PEKERJAAN PERSIAPAN
PS01 1 m2 - Pembersihan Lokasi
Pekerja 0.0500 hr 80,000.00 4,000.00
Mandor 0.0100 hr 120,000.00 1,200.00
JUMLAH 5,200.00
DIBULATKAN 5,200.00
PS02 1 bh - Papan nama proyek
Multipleks 120 x 240, 9 mm 0.5000 lbr 120,000.00 60,000.00
Kaso kayu meranti 0.0280 m3 3,000,000.00 84,000.00
Penulisan 1.0000 ls - -
Ongkos pasang 1.0000 ls - -
JUMLAH 144,000.00
DIBULATKAN 144,000.00
PS03 1 m2 - Direksikeet (lantai plesteran)
Pasir pasang 0.2500 m3 225,000.00 56,250.00
Pasir beton 0.0517 m3 230,000.00 11,891.00
Batu bata merah 25.0000 bh 800.00 20,000.00
Semen PC 50 kg 0.2500 zak 68,000.00 17,000.00
Kayu kaso meranti 0.0300 m3 3,000,000.00 90,000.00
Triplek 122 x 244 x 4 mm 1.0000 lbr 60,000.00 60,000.00
Engsel pintu uk 3 " 0.1667 bh 45,000.00 7,501.50
Asbes semen gelombang 250x92 x 0. 5 cm 0.5000 lbr 85,000.00 42,500.00
Paku segala ukuran ( rata-rata) 0.5000 kg 16,500.00 8,250.00
Kunci gembok 0.0834 bh 50,000.00 4,170.00
Pekerja 0.4000 hr 80,000.00 32,000.00
Tukang batu 0.0834 hr 90,000.00 7,506.00
Tukang kayu 0.3340 hr 90,000.00 30,060.00
Mandor 0.0200 hr 120,000.00 2,400.00
JUMLAH 389,528.50
DIBULATKAN 389,528.00
PS04 1 m1 - Pagar BRC tinggi 1,2 cm
BRC t = 1.2 m Ø 8 1.0000 m1 540,000.00 540,000.00
Tiang BRC 1.2500 m1 170,000.00 212,500.00
Galian tanah pondasi 0.1200 m3 63,000.00 7,560.00
Pasir beton 0.0150 m3 230,000.00 3,450.00
Batu pecah 3/4 0.0290 m2 220,000.00 6,380.00
Semen PC ( 50 kg ) 0.2250 m2 68,000.00 15,300.00
Pekerja 0.0420 hr 80,000.00 3,360.00
Tukang batu 0.0420 hr 90,000.00 3,780.00
Kepala Tukang Batu 0.0040 hr 100,000.00 400.00
Mandor 0.0020 hr 120,000.00 240.00
JUMLAH 792,970.00
DIBULATKAN 792,970.00
PS05 1 m1 - Pengukuran & pemasangan bouwplank
Kayu Kaso terentang 5/7-400 cm 0.0040 m3 3,000,000.00 12,000.00
Kayu Papan terentang 2/20- 400 cm 0.0060 m3 1,750,000.00 10,500.00
Paku segala ukuran 0.0200 kg 16,500.00 330.00
Pekerja 0.0500 hr 80,000.00 4,000.00
Tukang Kayu 0.0500 hr 90,000.00 4,500.00
Mandor 0.0050 hr 120,000.00 600.00
JUMLAH 31,930.00
DIBULATKAN 31,930.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
PEKERJAAN TANAH
PEKERJAAN PONDASI
PEKERJAAN BETON
JUMLAH 1,216,542.00
DIBULATKAN 1,216,542.00
BT17 1 m3 - Bekisting lantai beton
Kayu Kaso terentang 5/7-400 cm 0.2320 m3 3,000,000.00 696,000.00
Multiplex 9 mm 2.9050 lbr 120,000.00 348,600.00
Paku 2.0750 kg 16,500.00 34,237.50
Pekerja 1.3700 hr 80,000.00 109,600.00
Tukang kayu 3.2685 hr 90,000.00 294,165.00
Mandor 0.2245 hr 120,000.00 26,940.00
JUMLAH 1,509,542.50
DIBULATKAN 1,509,542.00
BT18 1 m2 - Perancah kayu / stoot werk - tinggi s/d 2 m
Kayu Kaso terentang 5/7-400 cm 0.0608 m3 3,000,000.00 182,400.00
Paku 0.3000 kg 16,500.00 4,950.00
Pekerja 0.6000 hr 80,000.00 48,000.00
Tukang kayu 0.4200 hr 90,000.00 37,800.00
Mandor 0.0300 hr 120,000.00 3,600.00
JUMLAH 276,750.00
DIBULATKAN 276,750.00
BT19 1 m2 - Perancah kayu / stoot werk - tinggi s/d 3 m
Kayu Kaso terentang 5/7-400 cm 0.0851 m3 3,000,000.00 255,300.00
Paku 0.4200 kg 16,500.00 6,930.00
Pekerja 0.8400 hr 80,000.00 67,200.00
Tukang kayu 0.5880 hr 90,000.00 52,920.00
Mandor 0.0420 hr 120,000.00 5,040.00
JUMLAH 387,390.00
DIBULATKAN 387,390.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
DIBULATKAN 4,342,570.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
JUMLAH 38,986.00
DIBULATKAN 38,986.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
ST04 1 bh - Wastafel
Wastafel + Accesoris 1.0000 bh - -
Pekerja 0.3000 hr 80,000.00 24,000.00
Tukang batu 0.2500 hr 90,000.00 22,500.00
Mandor 0.1800 hr 120,000.00 21,600.00
JUMLAH 68,100.00
DIBULATKAN 68,100.00
ST05 1 bh - Kitchen Zink
Kitchen Zink 1.0000 bh - -
Pekerja 0.3000 hr 80,000.00 24,000.00
Tukang batu 0.2500 hr 90,000.00 22,500.00
Mandor 0.1800 hr 120,000.00 21,600.00
JUMLAH 68,100.00
DIBULATKAN 68,100.00
ST05a 1 bh - Exhausfan
Exhausfan 1.0000 bh 385,000.00 385,000.00
Pekerja 0.3000 hr 80,000.00 24,000.00
Tukang batu 0.2500 hr 90,000.00 22,500.00
Mandor 0.1800 hr 120,000.00 21,600.00
JUMLAH 453,100.00
DIBULATKAN 453,100.00
ST07 1 bh - Floor drain
Floor drain stainless 1.0000 bh 110,000.00 110,000.00
Pekerja 0.0100 hr 80,000.00 800.00
Tukang batu 0.1000 hr 90,000.00 9,000.00
Mandor 0.0050 hr 120,000.00 600.00
JUMLAH 120,400.00
DIBULATKAN 120,400.00
ST08 1 bh - Shower
Shower 1.0000 bh 1,800,000.00 1,800,000.00
Pekerja 0.0100 hr 80,000.00 800.00
Tukang batu 0.1000 hr 90,000.00 9,000.00
Mandor 0.0050 hr 120,000.00 600.00
JUMLAH 1,810,400.00
DIBULATKAN 1,810,400.00
ST09 1 bh - Kran leher angsa 1/2"
Kran air leher angsa 1/2 1.0000 bh 325,000.00 325,000.00
Seal tape 0.0250 roll 2,500.00 62.50
Lem pipa PVC 0.1250 tube 12,000.00 1,500.00
Pekerja 0.0100 hr 80,000.00 800.00
Tukang batu 0.1000 hr 90,000.00 9,000.00
Mandor 0.0050 hr 120,000.00 600.00
JUMLAH 336,962.50
DIBULATKAN 336,962.00
ST10 1 bh - Kran air 1/2"
Kran air 1/2 1.0000 bh 191,000.00 191,000.00
Seal tape 0.0250 roll 2,500.00 62.50
Lem pipa PVC 0.1250 tube 12,000.00 1,500.00
Pekerja 0.0100 hr 80,000.00 800.00
Tukang batu 0.1000 hr 90,000.00 9,000.00
Mandor 0.0050 hr 120,000.00 600.00
JUMLAH 202,962.50
DIBULATKAN 202,962.00
ST11 1 unit - Pompa air jet pump + Instalasi dan pengeboran
Pompa air jet pump 1.0000 bh 4,200,000.00 4,200,000.00
Pipa PVC 1 " 40.0000 m1 14,000.00 560,000.00
Pipa PVC 4 " 16.0000 m1 55,000.00 880,000.00
Bocht LL-D 1" (lokal) 6.0000 bh 58,500.00 351,000.00
Water moer 2.0000 bh 78,000.00 156,000.00
Ongkos pengeboran 40.0000 m1 90,000.00 3,600,000.00
JUMLAH 9,747,000.00
DIBULATKAN 9,747,000.00
NO. URAIAN KOEF. SAT. HARGA SATUAN JUMLAH
1 m2 - Pasang Tangga Besi Maintenance + Tutup Manhole Plat Besi + Gembok + Finish Cat
Pipa Besi BSP 2" 2.0000 Btg 498,000.00 996,000.00
Besi Plat 14.0000 Kg 14,900.00 208,600.00
Besi Siku 4x4 9.6667 Kg 14,900.00 144,033.33
Kawat Las Listrik 0.3333 Dus 34,000.00 11,333.33
Gembok 60mm merk AXEL 1.0000 bh 50,000.00 50,000.00
Cat Kayu/Besi Setara Glotek 0.5000 Kg 46,400.00 23,200.00
Pengelasan 4.0000 jam 15,000.00 60,000.00
Pekerja 0.5000 hr 80,000.00 40,000.00
Tukang besi 0.5000 hr 90,000.00 45,000.00
Kepala Tukang Besi 0.0500 hr 100,000.00 5,000.00
Mandor 0.0250 hr 120,000.00 3,000.00
JUMLAH 1,586,166.67
DIBULATKAN 1,586,166.00
Penawar
PT. / CV. ...............................
NAMA DIREKTUR
DIREKTUR
HARGA PERKIRAAN SENDIRI (HPS)
TAHUN 2016
DINAS BANGUNAN - KOTA TANGERANG
II PAVING BLOCK
Paving Block K 250 Tebal 6 Abu-abu 89,100.00 m2
Paving Block K 250 Tebal 8 Abu-abu 111,100.00 m2
Paving Block K 350 Tebal 6 Abu-abu 108,900.00 m2
Paving Block K 350 Tebal 8 Abu-abu 130,900.00 m2
Grass Block uk. 20.40.6 cm 104,500.00 m2
Kolom pagar precast t = 3 m, mutu beton K225 297,000.00 bh
Panel precast t : 40 cm p : 2.4 m , mutu beton K225 201,300.00 bh
Kolom pagar precast t = 3.5 m, mutu beton K225 358,600.00 bh
Panel precast t : 50 cm p : 2.4 m , mutu beton K225 297,000.00 bh
Kanstin Abu-abu ukr. 10.20.40 K-250 51,700.00 m
V READYMIX
Readymix beton K-225 tanpa pompa 891,000.00 m3
Readymix beton K-250 tanpa pompa 913,000.00 m3
Readymix beton K-300 tanpa pompa 951,500.00 m3
Readymix beton K-225 tanpa pompa (Minimix) 1,276,000.00 m3
Readymix beton K-250 tanpa pompa (Minimix) 1,320,000.00 m3
Readymix beton K-300 tanpa pompa (Minimix) 1,342,000.00 m3
VI BETON
Buis Beton
Buis Beton Ukuran .1/2 Ø 20 cm tanpa tulangan panjang 1,00 m lokal 99,000.00 btg
Buis Beton Ukuran .1/2 Ø 30 cm tanpa tulangan panjang 1,00 m lokal 111,100.00 btg
Buis Beton Ukuran .Ø 20 cm tanpa tulangan panjang 1,00 m lokal 113,300.00 btg
Buis Beton Ukuran .Ø 30 cm tanpa tulangan panjang 1,00 m lokal 130,900.00 btg
VII CAT
Amplas Kayu 2,783.00 lbr
Ampelas Besi 3,003.00 lbr
Cat besi setara F Talit 58,630.00 kg
Cat tembok Dulux/ICI interior 78,650.00 kg
Cat tembok Dulux/ICI exterior (weathershield) 106,700.00 kg
Cat tembok setara Vinilex 46,646.00 kg
Cat dasar setara Dulux/ICI 74,403.00 kg
Cat lapangan (teknokote) 45,320.00 kg
Meni Besi setara Nippon 48,752.00 kg
Zincromate 5,000.00 m2
Cat Melamik 58,650.00 kg
Cat Pelitur 52,900.00 kg
Dempul plitur 36,556.00 kg
Ijuk 7,000.00 ikat
Kwas 3" 13,200.00 bh
NO. NAMA BAHAN/MATERIAL HPS 2016 SATUAN
1 2 3
Minyak Cat/Tinner 27,087.00 ltr
Pelamir Tembok 27,775.00 kg
Rool cat tembok 34,100.00 bh
Waterproofing ex. Aquaproof 48,977.00 kg
VIII KERAMIK
Keramik Lantai Uk. 20x20 Standar KW 1 (Roman/Mulia) 67,100.00 m2
Keramik Lantai Uk. 25x25 Standar KW 1 (Roman/Mulia) 112,750.00 m2
Keramik Lantai Uk. 30x30 Standar KW 1 (Roman/Mulia) 55,000.00 m2
Keramik Lantai Uk. 40x40 Standar KW 1 (Roman/Mulia) 77,275.00 m2
Keramik Dinding Uk. 20x25 Standar KW 1 (Roman/Mulia) 57,200.00 m2
Keramik Dinding Uk. 20x40 Standar KW 1 (Roman/Mulia) 103,400.00 m2
Keramik Dinding Uk. 25x40 Standar KW 1 (Roman/Mulia) 75,570.00 m2
Keramik Dinding Uk. 30x60 Standar KW 1 (Roman/Mulia) 143,550.00 m2
Homogeniustile Uk. 60x60 (niro granit/essenza) 192,500.00 m2
Granit Uk. 60x60 cm 150,638.00 m2
Granit Uk. 80x80 cm 199,231.00 m2
Stepnosing 10 x 20 22,000.00 bh
IX SANITASI AIR
Closet Jongkok Merk Toto Tipe Standar 286,550.00 bh
Closet duduk Merk Toto Tipe Standar (komplit) 2,200,000.00 bh
Wastafel Merk Toto Tipe Standart (komplit) 1,650,000.00 bh
Urinoir 2,108,480.00 bh
Kitchen Zink 202,400.00 bh
Floor Drain Kuningan 209,550.00 bh
Kran Air TOTO 1/2" 215,600.00 bh
Kran Leher angsa TOTO 1/2" 203,500.00 bh
Sealtape 3,300.00 bh
Lem Pipa PVC 35,750.00 tube
Sealent 17,600.00 tube
Pipa PVC dia. 1/2 inch type AW, tebal 22 mm, panjang 4 m 20,515.00 btg
Pipa PVC dia. 3/4 inch type AW, tebal 26 mm, panjang 4 m 27,324.00 btg
Pipa PVC dia. 1 inch type AW, tebal 32 mm, panjang 4 m 37,598.00 btg
Pipa PVC dia. 2 inch type AW, tebal 60 mm, panjang 4 m 80,080.00 btg
Pipa PVC dia. 3 inch type AW, tebal 89 mm, panjang 4 m 155,375.00 btg
Pipa PVC dia. 4 inch type AW, tebal 114 mm, panjang 4 m 233,112.00 btg
Knee PVC 1/2" 2,942.00 bh
Knee PVC 3/4" 3,410.00 bh
Knee PVC 1" 4,812.00 bh
Knee PVC 2" 15,262.00 bh
Knee PVC 3" 23,237.00 bh
Knee PVC 4" 38,500.00 bh
Jet spray 157,850.00 bh
Shower 303,000.00 bh
Bak Penampung Air / Tower Tanx Cap. 1000 ltr 1,991,550.00 bh
Bak Penampung Air / Tower Tanx Cap. 500 ltr 1,252,130.00 bh
