JUMLAH
NO. URAIAN PEKERJAAN HARGA
(Rp.)
Tiga Milyar Dua Juta Sembilan Ratus Sembilan Puluh Sembilan Ribu Rupiah
RENCANA ANGGARAN BIAYA (RAB)
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 25,000,000.00 25,000,000.00
2 Pematangan Lahan
- Pembersihan dan Pengupasan Lahan M2 7,000.00 11,720.00 82,040,000.00
- Pemotongan Pohon Pilihan Ø 15 - 40 Btng 40.00 125,000.00 5,000,000.00
3 Pengukuran dan Pemasangan Bowplank M' 244.00 81,937.50 19,992,831.94
4 Air Kerja Ls 1.00 2,500,000.00 2,500,000.00
5 Pembuatan Papan Nama Proyek Bh 1.00 250,000.00 250,000.00
6 Pembuatan Direksi Keet M2 20.00 225,000.00 4,500,000.00
JUMLAH 139,282,831.94
II. PEKERJAAN TANAH
1 Galian Tanah Pondasi M3 244.00 82,512.50 20,133,132.51
2 Urugan Tanah Bekas Galian M3 71.94 61,525.00 4,426,059.28
3 Urugan Pasir dibawah Pondasi M3 33.01 489,923.00 16,174,317.92
4 Urugan Pasir dibawah Lantai M3 56.86 489,923.00 27,856,531.86
5 Urug Tanah dibawah Lantai dipadatkan M3 56.86 336,283.00 19,120,715.10
JUMLAH 87,710,756.67
III. PEKERJAAN PASANGAN DAN BETON
1 Pasangan Pondasi Batu Kali, ad. 1 : 5 M3 183.03 1,381,908.54 252,924,363.30
2 Timbrisan Batu Kali M3 44.88 677,546.27 30,408,276.72
3 Pasangan Batako, ad. 1 : 4 M2 930.22 235,890.88 219,431,447.66
4 Beton Bertulang Mutu Beton, ad. (K 225)
- Balok Sloof 15/20 cm ( 174 Kg/M3) M3 8.98 11,179,903.91 100,350,817.49
- Kolom Praktis 15/15 cm ( 223 Kg/M3) M3 4.96 14,798,790.83 73,387,203.74
- Kolom Beton 20/25 cm ( 148 Kg/M3) M3 3.42 13,796,929.61 47,185,499.25
- Kolom Beton 15/45 cm ( 145 Kg/M3) M3 0.58 13,594,112.42 7,891,382.26
- Balok, Elev. +3.00 15/20 cm ( 145 Kg/M3) M3 3.73 13,120,260.58 48,964,812.47
- Balok enterance, Elev. +3.40 15/20 cm ( 174 Kg/M3) M3 0.15 13,120,260.58 1,968,039.09
- Balok kanopi, Elev. +3.00 15/20 cm ( 174 Kg/M3) M3 0.30 13,120,260.58 3,963,630.72
- Balok kanopi enterance, Elev. +3.40 15/20 cm ( 174 Kg/M3) M3 0.04 13,120,260.58 495,453.84
- Ring Balok 15/20 cm ( 174 Kg/M3) M3 8.98 13,120,260.58 117,767,458.93
- Plat Beton kanopi Tebal 8 cm ( 129 Kg/M3) M3 5.83 15,746,683.51 91,751,515.74
- Plat Beton enterance Tebal 8 cm ( 129 Kg/M3) M3 0.20 15,746,683.51 3,132,015.35
- Lisplank Beton Tebal 6 cm ( 173 Kg/M3) M3 1.70 20,437,841.23 34,845,701.79
- Lisplank Beton enterance Tebal 6 cm ( 173 Kg/M3) M3 0.17 20,437,841.23 3,527,980.15
5 Pengecoran Lantai Tegel, ad. (K 125) Tebal 5 cm M3 23.55 1,493,736.80 35,177,501.66
6 Rabat Beton Keliling (K125), tebal 7 cm M3 6.83 1,493,736.80 10,204,164.21
JUMLAH 1,034,467,618.36
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME
Rp. Rp.
