LANTAI / KERAMIK
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Cor Beton tumbuk 1:3:5 (F'c =16,9 Mpa K 200)
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Zak 7.0400 76,000.00 535,040.00
2 Pasir Pasang M3 0.5221 150,000.00 78,321.43
3 Batu Kerikil M3 0.7637 180,000.00 137,466.67
B. UPAH
1 Mandor OH 0.0800 -
2 Kepala Tukang OH 0.0250 150,000.00 3,750.00
3 Tukang Batu OH 0.2500 125,000.00 31,250.00
4 Pekerja OH 1.6500 100,000.00 165,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Lantai Keramik 40 x 40
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Keramik 40 x 40 cm Dos 1.0000 - -
2 Semen @50 Kg Zak 0.2276 - -
3 Pasir Pasang M3 0.0420 150,000.00 6,300.00
4 Semen Warna (grout) Zak 0.0375 - -
B. UPAH
1 Mandor OH 0.0300 -
2 Kepala Tukang OH 0.0350 150,000.00 5,250.00
3 Tukang Batu OH 0.3500 125,000.00 43,750.00
4 Pekerja OH 0.6200 100,000.00 62,000.00
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Keramik 20 x 20 cm Dos 1.0000 - -
2 Semen @50 Kg Zak 0.2080 - -
3 Pasir Pasang M3 0.0450 150,000.00 6,750.00
4 Semen Warna (grout) Zak 0.0375 - -
B. UPAH
1 Mandor OH 0.0350 -
2 Kepala Tukang OH 0.0350 150,000.00 5,250.00
3 Tukang Batu OH 0.3500 125,000.00 43,750.00
4 Pekerja OH 0.7000 100,000.00 70,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Dinding Keramik 20 X 25
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Keramik 20 x 25 cm Dos 1.0000 - -
2 Semen @50 Kg Zak 0.1860 - -
3 Pasir Pasang M3 0.0180 150,000.00 2,700.00
4 Semen Warna (grout) Zak 0.0375 - -
B. UPAH
1 Mandor OH 0.0450 -
2 Kepala Tukang OH 0.0450 150,000.00 6,750.00
3 Tukang Batu OH 0.4500 125,000.00 56,250.00
4 Pekerja OH 0.9000 100,000.00 90,000.00
A PEKERJAAN PERSIAPAN
1 Pek. Papan Proyek 1.00 Bh 250,000 250,000
2 Pembongkaran Sebagian atap, dinding Plafon, Teras dan Paving 1.00 Ls 25,000,000 25,000,000
B BIAYA PENYELENGGARAAN K3
1 Penyiapan RKK 0
-Dokumen RKK 1.00 Set 200,000 200,000
2 Sosialisasi, Promosi dan Pelatihan 0
-Papan Infomasi K3 1.00 Bh 100,000 100,000
3 Alat Pelindung kerja dan alat pelindung diri 0
-Topi Pelinding (safety Helmet) 10.00 Bh 75,000 750,000
-Pelindung pernafasan dan mulut (masker) 3.00 Dos 50,000 150,000
-Sarung tangan (safety gloves) 10.00 Bh 75,000 750,000
-Sepatu keselamatan 10.00 Bh 75,000 750,000
-Rompi Keselamtan 10.00 Bh 75,000 750,000
-Peralatan P3K 1.00 75,000 75,000
4 Rambu rambu yang diperlukan 0
-Rambu Peringatan 1.00 Bh 400,000 400,000
-Rambu Pekerjaan Sementara 1.00 Bh 400,000 400,000
C PEKERJAAN TANAH
1 Pek. Pemasangan Bowplank 24 M1 28,408 681,780
2 Pek. Galian Tanah Pondasi Batu Kali 27.48 M3 87,038 2,391,791
3 Pek. Galian Tanah Pondasi Telapak 16.88 M3 87,038 1,469,193
4 Timbunan Tanah Dalam Bangunan 29.40 M3 98,615 2,899,281
5 Timbunan Tanah Kembali 14.79 M3 44,000 650,760
D PEKERJAAN PONDASI 0
1 Urugan Pasir Bawah Pondasi 1.32 M3 198,000 261,360
2 Urugan Pasir dibawah Pondasi Telapak 0.50 M3 198,000 99,000
3 Pas. Timbrisan Batu Kosong 5.28 M3 478,830 2,528,222
4 Pek. Pondasi Batu Kali Sp. 1:4 15.60 M3 877,982 13,696,519
E PEKERJAAN BETON 0
1 Pondasi Telapak (PT) 80x80 cm Tbl. 25 cm Sp. 1 Pc : 2 Psr : 3 Krl 0
- Cor Lantai Kerja T=5 Cm 0.50 M3 785,297 392,648
- Pembesian Terpasang 261.79 Kg 12,860 3,366,619
