RENCANA ANGGARAN BIAYA

Propinsi : Kalimantan Barat No. RAB :


Kabupaten : Pontianak Program : PNPM MANDIRI PERDESAAN
Kecamatan : Sadaniang Jenis Kegiatan : PEKERJAAN PEMBUKAAN BADAN JALAN
Desa : Amawang Ukuran/Dimensi : 2.200 M
VOLUME Harga Jumlah dari Jumlah dari Jumlah
URAIAN Dari Dari Satuan Satuan Swadaya PNPM Total
Total
Swadaya Dana PNPM-MP ( Rp. ) ( Rp ) ( Rp ) ( Rp. )
BAHAN

Sub Total 1) - - -
ALAT
1 Excavator PC 100 377 - 377 jam 168,000 - 63,336,000 63,336,000
2 Mobilisasi Alat 2 - 2 kali 4,000,000 - 8,000,000 8,000,000
Sub Total 2) - 71,336,000 71,336,000
LAIN-LAIN
1 Papan Nama Proyek 1 - 1 bh 150,000 - 150,000 150,000
2 Papan Informasi Proyek 1 - 1 bh 100,000 - 100,000 100,000
3 Prasasti 1 - 1 bh 500,000 - 500,000 500,000
Sub Total 2) - 750,000 750,000
UPAH
1 Operator 54.00 - 54 HOK 75,000 - 4,050,000 4,050,000
2 Pekerja Terlatih 54.00 - 54 HOK 50,000 - 2,700,000 2,700,000
3 Pembantu Operator 54.00 - 54 HOK 40,000 - 2,160,000 2,160,000
Sub Total 3) - 8,910,000 8,910,000
TOTAL BIAYA - 80,996,000 80,996,000
Dari PNPM MP : 80,996,000
Sumber Dana
Dari Swadaya :
Catatan :
1 Sumbangan dalam bentuk bahan, upah, dan alat ditulis dalam kolom volume dari swadaya
2 Nilai RAB didapat dari kolom Volume Dari Dana dikalikan dengan kolom harga satuan yang kemudian ditotalkan
3 Sumbangan dalam bentuk uang dimasukkan pada baris terbawah (sumber dana dari swadaya)
4 Swadaya dalam bentuk lahan dituliskan dalam format lain

Disetujui Oleh, Dibuat Oleh,


PjOK Ketua TPK Fasilitator Kecamatan

Markurius Wantoro ........................ Yoyok Prasetyo Nugroho, ST Ebba Hamjumadi, AMd


NIP. 19620511 198503 1 009 FT-Kec F-Kec
RENCANA ANGGARAN BIAYA
Propinsi : Kalimantan Barat No. RAB :
Kabupaten : Pontianak Program : PNPM MANDIRI PERDESAAN
Kecamatan : Sadaniang Jenis Kegiatan : PEKERJAAN PENGRATAAN BADAN JALAN
Desa : Amawang Ukuran/Dimensi : 2.200 M
VOLUME Harga Jumlah dari Jumlah dari Jumlah
URAIAN Dari Dari Satuan Satuan Swadaya PNPM Total
Total
Swadaya Dana PNPM-MP ( Rp. ) ( Rp ) ( Rp ) ( Rp. )
BAHAN

Sub Total 1) - - -
ALAT
1 Sewa Alat Buldozer 100 377 - 377 jam 182,000 - 68,614,000 68,614,000
2 Mobilisasi Alat Buldozer 100 2 - 2 kali 4,000,000 - 8,000,000 8,000,000
Sub Total 2) - 76,614,000 76,614,000
LAIN-LAIN
1 - - -
2 - - -
3 - - -
Sub Total 2) - - -
UPAH
1 Operator 54.00 - 54 HOK 75,000 - 4,050,000 4,050,000
2 Pekerja Terlatih 54.00 - 54 HOK 50,000 - 2,700,000 2,700,000

Sub Total 3) - 6,750,000 6,750,000


TOTAL BIAYA - 83,364,000 83,364,000
Dari PNPM MP : 83,364,000
Sumber Dana
Dari Swadaya :
Catatan :
1 Sumbangan dalam bentuk bahan, upah, dan alat ditulis dalam kolom volume dari swadaya
2 Nilai RAB didapat dari kolom Volume Dari Dana dikalikan dengan kolom harga satuan yang kemudian ditotalkan
3 Sumbangan dalam bentuk uang dimasukkan pada baris terbawah (sumber dana dari swadaya)
4 Swadaya dalam bentuk lahan dituliskan dalam format lain

