Anda di halaman 1dari 69

ENGGINER ESTIMATE

( EE )
PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

1. PEKERJAAN PENYIAPAN LAHAN


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME
( Rp ) ( Rp )

A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan demobilisasi alat berat 1.00 Ls 1,500,000.00 1,500,000.00
3 Pembersihan Lokasi Proyek 1.00 Ls 20,000,000.00 20,000,000.00
5 Dokumentasi Proyek 3.00 Set 100,000.00 300,000.00
Sub Total 21,800,000.00
B. PEKERJAAN TANAH
1 Urugan Tanah Peninggian Lahan 1,215.00 m3 435,761.78 529,450,566.78
Sub Total 529,450,566.78

REKAPITULASI

I PEKERJAAN PERSIAPAN 21,800,000.00

II PEKERJAAN TANAH 529,450,566.78

Real Cost 551,250,566.78


PPN 10 % 55,125,056.68
Total Cost 606,375,623.46
Dibulatkan 606,375,000.00
ENGGINEER ESTIMATE
( EE ) DALAM NEGERI
PENINGKATAN EFISIENSI PERDAGANGAN
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

2. BANGUNAN LOS PASAR


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

I PEKERJAAN PERSIAPAN
1 Pas. Bouwplank M' 98.80 84,787.00 8,376,955.60
2 Dokumentasi Proyek Set 3.00 150,000.00 450,000.00
Sub Total 8,826,955.60
II PEKERJAAN TANAH DAN PASIR
1 Pekerjaan Galian Pondasi M3 33.16 41,126.00 1,363,869.76
2 Urugan kembali 1/4 Galian M3 8.29 19,706.00 163,378.50
3 Urugan Pasir Bawah Pondasi M3 393,417.00 0.00
4 Urugan Tanah Bawah Lantai M3 41.18 388,617.00 16,004,802.53
5 Urugan Pasir Bawah Lantai M3 17.16 393,417.00 6,751,035.72
Sub Total 24,283,086.52
III PEKERJAAN STRUKTUR DAN PASANGAN BATU
1 Pasangan Pondasi Camp. 1 : 3 M3 18.05 1,776,642.00 32,064,834.82
2 Pekerjaan Beton Cyclope camp. 1 : 3 : 5 M3 6.16 1,647,224.00 10,146,899.84
3 Pekerjaan kolom gelagar kayu kls. I M' 2.00 6,907,356.00 13,813,330.53
5 Pekerjaan plat meja beton tebal 10 cm M3 4.00 10,876,826.00 43,507,304.00
6 Pekerjaan plat duduk beton tebal 10 cm M3 2.50 10,876,826.00 27,192,065.00
7 Cor lantai slab beton bertulang camp. 1 : 2 : 3 tebal 8 cm M3 26.96 4,437,459.00 119,648,094.51
8 Pas. Rolag Batu Tela Kaki Meja dan Tempat Duduk Camp. 1 : 3 M2 45.60 453,440.00 20,676,864.00
9 Pas. Batu Tela sisi depan meja M2 28.00 226,720.00 6,348,160.00
10 Pekerjaan Plesteran dinding Camp. 1 : 3 M2 147.20 80,167.00 11,800,582.40
11 Pekerjaan Acian Dinding M2 147.20 21,627.00 3,183,494.40
12 Pas. Rolag Batu Tela Penahan Tanah Bawah Lantai Camp. 1 : 3 M2 27.78 453,440.00 12,594,749.44
13 Pekerjaan Plesteran Dinding Rolag Camp. 1 : 3 M2 10.42 80,167.00 835,019.47
14 Pekerjaan Acian Dinding Rolag Lantai M2 10.42 21,627.00 225,266.83
15 Pekerjaan Saluran Air Hujan M' 86.80 200,552.90 17,407,991.72
Sub Total 319,444,656.96
IV PEKERJAAN KAYU DAN ATAP
1 Pekerjaan Kuda-Kuda Kayu Besi 5/10 M3 2.88 6,870,976.00 19,783,003.42
2 Pekerjaan Gording Kayu Kls II 5/10 M3 3.14 5,293,853.00 16,596,229.16
3 Pekerjaan Lesplank Papan Kayu Besi M2 22.65 172,442.97 3,905,833.29
4 Pekerjaan Pasang Atap BJLS 30 M2 402.60 101,330.00 40,795,458.00
5 Pas. Nok Seng Plat BJLS 30 M2 13.24 56,356.00 746,153.44
6 Pas. Balok dudukan jalusi ky. Kls. I 5/10 M3 0.60 7,658,302.00 4,594,981.20
7 Pekerjaan Top Gevel Papan ky. Kls. I + Rangka ky. Kls. II M2 15.40 196,636.00 3,028,194.40
8 Pas. Papan jalusi ky. Kls. I M2 21.10 355,467.00 7,500,353.70
Sub Total 96,950,206.61
V PEKERJAAN LANTAI DAN KERAMIK
1 Plesteran lantai tebal 2 cm M2 343.20 80,167.00 27,513,314.40
2 Pekerjaan Acian Lantai M2 343.20 21,627.00 7,422,386.40
3 Pas. Keramik Meja uk. 30 x 30 M2 40.00 439,950.00 17,598,000.00
Sub Total 52,533,700.80
VIII PEKERJAAN PENGECATAN
2 Pengecatan Rangka Kayu M2 396.85 60,826.00 24,138,967.20
3 Pengecatan Top Gevel M2 15.40 60,826.00 936,720.40
4 Pengecatan Jalusi M2 42.20 60,826.00 2,566,857.20
5 Pengecatan Lesplank M2 22.65 60,826.00 1,377,708.90
Sub Total 29,020,253.70
IX PEKERJAAN INSTALASI LISTRIK
1 Pas. MCB Titik 1.00 123,530.00 123,530.00
2 Pas. Lampu TL 40 Watt Titik 5.00 763,228.00 3,816,140.00
Sub Total 3,939,670.00
XI PEKERJAAN AKHIR
1 Pembersihan Sisa Proyek Ls 1.00 500,000.00 500,000.00
Sub Total 500,000.00
REKAPITULASI

I PEKERJAAN PERSIAPAN 8,826,955.60

II PEKERJAAN TANAH DAN PASIR 24,283,086.52

III PEKERJAAN STRUKTUR DAN PASANGAN BATU 319,444,656.96

IV PEKERJAAN KAYU DAN ATAP 96,950,206.61

V PEKERJAAN LANTAI DAN KERAMIK 52,533,700.80

VIII PEKERJAAN PENGECATAN 29,020,253.70

IX PEKERJAAN INSTALASI LISTRIK 3,939,670.00

XI PEKERJAAN AKHIR 500,000.00

Real Cost 535,498,530.18


PPn 10 % 53,549,853.02
Total Cost 589,048,383.20
4 Unit Los 2,356,193,532.79
Dibulatkan 2,356,193,000.00
ENGGINEER ESTIMATE
( EE )DALAM NEGERI
PENINGKATAN EFISIENSI PERDAGANGAN
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

3. BANGUNAN PETAK KIOS


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi M2 17,136.00 0.00
2 Pas. Bouwplank M' 64.00 84,787.00 5,426,368.00
3 Pembuatan Direksi Keet M2 1,965,041.00 0.00
4 Papan Nama Proyek Bh 1,095,353.00 0.00
5 Dokumentasi Proyek Set 3.00 150,000.00 450,000.00
Sub Total 5,876,368.00
II PEKERJAAN TANAH DAN PASIR
1 Pekerjaan Galian Pondasi M3 133.12 41,126.00 5,474,693.12
2 Urugan kembali 1/4 Galian M3 33.28 19,706.00 655,815.68
3 Urugan Pasir Bawah Pondasi M3 8.32 393,417.00 3,273,229.44
4 Urugan Tanah Bawah Lantai M3 68.43 388,617.00 26,593,061.31
5 Urugan Pasir Bawah Lantai M3 22.81 393,417.00 8,973,841.77
Sub Total 44,970,641.32
III PEKERJAAN STRUKTUR DAN PASANGAN BATU
1 Pas. Batu Kosongan M3 17.76 1,102,892.00 19,587,361.92
2 Pasangan Pondasi Camp. 1 : 3 M3 42.18 1,776,642.00 74,938,759.56
3 Pekerjaan sloef beton 15/20 camp. 1 : 2 : 3 M3 4.44 8,260,888.00 36,678,342.72
4 Pekerjaan kolom beton 10/10 M' 123.10 148,411.64 18,269,472.88
5 Pekerjaan Ringbalk praktis 10/20 M' 196.20 221,587.78 43,475,522.44
6 Cor lantai tanpa tulangan camp. 1 : 3 : 5 tebal 7 cm M3 16.38 1,903,122.00 31,173,138.36
7 Pas. Dinding Batu Tela Camp. 1 : 3 M2 408.39 226,720.00 92,590,180.80
8 Pekerjaan Plesteran dinding Camp. 1 : 3 M2 816.78 80,167.00 65,478,802.26
9 Pekerjaan Acian Dinding M2 816.78 21,627.00 17,664,501.06
10 Pas. Rolag Batu Tela Penahan Tanah Bawah Lantai Camp. 1 : 3 M2 22.54 453,440.00 10,220,537.60
11 Pekerjaan Plesteran Dinding Rolag Camp. 1 : 3 M2 9.66 80,167.00 774,413.22
12 Pekerjaan Acian Dinding Rolag Lantai M2 9.66 21,627.00 208,916.82
13 Pekerjaan Saluran Air Hujan M' 64.40 200,552.90 12,915,606.76
Sub Total 423,975,556.40
IV PEKERJAAN KAYU DAN ATAP
1 Pekerjaan Kuda-Kuda Kayu Besi 5/10 M3 2.36 6,870,976.00 16,193,516.24
2 Pekerjaan Gording Kayu Kls II 5/10 M3 1.84 5,293,853.00 9,746,512.76
3 Pekerjaan Lesplank Papan Kayu Besi M2 16.80 172,442.97 2,897,041.91
4 Pekerjaan Pasang Atap BJLS 30 M2 259.92 101,330.00 26,337,693.60
5 Pas. Nok Seng Plat BJLS 30 M2 8.66 56,356.00 488,268.38
7 Pekerjaan Plafond tripleks 3 mm+ Rangka ky. Kls. II M2 238.26 178,927.00 42,631,147.02
8 Pekerjaan Kusen Kayu Kls. I M3 0.43 8,257,696.00 3,550,809.28
Sub Total 101,844,989.19
V PEKERJAAN LANTAI DAN KERAMIK
1 Screed Lantai M2 234.00 135,188.00 31,633,992.00
2 Pekerjaan Acian Lantai M2 234.00 21,627.00 5,060,718.00
Sub Total 31,633,992.00
VI PEKERJAAN DAUN PINTU, JENDELA, DAN KACA
1 Pek. Daun Pintu Panil M2 66.00 644,324.00 42,525,384.00
Sub Total 42,525,384.00
VII PEKERJAAN KUNCI DAN PENGGANTUNG
1 Pas. Engsel Daun Pintu Bh 180.00 61,547.00 11,078,460.00
6 Pas. Kunci Slot Daun Pintu Bh 40.00 49,574.00 1,982,960.00
7 Pas. Kunci Tanam 2 Slag Biasa Bh 10.00 245,736.00 2,457,360.00
Sub Total 15,518,780.00
VIII PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dalam dan Luar M2 816.78 23,705.00 19,361,769.90
2 Pengecatan Kusen M2 17.20 60,826.00 1,046,207.20
3 Pengecatan Pintu M2 132.00 60,826.00 8,029,032.00
4 Pengecatan Plafond M2 238.26 23,705.00 5,647,953.30
5 Pengecatan Lesplank M2 60,826.00 0.00
Sub Total 34,084,962.40
IX PEKERJAAN INSTALASI LISTRIK
1 Pas. MCB Titik 10.00 123,530.00 1,235,300.00
3 Pas. Lampu TL 40 Watt Titik 10.00 763,228.00 7,632,280.00
4 Pas. Lampu XL 18 Watt Titik 10.00 721,153.00 7,211,530.00
5 Pas. Stop Kontak Titik 10.00 389,547.00 3,895,470.00
Sub Total 19,974,580.00
XI PEKERJAAN AKHIR
1 Pembersihan Sisa Proyek Ls 1.00 500,000.00 500,000.00
Sub Total 500,000.00
REKAPITULASI
A BANGUNAN UTAMA
I PEKERJAAN PERSIAPAN 5,876,368.00
II PEKERJAAN TANAH DAN PASIR 44,970,641.32
III PEKERJAAN STRUKTUR DAN PASANGAN BATU 423,975,556.40
IV PEKERJAAN KAYU DAN ATAP 101,844,989.19
V PEKERJAAN LANTAI DAN KERAMIK 31,633,992.00
VI PEKERJAAN DAUN PINTU, JENDELA, DAN KACA 42,525,384.00
VII PEKERJAAN KUNCI DAN PENGGANTUNG 15,518,780.00
VIII PEKERJAAN PENGECATAN 34,084,962.40
IX PEKERJAAN INSTALASI LISTRIK 19,974,580.00
XI PEKERJAAN AKHIR 500,000.00
Real Cost 720,905,253.31
PPn 10 % 72,090,525.33
Total Cost 792,995,778.64
10 Unit Kios 7,929,957,786.43
Dibulatkan 7,929,957,000.00
ENGGINEER ESTIMATE
( EE ) DALAM NEGERI
PENINGKATAN EFISIENSI PERDAGANGAN
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

4. FASILITAS TOILET UMUM


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

I PEKERJAAN PERSIAPAN
1 Pas. Bouwplank M' 24.00 84,787.00 2,034,888.00
2 Dokumentasi Proyek Set 3.00 100,000.00 300,000.00
Sub Total 2,334,888.00
II PEKERJAAN TANAH DAN PASIR
1 Pekerjaan Galian Pondasi M3 10.56 41,126.00 434,290.56
2 Urugan kembali 1/4 Galian M3 2.64 19,706.00 52,023.84
3 Urugan Pasir Bawah Pondasi M3 0.66 393,417.00 259,655.22
4 Urugan Tanah Bawah Lantai M3 5.00 388,617.00 1,943,085.00
5 Urugan Pasir Bawah Lantai M3 1.25 393,417.00 491,771.25
Sub Total 3,180,825.87
III PEKERJAAN STRUKTUR DAN PASANGAN BATU
1 Pas. Batu Kosongan M3 1.98 1,102,892.00 2,183,726.16
2 Pasangan Pondasi Camp. 1 : 3 M3 4.70 1,776,642.00 8,354,659.01
3 Pekerjaan Sloof 15/20 M3 0.50 8,260,888.00 4,089,139.56
4 Pekerjaan kolom praktis 10/10 M' 28.80 148,411.64 4,274,255.23
5 Pekerjaan ringbalk praktis 10/20 M' 18.00 221,587.78 3,988,580.04
6 Cor lantai tanpa tulangan camp. 1 : 3 : 5 tebal 5 cm M3 1.25 1,903,122.00 2,378,902.50
7 Pas. Batu Tela Camp. 1 : 3 M2 52.59 226,720.00 11,923,204.80
8 Pekerjaan Plesteran dinding Camp. 1 : 3 M2 105.18 80,167.00 8,431,965.06
9 Pekerjaan acian dinding M2 105.18 21,627.00 2,274,727.86
10 Pas. Rolag Batu Tela Dinding Lantai Rabat Camp. 1 : 3 M2 6.00 453,440.00 2,720,640.00
11 Pekerjaan Saluran Air Hujan M' 20.00 200,552.90 4,011,058.00
Sub Total 54,630,858.22
IV PEKERJAAN KAYU DAN ATAP
1 Pekerjaan Kuda-Kuda Kayu Besi 5/10 M3 0.80 6,870,976.00 5,496,780.80
2 Pekerjaan Gording Kayu Kls II 5/10 M3 0.41 5,677,476.00 2,327,765.16
3 Pekerjaan Lesplank Papan Kayu Besi M2 6.00 62,607.00 375,642.00
4 Pekerjaan Pasang Atap BJLS 30 M2 35.68 101,330.00 3,615,454.40
5 Pas. Nok Seng Plat BJLS 30 M2 5.10 56,356.00 287,415.60
6 Pekerjaan Plafond tripleks 3 mm+ Rangka ky. Kls. II M2 25.00 178,927.00 4,473,175.00
7 Pekerjaan Kusen Kayu Kls. I M3 0.08 8,257,696.00 631,713.74
8 Pasang papan jalusi ky. Kls. I M2 0.42 355,467.00 149,296.14
Sub Total 17,357,242.84
V PEKERJAAN LANTAI DAN KERAMIK
1 Ssreed Lantai M2 16.00 135,188.00 2,163,008.00
2 Acian Lantai M2 16.00 21,627.00 346,032.00
Sub Total 2,509,040.00
VI PEKERJAAN DAUN PINTU, JENDELA, DAN KACA
1 Pek. Daun Pintu Panil M2 2.94 644,324.00 1,894,312.56

Sub Total 1,894,312.56


VII PEKERJAAN KUNCI DAN PENGGANTUNG
1 Pas. Engsel Daun Pintu Bh 6.00 61,547.00 369,282.00
2 Pas. Kunci Slot Daun Pintu Bh 2.00 49,574.00 99,148.00
3 Pas. Kunci Tanam 2 Slag Biasa Bh 2.00 245,736.00 491,472.00
Sub Total 959,902.00
VIII PEKERJAAN PENGECATAN
1 Pengecatan Dinding Dalam dan Luar M2 105.18 23,705.00 2,493,291.90
2 Pengecatan Kusen M2 3.06 60,826.00 186,127.56
3 Pengecatan Jalusi M2 0.84 60,826.00 51,093.84
4 Pengecatan Pintu Panil M2 5.88 60,826.00 357,656.88
5 Pengecatan Plafond M2 25.00 23,705.00 592,625.00
6 Pengecatan Lesplank M2 6.00 60,826.00 364,956.00
Sub Total 4,045,751.18
IX PEKERJAAN INSTALASI LISTRIK
1 Pas. MCB Titik 1.00 123,530.00 123,530.00
2 Pas. Lampu XL 18 Watt Titik 2.00 721,153.00 1,442,306.00
3 Pas. Lampu XL 8 Watt Titik 2.00 683,028.00 1,366,056.00
Sub Total 2,931,892.00
X PEKERJAAN SANITAIR
1 Pembuatan Septic Tank Ls 1.00 3,801,391.00 3,801,391.00
2 Pek. Bak air tanpa keramik Bh 2.00 962,894.00 1,925,788.00
3 Pas. Pipa 3" Pembuangan KM/WC M' 5.00 175,449.00 877,245.00
4 Pas. Pipa 4" Pembuangan Septic Tank M' 10.00 197,304.00 1,973,040.00
5 Pas. Kran air Titik 2.00 53,164.00 106,328.00
6 Pas. Pipa air bersih 1/2" M' 10.00 33,293.00 332,930.00
7 Pas. Floor Drain Bh 2.00 84,464.00 168,928.00
8 Pas. Closed Jongkok Bh 2.00 797,410.00 1,594,820.00
Sub Total 10,780,470.00
XI PEKERJAAN AKHIR
1 Pembersihan Sisa Proyek Ls 1.00 500,000.00 500,000.00
Sub Total 500,000.00
REKAPITULASI AKHIR

