Plate strip Galvanis 3mmx30mmx6m m 535.5 33,000.00 17,671,500.00

iv Trashrack sisi kanan & kiri 10,8 m²


1 Plate strip Galvanis 5mmx38mmx6m m 60.1 53,333.33 3,205,440.00
2 Plate strip Galvanis 3mmx30mmx6m m 170.1 33,000.00 5,613,300.00
Jumlah Harga Bahan Utama 74,852,096.20
C Bahan Bantu
1 Kawat Las RD 26 Kg 45.0 27,500.00 1,237,500.00
2 Sarung Tangan Pendek Stl 16.0 16,000.00 256,000.00
3 Batu Gerinda 4" Bh 50.0 5,500.00 275,000.00
4 Batu Gerinda Cutting 4" Bh 50.0 4,000.00 200,000.00
5 Olie Bor Ltr 1.0 35,000.00 35,000.00
6 Bensin Ltr 30.0 7,600.00 228,000.00
7 Cat anti karat utk Rangka Kg 1.0 63,500.00 63,500.00
8 Cat Finishing utk Rangka Kg 1.0 40,000.00 40,000.00
8 Kwas Kecil Bh 4.0 8,000.00 32,000.00
7 Sikat Kawat Bh 4.0 41,300.00 165,200.00
8 Kain Majun Kg 2.0 6,250.00 12,500.00
Jumlah Harga Bahan Bantu 2,544,700.00

D Peralatan Satuan Koef. Harga Satuan (Rp) Jumlah (Rp)


1 Mesin Las 500 A Sewa / Hari 12 150,000.00 1,800,000.00
2 Mesin Gerinda 4" Sewa / Hari 12 50,000.00 600,000.00
3 Lever Block 1 - 3 ton Sewa / Hari 28 50,000.00 1,400,000.00
4 Mesin Bor Tangan Sewa / Hari 6 10,500.00 63,000.00
5 Peralatan Painting Sewa / Hari 3 120,400.00 361,200.00
6 Mesin Genset Sewa / Hari 6 602,700.00 3,616,200.00
Jumlah Harga Peralatan 7,840,400.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 90,777,196.20


F Overhead + Profit 10% x E 9,077,719.62
Jumlah Harga (Total) 99,854,915.82
G Harga Satuan Pekerjaan per - Unit 99,854,916.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
PemasanganTrashrack & Frame set
Satuan / Unit : 1 Set
Harga Satuan : Rp 12,264,955.00
Lokasi : Sungai Cimanuk (CM -4c)
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 15.36 75,000.00 1,152,000.00
2 Tukang las OH 7.68 100,000.00 768,000.00
3 Tukang OH 0.78 98,000.00 76,440.00
4 Mandor OH 1.56 103,000.00 160,680.00
Jumlah Harga Tenaga Kerja 2,157,120.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 20.00 2,700.00 54,000.00
2 Baut Kuningan 10 x20 mm Bh 40.00 13,000.00 520,000.00
3 Batu Gerinda 4" Bh 20.00 30,000.00 600,000.00
4 Campuran beton fc'= 19,3 Mpa m³ 0.46 1,012,398.10 467,727.92
5 Pasangan bata, mortar tipe N m³ 0.00 - -
Jumlah Harga Bahan 1,641,727.92
C Peralatan
1 Trashrack **) koef 0.07 99,854,916.00 6,989,844.12
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 2.30 36,400.00 83,865.60
3 Mesin las listrik 500A, diesel Sewa/hari 2.30 120,400.00 277,401.60
Jumlah Harga Peralatan 7,351,111.32
D Jumlah Harga (A+B+C) 11,149,959.24
E Overhead + Profit 10% xD 1,114,995.92
F Harga Satuan Pekerjaan (D+E) 12,264,955.16
Dibulatkan 12,264,955.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan : Fabrikasi Trashrack Galvanis B= 1,85 m, H= 2,55 m
Satuan / Unit : 1 Set
Harga Satuan : Rp 15,038,600.00
Lokas :
Harga Satuan
No Uraian Satuan Koefisien Jumlah (Rp)
(Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 6 103,000.00 618,000.00
3 Tukang Las Listrik/Welder OH 6 100,000.00 600,000.00
4 Operator Gerinda OH 6 126,000.00 756,000.00
9 Helper /Pekerja OH 18 75,000.00 1,350,000.00
Jumlah Harga Tenaga Kerja 3,324,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Plate strip Galvanis 5mmx38mmx6m m 37.51 53,333.33 2,000,432.00
2 Plate strip Galvanis 3mmx30mmx6m m 74.31 33,000.00 2,452,180.50

C Bahan Bantu
1 Kawat Las RD 26 Kg 33.7 27,500.00 926,750.00
2 Sarung Tangan Pendek Stl 23.6 16,000.00 377,440.00
3 Batu Gerinda 4" Bh 40.0 5,500.00 220,000.00
4 Batu Gerinda Cutting 4" Bh 40.0 4,000.00 160,000.00
5 Olie Bor Ltr 0.5 35,000.00 17,500.00
6 Bensin Ltr 15.0 7,600.00 114,000.00
7 Cat anti karat Kg 1.0 63,500.00 63,500.00
8 Kwas Kecil Bh 2.0 8,000.00 16,000.00
7 Sikat Kawat Bh 2.0 41,300.00 82,600.00
8 Kain Majun Kg 1.0 6,250.00 6,250.00
Jumlah Harga Bahan 6,436,652.50

D Peralatan Satuan Hari Harga Satuan (Rp) Jumlah (Rp)


1 Mesin Las 500 A Sewa / Hari 6 150,000.00 900,000.00
2 Mesin Gerinda 4" Sewa / Hari 6 50,000.00 300,000.00
3 Lever Block 1 - 3 ton Sewa / Hari 6 50,000.00 300,000.00
4 Mesin Genset Sewa / Hari 4 602,700.00 2,410,800.00
Jumlah Harga Peralatan 3,910,800.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 13,671,452.50


F Overhead + Profit 10% x E 1,367,145.25
Jumlah Harga (Total) 15,038,597.75
G Harga Satuan Pekerjaan per - Unit 15,038,598.00
Dibulatkan 15,038,600.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
Pemasangan ,Trashrack (B= 1,85 m, H= 2,55 m)
Satuan / Unit : 1 Set
Harga Satuan : Rp 2,555,943.00

Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 5.12 75,000.00 384,000.00
2 Tukang las OH 2.56 100,000.00 256,000.00
3 Tukang OH 0.26 98,000.00 25,480.00
4 Mandor OH 0.52 103,000.00 53,560.00
Jumlah Harga Tenaga Kerja 719,040.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 20.00 2,700.00 54,000.00
2 Batu Gerinda 4" Bh 10.00 30,000.00 300,000.00
3 Campuran beton fc'= 19,3 Mpa m³ 0.15 1,012,398.10 155,909.31
4 Pasangan bata, mortar tipe N m³ 0.00 - -
Jumlah Harga Bahan 509,909.31
C Peralatan
1 Trashrack **) koef 0.07 15,038,600.00 1,052,702.00
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 1.15 36,400.00 41,932.80
3 Mesin las listrik 500A, diesel Sewa/hari 0.00 120,400.00 -
Jumlah Harga Peralatan 1,094,634.80
D Jumlah Harga (A+B+C) 2,323,584.11
E Overhead + Profit 10% xD 232,358.41
F Harga Satuan Pekerjaan (D+E) 2,555,942.52
Dibulatkan 2,555,943.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan : Fabrikasi Trashrack Galvanis B= 1 m, H= 2,1 m
Satuan / Unit : 1 Set
Harga Satuan : Rp 8,456,530.00
Lokas :
Harga Satuan
No Uraian Satuan Koefisien Jumlah (Rp)
(Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 4.29 103,000.00 441,870.00
3 Tukang Las Listrik/Welder OH 4.29 100,000.00 429,000.00
4 Operator Gerinda OH 4.29 126,000.00 540,540.00
9 Helper /Pekerja OH 12.87 75,000.00 965,250.00
Jumlah Harga Tenaga Kerja 2,376,660.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Plate strip Galvanis 5mmx38mmx6m m 11.13 53,333.33 593,600.00
2 Plate strip Galvanis 3mmx30mmx6m m 32.50 33,000.00 1,072,500.00

C Bahan Bantu
1 Kawat Las RD 26 Kg 14.3 27,500.00 393,250.00
2 Sarung Tangan Pendek Stl 7.0 16,000.00 112,000.00
3 Batu Gerinda 4" Bh 28.6 5,500.00 157,300.00
4 Batu Gerinda Cutting 4" Bh 35.8 4,000.00 143,000.00
5 Olie Bor Ltr 0.4 35,000.00 12,512.50
6 Bensin Ltr 7.2 7,600.00 54,340.00
7 Cat anti karat Kg 0.7 63,500.00 45,402.50
8 Kwas Kecil Bh 3 8,000.00 22,880.00
7 Sikat Kawat Bh 3 41,300.00 118,118.00
8 Kain Majun Kg 0.7 6,250.00 4,468.75
Jumlah Harga Bahan 2,729,371.75

D Peralatan Satuan Hari Harga Satuan (Rp) Jumlah (Rp)


1 Mesin Las 500 A Sewa / Hari 3 150,000.00 429,000.00
2 Mesin Gerinda 4" Sewa / Hari 4 50,000.00 214,500.00
3 Lever Block 1 - 3 ton Sewa / Hari 4 50,000.00 214,500.00
4 Mesin Genset Sewa / Hari 3 602,700.00 1,723,722.00
Jumlah Harga Peralatan 2,581,722.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 7,687,753.75


F Overhead + Profit 10% x E 768,775.38
Jumlah Harga (Total) 8,456,529.13
G Harga Satuan Pekerjaan per - Unit 8,456,529.00
Dibulatkan 8,456,530.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
Pemasangan Trashrack (B= 1m, H= 2,1 m)
Satuan / Unit : 1 Set
Harga Satuan : Rp 1,632,877.00

Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 3.66 75,000.00 274,560.00
2 Tukang las OH 1.83 100,000.00 183,040.00
3 Tukang OH 0.19 98,000.00 18,218.20
4 Mandor OH 0.37 103,000.00 38,295.40
Jumlah Harga Tenaga Kerja 514,113.60
B Bahan
1 Dynabol dla 12 x 120 mm Bh 12.00 2,700.00 32,400.00
2 Batu Gerinda 4" Bh 7.15 30,000.00 214,500.00
3 Campuran beton fc'= 19,3 Mpa m³ 0.11 1,012,398.10 111,475.15
4 Pasangan bata, mortar tipe N m³ 0.00 - -
Jumlah Harga Bahan 358,375.15
C Peralatan
1 Trashrack **) Koef 0.07 8,456,530.00 591,957.10
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 0.55 36,400.00 19,987.97
3 Mesin las listrik 500A, diesel Sewa/hari 0.00 120,400.00 -
Jumlah Harga Peralatan 611,945.07
D Jumlah Harga (A+B+C) 1,484,433.82
E Overhead + Profit 10% xD 148,443.38
F Harga Satuan Pekerjaan (D+E) 1,632,877.20
Dibulatkan 1,632,877.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan : Fabrikasi Trashrack Galvanis B= 1 m, H= 2,0 m
Satuan / Unit : 1 Set
Harga Satuan : Rp 8,420,229.00
Lokas :
Harga Satuan
No Uraian Satuan Koefisien Jumlah (Rp)
(Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 4.29 103,000.00 441,870.00
3 Tukang Las Listrik/Welder OH 4.29 100,000.00 429,000.00
4 Operator Gerinda OH 4.29 126,000.00 540,540.00
9 Helper /Pekerja OH 12.87 75,000.00 965,250.00
Jumlah Harga Tenaga Kerja 2,376,660.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Plate strip Galvanis 5mmx38mmx6m m 11.13 53,333.33 593,600.00
2 Plate strip Galvanis 3mmx30mmx6m m 31.50 33,000.00 1,039,500.00

C Bahan Bantu
1 Kawat Las RD 26 Kg 14.3 27,500.00 393,250.00
2 Sarung Tangan Pendek Stl 7.0 16,000.00 112,000.00
3 Batu Gerinda 4" Bh 28.6 5,500.00 157,300.00
4 Batu Gerinda Cutting 4" Bh 35.8 4,000.00 143,000.00
5 Olie Bor Ltr 0.4 35,000.00 12,512.50
6 Bensin Ltr 7.2 7,600.00 54,340.00
7 Cat anti karat Kg 0.7 63,500.00 45,402.50
8 Kwas Kecil Bh 3 8,000.00 22,880.00
7 Sikat Kawat Bh 3 41,300.00 118,118.00
8 Kain Majun Kg 0.7 6,250.00 4,468.75
Jumlah Harga Bahan 2,696,371.75