- Bekisting Pondasi Terpasang 2x Pakai 3.30 M2 240,669 794,208
- Beton Sp.1 Pc : 2 :Psr:3 Krl 1.24 M3 1,083,959 1,344,109
0
2 Sloop 20 x 25 0
- Pembesian Terpasang 356.12 Kg 14,860 5,291,943
- Bekisting Sloop Terpasang 2x Pakai 21.88 M2 240,669 5,265,838
- Beton Sp.1 Pc : 2 :Psr:3 Krl 2.19 M3 1,083,959 2,373,871
0
3 Kolom Struktur (KS) 25 x 25 0
- Pembesian Terpasang 627.50 Kg 14,860 9,324,650
- Bekisting Kolom Terpasang 2x Pakai 32.10 M2 216,550 6,951,255
- Beton Sp.1 Pc : 2 :Psr:3 Krl 4.01 M3 1,083,959 4,346,677
0
4 Kolom Praktis (KP) 12x12 0
- Pembesian Terpasang 47.93 Kg 14,860 712,240
- Bekisting Kolom Praktis Terpasang 2x Pakai 1.70 M2 216,550 368,135
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.11 M3 1,083,959 119,236
0
5 Balok Latey (LT) 12x12 , Sp.1 Pc : 2 :Psr:3 Krl 0
- Pembesian Terpasang 158.83 Kg 13,350 2,120,381
- Bekisting Balok latey Terpasang 2x Pakai 7.86 M2 216,550 1,702,083
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.47 M3 1,083,959 509,461
0
6 Ring Balok 20 x 40 0
- Pembesian Terpasang 157.64 Kg 14,860 2,342,530
- Bekisting Balok Terpasang 2x Pakai 8.80 M2 216,550 1,905,640
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.66 M3 1,083,959 715,413
0
7 Plat Dak Tbl =12 cm 0
- Pembesian Terpasang 249.74 Kg 12,860 3,211,656
- Bekisting Plat Terpasang 2x Pakai 10.22 M2 216,550 2,213,141
- Beton Sp.1 Pc : 2 :Psr:3 Krl 1.23 M3 1,083,959 1,333,270
0
8 Ring Balok 15 x 30 0
- Pembesian Terpasang 365.30 Kg 12,860 4,697,758
- Bekisting Balok Terpasang 2x Pakai 10.90 M2 216,550 2,360,395
- Beton Sp.1 Pc : 2 :Psr:3 Krl 1.64 M3 1,083,959 1,777,693
0
9 Ring Balok Sopi Sopi 12 : 20 0
- Pembesian Terpasang 116.78 Kg 12,860 1,501,791
- Bekisting Balok Terpasang 2x Pakai 7.50 M2 216,550 1,624,125
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.46 M3 1,083,959 498,621
F PEKERJAAN PASANGAN, PLESTERAN DAN ACIAN 0
1 Pas. Dinding 1/2 Bata 12 Sp 1:4 147.54 M2 128,993.10 19,031,642
2 Plesteran Dinding Sp 1:4 Tebal 15 mm 295.08 M2 42,795.15 12,627,992
3 Plesteran Beton Sp 1:4 Tebal 15 mm 61.70 M2 42,795.15 2,640,461
4 Plesteran Pondasi Sp 1:4 Tebal 15 mm 10.50 M2 42,795.15 449,349
5 Acian Dinding dan Beton 367.30 M2 35,606.08 13,078,112
G PEKERJAAN PEMINDAHAN KUSEN, JENDELA & VENTILASI DIPASANG KEMBALI 0
1 Pemindahan dan Pemasangan kembali Pintu Existing 1.00 Unit 500,000 500,000
2 Pemindahan dan Pemasangan kembali Jendela Existing 2.00 Unit 500,000 1,000,000
3 Pemindahan dan Pemasangan kembali VentilasiExisting 2.00 Unit 500,000 1,000,000
H PEKERJAAN KUSEN PINTU JENDELA VENTILASI 0
1 Kusen Aluminium 4" 67.88 M1 181,056 12,290,091
2 Bingkai Jendela Aluminium Silver 9.48 M1 181,056 1,716,412
3 Kaca 5mm Jendela dan Ventilasi 14.19 M2 180,000 2,554,200
4 Engsel 3" 6.00 Psg 15,000 90,000
5 kait Angin 3.00 Bh 15,000 45,000
6 Grendel Jendela 3.00 Bh 15,000 45,000
I PEKERJAAN ATAP 0
1 Pas. Baja Ringan Kuda Kuda Double Canal 75.75.5 + Reng 45.45.5 241.90 M2 297,840 72,047,526
2 Pekerjaan Penutup Atap Spandex T = 0,30 mm 241.90 M2 100,661 24,349,896
3 Pekerjaan Bubungan Atap Spandex T = 0,30 mm 14.40 M1 43,990 633,456
4 Pek. Listplank GRC (Lebar =30 cm, Tebal = 9 mm 54.00 M1 60,489 3,266,406
J PEKERJAAN LANGIT LANGIT 0