IV. PEKERJAAN PLESTERAN DINDING DAN LANTAI
1 Plesteran Dinding, ad. 1 : 5 M2 1,860.45 81,313.58 151,279,759.03
2 Lantai Keramik 40 x 40 cm (Warna) M2 436.50 381,530.33 166,537,986.86
3 Lantai Keramik 40 x 40 cm (Anti Slip) M2 6.00 381,530.33 2,289,181.95
4 Keramik 20 x 20 cm Anti Slip pada Lantai Wc/Km M2 28.50 323,551.24 9,221,210.20
5 Keramik 20 x 25 cm pada Dinding Wc/Km (polos) M2 88.64 365,334.30 32,383,232.35
JUMLAH 361,711,370.39
V. PEKERJAAN PLAFOND
1 Langit-Langit Kalsi Board 9 mm M2 595.40 58,408.50 34,776,420.90
2 Rangka Plafond Kalsi Board Besi Hollow M2 595.40 190,710.25 113,548,882.85
3 List Profil Plafond M' 722.80 34,597.75 25,007,253.70
JUMLAH 173,332,557.45
VI. PEKERJAAN ALLUMUNIUM DAN ATAP
1 Kusen Pintu, Jendela dan Ventilasi Allumunium 4 Inci (black) M' 514.01 226,997.35 116,678,453.88
2 Daun Pintu Kaca Rangka Allumunium + Pemasangan M2 9.60 1,100,000.00 10,560,000.00
3 Daun Pintu Alllumunium rangka Allumunium + Pemasangan M2 48.40 1,000,000.00 48,400,000.00
4 Daun Jendela Kaca Rangka Allumunium + Pemasangan M2 37.31 1,050,000.00 39,179,700.00
5 Ventilasi Kaca Bening 5 mm Rangka Allumunium 3 Inci (black) M2 7.31 400,000.00 2,924,480.00
6 Lisptlank Bahan Kalsiplank M' 124.40 74,980.00 9,327,512.00
7 Konstruksi Atap Baja Ringan M2 679.91 388,685.63 264,271,282.16
8 Atap Genteng Rainbow M' 679.91 184,103.50 125,173,829.10
9 Bubungan Atap Genteng Rainbow (bulat) M' 91.24 139,000.50 12,682,405.62
JUMLAH 629,197,662.76
VII. PEKERJAAN PENGGANTUNG
1 Engsel Pintu 4 Inci Mutu Baik (1 pintu dipasang 3 bh) Bh 75.00 60,731.50 4,554,862.50
2 Engsel Pintu 3 dan Ventilasi Inci Mutu Baik Bh 270.00 40,422.50 10,914,075.00
3 Grendel Pintu 3 Inci Mutu Baik Bh 33.00 25,000.00 825,000.00
4 Grendel Jendela dan Ventilasi 2 Inci Mutu Baik Bh 135.00 10,000.00 1,350,000.00
5 Kait Angin Jendela dan Ventilasi Mutu Baik Bh 270.00 54,981.50 14,845,005.00
JUMLAH 32,488,942.50
VIII. PEKERJAAN INSTALASI LISTRIK
1 Instalasi Titik Lampu dan Stop Kontak Ttk 138.00 125,000.00 17,250,000.00
2 Philips PLC 23 Watt Bh 61.00 55,000.00 3,355,000.00
3 Philips PLC 18 Watt Bh 17.00 45,000.00 765,000.00
4 Fetting Down Light - 888 4 inci Bh 61.00 60,000.00 3,660,000.00
5 Fetting Down Light - 888 3 inci Bh 17.00 55,000.00 935,000.00
6 Fetting Kembang Merk Broco Bh 7.00 15,000.00 105,000.00
7 Stop Kontak Merk Broco Bh 60.00 25,000.00 1,500,000.00
8 Saklar Ganda Merk Broco Bh 13.00 35,000.00 455,000.00
9 Saklar Tunggal Merk Broco Bh 15.00 25,000.00 375,000.00