D Peralatan Satuan Hari Harga Satuan (Rp) Jumlah (Rp)


1 Mesin Las 500 A Sewa / Hari 3 150,000.00 429,000.00
2 Mesin Gerinda 4" Sewa / Hari 4 50,000.00 214,500.00
3 Lever Block 1 - 3 ton Sewa / Hari 4 50,000.00 214,500.00
4 Mesin Genset Sewa / Hari 3 602,700.00 1,723,722.00
Jumlah Harga Peralatan 2,581,722.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 7,654,753.75


F Overhead + Profit 10% x E 765,475.38
Jumlah Harga (Total) 8,420,229.13
G Harga Satuan Pekerjaan per - Unit 8,420,229.00
Dibulatkan 8,420,229.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
Pemasangan Trashrack (B= 1m, H= 2,0 m)
Satuan / Unit : 1 Set
Harga Satuan : Rp 1,630,082.00

Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 3.66 75,000.00 274,560.00
2 Tukang las OH 1.83 100,000.00 183,040.00
3 Tukang OH 0.19 98,000.00 18,218.20
4 Mandor OH 0.37 103,000.00 38,295.40
Jumlah Harga Tenaga Kerja 514,113.60
B Bahan
1 Dynabol dla 12 x 120 mm Bh 12.00 2,700.00 32,400.00
2 Batu Gerinda 4" Bh 7.15 30,000.00 214,500.00
3 Campuran beton fc'= 19,3 Mpa m³ 0.11 1,012,398.10 111,475.15
4 Pasangan bata, mortar tipe N m³ 0.00 - -
Jumlah Harga Bahan 358,375.15
C Peralatan
1 Trashrack **) Koef 0.07 8,420,229.00 589,416.03
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 0.55 36,400.00 19,987.97
3 Mesin las listrik 500A, diesel Sewa/hari 0.00 120,400.00 -
Jumlah Harga Peralatan 609,404.00
D Jumlah Harga (A+B+C) 1,481,892.75
E Overhead + Profit 10% xD 148,189.28
F Harga Satuan Pekerjaan (D+E) 1,630,082.03
Dibulatkan 1,630,082.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan : Fabrikasi Trashrack Galvanis B= 1 m, H= 1,4 m
Satuan / Unit : 1 Set
Harga Satuan : Rp 6,122,463.00
Lokas :
Harga Satuan
No Uraian Satuan Koefisien Jumlah (Rp)
(Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 3 103,000.00 309,000.00
3 Tukang Las Listrik/Welder OH 3 100,000.00 300,000.00
4 Operator Gerinda OH 3 126,000.00 378,000.00
9 Helper /Pekerja OH 9 75,000.00 675,000.00
Jumlah Harga Tenaga Kerja 1,662,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Plate strip Galvanis 5mmx38mmx6m m 11.13 53,333.33 593,600.00
2 Plate strip Galvanis 3mmx30mmx6m m 22.05 33,000.00 727,650.00

C Bahan Bantu
1 Kawat Las RD 26 Kg 10.0 27,500.00 275,000.00
2 Sarung Tangan Pendek Stl 7.0 16,000.00 112,000.00
3 Batu Gerinda 4" Bh 20.0 5,500.00 110,000.00
4 Batu Gerinda Cutting 4" Bh 25.0 4,000.00 100,000.00
5 Olie Bor Ltr 0.3 35,000.00 8,750.00
6 Bensin Ltr 5.0 7,600.00 38,000.00
7 Cat anti karat Kg 0.5 63,500.00 31,750.00
8 Kwas Kecil Bh 2.0 8,000.00 16,000.00
7 Sikat Kawat Bh 2.0 41,300.00 82,600.00
8 Kain Majun Kg 0.5 6,250.00 3,125.00
Jumlah Harga Bahan 2,098,475.00

D Peralatan Satuan Hari Harga Satuan (Rp) Jumlah (Rp)


1 Mesin Las 500 A Sewa / Hari 2 150,000.00 300,000.00
2 Mesin Gerinda 4" Sewa / Hari 3 50,000.00 150,000.00
3 Lever Block 1 - 3 ton Sewa / Hari 3 50,000.00 150,000.00
4 Mesin Genset Sewa / Hari 2 602,700.00 1,205,400.00
Jumlah Harga Peralatan 1,805,400.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 5,565,875.00


F Overhead + Profit 10% x E 556,587.50
Jumlah Harga (Total) 6,122,462.50
G Harga Satuan Pekerjaan per - Unit 6,122,463.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
Pemasangan Trashrack (B= 1m, H= 1,4 m)
Satuan / Unit : 1 Set
Harga Satuan : Rp 1,168,667.00

Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 2.56 75,000.00 192,000.00
2 Tukang las OH 1.28 100,000.00 128,000.00
3 Tukang OH 0.13 98,000.00 12,740.00
4 Mandor OH 0.26 103,000.00 26,780.00
Jumlah Harga Tenaga Kerja 359,520.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 12.00 2,700.00 32,400.00
2 Batu Gerinda 4" Bh 5.00 30,000.00 150,000.00
3 Campuran beton fc'= 19,3 Mpa m³ 0.08 1,012,398.10 77,954.65
4 Pasangan bata, mortar tipe N m³ 0.00 - -
Jumlah Harga Bahan 260,354.65
C Peralatan
1 Trashrack **) Koef 0.07 6,122,463.00 428,572.41
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 0.38 36,400.00 13,977.60
3 Mesin las listrik 500A, diesel Sewa/hari 0.00 120,400.00 -
Jumlah Harga Peralatan 442,550.01
D Jumlah Harga (A+B+C) 1,062,424.66
E Overhead + Profit 10% xD 106,242.47
F Harga Satuan Pekerjaan (D+E) 1,168,667.13
Dibulatkan 1,168,667.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Fabrikasi Flap Gate Fiberglass ( 1 m x 1 m)
Satuan / Unit : 1 set
Harga Satuan : Rp 34,378,245.00
Lokasi :
No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)
1 2 3 4 5 6
A Tenaga Kerja
1 Mandor OH 2 103,000.00 206,000.00
2 Tukang OH 2 98,000.00 196,000.00
3 Tukang Cat OH 1 98,000.00 98,000.00
4 Tukang Gerinda OH 2 98,000.00 196,000.00
5 Pekerja ( Pembantu Tukang ) OH 2 75,000.00 150,000.00
Jumlah Harga Tenaga Kerja 846,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Resin Carbon Fiber Kg 206.10 110,000.00 22,671,000.00
2 Kobalt 35 ML Polyester Fiberglass Btl 5.00 25,000.00 125,000.00
3 Katalis Kg 4.00 73,500.00 294,000.00
4 Serat Fiber (MAT) Kg 206.40 19,500.00 4,024,800.00
5 Gelcoat Kg 0.50 69,900.00 34,950.00
6 Mirror Glaze Wax (130rb/311gr) Kg 0.50 418,000.00 209,000.00
7 Aseton Ltr 0.50 31,000.00 15,500.00
8 Pigmen (pewarna) gr 250.0 1,250.00 312,500.00
9 Penjernih ( MMA) Ltr 0.5 120,000.00 60,000.00
10 Engsel Pintu Stainless Stell SS 304 Set 1.0 508,000.00 508,000.00
11 Karet Seal m 6.5 175,000.00 1,137,500.00
Jumlah Harga Bahan 29,392,250.00
C Bahan Bantu
1 Dempul Kg 1.0 35,000.00 35,000.00
2 Cat Primer Kg 1.0 63,500.00 63,500.00
3 Cat Finish Kg 1.0 40,000.00 40,000.00
4 Sarung Tangan Pendek Stl 6.0 16,000.00 96,000.00
5 Batu Gerinda 4" Bh 4.0 5,500.00 22,000.00
6 Batu Gerinda Cutting 4" Bh 4.0 4,000.00 16,000.00
7 Amplas Lbr 9.0 3,000.00 27,000.00
Jumlah Harga Bahan 299,500.00