1 Pek. Rangka Plafond Hollow Galvalum 4x4 189.57 M2 55,000 10,426,350
2 Plafond GRC Tebal 3 mm 189.57 M2 51,590 9,779,916
3 Pek. List Kayu SP 4 cm 145.70 M1 33,908 4,940,323
K PEKERJAAN PENGECETAN 0
1 Pek. Cat Dinding Setara Metrolite/Envie 367.35 M2 24,236 8,903,003
2 Pek. Cat Plafond Setara Metrolite/Envie 189.57 M2 24,236 4,594,371
3 Pek. Cat Listplank 16.07 M2 24,236 389,469
4 Pek. Cat Sika 107 Plat Dak 15.76 M2 40,000 630,520
L PEK. INSTALASI LISTRIK DAN PENERANGAN 0
1 Philips LED DN027B GEN2 22 W 22 Watt Downlight Panel 8 Inch 4.00 Set 315,000 1,260,000
2 Philips LED Panel 60x60 RC091V GM G2 MR PCV 29 W - 4000K, Accous 6.00 Set 1,250,000 7,500,000
3 Sakelar Tunggal (Inbow) Brocco/Panasonic 1.00 Bh 24,000 24,000
4 Sakelar Ganda (Inbow) Brocco/Panasonic 4.00 Bh 35,000 140,000
5 Stok Kontak Dinding 2 Lubang (Inbow) Brocco/Panasonic 3.00 Bh 35,000 105,000
6 Jasa Pasang Instalasi Kontak 9.00 Titik 75,000 675,000
M PEKERJAAN LANTAI 0
1 Urugan Pasir dibawah Lantai, T = 5 cm 7.35 M3 198,000 1,455,300
2 Cor Beton Sp 1:3:5 Untuk Lantai Bangunan , T = 7 cm 10.29 M3 785,297 8,080,703
3 Pek. Penyambungan Keramik 40x40 147.80 M2 141,181 20,866,493
4 Plint Keramik Uk. 10 x 40 46.05 M1 43,261 1,992,171
N PEKERJAAN AKHIR 0
1 Administrasi Dan Dokumentasi 1.00 Ls 750,000 750,000
2 Pembersihan Akhir dan Penataan Paving Eksisting 1.00 Ls 3,000,000 3,000,000
TOTAL Rp 417,689,065
Harga Satuan Upah
Kota *****
Tahun 2022
NAMA TOKO :
ALAMAT :
150
ANALISA HARGA SATUAN PEKERJAAN TANAH
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pekerjaan pembuatan 1 m3 Bowplank
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
Kayu Balok 5/7 M³ 0.0120
Paku 2"-3" Kg 0.0200
Kayu papan 3/20 M³ 0.0070
Sub Total A -
B. Tenaga Kerja
1 Pekerja OH 0.1000 100,000.00 10,000.00
2 Tukang Kayu OH 0.1000 135,000.00 13,500.00
3 Kepala Tukang OH 0.0100 150,000.00 1,500.00
4 Mandor OH 0.0050 165,000.00 825.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Galian Tanah Keras Untuk Pondasi Sedalam 1 m
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
Sub Total A -
B. UPAH
1 Pekerja OH 0.7500 100,000.00 75,000.00
2 Mandor OH 0.0250 165,000.00 4,125.00
SATUAN KERJA : 0
ANALISA HARGA SATUAN PEKERJAAN TANAH
PEKERJAAN : 0
JENIS PEKERJAAN : Urugan Tanah Kembali
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
Sub Total A -
B. UPAH
1 Mandor OH 0.0400 165,000.00
2 Pekerja OH 0.4000 100,000.00 40,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Urugan Pasir
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Pasir Urug M3 1.2000 125,000.00 150,000.00
B. UPAH
1 Mandor OH 0.0100
2 Pekerja OH 0.3000 100,000.00 30,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Timbunan Tanah Pilihan
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Tanah Timbunan M3 1.2000 65,000.00 78,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Aanstamping Batu Kali / Belah
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Batu Kali Belah (15/20 cm) M3 1.2000 195,000.00 234,000.00
2 Pasir Urug M3 0.4320 150,000.00 64,800.00
B. UPAH
1 Mandor OH 0.0390 165,000.00
2 Kepala Tukang OH 0.0390 150,000.00 5,850.00
3 Tukang Batu OH 0.3900 135,000.00 52,650.00
