PEKERJAAN : Rehabilitasi Gedung CAT BKPP Bolaang Mongondow

LOKASI : Bolaang Mongondow

T.A : 2022
DAFTAR KUANTITAS HARGA

HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SAT.
SATUAN (Rp) (Rp)

A PEKERJAAN PERSIAPAN
1 Pek. Papan Proyek 1.00 Bh 250,000 0.11 27,500.00 277,500.00
2 Pembongkaran Sebagian atap, dinding Plafon, Teras dan Paving 1.00 Ls 23,000,000 0.11 2,530,000.00 25,530,000.00
B BIAYA PENYELENGGARAAN K3 0.11
1 Penyiapan RKK 0.11
-Dokumen RKK 1.00 Set 2,250,000 0.11 247,500.00 2,497,500.00
2 Sosialisasi, Promosi dan Pelatihan 0.11 0.00 0.00
-Papan Infomasi K3 1.00 Bh 750,000 0.11 82,500.00 832,500.00
3 Alat Pelindung kerja dan alat pelindung diri 0.11 0.00 0.00
-Topi Pelinding (safety Helmet) 10.00 Bh 40,000 0.11 44,000.00 444,000.00
-Pelindung pernafasan dan mulut (masker) 3.00 Dos 50,000 0.11 16,500.00 166,500.00
-Sarung tangan (safety gloves) 10.00 Bh 55,000 0.11 60,500.00 610,500.00
-Sepatu keselamatan 10.00 Bh 110,000 0.11 121,000.00 1,221,000.00
-Rompi Keselamtan 10.00 Bh 75,000 0.11 82,500.00 832,500.00
-Peralatan P3K 1.00 1,000,000 0.11 110,000.00 1,110,000.00
4 Rambu rambu yang diperlukan 0.11
-Rambu Peringatan 1.00 Bh 400,000 0.11 44,000.00 444,000.00
-Rambu Pekerjaan Sementara 1.00 Bh 400,000 0.11 44,000.00 444,000.00
C PEKERJAAN TANAH 0.11
1 Pek. Pemasangan Bowplank 24 M1 28,408 0.11 74,997.12 756,789.12
2 Pek. Galian Tanah Pondasi Batu Kali 27.48 M3 87,038 0.11 263,098.47 2,654,902.71
3 Pek. Galian Tanah Pondasi Telapak 16.88 M3 87,038 0.11 161,612.16 1,630,813.60
4 Timbunan Tanah Dalam Bangunan 29.40 M3 98,615 0.11 318,920.91 3,218,201.91
5 Timbunan Tanah Kembali 14.79 M3 44,000 0.11 71,583.60 722,343.60
D PEKERJAAN PONDASI 0.11
1 Urugan Pasir Bawah Pondasi 1.32 M3 198,000 0.11 28,749.60 290,109.60
2 Urugan Pasir dibawah Pondasi Telapak 0.50 M3 198,000 0.11 10,890.00 109,890.00
3 Pas. Timbrisan Batu Kosong 5.28 M3 478,830 0.11 278,104.46 2,806,326.86
4 Pek. Pondasi Batu Kali Sp. 1:4 15.61 M3 877,982 0.11 1,507,582.89 15,212,881.91
E PEKERJAAN BETON
1 Pondasi Telapak (PT) 80x80 cm Tbl. 25 cm Sp. 1 Pc : 2 Psr : 3 Krl
- Cor Lantai Kerja T=5 Cm 0.50 M3 785,297 0.11 43,191.34 435,839.84
- Pembesian Terpasang 216.79 Kg 12,860 0.11 306,671.13 3,094,590.53
- Bekisting Pondasi Terpasang 2x Pakai 3.30 M2 216,550 0.11 78,607.65 793,222.65
- Beton Sp.1 Pc : 2 :Psr:3 Krl 1.24 M3 1,083,959 0.11 147,852.01 1,491,961.17

2 Sloop 20 x 25
- Pembesian Terpasang 356.12 Kg 14,860 0.11 582,113.75 5,874,056.95
- Bekisting Sloop Terpasang 2x Pakai 21.88 M2 216,550 0.11 521,192.54 5,259,306.54
- Beton Sp.1 Pc : 2 :Psr:3 Krl 2.19 M3 1,083,959 0.11 261,125.72 2,634,995.93