D Peralatan Satuan Hari Harga Satuan (Rp) Jumlah (Rp)


1 Cetakan Sewa / Hari 1 500,000.00 500,000.00
2 Peralatan Painting Sewa / Hari 1 120,400.00 120,400.00
3 Mesin Gerinda 4" Sewa / Hari 2 7,700.00 15,400.00
4 Lever Block 1 - 3 ton Sewa / Hari 2 14,700.00 29,400.00
5 Compressor cat Sewa / Hari 1 50,000.00 50,000.00
Jumlah Harga Peralatan 715,200.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 31,252,950.00


F Overhead + Profit 10% x E 3,125,295.00
Jumlah Harga (Total) 34,378,245.00
G Harga Satuan Pekerjaan per - Unit 34,378,245.00

Berat jenis Fiberglass = 2632 kg/m3


ANALISA HARGA SATUAN PEKERJAAN
JENIS PEKERJAAN : Pemasangan Pintu Flap Gate (1 m x 1 m)
SATUAN : 1 Set
HARGA : Rp 3,421,915.00
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 2.56 75,000.00 192,000.00
2 Tukang Bor OH 1.28 98,000.00 125,440.00
3 Kepala tukang OH 0.13 98,000.00 12,740.00
4 Mandor OH 0.26 103,000.00 26,780.00
Jumlah Harga Tenaga Kerja 356,960.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 12.00 2,700.00 32,400.00
2 Mata Bor 12 Bh 2.00 31,100.00 62,200.00
3 Campuran beton fc'= 19,3 Mpa m3 0.08 1,012,398.10 77,954.65
4 Pasangan bata, mortar tipe N m 3 0.00 195,686.50 -
Jumlah Harga Bahan 172,554.65
C Peralatan
Flape Gate **)
1 buah 0.07 34,378,245.00 2,558,085.21

2 Tackle/Tripod tinggi 4- 5m
Sewa/hari 0.38 50,000.00 19,200.00

3 Meisn Bor Tangan Sewa/hari 0.38 10,500.00 4,032.00


3 Tools Kits Sewa/hari 0.38 10,500.00 4,032.00
Jumlah Harga Peralatan 2,581,317.21
Jumlah Harga Tenaga Kerja, Bahan dan 3,110,831.86
D Peralatan
(A+B+C)
E Overhead + Profit 10% x D 311,083.19
Harga Satuan Pekerjaan per - buah
F 3,421,915.05
(D+E)
Dibulatkan Rp 3,421,915.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Fabrikasi Flap Gate Fiberglass ( 0,4 m x 0,4 m)
Satuan / Unit : 1 set
Harga Satuan : Rp 17,051,348.00

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)


1 2 3 4 5 6
A Tenaga Kerja
1 Mandor OH 2 103,000.00 206,000.00
2 Tukang OH 2 98,000.00 196,000.00
3 Tukang Cat OH 1 98,000.00 98,000.00
4 Tukang Gerinda OH 2 98,000.00 196,000.00
5 Pekerja ( Pembantu Tukang ) OH 2 75,000.00 150,000.00
Jumlah Harga Tenaga Kerja 846,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Resin Carbon Fiber Kg 96.00 110,000.00 10,560,000.00
2 Kobalt 35 ML Polyester Fiberglass Btl 2.50 25,000.00 62,500.00
3 Katalis Kg 2.00 73,500.00 147,000.00
4 Serat Fiber (MAT) Kg 96.00 19,500.00 1,872,000.00
5 Gelcoat Kg 0.25 69,900.00 17,475.00
6 Mirror Glaze Wax (130rb/311gr) Kg 0.25 418,000.00 104,500.00
7 Aseton Ltr 0.25 31,000.00 7,750.00
8 Pigmen (pewarna) gr 125.0 1,250.00 156,250.00
9 Penjernih ( MMA) Ltr 0.3 120,000.00 30,000.00
10 Engsel Pintu Stainless Stell SS 304 Set 1.0 508,000.00 508,000.00
11 Karet Seal m 1.6 175,000.00 280,000.00
Jumlah Harga Bahan 13,745,475.00
C Bahan Bantu
1 Dempul Kg 0.5 35,000.00 17,500.00
2 Cat Primer Kg 0.5 63,500.00 31,750.00
3 Cat Finish Kg 0.5 40,000.00 20,000.00
4 Sarung Tangan Pendek Stl 6.0 16,000.00 96,000.00
5 Batu Gerinda 4" Bh 2.0 5,500.00 11,000.00
6 Batu Gerinda Cutting 4" Bh 2.0 4,000.00 8,000.00
7 Amplas Lbr 6.0 3,000.00 18,000.00
Jumlah Harga Bahan 202,250.00

D Peralatan Satuan Hari Harga Satuan (Rp) Jumlah (Rp)