4 Pekerja OH 0.7800 100,000.00 78,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pasangan Batu kali 1 : 4
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Kg 163.0000 1,520.00 247,760.00
2 Pasir Pasang M3 0.5200 130,000.00 67,600.00
3 Batu Kali Belah (15/20 cm) M3 1.2000 185,000.00 222,000.00
B. UPAH
1 Mandor OH 0.0750 165,000.00
2 Kepala Tukang OH 0.0750 150,000.00 11,250.00
3 Tukang Batu OH 0.7500 135,000.00 101,250.00
4 Pekerja OH 1.5000 100,000.00 150,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pasangan Batu kali 1 : 5
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Zak 2.7200 76,000.00 206,720.00
2 Pasir Pasang M3 0.5200 150,000.00 78,000.00
3 Batu Kali Belah (15/20 cm) M3 1.2000 195,000.00 234,000.00
B. UPAH
1 Mandor OH 0.0750
2 Kepala Tukang OH 0.0750 150,000.00 11,250.00
3 Tukang Batu OH 0.7500 135,000.00 101,250.00
4 Pekerja OH 1.5000 100,000.00 150,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Cor Beton K 100 (Lantai Kerja)
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Kg 227 1,520.00 345,040.00
2 Pasir Pasang M3 0.64 130,000.00 83,681.48
3 Batu Kerikil M3 0.769 150,000.00 115,384.62
B. UPAH
1 Mandor OH 0.1200 165,000.00 19,800.00
2 Kepala Tukang OH 0.0200 150,000.00 3,000.00
3 Tukang Batu OH 0.2000 135,000.00 27,000.00
4 Pekerja OH 1.2000 100,000.00 120,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Beton K 225
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Kg 371 1,520.00 563,920.00
2 Pasir Pasang M3 0.517 130,000.00 67,214.81
3 Batu Kerikil M3 0.805 150,000.00 120,807.69
B. UPAH
1 Mandor OH 0.1650 165,000.00 27,225.00
2 Kepala Tukang OH 0.0275 150,000.00 4,125.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pekerjaan Pembesian 10 Kg
SATUAN : Kg
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Besi Beton Dia. 12 Kg 1.0500 13,523.20 14,199.36
2 Kawat Beton Kg 0.0150 30,000.00 450.00
B. UPAH
1 Mandor OH 0.0004 -
2 Kepala Tukang OH 0.0007 150,000.00 105.00
3 Tukang Besi OH 0.0070 135,000.00 945.00
4 Pekerja OH 0.0070 100,000.00 700.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pekerjaan Pembesian 10 Kg
SATUAN : Kg
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Besi Beton Dia. 6 Kg 1.0500 13,147.55 13,804.93
2 Kawat Beton Kg 0.0150 -
B. UPAH
1 Mandor OH 0.0004 -
2 Kepala Tukang OH 0.0007 -
3 Tukang Besi OH 0.0070 -
4 Pekerja OH 0.0070 -
ANALISA HARGA SATUAN PEK. BETON
Sub Total B -
C. Jumlah Harga Satuan ( A + B ) 13,804.93
D. Overhead, Profit, dan Biaya K3 (15%)
E. Harga Satuan Pekerjaan (C+D) 13,804.93
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Memasang Bekisting Untuk Pondasi Telapak
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Kls III M3 0.0400 2,900,000.00 116,000.00
2 Paku Campuran Kg 0.3000 25,000.00 7,500.00
3 Minyak Bekisting Lt 0.1000 -
B. UPAH
1 Pekerja OH 0.52 100,000.00 52,000.00
2 Tukang Kayu OH 0.26 135,000.00 35,100.00
3 Kepala Tukang OH 0.026 150,000.00 3,900.00
4 Mandor OH 0.026 165,000.00 4,290.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Memasang Bekisting Untuk Sloof
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Terentang Kls III M3 0.0450 2,900,000.00 130,500.00
2 Paku Campuran Kg 0.3000 - -
3 Minyak Bekisting Lt 0.1000 -
B. UPAH
