REKAPITULASI

RENCANA ANGGARAN BIAYA

SATUAN KERJA : BALAI PERHUBUNGAN TRANSPORTASI DARAT WIAYAH XIII PROVINSI NTT
PEKERJAAN : PEMBANGUNAN PORTAL PELABUHAN
LOKASI : MARAPOKOT - KABUPATEN NAGEKEO
TAHUN ANGGARAN : 2020

NO. URAIAN PEKERJAAN JUMLAH BIAYA


(Rp.)
A. PEKERJAAN PERSIAPAN 22,034,634.00

B PERKERASAN POS OPERATOR PORTAL 40,069,414.94

C PEKERJAAN KANSTEEN DAN PUVING BLOCK 7,633,178.43

D PERKEJAAN PORTAL DAN PERALATAN PORTAL 97,668,869.08

E LAIN-LAIN 7,150,000.00

SUB TOTAL 174,556,096.45

PPN 10% 17,455,609.65

GRAND TOTAL 192,011,000.00

SUPERVISI 8,000,000.00

GRAND TOTAL DIBULATKAN 200,000,000.00

Terbilang : Dua Ratus Juta Rupiah

Kupang, ... September 2019


RENCANA ANGGARAN BIAYA

SATUAN KERJA : BALAI PERHUBUNGAN TRANSPORTASI DARAT WIAYAH XIII PROVINSI NTT
PEKERJAAN : PEMBANGUNAN PORTAL PELABUHAN
LOKASI : MARAPOKOT - KABUPATEN NAGEKEO
TAHUN ANGGARAN : 2020