1 Cetakan Sewa / Hari 1 500,000.00 500,000.00
2 Peralatan Painting Sewa / Hari 1 120,400.00 120,400.00
3 Mesin Gerinda 4" Sewa / Hari 1 7,700.00 7,700.00
4 Lever Block 1 - 3 ton Sewa / Hari 2 14,700.00 29,400.00
5 Compressor cat Sewa / Hari 1 50,000.00 50,000.00
Jumlah Harga Peralatan 707,500.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 15,501,225.00


F Overhead + Profit 10% x E 1,550,122.50
Jumlah Harga (Total) 17,051,347.50
G Harga Satuan Pekerjaan per - Unit 17,051,348.00

Berat jenis Fiberglass = 2632 kg/m3


ANALISA HARGA SATUAN PEKERJAAN
JENIS PEKERJAAN : Pemasangan Pintu Flap Gate (0,4 m x 0,4 m)
SATUAN : 1 Set
HARGA : Rp 1,848,006.00
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 2.00 75,000.00 150,000.00
2 Tukang Bor OH 0.95 98,000.00 93,100.00
3 Kepala tukang OH 0.10 98,000.00 9,800.00
4 Mandor OH 0.20 103,000.00 20,600.00
Jumlah Harga Tenaga Kerja 273,500.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 12.00 2,700.00 32,400.00
2 Mata Bor 12 Bh 1.00 31,100.00 31,100.00
3 Campuran beton fc'= 19,3 Mpa m3 0.04 1,012,398.10 40,495.92
4 Pasangan bata, mortar tipe N m 3 0.00 195,686.50 -
Jumlah Harga Bahan 103,995.92
C Peralatan
Flape Gate **)
1 Koef 0.08 17,051,348.00 1,279,277.38

2 Tackle/Tripod tinggi 4- 5m
Sewa/hari 0.38 50,000.00 19,200.00

3 Meisn Bor Tangan Sewa/hari 0.38 10,500.00 4,032.00


3 Tools Kits Sewa/hari 0.38 10,500.00 4,032.00
Jumlah Harga Peralatan 1,302,509.38
Jumlah Harga Tenaga Kerja, Bahan dan 1,680,005.31
D Peralatan
(A+B+C)
E Overhead + Profit 10% x D 168,000.53
Harga Satuan Pekerjaan per - buah
F 1,848,005.84
(D+E)
Dibulatkan Rp 1,848,006.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Fabrikasi Flap Gate Fiberglass ( 0,3 m x 0,3 m)
Satuan / Unit : 1 set
Harga Satuan : Rp 12,651,408.00

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)


1 2 3 4 5 6
A Tenaga Kerja
1 Mandor OH 1.5 103,000.00 154,500.00
2 Tukang OH 1.5 98,000.00 147,000.00
3 Tukang Cat OH 1 98,000.00 98,000.00
4 Tukang Gerinda OH 1.5 98,000.00 147,000.00
5 Pekerja ( Pembantu Tukang ) OH 2 75,000.00 150,000.00
Jumlah Harga Tenaga Kerja 696,500.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Resin Carbon Fiber Kg 69.60 110,000.00 7,656,000.00
2 Kobalt 35 ML Polyester Fiberglass Btl 2.25 25,000.00 56,250.00
3 Katalis Kg 2.25 73,500.00 165,375.00
4 Serat Fiber (MAT) Kg 69.60 19,500.00 1,357,200.00
5 Gelcoat Kg 0.20 69,900.00 13,980.00
6 Mirror Glaze Wax (130rb/311gr) Kg 0.20 418,000.00 83,600.00
7 Aseton Ltr 0.25 31,000.00 7,750.00
8 Pigmen (pewarna) gr 50.0 1,250.00 62,500.00
9 Penjernih ( MMA) Ltr 0.3 120,000.00 30,000.00
10 Engsel Pintu Stainless Stell SS 304 Set 1.0 508,000.00 508,000.00
11 Karet Seal m 1.2 175,000.00 210,875.00
10,151,530.00
C Bahan Bantu
1 Dempul Kg 0.5 35,000.00 17,500.00
2 Cat Primer Kg 0.5 63,500.00 31,750.00
3 Cat Finish Kg 0.5 40,000.00 20,000.00
4 Sarung Tangan Pendek Stl 5.0 16,000.00 80,000.00
5 Batu Gerinda 4" Bh 3.0 5,500.00 16,500.00
6 Batu Gerinda Cutting 4" Bh 3.0 4,000.00 12,000.00
7 Amplas Lbr 6.0 3,000.00 18,000.00
Jumlah Harga Bahan 195,750.00

D Peralatan Satuan Hari Harga Satuan (Rp) Jumlah (Rp)


1 Cetakan Sewa / Hari 1 250,000.00 250,000.00
2 Peralatan Painting Sewa / Hari 1 120,400.00 120,400.00
3 Mesin Gerinda 4" Sewa / Hari 1 7,700.00 7,700.00
4 Lever Block 1 - 3 ton Sewa / Hari 2 14,700.00 29,400.00
5 Compressor cat Sewa / Hari 1 50,000.00 50,000.00
Jumlah Harga Peralatan 457,500.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 11,501,280.00


F Overhead + Profit 10% x E 1,150,128.00
Jumlah Harga (Total) 12,651,408.00
G Harga Satuan Pekerjaan per - Unit 12,651,408.00

Berat jenis Fiberglass = 2632 kg/m3


ANALISA HARGA SATUAN PEKERJAAN
JENIS PEKERJAAN : Pemasangan Pintu Flap Gate (0,3 m x 0,3 m)
SATUAN : 1 Set
HARGA : Rp 1,598,500.00
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 2.00 75,000.00 150,000.00
2 Tukang Bor OH 0.95 98,000.00 93,100.00
3 Kepala tukang OH 0.10 98,000.00 9,800.00
4 Mandor OH 0.20 103,000.00 20,600.00
Jumlah Harga Tenaga Kerja 273,500.00
B Bahan
1 Dynabol dla 12 x 120 mm Bh 9.00 2,700.00 24,300.00
2 Mata Bor 12 Bh 1.00 31,100.00 31,100.00
3 Campuran beton fc'= 19,3 Mpa m3 0.02 1,012,398.10 20,247.96
4 Pasangan bata, mortar tipe N m 3 0.00 195,686.50 -
Jumlah Harga Bahan 75,647.96
C Peralatan
Flape Gate **)
1 Koef 0.09 12,651,408.00 1,100,027.27