Disetujui Oleh, Dibuat Oleh,


PjOK Ketua TPK Fasilitator Kecamatan

Markurius Wantoro ........................ Yoyok Prasetyo Nugroho, ST Ebba Hamjumadi, AMd


NIP. 19620511 198503 1 009 FT-Kec F-Kec
RENCANA ANGGARAN BIAYA

Propinsi : Kalimantan Barat No. RAB : No. RAB


Kabupaten : Pontianak Program : PNPM - MP
Kecamatan : Sadaniang Jenis Kegiatan : Box Curvert
Desa : Amawang Ukuran/Dimensi : 2 x 6 M

VOLUME Harga kategori Jumlah dari Jumlah dari


No Uraian Dari Dari Satuan Satuan biaya Swadaya PNPM
Total
Swadaya PNPM ( Rp. ) ( Rp ) ( Rp )
BAHAN
1 Semen 50 Kg 118 - 118 M3 80,000 I-b - 9,440,000
2 Pasir Beton/cor 12 - 12 M3 100,000 I-a - 1,200,000
3 Batu 1-2 16 - 16 M3 400,000 I-a - 6,400,000
4 Besi ø10-12 m 66 - 66 BTG 82,000 I-b - 5,412,000
5 papan mall 16 - 16 BTG 15,000 I-a - 240,000
6 cerucuk 14 - 14 btg 3,000 I-a - 42,000
7 paku 2 - 2 kg 18,000 I-b - 36,000
8 Kawat bendrat 13 - 13 KG 16,000 I-b - 208,000
Sub Total 1) - 22,978,000
ALAT
1 Arco 3 - 3 Unit 370,000 II-a - 1,110,000
2 Ember Anti Pecah 12 - 12 Bh 8,000 II-a - 96,000
3 Sekop 4 - 4 Bh 45,000 II-a - 180,000
4 Penggali 4 - 4 Bh 45,000 II-a - 180,000
5 Pungki 8 - 8 Bh 25,000 II-a - 200,000
6 Tali Nilon 2 - 2 Glg 15,000 II-a - 30,000
7 Pemotong Besi 1 - 1 Unit 300,000 II-a - 300,000
8 Pembengkok Besi 1 - 1 Unit 226,000 II-a - 226,000
Sub Total 2) - 2,322,000
LAIN-LAIN
Sub Total 3) - -
UPAH
1 Kepala tukang 4 - 4 HOK 75,000 III-a - 300,000
2 Tukang 8 - 8 HOK 65,000 III-a - 520,000
3 Pekerja 40 - 40 HOK 60,000 III-a - 2,400,000
Sub Total 4) - 3,220,000

TOTAL BIAYA 28,520,000


Dari PNPM MP :
Dari Swadaya :

catatan
1 Sumbangan dalam bentuk bahan, upah, dan alat ditulis dalam kolom volume dari swadaya
2 Nilai RAB didapat dari kolom Volume Dari Dana dikalikan dengan kolom harga satuan yang kemudian ditotalkan
3 Sumbangan dalam bentuk uang dimasukkan pada baris terbawah (sumber dana dari swadaya)
4 Swadaya dalam bentuk lahan dituliskan dalam format lain

kategori Biaya
I-a Pembelian bahan oleh tenaga manusia
I-b Pembelian bahan hasil industri

II-a Pembelian alat tangan


II-b Pembelian/penyewaan mesin
III-a Pembayaran tenaga kerja untuk kontruksi
III-b Pembayaran tenaga kerja untuk pengumpul bahan

Disetujui Oleh, Dibuat Oleh,


PjOK Ketua TPK Desa Amawang Fasilitator kecamatan

Markurius Wantoro ( ........................ ) Yoyok Prasetyo Nugroho, ST Ebba Hamjumadi, AMd


NIP. 19620511 198503 1 009 FT F-Kec
2unit

Jumlah
Total
( Rp. )