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN KWANTITAS SATUAN (Rp.) (Rp.)
A. PEKERJAAN PERSIAPAN
1 Pembuatan Kantor Sementara Direksi Keet 9.00 m2 1,381,626.00 12,434,634.00
2 Pelaporan dan Dokumentasi 1.00 ls 7,000,000.00 7,000,000.00
3 Penerangan, Keamanan dan Keselamatan Kerja 1.00 ls 2,000,000.00 2,000,000.00
4 Papan nama proyek 80 x 120 cm 1.00 ls 600,000.00 600,000.00
JUMLAH SUB A 22,034,634.00
B. PERKERASAN POS OPERATOR PORTAL
I. Pekerjaan Galian dan Urugan Tanah
1 Galian tanah untuk pondasi 9.98 m3 57,426.00 573,341.18
2 Urug tanah kembali 3.33 m3 33,660.00 112,020.48
3 Urug sirtu peninggi lantai 0.76 m3 292,800.00 221,356.80
4 Urugan pasir bawah pondasi 0.77 m3 292,200.00 224,409.60
5 Urugan pasir dibawah lantai 0.50 m3 292,200.00 147,268.80
II. Pekerjaan Pondasi
1 Anstamping 1.54 m3 418,170.00 642,309.12
2 Pasangan pondasi biasa, camp. 1SP : 5PP 5.41 m3 864,530.00 4,675,378.24
III. Pekerjaan Dinding, Plester, dan Acian
1 Pasangan dinding gedung 1SP : 4PP 17.48 m2 91,490.00 1,598,952.43
2 Plesteran 1 SP : 5 PP 41.94 m2 59,596.00 2,499,713.69
3 Acian 41.94 m2 35,175.00 1,475,391.46
IV. Pekerjaan Beton
1 Kolom beton 15x15 cm 1SP : 3PP : 5Kr 0.36 m3 4,823,891.53 1,736,600.95
2 Slof beton 15x20 cm, 1SP : 3PP : 5Kr 0.19 m3 3,820,199.53 733,478.31
3 Balok beton 15x25 cm, 1SP : 2PP : 3Kr 0.26 m3 3,820,199.53 1,002,802.38
4 Ringbalok beton 15x20 cm, 1SP : 3PP : 5Kr 0.19 m3 3,820,199.53 733,478.31
5 Plat beton atap tebal 12 cm, 1SP : 2PP : 3Kr 1.12 m3 4,823,891.53 5,426,530.65
V. Pekerjaan Lantai dan Keramik
1 Rabat lantai 2.52 m3 876,880.00 2,209,737.60
2 Keramik lantai 40x40 cm 2.97 m2 193,585.00 574,947.45
3 Plint keramik 20 cm 5.60 m2 264,530.00 1,481,368.00
VI Pekerjaan Kosen, Pintu dan jendela
1 Kosen alumunium 21.78 m 99,000.00 2,156,220.00
2 Kaca mati bening 5 mm 2.50 m2 151,049.33 377,623.33
3 Daun jendela kaca bening 3 mm profil alumunium 1.10 m2 1,095,278.51 1,204,806.36
4 Daun pintu kaca bening 3 mm profil alumunium 1.70 m2 1,095,278.51 1,861,973.47
5 Engsel 7.00 bh 44,846.00 313,922.00
6 Grendel 3.00 bh 28,796.00 86,388.00
7 Kait angin 4.00 bh 43,096.00 172,384.00
8 Kunci pintu silinder 1.00 unit 406,310.00 406,310.00
VII Pekerjaan Plafond
1 Plafond Gypsum dalam ruangan 9 mm 2.52 m2 51,519.40 129,828.89
3 Shadow line tepi gypsum 6.40 m 20,000.00 128,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN KWANTITAS SATUAN
(Rp.) (Rp.)
2 List plafond 6.40 m 61,660.00 394,624.00
VIII Pekerjaan Elektrikal
1 Pekerjaan instalasi titik kelistrikan 11.00 titik 222,280.00 2,445,080.00
2 Lampu Sorot LED 50 w 2.00 unit 922,200.00 1,844,400.00
3 Lampu 18 w 2.00 bh 72,200.00 144,400.00
4 Lampu 8 w 1.00 bh 47,200.00 47,200.00
5 Saklar tunggal 1.00 bh 78,900.00 78,900.00
6 Saklar ganda 2.00 bh 111,800.00 223,600.00
7 Stop kontak 3.00 bh 135,425.00 406,275.00
IX Pekerjaan Finishing
1 Pengecatan dinding 41.94 m2 35,498.00 1,488,939.47
2 Pengecatan plafond 2.52 m2 35,498.00 89,454.96
JUMLAH SUB B 40,069,414.94
C. PEKERJAAN KANSTEEN DAN PUVING BLOCK
1 Pengecoran kansteen 1SP : 3PP : 5Kr 0.81 m3 4,823,891.53 3,900,116.30
2 Pengecatan kansteen 5.39 m2 57,022.50 307,351.28
3 Urugan pasir dibawah puving block 1.41 m3 292,200.00 411,103.49
4 Pemasangan puving block 10.82 m2 278,550.00 3,014,607.38
JUMLAH SUB C 7,633,178.43
D PERKEJAAN PORTAL DAN PERALATAN PORTAL
I Pemasangan Portal Gate Barrier 2 Unit
1 Pengecoran pondasi 1SP : 3PP : 5Kr 0.32 m3 4,823,891.53 1,543,645.29
2 Pemasangan angkur bout 10" 8.00 bh 118,540.00 948,320.00
3 Pemasangan barrier dan lengan portal 2.00 unit 10,000,000.00 20,000,000.00
4 Instalasi jaringan kabel 2.00 titik 294,000.00 588,000.00
II Pemasangan Kontrol Manless Dispenser 2 Unit
1 Pengecoran pondasi 1SP : 3PP : 5Kr 0.38 m3 4,823,891.53 1,852,374.35
2 Pemasangan angkur bout 10" 8.00 bh 118,540.00 948,320.00
3 Pemasangan manless card dispenser 2.00 unit 4,000,000.00 8,000,000.00
4 Instalasi jaringan kabel 2.00 titik 294,000.00 588,000.00
III Pemasangan Antena Rader dan Lampu Rambu 2 Unit
1 Pengecoran pondasi 1SP : 3PP : 5Kr 0.06 m3 4,823,891.53 308,729.06
2 Pemasangan angkur bout 10" 8.00 bh 118,540.00 948,320.00
3 Pemasangan tiang pipa galv.3" 4.00 m 281,636.67 1,126,546.67
4 Pemasangan antena of the reader 2.00 unit 2,500,000.00 5,000,000.00
5 Pemasangan traffic light lampu ganda 2.00 unit 4,000,000.00 8,000,000.00
6 Instalasi jaringan kabel 4.00 titik 294,000.00 1,176,000.00
IV Pemasangan Kamera Monitoring 2 Unit
1 Pengecoran pondasi 1SP : 3PP : 5Kr 0.06 m3 4,823,891.53 308,729.06
2 Pemasangan angkur bout 10" 8.00 bh 118,540.00 948,320.00
3 Pemasangan tiang pipa Galv.3" 3.40 m 281,636.67 957,564.67
4 Pemasangan kamera monitoring 2.00 unit 1,200,000.00 2,400,000.00
5 Instalasi jaringan kabel kamera monitoring 2.00 unit 294,000.00 588,000.00
V Pekerjaan Sistim Tata Suara dan Komunikasi
1 DVD Player 1.00 unit 1,500,000.00 1,500,000.00
2 Paging Microphone 1.00 unit 1,450,000.00 1,450,000.00
3 Speaker outdor 2.00 unit 4,000,000.00 8,000,000.00
4 Handie Talkie (HT) 2.00 unit 950,000.00 1,900,000.00
VIII Sysistem topolpgical
1 Panel daya listrik systim portal 1.00 unit 7,000,000.00 7,000,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN PEKERJAAN KWANTITAS SATUAN
(Rp.) (Rp.)
2 PC Core I 5 , window 7 original / C560 1.00 unit 5,000,000.00 5,000,000.00
3 External Display 1.00 unit 1,600,000.00 1,600,000.00
4 Software system 1.00 Ls 600,000.00 600,000.00
5 Server system 1.00 unit 12,000,000.00 12,000,000.00
6 Instalasi jaringan kabel server (server dan display) 2.00 titik 294,000.00 588,000.00
7 UPS 1.00 unit 1,800,000.00 1,800,000.00
JUMLAH SUB D 97,668,869.08
E LAIN-LAIN
1 Pengadaan kursi operator 1.00 bh 450,000.00 450,000.00
2 Pengadaan meja operator 1.00 unit 1,500,000.00 1,500,000.00
3 Pengadaan road barier water 2.00 bh 1,200,000.00 2,400,000.00
4 Pengadaan stick cone 4.00 bh 350,000.00 1,400,000.00
5 Pengadaan kerucut Traffic Cone 4.00 bh 350,000.00 1,400,000.00
JUMLAH SUB D 7,150,000.00
JUMLAH SUB TOTAL A S/D E 174,556,096.45
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN : PEMBANGUNAN PORTAL PELABUHAN


