DAFTAR HARGA SATUAN

UPAH DAN BAHAN - BAHAN BANGUNAN / MATERIAL / LISTRIK

Satuan Kerja : Dinas Kebudayaan dan Pariwisata Kabupaten Sigi


Pekerjaan : Rehabilitasi Kolam Pemandian Air Panas Bora
Lokasi : Ds. Bora - Kabupaten Sigi
Tahun Anggaran : 2017

HARGA
NO U RAIAN SATUAN SATUAN
(Rp.)

I. UPAH TENAGA KERJA


### Tukang Hari 90,000.00
### Kepala Tukang Hari 135,000.00
### Pekerja Hari 72,000.00
### Mandor Hari 76,500.00

II. BAHAN-BAHAN / MATERIAL


1 Pasir Pasangan M³ 140,000.00
2 Pasir Timbunan / Pasir Urug M³ 110,500.00
3 Sirtu M³ 135,200.00
4 Tanah Taman M³ 180,000.00
5 Batu Bata Buah 900.00
6 K e r i k i l / Batu Pecah M³ 270,000.00
7 Portland Cement (PC) Zak 58,500.00
8 Semen Putih Kg 27,500.00
9 Kapur Acian Kg 39,600.00
10 Tegel Keramik 30 x 30 cm Dos 72,000.00
11 Tegel Keramik 20 x 20 cm Dos 64,800.00
12 Tegel Keramik 40 x 40 cm Dos 79,200.00
13 Tegel Keramik 40 x 40 cm Dos 95,000.00
14 Cat Tembok Ekterior Kg 65,000.00
15 Air Kerja Liter 100.00

Palu, 03 Oktober 2017


Penyedia Jasa
CV. LUNETTA KAHATULISTIWA

IRHAM, ST.
Direktur
TERIAL / LISTRIK

KETERANGAN

Motif Batu Alam


1,625,000,000.00

HATULISTIWA
ANALISA SATUAN PEKERJAAN

Satuan Kerja : Dinas Kebudayaan dan Pariwisata Kabupaten Sigi


Pekerjaan : Rehabilitasi Kolam Pemandian Air Panas Bora
Lokasi : Ds. Bora - Kabupaten Sigi
Tahun Anggaran : 2017

HARGA HARGA JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN SATUAN SATUAN MATERIAL SATUAN UPAH MATERIAL
(Rp) (Rp) (Rp)
A B C D E F G = (C x E)

1 1 m2 Membongkar lantai dan dinding keramik


Pekerja 0.0500 Oh 72,000.00
Mandor 0.0100 Oh 76,500.00
0.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
2 1 m3 Galian Tanah Biasa sedalam ≤ 1 M/ Cara Manual (Sumber Analisa PUPR No. 28/PRT/M/2016)
Pekerja 0.5630 Oh 72,000.00
Mandor 0.0563 Oh 76,500.00

Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)


Jumlah Harga Satuan Pekerjaan
3 1 m3 Urugan Pasir Sebagai Bahan Pengisi Bawah Lantai (Sumber Analisa PUPR No. 28/PRT/M/2016)
Pasir Urug 1.2000 m3 110,500.00 132,600.00
Pekerja 0.4000 Oh 72,000.00
Mandor 0.0400 Oh 76,500.00
132,600.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
A B C D E F G = (C x E)

4 1 m2 Pasangan Batu Bata 1/2 Batu 1 : 5 (Sumber Analisa PUPR No. 28/PRT/M/2016)
Batu Bata 70.0000 bh 900.00 63,000.00
Semen 0.1936 Zak 58,500.00 11,325.60
Pasir Pasangan 0.0450 m3 140,000.00 6,300.00
Kepala Tukang 0.0100 Oh 135,000.00
Tukang Batu 0.1000 Oh 90,000.00
Pekerja 0.3000 Oh 72,000.00
Mandor 0.0150 Oh 76,500.00
80,625.60
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan

5 1 m2 Plesteran 1 : 2 tebal 15 mm (Sumber Analisa PUPR No. 28/PRT/M/2016)


