Anda di halaman 1dari 8

ANALISA HARGA SATUAN

BONGKARAN

HARGA ( Rp)
No. Vol. URAIAN KOOEF St.
SATUAN JUMLAH TOTAL

1. 1 M2 PEMBONGKARAN PENUTUP ATAP SENG GELOMBANG 691,675.00


TENAGA
Pekerja Tak Terampil 0.333 Oh 75,000.00 24,975.00
Tukang Kayu 6.667 Oh 100,000.00 666,700.00 691,675.00

ALAT
JUMLAH 691,675.00
OVERHEAD 0 -
JUMLAH 691,675.00

2. 1 M3 PEMBONGKARAN BETON 549,975.00


TENAGA
Mandor 0.333 Oh 150,000.00 49,950.00
Pekerja Tak Terampil 6.667 Oh 75,000.00 500,025.00 549,975.00

ALAT
JUMLAH 549,975.00
OVERHEAD 0 -
JUMLAH 549,975.00

3. 1 M2 PEMBONGKARAN RANGKA ATAP BAJA


TENAGA
Mandor 0.025 Oh 150,000.00 3,750.00
Pekerja Tak Terampil 0.250 Oh 75,000.00 18,750.00 22,500.00

BAHAN
JUMLAH 22,500.00
OVERHEAD 0 -
JUMLAH 22,500.00

4. 1 UNIT PEMBONGKARAN KUSEN PINTU/JENDELA KAYU 22,500.00


TENAGA
Mandor 0.025 Oh 150,000.00 3,750.00
Pekerja Tak Terampil 0.250 Oh 75,000.00 18,750.00 22,500.00

BAHAN
JUMLAH 22,500.00
OVERHEAD 0 -
JUMLAH 22,500.00

5. 1 M2 STRIPPING SETINGGI 1.00 m 15,150.00


TENAGA
Mandor 0.005 Oh 150,000.00 750.00
Pekerja Tak Terampil 0.192 Oh 75,000.00 14,400.00 15,150.00

BAHAN
JUMLAH 15,150.00
OVERHEAD 0 -
JUMLAH 15,150.00

6. 1 M2 1 BUAH POHON DIA 60 CM TERMASUK PEMOTONGAN DAHAN SIAP ANGKUT


TENAGA
Mandor 1.022 Oh 150,000.00 153,300.00
Tukang Potong Pohon 0.500 Oh 100,000.00 50,000.00
Pekerja Tak Terampil 4.222 Oh 75,000.00 316,650.00 519,950.00

BAHAN
Bahan bakar 8.00 Ltr 7,000.00 56,000.00
Minyak Pelumas 2.00 Ltr 33,000.00 66,000.00
122,000.00
ALAT
Sewa Mesin Potong Pohon 2.00 jam 100,000.00 200,000.00
Alat Bantu 1.00 ls 30,000.00 30,000.00 230,000.00
JUMLAH 871,950.00
OVERHEAD 0 -
871,950.00

7. 1M BONGKAR KERAMIK 40,000.00


TENAGA
Mandor 0.200 Oh 150,000.00 30,000.00
Pekerja Tak Terampil 0.100 Oh 100,000.00 10,000.00 40,000.00
JUMLAH 40,000.00
OVERHEAD 0.0000 -
40,000.00

8. 1 M2 PEMBONGKARAN DINDING LAMA DAN PLESTERAN


TENAGA
Mandor 0.0330 oh 150,000.00 4,950.00
Pekerja tak terampil 0.6670 oh 100,000.00 66,700.00 71,650.00
JUMLAH 71,650.00
OVERHEAD 0.0000 -
JUMLAH 71,650.00

9. 1 M2 PEMBONGKARAN PAS BATA LAMA TANPA PLESTER (EKSPOSE)


TENAGA
Mandor 0.020 oh 150,000.00 3,000.00
Kepala tukang kayu 0.020 oh 100,000.00 2,000.00
Tukang kayu 0.200 oh 100,000.00 20,000.00
Pekerja tak terampil 0.400 oh 100,000.00 40,000.00
JUMLAH 65,000.00
OVERHEAD 0.0000 -
JUMLAH 65,000.00

10. 1 M3 BONGKARAN BETON BERTULANG


TENAGA
Mandor 0.3330 oh 150,000.00 49,950.00
Pekerja tak terampil 6.6670 oh 100,000.00 666,700.00 716,650.00
JUMLAH 716,650.00
OVERHEAD 0.0000 -
JUMLAH 716,650.00