Pembuatan sumur bor 100,000.00 m1
Pompa Air Jetpump 4,072,475.00 bh
NO. NAMA BAHAN/MATERIAL HPS 2016 SATUAN
1 2 3
Bocht LL-D 1" (lokal) 25,100.00 bh
Water moer 60,500.00 bh
Gate Valve dia 1-1/2" 125,000.00 bh
Roofdrain cast iron uk.80 mm 128,700.00 bh
XII LISTRIK
Kabel NYM 3x2.5 mm 7,773.00 m
Kabel NYY 4x35mm2 173,000.00 m
Kabel NYY 4x16mm2 103,000.00 m
Kabel NYY 4x10mm2 68,000.00 m
Kabel NYY 4x2.5 mm2 28,000.00 m
Klem kabel 12,595.00 dus
Pipa AW 1/2" 3,850.00 m
Saklar tunggal 15,862.00 bh
Saklar double 21,076.00 bh
Stop Kontak 17,336.00 bh
Lampu TL 2 x 18 watt, armatur, komplit philips 110,000.00 bh
Lampu TKI 2 x 18 watt, armatur, komplit philips 263,312.00 bh
Down Light Ø4" 66,421.00 bh
Lampu SL 18 watt, komplit philips 44,302.00 bh
Lampu baret kotak 40 w 236,500.00 bh
Lampu Halogen 50 Watt Merk : Philips/osram 500,000.00 bh
Lampu pagar 192,500.00 bh
Lampu taman lengkap (lampu + tiang galvanis) 511,500.00 bh
Fitting lampu 5,500.00 bh
Exhausfan 250,000.00 bh
Penyambungan Daya listrik 1,045.00 VA
Grounding Panel-panel listrik BC 50mm 385,000.00 ls
Box MCB, 150,000.00 unit
Box Panel 40x60 cm 728,200.00 unit
Box Panel 30x40 cm 520,000.00 unit
MCB 6 Ampere 45,000.00 bh
MCB 10 Ampere 65,816.00 bh
MCB 32 Ampere 74,800.00 bh
Penangkal petir 1,000,000.00 ttk
Sparing Kabel (Pipa conduit) 14,663.00 bh
XIII A T A P
Alumunium Foil 1 muka, medium weight (HF 404) 25,300.00 m2
Genteng Zincalume (Bahan) Gelombang Besar t=0.35 132,000.00 m2
Genteng Metal Multi Roof (Stone Chip) t=0.35 253,000.00 m2
Penutup atap Alderon 217,343.00 m2
Karpusan atap Alderon 36,333.00 m1
Nok Metal Multiroof (Stone Chip) 79,803.00 m1
Seng gelombang 180 x 90 x 0,20 69,300.00 lbr
Rangka Atap Baja Ringan (Terpasang) 229,900.00 m2
Listplank GRC l = 15 cm, p = 2.4 m, t=9mm 38,500.00 lbr
Listplank GRC l = 20 cm, p = 2.4 m, t=9mm 51,700.00 lbr
Listplank GRC l = 15 cm, p = 2.4 m, t=12mm 38,500.00 lbr
Listplank GRC l = 30 cm, p = 2.4 m, t=12mm 65,000.00 lbr
Talang PVC 20X20 cm, p=4 m 30,250.00 bh
Roofmesh spasi 75x75X1.3 55,000.00 m2
NO. NAMA BAHAN/MATERIAL HPS 2016 SATUAN
1 2 3
Glass wool 38,500.00 m2
Asbes semen gelombang 56,100.00 lbr
XV SEWA ALAT
Truck pompa beton 2,500,000.00 8 jam
Buldozer 100 - 150 HP 289,000.00 Jam
Compressor 4000-6500 liter/menit 77,000.00 Jam
Concrete Vibrator 24,000.00 Jam
Excavator 80 - 120 HP 253,000.00 Jam
Generator Set 125 KVA 201,000.00 Jam
Jack Hammer 25,000.00 Jam
Stamper 49,000.00 Jam
Concrete Mixer 0,30 - 0,60 m3 42,000.00 Jam
Mesin las 48,000.00 Jam
Mobdemob Alat Pancang Hidraulick 1 unit 15,000,000.00 unit
Scaffolding 50,000.00 set/bulan
Baby walles 21,000.00 Jam
Mesin Trowel 61,875.00 Jam
NO. NAMA BAHAN/MATERIAL HPS 2016 SATUAN
1 2 3
Finish Beton Menggunakan Mesin Trowel 5,500.00 m2
XVI UPAH
Pekerja / knek 92,000.00 hari
Tukang gali 102,000.00 hari
Kepala Tukang Batu 124,000.00 hari
Tukang Batu 102,000.00 hari
Kepala Tukang Kayu 125,000.00 hari
Tukang Kayu 113,000.00 hari
Kepala Tukang Besi 122,000.00 hari
Tukang Besi 113,000.00 hari
Kepala Tukang Cat 124,000.00 hari
Tukang Cat 102,000.00 hari
Mandor / pengawas 141,000.00 hari
Instalator / Tukang Listrik 113,000.00 hari
Pembantu Instalator 102,000.00 hari
Operator alat berat 138,000.00 hari
Pembantu operator alat berat 106,000.00 hari
XVII TAMBAHAN
Tiang pancang uk, 20x20 212,190.00 m
Tiang pancang uk, 25x25 241,816.00 m
Sewa alat pancang hidraulic 66,000.00 m
Sewa alat pancang hammer 36,850.00 m
Mobilisasi alat pancang hidraulic 22,000,000.00 unit
Mobilisasi alat pancang dropp hammer 7,500,000.00 unit
Mobilisasi alat Bored pile 4,950,000.00 unit
- Jasa Pengeboran Bored Pile Ø 30cm / m 206,000.00 m
- Jasa Pengeboran Bored Pile Ø 40cm / m 230,000.00 m
Aluminium Composit Panel (ACP) 0.3 mm uk,122x240 322,000.00 m2
Tiang Bendera 3,300,000.00 m
Penyambungan PDAM 1,650,000.00 m
Huruf Stainles 20 cm 242,000.00 bh
Huruf Stainles 15 cm 165,000.00 bh
Logo Kota Tangerang 1,650,000.00 bh
Rumput Gajah Mini 21,000.00 m2
Net Volley 264,770.00 bh
Jaring Gawang 570,350.00 set
Kepada Yth.
POKJA 1.19 Jasa Konstruksi
Kantor Layanan Pengadaan Barang dan Jasa
Pemerintah Kota Tangerang
Tahun Anggaran 2016
di
TANGERANG
P e r i h a l : Penawaran Pekerjaan :
PEMBANGUNAN GEDUNG SMPN 32 (KECAMATAN CIPONDOH) (TAHUN JAMAK) (PSP-06)
Penawaran ini sudah memperhatikan ketentuan dan persyaratan yang tercantum dalam dokumen
Pengadaan untuk melaksanakan pekerjaan tersebut. Jangka waktu penyelesaian pekerjaan selam
375 (Tiga Ratus Tujuh Puluh Lima) hari kalender sejak SMPK diterima.
Penawaran ini berlaku selama 60 (Enam Puluh) hari kalender sejak batas akhir pemasukan
Dokumen Penawaran, yaitu sesuai Jadwal Lelang.
Dengan disampaikannya Surat Penawaran ini, maka kami menyatakan sanggup dan akan tunduk
pada semua ketentuan yang tercantum dalam Dokumen Pengadaan.
Penawar
P T. DADO DIMENSI
Meterai
Terhutang
TRBILANG = Tiga Belas Milyar Lima Ratus Enam Puluh Tiga Juta Empat Ratus Ribu Rupiah
HARGA JUMLAH
NO URAIAN PEKERJAAN VOL. SAT. SATUAN HARGA
(Rp.) (Rp.)
A. PEKERJAAN PERSIAPAN
1 Papan nama Proyek 1.00 unit 144,000.00 144,000.00
2 Direksi Keet 30.00 m2 389,528.00 11,685,840.00
3 Pagar Pengaman Proyek 240.00 m 114,378.00 27,450,720.00
4 Air dan Listrik Kerja 1.00 ls 20,000,000.00 20,000,000.00
5 Dokumentasi Dan Laporan-Laporan 1.00 ls 15,000,000.00 15,000,000.00
6 Mobilisasi/Demobilisasi 1.00 Ls 30,000,000.00 30,000,000.00
104,280,560.00
DAFTAR KUANTITAS
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
B. BANGUNAN SEKOLAH 1
I PEKERJAAN PEMATANGAN LAHAN
1 Urugan peninggian lantai 95.95 m3 183,050.00 17,563,647.50
2 Pembersihan site 564.40 m2 5,200.00 2,934,880.00
3 Pengukuran dan pasang bouwplank 134.30 m 31,930.00 4,288,199.00
24,786,726.50
II PEKERJAAN PONDASI
A Pekerjaan Pancang Mini Pile
Type P1
1 Pemancangan mini pile Uk 25x25 cm kotak 324.00 m 210,000.00 68,040,000.00
2 Potong kepala tiang pancang 27.00 unit 60,000.00 1,620,000.00
Type P2
3 Pemancangan mini pile Uk 25x25 cm kotak 312.00 m 210,000.00 65,520,000.00
4 Potong kepala tiang pancang 26.00 unit 60,000.00 1,560,000.00
136,740,000.00
B Pekerjaan Pilecap
1 Galian tanah pile cap 142.44 m3 63,000.00 8,973,720.00
2 Buang tanah sekitar lokasi 29.29 m3 20,800.00 609,232.00
3 Urugan tanah sisi pondasi 113.15 m3 183,050.00 20,712,107.50
4 Lantai kerja beton tumbuk 1:3:5; t. 50 mm 1.86 m3 812,920.00 1,512,031.20
5 Pilecap P1
- Cor beton Readymix K- 300 11.70 m3 995,733.00 11,650,076.10
- Begisting Pondasi Kayu klas III 55.08 m2 182,025.00 10,025,937.00
- Tulangan besi U- 40
- dia. D16 mm 2,283.57 kg 11,555.00 26,386,651.35
- dia. D13 mm 88.52 kg 11,555.00 1,022,848.60
6 Pedestal P1 sampai FL 0.00
- Cor beton Readymix K- 300 3.45 m3 995,733.00 3,435,278.85
- Begisting Pondasi Kayu klas III 34.56 m2 182,025.00 6,290,784.00
- Tulangan besi U- 40
- dia. D19mm 1,030.80 kg 11,555.00 11,910,894.00
- Tulangan besi U- 24
- dia. 12 mm 418.69 kg 11,500.00 4,814,935.00
- dia. 12 mm 124.57 kg 11,500.00 1,432,555.00
7 Pilecap P2
- Cor beton Readymix K- 300 10.60 m3 995,733.00 10,554,769.80
- Begisting Pondasi Kayu klas III 38.22 m2 182,025.00 6,956,995.50
- Tulangan besi U- 40
- dia. D16 mm 1,819.03 kg 11,555.00 21,018,891.65
- dia. D13 mm 61.93 kg 11,555.00 715,601.15
8 Pedestal P2 sampai FL 0.00
- Cor beton Readymix K- 300 1.66 m3 995,733.00 1,652,916.78
- Begisting Pondasi Kayu klas III 16.64 m2 182,025.00 3,028,896.00
- Tulangan besi U- 40
- dia. D19 mm 496.31 kg 11,555.00 5,734,862.05
- Tulangan besi U- 24
- dia. 12 mm 201.59 kg 11,500.00 2,318,285.00
- dia. 12 mm 46.65 kg 11,500.00 536,475.00
161,294,743.53
Page 72 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
C Pekerjaan Tie Beam
1 Galian tanah tie beam 118.20 m3 63,000.00 7,446,600.00
2 Buang tanah sekitar lokasi 48.52 m3 20,800.00 1,009,216.00
3 Urugan tanah sisi pondasi 69.67 m3 183,050.00 12,753,093.50
4 Lantai kerja beton tumbuk 1:3:5; t. 50 mm 3.73 m3 812,920.00 3,032,191.60
5 Tie Beam TB1; 30x60
- Cor beton Readymix K- 300 44.79 m3 995,733.00 44,598,881.07
- Begisting Sloof Kayu klas III 298.62 m2 182,025.00 54,356,305.50
- Tulangan besi U- 24
- dia. 10 mm 2,023.68 kg 11,500.00 23,272,320.00
- Tulangan besi U- 40
- dia. D16 mm 7,663.31 kg 11,555.00 88,549,547.05
- dia. D13 mm 603.51 kg 11,555.00 6,973,558.05
241,991,712.77
D Pekerjaan Plat lantai dasar
1 Gelar plastik sheet 564.40 m2 6,560.00 3,702,464.00
2 Gelar wiremesh M6 (1lapis) 564.40 m2 89,801.00 50,683,684.40
3 Cor beton Readymix K-300 45.15 m3 995,733.00 44,957,344.95
99,343,493.35
III PEKERJAAN STRUKTUR
A LANTAI 1
1 Kolom K1
- Cor beton Readymix K- 300 22.40 m3 995,733.00 22,304,419.20
- Begisting Sloof Kayu klas III 224.00 m2 182,025.00 40,773,600.00
- Tulangan besi U- 24
- dia. 12 mm 1,987.90 kg 11,500.00 22,860,850.00
- Tulangan besi U- 40
- dia. D16 mm 4,600.80 kg 11,555.00 53,162,244.00
2 Kolom K2
- Cor beton Readymix K- 300 1.89 m3 995,733.00 1,881,935.37
- Begisting Sloof Kayu klas III 25.20 m2 182,025.00 4,587,030.00
- Tulangan besi U- 24
- dia. 10 mm 120.82 kg 11,500.00 1,389,430.00
- Tulangan besi U- 40
- dia. D16 mm 465.00 kg 11,555.00 5,373,075.00
152,332,583.57
B LANTAI 2
1 Kolom K1
- Cor beton Readymix K- 300 22.40 m3 995,733.00 22,304,419.20
- Begisting Sloof Kayu klas III 224.00 m2 182,025.00 40,773,600.00
- Tulangan besi U- 24
- dia. 12 mm 1,987.90 kg 11,500.00 22,860,850.00
- Tulangan besi U- 40
- dia. D16 mm 4,600.80 kg 11,555.00 53,162,244.00
2 Kolom K2
- Cor beton Readymix K- 300 1.89 m3 995,733.00 1,881,935.37
- Begisting Sloof Kayu klas III 25.20 m2 182,025.00 4,587,030.00
- Tulangan besi U- 24
- dia. 10 mm 120.82 kg 11,500.00 1,389,430.00
- Tulangan besi U- 40
- dia. D16 mm 465.00 kg 11,555.00 5,373,075.00
Page 73 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
3 Balok B1
- Cor beton Readymix K- 300 16.23 m3 995,733.00 16,160,746.59
- Begisting Sloof Kayu klas III 108.19 m2 182,025.00 19,693,284.75
- Tulangan besi U- 24
- dia. 10 mm 141.61 kg 11,500.00 1,628,515.00
- Tulangan besi U- 40
- dia. D16 mm 3,126.00 kg 11,555.00 36,120,930.00
4 Balok B2
- Cor beton Readymix K- 300 17.84 m3 995,733.00 17,763,876.72