9,440,000
1,200,000
6,400,000
5,412,000
240,000
42,000
36,000
208,000
22,978,000

1,110,000
96,000
180,000
180,000
200,000
30,000
300,000
226,000
2,322,000

300,000
520,000
2,400,000
3,220,000

28,520,000
28,520,000

Ebba Hamjumadi, AMd


F-Kec
REKAPITULASI ANGGARAN BIAYA

Propinsi : Kalimantan Barat Kecamatan : Sadaniang


Kabupaten : Pontianak Desa : Amawang

Kegiatan PEKERJAAN PEMBUKAAN BADAN JALAN Kegiatan PEKERJAAN PENGRATAAN BADAN JALAN Kegiatan Box Curvert
No. Uraian Ukuran 2.200 M Bobot Ukuran 2.200 M Bobot Ukuran 2x6M Bobot Bobot
JUMLAH TOTAL
Jumlah % Jumlah % Jumlah 2 unit % %
No. RAB No. RAB No. RAB
PNPM-Perdesaan Swadaya PNPM-Perdesaan Swadaya PNPM-Perdesaan Swadaya PNPM-Perdesaan Swadaya
I BAHAN - - - - - - 22,978,000 - 1 22,978,000 - 0
II PERALATAN 71,336,000 - 1 76,614,000 - 1 2,322,000 - 0 150,272,000 - 1
III LAIN-LAIN 750,000 - 0 - - - - - - 750,000 - 0
IV UPAH 8,910,000 - 0 6,750,000 - 0 3,220,000 - 0 18,880,000 - 0 RAB ASLI SELISIH
Jumlah 80,996,000 - 1 83,364,000 - 1 28,520,000 - 1 192,880,000 - 1 192,880,000 -

IV Operasional UPK 2 % 4,061,000 - 0 4,061,000 -


V Operasional TPK 3 % 6,091,000 - 0 6,091,000 -

Jumlah Total 80,996,000 - 1 83,364,000 - 1 28,520,000 - 1 203,032,000 1 203,032,000 -

Pembulatan
Jumlah Biaya Upah 8,910,000 - 6,750,000 - 3,220,000 -

Jumlah HOK Konstruksi

Sadaniang,12 Desember 2012

PjOK Kec. Sadaniang Ketua TPK Diperiksa Oleh :


FK / FT

Markurius Wantoro ( ........................ ) ( Ebba Hamjumadi, AMd ) ( Yoyok Prasetyo Nugroho, ST )


NIP. 19620511 198503 1 009
PNPM Mandiri - Perdesaan Form.19

Kabupaten : Pontianak Jenis Prasarana :


Kecamatan : Take Of Sheet Lokasi :
Kelurahan : Volume : 2.200 M

Volume Total Galian data survey :


10,758.00
170.85
Analisa Kebutuhan Exavator (Analisa K .224 a) Karena 200m3 dikerjakan sselama 7 Jam
1 M3= 0,035 Jam Jadi Untuk 1 m3= 7/200
0,035 x 10,758.00 0.035
376.53

377.00 Jam

Sewa Alat Analisa Kode E 020


167,527.31
Biaya Excapator 168,000.00

HOK Operator Excavator Pakai Analisa K.224a


Operator : Volume x 0,005
53.79
Dibulatkan 54.00

Pekerja Terlatih: voleme x 0,005


53.79
Dibulatkan 54.00

Pembantu Operator : VOLUME x 0,005


53.79
Dibulatkan 54.00

Sewa Alat Analisa Kode E 001


181,830.65
Biaya Buldozer 182,000.00

HOK Operator Buldozer Pakai Analisa K.224a


Operator : Volume x 0,005
53.79
Dibulatkan 54.00

Pekerja Tak Terlatih: voleme x 0,005


53.79
Dibulatkan 54.00
Pembantu Operator : VOLUME x 0,005
53.79
Dibulatkan 54.00

Tanggal Survei : Dibuat oleh : TPK/KPMD/T


BIAYA ALAT KODE
UNTUK PERHITUNGAN ANALISA E 020
BIAYA PERALATAN

PROPINSI KALIMANTAN BARAT KODE KABUPATEN LANDAK KODE


TYPICAL 61 TYPICAL

JENIS ALAT : HYDRAULIC EXCAVATOR TENAGA : 90 HP


HARGA : Rp. 405,637,620.00
UMUR KERJA : 8 TAHUN = 12,000 JAM FACTO(CRF) 0.20483
1 TAHUN = 300 HARI KERJA (12.50%)
ATAU : 1 HARI = 5 JAM KERJA