11. 1 M2 PEK. BONGKAR BAK BUNGA LAMA / DINDING BATA


TENAGA
Pekerja Tak Terampil 0.1250 oh 100,000.00 12,500.00
Mandor 0.0500 oh 150,000.00 7,500.00 20,000.00
JUMLAH 20,000.00
OVERHEAD 0.0000 -
JUMLAH 20,000.00

12. 1 M3 PEK. BUANGAN TANAH DAN TAMAN BEKAS BAK BUNGA LAMA
TENAGA
Mandor 1.2500 oh 150,000.00 187,500.00
Pekerja tak terampil 0.5000 oh 100,000.00 50,000.00
Peralatan Dan Alat Angkut 0.2500 oh 5,000.00 1,250.00 238,750.00
JUMLAH 238,750.00
OVERHEAD 0.0000 -
JUMLAH 238,750.00

13. 1 M2 PEK. BONGKAR ADUKAN / RABAT LANTAI LAMA DAN PEMBUANGAN BONGKARAN
TENAGA
Mandor 0.0300 oh 150,000.00 4,500.00
Pekerja tak terampil 0.3000 oh 100,000.00 30,000.00
- 34,500.00
ALAT
Sewa Alat Pembongkaran 0.4000 Jam 20,000.00 8,000.00
Alat Angkut (Pic Up) 0.2500 Jam 70,000.00 17,500.00 25,500.00
JUMLAH 60,000.00
OVERHEAD 0.0000 -
JUMLAH 60,000.00

14. 1 M3 BONGKAR RANGKA DAN PENUTUP PLAFOND LAMA 28,100.00


TENAGA
Pekerja Biasa 0.200 Org/hr 100,000.00 20,000.00
Tukang Kayu 0.060 Org/hr 100,000.00 6,000.00
Kepala Tukang Kayu 0.006 Org/hr 100,000.00 600.00
Mandor 0.010 Org/hr 150,000.00 1,500.00 28,100.00
ALAT
JUMLAH 28,100.00
OVERHEAD 0.0000 -
JUMLAH 28,100.00

15. 1 M2 PEMBONGKARAN GENTENG LAMA DAN MENURUNKAN UNTUK PASANG KEMBALI


TENAGA
Pekerja Biasa 0.20 oh 75,000.00 15,000.00
Tukang Kayu 0.15 oh 100,000.00 15,000.00
Kepala Tukang Kayu - oh 100,000.00 -
Mandor 0.05 oh 150,000.00 7,500.00 37,500.00
JUMLAH 37,500.00
OVERHEAD 0.0000 -
JUMLAH 37,500.00

16. 1 M2 BONGKAR BUBUNGAN LAMA


TENAGA
Pekerja Biasa 0.100 Org/hr 75,000.00 7,500.00
Tukang Kayu Org/hr -
Kepala Tukang Kayu Org/hr -
Mandor 0.005 Org/hr 150,000.00 750.00 8,250.00
JUMLAH 8,250.00
OVERHEAD 0.0000 -
JUMLAH 8,250.00

17. 1 M2 BONGKAR USUK DAN RENG LAMA


TENAGA
Pekerja Biasa 0.100 Org/hr 75,000.00 7,500.00
Tukang Kayu Org/hr -
Kepala Tukang Kayu Org/hr -
Mandor 0.010 Org/hr 150,000.00 1,500.00 9,000.00
JUMLAH 9,000.00
OVERHEAD 0.0000 -
JUMLAH 9,000.00

18. 1 M1 BONGKAR LISTPLANK


TENAGA
Pekerja Biasa 0.100 Org/hr 75,000.00 7,500.00
Tukang Kayu Org/hr -
Kepala Tukang Kayu Org/hr -
Mandor 0.001 Org/hr 150,000.00 150.00 7,650.00
JUMLAH 7,650.00
OVERHEAD 0.0000 -
JUMLAH 7,650.00

19. 1 M2 KUPAS PLESTERAN


TENAGA
Pekerja Biasa 0.125 Org/hr 75,000.00 9,375.00
Tukang Kayu Org/hr -
Kepala Tukang Kayu Org/hr -
Mandor 0.010 Org/hr 150,000.00 1,500.00 10,875.00
JUMLAH 10,875.00
OVERHEAD 0.0000 -
JUMLAH 10,875.00

20. 1 M2 BONGKAR PAGAR BESI


TENAGA
Pekerja 0.122 oh 75,000.00 9,150.00
Tukang besi 0.050 oh 100,000.00 5,000.00
Kepala tukang 0.002 oh 125,000.00 250.00
Mandor 0.002 oh 150,000.00 300.00 14,700.00
JUMLAH 14,700.00
OVERHEAD 0.0000 -
JUMLAH 14,700.00