I. PEKERJAAN PENDAHULUAN 2,334,888.00


II. PEKERJAAN TANAH DAN GALIAN 3,180,825.87
III. PEKERJAAN STRUKTUR DAN PASANGAN BATU 54,630,858.22
IV. PEKERJAAN KAYU DAN ATAP 17,357,242.84
V. PEKERJAAN LANTAI DAN KERAMIK 2,509,040.00
VI. PEKERJAAN DAUN PINTU, JENDELA, DAN KACA 1,894,312.56
VII. PEKERJAAN KUNCI DAN PENGGANTUNG 959,902.00
VIII. PEKERJAAN PENGECATAN 4,045,751.18
IX. PEKERJAAN INSTALASI LISTRIK 2,931,892.00
X. PEKERJAAN SANITAIR 10,780,470.00
XI. PEKERJAAN AKHIR 500,000.00
Real Cost 101,125,182.67
PPn 10 % 10,112,518.27
Total Cost 111,237,700.94
2 Unit Toilet 222,475,401.88
Dibulatkan 222,475,000.00
ENGGINEER ESTIMATE
( EE )DALAM NEGERI
PENINGKATAN EFISIENSI PERDAGANGAN
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

5. FASILITAS SUMUR GALI


HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

I PEKERJAAN PERSIAPAN
1 Pas. Bouwplank M' 20.00 84,787.00 1,695,740.00
2 Dokumentasi Proyek Set 3.00 100,000.00 300,000.00
Sub Total 1,995,740.00
II PEKERJAAN TANAH DAN PASIR
1 Pekerjaan Galian Sumur M3 12.00 41,126.00 493,512.00
2 Urugan kembali 1/4 Galian M3 3.00 19,706.00 59,118.00
3 Urugan Pasir Bawah Pondasi M3 0.30 393,417.00 118,025.10
4 Urugan koral/kerikil dasar sumur M3 0.16 388,617.00 60,624.25
5 Urugan Pasir dasar sumur M3 0.04 393,417.00 15,343.26
Sub Total 746,622.62
III PEKERJAAN STRUKTUR DAN PASANGAN BATU
1 Cor lantai kerja bawah poor camp. 1 : 3 : 5 M3 0.30 1,903,122.00 570,936.60
2 Pasangan pondasi titik poer camp. 1 : 2 : 3 besi 150 kg M3 1.20 1,647,224.00 1,976,668.80
3 Pek. Sloef beton bertulang camp. 1 : 2 : 3 uk. 15x30 besi 155 kg M3 0.54 9,654,912.00 5,170,205.38
4 Pek. kolom pedestal camp. 1 : 2 : 3 uk. 30x30 besi 120 kg M3 0.32 8,678,863.00 2,811,951.61
6 Pekerjaan menara air rangka besi siku 60x60x6 Kg 699.72 55,369.00 38,742,907.42
7 Pek. rangka lantai dan reiling menara air besi siku 40x40x4 Kg 145.20 55,369.00 8,039,578.80
8 Pas. Lantai papan ky. Kls. I 1"/20 M2 8.00 330,046.00 2,640,368.00
9 Pas. Cincin beton tanpa tulangan camp. 1 : 2 : 3 tebal 10 cm bh 5.00 2,665,559.00 13,327,795.00
10 Cor lantai tanpa tulangan t = 7 cm camp. 1 : 3 : 5 M3 1.12 1,903,122.00 2,131,496.64
11 Pas. Batu Tela Penahan Tanah Bawah Lantai Camp. 1 : 3 M2 4.80 226,720.00 1,088,256.00
12 Pekerjaan Plesteran Dinding Rolag Camp. 1 : 3 M2 2.56 80,167.00 205,227.52
13 Pekerjaan Acian Dinding Rolag Lantai M2 2.56 21,627.00 55,365.12
14 Pekerjaan Saluran Air Hujan M' 16.00 200,552.90 3,208,846.40
Sub Total 79,969,603.29
V PEKERJAAN LANTAI DAN KERAMIK
1 Screed Lantai M2 16.00 135,188.00 2,163,008.00
2 Pekerjaan Acian Lantai M2 16.00 21,627.00 346,032.00
Sub Total 2,509,040.00
VIII PEKERJAAN SANITAIR
1 Pasang Profil tank kap. 1200 Ltr. bh 2.00 3,000,000.00 6,000,000.00
2 Pengadaan+pasang instalasi filter air bersih setara ex. Yamaha Set 1.00 12,000,000.00 12,000,000.00
3 Penyediaan mesin pompa air setara ex. sanyo Unit 1.00 5,000,000.00 5,000,000.00
4 Pasag Pipa penyedot PVC 3/4" M' 10.00 36,258.00 362,580.00
5 Pasang Pipa distribusi PVC 1/2" M' 30.00 33,293.00 998,790.00
6 Pasang Gate Valve 3/4" bh 1.00 1,500,000.00 1,500,000.00
7 Pasang kran air bh 2.00 53,164.00 106,328.00
8 Pasang floor drain bh 1.00 84,464.00 84,464.00
Sub Total 26,052,162.00
IX PEKERJAAN INSTALASI LISTRIK
1 Pas. MCB Titik 1.00 123,530.00 123,530.00
2 Pas. Saklar Tunggal Titik 3.00 387,110.00 1,161,330.00
3 Pas. Stop kontak Titik 1.00 389,547.00 389,547.00
Sub Total 1,674,407.00
XI PEKERJAAN AKHIR
1 Pembersihan Sisa Proyek Ls 1.00 500,000.00 500,000.00
Sub Total 500,000.00
REKAPITULASI

I PEKERJAAN PERSIAPAN 1,995,740.00

II PEKERJAAN TANAH DAN PASIR 746,622.62

III PEKERJAAN STRUKTUR DAN PASANGAN BATU 79,969,603.29

V PEKERJAAN LANTAI DAN KERAMIK 2,509,040.00

VIII PEKERJAAN PENGECATAN 26,052,162.00

IX PEKERJAAN INSTALASI LISTRIK 1,674,407.00

XI PEKERJAAN AKHIR 500,000.00

Real Cost 113,447,574.90


PPn 10% 11,344,757.49
Total Cost 124,792,332.39
2 Unit Sumur Gali 249,584,664.78
Dibulatkan 249,584,000.00
ENGGINEER ESTIMATE
( EE )
PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

6. POS RETRIBUSI

NO. ITEM PEKERJAAN VOLUME HARGA SATUAN TOTAL HARGA

I PEKERJAAN PENDAHULUAN
Pas. Bouwplank 30.00 m' 84,787.00 2,543,610.00
Dokumentasi proyek 3.00 Set 100,000.00 300,000.00
Sub Total 2,843,610.00
II PEKERJAAN TANAH DAN PASIR
Pekerjaan Galian Pondasi 14.00 m3 41,126.00 575,764.00
Urugan kembali 1/4 Galian 3.50 m3 19,706.00 68,971.00
Urugan Pasir Bawah Pondasi 0.70 m3 393,417.00 275,391.90
Urugan Tanah Bawah Lantai 5.20 m3 388,617.00 2,020,808.40
Urugan Pasir Bawah Lantai 1.30 m3 393,417.00 511,442.10
Sub Total 3,452,377.40
III PEKERJAAN PASANGAN, BATU DAN BETON
Pas. Batu Kosongan 2.10 m3 1,102,892.00 2,316,073.20
Pasangan Pondasi Camp. 1 : 3 4.99 m3 1,776,642.00 8,861,001.98
Pekerjaan Sloof 15/20 0.53 m3 8,260,888.00 4,336,966.20
Pekerjaan kolom 20/20 0.45 m3 8,678,863.00 3,866,433.47
Pekerjaan ringbalk 10/20 17.50 m3 221,587.78 3,877,786.15
Pekerjaan dinding batu tela camp. 1 : 3 37.50 m2 226,720.00 8,502,000.00
Pekerjaan plesteran camp. 1 : 3 75.00 m2 80,167.00 6,012,525.00
Pekerjaan kolom praktis 10/10 1.00 m' 148,411.64 148,411.64
Cor balok 10/20 6.50 m' 221,587.78 1,440,320.57
Pekerjaan acian dinding 75.00 m2 21,627.00 1,622,025.00
Pasangan Rolag batu tela camp. 1 : 3 6.30 m3 226,720.00 1,428,336.00
Pekerjaan Saluran Air Hujan 26.00 m' 0.00
Sub Total 42,411,879.20
IV PEKERJAAN ATAP DAN PLAFOND
Pekerjaan Kuda-Kuda Kayu Besi 5/10 1.09 m3 6,870,976.00 7,489,363.84
Pekerjaan Gording Kayu Kls II 5/10 0.98 m3 5,677,476.00 5,584,933.14
Pekerjaan Lesplank Papan Kayu Besi 6.40 m2 62,607.00 400,684.80
Pasang Atap Seng BJLS 30 60.20 m2 101,330.00 6,100,066.00
Pasang Nok seng plat BJLS 30 8.13 m2 56,356.00 458,061.57
Pekerjaan Plafond 3 mm+ Rangka ky. Kls. II 16.00 m2 178,927.00 2,862,832.00
Sub Total 22,895,941.35
V PEKERJAAN LANTAI
Cor lantai kerja dan Lantai Rabat 1.82 m3 1,903,122.00 3,463,682.04
Screed lantai 26.00 m2 135,188.00 3,514,888.00
Acian lantai 26.00 m2 21,627.00 562,302.00
ENGGINEER ESTIMATE
( EE )
PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

6. POS RETRIBUSI

Sub Total 7,540,872.04


ENGGINEER ESTIMATE
( EE )
PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

6. POS RETRIBUSI

VI PEKERJAAN KUSEN, DAUN PINTU, JENDELA, DAN KACA


Pekerjaan Kusen Kayu besi 0.10 m3 8,257,696.00 825,769.60
Pek. Daun Pintu Panil 1.68 m2 644,324.00 1,082,464.32
Pas. Daun Jendela Panil Kaca 1.43 m2 837,779.00 1,198,023.97
Sub Total 3,106,257.89
VII PEKERJAAN KUNCI DAN PENGGANTUNG
Pas. Engsel Daun Pintu 3.00 Bh 61,547.00 184,641.00
Pas. Kunci Tanam 2 Slag 1.00 Bh 245,736.00 245,736.00
Pas. Engsel Daun Jendela Panil 4.00 Bh 32,776.00 131,104.00
Pas. Handle Jendela 2.00 Bh 35,977.00 71,954.00
Pas. Hak Angin 4.00 Bh 82,727.00 330,908.00
Pas. Grendel Jendela 4.00 Bh 49,574.00 198,296.00
Sub Total 1,162,639.00
VIII PEKERJAAN PENGECATAN
Pengecatan Dinding Interior 75.00 m2 23,705.00 1,777,875.00
Pengecatan Kusen 4.00 m2 60,826.00 243,304.00
Pengecatan Pintu Panil 3.36 m2 60,826.00 204,375.36
Pengecatan Daun Jendela Panil 0.57 m2 60,826.00 34,792.47
Pengecatan Plafond 16.00 m2 23,705.00 379,280.00
Pengecatan Lesplank 6.40 m2 60,826.00 389,286.40
Sub Total 3,028,913.23
IX PEKERJAAN INSTALASI LISTRIK
Pas. MCB 1.00 bh 123,530.00 123,530.00
Pas. Lampu XL 18 Watt 2.00 titik 721,153.00 1,442,306.00
Pas. Stop Kontak 1.00 titik 389,547.00 389,547.00
Sub Total 1,955,383.00
X PEKERJAAN AKHIR
Pembersihan akhir sisa proyek 1.00 Ls 300,000.00 300,000.00
Sub Total 300,000.00
ENGGINEER ESTIMATE
( EE )
PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

6. POS RETRIBUSI

REKAPITULASI BIAYA FISIK

I PEKERJAAN PENDAHULUAN 2,843,610.00


II PEKERJAAN TANAH DAN PASIR 3,452,377.40
III PEKERJAAN PASANGAN, BATU DAN BETON 42,411,879.20
IV PEKERJAAN ATAP DAN PLAFOND 22,895,941.35
V PEKERJAAN LANTAI 7,540,872.04
VI PEKERJAAN KUSEN, DAUN PINTU, JENDELA, DAN KACA 3,106,257.89
VII PEKERJAAN KUNCI DAN PENGGANTUNG 1,162,639.00
VIII PEKERJAAN PENGECATAN 3,028,913.23
IX PEKERJAAN INSTALASI LISTRIK 1,955,383.00
X PEKERJAAN AKHIR 300,000.00

REAL COAST 88,697,873.11

PPN 10 % 8,869,787.31
Total Cost 97,567,660.42
Dibulatkan 97,567,000.00
ENGGINEER ESTIMATE
( EE ) DALAM NEGERI
PENINGKATAN EFISIENSI PERDAGANGAN
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

7. PANGKALAN OJEK
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

I PEKERJAAN PERSIAPAN
1 Pas. Bouwplank M' 36.00 84,787.00 3,052,332.00
2 Dokumentasi Proyek Set 3.00 100,000.00 300,000.00
Sub Total 3,352,332.00
II PEKERJAAN TANAH DAN PASIR
1 Pekerjaan Galian Pondasi M3 0.69 41,126.00 28,294.69
2 Urugan Tanah Bawah Lantai M3 3.30 388,617.00 1,282,436.10
3 Urugan Pasir Bawah Lantai M3 1.38 393,417.00 540,948.38
Sub Total 1,851,679.16
III PEKERJAAN STRUKTUR DAN PASANGAN BATU
1 Pekerjaan Beton Cyclope camp. 1 : 3 : 5 M3 1.60 1,647,224.00 2,635,558.40
2 Pekerjaan kolom kayu kls. I M' 0.36 6,907,356.00 2,472,833.45
3 Pekerjaan plat duduk beton tebal 10 cm M 3
0.39 10,876,826.00 4,241,962.14
4 Cor lantai tanpa tulangan camp. 1 : 3 : 5 tebal 7 cm M3 1.93 1,903,122.00 3,663,509.85
5 Pas. Batu Tela Kaki Meja dan Tempat Duduk Camp. 1 : 3 M2 2.25 226,720.00 510,120.00
6 Pekerjaan Plesteran dinding Camp. 1 : 3 M2 4.50 80,167.00 360,751.50
7 Pekerjaan Acian Dinding M2 4.50 21,627.00 97,321.50
8 Pas. Rolag Batu Tela Penahan Tanah Bawah Lantai Camp. 1 : 3 M2 8.70 453,440.00 3,944,928.00
9 Pekerjaan Plesteran Dinding Rolag Camp. 1 : 3 M2 4.35 80,167.00 348,726.45
10 Pekerjaan Acian Dinding Rolag Lantai M2 4.35 21,627.00 94,077.45
Sub Total 18,369,788.74
IV PEKERJAAN KAYU DAN ATAP
1 Pekerjaan Kuda-Kuda Kayu Besi 5/10 M3 0.21 6,870,976.00 1,444,279.16
2 Pekerjaan Gording Kayu Kls II 5/10 M 3
0.50 5,293,853.00 2,668,101.91
3 Pekerjaan Lesplank Papan Kayu Besi M2 8.00 172,442.97 1,379,543.77
4 Pekerjaan Pasang Atap BJLS 30 M2 60.48 101,330.00 6,128,438.40
5 Pas. Nok Seng Plat BJLS 30 M2 2.24 56,356.00 126,237.44
Sub Total 11,746,600.68
V PEKERJAAN LANTAI DAN KERAMIK
1 Screed Lantai M2 27.50 135,188.00 3,717,670.00
2 Acian Lantai M2 27.50 21,627.00 594,742.50
Sub Total 4,312,412.50
VIII PEKERJAAN PENGECATAN
1 Pengecatan Rangka Kayu M2 64.33 60,826.00 3,913,058.23
### Pengecatan Lesplank M 2
8.00 60,826.00 486,608.00
Sub Total 4,399,666.23
IX PEKERJAAN INSTALASI LISTRIK
1 Pas. Sekring Khas 2 Group Titik 1.00 123,530.00 123,530.00
2 Pas. Lampu TL 40 Watt Titik 1.00 763,228.00 763,228.00
Sub Total 886,758.00
XI PEKERJAAN AKHIR
1 Pembersihan Sisa Proyek Ls 1.00 300,000.00 300,000.00
Sub Total 300,000.00

REKAPITULASI
A BANGUNAN UTAMA
I PEKERJAAN PERSIAPAN 3,352,332.00
II PEKERJAAN TANAH DAN PASIR 1,851,679.16
III PEKERJAAN STRUKTUR DAN PASANGAN BATU 18,369,788.74
IV PEKERJAAN KAYU DAN ATAP 11,746,600.68
V PEKERJAAN LANTAI DAN KERAMIK 4,312,412.50
VIII PEKERJAAN PENGECATAN 4,399,666.23
IX PEKERJAAN INSTALASI LISTRIK 886,758.00
XI PEKERJAAN AKHIR 300,000.00
Real Cost 45,219,237.31
PPn 10 % 4,521,923.73
Total Cost 49,741,161.04
2 Unit Pangkalan 99,482,322.08
Dibulatkan 99,482,000.00
ENGGINEER ESTIMATE
( EE )
PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

8. PAGAR KELILING
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SAT VOLUME
( Rp ) ( Rp )
1 2 3 4 5 6 = (4 x 5)

I PEKERJAAN PERSIAPAN
1 Pembersihan lokasi Ls 1.00 700,000.00 700,000.00
2 Pas. Bouwplank dan Pengukuran M' 1.00 1,000,000.00 1,000,000.00
Sub Total 1,700,000.00
II PEKERJAAN TANAH DAN PASIR
1 Pekerjaan Galian Pondasi M3 165.12 41,126.00 6,790,725.12
2 Urugan kembali Galian Pondasi M3
41.28 19,706.00 813,463.68
3 Urugan Pasir Bawah Pondasi M3
10.32 393,417.00 4,060,063.44
Sub Total 11,664,252.24
III PEKERJAAN STRUKTUR DAN PASANGAN BATU
1 Pas. Batu Kosongan M3 46.08 1,102,892.00 50,821,263.36
2 Pasangan Pondasi Camp. 1 : 3 M3
109.44 1,776,642.00 194,435,700.48
3 Pekerjaan Sloof 15/20 M3
11.52 8,260,888.00 95,165,429.76
4 Pekerjaan Kolom 30/30 M3 18.58 7,424,938.00 137,925,648.29
5 Pekerjaan Ringbalk 15/20 M' 11.52 8,260,888.00 95,165,429.76
6 Pas. Batu Tela Camp. 1 : 3 M2 393.80 226,720.00 89,282,336.00
7 Pekerjaan Plesteran dinding Camp. 1 : 3 M2
787.60 80,167.00 63,139,529.20
8 Pembuatan papan nama dari bahan adukan (spesi) Ls 1.00 1,000,000.00 1,000,000.00
9 Pek. Plesteran Penebalan Kolom Camp. 1 : 3 (sisi depan ) M2 61.44 80,167.00 4,925,460.48
10 Pekerjaan Les profilan dinding L = 5 cm M' 264.00 23,744.00 6,268,416.00
11 Pekerjaan Acian dinding M2 849.04 21,627.00 18,362,188.08
Sub Total 756,491,401.41
IV PEKERJAAN PENGECATAN
1 Pengecatan Dinding M2 849.04 23,705.00 20,126,493.20
Sub Total 20,126,493.20
V PEKERJAAN AKHIR
1 Pembersihan Sisa Proyek Ls 1.00 1,000,000.00 1,000,000.00
Sub Total 1,000,000.00
REKAPITULASI

I PEKERJAAN PERSIAPAN 1,700,000.00

II PEKERJAAN TANAH DAN PASIR 11,664,252.24

III PEKERJAAN STRUKTUR DAN PASANGAN BATU 756,491,401.41

IV PEKERJAAN PENGECATAN 20,126,493.20

V PEKERJAAN AKHIR 1,000,000.00

Real Cost 790,982,146.85


PPN 10 % 79,098,214.68
Total Cost 870,080,361.53
Dibulatkan 870,080,000.00
ENGGINER ESTIMATE
( EE )
PENINGKATAN EFISIENSI PERDAGANGAN DALAM NEGERI
PROGRAM :
PEKERJAAN : PERENCANAAN TEKNIS PEMBANGUNAN PASAR SENTRAL WAROPEN
LOKASI : SP-5, DISTRIK UREI FAISEI-KABUPATEN WAROPEN
T/A : 2015