Semen 0.2045 Zak 58,500.00 11,962.08
Pasir Plesteran 0.0200 m3 140,000.00 2,800.00
Kepala Tukang 0.0150 Oh 135,000.00
Tukang Batu 0.1500 Oh 90,000.00
Pekerja 0.2000 Oh 72,000.00
Mandor 0.0100 Oh 76,500.00
14,762.08
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
6 1 m3 Acian (Sumber Analisa PUPR No. 28/PRT/M/2016)
Semen 0.0650 Zak 58,500.00 3,802.50
Kepala Tukang 0.0100 Oh 135,000.00
Tukang Batu 0.1000 Oh 90,000.00
Pekerja 0.2000 Oh 72,000.00
Mandor 0.0100 Oh 76,500.00
3,802.50
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
A B C D E F G = (C x E)

7 1m3 Membuat beton tumbuk 1 : 3 :5 Setara dengan fc' = 1,8 s.d 3,7 (B0: K-40 s.d. K-60) / (Sumber Analisa PUPR No. 28/PRT/M/2016)
Pasir Beton 0.5220 m3 140,000.00 73,080.00
Kerikil 0.8620 m3 270,000.00 232,740.00
Semen 4.0000 Zak 58,500.00 234,000.00
Kepala Tukang 0.0220 Oh 135,000.00
Tukang Batu 0.2200 Oh 90,000.00
Pekerja 1.3200 Oh 72,000.00
Mandor 0.0220 Oh 76,500.00
539,820.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
8 1m3 Membuat beton tumbuk 1 : 2 :3 Beton Mutu Sedang fc' 20 MPa atau K-250 / (Sumber Analisa PUPR No. 28/PRT/M/2016)
Pasir Beton 0.6920 m3 140,000.00 96,880.00
Kerikil 1.0390 m3 270,000.00 280,530.00
Semen 7.6800 Zak 58,500.00 449,280.00
Air 215.0000 Liter 100.00 21,500.00
Kepala Tukang 0.0280 Oh 135,000.00
Tukang Batu 0.2750 Oh 90,000.00
Pekerja 1.6500 Oh 72,000.00
Mandor 0.1650 Oh 76,500.00
848,190.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
9 1 m2 Pasangan Lantai Keramik 20x20 (Sumber Analisa PUPR No. 28/PRT/M/2016)
Tegel keramik 20 x 20 1.1000 Dos 64,800.00 71,280.00
Semen 0.2080 Zak 58,500.00 12,168.00
Semen Warna 1.6200 Kg 27,500.00 44,550.00
Pasir Pasangan 0.0450 m3 140,000.00 6,300.00
Kepala Tukang 0.0350 Oh 135,000.00
Tukang Batu 0.3500 Oh 90,000.00
Pekerja 0.6200 Oh 72,000.00
Mandor 0.0300 Oh 76,500.00
134,298.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
A B C D E F G = (C x E)

10 1 m2 Pasangan dinding Keramik 30x30 (Sumber Analisa PUPR No. 28/PRT/M/2016)


Tegel keramik 30 x 30 1.1000 Dos 72,000.00 79,200.00
Semen 0.1752 Zak 58,500.00 10,249.20
Semen Warna 0.9000 Kg 27,500.00 24,750.00
Pasir Pasangan 0.0230 m3 140,000.00 3,220.00
Kepala Tukang 0.0130 Oh 135,000.00
Tukang Batu 0.1300 Oh 90,000.00
Pekerja 0.2700 Oh 72,000.00
Mandor 0.0135 Oh 76,500.00
117,419.20
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
11 1 m2 Pasang Tegel Keramik 40/40 (Sumber Analisa PUPR No. 28/PRT/M/2016)
Tegel Keramik 40/40 1.1000 Dos 79,200.00 87,120.00
Semen 0.1960 Zak 58,500.00 11,466.00
Pasir Pasangan 0.0450 m3 140,000.00 6,300.00
Semen Warna 1.3000 kg 27,500.00 35,750.00
Kepala Tukang 0.0120 Oh 135,000.00
Tukang Batu 0.1200 Oh 90,000.00
Pekerja 0.2500 Oh 72,000.00
Mandor 0.0130 Oh 76,500.00
140,636.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
12 1 m2 Pasang Tegel Keramik 40/40 (Motif Batu Alam) (Sumber Analisa PUPR No. 28/PRT/M/2016)
Tegel Keramik 40/40 1.1000 Dos 95,000.00 104,500.00
Semen 0.1960 Zak 58,500.00 11,466.00
Pasir Pasangan 0.0450 m3 140,000.00 6,300.00
Semen Warna 1.3000 kg 27,500.00 35,750.00
Kepala Tukang 0.0120 Oh 135,000.00
Tukang Batu 0.1200 Oh 90,000.00
Pekerja 0.2500 Oh 72,000.00
Mandor 0.0130 Oh 76,500.00
158,016.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
A B C D E F G = (C x E)