LOKASI : MARAPOKOT - KABUPATEN NAGEKEO
TAHUN ANGGARAN : 2020
1 Pembuatan kantor sernentara (m2) (RSNIT-12-2002)
Pekerja oh 1.0000 90,000.00 90,000.00
Mandor oh 0.0500 120,000.00 6,000.00
Kepala Tukang oh 0.3000 110,000.00 33,000.00
Tukang Kayu oh 2.0000 100,000.00 200,000.00
Dolken Kayu Dia. 8 cm btg 1.2500 24,600.00 30,750.00
Kayu kelas III m3 0.1800 3,745,000.00 674,100.00
Besi Strip kg 1.1000 13,000.00 14,300.00
Semen PC kg 35.0000 1,500.00 52,500.00
Pasir pasang m3 0.1500 245,000.00 36,750.00
Pasir beton m3 0.1000 250,000.00 25,000.00
Koral/krikil m3 0.1500 175,000.00 26,250.00
Bata Merah Press Mesin bh 30.0000 2,500.00 75,000.00
Atap Seng Gelombang lbr 0.2500 77,400.00 19,350.00
Jendela Nako + accessories set 0.2000 133,750.00 26,750.00
Kaca Polos tebal 3 mm m2 0.0800 61,525.00 4,922.00
Kunci Tanam bh 0.1500 400,000.00 60,000.00
Plywood (t=4 mm) lbr 0.0600 115,900.00 6,954.00
Harga Satuan Pekerjaan 1,381,626.00

2 Galian tanah biasa sedalam ≤ 1 m (m3) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.5630 90,000.00 50,670.00
Mandor oh 0.0563 120,000.00 6,756.00

Harga Satuan Pekerjaan 57,426.00

3 Timbunan atau urugan tanah kembali (m3) (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 0.3300 90,000.00 29,700.00
Mandor oh 0.0330 120,000.00 3,960.00

Harga Satuan Pekerjaan 33,660.00

4 Urugan sirtu peninggian lantai (m3) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.4000 90,000.00 36,000.00
Mandor oh 0.0400 120,000.00 4,800.00
Sirtu m3 1.2000 210,000.00 252,000.00
Harga Satuan Pekerjaan 292,800.00

5 Mengurug pasir urug (m3) (SNI 2835.2008-11)


Pekerja oh 0.3000 90,000.00 27,000.00
Mandor oh 0.0100 120,000.00 1,200.00
Pasir urug m3 1.2000 220,000.00 264,000.00
Harga Satuan Pekerjaan 292,200.00

Pemasangan batu kosong (anstamping)


6
(m3) (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 0.7800 90,000.00 70,200.00
Tukang batu oh 0.3900 100,000.00 39,000.00
Kepala tukang oh 0.0390 110,000.00 4,290.00
Mandor oh 0.0390 120,000.00 4,680.00
Batu belah m3 1.2000 250,000.00 300,000.00
Pasir urug m3 0.4320 0.00 0.00
Harga Satuan Pekerjaan 418,170.00

7 Pemasangan pondasi batu belah 1SP : 5PP (m3) (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 1.5000 90,000.00 135,000.00
Tukang batu oh 0.7500 100,000.00 75,000.00
Kepala tukang oh 0.0750 110,000.00 8,250.00
Mandor oh 0.0750 120,000.00 9,000.00
Batu belah m3 1.2000 250,000.00 300,000.00
Semen PC kg 136.0000 1,500.00 204,000.00
Pasir pasang m3 0.5440 245,000.00 133,280.00
Harga Satuan Pekerjaan 864,530.00

8 Memasang dinding batako besar pres ukuran (8 x 20 x30) cm, campuran spesi 1 PC : 4 PP (m2)
Pekerja oh 0.3000 90,000.00 27,000.00
Tukang Batu oh 0.1000 100,000.00 10,000.00
Kepala Tukang oh 0.0100 110,000.00 1,100.00
Mandor oh 0.0150 120,000.00 1,800.00
Semen PC kg 9.0000 1,500.00 13,500.00
Batu tela/batako/batu pres m3 11.0000 2,750.00 30,250.00
Pasir pasang bh 0.0320 245,000.00 7,840.00
Harga Satuan Pekerjaan 91,490.00

9 Plesteran 1 SP : 5 PP tebal 15 mm (m2) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.3000 90,000.00 27,000.00
Tukang Batu oh 0.1500 100,000.00 15,000.00
Kepala Tukang oh 0.0150 110,000.00 1,650.00
Mandor oh 0.0150 120,000.00 1,800.00
Semen PC kg 5.1840 1,500.00 7,776.00
Pasir pasang m3 0.0260 245,000.00 6,370.00
Harga Satuan Pekerjaan 59,596.00

10 Acian (m2) (SNI 2837:2008-27)


Pekerja oh 0.2000 90,000.00 18,000.00
Tukang Batu oh 0.1000 100,000.00 10,000.00
Kepala Tukang oh 0.0100 110,000.00 1,100.00
Mandor oh 0.0100 120,000.00 1,200.00
Semen PC kg 3.2500 1,500.00 4,875.00
Harga Satuan Pekerjaan 35,175.00
11 Pemasangan Baut Anker Baja (bh)
Pekerja oh 0.0850 90,000.00 7,650.00
Tukang kayu oh 0.0850 100,000.00 8,500.00
Kepala tukang oh 0.0090 110,000.00 990.00
Mandor oh 0.0050 120,000.00 600.00
Angker Bar 10 mm bh 4.5000 20,000.00 90,000.00
Baut Segala Ukuran bh 0.2700 40,000.00 10,800.00
Harga Satuan Pekerjaan 118,540.00