- Begisting Sloof Kayu klas III 142.74 m2 182,025.00 25,982,248.50
- Tulangan besi U- 24
- dia. 10 mm 1,502.45 kg 11,500.00 17,278,175.00
- Tulangan besi U- 40
- dia. D16 mm 3,703.52 kg 11,555.00 42,794,173.60
5 Plat lantai t:12cm
- Cor beton Readymix K- 300 65.56 m3 995,733.00 65,280,255.48
- Begisting Sloof Kayu klas III 546.40 m2 182,025.00 99,458,460.00
- Tulangan besi U- 40
- dia. D10 mm 9,334.94 kg 11,500.00 107,351,810.00
6 Sewa Scafolding 546.40 m2 133,600.00 72,999,040.00
674,844,099.21
C LANTAI 3
1 Kolom K1
- Cor beton Readymix K- 300 19.20 m3 995,733.00 19,118,073.60
- Begisting Sloof Kayu klas III 192.00 m2 182,025.00 34,948,800.00
- Tulangan besi U- 24
- dia. 12 mm 1,718.48 kg 11,500.00 19,762,520.00
- Tulangan besi U- 40
- dia. D16 mm 4,060.80 kg 11,555.00 46,922,544.00
2 Kolom K2
- Cor beton Readymix K- 300 1.62 m3 995,733.00 1,613,087.46
- Begisting Sloof Kayu klas III 21.60 m2 182,025.00 3,931,740.00
- Tulangan besi U- 24
- dia. 10 mm 104.16 kg 11,500.00 1,197,840.00
- Tulangan besi U- 40
- dia. D16 mm 408.84 kg 11,555.00 4,724,146.20
3 Balok B1
- Cor beton Readymix K- 300 16.23 m3 995,733.00 16,160,746.59
- Begisting Sloof Kayu klas III 108.19 m2 182,025.00 19,693,284.75
- Tulangan besi U- 24
- dia. 10 mm 141.61 kg 11,500.00 1,628,515.00
- Tulangan besi U- 40
- dia. D16 mm 3,126.00 kg 11,555.00 36,120,930.00
4 Balok B2
- Cor beton Readymix K- 300 17.18 m3 995,733.00 17,106,692.94
- Begisting Sloof Kayu klas III 137.47 m2 182,025.00 25,022,976.75
- Tulangan besi U- 24
- dia. 10 mm 1,447.89 kg 11,500.00 16,650,735.00
- Tulangan besi U- 40
- dia. D16 mm 3,572.12 kg 11,555.00 41,275,846.60
5 Plat lantai t:12cm
- Cor beton Readymix K- 300 65.56 m3 995,733.00 65,280,255.48
- Begisting Sloof Kayu klas III 546.40 m2 182,025.00 99,458,460.00
- Tulangan besi U- 40
- dia. D10 mm 9,334.94 kg 11,500.00 107,351,810.00
6 Sewa Scafolding 546.40 m2 133,600.00 72,999,040.00
650,968,044.37
Page 74 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
D DAK DAN ATAP
1 Balok B1
- Cor beton Readymix K- 300 6.01 m3 995,733.00 5,984,355.33
- Begisting Sloof Kayu klas III 40.08 m2 182,025.00 7,295,562.00
- Tulangan besi U- 24
- dia. 10 mm 42.45 kg 11,500.00 488,175.00
- Tulangan besi U- 40
- dia. D16 mm 954.50 kg 11,555.00 11,029,247.50
2 Balok B2
- Cor beton Readymix K- 300 36.68 m3 995,733.00 36,523,486.44
- Begisting Sloof Kayu klas III 293.40 m2 182,025.00 53,406,135.00
- Tulangan besi U- 24
- dia. 10 mm 2,163.30 kg 11,500.00 24,877,950.00
- Tulangan besi U- 40
- dia. D16 mm 4,440.37 kg 11,555.00 51,308,475.35
3 Plat dak t:12cm
- Cor beton Readymix K- 300 10.74 m3 995,733.00 10,694,172.42
- Begisting Sloof Kayu klas III 89.57 m2 182,025.00 16,303,979.25
- Tulangan besi U- 40
- dia. D10 mm 1,530.25 kg 11,500.00 17,597,875.00
4 Sewa Scafolding 89.57 m2 133,600.00 11,966,552.00
247,475,965.29
E TANGGA
- Cor beton Readymix K300 8.40 m3 995,733.00 8,364,157.20
- Begisting Sloof Kayu klas III 42.00 m2 182,025.00 7,645,050.00
- Tulangan besi U40
- dia. D16 mm 672.00 kg 11,555.00 7,764,960.00
- dia. D13 mm 336.00 kg 11,555.00 3,882,480.00
27,656,647.20
IV PEKERJAAN ARSITEKTUR
A Pekerjaan Dinding
Lantai 1
1 Pemasangan dinding bata ringan 670.45 m2 148,345.00 99,457,905.25
2 Plester aci dinding 1,313.91 m2 52,194.00 68,578,218.54
3 Kolom praktis 0.76 m3 3,740,273.00 2,842,607.48
4 Pasang keramik dinding kamar mandi 27.00 m2 175,459.00 4,737,393.00
Lantai 2
1 Pemasangan dinding bata ringan 710.88 m2 148,345.00 105,455,493.60
2 Plester aci dinding 1,421.76 m2 52,194.00 74,207,341.44
3 Kolom praktis 0.76 m3 3,740,273.00 2,842,607.48
4 Pasang keramik dinding kamar mandi 27.00 m2 175,459.00 4,737,393.00
Lantai 3
1 Pemasangan dinding bata ringan 710.88 m2 148,345.00 105,455,493.60
2 Plester aci dinding 1,421.76 m2 52,194.00 74,207,341.44
3 Kolom praktis 0.76 m3 3,740,273.00 2,842,607.48
4 Pasang keramik dinding kamar mandi 27.00 m2 175,459.00 4,737,393.00
550,101,795.31
B Pekerjaan Lantai
Lantai 1
1 Keramik lantai uk 40x40 unpolish 300.97 m2 130,026.00 39,133,925.22
2 Keramik lantai uk 40x40 polish 269.87 m2 130,026.00 35,090,116.62
3 Keramik lantai uk 30x30 unpolish 102.68 m2 130,026.00 13,351,069.68
4 Keramik lantai tangga uk 40x40 unpolish 25.11 m2 130,026.00 3,264,952.86
5 Step nosing 55.20 m' 113,922.00 6,288,494.40
6 Pasang plint keramik 497.67 m 58,460.00 29,093,788.20
7 Rabat Keliling Bangunan 130.00 m2 52,333.00 6,803,290.00
Lantai 2
1 Keramik lantai uk 40x40 unpolish 218.07 m2 130,026.00 28,354,769.82
2 Keramik lantai uk 40x40 polish 269.87 m2 130,026.00 35,090,116.62
3 Keramik lantai tangga uk 40x40 unpolish 16.56 m3 130,026.00 2,153,230.56
4 Pasang plint keramik 497.67 m 58,460.00 29,093,788.20
Lantai 3
1 Keramik lantai uk 40x40 unpolish 218.07 m2 130,026.00 28,354,769.82
2 Keramik lantai uk 40x40 polish 269.87 m2 130,026.00 35,090,116.62
3 Keramik lantai tangga uk 40x40 unpolish 16.56 m3 130,026.00 2,153,230.56
4 Pasang plint keramik 497.67 m 58,460.00 29,093,788.20
322,409,447.38
Page 75 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
C Pasangan plafon
Lantai 1
1 Pemasangan plafond gypsum 9mm rangka hollow 228.00 m2 130,085.00 29,659,380.00
2 Pemasangan plafond GRC 6mm rangka hollow 31.00 m2 129,707.00 4,020,917.00
3 Pemasangan plafond Gyptile rangka cross tee main tee 315.00 m2 145,000.00 45,675,000.00
4 List Plafon Kayu 30.00 m 33,725.00 1,011,750.00
5 List Plafon Gypsum 248.83 m 19,760.00 4,916,946.67
Lantai 2
1 Pemasangan plafond gypsum 9mm rangka hollow 228.00 m2 130,085.00 29,659,380.00
2 Pemasangan plafond GRC 6mm rangka hollow 31.00 m2 129,707.00 4,020,917.00
3 Pemasangan plafond Gyptile rangka cross tee main tee 315.00 m2 145,000.00 45,675,000.00
4 List Plafon Kayu 30.00 m 33,725.00 1,011,750.00
5 List Plafon Gypsum 248.83 m 19,760.00 4,916,946.67
Lantai 3
1 Pemasangan plafond gypsum 9mm rangka hollow 228.00 m2 130,085.00 29,659,380.00
2 Pemasangan plafond GRC 6mm rangka hollow 161.00 m2 129,707.00 20,882,827.00
3 Pemasangan plafond Gyptile rangka cross tee main tee 315.00 m2 145,000.00 45,675,000.00
4 List Plafon Kayu 30.00 m 33,725.00 1,011,750.00
5 List Plafon Gypsum 248.83 m 19,760.00 4,916,946.67
272,713,891.00
D Pengecatan dinding
Lantai 1
1 Pengecatan dinding luar 526.67 m2 61,025.00 32,140,036.75
2 Pengecatan dinding dalam 718.98 m2 60,045.00 43,171,154.10
3 Pengecatan plafond 259.00 m2 60,160.00 15,581,440.00
Lantai 2
1 Pengecatan dinding luar 567.10 m2 61,025.00 34,607,277.50
2 Pengecatan dinding dalam 854.66 m2 60,045.00 51,318,059.70
3 Pengecatan plafond 259.00 m2 60,160.00 15,581,440.00
Lantai 3
1 Pengecatan dinding luar 567.10 m2 61,025.00 34,607,277.50
2 Pengecatan dinding dalam 854.66 m2 60,045.00 51,318,059.70
3 Pengecatan plafond 389.00 m2 60,160.00 23,402,240.00
301,726,985.25
E Sanitary
Lantai 1,2,3
1 Closet duduk 15.00 unit 2,560,950.00 38,414,250.00
2 Urinoir 6.00 unit 2,265,700.00 13,594,200.00
3 Wastafel 12.00 unit 68,100.00 817,200.00
4 Skat urinoir 3.00 unit 967,120.00 2,901,360.00
5 Jet washer 15.00 unit 24,000.00 360,000.00
6 Kran dinding 15.00 unit 202,962.00 3,044,430.00
7 Tempat tisu 15.00 unit 300,000.00 4,500,000.00
8 Floor drain 18.00 unit 120,400.00 2,167,200.00
9 Cleaning out 12.00 unit 220,700.00 2,648,400.00
68,447,040.00
F Pintu dan jendela
Lantai 1
1 Pintu P1 5.00 unit 5,972,882.00 29,864,410.00
2 Pintu P4 Pintu Toilet 7.00 unit 667,800.00 4,674,600.00
3 Pintu P6 2.00 unit 3,077,940.00 6,155,880.00
4 Jendela J1 10.00 unit 2,403,465.00 24,034,650.00
5 Jendela J2 15.00 unit 4,610,755.00 69,161,325.00
Lantai 2
1 Pintu P1 5.00 unit 5,972,882.00 29,864,410.00
2 Pintu P4 Pintu Toilet 7.00 unit 667,800.00 4,674,600.00
3 Pintu P6 2.00 unit 3,077,940.00 6,155,880.00
4 Jendela J1 10.00 unit 2,403,465.00 24,034,650.00
5 Jendela J2 15.00 unit 4,610,755.00 69,161,325.00
Lantai 3
1 Pintu P1 5.00 unit 5,972,882.00 29,864,410.00
2 Pintu P4 Pintu Toilet 7.00 unit 667,800.00 4,674,600.00
3 Pintu P6 2.00 unit 3,077,940.00 6,155,880.00
4 Jendela J1 10.00 unit 2,403,465.00 24,034,650.00
5 Jendela J2 15.00 unit 4,610,755.00 69,161,325.00
401,672,595.00
Page 76 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
G Lain -lain
1 Lantai 1
Railling tangga besi pipa 2" dan hollow 40x40mm+15x40mm 31.70 m' 184,000.00 5,832,800.00
2 Lantai 2
Railling tangga besi pipa 2" dan hollow 40x40mm+15x40mm 31.70 m' 184,000.00 5,832,800.00
11,665,600.00
H Rangka dan Penutup Atap
Rangka atap baja ringan 476.25 m2 210,000.00 100,012,500.00
Penutup atap (Zincalume warna t:0,35mm + Roofmesh + alumunium foil 2 sisi 476.25 m2 248,464.00 118,330,980.00
Water proofing membran 3mm 64.21 m2 58,675.00 3,767,521.75
222,111,001.75
V PEKERJAAN MEKANIKAL
Pengadaan dan pemasangan instalasi pipa air bersih lengkap dengan fitting,
klem, support, hanger, assesoris, bobokan dan perapihannya kembali, PPR,
PN-10 : Ø 2"
A PEKERJAAN INSTALASI PLAMBING (INSTALASI AIR BERSIH)
LANTAI 1
1 Ø 1,5" 16.00 m 60,900.00 974,400.00
2 Ø 1" 24.00 m 56,200.00 1,348,800.00
3 Ø 3/4" 32.00 m 50,200.00 1,606,400.00
4 Ø 1/2" 40.00 m 49,400.00 1,976,000.00
5 Pompa air jet pump + Instalasi dan pengeboran 1.00 ls 9,747,000.00 9,747,000.00
LANTAI 2
1 Ø 1,5" 16.00 m 60,900.00 974,400.00
2 Ø 1" 24.00 m 56,200.00 1,348,800.00
3 Ø 3/4" 32.00 m 50,200.00 1,606,400.00
4 Ø 1/2" 40.00 m 49,400.00 1,976,000.00
LANTAI 3
1 Ø 1,5" 16.00 m 60,900.00 974,400.00
2 Ø 1" 24.00 m 56,200.00 1,348,800.00
3 Ø 3/4" 32.00 m 50,200.00 1,606,400.00
4 Ø 1/2" 40.00 m 49,400.00 1,976,000.00
5 Torn Air Kapasitas 1 m3 1.00 bh 1,933,500.00 1,933,500.00
6 WLC (Water Level Control) 1.00 bh 750,000.00 750,000.00
30,147,300.00
B INSTALASI AIR LIMBAH/AIR BUANGAN (AIR KOTOR DAN AIR KOTORAN)
LANTAI 1
1. Instalasi pipa air kotor
Ø 6" 8.00 m 120,090.00 960,720.00
Ø 4" 8.00 m 107,500.00 860,000.00
Ø 3" 16.00 m 85,200.00 1,363,200.00
Ø 2" 16.00 m 69,900.00 1,118,400.00
b. Instalasi pipa ventilasi
Ø 2" 16.00 m 69,900.00 1,118,400.00
Bioceramic Fiber Type C ukuran 65x30x55 berat 65kg Kapasitas 50 orang +
2 1.00 unit 3,250,000.00 3,250,000.00
Sumur Resapan
LANTAI 2
3 Instalasi pipa air kotor
Ø 6" 8.00 m 120,090.00 960,720.00
Ø 4" 8.00 m 107,500.00 860,000.00