1 Mandor OH 0.0260 -
2 Kepala Tukang OH 0.0260 - -
3 Tukang Kayu OH 0.2600 165,000.00 42,900.00
4 Pekerja OH 0.5200 150,000.00 78,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Memasang Bekisting Untuk Sloof
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Terentang Kls III M3 0.0450 2,900,000.00 130,500.00
2 Paku Campuran Kg 0.3000 - -
3 Minyak Bekisting Lt 0.1000 -
B. UPAH
1 Mandor OH 0.0260 -
2 Kepala Tukang OH 0.0260 - -
3 Tukang Kayu OH 0.2600 165,000.00 42,900.00
4 Pekerja OH 0.5200 150,000.00 78,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Memasang Bekisting Untuk Sloof
SATUAN : M2
ANALISA HARGA SATUAN PEK. BETON
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Terentang Kls III M3 0.0450 2,900,000.00 130,500.00
2 Paku Campuran Kg 0.3000 22,500.00 6,750.00
3 Minyak Bekisting Lt 0.1000 -
B. UPAH
1 Mandor OH 0.0260 -
2 Kepala Tukang OH 0.0260 150,000.00 3,900.00
3 Tukang Kayu OH 0.2600 135,000.00 35,100.00
4 Pekerja OH 0.5200 100,000.00 52,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pas. Bata Merah ½ Bata sp. 1 : 4 (1 m2)
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Batu Bata Bh 70 700.00 49,000.00
2 Semen @50 Kg Kg 11.5 1,520.00 17,480.00
3 Pasir Pasang M3 0.043 130,000.00 5,590.00
B. UPAH
1 Pekerja OH 0.3 100,000.00 30,000.00
2 Tukang batu OH 0.1 135,000.00 13,500.00
3 Kepala Tukang OH 0.01 150,000.00 1,500.00
4 Mandor OH 0.015 165,000.00 2,475.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pas. Bata Merah ½ Bata sp. 1 : 5 (1 m2)
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Batu Bata Bh 70 700.00 49,000.00
2 Semen @50 Kg Kg 9.68 1,520.00 14,713.60
3 Pasir Pasang M3 0.045 130,000.00 5,850.00
B. UPAH
1 Pekerja OH 0.3 100,000.00 30,000.00
2 Tukang batu OH 0.1 135,000.00 13,500.00
3 Kepala Tukang OH 0.01 150,000.00 1,500.00
4 Mandor OH 0.015 165,000.00 2,475.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Plesteran sp. 1 : 5
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Kg 5.184 1,520.00 7,879.68
2 Pasir Pasang M3 0.026 130,000.00 3,380.00
B. UPAH
1 Pekerja OH 0.15 100,000.00 15,000.00
2 Tukang batu OH 0.075 135,000.00 10,125.00
3 Kepala Tukang OH 0.008 150,000.00 1,200.00
4 Mandor OH 0.008 165,000.00 1,320.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Acian
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Kg 3.108 1,520.00 4,724.16
B. UPAH
1 Pekerja OH 0.15 100,000.00 15,000.00
2 Tukang batu OH 0.075 135,000.00 10,125.00
3 Kepala Tukang OH 0.008 150,000.00 1,200.00
4 Mandor OH 0.008 165,000.00 1,320.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Kusen Aluminium
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Profil aluminium 4 inch m 1.1 135,000.00 148,500.00
2 Skrup fixer buah 2 1,000.00 2,000.00
Sealant Tube 0.06 50,000.00 3,000.00
B. UPAH
1 Pekerja OH 0.043 100,000.00 4,300.00
2 Tukang Alumunium OH 0.043 135,000.00 5,805.00
3 Kepala Tukang OH 0.0043 150,000.00 645.00
4 Mandor OH 0.0021 165,000.00 346.50
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Kusen Pintu, Jendela dan Ventilasi Kayu Klas II
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Klas II M3 1.1000 5,100,000.00 5,610,000.00
2 Paku 10 Cm Kg 1.2500 22,500.00 28,125.00
B. UPAH