12 Membuat beton mutu f'c (m3) (PM= 14.5 Mpa, (slump (120 ± 20)mm (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 1.6500 90,000.00 148,500.00
Tukang batu oh 0.2750 100,000.00 27,500.00
Kepala Tukang oh 0.0280 110,000.00 3,080.00
Mandor oh 0.0830 120,000.00 9,960.00
Semen PC kg 326.0000 1,500.00 489,000.00
Pasir beton m3 0.5429 250,000.00 135,714.29
Kerikil (maks 30 mm) m3 0.7097 269,000.00 190,897.24
Harga Satuan Pekerjaan 1,004,651.53

13 Pembesian dengan besi polos atau besi ulir (10 kg) (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 0.0700 90,000.00 6,300.00
Tukang besi oh 0.0700 100,000.00 7,000.00
Kepala Tukang oh 0.0070 110,000.00 770.00
Mandor oh 0.0040 120,000.00 480.00
Besi Beton Polos kg 10.5000 11,000.00 115,500.00
Kawat Beton/Bendrat RRT kg 0.1500 21,000.00 3,150.00
Jumlah (a) 133,200.00
Utk 1 kg = a/10 13,320.00
Harga Satuan Pekerjaan 13,320.00

14 Pemasangan bekisting untuk sloof (m2) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.5200 90,000.00 46,800.00
Tukang kayu oh 0.2600 100,000.00 26,000.00
Kepala Tukang oh 0.0260 110,000.00 2,860.00
Mandor oh 0.0260 120,000.00 3,120.00
Kayu kelas III m3 0.0450 3,745,000.00 168,525.00
Paku 5 cm - 10 cm kg 0.3000 20,000.00 6,000.00
Minyak bekisting kg 0.1000 2,675.00 267.50
Harga Satuan Pekerjaan 253,572.50
15 Pemasangan bekisting untuk kolom (m2) (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 0.6600 90,000.00 59,400.00
Tukang kayu oh 0.3300 100,000.00 33,000.00
Kepala Tukang oh 0.0330 110,000.00 3,630.00
Mandor oh 0.0330 120,000.00 3,960.00
Kayu kelas III m3 0.0400 3,745,000.00 149,800.00
Paku 5 cm - 12 cm kg 0.4000 20,000.00 8,000.00
Minyak bekisting liter 0.2000 2,675.00 535.00
Kayu Balok Kelas II m3 0.0150 7,222,500.00 108,337.50
Plywood tebal 9 mm lbr 0.3500 133,750.00 46,812.50
Dolken kayu f8-10cm –panj 4 m btg 2.0000 24,600.00 49,200.00
Harga Satuan Pekerjaan 462,675.00

16 Beton sloof 15/20 K-175 (m3)


Beton m3 1.0000 1,004,651.53 1,004,651.53
Besi beton kg 120.0000 13,320.00 1,598,400.00
Bekisting m2 4.8000 253,572.50 1,217,148.00
Harga Satuan Pekerjaan 3,820,199.53

17 Beton Kolom K-175 (m3)


Beton m3 1.0000 1,004,651.53 1,004,651.53
Besi beton kg 120.0000 13,320.00 1,598,400.00
Bekisting m2 4.8000 462,675.00 2,220,840.00
Harga Satuan Pekerjaan 4,823,891.53

18 Pemasangan kaca tebal 5 mm (m2) ( AHSP PM.PUPR No.28/PRT/M/2016)


Pekerja oh 0.0150 90,000.00 1,350.00
Tukang kayu oh 0.1500 100,000.00 15,000.00
Kepala tukang oh 0.0150 110,000.00 1,650.00
Mandor oh 0.0008 120,000.00 96.00
Kaca bening tebal 5 mm m3 1.1000 109,200.00 120,120.00
Sealant tube 0.1667 77,000.00 12,833.33
Harga Satuan Pekerjaan 151,049.33

19 Pengadaan 1 m kusen alluminium


(sumber: pek.kusen alumunium AHSP PM.PUPR No.28/PRT/M/2016)
Rangka profil kusen alluminium m 1.1000 90,000.00 99,000.00

Harga Satuan Pekerjaan 99,000.00

20 Memasang 1 m2 pintu kaca rangka alluminium, (sumber: AHSP PM.PUPR No.28/PRT/M/2016)


Pekerja oh 0.0850 90,000.00 7,650.00
Tukang kayu oh 0.0850 100,000.00 8,500.00
Kepala tukang oh 0.0090 110,000.00 990.00
Mandor oh 0.0050 120,000.00 600.00
Rangka alumunium profil kaca m 4.5000 100,000.00 450,000.00
Sealant tube 0.2700 77,000.00 20,790.00
Harga Satuan Pekerjaan 488,530.00

21 Pemasangan 1m2 daun pintu / jendela kaca / daun boven alumunium


Pemasangan kaca tebal 5 mm (m2) m2 3.6000 151,049.33 543,777.60
Pengadaan 1 m kusen alluminium m 1.0000 99,000.00 99,000.00
Memasang 1 m2 pintu kaca rangka alluminium m2 0.9263 488,530.00 452,500.91
Harga Satuan Pekerjaan 1,095,278.51