9. LANDSCAPING
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN VOLUME
( Rp ) ( Rp )

A. PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 1.00 Ls 3,000,000.00 3,000,000.00
2 Dokumentasi Proyek 0.00
Sub Total 3,000,000.00
B. PEKERJAAN PENATAAN HALAMAN
1 Pas. Paving Blok 3,698.00 m2 265,036.00 980,103,128.00
2 Cor Kerb Camp. 1 : 3 : 5 20.32 m3 1,903,122.00 38,669,535.92
3 Urugan Pasir Bawah Lantai Cor 66.20 m3 393,417.00 26,044,205.40
4 Cor Lantai Sisi Dalam Area Pasar Camp. 1 : 3 : 5 1,324.00 m2 210,182.00 278,280,968.00
5 Pekerjaan Gorong-gorong
Pas. Batu kali/karang camp. 1 : 3 6.40 m3 1,776,642.00 11,370,508.80
Cor lantai saluran camp. 1 : 3 : 5 0.60 m3 1,903,122.00 1,141,873.20
Plesteran dinding saluran camp. 1 : 3 40.00 m2 80,167.00 3,206,680.00
Cor plat beton bertulang camp. 1 : 2 : 3 3.36 m3 8,064,022.00 27,095,113.92
6 Pas. Saluran Air hujan Camp. 1 : 3 368.00 m' 200,552.90 73,803,467.20
Sub Total 1,439,715,480.44

REKAPITULASI

I PEKERJAAN PERSIAPAN 3,000,000.00

II PEKERJAAN PENATAAN HALAMAN 1,439,715,480.44

Real Cost 1,442,715,480.44


PPN 10 % 144,271,548.04
Total Cost 1,586,987,028.48
Dibulatkan 1,586,987,000.00
REKAPITULASI

A. BIAYA PEKERJAAN FISIK

1. PEKERJAAN PENYIAPAN LAHAN 606,375,000.00

2. PEKERJAAN PEMBANGUNAN LOS PASAR 2,356,193,000.00

3. PEKERJAAN PEMBANGUNAN KIOS PASAR 7,929,957,000.00

4. PEKERJAAN PEMBANGUNAN TOILET UMUM 222,475,000.00

5. PEKERJAAN FASILITAS SUMUR GALI 249,584,000.00

6. PEKERJAAN PEMBANGUNAN POS RETRIBUSI 97,567,000.00

7. PEKERJAAN PEMBANGUNAN PANGKALAN OJEK 99,482,000.00

8. PEKERJAAN PAGAR KELILING 870,080,000.00

9. LANDSCAPING 1,586,987,000.00

TOTAL COST 14,018,700,000.00


B. BIAYA PERENCANAAN 560,740,000.00
C. BIAYA PENGAWASAN 420,560,000.00
GRAND TOTAL 15,000,000,000.00

TERBILANG : LIMA BELAS MILYAR RUPIAH

Waropen, Oktober 2015

DIPERIKSA : DISUSUN OLEH :


KEPALA BIDANG CIPTA KARYA DINAS PEKERJAAN UMUM CV. ASCOM KONSULTAN
KABUPATEN WAROPEN

JOHN A. F. TUAR, ST. SAPARUDDIN MD., ST.


NIP. 19660420 199712 1 002 Ka. Perwakilan

MENGETAHUI/MENYETUJUI :
KEPALA DINAS PERINDUSTRIAN, PERDAGANGAN, KOPERASI, DAN UKM
KABUPATEN WAROPEN

DEMIANUS ERARI
NIP. 19591222 198303 1 017
ANALISA SATUAN PEKERJAAN BETON
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN BETON
SNI 1.0000 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
6.13 336.0000 kg PC @ Rp. 2,856.25 959,700.00
0.5400 m3 Pasir beton @ Rp. 766,000.00 413,640.00
0.8100 m 3
Kerikil beton @ Rp. 787,000.00 637,470.00
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 2,010,810.00 2,208,259.56
DIBULATKAN 197,449.00 2,010,810.00 2,208,259.00

SNI 1.0000 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr


6.1 218.0000 kg PC @ Rp. 2,856.25 622,662.50
0.5200 m 3
Pasir beton @ Rp. 766,000.00 398,320.00
0.8700 m 3
Kerikil beton @ Rp. 787,000.00 684,690.00
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 1,705,672.50 1,903,122.06
DIBULATKAN 197,449.00 1,705,672.00 1,903,122.00

1.0000 m2 Membuat lantai beton tanpa tulangan, 1 Pc : 3 Ps : 6 Kr tebal 7 cm dan finishing plester
18.2000 kg PC @ Rp. 2,856.25 51,983.75
0.0440 m3 Pasir pasang @ Rp. 333,200.00 14,660.80
0.0700 m3 Kerikil beton @ Rp. 787,000.00 55,090.00
0.1350 org Tukang batu @ Rp. 137,088.00 18,506.88
0.0135 org Kepala tukang batu @ Rp. 154,224.00 2,082.02
0.7200 org Pekerja @ Rp. 85,680.00 61,689.60
0.0360 org Mandor @ Rp. 171,360.00 6,168.96
JUMLAH 88,447.46 121,734.55 210,182.01
DIBULATKAN 88,447.00 121,734.00 210,182.00

AK 1.0000 m3 Beton cyclope 1pc:3ps:5kr


0.7000 m3 Batu kali @ Rp. 900,000.00 630,000.00
61.2500 kg PC @ Rp. 2,856.25 174,945.31
0.4000 m3 Pasir pasang @ Rp. 333,200.00 133,280.00
0.6500 m 3
Kerikil beton @ Rp. 787,000.00 511,550.00
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kep. Tk. Batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 1,449,775.31 1,647,224.87
DIBULATKAN 197,449.00 1,449,775.00 1,647,224.00

SNI 1.0000 m3 Membuat beton bertulang, 1 Pc : 1,5 Ps : 2,5 Kr


6.16 400.0000 kg PC @ Rp. 2,856.25 1,142,500.00
0.4800 m 3
Pasir beton @ Rp. 766,000.00 367,680.00
0.8000 m3 Kerikil beton @ Rp. 787,000.00 629,600.00
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 2,139,780.00 2,337,229.56
DIBULATKAN 197,449.00 2,139,780.00 2,337,229.00

SNI 1.0000 m3 Membuat beton dengan mutu K 175


6.36 326.0000 kg PC @ Rp. 2,856.25 931,137.50
0.5428 m 3
Pasir beton @ Rp. 766,000.00 415,784.80
0.7622 m3 Kerikil beton @ Rp. 787,000.00 599,851.40
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 1,946,773.70 2,144,223.26
DIBULATKAN 197,449.00 1,946,773.00 2,144,223.00

SNI 1.0000 m3 Membuat beton dengan mutu K 200


6.36 352.0000 kg PC @ Rp. 2,856.25 1,005,400.00
0.5221 m3 Pasir beton @ Rp. 766,000.00 399,928.60
0.7637 m 3
Kerikil beton @ Rp. 787,000.00 601,031.90
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 2,006,360.50 2,203,810.06
DIBULATKAN 197,449.00 2,006,360.00 2,203,810.00

SNI 1.0000 m3 Membuat beton dengan mutu K 225


6.35 388.0000 kg PC @ Rp. 2,856.25 1,108,225.00
0.6500 m3 Pasir beton @ Rp. 766,000.00 497,900.00
0.6500 m 3
Kerikil beton @ Rp. 787,000.00 511,550.00
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 2,117,675.00 2,315,124.56
DIBULATKAN 197,449.00 2,117,675.00 2,315,124.00

SNI 1.0000 m3 Membuat beton dengan mutu K 250


6.36 384.0000 kg PC @ Rp. 2,856.25 1,096,800.00
0.4943 m 3
Pasir beton @ Rp. 900,000.00 444,870.00
0.7696 m3 Kerikil beton @ Rp. 895,000.00 688,792.00
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 2,230,462.00 2,427,911.56
DIBULATKAN 197,449.00 2,230,462.00 2,427,911.00

SNI 1.0000 m3 Membuat beton dengan mutu K 275


6.36 406.0000 kg PC @ Rp. 2,856.25 1,159,637.50
0.4886 m3 Pasir beton @ Rp. 1,012,500.00 494,707.50
0.7600 m 3
Kerikil beton @ Rp. 787,000.00 598,120.00
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 2,252,465.00 2,449,914.56
DIBULATKAN 197,449.00 2,252,465.00 2,449,914.00
1.0000 m3 Membuat beton dengan mutu K 300
413.0000 kg PC @ Rp. 2,856.25 1,179,631.25
0.4864 m 3
Pasir beton @ Rp. 1,012,500.00 492,480.00
0.7563 m3 Kerikil beton @ Rp. 787,000.00 595,208.10
0.2750 org Tukang batu @ Rp. 137,088.00 37,699.20
0.0275 org Kepala tukang batu @ Rp. 154,224.00 4,241.16
1.6500 org Pekerja @ Rp. 85,680.00 141,372.00
0.0825 org Mandor @ Rp. 171,360.00 14,137.20
JUMLAH 197,449.56 2,267,319.35 2,464,768.91
DIBULATKAN 197,449.00 2,267,319.00 2,464,768.00

SNI 1.0000 kg Pembesian dengan besi polos


6.25 1.0500 kg Besi beton polos @ Rp. 24,400.00 25,620.00
0.0150 kg Kawat beton @ Rp. 34,563.00 518.45
0.0070 org Tukang besi @ Rp. 137,088.00 959.62
0.0007 org Kepala tukang besi @ Rp. 154,224.00 107.96
0.0070 org Pekerja @ Rp. 85,680.00 599.76
0.0004 org Mandor @ Rp. 171,360.00 59.98
JUMLAH 1,727.31 26,138.45 27,865.75
DIBULATKAN 1,727.00 26,138.00 27,865.00

SNI 1.0000 kg Pembesian dengan besi ulir


6.25 1.0500 kg Besi beton ulir @ Rp. 24,400.00 25,620.00
0.0150 kg Kawat beton @ Rp. 34,563.00 518.45
0.0070 org Tukang besi @ Rp. 137,088.00 959.62
0.0007 org Kepala tukang besi @ Rp. 154,224.00 107.96
0.0070 org Pekerja @ Rp. 85,680.00 599.76
0.0004 org Mandor @ Rp. 171,360.00 59.98
JUMLAH 1,727.31 26,138.45 27,865.75
DIBULATKAN 1,727.00 26,138.00 27,865.00

F.8 1.0000 m2 Cetakan beton / begisting memakai papan


0.0170 m3 Usuk ky. Kls. II @ Rp. 3,135,000.00 53,295.00
0.0240 m 3
Papan cetakan @ Rp. 3,135,000.00 75,240.00
0.4000 kg Paku @ Rp. 27,325.00 10,930.00
0.5000 org Tukang kayu @ Rp. 137,088.00 68,544.00
0.0500 org Kep. Tk. Kayu @ Rp. 154,224.00 7,711.20
0.2000 org Pekerja @ Rp. 85,680.00 17,136.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 95,104.80 139,465.00 234,569.80
DIBULATKAN 95,104.00 139,465.00 234,569.00

F.8 1.0000 m2 Cetakan beton / begisting memakai multiplek


0.0170 m3 Usuk ky. Kls. II @ Rp. 3,135,000.00 53,295.00
0.3470 lbr Multiplek 9 mm @ Rp. 335,940.00 116,571.18
0.4000 kg Paku @ Rp. 27,325.00 10,930.00
0.5000 org Tukang kayu @ Rp. 137,088.00 68,544.00
0.0500 org Kep. Tk. Kayu @ Rp. 154,224.00 7,711.20
0.2000 org Pekerja @ Rp. 85,680.00 17,136.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 95,104.80 180,796.18 275,900.98
DIBULATKAN 95,104.00 180,796.00 275,900.00

F.V 1.0000 m3 Membongkar cetakan


4.0000 org Pekerja @ Rp. 85,680.00 342,720.00
JUMLAH 342,720.00 342,720.00
DIBULATKAN 342,720.00 342,720.00

Sup Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai dolken )


muko2 0.7000 m3 Perancah/dolken @ Rp. 1,895,000.00 1,326,500.00
hal 10.5000 org Tukang kayu @ Rp. 137,088.00 1,439,424.00
332 1.0500 org Kep. Tk. Kayu @ Rp. 154,224.00 161,935.20
3.5000 org Pekerja @ Rp. 85,680.00 299,880.00
0.1750 org Mandor @ Rp. 171,360.00 29,988.00
JUMLAH 1,931,227.20 1,326,500.00 3,257,727.20
DIBULATKAN 1,931,227.00 1,326,500.00 3,257,727.00

Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai scafolding )


32.0000 unit Scafolding @ Rp. 75,000.00 2,400,000.00
3.5000 org Tukang kayu @ Rp. 137,088.00 479,808.00
0.3500 org Kep. Tk. Kayu @ Rp. 154,224.00 53,978.40
2.2000 org Pekerja @ Rp. 85,680.00 188,496.00
0.1200 org Mandor @ Rp. 171,360.00 20,563.20
JUMLAH 742,845.60 2,400,000.00 3,142,845.60
DIBULATKAN 742,845.00 2,400,000.00 3,142,845.00

1.0000 m3 Kolom praktis beton bertulang (10x10 cm) camp. 1 : 2 : 3


1.0000 m3 Beton Camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
285.0000 kg Besi Beton @ Rp. 27,865.00 7,941,525.00
20.0000 m2 Papan Bekisting @ Rp. 234,569.00 4,691,380.00
JUMLAH 14,841,164.00
DIBULATKAN 14,841,164.00
1.0000 m' Kolom praktis beton bertulang (10x10 cm) camp. 1 : 2 : 3 148,411.64

1.0000 m3 Ring balok beton bertulang (10x20 cm)


1.0000 m3 Beton Camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
150.0000 kg Besi Beton @ Rp. 27,865.00 4,179,750.00
20.0000 m2 Papan Bekisting @ Rp. 234,569.00 4,691,380.00
JUMLAH 11,079,389.00
DIBULATKAN 11,079,389.00
1.0000 m' Ringbalk praktis beton bertulang (10x20 cm) camp. 1 : 2 : 3 221,587.78

1.0000 m3 Balok praktis beton bertulang (10x30 cm)


1.0000 m3 Beton K175 @ Rp. 2,144,223.00 2,144,223.00
150.0000 kg Besi Beton @ Rp. 27,865.00 4,179,750.00
20.0000 m2 Papan Bekisting @ Rp. 234,569.00 4,691,380.00
JUMLAH 11,015,353.00
DIBULATKAN 11,015,353.00
1.0000 m' Ringbalk praktis beton bertulang (10x30 cm) K175 110,153.53

1.0000 m3 Kolom Beton Bertulang K200 uk. 40x40 cm pembesian 145 kg


1.0000 m3 Beton K200 @ Rp. 2,203,810.00 2,203,810.00
145.0000 kg Besi Beton @ Rp. 27,865.00 4,040,425.00
10.0000 m2 Papan Bekisting @ Rp. 234,569.00 2,345,690.00
JUMLAH 8,589,925.00
DIBULATKAN 8,589,925.00

1.0000 m3 Kolom Beton Bertulang K200 uk. 15x30 cm pembesian 110 kg


1.0000 m3 Beton K175 @ Rp. 2,144,223.00 2,144,223.00
110.0000 kg Besi Beton @ Rp. 27,865.00 3,065,150.00
16.6000 m2 Papan Bekisting @ Rp. 234,569.00 3,893,845.40
JUMLAH 9,103,218.40
DIBULATKAN 9,103,218.00

1.0000 m3 Kolom Beton Bertulang camp. 1 : 2 : 3 uk. 30x30 cm pembesian 75 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
75.0000 kg Besi Beton @ Rp. 27,865.00 2,089,875.00
13.3300 m2 Papan Bekisting @ Rp. 234,569.00 3,126,804.77
JUMLAH 7,424,938.77
DIBULATKAN 7,424,938.00
1.0000 m3 Kolom Beton Bertulang camp. 1 : 2 : 3 uk. 30x30 cm pembesian 120 kg
1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
120.0000 kg Besi Beton @ Rp. 27,865.00 3,343,800.00
13.3300 m2 Papan Bekisting @ Rp. 234,569.00 3,126,804.77
JUMLAH 8,678,863.77
DIBULATKAN 8,678,863.00

1.0000 m3 Pondasi Poer Beton Bertulang camp. 1 : 2 : 3 pembesian 150 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
150.0000 kg Besi Beton @ Rp. 27,865.00 4,179,750.00
4.0000 m2 Papan Bekisting @ Rp. 234,569.00 938,276.00
JUMLAH 7,326,285.00
DIBULATKAN 7,326,285.00

1.0000 m3 Soof Beton Bertulang camp. 1 : 2 : 3 uk. 25x40 cm pembesian 140 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
140.0000 kg Besi Beton @ Rp. 27,865.00 3,901,100.00
8.0000 m2 Papan Bekisting @ Rp. 234,569.00 1,876,552.00
JUMLAH 7,985,911.00
DIBULATKAN 7,985,911.00

1.0000 m3 Soof Beton Bertulang camp. 1 : 2 : 3 uk. 15x30 cm pembesian 155 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
155.0000 kg Besi Beton @ Rp. 27,865.00 4,319,075.00
13.3333 m2 Papan Bekisting @ Rp. 234,569.00 3,127,578.85
JUMLAH 9,654,912.85
DIBULATKAN 9,654,912.00

1.0000 m3 Soof Beton Bertulang camp. 1 : 2 : 3 uk. 15x20 cm pembesian 105 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
105.0000 kg Besi Beton @ Rp. 27,865.00 2,925,825.00
13.3300 m2 Papan Bekisting @ Rp. 234,569.00 3,126,804.77
JUMLAH 8,260,888.77
DIBULATKAN 8,260,888.00

1.0000 m3 Balok Beton Bertulang K200 uk. 25x50 cm pembesian 145 kg


1.0000 m3 Beton K200 @ Rp. 2,203,810.00 2,203,810.00
145.0000 kg Besi Beton @ Rp. 27,865.00 4,040,425.00
10.0000 m2 Papan Bekisting @ Rp. 234,569.00 2,345,690.00
JUMLAH 8,589,925.00
DIBULATKAN 8,589,925.00

1.0000 m3 Ring Balok Beton Bertulang K200 uk. 15x30 cm pembesian 145 kg
1.0000 m3 Beton K200 @ Rp. 2,203,810.00 2,203,810.00
145.0000 kg Besi Beton @ Rp. 27,865.00 4,040,425.00
13.3300 m2 Papan Bekisting @ Rp. 234,569.00 3,126,804.77
JUMLAH 9,371,039.77
DIBULATKAN 9,371,039.00

1.0000 m3 Dak Beton Bertulang camp. 1 : 2 : 3 tebal 10 cm pembesian 110 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
110.0000 kg Besi Beton @ Rp. 27,865.00 3,065,150.00
10.0000 m2 Papan Bekisting @ Rp. 234,569.00 2,345,690.00
1.0000 Stutwerk (Perancah) @ Rp. 3,257,727.00 3,257,727.00
JUMLAH 10,876,826.00
DIBULATKAN 10,876,826.00

1.0000 m3 Dak Beton Bertulang camp. 1 : 2 : 3 tebal 12 cm pembesian 140 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
140.0000 kg Besi Beton @ Rp. 27,865.00 3,901,100.00
8.3330 m2 Papan Bekisting @ Rp. 234,569.00 1,954,663.48
Stutwerk (Perancah) @ Rp. 3,257,727.00 0.00
JUMLAH 8,064,022.48
DIBULATKAN 8,064,022.00