Ø 3" 16.00 m 85,200.00 1,363,200.00
Ø 2" 16.00 m 69,900.00 1,118,400.00
4 Instalasi pipa ventilasi
Ø 2" 16.00 m 69,900.00 1,118,400.00
LANTAI 3
5 Instalasi pipa air kotor
Ø 6" 8.00 m 120,090.00 960,720.00
Ø 4" 8.00 m 107,500.00 860,000.00
Ø 3" 16.00 m 85,200.00 1,363,200.00
Ø 2" 16.00 m 69,900.00 1,118,400.00
6 Instalasi pipa ventilasi
Ø 2" 16.00 m 69,900.00 1,118,400.00
19,512,160.00
Page 77 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
C INSTALASI AIR HUJAN
1 Ø 6" 12.00 m 120,090.00 1,441,080.00
2 Ø 4" 12.00 m 107,500.00 1,290,000.00
3 Pengadaan dan pemasangan Roof Drain (RD), Ø 4" 2.00 unit 560,400.00 1,120,800.00
3,851,880.00
VI PEKERJAAN ELEKTRIKAL
A PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK BANG. KEDATANGAN
LANTAI 1
1 Lampu TKI 2 x 18 watt bahan komplit 30.00 bh 273,238.00 8,197,140.00
2 Lampu PLC 18 Watt 16.00 bh 224,238.00 3,587,808.00
3 Stop Kontak type inbow 10A, 220V, 1P 10.00 bh 83,100.00 831,000.00
4 Saklar Ganda 10A, Type Inbow 9.00 bh 77,100.00 693,900.00
5 Saklar Tunggal 10A, Type Inbow 2.00 bh 77,100.00 154,200.00
6 Instalasi Penerangan kabel NYA 3X(1X2.5 mm2) PVC conduit high impack 2 46.00 ttk 124,335.00 5,719,410.00
7 Instalasi Stop kontak kabel NYA 3X(1X2.5 mm2) PVC conduit high impack 2 10.00 ttk 124,335.00 1,243,350.00
LANTAI 2
1 Lampu TKI 2 x 18 watt bahan komplit 30.00 bh 273,238.00 8,197,140.00
2 Lampu PLC 18 Watt 16.00 bh 224,238.00 3,587,808.00
3 Stop Kontak type inbow 10A, 220V, 1P 10.00 bh 83,100.00 831,000.00
4 Saklar Ganda 10A, Type Inbow 9.00 bh 77,100.00 693,900.00
5 Saklar Tunggal 10A, Type Inbow 2.00 bh 77,100.00 154,200.00
6 Instalasi Penerangan kabel NYA 3X(1X2.5 mm2) PVC conduit high impack 2 46.00 ttk 124,335.00 5,719,410.00
7 Instalasi Stop kontak kabel NYA 3X(1X2.5 mm2) PVC conduit high impack 2 10.00 ttk 124,335.00 1,243,350.00
LANTAI 3
1 Lampu TKI 2 x 18 watt bahan komplit 30.00 bh 273,238.00 8,197,140.00
2 Lampu PLC 18 Watt 16.00 bh 224,238.00 3,587,808.00
3 Stop Kontak type inbow 10A, 220V, 1P 10.00 bh 83,100.00 831,000.00
4 Saklar Ganda 10A, Type Inbow 9.00 bh 77,100.00 693,900.00
5 Saklar Tunggal 10A, Type Inbow 2.00 bh 77,100.00 154,200.00
6 Instalasi Penerangan kabel NYA 3X(1X2.5 mm2) PVC conduit high impack 2 46.00 ttk 124,335.00 5,719,410.00
7 Instalasi Stop kontak kabel NYA 3X(1X2.5 mm2) PVC conduit high impack 2 10.00 ttk 124,335.00 1,243,350.00
8 Penangkal Petir (lengkap aksesoris grounding dan bak kontrol terpasang) 3.00 ttk 1,750,000.00 5,250,000.00
66,530,424.00
B PEKERJAAN KABEL FEEDER
LANTAI 1, 2 DAN 3
1 Dari SDP 1 ke LP/PP-A
NYY 4X6mm2 + NYA 1X4mm2 4.00 m 105,000.00 420,000.00
2 Dari SDP 2 ke LP/PP-B
NYY 4X10mm2 + NYA 1X6mm2 8.00 m 165,000.00 1,320,000.00
3 Dari SDP 3 ke LP/PP-C
NYY 4X10mm2 + NYA 1X6mm2 12.00 m 165,000.00 1,980,000.00
3 Dari SDP 1 ke PP-POMPA TRANSFER
NYY 4X25mm2 12.00 m 215,000.00 2,580,000.00
4 Dari SDP 1 ke PP-POMPA BOSTER
NYY 3X6mm2 12.00 m 95,000.00 1,140,000.00
5 Dari SDP 1 ke SDP 2
NYY 4X35mm2 4.00 m 238,000.00 952,000.00
6 Dari SDP 2 ke SDP 3
NYY 4X35mm2 4.00 m 238,000.00 952,000.00
9,344,000.00
C PEKERJAAN PANEL LISTRIK
LANTAI 1, 2 DAN 3
1 SDP 1 1.00 unit 5,500,000.00 5,500,000.00
2 SDP 2 1.00 unit 5,500,000.00 5,500,000.00
3 SDP 3 1.00 unit 5,500,000.00 5,500,000.00
4 LP/PP-A 1.00 unit 7,500,000.00 7,500,000.00
5 LP/PP-B 1.00 unit 7,500,000.00 7,500,000.00
6 LP/PP-c 1.00 unit 7,500,000.00 7,500,000.00
7 PP-POMPA TRANSFER 1.00 unit 4,500,000.00 4,500,000.00
8 PP-POMPA BOSTER 1.00 unit 4,500,000.00 4,500,000.00
9 Test Commisioning 1.00 ls 500,000.00 500,000.00
48,500,000.00
Page 78 of 144
DAFTAR KUANTITAS
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
C. BANGUNAN SEKOLAH 2
I. PEKERJAAN PEMATANGAN LAHAN
1 Urugan peninggian lantai 95.95 m3 183,050.00 17,563,647.50
2 Pembersihan site 564.40 m2 5,200.00 2,934,880.00
3 Pengukuran dan pasang bouwplank 134.30 m 31,930.00 4,288,199.00
24,786,726.50
II. PEKERJAAN PONDASI
A Pekerjaan Pancang Mini Pile
Type P1
1 Pemancangan mini pile Uk 25x25 cm kotak 324.00 m 210,000.00 68,040,000.00
2 Potong kepala tiang pancang 27.00 unit 60,000.00 1,620,000.00
Type P2
3 Pemancangan mini pile Uk 25x25 cm kotak 312.00 m 210,000.00 65,520,000.00
4 Potong kepala tiang pancang 26.00 unit 60,000.00 1,560,000.00
136,740,000.00
B Pekerjaan Pilecap
1 Galian tanah pile cap 142.44 m3 63,000.00 8,973,720.00
2 Buang tanah sekitar lokasi 29.29 m3 20,800.00 609,232.00
3 Urugan tanah sisi pondasi 113.15 m3 183,050.00 20,712,107.50
4 Lantai kerja beton tumbuk 1:3:5; t. 50 mm 1.86 m3 812,920.00 1,512,031.20
5 Pilecap P1
- Cor beton Readymix K- 300 11.70 m3 995,733.00 11,650,076.10
- Begisting Pondasi Kayu klas III 55.08 m2 182,025.00 10,025,937.00
- Tulangan besi U- 40
- dia. D16 mm 2,283.57 kg 11,555.00 26,386,651.35
- dia. D13 mm 88.52 kg 11,555.00 1,022,848.60
6 Pedestal P1 sampai FL 0.00
- Cor beton Readymix K- 300 3.45 m3 995,733.00 3,435,278.85
- Begisting Pondasi Kayu klas III 34.56 m2 182,025.00 6,290,784.00
- Tulangan besi U- 40
- dia. D19mm 1,030.80 kg 11,555.00 11,910,894.00
- Tulangan besi U- 24
- dia. 12 mm 418.69 kg 11,500.00 4,814,935.00
- dia. 12 mm 124.57 kg 11,500.00 1,432,555.00
7 Pilecap P2
- Cor beton Readymix K- 300 10.60 m3 995,733.00 10,554,769.80
- Begisting Pondasi Kayu klas III 38.22 m2 182,025.00 6,956,995.50
- Tulangan besi U- 40
- dia. D16 mm 1,819.03 kg 11,555.00 21,018,891.65
- dia. D13 mm 61.93 kg 11,555.00 715,601.15
8 Pedestal P2 sampai FL 0.00
- Cor beton Readymix K- 300 1.66 m3 995,733.00 1,652,916.78
- Begisting Pondasi Kayu klas III 16.64 m2 182,025.00 3,028,896.00
- Tulangan besi U- 40
- dia. D19 mm 496.31 kg 11,555.00 5,734,862.05
- Tulangan besi U- 24
- dia. 12 mm 201.59 kg 11,500.00 2,318,285.00
- dia. 12 mm 46.65 kg 11,500.00 536,475.00
161,294,743.53
Page 79 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
C Pekerjaan Tie Beam
1 Galian tanah tie beam 118.20 m3 63,000.00 7,446,600.00
2 Buang tanah sekitar lokasi 48.52 m3 20,800.00 1,009,216.00
3 Urugan tanah sisi pondasi 69.67 m3 183,050.00 12,753,093.50
4 Lantai kerja beton tumbuk 1:3:5; t. 50 mm 3.73 m3 812,920.00 3,032,191.60
5 Tie Beam TB1; 30x60
- Cor beton Readymix K- 300 44.79 m3 995,733.00 44,598,881.07
- Begisting Sloof Kayu klas III 298.62 m2 182,025.00 54,356,305.50
- Tulangan besi U- 24
- dia. 10 mm 2,023.68 kg 11,500.00 23,272,320.00
- Tulangan besi U- 40
- dia. D16 mm 7,663.31 kg 11,555.00 88,549,547.05
- dia. D13 mm 603.51 kg 11,555.00 6,973,558.05
241,991,712.77
D Pekerjaan Plat lantai dasar
1 Gelar plastik sheet 564.40 m2 6,560.00 3,702,464.00
2 Gelar wiremesh M6 (1lapis) 564.40 m2 89,801.00 50,683,684.40
3 Cor beton Readymix K-300 45.15 m3 995,733.00 44,957,344.95
99,343,493.35
III. PEKERJAAN STRUKTUR
A LANTAI 1
1 Kolom K1
- Cor beton Readymix K- 300 22.40 m3 995,733.00 22,304,419.20
- Begisting Sloof Kayu klas III 224.00 m2 182,025.00 40,773,600.00
- Tulangan besi U- 24
- dia. 12 mm 1,987.90 kg 11,500.00 22,860,850.00
- Tulangan besi U- 40
- dia. D16 mm 4,600.80 kg 11,555.00 53,162,244.00
2 Kolom K2
- Cor beton Readymix K- 300 1.89 m3 995,733.00 1,881,935.37
- Begisting Sloof Kayu klas III 25.20 m2 182,025.00 4,587,030.00
- Tulangan besi U- 24
- dia. 10 mm 120.82 kg 11,500.00 1,389,430.00
- Tulangan besi U- 40
- dia. D16 mm 465.00 kg 11,555.00 5,373,075.00
152,332,583.57
B LANTAI 2
1 Kolom K1
- Cor beton Readymix K- 300 22.40 m3 995,733.00 22,304,419.20
- Begisting Sloof Kayu klas III 224.00 m2 182,025.00 40,773,600.00
- Tulangan besi U- 24
- dia. 12 mm 1,987.90 kg 11,500.00 22,860,850.00
- Tulangan besi U- 40
- dia. D16 mm 4,600.80 kg 11,555.00 53,162,244.00
2 Kolom K2
- Cor beton Readymix K- 300 1.89 m3 995,733.00 1,881,935.37
- Begisting Sloof Kayu klas III 25.20 m2 182,025.00 4,587,030.00
- Tulangan besi U- 24
- dia. 10 mm 120.82 kg 11,500.00 1,389,430.00
- Tulangan besi U- 40
- dia. D16 mm 465.00 kg 11,555.00 5,373,075.00
3 Balok B1
- Cor beton Readymix K- 300 16.23 m3 995,733.00 16,160,746.59
- Begisting Sloof Kayu klas III 108.19 m2 182,025.00 19,693,284.75
- Tulangan besi U- 24
- dia. 10 mm 141.61 kg 11,500.00 1,628,515.00
- Tulangan besi U- 40
- dia. D16 mm 3,126.00 kg 11,555.00 36,120,930.00
Page 80 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
4 Balok B2
- Cor beton Readymix K- 300 17.84 m3 995,733.00 17,763,876.72
- Begisting Sloof Kayu klas III 142.74 m2 182,025.00 25,982,248.50
- Tulangan besi U- 24
- dia. 10 mm 1,502.45 kg 11,500.00 17,278,175.00
- Tulangan besi U- 40
- dia. D16 mm 3,703.52 kg 11,555.00 42,794,173.60
5 Plat lantai t:12cm
- Cor beton Readymix K- 300 65.56 m3 995,733.00 65,280,255.48
- Begisting Sloof Kayu klas III 546.40 m2 182,025.00 99,458,460.00
- Tulangan besi U- 40
- dia. D10 mm 9,334.94 kg 11,500.00 107,351,810.00
6 Sewa Scafolding 546.40 m2 133,600.00 72,999,040.00
674,844,099.21
C LANTAI 3
1 Kolom K1
- Cor beton Readymix K- 300 19.20 m3 995,733.00 19,118,073.60
- Begisting Sloof Kayu klas III 192.00 m2 182,025.00 34,948,800.00
- Tulangan besi U- 24
- dia. 12 mm 1,718.48 kg 11,500.00 19,762,520.00
- Tulangan besi U- 40
- dia. D16 mm 4,060.80 kg 11,555.00 46,922,544.00
2 Kolom K2
- Cor beton Readymix K- 300 1.62 m3 995,733.00 1,613,087.46
- Begisting Sloof Kayu klas III 21.60 m2 182,025.00 3,931,740.00
- Tulangan besi U- 24
- dia. 10 mm 104.16 kg 11,500.00 1,197,840.00
- Tulangan besi U- 40
- dia. D16 mm 408.84 kg 11,555.00 4,724,146.20
3 Balok B1
- Cor beton Readymix K- 300 16.23 m3 995,733.00 16,160,746.59
- Begisting Sloof Kayu klas III 108.19 m2 182,025.00 19,693,284.75
- Tulangan besi U- 24
- dia. 10 mm 141.61 kg 11,500.00 1,628,515.00
- Tulangan besi U- 40
- dia. D16 mm 3,126.00 kg 11,555.00 36,120,930.00
4 Balok B2
- Cor beton Readymix K- 300 17.18 m3 995,733.00 17,106,692.94
- Begisting Sloof Kayu klas III 137.47 m2 182,025.00 25,022,976.75
- Tulangan besi U- 24
- dia. 10 mm 1,447.89 kg 11,500.00 16,650,735.00
- Tulangan besi U- 40
- dia. D16 mm 3,572.12 kg 11,555.00 41,275,846.60
5 Plat lantai t:12cm
- Cor beton Readymix K- 300 65.56 m3 995,733.00 65,280,255.48
- Begisting Sloof Kayu klas III 546.40 m2 182,025.00 99,458,460.00
- Tulangan besi U- 40