1 Mandor OH 0.3500 -
2 Kepala Tukang OH 2.1000 150,000.00 315,000.00
3 Tukang Kayu OH 21.0000 125,000.00 2,625,000.00
4 Pekerja OH 7.0000 100,000.00 700,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Daun Pintu Panel Kayu Klas II
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Klas II, Papan M3 0.0400 5,100,000.00 204,000.00
B. UPAH
1 Mandor OH 0.0500 -
2 Kepala Tukang OH 0.3000 150,000.00 45,000.00
3 Tukang Kayu OH 3.0000 125,000.00 375,000.00
4 Pekerja OH 1.0000 100,000.00 100,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Daun Jendela Panel Kaca Kayu Klas II
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Klas II, Papan M3 0.0140 5,100,000.00 71,400.00
2 Kaca Bening 3 mm M2 0.8200 95,000.00 77,900.00
B. UPAH
1 Mandor OH 0.0400 -
2 Kepala Tukang OH 0.2000 150,000.00 30,000.00
3 Tukang Kayu OH 2.0000 125,000.00 250,000.00
4 Pekerja OH 0.8000 100,000.00 80,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pasangan 1 Bh Kunci 2 Slaag
SATUAN : Bh
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kunci 2 Slaag Bh 1.0000 125,000.00 125,000.00
B. UPAH
1 Mandor OH 0.0050 -
2 Kepala Tukang OH 0.0100 150,000.00 1,500.00
3 Tukang Kayu OH 0.5000 125,000.00
4 Pekerja OH 0.0100 100,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pasangan 1 Bh Engsel Pintu 4"
SATUAN : Bh
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Engsel Pintu 4" Bh 1.0000 25,000.00 25,000.00
B. UPAH
1 Mandor OH 0.0010 -
2 Kepala Tukang OH 0.0150 150,000.00 2,250.00
3 Tukang Kayu OH 0.1500 125,000.00
4 Pekerja OH 0.0150 100,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pasangan 1 Bh Engsel Jendela 3"
SATUAN : Bh
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Engsel Jendela 3" Bh 1.0000 20,000.00 20,000.00
B. UPAH
1 Mandor OH 0.0010 -
2 Kepala Tukang OH 0.0100 150,000.00 1,500.00
3 Tukang Kayu OH 0.1000 125,000.00
4 Pekerja OH 0.0100 100,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pasangan 1 Bh Grendel
SATUAN : Bh
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
ANALISA HARGA SATUAN PEK. KAYU / KUSEN
1 Grendel Bh 1.0000 10,000.00 10,000.00
B. UPAH
1 Mandor OH 0.0010 -
2 Kepala Tukang OH 0.0150 150,000.00 2,250.00
3 Tukang Kayu OH 0.1500 125,000.00
4 Pekerja OH 0.0150 100,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pasangan 1 Bh Kait Angin Kuningan
SATUAN : Bh
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kait Angin Kuningan Bh 1.0000 10,000.00 10,000.00
B. UPAH
1 Mandor OH 0.0010 -
2 Kepala Tukang OH 0.0150 150,000.00 2,250.00
3 Tukang Kayu OH 0.1500 125,000.00
4 Pekerja OH 0.0150 100,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pekerjaan rangka Atap Baja Ringan c75
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Baja Ringan C 75 Btg 0.873 115,000.00 69,718.75
B. UPAH
1 Pekerja OH 0.734 100,000.00 73,400.00
2 Tukang besi OH 0.734 135,000.00 99,090.00
3 Kepala Tukang OH 0.073 150,000.00 10,950.00
4 Mandor OH 0.037 165,000.00 6,105.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Gording 5/5
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Kelapa M3 1.1000 2,050,000.00 2,255,000.00
2 Paku Campuran Kg 3.0000 - -
B. UPAH
1 Mandor OH 0.012 -
2 Kepala Tukang OH 0.08 150,000.00 12,000.00