1.0000 m3 Lantai Slab Beton Bertulang camp. 1 : 2 : 3 tebal 10 cm pembesian 75 kg


1.0000 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 2,208,259.00
80.0000 kg Besi Beton @ Rp. 27,865.00 2,229,200.00
m2 Papan Bekisting @ Rp. 234,569.00 0.00
JUMLAH 4,437,459.00
DIBULATKAN 4,437,459.00

1.0000 m' Cincin beton sumuran tanpa tulangan camp. 1 : 2 : 3 tebal 10 cm dan diameter dalam 1 m
0.3450 m3 Beton camp. 1 : 2 : 3 @ Rp. 2,208,259.00 761,849.36
6.9000 m2 Bekisting multipleks @ Rp. 275,900.00 1,903,710.00
JUMLAH 2,665,559.36
DIBULATKAN 2,665,559.00
ANALISA SATUAN PEKERJAAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN RANGKA BAJA


SNI 1.0000 kg Pasang rangka atap baja
1.1000 kg Besi baja @ Rp. 36,603.75 40,264.13
0.0050 kg Elektroda @ Rp. 60,000.00 300.00
0.0600 org @ Rp. 137,088.00 8,225.28
0.0060 org @ Rp. 154,224.00 925.34
0.0600 org @ Rp. 85,680.00 5,140.80
0.0030 org @ Rp. 171,360.00 514.08
JUMLAH 14,805.50 40,564.13 55,369.63
DIBULATKAN 14,805.00 40,564.00 55,369.00

SNI 1.0000 m3 Pasang Gording baja


6.1 1.1000 kg Gording baja @ Rp. 36,603.75 40,264.13
0.0050 kg Elektroda @ Rp. 60,000.00 300.00
0.0600 org Tukang besi @ Rp. 137,088.00 8,225.28
0.0060 org Kepala tukang besi @ Rp. 154,224.00 925.34
0.0600 org Pekerja @ Rp. 85,680.00 5,140.80
0.0030 org Mandor @ Rp. 171,360.00 514.08
JUMLAH 14,805.50 40,564.13 55,369.63
DIBULATKAN 14,805.00 40,564.00 55,369.00

1.0000 M2 Atap Superdeks


0.8700 Lbr Superdeks @ Rp. 231,000.00 200,970.00
0.0250 kg Paku Ardeks @ Rp. 45,475.00 1,136.88
0.2000 org Tukang @ Rp. 137,088.00 27,417.60
0.0200 org Kepala Tukang @ Rp. 154,224.00 3,084.48
0.1000 org Pekerja @ Rp. 85,680.00 8,568.00
0.0050 org Mandor @ Rp. 171,360.00 856.80
JUMLAH 39,926.88 202,106.88 242,033.76
DIBULATKAN 39,926.00 202,106.00 242,033.00
ANALISA SATUAN PEKERJAAN PENDAHULUAN DAN TANAH
No. Macam Pekerjaan Upah Bahan
(1) (2) (3) (4)

PEKERJAAN PERSIAPAN

SNI 1.0000 m1 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
6.4 0.0120 m3 Kayu kls. II @ Rp. 3,135,000.00 37,620.00
03-2835-2002 0.0200 kg Paku reng @ Rp. 27,325.00 546.50
0.0070 m3 Papan kayu kls. II @ Rp. 3,135,000.00 21,945.00
0.1000 org Tukang kayu @ Rp. 137,088.00 13,708.80
0.0100 org Kepala tukang kayu @ Rp. 154,224.00 1,542.24
0.1000 org Pekerja @ Rp. 85,680.00 8,568.00
0.0050 org Mandor @ Rp. 171,360.00 856.80
JUMLAH 24,675.84 60,111.50
DIBULATKAN 24,675.00 60,111.00

SNI 1.0000 m2 Membersihkan lapangan dan perataan


6.8 0.1000 org Pekerja @ Rp. 85,680.00 8,568.00
03-2835-2002 0.0500 org Mandor @ Rp. 171,360.00 8,568.00
JUMLAH 17,136.00
DIBULATKAN 17,136.00

A4 1.0000 bh Membuat Papan Nama Proyek 80x120 cm


0.0350 m3 Kayu meranti @ Rp. 3,135,000.00 109,725.00
1.4000 m1
Seng plat lebar 90 cm @ Rp. 100,200.00 140,280.00
0.6000 kg Paku @ Rp. 27,325.00 16,395.00
1.5000 kg Cat kayu @ Rp. 62,025.00 93,037.50
16.8000 kg PC @ Rp. 2,856.25 47,985.00
0.0270 m3 Pasir beton @ Rp. 1,012,500.00 27,337.50
0.0405 m3
Kerikil beton @ Rp. 787,000.00 31,873.50
0.0175 org Tukang batu @ Rp. 137,088.00 2,399.04
1.0000 org Tukang kayu @ Rp. 137,088.00 137,088.00
1.0000 org Tukang cat @ Rp. 137,088.00 137,088.00
2.1000 org Pekerja @ Rp. 85,680.00 179,928.00
1.0050 org Mandor @ Rp. 171,360.00 172,216.80
JUMLAH 628,719.84 466,633.50
DIBULATKAN 628,719.00 466,633.00

SNI 1.0000 m2 Pembuatan jalan sementara, tebal 25 cm


6.16 0.2750 m3 Batu belah @ Rp. 1,183,875.00 325,565.63
0.0300 m3
Kerikil @ Rp. 1,270,500.00 38,115.00
0.0500 m3 Pasir @ Rp. 333,200.00 16,660.00
1.0000 org Pekerja @ Rp. 85,680.00 85,680.00
0.1000 org Mandor @ Rp. 171,360.00 17,136.00
JUMLAH 102,816.00 380,340.63
DIBULATKAN 102,816.00 380,340.00

SNI 1.0000 m2 Pembuatan kantor sementara, dengan lantai plesteran


6.5 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 59,218.75 74,023.44
03-2835-2002 0.1800 m3 Kayu kls. II @ Rp. 3,135,000.00 564,300.00
0.8500 kg Paku biasa @ Rp. 27,325.00 23,226.25
1.1000 kg Baja strip @ Rp. 133,000.00 146,300.00
35.0000 kg PC @ Rp. 2,856.25 99,968.75
0.1500 m3 Pasir pasang @ Rp. 333,200.00 49,980.00
0.1000 m3 Pasir beton @ Rp. 766,000.00 76,600.00
No. Macam Pekerjaan Upah Bahan
(1) (2) (3) (4)
0.1500 m3 Kerikil beton @ Rp. 787,000.00 118,050.00
10.0000 bh Batu tela @ Rp. 5,800.00 58,000.00
0.2500 lbr Seng plat 3" x 6 " @ Rp. 100,200.00 25,050.00
2.0000 bh Jendela nako @ Rp. 18,562.00 37,124.00
0.0800 m2
Kaca polos @ Rp. 357,500.00 28,600.00
0.1500 bh Kunci tanam @ Rp. 123,750.00 18,562.50
0.0600 lbr Plywood 4 mm @ Rp. 129,954.00 7,797.24
2.0000 org Tukang kayu @ Rp. 137,088.00 274,176.00
1.0000 org Tukang batu @ Rp. 137,088.00 137,088.00
0.3000 org Kepala tukang @ Rp. 154,224.00 46,267.20
2.0000 org Pekerja @ Rp. 85,680.00 171,360.00
0.0500 org Mandor @ Rp. 171,360.00 8,568.00
JUMLAH 637,459.20 1,327,582.18
DIBULATKAN 637,459.00 1,327,582.00

SNI 1.0000 m1 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
6.2 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 59,218.75 74,023.44
03-2835-2002 2.5000 kg PC @ Rp. 2,856.25 7,140.63
1.2000 lbr Seng gelombang 2"-5" BJLS 24 @ Rp. 84,450.00 101,340.00
0.0050 m3 Pasir beton @ Rp. 1,012,500.00 5,062.50
0.0090 m3 Kerikil beton @ Rp. 787,000.00 7,083.00
0.0250 m3
Kaso 5/7 kayu meranti @ Rp. 3,135,000.00 78,375.00
0.0600 kg Paku biasa 2" - 5" @ Rp. 27,325.00 1,639.50
0.4000 kg Meni besi @ Rp. 49,650.00 19,860.00
0.2000 org Tukang kayu @ Rp. 137,088.00 27,417.60
0.0200 org Kepala tukang kayu @ Rp. 154,224.00 3,084.48
0.4000 org Pekerja @ Rp. 85,680.00 34,272.00
0.0200 org Mandor @ Rp. 171,360.00 3,427.20
JUMLAH 68,201.28 294,524.06
DIBULATKAN 68,201.00 294,524.00

PEKERJAAN TANAH
SNI 1.0000 m3 Galian tanah biasa sedalam sampai 1 meter
6.1 0.4000 org Pekerja @ Rp. 85,680.00 34,272.00
0.0400 org Mandor @ Rp. 171,360.00 6,854.40
JUMLAH 41,126.40
DIBULATKAN 41,126.00

SNI 1.0000 m3 Galian tanah biasa sedalam 1 - 2 meter


6.2 0.5260 org Pekerja @ Rp. 85,680.00 45,067.68
0.0526 org Mandor @ Rp. 171,360.00 9,013.54
JUMLAH 54,081.22
DIBULATKAN 54,081.00

SNI 1.0000 m3 Galian tanah biasa sedalam 2 - 3 meter


6.3 0.7350 org Pekerja @ Rp. 85,680.00 62,974.80
0.0735 org Mandor @ Rp. 171,360.00 12,594.96
JUMLAH 75,569.76
DIBULATKAN 75,569.00

SNI 1.0000 m3 Galian tanah keras sedalam sampai 1 meter


6.4 0.6250 org Pekerja @ Rp. 85,680.00 53,550.00
0.0620 org Mandor @ Rp. 171,360.00 10,624.32
JUMLAH 64,174.32
DIBULATKAN 64,174.00
No. Macam Pekerjaan Upah Bahan
(1) (2) (3) (4)
SNI 1.0000 m3 Galian tanah cadas sedalam sampai 1 meter
6.5 1.2500 org Pekerja @ Rp. 85,680.00 107,100.00
0.1250 org Mandor @ Rp. 171,360.00 21,420.00
JUMLAH 128,520.00
DIBULATKAN 128,520.00

SNI 1.0000 m3 Galian tanah lumpur sedalam 1 meter


6.6 0.8230 org Pekerja @ Rp. 85,680.00 70,514.64
0.0830 org Mandor @ Rp. 171,360.00 14,222.88
JUMLAH 84,737.52
DIBULATKAN 84,737.00

A6 1.0000 m3 Mengangkut tanah sejauh 30 meter


0.3300 org Pekerja @ Rp. 85,680.00 28,274.40
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 29,988.00
DIBULATKAN 29,988.00

SNI 1.0000 m3 Pembuangan tanah sejauh 150 meter


6.8 0.5160 org Pekerja @ Rp. 85,680.00 44,210.88
0.0500 org Mandor @ Rp. 171,360.00 8,568.00
JUMLAH 52,778.88
DIBULATKAN 52,778.00

A14 1.0000 m3 Membuang tanah dengan menghampar


0.2500 org Pekerja @ Rp. 85,680.00 21,420.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 23,133.60
DIBULATKAN 23,133.00

SNI 1.0000 m3 Urug kembali bekas galian


6.9 0.1920 org Pekerja @ Rp. 85,680.00 16,450.56
0.0190 org Mandor @ Rp. 171,360.00 3,255.84
JUMLAH 19,706.40
DIBULATKAN 19,706.00

1.0000 m2 Meratakan tanah ditumbuk halus


0.2500 org Pekerja @ Rp. 85,680.00 21,420.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 23,133.60
DIBULATKAN 23,133.00

A18 1.0000 m3 Urug pasir


1.2000 m3 Pasir urug @ Rp. 305,000.00 366,000.00
0.3000 org Pekerja @ Rp. 85,680.00 25,704.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 27,417.60 366,000.00
DIBULATKAN 27,417.00 366,000.00

MOD 1.0000 m3 Urug tanah mendatangkan


A18 1.2000 m3 Tanah urug @ Rp. 301,000.00 361,200.00
0.3000 org Pekerja @ Rp. 85,680.00 25,704.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 27,417.60 361,200.00
DIBULATKAN 27,417.00 361,200.00
No. Macam Pekerjaan Upah Bahan
(1) (2) (3) (4)
SNI 1.0000 m3 Urugan sirtu
6.15 1.2000 m3 Sirtu @ Rp. 305,000.00 366,000.00
0.2500 org Pekerja @ Rp. 85,680.00 21,420.00
0.0250 org Mandor @ Rp. 171,360.00 4,284.00
JUMLAH 25,704.00 366,000.00
DIBULATKAN 25,704.00 366,000.00
H
Jumlah
(5)

84,787.34
84,787.00

17,136.00
17,136.00

1,095,353.34
1,095,353.00

483,156.63
483,156.00
Jumlah
(5)

1,965,041.38
1,965,041.00

362,725.34
362,725.00

41,126.40
41,126.00

54,081.22
54,081.00

75,569.76
75,569.00

64,174.32
64,174.00
Jumlah
(5)

128,520.00
128,520.00

84,737.52
84,737.00

29,988.00
29,988.00

52,778.88
52,778.00

23,133.60
23,133.00

19,706.40
19,706.00

23,133.60
23,133.00

393,417.60
393,417.00

388,617.60
388,617.00
Jumlah
(5)

391,704.00
391,704.00
ANALISA SATUAN PEKERJAAN BATU DAN PASANGAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN PASANGAN

SNI 1.0000 m3 Pasangan pondasi batu kosong


6.14 1.2000 m3 Batu belah 15/20 cm @ Rp. 732,000.00 878,400.00
03-2836-2002 0.3000 m3 Pasir urug @ Rp. 305,000.00 91,500.00
0.3900 org Tukang batu @ Rp. 137,088.00 53,464.32
0.0390 org Kepala tukang batu @ Rp. 154,224.00 6,014.74
0.7800 org Pekerja @ Rp. 85,680.00 66,830.40
0.0390 org Mandor @ Rp. 171,360.00 6,683.04
JUMLAH 132,992.50 969,900.00 1,102,892.50
DIBULATKAN 132,992.00 969,900.00 1,102,892.00

SNI 1.0000 m3 Pasangan pondasi 1 Pc : 3 Ps


6.5 1.1000 m3 Batu belah 15/20 cm @ Rp. 732,000.00 805,200.00
03-2836-2002 202.0000 kg PC @ Rp. 2,856.25 576,962.50
0.4850 m3 Pasir pasang @ Rp. 333,200.00 161,602.00
0.6000 org Tukang batu @ Rp. 137,088.00 82,252.80
0.0600 org Kepala tukang batu @ Rp. 154,224.00 9,253.44
1.5000 org Pekerja @ Rp. 85,680.00 128,520.00
0.0750 org Mandor @ Rp. 171,360.00 12,852.00
JUMLAH 232,878.24 1,543,764.50 1,776,642.74
DIBULATKAN 232,878.00 1,543,764.00 1,776,642.00

SNI 1.0000 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps


6.11 70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 4,640.00 324,800.00
03-2837-2002 11.5000 kg PC @ Rp. 2,856.25 32,846.88
0.0430 m3 Pasir pasang @ Rp. 333,200.00 14,327.60
0.1000 org Tukang batu @ Rp. 137,088.00 13,708.80
0.0100 org Kepala tukang batu @ Rp. 154,224.00 1,542.24
0.3200 org Pekerja @ Rp. 85,680.00 27,417.60
0.0150 org Mandor @ Rp. 171,360.00 2,570.40
JUMLAH 45,239.04 371,974.48 417,213.52
DIBULATKAN 45,239.00 371,974.00 417,213.00

1.0000 m2 Pasangan batu Tela, 1 Pc : 3 Ps


20.0000 bh Batu Tela @ Rp. 5,800.00 116,000.00
12.6400 kg PC @ Rp. 2,856.25 36,103.00
0.0280 m3 Pasir pasang @ Rp. 333,200.00 9,329.60
0.1500 org Tukang batu @ Rp. 137,088.00 20,563.20
0.0150 org Kepala tukang batu @ Rp. 154,224.00 2,313.36
0.4500 org Pekerja @ Rp. 85,680.00 38,556.00
0.0225 org Mandor @ Rp. 171,360.00 3,855.60
JUMLAH 65,288.16 161,432.60 226,720.76
DIBULATKAN 65,288.00 161,432.00 226,720.00
1.0000 m2 Pasangan Rolag batu Tela, 1 Pc : 3 Ps 453,440.00

SNI 1.0000 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps


6.4 140.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 4,640.00 649,600.00
03-2837-2002 26.4500 kg PC @ Rp. 2,856.25 75,547.81
0.0980 m3 Pasir pasang @ Rp. 333,200.00 32,653.60
0.2000 org Tukang batu @ Rp. 137,088.00 27,417.60
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0200 org Kepala tukang batu @ Rp. 154,224.00 3,084.48
0.6500 org Pekerja @ Rp. 85,680.00 55,692.00
0.0300 org Mandor @ Rp. 171,360.00 5,140.80
JUMLAH 91,334.88 757,801.41 849,136.29
DIBULATKAN 91,334.00 757,801.00 849,136.00

G.50.q 1.0000 m2 Plesteran batu kali 1pc:4ps


6.5110 kg PC @ Rp. 2,856.25 18,597.04
0.0209 m3 Pasir pasang @ Rp. 333,200.00 6,963.88
0.2000 org Tukang batu @ Rp. 137,088.00 27,417.60
0.0200 org Kep. Tk. Batu @ Rp. 154,224.00 3,084.48
0.4000 org Pekerja @ Rp. 85,680.00 34,272.00
0.0200 org Mandor @ Rp. 171,360.00 3,427.20
JUMLAH 68,201.28 25,560.92 93,762.20
DIBULATKAN 68,201.00 25,560.00 93,762.00

SNI 1.0000 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm


6.4 5.2000 kg PC @ Rp. 2,856.25 14,852.50
03-2837-2002 0.0200 m3 Pasir pasang @ Rp. 333,200.00 6,664.00
0.1500 org Tukang batu @ Rp. 137,088.00 20,563.20
0.0150 org Kepala tukang batu @ Rp. 154,224.00 2,313.36
0.2000 org Pekerja @ Rp. 85,680.00 17,136.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 41,726.16 21,516.50 63,242.66
DIBULATKAN 41,726.00 21,516.00 63,242.00

SNI 1.0000 m2 Plesteran dinding 1 Pc : 3 Ps, tebal 15 mm


6.30 7.7760 kg PC @ Rp. 2,856.25 22,210.20
03-2837-2002 0.0230 m 3
Pasir pasang @ Rp. 333,200.00 7,663.60
0.1500 org Tukang batu @ Rp. 137,088.00 20,563.20
0.0150 org Kepala tukang batu @ Rp. 154,224.00 2,313.36
0.3000 org Pekerja @ Rp. 85,680.00 25,704.00
0.0100 org Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 50,294.16 29,873.80 80,167.96
DIBULATKAN 50,294.00 29,873.00 80,167.00

SNI 1.0000 m2 Screed lantai 1 Pc : 3 Ps, tebal 30 mm


6.30 15.5520 kg PC @ Rp. 2,856.25 44,420.40
03-2837-2002 0.0460 m 3
Pasir pasang @ Rp. 333,200.00 15,327.20
0.2250 org Tukang batu @ Rp. 137,088.00 30,844.80
0.0225 org Kepala tukang batu @ Rp. 154,224.00 3,470.04
0.4500 org Pekerja @ Rp. 85,680.00 38,556.00
0.0150 org Mandor @ Rp. 171,360.00 2,570.40
JUMLAH 75,441.24 59,747.60 135,188.84
DIBULATKAN 75,441.00 59,747.00 135,188.00