- dia. D10 mm 9,334.94 kg 11,500.00 107,351,810.00
6 Sewa Scafolding 546.40 m2 133,600.00 72,999,040.00
650,968,044.37
Page 81 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
D DAK DAN ATAP
1 Balok B1
- Cor beton Readymix K- 300 6.01 m3 995,733.00 5,984,355.33
- Begisting Sloof Kayu klas III 40.08 m2 182,025.00 7,295,562.00
- Tulangan besi U- 24
- dia. 10 mm 42.45 kg 11,500.00 488,175.00
- Tulangan besi U- 40
- dia. D16 mm 954.50 kg 11,555.00 11,029,247.50
2 Balok B2
- Cor beton Readymix K- 300 36.68 m3 995,733.00 36,523,486.44
- Begisting Sloof Kayu klas III 293.40 m2 182,025.00 53,406,135.00
- Tulangan besi U- 24
- dia. 10 mm 2,163.30 kg 11,500.00 24,877,950.00
- Tulangan besi U- 40
- dia. D16 mm 4,440.37 kg 11,555.00 51,308,475.35
3 Plat dak t:12cm
- Cor beton Readymix K- 300 10.74 m3 995,733.00 10,694,172.42
- Begisting Sloof Kayu klas III 89.57 m2 182,025.00 16,303,979.25
- Tulangan besi U- 40
- dia. D10 mm 1,530.25 kg 11,500.00 17,597,875.00
6 Sewa Scafolding 89.57 m2 133,600.00 11,966,552.00
247,475,965.29
E TANGGA
- Cor beton Readymix K300 8.40 m3 995,733.00 8,364,157.20
- Begisting Sloof Kayu klas III 42.00 m2 182,025.00 7,645,050.00
- Tulangan besi U40
- dia. D16 mm 672.00 kg 11,555.00 7,764,960.00
- dia. D13 mm 336.00 kg 11,555.00 3,882,480.00
27,656,647.20
IV. PEKERJAAN ARSITEKTUR
A Pekerjaan Dinding
Lantai 1
1 Pemasangan dinding bata ringan 670.45 m2 148,345.00 99,457,905.25
2 Plester aci dinding 1,313.91 m2 52,194.00 68,578,218.54
3 Kolom praktis 0.76 m3 3,740,273.00 2,842,607.48
4 Pasang keramik dinding kamar mandi 27.00 m2 175,459.00 4,737,393.00
Lantai 2
1 Pemasangan dinding bata ringan 710.88 m2 148,345.00 105,455,493.60
2 Plester aci dinding 1,421.76 m2 52,194.00 74,207,341.44
3 Kolom praktis 0.76 m3 3,740,273.00 2,842,607.48
4 Pasang keramik dinding kamar mandi 27.00 m2 175,459.00 4,737,393.00
Lantai 3
1 Pemasangan dinding bata ringan 710.88 m2 148,345.00 105,455,493.60
2 Plester aci dinding 1,421.76 m2 52,194.00 74,207,341.44
3 Kolom praktis 0.76 m3 3,740,273.00 2,842,607.48
4 Pasang keramik dinding kamar mandi 27.00 m2 175,459.00 4,737,393.00
550,101,795.31
B Pekerjaan Lantai
Lantai 1
1 Keramik lantai uk 40x40 unpolish 300.97 m2 130,026.00 39,133,925.22
2 Keramik lantai uk 40x40 polish 269.87 m2 130,026.00 35,090,116.62
3 Keramik lantai uk 30x30 unpolish 102.68 m2 130,026.00 13,351,069.68
4 Keramik lantai tangga uk 40x40 unpolish 25.11 m2 130,026.00 3,264,952.86
5 Step nosing 55.20 m' 113,922.00 6,288,494.40
6 Pasang plint keramik 497.67 m 58,460.00 29,093,788.20
7 Rabat Keliling Bangunan 130.00 m2 52,333.00 6,803,290.00
Lantai 2
1 Keramik lantai uk 40x40 unpolish 218.07 m2 130,026.00 28,354,769.82
2 Keramik lantai uk 40x40 polish 269.87 m2 130,026.00 35,090,116.62
3 Keramik lantai tangga uk 40x40 unpolish 16.56 m3 130,026.00 2,153,230.56
4 Pasang plint keramik 497.67 m 58,460.00 29,093,788.20
Lantai 3
1 Keramik lantai uk 40x40 unpolish 218.07 m2 130,026.00 28,354,769.82
2 Keramik lantai uk 40x40 polish 269.87 m2 130,026.00 35,090,116.62
Page 82 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
3 Keramik lantai tangga uk 40x40 unpolish 16.56 m3 130,026.00 2,153,230.56
4 Pasang plint keramik 497.67 m 58,460.00 29,093,788.20
322,409,447.38
Page 83 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
C Pasangan plafon
Lantai 1
1 Pemasangan plafond gypsum 9mm rangka hollow 228.00 m2 130,085.00 29,659,380.00
2 Pemasangan plafond GRC 6mm rangka hollow 31.00 m2 129,707.00 4,020,917.00
3 Pemasangan plafond Gyptile rangka cross tee main tee 315.00 m2 145,000.00 45,675,000.00
4 List Plafon Kayu 30.00 m 33,725.00 1,011,750.00
5 List Plafon Gypsum 248.83 m 19,760.00 4,916,946.67
Lantai 2
1 Pemasangan plafond gypsum 9mm rangka hollow 228.00 m2 130,085.00 29,659,380.00
2 Pemasangan plafond GRC 6mm rangka hollow 31.00 m2 129,707.00 4,020,917.00
3 Pemasangan plafond Gyptile rangka cross tee main tee 315.00 m2 145,000.00 45,675,000.00
4 List Plafon Kayu 30.00 m 33,725.00 1,011,750.00
5 List Plafon Gypsum 248.83 m 19,760.00 4,916,946.67
Lantai 3
1 Pemasangan plafond gypsum 9mm rangka hollow 228.00 m2 130,085.00 29,659,380.00
2 Pemasangan plafond GRC 6mm rangka hollow 161.00 m2 129,707.00 20,882,827.00
3 Pemasangan plafond Gyptile rangka cross tee main tee 315.00 m2 145,000.00 45,675,000.00
4 List Plafon Kayu 30.00 m 33,725.00 1,011,750.00
5 List Plafon Gypsum 248.83 m 19,760.00 4,916,946.67
272,713,891.00
D Pengecatan dinding
Lantai 1
1 Pengecatan dinding luar 526.67 m2 61,025.00 32,140,036.75
2 Pengecatan dinding dalam 718.98 m2 60,045.00 43,171,154.10
3 Pengecatan plafond 259.00 m2 60,160.00 15,581,440.00
Lantai 2
1 Pengecatan dinding luar 567.10 m2 61,025.00 34,607,277.50
2 Pengecatan dinding dalam 854.66 m2 60,045.00 51,318,059.70
3 Pengecatan plafond 259.00 m2 60,160.00 15,581,440.00
Lantai 3
1 Pengecatan dinding luar 567.10 m2 61,025.00 34,607,277.50
2 Pengecatan dinding dalam 854.66 m2 60,045.00 51,318,059.70
3 Pengecatan plafond 389.00 m2 60,160.00 23,402,240.00
301,726,985.25
E Sanitary
Lantai 1,2,3
1 Closet duduk 15.00 unit 2,560,950.00 38,414,250.00
2 Urinoir 6.00 unit 2,265,700.00 13,594,200.00
3 Wastafel 12.00 unit 68,100.00 817,200.00
4 Skat urinoir 3.00 unit 967,120.00 2,901,360.00
5 Jet washer 15.00 unit 24,000.00 360,000.00
6 Kran dinding 15.00 unit 202,962.00 3,044,430.00
7 Tempat tisu 15.00 unit 300,000.00 4,500,000.00
8 Floor drain 18.00 unit 120,400.00 2,167,200.00
9 Cleaning out 12.00 unit 155,000.00 1,860,000.00
67,658,640.00
F Pintu dan jendela
Lantai 1
1 Pintu P1 5.00 unit 5,972,882.00 29,864,410.00
2 Pintu P4 Pintu Toilet 7.00 unit 667,800.00 4,674,600.00
3 Pintu P6 2.00 unit 3,077,940.00 6,155,880.00
4 Jendela J1 10.00 unit 2,403,465.00 24,034,650.00
5 Jendela J2 15.00 unit 4,610,755.00 69,161,325.00
Lantai 2
1 Pintu P1 5.00 unit 5,972,882.00 29,864,410.00
2 Pintu P4 Pintu Toilet 7.00 unit 667,800.00 4,674,600.00
3 Pintu P6 2.00 unit 3,077,940.00 6,155,880.00
4 Jendela J1 10.00 unit 2,403,465.00 24,034,650.00
5 Jendela J2 15.00 unit 4,610,755.00 69,161,325.00
Lantai 3
1 Pintu P1 5.00 unit 5,972,882.00 29,864,410.00
2 Pintu P4 Pintu Toilet 7.00 unit 667,800.00 4,674,600.00
3 Pintu P6 2.00 unit 3,077,940.00 6,155,880.00
4 Jendela J1 10.00 unit 2,403,465.00 24,034,650.00
Page 84 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
5 Jendela J2 15.00 unit 4,610,755.00 69,161,325.00
401,672,595.00
Page 85 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
G Lain -lain
1 Lantai 1
Railling tangga besi pipa 2" dan hollow 40x40mm+15x40mm 31.70 m' 321,235.00 10,183,149.50
2 Lantai 2
Railling tangga besi pipa 2" dan hollow 40x40mm+15x40mm 31.70 m' 321,235.00 10,183,149.50
20,366,299.00
H Rangka dan Penutup Atap
Rangka atap baja ringan 476.25 m2 210,000.00 100,012,500.00
Penutup atap (Zincalume warna t:0,35mm + Roofmesh + alumunium foil 2 si 476.25 m2 248,464.00 118,330,980.00
Water proofing membran 3mm 64.21 m2 58,675.00 3,767,521.75
222,111,001.75
V. PEKERJAAN MEKANIKAL
Pengadaan dan pemasangan instalasi pipa air bersih lengkap dengan
fitting, klem, support, hanger, assesoris, bobokan dan perapihannya
kembali, PPR, PN-10 : Ø 2"
Page 86 of 144
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
C INSTALASI AIR HUJAN
1 Ø 6" 12.00 m 120,090.00 1,441,080.00
2 Ø 4" 12.00 m 107,500.00 1,290,000.00
3 Pengadaan dan pemasangan Roof Drain (RD), Ø 4" 2.00 unit 560,400.00 1,120,800.00
3,851,880.00
VI. PEKERJAAN ELEKTRIKAL
A PEKERJAAN INSTALASI PENERANGAN & STOP KONTAK BANG. KEDATANGAN
LANTAI 1
1 Lampu TKI 2 x 18 watt bahan komplit 30.00 bh 273,238.00 8,197,140.00
2 Lampu PLC 18 Watt 16.00 bh 224,238.00 3,587,808.00
3 Stop Kontak type inbow 10A, 220V, 1P 10.00 bh 83,100.00 831,000.00
4 Saklar Ganda 10A, Type Inbow 9.00 bh 77,100.00 693,900.00
5 Saklar Tunggal 10A, Type Inbow 2.00 bh 77,100.00 154,200.00
6 Instalasi Penerangan dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit hi 46.00 ttk 124,335.00 5,719,410.00
7 Instalasi Stop kontak dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit hi 10.00 ttk 124,335.00 1,243,350.00
LANTAI 2
1 Lampu TKI 2 x 18 watt bahan komplit 30.00 bh 273,238.00 8,197,140.00
2 Lampu PLC 18 Watt 16.00 bh 224,238.00 3,587,808.00
3 Stop Kontak type inbow 10A, 220V, 1P 10.00 bh 83,100.00 831,000.00
4 Saklar Ganda 10A, Type Inbow 9.00 bh 77,100.00 693,900.00
5 Saklar Tunggal 10A, Type Inbow 2.00 bh 77,100.00 154,200.00
6 Instalasi Penerangan dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit hi 46.00 ttk 124,335.00 5,719,410.00
7 Instalasi Stop kontak dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit hi 10.00 ttk 124,335.00 1,243,350.00
LANTAI 3
1 Lampu TKI 2 x 18 watt bahan komplit 30.00 bh 273,238.00 8,197,140.00
2 Lampu PLC 18 Watt 16.00 bh 224,238.00 3,587,808.00
3 Stop Kontak type inbow 10A, 220V, 1P 10.00 bh 83,100.00 831,000.00
4 Saklar Ganda 10A, Type Inbow 9.00 bh 77,100.00 693,900.00
5 Saklar Tunggal 10A, Type Inbow 2.00 bh 77,100.00 154,200.00
6 Instalasi Penerangan dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit hi 46.00 ttk 124,335.00 5,719,410.00
7 Instalasi Stop kontak dgn kabel NYA 3X(1X2.5 mm2) dlm PVC conduit hi 10.00 ttk 124,335.00 1,243,350.00
8 Penangkal Petir (lengkap aksesoris grounding dan bak kontrol terpasang) 3.00 ttk 1,750,000.00 5,250,000.00
66,530,424.00
B PEKERJAAN KABEL FEEDER
LANTAI 1, 2 DAN 3
1 Dari SDP 1 ke LP/PP-A
NYY 4X6mm2 + NYA 1X4mm2 4.00 m 105,000.00 420,000.00
2 Dari SDP 2 ke LP/PP-B
NYY 4X10mm2 + NYA 1X6mm2 8.00 m 165,000.00 1,320,000.00
3 Dari SDP 3 ke LP/PP-C
NYY 4X10mm2 + NYA 1X6mm2 12.00 m 165,000.00 1,980,000.00
3 Dari SDP 1 ke PP-POMPA TRANSFER
NYY 4X25mm2 12.00 m 215,000.00 2,580,000.00
4 Dari SDP 1 ke PP-POMPA BOSTER
NYY 3X6mm2 12.00 m 98,000.00 1,176,000.00
5 Dari SDP 1 ke SDP 2
NYY 4X35mm2 4.00 m 238,000.00 952,000.00
6 Dari SDP 2 ke SDP 3
NYY 4X35mm2 4.00 m 238,000.00 952,000.00
9,380,000.00
Page 87 of 144
RENCANA ANGGARAN BIAYA SEKOLAH MENENGAH PERTAMA
PEKERJAAN : ARSITEKTUR BANGUNAN SEKOLAH 1 NEGERI 32 TANGERANG
LOKASI : SMPN 32 TANGERANG
HARGA JUMLAH
SATUAN HARGA
NO URAIAN PEKERJAAN VOLUMESAT (Rp.) (Rp.)