2 Tackle/Tripod tinggi 4- 5m
Sewa/hari 50,000.00 -

3 Meisn Bor Tangan Sewa/hari 0.38 10,500.00 4,032.00


3 Tools Kits Sewa/hari 0.38 10,500.00 4,032.00
Jumlah Harga Peralatan 1,104,059.27
Jumlah Harga Tenaga Kerja, Bahan dan 1,453,207.24
D Peralatan
(A+B+C)
E Overhead + Profit 10% x D 145,320.72
Harga Satuan Pekerjaan per - buah
F 1,598,527.96
(D+E)
Dibulatkan Rp 1,598,500.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
Fabrikasi Pintu Sorong Spindle Tunggal B= 1m, H= 1 m
Satuan / Unit : 1 Set
Harga Satuan : Rp 37,214,111.00

Harga Satuan
No Uraian Satuan Koefisien Jumlah (Rp)
(Rp)
1 2 3 5 6 7
A Tenaga Kerja
1 Mandor OH 5 103,000.00 515,000.00
2 Tukang OH 5 98,000.00 490,000.00
3 Tukang Las Listrik/Welder OH 2 100,000.00 200,000.00
4 Tukang Cat OH 2 98,000.00 196,000.00
5 Operator Sandblasting OH 1 126,000.00 126,000.00
6 Tukang Gerinda OH 2 98,000.00 196,000.00
7 Tukang Skrap OH 2 98,000.00 196,000.00
8 Operator Bubut OH 2 126,000.00 252,000.00
9 Helper /Pekerja OH 30 75,000.00 2,250,000.00
Jumlah Harga Tenaga Kerja 4,421,000.00
B Bahan Utama Satuan Qty Harga Satuan (Rp) Jumlah (Rp)
-
1 Pelat SUS304 (12x1000x1000mm) Kg 99.54 50,000.00 4,977,000.00
2 Baja UNP 100 P = 5,2 m Kg 32.76 16,300.00 533,988.00
3 Drat Stang S45C ø 2,5" , P= 1,5m Kg 40.95 45,405.41 1,859,351.35
4 Karet Seal L m 3.15 350,000.00 1,102,500.00
5 Baut Kuningan 10x20 mm Bh 20.00 13,000.00 260,000.00
6 Pelat Kuningan Penjepit Seal 10x20mm m 3.15 212,500.00 669,375.00
7 Pelat Skoneng SUS 304 Kg 1.05 50,000.00 52,500.00
8 Mur Baut + Ring M.22 x 75 ( st 60/ HTB ) Bh 1.00 16,300.00 16,300.00
9 M+B M SUS 304 M16 x 50 Bh 1.00 30,000.00 30,000.00
10 Gear box assy. Spindle tunggal+Stir Bh 1.00 11,500,000.00 11,500,000.00
12 UNP 150X75X6,5X2500mm SS400 (4 bh) Kg 136.50 16,300.00 2,224,950.00
13 UNP UNP 80X45X6X130mm SS400 (2 bh) Kg 12.3 16,300.00 200,245.50

C Bahan Bantu
1 Kawat Las RD 26 Kg 5.0 27,500.00 137,500.00
2 Cat Primer Kg 1.0 30,000.00 30,000.00
3 Cat Finish Kg 1.0 40,000.00 40,000.00
4 Pasir Sandblast Kg 3.0 15,600.00 46,800.00
5 Sarung Tangan Pendek Stl 12.0 16,000.00 192,000.00
6 Batu Gerinda 4" Bh 20.0 5,500.00 110,000.00
7 Batu Gerinda Cutting 4" Bh 20.0 4,000.00 80,000.00
8 Olie Bor Ltr 0.3 35,000.00 8,750.00
9 Bensin Ltr 5.0 7,600.00 38,000.00
9 Sikat Kawat Bh 2.0 41,300.00 82,600.00
10 Kain Majun Kg 1.0 6,250.00 6,250.00
Jumlah Harga Bahan 24,198,109.85
D Peralatan Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)
1 Mesin Las 500 A Sewa / Hari 2 120,400.00 240,800.00
2 Peralatan Sandblasting Sewa / Hari 1 541,100.00 541,100.00
3 Peralatan Painting Sewa / Hari 2 120,400.00 240,800.00
4 Mesin Skrap Sewa / Hari 2 249,200.00 498,400.00
5 Mesin Gerinda 4" Sewa / Hari 5 7,700.00 38,500.00
6 Mesin Bor Sewa / Hari 5 10,500.00 52,500.00
7 Lever Block 1 - 3 ton Sewa / Hari 2 14,700.00 29,400.00
8 Compressor Sandblast Sewa / Hari 1 1,250,000.00 1,250,000.00
9 Compressor Cat Sewa / Hari 2 50,000.00 100,000.00
10 Genset Sewa / Hari 2 602,700.00 1,205,400.00
11 Tri Port / Box Gawang Sewa / Hari 5 36,400.00 182,000.00
12 Mesin Bubut Sewa / Hari 2 416,500.00 833,000.00
Jumlah Harga Peralatan 5,211,900.00

E Jumlah Harga Tenaga, Bahan dan Peralatan ( A + B + C + D ) 33,831,009.85


F Overhead + Profit 10% x E 3,383,100.99
Jumlah Harga (Total) 37,214,110.84
G Harga Satuan Pekerjaan per - Unit 37,214,111.00
ANALISA HARGA SATUAN PEKERJAAN
Pekerjaan :
Pemasangan Pintu Sorong Spindle Tunggal (B= 1m, H= 1 m)
Satuan / Unit : 1 Set
Harga Satuan : Rp 3,640,233.00

Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
1 2 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 2.56 75,000.00 192,000.00
2 Tukang las OH 1.28 100,000.00 128,000.00
3 Tukang OH 0.13 98,000.00 12,740.00
4 Mandor OH 0.26 103,000.00 26,780.00
Jumlah Harga Tenaga Kerja 359,520.00
B Bahan
1 Besi pengaku kg 7.68 16,301.25 125,193.60
2 Kawat las listrik RB 26 kg 1.71 30,000.00 51,300.00
3 Campuran beton fc'= 19,3 Mpa m³ 0.08 1,012,398.10 77,954.65
4 Pasangan bata, mortar tipe N m³ 0.15 195,686.50 30,135.72
Jumlah Harga Bahan 284,583.97
C Peralatan
1 Pintu air **) Koef 0.07 37,214,111.00 2,604,987.77
2 Tackle/Tripod tinggi 4- 5m Sewa/hari 0.38 36,400.00 13,977.60
3 Mesin las listrik 500A, diesel Sewa/hari 0.38 120,400.00 46,233.60
Jumlah Harga Peralatan 2,665,198.97
D Jumlah Harga (A+B+C) 3,309,302.94
E Overhead + Profit 10% x D 330,930.29
F Harga Satuan Pekerjaan (D+E) 3,640,233.24
3,640,233.00
DAFTAR HARGA SATUAN PEKERJAAN
KAB. BREBES
Pekerjaan : Pengendalian Banjir Sungai Cimanuk, Cisanggarum, Babakan
Lokasi : BBWS Cimanuk-Cisanggarum
Tahun Anggaran : 2022

