REKAPITULASI

PERKIRAAN HARGA PEKERJAAN

NAMA PEKERJAAN : PEMBUATAN PAGAR KANTOR CAMAT


LOKASI :
KABUPATEN :
TAHUN ANGGARAN :

HARGA
NO. URAIAN PEKERJAAN
(Rp.)

1 PEKERJAAN PERSIAPAN 974,815.00

2 PEKERJAAN TANAH/TANAMAN 1,087,560.00

3 PEKERJAAN DINDING 15,281,174.43

4 PEKERJAAN PLESTERAN 47,956,155.39

5 PEKERJAAN BETON 16,281,501.96

6 PEKERJAAN PAGAR BESI 21,178,687.50

7 PEKERJAAN PAPAN NAMA KANTOR 5,751,575.52

8 PEKERJAAN PENGECATAN 11,124,724.21

(A) Jumlah Biaya Pekerjaan (termasuk biaya umum dan keuntungan) 119,636,194.01
(B) Dibulatkan 119,636,000.00
(C) Pajak Pertambahan Nilai (PPN) 10% x ( B ) 11,964,000.00
(D) JUMLAH TOTAL HARGA PEKERJAAN = ( B ) + ( C ) 131,600,000.00
Terbilang : SERATUS TIGA PULUH SATU JUTA ENAM RATUS RIBU RUPIAH
131,600,000.00
DAFTAR KUANTITAS DAN HARGA

NAMA PEKERJAAN : PEMBUATAN PAGAR KANTOR CAMAT


LOKASI :
KABUPATEN :
TAHUN ANGGARAN :

JUMLAH
NO. URAIAN SAT. PERKIRAAN HARGA SATUAN
HARGA - HARGA
KUANTITAS (Rp.)
(Rp.)
1 2 3 4 5 6 = (4) x (5)

1 PEKERJAAN PERSIAPAN

1. 1 Pengukuran dan pemasangan bouplank Ls 1.00 500,000.00 500,000.00


1. 2 Membongkar dinding bata M3 5.00 94,963.00 474,815.00

974,815.00

2 PEKERJAAN TANAH/TANAMAN

2. 1 Timbunan Tanah Humus M3 2.52 253,000.00 637,560.00


2. 2 Bunga bawang-bawangan M2 10.00 20,000.00 200,000.00
2. 3 Bunga pandan M2 10.00 25,000.00 250,000.00

1,087,560.00

3 PEKERJAAN DINDING

3. 1 Pasangan Dinding Batu Bata Camp. 1:5 M3 14.33 1,009,965.00 14,471,174.43


3. 2 Pasangan Batu Alam M2 3.24 250,000.00 810,000.00

15,281,174.43

4 PEKERJAAN PLESTERAN

4. 1 Plesteran Camp. 1:5 M2 688.94 44,708.13 30,801,286.14


4. 2 Plesteran kaprot Camp. 1:5 M2 6.53 67,062.20 438,184.38
4. 3 Pekerjaan Profil Beton M1 231.09 59,942.30 13,852,066.11
4. 4 Acian Dinding Camp. 1 : 8 M2 688.94 4,158.00 2,864,618.76

47,956,155.39

5 PEKERJAAN BETON

5. 1 Beton Bertulang 1 : 2 : 3 pembesian 100 kg/m 3 M3 2.92 5,581,954.93 16,281,501.96

16,281,501.96

6 PEKERJAAN PAGAR BESI

6. 1 Pekerjaan Pagar Besi M2 54.84 375,000.00 20,563,687.50


6. 2 Pasang Grendel Bh 3.00 20,000.00 60,000.00
6. 3 Pasang Gembok Bh 3.00 45,000.00 135,000.00
6. 4 Pasang Roda Pintu Bh 12.00 35,000.00 420,000.00

21,178,687.50

7 PEKERJAAN PAPAN NAMA KANTOR

13. 1 Lantai Tegel Keramik Uk. 30 X 30 cm (Hitam) M2 3.15 161,975.69 509,575.52


13. 2 Huruf Stainless Steel Ls 1.00 5,000,000.00 5,000,000.00
13. 3 Saklar Tunggal Bh 1.00 12,000.00 12,000.00
13. 4 Lampu Spot Lite Bh 2.00 100,000.00 200,000.00
13. 5 Pemasangan Titik Lampu Titik 2.00 15,000.00 30,000.00

5,751,575.52

8 PEKERJAAN PENGECATAN

14. 1 Plamur Dinding M2 688.94 3,085.50 2,125,729.00


14. 2 Mengecat Dinding M2 688.94 13,062.06 8,998,995.21

11,124,724.21