D. BANGUNAN UTAMA
I. PEKERJAAN PEMATANGAN LAHAN
1 Urugan peninggian lantai 200.82 m3 183,050.00 36,760,650.15
2 Pembersihan site 478.15 m2 5,200.00 2,486,380.00
3 Pengukuran dan pasang bouwplank 104.40 m 31,930.00 3,333,492.00
42580522.15
II. PEKERJAAN PONDASI
A Pekerjaan Pancang Mini Pile Uk 25x25 cm kotak
A.1. Type P1
1 Pemancangan mini pile segitiga 28x28x28 cm 312.00 m 275,000.00 85,800,000.00
2 Potong kepala tiang pancang 26.00 unit 60,000.00 1,560,000.00
A.2. Type P2
3 Pemancangan mini pile segitiga 28x28x28 cm 432.00 m 275,000.00 118,800,000.00
4 Potong kepala tiang pancang 36.00 unit 60,000.00 2,160,000.00
5 PDA Test 1.00 ttk 4,000,000.00 4,000,000.00
212,320,000.00
B Pekerjaan Pilecap
1 Galian tanah pile cap 113.80 m3 63,000.00 7,169,400.00
2 Buang tanah sekitar lokasi 18.07 m3 20,800.00 375,856.00
3 Urugan tanah sisi pondasi 95.73 m3 183,050.00 17,523,376.50
4 Lantai kerja beton tumbuk 1:3:5; t. 50 mm 23.40 m3 812,920.00 19,022,328.00
5 Pilecap P1
- Cor beton Readymix K- 300 5.62 m3 995,733.00 5,596,019.46
- Begisting Pondasi Kayu klas III 37.44 m2 182,025.00 6,815,016.00
- Tulangan besi U- 40
- dia. D16 mm 1,018.87 kg 11,555.00 11,773,042.85
- dia. D13 mm 59.51 kg 11,555.00 687,638.05
6 Pedestal P1 sampai FL 0.00
- Cor beton Readymix K- 300 1.56 m3 995,733.00 1,553,343.48
- Begisting Pondasi Kayu klas III 22.88 m2 182,025.00 4,164,732.00
- Tulangan besi U- 40
- dia. D16mm 566.22 kg 11,555.00 6,542,672.10
- Tulangan besi U- 24
- dia. 10 mm 187.96 kg 11,500.00 2,161,540.00
7 Pilecap P2
- Cor beton Readymix K- 300 8.42 m3 995,733.00 8,384,071.86
- Begisting Pondasi Kayu klas III 41.04 m2 182,025.00 7,470,306.00
- Tulangan besi U- 40
- dia. D16 mm 1,346.72 kg 11,555.00 15,561,349.60
- dia. D13 mm 66.15 kg 11,555.00 764,363.25
8 Pedestal P2 sampai FL 0.00
- Cor beton Readymix K- 300 1.30 m3 995,733.00 1,294,452.90
- Begisting Pondasi Kayu klas III 17.28 m2 182,025.00 3,145,392.00
- Tulangan besi U- 40
- dia. D16 mm 470.40 kg 11,555.00 5,435,472.00
- Tulangan besi U- 24
- dia. 10 mm 142.40 kg 11,500.00 1,637,600.00
127,077,972.05
C Pekerjaan Tie Beam
1 Galian tanah tie beam 97.00 m3 63,000.00 6,111,000.00
2 Buang tanah sekitar lokasi 37.66 m3 20,800.00 783,328.00
3 Urugan tanah sisi pondasi 59.34 m3 183,050.00 10,862,187.00
4 Lantai kerja beton tumbuk 1:3:5; t. 50 mm 68.47 m3 812,920.00 55,660,632.40
HARGA JUMLAH
SATUAN HARGA
NO URAIAN PEKERJAAN VOLUMESAT (Rp.) (Rp.)
5 Tie Beam TB1; 30x60
- Cor beton Readymix K- 300 34.24 m3 995,733.00 34,093,897.92
- Begisting Sloof Kayu klas III 228.24 m2 182,025.00 41,545,386.00
- Tulangan besi U- 24
- dia. 10 mm 1,626.63 kg 11,500.00 18,706,245.00
- Tulangan besi U- 40
- dia. D16 mm 5,601.27 kg 11,555.00 64,722,674.85
232,485,351.17
D Pekerjaan Plat lantai dasar
1 Gelar plastik sheet 478.15 m2 6,560.00 3,136,664.00
2 Gelar wiremesh M6 (1lapis) 478.15 m2 89,801.00 42,938,348.15
3 -Cor beton Readymix K-300 38.25 m3 995,733.00 38,086,787.25
84,161,799.40
II PEKERJAAN STRUKTUR
A LANTAI 1
1 Kolom K1
- Cor beton Readymix K- 300 5.67 m3 995,733.00 5,645,806.11
- Begisting Sloof Kayu klas III 75.60 m2 182,025.00 13,761,090.00
- Tulangan besi U- 24
- dia. 10 mm 362.48 kg 11,500.00 4,168,520.00
- Tulangan besi U- 40
- dia. D16 mm 1,395.01 kg 11,555.00 16,119,340.55
2 Kolom K2
- Cor beton Readymix K- 300 6.83 m3 995,733.00 6,800,856.39
- Begisting Sloof Kayu klas III 100.10 m2 182,025.00 18,220,702.50
- Tulangan besi U- 24
- dia. 10 mm 476.83 kg 11,500.00 5,483,545.00
- Tulangan besi U- 40
- dia. D16 mm 1,679.18 kg 11,555.00 19,402,924.90
89,602,785.45
B LANTAI 2
1 Kolom K1
- Cor beton Readymix K- 300 1.89 m3 995,733.00 1,881,935.37
- Begisting Sloof Kayu klas III 25.20 m2 182,025.00 4,587,030.00
- Tulangan besi U- 24
- dia. 10 mm 120.83 kg 11,500.00 1,389,545.00
- Tulangan besi U- 40
- dia. D16 mm 465.00 kg 11,555.00 5,373,075.00
2 Kolom K2
- Cor beton Readymix K- 300 3.15 m3 995,733.00 3,136,558.95
- Begisting Sloof Kayu klas III 46.20 m2 182,025.00 8,409,555.00
- Tulangan besi U- 24
- dia. 10 mm 220.08 kg 11,500.00 2,530,920.00
- Tulangan besi U- 40
- dia. D16 mm 775.01 kg 11,555.00 8,955,240.55
3 Balok B1
- Cor beton Readymix K- 300 7.14 m3 995,733.00 7,109,533.62
- Begisting Sloof Kayu klas III 47.62 m2 182,025.00 8,668,030.50
- Tulangan besi U- 24
- dia. 10 mm 473.38 kg 11,500.00 5,443,870.00
- Tulangan besi U- 40
- dia. D16 mm 1,377.89 kg 11,555.00 15,921,518.95
- dia. 10 mm 62.38 kg 11,500.00 717,370.00
4 Balok B2
- Cor beton Readymix K- 300 16.16 m3 995,733.00 16,091,045.28
- Begisting Sloof Kayu klas III 129.28 m2 182,025.00 23,532,192.00
HARGA JUMLAH
SATUAN HARGA
NO URAIAN PEKERJAAN VOLUMESAT (Rp.) (Rp.)
- Tulangan besi U- 24
- dia. 10 mm 1,188.04 kg 11,500.00 13,662,460.00
- Tulangan besi U- 40
- dia. D16 mm 3,055.93 kg 11,555.00 35,311,271.15
5 Balok B3
- Cor beton Readymix K- 300 6.50 m3 995,733.00 6,472,264.50
- Begisting Sloof Kayu klas III 52.02 m2 182,025.00 9,468,940.50
- Tulangan besi U- 24
- dia. D10 mm 568.11 kg 11,500.00 6,533,265.00
- Tulangan besi U- 40
- dia. D16 mm 1,546.42 kg 11,555.00 17,868,883.10
6 Plat lantai t:12cm
- Cor beton Readymix K- 300 54.99 m3 995,733.00 54,755,357.67
- Begisting Sloof Kayu klas III 458.29 m2 182,025.00 83,420,237.25
- Tulangan besi U- 40
- dia. D10 mm 7,829.63 kg 11,500.00 90,040,745.00
7 Sewa Scafolding 458.29 m2 133,600.00 61,227,544.00
492,508,388.39
C DAK DAN ATAP
1 Balok B1
- Cor beton Readymix K- 300 2.68 m3 995,733.00 2,668,564.44
- Begisting Sloof Kayu klas III 17.86 m2 182,025.00 3,250,966.50
- Tulangan besi U- 24
- dia. 10 mm 177.52 kg 11,500.00 2,041,480.00
- Tulangan besi U- 40
- dia. D16 mm 516.71 kg 11,555.00 5,970,584.05
- dia. 10 mm 23.39 kg 11,500.00 268,985.00
2 Balok B2
- Cor beton Readymix K- 300 2.39 m3 995,733.00 2,379,801.87
- Begisting Sloof Kayu klas III 19.12 m2 182,025.00 3,480,318.00
- Tulangan besi U- 24
- dia. 10 mm 128.96 kg 11,500.00 1,483,040.00
- Tulangan besi U- 40
- dia. D16 mm 311.45 kg 11,555.00 3,598,804.75
3 Balok B3
- Cor beton Readymix K- 300 16.19 m3 995,733.00 16,120,917.27
- Begisting Sloof Kayu klas III 129.50 m2 182,025.00 23,572,237.50
- Tulangan besi U- 24
- dia. D10 mm 952.07 kg 11,500.00 10,948,805.00
- Tulangan besi U- 40
- dia. D16 mm 952.07 kg 11,555.00 11,001,168.85
4 Plat dak t:12cm
- Cor beton Readymix K- 300 8.75 m3 995,733.00 8,712,663.75
- Begisting Sloof Kayu klas III 72.91 m2 182,025.00 13,271,442.75
- Tulangan besi U- 40
- dia. D10 mm 1,245.66 kg 11,500.00 14,325,090.00
5 Sewa Scafolding 72.91 m2 133,600.00 9,740,776.00
132,835,645.73
E TANGGA
- Cor beton Readymix K300 5.60 m3 995,733.00 5,576,104.80
- Begisting Sloof Kayu klas III 28.00 m2 182,025.00 5,096,700.00
- Tulangan besi U40
- dia. D16 mm 448.00 kg 11,555.00 5,176,640.00
- dia. D13 mm 224.00 kg 11,555.00 2,588,320.00
18,437,764.80
III PEKERJAAN ARSITEKTUR
HARGA JUMLAH
SATUAN HARGA
NO URAIAN PEKERJAAN VOLUMESAT (Rp.) (Rp.)
A Pekerjaan Dinding
Lantai 1
1 Pemasangan dinding bata 516.60 m2 114,149.00 58,969,373.40
2 Plester aci dinding 938.10 m2 52,194.00 48,963,191.40
3 Kolom praktis 1.10 m3 3,740,273.00 4,118,414.60
4 Pasang keramik dinding kamar mandi 95.10 m2 175,459.00 16,686,150.90
Lantai 2
1 Pemasangan dinding bata 375.50 m2 114,149.00 42,862,949.50
2 Plester aci dinding 625.72 m2 52,194.00 32,658,829.68
3 Kolom praktis 1.21 m3 3,740,273.00 4,521,204.60
4 Pasang keramik dinding kamar mandi 95.10 m2 175,459.00 16,686,150.90
225,466,264.98
B Pekerjaan Lantai
Lantai 1
1 Keramik lantai uk 40x40 unpolish 294.05 m2 130,026.00 38,234,145.30
2 Keramik lantai uk 40x40 polish 146.90 m2 130,026.00 19,100,819.40
3 Keramik lantai uk 30x30 unpolish 37.20 m2 130,026.00 4,836,967.20
4 Keramik lantai tangga uk 40x40 unpolish 11.20 m2 130,026.00 1,456,291.20
5 Step nosing 48.00 m' 113,922.00 5,468,256.00
6 Rabat Keliling Bangunan 219.50 m2 52,333.00 11,487,093.50
Lantai 2
1 Keramik lantai uk 40x40 unpolish 127.85 m2 130,026.00 16,623,824.10
2 Keramik lantai uk 40x40 polish 240.50 m2 130,026.00 31,271,253.00
128,478,649.70
C Pasangan plafon
Lantai 1
1 Pemasangan plafond gypsum 9mm rangka hollow 324.50 m2 130,085.00 42,212,582.50
2 Pemasangan plafond GRC 6mm rangka hollow 37.20 m2 129,707.00 4,825,100.40
3 Pemasangan plafond Gyptile rangka cross tee main tee 156.75 m2 145,000.00 22,728,750.00
Lantai 2
1 Pemasangan plafond gypsum 9mm rangka hollow 65.00 m2 130,085.00 8,455,525.00
2 Pemasangan plafond GRC 6mm rangka hollow 219.50 m2 129,707.00 28,470,686.50
3 Pemasangan plafond Gyptile rangka cross tee main tee 175.50 m2 145,000.00 25,447,500.00
132,140,144.40
D Pengecatan dinding
Lantai 1
1 Pengecatan dinding luar 365.40 m2 61,025.00 22,298,535.00
2 Pengecatan dinding dalam 572.70 m2 60,045.00 34,387,771.50
3 Pengecatan plafond 361.70 m2 60,160.00 21,759,872.00
Lantai 2
1 Pengecatan dinding luar 62.64 m2 61,025.00 3,822,606.00
2 Pengecatan dinding dalam 563.08 m2 60,045.00 33,810,138.60
3 Pengecatan plafond 284.50 m2 60,160.00 17,115,520.00
133,194,443.10
E Sanitary
1 Closet duduk 6.00 unit 2,560,950.00 15,365,700.00
2 Urinoir 2.00 unit 2,265,700.00 4,531,400.00
3 Wastafel 2.00 unit 68,100.00 136,200.00
4 Skat urinoir 1.00 unit 967,120.00 967,120.00
5 Jet washer 6.00 unit 24,000.00 144,000.00
6 Kran dinding 6.00 unit 202,962.00 1,217,772.00
7 Tempat tisu 6.00 unit 300,000.00 1,800,000.00
8 Floor drain 8.00 unit 120,400.00 963,200.00
9 Cleaning out 4.00 unit 155,000.00 620,000.00
25,745,392.00
F Pintu dan jendela
HARGA JUMLAH
SATUAN HARGA
NO URAIAN PEKERJAAN VOLUMESAT (Rp.) (Rp.)