SNI 1.0000 m1 Les profil dinding L = 5 cm 1 Pc : 2 Ps ( untuk gedung )


6.31 0.8000 kg PC @ Rp. 2,856.25 2,285.00
03-2837-2002 0.0030 m3 Pasir pasang @ Rp. 333,200.00 999.60
0.0600 org Tukang batu @ Rp. 137,088.00 8,225.28
0.0060 org Kepala tukang batu @ Rp. 154,224.00 925.34
0.1200 org Pekerja @ Rp. 85,680.00 10,281.60
0.0060 org Mandor @ Rp. 171,360.00 1,028.16
JUMLAH 20,460.38 3,284.60 23,744.98
DIBULATKAN 20,460.00 3,284.00 23,744.00

SNI 1.0000 m2 Plesteran siar adukan 1 Pc : 2 Ps


No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
6.35 4.3200 kg PC @ Rp. 2,856.25 12,339.00
03-2837-2002 0.0160 m3 Pasir pasang @ Rp. 333,200.00 5,331.20
0.0700 org Tukang batu @ Rp. 137,088.00 9,596.16
0.0070 org Kepala tukang batu @ Rp. 154,224.00 1,079.57
0.1500 org Pekerja @ Rp. 85,680.00 12,852.00
0.0080 org Mandor @ Rp. 171,360.00 1,370.88
JUMLAH 24,898.61 17,670.20 42,568.81
DIBULATKAN 24,898.00 17,670.00 42,568.00

SNI 1.0000 m2 Plesteran Ciprat, 1 Pc : 2 Ps


6.34 4.3200 kg PC @ Rp. 2,856.25 12,339.00
0.0160 m 3
Pasir pasang @ Rp. 333,200.00 5,331.20
0.1000 org Tukang batu @ Rp. 137,088.00 13,708.80
0.0100 org Kepala tukang batu @ Rp. 154,224.00 1,542.24
0.2500 org Pekerja @ Rp. 85,680.00 21,420.00
0.0150 org Mandor @ Rp. 171,360.00 2,570.40
JUMLAH 39,241.44 17,670.20 56,911.64
DIBULATKAN 39,241.00 17,670.00 56,911.00

Analisa ZAZ 1.0000 m2 Acian dinding bata


3.5000 kg PC @ Rp. 2,856.25 9,996.88
0.0330 org Tukang batu @ Rp. 137,088.00 4,523.90
0.0033 org Kep. Tk. Batu @ Rp. 154,224.00 508.94
0.0700 org Pekerja @ Rp. 85,680.00 5,997.60
0.0035 org Mandor @ Rp. 171,360.00 599.76
JUMLAH 11,630.20 9,996.88 21,627.08
DIBULATKAN 11,630.00 9,996.00 21,627.00

SNI 1.0000 m2 Pasang dinding batu hias tempel


6.74 1.0500 m2 Batu tempel hitam @ Rp. 350,000.00 367,500.00
11.7500 kg PC @ Rp. 2,856.25 33,560.94
0.0350 m3 Pasir pasang @ Rp. 333,200.00 11,662.00
0.3500 org Tukang batu @ Rp. 137,088.00 47,980.80
0.0350 org Kepala tukang batu @ Rp. 154,224.00 5,397.84
0.6500 org Pekerja @ Rp. 85,680.00 55,692.00
0.0300 org Mandor @ Rp. 171,360.00 5,140.80
JUMLAH 114,211.44 412,722.94 526,934.38
DIBULATKAN 114,211.00 412,722.00 526,934.00

1.0000 m' Pasang kanstin uk. 15x25x40


2.5000 bh Kanstin @ Rp. 36,857.14 92,142.86
0.1500 kg Semen PC @ Rp. 2,856.25 428.44
0.0500 m3 Pasir pasang @ Rp. 333,200.00 16,660.00
0.1000 org Tukang batu @ Rp. 137,088.00 13,708.80
0.0500 org Kep. Tk. Batu @ Rp. 154,224.00 7,711.20
0.0500 org Pekerja @ Rp. 85,680.00 4,284.00
0.0250 org Mandor @ Rp. 171,360.00 4,284.00
JUMLAH 29,988.00 109,231.29 139,219.29
DIBULATKAN 29,988.00 109,231.00 139,219.00

1.0000 m2 Pasang paving blok uk. 10x20x7


50.0000 bh paving blok @ Rp. 4,300.00 215,000.00
0.0500 m3 Pasir urug @ Rp. 305,000.00 15,250.00
0.1600 org Tukang batu @ Rp. 137,088.00 21,934.08
0.0500 org Kep. Tk. Batu @ Rp. 154,224.00 7,711.20
0.0100 org Pekerja @ Rp. 85,680.00 856.80
0.0250 org Mandor @ Rp. 171,360.00 4,284.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH 34,786.08 230,250.00 265,036.08
DIBULATKAN 34,786.00 230,250.00 265,036.00

1.0000 m2 Pasangan keramik 30 x 30 campuran 1 PC : 3 PP


1.1000 m2 Keramik 30 x 30 @ Rp. 266,860.00 293,546.00
14.1500 kg Semen PC @ Rp. 2,856.25 40,415.94
0.0390 m3 Pasir pasang @ Rp. 333,200.00 12,994.80
0.2000 kg Semen nat (tile grout) @ Rp. 18,150.00 3,630.00
0.3500 org Tukang batu @ Rp. 137,088.00 47,980.80
0.0350 org Kep. Tk. Batu @ Rp. 154,224.00 5,397.84
0.3500 org Pekerja @ Rp. 85,680.00 29,988.00
0.0350 org Mandor @ Rp. 171,360.00 5,997.60
JUMLAH 89,364.24 350,586.74 439,950.98
DIBULATKAN 89,364.00 350,586.00 439,950.00

1.0000 m2 Pasangan keramik 40 x 40 campuran 1 PC : 3 PP


1.1000 m2 Keramik 40 x 40 @ Rp. 285,768.00 314,344.80
14.1500 kg Semen PC @ Rp. 2,856.25 40,415.94
0.0390 m3 Pasir pasang @ Rp. 333,200.00 12,994.80
0.2000 kg Semen nat (tile grout) @ Rp. 18,150.00 3,630.00
0.3500 org Tukang batu @ Rp. 137,088.00 47,980.80
0.0350 org Kep. Tk. Batu @ Rp. 154,224.00 5,397.84
0.3500 org Pekerja @ Rp. 85,680.00 29,988.00
0.0350 org Mandor @ Rp. 171,360.00 5,997.60
JUMLAH 89,364.24 371,385.54 460,749.78
DIBULATKAN 89,364.00 371,385.00 460,749.00

10.0000 m' Selokan pas. Batu tela camp. 1 : 3 uk. 25x25 cm diplester camp. 1 : 3
111.0000 Bh Batu tela @ Rp. 5,800.00 643,800.00
0.2100 m3 Pasir @ Rp. 333,200.00 69,972.00
44.8000 kg Semen PC @ Rp. 2,856.25 127,960.00
8.5000 m2 Plesteran @ Rp. 80,167.00 681,419.50
1.1250 org Tukang batu @ Rp. 137,088.00 154,224.00
0.1900 org Kep. Tk. Batu @ Rp. 154,224.00 29,302.56
3.1500 org Pekerja @ Rp. 85,680.00 269,892.00
0.1690 org Mandor @ Rp. 171,360.00 28,959.84
JUMLAH 482,378.40 1,523,151.50 2,005,529.90
DIBULATKAN 482,378.00 1,523,151.00 2,005,529.00
1.0000 m' Selokan pas. Batu tela camp. 1 : 3 uk. 25x25 cm diplester camp. 1 : 3 200,552.90

1.0000 Bh Bak air Uk. 0.60x0.60X0.60 tanpa keramik


1.9200 m2 Pasangan batu tela @ Rp. 226,720.00 435,302.40
3.8400 m2 Plesteran @ Rp. 80,167.00 307,841.28
3.8400 m2
Acian @ Rp. 21,627.00 83,047.68
0.0540 m3 Urugan pasir @ Rp. 393,417.00 21,244.52
0.0252 m3 Cor lantai 1 : 3 : 5 @ Rp. 1,903,122.00 47,958.67
1.0000 Bh Floor drain bak air @ Rp. 67,500.00 67,500.00
JUMLAH - - 962,894.55
DIBULATKAN - - 962,894.00
ANALISA SATUAN PEKERJAAN SANITAIR
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN SANITASI
SNI 1.0000 bh Memasang kloset duduk/monoblock
1.0000 bh Kloset duduk / monoblock @ Rp. 1,455,300.00 1,455,300.00
6.1 6% x Harga kloset (Perlengkapan) @ Rp. 1,455,300.00 87,318.00
1.1000 org Tukang batu @ Rp. 137,088.00 150,796.80
0.0010 org Kepala tukang batu @ Rp. 154,224.00 154.22
3.3000 org Pekerja @ Rp. 85,680.00 282,744.00
0.1600 org Mandor @ Rp. 171,360.00 27,417.60
JUMLAH 461,112.62 1,542,618.00 2,003,730.62
DIBULATKAN 461,112.00 1,542,618.00 2,003,730.00

SNI 1.0000 bh Memasang kloset jongkok porselen


1.0000 bh Kloset jongkok porselen @ Rp. 226,875.00 226,875.00
6.2 6.0000 kg PC @ Rp. 2,856.25 17,137.50
0.0100 m3 Pasir pasang @ Rp. 333,200.00 3,332.00
1.5000 org Tukang batu @ Rp. 137,088.00 205,632.00
1.5000 org Kepala tukang batu @ Rp. 154,224.00 231,336.00
1.0000 org Pekerja @ Rp. 85,680.00 85,680.00
0.1600 org Mandor @ Rp. 171,360.00 27,417.60
JUMLAH 550,065.60 247,344.50 797,410.10
DIBULATKAN 550,065.00 247,344.00 797,410.00

SNI 1.0000 bh Memasang urinoir


1.0000 bh Urinoir @ Rp. 1,629,477.00 1,629,477.00
6.4 30% x Harga urinoir (Perlengkapan) @ Rp. 1,629,477.00 488,843.10
6.0000 kg PC @ Rp. 2,856.25 17,137.50
0.0100 m3 Pasir pasang @ Rp. 333,200.00 3,332.00
1.0000 org Tukang batu @ Rp. 137,088.00 137,088.00
0.1000 org Kepala tukang batu @ Rp. 154,224.00 15,422.40
1.0000 org Pekerja @ Rp. 85,680.00 85,680.00
0.1000 org Mandor @ Rp. 171,360.00 17,136.00
JUMLAH 255,326.40 2,138,789.60 2,394,116.00
DIBULATKAN 255,326.00 2,138,789.00 2,394,116.00

SNI 1.0000 bh Memasang wastafel


1.0000 bh Wastafel @ Rp. 2,000,000.00 2,000,000.00
6.5 12% x Harga wastafel (Perlengkapan) @ Rp. 2,000,000.00 240,000.00
6.0000 kg PC @ Rp. 2,856.25 17,137.50
0.0100 m3 Pasir pasang @ Rp. 333,200.00 3,332.00
1.4500 org Tukang batu @ Rp. 137,088.00 198,777.60
0.1500 org Kepala tukang batu @ Rp. 154,224.00 23,133.60
1.2000 org Pekerja @ Rp. 85,680.00 102,816.00
0.1000 org Mandor @ Rp. 171,360.00 17,136.00
JUMLAH 341,863.20 2,260,469.50 2,602,332.70
DIBULATKAN 341,863.00 2,260,469.00 2,602,332.00

Analisa Gedung - 43
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
SNI 1.0000 bh Memasang bak mandi fiberglass volume 0,30 m3
1.0000 bh Bak fiberglass @ Rp. 562,500.00 562,500.00
6.7 18% x Harga bak(Perlengkapan) @ Rp. 562,500.00 101,250.00
2.7000 org Tukang batu @ Rp. 137,088.00 370,137.60
0.5400 org Kepala tukang batu @ Rp. 154,224.00 83,280.96
1.8000 org Pekerja @ Rp. 85,680.00 154,224.00
0.1100 org Mandor @ Rp. 171,360.00 18,849.60
JUMLAH 626,492.16 663,750.00 1,290,242.16
DIBULATKAN 626,492.00 663,750.00 1,290,242.00

SNI 1.0000 bh Memasang bak fiberglass volume 1 m3 air


1.0000 bh Bak fiberglass @ Rp. 906,250.00 906,250.00
6.11 12% x Harga bak (Perlengkapan) @ Rp. 906,250.00 108,750.00
4.5000 org Tukang batu @ Rp. 137,088.00 616,896.00
0.9000 org Kepala tukang batu @ Rp. 154,224.00 138,801.60
3.0000 org Pekerja @ Rp. 85,680.00 257,040.00
0.9000 org Mandor @ Rp. 171,360.00 154,224.00
JUMLAH 1,166,961.60 1,015,000.00 2,181,961.60
DIBULATKAN 1,166,961.00 1,015,000.00 2,181,961.00

SNI 1.0000 m1 Memasang pipa galvanis diameter 1/2"


1.2000 m1 Pipa galvanis @ Rp. 39,420.00 47,304.00
6.19 35% x Harga pipa (Perlengkapan) @ Rp. 39,420.00 13,797.00
0.0900 org Tukang batu @ Rp. 137,088.00 12,337.92
0.0090 org Kepala tukang batu @ Rp. 154,224.00 1,388.02
0.0540 org Pekerja @ Rp. 85,680.00 4,626.72
0.0270 org Mandor @ Rp. 171,360.00 4,626.72
JUMLAH 22,979.38 61,101.00 84,080.38
DIBULATKAN 22,979.00 61,101.00 84,080.00

SNI 1.0000 m1 Memasang pipa galvanis diameter 3/4"


1.2000 m1 Pipa galvanis @ Rp. 59,512.00 71,414.40
6.20 35% x Harga pipa (Perlengkapan) @ Rp. 59,512.00 20,829.20
0.0900 org Tukang batu @ Rp. 137,088.00 12,337.92
0.0090 org Kepala tukang batu @ Rp. 154,224.00 1,388.02
0.0540 org Pekerja @ Rp. 85,680.00 4,626.72
0.0270 org Mandor @ Rp. 171,360.00 4,626.72
JUMLAH 22,979.38 92,243.60 115,222.98
DIBULATKAN 22,979.00 92,243.00 115,222.00

SNI 1.0000 m1 Memasang pipa galvanis diameter 1"


1.2000 m1 Pipa galvanis @ Rp. 73,990.00 88,788.00
6.21 35% x Harga pipa (Perlengkapan) @ Rp. 73,990.00 25,896.50
0.0900 org Tukang batu @ Rp. 137,088.00 12,337.92
0.0090 org Kepala tukang batu @ Rp. 154,224.00 1,388.02
0.0540 org Pekerja @ Rp. 85,680.00 4,626.72
0.0270 org Mandor @ Rp. 171,360.00 4,626.72
JUMLAH 22,979.38 114,684.50 137,663.88
DIBULATKAN 22,979.00 114,684.00 137,663.00

Analisa Gedung - 44
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
SNI 1.0000 m1 Memasang pipa galvanis diameter 1 1/2"
1.2000 m1 Pipa galvanis @ Rp. 88,311.00 105,973.20
6.22 35% x Harga pipa (Perlengkapan) @ Rp. 88,311.00 30,908.85
0.1800 org Tukang batu @ Rp. 137,088.00 24,675.84
0.0180 org Kepala tukang batu @ Rp. 154,224.00 2,776.03
0.1080 org Pekerja @ Rp. 85,680.00 9,253.44
0.0054 org Mandor @ Rp. 171,360.00 925.34
JUMLAH 37,630.66 136,882.05 174,512.71
DIBULATKAN 37,630.00 136,882.00 174,512.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 1/2"


1.2000 m1 Pipa PVC @ Rp. 13,387.00 16,064.40
6.25 35% x Harga pipa (Perlengkapan) @ Rp. 13,387.00 4,685.45
0.0600 org Tukang batu @ Rp. 137,088.00 8,225.28
0.0060 org Kepala tukang batu @ Rp. 154,224.00 925.34
0.0360 org Pekerja @ Rp. 85,680.00 3,084.48
0.0018 org Mandor @ Rp. 171,360.00 308.45
JUMLAH 12,543.55 20,749.85 33,293.40
DIBULATKAN 12,543.00 20,749.00 33,293.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 3/4"


1.2000 m1 Pipa PVC @ Rp. 15,300.00 18,360.00
6.26 35% x Harga pipa (Perlengkapan) @ Rp. 15,300.00 5,355.00
0.0600 org Tukang batu @ Rp. 137,088.00 8,225.28
0.0060 org Kepala tukang batu @ Rp. 154,224.00 925.34
0.0360 org Pekerja @ Rp. 85,680.00 3,084.48
0.0018 org Mandor @ Rp. 171,360.00 308.45
JUMLAH 12,543.55 23,715.00 36,258.55
DIBULATKAN 12,543.00 23,715.00 36,258.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 1"


1.2000 m1 Pipa PVC @ Rp. 20,700.00 24,840.00
6.27 35% x Harga pipa (Perlengkapan) @ Rp. 20,700.00 7,245.00
0.0600 org Tukang batu @ Rp. 137,088.00 8,225.28
0.0060 org Kepala tukang batu @ Rp. 154,224.00 925.34
0.0360 org Pekerja @ Rp. 85,680.00 3,084.48
0.0018 org Mandor @ Rp. 171,360.00 308.45
JUMLAH 12,543.55 32,085.00 44,628.55
DIBULATKAN 12,543.00 32,085.00 44,628.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 1 1/2"


1.2000 m1 Pipa PVC @ Rp. 31,500.00 37,800.00
6.28 35% x Harga pipa (Perlengkapan) @ Rp. 31,500.00 11,025.00
0.0600 org Tukang batu @ Rp. 137,088.00 8,225.28
0.0060 org Kepala tukang batu @ Rp. 154,224.00 925.34
0.0360 org Pekerja @ Rp. 85,680.00 3,084.48
0.0018 org Mandor @ Rp. 171,360.00 308.45
JUMLAH 12,543.55 48,825.00 61,368.55
DIBULATKAN 12,543.00 48,825.00 61,368.00

Analisa Gedung - 45
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 2"
1.2000 m1 Pipa PVC @ Rp. 45,000.00 54,000.00
6.29 35% x Harga pipa (Perlengkapan) @ Rp. 45,000.00 15,750.00
0.0900 org Tukang batu @ Rp. 137,088.00 12,337.92
0.0090 org Kepala tukang batu @ Rp. 154,224.00 1,388.02
0.0544 org Pekerja @ Rp. 85,680.00 4,660.99
0.0027 org Mandor @ Rp. 171,360.00 462.67
JUMLAH 18,849.60 69,750.00 88,599.60
DIBULATKAN 18,849.00 69,750.00 88,599.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 2 1/2"


1.2000 m1 Pipa PVC @ Rp. 66,600.00 79,920.00
6.30 35% x Harga pipa (Perlengkapan) @ Rp. 66,600.00 23,310.00
0.0600 org Tukang batu @ Rp. 137,088.00 8,225.28
0.0060 org Kepala tukang batu @ Rp. 154,224.00 925.34
0.0360 org Pekerja @ Rp. 85,680.00 3,084.48
0.0018 org Mandor @ Rp. 171,360.00 308.45
JUMLAH 12,543.55 103,230.00 115,773.55
DIBULATKAN 12,543.00 103,230.00 115,773.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 3"