22 Pemasangan kunci tanam silinder (bh) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.0050 90,000.00 450.00
Tukang kayu oh 0.5000 100,000.00 50,000.00
Kepala tukang oh 0.0500 110,000.00 5,500.00
Mandor oh 0.0030 120,000.00 360.00
Kunci silinder buah 1.0000 350,000.00 350,000.00
Harga Satuan Pekerjaan 406,310.00

23 Pemasangan engsel pintu (bh) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.0150 90,000.00 1,350.00
Tukang kayu oh 0.1500 100,000.00 15,000.00
Kepala tukang oh 0.0150 110,000.00 1,650.00
Mandor oh 0.0008 120,000.00 96.00
Engsel pintu buah 1.0000 26,750.00 26,750.00
Harga Satuan Pekerjaan 44,846.00

24 Pemasangan Grendel Jendela (bh) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.0150 90,000.00 1,350.00
Tukang kayu oh 0.1500 100,000.00 15,000.00
Kepala tukang oh 0.0150 110,000.00 1,650.00
Mandor oh 0.0008 120,000.00 96.00
Grendel jendela buah 1.0000 10,700.00 10,700.00
Harga Satuan Pekerjaan 28,796.00

25 Pemasangan kait angin (bh) (PM PUPR No. 28/PRT/M/2016)


Pekerja oh 0.0150 90,000.00 1,350.00
Tukang kayu oh 0.1500 100,000.00 15,000.00
Kepala tukang oh 0.0150 110,000.00 1,650.00
Mandor oh 0.0008 120,000.00 96.00
Kait angin buah 1.0000 25,000.00 25,000.00
Harga Satuan Pekerjaan 43,096.00

26 Pemasangan Puving Block


Pekerja oh 0.2500 90,000.00 22,500.00
Mandor oh 0.0025 120,000.00 300.00
Kepala Tukang oh 0.0250 110,000.00 2,750.00
Tukang Batu oh 0.5000 100,000.00 50,000.00
Paving Block m2 1.0500 170,000.00 178,500.00
Pasir pasang m3 0.1000 245,000.00 24,500.00
Harga Satuan Pekerjaan 278,550.00
27 Pasang pipa tangga (m)
Pekerja oh 0.1300 90,000.00 11,700.00
Mandor oh 0.0060 120,000.00 720.00
Kepala Tukang oh 0.0050 110,000.00 550.00
Tukang Besi oh 0.2500 100,000.00 25,000.00
Angkur bh 3.0000 9,000.00 27,000.00
Pipa Galvanis Dia. 3" m 1.0000 216,666.67 216,666.67
Harga Satuan Pekerjaan 281,636.67

28 Lantai kerja beton tumbuk 1 Pc : 3 Ps : 5 Kr, tebal 5 cm (m3)


Pekerja oh 1.6500 90,000.00 148,500.00
Mandor oh 0.0800 120,000.00 9,600.00
KepaLa Tukang oh 0.0250 110,000.00 2,750.00
Tukang Batu oh 0.2500 100,000.00 25,000.00
Semen PC kg 218.0000 1,500.00 327,000.00
Agregat Pecah Mesin 20-30 mm m3 0.8700 269,000.00 234,030.00
Pasir beton m3 0.5200 250,000.00 130,000.00
Harga Satuan Pekerjaan 876,880.00

29 Pemasangan lantai keramik ukuran 40 cm x 40 cm (m2) (SNI 7395:2008 No.6.11)


Pekerja oh 0.2500 90,000.00 22,500.00
Tukang Batu oh 0.1250 100,000.00 12,500.00
Kepala Tukang oh 0.0130 110,000.00 1,430.00
Mandor oh 0.0130 120,000.00 1,560.00
Keramik Roman 40 x 40 Golongan D bh 6.6300 19,000.00 125,970.00
Semen PC Kg 9.8000 1,500.00 14,700.00
Pasir pasang M3 0.0450 245,000.00 11,025.00
Semen warna Kg 1.3000 3,000.00 3,900.00
Harga Satuan Pekerjaan 193,585.00

30 Pemasangan dinding keramik ukuran 20 cm x 20 cm (m2) (SNI 7395:2008 No.6.11)


Pekerja oh 0.9000 90,000.00 81,000.00
Tukang Batu oh 0.4500 100,000.00 45,000.00
Kepala Tukang oh 0.0450 110,000.00 4,950.00
Mandor oh 0.0450 120,000.00 5,400.00
Keramik Roman 20 x 20 Golongan D bh 26.5000 3,924.53 104,000.00
Semen PC Kg 9.3000 1,500.00 13,950.00
Pasir pasang M3 0.0180 245,000.00 4,410.00
Semen warna Kg 1.9400 3,000.00 5,820.00
Harga Satuan Pekerjaan 264,530.00

31 Pengadaan 1m shadow line gypsum


Shadow line oh 1.0000 20,000.00 20,000.00
Harga Satuan Pekerjaan 20,000.00
32 Pemasangan langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm (m2)
Pekerja oh 0.1000 90,000.00 9,000.00
Tukang kayu oh 0.0500 100,000.00 5,000.00
Kepala tukang oh 0.0050 110,000.00 550.00
Mandor oh 0.0050 120,000.00 600.00
Gypsum board Lembar 0.3640 90,850.00 33,069.40
Paku Sekrup kg 0.1100 30,000.00 3,300.00
Harga Satuan Pekerjaan 51,519.40