13 1 M2 Pengecatan Dinding Tembok Baru (1 lapis plamir, 1 lapis cat dasar 2 lapis) (Sumber Analisa PUPR No. 28/PRT/M/2016)
Cat penutup
Plamir tembok 0.1000 Kg 56,000.00 5,600.00
Cat dasar Alkali / Sealer 0.1000 Kg 58,000.00 5,800.00
Cat penutup 2 x 0.2600 Kg 65,000.00 16,900.00
Kertas Pasir 0.5000 Lbr. 18,000.00 9,000.00
Tukang 0.0630 Oh 90,000.00
Cat penutup 2 x (Cat Interior Setara Jotun/Nippon Pain) 0.0063 Oh 135,000.00
Pekerja 0.0200 Oh 72,000.00
Mandor 0.0025 Oh 76,500.00
37,300.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
14 1 m1 Pasang Knsteen (Sumber Analisa PUPR No. 28/PRT/M/2016)
Kansteen Batako Pres 1.6600 Buah 1,850.00 3,071.00
Semen 0.1200 Zak 58,500.00 7,020.00
Pasir Pasangan 0.0080 m3 140,000.00 1,120.00
Kepala Tukang 0.0200 Oh 135,000.00
Tukang Batu 0.2000 Oh 90,000.00
Pekerja 0.1500 Oh 72,000.00
Mandor 0.0100 Oh 76,500.00
11,211.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
15 1 m1 Pasang Kuku Tegel (Sumber Analisa PUPR No. 28/PRT/M/2016)
Kuku Tegel 10.1000 Buah 700.00 7,070.00
Semen 0.0120 Zak 58,500.00 702.00
Pekerja 0.1500 Oh 72,000.00
7,772.00
Over Head + Profit 15% (Lampiran Perpres 70/2012 Pasal 66 Ayat 8)
Jumlah Harga Satuan Pekerjaan
JUMLAH HARGA JUMLAH TOTAL
UPAH HARGA
(Rp) (Rp)
H = (C x F) I = (G + H)

3,600.00
765.00
4,365.00 4,365.00
70/2012 Pasal 66 Ayat 8) 654.75
5,019.75

40,536.00
4,306.95
44,842.95 44,842.95
70/2012 Pasal 66 Ayat 8) 6,726.44
51,569.39

28,800.00
3,060.00
31,860.00 164,460.00
70/2012 Pasal 66 Ayat 8) 24,669.00
189,129.00
H = (C x F) I = (G + H)

1,350.00
9,000.00
21,600.00
1,147.50
33,097.50 113,723.10
70/2012 Pasal 66 Ayat 8) 17,058.47
130,781.57

2,025.00
13,500.00
14,400.00
765.00
30,690.00 45,452.08
70/2012 Pasal 66 Ayat 8) 6,817.81
52,269.89

1,350.00
9,000.00
14,400.00
765.00
25,515.00 29,317.50
70/2012 Pasal 66 Ayat 8) 4,397.63
33,715.13
H = (C x F) I = (G + H)

2,970.00
19,800.00
95,040.00
1,683.00
119,493.00 659,313.00
70/2012 Pasal 66 Ayat 8) 98,896.95
758,209.95

3,780.00
24,750.00
118,800.00
12,622.50
159,952.50 1,008,142.50
70/2012 Pasal 66 Ayat 8) 151,221.38
1,159,363.88

4,725.00
31,500.00
44,640.00
2,295.00
83,160.00 217,458.00
70/2012 Pasal 66 Ayat 8) 32,618.70
250,076.70
H = (C x F) I = (G + H)

1,755.00
11,700.00
19,440.00
1,032.75
33,927.75 151,346.95
70/2012 Pasal 66 Ayat 8) 22,702.04
174,048.99

1,620.00
10,800.00
18,000.00
994.50
31,414.50 172,050.50
70/2012 Pasal 66 Ayat 8) 25,807.58
197,858.08

1,620.00
10,800.00
18,000.00
994.50
31,414.50 189,430.50
70/2012 Pasal 66 Ayat 8) 28,414.58
217,845.08
H = (C x F) I = (G + H)