3 Tukang Kayu OH 0.08 125,000.00 10,000.00
4 Pekerja OH 0.25 100,000.00 25,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pemasangan Atap Seng Gelombang BJLS
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Seng Gelombang BJLS Lbr 0.8500 - -
2 Paku Seng Kg 0.1000 - -
Sub Total A -
B. UPAH
1 Mandor OH -
2 Kepala Tukang OH - -
3 Tukang Kayu OH 0.200 - -
4 Pekerja OH 0.100 - -
Sub Total B -
C. Jumlah Harga Satuan ( A + B ) -
D. Overhead, Profit, dan Biaya K3 (15%)
E. Harga Satuan Pekerjaan (C+D) -
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pemasangan Bubungan Seng
SATUAN : M
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
ANALISA HARGA SATUAN PEK ATAP
A. BAHAN
1 Seng Plat Lbr 0.6500 - -
2 Paku Seng Kg 0.0500 - -
Sub Total A -
B. UPAH
1 Mandor OH -
2 Kepala Tukang OH - -
3 Tukang Kayu OH 0.250 - -
4 Pekerja OH 0.250 - -
Sub Total B -
C. Jumlah Harga Satuan ( A + B ) -
D. Overhead, Profit, dan Biaya K3 (15%)
E. Harga Satuan Pekerjaan (C+D) -
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pemasangan Atap SPandex
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Seng Spandex Pasir M2 0.4440 80,000.00 35,520.00
2 Paku Seng Kg 0.2000 25,000.00 5,000.00
B. UPAH
1 Pekerja OH 0.125 100,000.00 12,500.00
2 Tukang Kayu OH 0.25 135,000.00 33,750.00
3 Kepala Tukang OH 0.025 150,000.00 3,750.00
4 Mandor OH 0.006 165,000.00 990.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pemasangan Bubungan Seng
SATUAN : M
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Seng Plat Lbr 0.6500 25,000.00 16,250.00
2 Paku Seng Kg 0.0500 25,000.00 1,250.00
B. UPAH
ANALISA HARGA SATUAN PEK ATAP
1 Pekerja OH 0.15 100,000.00 15,000.00
2 Tukang Kayu OH 0.07 135,000.00 9,450.00
3 Kepala Tukang OH 0.007 150,000.00 1,050.00
4 Mandor OH 0.006 165,000.00 990.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pek. Listplank GRC (Lebar =30 cm, Tebal = 9 mm
SATUAN : M
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Lisplank GRC M 0.4000 60,000.00 24,000.00
2 Skrup/Paku GRC Kg 0.1000 45,000.00 4,500.00
B. UPAH
1 Pekerja OH 0.15 100,000.00 15,000.00
2 Tukang Kayu OH 0.07 135,000.00 9,450.00
3 Kepala Tukang OH 0.007 150,000.00 1,050.00
4 Mandor OH 0.006 165,000.00 990.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Rangka Plafond Kayu Kls III
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Kls III, Balok M3 0.015 3,850,000.00 59,290.00
2 Paku Kg 0.200 22,500.00 4,500.00
B. UPAH
1 Mandor OH 0.075 -
2 Kepala Tukang OH 0.030 150,000.00 4,500.00
3 Tukang Kayu OH 0.300 125,000.00 37,500.00
4 Pekerja OH 0.150 100,000.00 15,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Plafond GRC 3 mm
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 GRC 3 mm Lbr 0.3750 63,000.00 23,625.00
2 Paku GRC/Skrup Kg 0.1100 45,000.00 4,950.00
B. UPAH
1 Pekerja OH 0.100 100,000.00 10,000.00
2 Tukang Kayu OH 0.050 135,000.00 6,750.00
3 Kepala Tukang OH 0.005 150,000.00 750.00
4 Mandor OH 0.005 165,000.00 825.00
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Kayu Profil SP4 M' 1.0500 13,500.00 14,175.00
2 Paku Kg 0.0100 22,500.00 225.00
B. UPAH
1 Mandor OH 0.0030 -
2 Kepala Tukang OH 0.0050 135,000.00 675.00
3 Tukang Kayu OH 0.0500 150,000.00 7,500.00