1.2000 m1 Pipa PVC @ Rp. 90,900.00 109,080.00
6.31 35% x Harga pipa (Perlengkapan) @ Rp. 90,900.00 31,815.00
0.1350 org Tukang batu @ Rp. 137,088.00 18,506.88
0.0135 org Kepala tukang batu @ Rp. 154,224.00 2,082.02
0.0810 org Pekerja @ Rp. 85,680.00 6,940.08
0.0410 org Mandor @ Rp. 171,360.00 7,025.76
JUMLAH 34,554.74 140,895.00 175,449.74
DIBULATKAN 34,554.00 140,895.00 175,449.00

SNI 1.0000 m1 Memasang pipa PVC tipe AW diameter 4"


1.2000 m1 Pipa PVC @ Rp. 105,000.00 126,000.00
6.32 35% x Harga pipa (Perlengkapan) @ Rp. 105,000.00 36,750.00
0.1350 org Tukang batu @ Rp. 137,088.00 18,506.88
0.0135 org Kepala tukang batu @ Rp. 154,224.00 2,082.02
0.0810 org Pekerja @ Rp. 85,680.00 6,940.08
0.0410 org Mandor @ Rp. 171,360.00 7,025.76
JUMLAH 34,554.74 162,750.00 197,304.74
DIBULATKAN 34,554.00 162,750.00 197,304.00

SNI 1.0000 bh Memasang bak cuci piring stainless steel


1.0000 bh Bak cuci stainless steel @ Rp. 680,625.00 680,625.00
6.33 1.0000 set Water drain + asesories @ Rp. 88,968.00 88,968.00
0.3000 org Tukang batu @ Rp. 137,088.00 41,126.40
0.0300 org Kepala tukang batu @ Rp. 154,224.00 4,626.72
0.0300 org Pekerja @ Rp. 85,680.00 2,570.40
0.0015 org Mandor @ Rp. 171,360.00 257.04
JUMLAH 48,580.56 769,593.00 818,173.56
DIBULATKAN 48,580.00 769,593.00 818,173.00

Analisa Gedung - 46
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
SNI 1.0000 bh Memasang kran diameter 3/4" atau 1/2"
1.0000 bh Kran air @ Rp. 35,856.00 35,856.00
6.35 0.0250 bh Seal tape @ Rp. 13,750.00 343.75
0.1000 org Tukang batu @ Rp. 137,088.00 13,708.80
0.0100 org Kepala tukang batu @ Rp. 154,224.00 1,542.24
0.0100 org Pekerja @ Rp. 85,680.00 856.80
0.0050 org Mandor @ Rp. 171,360.00 856.80
JUMLAH 16,964.64 36,199.75 53,164.39
DIBULATKAN 16,964.00 36,199.00 53,164.00

SNI 1.0000 bh Memasang floor drain


1.0000 bh Floor drain @ Rp. 67,500.00 67,500.00
6.35 0.1000 org Tukang batu @ Rp. 137,088.00 13,708.80
0.0100 org Kepala tukang batu @ Rp. 154,224.00 1,542.24
0.0100 org Pekerja @ Rp. 85,680.00 856.80
0.0050 org Mandor @ Rp. 171,360.00 856.80
JUMLAH 16,964.64 67,500.00 84,464.64
DIBULATKAN 16,964.00 67,500.00 84,464.00

1.0000 UNIT SEPTIC TANK DAN RESAPAN UK. 1.5x1x1.5 M


2.2500 M3 Galian Tanah @ Rp. 54,081.00 121,682.25
9.0000 M2 Pas. Batu Tela @ Rp. 226,720.00 2,040,480.00
10.5000 M2 Plesteran Camp. 1 : 3 @ Rp. 80,167.00 841,753.50
16.7320 Kg Pembesian @ Rp. 27,865.00 466,237.18
0.1500 M3 Cor Beton Camp. 1 : 2 : 3 @ Rp. 2,208,259.00 331,238.85
JUMLAH 3,801,391.78
DIBULATKAN 3,801,391.00

Analisa Gedung - 47
ANALISA SATUAN PEKERJAAN PENGECATAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN CAT-CATAN

SNI 1.0000 m2 Pengecatan bidang kayu lama


6.7 0.1500 kg Plamir @ Rp. 41,334.00 6,200.10
0.1700 kg Cat dasar @ Rp. 62,025.00 10,544.25
0.1700 kg Cat penutup @ Rp. 62,025.00 10,544.25
0.0750 org Tukang cat @ Rp. 137,088.00 10,281.60
0.0075 org Kepala tukang cat @ Rp. 154,224.00 1,156.68
0.0700 org Pekerja @ Rp. 85,680.00 5,997.60
0.0025 org Mandor @ Rp. 171,360.00 428.40
JUMLAH 17,864.28 27,288.60 45,152.88
DIBULATKAN 17,864.00 27,288.00 45,152.00

SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
6.8 0.2000 kg Cat meni @ Rp. 41,334.00 8,266.80
0.1500 kg Plamir @ Rp. 41,334.00 6,200.10
0.1700 kg Cat dasar @ Rp. 62,025.00 10,544.25
0.2600 kg Cat penutup @ Rp. 62,025.00 16,126.50
0.0900 org Tukang cat @ Rp. 137,088.00 12,337.92
0.0060 org Kepala tukang cat @ Rp. 154,224.00 925.34
0.0700 org Pekerja @ Rp. 85,680.00 5,997.60
0.0025 org Mandor @ Rp. 171,360.00 428.40
JUMLAH 19,689.26 41,137.65 60,826.91
DIBULATKAN 19,689.00 41,137.00 60,826.00

SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
6.9 0.2000 kg Cat meni @ Rp. 41,334.00 8,266.80
0.1500 kg Plamir @ Rp. 41,334.00 6,200.10
0.1700 kg Cat dasar @ Rp. 62,025.00 10,544.25
0.3500 kg Cat penutup @ Rp. 62,025.00 21,708.75
0.1050 org Tukang cat @ Rp. 137,088.00 14,394.24
0.0040 org Kepala tukang cat @ Rp. 154,224.00 616.90
0.0700 org Pekerja @ Rp. 85,680.00 5,997.60
0.0025 org Mandor @ Rp. 171,360.00 428.40
JUMLAH 21,437.14 46,719.90 68,157.04
DIBULATKAN 21,437.00 46,719.00 68,157.00

SNI 1.0000 m2 Pelaburan bidang kayu dengan politur


6.11 0.1500 ltr Politur @ Rp. 58,650.00 8,797.50
0.3720 ltr Politur jadi @ Rp. 58,650.00 21,817.80
2.0000 lbr Amplas @ Rp. 9,400.00 18,800.00
0.0600 org Tukang cat @ Rp. 137,088.00 8,225.28
0.0160 org Kepala tukang cat @ Rp. 154,224.00 2,467.58
0.0025 org Mandor @ Rp. 171,360.00 428.40
JUMLAH 11,121.26 49,415.30 60,536.56
DIBULATKAN 11,121.00 49,415.00 60,536.00

SNI 1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14 0.1000 kg Plamir tembok @ Rp. 40,355.00 4,035.50
0.1000 kg Cat dasar @ Rp. 22,000.00 2,200.00
0.2600 kg Cat penutup 2 x @ Rp. 22,000.00 5,720.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0630 org Tukang cat @ Rp. 137,088.00 8,636.54
0.0063 org Kepala tukang cat @ Rp. 154,224.00 971.61
0.0200 org Pekerja @ Rp. 85,680.00 1,713.60
0.0025 org Mandor @ Rp. 171,360.00 428.40
JUMLAH 11,750.16 11,955.50 23,705.66
DIBULATKAN 11,750.00 11,955.00 23,705.00

SNI 1.0000 m2 Pengecatan tembok tidak terlindung dari panas dan hujan
6.14 0.1000 kg Cat alkali resisting primer @ Rp. 41,205.00 4,120.50
0.3600 kg Cat ICI Weathershield @ Rp. 82,410.00 29,667.60
0.0630 org Tukang cat @ Rp. 137,088.00 8,636.54
0.0063 org Kepala tukang cat @ Rp. 154,224.00 971.61
0.0200 org Pekerja @ Rp. 85,680.00 1,713.60
0.0025 org Mandor @ Rp. 171,360.00 428.40
JUMLAH 11,750.16 33,788.10 45,538.26
DIBULATKAN 11,750.00 33,788.00 45,538.00
ANALISA SATUAN PEKERJAAN KAYU
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)

PEKERJAAN RANGKA ATAP

SNI 1.000 m3 Membuat kuda-kuda kayu kelas I


6.28 1.100 m3 Kayu kls. I @ Rp. 4,220,000.00 4,642,000.00
03-3434-2002 0.800 kg Paku biasa 2" - 5" @ Rp. 27,325.00 21,860.00
12.000 OH Tukang kayu @ Rp. 137,088.00 1,645,056.00
1.200 OH Kepala tukang kayu @ Rp. 154,224.00 185,068.80
4.000 OH Pekerja @ Rp. 85,680.00 342,720.00
0.200 OH Mandor @ Rp. 171,360.00 34,272.00
JUMLAH 2,207,116.80 4,663,860.00 6,870,976.80
DIBULATKAN 2,207,116.00 4,663,860.00 6,870,976.00

SNI 1.000 m3 Pasang kuda-kuda kayu lama


03-3434-2002 0.800 kg Paku biasa 2" - 5" @ Rp. 27,325.00 21,860.00
12.000 OH Tukang kayu @ Rp. 137,088.00 1,645,056.00
1.200 OH Kepala tukang kayu @ Rp. 154,224.00 185,068.80
4.000 OH Pekerja @ Rp. 85,680.00 342,720.00
0.200 OH Mandor @ Rp. 171,360.00 34,272.00
JUMLAH 2,207,116.80 21,860.00 2,228,976.80
DIBULATKAN 2,207,116.00 21,860.00 2,228,976.00

SNI 1.000 m3 Pasang Nook,Goording dan Jurai kayu kelas II


1.100 m3 Kayu kls. II @ Rp. 3,135,000.00 3,448,500.00
0.800 kg Paku biasa 2" - 5" @ Rp. 27,325.00 21,860.00
12.000 OH Tukang kayu @ Rp. 137,088.00 1,645,056.00
1.200 OH Kepala tukang kayu @ Rp. 154,224.00 185,068.80
4.000 OH Pekerja @ Rp. 85,680.00 342,720.00
0.200 OH Mandor @ Rp. 171,360.00 34,272.00
JUMLAH 2,207,116.80 3,470,360.00 5,677,476.80
DIBULATKAN 2,207,116.00 3,470,360.00 5,677,476.00

1.000 m3 Pasang Gelagar dan balok skor


1.100 m3 Kayu Kls I @ Rp. 4,220,000.00 4,642,000.00
15.000 OH Tukang kayu @ Rp. 137,088.00 2,056,320.00
1.500 OH Kep. Tk. Kayu @ Rp. 154,224.00 231,336.00
5.000 OH Pekerja @ Rp. 85,680.00 428,400.00
0.250 OH Mandor @ Rp. 171,360.00 42,840.00
JUMLAH 2,764,302.00 4,894,000.00 7,658,302.00
DIBULATKAN 2,764,302.00 4,894,000.00 7,658,302.00

SNI 1.000 m3 Pasang Kolom Kayu Kelas I


1.100 m3 Kayu kls. I @ Rp. 4,220,000.00 4,642,000.00
0.250 kg Paku biasa 2" - 5" @ Rp. 27,325.00 6,831.25
12.000 OH Tukang kayu @ Rp. 137,088.00 1,645,056.00
1.200 OH Kepala tukang kayu @ Rp. 154,224.00 185,068.80
4.000 OH Pekerja @ Rp. 85,680.00 342,720.00
0.500 OH Mandor @ Rp. 171,360.00 85,680.00
JUMLAH 2,258,524.80 4,648,831.25 6,907,356.05
DIBULATKAN 2,258,524.00 4,648,831.00 6,907,356.00

1.000 m2 Pasang Dinding Papan Kayu Kls. I 2/20


0.022 m3 Kayu kls. I @ Rp. 4,220,000.00 92,840.00
0.200 kg Paku biasa 2" - 5" @ Rp. 27,325.00 5,465.00
0.013 m 3
Balok Kayu kls. II 5/10 @ Rp. 3,135,000.00 40,755.00
0.080 OH Tukang kayu @ Rp. 137,088.00 10,967.04
0.080 OH Kepala tukang kayu @ Rp. 154,224.00 12,337.92
0.200 OH Pekerja @ Rp. 85,680.00 17,136.00
0.100 OH Mandor @ Rp. 171,360.00 17,136.00
JUMLAH 57,576.96 139,060.00 196,636.96
DIBULATKAN 57,576.00 139,060.00 196,636.00

1.000 m2 Pasang Papan Lantai Kayu Kls. I 1"/20


0.026 m3 Kayu kls. I @ Rp. 4,220,000.00 110,775.00
0.750 kg Paku biasa 2" - 5" @ Rp. 27,325.00 20,493.75
1.100 OH Upah Menggergaji @ Rp. 94,248.00 103,672.80
0.500 OH Tukang kayu @ Rp. 137,088.00 68,544.00
0.050 OH Kepala tukang kayu @ Rp. 154,224.00 7,711.20
0.200 OH Pekerja @ Rp. 85,680.00 17,136.00
0.010 OH Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 198,777.60 131,268.75 330,046.35
DIBULATKAN 198,777.00 131,268.00 330,046.00

PEKERJAAN PINTU DAN JENDELA

SNI 1.000 m3 Membuat kusen pintu / jendela kayu kelas I


6.1 1.100 m3 Kayu kls. I @ Rp. 4,220,000.00 4,642,000.00
03-3434-2002 20.000 OH Tukang kayu @ Rp. 137,088.00 2,741,760.00
2.000 OH Kepala tukang kayu @ Rp. 154,224.00 308,448.00
6.000 OH Pekerja @ Rp. 85,680.00 514,080.00
0.300 OH Mandor @ Rp. 171,360.00 51,408.00
JUMLAH 3,615,696.00 4,642,000.00 8,257,696.00
DIBULATKAN 3,615,696.00 4,642,000.00 8,257,696.00

SNI 1.000 m2 Pasang pintu teakwood rangkap, rangka kayu kelas II


6.19 0.020 m3 Papan kayu kls. II @ Rp. 3,135,000.00 61,446.00
03-3434-2002 0.030 kg Paku biasa 1/2" - 1" @ Rp. 27,325.00 819.75
0.300 kg Lem kayu @ Rp. 125,000.00 37,500.00
1.000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 129,954.00 129,954.00
2.000 OH Tukang kayu @ Rp. 137,088.00 274,176.00
0.200 OH Kepala tukang kayu @ Rp. 154,224.00 30,844.80
0.600 OH Pekerja @ Rp. 85,680.00 51,408.00
0.030 OH Mandor @ Rp. 171,360.00 5,140.80
JUMLAH 361,569.60 229,719.75 591,289.35
DIBULATKAN 361,569.00 229,719.00 591,289.00

1.000 m2 Pasang pintu teakwood rangkap lapis seng plat BJLS 30, rangka kayu kelas II
0.020 m3 Papan kayu kls. II @ Rp. 3,135,000.00 61,446.00
0.030 kg Paku biasa 1/2" - 1" @ Rp. 27,325.00 819.75
0.300 kg Lem kayu @ Rp. 125,000.00 37,500.00
1.000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 129,954.00 129,954.00
1.000 lbr Seng Plat BJLS 30 @ Rp. 100,200.00 100,200.00
2.000 OH Tukang kayu @ Rp. 137,088.00 274,176.00
0.200 OH Kepala tukang kayu @ Rp. 154,224.00 30,844.80
0.600 OH Pekerja @ Rp. 85,680.00 51,408.00
0.030 OH Mandor @ Rp. 171,360.00 5,140.80
JUMLAH 361,569.60 329,919.75 691,489.35
DIBULATKAN 361,569.00 329,919.00 691,489.00
SNI 1.000 m2 Mengerjakan daun pintu / jendela panil kayu Kls I
6.7 0.040 m3 Kayu Kls I @ Rp. 4,220,000.00 168,800.00
03-3434-2002 2.500 OH Tukang kayu @ Rp. 137,088.00 342,720.00
0.250 OH Kepala tukang kayu @ Rp. 154,224.00 38,556.00
1.000 OH Pekerja @ Rp. 85,680.00 85,680.00
0.050 OH Mandor @ Rp. 171,360.00 8,568.00
JUMLAH 475,524.00 168,800.00 644,324.00
DIBULATKAN 475,524.00 168,800.00 644,324.00

SNI 1.000 m2 Pasang pintu dan jendela jalusi kayu kelas I


6.12 0.064 m3 Kayu Kls I @ Rp. 4,220,000.00 270,080.00
03-3434-2002 3.000 OH Tukang kayu @ Rp. 137,088.00 411,264.00
0.300 OH Kepala tukang kayu @ Rp. 154,224.00 46,267.20
1.000 OH Pekerja @ Rp. 85,680.00 85,680.00
0.300 OH Mandor @ Rp. 171,360.00 51,408.00
JUMLAH 594,619.20 270,080.00 864,699.20
DIBULATKAN 594,619.00 270,080.00 864,699.00

1.000 m2 Mengerjakan daun pintu / jendela panil kaca 5 mm


0.025 m3 Kayu Kls I @ Rp. 4,220,000.00 105,500.00
0.800 m2 Kaca 5 mm Bening @ Rp. 357,500.00 286,000.00
3.000 OH Tukang kayu @ Rp. 137,088.00 411,264.00
0.300 OH Kepala tukang kayu @ Rp. 154,224.00 46,267.20
1.000 OH Pekerja @ Rp. 85,680.00 85,680.00
0.050 OH Mandor @ Rp. 171,360.00 8,568.00
JUMLAH 551,779.20 286,000.00 837,779.20
DIBULATKAN 551,779.00 286,000.00 837,779.00

1.000 m2 Mengerjakan Jalusi Kayu Kls. I


0.022 m3 Kayu Kls I @ Rp. 4,220,000.00 92,840.00
0.200 kg Paku Campur @ Rp. 27,325.00 5,465.00
2.000 OH Tukang kayu @ Rp. 137,088.00 274,176.00
0.200 OH Kepala tukang kayu @ Rp. 154,224.00 30,844.80
0.500 OH Pekerja @ Rp. 85,680.00 42,840.00
0.025 OH Mandor @ Rp. 85,680.00 2,142.00
JUMLAH 350,002.80 5,465.00 355,467.80
DIBULATKAN 350,002.00 5,465.00 355,467.00

PEKERJAAN PLAFOND

1.000 m2 Pasang rangka langit-langit (60 x 120) m, kayu kelas II


0.013 m3 Kayu kls. II @ Rp. 3,135,000.00 40,755.00
0.120 kg Paku @ Rp. 27,325.00 3,279.00
0.270 OH Tukang kayu @ Rp. 137,088.00 37,013.76
0.027 OH Kepala tukang kayu @ Rp. 154,224.00 4,164.05
0.170 OH Pekerja @ Rp. 85,680.00 14,565.60
0.009 OH Mandor @ Rp. 171,360.00 1,456.56
JUMLAH 57,199.97 44,034.00 101,233.97
DIBULATKAN 57,199.00 44,034.00 101,233.00

1.000 m2 Langit-langit tripleks t; 4 mm, rangka 60 x 120 kayu kls. II


0.336 Lbr Tripleks 3 mm @ Rp. 95,590.00 32,118.24
0.017 M3 Kayu Matoa @ Rp. 3,135,000.00 53,295.00
0.200 Kg Paku @ Rp. 27,325.00 5,465.00
0.020 Kg Paku Tripleks @ Rp. 32,770.00 655.40
0.400 OH Tukang kayu @ Rp. 137,088.00 54,835.20
0.040 OH Kepala tukang kayu @ Rp. 154,224.00 6,168.96
0.280 OH Pekerja @ Rp. 85,680.00 23,990.40
0.014 OH Mandor @ Rp. 171,360.00 2,399.04
JUMLAH 87,393.60 91,533.64 178,927.24
DIBULATKAN 87,393.00 91,533.00 178,927.00