A. BIAYA PEMILIKAN (OWNERSHIP COST)

1. Depreasi : 90 % x HARGA ALAT x (CRF) x 1


JAM / HARI

= 0.90 x 405,637,620.00 x 0.20483 = 49,852.05


1,500

2. LAIN-LAIN
ASURANSI 3 % / TAHUN = 0.033 x HARGA ALAT
JAM / TAHUN

= 0.033 x 405,637,620.00 = 8,924.03


1,500
SUB TOTAL A ........... 58,776.08

B. BIAYA OPERASI (OPERATION COST) : (Rp. / JAM)


KEBUTUHAN BAHAN BAKAR DAN PELUMAS TIAP HP

DIESEL = 0.158 LITER/JAM


BENSIN = 0.167 LITER/JAM
PELUMAS = 0.006 LITER/JAM

HARGA : DIESEL = 4,500.00 PER LITER


BENSIN = 4,500.00 PER LITER
PELUMAS = 27,500.00 PER LITER

BAHAN BAKAR = 0.158 x 90 x 4,500.00 = 63,990.00


PELUMAS = 0.006 x 90 x 27,500.00 = 14,850.00
PERBAIKAN / SPARE PARTS
(60% BIAYA DEPREASI) = 0.600 x 49,852.05 = 29,911.23

SUB TOTAL B ........... 108,751.23

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT / JAM

SUB TOTAL A+B = 58,776.08 + 108,751.23 = 167,527.31


BIAYA ALAT KODE
UNTUK PERHITUNGAN ANALISA E 001
BIAYA PERALATAN

PROPINSI KALIMANTAN BARAT KODE KABUPATEN LANDAK KODE


TYPICAL 61 TYPICAL

JENIS ALAT : BULLDOZER TENAGA : 100 HP


HARGA : Rp. 344,793,370.00
UMUR KERJA : 8 TAHUN = 9,600 JAM FACTO(CRF) 0.20483
1 TAHUN = 300 HARI KERJA (12.50%)
ATAU : 1 HARI = 4 JAM KERJA

A. BIAYA PEMILIKAN (OWNERSHIP COST)

1. Depreasi : 90 % x HARGA ALAT x (CRF) x 1


JAM / HARI

= 0.90 x 344,793,370.00 x 0.20483 = 52,968.02


1,200

2. LAIN-LAIN
ASURANSI 3 % / TAHUN = 0.033 x HARGA ALAT
JAM / TAHUN

= 0.033 x 344,793,370.00 = 9,481.82


1,200
SUB TOTAL A ........... 62,449.84

B. BIAYA OPERASI (OPERATION COST) : (Rp. / JAM)


KEBUTUHAN BAHAN BAKAR DAN PELUMAS TIAP HP

DIESEL = 0.158 LITER/JAM


BENSIN = 0.167 LITER/JAM
PELUMAS = 0.006 LITER/JAM

HARGA : DIESEL = 4,500.00 PER LITER


BENSIN = 4,500.00 PER LITER
PELUMAS = 27,500.00 PER LITER

BAHAN BAKAR = 0.158 x 100 x 4,500.00 = 71,100.00


PELUMAS = 0.006 x 100 x 27,500.00 = 16,500.00
PERBAIKAN / SPARE PARTS
(60% BIAYA DEPREASI) = 0.600 x 52,968.02 = 31,780.81

SUB TOTAL B ........... 119,380.81

TOTAL BIAYA PEMILIKAN DAN BIAYA OPERASI ALAT / JAM

SUB TOTAL A+B = 62,449.84 + 119,380.81 = 181,830.65


170,000
34,000
DAFTAR ANALISA
HARGA SATUAN PEKERJAAN

KEGIATAN : PENATAAN DAN PEMAGARAN HALAMAN KANTOR BUPATI LANDAK


PEKERJAAN : PEMATANGAN LAHAN (CUT & FILL)
LOKASI : KABUPATEN LANDAK
TAHUN ANGGARAN : 2005

ANALISA BIAYA PEKERJAAN


KODE
TIMBUNAN KONSTRUKSI
K.230a
( MENGGUNAKAN ALAT )

KABUPATEN : NGABANG TANGGAL :


KECAMATAN : - …………………………..
URAIAN : ANGGAPAN /ASUMSI :
1 Urugan dikirim sampai ketempat Pekerjaan 1 Menggunakan Alat Berat ( 120m 3hari )
2 Menghampar dan Memadatkan 2 Dipakai Material Tanah Setempat
3 Pemadatnya mendekati pemadatan untuk LPB