33 Pemasangan list langit-langit kayu profil (m')


Pekerja oh 0.0500 90,000.00 4,500.00
Tukang besi oh 0.0500 100,000.00 5,000.00
Kepala tukang oh 0.0050 110,000.00 550.00
Mandor oh 0.0030 120,000.00 360.00
List gypsum m 1.0500 25,000.00 26,250.00
Paku Sekrup kg 0.0100 30,000.00 25,000.00
Harga Satuan Pekerjaan 61,660.00

34 Pengecatan tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) (m2) (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 0.0200 90,000.00 1,800.00
Tukang cat oh 0.0630 100,000.00 6,300.00
Kepala tukang oh 0.0063 110,000.00 693.00
Mandor oh 0.0030 120,000.00 360.00
Plamur kg 0.1000 12,700.00 1,270.00
Cat dasar kg 0.1000 68,750.00 6,875.00
Cat penutup kg 0.2600 70,000.00 18,200.00
Harga Satuan Pekerjaan 35,498.00

35 Pengecatan bid. kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) (m2) (PM PUPR No. 28/PRT/M/2016)
Pekerja oh 0.0700 90,000.00 6,300.00
Tukang cat oh 0.0090 100,000.00 900.00
Kepala tukang oh 0.0060 110,000.00 660.00
Mandor oh 0.0030 120,000.00 360.00
Cat meni kayu kg 0.2000 50,100.00 10,020.00
Plamur kg 0.1500 12,700.00 1,905.00
Cat dasar kg 0.1700 68,750.00 11,687.50
Cat penutup kg 0.2600 70,000.00 18,200.00
Kuas buah 0.0100 18,000.00 180.00
Pengencer kg 0.0300 41,000.00 1,230.00
Ampelas kg 0.2000 27,900.00 5,580.00
Harga Satuan Pekerjaan 57,022.50

36 Pekerjaan Instalasi Lampu dan Kotak Kontak (titik)


Pekerja oh 0.4800 90,000.00 43,200.00
Tukang Listrik oh 0.0480 100,000.00 4,800.00
Kepala Tukang oh 0.0480 110,000.00 5,280.00
Kabel NYA 3x2.5 mm m 11.0000 9,000.00 99,000.00
Instalasi penerangan ttk 1.0000 70,000.00 70,000.00
Harga Satuan Pekerjaan 222,280.00

37 Pemasangan Stop Kontak (Titik)


Pekerja oh 0.5000 90,000.00 45,000.00
Tukang Listrik oh 0.5000 100,000.00 50,000.00
Kepala Tukang oh 0.0500 110,000.00 5,500.00
Mandor oh 0.0500 120,000.00 6,000.00
Pipa PVC 5/8 (6m) ljr 0.6500 8,500.00 5,525.00
Kabel NYA 2.5 mm m 0.0000 9,000.00 0.00
Stop Kontak bh 1.0000 21,400.00 21,400.00
T dos PVC bh 1.0000 2,000.00 2,000.00
Harga Satuan Pekerjaan 135,425.00

38 Pekerjaan Saklar Ganda (bh)


Pekerja oh 0.2000 90,000.00 18,000.00
Tukang Listrik oh 0.0200 100,000.00 2,000.00
Kepala Tukang oh 0.0200 110,000.00 2,200.00
Saklar ganda bh 1.0000 89,600.00 89,600.00
Harga Satuan Pekerjaan 111,800.00

39 Pekerjaan Saklar Tunggal (bh)


Pekerja oh 0.2000 90,000.00 18,000.00
Tukang Listrik oh 0.0200 100,000.00 2,000.00
Kepala Tukang oh 0.0200 110,000.00 2,200.00
Saklar Tunggal bh 1.0000 56,700.00 56,700.00
Harga Satuan Pekerjaan 78,900.00

40 Pasang Lampu SL 23 Watt + fiting (buah)


Pekerja oh 0.2000 90,000.00 18,000.00
Tukang Listrik oh 0.0200 100,000.00 2,000.00
Kepala Tukang oh 0.0200 110,000.00 2,200.00
Lampu SL 18 Watt + fiting bh 1.0000 50,000.00 50,000.00
Harga Satuan Pekerjaan 72,200.00

41 Pasang Lampu sorot (unit)


Pekerja oh 0.2000 90,000.00 18,000.00
Tukang Listrik oh 0.0200 100,000.00 2,000.00
Kepala Tukang oh 0.0200 110,000.00 2,200.00
Lampu sorot LED 50 w Unit 1.0000 900,000.00 900,000.00
Harga Satuan Pekerjaan 922,200.00

42 Pasang Lampu SL 8 Watt + fiting (buah)


Pekerja oh 0.2000 90,000.00 18,000.00
Tukang Listrik oh 0.0200 100,000.00 2,000.00
Kepala Tukang oh 0.0200 110,000.00 2,200.00
Lampu SL 8 Watt + fiting bh 1.0000 25,000.00 25,000.00
Harga Satuan Pekerjaan 47,200.00

Pemasangan, penyambungan dan instalasi konektor (1 unit) (Permen.Hub PM.78 TAHUN 2014-hal.178-
43
no.6147)
Pekerja oh 1.5000 90,000.00 135,000.00
Tukang listrik oh 0.8500 100,000.00 85,000.00
Mandor oh 0.2000 120,000.00 24,000.00
Alat bantu instalasi listrik oh 1.0000 50,000.00 50,000.00
Harga Satuan Pekerjaan 294,000.00

