HARGA
NO. URAIAN PEKERJAAN
(Rp.)
(A) Jumlah Biaya Pekerjaan (termasuk biaya umum dan keuntungan) 119,636,194.01
(B) Dibulatkan 119,636,000.00
(C) Pajak Pertambahan Nilai (PPN) 10% x ( B ) 11,964,000.00
(D) JUMLAH TOTAL HARGA PEKERJAAN = ( B ) + ( C ) 131,600,000.00
Terbilang : SERATUS TIGA PULUH SATU JUTA ENAM RATUS RIBU RUPIAH
131,600,000.00
DAFTAR KUANTITAS DAN HARGA
JUMLAH
NO. URAIAN SAT. PERKIRAAN HARGA SATUAN
HARGA - HARGA
KUANTITAS (Rp.)
(Rp.)
1 2 3 4 5 6 = (4) x (5)
1 PEKERJAAN PERSIAPAN
974,815.00
2 PEKERJAAN TANAH/TANAMAN
1,087,560.00
3 PEKERJAAN DINDING
15,281,174.43
4 PEKERJAAN PLESTERAN
47,956,155.39
5 PEKERJAAN BETON
16,281,501.96
21,178,687.50
5,751,575.52
8 PEKERJAAN PENGECATAN
11,124,724.21