3 Kolom Struktur (KS) 25 x 25


- Pembesian Terpasang 627.50 Kg 14,860 0.11 1,025,711.50 10,350,361.50
- Bekisting Kolom Terpasang 2x Pakai 32.10 M2 216,550 0.11 764,638.05 7,715,893.05
- Beton Sp.1 Pc : 2 :Psr:3 Krl 4.01 M3 1,083,959 0.11 478,134.31 4,824,809.90

4 Kolom Praktis (KP) 12x12


- Pembesian Terpasang 47.93 Kg 14,860 0.11 78,346.38 790,586.18
- Bekisting Kolom Praktis Terpasang 2x Pakai 1.70 M2 216,550 0.11 40,494.85 408,629.85
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.11 M3 1,083,959 0.11 13,115.90 132,351.39

5 Balok Latey (LT) 12x12 , Sp.1 Pc : 2 :Psr:3 Krl


- Pembesian Terpasang 158.83 Kg 13,350 0.11 233,241.86 2,353,622.36
- Bekisting Balok latey Terpasang 2x Pakai 7.86 M2 216,550 0.11 187,229.13 1,889,312.13
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.47 M3 1,083,959 0.11 56,040.68 565,501.41
6 Ring Balok 20 x 40
- Pembesian Terpasang 157.64 Kg 14,860 0.11 257,678.34 2,600,208.74
- Bekisting Balok Terpasang 2x Pakai 8.80 M2 216,550 0.11 209,620.40 2,115,260.40
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.66 M3 1,083,959 0.11 78,695.42 794,108.36

7 Plat Dak Tbl =12 cm


- Pembesian Terpasang 249.74 Kg 13,350 0.11 366,743.19 3,700,772.19
- Bekisting Plat Terpasang 2x Pakai 10.22 M2 216,550 0.11 243,445.51 2,456,586.51
- Beton Sp.1 Pc : 2 :Psr:3 Krl 1.23 M3 1,083,959 0.11 146,659.65 1,479,929.22

8 Ring Balok 15 x 30
- Pembesian Terpasang 365.30 Kg 13,350 0.11 536,443.05 5,413,198.05
- Bekisting Balok Terpasang 2x Pakai 10.90 M2 216,550 0.11 259,643.45 2,620,038.45
- Beton Sp.1 Pc : 2 :Psr:3 Krl 1.64 M3 1,083,959 0.11 195,546.20 1,973,238.96