44 Pengadaan portal Barier (Unit)


Pengadaan portal barier unit 1.0000 10,000,000.00 10,000,000.00

Harga Satuan Pekerjaan 10,000,000.00

45 Pengadaan Antena Of The Reader (Unit)


Pengadaan Antena Of The Reader unit 1.0000 2,500,000.00 2,500,000.00

Harga Satuan Pekerjaan 2,500,000.00

46 Pengadaan Traffic Light Lampu Ganda (Unit)


Pengadaan Traffic Light Lampu Ganda unit 1.0000 4,000,000.00 4,000,000.00

Harga Satuan Pekerjaan 4,000,000.00

47 Pengadaan portal Barier (Unit)


Pengadaan manless tiket box (Unit) unit 1.0000 4,000,000.00 4,000,000.00

Harga Satuan Pekerjaan 4,000,000.00

48 Pengadaan kamera monitoring (Unit)


Pengadaan kamera monitoring (Unit) unit 1.0000 1,200,000.00 1,200,000.00

Harga Satuan Pekerjaan 1,200,000.00

49 Pemasangan trafic light (Unit)


Pemasangan trafic light unit 1.0000 5,100,000.00 5,100,000.00

Harga Satuan Pekerjaan 5,100,000.00

50 Pengadaan DVD Player(Unit)


Pengadaan DVD Player unit 1.0000 1,500,000.00 1,500,000.00

Harga Satuan Pekerjaan 1,500,000.00

51 Paging Microphone (unit)


Pemasangan Paging Microphone unit 1.0000 1,450,000.00 1,450,000.00
Harga Satuan Pekerjaan 1,450,000.00

52 Pemasangan speaker outdor (unit)


Pemasangan speaker outdor unit 1.0000 4,000,000.00 4,000,000.00

Harga Satuan Pekerjaan 4,000,000.00

53 Pengadaan Handie Talkie (HT) (unit)


Pemasangan Handie Talkie (HT) unit 1.0000 950,000.00 950,000.00

Harga Satuan Pekerjaan 950,000.00

54 Pemasangan Panel daya listrik systim portal (unit)


Pemasangan Panel daya listrik systim portal unit 1.0000 7,000,000.00 7,000,000.00

Harga Satuan Pekerjaan 7,000,000.00

55 Pemasangan PC Core I 5 , window 7 original / C560 (unit)


Pemasangan PC Core I 5 , window 7 original / C560 unit 1.0000 5,000,000.00 5,000,000.00

Harga Satuan Pekerjaan 5,000,000.00

56 Pemasangan External Display (unit)


Pemasangan External Display unit 1.0000 1,600,000.00 1,600,000.00

Harga Satuan Pekerjaan 1,600,000.00

57 Pemasangan Server system (unit)


Pemasangan Server system unit 1.0000 12,000,000.00 12,000,000.00

Harga Satuan Pekerjaan 12,000,000.00

58 Pemasangan UPS ICA atau yang setara, kapasitas 1000 Watt (unit)
Pemasangan UPS unit 1.0000 1,800,000.00 1,800,000.00

Harga Satuan Pekerjaan 1,800,000.00

59 Pengadaan kursi operator (unit)


Pengadaan kursi operator unit 1.0000 450,000.00 450,000.00

Harga Satuan Pekerjaan 450,000.00

60 Pengadaan meja operator (unit)


Pengadaan meja operator unit 1.0000 1,500,000.00 1,500,000.00

Harga Satuan Pekerjaan 1,500,000.00

61 Pengadaan road barier water (unit)


Pengadaan road barier water unit 1.0000 1,200,000.00 1,200,000.00
Harga Satuan Pekerjaan 1,200,000.00

62 Pengadaan stick cone (unit)


Pengadaan stick cone unit 1.0000 350,000.00 350,000.00

Harga Satuan Pekerjaan 350,000.00

63 Pengadaan kerucut Traffic Cone (unit)


Pengadaan kerucut Traffic Cone unit 1.0000 350,000.00 350,000.00

Harga Satuan Pekerjaan 350,000.00


DAFTAR HARGA SATUAN UPAH, ALAT DAN BAHAN

PEKERJAAN : BALAI PERHUBUNGAN TRANSPORTASI DARAT WIAYAH XIII PROVINSI NTT


LOKASI : PEMBANGUNAN PORTAL PELABUHAN
TAHUN ANGGARAN : MARAPOKOT - KABUPATEN NAGEKEO

Harga Dasar
No. Upah, Alat dan Bahan Satuan
(Rp.)
A. TENAGA KERJA
1 Pekerja oh 90,000.00
2 Tukang oh 100,000.00
3 Kepala Tukang oh 110,000.00
4 Mandor oh 120,000.00
5 Tukang Batu oh 100,000.00
6 Tukang Besi oh 100,000.00
7 Tukang Cat oh 100,000.00
8 Tukang Kayu oh 100,000.00
9 Tukang Listrik oh 100,000.00