JUMLAH JLH.VOL UPAH BIAYA SUB TOTAL


PEKERJA HARI KODE
ORANG (org.hari) (Rp./org/hari) (Rp) (Rp)
P Mandor 1.00 1.00 L.061 1.00 38,850.00 38,850.00
E
K Operator Terlatih 2.00 1.00 L.081 2.00 33,000.00 66,000.00
E Pekerja tak Terlatih 6.00 1.00 L.101 6.00 23,100.00 138,600.00
R
J
A

PEKERJA 243,450.00
TOTAL KODE BIAYA SUB
MATERIAL SATUAN HARGA
VOLUME (Rp./Unit) (Rp) TOTAL
M
A Alat Bantu 0.40 Set M.170 55,200.00 22,080.00
T
E
R
I
A
L

MATERIAL 22,080.00
JUMLAH HARI JAM HARGA BIAYA SUB
PERALATAN KODE
ALAT KERJA KERJA (Rp./Jam) (Rp) TOTAL
P
BULLDOZER 110 HP. 1.00 1.00 E.001 4.00 380,316.26 1,521,265.04
E
R VIBRATOR ROLLER 7 HP 1.00 1.00 E.087 5.00 50,515.05 252,575.27
A
L
A
T
A
N

PERALATAN 1,773,840.31
Total ( Rp ) 2,039,370.31
Catatan:
VOLUME/QUANTITY 120.00 SATUAN M3 HARGA SATUAN Rp. 16,994.75 PER M3
DAFTAR ANALISA
HARGA SATUAN PEKERJAAN

KEGIATAN : PENATAAN DAN PEMAGARAN HALAMAN KANTOR BUPATI LANDAK


PEKERJAAN : PEMATANGAN LAHAN (CUT & FILL)
LOKASI : KABUPATEN LANDAK
TAHUN ANGGARAN : 2005

ANALISA BIAYA PEKERJAAN


GALIAN TANAH UNTUK KONSTRUKSI KODE
K.224a
( MENGGUNAKAN ALAT )

KABUPATEN : NGABANG TANGGAL :


KECAMATAN : - …………………………..
URAIAN : ANGGAPAN /ASUMSI :
1 Penggalian tanah Buldozer (200M3/hari) 1 Menggunakan Alat Berat ( 120m 3hari )
2 Tanah Galian Disingkirkan Sejauh minimal 30 m 2 Dipakai Material Tanah Setempat
3 Tanah Galian Diangkut menggunakan Dump Truck 3 Pemadatnya mendekati pemadatan untuk LPB
4 Pemindahan T. Galian Menggunakan Excavator

JUMLAH JLH.VOL UPAH BIAYA SUB TOTAL


PEKERJA HARI KODE
ORANG (org.hari) (Rp./org/hari) (Rp) (Rp)
P Mandor 1.00 1.00 L.061 1.00 38,850.00 38,850.00
E
K Pekerja Terlatih 3.00 1.00 L.106 3.00 29,050.00 87,150.00
E Operator Terlatih 3.00 1.00 L.081 3.00 33,000.00 99,000.00
R 3.00
J Pembantu Operator 1.00 L.083 3.00 27,650.00 82,950.00
A

PEKERJA 307,950.00
TOTAL KODE BIAYA SUB
MATERIAL SATUAN HARGA
VOLUME (Rp./Unit) (Rp) TOTAL
M
A
T
E
R
I
A
L

MATERIAL 0.00
JUMLAH HARI JAM HARGA BIAYA SUB
PERALATAN KODE
ALAT KERJA KERJA (Rp./Jam) (Rp) TOTAL
P
BULLDOZER 110 HP. 1.00 1.00 E.001 7.00 380,316.66 2,662,216.61
E
R Excavator 90 HP 1.00 1.00 E.020 7.00 250,000.01 1,750,000.06
A Dump Truck 3,5 T 4.00 1.00 E.211 7.00 96,850.41 677,952.84
L
A
T
A
N

PERALATAN 5,090,169.51
Total (Rp.) 5,398,119.51
Catatan:
VOLUME/QUANTITY 200.00 SATUAN M3 HARGA SATUAN Rp. 26,990.60 PER M3
0.0050 HARI PER M3
0.0100 HARI PER M3
0.0300 HARI PER M3
0.005 HARI PER M3
0.015 HARI PER M3
0.015 HARI PER M3
0.015 HARI PER M3

28.571429 PER M3 0.035


28.571429 PER M3 0.035
28.571429 PER M3 0.035

KALAU 2.200 METER

2,200 6 0.8150
10,758
376.53 JAM
PNPM Mandiri Perdesaan Form. 19

Kabupaten : …………….. Jenis Prasarana : Gorong-gorong


Kecamatan : ……………. Take Of Sheet BOX CULVERT
Desa : ……………. Lokasi : …………………
Volume : 2
UNIT
Box Culvert, Ukr 2x 6 m
BOX CULVERT