NO. URAIAN SATUAN HARGA SATUAN KETERANGAN

I UPAH
1 Pekerja OH 75,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
2 Pembantu Tukang OH 90,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
3 Tukang OH 98,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
4 Mandor OH 103,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
5 Mekanik OH 98,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
6 Operator terlatih OH 126,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
7 Pembantu Operator OH 90,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
8 Tukang Las Konstruksi OH 100,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
9 Tukang Cat OH 98,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
10 Tukang Kayu/Batu OH 98,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
11 Pekerja OH 75,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021

NO. URAIAN SATUAN HARGA SATUAN KETERANGAN

II.1 BAHAN UTAMA


1 Paku Kg Rp 16,400.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
2 Paku skrup ( utk Gypsum) Kg Rp 16,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
3 Skrup atap onduline Bh Rp 600.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
4 Skrup vixer Bh Rp 700.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
5 Dynabol dla 12 x 120 mm Bh Rp 2,700.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
6 Paku asbes gelombang Kg Rp 36,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
7 Paku Panclng Kg Rp 17,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
8 Besl beton U-24 Kg Rp 12,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
9 Besl befon U-29 Kg Rp 12,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
10 Besi beton Polos U - 32 Kg Rp 12,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
11 Besi beton Ullr U - 32 Kg Rp 12,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
12 Besi Holk›w Galvanis 40x40x400x3 mm m Rp 25,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
13 Kawat beton (bindrad} Kg Rp 20,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
14 Baja struktur jembatan ranqka terpasang Kg Rp 40,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
15 Wlremash-M4 uk= 2.10 x 5.40 m’ (uk.Roll=2.10x50 m²) Lembar Rp 165,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
16 Wiremesh-M5 uk= 2.10 x 5.40 m' (uk. Roll=2.10x50 m'} Lembar Rp 245,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
17 Wiremesh-M6 uk= 2.10 x 5.40 m’ (uk. Roll=2.10x50 m’) Lembar Rp 415,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
18 Wiremesh-M7 uk= 2.10 x 5.40 m’ (uk. Roll=2.10x50 m’) Lembar Rp 480,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
19 Wiremesh-M8 uk= 2.10 x 5.40 m' (uk. Roll=2.10x50 m’) Lembar Rp 717,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
20 Wiremesh-M9 uk= 2.10 x 5.40 m' (uk. Roll=2.10x50 m') Lembar Rp 790,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
21 Wiremesh-M10 uk =2.10x5.40 m’ (uk. Roll=2.10x50 m') Lembar Rp 1,025,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
22 Wiremesh-M12 uk =2.10x5.40 m’ (uk. Roll=2.10x50 m’) Lembar Rp 1,450,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
23 Kawat bronjong D 4 mm ( Manual ) Kg Rp 16,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
24 Kawat bronjong D 3 mm (Pabrikasi) m³ Rp 405,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
25 Kawat bronjong D 2,70 mm ( Pabrikasi ) m³ Rp 362,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
26 Kawat bronjong D 2,70 mm (Pabrikasi) PVC Coated  m³ Rp 485,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
27 BaJa plate Kg Rp 14,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
28 Baja Plate SUS 304 8 mm Finishing 1B/1D Kg Rp 50,000.00 PT CITRA ANGGUN LESTARI
29 Baja Plate SUS 304 10 mm Finishing 1B/1D Kg Rp 50,000.00 PT CITRA ANGGUN LESTARI
30 Baja Plate SUS 304 12 mm Finishing 1B/1D Kg Rp 50,000.00 PT CITRA ANGGUN LESTARI
31 Baut Hitam 5/8" (6 cm) Bh Rp 6,500.00 Toped
32 Baut Kuningan 10 x20 mm Bh Rp 13,000.00 Toped
33 M+B M SUS 304 M16 x 50 Bh Rp 12,000.00 Toped
34 M+B M SUS 304 M20 x 60 Bh Rp 16,300.00 Toped
35 Mur Baut + Ring M.22 x 75 ( st 60/ HTB ) BH Rp 16,300.00 Toped
36 Plate Kuningan Penjepit 10 mmx20mm m Rp 212,500.00 Toped
37 Baia baud - baud struktur B 1" x 4" (102 mml Bh Rp 22,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
38 Baja baud - baud struktur 4l 1" x 2.3/4" (69 mm) Bh Rp 24,200.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
39 Bata baud - baud struktur 4\ 5/8”(16 mm} x 2" (5t mm } Bh Rp 6,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
40 Bala baud - baud struktur jg 3/4"(16 mm) x 2" (51 mm ) Bh Rp 10,100.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
41 Besi kanal C/CNP Kg Rp 16,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
42 Besi kanal U/UNP Kg Rp 16,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
43 Best siku L Kg Rp 16,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
44 Best IWF Kg Rp 16,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
45 Pagar BRC Galvanis 90 x 240 cm Lmbr Rp 300,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
46 Pagar BRC Galvanis 120 x 240 cm Lmbr Rp 320,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
47 Tiang BRC Galvanis panjang 120 cm Bh Rp 27,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
48 Tlang BRC Galvanis panjang 150 cm Bh Rp 45,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
49 Polyetylene 125 mikron Ltr Rp 24,400.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
50 Beton K 100 (ready mix} m³ Rp 875,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
51 Beton K 125 (ready mix} m³ Rp 900,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
52 Beton K 150 (ready mlx} m³ Rp 913,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
53 Beton K 175 (ready mix) m³ Rp 932,800.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
54 Beton K 200 (ready mix) m³ Rp 956,600.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
55 Beton K 225 (ready mix) m³ Rp 1,008,600.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
56 Beton K 250 (ready mlx) m³ Rp 1,028,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
57 Beton K 300 (ready mix) m³ Rp 1,065,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
58 Beton K 350 (ready mix) m³ Rp 1,131,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
59 Beton K 400 (readv mix) m³ Rp 1,177,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
62 Besi Strip (t=5 mm, L = 5 cm) Kg Rp 9,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
63 Besi Polos (t = 5 mm, L = 5 cm) Kg Rp 9,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
64 Plate strip Galvanis 5mmx38mmx6m m Rp 53,333.33 Toped (IDP Steel)
65 Plate strip Galvanis 3mmx30mmx6m m Rp 33,000.00 Toped (IDP Steel)
66 Engsel Pintu Stainless Stell SS 304 set (2 pc) Rp 508,000.00 RAFES (TOPED)
67 Besi As ( SS 400) Kg Rp 52,500.00 Toko Pedia (Automoves)
68 Besi As ( S45C) Kg Rp 45,405.41 Toko Pedia (Lapak Bintang)
69 Besi As SUS304 Kg Rp 100,000.00 Toko Pedia (Ganesha Logam)
70 Bronze as bronze Kg 1,076,471.00 Shopee Indonesia (tabel berat+harga/lmbr)
71 Karet P 30 m 350,000.00 TOPED
72 Karet L Kecil m 175,000.00 TOPED
73 Karet L Besar m 250,000.00 TOPED
74 Resin Carbon Fiber Kg 110,000.00 Toko Pedia ( Bahan Fiberglass)
75 Kobalt 35 ML Polyester Fiberglass Btl 25,000.00 Toko Pedia
76 Katalis Kg 73,500.00 Toko Pedia
77 Serat Fiber (MAT) Kg 38,000.00 Toko Pedia
78 Gelcoat Kg 69,900.00 Toko Pedia
79 Mirror Glaze Wax (130rb/311gr) Kg 418,000.00 Toko Pedia
80 Aseton Ltr 31,000.00 Toko Pedia
81 Pigmen (pewarna) gram 1,250.00 Toko Pedia
82 Penjernih ( MMA) Ltr 120,000.00 Toko Pedia