4 Pekerja OH 0.0500 165,000.00 8,250.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Cor Beton tumbuk 1:3:5 (F'c =16,9 Mpa K 200)
SATUAN : M3
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Semen @50 Kg Zak 7.0400 76,000.00 535,040.00
2 Pasir Pasang M3 0.5221 150,000.00 78,321.43
3 Batu Kerikil M3 0.7637 180,000.00 137,466.67
B. UPAH
1 Mandor OH 0.0800 -
2 Kepala Tukang OH 0.0250 150,000.00 3,750.00
3 Tukang Batu OH 0.2500 125,000.00 31,250.00
4 Pekerja OH 1.6500 100,000.00 165,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Lantai Keramik 40 x 40
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Keramik 40 x 40 cm Dos 1 58,000.00 58,000.00
2 Semen @50 Kg Kg 9.8 1,520.00 14,896.00
3 Pasir Pasang M3 0.045 130,000.00 5,850.00
4 Semen Warna (grout) Kg 1.3 2,250.00 2,925.00
B. UPAH
1 Pekerja OH 0.25 100,000.00 25,000.00
2 Tukang batu OH 0.125 150,000.00 18,750.00
3 Kepala Tukang OH 0.013 125,000.00 1,625.00
4 Mandor OH 0.013 100,000.00 1,300.00
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Keramik 20 x 20 cm Dos 1.0000 - -
2 Semen @50 Kg Zak 0.2080 1,520.00 316.16
3 Pasir Pasang M3 0.0450 130,000.00 5,850.00
4 Semen Warna (grout) Zak 0.0375 2,250.00 84.38
B. UPAH
1 Mandor OH 0.0350 -
2 Kepala Tukang OH 0.0350 150,000.00 5,250.00
3 Tukang Batu OH 0.3500 125,000.00 43,750.00
4 Pekerja OH 0.7000 100,000.00 70,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Dinding Keramik 20 X 25
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Keramik 20 x 25 cm Dos 1.0000 - -
2 Semen @50 Kg Zak 0.1860 1,520.00 282.72
3 Pasir Pasang M3 0.0180 130,000.00 2,340.00
4 Semen Warna (grout) Zak 0.0375 2,250.00 84.38
B. UPAH
1 Pekerja OH 0.0450 -
2 Tukang batu OH 0.0450 150,000.00 6,750.00
3 Kepala Tukang OH 0.4500 125,000.00 56,250.00
4 Mandor OH 0.9000 100,000.00 90,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pas. Plint 10 x 40
SATUAN : M2
ANALISA HARGA SATUAN PEK. LANTAI / KERAMIK
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Plin Lantai 10 x 40 Bh 3.53 5,000.00 17,650.00
2 Semen @50 Kg Kg 1.24 1,520.00 1,884.80
3 Pasir Pasang M3 0.003 130,000.00 390.00
4 Semen Warna (grout) Zak 0.005 2,250.00 11.25
B. UPAH
1 Pekerja OH 0.09 100,000.00 9,000.00
2 Tukang batu OH 0.09 135,000.00 12,150.00
3 Kepala Tukang OH 0.009 150,000.00 1,350.00
4 Mandor OH 0.005 165,000.00 825.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pengecetan Dinding / Plafon
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Plamir Kg 0.1000 - -
2 Cat Dasar Kg 0.1000 30,000.00 3,000.00
3 Cat Penutup 2x lapis Kg 0.2600 30,000.00 7,800.00
B. UPAH
1 Mandor OH 0.0025 165,000.00 412.50
2 Kepala Tukang OH 0.0063 150,000.00 945.00
3 Tukang Cat OH 0.0630 125,000.00 7,875.00
4 Pekerja OH 0.0200 100,000.00 2,000.00
SATUAN KERJA :
PEKERJAAN :
JENIS PEKERJAAN : Pengecetan Kayu (Mengkilap)
SATUAN : M2
Harga Jumlah
No. Uraian Sat Volume Satuan Harga
(Rp.) (Rp.)
A. BAHAN
1 Cat Meni Kg 0.2000 - -
2 Plamir Kg 0.1500 - -
3 Cat Dasar Kg 0.1700 25,000.00 4,250.00
4 Cat Penutup 3x lapis Kg 0.3500 25,000.00
5 Kuas Bh 0.0100 - -
6 Amplas Lbr 0.2000 - -
B. UPAH
1 Mandor OH 0.0025 -
2 Kepala Tukang OH 0.0040 150,000.00 600.00
3 Tukang Cat OH 0.1050 125,000.00 13,125.00