5,670.00
850.50
1,440.00
191.25
8,151.75 45,451.75
70/2012 Pasal 66 Ayat 8) 6,817.76

2,700.00
18,000.00
10,800.00
765.00
32,265.00 43,476.00
70/2012 Pasal 66 Ayat 8) 6,521.40
49,997.40

10,800.00
10,800.00 18,572.00
70/2012 Pasal 66 Ayat 8) 2,785.80
21,357.80

Palu, 03 Oktober 2017


Penyedia Jasa
CV. LUNETTA KAHATULISTIWA
IRHAM, ST.
Direktur
RENCANA ANGGARAN BIAYA
Satuan Kerja : Dinas Kebudayaan dan Pariwisata Kabupaten Sigi
Pekerjaan : Rehabilitasi Kolam Pemandian Air Panas Bora
Lokasi : Ds. Bora - Kabupaten Sigi
Tahun Anggaran : 2017

VOLUME / HARGA SATUAN JUMLAH HAR


NO. URAIAN PEKERJAAN
SATUAN (Rp) (Rp)

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 1.000 Ls Rp. 350,000.00 Rp.
2 Pekerjaan Pembongkaran Tegel Lama 1.000 Ls Rp. 3,000,000.00 Rp.
Rp.
II PEKERJAAN TANAH DAN PASIR
1 Urugan Pasir Bawah Lantai Keramik 31.933 M3 Rp. 189,129.00 Rp.
2 Pengadaan Tanah Taman 3.170 M3 Rp. 180,000.00 Rp.
Rp.
III PEK. PAS. BATU, DINDING DAN PLESTERAN
1 Pasangan Dinding Bata 18.036 M' Rp. 130,781.57 Rp.
Keterangan
Pemasangan pada bagian atas kolam
ditinggikan dari permukaan awal ± 15 cm
2 Plesteran Dinding Biasa 1 : 5 52.989 M² Rp. 52,269.89 Rp.
Keterangan
Plesteran pada dinding kolam dan bagian atas
sebelah samping tegel motif batu alam
3 Acian Dinding 1 PC : 7 Kapur 42.119 M² Rp. 33,715.13 Rp.
Keterangan
Acian dikerjakan sebelum pemsangan tegel dinding
kolam
4 Cor Beton 1 : 2 : 5 Tebal = 12 cm 23.335 M3 Rp. 1,159,363.88 Rp.
Keterangan
Pengecoran kedap air bagian dasar kolam sebelum
pemasangan tegel lantai motif catur ± 12 cn
5 Cor Rabat Beton 1 : 3 : 5 Tebal = 5 cm 9.723 M3 Rp. 758,209.95 Rp.
Keterangan
Pengecoran sebelum pemasangan tegel lantai
motif catur ± 5 cn
6 Pek. Lantai Keramik 40/40 194.461 M² Rp. 197,858.08 Rp.
Keterangan
Pemasangan tegel lantai kolam motif catur 40/40
VOLUME / HARGA SATUAN JUMLAH HAR
NO. URAIAN PEKERJAAN
SATUAN (Rp) (Rp)