II.2 BAHAN BANTU


1 Kawat Las Kg Rp 26,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
2 Kawat Las Listrik RD 26 Kg Rp 27,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
3 Kawat Las Listrik RB 26 Kg Rp 30,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
4 Olie Ltr Rp 35,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
5 Solar bersubsidl Ltr Rp 5,700.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
6 Solar Industri Ltr Rp 8,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
7 Solar Non Subsidi (Dexlite} Ltr Rp 9,700.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
8 Minyak tanah Ltr Rp 15,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
9 Minyak pelumas Ltr Rp 40,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
10 Grease Bh Rp 25,900.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
11 Mlnyak Transmisi Bh Rp 41,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
12 Bensin / premium Bh Rp 7,600.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
13 Hydraulic Oil Bh Rp 41,300.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
14 Sikat Baja Bh Rp 14,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
15 Sealant Kg Rp 15,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
16 Lem Kayu Kg Rp 20,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
17 Lem Kunlng Kg Rp 35,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
18 Cat Warna ( Kayu ). Kg Rp 58,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
19 Cat Warna ( besi ) Kg Rp 40,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
20 Cat dasar ( meni kayu ) Kg Rp 30,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
21 Cat dasar ( meni besi ) Kg Rp 30,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
22 Cat Jembatan ( besi ) Kg Rp 60,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
23 Dempul Kg Rp 35,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
24 Amplas Lbr Rp 3,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
25 cat anti karat Kg Rp 63,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
26 LPG 50 Kg Kg 675,000.00 Malaka Teknik (Toped)
27 Okigen M3 15,000.00 Malaka Teknik (Toped)
28 Pasir Sandblast Kg 4,000.00 Toped
29 Sarung Tangan Pendek Stl 16,000.00 Toped
30 Batu Gerinda 4" Bh 5,500.00 Toped
31 Batu Gerinda Cutting 4" Bh 4,000.00 Toped
32 Kuwas 2" Bh 8,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
33 Kuwas 3" Bh 10,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
34 Kuwas 4" Bh 18,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
35 Majun Kg 6,250.00 Toped
36 Pasir Qualitas 1 M3 182,500.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
37 Karung Plastik / Bagor / Goni Bh 1,200.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
38 Tali Rapia / Plastik M3 9,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
NO. URAIAN SATUAN HARGA SATUAN KETERANGAN

III PERALATAN
1 Mesin Las 500 A Sewa / Hari 120,400.00
2 Mesin Las 250 A Sewa / Hari 41,300.00
3 Manual Gas Cutting Sewa / Hari 17,220.00
4 Automatic Gas Cutting Sewa / Hari 31,500.00
5 Peralatan Sandblasting Sewa / Hari 541,100.00
6 Peralatan Painting Sewa / Hari 120,400.00
7 Mesin Bubut Kecil Sewa / Hari 124,600.00
8 Mesin Bubut Besar Sewa / Hari 416,500.00
9 Mesin Skrap Sewa / Hari 249,200.00
10 Mesin Frais Sewa / Hari 311,500.00
11 Mesin Bor Radial Sewa / Hari 218,400.00
12 Mesin Bor Magnet Sewa / Hari 13,300.00
13 Mesin Gerinda 4" Sewa / Hari 7,700.00
14 Mesin Gerinda 7" Sewa / Hari 13,300.00
15 Lever Block 1 - 3 ton Sewa / Hari 14,700.00
16 Chain Block 3 - 5 Ton Sewa / Hari 30,100.00
17 Mesin Genset Sewa / Hari 602,700.00
18 Tri Port / Box Gawang Sewa / Hari 36,400.00
19 Mesin Bor Tangan Sewa / Hari 10,500.00
20 Tool Kits Sewa / Hari 10,500.00
21 Mesin Gerinda Cutting 14" Sewa / Hari 23,100.00
22 Jack Hammer 1600 Bpm, 45 J Sewa / Hari 192,500.00
23 Truck Crane 3 Ton Sewa / Hari 4,361,000.00
24 Truck Sewa / Hari 6,246,800.00
25 Compressor Sandblast PDS 185s Sewa / Hari 1,250,000.00 AIRMAN (Toped)
25 Compresor Cat Sewa / Hari 50,000.00 Kaskus
26 Sewa Concrete Pump Beton Sewa / Hari 5,071,000,00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
26 Sewa Pontoon Sewa / Hari 435,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
27 Sewa Vibrator Sewa / Hari 304,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
27 Sewa Alat Perakitan Baja Sewa / Hari 83,000.00 SK KADIN PUPR BREBES NO 050/00247 Tgl 5 JANUARI 2021
28 Pompa Air Bensin 5 kw Sewa / Hari 95,200.00