10 Box MCB + MCB 1 Group Unit 1.00 50,000.00 50,000.00
JUMLAH 28,450,000.00
IX. PEKERJAAN SANITASI
1 Titik Instalasi Air Bersih Ttk 11.00 150,000.00 1,650,000.00
2 Titik Instalasi Air Kotor Ttk 11.00 125,000.00 1,375,000.00
3 Closed Duduk Setara KW - 1 (complite) Unit 4.00 4,427,040.00 17,708,160.00
4 Closed Jongkok Setara KW - 1 Unit 3.00 786,709.25 2,360,127.75
5 Wastafel Warna/Keramik + Cermin Setara KW - 1 Unit 3.00 1,165,180.00 3,495,540.00
6 Kran Air Stainless Steel 1/2 Inci Bh 11.00 98,224.38 1,080,468.13
7 Floor Drain Stainless Steel Bh 11.00 132,422.50 1,456,647.50
8 Hand Shower Mandi Bh 4.00 297,252.00 1,189,008.00
9 Hand Shower Closed Bh 4.00 268,502.00 1,074,008.00
10 Pipa Pembuangan Air Kotor PVC 3 Inci Type AW M' 150.00 154,763.55 23,214,532.50
11 Pipa Pembuangan Kotor PVC 4 Inci Type AW M' 50.00 243,888.55 12,194,427.50
12 Septic Tank dan Peresapan Kapasitas Type Sedang Unit 3.00 5,000,000.00 15,000,000.00
JUMLAH 81,797,919.38
HARGA SATUAN JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME
Rp. Rp.
X. PEKERJAAN PENGECATAN
1 Cat Plafond dengan Metrolite M2 595.40 27,774.80 16,537,115.92
2 Cat Dinding Bagian Luar/Dalam dengan Metrolite M2 1,860.45 27,774.80 51,673,593.33
3 Acian Bidang Dinding Bagian Luar/Dalam M2 1,860.45 45,338.18 84,349,353.27
JUMLAH 152,560,062.52
XI. PEKERJAAN AKHIR
1 Pembersihan Akhir Pekerjaan Ls 1.00 4,000,000.00 4,000,000.00
2 Dokumentasi dan Pelaporan Ls 1.00 2,500,000.00 2,500,000.00
3 As Built Drawing Ls 1.00 2,500,000.00 2,500,000.00
JUMLAH 9,000,000.00
DAFTAR ANALISA
HARGA SATUAN UPAH DAN BAHAN
PENGUMPULAN :
1 M3 - Balok Sloof 15/20 cm
1.000 M3 Beton mutu K 225 Rp 1,673,210.33 1,673,210.33
13.333 M2 Begesting Sloof Rp 237,716.50 3,169,553.33
174.186 Kg Pembesian Rp 36,381.40 6,337,140.24
11,179,903.91
HARGA SATUAN
NO. URAIAN SATUAN
( Rp. )
I. SATUAN UPAH :
1 Pekerja Org/Hr 90,000.00
2 Tukang Batu, Kayu, Besi, Allumunium dan Cat Org/Hr 120,000.00
3 Kepala Tukang Org/Hr 140,000.00
4 Mandor Org/Hr 170,000.00
B. BAHAN KAYU
1 Papan Kayu Kls. I M3 5,200,000.00
2 Papan Kayu Kls. II M3 2,500,000.00
3 Kayu Kls. II M3 2,500,000.00
4 Kalsiplank M' 25,000.00
5 Kalsioard Lbr 85,000.00
6 List Profif Kayu Klas II M' 12,500.00
7 Plywood 9 mm Lbr 193,500.00
C. BAHAN KERAMIK
1 Keramik 20/20 cm (Anti Slip) M2 115,500.00
2 Keramik 20/25 cm (Polos) M2 112,400.00
3 Keramik 40/40 cm (Polos) M2 112,400.00
4 Keramik 40/40 cm (Warna) M2 147,700.00
5 Keramik 40/40 cm (Anti Slip) M2 147,700.00
6 Batu Alam Type Marmer Bakar Uk. 20/25 cm M2 350,000.00
