KABUPATEN BOJONEGORO
Kecamatan Desa
BUBULAN CLEBUNG
DAFTAR HARGA SATUAN UNTUK PERENCANAAN
BAHAN - UPAH - ALAT
No J E N I S VOL SAT HARGA
A BAHAN
1 Koral 1/2 1 m3 Rp 300,000
2 Pasir Cor 1 m3 Rp 290,000
3 Semen 40 Kg 1 zak Rp 48,000
4 Pasir Urug 1 m3 Rp 65,000
5 Tanah Urug 1 m4 Rp 65,000
6 Besi Ø 10 1 ljr Rp 70,000
7 Besi Ø 6 1 ljr Rp 25,000
8 Kawat bendrat 1 kg Rp 15,000
9 Paku 1 kg Rp 18,000
10 Kayu 4/6 - 3m 1 btg Rp 32,000
11 Kayu 2/3 - 2.5m 1 btg Rp 8,000
12 Papan bekesting triplek 8 mm 1 lbr Rp 100,000
B UPAH
1 Pekerja 1 OH Rp 65,000
2 Tukang Batu 1 OH Rp 80,000
3 Tukang Besi 1 OH Rp 80,000
4 Tukang kayu 1 OH Rp 80,000
B PERENCANAAN DIMENSI :
: PATOK P0 P1 P2 P3 P4
: POSISI TPT Kn Kn Kn Kn Kn
B : Lebar Atas 0.20 0.20 0.20 0.20
T1
T1 : Tinggi Talud 1.00 1.00 1.00 1.00
P : Panjang Talud 81.3 81.3 81.3 81.3
D : Lebar Pondasi 0.70 0.70 0.70 0.70 0.60
P
T2 : Kedalaman Pondasi 0.20 0.20 0.20 0.20 0.20
DD Dia Strous 0.25 0.20 0.20 0.20 -
T2
Tinggi Strous 1.00 1.00 1.00 1.00 -
Jumlah Strous 27.00 27.00 27.00 27.00 -
Luas Talud atas 0.30 0.45 0.45 0.45 -
T3 Luas Pondasi 0.14 0.14 0.14 0.14 0.12
Luas Srous 0.79 0.63 0.63 0.63 -
Volume Talud atas 24.39 36.585 36.585 36.585 0
Volume Pondasi 11.38 11.38 11.38 11.38 -
Volume Strous 0.33 0.17 0.17 0.17 -
Galian Pondasi 11.71 11.55 11.55 11.55 0.00
Volume Plesteran 24.39 24.39 24.39 24.39 0.00
T1 Besi Ø 10 71.00 71.00 71.00 71.00 0.00
T2 Besi Ø 10 35.00 35.00 35.00 35.00 2.00
T3 Besi Ø 10 135.00 135.00 135.00 135.00 0.00
T3 Besi Ø 6 8.00 6.00 6.00 6.00 0.00
Tebal pasir urug 0.005 0.005 0.005 0.005 0.005
Volume Pasir urug 82.01
Volume Siar
Volume Siar
Volume Siar
KEBUTUHAN BAHAN, ALAT DAN UPAH TENAGA
Provinsi : Jawa Timur
Kabupaten : Bojonegoro
Asumsi Perencanaan :
Plesteran = Panjang Talud x Lebar yang akan di plester ( bagaian atas talud )
AN UPAH TENAGA KERJA ( SNI )
BUBUL
Kecamatan :
AN
CLEBU
Desa :
NG
Upah Total Kebutuhan
Rp. Rp. Bahan dan Upah
Bahan Kebutuhan dibulatkan Sat
43,934,400 Koral 1/2 146.45 146.00 m3
72,898,560 Pasir Cor 98.36 98.00 m3
28,523,008 Semen 40 Kg 1,518.72 1,519.00 zak
5,062,400 5,062,400 Pasir Urug 10.31 10.00 m3
2,314,240 2,314,240 Tanah Urug 162.63 163.00 m3
76,846,000 Besi Ø 10 1,097.80 1,098.00 ljr
715,000 Besi Ø 6 28.60 29.00 ljr
2,712,000 Kawat bendrat 180.80 181.00 kg
20,249,600 20,249,600 Paku 54.24 54.00 kg
45,832,800 45,832,800 Kayu 4/6 - 3m 162.63 163.00 btg
813,600 Kayu 2/3 - 2.5m 16.26 16.00 btg
976,320 Papan bekesting tripl 8.14 8.00 lbr