D. BAHAN / MATERIAL
SEMEN
1 Semen Pc kg 1,500.00
2 Semen warna kg 3,000.00
AGGREGAT
1 Agregat Kasar m3 269,000.00
2 Agregat 0.5 mm m3 269,000.00
3 Agregat Pecah Mesin 20-30 mm m5 269,000.00
4 Bata Merah Press Mesin bh 2,500.00
5 Batu belah m3 250,000.00
6 Batu tela/batako/batu pres bh 2,750.00
7 Kerikil (maks 30 mm) m3 269,000.00
8 Koral/krikil m3 175,000.00
9 Pasir beton m3 250,000.00
10 Pasir pasang m3 245,000.00
11 Pasir urug m3 220,000.00
12 Paving block m2 170,000.00
13 Sirtu m3 210,000.00
14 Besi beton kg 11,000.00
15 Besi Beton Polos kg 11,000.00
16 Besi Strip kg 13,000.00
17 Rangka profil kusen alluminium m 90,000.00
18 Rangka alumunium profil kaca m 100,000.00
PAKU-KAWAT-BAUT-MUR-ANGKUR
1 Paku 5 cm - 10 cm kg 20,000.00
Harga Dasar
No. Upah, Alat dan Bahan Satuan
(Rp.)
2 Paku 5 cm - 12 cm kg 20,000.00
3 Paku Sekrup kg 30,000.00
4 Kawat Beton/Bendrat RRT kg 21,000.00
5 Angkur bh 9,000.00
6 Angker Bar 10 mm bh 20,000.00
7 Baut Segala Ukuran kg 40,000.00
PIPA
1 Pipa Galvanis Dia. 3" m' 216,666.67
2 Pipa PVC 5/8 (6m) Ljr 8,500.00
KAYU
1 Dolken Kayu Dia. 8 cm btg 24,600.00
2 Kayu Balok Kelas II m3 7,222,500.00
3 Kayu kelas III m3 3,745,000.00
4 Plywood (t=4 mm) lbr 115,900.00
5 Plywood tebal 9 mm lbr 133,750.00
6 Minyak bekisting ltr 2,675.00
7 Thinner ltr 41,000.00
CAT-PLASTIK
1 Cat Dasar kg 68,750.00
2 Cat meni kayu kg 50,100.00
3 Cat Tembok kg 70,000.00
4 Kuas bh 18,000.00
5 Lem Pipa PVC kg 27,900.00
6 Plamur kg 12,700.00
ATAP DAN PLAFOND
1 Atap Seng Gelombang lbr 77,400.00
2 List Gypsum m' 25,000.00
3 Shadow line m 20,000.00
4 Gypsum Board lbr 90,850.00
Harga Dasar
No. Upah, Alat dan Bahan Satuan
(Rp.)
PINTU, JENDELA, KACA
1 Kunci Tanam Antik bh
2 Kunci Tanam bh 400,000.00
3 Kunci Silinder bh 350,000.00
4 Engsel Pintu bh 26,750.00
5 Hak Angin bh 35,600.00
6 Kait Angin bh 25,000.00
7 Grendel Jendela bh 10,700.00
8 Kaca bening tebal 5 mm m2 109,200.00
9 Kaca Polos tebal 3 mm m2 61,525.00
10 Jendela Nako + accessories set 133,750.00
11 Sealant kg 77,000.00
Harga Dasar
No. Upah, Alat dan Bahan Satuan
(Rp.)
LANTAI
1 Keramik Roman 40 x 40 Golongan D bh 19,000.00
2 Keramik Roman 20 x 20 Golongan D bh 3,924.53
LISTRIK
1 Alat bantu instalasi listrik Ls 50,000.00
2 Instalasi penerangan m' 70,000.00
3 Kabel NYA 2.5 mm m' 9,000.00
4 Lampu SL 8 Watt + fiting bh 25,000.00
5 Lampu SL 18 Watt + fiting bh 50,000.00
6 Lampu Sorot LED 50 w unit 900,000.00
7 Saklar ganda bh 89,600.00
8 Saklar tunggal bh 56,700.00
9 Stop Kontak bh 21,400.00
10 T dos PVC bh 2,000.00
LAIN-LAIN
1 Pemasangan kaca tebal 5 mm (m2) m2 151,049.33
2 Pengadaan 1 m kusen alluminium m 99,000.00
3 Memasang 1 m2 pintu kaca rangka alluminium m2 488,530.00
4 Pengadaan portal barier unit 10,000,000.00
5 Pengadaan manless tiket box (Unit) unit 4,000,000.00
6 Pengadaan Antena Of The Reader unit 2,500,000.00
7 Pengadaan Traffic Light Lampu Ganda unit 4,000,000.00
8 Pengadaan kamera monitoring (Unit) unit 1,200,000.00
9 Pemasangan trafic light unit 5,100,000.00
10 Pengadaan DVD Player unit 1,500,000.00
11 Pemasangan Paging Microphone unit 1,450,000.00
12 Pemasangan speaker outdor unit 4,000,000.00
13 Pemasangan Handie Talkie (HT) unit 950,000.00
14 Pemasangan Panel daya listrik systim portal unit 7,000,000.00
15 Pemasangan PC Core I 5 , window 7 original / C560 unit 5,000,000.00
16 Pemasangan External Display unit 1,600,000.00
17 Pemasangan Server system unit 12,000,000.00
18 Pemasangan UPS unit 1,800,000.00
19 Pengadaan kursi operator unit 450,000.00
20 Pengadaan meja operator unit 1,500,000.00
21 Pengadaan road barier water unit 1,200,000.00
22 Pengadaan stick cone unit 350,000.00
23 Pengadaan kerucut Traffic Cone unit 350,000.00