Lantai 1
1 Pintu P2 25.00 m2 425,000.00 10,625,000.00
2 Pintu P3 2.00 unit 1,405,050.00 2,810,100.00
3 Pintu P4 Pintu Toilet 7.00 unit 667,800.00 4,674,600.00
4 Pintu P6 6.00 unit 3,077,940.00 18,467,640.00
5 Jendela J1 10.00 unit 2,403,465.00 24,034,650.00
6 Jendela J2 2.00 unit 4,610,755.00 9,221,510.00
Lantai 2
1 Pintu P5 2.00 unit 5,035,044.00 10,070,088.00
2 Pintu P6 6.00 unit 3,077,940.00 18,467,640.00
3 Jendela J1 15.00 unit 2,403,465.00 36,051,975.00
4 Jendela J2 1.00 unit 4,610,755.00 4,610,755.00
139,033,958.00
G Lain -lain
1 Lantai 1
Railling tangga besi pipa 2" dan hollow 40x40mm+15x40mm 21.00 m' 321,235.00 6,745,935.00
2 Lantai 2
Railling tangga besi pipa 2" dan hollow 40x40mm+15x40mm 52.20 m' 321,235.00 16,768,467.00
23,514,402.00
H Rangka dan Penutup Atap
Rangka atap baja ringan 219.71 m2 210,000.00 46,139,100.00
Penutup atap (Zincalume warna t:0,35mm + Roofmesh + alumunium foil 2 sisi) 219.71 m2 248,464.00 54,590,025.44
Water proofing membran 3mm 72.64 m2 58,675.00 4,262,152.00
104,991,277.44
IV PEKERJAAN MEKANIKAL
A PEKERJAAN INSTALASI PLAMBING (INSTALASI AIR BERSIH)
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
D. BANGUNAN FASILITAS KANTIN
I PEKERJAAN PEMATANGAN LAHAN
1 Urugan peninggian lantai 62.37 m3 183,050.00 11,416,828.50
2 Pembersihan site 366.89 m2 5,200.00 1,907,828.00
3 Pengukuran dan pasang bouwplank 107.99 m 31,930.00 3,448,120.70
16,772,777.20
II PEKERJAAN PONDASI
A Pekerjaan Pancang Mini Pile
Type P1
1 Pemancangan mini pile segitiga 28x28x28 cm 252.00 m 275,000.00 69,300,000.00
2 Potong kepala tiang pancang 21.00 unit 60,000.00 1,260,000.00
Type P2
3 Pemancangan mini pile segitiga 28x28x28 cm 216.00 m 275,000.00 59,400,000.00
4 Potong kepala tiang pancang 18.00 unit 60,000.00 1,080,000.00
131,040,000.00
B Pekerjaan Pilecap
1 Galian tanah pile cap 73.60 m3 63,000.00 4,636,800.00
2 Buang tanah sekitar lokasi 11.64 m3 20,800.00 242,112.00
3 Urugan tanah sisi pondasi 61.97 m3 183,050.00 11,343,608.50
4 Lantai kerja beton tumbuk 1:3:5; t. 50 mm 14.58 m3 812,920.00 11,852,373.60
5 Pilecap P1
- Cor beton Readymix K- 300 4.54 m3 995,733.00 4,520,627.82
- Begisting Pondasi Kayu klas III 30.24 m2 182,025.00 5,504,436.00
- Tulangan besi U- 40
- dia. D16 mm 822.93 kg 11,555.00 9,508,956.15
- dia. D13 mm 48.07 kg 11,555.00 555,448.85
6 Pedestal P1 sampai FL 0.00
- Cor beton Readymix K- 300 2.16 m3 995,733.00 2,150,783.28
- Begisting Pondasi Kayu klas III 28.80 m2 182,025.00 5,242,320.00
- Tulangan besi U- 40
- dia. D16mm 783.99 kg 11,555.00 9,059,004.45
- Tulangan besi U- 24
- dia. 10 mm 237.34 kg 11,500.00 2,729,410.00
7 Pilecap P2
- Cor beton Readymix K- 300 4.21 m3 995,733.00 4,192,035.93
- Begisting Pondasi Kayu klas III 20.52 m2 182,025.00 3,735,153.00
- Tulangan besi U- 40
- dia. D16 mm 673.39 kg 11,555.00 7,781,021.45
- dia. D13 mm 33.07 kg 11,555.00 382,123.85
83,436,214.88
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(Rp.) (Rp.)
E. PEKERJAAN SARANA LUAR
1 Pagar Precast 120.00 m 451,330.00 54,159,600.00
2 Gerbang Pagar 2.00 unit 2,850,000.00 5,700,000.00
3 Pagar Teralis 60.00 m1 675,000.00 40,500,000.00
4 Tiang Bendera 1.00 unit 2,500,000.00 2,500,000.00
5 Urugan Macadam 37.50 m3 278,900.00 10,458,750.00
6 Urugan Pasir 18.75 m3 247,200.00 4,635,000.00
6 Pondasi Batu Kali 9.60 m3 761,860.00 7,313,856.00
7 Cor Lapangan Olah Raga 37.50 m3 1,519,429.00 56,978,587.50
8 Floor Hardener 375.00 m2 135,000.00 50,625,000.00
9 Saluran Buis Beton Terbuka 400.00 m 130,186.00 52,074,400.00
10 Paving Block t : 6cm 427.89 m2 99,360.00 42,515,150.40
11 Urugan Sirtu 98.40 m3 251,000.00 24,698,400.00
12 Urugan Abu batu 49.20 m3 318,400.00 15,665,280.00
13 Penanaman rumput gajah mini 350.00 m2 35,165.00 12,307,750.00
14 Penanaman Semak Perdu T 50-60 CM 40.00 phn 75,000.00 3,000,000.00
15 Penanaman Pohon Hias/Pelindung T 300-400 CM 40.00 phn 75,000.00 3,000,000.00
16 Tanah subur dan pembentukan tanah 44.00 m3 146,000.00 6,424,000.00
17 Lampu Taman Tinggi 5 m dan aksesories 8.00 unit 650,000.00 5,200,000.00
18 Tempat Sampah double bin 6.00 unit 3,000,000.00 18,000,000.00
415,755,773.90
ANALISA HARGA SATUAN PEKERJAAN
HARGA
NO. URAIAN KOEF. SAT. JUMLAH (Rp.)
SATUAN (Rp.)
A PEKERJAAN PERSIAPAN
1 1 m2 - Pembersihan Lokasi
Pekerja 0.0500 hr 80,000.00 4,000.00
Mandor 0.0100 hr 120,000.00 1,200.00
JUMLAH 5,200.00
DIBULATKAN 5,200.00
2 1 bh - Papan nama proyek
Multipleks 120 x 240, 9 mm 0.5000 lbr 120,000.00 60,000.00
Kaso kayu meranti 0.0280 m3 3,000,000.00 84,000.00
Penulisan 1.0000 ls - -
Ongkos pasang 1.0000 ls - -
JUMLAH 144,000.00
DIBULATKAN 144,000.00
3 1 m2 - Direksikeet
Pasir pasang 0.2500 m3 225,000.00 56,250.00
Pasir beton 0.0517 m3 230,000.00 11,891.00
Batu bata merah 25.0000 bh 800.00 20,000.00
Semen PC 50 kg 0.2500 zak 68,000.00 17,000.00
Kayu kaso meranti 0.0300 m3 3,000,000.00 90,000.00
Triplek 122 x 244 x 4 mm 1.0000 lbr 60,000.00 60,000.00
Engsel pintu uk 3 " 0.1667 bh 45,000.00 7,501.50
Asbes semen gelombang 250x92 x 0. 5 cm 0.5000 lbr 85,000.00 42,500.00
Paku segala ukuran ( rata-rata) 0.5000 kg 16,500.00 8,250.00
Kunci gembok 0.0834 bh 50,000.00 4,170.00
Pekerja 0.4000 hr 80,000.00 32,000.00
Tukang batu 0.0834 hr 90,000.00 7,506.00
Tukang kayu 0.3340 hr 90,000.00 30,060.00
Mandor 0.0200 hr 120,000.00 2,400.00
JUMLAH 389,528.50
DIBULATKAN 389,528.00
B PEKERJAAN PEMATANGAN LAHAN
4 1 m1 - Pengukuran & pemasangan bouwplank
Kayu Kaso terentang 5/7-400 cm 0.0040 m3 3,000,000.00 12,000.00
Kayu Papan terentang 2/20- 400 cm 0.0060 m3 1,750,000.00 10,500.00
Paku segala ukuran 0.0200 kg 16,500.00 330.00
Pekerja 0.0500 hr 80,000.00 4,000.00
Tukang Kayu 0.0500 hr 90,000.00 4,500.00
Mandor 0.0050 hr 120,000.00 600.00
JUMLAH 31,930.00
DIBULATKAN 31,930.00
5 1 m1 - Pagar Pengaman Proyek
Kaso Meranti Jambi Basah uk. 5 x 10 x 400 cm 0.0152 m³ 3,000,000.00 45,600.00
Seng Gelombang BJLS 28 (80x180) cm 0.3470 lbr 84,000.00 29,148.00
Paku Kayu Segala uk. 0.0200 kg 16,500.00 330.00
Pekerja 0.3000 hr 80,000.00 24,000.00
Tukang Kayu 0.1500 hr 90,000.00 13,500.00
P T. DADO DIMENSI
1 2 3 4
I PASIR DAN BATU
Abu Batu/Screening 5 mm 230,000.00 m3
Batu Belah Pondasi 215,000.00 m3
Batu Pecah/Split ukr. 2 - 3 cm 220,000.00 m3
Batu Pecah/Split ukr. 3 - 4 cm 220,000.00 m3
Macadam/Steel Slag ukr. 5 - 7 cm 220,000.00 m3
Pasir Beton 230,000.00 m3
Pasir pasang 225,000.00 m3
Pasir urug darat 185,000.00 m3
Sirtu 190,000.00 m3
Tanah Merah 100,000.00 m3
Batu Tempel Hitam 125,000.00 m2
Plastik cor 3,000.00 m2
II PAVING BLOCK
Paving Block K 250 Tebal 6 Abu-abu 75,000.00 m2
Paving Block K 250 Tebal 8 Abu-abu 95,000.00 m2
Paving Block K 350 Tebal 6 Abu-abu 85,000.00 m2
Paving Block K 350 Tebal 8 Abu-abu 101,600.00 m2
Grass Block uk. 20.40.6 cm 135,000.00 m2
Kastin Abu-abu ukr. 10.20.40 K 250 60,000.00 m1
VI READYMIX
Readymix beton K-225 tanpa pompa 800,000.00 m3
Readymix beton K-250 tanpa pompa 825,000.00 m3
Readymix beton K-300 tanpa pompa 845,000.00 m3
Readymix beton K-225 tanpa pompa (Minimix) 1,050,000.00 m3
Readymix beton K-250 tanpa pompa (Minimix) 1,075,000.00 m3
Readymix beton K-300 tanpa pompa (Minimix) 1,095,000.00 m3
VIII C A T
Amplas Kayu 1,500.00 lbr
Ampelas Besi 2,500.00 lbr
Cat minyak setara F Talit 46,400.00 kg
Cat tembok Dulux/ICI interior 30,500.00 kg
Cat tembok Dulux/ICI exterior 34,000.00 kg
Cat tembok setara Vinilex 24,200.00 kg
Cat dasar setara Dulux/ICI 33,000.00 kg
Cat lapangan (teknokote) 42,000.00 kg
Meni setara Nippon 11,500.00 kg
Zincromate 27,500.00 m2
Cat Melamik 210,000.00 kg
Cat Pelitur 47,500.00 kg
Dempul plitur 32,000.00 kg
Ijuk 26,000.00 ikat
Kwas 3" 5,500.00 bh
Minyak Cat/Tinner 16,500.00 ltr
Pelamir Tembok 21,400.00 kg
Rool cat tembok 17,500.00 bh
Aquaproof 35,000.00 kg
HPL 225,000.00 lmbr
Finish HPL 42,500.00 m2
IX LANTAI
Keramik Lantai Uk. 25x25 Standar KW 1 (Roman/Mulia) 75,000.00 m2
Keramik Lantai Uk. 30x30 Standar KW 1 (Roman/Mulia) 80,000.00 m2
Keramik Lantai Uk. 40x40 Standar KW 1 (Roman/Mulia) 80,000.00 m2
X SANITASI AIR
Closet Jongkok Merk Toto Tipe Standar 450,000.00 bh
Closet duduk Merk Toto Tipe Standar (komplit) 2,400,000.00 bh
Wastafel Merk Toto Tipe Standart (komplit) 2,100,000.00 unit
Urinoir 2,200,000.00 bh
Skat Urinoir Porcelain 950,000.00 bh
Kitchen zinck 650,000.00 bh
Floor Drain Kuningan 110,000.00 bh
Clean Out 155,000.00 bh
Kran Air TOTO 1/2" 191,000.00 bh
Kran leher angsa 325,000.00 bh
Jet spray 165,000.00 bh
Shower 1,800,000.00 bh
Tempat Tisu KM 300,000.00 bh
Sealtape 2,500.00 bh
Lem Pipa PVC 12,000.00 tube
Roofdrain cast iron uk.80 mm 550,000.00 bh
Bak Penampung Air / Tower Tanx Cap. 1000 ltr 1,900,000.00 bh
Bak Penampung Air / Tower Tanx Cap. 500 ltr 1,200,000.00 bh
Bocht LL-D 1" (lokal) 58,500.00 bh
Water moer 78,000.00 bh
Pembuatan sumur bor 90,000.00 m1
Pompa Air Jetpump 4,200,000.00 unit
Gate Valve dia 1-1/2" 55,000.00 bh
WLC (Water Level Control) 750,000.00 bh
Pipa PVC dia. 1/2 inch type AW, tebal 22 mm, panjang 4 m 32,000.00 btg
Pipa PVC dia. 1/2 inch type AW, tebal 22 mm 9,000.00 m'
Pipa PVC dia. 3/4 inch type AW, tebal 26 mm, panjang 4 m 34,000.00 btg
Pipa PVC dia. 3/4 inch type AW, tebal 26 mm 9,500.00 m'
Pipa PVC dia. 1 inch type AW, panjang 4 m 48,000.00 btg
Pipa PVC dia. 1 inch type AW 14,000.00 m'
Pipa PVC dia. 1,5 inch type AW 60,000.00 btg
Pipa PVC dia. 1,5 inch type AW 17,500.00 m'
Pipa PVC dia. 2 inch type AW, panjang 4 m 90,000.00 btg