7 Cor Rabat Beton 1 : 3 : 5 Tebal = 5 cm 2.106 Rp. 758,209.95 Rp.


Keterangan
Pengecoran sebelum pemasangan tegel dinding
motif abu-abu ± 5 cm
8 Pasangan Keramik Dinding Kolam 20/25 42.119 M² Rp. 250,076.70 Rp.
Keterangan
Pemasangan tegel dinding kolam motif abu-abu
20/25
9 Cor Rabat Beton 1 : 3 : 5 Tebal = 5 cm 2.064 Rp. 758,209.95 Rp.
Keterangan
Pengecoran sebelum pemasangan tegel tangga kolam
dan tegel motif kasar abu-abu 30/30 pada bagian
atas kolam
10 Pasangan Keramik 30/30 Teksture Kasar 41.270 M² Rp. 174,048.99 Rp.
Keterangan
Pemasangan tegel tangga dan bagian atas kolam
30/30 warna abu-abu dan krem
11 Cor Rabat Beton 1 : 3 : 5 Tebal = 5 cm 4.340 M3 Rp. 758,209.95 Rp.
Keterangan
Pengecoran sebelum pemasangan tegel lantai bagian atas
motif Batu alam ± 5 cm
12 Pek. Lantai Keramik 40/40 86.800 M² Rp. 217,845.08 Rp.
Keterangan
Pemasangan tegel lantai bagian atas kolam
40/40 motif batu alam
13 Pasangan Kuku Tegel 70.850 M' Rp. 20,000.00 Rp.
Keterangan
Pemasangan kuku tegel pada sekeliling kolam
dan tangga
14 Cor Rabat Beton 1 : 3 : 5 Tebal = 5 cm 1.904 M3 Rp. 758,209.95 Rp.
Keterangan
Pengecoran sebelum pemasangan tegel lantai 20/20
ruangan sauna
15 Pasangan Keramik Lantai 20/20 38.070 M² Rp. 250,076.70 Rp.
Keterangan
Pemasangan tegel lantai 20/20 pada ruang sauna
dan ruang ganti
16 Cor Rabat Beton 1 : 3 : 5 Tebal = 5 cm 14.155 M' Rp. 758,209.95 Rp.
Keterangan
Pengecoran pada areal sekeliling kolam bagian atas
dengan ketebalan ± 5 cm Rp.
VOLUME / HARGA SATUAN JUMLAH HAR
NO. URAIAN PEKERJAAN
SATUAN (Rp) (Rp)

IV PEKERJAAN LAIN-LAIN
1 Pembuatan Gazebo Besi Hollow 1.000 Unit Rp. 7,500,000.00 Rp.
2 Pemasangan Tutup Penguras Kolam 1.000 Buah Rp. 150,000.00 Rp.
3 Perbaikan Lisplank 1.000 Ls Rp. 200,000.00 Rp.
4 Pengadaan Buis Beton 6.000 Buah Rp. 200,000.00 Rp.
5 Pengadaan Tanaman Areal Kolam
- Tanaman Pohon Bintaro 4.000 Phn Rp. 600,000.00 Rp.
- Tanaman Pohon Tabe Puya 2.000 Phn Rp. 600,000.00 Rp.
- Tanaman Merambat Lee Kwan Yew 30.000 Buah Rp. 150,000.00 Rp.
5 Dokumentasi Proyek 1.000 Ls Rp. 250,000.00 Rp.
6 Pembersihan Akhir 1.000 Ls Rp. 2,000,000.00 Rp.
Rp.
JUMLAH HARGA
(Rp)

350,000.00
3,000,000.00
3,350,000.00

6,039,475.27
570,600.00
6,610,075.27

2,358,776.31

2,769,729.31

27,054,127.02

7,372,113.25

38,475,679.12
JUMLAH HARGA
(Rp)

10,532,980.53

1,564,566.23

7,183,001.92

3,290,631.18

18,908,952.51

1,417,000.00

1,443,252.64

9,520,419.97

10,732,461.84

142,623,691.83
JUMLAH HARGA
(Rp)

7,500,000.00
150,000.00
200,000.00
1,200,000.00

2,400,000.00
1,200,000.00
4,500,000.00
250,000.00
2,000,000.00
19,400,000.00
REKAPITULASI BIAYA
Satuan Kerja : Dinas Kebudayaan dan Pariwisata Kabupaten Sigi
Pekerjaan : Rehabilitasi Kolam Pemandian Air Panas Bora
Lokasi : Ds. Bora - Kabupaten Sigi
Tahun Anggaran : 2017

JUMLAH HARGA
NO URAIAN PEKERJAAN
(Rp)

I PEKERJAAN PENDAHULUAN Rp.

II PEKERJAAN TANAH DAN PASIR Rp.

III PEK. PAS. BATU, DINDING DAN PLESTERAN Rp.

IV PEKERJAAN LAIN-LAIN Rp.

JUMLAH Rp.
PPN 10% Rp.
JUMLAH REAL COST Rp.
PEMBULATAN HARGA Rp.

Terbilang :
Seratus Delapan Puluh Sembilan Juta Seratus Delapan Puluh Dua Ribu Ru
Palu, 03 Oktober 2017
Penyedia Jasa
CV. LUNETTA KAHATULISTIWA

IRHAM, ST.
Direktur
AYA
Sigi

JUMLAH HARGA
(Rp)

3,350,000.00

6,610,075.27

142,623,691.83

19,400,000.00

171,983,767.10
17,198,376.71
189,182,143.81
189,182,000.00