PEKERJAAN LISPLANK
SNI 1.000 m1 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu kelas I
0.009 m3 Kayu kls. I papan @ Rp. 4,220,000.00 36,292.00
03-3434-2002 0.060 kg Paku biasa 2" - 5" @ Rp. 27,325.00 1,639.50
0.100 OH Tukang kayu @ Rp. 137,088.00 13,708.80
0.010 OH Kepala tukang kayu @ Rp. 154,224.00 1,542.24
0.100 OH Pekerja @ Rp. 85,680.00 8,568.00
0.005 OH Mandor @ Rp. 171,360.00 856.80
JUMLAH 24,675.84 37,931.50 62,607.34
DIBULATKAN 24,675.00 37,931.00 62,607.00

PEKERJAAN TALANG
SNI 1.000 m1 Pasang talang datar, seng BJLS 30, papan kayu kelas II
6.18 0.500 lbr Seng plat 3' x 6' BJLS 30 @ Rp. 100,200.00 50,100.00
0.015 kg Paku biasa 1/2" - 1" @ Rp. 27,325.00 409.88
0.010 m3 Kayu kls. II papan @ Rp. 3,135,000.00 30,096.00
0.400 OH Tukang kayu @ Rp. 137,088.00 54,835.20
0.025 OH Kepala tukang kayu @ Rp. 154,224.00 3,855.60
0.150 OH Pekerja @ Rp. 85,680.00 12,852.00
0.001 OH Mandor @ Rp. 171,360.00 214.20
JUMLAH ( BELUM PPN ) 71,757.00 80,605.88 152,362.88
DIBULATKAN 71,757.00 80,605.00 152,362.00

PEKERJAAN ATAP

SNI 1.000 m2 Pasang atap Superdek 6 kaki


6.21 0.870 Lbr Superdeks @ Rp. 138,600.00 120,582.00
03-3436-2002 0.025 Kg Paku Ardeks @ Rp. 45,475.00 1,136.88
0.067 OH Tukang kayu @ Rp. 137,088.00 9,184.90
0.007 OH Kepala tukang kayu @ Rp. 154,224.00 1,079.57
0.140 OH Pekerja @ Rp. 85,680.00 11,995.20
0.007 OH Mandor @ Rp. 171,360.00 1,199.52
JUMLAH 23,459.18 121,718.88 145,178.06
DIBULATKAN 23,459.00 121,718.00 145,178.00
SNI 1.000 m2 Pasang atap Seng gelombang BJLS 30
6.21 0.870 Lbr Seng gelombang BJLS 30 @ Rp. 88,200.00 76,734.00
03-3436-2002 0.025 Kg Paku seng @ Rp. 45,475.00 1,136.88
0.067 OH Tukang kayu @ Rp. 137,088.00 9,184.90
0.007 OH Kepala tukang kayu @ Rp. 154,224.00 1,079.57
0.140 OH Pekerja @ Rp. 85,680.00 11,995.20
0.007 OH Mandor @ Rp. 171,360.00 1,199.52
JUMLAH 23,459.18 77,870.88 101,330.06
DIBULATKAN 23,459.00 77,870.00 101,330.00

SNI 1.000 m1 Pasang nok Seng plat BJLS 30


6.22 0.380 Lbr Seng Plat BJLS 30 @ Rp. 41,800.00 15,884.00
03-3436-2002 0.004 M3 Kayu Matoa @ Rp. 3,135,000.00 12,540.00
0.020 Kg Paku Seng @ Rp. 45,475.00 909.50
0.125 OH Tukang kayu @ Rp. 137,088.00 17,136.00
0.013 OH Kepala tukang kayu @ Rp. 154,224.00 2,004.91
0.084 OH Pekerja @ Rp. 85,680.00 7,197.12
0.004 OH Mandor @ Rp. 171,360.00 685.44
JUMLAH 27,023.47 29,333.50 56,356.97
DIBULATKAN 27,023.00 29,333.00 56,356.00

PEKERJAAN BESI DAN ALUMUNIUM

SNI 1.000 m2 Pasang Rolling door


1.000 m2 Roll door @ Rp. 500,000.00 500,000.00
6.8 1.050 OH Tukang besi konstruksi @ Rp. 137,088.00 143,942.40
0.105 OH Kepala tukang besi @ Rp. 154,224.00 16,193.52
1.050 OH Pekerja @ Rp. 85,680.00 89,964.00
0.005 OH Mandor @ Rp. 171,360.00 891.07
JUMLAH 250,990.99 500,000.00 750,990.99
DIBULATKAN 250,990.00 500,000.00 750,990.00

SNI 1.000 m2 Pasang pintu alumunium


1.000 m2 Pintu alumunium @ Rp. 400,000.00 400,000.00
6.9 1.050 OH Tukang besi konstruksi @ Rp. 137,088.00 143,942.40
0.105 OH Kepala tukang besi @ Rp. 154,224.00 16,193.52
1.050 OH Pekerja @ Rp. 85,680.00 89,964.00
0.005 OH Mandor @ Rp. 171,360.00 891.07
JUMLAH 250,990.99 400,000.00 650,990.99
DIBULATKAN 250,990.00 400,000.00 650,990.00

SNI 1.000 m2 Pasang teralis besi


11.500 m1 Baja strip 2 x 3 @ Rp. 9,790.00 112,585.00
6.12 1.200 OH Tukang las @ Rp. 137,088.00 164,505.60
0.012 OH Kepala tukang las @ Rp. 154,224.00 1,850.69
1.200 OH Pekerja @ Rp. 85,680.00 102,816.00
0.001 OH Mandor @ Rp. 171,360.00 102.82
JUMLAH ( BELUM PPN ) 269,275.10 112,585.00 381,860.10
DIBULATKAN 269,275.00 112,585.00 381,860.00

SNI 1.000 set Pasang jendela louver lengkap teralis


1.100 set jendela louver lengkap teralis @ Rp. 391,680.00 430,848.00
6.17 0.020 kg Paku skrup @ Rp. 20,725.00 414.50
0.025 m2 Besi strip @ Rp. 114,000.00 2,850.00
0.200 OH Tukang kayu @ Rp. 137,088.00 27,417.60
0.020 OH Kepala tukang kayu @ Rp. 154,224.00 3,084.48
0.200 OH Pekerja @ Rp. 85,680.00 17,136.00
0.001 OH Mandor @ Rp. 171,360.00 171.36
JUMLAH ( BELUM PPN ) 47,809.44 434,112.50 481,921.94
DIBULATKAN 47,809.00 434,112.00 481,921.00

PEKERJAAN KUNCI DAN KACA

6.1 1.000 bh Pasang kunci tanam antik


1.000 bh Kunci tanam antik @ Rp. 275,000.00 275,000.00
0.600 OH Tukang kayu @ Rp. 137,088.00 82,252.80
0.060 OH Kepala tukang kayu @ Rp. 154,224.00 9,253.44
0.060 OH Pekerja @ Rp. 85,680.00 5,140.80
0.003 OH Mandor @ Rp. 171,360.00 514.08
JUMLAH 97,161.12 275,000.00 372,161.12
DIBULATKAN 97,161.00 275,000.00 372,161.00

6.2 1.000 bh Pasang kunci tanam biasa


1.000 bh Kunci tanam biasa @ Rp. 173,937.00 173,937.00
0.500 OH Tukang kayu @ Rp. 137,088.00 68,544.00
0.010 OH Kepala tukang kayu @ Rp. 154,224.00 1,542.24
0.010 OH Pekerja @ Rp. 85,680.00 856.80
0.005 OH Mandor @ Rp. 171,360.00 856.80
JUMLAH 71,799.84 173,937.00 245,736.84
DIBULATKAN 71,799.00 173,937.00 245,736.00

6.5 1.000 bh Pasang engsel pintu


1.000 bh Engsel pintu @ Rp. 37,257.00 37,257.00
0.150 OH Tukang kayu @ Rp. 137,088.00 20,563.20
0.015 OH Kepala tukang kayu @ Rp. 154,224.00 2,313.36
0.015 OH Pekerja @ Rp. 85,680.00 1,285.20
0.001 OH Mandor @ Rp. 171,360.00 128.52
JUMLAH 24,290.28 37,257.00 61,547.28
DIBULATKAN 24,290.00 37,257.00 61,547.00

6.6 1.000 bh Pasang engsel jendela kupu-kupu


1.000 bh Engsel jendela @ Rp. 15,812.00 15,812.00
0.100 OH Tukang kayu @ Rp. 137,088.00 13,708.80
0.010 OH Kepala tukang kayu @ Rp. 154,224.00 1,542.24
0.010 OH Pekerja @ Rp. 85,680.00 856.80
0.005 OH Mandor @ Rp. 171,360.00 856.80
JUMLAH 16,964.64 15,812.00 32,776.64
DIBULATKAN 16,964.00 15,812.00 32,776.00

6.7 1.000 bh Pasang engsel angin


1.000 bh Engsel angin @ Rp. 14,231.00 14,231.00
0.200 OH Tukang kayu @ Rp. 137,088.00 27,417.60
0.020 OH Kepala tukang kayu @ Rp. 154,224.00 3,084.48
0.020 OH Pekerja @ Rp. 85,680.00 1,713.60
0.010 OH Mandor @ Rp. 171,360.00 1,713.60
JUMLAH 33,929.28 14,231.00 48,160.28
DIBULATKAN 33,929.00 14,231.00 48,160.00

6.9 1.000 bh Pasang kait angin


1.000 bh Kait angin @ Rp. 58,437.00 58,437.00
0.150 OH Tukang kayu @ Rp. 137,088.00 20,563.20
0.015 OH Kepala tukang kayu @ Rp. 154,224.00 2,313.36
0.015 OH Pekerja @ Rp. 85,680.00 1,285.20
0.001 OH Mandor @ Rp. 171,360.00 128.52
JUMLAH 24,290.28 58,437.00 82,727.28
DIBULATKAN 24,290.00 58,437.00 82,727.00

1.000 bh Pasang Tarikan jendela


1.000 bh Tarikan jendela @ Rp. 11,687.00 11,687.00
0.150 OH Tukang kayu @ Rp. 137,088.00 20,563.20
0.015 OH Kepala tukang kayu @ Rp. 154,224.00 2,313.36
0.015 OH Pekerja @ Rp. 85,680.00 1,285.20
0.001 OH Mandor @ Rp. 171,360.00 128.52
JUMLAH 24,290.28 11,687.00 35,977.28
DIBULATKAN 24,290.00 11,687.00 35,977.00

6.11 1.000 bh Pasang kunci selot


1.000 bh Kunci selot @ Rp. 17,187.00 17,187.00
0.200 OH Tukang kayu @ Rp. 137,088.00 27,417.60
0.020 OH Kepala tukang kayu @ Rp. 154,224.00 3,084.48
0.020 OH Pekerja @ Rp. 85,680.00 1,713.60
0.001 OH Mandor @ Rp. 171,360.00 171.36
JUMLAH 32,387.04 17,187.00 49,574.04
DIBULATKAN 32,387.00 17,187.00 49,574.00

6.16 1.000 m2 Pasang kaca, tebal 3 mm


1.100 m2 Kaca polos @ Rp. 341,000.00 375,100.00
0.150 OH Tukang kayu @ Rp. 137,088.00 20,563.20
0.015 OH Kepala tukang kayu @ Rp. 154,224.00 2,313.36
0.015 OH Pekerja @ Rp. 85,680.00 1,285.20
0.001 OH Mandor @ Rp. 171,360.00 128.52
JUMLAH 24,290.28 375,100.00 399,390.28
DIBULATKAN 24,290.00 375,100.00 399,390.00

6.17 1.000 m2 Pasang kaca, tebal 5 mm


1.100 m2 Kaca polos @ Rp. 357,500.00 393,250.00
0.150 OH Tukang kayu @ Rp. 137,088.00 20,563.20
0.015 OH Kepala tukang kayu @ Rp. 154,224.00 2,313.36
0.015 OH Pekerja @ Rp. 85,680.00 1,285.20
0.001 OH Mandor @ Rp. 171,360.00 128.52
JUMLAH 24,290.28 393,250.00 417,540.28
DIBULATKAN 24,290.00 393,250.00 417,540.00
ANJALISA PEKERJAAN LISTRIK
No. Macam Pekerjaan Upah Bahan
(1) (2) (3) (4)

23. 1.0000 bh Pasang MCB Ampere + box tutup panel ukuran 30 x 30


1.0000 bh MCB 10 Ampere + box @ Rp. 103,824.00 103,824.00
0.0500 org Tukang listrik @ Rp. 137,088.00 6,854.40
0.1000 org Pekerja @ Rp. 85,680.00 8,568.00
0.0250 org Mandor @ Rp. 171,360.00 4,284.00
JUMLAH 19,706.40 103,824.00
DIBULATKAN 19,706.00 103,824.00

1.0000 TITIK PASANG LAMPU XL 8 WATT


1.0000 Bh Fitting 27,500.00 27,500.00
1.0000 Bh Lampu Pijar XL-8 Watt 55,000.00 55,000.00
10.0000 M1 Kabel NYY 3x2½ 26,235.00 262,350.00
10.0000 M1 Pipa Paralon instalasi 5/8" 5,859.00 58,590.00
1.0000 Bh Saklar 27,500.00 27,500.00
4.0000 Bh Isolator 13,750.00 55,000.00
1.0000 H/O Tukang Listrik 137,088.00 137,088.00
1.0000 TTK Instalasi 60,000.00 60,000.00
JUMLAH 545,940.00 137,088.00
DIBULATKAN 545,940.00 137,088.00

1.0000 TITIK PASANG LAMPU XL 18 WATT


1.0000 Bh Fitting 27,500.00 27,500.00
1.0000 Bh Lampu Pijar XL 18 Watt 89,375.00 89,375.00
10.0000 M1 Kabel NYY 3x2½ 26,235.00 262,350.00
10.0000 M1 Pipa Paralon instalasi 5/8" 5,859.00 58,590.00
1.0000 Bh Saklar 31,250.00 31,250.00
4.0000 Bh Isolator 13,750.00 55,000.00
1.0000 H/O Tukang Listrik 137,088.00 137,088.00
1.0000 TTK Instalasi 60,000.00 60,000.00
JUMLAH 584,065.00 137,088.00
DIBULATKAN 584,065.00 137,088.00

1.0000 TITIK PASANG LAMPU TL 40 WATT


1.0000 Bh Lampu Pijar TL 40 Watt 158,950.00 158,950.00
10.0000 M1 Kabel NYY 3x2½ 26,235.00 262,350.00
10.0000 M1 Pipa Paralon instalasi 5/8" 5,859.00 58,590.00
1.0000 Bh Saklar 31,250.00 31,250.00
4.0000 Bh Isolator 13,750.00 55,000.00
1.0000 H/O Tukang Listrik 137,088.00 137,088.00
1.0000 TTK Instalasi 60,000.00 60,000.00
JUMLAH 626,140.00 137,088.00
DIBULATKAN 626,140.00 137,088.00

1.0000 TITIK PASANG STOP KONTAK


1.0000 Bh Stop Kontak 33,687.00 33,687.00
5.0000 M1 Kabel NYY 2x2½ 21,900.00 109,500.00
3.0000 M1 Pipa Paralon instalasi 5/8" 5,859.00 17,577.00
4.0000 Bh Isolator 13,750.00 55,000.00
0.8300 H/O Tukang Listrik 137,088.00 113,783.04
1.0000 TTK Instalasi 60,000.00 60,000.00
JUMLAH 275,764.00 113,783.04
(1) (2) (3) (4)
DIBULATKAN 275,764.00 113,783.00

1.0000 TITIK PASANG SAKLAR TUNGGAL


1.0000 Bh Saklar Tunggal 31,250.00 31,250.00
5.0000 M1 Kabel NYY 2x2½ 21,900.00 109,500.00
3.0000 M1 Pipa Paralon instalasi 5/8" 5,859.00 17,577.00
4.0000 Bh Isolator 13,750.00 55,000.00
0.8300 H/O Tukang Listrik 137,088.00 113,783.04
1.0000 TTK Instalasi 60,000.00 60,000.00
JUMLAH 273,327.00 113,783.04
DIBULATKAN 273,327.00 113,783.00

1.0000 TITIK PASANG SAKLAR GANDA


1.0000 Bh Saklar Ganda 34,375.00 34,375.00
5.0000 M1 Kabel NYY 2x2½ 21,900.00 109,500.00
3.0000 M1 Pipa Paralon instalasi 5/8" 5,859.00 17,577.00
4.0000 Bh Isolator 13,750.00 55,000.00
0.8300 H/O Tukang Listrik 137,088.00 113,783.04
1.0000 TTK Instalasi 60,000.00 60,000.00
JUMLAH 276,452.00 113,783.04
DIBULATKAN 276,452.00 113,783.00
Jumlah
(5)

123,530.40
123,530.00

683,028.00
683,028.00

721,153.00
721,153.00

763,228.00
763,228.00

389,547.04
(5)
389,547.00

387,110.04
387,110.00

390,235.04
390,235.00
DAFTAR HARGA BAHAN BANGUNAN DAN UPAH KABUPATEN WAROPEN
1687
1.25 A. DAFTAR HARGA UPAH ###
UPAH TENAGA
NO. TENAGA KERJA KERJA (Rp. /
HARI)
1 Mandor Rp 171,360.00
2 Mekanik Rp 154,224.00
3 Mekanik Pembantu Rp 137,088.00
4 Kepala Tukang Rp 154,224.00
5 Tukang Rp 137,088.00
6 Operator Terampil Rp 171,360.00
7 Operator Kurang Terampil Rp 154,224.00
8 Pembantu Opearator Rp 137,088.00
9 Sopir Truck Rp 137,088.00
10 Sopir Pribadi Rp 119,952.00
11 Pembantu Sopir Rp 119,952.00
12 Buruh Tak Terampil Rp 85,680.00
13 Buruh Kurang Terampil Rp 94,248.00
14 Buruh Terampil Rp 102,816.00

B. DAFTAR HARGA BAHAN BANGUNAN

Wilayah "A" Urfas


NO JENIS BAHAN BANGUNAN
s/d Waropen Bawah

BAHAN DASAR
1 Batu
Batu Gunung/Karang Laut M3 Rp 770,000.00
Batu Karang dari Serui M3 Rp 895,000.00
Batu Kali dari Botawa M3 Rp 732,000.00
Batu Kali dari Serui M3 Rp 900,000.00
2 Koral/Kerikil
Koral/Kerikil laut sudah diayak dari Waren/Urfas M3 Rp 535,000.00
Koral/Kerikil Sungai dari Botawa M3 Rp 787,000.00
3 Pasir
Pasir Beton dari Botawa M3 Rp 766,000.00
Pasir Pasang Laut M3 Rp 333,200.00
Pasir Batu (Sirtu) dari Waren/Urfas M3 Rp 305,000.00
Pasir Urug/Timbunan M 3
Rp 305,000.00
4 Tanah Urug/Timbunan M 3
Rp 301,000.00
5 Batu Merah Bh Rp 4,640.00
6 Batu Tela Bh Rp 5,800.00
7 Conblok Bh Rp 23,415.00
8 Kanstin 15x20x40 bh Rp 36,857.14
9 Paving Block 10x20 Tebal 7 cm Bh Rp 4,300.00
10 Paving Block Segi enam Tebal 7 cm Bh Rp 7,500.00
11 Batu tempel hitam M2 Rp 350,000.00
12 Semen
Semen 1 Zak = 40 Kg kg Rp 2,856.25
Semen Putih/Warna Kg Rp 18,150.00