Pipa PVC dia. 2 inch type AW 25,000.00 m'
Pipa PVC dia. 3 inch type AW, panjang 4 m 130,000.00 btg
Pipa PVC dia. 3 inch type AW 37,500.00 m'
Pipa PVC dia. 4 inch type AW, panjang 4 m 200,000.00 btg
Pipa PVC dia. 4 inch type AW 55,000.00 m'
Pipa PVC dia. 6 inch type AW, panjang 4 m 230,000.00 btg
Pipa PVC dia. 6 inch type AW 65,000.00 m'
Knee 1/2" 5,000.00 Bh
Knee 3/4" 6,000.00 Bh
Knee 1" 9,000.00 Bh
Knee 1,5" 11,500.00 Bh
Knee 2" 11,500.00 Bh
Knee 3" 13,000.00 Bh
XVI LISTRIK
Kabel NYY 1x4 mm 6,500.00 m
Kabel NYM 1x6 mm 12,000.00 m
Kabel NYM 3x2.5 mm 12,200.00 m
Kabel NYM 3x6 mm 48,000.00 m
Kabel NYY 4x2.5 mm 32,000.00 m
Kabel NYY 4x6 mm 55,000.00 m
Kabel NYY 4x25 mm 120,000.00 m
Kabel NYY 4x35 mm 180,000.00 m
Kabel NYY 4x16 mm 95,000.00 m
Kabel NYY 4x10 mm 73,000.00 m
Klem kabel 3,200.00 dus
Pipa AW 1/2" 8,000.00 m
Saklar tunggal 39,000.00 bh
Saklar double 39,000.00 bh
Stop Kontak 45,000.00 bh
Stop Kontak AC 85,000.00 bh
Lampu TL 2 x 18 watt, armatur, komplit philips 234,000.00 bh
Lampu TKI 2 x 18 watt, armatur, komplit philips 234,000.00 bh
Lampu Down Light 225,000.00 bh
Lampu baret kotak 40 w 315,000.00 bh
Lampu PLC 18 watt, komplit philips 185,000.00 bh
Lampu TL 1 x 36 watt, armatur, komplit philips 210,000.00 bh
Lampu Halogen 50 Watt Merk : Philips/osram 215,000.00 buah
Lampu gantung 7,500,000.00 bh
Lampu pagar 390,000.00 bh
Lampu taman lengkap (lampu + tiang galvanis) 650,000.00 bh
Fitting Keramik 39,000.00 bh
Exhausfan 385,000.00 bh
Penyambungan daya Listrik 2,600.00 watt
Grounding Panel 1,500,000.00 ls
Box MCB 100,000.00 unit
Box Panel 40x60 cm 140,000.00 unit
Box Panel 30x40 cm 120,000.00 unit
MCB 6 Ampere 60,000.00 bh
MCB 10 Ampere 70,000.00 bh
MCB 32 Ampere 70,000.00 bh
Perangkat Penangkal Petir 1,750,000.00 titik
Sparing Kabel (Pipa conduit) 11,500.00 bh
Material bantu 500,000.00 ls
Testing Commissioning 250,000.00 ls
XIII A T A P
Alumunium Foil 2 muka dengan insulin 90,000.00 m2
Genteng Zincalume (Bahan) Gelombang Besar t=0.35 105,000.00 m2
Genteng Metal Multi Roof (Stone Chip) t=0.35 105,000.00 m2
Penutup atap Alderon 215,000.00 m2
Karpusan atap Alderon 185,000.00 m1
Nok Metal Multiroof (Stone Chip) 145,000.00 m1
Seng gelombang 180 x 90 x 0,20 84,000.00 lbr
Rangka Atap Baja Ringan (Terpasang) 210,000.00 m2
Roofmesh spasi 75x75X1.3 25,000.00 m2
Page 135 of 144
Glass wool 40,000.00 m2
Asbes semen gelombang 85,000.00 lbr
XX UPAH
XIX TAMBAHAN
Upah Potong Pancang 60,000.00 unit
Upah Potong Kaca 45,000.00 m2
Upah Pasang dan Aksesoris 100,000.00 unit
Air dan Listrik Kerja 2,000,000.00 bln
Air dan Listrik Kerja 18,000,000.00 ls
Mobilisasi dan Demobilisasi 30,000,000.00 ls
Tiang pancang uk, 20x20 200,000.00 m
Tiang pancang uk, 25x25 210,000.00 m
Tiang pancang uk, 28x28 275,000.00 m
Sewa alat pancang hidraulic 18,000.00 m
Sewa alat pancang hammer 18,000.00 m
Mobilisasi alat pancang hidraulic 18,000.00 unit
Mobilisasi alat pancang dropp hammer 18,000.00 unit
Mobilisasi alat Bored pile 18,000.00 unit
Jasa Pengeboran Bored Pile Ø 30cm / m 180,000.00 m
Jasa Pengeboran Bored Pile Ø 40cm / m 200,000.00 m
Aluminium Composit Panel (ACP) 0.3 mm uk,122x240 620,000.00 m2
Tiang Bendera Stainless t : 5m 2,500,000.00 unit
Penyambungan PDAM 2,500,000.00 m
Huruf Stainles 20 cm 35,000.00 hrf
Huruf Stainles 15 cm 30,000.00 hrf
Logo kota tangerang 1,200,000.00 unit
Net Volley 800,000.00 bh
Jaring Gawang 600,000.00 set
Pipa listrik panjang 4 m 12,000.00 btg
Stop kontak telpon 48,000.00 bh
Material bantu air bersih 100,000.00 ls
Material bantu air kotor 100,000.00 ls
Testing 500,000.00 ls
Daun Jendela Alumunium 300,000.00 m2
Bak kontrol 600 x 600 x 400 425,000.00 bh
Rumput Gajah Mini 32,500.00 m2
Pohon Jakaranda 400,000.00 phn
Ketapang 370,000.00 phn
Kiara Payung 360,000.00 phn
Trembesi 350,000.00 phn
A. PERSIAPAN 0.843 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
B. BANGUNAN SEKOLAH 1
I. PEMATANGAN LAHAN 0.200 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
II. PONDASI 5.167 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
III. STRUKTUR 14.168 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
IV. ARSITEKTUR 17.381
V. MEKANIKAL 0.432
VI. ELEKTRIKAL 1.005
C. BANGUNAN SEKOLAH 2
I. PEMATANGAN LAHAN 0.200 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
II. PONDASI 5.167 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
III. STRUKTUR 14.168 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
IV. ARSITEKTUR 17.381
V. MEKANIKAL 0.432
VI. ELEKTRIKAL 1.005
D. BANGUNAN FASILITAS KANTIN
I. PEMATANGAN LAHAN 0.136 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
II. PONDASI 3.669 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33
III. STRUKTUR 5.165 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17
IV. ARSITEKTUR 8.947
V. MEKANIKAL 0.385
VI. ELEKTRIKAL 0.790
PROGRESS RENCANA 100.000 0.02 0.03 1.31 1.31 1.31 1.31 1.31 2.42 2.42 2.42 2.42 2.42 2.42 1.15 1.15 1.15 1.15 1.15 1.15 1.15 1.15 1.14
KUMULATIF PROGRESS RENCANA 100.000 0.02 0.05 1.36 2.67 3.97 5.28 6.59 9.01 11.43 13.85 16.28 18.70 21.12 22.27 23.42 24.57 25.72 26.87 28.02 29.17 30.32 31.47
JADWAL WAKTU PELAKSANAAN
100
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 90
0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 80
0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
70
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07
0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 60
0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
50
0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 0.07 40
30
0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17
20
0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 10
0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31
0
1.14 2.65 2.65 2.65 2.65 2.65 2.65 2.65 2.71 2.71 2.71 2.71 2.71 2.71 2.71 1.58 1.77 1.77 1.77 1.77 2.07 2.07 2.07 2.07 2.07 2.07 2.07 2.07 2.07 2.07 0.51 0.02
32.61 35.26 37.91 40.56 43.21 45.86 48.51 51.16 53.87 56.58 59.29 61.99 64.70 67.41 70.12 71.69 73.46 75.23 76.99 78.76 80.83 82.90 84.97 87.05 89.12 91.19 93.26 95.33 97.40 99.48 99.98 100.00
BOBOT W A K T U P E L A K S A N A A N
JUMLAH HARGA KETERANGA
NO. URAIAN PEKERJAAN DALAM PERIODE BULANAN N
( Rp ) ( % ) Bln.1 Bln.2 Bln.3 Bln.4 Bln.5 Bln.6 Bln.7 Bln.8 Bln.9 Bln.10 Bln.11 Bln.12 Bln.13
100
A. PERSIAPAN 104,280,560.00 0.84 0.17 0.17 0.17 0.17 0.17
B. BANGUNAN SEKOLAH 1
I. PEMATANGAN LAHAN 24,786,726.50 0.20 0.20 90
II. PONDASI 639,369,949.65 5.17 1.72 1.72 1.72
III. STRUKTUR 1,753,277,339.64 14.17 4.72 4.72 4.72
IV. ARSITEKTUR 2,150,848,355.69 17.38 5.79 5.79 5.79 80
C. BANGUNAN SEKOLAH 2
I. PEMATANGAN LAHAN 24,786,726.50 0.20 0.20 60
II. PONDASI 639,369,949.65 5.17 1.72 1.72 1.72
III. STRUKTUR 1,753,277,339.64 14.17 4.72 4.72 4.72
IV. ARSITEKTUR 2,150,848,355.69 17.38 5.79 5.79 5.79 50
V. MEKANIKAL 53,511,340.00 0.43 0.22 0.22
VI. ELEKTRIKAL 124,410,424.00 1.01 0.50 0.50
40
PROGRESS RENCANA PERIODIK 2.43 6.44 12.24 11.40 8.23 6.44 12.41 11.23 8.35 4.59 7.06 5.65 3.53
PROGRESS RENCANA KUMULATIF 2.43 8.87 21.11 32.51 40.75 47.19 59.60 70.83 79.18 83.77 90.82 96.47 100.00
- Tiang Pancang beton mini pile 25 x 25 JTP Square Jl. Mustikasari No.181 SNI-7833-2012 225,000.00 M'
PT. JayaTeknik Pondasi Bantar Gebang Bekasi
- Tiang Pancang beton mini pile 28 x 28 x JTP Trigonal SNI-7833-2012 295,000.00 M'
2 Semen SG PCC PT. Semen Indonesia Tbk Graha Irama lt.9 Jl. HR SNI 15-7064-2014 58,750.00 Zak @ 50 Kg
Rasuna Said Kuningan
Jakarta
3 Besi Beton
- Besi beton polos CS BJTP U-24 PT. Jakarta Cakra Tunggal Jl. Raya Bekasi KM21-22 SNI 07-2052-2002 6,655.00 Kg
Pulogadung Jakarta ISO
- Besi beton ulir CS BJTS U-32 Steel Mills ID03/00254.0
Timur SNI 07-2052-2002 6,655.00 Kg
1
- Besi beton ulir CS BJTS U-40 SNI 07-2052-2002 6,710.00 Kg
JL.Mitra Sunter
4 Rangka Atap Baja Ringan Alsun BJ LAS PT. Alsun Suksesindo Boulevard Blok B-21 SNI 07-2053-2006 155,000.00 M2
Jakarta Tlp.
(021)6508026
P T. DADO DIMENSI
1 2 3 4 5 6 7 8 9 10 11 12 13
1.6.602.1.144.09.1022
601
Ahli Managemen Proyek dan KOMP. PALEM KARTIKA, JL AHLI MANAJEMEN 464 dan
1 Ir. SUMARSONO S1, Sipil/ ArsitekturAhli Teknik Bangunan Gedung Utama 10 Tahun Sukoharjo, 23-12-19663174102312660004 PALEM KARTIKA RAYA No.39, PROYEK - UTAMA dan LPJK 1.2.201.1.057.09.1022
201
JAKARTA TIMUR 464
2 Hary Simadirja S1, Sipil/ Arsitektur Ahli K3 Konstruksi Madya 5 Tahun Tangerang, 11-01-19603671011101600001 Jl. Cirarab RT 02/03, Sukasari, AHLI K3 KONSTRUKSI - 603 LPJK 1.6.603.2.150.28.1069827
Kota Tangerang MADYA
3 Tedi Rusli S1, Arsitektur Ahli Arsitek Muda 3 Tahun Tangerang, 05-02-19563671070502560001 Jl. Otista 51RT 01/06, AHLI ARSITEK - MADYA 101 LPJK 1.1.101.2.144.28.1053539
Karawaci, Kota Tangerang
AHLI TEKNIK
Tenaga Ahli Listrik/ Ahli
Jl. Tebet Timur 1/H19, Tebet, PEMANFAATAN 401 /
4 Adang Priyatna S1, Elektro/ Listrik Teknik Pemanfaatan tenaga Muda 3 Tahun Bogor, 11-05-1957 3174011105570001
Jakarta Selatan TENAGA LISTRIK- 404
LPJK 1.4.404.3.150.28.1126350
listrik MUDA
PELAKSANA
Reni Jaya Blok C9/3, BANGUNAN
5 Mulyarso D3, Sipil/ Arsitektur Pelaksana Bangunan Gedung 5 Tahun Jakarta, 21-01-1977 3276112101770002 Bojongsari, Depok
GEDUNG/PEKERJAAN
022 LPJK 2.1.022.1.102.04.4031390
GEDUNG
P T. DADO DIMENSI
Sertifikat
Keterangan
Masa Berlaku
14 15
05 Oktober 2019
23 Desember 2018
26 Februari 2019
06 Februari 2018
20 Mei 2018
06 Februari 2018