9 Ring Balok Sopi Sopi 12 : 20


- Pembesian Terpasang 116.78 Kg 12,860 0.11 165,196.99 1,666,987.79
- Bekisting Balok Terpasang 2x Pakai 7.50 M2 216,550 0.11 178,653.75 1,802,778.75
- Beton Sp.1 Pc : 2 :Psr:3 Krl 0.46 M3 1,083,959 0.11 54,848.33 553,469.47
F PEKERJAAN PASANGAN, PLESTERAN DAN ACIAN
1 Pas. Dinding 1/2 Bata 12 Sp 1:4 147.54 M2 128,993 0.11 2,093,478.99 21,125,106.21
2 Plesteran Dinding Sp 1:4 Tebal 15 mm 295.08 M2 42,795 0.11 1,389,074.35 14,017,022.95
3 Plesteran Beton Sp 1:4 Tebal 15 mm 61.70 M2 42,795 0.11 290,449.67 2,930,901.17
4 Plesteran Pondasi Sp 1:4 Tebal 15 mm 10.50 M2 42,795 0.11 49,428.23 498,775.73
5 Acian Dinding dan Beton 367.30 M2 35,606 0.11 1,438,589.22 14,516,673.02
G PEKERJAAN PEMINDAHAN KUSEN, JENDELA & VENTILASI DIPASANG KEMB
1 Pemindahan dan Pemasangan kembali Pintu Existing 1.00 Unit 500,000 0.11 55,000.00 555,000.00
2 Pemindahan dan Pemasangan kembali Jendela Existing 2.00 Unit 500,000 0.11 110,000.00 1,110,000.00
3 Pemindahan dan Pemasangan kembali VentilasiExisting 2.00 Unit 500,000 0.11 110,000.00 1,110,000.00
H PEKERJAAN KUSEN PINTU JENDELA VENTILASI
1 Kusen Aluminium 4" 67.88 M1 181,056 0.11 1,351,908.94 13,641,990.22
2 Bingkai Jendela Aluminium Silver 9.48 M1 181,056 0.11 188,805.20 1,905,216.08
3 Kaca 5mm Jendela dan Ventilasi 14.19 M2 180,000 0.11 280,962.00 2,835,162.00
4 Engsel 3" 6.00 Psg 15,000 0.11 9,900.00 99,900.00
5 kait Angin 3.00 Bh 15,000 0.11 4,950.00 49,950.00
6 Grendel Jendela 3.00 Bh 15,000 0.11 4,950.00 49,950.00
I PEKERJAAN ATAP
1 Pas. Baja Ringan Kuda Kuda Double Canal 75.75.5 + Reng 45.45. 241.90 M2 297,840 0.11 7,925,224.56 79,972,720.56
2 Pekerjaan Penutup Atap Spandex T = 0,30 mm 241.90 M2 100,661 0.11 2,678,488.55 27,028,384.45
3 Pekerjaan Bubungan Atap Spandex T = 0,30 mm 14.40 M1 43,990 0.11 69,680.16 703,136.16
4 Pek. Listplank GRC (Lebar =30 cm, Tebal = 9 mm 54.00 M1 60,489 0.11 359,304.66 3,625,710.66
J PEKERJAAN LANGIT LANGIT
1 Pek. Rangka Plafond Hollow Galvalum 4x4 189.57 M2 55,000 0.11 1,146,898.50 11,573,248.50
2 Plafond GRC Tebal 3 mm 189.57 M2 51,590 0.11 1,075,790.79 10,855,707.09
3 Pek. List Kayu SP 4 cm 145.70 M1 33,908 0.11 543,443.52 5,483,839.12
K PEKERJAAN PENGECETAN
1 Pek. Cat Dinding Setara Metrolite/Envie 367.35 M2 24,236 0.11 979,340.41 9,882,435.01
2 Pek. Cat Plafond Setara Metrolite/Envie 189.57 M2 24,236 0.11 505,386.04 5,099,804.56
3 Pek. Cat Listplank 16.07 M2 24,236 0.11 42,841.98 432,314.50
4 Pek. Cat Sika 107 Plat Dak 15.76 M2 40,000 0.11 69,344.00 699,744.00
L PEK. INSTALASI LISTRIK DAN PENERANGAN
1 Philips LED DN027B GEN2 22 W 22 Watt Downlight Panel 8 Inch 4.00 Set 315,000 0.11 138,600.00 1,398,600.00
2 Philips LED Panel 60x60 RC091V GM G2 MR PCV 29 W - 4000K, 6.00 Set 1,250,000 0.11 825,000.00 8,325,000.00
3 Sakelar Tunggal (Inbow) Brocco/Panasonic 1.00 Bh 24,000 0.11 2,640.00 26,640.00
4 Sakelar Ganda (Inbow) Brocco/Panasonic 4.00 Bh 35,000 0.11 15,400.00 155,400.00
5 Stok Kontak Dinding 2 Lubang (Inbow) Brocco/Panasonic 3.00 Bh 35,000 0.11 11,550.00 116,550.00
6 Jasa Pasang Instalasi Kontak 9.00 Titik 75,000 0.11 74,250.00 749,250.00
M PEKERJAAN LANTAI
1 Urugan Pasir dibawah Lantai, T = 5 cm 7.35 M3 198,000 0.11 160,083.00 1,615,383.00
2 Cor Beton Sp 1:3:5 Untuk Lantai Bangunan , T = 7 cm 10.29 M3 785,297 0.11 888,877.67 8,969,583.80
3 Pek. Penyambungan Keramik 40x40 147.80 M2 141,181 0.11 2,295,320.70 23,161,872.50
4 Plint Keramik Uk. 10 x 40 46.05 M1 43,261 0.11 219,138.60 2,211,307.65
N PEKERJAAN AKHIR
1 Administrasi Dan Dokumentasi 1.00 Ls 750,000 0.11 82,500.00 832,500.00
2 Pembersihan Akhir dan Penataan Paving Eksisting 1.00 Ls 3,000,000 0.11 330,000.00 3,330,000.00

JUMLAH TOTAL + PAJAK 11% Rp 418,298,657

Bolaang Mongondow, 16 Juli 2022


CV. Rich Cahaya Internusa

Riman Mohamad
Direktur Utama