7 Batu Alam Type Alur Fress Uk. 20/40 cm M2 300,000.00
D. BAHAN BESI
1 Paku 5 - 10 cm Kg 25,000.00
2 Paku Sekrup Kg 35,000.00
3 Paku Zink Kg 50,000.00
4 Paku Genteng Kg 45,000.00
5 Ikat Beton (Bendrat) Kg 40,000.00
6 Besi Beton Polos Kg 28,000.00
HARGA SATUAN
NO. URAIAN SATUAN
( Rp. )
7 Baut Diameter 16 mm Bh 600.00
8 Baut Diameter 12 mm Bh 600.00
9 Dynabolt Bh 3,500.00
10 Sekrup/Mur Allumunium Bh 700.00
11 Sekrup Gypsum Kg 30,000.00
12 Besi Hollow 4x4x0,3 mm M' 18,750.00
13 Besi Hollow 2x4x0,3 mm M' 15,000.00
14 Kosen Pintu dan Jendela Allumunium 4" (black) M' 150,000.00
15 Kosen Jendela dan Ventilasi Allumunium 3" (blac) M' 135,000.00
16 Daun Pintu Kaca Rangka Allumunium + Pemasangan M2 1,100,000.00
17 Daun Pintu Allumunium rangka Allumunium + Pemasangan M2 1,000,000.00
18 Daun Jendela Kaca Rangka Allumunium + Pemasangan M2 1,050,000.00
19 Daun Ventilasi Kaca Rangka Allumunium + Pemasangan M2 1,050,000.00
20 Ventilasi Kaca Bening 5 mm Rangka allumunium 3 Inci (Black) M2 400,000.00
21 Atap Genteng Raibow Lbr 74,700.00
22 Bubungan Atap Genteng Rainbow M' 67,100.00
23 Bubungan Zink Plat Bjls 0,25 mm Lbr 120,000.00
24 Bubungan Zink Plat Bjls 0,25 mm M' 55,000.00
25 Truss Zam Uk. 75, L = 10 cm M' 35,000.00
26 Truss Zam Uk. 75, L = 6 cm M' 30,000.00
27 Reng /G-DB Roof Bettens Btg 25,000.00
28 Food Plate 1,4 mm Bh 2,000.00
29 PLD - Diaprama Plate (dudukan) Bh 4,500.00
30 Wind Bracing M' 4,500.00
31 Tensioner Bh 15,000.00
E. BAHAN PIPA
1 Pipa PVC 3" M' 70,000.00
2 Pipa PVC 4" M' 120,000.00
3 Tee 4" Set 20,000.00
H. BAHAN SANITASI
1 Titik Instalasi Air Bersih Ttk 150,000.00
2 Titik Instalasi Air Kotor Ttk 125,000.00
3 Clesed Duduk Unit 3,200,000.00
4 Closed Jongkok Unit 350,000.00
5 Wastafer Warna + Kaca Unit 700,000.00
6 Kran Air Stainless Steel Bh 30,000.00
7 Floor Drain Stainless Steel Bh 100,000.00
8 Hand Shower Mandi Bh 250,000.00
9 Hand Shower Closed Bh 225,000.00
10 Seal Type Bh 2,500.00
11 Septic Tank dan Perseapan Unit 6,500,000.00
I. BAHAN CAT
1 Plamir Tembok Kg 65,000.00
2 Waterproofing (MU) Kg 85,000.00
3 Thiner Ltr 45,000.00
4 Minyak Cat Batu Alam Ltr 20,000.00
5 Cat Dasar Tembok Kg 30,000.00
6 Cat Tembok Kg 65,000.00
7 Minyak Bakesting Ltr 6,500.00
8 Tepung Gypsum /Compout Kg 7,000.00
9 Kertas Aplas Lbr 7,000.00
J. PERALATAN
1 BULLDOZER 150-215 HP /Jam 865,422.46
2 MOTOR GRADER >100 HP 350,490.09
3 VIBRATORY ROLLER 309,878.03
4 WATER TANKER 269,116.58
5 EXCAVATOR 341,208.70
6 WHEEL ROLLER 520,433.21
7 DUMP TRUCK 193,165.12