Upah
1,196,000 1,196,000 Pekerja 44.80 45.00 OH
- - Tukang Batu 63.28 63.00 OH
Tukang Besi 253.12 253.00 OH
Tukang kayu 28.93 29.00 OH
670,313 Mandor 4.48 4.00 OH
117,000 117,000
- -
5,863,000
1,599,000 1,599,000
- -
5,204,000
130,100
76,371,000 315,527,200
Kabupaten : Bojonegoro
Kecamatan : BUBULAN
Desa : CLEBUNG
Perhitungan Volume Timbunan
VOLUME Harga
Satuan Jumlah Swadaya
URAIAN Dari Satuan Jumlah ( Rp )
Total P3MD ( Rp )
Swadaya ( Rp. )
BAHAN a b c=a-b d e f=bxe g=cxe
1 Koral 1/2 146 - 146 m3 300,000 - 43,800,000
2 Pasir Cor 98 - 98 m3 290,000 - 28,420,000
3 Semen 40 Kg 1,519 - 1,519 zak 48,000 - 72,912,000
4 Pasir Urug 10 - 10 m3 65,000 - 650,000
5 Tanah Urug 163 - 163 m4 65,000 - 10,595,000
6 Besi Ø 10 1,098 - 1,098 ljr 70,000 - 76,860,000
7 Besi Ø 6 29 - 29 ljr 25,000 - 725,000
8 Kawat bendrat 181 - 181 kg 15,000 - 2,715,000
9 Paku 54 - 54 kg 18,000 - 972,000
10 Kayu 4/6 - 3m 163 - 163 btg 32,000 - 5,216,000
11 Kayu 2/3 - 2.5m 16 - 16 btg 8,000 - 128,000
12 Papan bekesting triplek 8 8 - 8 ljr 100,000 - 800,000
Sub Total 1) - 243,793,000
ALAT
1 Bambu 5 - 5 btg 15,000 - 75,000
2 Benang 10 - 10 roll 3,500 - 35,000
3 Cikrak 2 - 2 bh 7,500 - 15,000
4 Ember Cor 5 - 5 bh 15,000 - 75,000
5 Slang Timbangan 10 - 10 m' 2,500 - 25,000
6 Kuas 3 - 3 bh 4,500 - 13,500
7 Prasasti 1 - 1 bh 300,000 300,000
8 Papan Proyek 1 - 1 bh 150,000 - 150,000
Sub Total 1 ) - - -
ALAT
Bambu 5 5 - btg 15,000 - - -
Benang 10 10 - roll 3,500 - - -
Cikrak 2 2 - bh 7,500 - - -
Ember Cor 5 5 - bh 15,000 - - -
Slang Timbangan 10 10 - m' 2,500 - - -
Kuas 3 3 - bh 4,500 - - -
Prasasti 1 1 - bh 300,000 - - -
Papan Proyek 1 1 - bh 150,000 - - -
Sub Total 2 )
UPAH - -
Pekerja 45 45 - OH 65,000 - - -
Tukang Batu 63 63 - OH 80,000 - - -
Tukang Besi 253 253 - OH 80,000 - - -
Tukang kayu 29 29 - OH 80,000 - - -
- - - - OH - - - -
Sub Total 3 ) - - -
TOTAL BIAYA SWADAYA - - -
Swadaya Selain Uang - -
Sumber Dana
Swadaya Uang - -
REKAPITULASI RENCANA ANGGARAN BIAYA
05 MARET 2017
GAMBAR RENCANA
PROPINSI JAWA TIMUR
Bojonegoro
BUBULAN
Rencana Urugan Peddel
DESA CLEBUNG
20 80
±0.00
Jalan Paving JENIS PRASARANA
-0.05
Pipa PVC. Ø 2''
TPT BETON
100
Rencana Urugan
Cor Beton
Tanah
LOKASI
20
Dusun Jenak
JUDUL GAMBAR
80
Strous Ø25-80
Dibuat Oleh :
SUKANDAR
Tim Pelaksana Kegiatan
Diperiksa Oleh
Dilatasi per 12 m
Pipa PVC Ø 2 ", Jarak 2m Besi Ø 9.60 mm - 200 mm
A Cor Beton
Besi Ø 9.60 mm - 200 mm
100
120
20
KASIHANTO
Sekretaris Desa