BAHAN KAYU
1 Balok/Papan Kayu Besi (Klas I) M3 Rp 4,220,000.00
2 Balok/Papan Kayu Matoa (Klas II) M 3
Rp 3,135,000.00
3 Balok/Papan Kayu Tinang (Klas III) M 3
Rp 2,535,000.00
4 Kayu Bakar M3 Rp 675,000.00
5 Kayu Perancah M3 Rp 1,895,000.00

BAHAN LANTAI
1 Tegel Mozaik 30 x 30 CM M2 Rp 266,860.00
2 Tegel Keramik
Putih 11 x 11 CM Bh Rp 3,200.00
Warna 11 x 11 CM Bh Rp 3,840.00
Putih 10 x 20 CM Bh Rp 3,520.00
Warna 10 x 20 CM Bh Rp 4,000.00
Putih 15 x 15 CM Bh Rp 6,066.00
Warna 15 x 15 CM Bh Rp 7,169.00
Putih 20 x 20 CM M2 Rp 272,975.00
Warna 20 x 20 CM M 2
Rp 310,200.00
Putih 20 x 25 CM M 2
Rp 266,860.00
Warna 20 x 25 CM M 2
Rp 317,700.00
Putih 30 x 30 CM M 2
Rp 266,860.00
Warna 30 x 30 CM M 2
Rp 317,691.00
Putih 40 x 40 CM M 2
Rp 285,768.00
Warna 40 x 40 CM M 2
Rp 299,376.00

BAHAN BESI/BAJA
1 Besi Beton
Besi Beton Polos Kg Rp 24,400.00
Besi Beton Ulir Kg Rp 24,400.00
2 Paku
Paku Colour Tiles/Metal Roof kg Rp 62,727.00
Paku Eternit kg Rp 40,493.00
Paku Seng Kg Rp 45,475.00
Paku Campur Kg Rp 27,325.00
Paku Ardeks Kg Rp 45,475.00
Paku Beton Kg Rp 61,601.00
Paku Jembatan Kg Rp 44,771.00
Paku Skrup Dos Rp 20,725.00
Paku Tripleks Kg Rp 32,770.00
3 Kawat
Kawat Ikat / Beton Kg Rp 34,563.00
6 Besi Baja/Strip
Besi Siku/Baja Kg Rp 36,603.75
Besi Strip 2 x 0,3 x 400 M1 Rp 9,790.00

BAHAN PIPA
2 Pipa Paralon PVC
Pipa Paralon Ø 1/4" M1 Rp 9,843.00
Pipa PVC Ø 1/2" M 1
Rp 13,387.00
Pipa PVC Ø 3/4" M 1
Rp 15,300.00
Pipa PVC Ø 1" M 1
Rp 20,700.00
Pipa PVC Ø 1½" M 1
Rp 31,500.00
Pipa PVC Ø 2" M 1
Rp 45,000.00
Pipa PVC Ø 2½" M 1
Rp 66,600.00
Pipa PVC Ø 3" M 1
Rp 90,900.00
Pipa PVC Ø 4" M 1
Rp 105,000.00
Pipa PVC Ø 5" M 1
Rp 137,300.00
Pipa PVC Ø 6" M1 Rp 192,500.00
Pipa PVC Ø 8" M1 Rp 328,500.00
Pipa PVC Ø 10" M1 Rp 499,500.00
3 Jenis Batang D u/Sal. Pembuangan Air
Ø 1/2" - 4 m M1 Rp 9,090.00
Ø 3/4" - 4 m M 1
Rp 12,120.00
Ø 1" - 4 m M1 Rp 18,558.75
Ø 1½" - 4 m M1 Rp 19,316.25
Ø 2" - 4 m M1 Rp 23,482.50
Ø 2½" - 4 m M 1
Rp 31,587.75
Ø 3" - 4 m M 1
Rp 41,662.50
Ø 4" - 4 m M 1
Rp 66,660.00
Ø 5" - 4 m Btg Rp 101,883.75
Ø 6" - 4 m Btg Rp 137,865.00
Ø 10" - 4 m Btg Rp 396,930.00
4 Jenis Batang C u/Instalasi Listrik
Ø 5/8" - 4 m M1 Rp 5,859.00
Ø 3/4" - 4 m M 1
Rp 15,750.00
Ø 1" - 4 m M 1
Rp 18,000.00
Ø 1½" - 4 m Btg Rp 23,437.00
5 Sock Lurus, Sock Drat Dalam, Sok Drat Luar, Knie & Bh Rp 42,281.00
Teste PVC
6 Lem PVC Tube Rp 15,125.00
7 Alat Bantu Set Rp 330,000.00
8 Gate Valve GIP f 1" Bh Rp 294,400.00
9 Gate Valve GIP f 2" Bh Rp 404,050.00
10 Gate Valve GIP f 3" Bh Rp 759,862.00
11 Gate Valve GIP f 4" Bh Rp 996,906.00
12 Gate Valve GIP f 6" Bh Rp 1,176,593.00
13 Gate Valve GIP f 8" Bh Rp 1,356,281.00
14 Seal Type Bh Rp 13,750.00

BAHAN LANGIT-LANGIT
1 Eternit 100 X 100 Lbr Rp 85,921.00
2 Tripleks
122x244x0,3 cm Lbr Rp 95,590.00
122x244x0,4 cm Lbr Rp 129,954.00
122x244x0,6 cm Lbr Rp 226,050.00
122x244x0,9 cm Lbr Rp 335,940.00
3 Tripleks melamin 122x244x0,3 cm Lbr Rp 115,610.00
4 Acoustic 40x60 Lbr Rp 44,625.00
5 Teakwood
122x244x0,3 cm Lbr Rp 162,140.00
80x244x0,3 cm Lbr Rp 121,605.00
6 Hard Board 122x244 cm Lbr Rp 221,100.00
7 Asbes Plat Harflek 200x100x0,3 cm Lbr Rp 112,500.00
8 Plywood Lbr Rp 152,278.00
9 Formika Lbr Rp 310,500.00
10 Kayu List Plafond M1 Rp 14,300.00

BAHAN ATAP
1 Genteng
Beton Bh Rp 26,538.00
Keramik Bh Rp 13,500.00
Asbes Lbr Rp 32,500.00
Harfles (115x85x0,5 cm) Lbr Rp 62,500.00
2 Asbes Gelombang Kaki/Lbr Rp 100,000.00
3 Sirap Ikat/M2 Rp 100,000.00
4 Seng Gelombang
BWG 34" BJLS 0,20 mm Lbr Rp 72,450.00
BWG 32" BJLS 0,30 mm Lbr Rp 88,200.00
BWG 28" BJLS 0,35 mm Lbr Rp 105,875.00
5 Seng Plat
BJLS 0,30 mm Lbr Rp 100,200.00
BJLS 0,20 mm Lbr Rp 84,450.00
6 Seng Super Dek
180x70 cm - 10 kaki Lbr Rp 231,000.00
180x70 cm - 8 kaki Lbr Rp 184,800.00
180x70 cm - 7 kaki Lbr Rp 161,700.00
180x70 cm - 6 kaki Lbr Rp 138,600.00
7 Seng Aluminium Gelombang
SWG 32" 0,27 mm Lbr Rp 85,470.00
SWG 32" 0,31 mm Lbr Rp 120,393.00
SWG 32" 0,38 mm Lbr Rp 127,050.00
8 Seng Plastik (Fiber) Kaki/Lbr Rp 138,600.00
9 Atap Plastik Gelombang Besar Lbr Rp 130,812.00
10 Atap Plastik Gelombang Kecil Lbr Rp 104,144.00
11 Ardek Gelombang Lbr Rp 110,975.00
12 Seng Galvanis Lbr Rp 113,437.00
13 Fiber Semen (Harlek)
Super 240x108 x0,6 cm Lbr Rp 137,500.00
Super 180x108 x0,6 cm Lbr Rp 94,600.00
Ekonomi 240x92x0,5 cm Lbr Rp 103,400.00
Ekonomi 180x92x0,4 cm Lbr Rp 91,300.00
Mini 240x105x0,4 cm Lbr Rp 88,000.00
Mini 180x92x0,5 cm Lbr Rp 81,400.00
Super 240x105 x0,4 cm Lbr Rp 103,400.00
Super 180x105 x0,4 cm Lbr Rp 92,400.00
14 Atap Harflex 30 x 110 x0.5 cm Lbr Rp 138,512.00
15 Atap Utomo Colour Tiles 7 Genteng Bh Rp 115,615.00
16 Nok/Bubungan
Genteng Beton Bh Rp 24,964.00
Genteng Asbes Bh Rp 30,800.00
Genteng Keramik Bh Rp 9,900.00
Alm. SWG 28" - 180 cm Lbr Rp 99,000.00
Alm. SWG 28" - 105 cm Lbr Rp 78,100.00
17 Nok Harflex 30 x 118 x0.5 cm Bh Rp 63,442.00
18 Nok Utomo Colour Tiles 7 genteng Bh Rp 95,403.00
19 Nok Steel Gelombang
Super - 180 cm Bh Rp 66,000.00
Mini - 105 cm Bh Rp 44,000.00
Ekonomi - 95 cm Bh Rp 34,100.00
20 Nok Steel Rata
Super - 108 cm Bh Rp 55,000.00
Mini - 105 cm Bh Rp 44,000.00
Ekonomi - 95 cm Bh Rp 41,800.00
21 Nok ½ Lingkaran Bh Rp 79,200.00
22 Karet Pelapis Genteng Roll Rp 340,000.00
23 Talang Paralon f 4" M1 Rp 93,008.00
24 Talang Paralon f 12" M1 Rp 126,774.00

BAHAN PINTU/ PENGGANTUNG


1 Rolling door aluminium 0,4 mm M2 Rp 500,000.00
2 Kusen Aluminium M 1
Rp 500,000.00
3 Kunci Tanam
Union 1 x slaag Bh Rp 240,625.00
Union 2 x slaag Bh Rp 275,000.00
Yalle 1 x Slaag Bh Rp 137,500.00
Yalle 2 x Slaag Bh Rp 173,937.00
Kuda Terbang 1 x Slaag Bh Rp 103,125.00
Kuda Terbang 2 x Slaag Bh Rp 123,750.00
4 Kunci Gembok No. 30 Bh Rp 47,565.00
5 Penggantung
Hak / Kait Angin Biasa Bh Rp 14,437.00
Hak / Kait Angin Kancing Bh Rp 58,437.00
Grendel Pintu Bh Rp 34,375.00
Grendel Jendela Bh Rp 17,187.00
Engsel Pintu Ring Nylon Bh Rp 37,257.00
Engsel H Pintu Bh Rp 26,616.00
Engsel Jendela Bh Rp 15,812.00
Engsel H Jendela Bh Rp 14,231.00
Engsel Almari Bh Rp 12,856.00
Tarikan Jendela Bh Rp 11,687.00
Expagnolet Bh Rp 75,625.00

BAHAN SANITAIR
1 Kloset Duduk INA Bh Rp 1,455,300.00
2 Kloset Jongkok Teraso Bh Rp 226,875.00
3 Wasthafel INA Set Rp 2,000,000.00
4 Wasthafel + Cermin INA Set Rp 2,500,000.00
5 Wasthafel Logam 1 Lubang Set Rp 680,625.00
6 Wasthafel Logam 2 Lubang Set Rp 983,125.00
7 Urinoir Porselin Bh Rp 1,629,477.00
8 Bak Air Viber Glass 200-300 ltr Bh Rp 562,500.00
9 Bak Air Viber Glass 300-500 ltr Bh Rp 656,250.00
10 Bak Air Viber Glass 750 ltr Bh Rp 906,250.00
11 Reservoir Viber Glass 650 ltr Bh Rp 1,925,000.00
12 Reservoir Viber Glass 1.100 ltr Bh Rp 2,812,500.00
13 Floor Drain dari Besi Bh Rp 67,500.00
14 Kran Air 1/2" Bh Rp 35,856.00
15 Kran Air 3/4" Bh Rp 39,468.00
16 Kran Air Aluminium Besar Bh Rp 65,868.00
17 Kran Air Wastafel Bh Rp 88,968.00
18 Penyambungan Air PDAM Ls Rp 907,500.00

BAHAN FINISHING/CAT
1 Cat Tembok Kg Rp 22,000.00
2 Cat Alkali resisting primer Kg Rp 41,205.00
3 Cat ICI Weathershield Kg Rp 82,410.00
4 Cat Kilat Kg Rp 62,025.00
5 Cat Besi Kg Rp 62,025.00
6 Cat Aluminium Kg Rp 127,516.00
7 Cat Atap/AGA Kg Rp 286,000.00
8 Meni Kayu Kg Rp 41,334.00
9 Meni Besi Kg Rp 49,650.00
10 Dempul Kayu Kg Rp 41,334.00
11 Dempul Besi Kg Rp 70,656.00
12 Plamur Besi Kg Rp 51,750.00
13 Plamur Tembok Kg Rp 40,355.00
14 Politur Kg Rp 58,650.00
15 Teak Oil Kg Rp 48,055.00
16 Minyak Cat Kg Rp 37,485.00
17 Residu Kg Rp 33,637.00
18 Dempul Kg Rp 38,053.00
19 Kertas Amplas Lbr Rp 9,400.00

BAHAN LISTRIK
1 Kabel Listrik
Type NYK
1½ mm M1 Rp 8,250.00
2½ mm M1 Rp 9,750.00
Type NYY
2 X 1½ mm M1 Rp 15,000.00
2 X 2½ mm M1 Rp 21,900.00
3 X 2½ mm M1 Rp 26,235.00
2 X 4 mm M1 Rp 30,000.00
2 Lampu TL
1 x 10 w Set Rp 63,690.00
1 x 20 w Set Rp 82,500.00
2 x 20 w Set Rp 135,575.00
1 x 40 w Set Rp 121,500.00
2 x 40 w Set Rp 158,950.00
10 Watt Bh Rp 18,750.00
20 Watt Bh Rp 26,250.00
40 Watt Bh Rp 30,000.00
3 Lampu Pijar
25 w Bh Rp 13,750.00
40 w Bh Rp 16,500.00
60 w Bh Rp 22,000.00
100 w Bh Rp 20,625.00
4 Lampu Mercuri Lengkap 250 watt Set Rp 2,567,250.00
5 Saklar
Tunggal Putih Bh Rp 31,250.00
Tunggal Hitam Bh Rp 26,875.00
Ganda Putih Bh Rp 34,375.00
Ganda Hitam Bh Rp 30,625.00
6 Stop Kontak
Putih Bh Rp 33,687.00
Hitam Bh Rp 29,562.00
7 Zekring Kast
1 Group Bh Rp 93,012.00
2 Group Bh Rp 103,824.00
3 Group Bh Rp 130,032.00
8 Fitting Tempel Kotak Bulat Putih Bh Rp 27,500.00
9 Fitting Biasa Bh Rp 17,187.00
10 Lampu XL 18 wattt Bh Rp 89,375.00
11 Lampu Sorot 500 watt Bh Rp 515,625.00
12 Lampu XL 8 wattt Bh Rp 55,000.00
13 Isolator Bh Rp 13,750.00
14 Instalasi Ttk Rp 60,000.00
15 Klem Kabel Dos Rp 24,062.00
16 Penyambungan Listrik PLTD Ls Rp 1,718,750.00
PROYEK : PEMBANGUNAN GEDUNG PUSAT PELAYANAN AKADEMIK
UNIVERSITAS NEGERI MAKASSAR TAHAP III
LOKASI : JL. A.P. PETTARANI, GUNUNGSARI BARU, RAPPOCINI, MAKASAR

RENCANA ANGGARAN BIAYA

NO URAIAN PEKERJAAN Satuan Harga

1 Air ltr 625.00


2 Beton
2.1 Beton readymix K 300 m3 784,000.00
2.2 Beton readymix K 350 m3 826,000.00

3 Besi
3.1 Besi beton kg 8,575.00
3.2 Wire mesh M8 m2 59,413.58
3.3 Besi beton ulir kg 8,575.00
3.4 Besi Hollow 40x40 kg 17,150.00
3.5 Besi plat sandaran 10x100 kg 17,150.00
3.6 Besi railing sandaran 10x50 kg 17,150.00

4 Kawat
4.1 Bendrat kg 12,740.00
4.2 Anyam m2 6,125.00

5 Keramik
5.1 Keramik 40x40 dos 112,500.00
5.2 Keramik 30x30 dos 100,000.00
5.3 Keramik 20x20 dos 100,000.00
5.4 Keramik 20x25 dos 92,500.00
5.5 Keramik step nossing 10x30 bj 8,000.00

6 Marmer
6.1 Marmer Pangkep 60x60 dinding m2 325,000.00
6.2 Marmer Pangkep 60x60 lantai m2 325,000.00

7 Paku
7.1 Paku kg 14,976.91

8 Pasir
8.1 Pasir beton m3 104,187.20
8.2 Pasir pasang m3 104,187.20
8.3 pasir urug m3 78,140.40
8.4 Sirtu m3 110,698.90

9 Semen
9.1 Semen PC kg 1,237.22
9.2 Semen hardener kg 2,604.68
9.3 Semen nat ( tile grout ) kg 19,535.10

10 Batako
10.1 Batako bj 3,255.85
10.2 Batako roster bj 3,907.02

11 Batu
11.1 Batu kali m3 117,210.60
11.2 Batu pecah 2-3 cm m3 123,722.30

12 Kayu
12.1 Balok klas I m3 2,344,212.00
12.2 Papan klas I m3 2,409,329.00
12.3 Balok klas II m3 2,213,978.00
12.4 Papan klas II m3 2,279,095.00
12.5 Balok klas III m3 1,953,510.00
12.6 Papan klas III m3 2,018,627.00
12.7 Kayu begisting m3 1,953,510.00
12.8 Multipleks 9 mm lbr 240,932.90

13 Cat
13.1 Cat besi kg 2,205.00
13.2 Cat Zincromate m2 -

14 Bahan khusus
14.1 Curing compound ltr 240,932.90
14.2 Minyak begisting ltr 240,932.90
14.3 Spacer ( untuk begisting dinding ) bh 240,932.90
14.4 Skimcoat kg 240,932.90
14.5 Waterproofing membran m2 110,698.90
14.6 Screed m2 45,581.90
14.7 Mortar utama kg 1,627.93

15 Bata
15.1 Bata merah bj 520.94
15.2 Bata ringan hebel m3 1,126,524.10
15.3 Bata tempel UNM m2

16 Granite
16.1 Granite tile 60x60 m2 211,250.00
16.2 Granite tile 40x40 m2 186,250.00
16.3 Granite tile 30x30 m2 187,500.00

19 Baja
19.1 Baja WF kg 11,147.50
19.2 Baja gording kg 9,555.00
19.3 Elektroda kg 30,625.00
PROYEK : PEMBANGUNAN GEDUNG PUSAT PELAYANAN AKADEMIK
UNIVERSITAS NEGERI MAKASSAR TAHAP III
LOKASI : JL. A.P. PETTARANI, GUNUNGSARI BARU, RAPPOCINI, MAKASAR

UPAH TENAGA KERJA

NO Uraian Tenaga Kerja Satuan Harga

I Tenaga Kerja
Mandor org/ hr 98,000.00
Kepala Tukang Batu org/ hr 85,750.00
Kepala Tukang Kayu org/ hr 85,750.00
Kepala Tukang Besi org/ hr 85,750.00
Kepala Tukang Las org/ hr 85,750.00
Tukang Batu org/ hr 67,375.00
Tukang Kayu org/ hr 67,375.00
Tukang Besi org/ hr 67,375.00
Tukang Las org/ hr 67,375.00
Pekerja org/ hr 49,000.00