A. Volume Cor 2.00 x 0.20 x 6.00 x 2.00 = 4.80 m3 Keterangan


Box Culvert 2.00 x 0.20 x 6.00 = 2.40 m3 Tutup Box Culvert
2.00 x 0.20 x 6.00 = 2.40 m3 menggunakan tulangan rangkap
dan ketebalan Cor 20 cm
Jumlah ( a ) = 9.600 m3

Head Wall Box Culvert

0.20 x 2x 0.2 x 2= 0.160 m3 ( b )

Jumlah (a) + (b) = 9.760 m3

B. Menghitung kebutuhan besi , digunakan Besi ф 10 mm

Sisi Atas = 2x 6/ 0.15 88.00 8 Btg Besi ф 10mm dipasang dg


Sisi Bawah = 2.4 x 6/ 0.15 105.60 9 Btg jarak 15 cm
Sisi Samping Kiri = 2x 6/ 0.15 88.00 8 Btg
Sisi Saming Kanan = 2x 6/ 0.15 88.00 8 Btg
KARENA ADA 2 UNIT

Jumlah Besi = 66 Btg


Kawat Bendrat dengan Menggunakan Analisa BOW I.2 = 13 Kg

C. Pasir alas , untuk Alas Gorong2 & Head Wall 3.00 m3

D. ANALISA K.725.a.i PEKERJAAN BETON BERTULANG PRAKTIS Camp. 1 : 2 : 3 / M3


Untuk struktur Analisa G.41 Beton Campuran 1 Pc : 2 Ps : 3 Kr
1 m³ digunakan PC 6 zak Analisa F.43 Cetakan Beton
Pasir 0.539 m³ Analisa I.2 Pembesian
batu pech 0.796 m³
2
2 UNIT
Kebutuhan SEMEN = vol.btn x koef 58.56 59.00 zak 118.00 zak 0,20
0,20

Kebutuhan PASIR = vol btn x koef 5.2606 6.00 m³ 12.00 m³


Kebutuhan BATU 1/2 = vol betn x koef 7.769 8.00 m³ 16.00 m³
0.20

kepala Tukang = V.b / 6 x 1


=8 /6x1 = 1.63 2.00 hok 4.00 hok
2
kebutuhan tukang= vol.btn /6 x 2
= 3.2533 4.00 hok 8.00 hok
kebutuhn pkrj = vol.btn / 6 x 12 =
0.20
= 19.52 20.00 hok 40.00 hok

2,4

E. Kebutuhan papan mall ANALISA BOW F.43 PEKERJAAN CETAKAN BETON (BEKISTING) / M2
Luas penampang 4.800 m²
Luas papan = 0.6 m²
Kebutuhan papan mall = 4,8/ 0,6 8.0 8.00 kpg 16.00 kpg
Kebutuhan paku 0.48 1.00 kg 2.00 kg
Kayu DIA 6/8 CERUCUK = 6.24 7.00 Btg 14.00 Btg
Tanggal Survei : ………… Dibuat oleh :

………………………….

Formulir untuk Desa


A
PANJANG : 2 M PROGRAM NASIONAL
PEMBERDAYAAN
LEBAR :6M MASYARAKAT
PNPM-Mandiri Perdesaan
MANDIRI PERDESAAN

M2 PROPINSI : KALBAR
B B
KABUPATEN : PONTIANAK
MUKA TANAH
KECAMATAN : Sadaniang
DESA

AMAWANG
COR BETON 1 : 3:5 JENIS PRASARANA
BOX COULVERT
LOKASI

A ASBUILT DRAWING
LANTAI KERJA T=20
CM Camp: 1:2:3 TAMPAK ATAS,DETAIL,POT.MEMANJANG
Head wall / Dudukan Tulangan ø10 DI BUAT OLEH:
TPK/KADER TEKNIS

POTONGAN B-B ........................


M2
DIPERIKSA OLEH :
FT-KEC

M6
YOYOK PRASETYO NUGROHO, ST
DIKETAHUI OLEH PJOK

Markurius Wantoro
POTONGAN A-A
TAMPAK ATAS NIP. 19620511 198503 1 009
PERSPEKTIF Lantai kerja LEMBAR KE …….. DARI…